1 I. Base Bidding Requirements Attachment A 00 Boiler Replacement This is a Base Bid project; the following describes the Base Bid requirements. Contractors are to provide bids for Base Bid #1. BASE BID #1 All work listed II. Work Included The following items are site specific requirements of the project. A. The project is intended to provide for the replacement of the existing #1 boiler, burner, and associated controls and safety devices to match the system of Boiler # 2. B. The Contractor shall provide and perform all labor, material, apparatus, trucking, tools, demolition, superintendence, and service required for the completion of the work. C. The Contractor is responsible for obtaining all permits, inspections, and certifications. A copy of all required shall be provided to the Facilities Administrator. D. The Contractor shall coordinate all aspects of this project with PENNDOT -0 Facilities, and Maintenance Units. E. The Contractor shall be responsible for providing and installing a new boiler per the specifications and scope of work, including addendum(s). The specifications and scope of work will be refined at the scheduled pre-bid meeting and changes disseminated prior to the bid opening date. F. The Department shall have the option of retaining ownership of all serviceable boiler sections, burner, controls, and safety devices not reused from the existing boiler. Unserviceable boiler sections, burner, controls, and safety devices from the existing boiler or unwanted parts shall become the property of the contractor and shall be removed from the premises. Page 1 of 12

2 00 Boiler Replacement G. When existing equipment meets or exceeds this specification, does not require extensive modification, and is verified to be in good working condition, the Department requires the contractor re-use the equipment. H. The Contractor shall provide and perform field modifications to existing piping, connections, mounting pad, gas supply and distribution lines/manifold, exhaust, valves, shut-offs, etc. as necessary and required to complete the project in accordance with the contractors design and installation requirements. I. The new boiler controls shall be compatible with and shall be connected to the existing building automation system by fully trained and qualified technician(s). III. SECTION HVAC BOILERS AND RELATED EQUIPMENT A. GENERAL 1.1 STIPULATIONS A. The specification section "General Conditions", "Special Requirements" and General Requirements form a part of this section and shall have the same force and effect as if printed herewith in full. B. The specification Section HVAC GENERAL forms a part of this section and shall have the same force and effect as if printed herewith in full. C. When existing equipment meets or exceeds this specification, does not require extensive modification, and is verified to be in good working condition, the Department may require the contractor re-use the equipment. 1.2 GENERAL A. The boiler, tanks, safety devices, piping, accessories, etc., in the boiler room shall meet the requirements of the Pennsylvania Department of Labor & Industry, Boiler Division. B. The Contract Drawings have received preliminary approval from the Boiler Division. It shall be the responsibility of this Contractor to furnish and install the equipment and accessories so that the complete installation will meet the Boiler Division's current requirements. This work will not be considered complete until after final approval of the boiler room is given by the Boiler Division. Page 2 of 12

3 00 Boiler Replacement C. The Contractor is responsible for obtaining all permits, approvals, and inspections required for boiler operation and certification. B. PRODUCTS A. BOILER/BURNER UNITS (CAST IRON) B. Provide boiler burner unit designed for use with flame retention type combination power gas burner capable of burning gas. C. The boilers will be of a low pressure, cast-iron, sectional type capable of developing full I-B-R gross output capacity of 100% firing rate. The boilers shall have pressurized fireboxes for forced draft and the burners shall be capable of delivering the necessary air for proper combustion and to pressurize the firebox. D. The boiler shall be a H. B. Smith Model 28A-SW-11or approved equal, with burners capable of burning gas. E. The boilers shall be constructed in accordance with the provisions of Section IV of the ASME boiler and Pressure Vessel Code and shall be stamped with the required official ASME symbol and meet all requirements of the Pennsylvania Department of Labor and Industry Boiler Division. Each boiler section shall be hydrostatically tested for 50 psig ASME working pressure. F. The boilers shall be capable of being overfired up to 20% or underfired as much as 20% providing burner capacity is adequate and adjustments are made for good combustion at the actual firing rate. G. The boilers shall be tested in accordance with the requirements of the Hydronics Institute (Institute of Boiler and Radiator Manufacturer's) and shall have 2,201 MBH per hour I=B=R net capacity rating at one-hundred percent firing rate. H. Flame safety guard controls shall automatically restart the boiler firing sequence only in the event of a power failure. I. The boiler sections shall be assembled with individual draw rods that distribute tension evenly on all boiler sections. The boiler sections will not be face ground in order that the corrosion protective outer skin will remain intact. The boiler sections shall be provided with accommodating sealing grooves and high temperature sealing rope shall be employed to assure a permanent gas-tight seal between the sections. The sealing rope shall be compressible and shall be impervious to heat and moisture. J. The boilers shall be provided with a flexible elastomer sealing ring for each port opening to assure a permanent water-tight seal between the boiler sections. Each section shall be provided with aligning lugs to assure positive alignment with the adjoining sections. Page 3 of 12

4 00 Boiler Replacement K. The boilers shall be provided with a flue collar adaptor with adjustable built-in breeching damper. Flue shall be top or back outlet to match existing. L. The water boiler shall be provided with built-in air elimination system to assure positive separation of air from circulating water. Separated air shall be diverted to the compression tanks from the compression tank tappings located at the top of the boilers. The water boilers shall be constructed to provide balanced water flow through the entire section assembly so that single supply and return connections can be employed; external headers will not be necessary. M. The boilers shall be of a compact low silhouette design to assure minimal space for headroom clearance and for servicing. N. The boiler sections shall be of the Hydro-Wall design to provide a completely water-backed combustion area with water circulated around the entire firebox. O. The boiler sections shall be provided with integral, cast-on legs to maintain ample space between the bottom of the boiler sections and the boiler foundation for natural aeration. P. The boilers shall be furnished with refractory insulated burner mounting plates, which shall be provided with the necessary holes and tappings to mount the burners. High temperature sealing rope shall be employed to provide a permanent gas-tight seal between the front sections and the burner mounting plates. Q. The boilers shall be furnished with observation ports, which shall be mounted on the front sections to permit visual inspection of the burner flame. R. The boilers shall be designed to assure efficient and rapid heat transfer from the combustion gases to the boiler water. The firebox design shall insure maximum radiant heat transfer from the burner flame, and the boiler sections shall be provided with cast-on heat absorbing studs for an enlarged prime heating surface. S. The boilers shall be designed to provide vertical to horizontal flue gas travel, and a horizontal flueway shall be cast into each intermediate section and back section to serve as an internal flue gas collector. T. The boilers shall be furnished with heavy gauge steel cleanout opening covers for the cleanout openings at the top of the boilers. High temperature sealing gaskets shall be employed to insure a permanent gas-tight seal between the boiler sections and the cleanout opening covers. The cleanout opening covers shall be readily removable for the purpose of cleaning the flueways between the boiler sections. U. The front and back sections of the boilers shall be provided with water passage inspection tappings at the bottom and just above the crown sheet. Page 4 of 12

5 00 Boiler Replacement V. The boilers shall be provided with insulated heavy gauge steel jackets with durable baked enamel finish. The jackets shall be insulated with heavy density, fiberglass on the front, back, top and side panels. The jackets shall be designed to permit installation after the connection of the supply and return piping. W. All electrical safety boiler controls are to be of accepted quality manufacture bearing UL Certification. X. Water Boiler Standard Controls 1. The boilers shall be furnished with combination low temperature limit operating and high temperature limit controls. The low temperature limit control shall be set according to the design requirements of the heating system. The high temperature limit control should be set at least 20 F higher than the low limit control setting (250 F maximum allowable boiler water temperature). 2. The boilers shall be furnished with combination pressure- temperature gauges to indicate boiler water temperature and system pressure; the combination gauges shall be of rugged guarded type construction and the gauge dial shall be clearly marked and easy to read. 3. The boilers shall be furnished with ASME certified pressure relief valves and the valves shall be set to relieve at the rated boiler ASME working pressure. The relief valves shall be of the side outlet discharge type. Y. The boilers shall be furnished with UL certified low water fuel cut-offs. The low water fuel cut-off shall have an ASME working pressure rating of at least the ASME working pressure of the boiler. Required if not already installed Discuss at Pre-Bid Meeting Z. The burner motor and control electrical characteristics shall be [120V/60 Hz/1 phase] match to existing. Discuss at Pre-Bid meeting. AA. The gas burner shall be UL certified and shall be of a design which produces flame retention with rapid intimate mixing of the fuel and combustion air. The burner shall be designed to insure high efficiency and good performance under either balanced draft or forced draft venting conditions. BB. The combination gas burners shall be arranged for on-off operation with pre-purge, low fire start, high fire run, and one-position air control. The burner shall be furnished with a prewired control panel which incorporates an electronic combustion safeguard burner primary control with pre-purge timing and an ultraviolet sensitive electronic flame detector Page 5 of 12

6 00 Boiler Replacement CC. For gas firing, each burner unit shall be complete with main as shutoff cock with wrench, spring loaded gas pressure regulator, Maxon Series 5000 main electric valve, ASCO vent valve, Honeywell V4055A block gas valve, Honeywell C437 high and low gas pressure switches with manual reset, gas regulating cock, and gas pressure gauge. Burner train shall be sized for a minimum pressure of 7 oz. to inlet of gas pressure regulator at burner, all to meet [FM] [IRI] approval. Discuss the use of existing equipment at pre-bid meeting. When existing equipment meets or exceeds this specification, does not require extensive modification, and is verified to be in good working condition, the Department may require the contractor re-use the equipment. i. Additionally, provide the following: 1. Stack thermometers mounted at boiler flue outlet 2. Low fire hold switches 3. ASME pressure temperature gauges 4. Necessary relief valves 5. Boiler burner mounted fused disconnect to allow one electric connection by Electrical Contractor, all other power and control wiring by this Contractor. 6. Fireye FP-2 combination control or equal. 7. Honeywell L4006A aquastat to maintain constant boiler water temperature. 8. (1) A second Honeywell L4006A aquastat to function as a high limit. 9. (2) Low water cut off mounted in boiler 10. [Limit switches, flame failure, fuel valves, etc., all [FM] [IRI] approved starters, switches, relays and transformers, all mounted and factory wired in a totally enclosed cabinet with three (3) panel mounted signal lights (limit pilot and main).] Match existing, Discuss at Pre-Bid meeting 11. Lead-lag switch (single 4PDT manual toggle switch). DD. Provide all additional controls to meet [FM] [IRI] requirements.] Match existing, Discuss at Pre-Bid meeting EE. The boiler manufacturer shall appoint a Service Contractor who will conduct a prestart-up inspection of the boiler burner unit. The Service Contractor shall then Page 6 of 12

7 00 Boiler Replacement perform start-up service including the initial start of the unit after installation, including burner adjustments, an efficiency check test, and instructions to the Owner and/or Owner's representative as to the proper burner operation. In addition, the Service Contractor will provide free service on the complete burner for twelve (12) calendar months following initial start-up. FF. Service during the twelve-month period shall be performed as necessitated by the physical condition of the burner and burner controls, defective material, workmanship or improper start-up, and include replacement of defective parts. Service calls for reasons such as incorrect or inadequate wiring, improper or inadequate fuel supply, unusual operating conditions, misapplied controls of equipment of other manufacturers not a part of the burner shall be charged for on a time, material and mileage basis by the Service Contractor to this Contractor. 1.3 BOILER STACK AND BREECHING (DOUBLE WALL TYPE) If Required, Discuss at Pre-Bid Meeting A. Stack system and shall be laboratory tested and listed by the Underwriters Laboratory, Inc., for use with building heating equipment burning: gas, solid or liquid fuels, as described in NFPA 211. The System must maintain airtight integrity for flue gas temperatures up to 1000 F at pressure up to 60 inches of water column at room temperature. The system shall be designed to compensate for all flue gas induced thermal expansion. B. The materials and construction of the modular sections and accessories shall be as specified by the terms of the product's UL listing. C. The stack system shall be installed according to the manufacturer's installation instructions and shall comply with the following additional codes or standards: PA Department of Labor & Industry, Boiler Code Div. #34PA. D. The entire stack system from the boiler to the termination, including accessories, except as noted, shall be from one manufacturer. E. The double wall insulated chimney and breeching will have an outer jacket of aluminum coated steel at 0.025" minimum thickness. The inner gas carrying pipe shall be type 304 stainless steel. The inner liner shall be minimum 0.035" thick. A nominal one (1") inch air space shall exist between walls. F. All exposed chimney shall have type 304 stainless steel outer jacket with nominal thickness of 0.025". G. The inner pipe joints shall be sealed by use of V-bands and sealant as specified by the manufacturer's installation instructions. At higher temperatures the joints shall be sealed with Metalbestos high temperature joint cement. The chimney shall Page 7 of 12

8 00 Boiler Replacement comply with National Safety Standards and all building codes when installed according to the manufacturers' installation instructions. Chimneys extended above the roof must terminate as required by local code, or as required in NFPA 211. H. When installed according to the manufacturer's installation instructions the piping and its supporting system shall resist side loads at least 1.5 times the weight per foot of the piping. I. The chimney stack and breeching manufacturer shall warrant the complete system against functional failure due to defects in material and workmanship for 10 years from date of delivery. The system manufacturer shall be responsible for checking the sizing, design and installation for the system. If any component fails to perform its intended function of exhausting combustion by-products from the boiler equipment, for any reason within 1 year of shipment, the system supplier shall, at no expense to the owner, provide a replacement part or parts FOB jobsite. J. Drawings showing the actual layout and drawn to scale shall be provided by the manufacturer. The system shall be installed as designed by the manufacturer and in accordance with the terms of the manufacturer's warranty and in conjunction with sound engineering practice. K. The inner diameter for the stack shall be verified by the manufacturer's computations. The computation shall be technically sound, shall follow ASHRAE calculation methods, and incorporate the specific flow characteristics of the inner pipe. The contractor shall furnish the exact boiler model and operating characteristics to the factory representative. Operating characteristics shall include flue gas flow rate, BTU input, outlet temperature, local altitude, stack layout, and available external pressure at boiler outlet, etc., necessary to determine system operation at maximum and minimum levels of burner turndown range. L. Aluminized steel surfaces exposed to the elements shall be protected by a minimum of one base coat of primer and one finished coat of corrosion resistant paint suitable for outer jacket skin temperature of the particular installation (such as Series 4100 or 9400 as manufactured by Rust-oleum) or approved. Paint to be supplied by the installing contractor. (Outer wall of type 304 or 316 stainless steel may be substituted for paint). M. Technical Services Support: The factory-built modular stack system shall be furnished by a vendor organization which assures design, installation and services coordination and provides in-warranty and post-warranty unified responsibility for Owner, Professional and Contractor. N. The chimney stack and breeching shall be Model PS as manufactured by Selkirk Metalbestos with barometric damper or equal as accepted. Page 8 of 12

9 00 Boiler Replacement 1.4 BOILER BREECHING (Discuss requirement at Pre-Bid meeting) A. Furnish and install breeching size as required by boiler manufacturer and as indicated on the drawings. Breeching shall be 12 gauge black steel with all joints welded gas tight. C. EXECUTION 1.5 GENERAL A. This Contractor shall prepare a rough-in-layout of the boiler room floor. The layout shall show the exact location of boilers, compressors, starters, electrical stubs and plumbing stubs required for the installation. This layout will be used for coordination rough-ins of all trades. 1.6 BOILER A. General 1. The pressure parts including shop installed piping, shall be subjected to a hydrostatic test pressure of one and one-half times the safe working pressure. A certificate of inspection written by the Hartford Steam Boiler Inspection and Insurance Company or its equivalent, and a manufacturer's ASME Data Report shall be furnished for each boiler. 2. If required, this contractor shall modify the existing concrete boiler foundation according to the manufacturer's erecting instructions. 3. The relief valve outlet shall be piped to a floor drain or near to the floor: the relief valve discharge must not be piped to any area where freezing temperatures could occur. 4. The low water fuel cut-off shall be installed according to the manufacturer's instructions and must be located on the boiler so the burner will become de-energized should the boiler water level fall below the lowest safe waterline. 5. The entire fuel burner system and its installation shall conform with the manufacturer's erecting instructions, with applicable codes. All equipment and materials shall be installed in an approved and workmanlike manner and in accordance with the specifications. 6. Make tests after burner has been firing at rated capacity of a minimum of two (2) hours. Make second test at low-fire. Conduct each test (rated capacity and lowfire) for a test duration of two (2) hours minimum with readings taken every fifteen (15) minutes. Page 9 of 12

10 00 Boiler Replacement 7. Combustion efficiency, based on flue gas analysis, as an acceptable percentage shall be not less than 80%. 1.7 BOILER STACK AND BREECHING A. Breeching to be supported from building steel and with isolation mounts and insulation as herein specified. D. Submittals and final Deliverable items 1. Contractor to provide three (3) copies of the entire project documentation in three (3) ring Binders. 2. Binders to include the following items: a. Bid Documents & Specifications b. All project meeting minutes (pre-bid, pre-job, Interim, and Final inspection) c. Correspondence d. Submittals e. L&I approved Engineered Drawings (Paper/CD) f. L&I Building Permits, Inspection Logs, Other correspondence g. Certifications h. Certified Payrolls (Prevailing Wage rates) i. Waste receipts j. Photos Before, during and after i. A sufficient amount of Photos is required for all phases of construction on all buildings, base on award. k. Operation and Maintenance manuals l. Contractors Warranty m. Manufactures Warranty IV. SUBMITTAL PROCEDURE A. Submit Two (2) copies of all items shown on submittal schedule except for "samples". B. Identify project number, project name and location, and contractor's name and address on all submittals. C. Provide space for review stamps of Contractor and Department. Put contractor stamp of approval on each item submitted. Page 10 of 12

11 00 Boiler Replacement D. Revise and resubmit submittals as required, identify all changes made since previous submittal. E. No work shall be performed until all submittals are approved by the Department. Work performed prior to submittal approval is performed at the Contractor's risk and may be subject to repair, replacement or other corrective measures as deemed necessary by the Department with no additional contract time or money. F. Review of shop drawings will be general and for the limited purpose of checking for general conformance with the design; and shall not relieve the Contractor from the responsibility for proper fitting and construction of the work, nor from furnishing materials and work required by the Contract which may not be indicated on the shop drawings when reviewed. G. The submittals required by this contract are subject to reproduction for the Department's internal use only. By signature on this bid proposal, both the Contractor and the equipment manufacturer authorize the Department to reproduce any materials including printed literature and training aids, submitted in fulfillment of this contract. V. MANUFACTURER'S INSTRUCTIONS A. When specified in individual specification sections, submit manufacturer's printed instructions for delivery, storage, assembly, installation, start-up, adjusting and finishing, and maintenance, in quantities specified for product data. B. Identify conflicts between manufacturer's instructions and contract documents. VI. MANUFACTURER'S CERTIFICATES A. When specified in individual specification sections or on submittal schedule, submit manufacturer's certificates to for review. B. Indicate that material or product conforms to or exceeds specified requirements. Submit supporting reference date, affidavits and certifications as appropriate. C. Certificates may be recent or previous test results on material or product, but in all cases must be acceptable to Department. VII. SUBMITTAL SCHEDULE Page 11 of 12

12 00 Boiler Replacement A. Abbreviations: SoSu - Source of Supply DeDa - Descriptive Data or Catalog Cuts ShDr - Shop or Installation Drawings CoCh - Color Chart Cert - Certificates Samp Samples B. Schedule: Description of items to be submitted SoSu DeDa ShDr CoCh Samp Cert 1. Cost Breakdown X 2. Work Schedule X 3. Boiler Information X X X 4. Burner information X X X 5. Controls information X X X X 6. Permits and inspections 7. Steel product certifications X X X X 8. Warranties x X X 9. Certified payrolls X X X Page 12 of 12

PART 0 A/E INSTRUCTIONS 0.01 DESIGN REQUIREMENTS

PART 0 A/E INSTRUCTIONS 0.01 DESIGN REQUIREMENTS PART 0 A/E INSTRUCTIONS 0.01 DESIGN REQUIREMENTS A. General: 1. To obtain maintenance and repair standards for boiler burners (Section 15555A) and boiler tubes (Section 15555B), contact the DPS Project

More information

SECTION HEATING BOILERS

SECTION HEATING BOILERS SECTION 23 52 00 HEATING BOILERS PART 1 - GENERAL 1.1 SUMMARY A. Section includes boilers, controls and boiler trim, steam and condensate connections, hot water connections, fuel burning system and connections,

More information

SECTION WATER-TUBE BOILERS

SECTION WATER-TUBE BOILERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Specification Sections, apply to this Section. B. Related Sections

More information

HORIZONTAL FIRE TUBE BOILERS Piping (HVAC) Pumping Equipment (HVAC).

HORIZONTAL FIRE TUBE BOILERS Piping (HVAC) Pumping Equipment (HVAC). SECTION 15555 HORIZONTAL FIRE TUBE BOILERS PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 15510 - Piping (HVAC). 2. 15540 - Pumping Equipment (HVAC). 1.02 SUBMITTALS A. Submit properly identified

More information

SAMPLE SPECIFICATION FOR RIELLO ARRAY MODULATING BOILER

SAMPLE SPECIFICATION FOR RIELLO ARRAY MODULATING BOILER SAMPLE SPECIFICATION FOR RIELLO ARRAY MODULATING BOILER PART 1 GENERAL 1.01 RELATED DOCUMENTS A. ANSI Z21.13 American National Standard for Gas-Fired Low Pressure Steam and Hot Water Boilers B. ASME Section

More information

mith Mills Smith Mills 6500A 6500A-4 OIL OR GAS CAST IRON BOILER/BURNER CAST IRON

mith Mills Smith Mills 6500A 6500A-4 OIL OR GAS CAST IRON BOILER/BURNER CAST IRON mith Mills Mills 00A OIL OR GAS CAST IRON BOILER/BURNER Smith CAST IRON 00A- - Gas I=B=R Ratings: Gross Output 7,19 to 1, FRONT VIEW WITH INDUS COMB BURNER SIDE VIEW WITH INDUS COMB BURNER SIDE VIEW -

More information

Revitalize Building Mechanical Systems (4619)

Revitalize Building Mechanical Systems (4619) SECTION 235216 FIRE-TUBE CONDENSING BOILERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

GSB8. CONSERVATOR Gas-Fired Steam Boiler. AFUE up to 82.7% Heating Input 75,000 to 299,000 Btuh GSB S MODEL NUMBER IDENTIFICATION FEATURES

GSB8. CONSERVATOR Gas-Fired Steam Boiler. AFUE up to 82.7% Heating Input 75,000 to 299,000 Btuh GSB S MODEL NUMBER IDENTIFICATION FEATURES P R O D U C T S P E C I F I C AT I O N S W A T E R H E A T E R S / B O I L E R S CONSERVATOR Gas-Fired Steam Boiler Bulletin No. 20263 October 200 Supersedes September 2008 AFUE up to 82.7% Heating Input

More information

SECTION (15486) - FUEL-FIRED, DOMESTIC WATER HEATERS

SECTION (15486) - FUEL-FIRED, DOMESTIC WATER HEATERS SECTION 22 34 00 (15486) - FUEL-FIRED, DOMESTIC WATER HEATERS System shall provide a complete hot water return throughout the entire system with balancing (flow control) valves not less than 10 feet from

More information

PACKAGED COMMERCIAL WATERTUBE BOILERS

PACKAGED COMMERCIAL WATERTUBE BOILERS PACKAGED COMMERCIAL WATERTUBE BOILERS PACKAGED COMMERCIAL WATERTUBE BOILER American Boiler Manufacturers Association 4001 N. 9 th Street, Suite 226 Arlington, VA 22203-1900 703/522-7350 2003, American

More information

WATER HEATERS / BOILERS GSB8-E. Gas-Fired Steam Boiler PRODUCT SPECIFICATIONS. AFUE up to 82.7% Heating Input 75,000 to 299,000 Btuh GSB E

WATER HEATERS / BOILERS GSB8-E. Gas-Fired Steam Boiler PRODUCT SPECIFICATIONS. AFUE up to 82.7% Heating Input 75,000 to 299,000 Btuh GSB E WATER HEATERS / BOILERS -E PRODUCT SPECIFICATIONS Gas-Fired Steam Boiler Bulletin No. 20653 September 202 Supersedes Bulletin No. 20263 AFUE up to 82.7% Heating Input 75,000 to 299,000 Btuh MODEL NUMBER

More information

BURNHAM COMMERCIAL 27 February 2008 MPC Multiple Pass Commercial Boiler Suggested Specifications

BURNHAM COMMERCIAL 27 February 2008 MPC Multiple Pass Commercial Boiler Suggested Specifications 2.1 GENERAL A. Reference is made to the clause entitled Buy American Act Balance of Payments Program Construction Materials FAR 52.225-9. Notwithstanding a bidder s right to offer identifiable foreign

More information

SECTION PLUMBING EQUIPMENT

SECTION PLUMBING EQUIPMENT PART 1 GENERAL 1.1 SECTION INCLUDES A. Water heaters B. Packaged water heating systems C. Water storage tanks D. Water softeners E. Pumps F. Circulators 1.2 REFERENCES SECTION 22 30 00 PLUMBING EQUIPMENT

More information

Design and Construction Standards SECTION PLUMBING EQUIPMENT

Design and Construction Standards SECTION PLUMBING EQUIPMENT SECTION 15450 PLUMBING EQUIPMENT PART 1 GENERAL 1.1 SECTION INCLUDES: A. Water heaters. B. Packaged water heating systems. C. Water storage tanks. D. Water softeners. E. Pumps. F. Circulators. 1.2 REFERENCES

More information

C. Manufactured double wall chimneys for fuel fired equipment. D. NFPA 54 - National Fuel Gas Code; National Fire Protection Association; 2009.

C. Manufactured double wall chimneys for fuel fired equipment. D. NFPA 54 - National Fuel Gas Code; National Fire Protection Association; 2009. SECTION 235100 - BREECHINGS, CHIMNEYS, AND STACKS PART 1 GENERAL 1.1 SECTION INCLUDES A. Fabricated breechings. B. Manufactured chimneys for gas fired equipment. C. Manufactured double wall chimneys for

More information

SERIES 19A. mith PRESSURIZED WET BASE

SERIES 19A. mith PRESSURIZED WET BASE SERIES 19A mith series19a BOILER/BURNER PRESSURIZED WET BASE UNIT series 19A STANDARD EQUIPMENT All s Cast iron wet-base sections tested for 80psi. Insulated metal jacket Cast iron smokehood with integral

More information

LGB COMMERCIAL GAS BOILER. Versatile combustion control systems. Made with Weil-McLain quality COMMERCIAL GAS BOILER APPLICATIONS INCLUDE:

LGB COMMERCIAL GAS BOILER. Versatile combustion control systems. Made with Weil-McLain quality COMMERCIAL GAS BOILER APPLICATIONS INCLUDE: www.weil-mclain.com COMMERCIAL GAS OILER Series Gas Water or Steam MH: 400-,860 Efficiency 85.% Net Load Range: Hot Water 80-, MH / Steam 975-7,40 Sq. Ft. COMMERCIAL GAS OILER APPLICATIONS INCLUDE: Apartment

More information

SERIES 24. Series 24 Features. Commercial, Forced Draft, Hot Water or Steam Boiler. The right fit for any commercial job

SERIES 24. Series 24 Features. Commercial, Forced Draft, Hot Water or Steam Boiler. The right fit for any commercial job SERIES Commercial, Forced Draft, Hot Water or Steam Boiler Sizes from to,8 MBH output The right fit for any commercial job The Series is built to handle any installation - businesses, institutions, apartments,

More information

WATER HEATERS / BOILERS GWB8-E. Gas-Fired Hot Water Boiler PRODUCT SPECIFICATIONS. AFUE up to 83.9% Heating Input 50,000 to 299,000 Btuh

WATER HEATERS / BOILERS GWB8-E. Gas-Fired Hot Water Boiler PRODUCT SPECIFICATIONS. AFUE up to 83.9% Heating Input 50,000 to 299,000 Btuh HEATERS / BOILERS GWB8-E PRODUCT SPECIFICATIONS Gas-Fired Hot Water Boiler Bulletin No. 065 September 0 Supersedes Bulletin No. 06 AFUE up to 83.9% Heating Input 50,000 to 99,000 Btuh MODEL NUMBER IDENTIFICATION

More information

AFUE up to 83.9% Heating Input 50,000 to 299,000 Btuh

AFUE up to 83.9% Heating Input 50,000 to 299,000 Btuh HEATERS / BOILERS GWB8-E Gas-Fired Hot Water Boiler PRODUCT SPECIFICATIONS Bulletin No. 065 July 06 Supersedes September 05 AFUE up to 83.9% Heating Input 50,000 to 99,000 Btuh MODEL NUMBER IDENTIFICATION

More information

DIVISION FINNED WATER-TUBE BOILERS

DIVISION FINNED WATER-TUBE BOILERS MVB, TYPE H - MODELS 503A-2003A SUGGESTED SPECIFICATIONS Catalog No.: 2000.932C Effective: 04-01-14 Replaces: 07-15-13 DIVISION 23 52 33.13 FINNED WATER-TUBE BOILERS PART 1 - GENERAL 1.1 SUMMARY A. Section

More information

A. Section Common Motor Requirements for HVAC Equipment: Fan motors.

A. Section Common Motor Requirements for HVAC Equipment: Fan motors. SECTION 235533 - FUEL-FIRED UNIT HEATERS PART 1 GENERAL 1.1 SECTION INCLUDES A. Gas fired unit heaters. B. Oil fired unit heaters. C. Tubular infrared heaters. 1.2 RELATED REQUIREMENTS A. Section 230513

More information

DIVISION FINNED WATER-TUBE WATER HEATERS

DIVISION FINNED WATER-TUBE WATER HEATERS HI DELTA, TYPE WH - MODELS 992C-2342C SUGGESTED SPECIFICATIONS Catalog No.: 3500.932A Effective: 04-01-17 Replaces: 10-31-16 DIVISION 23 52 33.13 FINNED WATER-TUBE WATER HEATERS - GENERAL 1.1 SUMMARY A.

More information

C. ASME Compliance: Fabricate and label water chiller heat exchangers to comply with ASME Boiler and Pressure Vessel Code: Section VIII, Division 1.

C. ASME Compliance: Fabricate and label water chiller heat exchangers to comply with ASME Boiler and Pressure Vessel Code: Section VIII, Division 1. SECTION 236426 - ROTARY-SCREW WATER CHILLERS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes packaged, water cooled or air cooled as scheduled, electric-motor-driven, rotary-screw water chillers

More information

DIVISION FINNED WATER-TUBE WATER HEATERS

DIVISION FINNED WATER-TUBE WATER HEATERS DELTA LIMITED, TYPE WH - MODELS 399B-899B SUGGESTED SPECIFICATIONS Catalog No.: 3500.97B Effective: 04-01-17 Replaces: 11-15-08 DIVISION 23 52 33.13 FINNED WATER-TUBE WATER HEATERS - GENERAL 1.1 SUMMARY

More information

SPECIFICATION DIVISION 23 SECTION DESCRIPTION DIVISION 23 HEATING, VENTILATING AND AIR CONDITIONING (HVAC) SECTION FIRE TUBE BOILERS (STEAM)

SPECIFICATION DIVISION 23 SECTION DESCRIPTION DIVISION 23 HEATING, VENTILATING AND AIR CONDITIONING (HVAC) SECTION FIRE TUBE BOILERS (STEAM) ARCHITECTURE, ENGINEERING AND CONSTRUCTION P00000000 0000 DOCUMENTS ARCHITECTURE & ENGINEERING 326 East Hoover, Mail Stop B Ann Arbor, MI 48109-1002 Phone: 734-764-3414 Fax: 734-936-3334 SPECIFICATION

More information

DIVISION FINNED WATER-TUBE BOILERS

DIVISION FINNED WATER-TUBE BOILERS MVB, TYPE H - MODELS 2503-4003 SUGGESTED SPECIFICATIONS Catalog No.: 2000.934A Effective: 04-01-14 Replaces: 06-01-13 DIVISION 23 52 33.13 FINNED WATER-TUBE BOILERS PART 1 - GENERAL 1.1 SUMMARY A. Section

More information

DIVISION FINNED WATER-TUBE BOILERS

DIVISION FINNED WATER-TUBE BOILERS MVB, TYPE H - MODELS 504A-2004A SUGGESTED SPECIFICATIONS Catalog No.: 2000.933C Effective: 06-25-15 Replaces: 12-21-09 DIVISION 23 52 33.13 FINNED WATER-TUBE BOILERS PART 1 - GENERAL 1.1 SUMMARY A. Section

More information

SECTION FUEL-FIRED, DOMESTIC WATER HEATERS

SECTION FUEL-FIRED, DOMESTIC WATER HEATERS SECTION 22 34 00 FUEL-FIRED, DOMESTIC WATER HEATERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

University of Houston Master Construction Specifications Insert Project Name SECTION DOMESTIC WATER HEATERS PART 1 - GENERAL

University of Houston Master Construction Specifications Insert Project Name SECTION DOMESTIC WATER HEATERS PART 1 - GENERAL SECTION 22 14 00 DOMESTIC WATER HEATERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS: A. The Conditions of the Contract and applicable requirements of Division 1, "General Requirements", and Section 23 00 10,

More information

SECTION AIR COILS

SECTION AIR COILS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Specification Sections, apply to this Section. B. Related Sections:

More information

A-8-01 Typical questions and answers on the boiler specifications on tender and boiler contract documents

A-8-01 Typical questions and answers on the boiler specifications on tender and boiler contract documents Boiler specifications A-8-01 Typical questions and answers on the boiler specifications on tender and boiler contract documents Burner General: Q. Burner and burner safeguards shall comply with the CGA

More information

Bryan Water-Pak Indirect Systems 360,000 BTU to 4,500,000 BTU Inputs 199 to 3,533 Gallons Storage Capacity

Bryan Water-Pak Indirect Systems 360,000 BTU to 4,500,000 BTU Inputs 199 to 3,533 Gallons Storage Capacity Form No. 2300-7 (Rev. 2/99) Gas, il or Dual Fuel Fired Bryan Water-Pak Indirect Systems 360,000 BTU to 4,500,000 BTU Inputs 199 to 3,533 Gallons Storage Capacity Originators of the Flexible Water Tube

More information

DIVISION COMMERCIAL, GRID-TYPE, FINNED-TUBE, GAS DOMESTIC WATER HEATERS

DIVISION COMMERCIAL, GRID-TYPE, FINNED-TUBE, GAS DOMESTIC WATER HEATERS MVB, TYPE WH - MODELS 503A-2003A SUGGESTED SPECIFICATIONS Catalog No.: 3500.952C Effective: 06-25-15 Replaces: 12-22-09 DIVISION 23 34 36.29 COMMERCIAL, GRID-TYPE, FINNED-TUBE, GAS DOMESTIC WATER HEATERS

More information

AFUE 95% Heating Input 50,000 to 200,000 Btuh

AFUE 95% Heating Input 50,000 to 200,000 Btuh PRODUCT SPECIFICATIONS WATER HEATERS / BOILERS GWM-IE Gas-Fired, Modulating, Condensing, Wall Hung Hot Water Boiler Bulletin No. 210650 March 2018 Supersedes December 2015 AFUE 95% Heating Input 50,000

More information

mith Mills 3500A Smith Mills 3500A 3500A-3 OIL, GAS OR COMBINATION GAS/LIGHT OIL COMMERCIAL BOILER/BURNER CAST IRON

mith Mills 3500A Smith Mills 3500A 3500A-3 OIL, GAS OR COMBINATION GAS/LIGHT OIL COMMERCIAL BOILER/BURNER CAST IRON Mills 300A mith Mills 300A Smith CAST IRON 300A3 OIL, GAS OR COMBINATION GAS/LIGHT OIL COMMERCIAL BOILER/BURNER COMBUSTION CHAMBER DETAILS SIDE VIEW GAS FIRED FRONT VIEW WATER SIDE VIEW NATURAL DRAFT WATER

More information

WATER-TUBE POOL HEATERS

WATER-TUBE POOL HEATERS XTHERM, TYPE P - MODELS 2505-4005 SUGGESTED SPECIFICATIONS Catalog No.: 6000.70 Effective: 09-15-16 Replaces: NEW WATER-TUBE POOL HEATERS - GENERAL 1.1 SUMMARY A. Section includes condensing, gas-fired

More information

Bryan Flexible Water Tube. Ultra-High Efficiency Condensing Hot Water Boilers. 3,000,000 BTUH Natural Gas Fired

Bryan Flexible Water Tube. Ultra-High Efficiency Condensing Hot Water Boilers. 3,000,000 BTUH Natural Gas Fired Form No. 8700 Bryan Flexible Water Tube TM Triple-Flex Series Ultra-High Efficiency Condensing Hot Water Boilers 3,000,000 BTUH Natural Gas Fired Minimum 90% Thermal Efficiency at 160 F Return with 20

More information

Suggested Specifications Prestige Excellence 110

Suggested Specifications Prestige Excellence 110 Suggested Specifications Prestige Excellence 110 General Requirements A. Furnish and install (qty) completely assembled, modulating, sealed combustion, high efficiency, combination gas-fired boiler(s)

More information

DIVISION WALL-HUNG STAINLESS STEEL HEATING BOILERS

DIVISION WALL-HUNG STAINLESS STEEL HEATING BOILERS XPAK FT TYPE H - MODELS 088AR-398A SUGGESTED SPECIFICATIONS Catalog No.: 2100.91 Effective: 05/01/15 Replaces: new DIVISION 23 52 33.13 WALL-HUNG STAINLESS STEEL HEATING BOILERS PART 1 - GENERAL 1.1 SUMMARY

More information

FINNED WATER-TUBE POOL HEATERS

FINNED WATER-TUBE POOL HEATERS HI DELTA, TYPE P - MODELS 992C-2342C SUGGESTED SPECIFICATIONS Catalog No.: 6000.611 Effective: 10-31-16 Replaces: NEW FINNED WATER-TUBE POOL HEATERS - GENERAL 1.1 SUMMARY A. Section includes gas-fired,

More information

AFUE up to 85.2% Heating Input 105,000 to 245,000 Btuh

AFUE up to 85.2% Heating Input 105,000 to 245,000 Btuh WATER HEATERS / BOILERS COWB3 Oil-Fired Hot Water Boiler PRODUCT SPECIFICATIONS Bulletin No. 0654 March 08 Supersedes September 05 AFUE up to 85.% Heating Input 05,000 to 45,000 Btuh MODEL NUMBER IDENTIFICATION

More information

SECTION DOMESTIC WATER HEATERS

SECTION DOMESTIC WATER HEATERS SECTION 223500 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to

More information

WATER-TUBE POOL HEATERS

WATER-TUBE POOL HEATERS XTHERM, TYPE P - MODELS 1005A-2005A SUGGESTED SPECIFICATIONS Catalog No.: 6000.63B Effective: 3-01-15 Replaces: 9-01-09 WATER-TUBE POOL HEATERS PART 1 - GENERAL 1.1 SUMMARY A. Section includes condensing,

More information

CHAPTER 10 STEAM AND HOT WATER BOILERS

CHAPTER 10 STEAM AND HOT WATER BOILERS CHAPTER 10 STEAM AND HOT WATER BOILERS 1001.0 Purpose. The purpose of this chapter is to establish and provide minimum standards for the protection of public welfare, health, safety, and property by regulating

More information

Engineering Bulletin. Gas Heat. for M-Series and T-Series Climate Changer Air Handlers CLCH-PRB010-EN. March 2004

Engineering Bulletin. Gas Heat. for M-Series and T-Series Climate Changer Air Handlers CLCH-PRB010-EN. March 2004 Engineering Bulletin Gas Heat for M-Series and T-Series Climate Changer Air Handlers March 2004 CLCH-PRB010-EN Preface Gas heat can be a good heating option for any of the following applications: Climates

More information

mith Mills 4500A Smith Mills 4500A 4500A-3R OIL, GAS OR COMBINATION GAS/OIL COMMERCIAL BOILER/BURNER CAST IRON

mith Mills 4500A Smith Mills 4500A 4500A-3R OIL, GAS OR COMBINATION GAS/OIL COMMERCIAL BOILER/BURNER CAST IRON Mills 00A mith Mills 00A Smith CAST IRON OIL, GAS OR COMBITION GAS/OIL COMMERCIAL BOILER/BURNER 00AR STEAM GAUGE OPERATING CONTROL MODULATING CONTROL HI LIMIT PRESSURE CONTROL 0" STEAM DRUM TEST COCK /"

More information

A. Product Data: Include rated capacities, furnished specialties and accessories.

A. Product Data: Include rated capacities, furnished specialties and accessories. BASE BID: SECTION 15542 FUEL-FIRED RADIANT HEATERS PART 1 - GENERAL 1.1 SUMMARY A. Furnish and install a Co-Ray-Vac Low Intensity Vented Infrared Radiant Vacuum Gas Heating System. System must be certified

More information

SECTION GAS-FIRED RADIANT HEATERS

SECTION GAS-FIRED RADIANT HEATERS SECTION 23 55 23 PART 1 - GENERAL 1.1 DESCRIPTION SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Delete between // // if not applicable to project. Also delete any other item or paragraph

More information

BuildingName The Description of the Project P DOCUMENTS

BuildingName The Description of the Project P DOCUMENTS ARCHITECTURE, ENGINEERING AND CONSTRUCTION P00000000 0000 DOCUMENTS ARCHITECTURE & ENGINEERING 326 East Hoover, Mail Stop B Ann Arbor, MI 48109-1002 Phone: 734-764-3414 Fax: 734-936-3334 SPECIFICATION

More information

Columbia Boiler Company

Columbia Boiler Company EMG Series Boilers Available in Natural Gas & Propane Rev 12012 Columbia Boiler Company PO Box 1070 Pottstown, PA 19464 Tel (610) 473-8457 Fax (610) 367-6800 Website www.columbiaboiler.com Email cbcsales@ptd.net

More information

XTHERM, TYPE WH - MODELS 1005A- 2005A DIVISION COMMERCIAL, WATER-TUBE, CONDENSING GAS DOMESTIC WATER HEATERS

XTHERM, TYPE WH - MODELS 1005A- 2005A DIVISION COMMERCIAL, WATER-TUBE, CONDENSING GAS DOMESTIC WATER HEATERS XTHERM, TYPE WH - MODELS 1005A- 2005A Catalog No.: 3500.801 Effective: 11-15-14 Replaces: NEW PART 1 - GENERAL 1.1 SUMMARY DIVISION 23 34 36.29 COMMERCIAL, WATER-TUBE, CONDENSING GAS DOMESTIC WATER HEATERS

More information

CHAPTER 8 CHIMNEYS AND VENTS

CHAPTER 8 CHIMNEYS AND VENTS CHAPTER 8 CHIMNEYS AND VENTS SECTION 801 GENERAL 801.1 Scope. This chapter shall govern the installation, maintenance, repair and approval of factory-built chimneys, chimney liners, vents and connectors.

More information

Series 8H. Cast Iron Gas Fired Commercial Water Boiler

Series 8H. Cast Iron Gas Fired Commercial Water Boiler Series 8H Cast Iron Gas Fired Commercial Water Boiler to 0 MBH Input Over 8% Efficient 0 or 0 PSI Cast Iron Sectional Design Atmospheric Vent Modular/Multiple Boiler Configurations Available Series 8H

More information

Design & Construction Standards, Revised January

Design & Construction Standards, Revised January PART 1 GENERAL 1.01 Scope of Standard A. This standard provides general requirements of The University of Texas at Austin for fire-extinguishing systems other than water-based fire suppression systems.

More information

C. Shop Drawings: For boilers, boiler trim, and accessories. Include plans, elevations, sections, details, and attachments to other work.

C. Shop Drawings: For boilers, boiler trim, and accessories. Include plans, elevations, sections, details, and attachments to other work. Buchtel/Perkins Community Learning Center GPD -2007271.15 OSFC Project # 55-7110-9029425 Phase 3 CLC Package Bidding Documents July 1, 2010 SECTION 15513 CONDENSING BOILERS PART I- GENERAL 1.1 RELATED

More information

DIVISION FINNED WATER-TUBE BOILERS

DIVISION FINNED WATER-TUBE BOILERS HI DELTA, TYPE H - MODELS 992C-2342C SUGGESTED SPECIFICATIONS Catalog No.: 2000.953 Effective: 10-31-16 Replaces: NEW DIVISION 23 52 33.13 FINNED WATER-TUBE BOILERS - GENERAL 1.1 SUMMARY A. Section includes

More information

Suggested Specification: Benchmark 1.5 Low NOx Gas-Fired Hydronic Boiler(s)

Suggested Specification: Benchmark 1.5 Low NOx Gas-Fired Hydronic Boiler(s) Furnish and install as shown on AERCO International plans and operation and maintenance manuals, with all applicable codes and authorities having local, state and federal jurisdiction, Benchmark Series

More information

SECTION PLUMBING EQUIPMENT

SECTION PLUMBING EQUIPMENT PART 1 GENERAL 1.01 SECTION INCLUDES A. Water heaters. B. Packaged water heating systems. C. Domestic water heat exchangers. D. Water storage tanks. E. Water softeners. F. Reverse osmosis equipment. G.

More information

SECTION DIRECT GAS-FIRED INDUSTRIAL HEATING AND VENTILATING UNITS

SECTION DIRECT GAS-FIRED INDUSTRIAL HEATING AND VENTILATING UNITS SECTION 237339 - DIRECT GAS-FIRED INDUSTRIAL HEATING AND VENTILATING UNITS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary

More information

FINNED WATER-TUBE POOL HEATERS

FINNED WATER-TUBE POOL HEATERS HI DELTA, TYPE P - MODELS 502C-902C SUGGESTED SPECIFICATIONS Catalog No.: 6000.601A Effective: 07-12-18 Replaces: 10-31-16 FINNED WATER-TUBE POOL HEATERS - GENERAL 1.1 SUMMARY A. Section includes gas-fired,

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 22 3300 - ELECTRIC, DOMESTIC WATER HEATERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

SECTION ROTARY-SCREW WATER CHILLERS

SECTION ROTARY-SCREW WATER CHILLERS PART 1 GENERAL 1.01 SECTION INCLUDES A. Factory-assembled packaged chiller. B. Charge of refrigerant and oil. C. Controls and control connections. D. Chilled water connections. E. Electrical power connections.

More information

LABORATORY AIR COMPRESSORS AND VACUUM PUMPING SYSTEMS

LABORATORY AIR COMPRESSORS AND VACUUM PUMPING SYSTEMS SECTION 22 20 00 LABORATORY AIR COMPRESSORS AND VACUUM PUMPING SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS: A. The Conditions of the Contract and applicable requirements of Division 1, "General Requirements",

More information

B. Product Data: Provide manufacturers catalogue information. Indicate valve data and ratings.

B. Product Data: Provide manufacturers catalogue information. Indicate valve data and ratings. DIVISION 21 21 05 00 COMMON WORK RESULTS FOR FIRE SUPPRESSION PART 1 GENERAL 1.1 SECTION INCLUDES A. Pipe, fittings, sleeves, escutcheons, seals, and connections for sprinkler systems. 1.2 RELATED REQUIREMENTS

More information

SECTION WET-PIPE SPRINKLER SYSTEMS

SECTION WET-PIPE SPRINKLER SYSTEMS SECTION 21 13 13 WET-PIPE SPRINKLER SYSTEMS PART 1 - GENERAL 1.1 SCOPE OF WORK A. Design, installation and testing shall be in accordance with NFPA 13 except for specified exceptions. B. The demolition

More information

A. American National Standards Institute (ANSI): Establishes requirements applicable to certifying direct gas-fired heaters.

A. American National Standards Institute (ANSI): Establishes requirements applicable to certifying direct gas-fired heaters. SECTION 15622 DIRECT GAS-FIRED BURNER & MANIFOLD SYSTEM PART 1: GENERAL 1.1 Section includes: A. Direct gas-fired heater modules B. Controls C. Equipment schedule 1.2 Related Sections A. Section 01655:

More information

FGR. Installation, Operation and Startup Instruction Manual FOR FLUE GAS RECIRCULATION SYSTEM. FGR-8 through FGR-22 (25 HP to 1000 HP)

FGR. Installation, Operation and Startup Instruction Manual FOR FLUE GAS RECIRCULATION SYSTEM. FGR-8 through FGR-22 (25 HP to 1000 HP) FGR Installation, Operation and Startup Instruction Manual FOR FLUE GAS RECIRCULATION SYSTEM FGR-8 through FGR-22 (25 HP to 1000 HP) Gas, Light Oil or Combination MANUFACTURED BY JOHN ZINK COMPANY, LLC

More information

BUDERUS. Superior Equipment by Design. Comfortable. Efficient. Intelligent Heating. BUDERUS. G Cast Iron Commercial Boilers

BUDERUS. Superior Equipment by Design. Comfortable. Efficient. Intelligent Heating. BUDERUS. G Cast Iron Commercial Boilers BUDERUS BUDERUS G1 1 1 G1 G1 G1Boilers Cast Iron Commercial High Efficiency Combustion Efficiencies Up to 88.2% 0 to,982 MBH Output Thermostream Design Eliminates Thermal Shock Superior Equipment by Design

More information

Low pressure boiler* inspection and maintenance

Low pressure boiler* inspection and maintenance 2-12.001 May 2011 Low pressure boiler* inspection and maintenance Introduction Even as our society evolves into a more technologically advanced, economically driven environment, many businesses and their

More information

STR-Series Indirect-Fired Air Turnover Units

STR-Series Indirect-Fired Air Turnover Units STR-Series Indirect-Fired Air Turnover Units Equipment Specifi cations 1.800.589.3691 www.weather-rite.com GAS/OIL HEATING ONLY INDIRECT-FIRED AIR TURNOVER UNIT GUIDE SPECIFICATIONS PART 1 GENERAL [Gas][Oil][Gas/Oil

More information

MOHICAN. MOHICAN 4-Pass Water Boiler, HP, PSI Section

MOHICAN. MOHICAN 4-Pass Water Boiler, HP, PSI Section SPECIFICATION SHEETS Steam Sample Specification Water Sample Specification MOHICAN SPECIFICATION SHEET The following sample specifications are provided by Superior Boiler Works to assist you in providing

More information

SECTION FUEL-FIRED DOMESTIC WATER HEATERS

SECTION FUEL-FIRED DOMESTIC WATER HEATERS SECTION 22 34 00 FUEL-FIRED DOMESTIC WATER HEATERS PART 1 - GENERAL 1.1 DESCRIPTION SPEC WRITER NOTES: 1. Delete between //----// if not applicable to project. Also delete any other item or paragraph not

More information

G315/6 Cast Iron Boiler

G315/6 Cast Iron Boiler Engineering Submittal Sheet Boiler Overview LISTED Engineering Specifications There shall be provided and installed G315-6 Buderus sectional cast iron hot water boiler(s), suitable for forced draft firing

More information

C. All components of the systems described shall meet the requirements as stated herein and shall be approved by the Architect and Consultant.

C. All components of the systems described shall meet the requirements as stated herein and shall be approved by the Architect and Consultant. SECTION 218800 - FIRE PROTECTION 1. GENERAL A. Provisions of Division 1, GENERAL REQUIREMENTS, and Section 230000, MECHANICAL GENERAL CONDITIONS, and Section 230050, SEISMIC PROTECTION are a part of this

More information

DESIGN AND CONSTRUCTION STANDARDS SPECIFICATION GUIDELINES

DESIGN AND CONSTRUCTION STANDARDS SPECIFICATION GUIDELINES SECTION 21 30 00 FIRE PUMPS GENERAL This standard provides general requirements of The University of South Alabama in Mobile Alabama for fire pumps. This document is not intended to serve as a guide specification.

More information

G615/11 Cast Iron Boiler

G615/11 Cast Iron Boiler Engineering Submittal Sheet Boiler Overview LISTED Engineering Specifications There shall be provided and installed G615-11 Buderus sectional cast iron hot water boiler(s), suitable for forced draft firing

More information

Replacement parts EG/PEG

Replacement parts EG/PEG Replacement parts EG/PEG Table 13 EG/PEG replacement parts A B Left hand end section with heater opening (Pattern No. 1814) Left end section without heater opening(pattern No. 1813) Right hand end section

More information

EHB Series. STONESTEEL Commercial Electric Water Heaters Individually Mounted Elements Vertical or Horizontal CEMLINE CORPORATION

EHB Series. STONESTEEL Commercial Electric Water Heaters Individually Mounted Elements Vertical or Horizontal CEMLINE CORPORATION EHB Series STONESTEEL Commercial Electric Water Heaters Individually Mounted Elements Vertical or Horizontal STONESTEEL is a registered trademark of Cemline Corporation CEMLINE CORPORATION P.O. BOX 55

More information

FLEXCORE SERIES MASTERSPEC

FLEXCORE SERIES MASTERSPEC FLEXCORE SERIES MASTERSPEC MSFC-2 SECTION 23 52 16 - CONDENSING HIGH EFFICIENCY STAINLESS STEEL FIRETUBE BOILERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract,

More information

SENTRY. High efficiency, cast-iron gas boiler LOWER PROFILE MAKES PROBLEM INSTALLATIONS EASY

SENTRY. High efficiency, cast-iron gas boiler LOWER PROFILE MAKES PROBLEM INSTALLATIONS EASY SENTRY High efficiency, cast-iron gas boiler LOWER PROFILE MAKES PROBLEM INSTALLATIONS EASY SENTRY High efficiency, cast-iron gas boiler A smarter choice for informed The boiler you choose for your home

More information

INVITATION FOR BID. May 17, Purchase Natural Gas Hot Water Boiler MAWSS Purchasing Department

INVITATION FOR BID. May 17, Purchase Natural Gas Hot Water Boiler MAWSS Purchasing Department mawss Buyer II Lisa Russell (251) 694-3162 Office Irussell@mawss.com TO INVITATION FOR BID NUMBER SEPARATE SEALED BIDS FOR BIDS WILL BE RECEIVED AT Prospective Bidders IFB 18-023 INVITATION FOR BID May

More information

.2 Section Waste Management and Disposal..4 Section Vibration Isolation and Seismic Control Measures.

.2 Section Waste Management and Disposal..4 Section Vibration Isolation and Seismic Control Measures. Issued 2005/06/01 Section 15510 Packaged Boilers Page 1 of 13 PART 1 GENERAL 1.1 RELATED SECTIONS.1 Section 01330 Submittal Procedures..2 Section 01355 Waste Management and Disposal..3 Section 01780 Closeout

More information

SAMPLE SPECIFICATIONS

SAMPLE SPECIFICATIONS Page 1 of 6 3-03 SAMPLE SPECIFICATIONS The following sample specifications are provided by Superior Boiler Works to assist you in providing your customer with the specific needs for that application. The

More information

Installation & Service Instructions for Jackson & Church Flexaire Packaged Furnaces SDF-125 thru SDF-400 Gas Firing

Installation & Service Instructions for Jackson & Church Flexaire Packaged Furnaces SDF-125 thru SDF-400 Gas Firing Installation & Service Instructions for Jackson & Church Flexaire Packaged Furnaces SDF-125 thru SDF-400 Gas Firing Important: To protect the unit and avoid damage to the heat exchanger, the blower speed

More information

G315/5 Cast Iron Boiler

G315/5 Cast Iron Boiler Engineering Submittal Sheet Boiler Overview LISTED Engineering Specifications There shall be provided and installed G315-5 Buderus sectional cast iron hot water boiler(s), suitable for forced draft firing

More information

Peerless Boilers. Series MI. Residential Gas Boilers

Peerless Boilers. Series MI. Residential Gas Boilers Peerless Boilers Series MI Residential Gas Boilers Hard work and dedication by skilled employees have made us one of today s top cast iron boiler manufacturers. From the beginning, our main priority has

More information

SECTION WATER HEATERS

SECTION WATER HEATERS SECTION 15457 WATER HEATERS PART 1 GENERAL 1.01 SUMMARY A. Section Includes: A complete hot water generating system with necessary accessories as indicated on Construction Documents, as specified, and

More information

Series. Gas/Oil Boilers Water. Oil, Gas & Installation, Operation & Maintenance Manual

Series. Gas/Oil Boilers Water. Oil, Gas & Installation, Operation & Maintenance Manual Series Oil, Gas & LC Gas/Oil Boilers Water Installation, Operation & Maintenance Manual TABLE OF CONTENTS TABLE OF CONTENTS USING THIS MANUAL A. INSTRUCTION MANUALS............... B. SPECIAL ATTENTION

More information

G515/7 Cast Iron Boiler

G515/7 Cast Iron Boiler Engineering Submittal Sheet Boiler Overview Engineering Specifications There shall be provided and installed G515-7 Buderus sectional cast iron hot water boiler(s), suitable for forced draft firing with

More information

KN2/4 SERIES MASTER SPECIFICATION

KN2/4 SERIES MASTER SPECIFICATION KN2/4SP4-2 SECTION 23 52 23 SAMPLE SPECIFICATION FOR HYDROTHERM KN-2 and KN-4 SERIES BOILERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General

More information

Internet Version for Reference Only INDUCED DRAFT COMMERCIAL WATER HEATERS SUPPLEMENT INSTRUCTIONS TO PART #

Internet Version for Reference Only INDUCED DRAFT COMMERCIAL WATER HEATERS SUPPLEMENT INSTRUCTIONS TO PART # INDUCED DRAFT COMMERCIAL WATER HEATERS SUPPLEMENT INSTRUCTIONS TO PART #238-39387-00 THIS INSTRUCTION SUPPLEMENT IS ONLY INTENDED TO GIVE INSTALLATION INSTRUCTIONS AND INFORMATION RELATED TO THE INDUCED

More information

High efficiency, cast-iron gas boiler

High efficiency, cast-iron gas boiler SENTRY High efficiency, cast-iron gas boiler LOWER PROFILE MAKES PROBLEM INSTALLATIONS EASY SENTRY High efficiency, cast-iron gas boiler A smarter choice for informed The boiler you choose for your home

More information

SECTION COMPRESSED AIR SYSTEM. A. Pipe and pipe fittings, including valves, unions and couplings.

SECTION COMPRESSED AIR SYSTEM. A. Pipe and pipe fittings, including valves, unions and couplings. SECTION 15481 COMPRESSED AIR SYSTEM PART 1 - GENERAL 1.1 SECTION INCLUDES A. Pipe and pipe fittings, including valves, unions and couplings. B. Air compressor. C. After cooler. D. Refrigerated air dryer.

More information

VICTORYII. Cast-iron, power vent gas boiler BOILER FOR OLDER HOMES.

VICTORYII. Cast-iron, power vent gas boiler BOILER FOR OLDER HOMES. VICTORYII Cast-iron, power vent gas boiler VHS SERIES are available in a sealed combustion model VSPH VICTORY BOILERS AN IDEAL REPLACEMENT BOILER FOR OLDER HOMES. A PERFECT BOILER FOR NEW CONSTRUCTION.

More information

CHAPTER 8 CHIMNEYS AND VENTS

CHAPTER 8 CHIMNEYS AND VENTS CHAPTER 8 CHIMNEYS AND VENTS SECTION 801 GENERAL 801.1 Scope. This chapter shall govern the installation, maintenance, repair and approval of factory-built chimneys, chimney liners, vents and connectors.

More information

Draft Controls. When to use a Draft Control

Draft Controls. When to use a Draft Control Draft s For proper operation and efficient fuel consumption in oil, gas and/or coal-fired heating appliances, draft must remain constant. When it is, combustion is more complete, fuels are utilized efficiently,

More information

RBI MASTERSPEC. A. This Section includes gas-fired, non-condensing finned copper water tube water heaters for heating hot water.

RBI MASTERSPEC. A. This Section includes gas-fired, non-condensing finned copper water tube water heaters for heating hot water. MSWFTIII-7 SECTION 22 34 36.29 - SAMPLE SPECIFICATION FOR RBI FUTERA III MODULATING WATER HEATER PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General

More information

2012 INTERNATIONAL FUEL GAS CODE VENTS

2012 INTERNATIONAL FUEL GAS CODE VENTS 2012 INTERNATIONAL FUEL GAS CODE SECTION 502 (IFGC) VENTS 502.1 General. All vents, except as provided in Section 503.7, shall be listed and labeled. Type B and BW vents shall be tested in accordance with

More information

SECTION ELECTRIC WATER HEATERS

SECTION ELECTRIC WATER HEATERS PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Specification Sections, apply to this Section. B. Related Sections:

More information