1 PLANNING REPORT CITY OF EAGAN REPORT DATE: January 17, 2018 CASE: 02-CG APPLICANT: TJ Design/Costco HEARING DATE: PROPERTY OWNER: MG Eagan LLC APPLICATION DATE: REQUEST: Comprehensive Guide Plan Amendment PREPARED BY: Pamela Dudziak LOCATION: Southeast corner of I-494/I-35E interchange COMPREHENSIVE PLAN: MO, Major Office ZONING: PD, Planned Development SUMMARY OF REQUEST TJ Design, on behalf of Costco, is requesting approval of a Comprehensive Guide Plan Amendment from Major Office (MO) to Retail Commercial (RC), to allow a members-only retail use on Lot 1, Block 1, Blue Gentian Corporate Center. The site consists of approximately 18.1 acres and is located east of Hwy 55 and north of Blue Gentian Road, southeast of the I-494/I- 35E interchange. AUTHORITY FOR REVIEW The city s Comprehensive Guide Plan was prepared pursuant to Minnesota Statutes, Section As defined by statute, the Land Use Plan is a guide and may be amended from time to time as conditions change. The city s Guide Plan is to be implemented by official controls such as zoning and other fiscal devices. The creation of land use districts and zoning is a formulation of public policy and a legislative act. As such, the classification of land uses must reasonably relate to promoting the public health, safety, morals and general welfare. When a change to a city s Comprehensive Guide Plan is requested, it is the city s responsibility to determine if the change is in the best long-range interests of the city. The standard of review of a city s action in approving or denying a Comprehensive Guide Plan amendment is whether there exists a rational basis. A rational basis standard has been described to mean having legally sufficient reasons supportable by the facts which promote the general health, safety and welfare of the city.

2 Page 2 BACKGROUND/HISTORY The site was rezoned from Business Park (BP) to Planned Development (PD) in The development and use of the subject site is governed by a Planned Development Agreement dated September 2, 2008, which allows a 261,000 s.f. multi-story office building with underground and structured parking. The property was platted at that time to consolidate multiple parcels. Prior to the 2008 development plan approval, a TIF District was created over the area to facilitate redevelopment and the removal of blighted structures and obsolete uses from the property that were inconsistent with the Business Park zoning at that time. To date, the property remains vacant and the approved office development has not been constructed. Land Use History The City s first Comprehensive Land Use Map was adopted in 1974 and shows the site designated for Industrial land use. At that time, there were several residential homes present with zoning designations of Single-family (R-1) and Agriculture (A). In 1988, the land use designation shows Commercial Planned Development (CPD), a designation which remained until 1996, when it changed to Business Park (BP) for consistency with the newly adopted Business Park zoning ordinance. With the 1998 Comprehensive Guide Plan Update, the City was required to create consistency between the land use and zoning designations of the property. At that time, the Special Area small area plan was adopted, which acknowledged existing residential uses as conforming, and established a long-term vision to transition the entire Special Area from a variety of scattered uses to a more cohesive business and industrial park. The TIF District to facilitate the redevelopment within the Special Area was approved in 2008 and certified in 2009, and the Major Office (MO) land use designation followed the approval of the current Planned Development for multi-story office use, and was applied to the property in the 2010 Comprehensive Plan Update which eliminated the Special Area designation. Zoning History The site was rezoned to Planned Development in 2008 with the approval of development plans for the Blue Gentian Corporate Center. PD remains the current zoning, with the PD Agreement identifying multi-story office as the approved use. Before 2008, the property consisted of three different zoning designations -- Business Park (BP), Agriculture (A), and Single-family (R-1) -- applied to various parcels that now comprise the subject site.

3 Page 3 EXISTING CONDITIONS The property is currently vacant. Access to the site is from Blue Gentian Road. There are wooded areas on the property and significant slopes, especially along the northern boundary. A wetland is present north of the property. Access to the site is available from Blue Gentian Road. SURROUNDING USES The following existing uses, zoning, and comprehensive guide plan designations surround the subject property: Existing Use Zoning Land Use Designation North I-494/I-35E Right-of-Way Right-of-Way South Office BP, Business Park SA, Special Area East Office BP, Business Park SA, Special Area West Hwy. 55/I-35E Right-of-Way Right-of-Way EVALUATION OF REQUEST Description of Proposal - The applicant is proposing a change in the land use designation of this 18.1-acre site from to MO, Major Office to RC, Retail Commercial to allow for construction of a members-only retail warehouse with liquor sales, a motor fueling station, and a tire center. The action to be considered in this application is whether to allow the change in land use from Major Office (MO) to Retail Commercial (RC) for the 18.1 acre site. If the amendment application is considered favorably, specific development plans will be reviewed at the time of a future development application for PD Amendment. Therefore, the submitted conceptual development plan illustrates the intended development, but is not part of the action before the City at this time. The narrative speaks to design details such as lighting, landscaping and building finish, and mechanical equipment screening which would be required and evaluated as part of a future PD Amendment application. Applicant s Narrative The applicant s narrative describes the proposed retail operations and site development concept. The tire center is about 5,300 s.f. and is accessed through the main building. The tire center provides for tire sales and installation with five service bays. Overhead doors for access to the bays face the south. The liquor pod occupies approximately 8,600 s.f. of the building. According to the narrative, it is anticipated that the development would employ approximately 200 to 250 people both full and part time. The submitted narrative indicates the fueling station includes an 8,127 square-foot canopy, with fueling capacity for 24 cars at a time. Eight stacking lanes feed the pumps, which are automated and self-serving for Costco members only. An attendant would be present to assist

4 Page 4 with problems. Typical fueling station hours are from 5:00 a.m. to 10:00 p.m. daily. Fuel deliveries are typically two trucks per day and the fuel facility is specifically designed to avoid traffic and queuing conflicts with the warehouse. The Costco warehouse store hours are typically from 10:00 a.m. to 8:30 p.m. Monday through Friday, and Saturdays 9:30 a.m. 6:00 p.m. Deliveries occur between 3:00 a.m. and 2:30 p.m. with most completed before the store opens. Compatibility with Surrounding Area - The property is located adjacent to I-35E and I-494 to the north and Hwy. 55 to the west. Thus, the site has high visibility from three major roadways. Adjacent to the site are the Spectrum Commerce Center and Grand Oak Business Park to the south and east. The proposed change in land use introduces retail commercial use in an area consisting largely of office and industrial uses. The nearest retail commercial uses are about one mile southeast of the site on the north side of the Hwy. 55 and Hwy. 149 intersection. Sam s Club is also located less than a mile south of the subject site. Site Plan The conceptual site plan identifies an approximately 166,000 s.f. building with a motor fuel station. The retail building includes indoor cart storage area and liquor sales. The majority of parking on the west half of the property, and the store on the eastern half of the site. Access is proposed from Blue Gentian Road in two locations. As compared to the approved PD for multi-story office, the proposed building size is smaller (~166,000 s.f. compared to ~261,000 s.f.) and the amount of parking is less (733 stalls as compared to 1,192 stalls). Density The proposed building provides 166,000 s.f. upon 18.1 acres, resulting in a building coverage ratio of 21.1%. This ratio excludes the motor fuel station canopy, which is approximately 8,100 s.f. Parks and Recreation This property is subject to park and trail dedication requirements. Cash dedications are payable at the time of Building Permit at the rates then in effect. The 2018 rate for parks is $939 per 1,000 square feet of building and for trails, $1,289 per net acre. ENVIRONMENTAL IMPACTS Grading/Topography The site has a combination of open and heavily treed areas. Former Blue Gentian Circle loops through the center of the site and connects to Blue Gentian Road near TH 55. The site has large variations in topography with the former Blue Gentian Circle roadway being the breakpoint (ridge) through the property. North of Blue Gentian Circle slopes towards I-494, and south of Blue Gentian Circle slopes toward Blue Gentian Road. Elevations range from approximately 910 down to 860. Almost the entire site would be disturbed for grading, installation of utilities, and construction of the proposed parking lot and building.

5 Page 5 Wetlands Because the applicant is proposing no Wetland Alteration Activities grading activities would occur no closer than approximately 100 feet from the wetland area the applicant is not required to delineate or assess the wetland for classification by the City. This development is therefore not subject to any requirements of Section of Eagan City Code. Tree Preservation The site does contain several wooded areas. A significant Tree Inventory and Tree Preservation Plan will be required with a future development application. As a singlelot commercial development, allowable removal would be 30% of existing significant vegetation. Proposed removal beyond that amount is subject to mitigation in accordance with the City s Tree Preservation Ordinance. Airport Noise Considerations - The City of Eagan considered airport noise as a factor in its Comprehensive Land Use Guide Plan. The Metropolitan Council has adopted land use compatibility guidelines which incorporate the 2007 Noise Policy Contours. Under these guidelines retail commercial is considered a compatible use within Noise Zone 4. INFRASTRUCTURE IMPACTS Storm Drainage The entire site lies within Drainage District F (as designated in the City Storm Water Management Plan 2007). The northern half of the site drains to the north toward I- 494 where it enters Pond FP-14, which is a public water (DNR# ) partially located in Mn/DOT right-of-way. Overflow from the pond drains westerly through a storm sewer system paralleling I-35E, where it ultimately discharges to the Minnesota River. Drainage from the south half of the site enters the storm sewer along Blue Gentian Road, where it drains easterly to City Pond FP-1 (O Neil Pond). Overflow from that pond drains via public storm sewer to FP- 14. The development of this property will be subject to the City Code 11.67, 4.34 stormwater requirements and to MN Department of Transportation storm water permit requirements for discharge to TH 55 right-of-way. Utilities The applicant s site plan did not include a utility plan. Sanitary sewer District N (as designated in the City s Comprehensive Sanitary Sewer Plan) serves the entire site. Sanitary sewer and water main of sufficient size, depth and capacity are available from Blue Gentian Road to the south for connection by this development. All existing water and sewer lines not utilized with this development should be abandoned in accordance with City standards. All existing well and septic systems on the site should be abandoned in accordance with Dakota County and City standards as part of this development. Telecommunications - In 2004, the Eagan Technology Task Force recommended that broadband and fiber optic telecommunications networks be expanded in the city wherever

6 Page 6 possible. Any development of the site should include the installation of fiber optic cable, or a conduit for future installation, in its construction plans. Water Quality The applicant s site plan does not show how stormwater management and water quality requirements will be addressed. This proposed new development is located in extreme north-central Eagan, where stormwater discharge leaves the City of Eagan in the public storm sewer system, crosses into Mendota Heights following Interstate 494 to the west, discharging into regional basin HP-1 before overflowing into the Minnesota River Valley. Any development will need to comply with the City of Eagan s Post Construction Stormwater Management Requirements (City Code 4.34) for stormwater management and surface water quality, including Runoff Rate Control and 1.1 Volume Control. These regulations include design standards for volume control and reduction, total phosphorus control, total suspended solids control, oil and grease control, and runoff rate control performance standards. They also provide for minimization of impervious surface area and maximization of infiltration and retention, acceptable complementary stormwater treatments, pond requirements, regional ponding, and maintenance of private stormwater facilities. Streets/Access/Circulation Public street access is proposed from Blue Gentian Road, a two lane collector roadway along the south edge of the site. Traffic/Parking Analysis For consideration of a Comprehensive Guide Plan Amendment, the applicant provided a trip generation and parking supply comparison for the site. The review involved estimating trip generation potential and required parking supply for the project site s approved land use (office) and comparing that to the trip generation potential and proposed parking supply for the project site s proposed land use (Retail Commercial). A copy of the study is included in the exhibits to this report. To summarize the study, when compared to the approved office development plan, the proposed development plan is anticipated to result in: A net decrease in AM peak-hour trip generation potential for inbound and outbound trips. A decrease in PM peak-hour, peak-directional trip generation potential (outbound). The decrease in the peak-hour, peak-directional trips is expected to benefit the peak hour operating conditions of the transportation system as compared to the approved land use. An increase in PM peak-hour off-peak directional trip generation potential (inbound). A net reduction in parking supply. Traffic Study If the Comprehensive Plan Amendment is approved, the applicant will be required to perform a more detailed and larger scale traffic study to determine any impacts to the surrounding roadway system, any necessary improvements (ie. access modifications, driveway alignment with surrounding properties, median extensions, turn lanes, striping

7 Page 7 modifications, traffic signal and intersection improvements, etc.), and be responsible to perform those improvements. Mn/DOT Plat Review Requirements Mn/DOT performed a plat review and provided a summary of their findings and requirements dated January 10, 2018 (see attached). To summarize, Mn/DOT is requesting the following items: Fix ALTA survey discrepancies Provide access controls Perform a detailed and expanded traffic study Any access into the site should not be any closer than 500 feet form TH 55 Provide a pedestrian connection between the bus stop in front of the property into the development Obtain a Mn/DOT drainage permit and right-of-way permit Future Greenway Corridor A future greenway corridor and trail is anticipated in this area. The development should be designed to accommodate these future improvements. Proposed 2018 Pavement Management Improvements - As part of the City s Pavement Management Program, Blue Gentian Road and Blue Water Road are both currently scheduled for mill and overlay improvements in 2018 (City Project 1265). The condition of the roads currently have a Pavement Condition Index (PCI) of 36, which is in the low end of the range considered for this type of improvement. If the proposed development moves forward, the City may delay the overlay until after the site improvements are complete. All benefitting properties will be assessed for the improvements after they are complete. Easements/Permits/Right-of-Way The development should be responsible for obtaining permits from applicable regulatory agencies, prior to building permit approval. Former Blue Gentian Circle right-of-way within the proposed plat was previously vacated by the City. A portion of the Blue Gentian Road/Circle public right-of-way remains east of the development, with the development s private drive being shown within this right-of-way. The developer should enter into an agreement with the City providing for the private maintenance of this drive within public right-of-way. Public drainage and utility easements only currently exist along Blue Gentian Road and a portion of the west property line. Standard drainage and utility easements around the perimeter of the property, adjacent to rights-of-ways, and over public utilities should be dedicated with the development. Financial Obligation At this time, a pending assessment in the amount of $49,212 is shown for this parcel for the proposed 2018 mill and overlay improvements (City Project 1265 Blue Gentian Road & Blue Water Road).

8 Page 8 Based upon a study by City staff of the financial obligations collected in the past and proposed use for the property, utility related Trunk and Lateral fees and previous roadway assessments that were not previously collected, and AUAR Mitigative Traffic Improvement fees, will be collected with any development of this property. COMPREHENSIVE LAND USE IMPACTS Land Supply The proposal shifts 18.1 acres of land from the Major Office land use category to Retail Commercial. The City is considered fully developed, with more than 95% of the City s land developed. In recent years, the City has seen increased retail commercial development, particularly in Cedar Grove with the outlet center, and at Yankee Doodle and Pilot Knob Roads with Central Park Commons. Major office developments have continued to occur elsewhere, particularly in the northeast and northwest portions of the City (e.g. Prime Therapeutics, White House Custom Colour, Viking Lakes, and Summit Orthopedics). Land Use Designations The current Major Office (MO) designation was applied to the property in 2010, acknowledging approved development plans for a multi-story office building on the site. The proposed Retail Commercial (RC) designation provides for a variety of retail related land uses. Shopping centers, supermarkets, drugstores, department stores, convenience center/gas stations, restaurants, hotels and other businesses offering goods and services are examples of uses allowed in this category. Neighborhood Business (NB), Commercial Shopping Center (CSC), and General Business (GB) are identified as corresponding zoning districts within the Retail Commercial land use designation. Compatibility Compatibility considerations vary with the type and scale of development. Larger commercial developments should include unifying design elements and greater buffering when adjacent to lower intensity residential uses. Access Needs Retail Commercial uses tend to generate substantial amounts of customer traffic. Visibility and convenient access is also important. According to the City of Eagan s Comprehensive Guide Plan, these uses should be located along arterial or collector roads, and larger development and certain uses such as hotels also benefit from close proximity to freeway access. The subject site has high visibility along two major arterial roadways, I-494 and I-35E. However, access to the site from those points of visibility is not direct. Drivers must access Blue Gentian Road from Hwy. 149 or Hwy. 55. Hwy. 55 has no nearby interchange with either I-35E or I-494, and Hwy. 149 interchange is ½-mile from the site and is not visible to the site.

9 Page 9 Physical Suitability According to the City of Eagan s Comprehensive Guide Plan, commercial developments are most suitable on flat, open sites with few physical constraints, to accommodate larger building footprints and high parking needs. The subject site has some physical constraints, with some significant topography and wooded areas. SUMMARY/CONCLUSION The applicant is proposing to amend the land use designation of the 18.1 acre site from Major Office (MO) to Retail Commercial (RC) to allow a members-only retail warehouse including a motor fueling station, tire center and liquor sales. The property has been approved for multistory office since 2008, and such development has not come to fruition. The site has high visibility from three major roadways (I-494, I-35E, and Hwy. 55). Some physical constraints are present in terms of topography and trees. Access is from Blue Gentian Road which connects to Hwy. 55 and Hwy The applicant submitted a generalized traffic study addressing peak traffic times for the proposed Retail Commercial use as compared to the existing approved Major Office use. A more detailed traffic analysis would be required with specific development plans to determine traffic impacts and possible improvements to the surrounding roadway system. Municipal utilities are present to serve the development. Any development of the site would be subject to park and trail dedications, and should accommodate a future greenway and trail corridor. A tree inventory also would be required, and mitigation applies for tree removal in excess of the allowable amount. The acceptability of the proposed Comp Guide Amendment and the proposed use is a policy matter for City officials. The Comp Guide Amendment also is subject to review and approval by the Metropolitan Council, after which the request is returned to the City for final action. It is the City s policy to withhold final action on implementation of a land use change until it is accompanied by specific development plans. In this case, specific development plans would be required in the form of a PD Amendment application, which would go through public hearing with the Advisory Planning Commission, and then to the City Council. ACTION TO BE CONSIDERED To recommend approval of a Comprehensive Guide Plan Amendment to change the land use designation from MO, Major Office to RC, Retail Commercial upon approximately 18.1 acres located southeast of the I-494 and I-35E interchange.

PLANNING REPORT CITY OF EAGAN. APPLICANT: Janet Manley HEARING DATE: August 22, PROPERTY OWNER: Janet Manley APPLICATION DATE: July 19, 2017

PLANNING REPORT CITY OF EAGAN. APPLICANT: Janet Manley HEARING DATE: August 22, PROPERTY OWNER: Janet Manley APPLICATION DATE: July 19, 2017 PLANNING REPORT CITY OF EAGAN REPORT DATE: August 16, 2017 CASE: 36-PS-03-04-17 APPLICANT: Janet Manley HEARING DATE: PROPERTY OWNER: Janet Manley APPLICATION DATE: July 19, 2017 REQUEST: Rezoning and

More information

OP Council Resolution June 16, Planning and Development Services

OP Council Resolution June 16, Planning and Development Services OP-08-01 Council Resolution June 16, 2008 Planning and Development Services Kingsgate Landing Outline Plan Table of Contents 1.0 Introduction 1 1.1 Purpose of Plan 1 1.2 Plan Area Location 1 1.3 Ownership

More information

PLANNING REPORT CITY OF EAGAN. APPLICANT: Wyatt Sharing & Caring, LLC HEARING DATE: January 27, 2015

PLANNING REPORT CITY OF EAGAN. APPLICANT: Wyatt Sharing & Caring, LLC HEARING DATE: January 27, 2015 PLANNING REPORT CITY OF EAGAN REPORT DATE: January 21, 2015 CASE: 12-CG-05-12-14 APPLICANT: Wyatt Sharing & Caring, LLC HEARING DATE: January 27, 2015 PROPERTY OWNER: Gift of Mary, LLC APPLICATION DATE:

More information

PLANNING REPORT CITY OF EAGAN. APPLICANT: Cedar Grove Hospitality, LLC HEARING DATE: December 18, 2014

PLANNING REPORT CITY OF EAGAN. APPLICANT: Cedar Grove Hospitality, LLC HEARING DATE: December 18, 2014 PLANNING REPORT CITY OF EAGAN REPORT DATE: December 8, 2014 CASE: 19-PA-11-11-14 APPLICANT: Cedar Grove Hospitality, LLC HEARING DATE: PROPERTY OWNER: The Flats at Cedar APPLICATION DATE: Nov. 21, 2014

More information

City of Grande Prairie Development Services Department KENNEDY DEVELOPMENTS LTD. OUTLINE PLAN OP-09-01

City of Grande Prairie Development Services Department KENNEDY DEVELOPMENTS LTD. OUTLINE PLAN OP-09-01 City of Grande Prairie Development Services Department KENNEDY DEVELOPMENTS LTD. OUTLINE PLAN OP-09-01 July 27, 2009 TABLE OF CONTENTS 1.0 Introduction... 1 1.1 Plan Area Location & Context... 1 1.2 Ownership

More information

Staff Report and Recommendation

Staff Report and Recommendation Community Planning and Development Planning Services 201 W. Colfax Ave., Dept. 205 Denver, CO 80202 p: 720.865.2915 f: 720.865.3052 www.denvergov.org/cpd TO: City Council Neighborhoods and Planning Committee

More information

City of Grande Prairie Development Services Department

City of Grande Prairie Development Services Department City of Grande Prairie Development Services Department ROYAL OAKS NORTH OUTLINE PLAN OP-07-03 NW 35-71-6 W6M May 7, 2007 Royal Oaks North Outline Plan TABLE OF CONTENTS 1.0 INTRODUCTION........ 3 1.1 Purpose

More information

Gold Line Bus Rapid Transit Transit Oriented Development (BRTOD) Helmo Station Area Plan

Gold Line Bus Rapid Transit Transit Oriented Development (BRTOD) Helmo Station Area Plan Appendix F Gold Line Bus Rapid Transit Transit Oriented Development (BRTOD) Helmo Station Area Plan Introduction and Purpose of the Plan The Gold Line Bus Rapid Transit facility is an eleven-mile dedicated

More information

Mitchell Ranch South MPUD Application for Master Planned Unit Development Approval Project Narrative. Introduction

Mitchell Ranch South MPUD Application for Master Planned Unit Development Approval Project Narrative. Introduction Mitchell Ranch South MPUD Application for Master Planned Unit Development Approval Project Narrative Introduction Mitchell Ranch South is a proposed single family (detached) residential development on

More information

ARGENTA TRAIL (CSAH 28/63) REALIGNMENT SOUTH PROJECT (CP 63-25)

ARGENTA TRAIL (CSAH 28/63) REALIGNMENT SOUTH PROJECT (CP 63-25) ARGENTA TRAIL (CSAH 28/63) REALIGNMENT SOUTH PROJECT (CP 63-25) Preliminary Design Report February 2015 Prepared For: City of Inver Grove Heights Dakota County Prepared By: Kimley-Horn and Associates,

More information

RESIDENTIAL PLANNED UNIT DEVELOPMENT / SUBDIVISION AND REZONING CONCEPT AND DEVELOPMENT STAGE PLAN SUBMITTAL NARRATIVE

RESIDENTIAL PLANNED UNIT DEVELOPMENT / SUBDIVISION AND REZONING CONCEPT AND DEVELOPMENT STAGE PLAN SUBMITTAL NARRATIVE RESIDENTIAL PLANNED UNIT DEVELOPMENT / SUBDIVISION AND REZONING CONCEPT AND DEVELOPMENT STAGE PLAN SUBMITTAL NARRATIVE DEVELOPMENT TEAM DONEGAL SOUTH Maple Grove, Minnesota March 27, 2017 Applicant/Developer/Builder:

More information

CONCEPTUAL DEVELOPMENT PLAN REVIEW - CITY OF MARYLAND HEIGHTS

CONCEPTUAL DEVELOPMENT PLAN REVIEW - CITY OF MARYLAND HEIGHTS APPLICATION NUMBER: CDP15-0004 APPLICATION (PROJECT) NAME: MARYLAND OAKS APPLICANT: PROPERTY OWNER NAME: APPLICANT S REQUEST: McBride Maryland Oaks, LLC 16091 Swingley Ridge Road, Suite 300 Chesterfield,

More information

VILLAGE OF CLEMMONS PLANNING BOARD DRAFT STAFF REPORT

VILLAGE OF CLEMMONS PLANNING BOARD DRAFT STAFF REPORT VILLAGE OF CLEMMONS PLANNING BOARD DRAFT STAFF REPORT PETITION INFORMATION Docket # C-226 Staff Megan Ledbetter Petitioner(s) JBJH Properties, LLC Owner(s) JBJH Properties, LLC Subject Property 5892-49-1766

More information

The transportation system in a community is an

The transportation system in a community is an 7 TRANSPORTATION The transportation system in a community is an important factor contributing to the quality of life of the residents. Without a sound transportation system to bring both goods and patrons

More information

AWH REPORT OF THE PLANNING AND DEVELOPMENT DEPARTMENT FOR APPLICATION FOR REZONING ORDINANCE TO PLANNED UNIT DEVELOPMENT

AWH REPORT OF THE PLANNING AND DEVELOPMENT DEPARTMENT FOR APPLICATION FOR REZONING ORDINANCE TO PLANNED UNIT DEVELOPMENT AWH REPORT OF THE PLANNING AND DEVELOPMENT DEPARTMENT FOR APPLICATION FOR REZONING ORDINANCE TO PLANNED UNIT DEVELOPMENT MAY 8, 2014 The Planning and Development Department hereby forwards to the Planning

More information

Net Land Area (NLA): Area within zoning lot boundaries NLA= sq. ft. a) Credited Street Area (total adjacent frontage) x ½ width of public rightof-way

Net Land Area (NLA): Area within zoning lot boundaries NLA= sq. ft. a) Credited Street Area (total adjacent frontage) x ½ width of public rightof-way PROJECT FACT SHEET Section A: Project Information Application type: Date: Project Name: Use Type: (check/list all that apply) Office/Institutional Residential Mixed-Use Other: Overlay District: (check

More information

4 January 11, 2012 Public Hearing APPLICANT:

4 January 11, 2012 Public Hearing APPLICANT: . 4 January 11, 2012 Public Hearing APPLICANT: MID-ATLANTIC AUTO PROPERTY OWNER: DZR, LLC STAFF PLANNER: Leslie Bonilla REQUEST: Conditional Use Permit (truck rental, automobile service, and automotive/bulk

More information

Advance Engineering & Surveying PLLC

Advance Engineering & Surveying PLLC Advance Engineering & Surveying, PLLC Consulting in: Civil & Environmental Engineering Land Surveying Land Development 11 Herbert Drive Phone: (518) 698-3772 Latham, N.Y. 12110 Email:ncostape@gmail.com

More information

WORK SESSION STAFF REPORT Work Session Item No. 2. Michael Grochala, Community Development Director

WORK SESSION STAFF REPORT Work Session Item No. 2. Michael Grochala, Community Development Director WORK SESSION STAFF REPORT Work Session Item No. 2 WS Item 2 Date: March, 2018 To: From: Re: City Council Michael Grochala, Community Development Director 200 Comprehensive Plan Mixed Use Districts Background

More information

Colerain Township report to. Hamilton County Regional Planning Commission. December 2, 2010, 1:00PM. t a f f r e p o r t

Colerain Township report to. Hamilton County Regional Planning Commission. December 2, 2010, 1:00PM. t a f f r e p o r t Colerain Township report to Hamilton County Regional Planning Commission December 2, 2010, 1:00PM Preliminary Plan: Case No.: ZA2001-04, Forevergreen Prepared By: Amy Bancroft, Land Use Planner t a f f

More information

City of Sun Prairie Wetland Buffer Reduction Request

City of Sun Prairie Wetland Buffer Reduction Request City of Sun Prairie Wetland Buffer Reduction Request Westside Development Area January 9, 2017 Prepared by: City of Sun Prairie 300 E. Main Street Sun Prairie, WI 53590 BACKGROUND The City of Sun Prairie

More information

PROJECT BACKGROUND. Preliminary Design Scope and Tasks

PROJECT BACKGROUND. Preliminary Design Scope and Tasks PROJECT BACKGROUND Preliminary Design Scope and Tasks The purpose of this Study is the development of preliminary designs for intersection improvements for Trunk Highway (TH) 36 at the intersections of

More information

I-494 Rehabilitation Project SP (I-394 to Fish Lake Interchange) June 2014 Section 4(f) De Minimis Determination

I-494 Rehabilitation Project SP (I-394 to Fish Lake Interchange) June 2014 Section 4(f) De Minimis Determination I-494 Rehabilitation Project SP 2785-330 (I-394 to Fish Lake Interchange) June 2014 Section 4(f) De Minimis Determination State Project Number 2785-330 Federal Project No. NHPP-I494 (002) Trunk Highway:

More information

McDonald s Restaurant - Purcellville Town of Purcellville Special Use Permit Statement of Justification July 24, 2014

McDonald s Restaurant - Purcellville Town of Purcellville Special Use Permit Statement of Justification July 24, 2014 Introduction / Written Statement McDonald s Restaurant - Purcellville McDonald s Corporation is proposing to redevelop the existing McDonald s eating establishment with a drive-through located at 121 N

More information

Leduc Industrial Outline Plan SE W4

Leduc Industrial Outline Plan SE W4 Leduc Industrial Outline Plan SE 1-50-25-W4 Within the North Leduc Industrial ASP Prepared for: Leduc Energy Park Ltd. Prepared by: Stantec Consulting Ltd. File No. 1161 104655 V5 Table of Contents 1.0

More information

Description of Preferred Alternative

Description of Preferred Alternative Chapter 2 Description of Preferred Alternative 2.1 Introduction This chapter of the programmatic Sammamish Town Center Sub-area Plan Final EIS provides a more detailed description of the Preferred Alternative

More information

12 January 12, 2011 Public Hearing APPLICANT: TAILWIND DEVELOPMENT GROUP,LLC PROPERTY OWNER: CITY OF VIRGINIA BEACH

12 January 12, 2011 Public Hearing APPLICANT: TAILWIND DEVELOPMENT GROUP,LLC PROPERTY OWNER: CITY OF VIRGINIA BEACH 12 January 12, 2011 Public Hearing APPLICANT: TAILWIND DEVELOPMENT GROUP,LLC PROPERTY OWNER: CITY OF VIRGINIA BEACH STAFF PLANNER: Faith Christie REQUEST: Conditional Change of Zoning (from PD-H1 Planned

More information

EXHIBIT B PROJECT NARRATIVE POULSBO MEADOWS

EXHIBIT B PROJECT NARRATIVE POULSBO MEADOWS EXHIBIT B PROJECT NARRATIVE POULSBO MEADOWS Name of Project: Poulsbo Meadows; A Planned Residential Development (PRD)/Plat Applicants Name: PBH Group LLC/Byron Harris PO Box 1010 Silverdale, WA 98038 Description

More information

RESOLUTION NO R

RESOLUTION NO R e e RESOLUTION NO R04 0054 BE IT RESOLVED by the Mayor and City Council ofthe City ofpapillion that The Papillion Comprehensive Plan is hereby amended to incorporate the Option A Future Land Use Map Transportation

More information

Request for Statement of Interest in Implementation of the Roosevelt Road Redevelopment Plan

Request for Statement of Interest in Implementation of the Roosevelt Road Redevelopment Plan 425 Hillside Avenue Request for Statement of Interest in Implementation of the Roosevelt Road Redevelopment Plan I. INTRODUCTION The is seeking the services of a qualified consulting firm to prepare plans

More information

KEIZER STATION PLAN INTRODUCTION

KEIZER STATION PLAN INTRODUCTION KEIZER STATION PLAN INTRODUCTION Planning for this area began in 1987 when the Keizer Comprehensive Plan established the Chemawa Activity Center and McNary Activity Center. The first Chemawa Activity Center

More information

S o u t h C e n t r a l O u t l i n e P l a n. Leduc Business Park. North Leduc Industrial Area Structure Plan C it y of Led u c.

S o u t h C e n t r a l O u t l i n e P l a n. Leduc Business Park. North Leduc Industrial Area Structure Plan C it y of Led u c. Leduc Business Park North Leduc Industrial Area Structure Plan C it y of Led u c Prepared for Farm Air Properties Inc. January, 2007 Table of Contents Page Number 1.0 Purpose of Plan and Definition of

More information

Baumgarten MPUD. Exhibit 3 Evaluation Criteria

Baumgarten MPUD. Exhibit 3 Evaluation Criteria Pursuant to LDC subsections 10.02.13 B, 10.02.08 F and Chapter 3 G. of the Administrative Code, staff s analysis and recommendation to the Planning Commission, and the Planning Commission s recommendation

More information

Planning Commission Staff Report June 5, 2008

Planning Commission Staff Report June 5, 2008 Owner/Applicant Taylor Village Sacramento Investments Partners, LP c/o Kim Whitney 1792 Tribute Road #270 Sacramento, CA 95815 Staff Recommendation Planning Commission Staff Report Project: File: Request:

More information

Application Number: SD Project Name: Walton Farms Preliminary Subdivision (acting as Master Plan)

Application Number: SD Project Name: Walton Farms Preliminary Subdivision (acting as Master Plan) STAFF REPORT Town of Clayton Planning Department 111 E. Second Street, Clayton, NC 27520 P.O. Box 879, Clayton, NC 27528 Phone: 919-553-5002 Fax: 919-553-1720 Planning Board May 22, 2017 Application Number:

More information

14 October 10, 2012 Public Hearing APPLICANT: MPB, INC

14 October 10, 2012 Public Hearing APPLICANT: MPB, INC 14 October 10, 2012 Public Hearing APPLICANT: MPB, INC PROPERTY OWNER: MUNDEN & ASSOCIATES, LP STAFF PLANNER: Karen Prochilo REQUEST: Conditional Change of Zoning (AG-1 & AG-2 to Conditional O-2) ADDRESS

More information

ZONING COMPLIANCE PERMIT APPLICATION

ZONING COMPLIANCE PERMIT APPLICATION ZONING COMPLIANCE PERMIT APPLICATION 405 Martin Luther King Jr. Blvd phone (919) 968-2728 fax (919) 969-2014 www.townofchapelhill.org Parcel Identifier Number (PIN): Date: Section A: Project Information

More information

Chapter 3 Site Planning and Low Impact Development

Chapter 3 Site Planning and Low Impact Development CHAPTER 3 Site Planning and Low Impact Development Chapter 3 Site Planning and Low Impact Development 3.0 Introduction The City of Charleston requires that major residential, large commercial (>1 acre),

More information

NORTH BETHANY ELEMENTARY SCHOOL SITE ASSESSMENT

NORTH BETHANY ELEMENTARY SCHOOL SITE ASSESSMENT NORTH BETHANY ELEMENTARY SCHOOL SITE ASSESSMENT Prepared for: Prepared by: October 10, 2014 Page 2 Introduction and Purpose This report provides an assessment of two potential sites for a new elementary

More information

Application for Site Plan Review

Application for Site Plan Review Application for Site Plan Review City of Pontiac Office of Land Use and Strategic Planning 47450 Woodward Ave, Pontiac, MI 48342 T: 248.758.2800 F: 248.758.2827 Property/Project Address: Sidwell Number:

More information

DEVELOPMENT FRAMEWORK POST 2030 LAND USE PLAN INTRODUCTION

DEVELOPMENT FRAMEWORK POST 2030 LAND USE PLAN INTRODUCTION INTRODUCTION Oak Grove s Comprehensive Plan identifies a future Metropolitan Urban Service Area (MUSA). The Metropolitan Council does not anticipate extending utilities to this area prior to 2030. The

More information

2. Would the proposed project comply with the Land Use map? 3. Would the proposed project require a rezoning? 4. What is the proposed zoning district?

2. Would the proposed project comply with the Land Use map? 3. Would the proposed project require a rezoning? 4. What is the proposed zoning district? TOWN OF CHAPEL HILL Planning and Sustainability Department 405 Martin Luther King Jr. Blvd. Chapel Hill, NC 27514 www.townofchapelhill.org phone (919) 9682728 Concept Plans are intended to be an opportunity

More information

Rezoning Petition Pre-Hearing Staff Analysis September 17, 2018

Rezoning Petition Pre-Hearing Staff Analysis September 17, 2018 Rezoning Petition 2017-043 Pre-Hearing Staff Analysis September 17, 2018 REQUEST Current Zoning: R-3 (single family residential), R-17MF (multi-family residential), and CC (commercial center) Proposed

More information

SITE PLAN REVIEW ITEMS - REFERENCE CHECKLIST

SITE PLAN REVIEW ITEMS - REFERENCE CHECKLIST City of Seminole 9199 113 th Street N. Seminole, FL 33772 Ph: (727) 392-1966 Fx: (727) 319-6583 SITE PLAN REVIEW ITEMS - REFERENCE CHECKLIST Note: This checklist is designed to aid designers in the review

More information

CONSENT CALENDAR CITY PLANNING COMMISSION AGENDA ITEM NO: A.1, A.2 STAFF: LARRY LARSEN

CONSENT CALENDAR CITY PLANNING COMMISSION AGENDA ITEM NO: A.1, A.2 STAFF: LARRY LARSEN Page 8 CONSENT CALENDAR CITY PLANNING COMMISSION AGENDA ITEM NO: A.1, A.2 STAFF: LARRY LARSEN FILE NO: CPC PUZ 14-00013 - QUASI-JUDICIAL FILE NO: CPC PUD 14-00014 QUASI-JUDICIAL PROJECT: APPLICANT: OWNER:

More information

Executive Summary. NY 7 / NY 2 Corridor

Executive Summary. NY 7 / NY 2 Corridor Executive Summary NY 7 / NY 2 Corridor Transportation and Land Use Study December 2005 Prepared for: Town of Colonie Capital District Transportation Committee Prepared by: Introduction: Land use decisions

More information

C ity of Grande Prairie Development Services Department

C ity of Grande Prairie Development Services Department C ity of Grande Prairie Development Services Department FAIRWAY DEVELOPMENT OUTLINE PLAN OP 08 09 Approved April 6, 2009 Prepared by: Focus Corporation Table of Contents 1.0. Introduction 2 3 1.1. Plan

More information

COLVER ROAD INDUSTRIAL CONCEPT PLAN

COLVER ROAD INDUSTRIAL CONCEPT PLAN COLVER ROAD INDUSTRIAL CONCEPT PLAN A CONCEPTUAL LAND USE AND TRANSPORTATION PLAN FOR TA-4 AN URBAN RESERVE AREA OF THE CITY TALENT City of Talent Adopted by City Council Resolution No., June, 2015 PART

More information

Information for File # MVP MMJ; Elim Care

Information for File # MVP MMJ; Elim Care Information for File # MVP-217-2628-MMJ; Elim Care Applicant: Elim Care of Maple Plain Corps Contact: Melissa Jenny Address: 18 Fifth Street East, Suite 7, St. Paul, MN 5511-168 E-Mail: Melissa.m.jenny@usace.army.mil

More information

Chapter 13: Implementation Plan

Chapter 13: Implementation Plan Implementation A. Introduction The Implementation Plan, in table form on the following pages, provides a summary of all the Action Items recommended in Chapters 2 through 12. The table also indicates which

More information

Bylaw C-1262 Adopted February 6, Planning and Development Department

Bylaw C-1262 Adopted February 6, Planning and Development Department Bylaw C-1262 Adopted February 6, 2012 Planning and Development Department CITY OF GRANDE PRAIRIE BYLAW C-1262 A Bylaw to adopt the Brookfield Neighbourhood Outline Plan THE MUNICIPAL COUNCIL OF THE CITY

More information

CITY OF INVER GROVE HEIGHTS 8150 Barbara Avenue Inver Grove Heights, MN (651) Fax: (651)

CITY OF INVER GROVE HEIGHTS 8150 Barbara Avenue Inver Grove Heights, MN (651) Fax: (651) CITY OF INVER GROVE HEIGHTS 8150 Barbara Avenue Inver Grove Heights, MN 55077 (651) 450-2545 Fax: (651) 450-2502 www.invergroveheights.org SKETCH PLAN REVIEW APPLICATION FOR THE NORTHWEST AREA OVERLAY

More information

REQUEST FOR COUNCIL ACTION 6A AGENDA ITEM ORIGINATING DEPT. AGENDA ITEM CITY ADMINISTRATOR APPROVAL

REQUEST FOR COUNCIL ACTION 6A AGENDA ITEM ORIGINATING DEPT. AGENDA ITEM CITY ADMINISTRATOR APPROVAL DATE REQUEST FOR COUNCIL ACTION 6A AGENDA ITEM ORIGINATING DEPT. AGENDA ITEM CITY ADMINISTRATOR APPROVAL Community Development Territorial Greens PUD Concept Plan Development Stage Plan Subdivision (Preliminary

More information

SITE PLAN REVIEW APPLICATION AND CHECKLIST

SITE PLAN REVIEW APPLICATION AND CHECKLIST SITE PLAN REVIEW APPLICATION AND CHECKLIST PROJECT SUMMARY: Project Name: City/ETA Location: City ETA (Application fee & number of copies needed are based on location) Property Location (Legal Description

More information

STORM WATER UTILITY FREQUENTLY ASKED QUESTIONS

STORM WATER UTILITY FREQUENTLY ASKED QUESTIONS STORM WATER UTILITY FREQUENTLY ASKED QUESTIONS In 2007, the City Council adopted Ordinance No. 1155 establishing a storm water utility in the City. No fee structure was adopted at that time. The idea of

More information

PRELIMINARY CONDITIONAL USE SUBMITTAL CHECKLIST REQUIREMENTS

PRELIMINARY CONDITIONAL USE SUBMITTAL CHECKLIST REQUIREMENTS This checklist must accompany your submittal as the cover page. CONDITIONAL USE Application Submittal Checklist for PRELIMINARY AND FINAL APPROVAL Per Winter Park Land Development Code Sec. 58-90 PRELIMINARY

More information

The West Vaughan Employment Area Secondary Plan Policies

The West Vaughan Employment Area Secondary Plan Policies Part 2: The West Vaughan Employment Area Secondary Plan Policies 2.1 General Policies It is the policy of Council: 2.1.1. That the West Vaughan Employment Area (the WVEA), identified on Schedule 1, will

More information

USA Addition of South & East Side Residential Parcels. USA Deletion of a Town of Christiana Parcel. Conversion from USA to Limited Service Area

USA Addition of South & East Side Residential Parcels. USA Deletion of a Town of Christiana Parcel. Conversion from USA to Limited Service Area Village of Rockdale Village of Rockdale 148 Water Street Cambridge, WI 53523 Phone 608.423.1497 Fax 608.423.9694 Urban Service Area (USA) Amendment USA Addition of South & East Side Residential Parcels

More information

17.11 Establishment of Land Use Districts

17.11 Establishment of Land Use Districts 17.11 Establishment of Land Use Districts 17.11.010 Purpose. To promote the health, safety, and general welfare of City residents and those who come to South Salt Lake to work, exchange commerce and recreate.

More information

INFRASTRUCTURE EXISTING INFRASTRUCTURE A. Circulation B. Signals C. Drainage D. Utilities

INFRASTRUCTURE EXISTING INFRASTRUCTURE A. Circulation B. Signals C. Drainage D. Utilities 7.01. EXISTING INFRASTRUCTURE A. Circulation B. Signals C. Drainage D. Utilities 7.02. PROPOSED INFRASTRUCTURE A. Overall Concept B. Circulation C. Signals D. Drainage 7.03. INFRASTRUCTURE MAP A. Key Infrastructure

More information

Drexel, Barrell & Co.

Drexel, Barrell & Co. Drexel, Barrell & Co. June 18, 2018 Engineers/Surveyors Boulder Colorado Springs Greeley 3 South 7 th Street Colorado Springs, Colorado 80905-1501 719 260-0887 719 260-8352 Fax El Paso County Planning

More information

REQUEST FOR COUNCIL ACTION 6A AGENDA ITEM

REQUEST FOR COUNCIL ACTION 6A AGENDA ITEM DATE REQUEST FOR COUNCIL ACTION 6A AGENDA ITEM ORIGINATING DEPT. AGENDA ITEM CITY ADMINISTRATOR APPROVAL Community Development PUD Concept & Development Stage Plan Preliminary Plat & Final Plat PREVIOUS

More information

Major Subdivision Sketch Plan Checklist

Major Subdivision Sketch Plan Checklist This checklist provides specific requirements that are apart of the Sketch process. The entire process is described by the Huntersville Subdivision Review Process which details all the submittal and resubmittal

More information

STAFF SUMMARY FOR S17-02 SPECIAL USE PERMIT APPLICATION

STAFF SUMMARY FOR S17-02 SPECIAL USE PERMIT APPLICATION APPLICATION SUMMARY Case Number: S17-02 Request: STAFF SUMMARY FOR S17-02 SPECIAL USE PERMIT APPLICATION SUP application in order to develop a convenience food store. Applicant: Property Owner(s): Cindee

More information

III. PROJECT DESCRIPTION

III. PROJECT DESCRIPTION III. PROJECT DESCRIPTION A. PROJECT LOCATION Regional Setting The project site is located in the southeast quadrant of the City of Chico in Butte County, California and is comprised of four parcels totaling

More information

Drexel, Barrell & Co.

Drexel, Barrell & Co. Drexel, Barrell & Co. December 21, 2018 Engineers/Surveyors Boulder Colorado Springs Greeley 3 South 7 th Street Colorado Springs, Colorado 80905-1501 719 260-0887 719 260-8352 Fax El Paso County Planning

More information

Applicant Name Phone / Fax / Address City State Zip Code . Property Owner Phone / Fax / Address City State Zip Code

Applicant Name Phone / Fax / Address City State Zip Code  . Property Owner Phone / Fax / Address City State Zip Code Master Development Plan Application Community Development Department City of Redmond 411 SW 9 th Street Redmond, Oregon 97756 541-923-7721 541-548-0706 FAX Master Development Plan Fee $38,862.52 File Number

More information

This page intentionally left blank

This page intentionally left blank This page intentionally left blank Page 3 of 18 This page intentionally left blank STAFF REPORT FOR PLAN AMENDMENT 2015-III-DS1 BACKGROUND On January 13, 2015, the Fairfax County Board of Supervisors (Board)

More information

PROJECT NARRATIVE AVENIR PCD SITE PLAN #2 SITE PLAN REVIEW March 14, 2018 Request Avenir Holdings, LLC, the owner of the approved Avenir Planned Urban Planning and Design Landscape Architecture Communication

More information

Rezoning Petition Final Staff Analysis June 18, 2018

Rezoning Petition Final Staff Analysis June 18, 2018 Rezoning Petition 2018-028 Final Staff Analysis June 18, 2018 REQUEST Current Zoning: MX-1 LLWPA (mixed use district, Lower Lake Wylie Protected Area), R-3 LLWPA (single family residential, Lower Lake

More information

SHEFFIELD PARK Paulding County, GA DRI #588

SHEFFIELD PARK Paulding County, GA DRI #588 SHEFFIELD PARK Paulding County, GA DRI #588 Supplemental Information for RDC s DRI (Form 2) Review August 16, 2004 Prepared for: Mr. David Howerin Coosa Valley RDC 1 Jackson Hill Drive Rome, GA 30161 P.O.

More information

Definitions. Average Daily Traffic Demand (ADT): The actual number or projected number of cars that pass a point in a 24-hour period.

Definitions. Average Daily Traffic Demand (ADT): The actual number or projected number of cars that pass a point in a 24-hour period. Definitions Access Management: A combination of physical techniques and transportation policies used to control the flow of traffic between roads and the surrounding lands. Alternative City Form Scenarios:

More information

Request for Decision. Recommendation. Presented: Monday, Jul 07, Report Date Friday, Jun 20, Type: Public Hearings

Request for Decision. Recommendation. Presented: Monday, Jul 07, Report Date Friday, Jun 20, Type: Public Hearings Presented To: Planning Committee Request for Decision Application for rezoning in order to permit a place of worship on a vacant lot zoned for C1, Local Commercial uses, Cam Street, Sudbury Sitiri Investments

More information

Strategic Growth Area #1 Northampton Boulevard Corridor Area

Strategic Growth Area #1 Northampton Boulevard Corridor Area Strategic Growth Area #1 Northampton Boulevard Corridor Area Description Strategic Growth Area #1 has established itself as a major employment center in Southside Hampton Roads. Opportunities exist to

More information

5.0 Community Design Plan

5.0 Community Design Plan 5.0 Community Design Plan The Community Design Plan for the Mer Bleue area is a composite of three plans: Land Use Plan Transportation Plan Municipal Servicing Plan Read together, these Plans and associated

More information

General Location Courtyard at LMH Final Development Plan and Final Plat

General Location Courtyard at LMH Final Development Plan and Final Plat R-1 LEYDEN RIDGE LOMA RIDGE LOBDELL R-3 MILLER PARKWAY LAUSSAC Subject Property R-3 LOCHENSHIRE LESMER R General Location Courtyard at LMH Final Development Plan and Final Plat ¹ 230 115 0 230 Feet Airport

More information

COMMUNITY DESIGN. GOAL: Create livable and attractive communities. Intent

COMMUNITY DESIGN. GOAL: Create livable and attractive communities. Intent COMMUNITY DESIGN Intent An attractive, well-designed County will attract quality development, instill civic pride, improve the visual character of the community, and create a strong, positive image for

More information

VILLAGE OF CLEMMONS PLANNING BOARD DRAFT STAFF REPORT. Single Family Residential, Townhomes

VILLAGE OF CLEMMONS PLANNING BOARD DRAFT STAFF REPORT. Single Family Residential, Townhomes VILLAGE OF CLEMMONS PLANNING BOARD DRAFT STAFF REPORT PETITION INFORMATION Docket # C-212 Staff Megan Ledbetter Petitioner(s) Peacehaven Development LLC Owner(s) Larry Jarvis, William Alexander and Peacehaven

More information

Coffee Creek Park Development Low Impact Development (LID)

Coffee Creek Park Development Low Impact Development (LID) Coffee Creek Park Development Low Impact Development (LID) City of Duluth, St. Louis County, MN Presented By: Christopher J. Rousseau, P.E. February 27, 2008 Developer / Owner Information Trinity Development

More information

WEST HILL BUSINESS PARK AREA STRUCTURE PLAN

WEST HILL BUSINESS PARK AREA STRUCTURE PLAN MUNICIPAL DISTRICT OF PEACE NO. 135 WEST HILL BUSINESS PARK AREA STRUCTURE PLAN Prepared by: TABLE OF CONTENTS 1.0 Introduction... 1 1.1 Purpose of Plan........ 1 1.2 Plan Area..... 1 1.3 Existing Conditions...

More information

2 January 13, 2010 Public Hearing APPLICANT: AUTOBELL CAR WASH, INC

2 January 13, 2010 Public Hearing APPLICANT: AUTOBELL CAR WASH, INC REQUEST: Conditional Use Permit (car wash) 2 January 13, 2010 Public Hearing APPLICANT: AUTOBELL CAR WASH, INC PROPERTY OWNER: MESSER 1060 INDEPENDENCE BOULEVARD STAFF PLANNER: Carolyn A.K. Smith ADDRESS

More information

6 May 14, 2014 Public Hearing

6 May 14, 2014 Public Hearing 6 May 14, 2014 Public Hearing APPLICANT: MICHAEL D. SIFEN, INC. PROPERTY OWNER: GEORGE STREET CORP. STAFF PLANNER: Stephen J. White REQUEST: Conditional Use Permit (Mini-Warehouse / Self Storage) ADDRESS

More information

M E M O R A N D U M. Chair and Members of North West Planning Advisory Committee

M E M O R A N D U M. Chair and Members of North West Planning Advisory Committee Item 9.1.1 PO Box 1749 Halifax, Nova Scotia B3J 3A5 Canada M E M O R A N D U M TO: FROM: Chair and Members of North West Planning Advisory Committee Stephanie Salloum, Planner II DATE: June 26, 2017 SUBJECT:

More information

APPLICATION FOR REZONING PROPERTY CITY OF HOLLAND, MICHIGAN. Name of Applicant. Address, and Phone # of Applicant

APPLICATION FOR REZONING PROPERTY CITY OF HOLLAND, MICHIGAN. Name of Applicant. Address,  and Phone # of Applicant APPLICATION FOR REZONING PROPERTY CITY OF HOLLAND, MICHIGAN Name of Applicant Address, Email and Phone # of Applicant Name and Address of Owner (if other than applicant) Ownership Interest of Applicant

More information

This chapter describes the purpose of the Plan, introduces how the Plan is organized and provides contextual background for the Plan.

This chapter describes the purpose of the Plan, introduces how the Plan is organized and provides contextual background for the Plan. Chapter 1: INTRODUCTION Purpose of a Comprehensive Plan The 2040 Comprehensive Plan establishes Medina s vision as a community and sets goals and objectives which guide future decisions and policies. The

More information

Staff Report to the North Ogden City Planning Commission

Staff Report to the North Ogden City Planning Commission Staff Report to the North Ogden City Planning Commission SYNOPSIS / APPLICATION INFORMATION Application Request: Concept review on a legislative application to rezone land located at approximately 1750

More information

Mill Conversion Overlay District Zoning Bylaw Amendment

Mill Conversion Overlay District Zoning Bylaw Amendment Mill Conversion Overlay District Zoning Bylaw Amendment To see if the Town will vote to amend the Zoning By-Law by adding a new Section 13, Mill Conversion Overlay District, and by amending Sections 2.1,

More information

Bylaw C-1186 Adopted November 5, Planning and Development Services

Bylaw C-1186 Adopted November 5, Planning and Development Services Bylaw C-1186 Adopted November 5, 2007 Planning and Development Services CITY OF GRANDE PRAIRIE OFFICE CONSOLIDATION BYLAW C-1186 A Bylaw to adopt the Westgate Area Structure Plan (As Amended by Bylaw C-1186-1,

More information

ARTICLE 6: Special and Planned Development Districts

ARTICLE 6: Special and Planned Development Districts ARTICLE 6: Special and Planned Development Districts 6-10 Traditional Neighborhood Development (TND) District 6-10.10 Purpose and Intent The Traditional Neighborhood Development (TND) District provides

More information

Goal 1: To Encourage the Orderly, Harmonious and Judicious Use of University Resources in the Development of University Land.

Goal 1: To Encourage the Orderly, Harmonious and Judicious Use of University Resources in the Development of University Land. 2.0 Future Land Use Goal 1: To Encourage the Orderly, Harmonious and Judicious Use of University Resources in the Development of University Land. Objective 1.1: Make available future building sites that

More information

Watertown City Council

Watertown City Council City of Watertown Watertown City Council April 14 th, 2015 Agenda Item: City Comment on Sun Share CUP Application Request for Action: Motion to Approve City Comments regarding CUP Application Department:

More information

City Of Sparks Planning Commission Item

City Of Sparks Planning Commission Item Page 1 of 12 City Of Sparks Planning Commission Item Meeting Date: May17, 2012 Subject: PCN12009, Public Hearing, Consideration and possible action on a Master Plan Amendment and Rezoning request to change

More information

9 th Street Sub Area Plan

9 th Street Sub Area Plan 9 th Street Sub Area Plan In the 1990 s, when the Township prepared the last Master Plan, the 9 th Street corridor was studied as part of a larger 9 th Street Focus Area that included the West Main Street

More information

KASPER. City of Georgetown, Texas PUD Planned Unit Development. December 30, 2015 Revised January 27, 2016

KASPER. City of Georgetown, Texas PUD Planned Unit Development. December 30, 2015 Revised January 27, 2016 KASPER City of Georgetown, Texas PUD Planned Unit Development December 30, 2015 Revised January 27, 2016 Applicant: Sentinel Land Company, LLC 4910 Campus Drive Newport Beach, CA Prepared by: SEC Planning

More information

MEMORANDUM AGENDA ITEM #6c

MEMORANDUM AGENDA ITEM #6c South Florida Regional Planning Council MEMORANDUM AGENDA ITEM #6c DATE: FEBRUARY 1, 2010 TO: FROM: SUBJECT: COUNCIL MEMBERS STAFF CITY OF PARKLAND PROPOSED COMPREHENSIVE PLAN AMENDMENT (ALTERNATIVE REVIEW)

More information

Planning Districts INTRODUCTION

Planning Districts INTRODUCTION INTRODUCTION To facilitate detailed examination of development prospects for all areas of the community, Delano has been divided into 14 planning districts. The location of these planning districts is

More information

CITY PLANNING COMMISSION AGENDA. ITEM NO(s): C.1 C.3 STAFF: STEVE TUCK

CITY PLANNING COMMISSION AGENDA. ITEM NO(s): C.1 C.3 STAFF: STEVE TUCK Page 34 CITY PLANNING COMMISSION AGENDA ITEM NO(s): C.1 C.3 STAFF: STEVE TUCK FILE NOS: CPC ZC 12-00035 QUASI-JUDICIAL CPC NV 12-00036 QUASI-JUDICIAL AR DP 12-00039 QUASI-JUDICIAL PROJECT: APPLICANT: OWNER:

More information

CITY COUNCIL STAFF REPORT

CITY COUNCIL STAFF REPORT COUNCIL AGENDA: 04/11/17 ITEM: W\0^ CITY OF e: :SS SAN JOSE CAPITAL OF SILICON VALLEY CITY COUNCIL STAFF REPORT File No. C16-030 Applicant: Alex Rubashevsky Location Northwest corner of Oakland Road and

More information

Approved: CITY OF ARDEN HILLS, MINNESOTA PLANNING COMMISSION WEDNESDAY, AUGUST 5, :30 P.M. - ARDEN HILLS CITY HALL

Approved: CITY OF ARDEN HILLS, MINNESOTA PLANNING COMMISSION WEDNESDAY, AUGUST 5, :30 P.M. - ARDEN HILLS CITY HALL Approved: CITY OF ARDEN HILLS, MINNESOTA PLANNING COMMISSION WEDNESDAY, AUGUST 5, 2015 6:30 P.M. - ARDEN HILLS CITY HALL PLANNING CASES A. Planning Case 15-016; Final Planned Unit Development Arden Plaza;

More information

PDR /21/15 Noah Beals 1/7/15 xx

PDR /21/15 Noah Beals 1/7/15 xx PDR150001 1/21/15 Noah Beals 1/7/15 xx 01.07.15 HTP Harmony Frontage Infrastructure Preliminary Design Review Project Narrative a) What are you proposing/use? The HTP Harmony Frontage Infrastructure project

More information