Crossharbour District Centre ENVIRONMENTAL STATEMENT: NON-TECHNICAL SUMMARY

Size: px
Start display at page:

Download "Crossharbour District Centre ENVIRONMENTAL STATEMENT: NON-TECHNICAL SUMMARY"

Transcription

1 1. Introduction ASDA Stores Limited and Ashbourne Beech Property Limited (hereafter referred to as the Applicants ) are seeking to obtain planning permission for the redevelopment of the existing supermarket and associated facilities on the Isle of Dogs, north of Mudchute Park (hereafter referred to as the Site ). The Site covers an area of approximately 4.6 hectares (ha) and is located within the administrative boundary of Tower Hamlets (LBTH). The location of the Site is shown on Figure 1. In 2011, the Applicant submitted a hybrid application for the redevelopment of the Site and this was granted permission in November However, it was considered that this original scheme would not be the most efficient use of the Site. As such a new hybrid (part detailed, part outline) planning application for the Site has been prepared by the Applicants. Figure 1: Site Location 1

2 The Site is currently occupied by: a single-storey supermarket; a surface car park comprising approximately 546 spaces; a hand car-wash; a bus terminus; and a self-service petrol filling station. As part of the hybrid planning application, an Environmental Impact Assessment (EIA) has been undertaken by Waterman WIE. EIA is a formal procedure that must be followed for certain types and scales of development projects, where the likely significant environmental effects of a project are assessed and reported. The purpose is to ensure that appropriate information about the likely environmental effects of a project is available for consideration by the relevant local planning authority (i.e. Tower Hamlets), consultees and the public, and that Tower Hamlets has this information before it can determine a planning application. The EIA process can also identify ways in which the project can be modified, or likely significant adverse effects mitigated, so as to reduce or avoid potentially significant adverse effects and to create and enhance beneficial effects. The legislation relevant to EIA is the Town and Country Planning (Environmental Impact Assessment) Regulations, 2011 (as amended 2015) (the EIA Regulations). The findings of the EIA are reported in the Environmental Statement (ES), which has been prepared to accompany the planning application. The likely significant environmental effects of the Development, both during the demolition and construction stage, and once completed and operational have been considered. This document provides a summary of the ES in non-technical language. 2. Environmental Impact Assessment Methodology The EIA has been undertaken in accordance with the EIA Regulations and best practice guidance using established methods, such as site surveys, reviews of available reports and data, computer modelling, consultation with a number of relevant organisations and specialist assessments. The first stage of the EIA process involved undertaking a Scoping Study. The purpose of the Scoping Study was to identify likely significant environmental effects that could arise from the Development and therefore provide the focus of the EIA. The findings of the scoping exercise, along with details of the proposed methods for the specialist assessments, were presented in a Scoping Study, were presented in a Scoping Study report and submitted to Tower Hamlets Council in March The scope of the was formally agreed with Tower Hamlets Council via their formal Scoping Opinion which was received in April The Scoping Study confirmed that the Development would likely give rise to a number of issues which need to be considered in the EIA. These comprise: socio-economics; transportation and access; air quality; noise and vibration; ground conditions and contamination; historic environment; ecology; water resources and flood risk; wind; daylight, sunlight and overshadowing; townscape, visual and built heritage; and 2

3 cumulative effects. Each of the above issues are addressed in the ES, with a chapter dedicated to each of them. The Townscape, Visual and Built Heritage Assessment is presented in a separate volume (Volume 3) of the ES. In each chapter, a description of the assessment methodology is given together with a description of the relevant environmental aspects of the Site and surrounding area. This is followed by an assessment of the potential significant effects of the Development (both beneficial and adverse) and any measures that should be adopted to reduce or offset any significant adverse effects identified during the assessment. The ES also provides an assessment of the residual effects that would remain after mitigation measures have been implemented, as well as the cumulative effects of the scheme. Cumulative effects can arise due to the combination of individual effects (e.g. dust and noise during construction works) or as a result of a combination of effects from several developments (referred to as cumulative schemes ). 3

4 3. Existing Land Uses and Activities The Site is currently occupied by a single-storey supermarket, comprising a floor area of approximately 9,471m 2 located in the southwest of the Site. To the north and east of this is a hard-standing surface car park, comprising 564 spaces. A bus terminus and a self-service petrol filling station are located to the north of the supermarket, a hand carwash is situated to the southeast and an electricity sub-station and a service yard are located to the west. A pharmacy and a photographic shop are located on the ground floor of the supermarket. The planning application boundary is shown in Figure 2. Figure 2: Planning Application Boundary The Site is located in a predominantly residential area, and is close to the commercial hub of Canary Wharf. Residential accommodation is located within Friars Mead adjacent to the east of the Site and within Glengall Grove, Marshfield Street, Strattondale Street and Galbraith Street which are located to the north of the Site. Additional land uses surrounding the Site include educational, commercial (offices and shops), leisure, community and health uses. Figures 3-8 provide some photographs of the Site and its surroundings. 4

5 Figure 3: View across the Site looking south Figure 4: View along Glengall Grove to the north of the Site. Figure 5: View looking south from the Site towards Mudchute Park Figure 6: view across the Site looking north towards Canary Wharf. Figure 7: View looking north along East Ferry Road to the adjacent west of the Site. Figure 8: View looking south east across the Site from the existing main entrance on East Ferry Road. Educational uses include Cubitt Town Infants School and Cubitt Town Junior School, located to the north-east of the Site. Commercial premises (offices) are located along Selsdon Way and within Lanark Square to the west of the Site and retail uses are located along Pepper Street, which runs perpendicular to East Ferry Road to the northwest of the Site. Community uses including St John s Community Centre located adjacent to the north of the Site and the City of Peace Community Church and Glengall Christian Centre are located adjacent to the northeast of the Site. The Island Health Centre is located adjacent to the north of the Site. There is no public open space within the Site boundary at present. The nearest public open space is Mudchute Park and Farm located to the south of the Site. 4. Alternatives and Design Evolution In line with the EIA Regulations, the ES provides a description of the main alternatives to the Development, considered by the Applicant. The principle alternatives that were considered by the Applicants, taking into account potential environmental effects, included the No Development Scenario and Alternative Layout Design. The No Development scenario was not considered to be a viable option by the Applicants because the Site is already identified for redevelopment as it is located within the Isle of Dogs Opportunity Area. This is identified as an area for intensive land use, including housing and commercial development. This scenario would retain the existing use on the Site and result in the following principle missed opportunities for the Site and the surrounding area: Provision of high quality residential accommodation with private and communal amenity spaces; Provision of new public open spaces with soft and hard landscaped areas; Improved pedestrian links through the Site and to the wider area, including enhancing the existing connection to Mudchute Park; Creation of a new district centre; Development of a new supermarket; 5

6 Development of new commercial and retail uses; Provision of new and enhanced community facilities; and Provision of an improved bus interchange. In addition, the No Development scenario would: Fail to contribute to the provision of new homes as required by national, regional and local planning policy; Fail to improve the environment of the Site and its environs; Fail to provide public realm provision, pedestrian permeability and children s playspace; Fail to maximise the potential of the Site; and Fail to deliver the anticipated regeneration of the Crossharbour area. It is considered appropriate to redevelop the Site to ensure it is utilised to its maximum potential, adhering to the national, regional and local aspirations and the aforementioned policy drivers for new homes. On establishing the need and acceptability for a residential-led mixed-use scheme, the Applicant and their design team worked up a Development in which the overall design, massing, external materiality and landscaping was informed by the Site s constraints and opportunities; particularly those relating to townscape and visual matters, ecology, microclimate, and pedestrian permeability. The final Development design emerged as a result of these factors together with an extensive programme of consultation with officers at LBTH and Greater London Authority. 5. The Development The Development involves the demolition of the existing buildings and structures on the Site, together with the construction of a new mixed-use development. The Development, designed by CZWG and McGuirk Watson, would provide: between 1,704 and up to 2,142 residential units of varying size and tenure within ten blocks; a new supermarket; new commercial retail use; a new 3 form entry primary school and associated nursery; a new multipurpose community space/hub; a flexible arts centre / performance space; a single level basement to accommodate residential and commercial car and cycle parking spaces and plant; transport improvements including a new bus interchange and provision of road and cycling improvements; and provision of new public spaces and private amenity space. The redevelopment would be supported by an upgrade to existing infrastructure, including a new electrical power supply to the Site, a new bus interchange and the diversion of the Barnfield Sewer. Part of the sewer diversion would be undertaken in an area off-site within Mudchute Park, close to the southern boundary of the Site. The Development would be built over 3 phases including: detailed (all of Phase 1 and Phase 2 basement to ground floor commercial and community use, hard and soft landscaping); and outline (the remainder of Phase 2 and all of Phase 3). The Development would comprise the construction of ten blocks in addition to the new Supermarket, as shown on Figure 9. 6

7 The proposed blocks vary in form and height, ranging from a height of 2 storeys (13.750m AOD) for the Supermarket to 35 levels (plus ground) ( m AOD) for blocks J and K. A number of areas of public realm would be provided, including a large public square as a focal point for the District Centre, improved pedestrian routes, and a new high street. Areas of playspace would be provided within each phase of the Development. Native plant species would be included throughout the design in order to provide ecological enhancement and to restore habitat. Green and brown roofs and private residential gardens, terraces and balconies are also proposed as part of the Development. Figure 9: Proposed Layout of the Development The completed Development would provide a number of features in order to accord with the principles of sustainable design including a commitment to target BREEAM Very Good, to achieve a carbon dioxide emission reduction of 36% beyond the requirements of the Part L Building Regulations, the provision of suitable access for all including the mobility impaired, the installation of secure cycle storage to encourage the use of bicycles, water efficient fixtures, recyclable waste storage for commercial spaces and a commitment to monitor, sort and recycle construction waste on-site and sustainably sourced, recycled or re-used building materials, where possible. 6. Development Programme, Demolition and Construction The current expectation is that the demolition and construction for the Development would commence in 2019 and progress in a phased manner over a 9 year period, with completion in This would enable the 7

8 existing supermarket to remain in operation throughout the construction of the new store in Phase 1. A temporary car park would be provided for use by supermarket customers whilst Phases 1 and 2 are being constructed, within Phase 3. All the existing structures, including the temporary car park, would be demolished by the time Phase 3 commences. In order to control and manage the potential environmental effects typically associated with the demolition and construction phases, a Construction Environmental Management Plan (CEMP) would be developed and implemented. This would specify a range of measures to manage the environmental effects that could arise and would provide, for example, details of controls in relation to noise and vibration and dust. The CEMP would be prepared in line with relevant legislative and best practice guidelines, including the LBTH s Code of Practice for Deconstruction and Construction Sites. The CEMP would be agreed with LBTH and contractors would be required to implement the CEMP, ensuring that monitoring and auditing is undertaken where this has been specified. CEMPs are an established method of managing environmental effects resulting from demolition and construction works and they are successfully adopted for other major schemes in urban areas. 7. Socio Economics A socio-economic assessment has been undertaken using a wide range of information sources. These sources include a detailed review of planning policies, guidance and standards, population Census data and professional experience of similar development schemes. It is estimated that the Development would generate in the region of 360 full time equivalent (FTE) jobs during the 9 years of construction. In addition, construction workers would be anticipated to spend money on convenience goods and services, such as food, drink and fuel, in the local area, which would further benefit the economy. The Development involves the demolition and relocation of the existing on-site supermarket. However, the store would not be demolished until the new supermarket has opened, thus preventing the displacement of jobs within the existing store. New commercial space in the Development would generate between 281 to 355 net additional jobs in a range of sectors. To provide a worst case economic assessment (i.e. less money spent and generated in and by the local economy), consideration of the minimum numbers of proposed housing was considered. This would bring forward a total of 1,704 units, accounting for around 43.3% of LBTH s annual monitoring target of 3,931 units per annum. The new residential population at the Development with the minimum amount of housing units, would contribute to the local economy by increasing household spending in the local area. Consideration of the maximum scheme was used to assess the effect on social infrastructure (i.e. the scheme that would generate the maximum child yield and adult population). The additional population with the larger scheme, estimated to be up to 3,712 new residents, would increase the demand on existing health facilities, although this would be ameliorated by financial contributions to the Primary Care Trust to an insignificant effect. The Development would provide a three form-entry primary school on-site which would provide 620 primary school places and 60 nursery school places. It would accommodate the primary school children generated by the Development in addition to additional primary school places for the local area. The Development is considered to have an adverse effect on secondary school capacity. However, subject to agreement, Community Infrastructure Levy (CIL) payments to LBTH would contribute towards improving secondary school education facilities, resulting in an insignificant effect. The communal amenity space and private amenity space provided would exceed LBTH s standard requirements. The open space provided does not meet LBTH s requirement for open space, though the adjacent Mudchute Park and Farm would cater for the additional open space required. Sufficient play space would be provided for the children generated by the Development as 4,360m 2 of dedicated play space would be provided on-site, with different spaces provided for different age groups. 8

9 8. Transportation and Access An assessment of the potential significant effects of the Development s traffic has been undertaken having regard to the relevant baseline conditions of the Site and surrounding area. In particular, consideration is given to the effects the Development would have on severance (the perceived division that can occur when a community becomes separated by a major road), pedestrian amenity, fear and intimidation, pedestrian delay, road safety and driver delay. The assessment including undertaking traffic surveys, desktop studies, Site visits, and obtaining data from LBTH. The Site is accessible by public transport including by bus, DLR (see Figure 10) and London Underground services (Jubilee line) and therefore has a Good Public Transport Accessibility Level (as determined by the greater London Authority). The assessment has considered the demolition and construction phase peak traffic generation as well as the traffic generated when the Development is completed and operational. Peak construction activity is anticipated to occur during the basement dig. If the dig takes place over five and a half days each week over a 12 month period, this equates to around 39 two-way vehicle movements a day (Monday to Friday) and 20 two-way movements on a Saturday morning. It is proposed that the management of HGV routing and phasing of capacity improvements is controlled through the development of the Construction Logistics Plan (CLP). Furthermore, the existing consented development for the Site (Ref: PA/11/03670) proposed traffic signal control at the junction of Marsh Wall/Limeharbour. This improvement would have the benefit of controlling traffic flows through the junction, eliminating the conflicts. It is therefore proposed that this mitigation is brought forward with this 2017 planning application to manage peak construction traffic effects. These inherent highway improvements would also mitigate driver delay effects to an insignificant level once the Development is completed. Figure 10: Proposed View of the Development from Crossharbour DLR Station 9

10 9. Air Quality The air quality in LBTH exceeds national air pollution objectives and as a result Tower Hamlets have designated the Borough as an Air Quality Management Area. An assessment was undertaken to determine the potential effects of the Development on local air quality. The main potential effects on local air quality during demolition and construction relate to dust emissions. A range of measures to minimise or prevent dust emissions would be implemented throughout the demolition and construction of the Development via the adoption of the CEMP. The likely impact of demolition and construction related traffic emissions is considered insignificant. However, as part of the CEMP, and as a matter of good practice, measures to control construction traffic would be discussed and agreed with LBTH. Emissions from equipment and machinery operation on Site during demolition and construction would not significantly affect air quality. Computer modelling has been carried out to predict the likely effect of future road traffic and heating plant emissions from the operation of the Development, and the likely changes that this would bring about to local air quality. The effect of the Development on air quality has been predicted for a number of existing sensitive locations surrounding the Site and at future sensitive locations within the Site (i.e. within the residential units of the Development itself). The results of the computer modelling demonstrate that the Development would not have a significant effect upon local air quality. Similarly, it has been demonstrated that with the Development in place, its operation would not give rise to any air quality effect that would adversely affect the existing sensitive locations surrounding the Site or the occupants of the proposed residential units of the Development. 10. Noise and Vibration Demolition and construction works are likely to include activities that would increase noise levels and potentially cause vibration within and immediately adjacent to the Site. In particular, when activities are occurring closest to the Site boundary, this could result in temporary effects on occupants in surrounding properties. However, the implementation of noise and vibration control and management measures through a CEMP for the demolition and construction works would help to reduce noise disturbance to occupants of existing properties. Such measures would include using low-noise machinery and equipment, enclosing and screening machinery and using low-vibratory foundation methods. Demolition and construction traffic flows are not anticipated to give rise to any significant additional noise and vibration at nearby sensitive receptors. An assessment of the suitability of the Site for residential and educational uses has been undertaken. The assessment results indicate that through the provision of an appropriate glazing and ventilation strategy, required internal noise levels would be met for all sensitive spaces. Noise levels in some external school areas may slightly exceed the stated criteria, and should therefore be subject to mitigation measures to reduce, as far as practicable the noise levels. Items of fixed building services plant installed as part of the Development would have the potential to generate noise. Suitable noise limits have therefore been proposed to ensure that noise from plant does not cause disturbance to future occupants of the Development as well as at surrounding sensitive receptors. 11. Ground Conditions and Contamination A desk-based study of ground contamination at the Site has established that owing to current and historical land uses and activities of the Site (e.g. petrol filling station, timber shed, and the presence of mud from the dredging of the docks in the 19 th century), there is the potential for localised contamination of the underlying soils and groundwater. As the Development would be undertaken in 3 phases, a detailed Site Investigation would be undertaken prior to each phase of the demolition and construction works to determine and quantify the nature and extent of contamination present at the Site. If required, a remediation strategy would be developed and agreed with the relevant statutory authorities, including Tower Hamlets and the Environment Agency, and would be implemented during the early stages of the demolition and construction programme. 10

11 The Environment Agency would be consulted to establish an appropriate piling methodology to minimise contamination risks to the aquifer underlying the Site. Implementation of the CEMP would minimise the potential risk to controlled waters during demolition and construction. Post World War II bomb damage maps identify that that previous buildings on and adjacent to the Site were damaged by incendiary devices. The existence of Unexploded Ordnance at the Site cannot therefore be discounted at this stage and a specialist survey of the Site would be undertaken prior to any intrusive works. Mandatory health and safety requirements would ensure all construction workers are provided with necessary awareness training to recognise potential unexploded ordnance and provided with safety instructions detailing actions to take should unexploded ordnance be encountered. In addition to any specific remediation measures, the Development would include the provision of buildings and hardstanding across the majority of the Site and the provision of clean topsoil in soft landscaping areas. All of the measures set out above would seek to ensure that the potential risk of harm to human health and the wider environment would be minimised so not to cause an unacceptable contamination risk. This, together with the inherent design of the completed Development would remove all contamination sources and pathways from all potential receptors. 12. Historic Environment The Site does not contain any designated heritage assets, or any known undesignated heritage assets. Although not currently identified as such in the Local Plan, the Isle of Dogs is an Area of Archaeological Priority, which has potential to contain both palaeo-environmental evidence and evidence of prehistoric human activity. Although the Site has been developed in the nineteenth and twentieth centuries, there is some potential for survival of prehistoric, medieval, and post medieval / industrial archaeology. More significantly, it is likely that palaeo-environmental materials survive across the Site at deeper levels, as evidenced by previous geotechnical site investigations; these potentially include a prehistoric forest floor. The potential adverse effects of the Development would be associated with excavation and foundation works required to facilitate the Development as well as the diversion of the Barnfield Sewer. Mitigation of development effects on any heritage assets that may be present would require further analysis of a geo-archaeological model of the Site. In the first instance, a suitable Written Scheme of Investigation which would describe a methodology to sample palaeo-environmental deposits and features using the appropriate geo-archaeological techniques as advised by Historic England s Regional Scientific Advisor, and produce a model of the Site s archaeological potential. This model would then inform the scope of further mitigation stages, as required. 13. Ecology The potential significant effects resulting from the Development were assessed in accordance with published guidelines. The ecological information considered in the chapter was derived from ecological appraisals undertaken for the Site, comprising Extended Phase 1 Habitat Surveys and desk studies, bat activity surveys and Jersey cudweed walkover surveys (a protected plant). The Site predominantly comprises an active supermarket, with an associated car parking area and soft landscaping comprising amenity grassland, scattered trees and introduced shrubs. Along the eastern and southern boundary of the Site, semi-natural broadleaved woodland is present. The southern section acts as a boundary between the Site and Mudchute Park Farm, a Local Nature Reserve (LNR) / Site of Importance for Nature Conservation (SINC) which contains improved grassland, scattered trees and a small area of seminatural broadleaved woodland (Figure 11). The area of off-site works associated with the diversion of the Barnfield Sewer is located within Mudchute Park Farm, within an area of improved grassland. Prior to the demolition and construction on the Site, the existing Barnfield Sewer would be diverted which would result in the removal of soil and habitats such as scattered trees, improved grassland and semi-natural broadleaved woodland. Some habitat loss would also take place in Mudchute Park Farm during the Site 11

12 clearance for access requirements. This would result in the permanent removal of soil, semi-natural broadleaved woodland and scattered trees within this proposed area. Upon completion of the Barnfield Sewer diversion works, all lost habitats would be re-instated like-for-like using plant species of wildlife benefit in keeping with the LNR/SINC conservation objectives. Any habitat loss to Mudchute Park Farm as a result of the demolition and construction works would be replaced by compensation in the form of additional planting in this area including native species or species of wildlife benefit, to minimise any gaps in vegetation. In addition, the improved grassland lost would be re-seeded with a species rich seed mix to help promote an increase in species diversity. Jersey cudweed has the potential to be present on-site and the loss of habitat known to support Jersey cudweed and the destruction of the plant itself would affect its abundance and distribution within LBTH. To ensure the protection of Jersey cudweed, annual monitoring surveys would take place every autumn for each specific phase of the Development before Site clearance/construction. Should any plants be found on-site, consultation with LBTH and NE would be undertaken and if required, a NE licence would be produced which may include the translocation of the plant to a suitable location such as on the proposed brown or green roofs within the Development. In order to carefully control and manage the potential environmental effects of the Development during the demolition and construction works, a CEMP would be implemented. The CEMP would follow all relevant legislative and best practice requirements to reduce disturbance resulting from noise, vibration, dust deposition, light spill and contamination / pollution events. The CEMP would accord with relevant British Standards Best Practice Guidelines to ensure that appropriate environmental controls are implemented to protect retained habitats. Figure 11: Proposed View of the Development from Mudchute Park and Farm Once the Development is complete and operational, mitigation would be provided through an annual Section 106 financial contribution for the life of the Development to safeguard the LNR / SINC from an increase in visitor numbers. A Landscape Habitat Management Plan (LHMP) would be provided detailing the long-term management strategy for the proposed ecological resources including the tree planting and biodiverse green and brown roofs. The LHMP would also include habitat mitigation along the southern boundary of the Site 12

13 which would create a partial buffer to Mudchute Park Farm LNR /SINC from disturbance caused by the operation of the Development. 14. Water Resources and Flood Risk The effects of the Development upon water resources and drainage have been informed by a review of various information sources including those made available by the Environment Agency and Thames Water; as well the ground conditions desk-top study. A Flood Risk Assessment and Drainage Management Plan have also been prepared to accompany the planning application and are included as part of the ES. The alluvium and gravels identified at the Site are classified as Secondary A Aquifers. The underlying Upper Chalk Formation has been classed as a Principal Aquifer. Groundwater is expected approximately 14m below ground level. There are no surface watercourses on the Site. The nearest natural surface water feature to the Site is the River Thames, which is located approximately 350m at its nearest point. The Site is located within Flood Zone 3, which denotes a high probability of tidal and/or fluvial flooding. However, the EA have confirmed that the Site is defended up to the 1 in 1000 year standard by the River Thames defences. During the demolition and construction works, a CEMP would be implemented. This would include temporary measures to be put in place to control surface water runoff from the Site and reduce the use of water. The proposed diversion route of the Barnfield sewer has been agreed in principle with Thames Water. Further consultation would be undertaken with Thames Water in relation to the diversion of the Sewer and to maintain and safeguard the stability and integrity of it and other Thames Water assets near the Site during the demolition and construction works. The Development has been designed to ensure the safety of occupiers and users of the buildings in the unlikely event of the flood defences failing. A Drainage Management Plan has been prepared to ensure the Development does not increase surface water runoff. Green and brown roofs and private residential gardens are also proposed as part of the Development which could reduce the rate of surface water runoff from the Site in addition to the provision of water attenuation tanks (which slow down the surface water to the sewer system). The total volume of attenuation would be confirmed during detailed design. The proposed basement is above the level of groundwater underneath the Site and would therefore not cause a significant blockage to the flow of groundwater and would not be sufficient to cause groundwater flooding in the vicinity of the Site. Foul water would be discharged into the combined Thames Water Sewer, as per the existing situation. The Development is likely to result in an insignificant effect in respect of the capacity of foul water and potable water infrastructure. 15. Wind Microclimate An assessment of the comfort and safety of the local wind microclimate within and surrounding the Site once the Development is completed and operational has been undertaken using wind tunnel testing of a scale model of the Development, with soft landscaping (which is proposed at ground level as part of the Development). The demolition of the existing car park on Phase 1 is not expected to give rise to any significant change to the existing wind microclimate, with no mitigation considered necessary. The area between Phase 1 and the proposed temporary car park on Phase 3 would be locally sheltered from wind blowing through this area (i.e. temporary canopies would be provided over entrances and pathways). Localised screening (at least 2m in height and extending at least 1m from the façade) would be provided to the south of the entrances to the school, along the northeast façade of Phase 1 and the temporary supermarket entrance, as Phase 1 becomes operational (prior to the completion of all Phases and the landscaping is completed). Temporary screening would be included to the south west podium space of Phase 1 to provide localised shelter prior to the completion of Phase 2. Localised shelter would also be provided to seating during the construction period. The likely effects on the wind microclimate during the construction period would range from adverse to beneficial 13

14 effects depending on proposed land use and location within the Site during the demolition and construction period. As construction of the Development proceeds, the wind conditions of the Site and its surrounds would gradually adjust to those for the completed Development with landscaping. Consideration was given to entrances, thoroughfares, drop-off locations and amenity spaces. The design of the Development includes features developed to benefit the wind microclimate, which consist of 1.8m high balustrades on publicly accessible roof top terraces, and corner wrap-around balconies on some façades in addition to the proposed soft landscaping. To assist in ameliorating some of the adverse wind conditions, additional mitigation measures would be developed at the detailed design stage for locations within Phases 2 and 3 to provide an acceptable wind environment for the intended use. 16. Daylight, Sunlight and Overshadowing An assessment has been undertaken to establish the likely significant effects of the Development proposed upon the amount of daylight and sunlight received by properties adjacent to the Site. An analysis of the amount of overshadowing of the existing amenity spaces around the Development Site has also been undertaken. The assessment has involved the use of a three-dimensional computer model of the Development and its relevant immediate surroundings. Following demolition of the existing buildings, daylight and sunlight levels at the Site and the immediate surrounds are likely to steadily increase in magnitude as the superstructure is built. As the construction works continue, the levels of daylight, sunlight and overshadowing received by neighbours for the Site would trend towards those of the completed Development. To assess the surrounding existing properties, the BRE Guidelines provide two main methods for assessing daylight: Vertical Sky Component (VSC) and No Sky Line (NSL). The VSC method measures the amount of light available on a vertical wall or window following the introduction of barriers such as buildings. The NSL method is a measure of the distribution of daylight at the working plane within a room (i.e. a horizontal desktop plane of 0.85 metres (m) in height). The NSL divides those areas of working plane in a room which receive direct sky light through the windows from those areas of the working plane which cannot. Where all of the windows meet the VSC and all of the rooms meet the NSL criteria within a property, the effect is considered to be insignificant. For the assessment of sunlight, the approach considers the Annual Probable Sunlight Hours (APSH) for a reference point on a window (i.e. if a window point can receive at least 25% APSH, then the room should still receive enough sunlight). Windows are checked to see if they are facing 90 due south, with the emphasis on main living rooms: other rooms such as the kitchen and bedrooms are less important. In regards to daylight, 2,255 (79%) windows assessed would meet the BRE guidelines for VSC, and 711 (88%) out of the 807 rooms assessed would meet the BRE guidelines for NSL. Given that the majority of the properties would not experience significant effects, no mitigation measures are considered necessary. For sunlight, out of the 2,354 windows assessed 2,483 (95%) would meet the BRE guidelines for Annual and Winter APSH as a result of the Development. Therefore, in regards to the sensitive properties, the Development would have a minor adverse effect and mitigation is not required. Whilst the levels of overshadowing in the surrounding area would be higher as a result of the Development, this would not significantly affect any of the key areas of public amenity space in the surrounding context. The assessment concludes that the impacts in regards on transient overshadowing on both public and private spaces range from insignificant to major adverse for the winter months and insignificant to minor adverse for the summer months. 17. Cumulative Effects Two types of cumulative effects have been assessed in relation to the Development: 14

15 Type 1 Effects: The combined effects of individual effects (for example noise, dust and visual effects) from one the Development on a particular receptor; and Type 2 Effects: The combination of effects arising from several developments (in this case, the Development together with other reasonably foreseeable schemes (hereafter referred to as cumulative schemes ), which individually might be insignificant, but when considered together could create a significant cumulative effect. During the demolition and construction period, a combination of nuisance effects from noise, vibration and dust together with visual and traffic effects could be experienced. The implementation of environmental control measures through a CEMP would minimise the nuisance effects on local residents, pedestrians and other users during demolition and construction. The cumulative effects of the Development, together with other planned (or committed) developments were assessed. In total, 28 cumulative schemes were considered and were agreed with Tower Hamlets Council through the Scoping process. These schemes were selected on the basis that they had a valid planning permission, were within 1km of the Site and have a floorspace uplift of greater than 10,000m 2 Gross External Area or introduced new sensitive receptors near to the Site. Figure 12 shows the location of the cumulative schemes. Figure 12: Cumulative Schemes 15

16 During the demolition and construction of the Development, similar works on other cumulative schemes would likely result in temporarily increased traffic, noise and visual intrusion but the significant distance between the Site and the sites of the cumulative schemes would help minimise cumulative effects. The implementation of environmental control measures, such as a CEMP for the Development and the other planned developments, would minimise the nuisance effects on the surrounding area during demolition and construction. The key cumulative effects of the Development, once completed, in conjunction with the planned developments were generally found to be minimal. Exceptions comprise the following cumulative effects as follows: cumulative beneficial effects in relation to socio-economic, due to the provision of housing within Tower Hamlets, additional expenditure in the local area and the creation of jobs within Tower Hamlets and London; cumulative beneficial effects in relation to water resources and flood risk, due to reductions to existing surface water run-off through attenuation, accounting for climate change; and cumulative beneficial effects on townscape character areas, built heritage assets, and views by appropriately reflecting the Site s status as the District Centre for the Isle of Dogs. If you would like to receive further copies of this Non-Technical Summary or would like to purchase a copy of the Environmental Statement, please contact: Waterman Infrastructure & Environment Pickfords Wharf Clink Street London SE1 9DG Tel: ie@watermangroup.com 16

185 Park Street ENVIRONMENTAL STATEMENT: NON-TECHNICAL SUMMARY

185 Park Street ENVIRONMENTAL STATEMENT: NON-TECHNICAL SUMMARY 1. Introduction DV4 Properties Park Street Co. Ltd (hereafter referred to as the Applicant ) is seeking to obtain full planning permission for the redevelopment of 185 Park Street, situated on land bounded

More information

LONDON BRIDGE STATION ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY

LONDON BRIDGE STATION ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY LONDON BRIDGE STATION ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY June 2011 1 EXECUTIVE SUMMARY 2 INTRODUCTION CONTENTS Page 2.1 Introduction 4 2.2 The Site 4 3 THE DEVELOPMENT 3.1 What is it? 5 3.2

More information

University Park, Worcester Non Technical Summary December 2011

University Park, Worcester Non Technical Summary December 2011 University Park, Worcester Non Technical Summary December 2011 Introduction UW Wrenbridge LLP, a Joint Venture Company of the University of Worcester and Wrenbridge Land Ltd (the Applicants ) intend to

More information

Replacement Golf Course Facilities and Residential Development, Churston. Environmental Statement Non-Technical Summary

Replacement Golf Course Facilities and Residential Development, Churston. Environmental Statement Non-Technical Summary Replacement Golf Course Facilities and Residential Development, Churston Environmental Statement Non-Technical Summary July 2011 Reproduced from the Ordnance Survey s map with the permission of the Controller

More information

Meridian Gate. Non Technical Summary. Submitted by Meridian Property Holdings Ltd.

Meridian Gate. Non Technical Summary. Submitted by Meridian Property Holdings Ltd. Meridian Gate Non Technical Summary Submitted by Meridian Property Holdings Ltd. Meridian Gate May 2014 Waterman Energy, Environment & Design Limited Pickfords Wharf, Clink Street, London SE1 9DG, www.watermangroup.com

More information

DEFGH. Crystal Place Park. Environmental Impact Assessment (EIA) Elin Thomas and Emily Low Waterman Environmental

DEFGH. Crystal Place Park. Environmental Impact Assessment (EIA) Elin Thomas and Emily Low Waterman Environmental DEFGH Crystal Place Park Environmental Impact Assessment (EIA) Elin Thomas and Emily Low Waterman Environmental 10.12.07 EIA Presentation Content What is EIA? Legal Requirements Process Q&A Key Topics

More information

17A. Wind Microclimate

17A. Wind Microclimate 17A. Wind Microclimate 17A.1 Introduction 17A.1.1 17A.1.2 17A.1.3 17A.1.4 This Chapter, which has been prepared by Waterman and BMT, provides further information with regard to the potential wind microclimate

More information

1. Introduction. Site Boundary

1. Introduction. Site Boundary 1. Introduction Workspace Group Plc (hereafter referred to as the Applicant ) is seeking to obtain full planning permission for the redevelopment of (hereafter referred to as the Site ), situated to the

More information

LAND SECURITIES REDEVELOPMENT OF NEWNHAM COURT SHOPPING VILLAGE, MAIDSTONE

LAND SECURITIES REDEVELOPMENT OF NEWNHAM COURT SHOPPING VILLAGE, MAIDSTONE LAND SECURITIES REDEVELOPMENT OF NEWNHAM COURT SHOPPING VILLAGE, MAIDSTONE Land at Environmental Statement: Non-Technical Summary Introduction Land Securities plc is applying to Maidstone Borough Council

More information

NON-TECHNICAL SUMMARY

NON-TECHNICAL SUMMARY Proposed Sand and Gravel Extraction and Associated Processing Operations with Restoration to a Mixture of Agriculture and Nature Conservation including Areas of Shallow Water at Hedgeley, Northumberland

More information

NON - TECHNICAL SUMMARY

NON - TECHNICAL SUMMARY WATERMAN ENERGY, ENVIRONMENT & DESIGN LTD 60 ludgate hill / 30 old bailey environmental STATEMENT NON - TECHNICAL SUMMARY REV. 01 january 2011 Non-Technical Summary 60 Ludgate Hill / 30 Old Bailey 1. Introduction

More information

The Place Solar Farm

The Place Solar Farm The Place Solar Farm Environmental Statement Non-Technical Summary 28 August 2014 Produced for Prepared by St John s House Queen Street, Manchester M2 5JB Contents Contents... 2 1 Introduction... 3 1.1

More information

South Whitehaven, Cumbria EIA

South Whitehaven, Cumbria EIA South Whitehaven, Cumbria EIA Environmental Statement - Non Technical Summary June 2013 in association with 1. Introduction Story Homes is applying to Copeland Borough Council (CBC) for a new residential

More information

Barvills Solar Farm Environmental Statement Non-Technical Summary

Barvills Solar Farm Environmental Statement Non-Technical Summary Barvills Solar Farm Environmental Statement Non-Technical Summary 13 March 2015 Produced for Prepared by St John s House Queen Street, Manchester M2 5JB Contents Contents... 2 1 Introduction... 3 1.1 Development

More information

ES 5. Drakelow Park. Environmental Statement. Volume 5: Non Technical Summary. Lead Author Waterman Energy, Environment and Design Ltd

ES 5. Drakelow Park. Environmental Statement. Volume 5: Non Technical Summary. Lead Author Waterman Energy, Environment and Design Ltd Drakelow Park ES 5 Environmental Statement Volume 5: Non Technical Summary Lead Author Waterman Energy, Environment and Design Ltd April 2009 Environmental Statement Volume 5: Non-Technical Summary DRAKELOW

More information

Marshgate Business Centre ENVIRONMENTAL STATEMENT: NON-TECHNICAL SUMMARY

Marshgate Business Centre ENVIRONMENTAL STATEMENT: NON-TECHNICAL SUMMARY 1. Introduction Workspace 14 Limited (hereafter referred to as the Applicant ) has applied for full planning permission for the redevelopment of and 14 Marshgate Lane, situated on land bound by Marshgate

More information

Grantham Southern Quadrant Link Road Environmental Statement

Grantham Southern Quadrant Link Road Environmental Statement Grantham Southern Quadrant Link Road Environmental Statement Non Technical Summary Introduction Lincolnshire County Council (LCC) is submitting a planning application for the proposed implementation of

More information

Meridian Water Phase 1 Application

Meridian Water Phase 1 Application Meridian Water Phase 1 Application MW11 Environmental Statement Non-Technical Summary London Borough of Enfield March 2016 Contents 1 Introduction 1 2 The proposed development 2 3 Evolution of the proposed

More information

BREEDON NORTHERN LIMITED

BREEDON NORTHERN LIMITED Non Technical Summary CONTENTS 1 INTRODUCTION... 1 2 SITE DESCRIPTION... 1 3 DESCRIPTION OF THE DEVELOPMENT... 6 4 NEED FOR THE DEVELOPMENT... 8 5 KEY ISSUES CONSIDERED IN THE ENVIRONMENTAL IMPACT ASSESSMENT...

More information

Longbridge Town Centre Phase 2 Planning Application

Longbridge Town Centre Phase 2 Planning Application Longbridge Town Centre Phase 2 Planning Application Non-Technical Summary of the Environmental Statement December 2013 Introduction A full application for Planning Permission has been submitted to Birmingham

More information

London Road, Derker. Non Technical Summary. Introduction

London Road, Derker. Non Technical Summary. Introduction London Road, Derker Non Technical Summary Introduction The Oldham Rochdale Housing Market Pathfinder was set up to tackle longstanding problems of poor quality housing and to provide the framework for

More information

BEAUFORT PARK BUILDINGS D3 TO D8 PLANNING APPLICATION ENVIRONMENTAL STATEMENT NON- TECHNICAL SUMMARY

BEAUFORT PARK BUILDINGS D3 TO D8 PLANNING APPLICATION ENVIRONMENTAL STATEMENT NON- TECHNICAL SUMMARY BEAUFORT PARK BUILDINGS D3 TO D8 PLANNING APPLICATION ENVIRONMENTAL STATEMENT NON- TECHNICAL SUMMARY November 2014 Introduction 1.1 St George Central London (the Applicant ) is seeking to obtain planning

More information

CA//16/00504/FUL. Canterbury City Council Military Road Canterbury Kent CT1 1YW. Crown copyright and database rights 2016 Ordnance Survey

CA//16/00504/FUL. Canterbury City Council Military Road Canterbury Kent CT1 1YW. Crown copyright and database rights 2016 Ordnance Survey O Scale 1:1,250 Map Dated: 09/05/2016 CA//16/00504/FUL Crown copyright and database rights 2016 Ordnance Survey 100019614 Canterbury City Council Military Road Canterbury Kent CT1 1YW AGENDA ITEM NO 13

More information

ABBEY MANOR GROUP/SAINSBURY S SUPERMARKETS LTD

ABBEY MANOR GROUP/SAINSBURY S SUPERMARKETS LTD ABBEY MANOR GROUP/SAINSBURY S SUPERMARKETS LTD Mixed Use Development including Business Park and Foodstore Land at Bunford Park, Bunford Lane, Yeovil Environmental Statement: Non-Technical Report June

More information

NON-TECHNICAL SUMMARY. October 2017 CLARENDON GAS WORKS WOOD GREEN

NON-TECHNICAL SUMMARY. October 2017 CLARENDON GAS WORKS WOOD GREEN NON-TECHNICAL SUMMARY October 2017 CLARENDON GAS WORKS WOOD GREEN CLARENDON GAS WORKS, HARINGEY ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY October 2017 Our Ref: Q70251 Contents 1 INTRODUCTION... 2 2

More information

PANSHANGER QUARRY, Hertfordshire

PANSHANGER QUARRY, Hertfordshire PANSHANGER QUARRY, Hertfordshire Proposed enhanced restoration of Phases F & H Briefing Note 1 March 2015 INERT (INACTIVE) RESTORATION MATERIALS, CONTROLS AND OPERATIONS 1 Introduction This briefing note

More information

SMITHFIELD QUARTER ENVIRONMENTAL STATEMENT: NON-TECHNICAL SUMMARY HENDERSON GLOBAL INVESTORS LTD. FEBRUARY Waterman Energy, Environment & Design

SMITHFIELD QUARTER ENVIRONMENTAL STATEMENT: NON-TECHNICAL SUMMARY HENDERSON GLOBAL INVESTORS LTD. FEBRUARY Waterman Energy, Environment & Design SMITHFIELD QUARTER ENVIRONMENTAL STATEMENT: NON-TECHNICAL SUMMARY HENDERSON GLOBAL INVESTORS LTD. FEBRUARY 2013 Waterman Energy, Environment & Design 1. Introduction Henderson Global Investors Limited

More information

Moat Lane Regeneration Project Environmental Statement

Moat Lane Regeneration Project Environmental Statement AECOM Environment Towcester Regeneration Ltd. October 2012 Moat Lane Regeneration Project Environmental Statement Non-Technical Summary Prepared by:... Checked by:... Sophie Collins Scott Wilson Environmental

More information

Comments on the proposed scope are requested from WCC/NBBC officers to be provided to SLC Rail by 25 th March 2016 and sent to

Comments on the proposed scope are requested from WCC/NBBC officers to be provided to SLC Rail by 25 th March 2016 and sent to Introduction WCC have indicated that in advance of the surveys and assessments being undertaken consultation should be undertaken with technical officers of both Warwickshire CC and Nuneaton and Bedworth

More information

Rochford District Council Allocations Development Plan Document: Discussion and Consultation Document Sustainability Appraisal

Rochford District Council Allocations Development Plan Document: Discussion and Consultation Document Sustainability Appraisal Option SWH1 Balanced Communities Option SWH1 1 To ensure the delivery of high quality sustainable communities where people want to live and work Will it ensure the phasing of infrastructure, including

More information

Cardiff International Sports Village Waterfront Development Volume IV : Non-Technical Summary of the Environmental Statement

Cardiff International Sports Village Waterfront Development Volume IV : Non-Technical Summary of the Environmental Statement Greenbank Partnerships Ltd October 2012 Cardiff International Sports Village Waterfront Development Volume IV : Non-Technical Summary of the Environmental Statement Environmental Statement - Non Technical

More information

Date: TOWN AND COUNTRY PLANNING (ENVIRONMENTAL IMPACT ASSESSMENT) REGULATIONS 2011: REGULATION 13 SCOPING OPINION

Date: TOWN AND COUNTRY PLANNING (ENVIRONMENTAL IMPACT ASSESSMENT) REGULATIONS 2011: REGULATION 13 SCOPING OPINION PLANNING & BUILDING CONTROL Tracy Harvey Head of Planning & Building Control Rob Wells Savills Innovation Court 121 Edmund Street Birmingham B3 2HJ Our Ref: 5/16/3441 E-mail: Date: planning@stalbans.gov.uk

More information

Unity Square, Nottingham Environmental Statement Non Technical Summary December 2013

Unity Square, Nottingham Environmental Statement Non Technical Summary December 2013 Unity Square, Nottingham Environmental Statement Non Technical Summary December 2013 in association with 1. Introduction Peel Holdings is applying to Nottingham City Council (NCC) for Outline planning

More information

Armourers Court, Woolwich

Armourers Court, Woolwich Armourers Court, Woolwich Environmental Statement, Non-Technical Summary December 2013 DESIGN PACKAGE C158 WOOLWICH STATION East End Over Site Development (Armourers Court, Arsenal Way, Woolwich) Environmental

More information

Longbridge East : Site Wide and Phase One Development

Longbridge East : Site Wide and Phase One Development Longbridge East : Site Wide and Phase One Development Non-Technical Summary of the August 2011 Introduction St Modwen Developments Ltd intend to submit a new outline planning application for Longbridge

More information

Departure from the Development Plan. Town Council objection to a major application. DETERMINE

Departure from the Development Plan. Town Council objection to a major application. DETERMINE Item No. 9 APPLICATION NUMBER CB/17/01642/OUT LOCATION Land rear of 43 to 91 Silver Birch Avenue South of Alder Green and Aspen Gardens, Aspen Gardens, Stotfold PROPOSAL Outline application for up to 95

More information

11. ISLINGTON ROUTE SECTION ENVIRONMENTAL BASELINE AND ASSESSMENT OF IMPACTS OVERVIEW OF ISLINGTON ROUTE SECTION... 2

11. ISLINGTON ROUTE SECTION ENVIRONMENTAL BASELINE AND ASSESSMENT OF IMPACTS OVERVIEW OF ISLINGTON ROUTE SECTION... 2 11. ISLINGTON ROUTE SECTION ENVIRONMENTAL BASELINE AND ASSESSMENT OF IMPACTS... 2 11.1 OVERVIEW OF ISLINGTON ROUTE SECTION... 2 11.2 POLICIES RELEVANT TO ALL WORKSITES IN ISLINGTON... 3 11.3 FARRINGDON

More information

BRIDGE OF DON MASTERPLAN & PLANNING SUMMARY

BRIDGE OF DON MASTERPLAN & PLANNING SUMMARY BRIDGE OF DON MASTERPLAN & PLANNING SUMMARY SITE LOCATION The site of the existing AECC lies in an area of predominately residential and business use in Bridge of Don and extends approximately 50 acres.

More information

on behalf of LS Portland House Developer Ltd Portland House, Bressenden Place, London Environmental Statement - Non-Technical Summary February 2013

on behalf of LS Portland House Developer Ltd Portland House, Bressenden Place, London Environmental Statement - Non-Technical Summary February 2013 on behalf of LS Portland House Developer Ltd Portland House, Bressenden Place, London Environmental Statement - Non-Technical Summary February 2013 1. INTRODUCTION LS Portland House Developer Limited (hereafter

More information

The Haymarket 189 Morrison Street, Edinburgh. Environmental Statement. Volume 1 Non Technical Summary

The Haymarket 189 Morrison Street, Edinburgh. Environmental Statement. Volume 1 Non Technical Summary The Haymarket 189 Morrison Street, Edinburgh Environmental Statement Volume 1 Non Technical Summary 16 August 2010 Tiger Haymarket Limited Partnership Non Technical Summary Contents 1 Introduction 1 2

More information

Rannoch 132 / 33 kv Substation Extension

Rannoch 132 / 33 kv Substation Extension Who we are Scottish and Southern Energy Power Distribution is part of the SSE plc group of companies. We own, maintain and invest in the networks in the north of Scotland the electricity transmission network

More information

Former RAF Sealand Site EIA

Former RAF Sealand Site EIA Praxis (Holdings) Ltd. Former RAF Sealand Site EIA Environmental Statement - Non Technical Summary February 2012 in association with P a g e 1 1. Introduction Praxis (Holdings) Ltd. is applying to Flintshire

More information

WELCOME. Land North of STEVENAGE. We would like to thank you for attending our public exhibition today.

WELCOME. Land North of STEVENAGE.   We would like to thank you for attending our public exhibition today. WELCOME We would like to thank you for attending our public exhibition today. The purpose of this event is to share our proposals and hear your thoughts on our ideas. Members of the project team are on

More information

Chapter 4. Route Window C12: Mile End Park and Eleanor Street Shafts

Chapter 4. Route Window C12: Mile End Park and Eleanor Street Shafts Chapter 4 Route Window C12: Mile End Park and Eleanor Street Shafts 48 Crossrail Amendment of Provisions 4 Route Window C12: Mile End Park and Eleanor Street Shafts Location plan of Mile End Park and Eleanor

More information

RECOMMENDATION APPROVE THE APPLICATION SUBJECT TO:

RECOMMENDATION APPROVE THE APPLICATION SUBJECT TO: LOCATION: Gateway House, 318-330 Regents Park Road, Finchley Church End, London, N3 REFERENCE: F/03933/13 Received: 03/09/2013 Accepted: 30/09/2013 WARD: Finchley Church End Expiry: 30/12/2013 APPLICANT:

More information

Welcome to our exhibition

Welcome to our exhibition Welcome to our exhibition The Homes & Communities Agency (HCA) welcomes you to this public exhibition explaining our proposals for the redevelopment of the former Lea Castle Hospital site. About the Homes

More information

LAND AT MIDDLETON STONEY ROAD AND HOWES LANE, BICESTER ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY. June 2017 Our Ref: Q70433

LAND AT MIDDLETON STONEY ROAD AND HOWES LANE, BICESTER ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY. June 2017 Our Ref: Q70433 LAND AT MIDDLETON STONEY ROAD AND HOWES LANE, BICESTER ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY June 2017 Our Ref: Q70433 Contents 1 INTRODUCTION... 2 2 SITE DESCRIPTION... 5 3 EIA METHODOLOGY...

More information

South Quay Plaza Tower Hamlets Community Forum; Record of Discussion

South Quay Plaza Tower Hamlets Community Forum; Record of Discussion South Quay Plaza Tower Hamlets Community Forum; 03.02.14 Record of Discussion Attendees: Jerry Bell - Tower Hamlets Council Nasser Farooq - Tower Hamlets Council Emily Harris - Berkeley Homes (South East

More information

GREENWICH PENINSULA CABLE CAR AREA MASTERPLAN ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY. 24 December 2010

GREENWICH PENINSULA CABLE CAR AREA MASTERPLAN ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY. 24 December 2010 GREENWICH PENINSULA CABLE CAR AREA MASTERPLAN ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY 24 December 2010 Our Ref: DT/JLL0509 Appeal Ref (optional): RPS 1 st Floor West Cottons Centre Cottons Lane London

More information

Kings Road Industrial Development, Immingham. Environmental Impact Assessment. Non Technical Summary

Kings Road Industrial Development, Immingham. Environmental Impact Assessment. Non Technical Summary Environmental Impact Assessment Non Technical Summary Report prepared by: Ecus Ltd. Brook Holt 3 Blackburn Road Sheffield S61 2DW 0114 266 9292 December 2013 Page left intentionally blank INTRODUCTION

More information

7 Scoping and Introduction to the Assessments

7 Scoping and Introduction to the Assessments 7 Scoping and Introduction to the Assessments 7.1 Scope of the assessments 7.1.1 Rule 8 of the TWR makes provision for an applicant to request a scoping opinion from the SoS indicating the information

More information

NORTH KENSINGTON GATE SOUTH ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY. September 2016 Our Ref: Q60157

NORTH KENSINGTON GATE SOUTH ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY. September 2016 Our Ref: Q60157 NORTH KENSINGTON GATE SOUTH ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY September 2016 Our Ref: Q60157 Contents 1 INTRODUCTION... 2 2 EIA METHODOLOGY... 5 3 SITE DESCRIPTION AND SETTING... 6 4 ALTERNATIVES...

More information

The Town and Country Planning (Environmental Impact Assessment) (Wales) Regulations 2016, Regulation 13 Scoping Opinion

The Town and Country Planning (Environmental Impact Assessment) (Wales) Regulations 2016, Regulation 13 Scoping Opinion Mr Graham Clark Berrys Newchurch Farm Kinnersley Hereford HR3 6QQ BY EMAIL The Town and Country Planning (Environmental Impact Assessment) (Wales) Regulations 2016, Regulation 13 Scoping Opinion SC/2017/0001

More information

Archaeology and Planning in Greater London. A Charter for the Greater London Archaeology Advisory Service

Archaeology and Planning in Greater London. A Charter for the Greater London Archaeology Advisory Service Archaeology and Planning in Greater London A Charter for the Greater London Archaeology Advisory Service THE PURPOSE OF THE CHARTER This Charter sets out how English Heritage will provide archaeological

More information

Newcourt Masterplan. November Exeter Local Development Framework

Newcourt Masterplan. November Exeter Local Development Framework Newcourt Masterplan November 2010 Exeter Local Development Framework Background The Exeter Core Strategy Proposed Submission sets out the vision, objectives and strategy for the development of Exeter up

More information

Principal Place ENVIRONMENTAL STATEMENT: NON-TECHNICAL SUMMARY

Principal Place ENVIRONMENTAL STATEMENT: NON-TECHNICAL SUMMARY 1. Introduction RT Group Property Investments Limited (the Applicant ) is seeking detailed planning permission for the redevelopment of 1.28 hectares of land off Norton Folgate to the north of Liverpool

More information

Non-Technical Summary

Non-Technical Summary Introduction The Brent Cross Cricklewood regeneration scheme is located in northwest London and comprises 151 hectares (ha) of land within the London Borough of Barnet (LBB) (the Site ). In July 2014,

More information

PLANNING STATEMENT. Market House Market Place Kingston upon Thames KT1 1JS

PLANNING STATEMENT. Market House Market Place Kingston upon Thames KT1 1JS PLANNING STATEMENT To support planning and listed building consent applications for change of use from Class A1 shop and Class A3 cafe to Class A3 restaurant at: Market House Market Place Kingston upon

More information

LAND AT WEST YELLAND. Environmental Statement Non-Technical Summary Welbeck Strategic Land LLP

LAND AT WEST YELLAND. Environmental Statement Non-Technical Summary Welbeck Strategic Land LLP LAND AT WEST YELLAND Environmental Statement Non-Technical Summary Welbeck Strategic Land LLP May 2014 Quality Management Issue/revision Issue 1 Revision 1 Revision 2 Revision 3 Remarks Draft FINAL Date

More information

volume 11 environmental assessment section 2 environmental impact assessment Part 4 ha 204/08 scoping of environmental impact assessments

volume 11 environmental assessment section 2 environmental impact assessment Part 4 ha 204/08 scoping of environmental impact assessments DESIGN MANUAL FOR ROADS AND BRIDGES volume 11 environmental assessment section 2 environmental impact assessment Part 4 ha 204/08 scoping of environmental impact assessments SUMMARY This Advice Note provides

More information

LAND AT HOWES LANE, BICESTER ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY. March 2017 Our Ref: Q70433

LAND AT HOWES LANE, BICESTER ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY. March 2017 Our Ref: Q70433 LAND AT HOWES LANE, BICESTER ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY March 2017 Our Ref: Q70433 Contents 1 INTRODUCTION AND SITE DESCRIPTION... 1 2 EIA METHODOLOGY... 5 3 ALTERNATIVES... 6 4 DESCRIPTION

More information

Sustainability Statement. Whitby Business Park Area Action Plan

Sustainability Statement. Whitby Business Park Area Action Plan Sustainability Statement Whitby Business Park Area Action Plan November 2014 Contents Page 1. Introduction 1 2. Scoping 3 3. Sustainability Appraisal of Options 6 4. Assessment of Draft Area Action Plan

More information

WELCOME GYPSY LANE. Wider Site Location plan. Proposals for the development of LAND OFF FOXLYDIATE LANE WEBHEATH. Proposals for the development of

WELCOME GYPSY LANE. Wider Site Location plan. Proposals for the development of LAND OFF FOXLYDIATE LANE WEBHEATH. Proposals for the development of WELCOME The developers are preparing an outline planning application for a residential led development and need the community s views in order to develop the proposals further WHAT IS PROPOSED? A high

More information

Cranbrook EXPANSION ENVIRONMENTAL STATEMENT: NON-TECHNICAL SUMMARY PRODUCED BY DAVID LOCK ASSOCIATES

Cranbrook EXPANSION ENVIRONMENTAL STATEMENT: NON-TECHNICAL SUMMARY PRODUCED BY DAVID LOCK ASSOCIATES Cranbrook EXPANSION ENVIRONMENTAL STATEMENT: NON-TECHNICAL SUMMARY PRODUCED BY DECEMBER 2014 CRANBROOK EXPANSION AREAS ENVIRONMENTAL STATEMENT NON TECHNICAL SUMMARY Submitted in support of Outline Planning

More information

E16: MAINTENANCE OF LANDSCAPED AREAS

E16: MAINTENANCE OF LANDSCAPED AREAS HIGH SPEED TWO INFORMATION PAPER E16: MAINTENANCE OF LANDSCAPED AREAS This paper outlines the proposed approach to the maintenance of landscaped areas created for HS2 Phase One. It will be of particular

More information

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL. REPORT TO: Planning Committee 1 April 2015 Planning and New Communities Director

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL. REPORT TO: Planning Committee 1 April 2015 Planning and New Communities Director SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL REPORT TO: Planning Committee 1 April 2015 AUTHOR/S: Planning and New Communities Director Application Number: Parish(es): Proposal: Site address: Applicant(s): Recommendation:

More information

RE: THE MALL, WALTHAMSTOW PLANNING APPLICATION REF: 17/1355 RESPONSE TO LBWF NEIGHBOUR CONSULTATION

RE: THE MALL, WALTHAMSTOW PLANNING APPLICATION REF: 17/1355 RESPONSE TO LBWF NEIGHBOUR CONSULTATION Gavin Chinniah Planning Manager Majors Team Development Management London Borough of Waltham Forest Sycamore House Town Hall Complex Forest Road London E17 4JF 19278/A3/RM/MJ/sl 4 th October 2017 Dear

More information

3.1 The hybrid planning application proposes the following description of development:

3.1 The hybrid planning application proposes the following description of development: CHAPTER 3: PROPOSED DEVELOPMENT 3.1 The hybrid planning application proposes the following description of development: Hybrid (part-outline/part-full) planning application for a single composite development

More information

Welcome to our public exhibition

Welcome to our public exhibition About Our Scheme Welcome to our public exhibition This exhibition gives you the chance to view and comment upon our emerging proposals for a new residential development of 68 new homes on the site of the

More information

Wyvern Park Skipton Environmental Statement. Non-technical Summary - April 2015

Wyvern Park Skipton Environmental Statement. Non-technical Summary - April 2015 Wyvern Park Skipton Environmental Statement Non-technical Summary - April 2015 BWB Consulting Ltd Whitehall Waterfront 2 Riverside Way Leeds LS1 4EH Telephone: +44(0)113 233 8000 Copyright This Report

More information

Perth and Kinross Council Development Management Committee 20 February 2013 Report of Handling by Development Quality Manager

Perth and Kinross Council Development Management Committee 20 February 2013 Report of Handling by Development Quality Manager Perth and Kinross Council Development Management Committee 20 February 2013 Report of Handling by Development Quality Manager 4(4)(iii) 13/81 Erection of sports hall, associated changing facilities, offices

More information

Environmental Impact Assessment

Environmental Impact Assessment Environmental Impact Assessment Environmental impact assessment (EIA) is the process of systematically drawing together an assessment of the likely significant environmental effects of a development project.

More information

Ʊ ± ªº Œª ºª ø ª ª ± ª

Ʊ ± ªº Œª ºª ø ª ª ± ª Ʊ ± ªº Œª ºª ø ª ª ± ª ø º Õ± ± ± Œ±øºÙ Õ ß Æª ø檺 ±Æ ƪ ø檺 æß Æ± Ʊ ª ø ø fl ª ª ± ê ø Õ øæß ª ª æªæ Ó ÔÌ Non-Technical Summary Introduction A planning application has been submitted to the Vale

More information

ENVIRONMENTAL STATEMENT NON TECHNICAL SUMMARY

ENVIRONMENTAL STATEMENT NON TECHNICAL SUMMARY ENVIRONMENTAL STATEMENT NON TECHNICAL SUMMARY HWK-DOC-INF-ESNTA-02 FEBRUARY 2017 REVISION HACKNEY WICK CENTRAL OUTLINE PLANNING APPLICATION Contents Introduction... 1 Application Site and Surroundings...2

More information

Environmental Impact Assessment for Waterway Restoration Projects. Chris John, Technical Director Ecus Ltd.

Environmental Impact Assessment for Waterway Restoration Projects. Chris John, Technical Director Ecus Ltd. Environmental Impact Assessment for Waterway Restoration Projects Chris John, Technical Director Ecus Ltd. Environmental Impact Assessment for Waterway Restoration Projects What is Environmental Impact

More information

Environmental Statement (Volume 1) Non Technical Summary

Environmental Statement (Volume 1) Non Technical Summary Environmental Statement (Volume 1) Non Technical Summary Prepared by: The Environment Partnership Haydock Point Environmental Statement (Volume 1): Non-Technical Summary March 2017 Contents 1. Introduction

More information

NATIONAL INSTITUTE FOR MEDICAL RESEARCH REDEVELOPMENT THE RIDGEWAY, MILL HILL. Environmental Statement, Non-Technical Summary Prepared by:

NATIONAL INSTITUTE FOR MEDICAL RESEARCH REDEVELOPMENT THE RIDGEWAY, MILL HILL. Environmental Statement, Non-Technical Summary Prepared by: NATIONAL INSTITUTE FOR MEDICAL RESEARCH REDEVELOPMENT THE RIDGEWAY, MILL HILL Document name: Environmental Statement, Non-Technical Summary Prepared by: Deloitte Real Estate Date submitted: June 2016 National

More information

Battersea Park East Environmental Statement

Battersea Park East Environmental Statement Environmental Statement Non-Technical Summary July 2014 , Battersea, London July 2014 Waterman Energy, Environment & Design Limited Pickfords Wharf, Clink Street, London SE1 9DG, www.watermangroup.com

More information

Schedule of Planning Applications Committee Date: 23 May Reference: 06/17/0726/F Parish: Hemsby Officer: Mr J Beck Expiry Date:

Schedule of Planning Applications Committee Date: 23 May Reference: 06/17/0726/F Parish: Hemsby Officer: Mr J Beck Expiry Date: Schedule of Planning Applications Committee Date: 23 May 2018 Reference: 06/17/0726/F Parish: Hemsby Officer: Mr J Beck Expiry Date: 22-05-2018 Applicant: Proposal: Site: Mr Gillett Change of use to the

More information

1 INTRODUCTION 1.1 INTRODUCTION

1 INTRODUCTION 1.1 INTRODUCTION 1 INTRODUCTION 1.1 INTRODUCTION RREEF (UK) Ltd in partnership with Sheffield City Council (SCC) is applying for planning permission for the construction of: a new indoor city centre market hall and indoor

More information

Peckham Peckham Area Vision Map

Peckham Peckham Area Vision Map Area Vision Map PNAAP13 PNAAP8 Sumner Road Surrey Canal Walk Bird in Bush Park Key: NSP Site Allocations PNAAP Allocations Greenspace Low Line Cycle Network Primary Shopping Areas Square Surrey Canal Walk

More information

here today Public exhibition

here today Public exhibition Public exhibition here today Find out more about Central England Co-operative and Hawkstone Vale Developments Ltd s redevelopment proposal to bring new retail and community facilities to Wilnecote. The

More information

Site ref: AS06 Site Name or Address: Murreys Court, Agates Lane

Site ref: AS06 Site Name or Address: Murreys Court, Agates Lane Site ref: AS06 Site Name or Address: Murreys Court, Agates Lane Proposed Land Use: Total Site Area (Ha): Housing 1.85 Ha Description: It is understood that the owner has no plans to dispose of the site

More information

9 Archaeology & Cultural Heritage

9 Archaeology & Cultural Heritage High Clachaig Wind Farm Scoping Report Page 56 9 Archaeology & Cultural Heritage 9.1 Introduction Cultural heritage in this context means the above- and below-ground archaeological resources, built heritage,

More information

intu Bromley Planning Summary Bringing more to Bromley February 2014

intu Bromley Planning Summary Bringing more to Bromley February 2014 intu Bromley Planning Summary February 2014 Bringing more to Bromley Contents Introduction 1 Description of the Proposals 2 Economic Benefits 4 Planning Policy 6 Cinema and Catering Assessment 7 Design

More information

Public Consultation. Land at Monks Farm, North Grove. Welcome

Public Consultation. Land at Monks Farm, North Grove. Welcome Welcome Welcome to our public exhibition for development on Land at Monks Farm, orth Grove. Gallagher Estates and Gleeson Strategic Land are preparing an outline planning application for new homes, open

More information

Welcome to our public exhibition

Welcome to our public exhibition About our scheme Welcome to our public exhibition Taylor Wimpey East Anglia intends to submit a detailed planning application for a new residential development of 39 high-quality homes at the B&M Concrete

More information

Proposed World-Class Hotel at Former Royal High School, Regent Road, Edinburgh

Proposed World-Class Hotel at Former Royal High School, Regent Road, Edinburgh Duddingston House Properties and Urbanist Hotels Proposed World-Class Hotel at Former Royal High School, Regent Road, Edinburgh Environmental Statement Non-Technical Summary 3rd September 2015 www.oldroyalhighschool.com

More information

Hounsome Fields, Basingstoke Environmental Statement Non- Technical Summary. For Wates Developments Ltd and Pellipar Investments Ltd

Hounsome Fields, Basingstoke Environmental Statement Non- Technical Summary. For Wates Developments Ltd and Pellipar Investments Ltd Hounsome Fields, Basingstoke Environmental Statement Non- Technical Summary For Wates Developments Ltd and Pellipar Investments Ltd December 2015 Contents 1 Introduction 3 2 The Proposals 8 3 Environmental

More information

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL. Executive Director (Operational Services) Corporate Manager (Planning and New Communities)

SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL. Executive Director (Operational Services) Corporate Manager (Planning and New Communities) SOUTH CAMBRIDGESHIRE DISTRICT COUNCIL REPORT TO: Planning Committee 12 January 2011 AUTHOR/S: Executive Director (Operational Services) Corporate Manager (Planning and New Communities) Notes: S/1848/10

More information

Aspirations Ltd. art otel, Hoxton London, EC2. ES Volume VII: Non Technical Summary

Aspirations Ltd. art otel, Hoxton London, EC2. ES Volume VII: Non Technical Summary Aspirations Ltd. art otel, Hoxton London, EC2 ES Volume VII: Non Technical Summary October 2009 Non-Technical Summary 1. Introduction Aspirations Limited (hereinafter referred to as the Applicant) is

More information

CENTRAL CHELMSFORD DEVELOPMENT AGENCY: CITY PARK WEST (PHASE 2)

CENTRAL CHELMSFORD DEVELOPMENT AGENCY: CITY PARK WEST (PHASE 2) CENTRAL CHELMSFORD DEVELOPMENT AGENCY: CITY PARK WEST (PHASE 2) Central Chelmsford Development Agency / Genesis 27/08/2014 Central Chelmsford Development Agency: Environmental Statement Quality Management

More information

Planning Committee 04/02/2015 Schedule Item 6. Smith Farm Estate, Old Bridge Close, Northolt, UB5 6UA.

Planning Committee 04/02/2015 Schedule Item 6. Smith Farm Estate, Old Bridge Close, Northolt, UB5 6UA. Planning Committee 04/02/2015 Schedule Item 6 Ref: Address: Ward: Proposal: PP/2014/5145 Smith Farm Estate, Old Bridge Close, Northolt, UB5 6UA. Greenford Broadway Installation of sports pitch, reconstruction

More information

Page 1 of 19 URBAN DESIGN FRAMEWORK FOR BOLTON STREET WATERFORD

Page 1 of 19 URBAN DESIGN FRAMEWORK FOR BOLTON STREET WATERFORD Page 1 of 19 URBAN DESIGN FRAMEWORK FOR BOLTON STREET WATERFORD 1.0 Introduction: The relocation of the City Council stores and depot from Bolton Street creates an exciting opportunity for development

More information

volume 11 environmental assessment section 2 environmental impact assessment Part 7 ha 218/08

volume 11 environmental assessment section 2 environmental impact assessment Part 7 ha 218/08 DESIGN MANUAL FOR ROADS AND BRIDGES volume 11 environmental assessment section 2 environmental impact assessment Part 7 ha 218/08 glossary of terms Used in DMRB Volume 11, Sections 1 and 2 SUMMARY This

More information

This document provides a summary of the ES findings in non-technical language.

This document provides a summary of the ES findings in non-technical language. Introduction MOTO Hospitality Limited (the Applicant ) is seeking full planning permission to redevelop the Kinross Motorway Service Area (the Site ) located at Turfhills, near Kinross, west of Junction

More information

Application Recommended for Approval Hapton with Park Ward

Application Recommended for Approval Hapton with Park Ward Application Recommended for Approval Hapton with Park Ward APP/2017/0036 Outline Planning Application Outline application for the construction of a new 3 bedroom dwelling (with all matters reserved for

More information

WHITELEY TOWN COUNCIL NORTH WHITELEY DEVELOPMENT SEPTEMBER 2014

WHITELEY TOWN COUNCIL NORTH WHITELEY DEVELOPMENT SEPTEMBER 2014 WHITELEY TOWN COUNCIL NORTH WHITELEY DEVELOPMENT SEPTEMBER 2014 Dear Resident This Special Edition of the Whiteley Voice which has been prepared in conjunction with the North Whiteley Consortium is to

More information

4 RESIDENTIAL ZONE. 4.1 Background

4 RESIDENTIAL ZONE. 4.1 Background 4 RESIDENTIAL ZONE 4.1 Background The residential areas within the City are characterised by mainly lowrise dwellings sited on individual allotments. Past architectural styles, settlement patterns and

More information

I615. Westgate Precinct

I615. Westgate Precinct I615. Westgate Precinct I615.1. Precinct Description The Westgate Precinct is located approximately 18km west of the Auckland city centre. There are seven Sub-precincts in the Westgate Precinct: Sub-precinct

More information