ENVIRONMENTAL IMPACT ASSESSMENT

Size: px
Start display at page:

Download "ENVIRONMENTAL IMPACT ASSESSMENT"

Transcription

1 ENVIRONMENTAL IMPACT ASSESSMENT NOTICE OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE SARATOGA VEGETATION CLEARING SECTION 24G ON PORTION 4 OF THE FARM KLAAS VOOGDS RIVIER NO. 40, ROBERTSON, WESTERN CAPE. 1. PURPOSE OF THIS DOCUMENT BACKGROUND INFORMATION DOCUMENT (BID) AND INVITATION TO PARTICIPATE 12 June 2016 DEA&DP REFERENCE No: 14/2/1/2/B1/14/0011/16 The purpose of this document is to: Provide stakeholders with information about the illegal vegetation clearing and a proposed blueberry orchard on Portion 4 of Farm 40, Klaas Voogds Rivier, Robertson, Western Cape. Introduce and explain the Section 24G and Public Participation process to be followed for the proposed development, in terms of applicable environmental legislation (National Environmental Management Act (NEMA), (Act No.107 of 1998), as amended; Invite all stakeholders to register between the 12 th of July 2016 and 15 th of August 2016 as an Interested and Affected Party for the proposed development; 2. PROJECT DESCRIPTION Two patches of indigenous vegetation were illegally cleared on portion 4 of farm 40 Klaas Voodgs Rivier (Saratoga Farm), which is privately owned by the client Mr. Marc Doms, and is located approximately 10 km north east of the town of Robertson and approximately 8.4 km north west of Ashton. The farm is located outside the urban edge (appropriately zoned agricultural zone 1) and falls under the Langeberg Local Municipality. Saratoga farm is a fully functioning farm specializing in the growing of blueberries under tunnels. The land use of the surrounding area is also predominantly for agricultural purposes. The topography of the site is can be described as an open valley surrounded by the Langeberg-Wes Mountain range. Mr. Doms had planned on clearing two patches of indigenous vegetation adjacent to an existing agricultural field (to the north and to the south side of the existing field) with the aim to enlarge the field for the preparation of an additional blueberry orchard. P.O. Box

2 The orchard footprint has been cleared in its entirety, however an assessment of the vegetation adjacent to the clearing perimeter was done by a botanical specialist, Dr Dave McDonald. This indicated that the vegetation type was likely incorrectly mapped as Breede Shale Renosterveld (which is listed as Vulnerable) and is more likely that of South Langeberg Sandstone Fynbos (which listed as Least Threatened). Some alien species were also located in the area adjacent to where the clearing had occurred. The site does not fall within a CBA, no plant species of conservation concern were found within the undisturbed area (adjacent to the site) and the clearing was confined to the periphery and did not introduce any fragmentation. It is therefore confidently assumed that the impacts can be considered highly insignificant or LOW NEGATIVE. The cleared areas are however also mapped as part of the Breede Alluvium Renosterveld threatened ecosystem (listed as vulnerable), however no threatened plant species or species of conservation concern were found within this ecosystem adjacent to the site, therefore possibly also erroneously mapped. The construction of the blueberry orchard is not yet complete and will only commence once environmental authorisation is granted. This will include the installation of infrastructure (irrigation and tunnelling) and the planting of a crop of blueberries. This blueberry orchard will have positive socio-economic impacts, by creating temporary and permanent jobs, and will not result in any further environmental damage. No cultural or heritage resources were impacted upon by the vegetation clearing and are not expected to occur during the construction of the proposed blueberry orchard. No direct rectification is possible as the footprint has been cleared in its entirety, however a conservation offset agreement could be arranged to have non-arable areas on the farm assigned for conservation under a biodiversity conservation agreement. Taking the above mentioned vegetation clearing and the proposed blueberry orchard into account, the following legislation was considered: NATIONAL ENVIRONMENTAL MANAGEMENT ACT (Act No. 107 of 1998), AS AMENDED Environmental Assessment The National Environmental Management Act (NEMA) (Act No. 107 of 1998) identifies the clearing of indigenous vegetation as an activity that may have detrimental effects on the environment with the following listed activities: Government Notice No. R.983 of 2014: Activity 27 The clearance of an area of 1 hectares or more, but less than 20 hectares of indigenous vegetation, except where such clearance of indigenous vegetation is required for the undertaking of a linear activity; or maintenance purposes undertaken in accordance with a maintenance management plan. Activity 67 Phased activities for all activities: (i) listed in this Notice, which commenced on or after the effective date of this Notice; or (ii) similarly listed in any of the previous NEMA notices, which commenced on or after the effective date of such previous NEMA Notices; where any phase of the activity may be below a threshold P.O. Box

3 but where a combination of the phases, including expansions or extensions, will exceed a specified threshold; excluding the following activities listed in this Notice: 17(i)(a-d); 17(ii)(a-d); 17(iii)(a-d); 17(iv)(ad); 17(v)(a-d); 20; 21; 22; 24(i); 29; 30; 31; 32; 34; 54(i)(a-d); 54(ii)(a-d); 54(iii)(a-d); 54(iv)(a-d); 54(v)(a-d); 55; 61; 62; 64 and 65. Government Notice R. 985 of 2014 Activity 12 The clearance of an area of 300 square metres or more of indigenous vegetation except where such clearance of indigenous vegetation is required for maintenance purposes undertaken in accordance with a maintenance management plan. In Eastern Cape, Free State, Gauteng, Limpopo, North West and Western Cape provinces: (i) within any critically endangered or endangered ecosystem listed in terms of section 52 of the NEMBA or prior to the publication of such a list, within an area that has been identified as critically endangered in the National Spatial Biodiversity Assessment 2004; (ii) within critical biodiversity areas identified in bioregional plans; (iii) within the littoral active zone or 100 metres inland from high water mark of the sea or an estuarine functional zone, whichever distance is the greater, excluding where such removal will occur behind the development setback line on erven in urban areas; or (iv) on land, where, at the time of the coming into effect of this Notice or thereafter such land was zoned open space, conservation or had an equivalent zoning. Definition of an Environmental Impact Assessment (EIA) An environmental impact assessment is a good planning tool to assist in the identification, evaluation and assessment of potential positive and negative impacts of a proposed development on the environment. It also recommends ways to avoid or reduce negative impacts, and ensure that developments are sustainable without affecting people s lives and the environment adversely. As mentioned, an EIA is undertaken in terms of the NEMA (Act No 107 of 1998) as amended, and the EIA Regulations. 3. POTENTIAL ENVIRONMENTAL ISSUES Potential environmental issues for the proposed construction of the blueberry orchard will be addressed in the assessment include inter alia: Impact on fauna and flora: Indigenous vegetation on either side of an existing agricultural field was cleared in its entirety. The vegetation is however least threatened and not endangered in any way. The clearing was confined to the periphery and did not introduce any fragmentation. No threatened plant species or species of conservation concern were found adjacent to the site. Therefore these impacts can be considered minimal and have already occurred, however no further impacts on any fauna or flora are expected during the construction and maintenance of the proposed blueberry orchard. Noise pollution: P.O. Box

4 The construction/installation of a new blueberry orchard will result in minimal noise impacts as these impacts are expected to be temporary in nature. This noise will be similar to the current level of noise experienced on the farm. Heritage impact: No heritage resources were impacted by the vegetation clearing and are not expected to occur during the construction of the orchard infrastructure. This is because a large portion of the site had already been disturbed by agricultural activities. Heritage Western Cape has issued a positive Record of Decision on the 30 th of May 2016, to permit the proposed construction of a new orchard. Visual impact: There will be some visual impacts during the construction phase but this will only be temporary. The visual impact during the operational phase is not expected to be significant since the site is bounded by and in close proximity to similar existing orchards. The site is also located within a valley meaning that it will not be visible from afar. Heritage Western Cape has issued a positive Record of Decision on the 30 th of May 2016, to permit the proposed construction of a new orchard. As mentioned, the Environmental Impact Assessment Report will identify measures to reduce identified negative impacts, and optimise positive impacts. 4. PUBLIC PARTICIPATION In terms of the NEMA, public participation forms an integral part of the environmental assessment process. The public participation process provides people who may be affected by the proposed development with an opportunity to provide comment and to raise issues of concern about the project or to make suggestions that may result in enhanced benefits for the project. Comments and issues raised during the public participation process will be captured, evaluated and included in a Comment and Response Report. These issues will be addressed and included in the final Section 24G Environmental Impact Assessment Report, which will be submitted to the Department of Environmental Affairs and Development Planning (DEA&DP). 5. DELIVERABLES The environmental assessment will culminate in the compilation of a Section 24G Environmental Impact Assessment Report and an Environmental Management Plan. These documents will be submitted to the Department of Environmental Affairs and Development Planning (DEA&DP), who are the regulatory authority responsible for the review of these reports within the Western Cape. The DEA&DP has to reach a decision as to whether, and under what conditions, the project may proceed, based on environmental considerations. An environmental authorisation will be issued based on the information provided in the Section 24G Environmental Impact Assessment Report and the Environmental Management Plan. Interested and Affected Parties who have registered will be notified of the environmental authorisation when granted. P.O. Box

5 6. TIMEFRAMES Activity The table below provides an indication of the proposed timeframes for the project. Estimated Timeframe Compilation of Notice of Intent to Develop (NID) (HWC) 01 May May 2016 Submission of NID 13 May 2016 Heritage Western Cape review of NID May 2016 Specialist assessments (freshwater and botanical) 15 May 29 June 2016 Compilation of Section 24G Application 16 May 3 June 2016 Submission of S 24G Application to Department of Environmental Affairs & Development Planning (DEA&DP) 3 June 2016 Review of Application by DEA&DP 3 June 29 June 2016 Compilation of Draft S 24G Report and Environmental Management Plan (EMP) 3 June 8 July 2016 Submission of Draft S 24G Report and EMP to DEA&DP 11 July st Public Participation Process (30 days) 12 July 15 August 2016 Amend Draft S 24G and EMP, Include Possible Specialist Assessments August nd Public Participation Process on (30 days) September October 2016 Amend Draft Final S 24G and EMP and submit Finals to decision-making Authority for a decision October 2016 DEA&DP Review of Final S 24G and EMP October January 2017 Authorisation January 2017 Notify all Interested and Affected Parties January 2017 P.O. Box

6 7. INVITATION TO PARTICIPATE Guillaume Nel Environmental Consultants were appointed as an independent environmental consultancy by Mr. Marc Doms to facilitate the environmental impact assessment and public participation process for the requirements of NEMA Section 24G for the illegal clearing of indigenous vegetation and subsequent construction of a new orchard. A hardcopy of the first Draft Section 24G Environmental Impact Assessment Report will be available at the Robertson public library (Ms. Christa Joubert; Tel: ) and an electronic copy will also be available on GNEC s website ( We would like to invite and encourage all stakeholders to complete and return the enclosed registration sheet and submit any written comments to: GNEC Att: Ruben Schoombie P.O. Box Tel: Fax: ruben@gnec.co.za GNEC Ref No: DEA&DP Ref No: 14/2/1/2/B1/14/0011/16 Please submit the registration sheet to GNEC by no later than Monday the 15 th of August P.O. Box

7 NOTICE OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE SARATOGA VEGETATION CLEARING SECTION 24G ON PORTION 4 OF THE FARM KLAAS VOOGDS RIVIER NO. 40, ROBERTSON, WESTERN CAPE. REGISTRATION AND COMMENT SHEET 12 July 2016 DEA&DP REFERENCE No: 14/2/1/2/B1/14/0011/16 GNEC REF: Title Name and Surname Company Name/Interest Postal-or-Residential Address Area Postal Code Tel: Cell Phone Fax: Address Please indicate you preferred method of communication (Please indicate with an X) Fax Post Comments (You are welcome to attach more sheets if necessary (Your comments will be considered in the Section 24G EIA process) Please provide details of any other person/company whom you would like us to add to our mailing list Title Name and Surname Company Name Tel: Fax No: Please complete and return to GNEC by no later than Monday 15 th August 2016 Attention Ruben Schoombie P.O. Box 2632,, 7620 Tel: , Fax: ruben@gnec.co.za Thank you for your participation P.O. Box

Fabriek Street 45 Paarl. P.O. Box 2632 Paarl Tel: Cell:

Fabriek Street 45 Paarl. P.O. Box 2632 Paarl Tel: Cell: 11 July 2016 Organisation: Department of Environmental Affairs and Development Planning Attention: Mr. Shafeeq Mallick NOTICE OF FIRST PUBLIC PARTICIPATION PERIOD: 12 July 2016 15 August 2016 GNEC Code:

More information

RIVER MAINTENANCE MANAGEMENT PLAN APPLICATION

RIVER MAINTENANCE MANAGEMENT PLAN APPLICATION RIVER MAINTENANCE MANAGEMENT PLAN APPLICATION NOTICE OF PUBLIC PARTICIPATION PERIOD OF A RIVER MAINTENANCE MAANGEMENT PLAN (RMMP) FOR THE PROPOSED MAINTENANCE OF THE KM 8.920 CULVERT, WAARBURGH ROAD, PAARL,

More information

BASIC ASSESSMENT PROCESS

BASIC ASSESSMENT PROCESS BASIC ASSESSMENT PROCESS NOTICE OF A BASIC ASSESSMENT PROCESS FOR THE PROPOSED MIXED USE DEVELOPMENT ON THE REMAINDER OF PORTION 2, REMAINDER OF PORTION 7, PORTION 7, REMAINDER OF PORTION 9, REMAINDER

More information

ENVIRONMENTAL IMPACT ASSESSMENT

ENVIRONMENTAL IMPACT ASSESSMENT ENVIRONMENTAL IMPACT ASSESSMENT NOTICE OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED HAASENDAL DEVELOPMENT AND KUILS RIVER GOLF COURSE RE-DEVELOPMENT ON ERF 23580, ERF 23579, ERF 23582, ERF

More information

BACKGROUND INFORMATION DOCUMENT (BID) AND INVITATION TO PARTICIPATE

BACKGROUND INFORMATION DOCUMENT (BID) AND INVITATION TO PARTICIPATE To: Interested and Affected Parties 2 October 2017 NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED DEVELOPMENT OF RESIDENTIAL HOUSING ON PORTION 56 OF THE FARM CHELSEA NO. 25,

More information

ENVIRONMENTAL IMPACT ASSESSMENT

ENVIRONMENTAL IMPACT ASSESSMENT ENVIRONMENTAL IMPACT ASSESSMENT NOTICE OF APPLICATION FOR AMENDMENT OF AN ENVIRONMENTAL AUTHORISATION FOR THE HAASENDAL DEVELOPMENT ON PORTIONS 1, 11, 26, 30, 34, 58, AND 87 OF FARM HAASENDAL NO. 222,

More information

Attention: Interested and Affected Party (I&AP) Commenting Period: 22 November January 2018 GNEC Code: 20327

Attention: Interested and Affected Party (I&AP) Commenting Period: 22 November January 2018 GNEC Code: 20327 22 November 2017 Attention: Interested and Affected Party (I&AP) Commenting Period: 22 November 2017 15 January 2018 GNEC Code: 20327 Dear Interested and Affected Party INFORMING START OF 30 DAY PUBLIC

More information

Cape Environmental Assessment Practitioners(Pty)

Cape Environmental Assessment Practitioners(Pty) BACKGROUND INFORMATION DOCUMENT (BID) Introduction Cape Environmental Assessment Practitioners(Pty) Ltd Reg. No. 2008/004627/07 Telephone: (044) 874 0365 First Floor, Eagles View Building Facsimile: (044)

More information

Fabriek Street 45 Paarl. P.O. Box 2632 Paarl Tel: Cell:

Fabriek Street 45 Paarl. P.O. Box 2632 Paarl Tel: Cell: 8 March 2018 Department: Department of Environmental Affairs and Development Planning Attention: Ms Bernadette Osborne NOTICE OF FIRST PUBLIC PARTICIPATION PERIOD: 8 March 2018 18 April 2018 GNEC Code:

More information

BACKGROUND INFORMATION DOCUMENT:

BACKGROUND INFORMATION DOCUMENT: BACKGROUND INFORMATION DOCUMENT: Proposed Construction of Mpophomeni Shopping Centre, Umgungundlovu District Municipality, KZN A Project of Dymatron (Pty) Ltd 21 NOVEMBER 2014 BID DOCUMENT DESCRIPTION

More information

BASIC ASSESSMENT REPORT. Background Information Document

BASIC ASSESSMENT REPORT. Background Information Document BASIC ASSESSMENT REPORT Background Information Document BASIC ASSESSMENT FOR THE PROPOSED LUIPERDSHOEK 33 KV POWER LINE PROJECT TO BE LOCATED NORTH OF THE TOWN OF POFADDER IN THE NORTHERN CAPE (DEA Ref

More information

BACKGROUND INFORMATION DOCUMENT

BACKGROUND INFORMATION DOCUMENT BACKGROUND INFORMATION DOCUMENT PROPOSED UPGRADING OF THE N2 NATIONAL ROAD FROM KRAAIBOSCH TO DIE VLEIE BASIC ENVIRONMENTAL IMPACT ASSESSMENT The South African National Roads Agency Society Limited (SANRAL)

More information

BASIC ASSESSMENT PROCESS THE PROPOSED CANELANDS EXTENSION, KWAZULU-NATAL KZN DAEA REF NO: DM/0031/2012 BACKGROUND INFORMATION DOCUMENT AUGUST 2012

BASIC ASSESSMENT PROCESS THE PROPOSED CANELANDS EXTENSION, KWAZULU-NATAL KZN DAEA REF NO: DM/0031/2012 BACKGROUND INFORMATION DOCUMENT AUGUST 2012 BASIC ASSESSMENT PROCESS THE PROPOSED CANELANDS EXTENSION, KWAZULU-NATAL KZN DAEA REF NO: DM/0031/2012 BACKGROUND INFORMATION DOCUMENT AUGUST 2012 WHAT DOES THIS DOCUMENT TELL YOU? This document aims to

More information

PURPOSE OF MEETING MEETING GUIDELINES PROJECT BACKGROUND ESKOM CLOCOLAN-FICKSBURG 88 KV POWERLINE, FREE STATE

PURPOSE OF MEETING MEETING GUIDELINES PROJECT BACKGROUND ESKOM CLOCOLAN-FICKSBURG 88 KV POWERLINE, FREE STATE ESKOM CLOCOLAN-FICKSBURG 88 KV POWERLINE, FREE STATE DRAFT BASIC ASSESSMENT REPORT PUBLIC REVIEW LANDOWNERS MEETING FICKSBURG 23 JULY 2013 T his project is being conducted on behalf of Eskom PRESENTATION

More information

The Jigsaw: Legal Instruments for Biodiversity Planning in South Africa

The Jigsaw: Legal Instruments for Biodiversity Planning in South Africa The Jigsaw: Legal Instruments for Biodiversity Planning in South Africa Annual Conference, Environmental Law Association AUGUST 2012 Dr. Marie Parramon-Gurney Head of Programmes: Sustainability and Development

More information

TSHWANE STRENGTHENING PROJECT PHASE 1, GAUTENG PROVINCE: Draft Scoping Report: Apollo - Verwoerdburg July 2009

TSHWANE STRENGTHENING PROJECT PHASE 1, GAUTENG PROVINCE: Draft Scoping Report: Apollo - Verwoerdburg July 2009 APPROACH TO UNDERTAKING THE ENVIRONMENTAL SCOPING STUDY CHAPTER 3 An Environmental Impact Assessment (EIA) process refers to that process (as per the EIA Regulations) which involves the identification

More information

!"#"$%&'"()*%+*,*-.%/"0.%(,$*&$,(*+%/*)1"* 2"314314("*!.2)/.5)* 0/%-$"/2!,$*+./"*2),).%(*-%,/!/%%'6*78*',/51*9:7;*

!#$%&'()*%+*,*-.%/0.%(,$*&$,(*+%/*)1* 2314314(*!.2)/.5)* 0/%-$/2!,$*+./*2),).%(*-%,/!/%%'6*78*',/51*9:7;* !"#"$%&'"()*%+*,*-.%/"0.%(,$*&$,(*+%/*)1"* 2"314314("*!.2)/.5)* 0/%-$"/2!,$*+./"*2),).%(*-%,/!/%%'6*78*',/51*9:7;* Meeting Agenda Item Discussion Item Presenter 1. Opening and Welcome 2. Introductions

More information

Quick Introduction to Biodiversity Planning in South Africa

Quick Introduction to Biodiversity Planning in South Africa Quick Introduction to Biodiversity Planning in South Africa BGIS training UWC December 2013 Fahiema Daniels and Jeffrey Manuel Biodiversity Planning and Mainstreaming j.manuel@sanbi.org.za Acknowledgements:

More information

Anglo American Platinum; Mogalakwena Mine: Construction of Bridge and Gravel Road. Consultation with community members 26 July 2016

Anglo American Platinum; Mogalakwena Mine: Construction of Bridge and Gravel Road. Consultation with community members 26 July 2016 Anglo American Platinum; Mogalakwena Mine: Construction of Bridge and Gravel Road Consultation with community members 26 July 2016 AGENDA Welcome and introduction. Meeting protocol. Purpose of the meeting.

More information

Our Constitutional imperative

Our Constitutional imperative PARLIAMENT: PUBLIC HEARINGS EFFICACY OF SOUTH AFRICA'S ENVIRONMENTAL IMPACT ASSESSMENT (EIA) REGIME Henri Fortuin Cape Town 29July 2013 Our Constitutional imperative Section 24 of our Constitution gives

More information

Reg. No. 2008/004627/07 VAT No Facsimile: (044) Progress Street, George Web:

Reg. No. 2008/004627/07 VAT No Facsimile: (044) Progress Street, George Web: C ape E nvironmental A ssessment P ractitioners (Pty) Ltd Reg. No. 2008/004627/07 VAT No 4720248386 Telephone: (044) 4) 874 0365 1 Floor Eagles View Building Facsimile: (044) 874 0432 5 Progress Street,

More information

PUBLIC CONSULTATION MACROBERT INCORPORATED GREENWAY FARMS (PTY) LTD BOKPOORT OPERATIONS INTEGRATED WATER USE LICENCE APPLICATION

PUBLIC CONSULTATION MACROBERT INCORPORATED GREENWAY FARMS (PTY) LTD BOKPOORT OPERATIONS INTEGRATED WATER USE LICENCE APPLICATION MACROBERT INCORPORATED GREENWAY FARMS (PTY) LTD BOKPOORT OPERATIONS INTEGRATED WATER USE LICENCE APPLICATION Report: JW35/16/F481 - Rev 2 PUBLIC CONSULTATION APPENDIX E - Table of Contents E.1 Minutes

More information

PROPOSED GARDEN CITY NEW TOWN DEVELOPMENT, KRAAIFONTEIN DRAFT ENVIRONMENTAL IMPACT REPORT Summary Document

PROPOSED GARDEN CITY NEW TOWN DEVELOPMENT, KRAAIFONTEIN DRAFT ENVIRONMENTAL IMPACT REPORT Summary Document 1 PROPOSED GARDEN CITY NEW TOWN DEVELOPMENT, KRAAIFONTEIN DRAFT ENVIRONMENTAL IMPACT REPORT Summary Document What is an Environmental Impact Assessment? Garden Cities Incorporated Association Not For Gain

More information

REDZ & POWER CORRIDOR GAZETTING. 25 July Environmental Advisory Services

REDZ & POWER CORRIDOR GAZETTING. 25 July Environmental Advisory Services REDZ & POWER CORRIDOR GAZETTING 25 July 2017 Environmental Advisory Services PURPOSE To provide general progress on the REDZs and Power corridor gazetting process To provide a range of comments received

More information

PHASE 1 ARCHAEOLOGICAL IMPACT ASSESSMENT PROPOSED DEVELOPMENT ERF 3 ROBERTSON WESTERN CAPE PROVINCE

PHASE 1 ARCHAEOLOGICAL IMPACT ASSESSMENT PROPOSED DEVELOPMENT ERF 3 ROBERTSON WESTERN CAPE PROVINCE PHASE 1 ARCHAEOLOGICAL IMPACT ASSESSMENT PROPOSED DEVELOPMENT ERF 3 ROBERTSON WESTERN CAPE PROVINCE Prepared for BOLAND ENVIRO Att: Mr Nik Wullschleger PO Box 250 Worcester 6849 Fax: (023) 347 0336 By

More information

Environmental Impact Assessment for Waterway Restoration Projects. Chris John, Technical Director Ecus Ltd.

Environmental Impact Assessment for Waterway Restoration Projects. Chris John, Technical Director Ecus Ltd. Environmental Impact Assessment for Waterway Restoration Projects Chris John, Technical Director Ecus Ltd. Environmental Impact Assessment for Waterway Restoration Projects What is Environmental Impact

More information

Perth and Kinross Council Development Management Committee 8 June Pre-Application Report by Development Quality Manager

Perth and Kinross Council Development Management Committee 8 June Pre-Application Report by Development Quality Manager Perth and Kinross Council Development Management Committee 8 June 2016 5(3)(i) 16/259 Pre-Application Report by Development Quality Manager Residential development at St Martins Road, Land 120 metres West

More information

NATIONAL ROAD 3: KEEVERSFONTEIN TO WARDEN (DE BEERS PASS SECTION) CHAPTER 1: INTRODUCTION

NATIONAL ROAD 3: KEEVERSFONTEIN TO WARDEN (DE BEERS PASS SECTION) CHAPTER 1: INTRODUCTION February 2016 NATIONAL ROAD 3: KEEVERSFONTEIN TO WARDEN (DE BEERS PASS SECTION) CHAPTER 1: INTRODUCTION 1. INTRODUCTION This Environmental Impact Assessment Report (EIR) has been compiled as part of an

More information

MEETING HELD AT THE EDTEA OFFICES (ethekwini) ON 03 July 2018 AT 10h00. Ms. Naadira Nadasen (NN) Mrs Chen read (CR) and Mrs Tejal Singh (TS)

MEETING HELD AT THE EDTEA OFFICES (ethekwini) ON 03 July 2018 AT 10h00. Ms. Naadira Nadasen (NN) Mrs Chen read (CR) and Mrs Tejal Singh (TS) MINUTES OF THE PRE-APPLICATION MEETING IN RESPECT OF THE APPLICATION FOR ENVIRONMENTAL AUTHORISATION OF THE PROPOSED BEACHWOOD RESORT AND ESTATE DEVELOPEMENT MEETING HELD AT THE EDTEA OFFICES (ethekwini)

More information

APPENDIX D PUBLIC NOTIFICATIONS

APPENDIX D PUBLIC NOTIFICATIONS APPENDIX D PUBLIC NOTIFICATIONS APPENDIX D1 NEWSPAPER ADVERT APPENDIX D2 CORRESPONDENCE TO I&APs 18 February 2011 Dear Interested and Affected Party (I&AP), NOTICE OF ENVIRONMENTAL IMPACT ASSESSMENT FOR

More information

Interim Advice Note 76 / 06 ASSESSMENT PART 1 AIMS AND OBJECTIVES OF ENVIRONMENTAL ASSESSMENT. Contents

Interim Advice Note 76 / 06 ASSESSMENT PART 1 AIMS AND OBJECTIVES OF ENVIRONMENTAL ASSESSMENT. Contents Interim Advice Note 76 / 06 VOLUME 11 SECTION 1: ENVIRONMENTAL ASSESSMENT INTRODUCTION PART 1 AIMS AND OBJECTIVES OF ENVIRONMENTAL ASSESSMENT Contents 1. Introduction and Application 2. Aims and Objectives

More information

Planning Justification Brief

Planning Justification Brief Planning Justification Brief Proposed Re-Zoning Halton Catholic District School Board 302, 312, 324, 332 Rebecca Street Lots 4, 5, 6, & 7 and Blocks A & B Registered Plan 552 May 2017 Introduction Strategy

More information

N O T I F I C A T I O N O F I N T E N T T O D E V E L O P

N O T I F I C A T I O N O F I N T E N T T O D E V E L O P HWC 002/02/ED (4 Jul 14) N O T I F I C A T I O N O F I N T E N T T O D E V E L O P Completion of this form is required by Heritage Western Cape for the initiation of all impact assessment processes under

More information

Ashton WMF WP

Ashton WMF WP 09/26/2017 31 Allen Drive Loevenstein Cape Town 7530 South Africa C00720-AWMF-VIA-001 www.advisian.com Disclaimer This report has been prepared on behalf of and for the exclusive use of Legacy Environmental

More information

CHAPTER 4: CONTEXTUALISING THE PROPOSED PROJECT ENVIRONMENT WITHIN THE NATIONAL AND LOCAL

CHAPTER 4: CONTEXTUALISING THE PROPOSED PROJECT ENVIRONMENT WITHIN THE NATIONAL AND LOCAL : CONTEXTUALISING THE PROPOSED PROJECT WITHIN THE NATIONAL AND LOCAL ENVIRONMENT CONTENTS 4. CONTEXTUALISING THE PROPOSED PROJECT WITHIN THE NATIONAL AND LOCAL ENVIRONMENT 4-1 4.1 Introduction to the Coega

More information

Progress on implementation of the REDZs and Power Corridors SAPVIA Protea Hotel Balalaika 25 November 2016

Progress on implementation of the REDZs and Power Corridors SAPVIA Protea Hotel Balalaika 25 November 2016 Progress on implementation of the REDZs and Power Corridors SAPVIA Protea Hotel Balalaika 25 November 2016 Ms D Fischer Integrated Environmental Management Support Background Implementation systems Progress

More information

14.5 HOPEFIELD: (REFER PLAN 39 AND PLAN 40)

14.5 HOPEFIELD: (REFER PLAN 39 AND PLAN 40) URBAN DYNAMICS WESTERN CAPE INC. 248 14.5 HOPEFIELD: (REFER PLAN 39 AND PLAN 40) FIGURE 83: LOCALITY - HOPEFIELD Within the context of the Saldanha Bay Municipal area, Hopefield, an historical agricultural

More information

Planning Proposal under section 55 of the EP&A Act

Planning Proposal under section 55 of the EP&A Act FOR PUBLIC EXHIBITION [Brief description] Monday 10 October to Monday 27 October 2014 Planning Proposal under section 55 of the EP&A Act Port Macquarie-Hastings LEP 2011 (Amendment No 32) Mixed land zone

More information

HARTENBOS NORTH (population: Census 2011)

HARTENBOS NORTH (population: Census 2011) 5.8 HARTENBOS NORTH (population: + 184 Census 2011) Figure 5.8.1.1 Hartenbos North: Aerial photograph CNdV africa (Pty) Ltd DRAFT CONCEPTUAL DEVELOPMENT FRAMEWORK REPORT page 439 5.8.1 SPATIAL ANALYSIS,

More information

SITE INVESTIGATION REPORT: CONSTRUCTION OF NTUMBA VEHICULAR/PEDESTRIAN BRIDGE ACROSS A STREAM IN ROOKDALE, OKHAHLAMBA LOCAL MUNICIPALITY

SITE INVESTIGATION REPORT: CONSTRUCTION OF NTUMBA VEHICULAR/PEDESTRIAN BRIDGE ACROSS A STREAM IN ROOKDALE, OKHAHLAMBA LOCAL MUNICIPALITY SITE INVESTIGATION REPORT: CONSTRUCTION OF NTUMBA VEHICULAR/PEDESTRIAN BRIDGE ACROSS A STREAM IN ROOKDALE, OKHAHLAMBA LOCAL MUNICIPALITY PREPARED ON BEHALF OF: ECA CONSULTING CIVIL & STRUCTURAL ENGINEERS

More information

Stock-Taking on Integrated Coastal Zone Management (ICZM) in the Black Sea IMPLEMENTATION AUDIT QUESTIONNAIRE 2010

Stock-Taking on Integrated Coastal Zone Management (ICZM) in the Black Sea IMPLEMENTATION AUDIT QUESTIONNAIRE 2010 Stock-Taking on Integrated Coastal Zone Management (ICZM) in the Black Sea IMPLEMENTATION AUDIT QUESTIONNAIRE 2010 PURPOSE The purposes of this questionnaire are: (a) to perform the policy, legal and institutional

More information

MERIDAN PLAINS SAND RESOURCE AREA

MERIDAN PLAINS SAND RESOURCE AREA MERIDAN PLAINS SAND RESOURCE AREA INFORMATION SHEET October 2010 BACKGROUND The Meridan Plains Extractive Resource Area is located on the western fringe of the coastal urban communities of Caloundra West

More information

Baseline Study for Clamp Kilns in South Africa and Possible Regulatory Approaches

Baseline Study for Clamp Kilns in South Africa and Possible Regulatory Approaches Baseline Study for Clamp Kilns in South Africa and Possible Regulatory Approaches Session 3.1 Presentation to the 8 th Annual Air Quality Governance Lekgotla Cape Town, 30 September 2013 Presented by:

More information

Appropriate Assessment in relation to County Donegal Draft Heritage Plan

Appropriate Assessment in relation to County Donegal Draft Heritage Plan Appendix 12 - Consultation Response a) Sinead Harkin Central Planning Unit Donegal County Council County House Lifford County Donegal Dear Ms Harkin, Appropriate Assessment in relation to County Donegal

More information

CONSULTING SERVICES FOR THE WHITEBELT VISIONING EXERCISE ADDENDUM TO THE GTA WEST LAND USE STUDY WORK PROGRAM

CONSULTING SERVICES FOR THE WHITEBELT VISIONING EXERCISE ADDENDUM TO THE GTA WEST LAND USE STUDY WORK PROGRAM CONSULTING SERVICES FOR THE WHITEBELT VISIONING EXERCISE ADDENDUM TO THE GTA WEST LAND USE STUDY 1. Introduction WORK PROGRAM The Town of Caledon is a large, local municipality located in the Greater Toronto

More information

PHASE 1 ARCHAEOLOGICAL IMPACT ASSESSMENT THE PROPOSED SWARTLAND SHOPPING MALL

PHASE 1 ARCHAEOLOGICAL IMPACT ASSESSMENT THE PROPOSED SWARTLAND SHOPPING MALL 10 ( PHASE 1 ARCHAEOLOGICAL IMPACT ASSESSMENT THE PROPOSED SWARTLAND SHOPPING MALL Remainder Farm Tweefontein No. 696, Erf 2654 (Portion of Erf 327), Erf 9215 (Portion of Erf 2654) & Portion of Erf 327

More information

ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED MONAVONI X 51

ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED MONAVONI X 51 ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED MONAVONI X 51 Part of the Remainder of Portion 5 of the farm Mooiplaats 355 JR and part of Portion 2 of the farm Zwartkop 383 JR GAUT: 002/13-14/E0032 OCTOBER

More information

THE CORPORATION OF THE CITY OF WINDSOR Office of the City Solicitor Planning Department

THE CORPORATION OF THE CITY OF WINDSOR Office of the City Solicitor Planning Department THE CORPORATION OF THE CITY OF WINDSOR Office of the City Solicitor Planning Department REPORT TO THE CITY OF WINDSOR PLANNING ADVISORY COMMITTEE DATE OF REPORT: August 19, 2010 SUBJECT: Official Plan

More information

ROCHFORD LOCAL DEVELOPMENT FRAMEWORK: Sustainability Appraisal/ Strategic Environmental Assessment. Rochford Core Strategy Preferred Options Document

ROCHFORD LOCAL DEVELOPMENT FRAMEWORK: Sustainability Appraisal/ Strategic Environmental Assessment. Rochford Core Strategy Preferred Options Document ROCHFORD LOCAL DEVELOPMENT FRAMEWORK: Sustainability Appraisal/ Strategic Environmental Assessment Non Technical Summary Rochford Core Strategy Preferred Options Document October 2008 SUSTAINABILITY APPRAISAL

More information

Cape Environmental Assessment Practitioners (Pty) Ltd

Cape Environmental Assessment Practitioners (Pty) Ltd Cape Environmental Assessment Practitioners (Pty) Ltd Reg. No. 2008/004627/07 Telephone: (044) 874 0365 1 st Floor Eagles View Building Facsimile: (044) 874 0432 5 Progress Street, George Web: www.cape-eaprac.co.za

More information

Water Demand Management Plan

Water Demand Management Plan ADDENDUM I ARCHITECTURAL GUIDELINES WELGELEGEN RESIDENTIAL DEVELOPMENT June 2011 : Revision 2 Water Demand Management Plan Welgelegen Estate on Remainder of Kraaibosch 195/1 & 279 Compiled by: HilLand

More information

University Park, Worcester Non Technical Summary December 2011

University Park, Worcester Non Technical Summary December 2011 University Park, Worcester Non Technical Summary December 2011 Introduction UW Wrenbridge LLP, a Joint Venture Company of the University of Worcester and Wrenbridge Land Ltd (the Applicants ) intend to

More information

INSTITUTE OF TOWN PLANNERS, INDIA TOWN PLANNING EXAMINATION BOARD ASSOCIATESHIP EXAMINATION. ASSIGNMENT: Semester -II Year 2019

INSTITUTE OF TOWN PLANNERS, INDIA TOWN PLANNING EXAMINATION BOARD ASSOCIATESHIP EXAMINATION. ASSIGNMENT: Semester -II Year 2019 SUBJECT: C.2.1. Design of Human Settlements Maximum Marks: 20 1. Describe the link between urban design and urban planning. Explain the role of urban design in town planning. 2. Explain the importance

More information

PROJECT INFORMATION. The type of development

PROJECT INFORMATION. The type of development A LETTER OF RECOMMENDATION (WITH CONDITIONS) FOR THE EXEMPTION OF A FULL PHASE 1 ARCHAEOLOGICAL HERITAGE IMPACT ASSESSMENT FOR THE PROPOSED, CONSTRUCTION OF A FILLING STATION AND ASSOCIATED INFRASTRUCTURE

More information

SINGITA SWENI LODGE EXPANSION: SUMMARY REPORT - BAR

SINGITA SWENI LODGE EXPANSION: SUMMARY REPORT - BAR 7 PROJECT: SINGITA SWENI LODGE EXPANSION: SUMMARY REPORT - BAR Basic Environmental Assessment for Lodge expansion and Refurbishment of the Singita Sweni Lodge, within the Singita Private Concession in

More information

volume 11 environmental assessment section 2 environmental impact assessment Part 7 ha 218/08

volume 11 environmental assessment section 2 environmental impact assessment Part 7 ha 218/08 DESIGN MANUAL FOR ROADS AND BRIDGES volume 11 environmental assessment section 2 environmental impact assessment Part 7 ha 218/08 glossary of terms Used in DMRB Volume 11, Sections 1 and 2 SUMMARY This

More information

DELEGATED REPORT. LOCATION Land At Hawley Common Minley Road Blackwater Camberley Surrey

DELEGATED REPORT. LOCATION Land At Hawley Common Minley Road Blackwater Camberley Surrey DELEGATED REPORT APPLICATION NO. 16/03200/FUL LOCATION Land At Hawley Common Minley Road Blackwater Camberley Surrey PROPOSAL APPLICATION FOR TEMPORARY PLANNING PERMISSION FOR USE OF LAND FOR FILMING AND

More information

IUCN World Heritage Advice Note Environmental Assessment & World Heritage

IUCN World Heritage Advice Note Environmental Assessment & World Heritage FINAL DRAFT, 07 June 2013 1 IUCN World Heritage Advice Note Environmental Assessment & World Heritage This Advice Note is intended to provide States Parties and other stakeholders with guidance on integrating

More information

Chapter 3: Natural Environment. Proposed Waikato District Plan Stage 1. (Notified version)

Chapter 3: Natural Environment. Proposed Waikato District Plan Stage 1. (Notified version) Chapter 3: Natural Environment Proposed Waikato District Plan Stage 1 Page 2 of 7 Contents Chapter 3: Natural Environment... 3 3.1 Indigenous Vegetation and Habitats... 3 3.1.1 Objective Biodiversity and

More information

Site Assessment Technical Document Appendix A: Glossary

Site Assessment Technical Document Appendix A: Glossary Central Bedfordshire Council www.centralbedfordshire.gov.uk Site Assessment Technical Document Appendix A: Glossary July 2017 1.1.11-1 - ii Appendix A: Glossary Term Agricultural Land Classification AONB

More information

Figure 1- Site Plan Concept

Figure 1- Site Plan Concept Figure 1- Site Plan Concept Parking will be provided underground on three levels at rate of 1.0 space/ unit; this rate includes all visitors parking. MMM Group has prepared a parking assessment (April,

More information

9 CITY OF VAUGHAN OFFICIAL PLAN AMENDMENT NO BOCA EAST INVESTMENTS LIMITED

9 CITY OF VAUGHAN OFFICIAL PLAN AMENDMENT NO BOCA EAST INVESTMENTS LIMITED 9 CITY OF VAUGHAN OFFICIAL PLAN AMENDMENT NO. 631 - BOCA EAST INVESTMENTS LIMITED The Planning and Economic Development Committee recommends the adoption of the recommendations contained in the following

More information

AMENDMENTS. Date Effective. Amendment No. Council. DCP 14 Davidson St, Greenacre Page 2

AMENDMENTS. Date Effective. Amendment No. Council. DCP 14 Davidson St, Greenacre Page 2 AMENDMENTS Amendment No. Description Adopted by Council Date Effective DCP 14 Davidson St, Greenacre Page 2 TABLE OF CONTENTS 1.0 INTRODUCTION... 4 1.1 NAME OF THIS PLAN... 4 1.2 COMMENCEMENT OF DEVELOPMENT

More information

Authority. any changes required as a result of the approved CHMP.

Authority. any changes required as a result of the approved CHMP. PLANNING PERMIT Permit No. Planning Scheme Responsible Authority../2013 Greater Geelong Planning Scheme Greater Geelong City Council ADDRESS OF THE LAND 5, 15, 21, 23, 1/23, 25, 33, 40 and 50 Caddys Road;

More information

South of Eastern Strategic Direction Status Update

South of Eastern Strategic Direction Status Update STAFF REPORT ACTION REQUIRED South of Eastern Strategic Direction Status Update Date: July 10, 2014 To: From: Planning and Growth Management Committee Chief Planner and Executive Director, City Planning

More information

COUNTY OF LAMBTON OFFICIAL PLAN UPDATE BACKGROUND REPORT NO.

COUNTY OF LAMBTON OFFICIAL PLAN UPDATE BACKGROUND REPORT NO. COUNTY OF LAMBTON OFFICIAL PLAN UPDATE BACKGROUND REPORT NO. 7 TELECOMMUNICATIONS Image Source: (Word Clip Art Stock Photos, 2011) Date: May, 2015 PLANNING AND DEVELOPMENT SERVICES DEPARTMENT 789 Broadway

More information

VCA Guidance Note. Contents

VCA Guidance Note. Contents Contents 1. Introduction... 2 2. Who can register a VCA?... 2 3. VCAs and sustainable development... 3 4. Verifying conservation performance... 4 4.1 Transparent, voluntary commitments... 4 4.2 Independent

More information

U N. United Nations Decade on Biodiversity. Convention on Biological Diversity. Ref.: SCBD/SPS/DC/SBG/JL/JA/ November 2017

U N. United Nations Decade on Biodiversity. Convention on Biological Diversity. Ref.: SCBD/SPS/DC/SBG/JL/JA/ November 2017 United Nations Decade on Biodiversity Ref.: SCBD/SPS/DC/SBG/JL/JA/86906 23 November 2017 Dear Ms. Goettsche-Wanli, Reference is made to the letter of Mr. Miguel de Serpa Soares, Under-Secretary-General

More information

Environmental Impact Assessment

Environmental Impact Assessment Environmental Impact Assessment Environmental impact assessment (EIA) is the process of systematically drawing together an assessment of the likely significant environmental effects of a development project.

More information

EUROPEAN COMMISSION DIRECTORATE-GENERAL FOR HEALTH AND FOOD SAFETY

EUROPEAN COMMISSION DIRECTORATE-GENERAL FOR HEALTH AND FOOD SAFETY EUROPEAN COMMISSION DIRECTORATE-GENERAL FOR HEALTH AND FOOD SAFETY Brussels, 23 October 2018 REV1 Replaces the Q&A document published on 13 September 2017 QUESTIONS AND ANSWERS RELATED TO THE UNITED KINGDOM'S

More information

Land Use Amendment in Southwood (Ward 11) at and Elbow Drive SW, LOC

Land Use Amendment in Southwood (Ward 11) at and Elbow Drive SW, LOC 2018 November 15 Page 1 of 10 EXECUTIVE SUMMARY This land use amendment application was submitted by Rick Balbi Architect on 2017 August 31 on behalf of Sable Developments Ltd, and with authorization from

More information

Alternative Routes. St. Vital to La Verendrye Station - Southern Loop Transmission Corridor. 20 different segments 4 segments common to all routes

Alternative Routes. St. Vital to La Verendrye Station - Southern Loop Transmission Corridor. 20 different segments 4 segments common to all routes Alternative Routes St. Vital to La Verendrye Station - Southern Loop Transmission Corridor In a fixed right-of-way St. Vital to Letellier Station 20 different segments 4 segments common to all routes Goal

More information

RURAL ZONE - POLICY. Rural Zone Policy. Issue: Rural Environment. Ruapehu District Plan Page 1 of 8

RURAL ZONE - POLICY. Rural Zone Policy. Issue: Rural Environment. Ruapehu District Plan Page 1 of 8 Rural Zone Policy RU2 RURAL ZONE - POLICY RU2.1 Introduction The natural resources of the rural environment in the Ruapehu District provide the basis for the existing and potential character, intensity

More information

Services Department B September 10, 2007

Services Department B September 10, 2007 Report To: Development Services Committee Item: Date of Report: DS-07-246 September 5, 2007 From: Commissioner, Development File: Date of Meeting: Services Department B7200-0001 September 10, 2007 Subject:

More information

Significant Tree Register

Significant Tree Register Significant T Register t City of Mandurah, 3 Peel Stt Mandurah WA 6210 Phone: (08) 9550 3812 email: EcoServices@mandurah.wa.gov.au Contents 1. Introduction and Background 2. Purpose of the Register 3.

More information

THE ENVIRONMENTAL PROTECTION IN THE URBANISTICPLANNING AND LAND DEVELOPMENT IN EUROPEAN UNION LAW

THE ENVIRONMENTAL PROTECTION IN THE URBANISTICPLANNING AND LAND DEVELOPMENT IN EUROPEAN UNION LAW THE ENVIRONMENTAL PROTECTION IN THE URBANISTICPLANNING AND LAND DEVELOPMENT IN EUROPEAN UNION LAW The answes must be sent, imperatively in English or in French, before the 15th August 2011 to Ms. Anna

More information

Rapid Transit Implementation Working Group September 14, 2017

Rapid Transit Implementation Working Group September 14, 2017 Rapid Transit Implementation Working Group September 14, 2017 BACKGROUND Council approved the Rapid Transit Master Plan and Updated Business Case on July 25, 2017. Approval of the RTMP confirmed the BRT

More information

Executive Summary. Final Environmental Impact Report: Walmer Housing Development, Erf 11305, Port Elizabeth

Executive Summary. Final Environmental Impact Report: Walmer Housing Development, Erf 11305, Port Elizabeth Ground Floor, Bay Suites 1a Humewood Rd, Humerail Port Elizabeth, 6001 P O Box 21842 Port Elizabeth 6000 South Africa T: +27 (0) 41 509 4800 F: +27 (0) 41 509 4850 E: portelizabeth@srk.co.za www.srk.co.za

More information

Circular L8/08 2 September Water Services Investment and Rural Water Programmes Protection of Natural Heritage and National Monuments

Circular L8/08 2 September Water Services Investment and Rural Water Programmes Protection of Natural Heritage and National Monuments Circular L8/08 2 September 2008 Water Services Investment and Rural Water Programmes Protection of Natural Heritage and National Monuments 1. The purpose of this Circular is to provide local authorities

More information

PDS June 1, 2016 Page 1. Planning and Development Committee. MEETING DATE: Wednesday, June 01, 2016

PDS June 1, 2016 Page 1. Planning and Development Committee. MEETING DATE: Wednesday, June 01, 2016 Page 1 REPORT TO: Planning and Development Committee MEETING DATE: Wednesday, June 01, 2016 SUBJECT: ROPA 12: Project Initiation Report Regional Official Plan Amendment (ROPA # 12) Watercourse Policies

More information

WESTERN CAPE GOVERNMENT: DEPARTMENT OF TRANSPORT AND PUBLIC WORKS

WESTERN CAPE GOVERNMENT: DEPARTMENT OF TRANSPORT AND PUBLIC WORKS WESTERN CAPE GOVERNMENT: DEPARTMENT OF TRANSPORT AND PUBLIC WORKS PROPOSED UPGRADE OF TRUNK ROAD 11/1 TO FREEWAY STANDARDS, FROM THE POTSDAM INTERCHANGE TO THE MELKBOS INTERCHANGE (N7/1), CAPE TOWN FINAL

More information

EIA process in Malaysia. Approaches and Strategies. Way Forward

EIA process in Malaysia. Approaches and Strategies. Way Forward PUBLIC PARTICIPATION APPROACHES AND STRATEGIES UNDER THE EIA PROCESS IN MALAYSIA By Norhayati Mohamad Yusof Principal Assistant Director Department of Environment Malaysia AECEN REGIONAL WORKSHOP Strengthening

More information

Proposed St. Vital Transmission Complex

Proposed St. Vital Transmission Complex Proposed St. Vital Transmission Complex Round 2 Preferred Route for the St. Vital to Letellier Line What is it? Manitoba Hydro is proposing construction of two 230-kilovolt (kv) transmission lines to improve

More information

(For official use only)

(For official use only) APPLICATION FORM FOR ENVIRONMENTAL AUTHORISATION File Reference Number: NEAS Reference Number: Date Received: (For official use only) DEA/EIA/ Application for authorisation in terms of the National Environmental

More information

CULTURAL HERITAGE IMPACT ASSESSMENT TERMS OF REFERENCE

CULTURAL HERITAGE IMPACT ASSESSMENT TERMS OF REFERENCE CULTURAL HERITAGE IMPACT ASSESSMENT TERMS OF REFERENCE The Corporation of the Town of Whitby Planning and Development Department 575 Rossland Road East, Whitby Ontario, L1N 2M8 Telephone: 905-430-4306

More information

ENVIRONMENTAL ISSUES and TEN-T PROJECTS Key elements for a sustainable network development

ENVIRONMENTAL ISSUES and TEN-T PROJECTS Key elements for a sustainable network development ENVIRONMENTAL ISSUES and TEN-T PROJECTS Key elements for a sustainable network development TEN-T Project Management Workshop 2010 George Kremlis DG ENV B4, European Commission 13 January 2010 Environmental

More information

SIBAYA WATERLINE BASIC ASSESSMENT PROCESS. PRE-APPLICATION MEETING WITH EDTEA March 2016

SIBAYA WATERLINE BASIC ASSESSMENT PROCESS. PRE-APPLICATION MEETING WITH EDTEA March 2016 SIBAYA WATERLINE BASIC ASSESSMENT PROCESS PRE-APPLICATION MEETING WITH EDTEA March 2016 Agenda Item No. Topic 1. Welcome & Introduction 2. Purpose of the Meeting 3. Presentation 4. Queries / Discussion

More information

MINIMUM STANDARDS: ARCHAEOLOGICAL AND PALAEONTOLOGICAL COMPONENTS OF IMPACT ASSESSMENT REPORTS

MINIMUM STANDARDS: ARCHAEOLOGICAL AND PALAEONTOLOGICAL COMPONENTS OF IMPACT ASSESSMENT REPORTS 111 H ARRINGTON STREET, CAPE TOWN, 8001 PO BOX 4637, CAPE TOWN, 8000 TEL: 021 462 4502 FX: 021 462 4509 TABLE OF CONTENTS MINIMUM STANDARDS: ARCHAEOLOGICAL AND PALAEONTOLOGICAL COMPONENTS OF IMPACT ASSESSMENT

More information

Communicate the results of the EIA for the proposed development;

Communicate the results of the EIA for the proposed development; 1 INTRODUCTION Burgan Cape Terminals (Proprietary) Limited hereafter referred to as Burgan Oil, appointed Environmental Resources Management Southern Africa (Pty) Ltd, hereafter referred to as ERM, as

More information

Land North of Hall Road, Rochford. Rochford District Council. Planning Application Index. Prepared on behalf of Bellway Homes Ltd

Land North of Hall Road, Rochford. Rochford District Council. Planning Application Index. Prepared on behalf of Bellway Homes Ltd Land North of Hall Road, Rochford Rochford District Council Planning Application Index Prepared on behalf of Bellway Homes Ltd April 2010 Land North of Hall Road, Rochford Rochford District Council Scope

More information

VILLAGE OF BOLTON HERITAGE CONSERVATION DISTRICT PLAN

VILLAGE OF BOLTON HERITAGE CONSERVATION DISTRICT PLAN Page 1 1. INTRODUCTION AND BACKGROUND 1.1 THE PROJECT VILLAGE OF BOLTON HERITAGE CONSERVATION DISTRICT PLAN TERMS OF REFERENCE The Town of Caledon (Town) is a large, predominantly rural municipality with

More information

DEVELOPMENT APPLICATION DECISION NOTICE Sustainable Planning Act 2009 (SPA)

DEVELOPMENT APPLICATION DECISION NOTICE Sustainable Planning Act 2009 (SPA) Date >> 06 July TOWNSVILLE CITY COUNCIL LEVEL 1 GOLD FOYER 143 WALKER STREET PO BOX 1268, TOWNSVILLE QUEENSLAND 4810 Ross River Solar Farm Pty Ltd C/- AECOM Australia Pty Ltd PO Box 5423 TOWNSVILLE QLD

More information

Environmental Impact Assessment Screening Report for proposed Environmental Improvement Works to the Front of Emily Square, Athy

Environmental Impact Assessment Screening Report for proposed Environmental Improvement Works to the Front of Emily Square, Athy Environmental Impact Assessment Screening Report for proposed Environmental Improvement Works to the Front of Emily Square, Athy by CAAS Ltd for Kildare County Council July 2018 CAAS Ltd, 1 st Floor, 24-26

More information

Cape Environmental Assessment Practitioners (Pty) Ltd

Cape Environmental Assessment Practitioners (Pty) Ltd Cape Environmental Assessment Practitioners (Pty) Ltd Reg. No. 2008/004627/07 Telephone: (044) 874 0365 Facsimile: (044) 874 0432 17 Progress Street, George Web: www.cape-eaprac.co.za PO Box 2070, George

More information

To evaluate the magnitude and significance of likely impacts and to propose appropriate measures to mitigate potential adverse impacts.

To evaluate the magnitude and significance of likely impacts and to propose appropriate measures to mitigate potential adverse impacts. .0 INTRODUCTION. PURPOSE OF REPORT This Environmental Impact Statement (EIS) has been prepared as part of an application for a railway order for Luas Line A, a proposed 4.2km spur from the existing Luas

More information

REQUEST FOR QUALIFICATIONS

REQUEST FOR QUALIFICATIONS REQUEST FOR QUALIFICATIONS for the City of Lake Forest Issue Date: September 23, 2015 Bid Due Date: October 19, 2015 The City of Lake Forest 800 N. Field Drive Lake Forest, Illinois 60045 THE CITY OF LAKE

More information

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF NOVEMBER 15, 2016

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF NOVEMBER 15, 2016 Item 11, Report No. 38, of the Committee of the Whole, which was adopted without amendment by the Council of the City of Vaughan on November 15, 2016. Regional Councillor Di Biase declared an interest

More information

Township of Adjala-Tosorontio Official Plan Review. Natural Heritage

Township of Adjala-Tosorontio Official Plan Review. Natural Heritage Township of Adjala-Tosorontio Official Plan Review 13 Natural Heritage Introduction What is an Official Plan? An official plan is a municipal policy document which sets out the community s vision and strategies

More information

Draft Resolution XII.10

Draft Resolution XII.10 12 th Meeting of the Conference of the Parties to the Convention on Wetlands (Ramsar, Iran, 1971) Punta del Este, Uruguay, 1-9 June 2015 Ramsar COP12 DR10, Rev. 2 21:45, 8 June Draft Resolution XII.10

More information

Digital Terrestrial Television Infrastructure Rollout. Environmental Impact Assessment - Corridor -

Digital Terrestrial Television Infrastructure Rollout. Environmental Impact Assessment - Corridor - Digital Terrestrial Television Infrastructure Rollout Environmental Impact Assessment - Corridor - 1 1 ENVIRONMENTAL IMPACT ASSESSMENT (EIA): CORRIDOR 1.1 INTRODUCTION Corridor is a small farming community

More information