WorkFace Planning Best Practice XVI Conference. Jeph Virtue
|
|
- Hilary Phelps
- 6 years ago
- Views:
Transcription
1 WorkFace Planning Best Practice XVI Conference Jeph Virtue May 21, 2008
2 This Year s Sweat Equity Jeph Virtue (Chair) Suncor Darrell Coughlin Flint Energy Niels Frederiksen Jacobs Roger Van Den Bossche Flint Energy Sandy MacElheron Jacobs Ray Johnson Bantrel Maurice D Aoust Jacobs Doug Hawkins CLRA Jose Herrero Fluor Canada George Jergeas UofC Preston Noton Hatch Lloyd Rankin Ascension Systems Todd Rapp Conoco Phillips Raymond Rewcastle Lockerbie & Hole Ron Embury NOVA Dave Witskin Brand Aluma Scaffold Paul Kristensen BA Energy Brian Roy Brand Aluma Scaffold Dennis Meads Nexen Bill Luxton SAIT Dennis Krenz Total Gary Semaniuk Stantec Kevin Moorehouse Petro-Canada John Vincent Worley Parsons/Colt Doug Mitchell Petro-Canada Kalvin Tsang JV Driver Randy Regan Suncor Kelly Jawhari JV Driver Linda Savage Suncor Morris Youell JV Driver Stewart Garry Suncor Geoff Ryan Insight-WFP Jerry Bell Shell Added more Owners for Implementation Phase
3 WorkFace Planning Definition WorkFace Planning is the process of organizing and delivering all the elements necessary, before work is started, to enable craft persons to perform quality work in a safe, effective and efficient manner.
4 Owner Commitment Securing Canada s Energy Future
5 Plan the Work WorkFace Planning Dedicated Planner Release the Work Work the Plan Supervisor Materials & Equipment Coordinators Prerequisites Field Installation Work Package Safety Requirements Tools Equipment Trades/Specialists Detailed Plan Drawings Vendor Info. Materials Supervisor Review 1 day to 4 weeks of defined scope. Ready Team 37% Tools 47% Scope Tool Time Improvement
6 With WorkFace Planning Without. Improved: Safety Schedule Predictability Productivity Quality Morale
7 Evidence Building But Need More 2 Identical Hydrotreater Projects: Project using WorkFace Planning had 25% better productivity and better schedule predictability COAA Award Submission: Ledcor (Nisku Mod Shop): 25% productivity savings vs. historical Jacobs (Petro-Canada RCP Sulphur Project): reduced wait time, no labour disputes, improved tracking and schedule performance COAA Benchmarking WorkFace Planning scorecard key elements added Rigorous and credible
8 Rules and Scorecard Update Timeline Champion and Sponsor Owner Execution Strategy CWP Best Practice Flowchart Work Process WorkFace Planning Success
9 DBM (FEL 2) EDS (BDS, FEL 3) Detailed Engineering Construction Construction Management Team Owner Engineer Construction Contractor
10 ½ Day Essentials Training Executive, Management, Supervision Owner, EPCM, Construction Contractors 4 Day Fundamentals WorkFace Area and Integration Planners, Champions, Coordinators (Equipment, Material, Tool, Scaffold) Owner, Construction Contractor, Construction Manager Book now learn more at the booth.
11 1/2-day course Bantrel Bird Chemco Electric Fluor Graham Hatch Energy Jacobs Ledcor Monad Industrial Constructors PCL Industries Petro Canada Pillar Oilfield Projects Shell Canada Energy SNC Lavalin Steeplejack Suncor Syncrude ThyssenKrupp Safway TIC Canada 4-day coursealuma Systems Bantrel Flint Energy Fluor Graham Industrial Horton CBI Intergraph IPA Ironworkers 720 Jacobs JV Driver Steeplejack Suncor Technip TIC Canada Waiward Steel Worley Parsons Colt
12 Working the Plan
13 Pipe Rack WFP Assembled
14
15
16 Next Year s Focus Best Practice developing the Path of Construction More verification Execution Strategy Template Designated Occupation Presentations to ENR, CURT, PMI
17 Presentation Workshop WorkFace Planning Overview Panel Discussion: Industry leaders using WorkFace planning now Lessons Learned.share your learnings too
18 Learnings How well did you do your Path of Construction?
19 More Info Thankyou
CLIENTS INDUSTRIAL NOISE CONTROL SERVICES GAS TRANSMISSION & OIL PIPELINES. Alliance Pipeline. ANR Pipeline. B.C. Gas. Canadian Western Natural Gas
INDUSTRIAL NOISE CONTROL SERVICES GAS TRANSMISSION & OIL PIPELINES Alliance Pipeline ANR Pipeline B.C. Gas Canadian Western Natural Gas Canterra Energy Duke Energy Dynegy El Paso Express Pipeline Foothills
More informationJURISDICTIONAL ASSIGNMENT PLAN of the ALBERTA CONSTRUCTION INDUSTRY DECISION OF THE UMPIRE REVIEW OF CONTRACTOR S WORK ASSIGNMENT
IBEW-Local 488-Handling/Installation of Solenoid Panel-Nova Chemicals File 9914 JURISDICTIONAL ASSIGNMENT PLAN of the ALBERTA CONSTRUCTION INDUSTRY DECISION OF THE UMPIRE REVIEW OF CONTRACTOR S WORK ASSIGNMENT
More informationGENERAL CONTRACTOR LARGE. Best of the Best
GENERAL CONTRACTOR LARGE Gold: Jacobs Field Services North America & Zachry Industrial, Inc Silver: The Mundy Companies Bronze: Brown & Root, Cajun Constructors, LLC, Matrix Service, S&B Engineers and
More informationNORTH SCOTT CORRIDOR. October 13 TH PUBLIC VISIONING MEETING. October 13, Click to edit Master subtitle style WELCOME!
NORTH SCOTT CORRIDOR October 13 TH WELCOME! AGENDA WELCOME + INTRODUCTIONS PROJECT OVERVIEW + ROLES PLANNING PROCESS + APPROACH SCHEDULE REVIEW CORRIDOR CONTEXT INPUT + DISCUSSION WRAP UP + NEXT STEPS
More informationCANADA 952.0M 7,500 SELECTED AWARDS NET REVENUES BY MARKET SEGMENT (%) 2016 ANNUAL REPORT TRANSPORTATION & INFRASTRUCTURE 25 PROPERTY & BUILDINGS 19
36 26 ANNUAL REPORT SELECTED AWARDS Roundabout Network Project, Mont- Tremblant, QC (partnership with MTMDET) Road Safety Award - Excellence in Transportation Awards, AQTR (Association québécoise des transports)
More informationIIRSM UAE 69 th Branch Meeting. Name of Facilitator: Matt Cox Date: 7 th March, 2018
IIRSM UAE 69 th Branch Meeting Name of Facilitator: Matt Cox Date: 7 th March, 2018 Before we start Fire alarms, Tests & Evacuations Welfare Facilities Mobile Phones Agenda Welcome and Introductions Presentation
More informationPikes Peak Regional Building Department 2880 International Circle Colorado Springs, Colorado 80910
2880 International Circle Colorado Springs, Colorado 80910 MECHANICAL COMMITTEE MINUTES 10:00 a.m. MEMBERS PRESENT: OTHERS PRESENT: Chairman Edward Pine Vice Chairman Dan Rial Mr. Mark Pelletier Mr. Curt
More informationSolarPower Europe O&M Task Force
SolarPower Europe O&M Task Force Guidelines and Best Practices for Utility-scale PV Power Plants in Europe Paolo Chiantore 8 April 2016, IEA PVPS Task 13 workshop, Bolzano Why an O&M Task Force? Protect
More informationTEMPERING SOLUTIONS. Haws Integrated provides standardized and customized tempered water solutions for complete ANSI compliance.
TEMPERING SOLUTIONS Haws Integrated provides standardized and customized tempered water solutions for complete ANSI compliance. SOLUTION SPECIFIC ENGINEERING Quality, reliability and value are driven by
More informationLaser Safety Subgroup Charter
Laser Safety Subgroup Charter Laser Safety is one of several Subgroups of the Environmental Safety & Health Working Group of the DOE Energy Facilities Contractors Group (EFCOG) Mission The Laser Safety
More informationNotification Policy & Procedures Training
Facilities Notification Policy & Procedures Training October 18, 2013 BSA Conference Room Facilitators: Joe Rubio & Victoria O Connor Agenda 8:30 Opening Comments: Dave Riker 8:40 Training Overview Joe
More informationCOMMUNITY PARTNERING TEAM
ROUTE 18 TRANSPORTATION IMPROVEMENTS COMMUNITY PARTNERING TEAM CITY OF NEW BRUNSWICK COMMUNITY PARTNERING TEAM MEETING NO. 9 REPORT January 28, 1999 DATE: January 19, 2000 TIME: 9:00 a.m. - 12:00 p.m.
More informationPuget Sound A Great Region!
Puget Sound A Great Region! Conservation is a state of harmony between man and nature. -Aldo Leopold Regional Problems Require Regional Solutions Keys to Regional Visioning Working Together Developers
More informationWelcome to Vegas - Once again!
Welcome to Vegas - Once again! Great attendance (pre-registered) 5,000+ retailers 2,800+ domestic stores 250+ international retailers Ace Retailers had another record breaking year Retailers continue to
More informationMARVIN ELLISON PRESIDENT & CHIEF EXECUTIVE OFFICER
MARVIN ELLISON PRESIDENT & CHIEF EXECUTIVE OFFICER TERRIFIC COMPANY WITH A STRONG BRAND AND BALANCE SHEET 1 CONDUCTED COMPREHENSIVE REASSESSMENT OF OUR BUSINESS LOWE S WELL POSITIONED IS WELL POSITIONED
More informationTom Peters Memorial Mine Reclamation Award. (Industry Trophy)
Canadian Land Reclamation Association/Ontario Mining Association Tom Peters Memorial Mine Reclamation Award (Industry Trophy) Tom Peters was a founding member of the Canadian Land Reclamation Association
More informationA guide to preparing the land use element of a local comprehensive plan. Land Use. Resource guide
Chapter 0 A guide to preparing the land use element of a local comprehensive plan Title Land Use Resource guide A strong economy, a healthy environment, and an enjoyable quality of life all depend on the
More informationTEMPERING SOLUTIONS. Haws Integrated provides standardized and customized tempered water solutions for complete ANSI compliance.
TEMPERING SOLUTIONS Haws Integrated provides standardized and customized tempered water solutions for complete ANSI compliance. SOLUTION SPECIFIC ENGINEERING Quality, reliability and value are driven by
More informationBuilding Performance Services. September 24, 2003
Building Performance Services September 24, 2003 1 Building Performance Services www.pse.com www.seattle.gov/light www.snopud.com The Building Performance Services (BPS) initiative is sponsored by the
More informationI-4 Ultimate Project Update and QA/QC Process on a P3. FTBA Annual Construction Conference February 18, 2015
I-4 Ultimate Project Update and QA/QC Process on a P3 FTBA Annual Conference February 18, 2015 Project Overview 21 miles in Orange and Seminole counties From west of Kirkman Road to east of SR 434 Scope
More informationSession Four Functional safety: the next edition of IEC Mirek Generowicz Engineering Manager, I&E Systems Pty Ltd
Abstract Session Four Functional safety: the next edition of IEC 61511 Mirek Generowicz Engineering Manager, I&E Systems Pty Ltd The functional safety standard IEC 61511 provides a framework for managing
More informationELECTRICAL INSPECTION BULLETIN (Effective )
ELECTRICAL INSPECTION BULLETIN (Effective 2013-11-01) B-B1-001 NS Power Electrical Inspection Business This bulletin has been issued to provide useful service and directory information related to the business
More informationSri Chinmoy Barwon River Run. 12km Run
Barwon River Run km Run Scott Peter MCPHERSON Male - 00:: 00:: Branden PEARCE Male - 00::0 00::0 Adam BECKWORTH 0 Male - 00:: 00:: Ken WALKER Male 0-00:: 00:: Josh DILLON 00 Male - 00::0 00::0 Charlie
More informationUnderstanding and Applying NFPA 25
Understanding and Applying NFPA 25 Texas Edition Learning Objectives Describe the scope of NFPA 25. Distinguish between sprinkler system problems that fall within the scope of NFPA 25 and those that do
More informationHigher Education Energy Efficiency Partnership Program BEST PRACTICES AWARDS
Higher Education Energy Efficiency Partnership Program BEST PRACTICES AWARDS UC / CSU Sustainability Conference, June 2005 A program created by the UC/CSU/IOU Partnership under the auspices of the California
More informationAPI RP 1175 PIPELINE LEAK DETECTION- PROGRAM MANAGEMENT WORKSHOP APRIL 26 TH AND 27 TH, 2017
API RP 1175 PIPELINE LEAK DETECTION- PROGRAM MANAGEMENT WORKSHOP APRIL 26 TH AND 27 TH, 2017 PIPELINELEAKDETECTION PROGRAM MANAGEMENT It s Not Enough to have a Leak Detection System It must be designed
More informationPlanning Matters an update
Planning Matters an update Dy Currie MPIA CPP National President Planning Institute Australia Kirsty Kelly MPIA CPP Chief Executive Officer Planning Institute Australia @DyanCurrie @kkplanner Planning
More informationPINE RIVER WATERSHED INITIATIVE NETWORK
PINE RIVER WATERSHED INITIATIVE NETWORK Updates on projects from 2006 and 2007 New projects 2008 By Anne Eadie Map of Watershed Projects Land Use 89% agricultural Forest cover (7.8%) is mainly along the
More informationCentre For Transportation Engineering & Planning. WELCOME The Western Canada Pavement Workshop 2010 Edition. Kelly Yuzdepski, P.Eng.
Centre For Transportation Engineering & Planning WELCOME The Western Canada Pavement Workshop 2010 Edition Edmonton, Alberta February 2 & 3, 2010 Kelly Yuzdepski, P.Eng., President Presentation Outline
More informationCASS COUNTY MICHIGAN MASTER PLAN
CASS COUNTY MICHIGAN MASTER PLAN and the Village of Edwardsburg Master Plan Village of Vandalia Master Plan Pokagon Township Master Plan Silver Creek Township Master Plan Volinia Township Master Plan Wayne
More informationMINUTES FROM THE SEVENTH MEETING OF THE MAIN STREET MARKHAM COMMITTEE IN City of Markham Canada Room - Civic Centre. September 17, 2014
MINUTES FROM THE SEVENTH MEETING OF THE MAIN STREET MARKHAM COMMITTEE IN 2014 City of Markham Canada Room - Civic Centre Members Councillor Campbell Councillor Moretti Phil Howes Jonathon Mingay Dianne
More informationPlumas Eureka Fire Department Fire Chief s Report For August 9, 2017 By Tom Forster
Plumas Eureka Fire Department Fire Chief s Report For August 9, 2017 By Tom Forster Personnel: No changes. PECAUX: Special thanks are due to our neighbors Sue and Bill Carrera, for their outstanding support
More informationBrotherhood Way Community Garden Welcome
Welcome Agenda 6:30 7:00 Participants arrive / sign-in 7:00 7:15 Brief opening statements and welcome from Supervisor. / Introduce SFDPW, Rec Park, and Parks Alliance 7:15 7:45 Provide overview of the
More informationCorridor Management Committee. September 29, 2017
Corridor Management Committee September 29, 2017 1 Today s Topics Chair s Update Proposed Corridor Protection Wall Aesthetic Design Overview Public Outreach Environmental Review Civil Construction Update
More informationPROSPECTUS 10-13, 2018 NOVEMBER PHOENIX CONVENTION CENTER PHOENIX, AZ HCDEXPO.COM. Association Partners. In Association with. Founded and Produced by
NOVEMBER 10-13, 2018 PHOENIX CONVENTION CENTER PHOENIX, AZ PROSPECTUS HCDEXPO.COM Founded and Produced by Presenting sponsor In Association with Association Partners The Healthcare Design Expo & Conference
More informationCOYOTE LAKE HARVEY BEAR RANCH COUNTY PARK
SANTA CLARA COUNTY PARKS & RECREATION DEPARTMENT COYOTE LAKE HARVEY BEAR RANCH COUNTY PARK DRAFT MASTER PLAN May 2003 Bellinger Foster Steinmetz Landscape Architecture Environmental Science Associates
More informationNOTICE TO ALL FIRMS. Bid RFI Questions and Answers
Purchasing Department 227 West 27 th Street New York, NY 10001 Purchasing Dept. Tel. 212-217-3630 Purchasing Dept. Fax 212-217-3631 Purchasing@fitnyc.edu NOTICE TO ALL FIRMS Date: March 8, 2018 To: From:
More informationHorizontal Well Downhole Dynamometer Data Acquisition
11 th Annual Sucker Rod Pumping Workshop Renaissance Hotel Oklahoma City, Oklahoma September 15-18, 2015 Horizontal Well Downhole Dynamometer Data Acquisition Project sponsored by ALRDC Chair: Victoria
More informationCAN/ULC S Integrated Systems Testing of Fire Protection and Life Safety Systems and Fire Protection Commissioning
CAN/ULC S1001-11 Integrated Systems Testing of Fire Protection and Life Safety Systems and Fire Protection Commissioning Presentation To: Canadian Fire Alarm Association (CFAA) National Capital Region
More informationCANADIAN SOCIETY OF LANDSCAPE ARCHITECTS STRATEGIC PLAN 2012_14
CANADIAN SOCIETY OF LANDSCAPE ARCHITECTS STRATEGIC PLAN 2012_14 about the CSLA _ history The Canadian Society of Landscape Architects was founded in 1934. By that time, landscape architects were active
More informationIndividual Team First Last Score
Individual Frost Bank Stephen Ethridge 95 Primo Plumbing Mike Swientek 93 Tietze Plumbing James Bump 91 Morrison Supply #1 Mike Mizell 89 Morrison Supply #1 Shawn McCorkle 89 Tietze Plumbing Clinton Witheral
More informationIndividual Team First Last Score Award
Individual FROST BANK Steven Ethridge 93 CH Brandt Sid Edwards 90 RU TEXAS FIRST RENTALS Mark Didway 89 A1 PRIMO PLUMBING Chelsea Carmichael 88 TIETZE PLUMBING Justin Nesloney 86 HUGHES SUPPLY Brad Silver
More informationCityStudio is an experimentation and innovation hub for the City of Vancouver where city staff, community members, experts and students from our 6
CityStudio is an experimentation and innovation hub for the City of Vancouver where city staff, community members, experts and students from our 6 universities and colleges co-create projects on the ground
More informationWELCOME TO THE CHOUTEAU GREENWAY DESIGN, DEVELOPMENT AND CONSTRUCTION WORKING GROUP!
WELCOME TO THE CHOUTEAU GREENWAY DESIGN, DEVELOPMENT AND CONSTRUCTION WORKING GROUP! Chouteau Greenway Steering Committee and Working Groups Overview Overview January 9, 2019 Chouteau Greenway will transform
More informationVillas at Downing Creek Condominium Association, Inc. Resident Address and List
Last Name First Name Property Address Email Telephone Pitchford Tawana & Ken 200 Villa Creek Parkway tkaylowery@gmail.com; kpitchfo@hotmail.com (770) 630-0444 (770) 851-0677 Dover Lavelle 201 Villa Creek
More information2.0 Welcome, 2.1 training introduction, 2.2 review of training objectives, 2.3 facility logistics, and 3.0 Attendee introductions
2.0 Welcome, 2.1 training introduction, 2.2 review of training objectives, 2.3 facility logistics, and 3.0 Attendee introductions Patrick Goggin Lakes Specialist UW-Stevens Point / UW Extension Lakes/WI
More informationNew Developments in Green Building. HRM Environment & Sustainability Standing Committee Halifax, NS March 1, 2012
New Developments in Green Building HRM Environment & Sustainability Standing Committee Halifax, NS March 1, 2012 CaGBC focus areas Positioning green building as climate change solution Advancing the next
More informationBUILDING CODE INTERPRETATION
BUILDING CODE INTERPRETATION November 2017 14-BCI-009 Page 1 of 6 FIRE ALARM AND FIRE SUPPRESSION SYSTEM VERIFICATION AND TESTING CERTIFICATES PURPOSE This STANDATA has been developed to give municipalities
More informationChairman s Report for the TC on NEC CMP 2
Chairman s Report for the TC on NEC CMP 2 Signature: 1) Date(s) and location of meeting: CMP-2 met from January 19-23, 2015 at the Sonesta Hilton Head Island, SC Task Groups 1, 2 & 3 met on Sunday, January
More informationCAMPUS MASTER PLAN UPATE
19 MAY 2016 CAMPUS MASTER PLAN UPATE Metropolitan Planning Organization AGENDA Introductions Planning Scope Observation & Analysis: Mobility Systems Campus Development Plan Mobility Planning Scenarios
More informationDecorative Architectural Products. Jeff Filley / President Masco Coatings Group
Decorative Architectural Products Jeff Filley / President Masco Coatings Group Safe Harbor Statement This presentation contains statements that reflect our views about our future performance and constitute
More informationIntroducing the Digital Illumination Interface Alliance
Introducing the Digital Illumination Interface Alliance The global industry alliance for DALI lighting control March 2019 1 DiiA: The global industry alliance for DALI DiiA the Digital Illumination Interface
More informationMillennium Series In-Ground Trash Cans and Recycling Containers Prepared for and Presented by Rob Mitchell and Randy Unrau
Millennium Series In-Ground Trash Cans and Recycling Containers Prepared for and Presented by Rob Mitchell and Randy Unrau The Norm (Issues with animals, birds, wind and over-flowing Trash Cans) Would
More informationGreen Sky Thinking May. people first
Green Sky Thinking 2018 10-18 May people first Contents Welcome p.1 1. This year s theme: people first p.2 2. Building on last year s success p.3 3. Pre-Programme Schedule p.4 About Open City p.5 Previous
More informationRevolutionizing Green Roof and Green Wall Performance: The Living Architecture Performance Tool
Revolutionizing Green Roof and Green Wall Performance: The Living Architecture Performance Tool April 23, 1-2pm EST Professional Development Hours: 1.0 LA CES/HSW LANDSCAPE ARCHITECTURE FOUNDATION 501(c)(3)
More informationDesign and Sustainability for Winter Operations
Design and Sustainability for Rational: For Operations staff to be more involved in the Design of our road infrastructure. What gets designed and built by others, Becomes our maintenance legacy The Regional
More informationInspired Design With Heart
Inspired Design With Heart 9250 E. Costilla Ave. Greenwood Village, CO 80112 720-724-3149 designstudio-blue.com 01 02 03 04 Firm Profile Services Involvement Career Client List 01 Firm Profile Design Studio
More informationTechnology for Safety AND Survival
Technology for Safety AND Survival Deputy Chief John Sullivan Worcester Fire Department Fire Engineer Ric Plummer Berlin, MA Fire Department Sixth Annual Conference on Precision Personnel Location Remember
More information2-day Fire-fighting Foam Workshop conducted by Dr Niall Ramsden. 18 th IAFPA Aircraft Rescue and Fire-fighting Conference
2-day Fire-fighting Foam Workshop conducted by Dr Niall Ramsden Date: 7 8 May 2018 Fee: S$1,730 About the Workshop The 2-day workshop is designed to enhance responders knowledge in fire-fighting foam,
More informationEducational Programs for Architectural Door Openings. AIA/CES and GBCI/CMP
s for Architectural Door Openings AIA/CES and GBCI/CMP AIA/CES and GBCI/CMPC s... 3 6 Request for Continuing Education Programs.... 7 s Overview As an approved provider of AIA/CES (American Institute of
More informationSCSA COR Companies in good standing (generated: Dec. 16, 2015)
SCSA COR Companies in good standing (generated: Dec. 16, 2015) 101116402 Saskatchewan Ltd. O/A Eagle Construction 101200672 Saskatchewan Ltd. O/A Concept Saskatchewan 101246430 Saskatchewan Ltd O/A Concept
More informationFCIA Education and Committee Action Conference DRAFT* Agenda The Adolphus ~ Dallas, TX Tuesday, May 5, 2015
The Adolphus ~ Dallas, TX Tuesday, May 5, 2015 Time / Location Event FCIA Education Sessions help attain and maintain status as a FM 4991 Approved Contractor DRI, UL ULC Qualified Firestop Contractor DRI
More informationPresenter. Pam Blixt, MA Preparedness Manager City of Minneapolis Health Department
Presenter Pam Blixt, MA Preparedness Manager City of Minneapolis Health Department Presenter Kelly Muellman, MUP Sustainability Program Coordinator City of Minneapolis CITY OF MINNEAPOLIS Climate Change
More informationFire Safety Account Financial Report for Fiscal Year 2018
This document is made available electronically by the Minnesota Legislative Reference Library as part of an ongoing digital archiving project. http://www.leg.state.mn.us/lrl/lrl.asp Minnesota Department
More informationEU Delegation to Albania Vlora Municipality Albanian Development Fund
VISIBILITY ARTWORK COMPETITION FOR THE VLORA WATERFRONT VISIBILITY ARTWORK COMPETITION FOR THE VLORA WATERFRONT INVITATION We invite figurative arts artists to participate in an Arts Competition. The Vlora
More informationJanuary 25 26, Chicagoland Electrical Construction Industry Trade Show and Conference
Chicagoland Electrical Construction Industry Trade Show and Conference Featuring the NEW City of Chicago Electrical Code January 25 26, 2018 Drury Lane Theater & Conference Center Oakbrook Terrace, Illinois
More informationLake Oswego to Portland Transit Project. Lessons Learned. John Cullerton Senior Project Manager, URS 2012 APTA/TRB Light Rail Conference
Lake Oswego to Portland Transit Project Lessons Learned John Cullerton Senior Project Manager, URS 2012 APTA/TRB Light Rail Conference Overview Project Location and Context Corridor History and Project
More informationUMass Amherst Campus Green Building Resources
University of Massachusetts Amherst ScholarWorks@UMass Amherst Campus Planning Community and Conference Presentations Campus Planning 2015 UMass Amherst Campus Green Building Resources Ludmilla D. Pavlova-Gillham
More information2009 PCIC Annual Conference Safety Subcommittee Meeting Agenda. Tuesday, September 15, 2009 Hilton California-B Room 3:30pm 5:00pm
2009 PCIC Annual Conference Safety Subcommittee Meeting Agenda Tuesday, September 15, 2009 Hilton California-B Room 3:30pm 5:00pm 1 Agenda Welcome Safety Subcommittee Officers PCIC Safety Excellence Award
More information3.0 STAKEHOLDER AND PUBLIC ENGAGEMENT
3.0 STAKEHOLDER AND PUBLIC ENGAGEMENT 3.1. OVERVIEW The primary source of research for this Parks Master Plan was an extensive municipal public consultation process. This integral component of the planning
More information2000 Western Ontario Regional
2000 Western Ontario Regional Windsor, ON. Individual Results Name Department/FireFit Team Time 1. Jack Bailey Windsor Fire Dept. 1:28.45 2. Steve Denomme North Bay F.D. 1:31.96 3. Brent Hastings Brampton
More informationHow to Optimize the Performance of Your Hospital Boiler Plant: A Case Study
How to Optimize the Performance of Your Hospital Boiler Plant: A Case Study HESNI Annual Conference May 11, 2018 Presenters: Ryan Ollie, E.I.T., CEM, CMVP Manager of Energy Solutions, Advocate Health Care
More informationHARBOR BRIDGE. Randall C. Grones, PE - SPD. US 181 Harbor Bridge October
HARBOR BRIDGE Randall C. Grones, PE - SPD US 181 Harbor Bridge October October 13, 13, 2015 2015 Project Scope Develop, design, construct and maintain a total project length of 6.44 miles. Base scope New
More informationMember Services Guide
Member Services Guide Value. Engagement. ROI. TM Remodeling Done Right. Join NARI s $326 Billion Residential Remodeling and $380 Billion Commercial Remodeling Industry ship. Remodeling Done Right. TM NARI
More informationNFPA TECHNICAL COMMITTEE ON ELECTRONIC SAFETY EQUIPMENT. March 18-19, 2014 Fort Lauderdale, FL AGENDA
NFPA TECHNICAL COMMITTEE ON ELECTRONIC SAFETY EQUIPMENT March 18-19, 2014 Fort Lauderdale, FL AGENDA Tuesday, March 18, 2014 1. 8:00 a.m. Call to Order - Chairman Bob Athanas 2. Introduction of Members
More informationMinnesota Erosion Control Association EROSION MATTERS
Minnesota Erosion Control Association EROSION MATTERS Advancing Effective Stormwater Management and Erosion Control V O L U M E 2 5, I S S U E 7 SPRING 2015 The Minnesota Erosion Control Association 2015
More informationFax: (707) Mission Circle #124 PMB 167 Santa Rosa, California 95409
ELECTRICAL ENGINEER: WILLIAM R. HAACK, M.B.A., M.S.E.E., P.E. Phone: (925) 381-2222 Engineering Design & Testing Corp. Fax: (707) 578-9034 52 Mission Circle #124 billhaack@edtengineers.com PMB 167 Santa
More informationSpecification of urban planning regulation in a sustainable city
Sustainable Development and Planning III 165 Specification of urban planning regulation in a sustainable city E. Salehi Faculty of Environment, University of Tehran, Iran Abstract The city form is shaped
More informationOutdoor Display A.H.McElroy 22
Company Name Booth # 3twenty Modular Outdoor Display A.H.McElroy 22 ABB / Baldor Outdoor Display Acklands-Grainger 120 & 121 ACP Applied Products 69 Acuren Group Inc. 110A Adria 41 Aggreko 223 AGI Envirotank
More informationStandards and Safety Update
Standards and Safety Update Presented By: Michael J. Johnston Executive Director Standards and Safety, NECA Update Objectives Update on NFPA 70E and NECA Safety products Update on NECA S National Electrical
More informationPERSONAL PROFILE WORK EXPERIENCES. August 2005 to Present Astaldi Arabia Ltd. Construction Engineer/Supervisor E & I
PERSONAL PROFILE Date of Birth : August 30, 1974 Place of Birth : Tanjay City, Negros Oriental, Philippines Age : 37 Gender : Male Status : Married Height : 5 8 Weight : 74 kg. Citizenship : Filipino Religion
More informationFlorida Senate SB 982 By Senator Bennett
By Senator Bennett 1 A bill to be entitled 2 An act relating to electrical and alarm system 3 contracting; amending s. 489.503, F.S.; 4 requiring certain contractors to be certified 5 pursuant to part
More informationPRE-CONSTRUCTION CONFERENCE AGENDA 2:00 PM October 8, Type of Work: Grading, Concrete/Bituminous Paving, Storm Sewer, Watermain, Signal/Lighting
Project No.: SAP 055-622-050 / SAP 055-633-003 Location: CSAH 22 / CSAH 33 Type of Work: Grading, Concrete/Bituminous Paving, Storm Sewer, Watermain, Signal/Lighting Contractor: Hoffman Construction Company
More informationA MESSAGE FROM ALBERTA S CHAPTER PRESIDENT: Daryll de Waal
CANADIAN FIRE ALARM ASSOCIATION (ALBERTA) Mar 2013 Volum e 4 Mission: Maximize the Effectiveness and use of fire alarms in the protection of life and property throughout Canada Daryll de Waal Alberta Chapter
More informationValue Paper Authors: Stuart Nunns CEng, BSc, FIET, FInstMC. Compliance to IEC means more than just Pfd!
Value Paper Authors: Stuart Nunns CEng, BSc, FIET, FInstMC Compliance to IEC 61508 means more than just Pfd! Compliance to IEC 61508 means more than just Pfd! Market environment Statistics relating to
More informationCANADIAN GUIDE FOR GREENER ROADS AND SUSTAINABILITY CONSIDERATIONS FOR BRIDGES GUIDE 2016 CANADIAN CONSULTING ENGINEERING AWARDS
CANADIAN GUIDE FOR GREENER ROADS AND SUSTAINABILITY CONSIDERATIONS FOR BRIDGES GUIDE 2016 CANADIAN CONSULTING ENGINEERING AWARDS SUSTAINABILITY CONSIDERATIONS PROJECT TITLE PAGE Member Firm Submitting
More informationPurdue Process Safety & Assurance Center P2SAC. Davidson School of Chemical Engineering Purdue University
Purdue Process Safety & Assurance Center P2SAC Davidson School of Chemical Engineering Purdue University 1 Bhopal, India 1984; +2,000 fatalities Imperial Sugar, Georgia 2008; 14 fatalities BP Texas City,
More informationState Highway 5 Corridor Context Sensitive Master Plan
ADOPTED June 17, 2014 (Resolution 2014-06-071) Travel Lane Travel Lane 11 11 Median 16 Min State Highway 5 Corridor Context Sensitive Master Plan 1 Prepared for: Prepared by: State Highway 5 Corridor
More information36 th International Conference on Coastal Engineering 2018 Baltimore, Maryland USA
36 th International Conference on Coastal Engineering 2018 Baltimore, Maryland USA Short Course: Natural and Nature-Based Features (NNBF) for Coastal Resilience Sunday, July 29, 2018 8:00 5:00 PM Baltimore
More informationFire Safety Management Audit Specification August 2017
Fire Safety Management Audit Specification August 2017 Membership Training Qualifications Audit and Consultancy Policy and Opinion Awards Contents Page 1 Introduction to the Fire Safety Management Audit
More informationSubject: Fire Protection Impairment Program Reference: NFPA (see bottom of page 5) Effective Date: August 2014 Distribution All YC Employees
Subject: Fire Protection Impairment Program Reference: NFPA (see bottom of page 5) Effective Date: August 2014 Distribution All YC Employees Purpose: To establish procedures to be followed when a fire
More informationNext steps Vision and Mission Science Priorities Objective Conservation Framework Actions
Vision: A conservation community, that while governed by their unique purposes and missions, collaborates on sustaining lands and waters that support natural and cultural resources and the services they
More informationExecutive Office of Energy and Environmental Affairs Massachusetts Vulnerability Preparedness Program. June 6, 2018
Executive Office of Energy and Environmental Affairs Massachusetts Vulnerability Preparedness Program June 6, 2018 Presentation Outline: 1. What Natural Hazards Impact Falmouth 2. Coastal Resiliency Efforts
More informationCAN/ULC-S1001, INTEGRATED SYSTEMS TEST OF FIRE PROTECTION AND LIFE SAFETY SYSTEMS
RANDAL BROWN & ASSOCIATES ENGINEERING LTD. CONSULTING ENGINEERS LIFE SAFETY & FIRE PROTECTION 105 6 LANSING SQUARE TORONTO, ONTARIO CAN/ULC-S1001, INTEGRATED SYSTEMS TEST OF FIRE PROTECTION AND LIFE SAFETY
More informationThe Urban Exploration Program
International Downtown Association 2010 Downtown Achievement Award Submission Planning Elevating understanding Building relationships Forming partnerships Learning together An important program for implementing
More informationCuyamaca College Administrative Services
Follow-ups Thursday, July 22 1:00 PM Emergency Procedure Presentation a. Kits Sandi s Recommendations Purchase 3 more 54 gallon can on wheels, 1 for Health Services, 1 CDC and 1 for REBRAC Purchase 8 First
More informationLiNC Inspection Program
LiNC Inspection Program Request a Presentation or Webinar 800-773-FIRE LiNC Inspection Program Know the condition of every facility nationwide in SECONDS! View, Track and Download any inspection report
More informationi n S o u t h e r n M a i n e
Coastal Access i n S o u t h e r n M a i n e an open discussion among regional stakeholders Friday, June 2, 2006 9 am 4 pm University of New England Campus Center Multipurpose Room Biddeford, ME SITUATION
More informationSOUTH FLORIDA ECOSYSTEM RESTORATION TASK FORCE SCG SPONSORED PUBLIC WORKSHOP ON SCIENCE CENTRAL EVERGLADES PLANNING PROJECT MINUTES
SOUTH FLORIDA ECOSYSTEM RESTORATION TASK FORCE SCG SPONSORED PUBLIC WORKSHOP ON SCIENCE CENTRAL EVERGLADES PLANNING PROJECT MINUTES February 13, 2012 9:30 AM District Headquarters - B-1 Auditorium 3301
More informationCOURSE DETAILS. ECSSA in conjunction with PCCE Training are offering a. One Day Review Course
Course upgrade details: F01.1 31st August 2016 COURSE DETAILS ECSSA in conjunction with PCCE Training are offering a One Day Review Course on Fire Detection & Alarm Systems (IS3218:2013) System Design,
More information