To: Steve Ardolf, MSU Mankato From: Chris Plum, CEE. CC: Tim Ellingson, CEE. Angela Vreeland, CEE Dan Briese, MSU Mankato Date: April 21, 2014.

Size: px
Start display at page:

Download "To: Steve Ardolf, MSU Mankato From: Chris Plum, CEE. CC: Tim Ellingson, CEE. Angela Vreeland, CEE Dan Briese, MSU Mankato Date: April 21, 2014."

Transcription

1 To: Steve Ardolf, MSU Mankato From: Chris Plum, CEE CC: Tim Ellingson, CEE Angela Vreeland, CEE Dan Briese, MSU Mankato Date: April 21, 2014 Re: MSU Mankato Verification State PBEEEP Executive Summary The Center Energy and Environment has completed a review of trend data collected 16 buildings in support of the Measurement and Verification Phase of the State PBEEEP Program. Thirty one measures were reviewed. We found that only six were fully implemented, 21 were partially implemented and insufficient data is available to investigate four others. Four of the measures are no longer applicable and were not reviewed; this could happen if a building is being torn down or a major renovation is underway. The May and June 2012 PBEEEP Reports identified 35 Energy Conservation Opportunities (ECOs) spanning across 16 facilities. If implemented, they would save the campus $110,112 annually. In April 2013 CEE conducted a site visit to MSU Mankato and initiated trend data collection in support of measurement and verification activities. MSU Mankato sent trend data to CEE on a monthly basis so that the equipment operation could be analyzed during all weather conditions and modes of operation (summer break and school in session). Extensive review of the data indicates that many of the energy conservation opportunities have not yet been implemented as expected, thus preventing achievement of the full amount of potential energy savings. The report details the results of the current review all 16 buildings. Suggested action items are provided after a brief explanation and current status of each measure. The following table provides a summary of the status of ECOs at each building. CEE engineers have permed the measurement and verification as part of the Public Buildings Enhanced Energy Efficiency Program. Our contract that program ends on February 16, After that date we are available to meet with MSU Mankato staff in order to review the 31 energy conservation opportunities in further detail on a fee service basis. 1

2 Status Categories: Complete: has been completed as recommended by the PBEEEP provider. Partial: Some, but not all, of the implementation was completed OR changes were made, but they are not the changes that were recommended by the PBEEEP provider but get closer to the solution. Incomplete: The measure has not been implemented at all OR changes were made, but they are not the changes that were recommended by the PBEEEP provider and may worsen the problem. Inconclusive: More data is needed to verify the measure (i.e. heating season data is required, but not available at this time). Building Armstrong Hall Centennial SU Complete Partial/Incomplete Inconclusive Finding # Savings Finding # Savings Finding # Savings 2, 5 $1,503 1, 4, 7 $26, , 3 $7,560 - Ford Hall Highland Center Memorial Library - 5, 6, 8, 9 $7, , 2, 3 $24,218 4 $560 Morris Hall Myers Field House Nelson Hall w/ Addition Pennington Hall Perf Arts & Andreas Theater - 4 $2, , 5 $4, $164-1 $1,274 3 $1,444 2 $557 Taylor Center - 1 $3,830 - Trafton Hall 1 $7,372 2 $1,723 3 $4,341 Utility Plant 1 $6, $2,630 Wiecking Center Wigley Admin - 1, 3 $2,724-1 $2, TOTAL SUM 6 $18, $83,028 4 $8,088 2

3 Armstrong Hall High Priority Item: Potential savings of $21,796 will not be fully achieved because this measure has only been partially implemented. Status: Partial Eco #: 1 Building: Armstrong Hall AHU Runtime Reduction Reviewed building schedule with Owner to determine actual occupancy. New schedule will need to be added. : A schedule will be initiated on SF-1 and SF-2 to shut down the units when there is no occupancy in the building. There will be two schedules. During regular school session from August 24 to May 5 the units will run from 7 AM to 9 PM Monday through Thursday, 7 AM to 4 PM on Friday, 8 AM to 2 PM on Saturday, and off on Sunday. During summer session from May 6 to August 23 the units will run from 8 AM to 4 PM Monday through Friday and be off Saturday and Sunday. The SF status of SF-1 and SF-2 will be trended 15 minute intervals one week during the time period of August 24 to May 5 and one week from May 6 to August 23 to verify it is following the schedule specified in the section of the Findings Workbook. All space temperatures will be trended one week as well during peak heating season and peak cooling season to assure spaces are warming up or cooling down to the desired setpoints bee occupancy of the building. No on/off fan scheduling appears to have been completed. Instead, the operator noted that a day/night control mode w/ continuous fan operation is in place. Although the day/night terminal mode has been observed in the trend data, the originally estimated fan and outdoor air associated with this finding are in question. Summer Schedule: Day mode appears to be set : M-F 5am - 9pm. Sa,Su 5am-6pm. Fans are never off, but they can ramp down. Semester Schedule: Day appears to be set : M-Th 5:15am-10pm. Sa All day Su Through 5pm Fans are never off, but they vary in output down to 68 to 70% from max of ~80%. General: OA dampers are never commanded closed at night during anticipated unoccupied timeframe. OA dampers remain 47-49% open at night. 1) Command OA dampers close in unoccupied (night) mode. 2) If fans will not be scheduled completely off in unoccupied mode, provide clarification to the reviewer as to how fan speed is controlled in the night mode. Confirm that all points impacting fan speed control 3

4 within the desired sequence are currently being recorded so that the reviewer can confirm successful implementation. 4

5 Status: Complete Eco #: 2 Building: Armstrong Hall Optimize Economizer Modify the existing control economizer enable/disable sequence setpoint : In the building automation system, modify the economizer enable/disable setpoint to 71 deg. F SF-1, SF-2 and SF-3. Training will be given to staff so they are aware this value is now 71 F and if they change it due to operational issues, it needs to be documented and investigated why this value was changed. Review control sequence BAS screen verification that the modification of the economizer enable/disable took place. Trend the damper position each of the units during the outside air temperature of 71 deg. F to verify that the damper position transitioned between economizer and non-economizer. Using the Armstrong building-specific outdoor air temperature point MISC_SYS- OA-OAT_ARM, it appears that the 71 deg F setpoint has been implemented. No Action. 5

6 Status: Incomplete Eco #: 4 Building: Armstrong Hall Supply Air Temperature Reset is not implemented or is sub-optimal Modify the existing control programming of allow the supply air temperature to float between a minimum and maximum setpoint based on demand. : Modify the existing control programming SF-1 and SF-2 to allow the supply air temperature to float between a minimum (55 deg. F - adj) and maximum (65 deg. F - adj) setpoint based on cooling demand. Monitor the space temperatures being served by the AHU, once 20% (adj) of the space temperature require cooling, allow the supply air temperature setpoint to step from maximum to minimum. Once the space temperature cooling demand has dropped below 5% allow the supply air temperature setpoint to step from minimum to maximum. A DAT reset should be implemented unit SF-3 as well, but with the unit serving two zones and one of them contains a reheat, the zone without the reheat may require a DAT higher than 65 F and the calculation did not factor this in so savings it were not calculated, but the measure would save energy in SF-3 as well, just hard to quantify how much. Review control sequence program modifications and perm functional testing. Trend the number of cooling demand requests (or space temperatures) a minimum of two weeks to verify that all of the spaces meeting the required setpoints. Based on review of the DAT setpoint trend data SF-1 and SF-2, the measure has not been implemented. Also, SF-3 DAT and DAT-SP were not provided as requested in the last 10/18/13 correspondence with MSU Mankato. MSU Mankato: 1) Implement DAT reset SF-1, SF-2, and SF-3. 2) Include SF-3 DAT and DAT-SP within future trend data collection. 6

7 Status: Complete Eco #: 5 Building: Armstrong Hall The steam control valve is leaking steam Repair control valve to allow have it seat properly. : Repair steam valves AHU SF-1 and SF-2 so that it will seat and not allow steam by when in fully closed position. Trend the steam valve position, mixed air temperature and supply air temperature or datalog the temperature of the supply steam piping a minimum of two weeks to verify that when the steam valve is in the closed position, no steam is migrating into the heating coil. It appears that the measure has been implemented. If further trend data will be collected, include CLG-VLV SF-1 and SF-2. Otherwise, no action is required. 7

8 Status: Incomplete Eco #: 7 Building: Armstrong Hall Equipment is enabled regardless of need, or such enabling is excessive. VAV terminal unit Modify the control programming to allow scheduling of the VAV box fan to go unoccupied as per Owner's schedule : Modify the control programming all Fan Powered VAV boxes' fan speed to allow occupied/unoccupied control by reducing the fan speed to zero during unoccupied conditions. The VAV boxes will have to engage during unoccupied times if the space temperature falls below space temperature setpoint. Review programming of VAV boxes and perm functional testing. Trend the VAV box fan speed a minimum of two weeks to verify that when the VAV box is in unoccupied mode the fan speed drops to zero. The measure could not be verified at this time. Additional operational details including fan-powered box status or box flow points are required. Furthermore, if the main AHU fans do not turn off per ECO 1, this ECO cannot be implemented as originally planned. If this measure is still intended implementation, MSU Mankato will: 1) Confirm intent. 2) Confirm which fan-powered boxes are impacted by this measure. 3) Enable VMA fan status and/or flow (CFM) trend data on all (or a sample) of applicable fan-powered units as well as clarify what activates/deactivates terminal unit fans. 4) Continue collecting the previously trended points. 8

9 Centennial Student Union High Priority Item: Potential savings of $7,219 will not be fully achieved because this measure has only been partially implemented. Status: Partial Eco #: 1 Building: Centennial Student Union AHU Run Time Reduction Modification of the existing equipment schedule residing in the BAS. : A schedule will be initiated on all AHUs to shut down the units when there is no occupancy in the building. There will be two schedules. During regular school session the units will run as per the earliest scheduled posted on the University's website. The AHU schedule will change each semester and the owner should update the schedules accordingly. The new current schedule was set to the following: SF-23: From September 1st to May 31st: Monday through Thursday 7 AM to 7 PM, Friday 7 AM to 4 PM Saturday 11 AM to 3 PM. The unit will be off on Sunday. From June 1st to August 31st, SF-23 is on Monday through Friday 8 AM to 4 PM Off Saturday and Sunday SF-27 will operate continuously, Monday through Friday 6 AM to Midnight, Saturday 8 AM to midnight and Sunday 10 AM to midnight. The SF status of all AHUs will be trended 15 minute intervals one week during the time period of regular school session and one week the summer school session to verify it is following the schedule specified in the section of the Findings Workbook. All space temperatures will be trended one week as well during peak heating season and peak cooling season to assure spaces are warming up or cooling down to the desired setpoints bee occupancy of the building. SF-23 appears to be scheduled partially in accordance with the ECO. Generally, the AHU is operated longer than the originally proposed M-F and Sa. The AHU also operates on Sunday where previously it was expected to be off. M-F: ~6:30am-11pm Sa,Su: ~6:30am-12am SF-27 trend data still has not been received and thus the schedule has not been verified. BAS review on April 2013 indicated no operating schedule was available SF-27. Additional trend points as requested in the last 10/18/13 correspondence with MSU Mankato were not provided. 9

10 MSU Mankato: 1) Confirm the intended semester SF-23 and SF-27 operating schedule. 2) Collect additional trend data. Include points SU_SF27_Sta-Sto and SU_SF27_SF-Stat in addition to previously trended points. 10

11 Status: Partial Eco #: 3 Building: Centennial Student Union Reheat Pumps Runtime Reduction Pump, HW distribution Modify the existing control sequence programming to allow the pumps to run whenever the outside air temperature is less than 75 deg. F. : Modify the existing control sequence programming to allow the pumps to run whenever the outside air temperature is less than 75 deg. F and any combination of reheat valve control is greater than 10% (adj). If the outside air temperature is greater than 75 deg. F (adj), monitor the reheat valve position and if 20% (adj) of the reheat valves are opening, allow the pumps to start. Disable the pumps when the valve positions are less that 5% (adj). Review the control sequence program modifications and perm functional testing. Trend the reheat valve positions and space temperatures two weeks when the outside air temperature is great than 75 deg. F to verify that the spaces are getting adequate reheat. The OAT lockout setpoint has been changed to 75 deg F, thus completing the major requirement of the measure. However, only SF1-RH03-VLV was available terminal unit review. It indicated no call reheat during the sample set, thus preventing the ability to verify if the sequence polls multiple reheat valves. MSU Mankato: 1) Confirm if the control sequence will monitor multiple reheat positions to activate pumps when above 75 deg F OAT. 2) If item 1 will be completed, trend additional reheats beyond just SF1- RH03-VLV. Otherwise, if staff has found no issues with zone temperature, the measure is complete. **Note that HWP-1 did not activate during the entire summer data set. HWP-2 was the only pump that would operate, indicating a need additional programming to rotate lead pump designation. Continuous operation of one pump may lead to early failure.** 11

12 Ford Hall Status: N/A Eco #: 1 Building: Ford Hall Exhaust Fan Volume Reduction Other This ECO proposes to ramp the exhaust fans based on laboratory demand and leave the outside air damper in the closed position. : For EF-30A, EF-30B, EF-31A, EF-31B, EF-32A, EF-32B, EF-33A and EF-33B. These exhaust fans will have the OA damper associated with Exhaust fans on AHU-30, 31, 32, and 33 closed off. If the exhaust fans don't already have VFDs on them, a VFD will have to be installed on the fans. The cost that is included in the Contractor Cost this measure. If the units do have VFDs, the cost will decrease. The exhaust fans will modulate their speed based off the duct static pressure setpoints. This setpoint will be set by a balancer. The setpoint will be when the fan is at 100% and all spaces require 100% exhaust flow. Units 31 and 33 don't have duct static pressure readings on them at this time, if they require these points to be mapped and setup they will have to be. This cost was also factored into the contractor cost, if it is not needed the cost will decrease to implement this measure. There are two areas of concern which need to be addressed bee this measure is implemented. One is if the OA dampers are used in any way to assure space pressure. If they are, this measure needs to be re-visited bee it is implemented. The other area is associated with the throw of the exhaust fan. If the exhaust requires a certain throw from the diffuser it will be decreased if the speed of the fan is reduced. Throw requirements of the exhaust air need to be investigated bee this measure can be implemented. Functional testing, equipment inspection and trending of the EFs VFD Speed, Exhaust Duct Static Pressure, Exhaust Duct Static Pressure Setpoint, Exhaust Fans Outside Air Damper Position at an interval of 15 minutes a period of two weeks during the normal school session and summer school sessions. Based on feedback from MSU Mankato, this measure has not been implemented and is not planned implementation at this time. N/A 12

13 Highland Center Status: Partial Eco #: 5 Building: Highland Center HIGHLAND SF-2 Implementing VFD's on both the supply and return fans will allow fan energy savings as well as cooling and heating savings of outdoor air during low occupancy times. : is to provide appropriately sized VFD's the supply fan. During occupied conditions, the supply fan speed shall modulate to maintain a space temperature setpoint and the heating and cooling valves shall modulate to maintain a constant discharge air temperature. During unoccupied times, the supply fan VFD settings shall be set to maintain a constant exhaust rate per ASHRAE guidelines. The heating and cooling valves shall continue to modulate to maintain a night setback temperature at a reduced temperature during winter and an increased temperature during summer during unoccupied times additional energy savings. Electrical contractor to install VFD's, test and balancer shall set minimum VFD speeds as required to maintain minimum exhaust rate required the space. Controls contractor to provide additional points related to VFD operation and upgrade controls strategy as required. Trending of all relevant points including zone temperature, chilled water and hot water valve positions, damper position, DAT, RAT, MAT, RAH, EAT, and OAT will demonstrate unit operation. The additional VFD fan speed shall be trended to verify a reduction in fan speed. The trending shall take place during both summer and winter conditions to ensure unit operates to maintain space temperature requirements both during occupied and unoccupied times. A supply fan VFD has been implemented, and the unoccupied VFD state reaches 50% output. This state occurs any time other than M-F ~5:30am-11:00pm. Otherwise, the supply fan is at 100%. MSU Mankato: 1) Clarify how the 50% unoccupied fan speed setpoint setback was determined. Can this go lower? **Note that during the summer data review, the heating valve had appeared to continuously modulate. It appears that this issue may have been resolved. If not, consider reviewing htg lockouts.** 13

14 Status: Partial Eco #: 6 Building: Highland Center HIGHLAND SF-3 (HY_SF3) Provide an occupancy schedule the unit to save energy. : The recommendation is to utilize the existing AHU schedule provided. The new unit operation calculated energy savings occupancy between 6:00AM and 10:00PM and off during unoccupied times. This is a reasonable runtime as the unit serves both offices as well as corridor spaces. The unit will be operated 7 days a week due to some of the spaces it serves (corridors and hallways). In addition, the calculation assumed the unit would operate when outdoor air temperatures were below 20 degrees to prevent space freezing in a night setback operation. Trending of all relevant points including zone temperature, chilled water and hot water valve positions, damper position, DAT, RAT, MAT, fan speeds and OAT will demonstrate the existing unit operation. Upon the schedule alteration, the unit VFD speeds shall demonstrate they follow the appropriate schedule. The outdoor air damper position shall close when the VFD's are in the unoccupied mode. The chilled water valve shall stay closed when unoccupied and the hot water valve position shall close unless a call freeze protection opens valve. Trends indicate fan operation 4:15am to 10pm M-F and Sa-Su. This represents 1.75 more hours per day (638 hours annually) than originally calculated. Furthermore, it is uncertain whether the outdoor air damper is closed when the unit is in unoccupied mode. MSU Mankato: 1) Confirm occupied/unoccupied and any system warm-up or cool-down schedule(s). Confirm when OA damper is intended to be closed. 2) MSU Mankato to provide additional trend data a swing and heating season that also includes HY_SF3 points OCCUPIED, RF-STAT, RF- VFD, MAT, MIN-POS, OA-CFM, MIN-CFM, DEAD-BND, DAT, DAT-SP, HTG-VLV, CLG-VLV, RAT, ZN-T, and ZN-SP. 14

15 Status: N/A Eco #: 7 Building: Highland Center HIGHLAND SF-4 Provide a space cooling device such as a split system to provide cooling during unoccupied times. The unit shall operate when the air handling unit is not in operation. : The recommendation is to provide a Mitsubishi Mr. Slim split DX system to provide cooling to the store area to allow the air handling unit to disable during unoccupied times. The split system shall operate off a space temperature thermostat and be provided with internal controls. The cooling device shall be wall mounted within the shop space. The CU shall be installed within the mechanical room on the second floor. The air handling unit shall return to its original occupancy operation. The calculation energy savings assumed the unit operation would be from 6:00AM to 10:00 PM. The unit shall be scheduled to operate 7 days a week due to the spaces it serves. In addition, the calculation assumed the unit would operate when outdoor air temperatures were below 20 degrees to prevent space freezing in a night setback operation. Trending of all relevant points including zone temperature, chilled water and hot water valve positions, damper position, DAT, RAT, MAT, fan speeds and OAT will demonstrate the existing unit operation. Upon the schedule alteration, the unit VFD speeds shall demonstrate they follow the appropriate schedule. The outdoor air damper position shall close when the VFD's are in the unoccupied mode. The chilled water valve shall stay closed when unoccupied and the hot water valve position shall close unless a call freeze protection opens valve. Trending of the space temperature where the split system is installed will demonstrate the space temperature remains at acceptable levels during unoccupied times regardless of the AHU operation. Spot verification of unit operation will also demonstrate an appropriate installation of the CU by adjusting the wall thermostat to ensure the unit energizes as required to maintain an appropriate space temperature. Based on inmation received in April 2013 from MSU Mankato, a separate DX unit has not been installed. N/A 15

16 Status: Incomplete Eco #: 8 Building: Highland Center OTTOS SF-4 Releasing the control of the chilled water valve will allow unit to operate per the original sequence. : The recommendation was to correct the valve modulation issue. It was discussed and this finding has already been corrected. This calculation and finding was included to report the calculated energy savings. This calculation is conservative because it only calculates heating savings during times the air handling unit could be economizing and does not look at time the unit is subcooling when the AHU is operating in a cooling mode. Trending of all relevant points including zone temperature, chilled water and hot water valve positions, damper position, DAT, RAT, MAT, fan speeds and OAT will demonstrate the unit operation. The unit shall not be operating in a simultaneous heating and cooling scenario due to the previous excessive cooling. Based on review of trend data from May 29 through September 29, 2013, the cooling valve remained at 50% the entire data sample set. OTTO_SF4-CLG- O remained at 50% regardless of SF-4 status. MSU Mankato: Release the cooling coil to automatic control and confirm cooling valve actuation. Provide an additional trend data set review after the coil is released. 16

17 Status: Partial Eco #: 9 Building: Highland Center OTTO SF-2 Implementing VFD's on both the supply and return fans will allow fan energy savings as well as cooling and heating savings of outdoor air during low occupancy times. : is to provide appropriately sized VFD's both supply and return fans. During occupied conditions, the supply fan speed shall modulate to maintain a space temperature setpoint and the heating and cooling valves shall modulate to maintain a constant discharge air temperature. The return fan VFD shall modulate to maintain a set offset with the supply fan VFD to maintain a negative pressure with respect to adjacent spaces. During unoccupied times, the supply and return fan VFD settings shall be set to maintain a constant exhaust rate per ASHRAE guidelines. The heating and cooling valves shall continue to modulate to maintain a night setback temperature at a reduced temperature during winter and an increased temperature during summer during unoccupied times additional energy savings. Electrical contractor to install VFD's, test and balancer shall set minimum VFD speeds as required to maintain minimum exhaust rate required the space. Controls contractor to provide additional points related to VFD operation and upgrade controls strategy as required. Trending of all relevant points including zone temperature, chilled water and hot water valve positions, damper position, DAT, RAT, MAT, RAH, EAT, and OAT will demonstrate unit operation. The additional VFD fan speed shall be trended to verify a reduction in fan speed. The trending shall take place during both summer and winter conditions to ensure unit operates to maintain space temperature requirements both during occupied and unoccupied times. Although VFDs appear to have been installed on the supply and return fans, the schedule should be inspected. All days of the week show supply and return fans off briefly ~15-30 minutes at midnight, then immediately operating at 50% output until 4:30am, leading to 100% output until 11:45pm. Also, select points that were requested in the last 10/18/13 correspondence with MSU Mankato were not provided. MSU Mankato: 1) Provide intended SF-2 sequence of operation 2) Include trend points OCCUPIED, NITSFSPD, NITRFSPD, and RAT-SP in next iterations of trend data swing and heating seasons. 3) Confirm if temperature setback was pursued or implemented. At this time, it appears that a setback has not been implemented. 17

18 Memorial Library High Priority Item: Potential savings of $22,026 will not be achieved because this measure has not been implemented. Status: Incomplete Eco #: 1 Building: Memorial Library AHU Runtime Reduction (SF-1, SF-2, SF-3, and SF- 36) Modification of the existing equipment schedule residing in the BAS. : A schedule will be initiated on SF-1, SF-2, SF-3 and SF-36 to shut down the units when there is no occupancy in the building. There will be two schedules. During regular school and during the summer session. The AHUs will follow the schedule below the regular school year: SF-1, SF-2, SF-3 and SF-36: 7 AM to 2 AM Monday through Thursday, 7 AM to 7 PM Friday, 10 AM to 6 PM Saturday, 1 PM to midnight on Sunday. The AHU will follow the schedule below the summer session will follow the schedule below: SF-1, SF-2, SF-3 and SF-36: 7 AM to 7 PM Monday through Thursday, 7 AM to 5 PM Friday, 10 AM to 5 PM Saturday, 1 PM to 9 PM Sunday The SF status of all AHUs will be trended 15 minute intervals one week during the time period of regular school session and one week the summer school session to verify it is following the schedule specified in the section of the Findings Workbook. All space temperatures will be trended one week as well during peak heating season and peak cooling season to assure spaces are warming up or cooling down to the desired setpoints bee occupancy of the building. General observations: 1) SF-1 and SF-3 VFD operate at 80% speed occupied periods and increase to ~100% during unoccupied periods. 2) SF-2 and SF-36 appear to adhere to a finite on/off schedule. 3) SF-1 and SF-3 never turn off, and it is uncertain whether the 80%/100% fan rates were already in place bee the PBEEEP study. Projected savings 80%/100% operation will vary significantly from the suggested ECO on/off mode. SF-1 and SF-3 account 95 HP of fan energy. 4) SF-2 humidification setpoint (40%) differs from SF-1,3, and 36 (30%). 5) Day night control point DN-CTRL appears to hold the same state, and DN2-CTRL, and DN3-CTRL data are incomplete, possibly due to a sampling rate or resolution issue. Additional inmation is required (below) in order to verify energy savings (if any) due to the current operating schedule. 18

19 MSU Mankato: 1) Confirm that DN-CTRL, DN2-CTRL, DN3-CTRL, and all SF minute trend data will collect the same duration as other trended points without gaps. 2) Confirm which return condition (temperature, relative humidity, enthalpy), trend point (average VAV zone temperature), or summer/winter/day/night setpoint controls SF-1, 2, 3, and 36 fan speeds. SF-2 is of specific interest since it does not have summer/winter day/night setpoints. 3) Clarify the intended impact of item 2 to AHU fan speeds SF-1, 2, 3, and 36. 4) Continue to collect trend data 19

20 Status: Incomplete (Updated) Eco #: 2 Building: Memorial Library AHU Optimize Economizer Modification of the existing BAS economizer enable/disable setpoint. : Modify the economizer enable/disable setpoint SF-1, SF-2, SF-3 and SF-36 from the existing value of 68 deg. F to the recommended value of 71 deg. F Review control sequence BAS screen verification that the modification of the economizer enable/disable took place. Trend the damper position each of the units during the outside air temperature of 71 deg. F to verify that the damper position transitioned between economizer and non-economizer. Review of heating season data indicates the air handlers still have suboptimal economizer lockout setpoints. MSU Mankato: 1) Confirm which outdoor air temperature trend point is used by the building automation system Memorial Library. 2) Implement a 71 deg economizer OAT lockout SF-1, SF-2, SF-3, and SF-36. 3) Include screen captures showing the economizer lockout SF-1, SF-2, SF-3, and SF-36 4) Continue collecting trend data this measure. Include the relevant Memorial Library OAT point referenced in item 1 of this message block (if a global points is not included already). 20

21 Status: Incomplete (Updated) Eco #: 3 Building: Memorial Library AHU Supply Air Temperature Reset Modify the existing control programming of allow the supply air temperature to float between a minimum and maximum setpoint based on demand. : Modify the existing control programming SF-1 and SF-2 to allow the supply air temperature to float between a minimum (55 deg. F - adj) and maximum (65 deg. F - adj) setpoint based on cooling demand. Monitor the space temperatures being served by the AHU, once 20% (adj) of the space temperature require cooling, allow the supply air temperature setpoint to step from maximum to minimum. Once the space temperature cooling demand has dropped below 5% allow the supply air temperature setpoint to step from minimum to maximum. Review control sequence program modifications and perm functional testing. Trend the number of cooling demand requests (or space temperatures) a minimum of two weeks to verify that all of the spaces meeting the required setpoints. Trend the MAT, DAT, RAT, OAT, SF speed, SF status, DAT setpoint, and OA damper to assure the unit is operating properly to maintain the DAT setpoint. Review of trend data indicates no DAT reset SF-1 and SF-2. MSU Mankato: 1) Clarify if the DAT reset has been implemented, or clarify how the DAT reset will be implemented. 2) Continue to collect trend data. 21

22 Status: Inconclusive Eco #: 4 Building: Memorial Library Reheat Pump Runtime Reduction Pump, HW distribution Modify the existing control sequence programming to allow the pumps to run whenever the outside air temperature is less than 50 deg. F. : Modify the existing control sequence programming to allow the pumps to run whenever the outside air temperature is less than 50 deg. F and any combination of reheat valve control is greater than 10% (adj). If the outside air temperature is greater than 50 deg. F (adj), monitor the reheat valve position and if 15% (adj) of the reheat valves are opening, allow the pumps to start. Disable the pumps when the valve positions are less that 5% (adj). Review the control sequence program modifications and perm functional testing. Trend the reheat valve positions and space temperatures two weeks when the outside air temperature is great than 50 deg. F to verify that the spaces are getting adequate reheat. Trend P-1, P-2, P-5, and P-6 pump status as well to assure they are disengaging and engaging when they should be. Temperature data were not available within the desired OAT range after 10/18/13 to properly confirm implementation. Furthermore, additional points requested in 10/18/13 correspondence were not available review. MSU Mankato: 1) Confirm if MSU Mankato intends to monitor reheat control valves as part of measure implementation. 2) Confirm which outdoor air temperature trend point is used by the building automation system enabling the referenced pumps. 3) Continue to collect trend data. Also, include points HWP1-ST, HWP2-ST, OA-NEWHX, OA-RHTHX, and in addition to previously supplied trend data. 22

23 Morris Hall Status: N/A Eco #: 1 Building: Morris Hall SF-1 Runtime Reduction Modification of the existing BAS schedule. : A schedule will be initiated on SF-1 to shut down the units when there is no occupancy in the building. There will be two schedules. During regular school session from August 24 to May 5 the units will run from 8 AM to 10 PM Monday through Thursday, 8 AM to 5 PM on Friday, and off on Saturday and Sunday. During summer session from May 6 to August 23 the units will run from 8 AM to 4 PM Monday through Friday and be off Saturday and Sunday. The SF status of SF-1 will be trended 15 minute intervals one week during the time period of August 24 to May 5 and one week from May 6 to August 23 to verify it is following the schedule specified in the section of the Findings Workbook. All space temperatures will be trended one week as well during peak heating season and peak cooling season to assure spaces are warming up or cooling down to the desired setpoints bee occupancy of the building. This building was going through a full HVAC renovation, so this measure is no longer valid. None Status: N/A Eco #: 2 Building: Morris Hall SF-1 Optimizer Economizer Modification of the existing BAS economizer enable/disable setpoint. : Modify the economizer enable/disable setpoint from the existing value of 66 deg. F to the recommended value of 71 deg. F. Training will be given to staff so they are aware this value is now 71 F and if they change it due to operational issues, it needs to be documented and investigated why this value was changed. Review control sequence BAS screen verification that the modification of the economizer enable/disable took place. Trend the damper position a two week period each of the units during the outside air temperature range of 60 to 75 deg. F to verify that the damper position transitioned between economizer and noneconomizer. This building was going through a full HVAC renovation, so this measure is no longer valid. None 23

24 Myers Field House Status: Partial (Updated) Eco #: 4 Building: Myers Field House SF-5 and SF-6 have leaky heating valves. Replace leaky steam valve on SF-5 and leaky hot water valve on SF-6 : Building engineer will replace existing low pressure steam valve with new valve. Trending of all relevant points including zone temperature, chilled water and heating valve positions, damper position, DAT, RAT, MAT, and OAT will demonstrate unit operation. The trending shall take place during both summer and winter conditions to ensure unit operates to maintain space temperature requirements both during occupied and unoccupied times. The heating valve SF-5 no longer leaks, but the heating valve SF-6 does. There is a 20F rise across the heating coil, regardless of the valve position. MSU Mankato: Repair/replace the heating valve SF-6. 24

25 Nelson Hall with Addition Status: Incomplete (Updated) Eco #: 1 Building: Nelson w/addition AHU/RTU Runtime Reduction Modification of the existing equipment schedule residing in the BAS. : A schedule will be initiated on all AHUs and RTUs to shut down the units when there is no occupancy in the building. There will be two schedules. During regular school session the units will run as per the earliest scheduled classroom or 8AM whichever is earliest staff and students. Currently the new proposed regular school session schedule unit would be: SF-1: 8 AM-9PM Monday through Thursday, 8 AM to 3 PM Friday and off Saturday and Sunday RTU-2: 8 AM to 10 PM Monday through Thursday, 8 AM to 5 PM Friday and off Saturday and Sunday SF-5: 8 AM to 8 PM Monday through Thursday, 8 AM to 5 PM Friday and off Saturday and Sunday SF-6: 8 AM to 10 PM Monday through Thursday, 8 AM to 5 PM Friday and off Saturday and Sunday SF-7: 8 AM to 6 PM Monday through Thursday, 8 AM to 5 PM Friday and off Saturday and Sunday SF-8: 8 AM to 9 PM Monday through Thursday, 8 AM to 5 PM Friday and off Saturday and Sunday RU-1: 8 AM to 10Pm Monday through Thursday, 8 AM to 6 PM Friday and off Saturday and Sunday RU-2: 8 AM to 5 PM Monday through Friday, off Saturday and Sunday RU-3: 8 AM to 9 PM Monday through Thursday, 8 AM to 6 PM Friday and off Saturday and Sunday The summer schedule each unit currently would be as follows: SF-1: 8 AM to 3 PM Monday through Thursday, 8 AM to noon on Friday, and off Saturday and Sunday RTU-2: 8 AM to 4 PM Monday through Friday and off Saturday and Sunday SF-5: 8 AM to 4 PM Monday through Friday and off Saturday and Sunday SF-6: Monday through Friday 8 AM to 3 PM off Saturday and Sunday SF-7: 8 AM to 4 PM Monday to Friday and off Saturday and Sunday SF-8: Off RU-1: 8 AM to 4 PM Monday through Friday and off Saturday and Sunday RU-2: 8 AM to 4 PM Monday through Friday and off Saturday and Sunday RU-3: 8 AM to 4 PM Monday through Friday and off Saturday and Sunday The SF status of all AHUs will be trended 15 minute intervals one week during the time period of regular school session and one week the summer school session to verify it is following the schedule specified in the section of the Findings Workbook. All space temperatures will be trended one week as well during peak heating season and peak cooling season to assure spaces are warming up or cooling down to the desired setpoints bee occupancy of the building. In general, this measure has not been implemented because all of the AHUs operate at least one more hour per day than the recommended schedule provided in the section above, often as much as 4 extra hours per day. In addition, RTU-2 and RU-3 are run 24/7 during the school year. MSU Mankato: Adjust air handler schedules so that they are operated as few hours as possible while still maintaining comtable spaces occupancy. 25

26 Status: Incomplete Eco #: 5 Building: Nelson w/addition Reheat Pump Runtime Reduction Pump, HW distribution Modify the existing control sequence programming to allow the pumps to run whenever the outside air temperature is less than 55 deg. F. : Modify the existing control sequence programming to allow the pumps to run whenever the outside air temperature is less than 55 deg. F and any combination of reheat valve control is greater than 10% (adj). If the outside air temperature is greater than 55 deg. F (adj), monitor the reheat valve position and if 15% (adj) of the reheat valves are opening, allow the pumps to start. Disable the pumps when the valve positions are less that 5% (adj). Review the control sequence program modifications and perm functional testing. Trend the reheat valve positions and space temperatures two weeks when the outside air temperature is great than 55 deg. F to verify that the spaces are getting adequate reheat. The status of Reheat pump 1 and 2, Auto HW 1 and 2 and the Radiation pump will be trended during this same period to assure they are turning off. The lockout the pumps has been reduced to 75F (from 99F) regardless of the reheat and radiation valve positions. Although the pumps no longer operate between 75 and 99F, they are not operating according to the provider s recommendation. MSU Mankato: Determine if the current pump lockout is sufficient or if the valve positions should be taken into account. The trends indicate that the heating valves were opening well above 75F, which could lead to some spaces getting overcooled. If this was an issue, polling the valves is recommended. 26

27 Pennington Hall NOTE: During verification, CEE discovered that the duct static pressure sensor AHU-5 is likely out of calibration. It reads 0.5 wc when the unit is off. Status: Incomplete Eco #: 4 Building: Pennington Hall Leaky valve chilled water valve Replace leaky chilled water valve : The current leaking valve will have to be replaced by a new valve. The sequences will then have to be checked to assure when the valve is closed it is not leaking and when it is 100% open it is meeting system design requirements. Field verify the valve replacement. Trend the following points on the building automation system AHU5 and CHWP-3 a two week period during the summer season: SF status, SF speed. OAT, RAT, MAT, DAT, OA Damper, chilled water valve, hot water valve, zone temperature, CHWP 3 status, and CHWP 3 differential pressure. When the chilled water valve is closed and AHU-5 is on, the DAT is much lower than the MAT, even with the hot water valve wide open. The chilled water valve is clearly still leaking. MSU Mankato: Replace the chilled water valve. 27

28 Status: Inconclusive (Updated) Perming Arts Eco #: 2 Building: Perming Arts Exhaust fan 31 Other Currently exhaust fan 31(10,000cfm) serves the scene shop area in the preming arts center and is being left on extensive periods of time. : The existing on/off switch will be replaced with a timer switch the will energize the fan four hours once it is turned on then turn off until the button is re-energized. The exhaust fan status will be trended a two week period. A temperature logger will be placed in the area as well to show when the fan is off, the zone temperature is remaining constant and not requiring as much heat as bee. If there is a reheat valve associated with the room the data logger is in that will be trended as well. This exhaust fan was never operated during the summer or school year. It is unclear why it was never operated and if it is turned on, whether the fan will only operate 4 hours as intended. MSU Mankato: review changes that were made to the exhaust fan on/off switch to ensure the fan will run when switched on to avoid issues with indoor air quality. 28

29 Status: Incomplete Eco #: 3 Building: Perming Arts Simultaneous heating and cooling on AHU1 Air handler unit 1 and 2 are simultaneously heating and cooling due to poor controls sequencing. : Revise existing controls sequence: When there is a call mechanical cooling, the cooling control valve is modulated to maintain a discharge temperature set point of 55F. The fan speed is modulated to maintain the space temperature set point. The heating valve shall be disabled when the outdoor air temperature is greater than 55F. When there is a call heating open reheat control valve to maintain space temperature. The unit will be trended two weeks during the summer season. The following points will be trended, SF status, SF speed, OAT, RAT, MAT, DAT, Chilled water valve, Hot water valve, Space temperature, and RF VFD. This measure has not been implemented. During the summer the cooling valve fully opens when the AHU turns on and remains at 100% open all day. Meanwhile, the heating valve modulates open and closed throughout the day to raise the DAT, since the fully open cooling valve lowers the DAT too much. MSU Mankato: Revise the controls sequences per the above. 29

30 Status: Complete (Updated) Eco #: 1 Building: Perming Arts Andreas Theater Makeup/changing room and bathroom exhaust is running 24/7 when area is unoccupied. Currently the exhaust fans the two make-up/changing areas and the two bathrooms located backstage are operating 24/7. These areas are not used except during dress rehearsals and theater permances. : The controls contractor will install 2 occupancy sensors. One located in the women's makeup changing room and one located in the men's makeup changing room. The Controls contractor will also interlock the bathroom exhaust fans with the corresponding make-up room exhaust fans. Once the occupancy sensor is triggered the corresponding exhaust fans will energize and the outdoor air damper on AHU-2 will modulate open to accommodate additional makeup air demand once the room becomes unoccupied the exhaust fans will de-energize and the outdoor air damper will modulate back to a minimum position. A balancer will have to balance the OA dampers to assure the OA dampers are allowing the proper amount of air. There will have to be 2 balance points, one when the exhaust fans are on and one when the exhaust fans are off. The Exhaust fan status, OA dampers, OAT, MAT, RAT, DAT, OACFM, heat valve, and chilled water valve will be trended a two week period to insure the unit is operating as specified. The PRVs and AHU turn on and off and are no longer running 24/7, but the operating hours seem to be excessive. The PRVs are frequently operated 10 hours at a time, often starting at 2AM, which would not be the expected occupancy start time. In addition, AHU-2 was operated non-stop from Jan AHU-2 does appear to be bringing in the proper amounts of outside air and is no longer running 24/7, so this measure is considered implemented. None 30

31 Taylor Center Status: Incomplete Eco #: 1 Building: Taylor Center SF-5/EF-9 Schedule Utilizing the existing VFD's on both the supply and exhaust fans will allow fan energy savings as well as cooling and heating savings of outdoor air during low occupancy times. : is to utilize VFD's both the supply and exhaust fans. During occupied conditions, the supply fan speed shall modulate to maintain a space temperature set point and the heating and cooling valves shall modulate to maintain a constant discharge air temperature. The exhaust fan VFD shall modulate to maintain a set offset with the supply fan VFD to maintain a negative pressure with respect to adjacent spaces. During unoccupied times, the supply and exhaust fan VFD settings shall be set to maintain a constant exhaust rate per ASHRAE guidelines. The heating and cooling valves shall continue to modulate to maintain a night setback temperature at a reduced temperature during winter and an increased temperature during summer during unoccupied times additional energy savings. Test and balancer shall set minimum VFD speeds as required to maintain minimum exhaust rate required the space. Controls contractor to upgrade controls strategy as required. Trending of all relevant points including zone temperature, chilled water and hot water valve positions, damper position, VFD fan speeds, DAT, RAT, MAT, RAH, EAT, and OAT will demonstrate unit operation. The trending shall take place during both summer and winter conditions to ensure unit operates to maintain space temperature requirements both during occupied and unoccupied times. This measure was not implemented as intended. Rather than creating a setback where the temperature in the space sets back and the fan speed slows down, the static pressure setpoint was changed from 1.5" to 0.5" at all times. As a result, the space temperature setpoint of 68 is not being met during the summer. It stays in the mid-70s due to insufficient airflow. This measure needs to be adjusted or there will be comt complaints. MSU Mankato: Revise the controls sequences per the above. 31

32 Trafton Hall Status: Complete Eco #: 1 Building: Trafton Hall AHU Scheduling AHU's 1A, 1B, 2, and 3. Currently AHU's 1A, 1B, 2, and 3 are operating 24/7. Building management along with the controls contractor shall adjust AHU's to follow occupancy schedule on BAS system : Air handler units 1A, 1B, 2, and 3 will be scheduled on from 7 AM to 9 PM Monday through Friday and off on Saturday and Sunday. Hours of operation will be determined at the start of each semester and dictated by class schedules. Summer operation air handler units 1A, 1B, 2, and 3 is as follows: When the space is unoccupied and the outdoor air temperature is above 55 deg. F the unit will de-energize, the chilled water and heating water valves will close, and the outdoor air dampers will close. Winter operation air handler units 1A, 1B, and 3 is as follows: When the space is unoccupied and the outdoor air temperature is below 55deg. F the unit will de-energize, the chilled water valve will close, the heating water valve will open, and the outdoor air dampers will close. When the space temperature is below the unoccupied set point of 55deg. F, the unit will energize to meet the unoccupied set point, at this time the OA dampers will remain closed. Winter operation air handler unit 2 is as follows: When the space is unoccupied and the outdoor air temperature is below 55deg. F but warmer than 40deg. F the unit will de-energize, the chilled water valve will close, the heating water valve will open, and the outdoor air dampers will close. When the space temperature is below the unoccupied set point of 55deg. F, the unit will energize to meet the unoccupied set point, at this time the OA dampers will open to minimum position. The AHU status, OA dampers, MAT, RAT, DAT, heating water valve, chilled water valve, and space temperatures will be trended a two week period to assure the units are off when specified. Trends will be recorded during the winter season to verify the unit will operate when the outdoor air temperature is too cold, the unit turns on to bring the required space to unoccupied set point. The morning warmup routine will be seen in the trends as well. The units now operate 7am - 9pm M-F and are off weekends. This measure has been implemented. None required 32

AIR HANDLING SYSTEM RETRO-COMMISSIONING TRENDING ANALYSIS

AIR HANDLING SYSTEM RETRO-COMMISSIONING TRENDING ANALYSIS AIR HANDLING SYSTEM RETRO-COMMISSIONING TRENDING ANALYSIS 1 AIR HANDLING UNIT TRENDS 2 1. The trending charts provided on the following pages prepared as part of a retro-commissioning investigation. The

More information

SEQUENCE OF OPERATION GUIDELINE. AIR TERMINAL UNITS SINGLE DUCT VARIABLE AIR VOLUME with HOT WATER REHEAT or ELECTRIC HEAT

SEQUENCE OF OPERATION GUIDELINE. AIR TERMINAL UNITS SINGLE DUCT VARIABLE AIR VOLUME with HOT WATER REHEAT or ELECTRIC HEAT SEQUENCE OF OPERATION GUIDELINE AIR TERMINAL UNITS SINGLE DUCT VARIABLE AIR VOLUME with HOT WATER REHEAT or ELECTRIC HEAT Document: VAV-HTG rev1 Revision: 1.0 Rev. Date: July 22, 2011 NOTES: 1. THIS SEQUENCE

More information

HVAC Controls Upgrades: Requirement Details ( )

HVAC Controls Upgrades: Requirement Details ( ) REQUIRED CONTROLS/FEATURES HVAC non CENTRAL PLANT 1) Zone Level Scheduling & Override for all air handlers (supply and exhaust) to match occupied hours by zone DDC or occupancy sensors (OS) allowed. (403.2.4.3,

More information

Retrocommissioning Findings Summary: Building X #1 Priority: Major Comfort/Control Problems

Retrocommissioning Findings Summary: Building X #1 Priority: Major Comfort/Control Problems IMPORTANT NOTICE: This sample document is provided for instructional purposes only. CCC is not rendering advice concerning any commission project or practices. This document is neither approved nor intended

More information

HVAC Controls Upgrades: Requirement Details ( )

HVAC Controls Upgrades: Requirement Details ( ) REQUIRED CONTROLS/FEATURES To qualify the upgrade must add or substantially modify 3 or more sequences/system capabilities. Also, all sequences and items listed under the required section are needed in

More information

Digital Precise Air Control - DPAC

Digital Precise Air Control - DPAC Digital Precise Air Control - DPAC Mode Enable Sensor Options The temperature of this sensor will determine if the unit is in heating, cooling or vent mode during Occupied operation. The following options

More information

SECTION SEQUENCE OF OPERATION FOR HVAC CONTROLS PART 1 GENERAL

SECTION SEQUENCE OF OPERATION FOR HVAC CONTROLS PART 1 GENERAL SECTION 15910 SEQUENCE OF OPERATION FOR HVAC CONTROLS PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

Job Name Control Systems Description Date

Job Name Control Systems Description Date Job Name Control Systems Description Date Project Overview The project is a describe the building and its major HVAC systems (e.g. three-story office building, served by a rooftop unit VAV system ). In

More information

A. Base Bid: 1. Heating Contractor provide: a. Control sequences for HVAC systems, subsystems, and equipment.

A. Base Bid: 1. Heating Contractor provide: a. Control sequences for HVAC systems, subsystems, and equipment. SECTION 23 09 93 - SEQUENCE OF OPERATIONS FOR HVAC CONTROLS PART 1 - GENERAL 1 WORK INCLUDES A. Base Bid: Heating Contractor provide: Control sequences for HVAC systems, subsystems, and equipment. B. Alternate

More information

Civil Engineering Building

Civil Engineering Building Continuous Commissioning Report For the Civil Engineering Building Building 492 Submitted to: Utilities Energy Office Physical Plant Department Texas A&M University Prepared by: Energy Systems Laboratory

More information

SECTION SEQUENCE OF OPERATIONS FOR HVAC CONTROLS

SECTION SEQUENCE OF OPERATIONS FOR HVAC CONTROLS SECTION 23 09 93 SEQUENCE OF OPERATIONS FOR HVAC CONTROLS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes control sequences for HVAC systems, subsystems, and equipment. B. See Division 23 Section

More information

Submitted to. Texas A&M University at Galveston The Texas A&M University System. Submitted by. Yeqiao Zhu Dan Turner David Claridge

Submitted to. Texas A&M University at Galveston The Texas A&M University System. Submitted by. Yeqiao Zhu Dan Turner David Claridge ESL-TR-99/12-05 Report of Energy Efficiency Study and Metering/Utilities Profile for Electricity Deregulation at the Texas A&M University at Galveston (TAMU-G) Galveston, Texas Submitted to Texas A&M University

More information

Your Home. Jacco & Assoc.

Your Home. Jacco & Assoc. Your Home Fan on with call for heating or cooling Heating on with call from space thermostat Stage as required to maintain The 75F Basics adj. - First stage of heating shall be heat pump Cooling on with

More information

Submitted to. Texas A&M University-Corpus Christi The Texas A&M University System. Submitted by. Yeqiao Zhu Dan Turner David Claridge

Submitted to. Texas A&M University-Corpus Christi The Texas A&M University System. Submitted by. Yeqiao Zhu Dan Turner David Claridge ESL-TR-99/12-04 Report of Energy Efficiency Study and Metering/Utilities Profile for Electricity Deregulation at the Texas A&M University-Corpus Christi (TAMU-CC) Corpus Christi, Texas Submitted to Texas

More information

SEQUENCE OF OPERATION FOR ALC CONTROL AIR SOURCE HEATPUMP 100% OUTSIDE AIR

SEQUENCE OF OPERATION FOR ALC CONTROL AIR SOURCE HEATPUMP 100% OUTSIDE AIR SEQUENCE OF OPERATION FOR ALC CONTROL AIR SOURCE HEATPUMP 100% OUTSIDE AIR Printed in the USA ADSOOASHPOA 0117 Orig SEQUENCE OF OPERATION The ALC controller is turned on by a switch located on its front

More information

Computing Services Center

Computing Services Center Continuous Commissioning Report for the Computing Services Center Building #516 Submitted to: Utilities Energy Office Physical Plant Department Texas A&M University Prepared by: Energy Systems Laboratory

More information

CARRIER edesign SUITE NEWS. Modeling 100% OA Constant Volume Air Systems. Volume 6, Issue 1. Page 1 Modeling 100% OA Constant Volume Air Systems

CARRIER edesign SUITE NEWS. Modeling 100% OA Constant Volume Air Systems. Volume 6, Issue 1. Page 1 Modeling 100% OA Constant Volume Air Systems Volume 6, Issue 1 CARRIER edesign SUITE NEWS Modeling 100% OA Constant Volume Air Systems This article provides an overview of how to model a stand-alone constant air volume (CAV) 100% OA system in HAP.

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-23 09 93 (November 2015) ----------------------------- Preparing Activity: USACE Superseding UFGS-23 09 23 (May 2011) UNIFIED FACILITIES GUIDE SPECIFICATIONS References

More information

UNIVERSITY OF MISSOURI Heating Ventilating and Air-Conditioning (HVAC) 2016 Q1

UNIVERSITY OF MISSOURI Heating Ventilating and Air-Conditioning (HVAC) 2016 Q1 GENERAL: This section provides general standards for overall sizing and design of Heating, Ventilating, and Air Conditioning (HVAC) systems. Other sections contain specific standards for each system per

More information

Continuous Commissioning: A Valuable Partner to Retrofit Projects

Continuous Commissioning: A Valuable Partner to Retrofit Projects Continuous Commissioning: A Valuable Partner to Retrofit Projects Yeqiao Zhu Aamer Athar Kenneth Banks Ph.D. PE, CEM PE, CEM Energy Systems Laboratory Sempra Energy Solutions Sempra Energy Solutions Charles

More information

ZIP Economizer Method of Operation Sequence of Operation States Virgin State The ZIP Economizer comes shipped from the factory in this state. Setup Incomplete will be displayed. No control will occur until

More information

SEQUENCE OF OPERATION FOR ALC CONTROL AIR SOURCE HEATPUMP RECIRCULATION AIR WITH ECONOMIZER

SEQUENCE OF OPERATION FOR ALC CONTROL AIR SOURCE HEATPUMP RECIRCULATION AIR WITH ECONOMIZER SEQUENCE OF OPERATION FOR ALC CONTROL AIR SOURCE HEATPUMP RECIRCULATION AIR WITH ECONOMIZER Printed in the USA ADSOOASHPRAE 0117 Orig SEQUENCE OF OPERATION The ALC controller is turned on by a switch located

More information

Verasys System Operation Overview Technical Bulletin

Verasys System Operation Overview Technical Bulletin Contents subject to change. Verasys System Operation Overview Technical Bulletin Code No. LIT-12012370 Issued January 2016 Refer to the QuickLIT Web site for the most up-to-date version of this document.

More information

RE: Phase 2 Improvements DATE: July 1, 2016 New Administration Building Wernle Youth & Family Treatment Center 2000 Wernle Road Richmond, Indiana

RE: Phase 2 Improvements DATE: July 1, 2016 New Administration Building Wernle Youth & Family Treatment Center 2000 Wernle Road Richmond, Indiana ADDENDUM NO. 2 RE: Phase 2 Improvements DATE: July 1, 2016 New Administration Building Wernle Youth & Family Treatment Center 2000 Wernle Road Richmond, Indiana TO: All Bidders Gentlemen: This Addendum

More information

SECTION SEQUENCE OF OPERATIONS FOR HVAC CONTROLS

SECTION SEQUENCE OF OPERATIONS FOR HVAC CONTROLS PART 1 - GENERAL SECTION 23 09 93 SEQUENCE OF OPERATIONS FOR HVAC CONTROLS 1.1 SUMMARY A. This Section includes control sequences for HVAC systems, subsystems, and other equipment. B. See Division 23 Section

More information

OSU Alumni Center Phase I Implementation Review. Oregon State University 130 Oak Creek Bldg. Corvallis, Oregon

OSU Alumni Center Phase I Implementation Review. Oregon State University 130 Oak Creek Bldg. Corvallis, Oregon OSU Alumni Center Phase I Implementation Review Prepared for Oregon State University 130 Oak Creek Bldg. Corvallis, Oregon 97331 October 31, 2011 Job No. 02.11.00113 Introduction: Glumac was engaged by

More information

IAQ: Re-tuning Commercial Buildings

IAQ: Re-tuning Commercial Buildings IAQ: Re-tuning Commercial Buildings A low-cost path to improved air quality and energy efficiency. B y S c o t t G o r d o n, C M All images courtesy of Johnson Controls Service. 10 RSES Journal FEBRUARY

More information

Submitted to. Texas A&M University at Commerce The Texas A&M University System. Submitted by. Guanghua Wei Craig Campbell David Claridge Dan Turner

Submitted to. Texas A&M University at Commerce The Texas A&M University System. Submitted by. Guanghua Wei Craig Campbell David Claridge Dan Turner ESL-TR-99/12-09 Report of Energy Efficiency Study and Metering/Utilities Profile for Electricity Deregulation at the Texas A&M University at Commerce (TAMU-Commerce) Commerce, Texas Submitted to Texas

More information

1.0 Digital Controller

1.0 Digital Controller Form CP-AHU D19_D21_D22 (11-17) D303072-A Obsoletes Forms CP-Preeva-D21 (1-16) Doc No 303072, CP-Preeva-D19 (1-16) Doc No 303071 Applies to: Preeva, MAPS, MAPS II, RPB, RPBL & SSCBL Series For Air Handler

More information

Improving Performance with a Building Tune-Up. Janice Peterson, P.E. LEED AP Market Manager, Building Operations BetterBricks

Improving Performance with a Building Tune-Up. Janice Peterson, P.E. LEED AP Market Manager, Building Operations BetterBricks Improving Performance with a Building Tune-Up Janice Peterson, P.E. LEED AP Market Manager, Building Operations BetterBricks How much is too much? Most buildings can cut total energy use by 5-30% while

More information

FLORIDA A&M UNIVERSITY PERFORMANCE CONTRACT SCOPE OF WORK

FLORIDA A&M UNIVERSITY PERFORMANCE CONTRACT SCOPE OF WORK FLORIDA A&M UNIVERSITY PERFORMANCE CONTRACT SCOPE OF WORK ENERGY CONSERVATION MEASURE 1 Partial Steam System Decentralization SIEMENS will Furnish and Install condensing hot water boilers with associated

More information

SECTION SEQUENCE OF OPERATIONS FOR BUILDING CONTROLS

SECTION SEQUENCE OF OPERATIONS FOR BUILDING CONTROLS PART 1 GENERAL 1.01 SECTION INCLUDES SECTION 23 0993 SEQUENCE OF OPERATIONS FOR BUILDING CONTROLS A. This section defines the manner and method by which controls function. Requirements for each type of

More information

American University Design Standards

American University Design Standards 25 95 00 CONTROL SEQUENCES FOR HVAC PART 1. GENERAL 1.01 SECTION INCLUDES A. Description of Work B. Control Sequences General Requirements C. System Specific Control Sequences 1.02 RELATED DOCUMENTS A.

More information

TEC Controller VAV 0-10V Fan Control with Hot Water Heat, Application Application Note Building Technologies

TEC Controller VAV 0-10V Fan Control with Hot Water Heat, Application Application Note Building Technologies TEC Controller VAV 0-10V Fan Control with Hot Water Heat, Application 2236 Application Note 140-1228 Building Technologies Table of Contents Overview... 4 Hardware Inputs... 10 Hardware Outputs... 10

More information

Metasys Integrator TITUS Application

Metasys Integrator TITUS Application Metasys Connectivity Technical Manual 629.5 Metasys Integrator Section Application Note Issue Date October 12, 2005 APPLICATION NOTE Metasys Integrator TITUS Application lntroduction Page 3 Application

More information

Continuous Commissioning of Commercial Kitchen and Dining Facilities Case Study

Continuous Commissioning of Commercial Kitchen and Dining Facilities Case Study The 7 th International onference for Enhanced Building Operations (IEBO 2007) ontinuous ommissioning of ommercial Kitchen and Dining Facilities ase Study Hui Li, hen Xu, Qiang hen and Song Deng Energy

More information

Technical Report #3 Mechanical Systems Existing Conditions Evaluation

Technical Report #3 Mechanical Systems Existing Conditions Evaluation Mechanical Option Technical Report #3 Technical Report #3 Mechanical Systems Existing Conditions Evaluation Instructor: Dr. Bahnfleth 11.15.04 Building Sponsor: CCG Facilities Integration Table of Contents

More information

MicroTech Self-Contained Air Conditioning System

MicroTech Self-Contained Air Conditioning System Open Protocol Data Information Packet Version 2.3 Group: Controls Date: October 1999 MicroTech Self-Contained Air Conditioning System Open Protocol Data Communications t 2002 McQuay International - C O

More information

DIGI-VAV APPLICATIONS

DIGI-VAV APPLICATIONS DIGI-VAV DIGI-VAV APPLICATIONS Digi-VAV: An optimization kit for Variable Air Volume Air Handling Units (VAV AHU) that ensures individual zone indoor air quality (IAQ), and minimizes system energy consumption.

More information

Physical Plant Complex

Physical Plant Complex Continuous Commissioning Report For the Physical Plant Complex Building #1156 Submitted to: Utilities Energy Office Physical Plant Department Texas A&M University Prepared by: Energy Systems Laboratory

More information

RCE # April 30, 2013 Centennial School District William Tennent HS, Region 3 ES, Region 1 ES, Region 2 ES

RCE # April 30, 2013 Centennial School District William Tennent HS, Region 3 ES, Region 1 ES, Region 2 ES RCE #12-4181 April 30, 2013 Centennial School District William Tennent HS, Region 3 ES, Region 1 ES, Region 2 ES Commissioning Progress Report The Commissioning Technician returned to visit R2ES and R1ES

More information

control sequences model QST / EST Series Table 47: QST / EST Analog Electronic Control Strategies Fan Powered Air Terminals

control sequences model QST / EST Series Table 47: QST / EST Analog Electronic Control Strategies Fan Powered Air Terminals control sequences Table 47: QST / EST Analog Electronic Control Strategies Control Package Number QST EST FS-A-5000 FSE-A-5000 FS-A-5001 FSE-A-5001 FS-A-5002 FSE-A-5002 FS-A-5003 FSE-A-5003 FS-A-5004 FSE-A-5004

More information

Prescriptions for Critical Healthcare Cx. John D. Villani, P.E. Associate Grumman/Butkus Associates

Prescriptions for Critical Healthcare Cx. John D. Villani, P.E. Associate Grumman/Butkus Associates Prescriptions for Critical Healthcare Cx John D. Villani, P.E. Associate Grumman/Butkus Associates AIA Quality Assurance Learning Objectives 1. Medical Industry Changes and how they impact Design, Construction,

More information

Building Automation System (BAS) Design Criteria

Building Automation System (BAS) Design Criteria 25 0520 Building Automation System (BAS) Design Criteria 1. Design Statement a. During the various design phases of this project, the Engineer will develop options and strategies for selection of the appropriate

More information

The Creative and Performing Arts High School (CAPA) Pittsburgh, PA 11/11/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma

The Creative and Performing Arts High School (CAPA) Pittsburgh, PA 11/11/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma Objectives and Requirements For the Creative and Performing Arts High School (CAPA), the main objective of the mechanical design is to provide an energy efficient system that is easily maintainable and

More information

BAS Point Trend Data Guidance

BAS Point Trend Data Guidance BAS Point Trend Data Guidance Rev. 3, January 2018 Introduction The Building Automation System (BAS also, referred to as a DDC system, or a Direct Digital Control system) at your building has been set-up

More information

ASHRAE JOURNAL ON REHEAT

ASHRAE JOURNAL ON REHEAT Page: 1 of 7 ASHRAE JOURNAL ON REHEAT Dan Int-Hout Chief Engineer Page: 2 of 7 Overhead Heating: A lost art. March 2007 ASHRAE Journal Article Dan Int-Hout Chief Engineer, Krueger VAV terminals provide

More information

4. OVERVIEW OF MECHANICAL SYSTEM

4. OVERVIEW OF MECHANICAL SYSTEM 4. OVERVIEW OF MECHANICAL SYSTEM The 87,000 SF SLCC is served by six (6) Trane M-Series Climate Changer Air Handing Units (AHUs). Each unit serves a distinct zone within the facility that is unique in

More information

Sequence of Operations (excerpt)

Sequence of Operations (excerpt) Sequence of Operations (excerpt) Chilled Water System Consists of one (1) 600 cooling ton Trane CVHE 3 stage centrifugal chiller, with associated chilled water pumps, condenser water pumps and one (1)

More information

Your Home. Jacco & Assoc. Fan on with call for heating or cooling Heating on with call from space thermostat Stage as

Your Home. Jacco & Assoc. Fan on with call for heating or cooling Heating on with call from space thermostat Stage as Your Home Fan on with call for heating or cooling Heating on with call from space thermostat Stage as required Controlling to maintain 75F HVAC adj. Systems First stage of heating shall be heat pump Cooling

More information

The M & V Guided Recommissioning Process. Energy & Water Conservation Program. September 2015 MOO

The M & V Guided Recommissioning Process. Energy & Water Conservation Program. September 2015 MOO The M & V Guided Recommissioning Process MOO Energy & Water Conservation Program September 2015 EWC Agenda MOO EWC Overview Our approach Progress Fault Detection Zone & customer feedback Variance reporting

More information

Andrea Borowski The Pennsylvania State University University Park, PA November 11, 2002 Consultant: Dr. Bahnfleth Technical Assignment M-3

Andrea Borowski The Pennsylvania State University University Park, PA November 11, 2002 Consultant: Dr. Bahnfleth Technical Assignment M-3 Existing System Evaluation Executive Summary The MBNA Career Services Center is a 44,000 square foot, 4-story office type building at Penn State University, University Park Campus. The building is located

More information

ADDISON SEQUENCE OF OPERATION FOR ALC CONTROL AIRSOURCE HEATPUMP 100% OUTDOOR AIR VERSION Telephone:

ADDISON SEQUENCE OF OPERATION FOR ALC CONTROL AIRSOURCE HEATPUMP 100% OUTDOOR AIR VERSION Telephone: ADDISON SEQUENCE OF OPERATION FOR ALC CONTROL AIRSOURCE HEATPUMP 100% OUTDOOR AIR VERSION 2.0 www.addison-hvac.com Telephone: +1.407.292.4400 1 2 OCCUPIED MODE: When the program control source calls for

More information

Reference Guide for Microprocessor Controller

Reference Guide for Microprocessor Controller Document 483586 Microprocessor Controller for Dedicated Outdoor Air System Reference Guide for Microprocessor Controller Please read and save these instructions for future reference. Read carefully before

More information

York 25-Ton VAV Rooftop Unit

York 25-Ton VAV Rooftop Unit HVAC PRO for Windows User s Manual 637.5 OEM Section Technical Bulletin Issue Date 0996 York 25-Ton VAV Rooftop Unit Introduction Page 3 Overview *3 Configuration 5 Sequence of Operation 7 Modes of Operation

More information

Madeira City Schools Madeira, Ohio. HVAC Assessment. December 2011 (Revised February 2012)

Madeira City Schools Madeira, Ohio. HVAC Assessment. December 2011 (Revised February 2012) Madeira City Schools Madeira, Ohio HVAC Assessment December 2011 (Revised February 2012) Prepared by: CMTA Engineering Consultants, Inc. 10411 Meeting Street Prospect, KY 40059 www.cmtaegrs.com (502) 326-3085

More information

DX-9100 Applications from Engineering Services

DX-9100 Applications from Engineering Services System 9100 Technical Manual 636.4 Application Examples Section Technical Bulletin Issue Date 0896 DX-9100 Applications from Engineering Services Introduction Page 3 Overview 3 Air Handling Unit Applications

More information

DACC Health Sciences Building Air Handler Assessment/Study

DACC Health Sciences Building Air Handler Assessment/Study DACC Health Sciences Building Air Handler Assessment/Study NMSU Facilities and Services Department P.O. Box 30001 Las Cruces, NM 88003-8001 June 14, 2016 Final Submittal 1065 S. Main St., Bldg. D, Ste.

More information

MicroTech Rooftop/RMC

MicroTech Rooftop/RMC Open Protocol Data Communications Packet Version 4.1 Group: Controls Date: March 1999 MicroTech Rooftop/RMC Data Information Packet for Open Protocol 1999 McQuay International Revision History Version

More information

ADDISON SEQUENCE OF OPERATION FOR ALC CONTROL AIRSOURCE COOLING-ONLY 100% OUTSIDE AIR VERSION Telephone:

ADDISON SEQUENCE OF OPERATION FOR ALC CONTROL AIRSOURCE COOLING-ONLY 100% OUTSIDE AIR VERSION Telephone: ADDISON SEQUENCE OF OPERATION FOR ALC CONTROL AIRSOURCE COOLING-ONLY 100% OUTSIDE AIR VERSION 2.0 www.addison-hvac.com Telephone: +1.407.292.4400 1 SEQUENCE OF OPERATION The ALC controller is turned on

More information

Reference Guide for Microprocessor Controller

Reference Guide for Microprocessor Controller Document 483232 Microprocessor Controller for Energy Recovery Reference Guide for Microprocessor Controller Please read and save these instructions for future reference. Read carefully before attempting

More information

Auburn University Basketball Arena:

Auburn University Basketball Arena: Auburn University Basketball Arena: How Building Data Analytics Achieved Energy and O&M Savings While Improving Comfort and Sustainability Eric Moore, PE, CEM, Auburn University Hadas Webb, CEM, Cimetrics

More information

Florida Department of Transportation

Florida Department of Transportation Page 1 of 7 RICK SCOTT GOVERNOR Florida Department of Transportation 1109 S. Marion Avenue Lake City, Florida 32025 ANANTH PRASAD SECRETARY September 27, 2011 To: Proposal Holders Addendum No: 1, E2Q23,

More information

ADDENDUM No: 3 JOSEPHINE COUNTY BUILDING OPERATIONS DEPARTMENT. February 29, NO CHANGE: March 8, 2012 / NOT LATER THAN 2:00 PM

ADDENDUM No: 3 JOSEPHINE COUNTY BUILDING OPERATIONS DEPARTMENT. February 29, NO CHANGE: March 8, 2012 / NOT LATER THAN 2:00 PM ADDENDUM No: 3 JOSEPHINE COUNTY BUILDING OPERATIONS DEPARTMENT February 29, 2012 RFP NO: 17 PROJECT: Josephine County Justice Center HVAC Upgrades BID CLOSING DATE: NO CHANGE: March 8, 2012 / NOT LATER

More information

SEQUENCE OF OPERATIONS

SEQUENCE OF OPERATIONS SEQUENCE OF OPERATIONS DDC CONTROLLER: Controller with integral LCD readout for changing set points and monitoring unit operation. Provided with required sensors and programming. Factory programmed, mounted,

More information

Paul McCown, PE, CEM, LEED AP, CxA Sr. Mechanical Engineer SSRCx, LLC Nashville, TN USA

Paul McCown, PE, CEM, LEED AP, CxA Sr. Mechanical Engineer SSRCx, LLC Nashville, TN USA Continuous Commissioning of a LEED-EB Gold Certified Office Building Paul McCown, PE, CEM, LEED AP, CxA Sr. Mechanical Engineer SSRCx, LLC Nashville, TN USA KEYWORDS Continuous Commissioning, Retro-Commissioning,

More information

Meter* (Existing or New) Comments 13,800 volt at plant or piggy back All Campus Utility Service Val Imm Electric Generator Building Existing

Meter* (Existing or New) Comments 13,800 volt at plant or piggy back All Campus Utility Service Val Imm Electric Generator Building Existing Attachment 1 - Projected metering points The following tables are the good faith attempt to indentify all metering points for base bid. However, due to the complexity of the project and anticipation of

More information

INTRODUCTION TO: ASHRAE STANDARD 90.1, HVAC System Requirements for Reducing Energy Consumption in Commercial Buildings

INTRODUCTION TO: ASHRAE STANDARD 90.1, HVAC System Requirements for Reducing Energy Consumption in Commercial Buildings INTRODUCTION TO: ASHRAE STANDARD 90.1, 2013 HVAC System Requirements for Reducing Energy Consumption in Commercial Buildings Rocky Mountain ASHRAE Technical Conference, April 29, 2016 SEAN BEILMAN, P.E.,

More information

Guide Spec Summary. Option List. Date: 05/21/2001. EarthWise VAV Terminal Units Full Spec. Prepared by: Phone Number: Prepared for:

Guide Spec Summary. Option List. Date: 05/21/2001. EarthWise VAV Terminal Units Full Spec. Prepared by: Phone Number: Prepared for: Date: 05/21/2001 Time: 02:57:44 PM Job Name: EarthWise VAV Terminal Units Full Spec Location: AnyTown, Earth Prepared by: Phone Number: Prepared for: Guide Spec Summary Option List SINGLE & DUAL DUCT UNIT

More information

Product Manual SZ1009

Product Manual SZ1009 Product Manual SZ1009 Conventional Heating & Cooling Thermostats with Heat Pump Mode Communicating Thermostats Description The SZ1009 is a microprocessor-based mable thermostats designed for conventional

More information

Single zone RTU, controlled by a programmable thermostat. Single zone RTU, generic description, with power exhauster

Single zone RTU, controlled by a programmable thermostat. Single zone RTU, generic description, with power exhauster Rooftop Units CV Reheat RTU Reheat Reheat system RTU, serving electric reheat coils, w/dehumidification cycle & RA CO2 override of OAD CV Single Zone RTU SZ (from PC) RTU SZ Generic RTU SZ Multiple Units

More information

1.1 DESCRIPTION A. The purpose of this section is to specify Division 23 responsibilities in the commissioning (Cx) process.

1.1 DESCRIPTION A. The purpose of this section is to specify Division 23 responsibilities in the commissioning (Cx) process. SECTION 239950 MECHANICAL COMMISSIONING SYSTEMS PART 1 - GENERAL 1.1 DESCRIPTION A. The purpose of this section is to specify Division 23 responsibilities in the commissioning (Cx) process. B. Commissioning

More information

Case Study: Furman University Charles H. Townes Center for Science. Michael K. Mantai, PE, CCP President System WorCx

Case Study: Furman University Charles H. Townes Center for Science. Michael K. Mantai, PE, CCP President System WorCx Case Study: Furman University Charles H. Townes Center for Science Michael K. Mantai, PE, CCP President System WorCx AIA Quality Assurance Learning Objectives 1. Case study example of Chilled Beam technology

More information

COMcheck Software Version Review Mechanical Compliance Certificate

COMcheck Software Version Review Mechanical Compliance Certificate COMcheck Software Version 4.0.7.2 Review Mechanical Compliance Certificate Section 1: Project Information Energy Code: 2014 Oregon Energy Efficiency Specialty Code Project Title: Benton County Health Project

More information

Welsh Commissioning Group, Inc.

Welsh Commissioning Group, Inc. Ongoing Commissioning with Building Automation System and Data Loggers Bryan W. Welsh, P.E. President Welsh Commissioning Group, Inc. AIA Quality Assurance Learning Objectives 1. General understanding

More information

User s Manual

User s Manual 997-060180-4e User s Manual 8403-060 Menu Driven Display 1120-445 I. CONTROLLER OPERATION ADJUSTING TEMPERATURE (Temporary Override when in Programmable mode) 1. Before you can adjust the temperature,

More information

BES-TECH TECHNOLOGY & SYSTEM INTEGRATION

BES-TECH TECHNOLOGY & SYSTEM INTEGRATION BES-TECH TECHNOLOGY & SYSTEM INTEGRATION BES-TECH TECHNOLOGY & SYSTEM INTEGRATION DIGI-ACC Digi-ACC is a control kit for air cooled chiller systems, optimizing both chiller and pumps thereby reducing consumption

More information

OWNER S MANUAL. Part Number P

OWNER S MANUAL. Part Number P OWNER S MANUAL CPV230 Commercial Thermostat Part Number P374-2300 CONTENTS Page GENERAL...2 CONFIGURATION...3-12 Thermostat Display...3 Heat or Cool Indicator...4 Thermostat Front Panel Buttons...4 Thermostat

More information

1.0 Digital Controller

1.0 Digital Controller 1.0 Digital Controller...1 1.1 Display Function Keys...1 1.2 Thermostat Display...2 1.3 Controller hardware input output points... 4 2.0 Sequence of Operation...5 2.1 States of Operation...5 2.2 Modes

More information

OWNER S MANUAL. Part Number P RF

OWNER S MANUAL. Part Number P RF OWNER S MANUAL CPE230RF Commercial Programmable Thermostat Wireless Transmitter Part Number P474-2300RF CONTENTS Page GENERAL... 2 CONFIGURATION... 3-12 Transmitter Display... 3 Transmitter Indicator...

More information

TAP v2.10 Version Date: 6/12/13. Document Microprocessor Controller for Tempered Air Products

TAP v2.10 Version Date: 6/12/13. Document Microprocessor Controller for Tempered Air Products Document 475595 Microprocessor Controller for Tempered Air Products Reference Guide for the Microprocessor Controller Please read and save these instructions. Read carefully before attempting to operate

More information

Engineering Guide VAV Diffusers. Please refer to the Price Engineer s HVAC Handbook for more information on VAV Diffusers.

Engineering Guide VAV Diffusers. Please refer to the Price Engineer s HVAC Handbook for more information on VAV Diffusers. VAV Diffusers lease refer to the rice Engineer s HVAC Handbook for more information on VAV Diffusers. Diffuser Types Ceiling Diffusers Conventional air distribution systems typically group several rooms

More information

Dehumidifying with Dedicated Outdoor Air

Dehumidifying with Dedicated Outdoor Air Dehumidifying with Dedicated Outdoor Air System Configurations Figure 71. Configurations for dedicated outdoor-air systems A dedicated outdoor-air handler separately filters, cools, dehumidifies, heats,

More information

Owner s Manual. Part Number 33CS250-01

Owner s Manual. Part Number 33CS250-01 33CS Commercial Programmable Thermostat IMPORTANT: Read entire instructions before programming the thermostat. Owner s Manual Part Number 33CS250-01 GENERAL Carrier s 7-day, commercial, programmable thermostats

More information

Selected Laboratory Energy Efficiency Measures

Selected Laboratory Energy Efficiency Measures Selected Laboratory Energy Efficiency Measures These are some of the most effective energy efficiency measures for laboratories 1. Reduce (optimize) air changes per hour in lab space 2. Design to the proper

More information

Continuous Commissioning Report

Continuous Commissioning Report Continuous Commissioning Report for the Bush Academic Facility (Bldg. 1607) Submitted to: Office of Energy Management Physical Plant Department Texas A&M University Prepared by: Energy Systems Laboratory

More information

AirTrak. Digital Control System. User Manual. Touchscreen Systems

AirTrak. Digital Control System. User Manual. Touchscreen Systems AirTrak Digital Control System User Manual Touchscreen Systems Rev. 10-29-15 1 2 Table of Contents OVERVIEW... 8 NETWORKING... 9 AIRTRAK DEFAULT SETTINGS... 9 Unit Operating Modes... 10 MRT Controls...

More information

Harrington Tower Building

Harrington Tower Building Continuous Commissioning Report For the Harrington Tower Building Building #435 Submitted to: Utilities Energy Office Physical Plant Department Texas A&M University Prepared by: Energy Systems Laboratory

More information

November 11, City of Sparks 215 S. 21 st St. Sparks, NV

November 11, City of Sparks 215 S. 21 st St. Sparks, NV November 11, 2014 City of Sparks 215 S. 21 st St. Sparks, NV 89432-0857 Attn: Brian Cason Re: Sparks City Hall HVAC Upgrade Project-Alerton Direct Digital HVAC Control System to Match Existing City of

More information

Feature Summary. I. System

Feature Summary. I. System I. System A. Supports up to 60 VAV HVAC Units 1. Each HVAC Unit Can Support up to 59 VAV Boxes 2. Constant Volume Units Can Be Integrated With VAV Units 3. System Can Support Over 3000 Controllers B. Fill-in

More information

BACnet PTEC Controller VAV 0 to 10V Series Fan and 3- Stage Electric Heat, Application 6657

BACnet PTEC Controller VAV 0 to 10V Series Fan and 3- Stage Electric Heat, Application 6657 BACnet PTEC Controller VAV 0 to 10V Series Fan and 3- Stage Electric Heat, Application 6657 140-1158 Building Technologies Table of Contents Overview... 5 BACnet 14 Hardware Inputs... 14 Room Unit Identification...

More information

Technical Assignment 3 11/15/04. Executive Summary

Technical Assignment 3 11/15/04. Executive Summary Executive Summary This report is an analysis of the existing systems within the Outreach Innovation Building in University Park, PA. One significant design criteria was a lower than average noise criteria

More information

AireLogic. Digital Control System. User Manual

AireLogic. Digital Control System. User Manual AireLogic Digital Control System User Manual Rev. 04-11-13 1 Table of Contents OVERVIEW... 6 NETWORKING... 8 AIRELOGIC DEFAULT SETTINGS... 8 UNIT OPERATING MODES... 9 MRT Controls:... 9 UNIT OFF MODE...

More information

THIS IS A DESIGN GUIDE NOT A SPECIFICATION. Montgomery County Public Schools Facilities Guide DIVISION 15 MECHANICAL

THIS IS A DESIGN GUIDE NOT A SPECIFICATION. Montgomery County Public Schools Facilities Guide DIVISION 15 MECHANICAL SECTION 15100 PART 1 GENERAL THIS IS A DESIGN GUIDE NOT A SPECIFICATION Montgomery County Public Schools Facilities Guide DIVISION 15 MECHANICAL HVAC SYSTEMS APPLICATIONS 1.1 SCOPE: The intent of this

More information

Owner s Manual. Part Number 33CS250-FS and 33CS220-FS

Owner s Manual. Part Number 33CS250-FS and 33CS220-FS Debonair 33CS Flush-Mounted Flatstat Commercial Programmable Thermostat IMPORTANT: Read entire instructions before programming the thermostat. Owner s Manual Part Number 33CS250-FS and 33CS220-FS GENERAL

More information

System Components with ` Emphasis on Packaged Rooftop Application and Installation. Jerry Cohen President Jacco & Assoc.

System Components with ` Emphasis on Packaged Rooftop Application and Installation. Jerry Cohen President Jacco & Assoc. System Components with ` Emphasis on Packaged Rooftop Application and Installation Jerry Cohen President Jacco & Assoc. Agenda Define and relate in practical terms the following components: System Effect

More information

Product Manual SZ1022/SZ1031/SZ1035/

Product Manual SZ1022/SZ1031/SZ1035/ Product Manual SZ1022/SZ1031/SZ1035/ Conventional Heating & Cooling Thermostats Communicating Thermostats Description The SZ1022, SZ1031, and SZ1035, are microprocessorbased mable thermostats designed

More information

1080 Marina Village Parkway, Suite 501 Alameda, CA (510) Fax (510) HVAC DESIGN INTENT

1080 Marina Village Parkway, Suite 501 Alameda, CA (510) Fax (510) HVAC DESIGN INTENT Taylor Engineering 1080 Marina Village Parkway, Suite 501 Alameda, CA 94501-1142 (510) 749-9135 Fax (510) 749-9136 LLC HVAC DESIGN INTENT PART 1 - GENERAL 1.1 Overview A. The project consists of a 3-story

More information

I/O ZONE 560/583 USERS GUIDE

I/O ZONE 560/583 USERS GUIDE I/O ZONE 560/583 USERS GUIDE 641-224 641-242 641-237 1 Table of Contents Hot Gas Re-Heat Valve On/Off:... 15 THE ZONE CONTROLLER...4 Modulating Re-Heat Valve:... 16 SPECIFICATIONS...5 CONTROLLER COMPONENTS...6

More information

TEC Controller Terminal Box Controller (VAV) - Series Fan Powered with Hot Water Reheat, Application Application Note

TEC Controller Terminal Box Controller (VAV) - Series Fan Powered with Hot Water Reheat, Application Application Note TEC Controller Terminal Box Controller (VAV) - Series Fan Powered with Hot Water Reheat, Application 2025 Application Note 140-1054 Building Technologies Table of Contents Overview... 4 Hardware Inputs...

More information