CASE # JC EXECUTIVE SUMMARY CONDITIONAL USE PERMIT - FLOODPLAIN STAFF CONTACT: MIKE TERTINGER

Size: px
Start display at page:

Download "CASE # JC EXECUTIVE SUMMARY CONDITIONAL USE PERMIT - FLOODPLAIN STAFF CONTACT: MIKE TERTINGER"

Transcription

1 CASE # JC EXECUTIVE SUMMARY CONDITIONAL USE PERMIT - FLOODPLAIN STAFF CONTACT: MIKE TERTINGER OWNER/APPLICANT INFORMATION OWNER/APPLICANT: MAILING ADDRESS: PROPERTY ADDRESS: Linn County Secondary Road Dept. % Garret Reddish 1888 County Home Rd. Marion, IA Spencers Grove Road public right-of-way over Blue Creek REQUEST This applicant is requesting a Conditional Use Floodplain Permit to replace the existing Spencers Grove bridge over Blue Creek. The project involves removing the existing 28 x 43 single-span steel beam bridge, and constructing a 3-span, 40 x 80 continuous concrete slab bridge with associated approach grading. The applicant has estimated that the project will be completed in OUTSTANDING ISSUES AND STANDARDS FOR APPROVAL The applicant must obtain all relevant permits as required by state and federal entities. The applicant must submit a No-Rise certificate to ensure the excavation and new bridge construction will not cause a rise in flood heights or velocities. The proposal must meet all of the standards for approval found in Article 7, Section 13 of the Unified Development Code (UDC). STAFF RECOMMENDATION Staff recommends approval subject to the conditions of the staff report.

2 Planning & Development Linn County, Iowa phone fax Jean Oxley Public Service Center 935 Second Street Southwest Cedar Rapids, Iowa STAFF REPORT CONDITIONAL USE - FLOODPLAIN PERMIT JC Planning and Zoning Commission Meeting: SEPTEMBER 18, 2017 Board of Adjustment Meeting: SEPTEMBER 27, 2017 PROPERTY INFORMATION: MAP DESIGNATION: Spencers Grove Road public right-of-way CURRENT ZONING: n/a CURRENT USE: Spencers Grove Road Bridge at Blue Creek SURROUNDING LAND USES North Agricultural; AG South Agricultural, 1 single-family dwelling; AG East Spencers Grove Road public right-of-way West- Spencers Grove Road public right-of-way CONDITIONAL USE PERMIT AREA: 0.50 acres FINDINGS OF FACT: 1. Linn County is the owner of record of the subject property. 2. The applicant is Garret Reddish on behalf of the Linn County Secondary Road Department. 3. The subject property is the Spencers Grove Road Bridge right-of-way at Blue Creek.

3 Case # JC , Page 3 of 7 4. Excavation within an unstudied floodplain overlay district requires a Conditional Use Floodplain permit in accordance with the Linn County Unified Development Code Floodplain Overlay District requirements. 5. A pre-application meeting was held with the applicant on August 16th, An application for a conditional use floodplain permit was received on August 16th, A licensed engineer submitted a signed Engineering No-Rise Certification on September 7th, CONFORMANCE TO THE UNIFIED DEVELOPMENT CODE ARTICLE 7, SECTION 13 FLOODPLAIN OVERLAY DISTRICT (b)(iii)(3) Factors. In reviewing applications for conditional uses or requests for variances, the Board of Adjustment shall consider all relevant factors specified in other sections of the UDC and: (A): The danger to life and property due to increased flood heights or velocities caused by encroachments. The nature of the proposed use (bridge replacement) will not cause increased flood heights or velocities. (B): The danger that materials may be swept on to other lands or downstream to the injury of others. The replacement bridge is expected to lessen the danger that materials may be swept on to other lands downstream to the injury of others. (C): The proposed water supply and sanitation systems and the ability of these systems to prevent disease, contamination and unsanitary conditions. No water supply or sanitation systems are proposed for the bridge replacement. (D): The susceptibility of the proposed facility and its contents to flood damage and the effect of such flood damage on the individual owner. The replacement bridge is expected to lessen the susceptibility of the facility to flood damage and the effect of such flood damage on the individual owner. (E): The importance of the services provided by the proposed facility to the County Board. The bridge is an integral component of the Linn County road system. (F): The requirements of the facility for a floodplain location. The Spencers Grove Road Bridge at Heatons creek cannot be relocated.

4 Case # JC , Page 4 of 7 (G): The availability of alternate locations not subject to flooding for the proposed uses. The Spencers Grove Road Bridge at Heatons creek cannot be relocated. (H): The compatibility of the proposed use with existing development and development anticipated in the foreseeable future. The proposed replacement bridge is compatible with surrounding development. (I): The relationship of the proposed use to the comprehensive plan and flood plain management program for the area. The proposed use supports the growth and development of Linn County by recognizing the need for and promoting adequate and well-maintained rural infrastructure. The proposed use also is consistent with the floodplain management practices of Linn County. (J): The safety of access to the property in times of flood for ordinary and emergency vehicles. The replacement bridge will improve the long term safety of access to either side of Blue Creek in times of flood for ordinary and emergency vehicles. (K): The expected height, velocity, duration, rate of rise and sediment transport of the flood water expected at the site. It is not anticipated that the proposed use will affect existing conditions for any of these elements. (L): Such other factors which are relevant to the purpose of this ordinance. There are no other factors which are relevant. ALTERNATIVES: The following alternatives may be considered: 1. Recommend approval of the proposal subject to conditions. 2. Recommend denial of the proposal. 3. Refer the proposal back to the applicant for additional review / information. STAFF RECOMMENDATION: 1. Staff recommends Alternative 1, recommend approval of the Conditional Use Floodplain Permit subject to the conditions of the staff report, as the requirements in UDC Article 7, Section 13 Floodplain Overlay District have been met, as evidenced by:

5 Case # JC , Page 5 of 7 1. A licensed engineer submitted a signed Engineering No-Rise Certification. 2. No structures, grading or other activity is proposed that would cause a long-term obstruction of the conveyance of the floodplain area. Therefore, no increase in the 100-year flood level is anticipated. 3. The proposed activities minimize flood damage and are flood resistant. The general nature of the activity proposed in the floodplain is excavation. IT IS THE RESPONSIBILITY OF THE APPLICANT TO COMPLETE ALL CONDITIONS, AS OUTLINED IN THIS STAFF REPORT, PRIOR TO FINAL APPROVAL OF THE CASE. IF YOU HAVE QUESTIONS REGARDING A CONDITION, CONTACT THE DEPARTMENT UNDER WHICH THAT CONDITION IS LISTED. THE CONTACTS NAMES AND PHONE NUMBERS ARE LISTED BELOW. ITEMS IN THE COMMENTS SECTION ARE NOT A REQUIREMENT TO BE MET PRIOR TO APPROVAL. THEY ARE INTENDED TO INCREASE YOUR KNOWLEDGE AND AWARENESS OF ISSUES THAT MAY POSSIBLY EXIST ON THE PROPERTY. LINN COUNTY ENGINEERING DEPARTMENT STEVE GANNON, COUNTY ENGINEER, Steve.Gannon@linncounty.org Brad.Ketels@linncounty.org This is a County bridge replacement project with State and Federal permits. IOWA DEPARTMENT OF TRANSPORTATION JOEL KEIM, ENGINEERING OPERATIONS TECHNICIAN, Joel.Keim@dot.iowa.gov 1. Not within the jurisdiction of the Iowa Department of Transportation. LINN COUNTY PUBLIC HEALTH DEPARTMENT SUE ELLEN HOSCH, ENVIRONMENTAL SPECIALIST, SueEllen.Hosch@linncounty.org NATURAL RESOURCES CONSERVATION SERVICE JON GALLAGHER, LINN COUNTY SOIL CONSERVATIONIST JOHN BRUENE, DISTRICT CONSERVATIONIST, x3 Jon.Gallagher@ia.nacdnet.net 1. Submit erosion and sediment control plan for review and acceptance. Comments:

6 Case # JC , Page 6 of 7 1. Submit all required items above to Jon Gallagher at the NRCS office. LINN COUNTY CONSERVATION DEPARTMENT DENNIS GOEMAAT, Dennis.Goemaat@linncounty.org 1. There is a significant stream present. This stream should be protected by following the NPDES permit requirements for erosion control. LINN COUNTY EMERGENCY MANAGEMENT MIKE GOLDBERG, mike.goldberg@linncounty-ema.org LINN COUNTY 911 COORDINATOR SHARENE OTTAWAY, Sharene.Ottaway@linncounty.org LINN COUNTY PLANNING AND DEVELOPMENT - ZONING DIVISION MIKE TERTINGER, PLANNER, Mike.Tertinger@linncounty.org 1. All applicable State and Federal Permits must be obtained prior to excavation. 2. All such uses shall be reviewed by the Department of Natural Resources to determine: (i) whether the land involved is either wholly or partly within the floodway or floodway fringe; and (ii) the 100-year flood level. The applicant shall be responsible for providing the Department of Natural Resources with sufficient technical information to make the determination 3. The petitioner shall sign an Acceptance of Conditions form, which provides assurance that all conditions will be met on a continuous basis and specifically agrees to hold Linn County harmless from any and all damages or claims for damages that might arise or accrue by reason of approval of the conditional use case by the Linn County Board of Adjustment. Further, by signing the Acceptance of Conditions form, the petitioner shall agree to allow employees of the County reasonable access to the property for inspection and for submission of documents to verify employment level of off-site employees. 4. A certificate of no-rise shall be submitted and executed by the applicant s engineer.

7 Case # JC , Page 7 of 7 5. Overburden and other construction material should be stored outside the floodway wherever possible; if these materials are stored within the floodway, they should be removed in the event of heavy rainfall or possible flash flooding conditions. LINN COUNTY PLANNING AND DEVELOPMENT - BUILDING DIVISION ANDREW OIEN, BUILDING OFFICIAL, Andrew.Oien@linncounty.org

Existing Conditions and Environmental Consequences Floodplains

Existing Conditions and Environmental Consequences Floodplains 3.9 Environmental Consequences 3.8 3.8.1 WHAT ARE FLOODPLAINS? are low-lying areas adjacent to rivers, streams, and other waterbodies that are susceptible to inundation (flooding) during rain events. These

More information

Chapter 1: General Program Information

Chapter 1: General Program Information Chapter 1: General Program Information 1.1 Introduction The Montgomery County Stormwater Management Resolution (#03-1-5) was adopted by the County Board of Commissioners on January 22, 2003. The purpose

More information

SEMSWA s Role in the Land Development Process

SEMSWA s Role in the Land Development Process SEMSWA s Role in the Land Development Process One of SEMSWA s responsibilities is to ensure that any new development or redevelopment within its service area is designed and constructed in compliance with

More information

Project phasing plan (if applicable) 12 copies of site plan

Project phasing plan (if applicable) 12 copies of site plan SITE PLAN REVIEW PERMIT APPLICATION City of Grand Haven, 11 N. Sixth Street, Grand Haven, MI 49417 Phone: (616) 847-3490 Fax: (616) 844-2051 Website: www.grandhaven.org 1. Project Information Address/location

More information

MANUAL OF DESIGN, INSTALLATION, AND MAINTENANCE REQUIREMENTS FOR STORMWATER MANAGEMENT PLANS

MANUAL OF DESIGN, INSTALLATION, AND MAINTENANCE REQUIREMENTS FOR STORMWATER MANAGEMENT PLANS MANUAL OF DESIGN, INSTALLATION, AND MAINTENANCE REQUIREMENTS FOR STORMWATER MANAGEMENT PLANS May 2007 SECTION 1 Responsibility of Applicant TABLE OF CONTENTS A. Stormwater Management Plan Required Information

More information

Appendix E Preliminary Location Hydraulic Study

Appendix E Preliminary Location Hydraulic Study Appendix E Prepared for: State of Alaska Department of Transportation and Public Facilities Prepared by: HDR Alaska, Inc. 2525 C Street, Suite 305 Anchorage, Alaska 99503 February 2014 This page intentionally

More information

City of Waco Stormwater Management Regulations

City of Waco Stormwater Management Regulations 1.0 Applicability: City of Waco Stormwater Management Regulations These regulations apply to all development within the limits of the City of Waco as well as to any subdivisions within the extra territorial

More information

13. PRELIMINARY PLAT NO MILLS FARM - Vicinity of the southeast corner of 159 th Street and Quivira Road

13. PRELIMINARY PLAT NO MILLS FARM - Vicinity of the southeast corner of 159 th Street and Quivira Road 13. corner of 159 th Street and Quivira Road 1. APPLICANT: HNTB Corporation is the applicant for this request. 2. REQUESTED ACTION: The applicant is requesting approval of a preliminary plat for a 383-lot

More information

UNIVERSITY OF NORTHERN IOWA

UNIVERSITY OF NORTHERN IOWA UNIVERSITY OF NORTHERN IOWA Municipal Separate Storm Sewer System September 2008 Report Permit Number 07-09-0-04 August 2008 Prepared by: University of Northern Iowa Environmental Health and Safety Office

More information

Northeast Ohio Regional Sewer District Stormwater Management Plan Review Policy

Northeast Ohio Regional Sewer District Stormwater Management Plan Review Policy Northeast Ohio Regional Sewer District Stormwater Management Plan Review Policy Introduction As a component of the Northeast Ohio Regional Sewer District s (District) Regional Stormwater Management Program,

More information

Article 20 Stormwater Management

Article 20 Stormwater Management Article 20 Section 20.01 Intent Article 20 The purpose of this Article is to protect the health, safety, and general welfare of the citizens by requiring compliance with accepted standards and practices

More information

STORMWATER GREEN INFRASTRUCTURE AND PLANNING/ZONING BOARDS

STORMWATER GREEN INFRASTRUCTURE AND PLANNING/ZONING BOARDS STORMWATER GREEN INFRASTRUCTURE AND PLANNING/ZONING BOARDS Source: Center for Watershed Protection, 2007 Southern Tier Central Regional Planning & Development Board Chemung County Stormwater Team OUTLINE

More information

CHAPTER 156 POST-CONSTRUCTION STORM WATER RUNOFF...

CHAPTER 156 POST-CONSTRUCTION STORM WATER RUNOFF... 1 of 10 11/26/2013 11:06 AM North Liberty, IA Code of Ordinances CHAPTER 156 POST-CONSTRUCTION STORM WATER RUNOFF CONTROL 156.01 Purpose 156.12 Issuance of Permit 156.02 Findings 156.13 Denial of Permit

More information

Washington County, Maryland Division of Public Works Policy Manual

Washington County, Maryland Division of Public Works Policy Manual Washington County, Maryland Division of Public Works Policy Manual Subject: Downstream Drainage Easement Category: Land Development Engineering Number: 7-4.1 Date: June 1, 2009 (effective) PURPOSE: The

More information

FLOODPLAIN USE PERMIT APPLICATION COMMUNITY DEVELOPMENT DEPARTMENT W. Ten Mile Road Novi, MI (248)

FLOODPLAIN USE PERMIT APPLICATION COMMUNITY DEVELOPMENT DEPARTMENT W. Ten Mile Road Novi, MI (248) FLOODPLAIN USE PERMIT APPLICATION COMMUNITY DEVELOPMENT DEPARTMENT 45175 W. Ten Mile Road Novi, MI 48375 (248) 347-0415 Office Use Only Permit Number: Date Issued: Processed By: Type of Permit: Date: Project

More information

Section General Tree Preservation Requirements for New Nonresidential and Residential Development

Section General Tree Preservation Requirements for New Nonresidential and Residential Development DIVISION 2: TREE PRESERVATION AND PROTECTION Section 5.5.2.1 General Tree Preservation Requirements for New Nonresidential and Residential Development (a) Application. The provisions of this Section apply

More information

Planning Proposal under section 55 of the EP&A Act

Planning Proposal under section 55 of the EP&A Act FOR PUBLIC EXHIBITION [Brief description] Monday 10 October to Monday 27 October 2014 Planning Proposal under section 55 of the EP&A Act Port Macquarie-Hastings LEP 2011 (Amendment No 32) Mixed land zone

More information

At Your Disposal CUP Amendment, Lot 20, Village Service Commercial, at 128 Bastille Dr. (PLN17-208)

At Your Disposal CUP Amendment, Lot 20, Village Service Commercial, at 128 Bastille Dr. (PLN17-208) MEMORANDUM Archuleta County Development Services Planning Department 1122 HWY 84 P. O. Box 1507 Pagosa Springs, Colorado 81147 970-264-1390 Fax 970-264-3338 TO: Archuleta County Planning Commission FROM:

More information

Draft Rhode Island Stormwater Design and Installation Standards Manual

Draft Rhode Island Stormwater Design and Installation Standards Manual Draft Rhode Island Stormwater Design and Installation Standards Manual Summary The May 2009 Public Review Draft version of the RI Stormwater Design and Installation Standards Manual consists of approximately

More information

SITE PLAN REVIEW APPLICATION AND CHECKLIST

SITE PLAN REVIEW APPLICATION AND CHECKLIST SITE PLAN REVIEW APPLICATION AND CHECKLIST PROJECT SUMMARY: Project Name: City/ETA Location: City ETA (Application fee & number of copies needed are based on location) Property Location (Legal Description

More information

TOWNSHIP OF LOGAN SOIL & FILL IMPORTATION AND PLACEMENT APPLICATION SUBMITTAL CHECKLIST

TOWNSHIP OF LOGAN SOIL & FILL IMPORTATION AND PLACEMENT APPLICATION SUBMITTAL CHECKLIST TOWNSHIP OF LOGAN SOIL & FILL IMPORTATION AND PLACEMENT APPLICATION SUBMITTAL CHECKLIST Applications: 5 copies of application - Applicant will reproduce the copies at his/her costs. The Township Clerk

More information

Humber Bay Shores Precinct Plan Final Report

Humber Bay Shores Precinct Plan Final Report STAFF REPORT ACTION REQUIRED Humber Bay Shores Precinct Plan Final Report Date: May 21, 2010 To: From: Wards: Reference Number: Etobicoke York Community Council Director, Community Planning, Etobicoke

More information

PLANNED UNIT DEVELOPMENT STAFF REPORT Date: June 2, 2016

PLANNED UNIT DEVELOPMENT STAFF REPORT Date: June 2, 2016 # 9 ZON2016-01032 PLANNED UNIT DEVELOPMENT STAFF REPORT Date: June 2, 2016 DEVELOPMENT NAME JJT Properties LLC LOCATION 1147 & 1151 East I-65 Service Road South and 1180 Sledge Drive (Southeast corner

More information

Project: Mooney Lake Preserve Received: Location: 300 Sixth Ave. N., Orono Complete: Noticed:

Project: Mooney Lake Preserve Received: Location: 300 Sixth Ave. N., Orono Complete: Noticed: Permit Application No.: 15-445 Rules: Erosion Control, Wetland Protection, & Stormwater Management Applicant: BPS Properties, LLC Project: Mooney Lake Preserve Received: 8-24-15 Location: 300 Sixth Ave.

More information

Big Thompson River Restoration Master Plan. Stakeholder Kick off Meeting and Workshop April 12, 2014

Big Thompson River Restoration Master Plan. Stakeholder Kick off Meeting and Workshop April 12, 2014 Big Thompson River Restoration Master Plan Stakeholder Kick off Meeting and Workshop April 12, 2014 AGENDA 1:30 to 2:10 Information 2:10 to 2:35 Questions 245t 2:45 to 4:00 400 Worksession in Cafeteria

More information

Pennsylvania Stormwater Best Management Practices Manual. Chapter 1. Introduction and Purpose

Pennsylvania Stormwater Best Management Practices Manual. Chapter 1. Introduction and Purpose Pennsylvania Stormwater Best Management Practices Manual Chapter 1 Introduction and Purpose Chapter 1 Introduction and Purpose 1.1 Purpose of this Manual 1 1.2 How to Use this Manual...1 1.3 Overview

More information

PLANNING APPROVAL & SIDEWALK WAIVER STAFF REPORT Date: December 1, 2016

PLANNING APPROVAL & SIDEWALK WAIVER STAFF REPORT Date: December 1, 2016 PLANNING APPROVAL & SIDEWALK WAIVER STAFF REPORT Date: December 1, 2016 NAME Dennis P. Wilkins LOCATION. CITY COUNCIL DISTRICT District 6 7078 Bruns Drive (Northeast corner of Bruns Drive and Cody Road)

More information

PALM BEACH COUNTY PLANNING, ZONING AND BUILDING DEPARTMENT ZONING DIVISION

PALM BEACH COUNTY PLANNING, ZONING AND BUILDING DEPARTMENT ZONING DIVISION PALM BEACH COUNTY PLANNING, ZONING AND BUILDING DEPARTMENT ZONING DIVISION Petition No.: Z2004-016 Petitioner: PBC Facilities Development & Operations Owner: Palm Beach County Agent: Melaine Borkowski

More information

Poisoned Park? How Exide s Lead Contamination Risks Frisco s Grand Park

Poisoned Park? How Exide s Lead Contamination Risks Frisco s Grand Park Frisco City Hall has big plans to transform Stewart Creek into a Grand Park with lots of water features for kids to play in. Poisoned Park? How Exide s Lead Contamination Risks Frisco s Grand Park But

More information

Zoning Ordinance Article 3

Zoning Ordinance Article 3 Article 3 Natural Resources Protection Section 301 Natural Resources Protection 301.1. Purpose - The following natural resources protection standards are established to protect the public health, safety

More information

Application for Certification for an Alarm System Contractor

Application for Certification for an Alarm System Contractor Application for Certification for an Alarm System Contractor IOWA STATE FIRE MARSHAL S OFFICE 215 E 7 th STREET DES MOINES, IA 50319 PH: 515-725-6145 FAX: 515-725-6172 NEW AMEND RENEWAL This form is to

More information

PLANNED UNIT DEVELOPMENT Date: April 5, 2018

PLANNED UNIT DEVELOPMENT Date: April 5, 2018 PLANNED UNIT DEVELOPMENT Date: April 5, 2018 DEVELOPMENT NAME SUBDIVISION NAME LOCATION Robert Myers Robert Myers 2955 and 2989 Dauphin Street (Southeast corner of Dauphin Street and Sage Avenue) CITY

More information

WELCOME! 8 8:30 6: TH STREET IMPROVEMENTS. Open House. Presentation & Q&A

WELCOME! 8 8:30 6: TH STREET IMPROVEMENTS. Open House. Presentation & Q&A WELCOME! 168 TH STREET IMPROVEMENTS 6:30 Open House 7 8 Presentation & Q&A 8 8:30 Open House WELCOME Todd Pfitzer City of Omaha Engineer Bob Stubbe City of Omaha Public Works Director Jon Meyer Project

More information

SPECIFIC DESIGN PLAN

SPECIFIC DESIGN PLAN The Maryland-National Capital Park and Planning Commission Prince George's County Planning Department Development Review Division 301-952-3530 Note: Staff reports can be accessed at www.mncppc.org/pgco/planning/plan.htm.

More information

5. LOW IMPACT DEVELOPMENT DESIGN STANDARDS

5. LOW IMPACT DEVELOPMENT DESIGN STANDARDS 5. LOW IMPACT DEVELOPMENT DESIGN STANDARDS Low Impact Development (LID) requires a shift in stormwater management away from conveying runoff to a small number of downstream points through hydraulically

More information

GREEN SHEET ENVIRONMENTAL COMMITMENTS FOR THE IOWA HIGHWAY 100 EXTENSION

GREEN SHEET ENVIRONMENTAL COMMITMENTS FOR THE IOWA HIGHWAY 100 EXTENSION County: Linn County, IA GREEN SHEET Location: IA 100, from its terminus at Edgewood Rd. to US 30 southwest of Cedar Rapids Route: IA 100 Extension Project No.: NHS-100-1(36) 19-57 OLE Project Managers:

More information

City Of Sparks Planning Commission Item

City Of Sparks Planning Commission Item Page 1 of 12 City Of Sparks Planning Commission Item Meeting Date: May17, 2012 Subject: PCN12009, Public Hearing, Consideration and possible action on a Master Plan Amendment and Rezoning request to change

More information

R E S O L U T I O N. Designation: Section 2, Block 17, Lot 20.G-1 ( ) R-2A (1-Family, 2-acre Minimum Lot Size) 46 North Greenwich Road

R E S O L U T I O N. Designation: Section 2, Block 17, Lot 20.G-1 ( ) R-2A (1-Family, 2-acre Minimum Lot Size) 46 North Greenwich Road PLANNING BOARD Arthur Adelman, Chair TOWN OF NORTH CASTLE WESTCHESTER COUNTY 17 Bedford Road Armonk, New York 10504-1898 R E S O L U T I O N Telephone: (914) 273-3542 Fax: (914) 273-3554 www.northcastleny.com

More information

TO: Port of Orcas FROM: Tina Whitman, Science Director SUBJECT: Master Plan Update DATE: September 7, 2018

TO: Port of Orcas FROM: Tina Whitman, Science Director SUBJECT: Master Plan Update DATE: September 7, 2018 TO: Port of Orcas FROM: Tina Whitman, Science Director SUBJECT: Master Plan Update DATE: September 7, 2018 Friends of the San Juans appreciates the opportunity to provide input to the Port of Orcas Master

More information

DEPARTMENT OF PLANNING JEFFERSON PARISH, LOUISIANA

DEPARTMENT OF PLANNING JEFFERSON PARISH, LOUISIANA DEPARTMENT OF PLANNING JEFFERSON PARISH, LOUISIANA DESIGN REVIEW REPORT DOCKET NO: : : : Paul D. Johnston AT LARGE: A: Christopher L. Roberts B: Cynthia Lee-Sheng ADVERTISING DATES: PAB PUBLIC HEARING:

More information

Asbury Chapel Subdivision Sketch Plan

Asbury Chapel Subdivision Sketch Plan Asbury Chapel Subdivision Sketch Plan PART 1: PROJECT SUMMARY Applicant: NVR Inc. Project Size: +/- 76.13 acres Parcel Numbers: 02101112,02116101,02116112, 02116113 Current Zoning: Transitional Residential

More information

Camden County Development Regulations. Updated February 2017

Camden County Development Regulations. Updated February 2017 Camden County Development Regulations Updated February 2017 GENERAL MEETING SCHEDULE OF THE CAMDEN COUNTY PLANNING BOARD All meetings will convene at 6:00 PM on the 4th Tuesday of each month and will be

More information

Rapid City Planning Commission Rezoning Project Report

Rapid City Planning Commission Rezoning Project Report Rapid City Planning Commission Rezoning Project Report July 21, 2016 Applicant Request(s) Case # 16RZ022 Rezoning from Office Commercial District to Light Industrial District Companion Case(s): 16RZ023-Rezoning

More information

Village of Glenview Appearance Commission

Village of Glenview Appearance Commission Village of Glenview Appearance Commission STAFF REPORT July 23, 2014 TO: Chairman and Appearance Commissioners CASE #: A2014-059 LOCATION: 727 Harlem Avenue FROM: Community Development Department PROJECT

More information

The Town Board of the Town of Vienna, County of Dane, State of Wisconsin, does ordain and adopt as follows.

The Town Board of the Town of Vienna, County of Dane, State of Wisconsin, does ordain and adopt as follows. ORDINANCE DRIVEWAYS AND CULVERTS NO. 6-5-06 ORDINANCE CONCERNING DRIVEWAY AND CULVERT REQUIREMENTS 1-1-1 Driveway Permits; Culvert Requirements 1-1-2 Driveway and Culvert Location, Design and Construction

More information

Approved: CITY OF ARDEN HILLS, MINNESOTA PLANNING COMMISSION WEDNESDAY, AUGUST 5, :30 P.M. - ARDEN HILLS CITY HALL

Approved: CITY OF ARDEN HILLS, MINNESOTA PLANNING COMMISSION WEDNESDAY, AUGUST 5, :30 P.M. - ARDEN HILLS CITY HALL Approved: CITY OF ARDEN HILLS, MINNESOTA PLANNING COMMISSION WEDNESDAY, AUGUST 5, 2015 6:30 P.M. - ARDEN HILLS CITY HALL PLANNING CASES A. Planning Case 15-016; Final Planned Unit Development Arden Plaza;

More information

MUNICIPAL SEPARATE STORM SEWER SYSTEM 2009 ANNUAL REPORT

MUNICIPAL SEPARATE STORM SEWER SYSTEM 2009 ANNUAL REPORT MUNICIPAL SEPARATE STORM SEWER SYSTEM 2009 ANNUAL REPORT Permit Number 85 03 0 04 March 2010 Prepared by: Iowa State University Department of Environmental Health and Safety 2809 Daley Drive Ames, Iowa

More information

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF MAY 27, 2014

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF MAY 27, 2014 CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF MAY 27, 2014 Item 6, Report No. 21, of the Committee of the Whole, which was adopted without amendment by the Council of the City of Vaughan on May

More information

Michael D, Harvey, Current Planning Supervisor. This project was originally approved in 2012 by the BOCC and is summarized as follows:

Michael D, Harvey, Current Planning Supervisor. This project was originally approved in 2012 by the BOCC and is summarized as follows: PLANNING & INSPECTIONS DEPARTMENT Craig N. Benedict, AICP, Director Current Planning (919) 245-2575 (919) 644-3002 (FAX) www.orangecountync.gov 131 W. Margaret Lane Suite 201 P. O. Box 8181 Hillsborough,

More information

Woodburn Comprehensive Plan Growth Management Goals and Policies

Woodburn Comprehensive Plan Growth Management Goals and Policies Goal Woodburn Comprehensive Plan Growth Management Goals and Policies G-1. The City's goal is to manage growth in a balanced, orderly and efficient manner, consistent with the City s coordinated population

More information

Planning Commission Retreat March 23 rd Comprehensive Plan Update Discussion

Planning Commission Retreat March 23 rd Comprehensive Plan Update Discussion Planning Commission Retreat March 23 rd 2011 Comprehensive Plan Update Discussion Purpose of This Discussion Go Over Key Aspects of the Update Discuss Element By Element Key Concepts Big Ideas What Policies

More information

Rezoning Transportation Analysis Petition Number: General Location Identifier:

Rezoning Transportation Analysis Petition Number: General Location Identifier: From: Kelsie Anderson, PE Kelsie.Anderson@charlottenc.gov 704-432-5492 Staff Reviewer: Kory Hedrick, PE, PMP Khedrick@charlottenc.gov 704-432-6511 CDOT s review of this rezoning petition is intended to

More information

DRIVEWAY REGULATIONS

DRIVEWAY REGULATIONS TOWN OF NEW LONDON PLANNING BOARD DRIVEWAY REGULATIONS INSTRUCTIONS TO APPLICANTS FOR THE CONSTRUCTION OR ALTERATION OF DRIVEWAYS IMPORTANT: READ CAREFULLY BEFORE FILLING OUT ATTACHED APPLICATION Revised

More information

COLVER ROAD INDUSTRIAL CONCEPT PLAN

COLVER ROAD INDUSTRIAL CONCEPT PLAN COLVER ROAD INDUSTRIAL CONCEPT PLAN A CONCEPTUAL LAND USE AND TRANSPORTATION PLAN FOR TA-4 AN URBAN RESERVE AREA OF THE CITY TALENT City of Talent Adopted by City Council Resolution No., June, 2015 PART

More information

Chapter 1 Vision Statement & Goals

Chapter 1 Vision Statement & Goals Chapter 1 Section 1.1 Section 1.2 Section 1.3 Section 1.4 Section 1.5 Introduction Vision Statement Visioning Exercise Prioritization of Land Use Issues Goals of the Comprehensive Plan CHAPTER 1 SECTION

More information

STAFF REPORT FOR STANDARD COASTAL DEVELOPMENT PERMIT #CDP FEBRUARY 26, 2015 CPA - 1 PO BOX 238 APTOS, CA 94001

STAFF REPORT FOR STANDARD COASTAL DEVELOPMENT PERMIT #CDP FEBRUARY 26, 2015 CPA - 1 PO BOX 238 APTOS, CA 94001 STAFF REPORT FOR STANDARD COASTAL DEVELOPMENT PERMIT #CDP 2014-0030 FEBRUARY 26, 2015 CPA - 1 OWNER/APPLICANT: AGENT: REQUEST: HANS HEIM PO BOX 238 APTOS, CA 94001 JAMES HAY PO BOX 762 MENDOCINO, CA 95460

More information

Radnor Township. Factors affecting storm water issues.

Radnor Township. Factors affecting storm water issues. Radnor Township Factors affecting storm water issues. Climate Changes and Changing Weather Patterns Intensity of rains over the last 7 to 10 years. Larger number of smaller storms delivering greater amounts

More information

RRW Stonebrook, LLC Tentative Map Findings

RRW Stonebrook, LLC Tentative Map Findings RRW Stonebrook, LLC Tentative Map Findings FINDING T1: The request conforms to the Master Plan and zoning ordinances. RELATIONSHIP TO THE MASTER PLAN 1. The respective development is located within an

More information

Goal 1 To establish and follow land use patterns for the long-range development of the campus.

Goal 1 To establish and follow land use patterns for the long-range development of the campus. ELEMENT 4 FUTURE LAND USE Goal 1 To establish and follow land use patterns for the long-range development of the campus. Objective 1A Correct existing incompatible campus land uses. Policy 1A-1 Reduce

More information

GRACE CHURCH EXPANSION

GRACE CHURCH EXPANSION GRACE CHURCH EXPANSION REVIEW: NOVEMBER 24, 2014 200 SAGE ROAD, CHAPEL HILL NORTH CAROLINA PROJECT DATA OVERALL SITE MAP SITE INFORMATION OWNER PIN ACREAGE VICINITY MAP GRACE CHURCH 9890503171 271,600

More information

Review Zone Application for D&R Canal Commission Decision

Review Zone Application for D&R Canal Commission Decision Review Zone Application for D&R Canal Commission Decision MEETING DATE: July 20, 2016 DRCC #: 16-4803 Latest Submission Received: June 13, 2016 Applicant: Robert McCarthy, PE PSE&G 4000 Hadley Road, 2

More information

COMMISSION ACTION FORM

COMMISSION ACTION FORM ITEM #: 6 DATE: 09-06-17 COMMISSION ACTION FORM REQUEST: Introduction and Initial Review of Proposed Amendments to the Ames Urban Fringe Future Land Map for the North Growth Gap Area BACKGROUND INFORMATION:

More information

Town of Malta Planning Board 2540 Route 9 Malta, NY (518) Fax: (518)

Town of Malta Planning Board 2540 Route 9 Malta, NY (518) Fax: (518) William Smith - Chairman Dave Bowman Kyle Kordich Roger Laime Jean Loewenstein John Viola David Wallingford Joseph Lopez (Alt) Town of Malta Planning Board 2540 Route 9 Malta, NY 12020 (518) 899-2685 Fax:

More information

Erosion & Sediment Control Plan Application Form & Checklist

Erosion & Sediment Control Plan Application Form & Checklist Erosion & Sediment Control Plan Application Form & Checklist GENERAL INFORMATION Application Date: Project Address: Tax Map / Parcel Number(s): PROPERTY OWNER / DEVELOPER Firm Name: Contact Person: Title:

More information

Complete Neighbourhood Guidelines Review Tool

Complete Neighbourhood Guidelines Review Tool Complete Neighbourhood Guidelines Review Tool Prepared By: City of Regina Planning Department October 2014 Page 1 of 14 Community Development Review Checklist for Secondary Plans and Concept Plans The

More information

North Metro Natural Gas Pipeline Project Routing Study. Exhibit I: Comment and Response Document

North Metro Natural Gas Pipeline Project Routing Study. Exhibit I: Comment and Response Document North Metro Natural Gas Pipeline Project Routing Study Exhibit I: Comment and Response Document North Metro Natural Gas Pipeline Project Routing Study This page intentionally left blank. North Metro Natural

More information

General Location Annex, Rezone & Preliminary Plat Lansdowne Addition, Unit Three

General Location Annex, Rezone & Preliminary Plat Lansdowne Addition, Unit Three NEWFOUNDLAND I-5 Agricultural District Subject Site SUNDANCE ANDERSON Single Family Residential CHRISTY PUD Agricultural District Highway Business General Location Annex, Rezone & Preliminary Plat Lansdowne

More information

Chesapeake Bay Critical Area Conservation Plan

Chesapeake Bay Critical Area Conservation Plan The Maryland-National Capital Park and Planning Commission Prince George s County Planning Department Development Review Division 301-952-3530 Note: Staff reports can be accessed at www.mncppc.org/pgco/planning/plan.htm.

More information

UNIVERSITY PRESBYTERIAN CHURCH - RENOVATION & ADDITION 209 EAST FRANKLIN ST., CHAPEL HILL, NC 27514

UNIVERSITY PRESBYTERIAN CHURCH - RENOVATION & ADDITION 209 EAST FRANKLIN ST., CHAPEL HILL, NC 27514 UNIVERSITY PRESBYTERIAN CHURCH - RENOVATION & ADDITION 209 EAST FRANKLIN ST., CHAPEL HILL, NC 27514 PROJECT DATA OVERALL SITE MAP HDC CONCEPT PLAN SUBMITTAL: OCT. 8, 2012 SUP SUBMITTAL: MAY 28, 2013 SUP

More information

APPENDIX K WINDSOR OFFICIAL PLAN

APPENDIX K WINDSOR OFFICIAL PLAN CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT Replacement Span and Plaza Expansion APPENDIX K WINDSOR OFFICIAL PLAN Avalon Consulting Professionals of Ontario,

More information

We have reviewed the proposed concept plans for Beehive Homes and have the following comments:

We have reviewed the proposed concept plans for Beehive Homes and have the following comments: 12800 Arbor Lakes Parkway, P.O. Box 1180, Maple Grove, MN 55311-6180 FIRE-RESCUE DEPARTMENT Fire Operations Fire Prevention 763-494-6300 763-494-6090 763-494-6421 Fax 763-494-6439-Fax August 22, 2018 RE:

More information

KNOXVILLE/KNOX COUNTY METROPOLITAN PLANNING COMMISSION SUBDIVISION REPORT - CONCEPT/USE ON REVIEW

KNOXVILLE/KNOX COUNTY METROPOLITAN PLANNING COMMISSION SUBDIVISION REPORT - CONCEPT/USE ON REVIEW KNOXVILLE/KNOX COUNTY METROPOLITAN PLANNING COMMISSION SUBDIVISION REPORT - CONCEPT/USE ON REVIEW FILE #: 10-SF-17-C 10-I-17-UR AGENDA ITEM #: 12 AGENDA DATE: 11/9/2017 POSTPONEMENT(S): 10/12/2017 SUBDIVISION:

More information

PLANNING APPROVAL & PLANNED UNIT DEVELOPMENT Date: April 6, 2017

PLANNING APPROVAL & PLANNED UNIT DEVELOPMENT Date: April 6, 2017 PLANNING APPROVAL & PLANNED UNIT DEVELOPMENT Date: April 6, 2017 DEVELOPMENT NAME LOCATION Mobile Christian School 5900 Cottage Hill Road (North side of Cottage Hill Road, 230 ± West of Freemont Drive

More information

South fields. Community Architectural Design Guidelines. The Planning Partnership

South fields. Community Architectural Design Guidelines. The Planning Partnership South fields Community Architectural Design Guidelines The Planning Partnership Table Of Contents Table of Contents 1.0 GUIDING PRINCIPLES 1.1 Function of Architectural Design Guidelines 1.2 Administration

More information

Red Hill Valley Project More Than A Road October 16, 2006

Red Hill Valley Project More Than A Road October 16, 2006 Red Hill Valley Project Presented By: More Than A Road October 16, 2006 September, 2007 Gerry Davis, C.M.A., Senior Director, Capital Planning and Implementation Division Public Works Department City of

More information

PLANNED UNIT DEVELOPMENT & PLANNING APPROVAL STAFF REPORT Date: April 4, 2013

PLANNED UNIT DEVELOPMENT & PLANNING APPROVAL STAFF REPORT Date: April 4, 2013 PLANNED UNIT DEVELOPMENT & PLANNING APPROVAL STAFF REPORT Date: April 4, 2013 NAME LOCATION The North American Islamic Trust, Inc. 63 East Drive (East side of East Drive, 400 South of Old Shell Road, and

More information

CITY OF FORT COLLINS TYPE 1 ADMINISTRATIVE HEARING FINDINGS AND DECISION. Elevations Credit Union (2025 S. College Avenue)

CITY OF FORT COLLINS TYPE 1 ADMINISTRATIVE HEARING FINDINGS AND DECISION. Elevations Credit Union (2025 S. College Avenue) CITY OF FORT COLLINS TYPE 1 ADMINISTRATIVE HEARING FINDINGS AND DECISION HEARING DATE: September 28, 2016 PROJECT NAME: Elevations Credit Union (2025 S. College Avenue) CASE NUMBER: PDP #160021 APPLICANT:

More information

What Can We Do to Reduce the Impact of Floods? Joe Barron, P.E. Fletcher Group, Inc. 148 River St. Suite 220 Greenville, S.C.

What Can We Do to Reduce the Impact of Floods? Joe Barron, P.E. Fletcher Group, Inc. 148 River St. Suite 220 Greenville, S.C. What Can We Do to Reduce the Impact of Floods? Joe Barron, P.E. Fletcher Group, Inc. 148 River St. Suite 220 Greenville, S.C. 29601 1 Historical highlights of flood management attempts 1726 first New Orleans

More information

APPLICATION FOR MINOR SITE PLAN REVIEW

APPLICATION FOR MINOR SITE PLAN REVIEW www.appleton.org APPLICATION FOR MINOR SITE PLAN REVIEW Community and Economic Development Department 100 N. Appleton St. PH: 920-832-6468 Appleton, WI 54911 FAX: 920-832-5994 Stamp date received PROPERTY

More information

ATTACHMENT 1 WILSON MINE LECROY AREA SEMIPERMANENT DEWATERING SYSTEM

ATTACHMENT 1 WILSON MINE LECROY AREA SEMIPERMANENT DEWATERING SYSTEM ATTACHMENT 1 WILSON MINE LECROY AREA SEMIPERMANENT DEWATERING SYSTEM Reclamation plans for the Wilson Mine Lecroy area were approved by the Arkansas Department of Environmental Quality with a passive barrier

More information

Northern Branch Corridor DEIS December 2011

Northern Branch Corridor DEIS December 2011 16 Floodplains 161 Chapter Overview 1611 Introduction The flowing chapter identifies floodplains found within the Northern Branch Corridor in accordance with Executive Order 11988, Floodplain Management

More information

ARTICLE VI: SITE PLAN REVIEW

ARTICLE VI: SITE PLAN REVIEW Section 6.01 - Site Plan Review (All Districts) ARTICLE VI: SITE PLAN REVIEW Site plans give the Planning commission an opportunity to review development proposals in a concise and consistent manner. The

More information

City of Westbrook. 2 York Street Westbrook, Maine (207) Fax:

City of Westbrook. 2 York Street Westbrook, Maine (207) Fax: City of Westbrook DEPARTMENT OF PLANNING & CODE ENFORCEMENT 2 York Street Westbrook, Maine 04092 (207) 854-0638 Fax: 1-866-559-0642 WESTBROOK PLANNING BOARD TUESDAY, JANUARY 2, 2018, 7:00 P.M. WESTBROOK

More information

Port Marigny TND Planning and Zoning Commission Workshop September 1, 2015 Preliminary Observations - David Bailey, AIA, AICP

Port Marigny TND Planning and Zoning Commission Workshop September 1, 2015 Preliminary Observations - David Bailey, AIA, AICP Planning and Zoning Commission Workshop September 1, 2015 Preliminary Observations - David Bailey, AIA, AICP Outline, per 8-27-15 Memorandum: 1. Background 2. General Observations 3. Comprehensive Plan

More information

Warren County/Bowling Green Focus 2030 Comprehensive Plan VOLUME 1 INDEX

Warren County/Bowling Green Focus 2030 Comprehensive Plan VOLUME 1 INDEX Appendix 5: Index VOLUME 1 INDEX A Aesthetics ES-6, FLU-15, FLU-17, FLU-24, NCR-7 Agricultural Base FLU-18, FLU-20 Agricultural Centers, Rural FLU-11 Agricultural District NCR-17-NCR-18 Agricultural Economy

More information

7 May 9, 2012 Public Hearing APPLICANT AND PROPERTY OWNER: COASTAL ENTERPRISES, LLC

7 May 9, 2012 Public Hearing APPLICANT AND PROPERTY OWNER: COASTAL ENTERPRISES, LLC 7 May 9, 2012 Public Hearing APPLICANT AND PROPERTY OWNER: COASTAL ENTERPRISES, LLC REQUEST: Variance to Section 5B of the Site Plan Ordinance (Floodplain Regulations) ADDRESS / DESCRIPTION: 601 Sandbridge

More information

KYTC and NFIP: Bridging Floodplain Management and Design KAMM CONFERENCE AUGUST 25, 2015

KYTC and NFIP: Bridging Floodplain Management and Design KAMM CONFERENCE AUGUST 25, 2015 KYTC and NFIP: Bridging Floodplain Management and Design KAMM CONFERENCE AUGUST 25, 2015 KYTC STATEWIDE DRAINAGE DESIGN Provide Drainage Design Services on an as needed basis: Perform hydraulic analysis

More information

When planning stormwater management facilities, the following principles shall be applied where possible.

When planning stormwater management facilities, the following principles shall be applied where possible. 2.0 Principles When planning stormwater management facilities, the following principles shall be applied where possible. 2.0.1 Drainage is a regional phenomenon that does not respect the boundaries between

More information

CHECKLIST FOR PHASE II DRAINAGE REPORT

CHECKLIST FOR PHASE II DRAINAGE REPORT I. COVER SHEET CHECKLIST FOR PHASE II DRAINAGE REPORT A. Name of Project B. Address C. Owner D. Developer E. Engineer F. Submittal date and revision dates as applicable II. GENERAL LOCATION AND DESCRIPTION

More information

MONTGOMERY COUNTY PLANNING DEPARTMENT THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION

MONTGOMERY COUNTY PLANNING DEPARTMENT THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION MONTGOMERY COUNTY PLANNING DEPARTMENT THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION MCPB Item No.: 11 Date: 06-28-18 Black Hill Infrastructure Site Plan Amendment No. 82013025C Benjamin Berbert,

More information

STORMWATER MANAGEMENT CODES ANALYSIS RICHLAND COUNTY, SC SITE PLANNING ROUNDTABLE

STORMWATER MANAGEMENT CODES ANALYSIS RICHLAND COUNTY, SC SITE PLANNING ROUNDTABLE STORMWATER MANAGEMENT CODES ANALYSIS RICHLAND COUNTY, SC SITE PLANNING ROUNDTABLE Codes analyses for each subcommittee were completed to assist participants of the Richland County Site Planning Roundtable.

More information

Improving an Urban Watershed The Past, Present and Future of Addison Creek

Improving an Urban Watershed The Past, Present and Future of Addison Creek Improving an Urban Watershed The Past, Present and Future of Addison Creek IAFSM Conference March 14, 2018 Stormwater Management 1 Stormwater Management 2 PAST Reservoirs and Channel Improvements Stormwater

More information

5. FINAL DEVELOPMENT PLAN APPROVAL MENORAH MEDICAL CENTER OFFICE BUILDING Vicinity of the southwest corner of 119 th Street and Nall Avenue

5. FINAL DEVELOPMENT PLAN APPROVAL MENORAH MEDICAL CENTER OFFICE BUILDING Vicinity of the southwest corner of 119 th Street and Nall Avenue 5. FINAL DEVELOPMENT PLAN APPROVAL MENORAH MEDICAL CENTER Avenue 1. APPLICANT: Hoefer Wysocki Architects, L.L.C., is the applicant for this request. 2. REQUESTED ACTION: The applicant is requesting final

More information

Variance Staff Report St. Croix County Board of Adjustment Ben Hanke / Calda Donna LLC Hearing Date: January 20 & 21, 2016

Variance Staff Report St. Croix County Board of Adjustment Ben Hanke / Calda Donna LLC Hearing Date: January 20 & 21, 2016 Applicant: Agent: Calda Donna LLC / Ben Hanke Bruce Lenzen Site Address: Salishan Drive Government Lots 1 and 2 Parcel ID #: 040-1146-40-000 Computer #: Site Location: Zoning District: Site Size: Requests:

More information

J. WILLIAM (BILL) BROWN Office Phone: (608) Cellular Phone: (817)

J. WILLIAM (BILL) BROWN Office Phone: (608) Cellular Phone: (817) J. WILLIAM (BILL) BROWN Office Phone: (608) 828-6333 Cellular Phone: (817) 879-8775 e-mail: Bill@floods.org ACADEMIC BACKGROUND Graduate Work, Biosystems and Agricultural Engineering, Water Resources Minor,

More information

APPLICATION FOR MINOR SITE PLAN REVIEW

APPLICATION FOR MINOR SITE PLAN REVIEW www.appleton.org APPLICATION FOR MINOR SITE PLAN REVIEW Community and Economic Development Department 100 N. Appleton St. PH: 920-832-6468 Appleton, WI 54911 FAX: 920-832-5994 Stamp date received PROPERTY

More information

Stormwater Utility and Connection Fees

Stormwater Utility and Connection Fees Stormwater Utility and Connection Fees Environmentally conscious We will make decisions that preserve and protect the environment to the highest feasible degree Outline (click question to be directed to

More information

Checklists. Project Name: Location: File Number: Date of Submittal: Reviewer: Date: Applicant: Contact Name: Phone Number:

Checklists. Project Name: Location: File Number: Date of Submittal: Reviewer: Date: Applicant: Contact Name: Phone Number: Applicant: Contact Name: Phone Number: Email: Project Name: Location: File Number: Date of Submittal: Reviewer: Date: Concept Plan Requirements: I. General Project Information 1. Address or parcel number

More information

McDonald s Restaurant - Purcellville Town of Purcellville Special Use Permit Statement of Justification July 24, 2014

McDonald s Restaurant - Purcellville Town of Purcellville Special Use Permit Statement of Justification July 24, 2014 Introduction / Written Statement McDonald s Restaurant - Purcellville McDonald s Corporation is proposing to redevelop the existing McDonald s eating establishment with a drive-through located at 121 N

More information

South Bismarck Watershed Model Update and Stormwater Improvement Project

South Bismarck Watershed Model Update and Stormwater Improvement Project Preliminary Engineering Report Bismarck Tribune South Bismarck Watershed Model Update and Stormwater Improvement Project City of Bismarck, ND January 2017 14.105.0046 1.0 Executive Summary The focus of