1 Arden Cross The Arden Cross Consortium s Vision

2 Contents 1. Scale of Opportunity 2. Capitalising on the Location 3. Capturing the Economic Potential 4. Placemaking Principles 5. Delivering the Ambition An exceptional opportunity to create a vibrant place that provides a competitive edge to the city region. BIR MIN GHAM AIRPORT NEC HS2 IN TE RCHA NGE Image from Google Earth 2

3 1 Scale of Opportunity Four landowners have come together to form the Arden Cross Consortium and create a vision for the development of Arden Cross, the major development zone around the HS2 Interchange Station. This is a once-in-a-generation opportunity for the area, but for those whose ownership goes back hundreds of years, this is also about long-term legacy. The Arden Cross Consortium want to create a successful and connected place, one that contributes far beyond the immediate site and well into the future. MANCHESTER BIRMINGHAM CURZON STREET LEEDS HS2 INTERCHANGE HS2 The opportunity to create an exceptional mixed use development is stimulated by the arrival in 2026 of HS2. The high speed line bisects the 150 hectare triangle site with the station located squarely in the middle. This creates 360 degrees of potential; however this is not a city centre location like Curzon in Birmingham. It is on the edge of the conurbation, in fact currently in the Green Belt. The station is intended to serve the purpose of interchange being at the Y-fork of the high speed network, linking other parts of the Midlands and major economic assets such as the Airport and NEC. To make it a successful place, it needs to be more than just a station; more than a transient place to make other connections. To warrant its release from the Green Belt, the place created needs to be more than just a major development around a station. It needs to be exceptional. It should deliver the right development in the right place at the right time: a place above all for people, to sustain a community, to generate regional economic benefits, some even of national significance, building on the exceptional locational and connectivity advantages. These should be complementary and additional to the wider effects of HS2 on the Midlands, not something that could be provided elsewhere. The site offers an unrivalled location capable of global status as a business destination. An opportunity lost if not pursued. It can also create a unique residential environment, supported by leisure, retail and social facilities as part of a mix which can deliver something major cities need: a vibrant urban district in an edge of urban setting. Something that major cities need: a vibrant urban district in an edge of urban setting Somewhere that provides a competitive edge to the city region LONDON EUROPE 3

4 HafenCity, Hamburg (image: 4

5 Life, spaces, buildings and in that order please. Jan Gehl HS2 will provide a world class station and funding of associated infrastructure to stimulate significant economic growth and wider regional prosperity. There is an unprecedented opportunity in this location for the Midlands to capitalise on this major investment; to begin to balance the national economy. The development of Arden Cross will capitalise on its national and international connectivity and the potential created around both arrivals and departures: People and businesses that require high speed connectivity to the rest of the UK and beyond, using the HS2 station or the Airport as a point of departure to export services or travel to other places. Visitors to the city region who arrive wanting to interchange with other modes of transport (air, rail or road) to other locations, including within the Midlands, or to interact with businesses and leisure activities present on the site or nearby, such as the NEC. The scale of the site creates opportunities for a range of environments broader than can be achieved in a city centre location. It can facilitate both swift transit onto ultimate destinations and greater dwell time to create a destination of the place itself. Proximity to the countryside also offers the potential for recreation and leisure pursuits on the doorstep. This can be a location for an international business which require quick access to overseas markets, a campus-style operation looking for space to grow and expand, or a research-intensive activity seeking collaboration with national and international partners in high density interactive space. To create added vibrancy, the development should provide retail, leisure and residential environments to support a new business community and foster a sustainable urban neighbourhood. These uses should be tailored to creating a successful and connected place, providing appropriate levels of accommodation to capitalise on the location and economic potential of the site. They should complement other provision in the vicinity. Other uses may be captured where they add to the overall vitality and dynamism of the place. Such uses may respond to the potential for synergy with other activities and functions of the site (e.g. R&D, education or skills and training facilities, and other service uses benefiting from proximity to major travel terminals). The strategic intent set out in the Midlands HS2 Growth Strategy (July 2015) and SMBC s Interchange Prospectus (July 2014) identifies the potential for in the region of 20,000 jobs and 2,000 homes on the Interchange site. The Arden Cross Consortium believes that these figures are achievable, and could be exceeded, particularly if the residential element is to be self-sustaining. The real prize will be to deliver an integrated place connecting the Airport, NEC and Interchange station which will complete the grand project started in this location forty years ago. The station should be fully integrated into the development from day one, generating demands from arrivals and departures which can be served by a range of uses in the immediate vicinity, rather than merely a transport facility surrounded by car parking and land awaiting development. This will be a place that redefines our very idea of a city: An international business hub Unrivalled connectivity Vibrant and welcoming A highly desirable place to live In touch with nature A competitive edge 5

6 2 Capitalising on the Location HS2 will transform the rail infrastructure of the UK. Along its route, it will create the potential for a step-change in economic growth in the areas around the proposed new stations. In the case of the station at the Interchange site, there is an opportunity to capitalise on the latent investment potential of the UK Central area. In combination with Curzon Street in Birmingham City Centre, and with the additionality arising from other complementary planned investments including at the adjoining NEC and Airport, the wider prosperity benefits for the Greater Birmingham area should be substantial. HS2 as a catalyst for growth The HS2 Task Force and Government have challenged stakeholders in each station location to maximise the potential for growth. The Midlands HS2 Growth Strategy states: Our vision is to harness the unrivalled connectivity and investment of HS2 to create a step change in the Midlands economic performance, driving growth and significantly improving outcomes for its people, businesses and places. The Midlands will have two stations (at Birmingham Curzon and Arden Cross) with differing roles and opportunities to: Develop world class integrated stations Attract inward investment Create internationally competitive business hubs Be home to sustainable residential communities Attract visitors to the Midlands In developing proposals for the Interchange site, the Arden Cross Consortium recognise the need for strategic fit with wider investment priorities and projects across the GBSLEP area and Midlands as a whole. Over 40% of passengers from London are expected to use the Interchange station rather than Birmingham Curzon. HS2 Information Paper: Birmingham Interchange Station (2015) 6

7 HS2 A unique concentration of economic assets and growth drivers of national and regional significance. The vision must reflect the particular characteristics of Arden Cross and wider area (referred to in the Midlands HS2 Growth Strategy and the Interchange Prospectus as the UK Central). The proximity of the Airport, the NEC, Jaguar Land Rover, as well as other nearby employment generating assets, represents an exceptional collocation of uses. All benefit from existing high levels of connectivity, which will be elevated to an outstanding level with HS2. This area will also benefit from a commitment to enhancement of existing infrastructure, including works to increase the capacity of the strategic highway network. Even ahead of the arrival of HS2 there is momentum behind the potential scale of growth that can be achieved in this location. The Airport is growing, and is forecast to handle 17m passengers a year by 2020, up 7m on 2014 The NEC, which is under new operational ownership and enjoying renewed success with the recent opening of Resorts World, has the potential for commercial expansion and regeneration Jaguar Land Rover, is spearheading the export success of the Midlands automotive sector helping generate a trade surplus with China which is likely to lead to future expansion The potential for each to capitalise on the arrival of HS2 needs to be built into the vision for the site in an holistic manner and which provides for a shared level of ambition. Aligned with the UK Central initiative, linkages will be made with Birmingham and Blythe Valley Business Parks and Solihull town centre to reflect the scale of wider economic opportunity for growth in this area. HS2 M6 HS2 Curzon St Birmingham City Centre North Solihull Regeneration BBP M6 A45 Birmingham Birmingham Airport NEC jct6 HS2 Interchange h S o l i l l u b o g r o u h Jaguar Land Rover Meriden A45 Hamptonin-Arden A41 M42 Solihull Town Centre Solihull Coventry Dickens A34 M42 Knowle Balsall Common H S2 7

8 Unrivalled connectivity The configuration of strategic transport infrastructure on the edge of the second most populous metropolitan area in the UK creates compelling potential. 70% of the UK s population lives within a 120 mile (200km) radius. GBSLEP identifies this location as the principal international gateway to the Midlands, stating: International connectivity is vital to attracting and retaining inward investment. HS2 will significantly improve links with our largest export market Europe. GBSLEP The old fingerpost at Birmingham Airport: worldwide destinations 8

9 The HS2 station at the Airport/NEC will act as a major integrated transport hub, linking to the motorway network, London Heathrow, London Euston station, London Crossrail, HS1 and Eurostar. GBSLEP HS2 will therefore strengthen the location s advantages to business: Phase 1 will enlarge the potential labour force and customer catchment to comprise a much larger area of London and the South East Phase 2 will expand access to the North West, East Midlands and South Yorkshire within easy journey times International connectivity is already strong with the proximity of the Airport but will be further strengthened by enhanced connections to London St Pancras and onward high speed travel to Northern Europe and potentially enhanced connections to London Heathrow Phase 2 will improve links to Manchester Airport, providing a wider range of international destinations for business travel These enhanced connections will offer a real source of competitive advantage to growing businesses that thrive on business-to-business interaction and require a wide range of skills and labour. Major economic benefits can be achieved through agglomeration and clustering with new and existing businesses taking advantage of a larger base of suppliers and a potentially wider labour market for economies of scale. A new residential community can be created which taps into the job opportunities available and made more accessible at UK Central. This will be a highly mobile population, attracted to this location for its vibrancy and connectivity. There is also the scope for improved regional and local connectivity: Releasing capacity on the existing rail network for the benefit of other towns and cities in the Midlands Midlands Connect, an inter-regional initiative looking to improve east-west movement corridors Midland Metro line from Birmingham city centre to the Airport/NEC and Interchange through the deprived eastern corridor, enhancing access to job opportunities Provision of SPRINT bus links to Solihull and Coventry The People Mover between the Interchange Station, the NEC, Airport and Birmingham International rail station on the WCML Improvements to the M42 junction 6 albeit the extent of change is yet to be determined. Engagement with Highways England will be critical alongside their commitment to improve local strategic highway capacity These are captured in the Midlands HS2 Growth Strategy and the West Midlands Connectivity Package. 9

10 3 Capturing the Economic Potential This is an opportunity which will be realised over the next ten, twenty, even thirty years, meeting needs beyond immediate and pressing requirements, involving anticipation of future market trends, lifestyles and work patterns. The Arden Cross Consortium s ambition is to identify those sectors which stand to benefit most from the unique location of the HS2 Interchange and its unrivalled regional, national, and international connectivity. The Midlands HS2 Growth Strategy articulates the impact of HS2 on the sub-regional economy: - Over 100,000 new or safeguarded jobs (of which 10% are estimated to be taken up by local residents that are unemployed) - Improvements to the skills profile ensuring that 36% of the local population is qualified to NVQ Level ,000 apprenticeships - An additional 14 billion GVA per annum. 10

11 Chiswick Park, London W4 11

12 Cost Advantages The commercial advantages of Arden Cross extend far beyond savings in journey time for business travel and staff commuting Distinctive business environments This will be a cost competitive location (based on comparative rental levels in the City of London versus the NEC/Solihull market) which will appeal to corporate occupiers looking to relocate to achieve savings, as well as offering the inward investment market a competitive alternative to London with exceptional links to the capital. There are distinct advantages for businesses in terms of the attraction and retention of workforce within Greater Birmingham and Solihull when residential costs are taken into consideration. Average house prices in the West Midlands are approximately one third of average house prices in London. This makes it easier for people to access housing within the area than competing locations and therefore for companies to retain staff who also live locally. The costs of doing business in London compared to the alternative at the Interchange site make a compelling case for investment. Grade A 67 psf 493,026 (London) Grade A 21 psf 140,417 (West Midlands) Comparison of NEC/Solihull rents and City of London rents Average house prices in London and the West Midlands (Q3 2015) 12

13 Sector Advantages The GBSLEP area has well documented strengths in advanced manufacturing and engineering, with particular specialisms in the automotive and aerospace sectors. It has a nationally significant concentration of financial and business services and growing life science, ICT and creative industries. These established and growing sectors and clusters of businesses provide a very strong basis for commercial demand for UK Central, however the extent to which the connectivity benefits of HS2 apply to these sectors is not equal. The capacity for businesses to derive commercial advantages from HS2 connectivity is closely related to factors such as: The level of business to business interaction The need for staff to travel to interface with colleagues and clients The need to travel to gain access to knowledge, professional networks, finance etc. The propensity of staff in different sectors to commute by rail The propensity of companies to use rail for component supply and onward distribution of finished products (based on potential for additional rail freight capacity on the West Coast Mainline) The sectors which are most likely to benefit from HS2 connections include Business and Professional Services and Life Sciences. Both exhibit a high propensity for workforce travel by rail and the need for high levels of business to business interaction. Additionally, there is the potential for aspects of advanced manufacturing associated with research and design activities to benefit from this location and enhanced connectivity to other companies and research institutions, including the region s universities. Clustering Advantages The site is located close to Jaguar Land Rover (with its major manufacturing plants in Solihull and Coventry) and at the heart of the most significant cluster of automotive engineering and component supply businesses in the UK. Almost 280,000 people are employed in automotive industries. The Interchange site provides an opportunity to capture demand from businesses in the automotive sector with a requirement for access to the wider supply chain as well as seeking to benefit from the locational and connectivity advantages of the site. 13

14 Alignment with LEP priority sectors Sector Advanced Manufacturing/Engineering Aerospace Greater Birmingham and Solihull Coventry and Warwickshire A34 Perry Barr / Birchfield Centre Corridor Curzon City Centre Enterprise Zone Digbeth Creative Quarter Science Park Aston Automotive Business Services Creative Industries Selly Oak Life Science Campus Financial Services ICT Longbridge ITEC Occupier Appeal and Economic Potential The location of Arden Cross will appeal to multiple business sectors and an array of different occupier groups that derive benefit from HS2 connectivity. These include: Businesses with a mobile workforce and high levels of business to business interaction Corporate occupiers seeking to relocate to achieve cost savings in a location that is highly accessible to Central London and other parts of the UK WYRE FOREST Large occupiers with requirements to create a distinct or branded environment Larger research and development facilities and or higher education institutions in the future Inward investors to the UK, particularly those looking to capitalise on links to London while enjoying cost and labour force advantages Arden Cross will work most effectively as part of a portfolio of investment locations across Greater Birmingham, complementing the city centre offer and planned projects / sector priorities across the wider LEP area. Key investment locations, Greater Birmingham 14

15 Advanced Manufacturing Hub UKC Friargate BIRMINGHAM SOLIHULL COVENTRY BROMSGROVE Coventry and Warwickshire Gateway REDDITCH Redditich Eastern Gateway 15

16 4 Placemaking Principles Around the world, highly connected places are centres for human interaction, and magnets for sustainable development. They are capable of meeting a multiplicity of needs in a location which will reduce the need to travel due to enhanced connectivity. At Arden Cross, there will be a generational step change in the location, and the economic potential of HS2 Interchange as part of this is clear: this will be an extraordinary regional connector and a national hub of European significance. It will generate supergrowth over and above what would arise from the existing economic assets and residential community. This will attract new people to live and work in the area. The Arden Cross Consortium promotes an approach which aims to inspire, attract and sustain a mixed use community at the site. This must be a place for people, a place with identity, and a destination in its own right. The Arden Cross Consortium is at the early stages of preparing a development framework for the site, based on a set of emerging spatial concepts. These draw upon and respect the work undertaken over recent years by UK Central, but include different and new proposals too. They reflect the aspirations of the Arden Cross Consortium to create an exemplar sustainable development, that meets a wide range of needs. There is potential for a new urban quarter. A leading business address, defined by busy thriving neighbourhoods - convivial places to meet, interact, create and live. 16

17 Chiswick Park, London W4 Principle 1 Fostering enterprise and growth through place not just space HS2 will make Arden Cross the focus of arrivals and departures, and there is clear opportunity to integrate employment development that captures the economic potential of this activity. But development must create more than just a space for transport interchange or business pursuit. It must be a place of interaction and life. The combination of powerful economic assets and unrivalled connectivity will support investment decisions that bring not just business, but people, to this site. Development must create a place that is rich, layered and rewarding, where people have access to employment, business, leisure, homes, a quality environment and social infrastructure. A sustainable and authentic place that encourages dwell time and generates multiple opportunities and benefits for the wider area. Through this approach the site will appeal to multiple business sectors and an array of different occupier groups. Employment space can be intensified towards the core in urban formats (see principle 2), balanced by more self contained business park or campus style layouts. These could offer flexibility not always offered by urban formats, whilst maximising and giving life to more peripheral areas and drawing advantage of visibility from the adjacent strategic highway network. 17

18 Principle 2 An intense, mixed core The Arden Cross Consortium envisages an area of concentrated development density and activity, stretching east-west from station to station. This will be the central focus of interchange: not just HS2 and rail as the wider strategic connections, but local links into diverse new neighbourhoods. The core will be characterised by; An urban grain diverse, intimate, walkable. Active buildings which meet the street well. A world class public realm integrating the natural environment and water. Principle 3 Places to live and put down roots A rising population in the sub-region and the attraction of this burgeoning economic hub will drive demand for residential space. This will be critical to overall success as a sustainable place. New homes will deliver activity outside of the working day, animating streets and spaces. This could be offered in formats not currently prevalent in this part of the region but proven successful in urban contexts internationally, which combine to create well defined, active streets: This can be a place for families. This is the heart of the country, presenting one of its most attractive rural settings with diverse natural and recreational assets. Development can integrate a network of family friendly streets. Live, active spaces animated by homes with their own front doors and a human scale. This will drive a need for high quality social infrastructure. Urban living overlapping with and extending out from the core. 24/7 presence and activity through the area of highest value public realm and richest mix of land use. Some apartment buildings, but not exclusively: moving out to a broader range of homes and block forms. 18

19 Hamburg European Green Capital 2011 launched by the Train of Ideas based on life in a green city (mobility, energy, climate protection, nature, economy and consumption) 19

20 Principle 4 An Integrated Station The station itself and the development that immediately surrounds it will be a key destination. It will have a vibrant and active feel generated by overstation development and a concourse environment which connects to a series of welcoming streets and public spaces. Surrounding development will be dense but not high rise; a human scaled place characterised by a green urbanism. Our research on the impacts of high speed rail in France, Belgium and the Netherlands, has shown that, far from being a white elephant, there are very many examples where investment in HSR has been the catalyst for significant urban and regional renewal. John Worthington, Independent Transport Commissioner and Chairman of the HSR working group Below: Lille Europe has helped to transform the economic prospects of the city and deliver a new city quarter. The masterplan concentrated on developing a positive public realm and easy connections between the new and existing station. Regional links were upgraded, achieving a seamless interchange to HSR. The station can also be reached by both tram and bus. Some key lessons include: High quality, legible links between transport modes Integration of over-station / rail line development Multiple linkages across rail lines (pedestrian and vehicular) 20

21 This is HS2 a project that will set designers, from the widest range of disciplines, the challenge of reaching new heights of creativity and innovation in everything they design. HS2 Design Vision, Preview Publication, June

22 Often in the UK, the urban realm falls to the bottom of the hierarchy of things to consider, but it is critical that the urban realm is not be thought of as an add-on. A station should be balanced behind and in front The Spatial Impacts of High Speed Rail: Learning from Europe Expert Panel, Space Syntax, 18th June 2014 By learning from European HSR experience, the Arden Cross Consortium see station design as an opportunity to: A. Overcome severance. Rail infrastructure can be a significant barrier to movement. This can be overcome through innovative building and landscape design. B. Address and link 3D levels. Vertical stacking of infrastructure within the station building, working with changes in ground levels, can create an efficient footprint and a more connected place. C. Intensify public realm quality. A high quality public realm around the station can welcome people into the place and enhance the setting of new development, driving up density and value. D. Connect at point of interchange. Links between modes of public transport should be direct, obvious and convenient. They must be considered at the outset to integrate with development and avoid expensive retrofitting. 22

23 ARRIVALS PLAN interaction tion dwell place functional people pragmatic DEPARTURES efficiency landscaped operational E. Balance, function and impact. The station must create a strong and attractive urban arrival point and deliver the functional requirements of a significant regional HSR station. There is also a tremendous opportunity to accommodate much of the station infrastructure needed below ground, using areas generated by mineral extraction. The Arden Cross Consortium must consider its design in the round; interfacing with an urban centre and strategic highway connections and parking requirements. A R R I V A S L A N D P L A C E SECTION HS2 Station & I N F R A S T R UCTURE D E P A R T U R E S 23

24 West Coast Main Line HS2 NEC - unique, innovative and growing international conferencing destination Birmingham Airport - ambitious, major UK passenger and freight hub HS2 Interchange - the triangle site offering core development opportunity Birmingham Business Park Sita (reclaimed landfill) National Exhibition Centre Birmingham Airport Birmingham International Station New bridge links HS2 Interchange West Coast Main Line HS2 Principle 5 Thinking outside the triangle Only by taking a holistic approach can Arden Cross be viewed as a credible and integrated part of the city region. The Arden Cross Consortium see development within the site being part of a coordinated east-west corridor: Connected and complementing the unique environments and economic vitality of the NEC and Airport Presenting an appropriate and responsive edge to the east a sensitive transition but a definitive Green Belt boundary. These three inter-connecting places each have their own scale and character, but the act of connection, through the People Mover but also pedestrian and vehicular links, will bring them closer together and enable the needs of one to be met by the others and vice versa. 24

25 A co-ordinated east-west corridor of strategic destinations. M42 Birmingham Business Park West Coast Main Line Sita (reclaimed landfill) National Exhibition Centre A452 Birmingham Airport Birmingham International Station HS2 Interchange Jct6 A45 M42 25

26 Principle 6 Clear, people-friendly environments quality landscape AIRPORT NEC CENTRAL AVENUE HS2 streets intensity varied open grain rural views WEST COAST MAIN LINE grid URBAN EDGE HS2 as the start, not the heart While ensuring the benefits of the new station are maximised, it need not be at the epi-centre of this new place. Rather it will form a key entry point to, and area of activity within a broader and more diverse economic and social centre. This linear centre; the Central Avenue will provide an active and attractive walking link to economic drivers beyond the site boundary, such as the NEC and Airport. Urban and edge (not sub-urban) The form of any new development must respond to both its setting and the functional demands placed upon it. The rail corridor provides a strong break between an urban environment, focused on buildings, to an edge condition, heavily influenced by transport and landscape. This requires the Arden Cross Consortium to neither pack the site, nor suburbanise it. The transition from a more urban core through to an attractive rural edge must be carefully handled. 26

27 People make it, and it is to them, not buildings, that we must fit our plans. Jane Jacobs URBAN LINKS over over station connector PEOPLE CORRIDOR local hubs city experience 24/7 connect diversity public realm mix over under transit local hubs Connected and bridged To become an integrated place, strong strategic connectivity must be reinforced by local links. These will allow for the rich interaction and exchange that the Arden Cross Consortium expect of successful urban areas, spreading the range and value of development opportunities. Engineered infrastructure in the form of adjacent highways and the HS2 line will present barriers, therefore the need to define credible and deliverable connectivity solutions is a priority. This must include exploring underground opportunities via the voids created by current mineral extraction activity. Route hierarchy people corridors The new Central Avenue, connecting the station to development and destinations to the west, will form a strong central corridor. Rather than a highway the Arden Cross Consortium see this as a people place; a sequence of attractive streets and spaces. Supporting links to north and south can blend walking and cycling with highway demands, buses and metros. These can in turn create a series of local hubs; pockets of activity and density centred around sustainable transport stops. 27

28 WCML An emerging framework: blending the principles Birmingham NEC Potential future metro extension Metro M42 R & D Campus Education Campus Parkland Business Airport Mixed-use Station Area Central Avenue A45 Pendigo Lake Solihull Metro People mover Higher Density Office Urban Living Mixed-use Station Area Urban Living Higher Density Office Access & interchange Hollywell Brook Family Living Parkland Business A45 A452 M42 28

29 Central Avenue Working environments Residential environments Access and interchange There is potential in this core area to deliver an intense and vibrant mix of uses focused on commercial and business activity. The Arden Cross Consortium anticipate an urban grain of mid-rise buildings extending across 20-30ha of land, integrating NEC. Employment space is likely to be orientated more towards financial services / business and professional services. Retail and leisure would be part of the mix sustained by a large working population, plus both integrated and adjacent residential. A major focus on public realm quality, and an environment that supports residential as much as business communities Higher density office - Around 20-25ha of self contained office environments which could attract general office requirements in buildings of up to 10,000sqm (with scope for some larger corporate headquarters). Campus - Around 20-25ha of looser grained, more informal environments and plots that help nurture innovation, research and development and higher education. Occupying sectors are likely to be advanced manufacturing, life sciences and higher and further education, and could include large lower density plots with allowance for grow-on space. Parkland - Accessible, landscape driven settings for occupiers not otherwise catered for by the above environments which can complement the wider investment locations across the LEP area for example automotive and aerospace supply chain businesses. A range of densities and typologies: a mixed environment supporting different occupiers and tenure. The Arden Cross Consortium anticipate residential development increasing from current estimates of c.2,000 homes by integrating: Urban living - A dynamic living environment: apartments primarily, but not exclusively. This can be mixed, catering for all ages, including a good proportion of larger units suitable for families. Flexible campus - Innovation, R+D and education uses could possibly drive bespoke residential formats, such a student accommodation and/or certain PRS typologies. Family living - Medium to high density, high quality familyorientated homes set in high quality landscape setting. Incorporating highway and rail infrastructure demands is a key challenge. There is opportunity to consolidate the infrastructure elements needed to support its role as a regional HSR station, and the immediate on-site development opportunities, towards the east of the site, with immediate access to/ from the A452. This part of this site can play a key role accommodating high capacity highway infrastructure and extensive multi-level parking that utilise the deep excavations created by mineral extraction. This would facilitate the creation of the composed urban core to the west. 29

30 5 Delivering the Ambition The Arden Cross Consortium s vision will be brought forward through proactive engagement with the planning process and by collaborating with key stakeholders. Allocating the Site First, the Arden Cross site needs to be removed from the Green Belt and allocated through the Local Plan, which requires exceptional circumstances to be shown. The Arden Cross Consortium believe the enormous benefits of this site being part of the region s response to HS2 will outweigh the harm to the Meriden Gap, the swathe of Green Belt separating Birmingham and Coventry which at this point is six miles wide. It is anticipated that the local plan will remove the site from the Green Belt and allocate it for a major mixed use development associated with the HS2 Interchange. This will comprise an allowance for residential and employment uses, as well as supporting social facilities, retail and leisure, and necessary infrastructure. The scale of the opportunity and the Arden Cross Consortium s ambition brings with it a high level of responsibility. They intend to be an active partner in delivering the development over the long term. 30

31 Engaging in the design process The UK Central overarching vision captures the potential of the wider area comprising the Airport, NEC, Jaguar Land Rover and Birmingham Business Park. The Arden Cross Consortium is working in collaboration with all stakeholders to ensure its vision for the site is consistent with and contributes to wider objectives. The Consortium is also working with UKC and HS2 on the emerging station design, ensuring that the interface between the station and the development maximises opportunities to connect, generate footfall, and bring forward early phases. The likelihood is that a local delivery vehicle will be formed to ensure that strategic infrastructure is provided, including the HS2 Connectivity Package and major improvements to the M42 junctions. The Arden Cross Consortium will play its part and commit to effective partnership working. The Arden Cross Consortium also wants to engage with the local community to gain support for the vision and explore the potential for wider benefits to be secured. The Lead in to Delivery The Arden Cross Consortium wants to see the site ready to receive HS2 passengers at a world class station from This means ensuring that the necessary planning, design and technical work is done over the next 10 years, including completion of mineral extraction, appropriate site levelling, strategic infrastructure provision, site access and early phases of development and environmental enhancement. Working together with HS2 and UKC, a programme for the unfettered construction of the HS2 works can be agreed which allows for early wins, such as site preparation and access so that development can be underway before Whilst the overall vision may take 20 to 30 years to achieve, it is vital that, on opening, HS2 is not a station in a development site but has immediate environs of vibrant new businesses and visitor facilities in a high density urban core. Finally, the Arden Cross Consortium s interests include the long-standing stewardship of the adjoining Packington Estate which has been family owned and managed since The setting of Packington Hall and the associated Registered Park and Gardens add a further dimension to the importance of context and the need to address the relationship with the adjoining countryside. This will be a unique place in the West Midlands a vibrant urban district on the edge of the city. 31

32 Arden Cross is part of UK Central & being delivered by: with support from Arden Cross Consortium Packington Hall Warwickshire CV7 7HF T E info@ardencross.com ardencross.com 32

HS2 Interchange Station Design

HS2 Interchange Station Design Working on behalf of HS2 Interchange Station Design October 2018 www.hs2.org.uk 1 Interchange Station, Solihull Introduction In February 2018, HS2 Ltd appointed Arup to take forward the design of Interchange

More information

Response to the London Bridge Area Vision and Site Allocations within the New Southwark Plan

Response to the London Bridge Area Vision and Site Allocations within the New Southwark Plan 1 Melior Place London SE1 3SZ 020 7407 4701 teamlondonbridge.co.uk info@teamlondonbridge.co.uk 28 April 2017 Response to the London Bridge Area Vision and Site Allocations within the New Southwark Plan

More information

West Midlands Local Transport Plan ( ) Making the Connections

West Midlands Local Transport Plan ( ) Making the Connections West Midlands Local Transport Plan (2011 2026) Making the Connections Our Vision for the Metropolitan Area: To make the West Midlands Metropolitan Area more prosperous, healthier and safer, offering a

More information

Welcome to our exhibition

Welcome to our exhibition Welcome to our exhibition housing development A46 Wildmoor Alcester Road Canal Quarter A422 Town Centre housing development Warwickshire-based IM Properties, one of the UK s largest privately owned property

More information

Euston Area Plan - Examination: Statement in response to the Inspector s Matters, Issues and Questions

Euston Area Plan - Examination: Statement in response to the Inspector s Matters, Issues and Questions 1 Euston Area Plan - Examination: Statement in response to the Inspector s Matters, Issues and Questions Sydney and London Properties Limited June 2014 2 3 This document is the Statement in response to

More information

WINCHESTER TOWN 3.1 LOCATION, CHARACTERISTICS & SETTING

WINCHESTER TOWN 3.1 LOCATION, CHARACTERISTICS & SETTING WINCHESTER TOWN 3.1 LOCATION, CHARACTERISTICS & SETTING 3.1.1 The area referred to by the City Council, as Winchester Town, consists of the Winchester Wards plus the adjoining built up areas of Badger

More information

Sheffield City Centre: shaping the future

Sheffield City Centre: shaping the future Sheffield City Centre: shaping the future A discussion paper Sheffield Executive Board (SEB) discussed the future of Sheffield City Centre at its March 2013 meeting. The Board agreed that the last decade

More information

WELCOME GYPSY LANE. Wider Site Location plan. Proposals for the development of LAND OFF FOXLYDIATE LANE WEBHEATH. Proposals for the development of

WELCOME GYPSY LANE. Wider Site Location plan. Proposals for the development of LAND OFF FOXLYDIATE LANE WEBHEATH. Proposals for the development of WELCOME The developers are preparing an outline planning application for a residential led development and need the community s views in order to develop the proposals further WHAT IS PROPOSED? A high

More information

Our City Centre is a vibrant, creative and welcoming destination, with a modern business, cultural, shopping, leisure and residential offer

Our City Centre is a vibrant, creative and welcoming destination, with a modern business, cultural, shopping, leisure and residential offer 3. Sheffield in 2034 Our City sits at the heart of a strong, distinctive and internationally successful City Region economy which supports innovation and enterprise Our City Centre is a vibrant, creative

More information

Chapter 03 Planning framework

Chapter 03 Planning framework Vauxhall Nine Elms Battersea Opportunity Area Planning Framework Chapter 03 Planning framework Mayor of London 25 preferred option - 16,000 residential units 20,000-25,000 jobs northern line extension

More information

Tauranga City Centre Spatial Framework

Tauranga City Centre Spatial Framework Tauranga City Centre Spatial Framework Stakeholder Engagement Workshop 15 October 2015 Project Design Team Beca & LandLAB Our team Henry Crothers (LandLab) Landscape Architect/Urban Designer Urban and

More information

OUR GREATER SYDNEY A metropolis of three cities. OVERVIEW. connecting people. DRAFT Greater Sydney Region Plan

OUR GREATER SYDNEY A metropolis of three cities. OVERVIEW. connecting people. DRAFT Greater Sydney Region Plan OUR GREATER SYDNEY 2056. A metropolis of three cities. OVERVIEW. connecting people. DRAFT Greater Sydney Region Plan October 2017 This document is an overview of the draft Greater Sydney Region Plan. To

More information

Birmingham. Summer study!!

Birmingham. Summer study!! Birmingham Summer study!! Urban Change in the UK - Birmingham - Part 1 Location / Facts - Birmingham is located in the centre of England - It is the 2nd largest city with a population of around 1 million

More information

Western City District What we heard

Western City District What we heard What we heard Vision to 2056 and Priorities Governance and implementation Infrastructure and funding The protection of the natural landscape including biodiversity and the Metropolitan Rural Area for food

More information

Vision for Mayfair and Belgravia

Vision for Mayfair and Belgravia Vision for Mayfair and Belgravia Vision for Mayfair and Belgravia Foreword We have a 20 year vision for Mayfair and Belgravia. It summarises our aspirations for the future of this London estate, which

More information

Tāhuhu whakaruruhau ā-taone The sheltering ridge pole

Tāhuhu whakaruruhau ā-taone The sheltering ridge pole B2. Tāhuhu whakaruruhau ā-taone - Urban growth and form B2.1. Issues Tāhuhu whakaruruhau ā-taone The sheltering ridge pole Auckland s growing population increases demand for housing, employment, business,

More information

Sheffield Victoria Station Development Prospectus January 2014

Sheffield Victoria Station Development Prospectus January 2014 6 Billion extra GVA growth for Sheffield City Region s economy Sheffield Victoria Station Development Prospectus January 2014 Document produced by Sheffield City Council Introduction The construction of

More information

Ebbsfleet Development Corporation Corporate Plan

Ebbsfleet Development Corporation Corporate Plan Ebbsfleet Development Corporation Corporate Plan 2016-2021 1 Ministerial Foreword In 2014, the Chancellor announced his intention to promote a Garden City at Ebbsfleet, and to create an Urban Development

More information

Droitwich Spa 6. Reasoned Justification

Droitwich Spa 6. Reasoned Justification 87 Droitwich Spa 6 Reasoned Justification 6.1 Droitwich Spa is identified in the settlement hierarchy (Policy SWDP1) as a main town being the largest settlement in Wychavon District with an estimated population

More information

2. Spatial Portrait, Vision and Objectives

2. Spatial Portrait, Vision and Objectives VISION & OBJECTIVES 2. Spatial Portrait, Vision and Objectives Introduction 2.1 This section sets out the spatial portrait of Uttlesford, the vision we have for the future of the area and the objectives

More information

UDF PLANS AND GUIDELINES

UDF PLANS AND GUIDELINES UDF PLANS AND GUIDELINES 5 Land Use Land Use Development Plan Plan no. 3 Land Use Development Mixed Use Retail / Leisure Residential Civic and Institutional Proposed Zoning Table Development Edges Plan

More information

0 9 Areas of Change 59

0 9 Areas of Change 59 09 Areas of Change 59 09 Areas of Change This section explores seven areas of change within Solihull Town Centre which provide practical interventions in order to deliver the emerging concepts outlined

More information

World Towns Agreement

World Towns Agreement World Towns Agreement A Public-Private-Social Vision for Urban Centres Sponsored by Developed with support from MISSION STATEMENT We, the delegates and online participants at the World Towns Leadership

More information

DRAFT WESTERN CITY DISTRICT PLAN PLANNING PRIORITIES AND ACTIONS

DRAFT WESTERN CITY DISTRICT PLAN PLANNING PRIORITIES AND ACTIONS Greater Sydney Commission DRAFT WESTERN CITY DISTRICT PLAN PLANNING PRIORITIES AND ACTIONS Issued: 26 OCTOBER 2017 Version: 1 Subject: Greater Sydney Region and District Plans This information note is

More information

The Master Plan Framework

The Master Plan Framework The Master Plan Framework The East Harbour Master Plan advances the development of 60 acres of former industrial lands east of the Don River. The Master Plan outlines a vision for a vibrant, transit-oriented

More information

elbridge Core Strategy

elbridge Core Strategy C elbridge Core Strategy Celbridge is designated as a Moderate Growth Town in the RPGs. The County Development Plan reinforces this designation in its settlement strategy. Moderate Growth Towns within

More information

intu Bromley Planning Summary Bringing more to Bromley February 2014

intu Bromley Planning Summary Bringing more to Bromley February 2014 intu Bromley Planning Summary February 2014 Bringing more to Bromley Contents Introduction 1 Description of the Proposals 2 Economic Benefits 4 Planning Policy 6 Cinema and Catering Assessment 7 Design

More information

Create Policy Options Draft Plan Plan Approval. Public Consultation Events. Phase 2

Create Policy Options Draft Plan Plan Approval. Public Consultation Events. Phase 2 Background Grandview-Woodland Community Plan In the spring of 2012, the City of Vancouver embarked on a comprehensive community planning program in the Grandview-Woodland neighbourhood. The process has

More information

DRAFT GREATER SYDNEY REGION PLAN OBJECTIVES, STRATEGIES AND ACTIONS

DRAFT GREATER SYDNEY REGION PLAN OBJECTIVES, STRATEGIES AND ACTIONS Greater Sydney Commission DRAFT GREATER SYDNEY REGION PLAN OBJECTIVES, STRATEGIES AND ACTIONS Issued: 26 OCTOBER 2017 Version: 1 Subject: Greater Sydney Region and District Plans This information note

More information

Scottish Natural Heritage. Better places for people and nature

Scottish Natural Heritage. Better places for people and nature Scottish Natural Heritage Better places for people and nature Contents Summary... 3 SNH approach... 5 Place-making in policy and practice... 6 Developing the contribution of the natural heritage to place-making...

More information

EFUF 2014 : Lausanne. Alan Simson Professor of Landscape Architecture + Urban Forestry Leeds Metropolitan University Green Streets Task Group

EFUF 2014 : Lausanne. Alan Simson Professor of Landscape Architecture + Urban Forestry Leeds Metropolitan University Green Streets Task Group EFUF 2014 : Lausanne Green Streets an innovative partnership project designed to enhance and extend the urban forestry associated with the public transport routes in the Leeds City Region Research into

More information

Cotswolds AONB Landscape Strategy and Guidelines. June 2016

Cotswolds AONB Landscape Strategy and Guidelines. June 2016 Cotswolds AONB Landscape Strategy and Guidelines June 2016 Cotswolds AONB Landscape Strategy and Guidelines Introduction The evolution of the landscape of the Cotswolds AONB is a result of the interaction

More information

Draft Eastern District Plan

Draft Eastern District Plan Draft Eastern District Plan Submission_id: 31238 Date of Lodgment: 13 Dec 2017 Origin of Submission: Online Organisation name: Turrulla Gardens Pty Ltd C/- Mecone Organisation type: Industry First name:

More information

PUBLIC REALM STRATEGY

PUBLIC REALM STRATEGY CONSULTATION DRAFT PUBLIC REALM STRATEGY Trenchard Street & Frogmore Street City Design Group Place Directorate Public Realm Strategy Trenchard Street & Frogmore Street Contents 1. Introduction 2. Understanding

More information

North District What we heard

North District What we heard What we heard Vision to 2056 and Priorities Governance and implementation Infrastructure and funding The vision for a metropolis of three cities, and the 30 minute city. Feedback emphasised: That for the

More information

REVISED DRAFT NORTH DISTRICT PLAN PLANNING PRIORITIES AND ACTIONS

REVISED DRAFT NORTH DISTRICT PLAN PLANNING PRIORITIES AND ACTIONS Greater Sydney Commission REVISED DRAFT NORTH DISTRICT PLAN PLANNING PRIORITIES AND ACTIONS Issued: 26 OCTOBER 2017 Version: 1 Subject: Greater Sydney Region and District Plans This information note is

More information

Chapter 2: OUTLINE PLANNING APPLICATION PROPOSALS. A New Garden Neighbourhood Matford Barton 17

Chapter 2: OUTLINE PLANNING APPLICATION PROPOSALS. A New Garden Neighbourhood Matford Barton 17 Chapter 2: OUTLINE PLANNING APPLICATION PROPOSALS A New Garden Neighbourhood Matford Barton 17 2.1. SUMMARY AND STATUS OF THE PROPOSALS 2.1.1. The parameter plans and associated wording in this chapter

More information

HS2 Hybrid Bill Petitioning. Summary of SMBC Asks 23/09/13. Background

HS2 Hybrid Bill Petitioning. Summary of SMBC Asks 23/09/13. Background Summary of SMBC Asks 23/09/13 Background The Council has a developed a significant number of asks and propositions for consideration by HS2 Ltd and Government throughout further development of the HS2

More information

The Tonsley Park Sustainable. Precinct

The Tonsley Park Sustainable. Precinct Planning Institute of Australia Economic Development Australia The Tonsley Park Sustainable Technologies Employment Precinct Len Piro 5 August 2010 Project Overview The Site SA Government, through the

More information

Town of Oakville Streetscape Strategy

Town of Oakville Streetscape Strategy Town of Oakville Streetscape Strategy Endorsed by PDC on February 10, 2014 (PD-011-14) Town of Oakville Streetscape Strategy [endorsed by PDC February 10, 2014] 0 Town of Oakville Streetscape Strategy

More information

City Regions Ireland

City Regions Ireland City Regions Ireland 01 CITY REGIONS IRELAND COMPRISES OF CORK CHAMBER, DUBLIN CHAMBER, LIMERICK CHAMBER, WATERFORD CHAMBER AND GALWAY CHAMBER, ALL MEMBERS OF CHAMBERS IRELAND. 5 CITIES 8 PRINCIPLES A

More information

2.0 Strategic Context 4

2.0 Strategic Context 4 2.0 Strategic Context 4 2.1 The Area Action Plan is a non-statutory plan, which forms a corporate policy document, expressing particular issues and areas of concern while also providing a vision for the

More information

Taking forward the All London Green Grid

Taking forward the All London Green Grid Taking forward the All London Green Grid Foreword Earlier this year, the Mayor published the All London Green Grid Supplementary Planning Guidance to the London Plan which set the vision, and framework,

More information

The University District envisions, in its neighborhood

The University District envisions, in its neighborhood Envisioning the University District Link Light Rail in Seattle s neighborhoods CIY OF SEALE CONCEP-LEVEL SAION AREA PLANNING RECOMMENDAION RESOLUION # 30165 EXHIBI L Vision 08.2000 he University District

More information

Plan Modification to Chapter B2 of the Auckland Unitary Plan(AUP) Operative in part (15 November 2016)

Plan Modification to Chapter B2 of the Auckland Unitary Plan(AUP) Operative in part (15 November 2016) UNITARY PLAN UPDATE REQUEST MEMORANDUM TO FROM Phill Reid Linley Wilkinson DATE 25 September 2018 SUBJECT Plan Modification to Chapter B2 of the Auckland Unitary Plan(AUP) Operative in part (15 November

More information

Woodbrook - Shanganagh

Woodbrook - Shanganagh Section 4: Key Sites Framework Strategy Woodbrook - Shanganagh Local Area Plan 2017-2023 4. Site Framework Strategies The Master Plans shall have regard to the thematic objectives under the LAP Development

More information

Making the case for Sustainable Transport Project Potential

Making the case for Sustainable Transport Project Potential Making the case for Sustainable Transport Project Potential The Structural Investment Fund (SIF) Strategy for Greater Lincolnshire identifies the barriers to growth identified by having poor transport

More information

01 the vision NEW LYNN IS WAITING FOR THE GREAT LEAP FORWARD

01 the vision NEW LYNN IS WAITING FOR THE GREAT LEAP FORWARD [A] FRAMEWORK 01 the vision 02 the framework 03 urban design principles 04 c o n t e x t 05 issues a n d o p p o r t u n i t i e s 06 creating a t.o.d. 07 key recommendations 08 seven strategic areas of

More information

an inspirational new destination residential commercial retail leisure education CW brochure FINAL version NEW.indd 3-4

an inspirational new destination residential commercial retail leisure education CW brochure FINAL version NEW.indd 3-4 an inspirational new destination residential commercial retail leisure education CW brochure FINAL version NEW.indd 3-4 01/09/2015 10:06 residential commercial retail leisure education Welcome to Chatham

More information

Paignton Neighbourhood Plan (Submission version 2017)

Paignton Neighbourhood Plan (Submission version 2017) Paignton Neighbourhood Plan (Submission version 2017) Introduction This brief statement covers the views of the TDA, only in relation to its role as adviser to the Council on delivery of town centre regeneration.

More information

1.0 PLANNING MARKHAM S FUTURE CONTENTS

1.0 PLANNING MARKHAM S FUTURE CONTENTS 1-1 Planning Markham s Future 1.0 PLANNING MARKHAM S FUTURE CONTENTS 1.1 THE PURPOSE OF THE OFFICIAL PLAN 1.2 THE MARKHAM CONTEXT 1.3 THE REGULATORY CONTEXT 1.3.1 Province of Ontario 1.3.2 York Region

More information

Appendix A: Retail Planning Assessment

Appendix A: Retail Planning Assessment Rotherham Town Centre Masterplan Appendix A: Retail Planning Assessment 139 Appendix A Rotherham Town Centre Masterplan Retail Planning Background and Policy Context 1. Introduction 1.1 The Masterplan

More information

Eastern City District Plan

Eastern City District Plan OUR GREATER SYDNEY 2056 Revised Draft Eastern City District Plan OVERVIEW Bayside Burwood Canada Bay City of Sydney Inner West Randwick Strathfield Waverley Woollahra Snapshot of the Eastern City District

More information

C. Westerly Creek Village & The Montview Corridor

C. Westerly Creek Village & The Montview Corridor C. Westerly Creek Village & The VISION Community Vision When the goals of the city are achieved Westerly Creek Village, a distinctive community defined by Montview Boulevard and Westerly Creek, is a strong

More information

ELK GROVE GENERAL PLAN VISION

ELK GROVE GENERAL PLAN VISION 2-1 CHAPTER 2: 2-2 CREATING OUR The Community Vision for Elk Grove, expressed through a Vision Statement and a series of Supporting Principles, is a declaration of the kind of community that Elk Grove

More information

Eastbourne Borough Council. Summary Proof of Evidence Of Barry John Cansfield BA (Hons), BTP, MRTPI on behalf of PRLP

Eastbourne Borough Council. Summary Proof of Evidence Of Barry John Cansfield BA (Hons), BTP, MRTPI on behalf of PRLP Eastbourne Borough Council (Arndale Centre and surrounding Land at Terminus Road, Sutton Road and Ashford Road) (Compulsory Purchase Order 2015) Section 226 (1)(a) of the Town and Country Planning Act

More information

1 Introduction. Chapter. In this chapter:

1 Introduction. Chapter. In this chapter: Chapter 1 Introduction In this chapter: 1.1 A Snapshot of the Region 1.2 Towards a Sustainable Region 1.3 The Provincial Context 1.4 Purpose and Organization The Regional Municipality of York Official

More information

Draft Western District Plan

Draft Western District Plan Powered by TCPDF (www.tcpdf.org) Draft Western District Plan Submission_id: 31440 Date of Lodgment: 15 Dec 2017 Origin of Submission: Online Organisation name: Goodman Property Services Australia Pty Ltd

More information

10.0 Open Space and Public Realm

10.0 Open Space and Public Realm 10.0 Open Space and Public Realm 10.0 Open Space and Public Realm The Public Open Space System is comprised of: outdoor spaces available for public use that are either publicly owned (e.g., parks and

More information

SUB AREA 3 CENTRAL STRATFORD AND SOUTHERN QUEEN ELIZABETH OLYMPIC PARK

SUB AREA 3 CENTRAL STRATFORD AND SOUTHERN QUEEN ELIZABETH OLYMPIC PARK 191 ADOPTED LOCAL PLAN: THE SUB AREAS SUB AREA 3 CENTRAL STRATFORD AND SOUTHERN QUEEN ELIZABETH OLYMPIC PARK SECTION 12 Vision VISION Central Stratford and Southern Queen Elizabeth Olympic Park will become

More information

I615. Westgate Precinct

I615. Westgate Precinct I615. Westgate Precinct I615.1. Precinct Description The Westgate Precinct is located approximately 18km west of the Auckland city centre. There are seven Sub-precincts in the Westgate Precinct: Sub-precinct

More information

DUBLIN DOCKLANDS MASTER PLAN AND RELATIONSHIP WITH OTHER PLANS

DUBLIN DOCKLANDS MASTER PLAN AND RELATIONSHIP WITH OTHER PLANS .1 National Policy and Programmes.1.1 Sustainable Development A Strategy for Ireland, 1997.1.2 National Climate Change Strategy, 2007-2012.1. National Development Plan 2007-201.1.4 National Spatial Strategy,

More information

Central City District What we heard

Central City District What we heard What we heard Vision to 2056 and Priorities Governance and implementation Infrastructure and funding The vision for a metropolis of three cities, and the 30 minute city. Feedback requested: Clearer communication

More information

97 Lea Bridge Road, Leyton, E10 7QL London Borough of Waltham Forest December 2015

97 Lea Bridge Road, Leyton, E10 7QL London Borough of Waltham Forest December 2015 97 Lea Bridge Road, Leyton, E10 7QL London Borough of Waltham Forest December 2015 Public Realm and Landscape Proposals LEA BRIDGE ROAD, WALTHAMSTOW Public Realm & Landscape Proposals BDP(90)RPT001 December

More information

(Y)OUR BROOMIELAW SUMMARY DOCUMENT

(Y)OUR BROOMIELAW SUMMARY DOCUMENT (Y)OUR BROOMIELAW SUMMARY DOCUMENT Glasgow City Centre District Regeneration Frameworks Broomielaw District August 2018 Broomielaw District Regeneration Framework as defined in Glasgow City Centre Strategy

More information

OUR AREA SECTION 02 I NEXT PAGE. 2.1 This section sets the scene in regard to the role of the Legacy Corporation and the baseline

OUR AREA SECTION 02 I NEXT PAGE. 2.1 This section sets the scene in regard to the role of the Legacy Corporation and the baseline 7 ADOPTED LOCAL PLAN SECTION 02 2.1 This section sets the scene in regard to the role of the Legacy Corporation and the baseline position of the Local Plan. It sets out the historical context and current

More information

BROOKLYN PARK / 85TH AVE LRT STATION CDI DEVELOPMENT GUIDELINES DRAFT

BROOKLYN PARK / 85TH AVE LRT STATION CDI DEVELOPMENT GUIDELINES DRAFT August 2018 Page intentionally left blank The Brooklyn Park Library adjacent to the 85th Ave LRT Station Area. OVERVIEW The Blue Line LRT Extension / Bottineau corridor offers a unique opportunity to leverage

More information

3. Endorse the LRT vision in transforming Surrey into Connected-Complete-Livable communities, and more specifically, the official vision statement:

3. Endorse the LRT vision in transforming Surrey into Connected-Complete-Livable communities, and more specifically, the official vision statement: CORPORATE REPORT NO: R038 COUNCIL DATE: February 20, 2017 REGULAR COUNCIL TO: Mayor & Council DATE: February 16, 2017 FROM: General Manager, Engineering FILE: 8740-01 SUBJECT: Surrey Light Rail Transit

More information

Introduction to MP3. MP3 H4 Park Central (North)

Introduction to MP3. MP3 H4 Park Central (North) MP H4 Park Central (North) Introduction to MP A visualisation of the Illustrative Masterplan with MP shaded in blue MP is the third phase of the Elephant Park regeneration and is bounded by on the north,

More information

Municipal Development Plan 2013

Municipal Development Plan 2013 UNIQUELY STONY PLAIN: Municipal Development Plan 2013 Quick Reference Guide What is a Municipal Development Plan (MDP)? The Town s highest-level planning document Sets the long-term vision and key themes

More information

Appendix A. Planning Processes. Introduction

Appendix A. Planning Processes. Introduction 1 Planning Processes Introduction This appendix outlines a number of planning processes which are used in the Auckland Region to support the effective management of development in the region s rural and

More information

Spatial and Economic Master Planning. Resilient, healthy and happy places to live, work and learn

Spatial and Economic Master Planning. Resilient, healthy and happy places to live, work and learn Spatial and Economic Master Planning Resilient, healthy and happy places to live, work and learn Leisure Integrated planning expertise Economy Driven Design By 2050, 70% of the world s population will

More information

North Somerset Council Local Development Framework

North Somerset Council Local Development Framework North Somerset Council Local Development Framework Sites and Policies Development Plan Document Evidence Paper Re-opening Portishead Railway Line and Options for the Location of Portishead Railway Station

More information

Rochford District Council Allocations Development Plan Document: Discussion and Consultation Document Sustainability Appraisal

Rochford District Council Allocations Development Plan Document: Discussion and Consultation Document Sustainability Appraisal Option SWH1 Balanced Communities Option SWH1 1 To ensure the delivery of high quality sustainable communities where people want to live and work Will it ensure the phasing of infrastructure, including

More information

Newcourt Masterplan. November Exeter Local Development Framework

Newcourt Masterplan. November Exeter Local Development Framework Newcourt Masterplan November 2010 Exeter Local Development Framework Background The Exeter Core Strategy Proposed Submission sets out the vision, objectives and strategy for the development of Exeter up

More information

South District Plan OVERVIEW

South District Plan OVERVIEW OUR GREATER SYDNEY 2056 Revised Draft South District Plan OVERVIEW Canterbury-Bankstown Georges River Sutherland Snapshot of the South District today and into the future The Greater Sydney Commission acknowledges

More information

Phase 1 : Understanding the Campus Context. Phase 2 : APPROACHES - Alternates & Preferred Plan

Phase 1 : Understanding the Campus Context. Phase 2 : APPROACHES - Alternates & Preferred Plan Introduction MASTER PLAN PURPOSE WHY A CAMPUS MASTER PLAN? The purpose of the Master Plan at the University of Illinois at Chicago is to translate UIC s strategic goals and objectives into a compelling

More information

Consultation Response to Lisburn and Castlereagh City Council LDP Preferred Options Paper (POP)

Consultation Response to Lisburn and Castlereagh City Council LDP Preferred Options Paper (POP) Consultation Response to Lisburn and Castlereagh City Council LDP Preferred Options Paper (POP) Retail NI welcomes the opportunity to respond to the Council s Preferred Options Paper (POP) consultation

More information

South District What we heard

South District What we heard What we heard Vision to 2056 and Priorities Governance and implementation Infrastructure and funding Feedback supported: The vision for a metropolis of three cities, but emphasised the importance of infrastructure

More information

Corridor Vision. 1Pursue Minnehaha-Hiawatha Community Works Project. Mission of Hennepin County Community Works Program

Corridor Vision. 1Pursue Minnehaha-Hiawatha Community Works Project. Mission of Hennepin County Community Works Program 1Pursue Minnehaha-Hiawatha Community Works Project Minnehaha-Hiawatha Community Works is a project within the Hennepin Community Works (HCW) program. The mission of the HCW program is to enhance how the

More information

building activity into new devevelopment

building activity into new devevelopment active design case study essex design guide: building activity into new devevelopment active design principles in action: 1. ACTIVITY FOR ALL 2. WALKABLE COMMUNITIES 3. CONNECTED WALKING & CYCLING ROUTES

More information

Submission to the Kildare County Council Development Plan North Kildare Chamber. Executive Summary

Submission to the Kildare County Council Development Plan North Kildare Chamber. Executive Summary ` 28 th May 2015 Submission to the Kildare County Council Development Plan 2017-2023 North Kildare Chamber Executive Summary North Kildare Chamber s mission is to work with businesses, community groups,

More information

Growth Point Connectivity: Executive Summary

Growth Point Connectivity: Executive Summary Growth Point Connectivity: Executive Summary Background to the study This study addresses issues in the rural west of the Region. It focuses on Telford, Shrewsbury and Hereford, which as Growth Points

More information

Landscape Architecture & Urban Design

Landscape Architecture & Urban Design Landscape Architecture & Urban Design Delivering excellence in the built environment What we do Landscape architecture Urban design Masterplanning Public consultation Design briefs Design codes Conservation

More information

Horwood Map of London, Westminster & Southwark First edition

Horwood Map of London, Westminster & Southwark First edition Barratt London is developing plans in tandem with Southwark Council and TfL to transform the southern end of Blackfriars Road. The residential-led, mixed-use scheme will deliver new private and affordable

More information

A Strategic Regeneration Initiative Manchester City Centre

A Strategic Regeneration Initiative Manchester City Centre A Strategic Regeneration Initiative Manchester City Centre May 2009 Introduction The Vision Where we are Where we are going How we get there A Strategic Regeneration Initiative / Manchester City Centre

More information

TRANSPORT ARCHITECTURE. JOHN McASLAN + PARTNERS

TRANSPORT ARCHITECTURE. JOHN McASLAN + PARTNERS TRANSPORT ARCHITECTURE JOHN McASLAN + PARTNERS The practice has, from the outset, been involved in significant infrastructure projects. Its first rail scheme, the redevelopment of Redhill Station in Surrey,

More information

38 Queen s University Campus Master Plan Part 1

38 Queen s University Campus Master Plan Part 1 38 Queen s University Campus Master Plan Part 1 46 The Campus at the City Scale Chapter 4 The Campus at the City Scale 39 Queen s is an urban University centrally located in Kingston. Decisions made by

More information

SECTION ONE North East Industrial Zone Design Guide Palmerston North City Council June 2004

SECTION ONE North East Industrial Zone Design Guide Palmerston North City Council June 2004 SECTION ONE North East Industrial Zone Design Guide Palmerston North City Council June 2004 young heart easy living 1 Preface Industrial areas are a very important component of the economic well-being

More information

Pioneering the Sustainable Future of Pakistan. A New Destination of Islamabad

Pioneering the Sustainable Future of Pakistan. A New Destination of Islamabad Pioneering the Sustainable Future of Pakistan A New Destination of Islamabad A New Destination of Islamabad C A P I TAL S M A R T CIT Y ISL A M A B A D, PAKISTA N CAPITAL SMART CITY ISLAMABAD C A P I TAL

More information

[PLANNING RATIONALE] For Site Plan Control and Lifting of Holding Zone By-Law 101 Champagne Avenue. May 23, 2014

[PLANNING RATIONALE] For Site Plan Control and Lifting of Holding Zone By-Law 101 Champagne Avenue. May 23, 2014 [PLANNING RATIONALE] For Site Plan Control and Lifting of Holding Zone By-Law 101 Champagne Avenue May 23, 2014 Contents 1.0 Introduction... 2 2.0 Site Context... 2 2.1 Adjacent Uses... 2 Figure 1: Site

More information

Inspiring Technovation

Inspiring Technovation 1 2 Table of content List of table and figures... Executive summary... 1. Introduction... 2. Material and methods... 3. Results... 3.1 Today s facts about Versailles: a diagnostic approach... 3.1 Vision

More information

Midtown Greenway Land Use and Development Plan Executive Summary

Midtown Greenway Land Use and Development Plan Executive Summary Midtown Greenway Land Use and Development Plan Executive Summary Introduction The Midtown Greenway Land Use and Development Plan sets policy direction for land use and development in the Midtown Greenway

More information

13 THORNHILL YONGE STREET STUDY IMPLEMENTATION CITY OF VAUGHAN OPA 669 AND TOWN OF MARKHAM OPA 154

13 THORNHILL YONGE STREET STUDY IMPLEMENTATION CITY OF VAUGHAN OPA 669 AND TOWN OF MARKHAM OPA 154 13 THORNHILL YONGE STREET STUDY IMPLEMENTATION CITY OF VAUGHAN OPA 669 AND TOWN OF MARKHAM OPA 154 The Planning and Economic Development Committee recommends the adoption of the recommendations contained

More information

A VISION FOR THE FUTURE

A VISION FOR THE FUTURE A VISION FOR THE FUTURE Doncaster Urban Centre Masterplan Foreword CREATING A SUCCESSFUL URBAN CENTRE THE MASTERPLAN Doncaster is an ambitious borough and very few places in the UK come close to us in

More information

TOMORROW S GARDEN VILLAGE

TOMORROW S GARDEN VILLAGE TOMORROW S GARDEN VILLAGE TOMORROW S GARDEN VILLAGE Context This concept brochure sets out a vision for a new community at Lighthorne Heath. Government support for innovative planning solutions, such

More information

RE-Imagining the Downtown Colorado Springs Master Plan

RE-Imagining the Downtown Colorado Springs Master Plan RE-Imagining the Downtown Colorado Springs Master Plan 2016 APA Colorado State Conference October 25, 2016 Overview 8:00 Welcome, Introductions, and Overview 8:15 Downtown s Planning History 8:30 A Market

More information

Chapter 3 Core Strategy

Chapter 3 Core Strategy Chapter 3 Core Strategy 3.0 Introduction The core strategy sets out how the development objectives in the Development Plan are consistent with the National Spatial Strategy and the Regional Planning Guidelines.

More information

Preliminary Plan Framework: Vision and Goals

Preliminary Plan Framework: Vision and Goals Preliminary Plan Framework: Vision and Goals Draft: May 2015 Introduction Since the Town of Milliken s comprehensive plan was last updated in 2010, the community was heavily impacted by the 2013 flood,

More information

ISIS BCC MADE. Warwick Bar Development in Eastside Birmingham. Artist s Brief

ISIS BCC MADE. Warwick Bar Development in Eastside Birmingham. Artist s Brief ISIS BCC MADE Warwick Bar Development in Eastside Birmingham Artist s Brief Grand Union Canal towards Warwick Bar and city centre INTRODUCTION A lead artist is being sought to join the masterplanning team

More information