Machinery Room Electrical Best Practices

Size: px
Start display at page:

Download "Machinery Room Electrical Best Practices"

Transcription

1 Machinery Room Electrical Best Practices Brad Heeres Angus-Young Associates February 8, 2007

2 Understand and comply with applicable codes and standards The National Electrical Code requirements for a safe electrical installation Working clearances Egress away from equipment Proper grounding and bonding NFPA 70E Standard for Electrical Safety in the Workplace Article 130 requirements for protection against arcflash hazard IEEE Standards for design and analysis of electrical distribution systems Color Book Series Red and Green Books

3 Understand and comply with applicable codes and standards ASHRAE 15 Ventilation requirements for machine rooms Provide 0.5 cfm/ft 2 continuous ventilation and alarm on failure Provide shutdown controls outside the machine room Feed ventilation fans from a separate circuit and provide controls outside the machine room

4 Understand and comply with applicable codes and standards International Institute of Ammonia Refrigeration (ANSI/IIAR-2 and Bulletin 112) Minimize the electrical equipment in the machine room Consider Class 1 Div. 2 electrical installation for circuits/equipment that may operate in an emergency Provide adequate lighting for operations Provide emergency and exit lighting with power source located outside the machine room

5 Good electrical equipment and machine room design is shown in this illustration Locate non-machine room panels outside of machine room Starters for compressors located in room but away from ammonia sources Separated Electrical Room Control panels readily accessible Plan for future equipment

6 Maintain appropriate electrical and machine room conditions Keep electrical equipment cool Ventilate electrical rooms approx. 200 CFM/kW loss Keep electrical equipment dry Provide heating if necessary Be aware of moist air passing through conduits Use supply fans not exhaust fans for electrical room ventilation Keeps contaminants out Provide 30% or MERV 7 filters

7 Consider medium voltage distribution when: Individual loads exceed 500HP The facility covers a large area and has distributed large loads Where the total facility load exceeds 5000 kva or utility requirements dictate

8 Provide ground fault protection on feeders when GFP is required on main devices NEC requires ground fault protection on 480V solidly grounded services > 1000A Phase fuses and CBs may not clear ground faults before the main trips Overcurrent protection coordination is important for safety and reliability

9 Electrical systems studies can improve electrical system safety and reliability Fault current studies determine appropriate equipment ratings Coordination studies ensure proper fault clearing Arc flash evaluation improves safety

10 Fault current studies determine appropriate equipment ratings Establishes interrupting ratings for fuses & CBs Establishes proper trip settings or fuse ratings Provides information that can be used to limit damage due to faults

11 Coordination studies ensure proper fault clearing Circuit breakers are set or fuses selected to: Limit fault damage to equipment and conductors Minimize nuisance trips Isolate faults

12 Arc flash evaluation improves safety Proper labeling indicates the level of hazard and appropriate protective gear Fuse selections or circuit breaker settings may be adjusted to reduce the hazard

13 Preventative maintenance improves both safety and reliability PC Process East Wall Markers: Label Emissivity Background Average Std Dev Max Min L L L L L L L Info: File Location F:\images\IR PC Process East Wall.is2 Image Time 28-Sep-05 10:09 AM Emissivity 0.95 Background Temp F Image Range to F Average Temp F Calibration Range to F Lens , 20mm/F.8 Camera S/N FLX IR PC Process East Wall.is2 Notations: 600Amp Breaker. Phase A 296 amps, Phase B 302 amps and Phase C 304 amps Comments: Use good installation practices Check for hot equipment and terminations (thermal scan) Monitor large loads like compressors and MCCs for changes in operation

14 Electrical best practices: Understand Codes and Standards Use good planning for new construction, additions and upgrades Properly select and adjust electrical devices Monitor the electrical system operation Properly inspect and maintain electrical equipment Follow good safety practices

Brown University Revised June 29, 2012 Facilities Design & Construction Standards SECTION ELECTRICAL DESIGN CRITERIA

Brown University Revised June 29, 2012 Facilities Design & Construction Standards SECTION ELECTRICAL DESIGN CRITERIA PART 1 - GENERAL 1.1 Background SECTION 26 00 10- ELECTRICAL DESIGN CRITERIA A. Brown University maintains it own campus electrical distribution system which serves the majority of the buildings and facilities

More information

National Electrical Code

National Electrical Code National Electrical Code 409.30 Disconnecting Means Disconnecting means that supply motor loads shall comply with Part IX of Article 30. 410.81 Control (A) Disconnection Luminaires (fixtures) or lamp installation

More information

2012 Edition. Tech Topics: Standards & Codes. Note 4, Issue 1. Points of Interest: Introduction. Background. Changes to Definitions in Article 100

2012 Edition. Tech Topics: Standards & Codes. Note 4, Issue 1. Points of Interest: Introduction. Background. Changes to Definitions in Article 100 Significant Changes to the NFPA 70E Standard 2012 Edition Tech Topics: Standards & Codes Note 4, Issue 1 Peter Walsh, PE Sr. Field Engineer Points of Interest: Arc-Rated (AR) vs. Flame-Resistant (FR) Training

More information

GPS 140 NEC Requirements for Generators. Professional Development Seminar Series NEC Requirements for Generators

GPS 140 NEC Requirements for Generators. Professional Development Seminar Series NEC Requirements for Generators GPS 140 NEC Requirements for Generators WHAT YOU WILL LEARN NEC requirements for on-site power generation. Recent events have created increased interest in standby power This module organizes NEC requirements

More information

ELECTRICAL BULLETIN

ELECTRICAL BULLETIN PO Box 697 Halifax, Nova Scotia B3J 2T8 Labour and Workforce Development ELECTRICAL BULLETIN 2011-01 From: David MacLeod,C.E.I.,P.Eng. Pg 1 of 6 Provincial Chief Electrical Inspector Date: January 5,2011

More information

Welcome DISCLAIMER. Testing Electric Fire Pumps You Need to Understand the Arc Flash Hazard 5/1/ NFPA Conference & Expo

Welcome DISCLAIMER. Testing Electric Fire Pumps You Need to Understand the Arc Flash Hazard 5/1/ NFPA Conference & Expo 2017 NFPA Conference & Expo Testing Electric Fire Pumps You Need to Understand the Arc Flash Hazard Presented by: Tracey D. Bellamy, PE, CFPS Chief Engineering Officer Telgian Corporation Welcome Instructor

More information

Todd Jekel, Assistant Director, IRC Feb. 8, Standard Definition. What is a machinery room?

Todd Jekel, Assistant Director, IRC Feb. 8, Standard Definition. What is a machinery room? Machinery Room Requirements & Best Practices Design Todd Jekel, Assistant Director, IRC Feb. 8, 2007 Standard Definition What is a machinery room? ASHRAE 15-2004 3 states: a space, meeting the requirements

More information

VACUUM BREAKER MEDIUM VOLTAGE AUTOMATIC TRANSFER SWITCHES

VACUUM BREAKER MEDIUM VOLTAGE AUTOMATIC TRANSFER SWITCHES Part One General 1.01 Scope A. It is the intent of this specification to provide a medium voltage automatic transfer system. B. All components, testing and services specified and required for a complete

More information

NATIONAL ELECTRICAL CODE (NEC) & NFPA 70E ARC FLASH ELECTRICAL SAFETY

NATIONAL ELECTRICAL CODE (NEC) & NFPA 70E ARC FLASH ELECTRICAL SAFETY A new twist on the National Electrical Code - a practical application workshop. If you sign up in this class, prepare to work! Day 1: Fundamentals of OSHA requirements for performing electrical work -

More information

Changes to NFPA 70E. - The Role of PdM &Safe PdM Work Practices. Tim Rohrer Exiscan LLC

Changes to NFPA 70E. - The Role of PdM &Safe PdM Work Practices. Tim Rohrer Exiscan LLC Changes to NFPA 70E - The Role of PdM &Safe PdM Work Practices Tim Rohrer Exiscan LLC Tim@Exiscan.com 585-705-7775 Joe Gierlach ABM Joseph.Gierlach@ABM.com 412-394-4678 Preview Electrical Safety Risk Management

More information

NEC Requirements for Standby Power Systems. New England Building Officials Education Association Annual Conference October 5, 2015

NEC Requirements for Standby Power Systems. New England Building Officials Education Association Annual Conference October 5, 2015 NEC Requirements for Standby Power Systems New England Building Officials Education Association Annual Conference October 5, 2015 Emergency & Standby Power Systems Alternative power sources are utilized

More information

PART 4 ELECTRICAL STANDARDS

PART 4 ELECTRICAL STANDARDS PART 4 ELECTRICAL STANDARDS 1.0 INTRODUCTION AND SCOPE: These standards reflect the general requirements and recommendations of elevator contractors, with respect to the power distribution system to achieve

More information

SECTION PANELBOARDS. A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section.

SECTION PANELBOARDS. A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section. PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section. 1.2 SUMMARY A. This Section includes the

More information

Chapter 1 General...9 Article 100 Definitions...11 Article 100 Questions Article 110 Requirements for Electrical Installations...

Chapter 1 General...9 Article 100 Definitions...11 Article 100 Questions Article 110 Requirements for Electrical Installations... Article 90 Introduction...1 90.1 Purpose of the NEC...1 90.2 Scope of the NEC...2 90.3 Code Arrangement...4 90.4 Enforcement...5 90.5 Mandatory Requirements and Explanatory Material...6 90.6 Formal Interpretations...6

More information

Electrical Inspection Service & Distribution

Electrical Inspection Service & Distribution 0911 Distribution Panels & Switchgear Equipment, conduit, feeders, and grounding 480 Volt Switchboard: This switchboard contains the utility meter and two main, service, circuit breakers. One circuit breaker

More information

CHAPTER 20 SERVICE EQUIPMENT

CHAPTER 20 SERVICE EQUIPMENT SERVICE EQUIPMENT CHAPTER 20 SERVICE EQUIPMENT Service equipment includes service cabinets and the equipment and materials necessary for installation. 20.1 Signal Service Cabinet For MnDOT traffic control

More information

1S25. Arc Fault Monitor 4 Zones, 8 Sensors. Features. Introduction. ARC Fault Protection

1S25. Arc Fault Monitor 4 Zones, 8 Sensors. Features. Introduction. ARC Fault Protection Technical Bulletin Arc Fault Monitor 4 Zones, 8 Sensors Features Four independent arc fault tripping zones 1 or 2 arc fault sensors per zone allowing up to 8 arc fault sensors per module Trip indication

More information

SECTION AUTOMATIC TRANSFER SWITCHES

SECTION AUTOMATIC TRANSFER SWITCHES PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 36 23 SPEC WRITER NOTE: Use this section only for NCA projects. Delete between //--// if not applicable to project. Also, delete any other item or paragraph

More information

IMPORTANT NOTICE BUILDERS AND CONTRACTORS WORKING IN NORTH RICHLAND HILLS, TEXAS. June 17th, 2016

IMPORTANT NOTICE BUILDERS AND CONTRACTORS WORKING IN NORTH RICHLAND HILLS, TEXAS. June 17th, 2016 IMPORTANT NOTICE BUILDERS AND CONTRACTORS WORKING IN NORTH RICHLAND HILLS, TEXAS June 17th, 2016 RE: City Council Adopts 2014 National Electrical Code with Pool Alarm Requirements On April 25th, 2016 the

More information

Alex Masterton, PE Electrical Engineer Reviewer AHCA Neal Boothe, PE Electrical Engineer/Principal

Alex Masterton, PE Electrical Engineer Reviewer AHCA Neal Boothe, PE Electrical Engineer/Principal Alex Masterton, PE Electrical Engineer Reviewer AHCA Neal Boothe, PE Electrical Engineer/Principal FBC 419.3.15.6 All low-voltage system main or branch circuits entering or exiting the structure shall

More information

ELECTRICAL POWER SYSTEMS

ELECTRICAL POWER SYSTEMS Scope The various Codes applicable to the University's electrical power system are mainly based upon a model of a single utility service, connected to a single premise. The University s electrical system,

More information

PANELBOARDS & BUILDING DISTRIBUTION

PANELBOARDS & BUILDING DISTRIBUTION 262416 PANELBOARDS & BUILDING DISTRIBUTION PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. Distribution panelboards 2. Power panelboards B. Related Sections: 1.02 POLICY 1. CU Standard 260500, Basic

More information

Introduction Consultant shall incorporate the material in the DSS into the project specifications.

Introduction Consultant shall incorporate the material in the DSS into the project specifications. DIVISION 16 - ELECTRICAL Section 16000 - General Discussion Introduction Consultant shall incorporate the material in the DSS into the project specifications. Refer any questions, clarifications regarding

More information

Implementing an Energized Electrical Work Program. SESHA Hill Country Chapter. Brett Jay Davis, PE Zephyr Environmental Corporation

Implementing an Energized Electrical Work Program. SESHA Hill Country Chapter. Brett Jay Davis, PE Zephyr Environmental Corporation Implementing an Energized Electrical Work Program SESHA Hill Country Chapter May 22, 2009 Brett Jay Davis, PE Zephyr Environmental Corporation bdavis@zephyrenv.com, 512 879-6628 Presentation Outline 1.

More information

SECTION ISOLATED POWER SYSTEMS

SECTION ISOLATED POWER SYSTEMS PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 20 11 ISOLATED POWER SYSTEMS SPEC WRITER NOTE: Delete between //---// if not applicable to project. Also, delete any other item or paragraph not applicable to

More information

MODEL YVAA EQUIPMENT PRE-STARTUP AND STARTUP CHECKLIST CUSTOMER: LOCATION: ADDRESS: CUSTOMER ORDER NO: PHONE: JCI CONTRACT NO: JOB NAME:

MODEL YVAA EQUIPMENT PRE-STARTUP AND STARTUP CHECKLIST CUSTOMER: LOCATION: ADDRESS: CUSTOMER ORDER NO: PHONE: JCI CONTRACT NO: JOB NAME: Supersedes: 201.28-CL2 (817) Form 201.28-CL2 (1017) MODEL YVAA EQUIPMENT PRE-STARTUP AND STARTUP CHECKLIST CUSTOMER: LOCATION: ADDRESS: PHONE: JOB NAME: CUSTOMER ORDER NO: JCI CONTRACT NO: CHILLER MODEL

More information

Chapter 1 General... 5

Chapter 1 General... 5 About This Textbook...xi About the National Electrical Code...xv About the Authors and Illustrator...xix About the Team...xxi Article 90 Introduction to the National Electrical Code... 1 90.1 Purpose of

More information

Ammonia Refrigeration RAGAGEP

Ammonia Refrigeration RAGAGEP Providing Solutions. Simplifying Regulation. Ammonia Refrigeration RAGAGEP Peter Thomas, P.E., CSP Resource Compliance, Inc. Introduction Providing Solutions. Simplifying Regulation. Providing Solutions.

More information

EQUIPMENT PRE-STARTUP AND STARTUP CHECKLIST TEL NO: ORDER NO: CONTRACT NO:

EQUIPMENT PRE-STARTUP AND STARTUP CHECKLIST TEL NO: ORDER NO: CONTRACT NO: Supersedes: (316) Form QTC4-CL2 (617) MODEL QTC4 EQUIPMENT PRE-STARTUP AND STARTUP CHECKLIST CUSTOMER: ADDRESS: PHONE: JOB NAME: LOCATION: CUSTOMER ORDER NO: TEL NO: ORDER NO: CONTRACT NO: CHILLER MODEL

More information

Ground Fault Protection Improvements to Prevent Fires Description of problem and potential solutions Presented by Bill Brooks, PE Principal, Brooks

Ground Fault Protection Improvements to Prevent Fires Description of problem and potential solutions Presented by Bill Brooks, PE Principal, Brooks Ground Fault Protection Improvements to Prevent Fires Description of problem and potential solutions Presented by Bill Brooks, PE Principal, Brooks Engineering Code Official Panel Lead, SolarABCs 1 Ground-Fault

More information

SECTION AUTOMATIC TRANSFER SWITCHES

SECTION AUTOMATIC TRANSFER SWITCHES SECTION 26 36 23 AUTOMATIC TRANSFER SWITCHES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. General provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

Arc Flash Codes & Compliance: What You Need to Know to Deliver Both Protection and Performance

Arc Flash Codes & Compliance: What You Need to Know to Deliver Both Protection and Performance Arc Flash Codes & Compliance: What You Need to Know to Deliver Both Protection and Performance An arc flash can cause serious injury or death to anyone in its path. The National Electrical Code provides

More information

Safety Meeting Topic #37 NFPA 70E What is it?

Safety Meeting Topic #37 NFPA 70E What is it? Safety Meeting Topic #37 NFPA 70E What is it? The National Fire Protection Association (NFPA) 70E is the standard for Electrical Safety Requirements for Employee Workplaces and is a supplement to the NFPA70

More information

Informational Bulletin on Mobile office Units Prepared by Mark Hilbert May 17, 2017

Informational Bulletin on Mobile office Units Prepared by Mark Hilbert May 17, 2017 Informational Bulletin on Mobile office Units Prepared by Mark Hilbert May 17, 2017 It has come to the attention of the electrical authorities having jurisdiction (AHJs) at the DOE sites there is inconsistency

More information

2017 NEC Presented by: Russ LeBlanc

2017 NEC Presented by: Russ LeBlanc 2017 NEC Presented by: Russ LeBlanc 1. 90.2(A)-installation and removal 2. 90.3-code layout 3. 100-readily accessible 4. 100-field evaluation body (FEB) 5. 100-field labeled 6. 100-receptacle 7. 100-structure

More information

HESNI ANNUAL CONFERENCE May 3, 2012 Aramark Conference Center, Downers Grove

HESNI ANNUAL CONFERENCE May 3, 2012 Aramark Conference Center, Downers Grove HESNI ANNUAL CONFERENCE May 3, 2012 Aramark Conference Center, Downers Grove Jim Dungar, P.E. Principal Engineer Schneider Electric Engineering Services Jim.dungar@schneider-electric.com (920-766-8012)

More information

Monitoring of Electrical Equipment Failure Indicators and Alarming

Monitoring of Electrical Equipment Failure Indicators and Alarming Past, Present and Future Maintenance Practices: Monitoring of Electrical Equipment Failure Indicators and Alarming Author: Gabe Paoletti, P.E. Eaton Corporation Senior Member, IEEE gabrieljpaoletti@eaton.com

More information

A. Section includes distribution panelboards and lighting and appliance branch-circuit panelboards.

A. Section includes distribution panelboards and lighting and appliance branch-circuit panelboards. SECTION 262416 - PANELBOARDS PART 1 - GENERAL 1.1 SUMMARY A. Section includes distribution panelboards and lighting and appliance branch-circuit panelboards. 1.2 PERFORMANCE REQUIREMENTS A. Seismic Performance:

More information

1. Distribution panelboards. 2. Lighting and appliance branch-circuit panelboards. 3. Load centers.

1. Distribution panelboards. 2. Lighting and appliance branch-circuit panelboards. 3. Load centers. September 2012, rev. 00 26 2416 Panelboards PART 1. GENERAL 1.01 Summary A. Section includes: 1.02 Definitions 1. Distribution panelboards. 2. Lighting and appliance branch-circuit panelboards. 3. Load

More information

T22 - Arc Flash Hazards and Arc Resistant Equipment- Understanding the Standards

T22 - Arc Flash Hazards and Arc Resistant Equipment- Understanding the Standards T22 - Arc Flash Hazards and Arc Resistant Equipment- Understanding the Standards v2-5058-co900h Copyright 2016 Rockwell Automation, Inc. All Rights Reserved. 1 Agenda 1. Background 2. Related Electrical

More information

SECTION AUTOMATIC TRANSFER SWITCHES

SECTION AUTOMATIC TRANSFER SWITCHES PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 36 23 This section specifies the furnishing, complete installation, and connection of automatic transfer switches. 1.2 RELATED WORK A. Section 14 21 00, ELECTRIC

More information

TABLE OF CONTENTS CHAPTER 5 SPECIAL OCCUPANCIES CHAPTER 1 GENERAL RULES... 19

TABLE OF CONTENTS CHAPTER 5 SPECIAL OCCUPANCIES CHAPTER 1 GENERAL RULES... 19 TABLE OF CONTENTS About This Textbook...xiii How to Use the National Electrical Code... 1 Article 90 Introduction to the National Electrical Code... 7 90.1 Purpose of the NEC... 7 90.2 Scope of the NEC...

More information

Building Division 201 SE 3 rd STREET (Second Floor) OCALA, FL Phone: (352) BUILDING CODE GUIDELINES FOR ELECTRICAL INSPECTIONS

Building Division 201 SE 3 rd STREET (Second Floor) OCALA, FL Phone: (352) BUILDING CODE GUIDELINES FOR ELECTRICAL INSPECTIONS BUILDING CODE GUIDELINES FOR ELECTRICAL INSPECTIONS Building Code compliance is the obligation of design professionals and/or contractors. Plan Review and Inspection Guidelines are intended to be used

More information

IMPROVE SAFETY WITH ARC FLASH LABELING COMPLY WITH THE 2015 NFPA 70E REGULATIONS

IMPROVE SAFETY WITH ARC FLASH LABELING COMPLY WITH THE 2015 NFPA 70E REGULATIONS IMPROVE SAFETY WITH ARC FLASH LABELING COMPLY WITH THE 2015 NFPA 70E REGULATIONS By Thomas Smith, Product Specialist, Brady Corporation Last updated: February, 2015 The Occupational Safety and Health Administration

More information

Property risk solutions

Property risk solutions Property risk solutions Inside this issue Welcome to this edition of the Property risk solutions newsletter. This quarterly publication focuses on fixed fire protection and human element safety solutions

More information

Subcontract Agreement No.

Subcontract Agreement No. ATTACHMENT G TRADE INTERFACE AGREEMENT Subcontract Agreement No. PROJECT: TEXASTECH UNIVERSITY HEALTH SCIENCES CAMPUS, EL PASO, TEXAS MEDICAL SCIENCE BUILDING II PARTICIPANTS: Sundt Construction, Inc.

More information

Student Services & Classroom Addition. A. Section includes distribution panelboards and lighting and appliance branch-circuit panelboards.

Student Services & Classroom Addition. A. Section includes distribution panelboards and lighting and appliance branch-circuit panelboards. SECTION 262416 - PANELBOARDS PART 1 - GENERAL 1.1 SUMMARY A. Section includes distribution panelboards and lighting and appliance branch-circuit panelboards. 1.2 PERFORMANCE REQUIREMENTS A. Seismic Performance:

More information

Guide to Compliance with the Electrical Workplace Safety Standards in the United States

Guide to Compliance with the Electrical Workplace Safety Standards in the United States Guide to Compliance with the Electrical Workplace Safety Standards in the United States July 2011/1910DB1102 by Joseph H. Weigel, Product Manager Schneider Electric USA, Inc. Make the most of your energy

More information

Electrical Safety Program

Electrical Safety Program Electrical Safety Program Developed by: The Office of Environmental Health and Safety June, 2010 Table of Contents Introduction 3 Scope..3 Definitions.3-5 CSU Electrical Shop...5 Responsibilities.5-6 Employees.....5

More information

Hazardous Location Certified

Hazardous Location Certified Certified. Not Modified. EONA2-72 and EXNDA/EONDA90-240 2,000 BTUH (3.5Kw) to 240,000 BTUH (70.3Kw) Increased Safety Vertical Wall Mount Air Conditioners General Description EXNA60 The old approach to

More information

Risk Mitigation of Aging Electrical Infrastructure

Risk Mitigation of Aging Electrical Infrastructure Risk Mitigation of Aging Electrical Infrastructure 2014 WWOA Annual Conference 10:55am Thursday October 9 th, 2014 Presented by and Authored by Jeff M. Miller, PE, ENV SP About the Presenter Jeff M. Miller,

More information

ITC 2000 HEATING CONTROL CABINET. Installation & Operation Manual

ITC 2000 HEATING CONTROL CABINET. Installation & Operation Manual ITC 2000 HEATING CONTROL CABINET Installation & Operation Manual VTI, Incorporated 24 McMillan Way Newark, DE 19713 Phone (302) 738 0500 FAX (302) 738 6594 Revision Level 0.03 Manual No. 90003314 June,

More information

AFCI. RECEPTACLEFAQs. What is an arc fault? What causes arc faults?

AFCI. RECEPTACLEFAQs. What is an arc fault? What causes arc faults? RECEPTACLEFAQs AFCI 1 What is an arc fault? UL provides a definition for an arc fault in UL 1699 (Standard for Safety Arc Fault Circuit Interrupters). It is an unintentional arcing condition in a circuit.

More information

Short Circuit Current Rating

Short Circuit Current Rating Short Circuit Current Rating Customer Need There has been a significant increase in the misapplication of control panel products that brings into question the safety of those installing and using this

More information

Guide Specification Model CTG Automatic Transfer Switch

Guide Specification Model CTG Automatic Transfer Switch Guide Specification Model CTG Automatic Transfer Switch PART 1 GENERAL 1.1 Scope A. It is the intent of this specification to secure a transfer switch that has been prototype tested, factory built, production

More information

9/7/2010. Chapter , The McGraw-Hill Companies, Inc. AND BONDING. 2010, The McGraw-Hill Companies, Inc.

9/7/2010. Chapter , The McGraw-Hill Companies, Inc. AND BONDING. 2010, The McGraw-Hill Companies, Inc. Chapter 1 GROUNDING AND BONDING 1 Proper grounding practices protect people from the hazards of electric shock and ensure the correct operation of overcurrent protection devices. Grounding is the intentional

More information

Electrical Energy department

Electrical Energy department Al-Balqa Applied University Power systems Protection course Dr Audih al-faoury Electrical Energy department 2018-2019 Department of Electrical Energy Engineering 1 Part 1 Power System protection Introduction

More information

PGR-8800 TECHNICAL FAQ

PGR-8800 TECHNICAL FAQ PGR-8800 SOLAR ARC-FLASH PRODUCTS RELAY CATALOG TECHNICAL FAQ What are the typical applications / system voltages? The PGR-8800 can be used on electrical systems operating at any voltage (AC or DC) since

More information

ANSI/NETA Standards Update

ANSI/NETA Standards Update Specifications and Standards Activity ANSI/NETA Standards Update NOW AVAILABALE!!!! NETA Standard for Acceptance Testing Specifications for Electrical Power Equipment and Systems The NETA Acceptance Testing

More information

US Navy Leading the Way in Switchboard Protection

US Navy Leading the Way in Switchboard Protection US Navy Leading the Way in Switchboard Protection Rick Kurek Naval Sea Systems Command (NAVSEA) 2341 Jefferson Davis Highway Arlington, VA 22202 Ph: 202-781-1274 rick.kurek@navy.mil Abstract According

More information

Arc Flash Protection Training - NFPA 70e Electrical Safety

Arc Flash Protection Training - NFPA 70e Electrical Safety Arc Flash Protection Training - NFPA 70e Electrical Safety Contact us Today for a FREE quotation to deliver this course at your company?s location. https://www.electricityforum.com/onsite-training-rfq

More information

Ammonia Detection System Codes and Design Specifications

Ammonia Detection System Codes and Design Specifications Ammonia Detection System Codes and Design Specifications January 15, 2018 Revision 6 Ammonia detection system codes and design specifications Following is a discussion of ammonia detection system design

More information

Pilz Safety Lockout System (PSLS)

Pilz Safety Lockout System (PSLS) Pilz Safety Lockout System (PSLS) An alternative isolation method for LOTO By Doug Sten, Safety Consultant, Pilz Automation Safety Objectives Challenges with manual, mechanical isolation disconnects Challenges

More information

Overview of Significant 2017 NEC Changes

Overview of Significant 2017 NEC Changes Overview of Significant 2017 NEC Changes National Fire Protection Association. All rights reserved. Five New NEC Articles Article 426 Fixed Resistance and Electrode Industrial Heating Equipment Article

More information

Electrical Safety Through Design. Mersen EP formerly Ferraz Shawmut

Electrical Safety Through Design. Mersen EP formerly Ferraz Shawmut Electrical Safety Through Design Mersen EP formerly Ferraz Shawmut Agenda Who is Mersen? Selective Coordination Code Requirements Coordination Made Easy Mitigating Arc Flash Energy on Transformer Secondary

More information

SEL Arc-Flash Solutions

SEL Arc-Flash Solutions SEL Arc-Flash Solutions Arc-Flash Protection at the Speed of Light Protect personnel and equipment Detect arc-flash events and send a trip signal in as little as 2 ms to enhance safety and minimize equipment

More information

WHY ELECTRICAL PREVENTIVE MAINTENANCE IS ESSENTIAL TO A SAFE AND PRODUCTIVE WORKPLACE

WHY ELECTRICAL PREVENTIVE MAINTENANCE IS ESSENTIAL TO A SAFE AND PRODUCTIVE WORKPLACE WHY ELECTRICAL PREVENTIVE MAINTENANCE IS ESSENTIAL TO A SAFE AND PRODUCTIVE WORKPLACE AGENDA SCRWA 14 SEPTEMBER 2016 Definition Why EDPM is essential to productivity Fiscal sustainability Why EDPM is essential

More information

ASSESSING THE HIDDEN DANGERS IN YOUR INDUSTRIAL CONTROL PANELS

ASSESSING THE HIDDEN DANGERS IN YOUR INDUSTRIAL CONTROL PANELS Schneider Electric NEC 409.2 January 15, 2008 ASSESSING THE HIDDEN DANGERS IN YOUR INDUSTRIAL CONTROL PANELS by Grant Van Hemert, P.E., application engineer, Water and Wastewater Competency Center, Schneider

More information

SYSCO CENTRAL PENNSYLVANIA, LLC. HARRISBURG, PENNSYLVANIA

SYSCO CENTRAL PENNSYLVANIA, LLC. HARRISBURG, PENNSYLVANIA SYSCO CENTRAL PENNSYLVANIA, LLC. HARRISBURG, PENNSYLVANIA July, 2018 Infrared Inspection Report Sysco Central Pennsylvania, LLC. 3905 Corey Road Harrisburg, Pennsylvania, 17109 Company Contact Christopher

More information

Electric Shock Drowning

Electric Shock Drowning Electric Shock Drowning Your logo here Electric Shock Drowning Navigating Changing Code Requirements Slide 1 Electric Shock Drowning - Safety and Maintenance 2 What is Electric Shock Drowning? Electric

More information

Building Electrical System Overview

Building Electrical System Overview Philip Mackey L/E Dr. Mistrick Holy Cross Hospital North Addition Silver Spring, MD 0/3/05 Building Electrical System Overview Executive Summary: The following report describes the existing emergency power

More information

Arc Flash Analysis: IEEE Method versus the NFPA 70E Tables July 2017 / 1910DB1702

Arc Flash Analysis: IEEE Method versus the NFPA 70E Tables July 2017 / 1910DB1702 Arc Flash Analysis: IEEE Method versus the NFPA 70E Tables July 2017 / 1910DB1702 by Reza Tajali, Schneider Electric Engineering Services Summary 1.0 Abstract 2.0 OSHA and NFPA Rules 3.0 Use of NFPA 70E

More information

Lord Stirling Community School Electrical Systems Existing Conditions & Building Load Summary Technical Assingment#2 Due October 26, 2004

Lord Stirling Community School Electrical Systems Existing Conditions & Building Load Summary Technical Assingment#2 Due October 26, 2004 Electrical Systems Existing Conditions & Building Load Summary Technical Assingment#2 Due October 26, 2004 Table of Content: Page 1 ~ Single Line Diagram 1 2 ~ Electrical System Narrative 2-3 3 ~ Lamp

More information

TABLE LIGHTING POWER DENSITIES FOR BUILDING EXTERIORS ASHRAE Uncovered Parking Areas. Building Grounds. Walkways 10 feet wide or greater

TABLE LIGHTING POWER DENSITIES FOR BUILDING EXTERIORS ASHRAE Uncovered Parking Areas. Building Grounds. Walkways 10 feet wide or greater TABLE 9.4.5 LIGHTING POWER DENSITIES FOR BUILDING EXTERIORS ASHRAE 90.1 Uncovered Parking Areas Parking Lots and drives Building Grounds Walkways less that 10 feet wide Walkways 10 feet wide or greater

More information

APPENDIX - L INTERNATIONAL RESIDENTIAL CODE ELECTRICAL

APPENDIX - L INTERNATIONAL RESIDENTIAL CODE ELECTRICAL This Appendix (2000 IRC Appendix-L) is produced, copyrighted, and maintained by the National Fire Protection Association Association, all rights reserved. Use of this Appendix is pursuant to license with

More information

SEL Arc-Flash Solutions

SEL Arc-Flash Solutions SEL Arc-Flash Solutions Arc-Flash Protection at the Speed of Light Protect personnel and equipment. Detect arc-flash events and send a trip signal in as little as 2 ms to enhance safety and minimize equipment

More information

Ground Fault Protection Improvement Study

Ground Fault Protection Improvement Study Ground Fault Protection Improvement Study Greg Ball DNV KEMA Solar ABCs Stakeholder Meeting July 11, 2013 San Francisco, CA Study Authors 2 Bill Brooks Brooks Engineering Andy Rosenthal New Mexico State

More information

DLCSRA. INSTALLATION INSTRUCTIONS Outdoor Unit Ductless Split System Sizes 09 to 36 TABLE OF CONTENTS

DLCSRA. INSTALLATION INSTRUCTIONS Outdoor Unit Ductless Split System Sizes 09 to 36 TABLE OF CONTENTS DLCSRA INSTALLATION INSTRUCTIONS Outdoor Unit Ductless Split System Sizes 09 to 36 NOTES: Read the entire instruction manual before starting the installation. Images are for illustration purposes only.

More information

BASIC ELECTRICAL ENGINEERING FOR CE

BASIC ELECTRICAL ENGINEERING FOR CE EE24 BASIC ELECTRICAL ENGINEERING FOR CE LECTURE NO. B-2 Basic Electrical Code Provisions Codes/Standards/Organizations PEC Philippine Electrical Code NEC National Electrical Code IEEE - Institute of Electrical

More information

elite Model ELN Centralized Emergency Lighting Inverter Systems 550 W to 1.5 KW Systems

elite Model ELN Centralized Emergency Lighting Inverter Systems 550 W to 1.5 KW Systems 5/25/16 rev 6 elite Model ELN General Specification 550 W to 1.5 KW elite Model ELN Centralized Emergency Lighting Inverter Systems 550 W to 1.5 KW Systems 1.0 General General Specification This specification

More information

MODEL SST 2 40 FREEZE PROTECTION THERMOSTAT MODEL SST FIXED SET POINT THERMOSTAT. Installation and Operation Manual

MODEL SST 2 40 FREEZE PROTECTION THERMOSTAT MODEL SST FIXED SET POINT THERMOSTAT. Installation and Operation Manual Electronic Thermostats with Ground Fault Equipment Protection MODEL SST 2 40 FREEZE PROTECTION THERMOSTAT P/N 22744 MANUAL We Manage Heat MODEL SST 2 175 FIXED SET POINT THERMOSTAT P/N 23708 Installation

More information

A. This Section includes transfer switches rated 600 V and less, including the following:

A. This Section includes transfer switches rated 600 V and less, including the following: SECTION 16415 - TRANSFER SWITCHES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

ENGINE GENERATORS AND ACCESSORIES

ENGINE GENERATORS AND ACCESSORIES ENGINE GENERATORS AND ACCESSORIES GENERAL INFORMATION 1.1 This section applies to engine generators and accessories. DESIGN REQUIREMENTS 2.1 The Engineer of Record will consult with the University s Engineering

More information

THE WALL-MOUNT ONE TON AIR CONDITIONER GREEN REFRIGERANT R-410A. 10,800 Btuh 9.00 EER Right Side Control Panel. Engineered Features

THE WALL-MOUNT ONE TON AIR CONDITIONER GREEN REFRIGERANT R-410A. 10,800 Btuh 9.00 EER Right Side Control Panel. Engineered Features THE WALL-MOUNT ONE TON AIR CONDITIONER W2A,800 Btuh 9.00 EER Right Side Control Panel 60Hz GREEN REFRIGERANT R-A The Bard Wall-Mount One Ton Air Conditioner is a self contained energy efficient heating

More information

THE WALL-MOUNT ONE TON AIR CONDITIONER. Green Refrigerant. 12,000 Btuh EER Right Side Control Panel. Engineered Features

THE WALL-MOUNT ONE TON AIR CONDITIONER. Green Refrigerant. 12,000 Btuh EER Right Side Control Panel. Engineered Features THE WALL-MOUNT ONE TON AIR CONDITIONER W2AAA 2,000 Btuh.00 EER Right Side Control Panel 60Hz Green Refrigerant R-4A The Bard Wall-Mount One Ton Air Conditioner is a self contained energy efficient heating

More information

Understanding NFPA, NEC 2005 Article 409 a White Paper by Paul A. Terry, P.E.

Understanding NFPA, NEC 2005 Article 409 a White Paper by Paul A. Terry, P.E. a White Paper by Paul A. Terry, P.E. NFPA 70, NEC 2005: Article 409 Industrial Control Panel Short Circuit Panel Ratings Executive Summary Many panel shops are providing industrial control panels with

More information

CENTERLINE 2100 Motor Control Center (MCC) Doors and Units with Vertical Operating Handles

CENTERLINE 2100 Motor Control Center (MCC) Doors and Units with Vertical Operating Handles Installation Instructions Original Instructions CENTERLINE 2100 Motor Control Center (MCC) Doors and Units with Vertical Operating Handles Bulletin Number 2100 Topic Page About This Publication 1 Important

More information

SECTION : MEPS IDENTIFICATION & LABELING

SECTION : MEPS IDENTIFICATION & LABELING SECTION 01 70 10: MEPS IDENTIFICATION & LABELING 1. GENERAL A. The intent of this section is to define the labeling and identification requirements for building mechanical, electrical, plumbing, and specialty

More information

DLCLRA. INSTALLATION INSTRUCTIONS Outdoor Unit Single Zone Ductless System Sizes 36 to 58 TABLE OF CONTENTS

DLCLRA. INSTALLATION INSTRUCTIONS Outdoor Unit Single Zone Ductless System Sizes 36 to 58 TABLE OF CONTENTS DLCLRA INSTALLATION INSTRUCTIONS Outdoor Unit Single Zone Ductless System Sizes 36 to 58 Fig. 1 - Size 36 TABLE OF CONTENTS PAGE SAFETY CONSIDERATIONS... 2 PARTS LIST... 3 SYSTEM REQUIREMENTS... 4 WIRING...

More information

2014 National Electrical Code & NFPA 70E/Arc Flash

2014 National Electrical Code & NFPA 70E/Arc Flash Gain an understanding of the 2014 NEC s latest additions, revisions and changes. Learn the precautions needed when working with and around electricity. People and property need to be safeguarded from the

More information

2009 ELECTRICAL CODE REQUIREMENTS

2009 ELECTRICAL CODE REQUIREMENTS 2009 ELECTRICAL CODE REQUIREMENTS ANTRIM COUNTY BUILDING DEPARTMENT PO BOX 188 205 CAYUGA STREET BELLAIRE, MI 49615 (231) 533-8373 FAX (231) 533-6041 Inspection Request Line (231) 533-3510 Electrical requirements

More information

Wiring Diagrams Units Produced After April 20, 2009

Wiring Diagrams Units Produced After April 20, 2009 UNIT 38AH 0-034 Wiring Diagrams Units Produced After April 20, 2009 (Includes Variable Air Volume ModuPanel Control) ELECTRICAL CHARACTERISTICS (V-Ph-Hz) 208/-3-60, 460-3-60 575-3-60 380-3-60-3-50, 380/415-3-50

More information

Liebert Fin/Tube Condenser Warranty Inspection Check Sheet

Liebert Fin/Tube Condenser Warranty Inspection Check Sheet The following information must be fully completed and forwarded to your local Liebert sales office to establish your equipment warranty. Installer Address Owner Address Owner e-mail address Installation

More information

Installation Instructions

Installation Instructions 38MHR Outdoor Unit Single Zone Ductless System Sizes 09 to 24 Installation Instructions NOTE: Read the entire instruction manual before starting the installation. NOTE: Images are for illustration purposes

More information

Element D Services Electrical

Element D Services Electrical PART 1 - GENERAL 1.01 OVERVIEW A. This Section includes design standards and requirements for electrical service and distribution. This is a design standard and is not intended to be used as a Specification.

More information

XRRS Specification Fire Ready Hood

XRRS Specification Fire Ready Hood XRRS Specification Fire Ready Hood ************************************************************************************************************************ Note to User: This document is subject to copyright

More information

Installation Instructions

Installation Instructions 40MBFQ Floor Console Ductless System Sizes 09 to 58 Installation Instructions TABLE OF CONTENTS PAGE SAFETY CONSIDERATIONS... 2 PARTS LIST... 3 SYSTEM REQUIREMENTS... 4 WIRING... 4 DIMENSIONS... 5 CLEARANCES...

More information

Heat Recovery Units. EXTERNAL STATIC REQUIRED (in.h2o) (Pa) MOTOR (Bhp/Hp) (bkw/kw) SPEED (rpm)

Heat Recovery Units. EXTERNAL STATIC REQUIRED (in.h2o) (Pa) MOTOR (Bhp/Hp) (bkw/kw) SPEED (rpm) Heat Recovery Units AIR HANDLING UNIT No. SERVICE AREA MANUFACTURER MODEL HRU-3 & HRU-4 B-Section Low Rate Ventilation Tempeff RG 16000 (9500) SUPPLY FAN - SIZE/TYPE AIRFLOW RATE (cfm) (l/s) TOTAL STATIC

More information

Spring Test 6 due 04/26/2013

Spring Test 6 due 04/26/2013 Spring Test 6 due 04/26/2013 Multiple Choice Identify the letter of the choice that best completes the statement or answers the question. 1. The article that covers TV wiring installations in residences

More information

NFPA 70E Arc Flash Considerations for MV Equipment. By: Dominik Pieniazek, P.E. HV Engineering, LLC

NFPA 70E Arc Flash Considerations for MV Equipment. By: Dominik Pieniazek, P.E. HV Engineering, LLC NFPA 70E Arc Flash Considerations for MV Equipment By: Dominik Pieniazek, P.E. dominik@hv-eng.com HV Engineering, LLC http://sites.ieee.org/houston/ Full link for PDF copies of presentations: http://sites.ieee.org/houston/communities/ie

More information