1 Executive Summary This report is an analysis of the existing systems within the Outreach Innovation Building in University Park, PA. One significant design criteria was a lower than average noise criteria within some spaces of the building such as the radio and television production rooms. The project is currently being constructed and therefore utility billing and energy consumption data is not available. General descriptions and system requirements are given for all air handlers, chilled water control sequence, and heating hot water control sequence. The critique of the system includes mechanical system costs (actual costs were not available, RS Means was used to estimate major equipment only), space requirements, maintainability, and environmental control and indoor air quality. Schedules and schematic diagrams were made using the design documents. Schematics include air handling diagrams, heating hot water diagram, and chilled water diagram. Schedules include all major equipment information. The analysis concluded that the existing systems are adequate in all areas analyzed.

2 Table of Contents Design Objectives and Requirements 1 Energy Sources and Rates 1 Site Factors 1 Design Conditions 2 System Requirements 3 Chilled Water Temperature Control System 4 Heating Hot Water Temperature Control Sequence 5 Operating History 5 Critique of System 6-7 AHU Diagram 1 8 AHU Diagram 2 9 Heating/Chilled Water Diagrams 10 Equipment Schedules 11-12

3 Design Objectives and Requirements The design requirements for the are that of a type B building in the International Building Code The mechanical systems must meet the heating/cooling loads and the ventilation requirements set by the International Building Code Noise Criteria was also considered due to the multiple television and radio studios throughout the building. An NC of 20 to 25 was designed for such spaces. Duct sizes were increased to reduce the velocity of the supply air and therefore lower the sound pressure level in order to comply with these design standards. Under-floor air distribution was used in open office areas. This enables a floor plan that can easily be changed. Also the large amounts of telecommunication cables can be placed within this raised floor area. Energy Sources and Rates The electricity rates for the were taken from a document about the West Penn Power Company: Rates, Terms, and Conditions Governing Interchange of Electricity with The Pennsylvania State University (Issued Dec 30, 2003). DEMAND CHARGE First 10,000 kilovolt-amperes Additional kilovolt-amperes ENERGY CHARGE All kilowatt-hours All kilowatt-hours $0.91 per kilovolt-ampere $0.90 per kilovolt-ampere $ per kilowatt-hour $ per kilowatt-hour (Effective ) Site Factors No major site factors influenced the design. The building is being built in a developing region on Penn State University land. 1

4 Design Conditions Outdoor design conditions Summer 89 F DB, 72 F MWB (0.4%) Winter 5 F DB (99.6%) Indoor design conditions 74 F and 50% relative humidity year round (Design conditions taken from ASHRAE Fundamentals 2001) Design Heating/Cooling Loads SYMBOL HEATING COOLING MBH MBH AHU-1A AHU-1B AHU-2A AHU-2B AHU-3A AHU-3B B B B CH CH CH

5 System Requirements AHU-1A, 1B, 2A, 2B General Description Air units are variable air volume units, comprised of the following: mixing box with separate minimum and modulating outdoor dampers, filter section, hot water heating coil, access section, chilled water cooling coil, humidifier, access section, and plenum supply fan. The system return fans are vane axial frequency drives. These units serve production areas on the First Floor. Freezestat shall de-energize the fans whenever the temperature falls below setpoint (36F, adj.). Smoke Detector: The unit shall shut down upon actuation of any smoke detector and initiation by the Fire Alarm System for air unit shutdown. Start Time Optimization: The Building Automation System (BAS) shall automatically calculate the optimum time to start the unit(s) based on space temperature, ambient temperature, and a building heat loss/gain coefficient in order to bring the space temperature to the proper setpoint no more than 15 minutes before scheduled occupancy time. Static Pressure High Limit Sensor: System shall turn off upon actuation of duct static pressure high limit sensor. Fan Tracking: Supply fan air volume shall be controlled with variable frequency drive via static pressure sensors in the supply air ductwork, setpoint 0.75 in/wg, adj. Return fan shall be modulated with variable frequency drive to maintain a fixed CFM differential between supply and return as measured by air measuring devices, equal to minimum outside air and/or building exhaust, plus building pressurization CFM. AHU-3A and 3B These units supply the under-floor air distribution system. General Description similar to AHU-1A, 1B, 2A, 2B above. 3

6 Chilled Water Temperature Control Sequence General Description The chilled water system is primary-secondary plant, comprised of the following components: air-cooled chillers with evaporator barrel remotely located in mechanical Penthouse, primary chilled water pumps (constant speed) dedicated to each evaporator barrel, and variable speed secondary chilled water pumps that deliver chilled water to terminal cooling coils. To prevent short cycling, each chiller shall run for a minimum of 30 minutes and be off a minimum of 20 minutes. On failure of the lead pump, the lag pump will run and the lead pump will be de-energized. The chiller will shut down and an alarm set off if a refrigerant leak is detected within the mechanical penthouse. The chiller plant shall be enabled to run whenever ambient temperature is greater than 50F. Secondary chilled water pump(s) will be energized any time the chiller(s) is called to run. Pump speed will be modulated to maintain differential pressure sensor setpoint of 25 ft/wg. 4

7 Heating Hot Water Temperature Control Sequence General Description The heating hot water system is primary-secondary plant, comprised of the following components: gas-fired hot water boilers, primary hot water pumps (constant speed) dedicated to each boiler, and variable speed secondary hot water pumps that deliver heating hot water to terminal heating units (coils, finned tube radiation, radiant ceiling panels, and cabinet unit heaters). To prevent short cycling of the boilers, each boiler shall run for a minimum of 5 minutes and be off a minimum of 1 minute. The boiler plant will run whenever ambient temperature is less than 65 F. Secondary hot water pump(s) will be energized any time the boiler(s) is called to run. Pump speed will be modulated to maintain differential pressure sensor setpoint of 15 ft/wg. Operating History The operating history for the is not available. (Building not complete as of November 15, 2004) 5

8 Critique of System Mechanical System Cost Actual mechanical system costs were not able to be obtained. Only major mechanical equipment such as air-handling units, chillers, boilers, etc. was taken into account. No piping, ductwork, under-floor air distribution system (including grilles), or labor were taken into consideration for this assignment. Actual bidding documents could not be obtained, therefore RS Means Facilities Construction Cost Data, 17 th Annual Edition was used to estimate the major mechanical equipment cost. Due to the omission of parts of the mechanical system the cost estimation is low compared to the actual value. The following chart is a breakdown of equipment estimated. RS MEANS 2002 Cost Estimation CHILLER SIZE TYPE QUANTITY UNIT PRICE TOTAL COST CH KW AIR CH KW AIR CH KW AIR AIR HANDLING SIZE TYPE QUANTITY UNIT PRICE TOTAL COST AHU-1A&B 10,000 CFM HORIZ. DRAW AHU-2A&B 17,500 CFM HORIZ. DRAW AHU-3A&B 35,000 CFM HORIZ. DRAW HUMIDIFIERS SIZE TYPE QUANTITY UNIT PRICE TOTAL COST H LBS/HR H LBS/HR H LBS/HR FAN SIZE TYPE QUANTITY UNIT PRICE TOTAL COST EF CFM EF CFM EF CFM EF CFM CSF CFM PUMP SIZE TYPE QUANTITY UNIT PRICE TOTAL COST P-1A&B 80 GPM INLINE P-2&3 280 GPM END SUCT P-4A&B 640 GPM END SUCT P-5,6,7 130 GPM INLINE P-8A&B 320 GPM END SUCT BOILER SIZE TYPE QUANTITY UNIT PRICE TOTAL COST B MBH TOTAL EQUIP. COST EQUIP. COST PER FT^

9 Space Requirements Floor area for the mechanical equipment including shaft area totals approximately 7,400 sq.ft. This does not include the exterior penthouse space which is approximately 1600 sq.ft. These areas appear to be adequate for the mechanical systems and do not seem to pose any problems such as duct or pipe layout, etc. Maintainability Serviceability of equipment does not appear to be an issue. All major equipment appears to have adequate clearance in order for maintenance and/or replacement of parts. Under-floor air distribution system allows for flexibility of spaces and access to under-floor VAV boxes and equipment. All ceilings allow for access to piping and ductwork where necessary. Environmental Control and Indoor Air Quality The ASHRAE Standard analysis showed that ventilation rates meet the minimum requirements and IAQ is not an issue. Equipment selected is also able to meet the required load, and therefore environmental control is also not an issue. 7

10 AHU 1A & 1B DIAGRAM (AHU-2A &2B SIMILAR, EXCEPT AS NOTED) COMPONENT LEGEND 1. MIXING BOX 2. PRE- AND FINAL FILTERS 3. HEATING COIL 4. ACCESS SECTION 5. COOLING COIL/ COND. DRAIN PAN 6. HUMIDIFIER 7. ACCESS SECTION 8. SUPPLY FAN (PLENUM TYPE) 9. RETURN FAN (VANE AXIAL TYPE) NOTES 1. MIXED AIR TEMPERATURE SETPOINT - AHU-1A/B = 49.5 F - AHU-2A/B = 51.5 F 2. DISCHARGE TEMPERATURE SETPOINT - AHU-1A/B = 50.5 F - AHU-2A/B = 52.5 F 3. STATIC PRESSURE SENSORS - AHU-1A/B = QTY.1 - AHU-2A/B = QTY.2 8

11 AHU 3A & 3B DIAGRAM (UNDERFLOOR AIR SYSTEM) COMPONENT LEGEND 1. MIXING BOX 2. PRE- AND FINAL FILTERS 3. HEATING COIL 4. ACCESS SECTION 5. COOLING COIL/ COND. DRAIN PAN 6. RETURN AIR BYPASS SECTION W/ FILTER AND CNTRL. DAMP. 7. HUMIDIFIER 8. ACCESS SECTION 9. SUPPLY FAN (PLENUM TYPE) 10. RETURN FAN (VANE AXIAL TYPE) 9

12 10

13 CHILLER SCHEDULE SYMBOL CAPACITY EVAPORATOR CONDENSER COMPRESSOR GENERAL REFRIGERANT (TON) GPM EWT(F) LWT(F) AMB. (F) QTY. FANS TOT. FAN KW TOTAL KW TOT. CH. KW V-Ph-Hz CH-1 54 HCFC CH HCFC CH HCFC BOILER SCHEDULE SYMBOL CAPACITY (MBH) BURNER (GAS) PRESSURE (IN/WG) DESIGN PRESSURE ELECTRICAL DATA INPUT OUTPUT MIN. MAX. (PSIG) AMPS V-Ph-Hz B B B AIR TERMINAL SCHEDULE AIR SEPARATOR SCHEDULE EXPANSION TANK SCHEDULE SYMBOL MIN CFM MAX CFM TYPE MAX SP. (IN/WG) SYMBOL SERVICE SYMBOL SERVICE TYPE AD AS-1 HW SYSTEM ET-1 HW SYS. VERTICAL AD AS-2 CW SYSTEM ET-2 CHW SYS. VERTICAL AD P-4A (4B) SECOND CHW AD AD AD AD AD AD CFM/LF - LINEAR 0.02 AD CFM/LF - LINEAR 0.05 AD AD ROUND CONE RG/EG EGGCRATE 0.05 RG/EG EGGCRATE 0.05 RG/EG EGGCRATE 0.05 RG/EG EGGCRATE 0.02 RG/EG BAR GRILLE 0.05 RG/EG BAR GRILLE 0.05 RG/EG BAR GRILLE 0.05 RG/EG BAR GRILLE 0.05 AIR HANDLING UNIT SCHEDULE (CONTINUED BELOW) SYMBOL TYPE SUPPLY FAN RETURN FAN COOLING COIL TOTAL CFM TSP (IN/WG) MIN OA CFM MOTOR HP TOTAL CFM TSP (IN/WG) MOTOR HP TOT TONS CFM EAT (DB/WB) LAT (DB/WB) FACE VEL. (FPM) EWT (F) LWT (F) GPM AHU-1A VAV HOR DRAW / / AHU-1B VAV HOR DRAW / / AHU-2A VAV HOR DRAW / / AHU-2B VAV HOR DRAW / / AHU-3A VAV HOR DRAW / / AHU-3B VAV HOR DRAW / / AIR HANDLING UNIT SCHEDULE (CONTINUED) SYMBOL PREHEAT COIL HUMIDIFIER TOTAL MBH CFM EAT (DB/WB) LAT (DB/WB) FACE VEL (FPM) EWT (F) LWT (F) GPM STEAM LB/HR STM PRES. (PSI) AHU-1A AHU-1B AHU-2A AHU-2B AHU-3A AHU-3B

14 FAN-POWERED TERMINAL BOX SCHEDULE - SERIES FLOW (FPB) SYMBOL PRIMARY AIR (COOLING) FAN DATA (HEATING) HEATING COIL HOT (HOT WATER) MAX CFM MIN CFM SP (IN/WG) SP (IN/WG) HP CFM MBH SP GPM EWT FPB FPB FPB FPB FPB FPB FPB FPB FAN COIL UNIT SCHEDULE SYMBOL FAN DATA HEATING COIL (HOT WATER) TOTAL CFM MIN OA CFM MOTOR HP&W V-Ph-Hz CFM CAPACITY (MBH) EAT (DB) LAT(DB) GPM EWT (F) FCU /16 95W FCU /8 95W FCU /8 125W FCU /8 125W FAN SCHEDULE SYMBOL CFM SP W.C. HP OR WATTS RPM TIP SPEED V-Ph-Hz EF /2 HP EF /3 HP EF HP EF W CSF W VARIABLE VOLUME BOX SCHEDULE (V V) SYMBOL INLET MAX DESIGN MIN. SP HEATING COIL (HOT WATER) (4) DIA (IN) CFM (1) CFM (2) (IN/WG) (3) CFM MBH (5) EAT (F) SP (IN/WG) (6) GPM (7) EWT (F) WPD (FT/WG) V V V V V V V V V V V V V V V V HUMIDIFIERS SYMBOL SERVICE TOTAL OUTDOOR AIR HUMIDITY ROOM TEMP MAX STEAM MAX INPUT GAS INLET ELECTRICAL CFM % (F) FLOW (LBS/HR) (MBH) PRES. (INWC) H-1 AHU 1A&1B FLA H-2 AHU 2A&2B FLA H-3 AHU 3A&3B PUMP SCHEDULE SYMBOL SERVICE TYPE PUMP MOTOR GPM HEAD (FT/WG) MHP RPM V-Ph-Hz P-1A (P-1B) PRIM CHW (CH-1) INLINE P-2 (P-3) PRIM CHW (CH-2&3) END SUCT P-4A (P-4B) SECOND CHW END SUCT P-5 (P-6&7) PRIM HW (B-1,2,3) INLINE P-8A (P-8B) SECOND HW END SUCT UNIT HEATER SCHEDULE SYMBOL TYPE HEATING COIL (HOT WATER) MBH GPM EAT (F) EWT (F) WPD (FT/WG) FAN CFM FAN HP V-Ph-Hz UH-1 HORIZ / UH-2 HORIZ /

Andrea Borowski The Pennsylvania State University University Park, PA November 11, 2002 Consultant: Dr. Bahnfleth Technical Assignment M-3

Andrea Borowski The Pennsylvania State University University Park, PA November 11, 2002 Consultant: Dr. Bahnfleth Technical Assignment M-3 Existing System Evaluation Executive Summary The MBNA Career Services Center is a 44,000 square foot, 4-story office type building at Penn State University, University Park Campus. The building is located

More information

The Creative and Performing Arts High School (CAPA) Pittsburgh, PA 11/11/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma

The Creative and Performing Arts High School (CAPA) Pittsburgh, PA 11/11/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma Objectives and Requirements For the Creative and Performing Arts High School (CAPA), the main objective of the mechanical design is to provide an energy efficient system that is easily maintainable and

More information

I. Introduction and Arrangement

I. Introduction and Arrangement Joseph Firrantello - Mechanical Option Primary Faculty Consultant: Freihaut Laboratory Facility, Eastern Pennsylvania Mechanical Assignment 3 Existing Conditions Report 11.14.03 Executive Summary The purpose

More information

Technical Report #3 Mechanical Systems Existing Conditions Evaluation

Technical Report #3 Mechanical Systems Existing Conditions Evaluation Mechanical Option Technical Report #3 Technical Report #3 Mechanical Systems Existing Conditions Evaluation Instructor: Dr. Bahnfleth 11.15.04 Building Sponsor: CCG Facilities Integration Table of Contents

More information

4. OVERVIEW OF MECHANICAL SYSTEM

4. OVERVIEW OF MECHANICAL SYSTEM 4. OVERVIEW OF MECHANICAL SYSTEM The 87,000 SF SLCC is served by six (6) Trane M-Series Climate Changer Air Handing Units (AHUs). Each unit serves a distinct zone within the facility that is unique in

More information

SECTION SEQUENCE OF OPERATIONS FOR HVAC CONTROLS

SECTION SEQUENCE OF OPERATIONS FOR HVAC CONTROLS SECTION 23 09 93 SEQUENCE OF OPERATIONS FOR HVAC CONTROLS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes control sequences for HVAC systems, subsystems, and equipment. B. See Division 23 Section

More information

A. Base Bid: 1. Heating Contractor provide: a. Control sequences for HVAC systems, subsystems, and equipment.

A. Base Bid: 1. Heating Contractor provide: a. Control sequences for HVAC systems, subsystems, and equipment. SECTION 23 09 93 - SEQUENCE OF OPERATIONS FOR HVAC CONTROLS PART 1 - GENERAL 1 WORK INCLUDES A. Base Bid: Heating Contractor provide: Control sequences for HVAC systems, subsystems, and equipment. B. Alternate

More information

Technical Assignment 3. Mechanical Systems Existing Conditions Evaluation

Technical Assignment 3. Mechanical Systems Existing Conditions Evaluation Technical Assignment 3 Mechanical Systems Existing Conditions Evaluation The Milton Hershey School New Supply Center Prepared for: William P. Bahnfleth, Ph.D., P.E., Professor Department of Architectural

More information

SHOE PALACE HUNTINGTON PARK M.200

SHOE PALACE HUNTINGTON PARK M.200 M.200 SPLIT SYSTEM CONDENSING UNIT SCHEDULE MARK SERVICE MODEL NO. COOLING DIMENSIONS ELECTRICAL REMARKS CAPACITY AMBIENT DB REFRIGERANT LENGTH WIDTH HEIGHT WEIGHT VOLT/PHASE MCA MOP (MBH) (DEG F) (IN)

More information

SECTION SEQUENCE OF OPERATIONS FOR HVAC CONTROLS

SECTION SEQUENCE OF OPERATIONS FOR HVAC CONTROLS PART 1 - GENERAL SECTION 23 09 93 SEQUENCE OF OPERATIONS FOR HVAC CONTROLS 1.1 SUMMARY A. This Section includes control sequences for HVAC systems, subsystems, and other equipment. B. See Division 23 Section

More information

C13-Series Engineering Guide

C13-Series Engineering Guide Engineering Guide Effective January 2018 Horizontal Air-Cooled, Water-Cooled, Chilled Water and Heat Pump Contents Product Features............................... 3 Product Options................................

More information

VertiCool Aurora Engineering Guide

VertiCool Aurora Engineering Guide Engineering Guide Effective August 2016 Air-Cooled, Water-Cooled and Water Source Heat Pump Contents Product Features... 3 Options... 4 Physical Data...5-6 Air-Cooled Performance Data (a) (b) (c)...7-8

More information

VERSECON Indoor Vertical Self-Contained Air Conditioner YSWU Ton Water-Cooled

VERSECON Indoor Vertical Self-Contained Air Conditioner YSWU Ton Water-Cooled FORM 145.05-EG1 (1004) VERSECON Indoor Vertical Self-Contained Air Conditioner YSWU 10 105 Ton Water-Cooled Table of Contents FORM 145.05-EG1 (0804) Features and Benefits.....................................................

More information

Technical Development Program. COMMERCIAL HVAC PACKAGED EQUIPMENT Split Systems PRESENTED BY: Ray Chow Sigler

Technical Development Program. COMMERCIAL HVAC PACKAGED EQUIPMENT Split Systems PRESENTED BY: Ray Chow Sigler Technical Development Program COMMERCIAL HVAC PACKAGED EQUIPMENT Split Systems PRESENTED BY: Ray Chow Sigler Menu Section 1 Section 2 Section 3 Section 4 Section 5 Section 6 Section 7 Introduction System

More information

Mechanical Systems Existing Conditions Evaluation. Instructor: Dr. Bahnfleth. November 12, Thesis Building Sponsor s: INOVA Fairfax Hospital

Mechanical Systems Existing Conditions Evaluation. Instructor: Dr. Bahnfleth. November 12, Thesis Building Sponsor s: INOVA Fairfax Hospital David J. Peterson Mechanical Option Mechanical Technical Report #3 The INOVA HEART INSTITUTE AT, Falls Church, VA. Mechanical Technical Report #3 Mechanical Systems Existing Conditions Evaluation Instructor:

More information

Mechanical Technical Report 3. Mechanical Systems Existing Conditions Evaluation

Mechanical Technical Report 3. Mechanical Systems Existing Conditions Evaluation Mechanical Technical Report 3 Lutheran Theological Seminary at Philadelphia The New Learning Center Prepared For: William P. Bahnfleth, Ph.D., P.E. Department of Architectural Engineering Pennsylvania

More information

K*ES120 DESCRIPTION TECHNICAL GUIDE SPLIT-SYSTEM EVAPORATOR BLOWERS 10 NOMINAL TONS EER 8.5 ACCESSORIES FIELD INSTALLED TABLE 1: ARI RATINGS*

K*ES120 DESCRIPTION TECHNICAL GUIDE SPLIT-SYSTEM EVAPORATOR BLOWERS 10 NOMINAL TONS EER 8.5 ACCESSORIES FIELD INSTALLED TABLE 1: ARI RATINGS* TECHNICAL GUIDE SPLIT-SYSTEM EVAPORATOR BLOWERS K*ES120 10 NOMINAL TONS EER 8.5 DESCRIPTION These completely assembled dual circuit evaporator blower units include a well-insulated cabinet, a DX cooling

More information

VariCool VAV Engineering Guide

VariCool VAV Engineering Guide Engineering Guide Effective September 2017 Water-Cooled and Chilled Water, Variable Air Volume Contents Product Features... 3 UNIT FEATURES... 3 Product Features... 4 Marvel Plus Microprocessor Control

More information

ISERIES VERTICAL AHU ENGINEERING SPECIFICATIONS

ISERIES VERTICAL AHU ENGINEERING SPECIFICATIONS ISERIES VERTICAL AHU ENGINEERING SPECIFICATIONS BULLETIN 20-131.001 Page 1 Copyright 2017 Unico Inc. TABLE OF CONTENTS APPLICATIONS... 3 CABINET CONSTRUCTION... 3 FEATURES AND CONTROLS... 3 DIMENSIONAL

More information

EMBASSY SERIES SINGLE PACKAGE AIR CONDITIONERS (WATER-COOLED) C2ED060, 090, 120 & 180 5, 7-1/2, 10 & 15 Nominal Tons

EMBASSY SERIES SINGLE PACKAGE AIR CONDITIONERS (WATER-COOLED) C2ED060, 090, 120 & 180 5, 7-1/2, 10 & 15 Nominal Tons 560.20-TG1Y (388) EMBASSY SERIES SINGLE PACKAGE AIR CONDITIONERS (WATER-COOLED) C2ED060, 090, 120 & 180 5, 7-1/2, 10 & 15 Nominal Tons Each circuit includes a fully hermetic compressor with a crankcase

More information

CoolSpot Engineering Guide

CoolSpot Engineering Guide Engineering Guide Effective December 2017 Air-Cooled, Water-Cooled, Chilled Water or Magna Cool Precision Cooling Package Contents Contents....................................................... 2 Product

More information

SPLIT-SYSTEM EVAPORATOR BLOWER DESCRIPTION FEATURES L4EU NOMINAL TONS

SPLIT-SYSTEM EVAPORATOR BLOWER DESCRIPTION FEATURES L4EU NOMINAL TONS 036-21096-001 (0101) SPLIT-SYSTEM EVAPORATOR BLOWER L4EU240 20 NOMINAL TONS DESCRIPTION This 20 ton evaporator blower is designed with two distinct modules to provide maximum application flexibility. The

More information

VertiCool CLASSIC. Engineering Guide. Effective March Air-Cooled, Water-Cooled, Chilled Water and Water Source Heat Pump

VertiCool CLASSIC. Engineering Guide. Effective March Air-Cooled, Water-Cooled, Chilled Water and Water Source Heat Pump VertiCool CLASSIC Engineering Guide Effective March 2018 Air-Cooled, Water-Cooled, Chilled Water and Water Source Heat Pump Contents Product Features... 3 UNIT FEATURES... 3 OPTIONS:... 3 Physical Data...

More information

11/2 ORT THREEE. Virtua Repla. acement Hospi. ital. Voorhees NJ. Justin Prior. Mechanical

11/2 ORT THREEE. Virtua Repla. acement Hospi. ital. Voorhees NJ. Justin Prior. Mechanical 11/2 29 Virtua West Jersey Repla acement Hospi ital Voorhees NJ TECHNICAL REPO ORT THREEE System Overview Justin Prior Mechanical Table of Contents Executive Summary 3 System Overview 4 Design Factors

More information

EADQUARTERS. Technical Report One. Stephanie Kunkel Mechanical Option

EADQUARTERS. Technical Report One. Stephanie Kunkel   Mechanical Option EADQUARTERS 707 N. Calvert St. Technical Report One ASHRAE Standard 62.1 Ventilation ASHRAE Standard 90.1 Energy Design Stephanie Kunkel www.engr.psu.edu/ae/thesis/portfolios/2011/slk5061 Mechanical Option

More information

AIR HANDLER DESIGN WORK SHEET

AIR HANDLER DESIGN WORK SHEET AIR HANDLER DESIGN WORK SHEET JOB Project: Date Representative Unit Model No. of Units Unit Tag(s) UNIT CONSTRUCTION UNIT ARRANGEMENT: [ HORIZ VERT] [ INDOOR OUTDOOR] [ BASE MTD CEILING HUNG CURB MTD]

More information

Appendices. Included in this section are

Appendices. Included in this section are Appendices Included in this section are Appendix A Building Overview Appendix B Alternative Mechanical Designs Appendix C Integration of Structural System and Constructability 68 Appendix A Building Overview

More information

Technical Guide DESCRIPTION ACCESSORIES FIELD INSTALLED SPLIT-SYSTEM EVAPORATOR BLOWERS. 7-1/2 and 10 NOMINAL TONS LA090 & LA120 SUPPLY AIR PLENUMS

Technical Guide DESCRIPTION ACCESSORIES FIELD INSTALLED SPLIT-SYSTEM EVAPORATOR BLOWERS. 7-1/2 and 10 NOMINAL TONS LA090 & LA120 SUPPLY AIR PLENUMS Technical Guide SPLIT-SYSTEM EVAPORATOR BLOWERS 7-1/2 and 10 NOMINAL TONS LA090 & LA120 DESCRIPTION These completely assembled units include a well-insulated cabinet, a DX cooling coil with copper tubes

More information

1080 Marina Village Parkway, Suite 501 Alameda, CA (510) Fax (510) HVAC DESIGN INTENT

1080 Marina Village Parkway, Suite 501 Alameda, CA (510) Fax (510) HVAC DESIGN INTENT Taylor Engineering 1080 Marina Village Parkway, Suite 501 Alameda, CA 94501-1142 (510) 749-9135 Fax (510) 749-9136 LLC HVAC DESIGN INTENT PART 1 - GENERAL 1.1 Overview A. The project consists of a 3-story

More information

photo by PFC Price Fan Column

photo by   PFC Price Fan Column photo by www.mrobinsonphoto.com PFC Price Fan Column Typical Applications The Price Fan Column (PFC) is a vertical fan unit designed to discharge into a raised access floor plenum. The unit s compact design

More information

CHAMPION SPLIT-SYSTEM EVAPORATOR BLOWER DESCRIPTION FEATURES L2EU NOMINAL TONS

CHAMPION SPLIT-SYSTEM EVAPORATOR BLOWER DESCRIPTION FEATURES L2EU NOMINAL TONS 550.23-TG5Y (893) CHAMPION SPLIT-SYSTEM EVAPORATOR BLOWER L2EU240 20 NOMINAL TONS DESCRIPTION This 20 ton evaporator blower is designed with two distinct modules to provide maximum application flexibility.

More information

The Temperature and Relative Humidity Control in Cushing Library

The Temperature and Relative Humidity Control in Cushing Library The Temperature and Relative Humidity Control in Cushing Library Chenggang Liu Research Associate Song Deng Assistant Director Homer L. Bruner, Jr., CEM Mechanical Systems Specialist Utilities Office of

More information

Technical Assignment 3 Mechanical Systems Existing Conditions Evaluation

Technical Assignment 3 Mechanical Systems Existing Conditions Evaluation Technical Assignment 3 Mechanical Systems Existing Conditions Evaluation City of Hope: Amini Medical Center Duarte, CA Christopher Bratz Pennsylvania State University Architectural Engineering Mechanical

More information

R7DA Series TECHNICAL SPECIFICATIONS. FEATURES and BENEFITS. 6 and 7 ½ Ton DOAS Packaged Gas/Electric Units

R7DA Series TECHNICAL SPECIFICATIONS. FEATURES and BENEFITS. 6 and 7 ½ Ton DOAS Packaged Gas/Electric Units TECHNICAL SPECIFICATIONS R7DA Series 6 and 7 ½ Ton DOAS Packaged Gas/Electric Units 5.4 ISMRE Commercial System 81% Steady State Efficiency Standard Features Fits Pre-Existing Curbs High-Efficiency Low

More information

H3/V3 Series Horizontal and Vertical Indoor Air Handling Units. Engineering Catalog

H3/V3 Series Horizontal and Vertical Indoor Air Handling Units. Engineering Catalog H3/V3 Series Horizontal and Vertical Indoor Air Handling Units Engineering Catalog Table of Contents AAON H3/V3 Series Features and Options Introduction... 6 H3/V3 Base Model Description... 7 Unit Size...

More information

HVAC Mandatory Provisions Part II, Page 1

HVAC Mandatory Provisions Part II, Page 1 HVAC Mandatory Provisions Part II, Page 1 Mandatory Equipment Efficiency Worksheet (6.4.1.1) System Equipment Type Size Category (Tables 6.8.1A through K) Sub-Category or Rating Condition Units of Efficiency

More information

City of Duluth Festival Center 04/25

City of Duluth Festival Center 04/25 SECTION 230593 - TESTING, ADJUSTING, AND BALANCING FOR HVAC PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and

More information

Architectural Alliance Incorporated MDP CONSULTING ENGINEERS, INC N 11th Street Beaumont, TX 77702

Architectural Alliance Incorporated MDP CONSULTING ENGINEERS, INC N 11th Street Beaumont, TX 77702 04/08/2013 last saved: TRENT plotted: DRAWN BY: TLH CHECKED BY: DWD 04/08/2013 last saved: DMCPHERSON plotted: DRAWN BY: TLH CHECKED BY: DWD 04/08/2013 last saved: DMCPHERSON plotted: DRAWN BY: TLH CHECKED

More information

Multi-Path RTU-TYPE 2

Multi-Path RTU-TYPE 2 ALDI # CITY, STATE SUPERMARKET MultiPath RTUTYPE 2 (RTU1) CESMPU025RHVAV2 Date: February 17, 201 2013 Consolidated Energy Solutions, Inc. UNIT FEATURES CES TYPE VAV2 Unit features include: 25 Ton MultiPath

More information

DIGI-VAV APPLICATIONS

DIGI-VAV APPLICATIONS DIGI-VAV DIGI-VAV APPLICATIONS Digi-VAV: An optimization kit for Variable Air Volume Air Handling Units (VAV AHU) that ensures individual zone indoor air quality (IAQ), and minimizes system energy consumption.

More information

Dates of Construction Construction Start 2/28/1999 Date of Completion 4/2000 Occupancy 5/2000

Dates of Construction Construction Start 2/28/1999 Date of Completion 4/2000 Occupancy 5/2000 Executive Summary The Milton S. Hershey Medical Center Academic Support Building is located on The Pennsylvania State University's campus in Hershey, PA. The building is owned by The Pennsylvania State

More information

SPLIT-SYSTEM EVAPORATOR BLOWER DESCRIPTION ACCESSORIES - FIELD INSTALLED. K5EU090 and K4EU Hz 7.5 and 10 NOMINAL TONS SUNLINE 2000 (WORLD 50 HZ)

SPLIT-SYSTEM EVAPORATOR BLOWER DESCRIPTION ACCESSORIES - FIELD INSTALLED. K5EU090 and K4EU Hz 7.5 and 10 NOMINAL TONS SUNLINE 2000 (WORLD 50 HZ) (994) SPLIT-SYSTEM EVAPORATOR BLOWER K5EU090 and K4EU120 50 Hz 7.5 and 10 NOMINAL TONS SUNLINE 2000 (WORLD 50 HZ) DESCRIPTION These completely assembled units include a well-insulated cabinet, a DX coil

More information

TECHNICAL REPORT III Mechanical Systems Existing Conditions

TECHNICAL REPORT III Mechanical Systems Existing Conditions TECHNICAL REPORT III Mechanical Systems Existing Conditions TEMPLE UNIVERSITY TYLER SCHOOL OF ART Pennsylvania State University Architectural Engineering Mechanical Option Faculty Adviser: Dr. Jim Freihaut

More information

GARCIA GALUSKA DESOUSA Consulting Engineers

GARCIA GALUSKA DESOUSA Consulting Engineers L#57295/Page 1/July 21, 2017 HVAC SYSTEMS NARRATIVE REPORT The following is the HVAC system narrative, which defines the scope of work and capacities of the HVAC system as well as the Basis of Design.

More information

VERTICAL AHU ENGINEERING SPECIFICATIONS BULLETIN

VERTICAL AHU ENGINEERING SPECIFICATIONS BULLETIN VERTICAL AHU ENGINEERING SPECIFICATIONS BULLETIN 20-019 TABLE OF CONTENTS DESIGN & SPECIFICATIONS...3 APPLICATIONS... 3 CABINET CONSTRUCTION... 3 FEATURES AND CONTROLS... 3 DIMENSIONAL DATA... 5 SPECIFICATIONS...

More information

SPLIT-SYSTEM EVAPORATOR BLOWERS K2EU060, K4EU090, K3EU120 & K1EU180 5 Thru 15 Nominal Tons DESCRIPTION ACCESSORIES FIELD INSTALLED

SPLIT-SYSTEM EVAPORATOR BLOWERS K2EU060, K4EU090, K3EU120 & K1EU180 5 Thru 15 Nominal Tons DESCRIPTION ACCESSORIES FIELD INSTALLED (491) SPLIT-SYSTEM EVAPORATOR BLOWERS K2EU060, K4EU, K3EU & K1EU180 5 Thru 15 Nominal Tons DESCRIPTION These completely assembled units include a well-insulated cabinet, a DX cooling coil with copper tubes

More information

RE: Phase 2 Improvements DATE: July 1, 2016 New Administration Building Wernle Youth & Family Treatment Center 2000 Wernle Road Richmond, Indiana

RE: Phase 2 Improvements DATE: July 1, 2016 New Administration Building Wernle Youth & Family Treatment Center 2000 Wernle Road Richmond, Indiana ADDENDUM NO. 2 RE: Phase 2 Improvements DATE: July 1, 2016 New Administration Building Wernle Youth & Family Treatment Center 2000 Wernle Road Richmond, Indiana TO: All Bidders Gentlemen: This Addendum

More information

Job Name Control Systems Description Date

Job Name Control Systems Description Date Job Name Control Systems Description Date Project Overview The project is a describe the building and its major HVAC systems (e.g. three-story office building, served by a rooftop unit VAV system ). In

More information

Retrocommissioning Findings Summary: Building X #1 Priority: Major Comfort/Control Problems

Retrocommissioning Findings Summary: Building X #1 Priority: Major Comfort/Control Problems IMPORTANT NOTICE: This sample document is provided for instructional purposes only. CCC is not rendering advice concerning any commission project or practices. This document is neither approved nor intended

More information

CHAPTER 4. HVAC DELIVERY SYSTEMS

CHAPTER 4. HVAC DELIVERY SYSTEMS CHAPTER 4. HVAC DELIVERY SYSTEMS 4.1 Introduction 4.2 Centralized System versus Individual System 4.3 Heat Transfer Fluids 4.4 CAV versus VAV Systems 4.5 Common Systems for Heating and Cooling 4.6 Economizer

More information

CLIMATAIR PENTHOUSE AIR HANDLING SYSTEMS

CLIMATAIR PENTHOUSE AIR HANDLING SYSTEMS 7 Rosemex Products 97 VENTILATION CLIMATAIR PENTHOUSE AIR HANDLING SYSTEMS 2 INTRODUCTION Rosemex "Penthouse" units are essentially outdoor mechanical rooms. They group in one compact weather proof outdoor

More information

SECTION SEQUENCE OF OPERATION FOR HVAC CONTROLS PART 1 GENERAL

SECTION SEQUENCE OF OPERATION FOR HVAC CONTROLS PART 1 GENERAL SECTION 15910 SEQUENCE OF OPERATION FOR HVAC CONTROLS PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

Vertical Air Handler Unit

Vertical Air Handler Unit Bulletin 20-019 (September 2016) Vertical Air Handler Unit For cooling, the unit is designed for R-410A refrigerant (both A/C and Heat Pump) or a chilled water coil. For heating, the unit offers an optional

More information

Technical Guide DESCRIPTION CHAMPION SPLIT-SYSTEM EVAPORATOR BLOWER L4EU240A 20 NOMINAL TONS (WORLD 50 HZ) FEATURES XTG-A-0307

Technical Guide DESCRIPTION CHAMPION SPLIT-SYSTEM EVAPORATOR BLOWER L4EU240A 20 NOMINAL TONS (WORLD 50 HZ) FEATURES XTG-A-0307 DESCRIPTION Technical Guide CHAMPION SPLIT-SYSTEM EVAPORATOR BLOWER L4EU240A 20 NOMINAL TONS (WORLD 50 HZ) This 20 ton evaporator blower is designed with two distinct modules to provide maximum application

More information

System Components with ` Emphasis on Packaged Rooftop Application and Installation. Jerry Cohen President Jacco & Assoc.

System Components with ` Emphasis on Packaged Rooftop Application and Installation. Jerry Cohen President Jacco & Assoc. System Components with ` Emphasis on Packaged Rooftop Application and Installation Jerry Cohen President Jacco & Assoc. Agenda Define and relate in practical terms the following components: System Effect

More information

FLORIDA A&M UNIVERSITY PERFORMANCE CONTRACT SCOPE OF WORK

FLORIDA A&M UNIVERSITY PERFORMANCE CONTRACT SCOPE OF WORK FLORIDA A&M UNIVERSITY PERFORMANCE CONTRACT SCOPE OF WORK ENERGY CONSERVATION MEASURE 1 Partial Steam System Decentralization SIEMENS will Furnish and Install condensing hot water boilers with associated

More information

AIR-CONDITIONING SYSTEMS AND APPLICATIONS. Abdullah Nuhait Ph D. King Saud University

AIR-CONDITIONING SYSTEMS AND APPLICATIONS. Abdullah Nuhait Ph D. King Saud University AIR-CONDITIONING SYSTEMS AND APPLICATIONS Abdullah Nuhait Ph D. King Saud University AIR-CONDITIONING SYSTEMS Earliest air conditioning system used only for heating (winter) Provided heated air for comfort

More information

Technical Assignment #2a. Atlanta, GA Green Building Mechanical

Technical Assignment #2a. Atlanta, GA Green Building Mechanical Tubman African American Museum Technical Assignment #2a Chris Champagne Atlanta, GA Green Building Mechanical Green Building Certification Analysis- The major categories of the U.S. Green Building Council

More information

Technical Guide SUNLINE 2000 DESCRIPTION ACCESSORIES FIELD INSTALLED SPLIT-SYSTEM EVAPORATOR BLOWER K4EU NOMINAL TONS (WORLD 50 HZ)

Technical Guide SUNLINE 2000 DESCRIPTION ACCESSORIES FIELD INSTALLED SPLIT-SYSTEM EVAPORATOR BLOWER K4EU NOMINAL TONS (WORLD 50 HZ) Technical Guide SUNLINE 2000 SPLIT-SYSTEM EVAPORATOR BLOWER K4EU180 15 NOMINAL TONS (WORLD 50 HZ) DESCRIPTION These completely assembled units include a well-insulated cabinet, a DX cooling coil with copper

More information

7. MECHANICAL SYSTEM DESIGN

7. MECHANICAL SYSTEM DESIGN 7. MECHANICAL SYSTEM DESIGN The second primary topic of this thesis is to investigate the application of a dedicated outdoor air system (DOAS) to the SLCC. The stated goals for this thesis of improved

More information

DACC Health Sciences Building Air Handler Assessment/Study

DACC Health Sciences Building Air Handler Assessment/Study DACC Health Sciences Building Air Handler Assessment/Study NMSU Facilities and Services Department P.O. Box 30001 Las Cruces, NM 88003-8001 June 14, 2016 Final Submittal 1065 S. Main St., Bldg. D, Ste.

More information

Computing Services Center

Computing Services Center Continuous Commissioning Report for the Computing Services Center Building #516 Submitted to: Utilities Energy Office Physical Plant Department Texas A&M University Prepared by: Energy Systems Laboratory

More information

Architectural Engineering Senior Thesis Mechanical System Redesign

Architectural Engineering Senior Thesis Mechanical System Redesign Saint Joseph Medical Center Architectural Engineering Senior Thesis Mechanical System Redesign Chris Nicolais Building Description Existing Mechanical System Proposed Redesign Alternative Option Emergency

More information

Technical Development Program

Technical Development Program Technical Development Program PRESENTED BY: James Parker Insert your logo here AIR HANDLERS Coils: Direct Expansion Chilled Water and Heating Menu Section 1 Introduction Section 2 Typical Coil Applications

More information

TECHNICAL REPORT 3 Mechanical Systems and Existing Conditions Northfield Mental Healthcare Center Northfield, Ohio

TECHNICAL REPORT 3 Mechanical Systems and Existing Conditions Northfield Mental Healthcare Center Northfield, Ohio Technical Report 3 Northfield Mental Healthcare Center Dr. Stephen Treado Ji Won Park Mechanical Option Fall 2012 TECHNICAL REPORT 3 Mechanical Systems and Existing Conditions Northfield Mental Healthcare

More information

Description of All Alternatives Considered-

Description of All Alternatives Considered- Description of All Alternatives Considered- Energy efficiency is an area where the Tubman design can be improved. The design heating load is 1807.8 MBH and the design cooling load is 1702.2 MBH or 142

More information

CONTROLLED CHILLED BEAM PUMP MODULE

CONTROLLED CHILLED BEAM PUMP MODULE FIRST COST SAVINGS PROACTIVE CONTROL CONTROLLED CHILLED BEAM PUMP MODULE Active condensation control system effectively eliminates chilled beam condensation High efficiency, variable speed pump uses a

More information

Civil Engineering Building

Civil Engineering Building Continuous Commissioning Report For the Civil Engineering Building Building 492 Submitted to: Utilities Energy Office Physical Plant Department Texas A&M University Prepared by: Energy Systems Laboratory

More information

TECHNICAL GUIDE SPLIT-SYSTEM AIR-COOLED EVAPORATOR BLOWER 25, 30, 40 & 50 TON LA300, LB360, 480 & 600 (50 Hz) PROVEN PERFORMANCE GENERAL FEATURING

TECHNICAL GUIDE SPLIT-SYSTEM AIR-COOLED EVAPORATOR BLOWER 25, 30, 40 & 50 TON LA300, LB360, 480 & 600 (50 Hz) PROVEN PERFORMANCE GENERAL FEATURING TECHNICAL GUIDE SPLIT-SYSTEM AIR-COOLED EVAPORATOR BLOWER 25, 30, 40 & 50 TON LA300, LB360, 480 & 600 (50 Hz) PROVEN PERFORMANCE GENERAL The LA/LB line is a flexible performer. LA300, LB360 & 480 can be

More information

Technical Assignment 3

Technical Assignment 3 0 David H. Koch Institute for Integrative Cancer Research Senior Capstone Mechanical Option Technical Assignment 3 Mechanical Systems and Existing Conditions Report David H. Koch Institute for Integrative

More information

APPLICATION GUIDE BEAMS

APPLICATION GUIDE BEAMS BEAMS There is an increasing need for energy efficient air conditioning systems as energy codes become more stringent. Chilled beam systems are one such alternate to traditional all air conditioning systems.

More information

HVAC Controls Upgrades: Requirement Details ( )

HVAC Controls Upgrades: Requirement Details ( ) REQUIRED CONTROLS/FEATURES To qualify the upgrade must add or substantially modify 3 or more sequences/system capabilities. Also, all sequences and items listed under the required section are needed in

More information

UNIVERSITY OF MISSOURI Heating Ventilating and Air-Conditioning (HVAC) 2016 Q1

UNIVERSITY OF MISSOURI Heating Ventilating and Air-Conditioning (HVAC) 2016 Q1 GENERAL: This section provides general standards for overall sizing and design of Heating, Ventilating, and Air Conditioning (HVAC) systems. Other sections contain specific standards for each system per

More information

Brown University Revised August 3, 2012 Facilities Design & Construction Standards SECTION AIR HANDLING UNITS

Brown University Revised August 3, 2012 Facilities Design & Construction Standards SECTION AIR HANDLING UNITS SECTION 23 70 00 AIR HANDLING UNITS PART 1. GENERAL 1.1 Section includes air-handling units to 15,000 cfm and accessories. 1.2 Related Sections 1 : A. Division 01 - Brown University Standard for Narragansett

More information

MT. AIRY MIDDLE SCHOOL CARROLL COUNTY PUBLIC SCHOOLS

MT. AIRY MIDDLE SCHOOL CARROLL COUNTY PUBLIC SCHOOLS CARROLL COUNTY PUBLIC SCHOOLS LIFE CYCLE COST ANALYSIS SUMMARY DGS PROCEDURES FOR THE IMPLEMENTATION OF LIFE CYCLE COST ANALYSIS AND ENERGY CONSERVATION OCTOBER, 2010 G.A.I.#09090 GIPE ASSOCIATES, INC.

More information

BULLETIN. Temperature Controls (Chilled Water) Phase III only (3/11/2010)

BULLETIN. Temperature Controls (Chilled Water) Phase III only (3/11/2010) BULLETIN Temperature Controls (Chilled Water) Phase III only (3/11/2010) This bulletin is to advise you of the fees and responsibilities associated with the tenant s temperature controls. Tenant Responsibility:

More information

Now In Production JULY 2008

Now In Production JULY 2008 Now In Production JULY 2008 OptiSolar, McClellan, CA Nine (9) Custom new single-zone units with 135 tons of DX cooling, air cooled condensing sections and direct drive supply air blowers. Ambient design

More information

Submitted to. Texas A&M University-Corpus Christi The Texas A&M University System. Submitted by. Yeqiao Zhu Dan Turner David Claridge

Submitted to. Texas A&M University-Corpus Christi The Texas A&M University System. Submitted by. Yeqiao Zhu Dan Turner David Claridge ESL-TR-99/12-04 Report of Energy Efficiency Study and Metering/Utilities Profile for Electricity Deregulation at the Texas A&M University-Corpus Christi (TAMU-CC) Corpus Christi, Texas Submitted to Texas

More information

Madeira City Schools Madeira, Ohio. HVAC Assessment. December 2011 (Revised February 2012)

Madeira City Schools Madeira, Ohio. HVAC Assessment. December 2011 (Revised February 2012) Madeira City Schools Madeira, Ohio HVAC Assessment December 2011 (Revised February 2012) Prepared by: CMTA Engineering Consultants, Inc. 10411 Meeting Street Prospect, KY 40059 www.cmtaegrs.com (502) 326-3085

More information

VERTICOOL TECHNICAL DATA MANUAL. Vertical Air/Water Cooled 3-25 Tons

VERTICOOL TECHNICAL DATA MANUAL. Vertical Air/Water Cooled 3-25 Tons 491 East Princess Street York, PA 17403 877-905-1111 717-843-4311 Fax: 717-854-4462 uca@unitedcoolair.com www.unitedcoolair.com VERTICOOL TECHNICAL DATA MANUAL Vertical Air/Water Cooled 3-25 Tons UNITED

More information

Introduction to HVAC. American Standard Inc Air Conditioning Clinic TRG-TRC018-EN

Introduction to HVAC. American Standard Inc Air Conditioning Clinic TRG-TRC018-EN Introduction to HVAC Agenda Psychrometrics Human Comfort Heat Transfer Refrigeration Cycle HVAC Terminology HVAC Systems Introduction to HVAC Psychrometrics 2000 TRG-TRC002-EN Properties of Air Dry-bulb

More information

LGH/LCH WARNING. CAUTION Danger of sharp metallic edges. Can cause injury. Take care when servicing unit to avoid accidental contact with sharp edges.

LGH/LCH WARNING. CAUTION Danger of sharp metallic edges. Can cause injury. Take care when servicing unit to avoid accidental contact with sharp edges. Service Literature The LGH/LCH high and standard efficiency 5, 0, 5 and 50 ton (, 0.7, 58. and 75.9 kw) units, are configure to order units (CTO) with a wide selection of factory installed options. The

More information

Christopher Kelly Technical Report Three

Christopher Kelly Technical Report Three Christopher Kelly Technical Report Three Mechanical Systems and Existing Conditions Evaluation SALK HALL ADDITION The University of Pittsburgh, Pittsburgh Christopher Kelly, Mechanical Option Professor

More information

Mechanical System Redesign. Dedicated Outdoor Air System. Design Criteria

Mechanical System Redesign. Dedicated Outdoor Air System. Design Criteria Mechanical System Redesign Dedicated Outdoor Air System Design Criteria The outdoor air conditions used were for Philadelphia, Pennsylvania IAP at a 0.4% occurrence. The supply air conditions were developed

More information

Packaged Heat Pump. 20 Ton Rooftop Units with ReliaTel TM Controls NOTICE

Packaged Heat Pump. 20 Ton Rooftop Units with ReliaTel TM Controls NOTICE Service Facts Customer Property: Contains wiring and service information. Please retain. WC*240-SF-1H Library Service Literature Product Section Unitary Product Package Air Conditioner Model WC* Literature

More information

Appendix 13. Categories of Cooling and Heating systems

Appendix 13. Categories of Cooling and Heating systems EcoShopping - Energy efficient & Cost competitive retrofitting solutions for Shopping buildings Co-funded by the European Commission within the 7 th Framework Programme. Grant Agreement no: 609180. 2013-09-01

More information

Submitted to. Texas A&M University at Galveston The Texas A&M University System. Submitted by. Yeqiao Zhu Dan Turner David Claridge

Submitted to. Texas A&M University at Galveston The Texas A&M University System. Submitted by. Yeqiao Zhu Dan Turner David Claridge ESL-TR-99/12-05 Report of Energy Efficiency Study and Metering/Utilities Profile for Electricity Deregulation at the Texas A&M University at Galveston (TAMU-G) Galveston, Texas Submitted to Texas A&M University

More information

MACH N-407 Heat Pump Air-Cooled Chiller

MACH N-407 Heat Pump Air-Cooled Chiller MACH060-01-N-407 Heat Pump Air-Cooled Chiller Heat Pump Air-Cooled Chillers for Global Residential and Light Commercial Microclimates MACH NOMENCLATURE BREAKDOWN MACH-060-01 - N - 407 Refrigerant Type

More information

HVAC 101. The Basics of Heating, Ventilation and Air Conditioning

HVAC 101. The Basics of Heating, Ventilation and Air Conditioning HVAC 101 The Basics of Heating, Ventilation and Air Conditioning HVAC Heating, Ventilation and Air Conditioning Provides comfort for people Allows humans to exist under adverse conditions. Comfort Comfort

More information

B. Use UT Austin specifications and equipment schedule format for HVAC equipment where available.

B. Use UT Austin specifications and equipment schedule format for HVAC equipment where available. PART 1: GENERAL 1.01 General Requirements A. This standard is intended to provide useful information to the Professional Service Provider (PSP) to establish a basis of design. The responsibility of the

More information

UNIVERSITY OF MISSOURI Central Station Air-Handling Units March

UNIVERSITY OF MISSOURI Central Station Air-Handling Units March GENERAL: 1. This section provides criteria for the design and installation of air handling units. DESIGN GUIDELINES: Design General 1. Location 1.1. For new construction, and existing buildings where possible,

More information

ADDENDUM No: 3 JOSEPHINE COUNTY BUILDING OPERATIONS DEPARTMENT. February 29, NO CHANGE: March 8, 2012 / NOT LATER THAN 2:00 PM

ADDENDUM No: 3 JOSEPHINE COUNTY BUILDING OPERATIONS DEPARTMENT. February 29, NO CHANGE: March 8, 2012 / NOT LATER THAN 2:00 PM ADDENDUM No: 3 JOSEPHINE COUNTY BUILDING OPERATIONS DEPARTMENT February 29, 2012 RFP NO: 17 PROJECT: Josephine County Justice Center HVAC Upgrades BID CLOSING DATE: NO CHANGE: March 8, 2012 / NOT LATER

More information

EarthWise System Seminar

EarthWise System Seminar EarthWise System Seminar Tim Gasper, P.E. Solutions Engineer Brady-Trane Services, Inc. EarthWise Systems? Energy Efficiency Emissions Buildings use 39% of the Primary Energy Consumed in the United States

More information

ENGINEERING BULLETIN. Overview of Chilled Beam Technology. Purpose. Summary. Theory

ENGINEERING BULLETIN. Overview of Chilled Beam Technology. Purpose. Summary. Theory Overview of Chilled Beam Technology Purpose Chilled beam technology is new to the United States but has been used in Europe since the 1950 s. Chilled beams can reduce energy costs, improve indoor air quality,

More information

HVAC 101. H V A C S y s t e m s

HVAC 101. H V A C S y s t e m s H V A C 1 0 1 S y s t e m s Introduction & Overview Should you care? Mechanical System Types Components & operation Popular Application Key Issues and Design Considerations System Comparisons First Cost

More information

2 Existing Mechanical System

2 Existing Mechanical System 2 Existing Mechanical System 2.1 Design Objectives and Requirements The Gossett Field House project consists of a 25,000 sqft addition and a 40,000 sqft renovation of the existing facility for the University

More information

Linear Floor Heaters

Linear Floor Heaters Linear Floor Heaters The Price Linear Floor Heater family provides ultimate flexibility in terms of style, performance, and ease of installation. Using room-side heat virtually eliminates the requirement

More information

Terminal. Las Vegas, NV. Technical

Terminal. Las Vegas, NV. Technical McCarran International port Terminal 3 Technical Assignment 3 Mechanical System Existing Conditions Evaluation December 3, 2007 Prepared By: Faculty Advisor: Dr. William Bahnfleth, Ph.D., P..E. Table of

More information

AIR DISTRIBUTION. C. Section Building Automation and Control System Guidelines. D. Section Fire Alarm System & Detection Systems

AIR DISTRIBUTION. C. Section Building Automation and Control System Guidelines. D. Section Fire Alarm System & Detection Systems 233100 AIR DISTRIBUTION PART 1: GENERAL 1.01 RELATED SECTIONS A. Section 230700 HVAC Insulation B. Section 237300 Air Handling C. Section 230900 Building Automation and Control System Guidelines D. Section

More information

MBNA Career Services Center The Pennsylvania State University University Park Campus

MBNA Career Services Center The Pennsylvania State University University Park Campus University Park Campus Variable Air Volume System and Dedicated Outdoor Air System with Fan Coil Units Comparison AE Senior Thesis Primary Consultant Spring 2003 Dr. Bahnfleth Table of Contents Executive

More information