1 Prescriptions for Critical Healthcare Cx John D. Villani, P.E. Associate Grumman/Butkus Associates
2 AIA Quality Assurance Learning Objectives 1. Medical Industry Changes and how they impact Design, Construction, Operations and Commissioning 2. Review the current construction process and how Cx can enhance the process 3. Review the Case Study of a hospital surgical pavilion addition, and the design and operational issues and results of Retrocommissioning
3 Medical Industry Developments October 2009, Medicare will cease paying for several reasonably preventable hospital mistakes Eight preventable mistakes approved for 2009 More mistakes targeted for 2010 and beyond Other insurance carriers watching and speculated to follow Medicare s lead
4 Medical Industry Developments Medicare s list for 2009 Urinary tract infections from catheters Bloodstream infections from catheters Falls Bed Sores, or pressure ulcers Objects left in patient during surgery Blood incompatibility An infection after heart surgery Air embolism (air bubble in a blood vessel)
5 Medical Industry Developments What possible reasonably preventable hospital mistakes that might have funding eliminated in the future? Airborne, waterborne, blood borne pathogens? Airborne Tuberculosis, Aspergillosis, Staphylococcus Waterborne Legionella
6 Medical Industry Developments Common thread to airborne pathogens? HVAC Systems Filtration Pressurization Air changes Cooling coils Drain Pans Ventilation Exhaust
7 Medical Industry Developments Common thread to waterborne pathogens? Domestic Water Systems Cold Water Hot Water Hot Water Recirculation
8 Medical Industry Developments Impact to current projects Infectious Control Department documents infection rates in hospitals Case Study Project Had increase in infection rates HVAC system was identified due to uncontrolled temperature and humidity swings All supply air ductwork was cleaned and sterilized
9 Current Construction Process Design Bid Build, who controls the quality for MEP systems? HVAC and Plumbing Systems Design Team Contractors Testing, Adjusting and Balancing Contractor Local Authority Having Jurisdiction State Health Inspectors Operations Staff
10 Current Construction Process What happens after the occupancy? New team of staff take over operations and maintenance Poor transfer of knowledge of proper system operation, nuisances, backup modes System deviations Tweaking Loss of critical system parameters Controls system fire fighting
11 Current Construction Process Controls System can be the key Control System Design System Diagram with Sequence of Operations Points List Specification Monitoring Alarming? Trending??
12 Adding Cx to the Current Construction Process Controls System can be the key Commissioning the Control System FPT Testing Alarming Trending Persistence Operator Training OR Pressure
13 Case Study Hospital Retro-Commissioning New surgical Pavilion Project Details 56,000 Sq.Ft New Construction Space 45,000 Sq.Ft. Renovation of Existing Hospital $35M Construction costs 3 New Air Handlers, ORs and Central Sterile 15 New Operating Rooms (ORs)
14 Case Study Air Handlers Air Handler Design Details ORs served by two air handlers 50,000 CFM each Back up through cross over dampers 50,000 CFM design during backup mode 25,000-30,000 CFM during normal mode Oversized design to handle backup mode
15 Case Study Air Handlers Air Handler Equipment Details
16 Case Study Air Handlers Air Handler Equipment Details
17 Case Study Operating Rooms Operating Room (OR) Design Details 15 Operating Rooms Temperature Range Deg F Relative Humidity Range % RH Occupied Mode 30 Air Changes per Hour Unoccupied Mode 15 Air Changes per Hour Supply VAV Return Modulating Damper Static Pressure Room Control
18 Case Study Operating Rooms Operating Room (OR) Design Details
19 Case Study Humidification Humidification Issues Humidification controlled based on measured return air RH vs. setpoint via reset schedule Frequent high humidity alarms
20 Case Study Humidification Operating Conditions AHU-2 Conditions on 11/7/08 at 18:02 Discharge Air Temperature = 53.6F Discharge Air Relative Humidity = 81.8% RH Humidifier Valve Position = 100% Open AHU Common Return Air Temperature = 70.7F AHU Common Return Air Relative Humidity = 45.7% RH AHU Common Return Air Relative Humidity Setpoint = 58% RH
21 Case Study Humidification Operating Conditions AHU-2 Conditions on 11/7/08 at 18:02 OR s Discharge Air Temperature Range = 59.1F 70.0F OR s Room Temperature Setpoint Range = 60.0F 75.1F OR s Room Relative Humidity Range = ( ) % OR s Room Relative Humidity Average = 47.0% RH
22 Case Study Humidification Operating Conditions
23 Case Study Humidification Implemented Changes Utilize booster humidifiers first followed by unit humidifier Poll individual ORs to maintain lowest OR to 40% RH High humidity takes precedence to low humidity
24 Case Study OR Pressurization Operating Conditions ORs were found going negatively pressurized during transition from occupied to unoccupied 30 ACH to 15 ACH Supply VAV box can decrease from occupied to unoccupied CFM in approx. 60 seconds Return damper controlled by room pressure sensor takes 15 to 20 minutes to regain stable pressure control
25 Case Study OR Pressurization Operating Conditions
26 Case Study OR Pressurization
27 Case Study Occupancy Sensors Operating Conditions OR minimum ON time 30 minutes Found the occupancy sensors with 30 minute on time windows occurring 4 to 5 times per day At 15 minutes of negative pressure per occupancy change over, that is 1 hour per day the ORs are negative
28 Case Study Occupancy Sensors Operating Conditions
29 OR Pressurization & Occupancy Sensors Implemented Changes Slow down of OR supply VAV box to decrease from occupied to unoccupied mode over a 20 minute period Note behind return dampers in lieu of VAV boxes VALUE ENGINEERING??
30 Case Study Economizer Cycle
31 Case Study Economizer Cycle
32 Case Study - IFB steam preheat coil AHU Design Details Air handlers equipped with Integral Face and Bypass (IFB) vertical steam preheat coils Coils sized for 50,000 CFM at -15 Deg F and a 57 degree rise
33 Case Study - IFB steam preheat coil Observed Operating Conditions Outside air temperature = 30.8F Mixed air temperature = 30.2F OA dampers min and max were 100% open Return air dampers closed Preheat steam valve was 100% open IFB dampers were 0% open (fully closed around the vertical steam coil) Humidifier valve 40% open Cooling coil inactive, no cooling Cooling coil discharge air temperature = 53.3F
34 Case Study - IFB steam preheat coil Resulting Effects from operating conditions 23.1 Degree Heat Gain from Preheat and humidifier
35 Case Study - IFB steam preheat coil Why is this happening? Chilled water active above 45 degrees OA Glycol active above 40 degrees OA IFB sequence: Above 40 Deg OA, IFB damper open to coil and steam valve modulates Below 40 Deg OA, steam valve goes 100% open, IFB damper modulates Why typical design for 100% outside air, backup mode, not normal mode Cost of Existing Operation Est. $35,000/year
36 Case Study - IFB steam preheat coil Implemented Changes IFB damper control is based on Mixed Air instead of Outside Air (warranty issue) Steam valve modulates open instead of going 100% open IFB damper modulates open after steam valve is 100% open
37 Case Study - IFB steam preheat coil Implemented Changes
38 Case Study Humidification Issues Operating Conditions Carry Over Problem thru Chilled Water Coil Glycol Coil Supply Fan Reheat Coil Up to and/or through final filters (HEPA) Valve Modulation from 0 to 100% open Tripping off in high humidity safety switch Sized for 100% Outside Air
39 Case Study Humidification Issues Findings and Implemented Changes Found bad discharge air humidity sensor Tripping on High humidity safety switch Valve opening too fast, and too much for recirculation (normal) mode of operations Limited valve to 60% during normal mode No limit in valve travel in emergency mode
40 Simultaneous Humidification and Cooling Operating Conditions
41 Simultaneous Humidification and Cooling Operating Conditions Found conditions Outside air temperature = 63.7F Outside air relative humidity = 56.1% RH Outside air enthalpy = 22.9 Btu/Lb Return air enthalpy = 25.2 Btu/Lb (Since the return air enthalpy is greater than the outside air enthalpy the unit is economizer mode) Humidifier Valve Position = 92% open Chilled Water Coil Valve Position = 36.7% open Flooding and excessive condensate after cooling coil, even beyond drain pan
42 Simultaneous Humidification and Cooling Implemented Changes Air handler humidification was deactivated at 50 degrees wet bulb Missed criteria as per the specifications
43 Case Study - Summary Design Issues Oversized AHU s for backup mode 100% outside air design for smoke purge Control sequences did not address normal mode of operation at reduced operating capacities No VAV boxes on the ORs return air OR pressurization Occupancy Sensors
44 Construction Issues Case Study - Summary No trending setup to track or monitor systems Poor communication between controls contractor and engineer regarding normal vs. backup mode Controls interpretation of sequences Very poor owner turnover, no ownership of systems or controls Outside Air Flow Station (Min vs. Max) Fire/Smoke Dampers (NFPA 90A)
45 Case Study Summary & Results Retro Commissioning Issues No documented sequences of operation Trending established Extensive effort to re-write new sequences Resolved issue of IFB preheat coil and manufacture s warranty Corrected OR negative pressurization Improved operations staff ownership of systems and controls through training
46 Case Study Results Retro Commissioning Results RCx Costs y $125,000, includes Retro-Cx Engineering General Contractor Mechanical Contractor TAB Contractor Controls Contractor (New Controllers) $35,000 in savings from IFB coil changes 3 4 year payback Average cost/ week in the hospital y $75,000
47 Case Study Real World Retro Commissioning Hospitals Hospitals 24/7 Operation Interruptions due to cases Impact to communicable pathogens and the spread of infections Support the elimination of reasonably preventable hospital mistakes
48 AIA Quality Assurance Portland Energy Conservation, Inc is a registered provider with The American Institute of Architects Continuing Education Systems. Credit earned on completion of this program will be reported to CES Records for AIA members. Certificates of Completion for non-aia members are available on request. This program is registered with the AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product. Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.
49 Thank-you John D. Villani, P.E., LEED AP, C.E.M., QCxP Grumman/Butkus Associates (847)
Case Study: Furman University Charles H. Townes Center for Science. Michael K. Mantai, PE, CCP President System WorCx
Case Study: Furman University Charles H. Townes Center for Science Michael K. Mantai, PE, CCP President System WorCx AIA Quality Assurance Learning Objectives 1. Case study example of Chilled Beam technology
More informationAIR HANDLING SYSTEM RETRO-COMMISSIONING TRENDING ANALYSIS
AIR HANDLING SYSTEM RETRO-COMMISSIONING TRENDING ANALYSIS 1 AIR HANDLING UNIT TRENDS 2 1. The trending charts provided on the following pages prepared as part of a retro-commissioning investigation. The
More informationHumidity Control Design Tips. R. Mark Nunnelly, PE, CxA, LEED AP President
Humidity Control Design Tips R. Mark Nunnelly, PE, CxA, LEED AP President AIA Quality Assurance The Building Commissioning Association is a Registered Provider with The American Institute of Architects
More informationBuilding Analytics and Compliance: How analytics can be used to aid in performancebased certifications. Bryant M. Kirkland Jr, PE, CCP, LEED AP
Building Analytics and Compliance: How analytics can be used to aid in performancebased certifications Bryant M. Kirkland Jr, PE, CCP, LEED AP AIA Quality Assurance The Building Commissioning Association
More informationSmoke Management in Operating Room Renovations
Smoke Management in Operating Room Renovations Sandy Bonderman PE, LEED AP Sean Riley PE, LEED AP Brian Robinett PE, LEED AP Notkin Mechanical Engineers Overview Smoke Management in OR Renovations Why
More informationINTRODUCTION TO: ASHRAE STANDARD 90.1, HVAC System Requirements for Reducing Energy Consumption in Commercial Buildings
INTRODUCTION TO: ASHRAE STANDARD 90.1, 2013 HVAC System Requirements for Reducing Energy Consumption in Commercial Buildings Rocky Mountain ASHRAE Technical Conference, April 29, 2016 SEAN BEILMAN, P.E.,
More informationVentilation for Healthcare Facilities
Ventilation for Healthcare Facilities Presented to Wisconsin Healthcare Engineering Association November 13, 2014 Need ideas to make this first page interesting; picture? Henneman logo? 1 Topics to be
More informationASHRAE Region VI CRC Track III: Session 3 Ventilation Energy Recovery. Steven T. Taylor, PE Principal Taylor Engineering
ASHRAE Region VI CRC Track III: Session 3 Ventilation Energy Recovery Steven T. Taylor, PE Principal Taylor Engineering This program is registered with the AIA/CES for continuing professional education.
More informationVentilation for Healthcare Facilities. Topics to be Covered
Ventilation for Healthcare Facilities Presented to Wisconsin Healthcare Engineering Association November 13, 2014 Need ideas to make this first page interesting; picture? Henneman logo? Topics to be Covered
More informationCleveland Clinic Design Standards MECHANICAL SYSTEMS DESIGN GUIDELINES HVAC AIR DISTRIBUTION PART I - GENERAL 1.1 SUMMARY
PART I - GENERAL 1.1 SUMMARY A. This section addresses the general requirements for air handling distribution systems, including air handlers, ductwork, ductwork accessories, terminal units, air devices,
More informationRetrocommissioning Findings Summary: Building X #1 Priority: Major Comfort/Control Problems
IMPORTANT NOTICE: This sample document is provided for instructional purposes only. CCC is not rendering advice concerning any commission project or practices. This document is neither approved nor intended
More informationUNIVERSITY OF MISSOURI Heating Ventilating and Air-Conditioning (HVAC) 2016 Q1
GENERAL: This section provides general standards for overall sizing and design of Heating, Ventilating, and Air Conditioning (HVAC) systems. Other sections contain specific standards for each system per
More informationSEQUENCE OF OPERATION GUIDELINE. AIR TERMINAL UNITS SINGLE DUCT VARIABLE AIR VOLUME with HOT WATER REHEAT or ELECTRIC HEAT
SEQUENCE OF OPERATION GUIDELINE AIR TERMINAL UNITS SINGLE DUCT VARIABLE AIR VOLUME with HOT WATER REHEAT or ELECTRIC HEAT Document: VAV-HTG rev1 Revision: 1.0 Rev. Date: July 22, 2011 NOTES: 1. THIS SEQUENCE
More informationHow to Optimize the Performance of Your Hospital Boiler Plant: A Case Study
How to Optimize the Performance of Your Hospital Boiler Plant: A Case Study HESNI Annual Conference May 11, 2018 Presenters: Ryan Ollie, E.I.T., CEM, CMVP Manager of Energy Solutions, Advocate Health Care
More informationA. Base Bid: 1. Heating Contractor provide: a. Control sequences for HVAC systems, subsystems, and equipment.
SECTION 23 09 93 - SEQUENCE OF OPERATIONS FOR HVAC CONTROLS PART 1 - GENERAL 1 WORK INCLUDES A. Base Bid: Heating Contractor provide: Control sequences for HVAC systems, subsystems, and equipment. B. Alternate
More informationCARRIER edesign SUITE NEWS. Modeling 100% OA Constant Volume Air Systems. Volume 6, Issue 1. Page 1 Modeling 100% OA Constant Volume Air Systems
Volume 6, Issue 1 CARRIER edesign SUITE NEWS Modeling 100% OA Constant Volume Air Systems This article provides an overview of how to model a stand-alone constant air volume (CAV) 100% OA system in HAP.
More informationRE: Phase 2 Improvements DATE: July 1, 2016 New Administration Building Wernle Youth & Family Treatment Center 2000 Wernle Road Richmond, Indiana
ADDENDUM NO. 2 RE: Phase 2 Improvements DATE: July 1, 2016 New Administration Building Wernle Youth & Family Treatment Center 2000 Wernle Road Richmond, Indiana TO: All Bidders Gentlemen: This Addendum
More informationOpen to Below: A Discussion of Allowed Floor Openings. Jay A. Ierardi, Ph.D., P.E., LEED AP. Kevin S. Hastings, P.E., LEED AP
Open to Below: A Discussion of Allowed Floor Openings Kevin S. Hastings, P.E., LEED AP Jay A. Ierardi, Ph.D., P.E., LEED AP R.W. Sullivan Engineering (617) 523-8227, Fax (617) 523-8016 http://www.rwsullivan.com
More informationTechnical Report Three
Technical Report Three Existing Conditions for Mechanical Systems Contents Executive Summary...2 Building Overview...2 Mechanical Systems Overview...2 Mechanical System...3 Outdoor & Indoor Design Conditions...3
More informationEarthWise System Seminar
EarthWise System Seminar Tim Gasper, P.E. Solutions Engineer Brady-Trane Services, Inc. EarthWise Systems? Energy Efficiency Emissions Buildings use 39% of the Primary Energy Consumed in the United States
More informationPharmaceutical Facility Design
PhEn-602 Pharmaceutical Facility Design J. Manfredi Notes 9A PhEn-602 J. Manfredi 1 Primary & Secondary HVAC units Primary Primary air handling unit arrangement: One unit is responsible for all of the
More informationYour Home. Jacco & Assoc.
Your Home Fan on with call for heating or cooling Heating on with call from space thermostat Stage as required to maintain The 75F Basics adj. - First stage of heating shall be heat pump Cooling on with
More informationSelected Laboratory Energy Efficiency Measures
Selected Laboratory Energy Efficiency Measures These are some of the most effective energy efficiency measures for laboratories 1. Reduce (optimize) air changes per hour in lab space 2. Design to the proper
More information4. OVERVIEW OF MECHANICAL SYSTEM
4. OVERVIEW OF MECHANICAL SYSTEM The 87,000 SF SLCC is served by six (6) Trane M-Series Climate Changer Air Handing Units (AHUs). Each unit serves a distinct zone within the facility that is unique in
More informationWelsh Commissioning Group, Inc.
Ongoing Commissioning with Building Automation System and Data Loggers Bryan W. Welsh, P.E. President Welsh Commissioning Group, Inc. AIA Quality Assurance Learning Objectives 1. General understanding
More informationBalancing Energy & Performance in Healthcare. Dan Koenigshofer, PE, MSPH, HFDP, SASHE Dewberry Engineers Inc. Raleigh, NC - November 12, 2014
Balancing Energy & Performance in Healthcare Dan Koenigshofer, PE, MSPH, HFDP, SASHE Dewberry Engineers Inc. Raleigh, NC - November 12, 2014 Elements of HPHC HVAC Systems 1. Performance Infection Control,
More informationOSU Alumni Center Phase I Implementation Review. Oregon State University 130 Oak Creek Bldg. Corvallis, Oregon
OSU Alumni Center Phase I Implementation Review Prepared for Oregon State University 130 Oak Creek Bldg. Corvallis, Oregon 97331 October 31, 2011 Job No. 02.11.00113 Introduction: Glumac was engaged by
More informationHVAC Controls Upgrades: Requirement Details ( )
REQUIRED CONTROLS/FEATURES To qualify the upgrade must add or substantially modify 3 or more sequences/system capabilities. Also, all sequences and items listed under the required section are needed in
More informationAIR-CONDITIONING SYSTEMS AND APPLICATIONS. Abdullah Nuhait Ph D. King Saud University
AIR-CONDITIONING SYSTEMS AND APPLICATIONS Abdullah Nuhait Ph D. King Saud University AIR-CONDITIONING SYSTEMS Earliest air conditioning system used only for heating (winter) Provided heated air for comfort
More informationVariable Air Volume with Indoor Air Quality
Variable Air Volume with Indoor Air Quality and a Cure for the Spread of the Airborne Flu Virus January 11, 2017 Dinner Meeting Golden Gate ASHRAE Chapter Presented By: Thomas S. Weaver, P.E., Member ASHRAE
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-23 09 93 (November 2015) ----------------------------- Preparing Activity: USACE Superseding UFGS-23 09 23 (May 2011) UNIFIED FACILITIES GUIDE SPECIFICATIONS References
More informationHVAC Controls Upgrades: Requirement Details ( )
REQUIRED CONTROLS/FEATURES HVAC non CENTRAL PLANT 1) Zone Level Scheduling & Override for all air handlers (supply and exhaust) to match occupied hours by zone DDC or occupancy sensors (OS) allowed. (403.2.4.3,
More informationSECTION SEQUENCE OF OPERATIONS FOR HVAC CONTROLS
SECTION 23 09 93 SEQUENCE OF OPERATIONS FOR HVAC CONTROLS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes control sequences for HVAC systems, subsystems, and equipment. B. See Division 23 Section
More informationSECTION SEQUENCE OF OPERATION FOR HVAC CONTROLS PART 1 GENERAL
SECTION 15910 SEQUENCE OF OPERATION FOR HVAC CONTROLS PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division
More informationJob Name Control Systems Description Date
Job Name Control Systems Description Date Project Overview The project is a describe the building and its major HVAC systems (e.g. three-story office building, served by a rooftop unit VAV system ). In
More informationCARRIER edesign SUITE NEWS. Interpreting High (Low) Peak Design Airflow Sizing Results for HVAC. Equipment Selection.
Volume 5, Issue 1 CARRIER edesign SUITE NEWS Interpreting High (Low) Peak Design Airflow Sizing Results for HVAC Equipment Selection A design challenge sometimes occurs when computing design loads using
More informationGreen Maintenance Needed to Keep HVAC Systems Green
Green Maintenance Needed to Keep HVAC Systems Green Robert G. (Bob) Baker BBJ Consulting Service 235 Apollo Beach Blvd. #157 Apollo Beach, Florida bbaker@bbjconsultingservice.com ASHRAE is a Registered
More informationPaul McCown, PE, CEM, LEED AP, CxA Sr. Mechanical Engineer SSRCx, LLC Nashville, TN USA
Continuous Commissioning of a LEED-EB Gold Certified Office Building Paul McCown, PE, CEM, LEED AP, CxA Sr. Mechanical Engineer SSRCx, LLC Nashville, TN USA KEYWORDS Continuous Commissioning, Retro-Commissioning,
More informationTerminal Commissioning Case Study- Terminal A Logan International Airport
Terminal Commissioning Case Study- Terminal A Logan International Airport ACI-NA Environmental and Operations & Technical Conference May 4, 2008 Brad Jones, PE, AP Sebesta Blomberg Sam Sleiman, PE, CCM
More informationAIRSIDE COMPONENTS AND SYSTEMS
Ventilation: Outdoor air (OA) ventilation shall be introduced into each occupied building space in compliance with ASHRAE Standard 62. Adequate additional OA capability is needed to keep buildings under
More informationINTRODUCTION HVAC BASICS AND HVAC SYSTEM EFFICIENCY IMPROVEMENT SECTION O 4/19/2012
HVAC BASICS AND HVAC SYSTEM EFFICIENCY IMPROVEMENT SECTION O INTRODUCTION HVAC systems or Heating, Ventilating and Air-Conditioning systems control the environment for people and equipment in our facilities.
More informationDEHITMIDlFICATION WITHOUT REHEAT USING FACE AND BYPASS DAMPERS
DEHITMIDlFICATION WITHOUT REHEAT USING FACE AND BYPASS DAMPERS Dale T. Warila Member Group Technical Staff Texas Instruments Dallas, Texas ABSTRACT: Installations with chill water cooling, needing constant
More informationContinuous Commissioning: A Valuable Partner to Retrofit Projects
Continuous Commissioning: A Valuable Partner to Retrofit Projects Yeqiao Zhu Aamer Athar Kenneth Banks Ph.D. PE, CEM PE, CEM Energy Systems Laboratory Sempra Energy Solutions Sempra Energy Solutions Charles
More informationSECTION SEQUENCE OF OPERATIONS FOR HVAC CONTROLS
PART 1 - GENERAL SECTION 23 09 93 SEQUENCE OF OPERATIONS FOR HVAC CONTROLS 1.1 SUMMARY A. This Section includes control sequences for HVAC systems, subsystems, and other equipment. B. See Division 23 Section
More informationImproving Performance with a Building Tune-Up. Janice Peterson, P.E. LEED AP Market Manager, Building Operations BetterBricks
Improving Performance with a Building Tune-Up Janice Peterson, P.E. LEED AP Market Manager, Building Operations BetterBricks How much is too much? Most buildings can cut total energy use by 5-30% while
More informationDigital Precise Air Control - DPAC
Digital Precise Air Control - DPAC Mode Enable Sensor Options The temperature of this sensor will determine if the unit is in heating, cooling or vent mode during Occupied operation. The following options
More informationStrategies for Building Energy Efficiency
Strategies for Building Energy Efficiency Ben Sliwinski Technical Director SEDAC University of Illinois at Urbana-Champaign How Buildings Use Energy Building Envelope (Walls, Roof, Windows, Floors) Lighting
More informationTechnical Report Rouse Boulevard. The Navy Yard Philadelphia, PA 19112
Technical Report 1 201 Rouse Boulevard The Navy Yard Philadelphia, PA 19112 Nicholas W. Mattise Option: Mechanical;; Advisor: Dr. Miller September 23, 2013 Nicholas W. Mattise 1 of 22 Contents Executive
More informationRichard B. Alpert, P.E. Senior FPE, Clark Nexsen
Richard B. Alpert, P.E. Senior FPE, Clark Nexsen Clark Nexsen is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES). Credit(s) earned on completion of
More informationAgenda and Objectives
Agenda and Objectives Trane Engineers Newsletter Live Series Rooftop variable-air-volume (VAV) systems are used to provide comfort in a wide range of building types and climates. This ENL discusses HVAC
More informationHigh Efficiency Heating and Cooling Systems for Community Colleges Kirk Mescher, PE, LEED AP Principal ICCCFO
High Efficiency Heating and Cooling Systems for Community Colleges Kirk Mescher, PE, LEED AP Principal ICCCFO 2012 1 Learning Objectives for this Session Get acquainted with typical systems used in the
More informationStandards and Guidelines. Presented by: Aric Murray December 12, 2014
TDSHS Ventilation Standards and Guidelines Presented by: Aric Murray December 12, 2014 Agenda 1. What are the TDSHS ventilation 1. What are the TDSHS ventilation requirements? 2. Pressure relationships.
More informationSYNOPSIS. Part-Load Control Strategies for Packaged Rooftop Units. In this issue... Bin Hour Profile Charlotte, NC
VOLUME ONE NUMBER THREE SYNOPSIS A N H V A C N E W S L E T T E R F O R B U I L D I N G O W N E R S A N D M A N A G E R S In this issue... Part-Load Strategies Why they re important.......... 1 What Things
More informationIAQ: Re-tuning Commercial Buildings
IAQ: Re-tuning Commercial Buildings A low-cost path to improved air quality and energy efficiency. B y S c o t t G o r d o n, C M All images courtesy of Johnson Controls Service. 10 RSES Journal FEBRUARY
More informationBAS Point Trend Data Guidance
BAS Point Trend Data Guidance Rev. 3, January 2018 Introduction The Building Automation System (BAS also, referred to as a DDC system, or a Direct Digital Control system) at your building has been set-up
More informationSEQUENCE OF OPERATION FOR ALC CONTROL AIR SOURCE HEATPUMP RECIRCULATION AIR WITH ECONOMIZER
SEQUENCE OF OPERATION FOR ALC CONTROL AIR SOURCE HEATPUMP RECIRCULATION AIR WITH ECONOMIZER Printed in the USA ADSOOASHPRAE 0117 Orig SEQUENCE OF OPERATION The ALC controller is turned on by a switch located
More informationTo: Steve Ardolf, MSU Mankato From: Chris Plum, CEE. CC: Tim Ellingson, CEE. Angela Vreeland, CEE Dan Briese, MSU Mankato Date: April 21, 2014.
To: Steve Ardolf, MSU Mankato From: Chris Plum, CEE CC: Tim Ellingson, CEE Angela Vreeland, CEE Dan Briese, MSU Mankato Date: April 21, 2014 Re: MSU Mankato Verification State PBEEEP Executive Summary
More informationThe M & V Guided Recommissioning Process. Energy & Water Conservation Program. September 2015 MOO
The M & V Guided Recommissioning Process MOO Energy & Water Conservation Program September 2015 EWC Agenda MOO EWC Overview Our approach Progress Fault Detection Zone & customer feedback Variance reporting
More informationCustom Air Handler Solutions Custom Units to Meet Your Unique Design Needs
Custom Units to Meet Your Unique Design Needs Engineered for flexibility and performance Contents Horizontal Configuration....1 Horizontal with Standard Economizer Configuration...2 Stacked Configuration...3
More informationAuburn University Basketball Arena:
Auburn University Basketball Arena: How Building Data Analytics Achieved Energy and O&M Savings While Improving Comfort and Sustainability Eric Moore, PE, CEM, Auburn University Hadas Webb, CEM, Cimetrics
More informationASHRAE WILL GIVE YOU THE WORLD. This ASHRAE Distinguished Lecturer is brought to you by the Society Chapter Technology Transfer Committee
ASHRAE WILL GIVE YOU THE WORLD This ASHRAE Distinguished Lecturer is brought to you by the Society Chapter Technology Transfer Committee Complete the Distinguished Lecturer Event Summary Critique CTTC
More informationH3/V3 Series Horizontal and Vertical Indoor Air Handling Units. Engineering Catalog
H3/V3 Series Horizontal and Vertical Indoor Air Handling Units Engineering Catalog Table of Contents AAON H3/V3 Series Features and Options Introduction... 6 H3/V3 Base Model Description... 7 Unit Size...
More information1. Packaged Variable Air Volume (VAV) Rooftop Units (RTU) with Hot Water Reheat. 2. Geothermal Heat Pump VAV Rooftop Units with Hot Water Reheat
July 6, 2017 City of Countryside Attn: Mayor Sean McDermott City Hall 5550 East Avenue Countryside, IL 60525 RE: New City Hall & Police Building HVAC Options Dear Mayor McDermott, Per your request at our
More informationDX-9100 Applications from Engineering Services
System 9100 Technical Manual 636.4 Application Examples Section Technical Bulletin Issue Date 0896 DX-9100 Applications from Engineering Services Introduction Page 3 Overview 3 Air Handling Unit Applications
More informationTechnical Report #3 Mechanical Systems Existing Conditions Evaluation
Mechanical Option Technical Report #3 Technical Report #3 Mechanical Systems Existing Conditions Evaluation Instructor: Dr. Bahnfleth 11.15.04 Building Sponsor: CCG Facilities Integration Table of Contents
More informationPRESSURE RELATIONSHIPS IN HOSPITAL CRITICAL-CARE FACILITIES
PRESSURE RELATIONSHIPS IN HOSPITAL CRITICAL-CARE FACILITIES A. J. Streifell, B.B. Bridgesl, D.T. Grimsrudl, B.C. Krafihefer2 luniversitv of Minnesota, USA 2Honeywe~l, Inc. USA ABSTRACT This field study
More informationประธานกรรมการว ชาการฯสมาคมปร บอากาศแห งประเทศไทย
AIA Guidelines for Design and Construction of Health Care Facilities อาจารย อรรณพ ก งขจ Asst. Managing Director EEC Engineering Network ประธานกรรมการว ชาการฯสมาคมปร บอากาศแห งประเทศไทย สถาบ นพ ฒนาและร
More informationSubmitted to. Texas A&M University at Galveston The Texas A&M University System. Submitted by. Yeqiao Zhu Dan Turner David Claridge
ESL-TR-99/12-05 Report of Energy Efficiency Study and Metering/Utilities Profile for Electricity Deregulation at the Texas A&M University at Galveston (TAMU-G) Galveston, Texas Submitted to Texas A&M University
More informationArchitectural Engineering Senior Thesis Mechanical System Redesign
Saint Joseph Medical Center Architectural Engineering Senior Thesis Mechanical System Redesign Chris Nicolais Building Description Existing Mechanical System Proposed Redesign Alternative Option Emergency
More information11/2 ORT THREEE. Virtua Repla. acement Hospi. ital. Voorhees NJ. Justin Prior. Mechanical
11/2 29 Virtua West Jersey Repla acement Hospi ital Voorhees NJ TECHNICAL REPO ORT THREEE System Overview Justin Prior Mechanical Table of Contents Executive Summary 3 System Overview 4 Design Factors
More informationVerasys System Operation Overview Technical Bulletin
Contents subject to change. Verasys System Operation Overview Technical Bulletin Code No. LIT-12012370 Issued January 2016 Refer to the QuickLIT Web site for the most up-to-date version of this document.
More informationYork 25-Ton VAV Rooftop Unit
HVAC PRO for Windows User s Manual 637.5 OEM Section Technical Bulletin Issue Date 0996 York 25-Ton VAV Rooftop Unit Introduction Page 3 Overview *3 Configuration 5 Sequence of Operation 7 Modes of Operation
More informationTECHNICAL REPORT 3 Mechanical Systems and Existing Conditions Northfield Mental Healthcare Center Northfield, Ohio
Technical Report 3 Northfield Mental Healthcare Center Dr. Stephen Treado Ji Won Park Mechanical Option Fall 2012 TECHNICAL REPORT 3 Mechanical Systems and Existing Conditions Northfield Mental Healthcare
More informationCivil Engineering Building
Continuous Commissioning Report For the Civil Engineering Building Building 492 Submitted to: Utilities Energy Office Physical Plant Department Texas A&M University Prepared by: Energy Systems Laboratory
More informationTechnical Assignment 3 11/15/04. Executive Summary
Executive Summary This report is an analysis of the existing systems within the Outreach Innovation Building in University Park, PA. One significant design criteria was a lower than average noise criteria
More informationSenior Thesis Centre Community Hospital East Wing Addition - Proposal Keith Beidel Mechanical Option 12/05/02 1
Table of Contents Page Number(s) Executive Summary 2 Project Background 3 Proposed Depth Alternatives 4 Proposed Depth Redesign 5-7 Justification of Proposed Depth Redesign 8 Proposed Breath Redesign 9
More informationHAP e-help. Modeling Induction Beams in HAP v4.8 QB TIP 001
This HAP e-help provides a high-level overview of induction beams, how they work and how to model them in HAP 4.8 (and later versions). The first half of the article explains how induction beams work.
More information9/18/2017. Nicholas Thornton, CEM. Systems: HVAC, Electrical, and Technology. Overview. Today s Goals Introductions HVAC Electrical Technology Q&A
Nicholas Thornton, CEM 1 Overview Today s Goals Introductions HVAC Electrical Technology Q&A 2 1 Today s Goals An overview, a crash course Maybe a few tangents (ASK QUESTIONS!) Show typical arrangements
More informationSubmitted to. Texas A&M University-Corpus Christi The Texas A&M University System. Submitted by. Yeqiao Zhu Dan Turner David Claridge
ESL-TR-99/12-04 Report of Energy Efficiency Study and Metering/Utilities Profile for Electricity Deregulation at the Texas A&M University-Corpus Christi (TAMU-CC) Corpus Christi, Texas Submitted to Texas
More informationCultivator & Hybrid Cultivator
Cultivator & Hybrid Cultivator Precision Temperature & Humidity Packaged Unit INTRODUCTION The Cultivator Series package unit is the industry s MOST ENERGY EFFICIENT and HIGHEST capacity dehumidifier on
More informationSECTION FUNCTIONAL PERFORMANCE TESTING (FPT) PROCEDURES - CONSTRUCTION MANAGER EDITION
Montgomery County Public Schools Facilities DIVISION 1 - GENERAL REQUIREMENTS SECTION 01915 - FUNCTIONAL PERFORMANCE TESTING (FPT) PROCEDURES - CONSTRUCTION MANAGER EDITION PART 1 GENERAL 1.1 Section includes:
More informationEnergy-Efficient Makeup Air Units BY HUGH CROWTHER, P.ENG., MEMBER ASHRAE
This article was published in ASHRAE Journal, March 20145 Copyright 2015 ASHRAE. Posted at www.ashrae.org. This article may not be copied and/or distributed electronically or in paper form without permission
More informationHVAC DISTRIBUTION and DELIVERY SYSTEMS
HVAC DISTRIBUTION and DELIVERY SYSTEMS (Part 1) Ball State Architecture ENVIRONMENTAL SYSTEMS 2 Grondzik 1 REMINDER HVAC = Heating, Ventilating, Air-Conditioning The AC part of HVAC implies a system that
More informationThe Creative and Performing Arts High School (CAPA) Pittsburgh, PA 11/11/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma
Objectives and Requirements For the Creative and Performing Arts High School (CAPA), the main objective of the mechanical design is to provide an energy efficient system that is easily maintainable and
More informationThe Role of Air Handling Units in Combating the Spread of Infectious Disease
The Role of Air Handling Units in Combating the Spread of Infectious Disease Goal To identify those areas within an air handler which poses risk to the healthcare industry and recommended four solutions
More informationElement D Services Heating, Ventilating, and Air Conditioning
Air Handling Distribution PART 1 - GENERAL 1.01 OVERVIEW A. This section describes criteria for design of facility air handling distribution systems, including air handlers, ductwork, ductwork accessories,
More informationTechnical Development Program
Technical Development Program PRESENTED BY: James Parker Insert your logo here AIR HANDLERS Coils: Direct Expansion Chilled Water and Heating Menu Section 1 Introduction Section 2 Typical Coil Applications
More information2 Existing Mechanical System
2 Existing Mechanical System 2.1 Design Objectives and Requirements The Gossett Field House project consists of a 25,000 sqft addition and a 40,000 sqft renovation of the existing facility for the University
More informationInspection Phase Three. Mechanical, Electrical & Plumbing Section 503
Inspection Phase Three Mechanical, Electrical & Plumbing Section 503 COMCheck Mechanical Field Inspection Checklist Mechanical Mechanical, Electrical & Plumbing Equipment Efficiencies But a lot ore too
More informationASCENDANT CONVENTIONAL COOLING, ACTIVE DESICCANT DEHUMIDIFICATION SYSTEM ASCENDANT LOW DEW POINT EFFICIENT & EFFECTIVE
LOW DEW POINT EFFICIENT & EFFECTIVE ASCENDANT CONVENTIONAL COOLING, ACTIVE DESICCANT DEHUMIDIFICATION SYSTEM ASCENDANT HVAC systems have a major impact on: Specialized solution for the high demands of
More informationIAQ Building Education and Assessment Model (I-BEAM)
Heating, Ventilation, and Airconditioning (HVAC) Text Modules IBEAM IAQ in L... http://www.epa.gov/iaq/largebldgs/ibeam/text/hvac.html Page 1 of 6 10/21/08 IAQ in Large Buildings http://www.epa.gov/iaq/largebldgs/ibeam/text/hvac.html
More informationHEALTHCARE SURGERY VENTILATION HUMIDITY CONTROL
EFFECTIVE LOW DEW POINT EFFICIENT HEALTHCARE SURGERY VENTILATION HUMIDITY CONTROL HVAC systems have a major impact on: Specialized solution for the high demands of healthcare applications HVAC systems
More informationTechnical Assignment 3
0 David H. Koch Institute for Integrative Cancer Research Senior Capstone Mechanical Option Technical Assignment 3 Mechanical Systems and Existing Conditions Report David H. Koch Institute for Integrative
More informationFan Power in 90.1 & IECC
AMCA International Fan Power in 90.1 & IECC Jeff Boldt, Principal IMEG Corp Jeff.G.Boldt@IMEGcorp.com Air System Engineering & Technology (ASET) Conference US San Antonio, TX Hyatt Regency San Antonio
More informationPDH & Professional Training
510 N. Crosslane Rd. Monroe, Georgia 30656 (770) 266-6915 fax (678) 643-1758 PDH & Professional Training PDH Storm, by Engineers Edge, LLC An Introduction to HVAC Systems for Medical Facilities J. Paul
More informationTo Keep Docs Cool, Dry and Happy
To Keep Docs Cool, Dry and Happy David N. Schurk DES., CEM., LEED-AP., CDSM., SFP., CWEP. Director of Healthcare Accounts for Heat Transfer Solutions in Houston, TX. Learning Objectives 1. Understand the
More informationGARCIA GALUSKA DESOUSA Consulting Engineers
L#57295/Page 1/July 21, 2017 HVAC SYSTEMS NARRATIVE REPORT The following is the HVAC system narrative, which defines the scope of work and capacities of the HVAC system as well as the Basis of Design.
More informationFAARM-Underground Facility. Conceptual Design Review. Mechanical Systems. Dunham Associates, Inc.
FAARM-Underground Facility Conceptual Design Review Mechanical Systems Prepared by: Dunham Associates, Inc. April 17, 2012 Dunham Project Number: 0412145-000-00 Dunham Associates Inc. Page 1 of 8 Mechanical
More information10+ HVAC Troubleshooting Tips for Healthcare Facilities Jerry Hirsch JCI Facility O&M Performance Development Manager.
10+ HVAC Troubleshooting Tips for Healthcare Facilities Jerry Hirsch JCI Facility O&M Performance Development Manager 2019 WHEA Webinar Johnson Controls Institute Overview Operation & Maintenance (O&M)
More informationCOMcheck Software Version Mechanical Compliance Certificate
COMcheck Software Version 4.0.6.2 Mechanical Compliance Certificate Project Information Energy Code: Location: Climate Zone: Project Type: 90.1 (2007) Standard HALCYON Bldg. 400 Alpharetta, Georgia 3a
More information