1 WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY SAMPLE TASK WORK STATEMENT Fire Life Safety Upgrade Alexandria Facilities 1. BACKGROUND The Washington Metropolitan Area Transit Authority (Metro) was created by an interstate compact in 1967 to plan, develop, build, finance, and operate a balanced regional transportation system in the national capital area. The Authority began building its rail system in 1969, acquired four regional bus systems in 1973, and began operating the first phase of Metrorail in Today, Metrorail serves 86 stations and has 106 miles of track. Metrobus serves the nation's capital 24 hours a day, seven days a week with 1,500 buses. Metrorail and Metrobus serve a population of 3.4 million within a 1,500-square mile jurisdiction. Metro began its paratransit service, MetroAccess, in 1994; it provides about 1.5 million trips per year. 2. SCOPE / OBJECTIVE The objective of this task order is to upgrade and replace the existing fire alarm system at the following facilities located in Alexandria, VA. This includes the removal of all existing equipment and/or components not required for the functionality of the new system. Alexandria Yard S&I Shop Alexandria Yard Field Maintenance Center/TSSM Alexandria Yard Operations Building Alexandria Yard Traction Power Substation Alexandria Yard Equipment Storage Building Alexandria Yard Covered Storage Building Revenue Collection Facility (RCF) Telegraph Rd Training Facility Huntington Parking Garages Franconia Parking Garages The scope of this task order is to provide the Authority with all necessary materials, services, support, warranty repair, identification, and performance of installation and integration services for new Edwards EST fire alarm system required for the above mentioned facilities (address provided in Section 8.2), to begin no later than (NLT) a period of 90 days after receipt of the Notice to Proceed (NTP). The required tasks include demolition and removal of all equipment not necessary for the installation, configuration, testing, documentation, and final integration of the new fire alarm system. Additionally, it is critical that the buildings and all areas of work remain secure at all times during demolition and installation of equipment. 1 P a g e o f 1 0
2 All information and documentation developed by the Contractor under this task order shall be the property of the Authority and provided upon request and at the end of the contract. 3. TASKS The Contractor shall be directly responsible for ensuring the accuracy, timeliness, and completion of all tasks under this effort and shall coordinate with both facility management and the security staff to ensure there will be no lapses in security during the performance of the tasks. 3.1 Demolition of Existing Fire Alarm System The Contractor shall demolish and remove any and all components of the existing fire alarm system that are not required for use with the replacement system. This may include, but is not limited to, smoke detectors, heat detectors, manual pull stations, conduit, cabling, horns and strobes, terminal cabinets, indicating lights, and interface boxes The existing equipment to be removed must be identified on Demolition Plan(s) to be provided by the Contractor as part of the SSWP package identified in Section 4, subsection Unused equipment and/or components shall be identified and removed upon approval of the Demolition Plan(s). This may include, but is not limited to, wires and cables, conduit, panels and junction boxes All unused equipment shall be documented on a Parts Transfer Request (PTR) form and returned to the Authority. The Contractor shall coordinate with WMATA personnel to have surplus delivered to WMATA Open Material Storage (OMS) Warehouse located in Landover, MD All cabling to remain shall be neatly consolidated within its intended routing or path (i.e. cable trays, j-hooks). There shall be no hanging or loose cables or wires upon completion of this task A detailed Demolition Plan shall be included in the shop drawings The existing fire alarm system shall remain operational during demolition and shall remain functional until full integration of the new system is complete. 3.2 Installation and Configuration of New Fire Alarm System The Contractor shall supply, install, configure and test control panels, smoke and heat detectors, horns and strobes, cabling, and all other necessary fire alarm equipment required in a turnkey system. The new system shall be an Edwards EST3 Fire Alarm System The Contractor shall be responsible for the design, procurement, permits and fees, installation, configuration, testing and startup of the new fire alarm system to the unique conditions and requirements of the facility The Contractor shall provide configuration files of the new fire alarm system in accordance with Section Labels shall be placed on each end of the wires to identify the devices and the destination of the wire. 2 P a g e o f 1 0
3 3.2.5 All wiring, jacks, pathways, and patch panels will be labeled using TIA/EIA-606A-2010 Standards for Telecommunications Infrastructure of Commercial Buildings The cabling infrastructure for the new fire alarm system shall be in accordance with WMATA Design Criteria and Specifications in Attachment I. All interior cable shall be plenum rated The Contractor is to maintain a minimum 5 spacing between cables and sources of EMI, such as fluorescent light fixtures or unshielded power lines Pull boxes shall be sized per TIA/EIA 569 standards Ensure water tight integrity is maintained for all conduits, junction boxes and kiosk penetrations made during this project All strapping and lashing of cable within telecommunications and server rooms shall be with hook and replaceable loop straps for easy access to cable bundles to facilitate future moves, additions, and/or changes. Cable bundles shall consist of no more than 50 cables per bundle Traditional nylon cinch style tie wraps shall not be used to bundle cables. Only hook and replaceable loop style wraps are acceptable to bundle cables. 3.3 Installation of Fire Alarm Control Panels The Contractor shall install and configure EST Fire Alarm Control Panels at the sites shown on the drawings in Attachment II The Contractor shall provide all software licenses The Contractor shall install and configure software in accordance with manufacturer s specifications The Contractor shall provide software configuration files in a format to be determined by manufacturer. 3.4 Name Plates and Labels: The Contractor shall apply nameplates and/or labels to each electrical distribution and control equipment enclosure, telecommunication backboards and racks, and special systems backboards and racks Nameplates shall be engraved, laminated acrylic or melamine label, with black letters on white background /8 inch letters shall be used for identifying individual equipment and loads /4 inch letters shall be used for identifying grouped equipment and loads For Field-Installed Labels, the Contractor shall use encoded identifiers to comply with TIA/EIA-606A The Contractor shall install color coded labels on both ends The Contractor shall select size, color, and contrast of all labels to ensure that the identifiers are easily read Labels should be visible during the installation and normal maintenance of the infrastructure Labels should be resistant to the environmental conditions at the point of installation (such as moisture, heat, or ultraviolet light), and should have a design life equal to or greater than that of the labeled component All labels shall be generated by a mechanical device From and to locations shall be identified within the naming convention. 3 P a g e o f 1 0
4 3.5 Training The Contractor shall provide two 8-hour training sessions on any devices or electronics provided under this contract, for WMATA staff prior to SCI. 4. DOCUMENTATION 4.1 Project Schedule The Contractor shall provide a project schedule no later than five (5) business days after receipt of the Notice to Proceed. The project schedule shall include, but not be limited to the following: Project Title Project Working Title Prepared by Date/Control Number Element Number WBS Elements, Activity, Task, or Sub-Task Names Estimated Duration Start Date Finish Date Resources Required 4.2 Site Specific Work Plan (SSWP) Requirements The Contractor shall work with the project manager to complete a SSWP using a WMATA template The Contractor shall provide a demolition plan for each facility. 4.3 Shop Drawings and Submittals Prior to the start of work, the Contractor shall survey the facilities and notify WMATA of any issues that may arise during demolition and/or installation. The Contractor shall submit drawings to demonstrate a solution prior to any deviations in the design plans provided to WMATA Shop drawings and product submittals shall be presented to and approved by WMATA prior to installation of system. 4 P a g e o f 1 0
5 4.4 As-Built Drawings The Contractor shall present shop drawings based on concept drawings provided by WMATA (Attachment I). The drawings shall be readable when printed on 11x17 paper and meet WMATA s 2012 AutoCAD Standards The Contractor shall coordinate with WMATA s IT department for a list of IP addresses as needed. The IP addresses shall be included in the device schedule as part of the As- Built package The Contractor shall provide an As-Built device schedule in MS Excel file format The Contractor shall provide three (3) 11x17 printed sets of final As-Built drawings that clearly show new and existing equipment with all interface points on the drawings in accordance with concepts drawings and WMATA Design Criteria and Specifications. The Contractor shall provide one (1) Universal Serial Bus (USB) Drive (i.e. Flash Drive, Thumb Drive, Pen Drive, Jump Drive) with files in both AutoCAD 2010 (or newer) and PDF formats. 4.5 Fire Alarm Test Requirements The Contractor shall develop a comprehensive test plan for WMATA approval. 4.6 Substantial Completion Interim (SCI) The Contractor will notify the project manager once all devices have been tested and deemed functional by their technicians and are ready for WMATA inspection An inspection date will be set A device test data sheet will be completed, wire labeling will be verified and all aspects of the installation will be reviewed by a WMATA Inspector In the event of SCI failure, the Contractor shall generate a punch list for non-compliant items, provide corrective action plans, and a completion date shall be agreed upon with WMATA. 4.7 Operation and Maintenance Manuals The Contractor shall provide operation and maintenance (O&M) manuals for all equipment, devices, and components supplied under this contract. The O&M manual shall provide technical support and troubleshooting assistance for all fire alarm equipment, devices, or components provided under this task order The Contractor shall provide a recommended life cycle system maintenance plan for the installed fire alarm system. 5. REPORTS 5.1 Progress Schedule The Contractor shall provide a weekly progress schedule detailing advancements and complications that may delay the project. 5 P a g e o f 1 0
6 5.2 Monthly Status Report The Contractor shall provide a monthly status report documenting task support, issues, and progress. The report shall detail the Contractor activities during the reporting month and plans for the following two months. The report shall include a summary of work performed and deliverables completed, current or projected problems and issues and their resolution, an explanation of deviations from the previous month's projections, and any recommendations related to the effort. 5.3 Progress Reviews Progress Reviews will be performed as directed by the Contracting Officer's Representative (COR) and will generally summarize the status and progress of all activities being performed by the Contractor under this task work statement. Progress reviews will take place at those locations requested by the COR. Specific dates for progress reviews will be agreed between the COR and the Contractor's Program Manager. 6. DELIVERABLES SOW Subsection 4.1 Project Schedule 5.1 Progress Schedule Deliverable Due Format NTL 5 business days after receipt of Notice to Proceed NLT 10th business day of each month PDF PDF 5.2 Monthly Status Report NLT 10th business day of each month PDF 4.4 As-Built Drawing Package NLT 5 days prior to SCI AutoCAD 2010 or newer and PDF formats; 3 printed and 1 USB 4.6 Fully Operational Code Compliant EST3 Fire SCI Alarm System 4.5 Test Description Document and Test NLT 15 days prior to SCI Microsoft Word Report EST3 Software Configuration Files NLT 5 days prior to SCI Vendor Specific 4.7 O&M Manual NLT 5 days prior to SCI Vendor Specific 6 P a g e o f 1 0
7 7. TYPE OF CONTRACT AND PERIOD OF PERFORMANCE 7.1 This is a Firm Fixed Price order. The contract will contain a CLIN for Other Direct Charges. The period of performance will be 15 months after receipt of the Notice to Proceed. 8. AREA OF WORK 8.1 Work will be performed at an Authority sites within the National Capital Region. 8.2 The specific work locations are as follows: Alexandria Yard S&I Shop 3201 Eisenhower Avenue Alexandria Yard Field Maintenance Center/TSSM 3101 Eisenhower Avenue Alexandria Yard Operations Building 3401 Eisenhower Avenue Alexandria Yard Traction Power Substation 3965 Eisenhower Avenue Alexandria Yard Equipment Storage Building 3103 Eisenhower Avenue Alexandria Yard Covered Storage Building 3105 Eisenhower Avenue Revenue Collection Facility (RCF) (Bldg. C-94) 3301 Eisenhower Avenue, Alexandria, VA Telegraph Rd Training Facility 195 Telegraph Rd 7 P a g e o f 1 0
8 Huntington Parking Garages 2507 Huntington Avenue Alexandria, VA Franconia Parking Garages 6775 Frontier Dr Springfield, VA Staging Area All work will be performed at the above Alexandria facilities; all materials shall be removed at the end of each shift and the area clear of all debris (wire fragments, packaging materials and trash) The Contractor shall present an installation plan to WMATA prior to commencement of work as part of their Project Schedule. This plan shall include required area at each WMATA facility needed by the contractor for efficient operations The Contractor shall take all necessary steps to minimize adverse impacts to WMATA employees arising from the performance of the contracted work. 8.4 Work Hours The core work hours for the Alexandria Facilities are 6AM 4PM, Monday Friday. Actual hours vary from facility to facility Any work that requires drilling (core, hammer, etc.) or sawing must be done after 4PM. It is the responsibility of the Contractor to coordinate with facility management no later than 42 hours prior to the start of any such work Facility availability must be verified with the Facility s support staff; scheduled or unforeseen events or circumstances within the surrounding area could prevent entrance into the Alexandria S&I Yard or other facilities The standard workweek is Monday through Friday, except on Federal holidays or when the WMATA facility is closed due to local or national emergencies, administrative closings, or similar Government-directed facility closings. Actual hours vary from office to office within the Authority Recognized Holidays: Unless required under the terms of the contract or authorized by the contracting officer, the Contractor shall not plan to work at a WMATA facility on any of the following observed legal holidays: New Year s Day, Labor Day, Martin Luther King Jr. s Birthday, Columbus Day, President s Day, Veteran s Day, Memorial Day, Thanksgiving Day, Independence Day, and Christmas Day. 8 P a g e o f 1 0
9 8.5 Track Rights The Contractor shall work with WMATA personnel to obtain track rights and escorts. 9. OTHER DIRECT CHARGES (ODC) 9.1 The Contractor will be reimbursed for allowable, allocable and reasonable Other Direct Charges when approved in advance by the Contracting Officer. 10. SECURITY 10.1 All Contractor personnel in performance of this task order shall obtain a WMATA Contractor badge and Roadway Worker Protection (RWP) training. A background check is a requirement of this process and may take up to 3 business days to complete. Upon approval, the badges may be obtained at the ID office located at the lobby level of the Jackson Graham Building (JGB), Monday-Friday between the hours of 8:30 AM and 4:00 PM. The address for JGB is: Jackson Graham Building 600 Fifth Street, NW Washington, DC In the event that the necessary badges are not adjudicated within the timelines described above, the Authority will require the Contractor to develop a work-around plan to meet the requirements of the Task Work Schedule (TWS) and submit it to the Contracting Officer for acceptance. In the event that an acceptable plan is not submitted, the Authority shall be entitled to an equitable adjustment to the task order MTPD will provide escorts to all personnel working in the security sensitive portions of the facility. The Contractor shall notify the Contractor Officer s Representative (COR), in writing, NLT five (5) business days prior to requested date of access to security sensitive portions of the facility. 11. CONTRACTOR QUALITY CONTROL. The Contractor shall perform all technical and administrative planning, coordination, analysis and tracking of the diverse activities and disciplines provided by the Contractor to meet the requirements of this TWS. The Contractor shall manage and control task order resources to assure completion of all tasks within schedule and performance requirements. 9 P a g e o f 1 0
10 12. CONTRACTING OFFICER S REPRESENTATIVE. The COR shall be the focal point for all task order administration matters related to performance of this TWS. Only the Contracting Officer can make changes to the task order or this TWS, and any such changes are not effective unless directed in writing by the Contracting Officer. The initial COR for this task order is: Nicolas Dimitracopoulos TIES CENI Program Management 600 Fifth Street, NW Washington DC ndimitracopoulos@wmata.com The Contractor will be notified in writing concerning the replacement, if any of the COR for this task order. Subsequent CORs will be appointed in writing and a copy of the appointment letter will be provided to the Contractor. 13. LIST OF ATTACHMENTS Attachment Title Pages I Concept Drawings P a g e o f 1 0
RFP-FQ18063/KKB-Replace Three Roofs, DC, MD AND VA GREETINGS
RFP-FQ18063/KKB-Replace Three Roofs, DC, MD AND VA GREETINGS Good morning, on behalf of the Washington Metropolitan Area Transit Authority, we would like to welcome you to the Pre-proposal meeting for
More informationRancho Cucamonga Fire Protection District Prevention Bureau Standard
Rancho Cucamonga Fire Protection District Prevention Bureau Standard Title: Fire Alarm and Monitoring Systems Standard # 9-3 Effective: May 2002 Number of Pages: 7 Updated: December 2016 for consistency
More informationNORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017
SECTION 21 0800 - COMMISSIONING OF FIRE SUPPRESSION SYSTEMS GENERAL 1.1 SUMMARY General 1. Work under this contract shall meet the requirements of Division 01, General Requirements, Conditions of Contract,
More informationWeb Pages for Construction and Traveler Information Condition Reporting System 511 Phone Power. Data Processing and Response Formulation
Existing Existing To Be Modified To Be Developed Not Applicable Visual Surveillance (e.g. CCTV) Traffic Detectors (excluding presence detectors at intersections for signal control) Dynamic Message Sign
More informationPROJ. NO SECTION PAGING, SPEAKERS AND HARD-WIRED CLOCK SYSTEMS
SECTION 26 92 50 PAGING, SPEAKERS AND HARD-WIRED CLOCK SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions
More informationSUWANNEE RIVER WATER MANAGEMENT DISTRICT REQUEST FOR BID NO. 15/16-003AO FIRE ALARM SYSTEM INSTALLATION AND MONITORING.
SUWANNEE RIVER WATER MANAGEMENT DISTRICT REQUEST FOR BID NO. 15/16-003AO FIRE ALARM SYSTEM INSTALLATION AND MONITORING Table of Contents Section Title Page 1 Introduction 2 2 Proposed Schedule 2 3 Instructions
More information1. Floor above/floor below notification. 2. Private alarm notification. 3. Not Used 4. Voice alarm notification. 5. Not Used.
PART 1 GENERAL 1.01 Scope of Standard A. This Standard is intended to assure that fire alarm and signaling systems at Sam Houston State University provide the highest level of life safety possible. This
More informationMajis Industrial Services SAOC TENDER NO. MISCP/09/2014
Majis Industrial Services SAOC TENDER NO. MISCP/09/2014 Expression of Interest for Performance-based Operation and Maintenance (O&M) Services for the 20 MLD Majis Seawater Desalination Plant in Sohar,
More informationPOTOMAC YARD METRORAIL STATION
POTOMAC YARD METRORAIL STATION DRAFT ENVIRONMENTAL IMPACT STATEMENT EXECUTIVE SUMMARY R Introduction Environmental Impact Statement for a New Metrorail Station at Potomac Yard The Federal Transit Administration
More information1.3 REFERENCE STANDARDS
SECTION 28 4600 FIRE DETECTION AND ALARM PART 1 -GENERAL 1.1 SECTION INCLUDES A. Fire alarm system design and installation, including all components, wiring, and conduit. B. Circuits from protected premises
More informationA. The requirements of this Section and the other Division 26, 27 & 28 Sections apply to all the video surveillance system work.
PART 1 GNRAL 1.1. APPLICABL PROVISIONS A. The General, Supplementary and other Conditions of the Contract, modifications to the General Conditions, the Drawings, and the applicable provisions of the other
More informationDESIGN & CONSTRUCTION GUIDELINES
ADMINISTRATIVE SERVICES 4202 E. FOWLER AVENUE, FPC110 PHONE: (813) 974-2625 FACILITIES PLANNING & CONSTRUCTION TAMPA, FLORIDA 33620-7550 WEBSITE: USF.EDU/FPC DESIGN & CONSTRUCTION GUIDELINES DIVISION 21
More informationSECTION DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM
SECTION 283111 - DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division
More informationPurpose : Project Manager. Professional. Contractor: devices/system. compatibility
I. Title: Fire Alarm Systems Design, Construction and Commissioning II. Purpose : Define activities, identify stakeholders, and assign responsibilities as it relates to the installation of fire alarm devices
More informationDONALD H. BERG, ARCHITECT
DONALD H. BERG, ARCHITECT DVA PROJECT 632-CSI-402 PET/CT ROOM #A0-10 RENOVATION BASEMENT LEVEL, BUILDING 200 ARCHITECT S PROJECT No. 0917-02 ADDENDUM NO. 1 JUNE 25, 2018 Page 1 of 1 ARCHITECTURAL 1. Specifications:
More informationAddendum # 2 Wicomico County Circuit Court Second Floor Renovations Date of Addendum: 2/6/2017
Wicomico County Purchasing 125 N. Division St. Room B-3 Salisbury, MD 21801 Ph. 410-548-4805 Fax 410-334-3130 Email: purchasing@wicomicocounty.org Addendum # 2 Wicomico County Circuit Court Second Floor
More informationPRO-WATCH NOTIFIER SECONDARY FIRE INTERFACE ARCHITECT AND ENGINEERING SPECIFICATION
Section 00000 SECURITY PRO-WATCH NOTIFIER SECONDARY FIRE INTERFACE ARCHITECT AND ENGINEERING SPECIFICATION PART 1 GENERAL A. The intent of this document is to specify the minimum criteria for the design,
More informationI. INTRODUCTION SITE DESCRIPTION
Request for Proposals Design Services for the Visitor Access and Engagement Project at Roy s Redwoods Open Space Preserve Marin County Parks & Open Space Preserve Woodacre, Marin County, CA November 12,
More informationCampus Wide Fire Alarm Repairs
BID # 15-24 Campus Wide Fire Alarm Repairs SECTION "C" TECHNICAL SPECIFICATIONS OWNER Board of Trustees Middlesex County College 2600 Woodbridge Avenue P.O. Box 3050 Edison, New Jersey 08818-3050 PREPARED
More informationSECTION AUTOMATIC TRANSFER SWITCHES PART 1 - GENERAL
SECTION 16400 AUTOMATIC TRANSFER SWITCHES 1.01 RELATED DOCUMENTS PART 1 - GENERAL A. Drawings and general provisions of Contract, including General Conditions and Division 1 Specification sections, apply
More informationSECTION CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND SECURITY
SECTION 28 0513 -CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND SECURITY PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions
More informationREQUEST FOR PROPOSALS CLEANING SERVICES
REQUEST FOR PROPOSALS CLEANING SERVICES Jeffrey Gray City Manager City of Jonesville 265 E. Chicago Street Jonesville, MI 49250 manager@jonesville.org (517) 849-2104 Overview The City of Jonesville is
More informationAnnual Fire Systems and Backflow Preventers Testing
Facilities Management Request for Qualifications Annual Fire Systems and Backflow Preventers Testing At Various Facilities Proposals Due: 2:30 PM, Tuesday May 15, 2018 Deliver to: Attn: Sara Winger, Purchasing
More informationSECTION ENCLOSED CONTROLLERS
PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section. 1.2 SUMMARY A. This Section includes ac,
More informationCOUNTY OF ROCKLAND Department of General Services Purchasing Division
Department of General Services Purchasing Division Title: Contract Period: Fire Extinguishers and Suppression Systems-Inspection, Testing, Maintenance, Repair and Recharging 3/1/18 through 2/28/19 with
More informationAttachment F. Campus Capital Needs Sales Surtax Funded Detail Report
Facility Attachment F Campus Capital Needs Sales Surtax Funded Detail Report Facilities Services 2700 Judge Fran Jamieson Way Viera, Florida 32940-6601 Condition Code Estimate Longleaf Elementary 1.78
More informationPART 1 GENERAL Quality Assurance A. Fire Alarm Contractor Qualifications:
PART 1 GENERAL 1.01 Quality Assurance A. Fire Alarm Contractor Qualifications: 1 The Fire Alarm contractor shall be an Edwards Systems Technology (EST) designated representative and authorized to sell,
More informationC. The system shall be capable of turning luminaires on/off (where supported by the luminaire) as well as full range dimming.
SECTION 260943 SPECIFICATIONS - Wireless Network Lighting Controls. PART 1 - GENERAL 1.1 RELATED DOCUMENTS 1.2 SUMMARY AND KEY SYSTEM DIFFERENTIATORS A. The lighting control system specified herein shall
More informationGOLDFIELDS PRIMARY SCHOOL. TENDER SPECIFICATION For ELECTRICAL SERVICES MECHANICAL ENGINEER:
GOLDFIELDS PRIMARY SCHOOL TENDER SPECIFICATION For ELECTRICAL SERVICES PROJECT MANAGER: School Support Dunedin ARCHITECTURAL DESIGNER: Katipo Design ELECTRICAL ENGINEER: Pedersen Read Dunedin MECHANICAL
More informationSECTION ELECTRICAL IDENTIFICATION
SECTION 16075 - ELECTRICAL IDENTIFICATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification
More informationPre-Bid Meeting Minutes 2018 A & E RFP February 6, :00 a.m.
Attendees: Pre-Bid Meeting Minutes 2018 A & E RFP February 6, 2019 10:00 a.m. Anthony Shomin Sue Martin Architectural & Engineer Professionals KCKHA Modernization Coordinator KCKHA Modernization Admin.
More informationDERRY FIRE DEPARTMENT LISTED AGENT CERTIFICATION PROGRAM
DERRY FIRE DEPARTMENT LISTED AGENT CERTIFICATION PROGRAM THIS COURSE IS FOR AGENTS WISHING TO DISABLE TRANSMITTING SIGNALS IN ORDER TO PERFORM MAINTENANCE TESTING AND DRILLS. OBJECTIVE The objective of
More informationB. After installation, the Owner shall be able to perform hardware configuration changes as desired without the services of the Integrator.
SECTION 281300 - ACCESS CONTROL SYSTEM PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Minimum standards for Access Control Systems. B. Related Requirements: 1. Section 087100 Door Hardware. 1.2 REFERENCES
More informationRecommended location under the current MasterFormat 2004 is Section Elevator Door Smoke Containment System.
SMOKE GUARD SYSTEM MODEL 400 SPECIFICATION Smoke Guard, Inc. 287 N. Maple Grove Boise, ID 83704 Toll Free: 800.574.0330 Fax: 208.376.1600 e-mail: info@smokeguard.com website: http://www.smokeguard.com/
More informationPART 1 GENERAL Quality Assurance A. Fire Alarm Contractor Qualifications:
PART 1 GENERAL 1.01 Quality Assurance A. Fire Alarm Contractor Qualifications: 1 The Fire Alarm contractor shall be an Edwards Systems Technology (EST) designated representative and authorized to sell,
More informationOF AIRPORT COMMISSIONERS
OY i -401 0*11 oir". 4Los Angeles World Airports REPORT TO THE BOARD. OF AIRPORT COMMISSIONERS Meeting Date: Gvt A. Approved by: Aura Moor Chief In ormation Officer c -A/ / v Reviewed by: Samson Mengistu,
More informationREQUEST FOR QUALIFICATIONS
REQUEST FOR QUALIFICATIONS for the City of Lake Forest Issue Date: September 23, 2015 Bid Due Date: October 19, 2015 The City of Lake Forest 800 N. Field Drive Lake Forest, Illinois 60045 THE CITY OF LAKE
More informationNorthwestern University Scope of BAS Contractor
The purpose of this document is to describe the Enterprise Level Server at Northwestern University, and the separation of roles between the System Integrator and the Building Automation System Contractor.
More informationRecommended location under the current MasterFormat 2004 is Section Elevator Door Smoke Containment System.
SMOKE GUARD SYSTEM MODEL 200 SPECIFICATION Smoke Guard inc. 287 N. Maple Grove Boise, ID 83704 Toll Free: 800.574.0330 Fax: 208.639.7851 e-mail: info@smokeguard.com website: http://www.smokeguard.com/
More informationPROGRAMMABLE ENERGY SAVING TIMER. ASAP Timers, LLC Multi-Family Timer Model A-1. User Manual
PROGRAMMABLE ENERGY SAVING TIMER ASAP Timers, LLC Multi-Family Timer Model A-1 User Manual Table of Contents Product Information...1 Normal Operation...2 Display and Touch points...2 Peak Electricity Demand
More informationSECTION C. Section Cable Trays for Electrical Systems: Additional identification requirements for cable tray systems.
SECTION 26 0553 PART 1 GENERAL 1.1 SECTION INCLUDES A. Electrical identification requirements. B. Identification nameplates and labels. C. Wire and cable markers. D. Voltage markers. E. Underground warning
More informationMichigan State University Construction Standards COMMISSIONING OF FIRE ALARM SYSTEMS PAGE
PAGE 280800-1 SECTION 280800 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification
More informationM001. Revenue Services ISSUED FOR CONSTRUCTION SEPTEMBER. 2, East State Parkway Schaumburg, Illinois Do Not Scale Drawings
1 T Consultant: NOTES, SYMBOLS & ABBREVIATIONS - MECHANICAL Number Description M001 Vestibule 117 LAN/IT Coffee 115 116 Mail Room 118 114 113 112 Scanning 119 Open Office 101 FIRST FLOOR PLAN - MECHANICAL
More informationSMALL WORKS PROJECT REQUEST FOR SEALED BIDS
SMALL WORKS PROJECT REQUEST FOR SEALED BIDS PIERCE COUNTY FIRE PROTECTION DISTRICT #22 18421 OLD BUCKLEY HIGHWAY BONNEY LAKE, WA 98391 (253) 863-1800 (253) 863-1848 (FAX) Date Bid Requested: 5/24/2012
More informationHIGH-RISE RETROFIT ORDINANCES - NO and NO
INFORMATION BULLETIN / PUBLIC - BUILDING CODE REFERENCE NO.: LAMC 91.8604 Effective: 9-06-90 DOCUMENT NO. P/BC 2002-054 Revised: 4-15-03 Previously Issued As: MGD 88 HIGH-RISE RETROFIT ORDINANCES - NO.
More informationRequest for Statement of Interest in Implementation of the Roosevelt Road Redevelopment Plan
425 Hillside Avenue Request for Statement of Interest in Implementation of the Roosevelt Road Redevelopment Plan I. INTRODUCTION The is seeking the services of a qualified consulting firm to prepare plans
More informationRocky Mountain Fire Protection District 4390 Eldorado Springs Drive Boulder, CO
Rocky Mountain Fire Protection District 4390 Eldorado Springs Drive Boulder, CO 80303 303-494-3735 Contractor s Checklist and Installation Guide TABLE OF CONTENTS Fire Protection Narrative........... 3
More informationSECTION WET-PIPE SPRINKLER SYSTEMS
SECTION 21 13 13 WET-PIPE SPRINKLER SYSTEMS PART 1 - GENERAL 1.1 SCOPE OF WORK A. Design, installation and testing shall be in accordance with NFPA 13 except for specified exceptions. B. The demolition
More informationRevised March 2015 Fire Alarm Systems Verification. Schedule I(A) Services. *Manditory Site visit required*
1.0 Description of Services Required: Revised March 2015 Fire Alarm Systems Verification Schedule I(A) Services *Manditory Site visit required* Perform the annual fire alarm system and sprinkler system
More informationRequest for Proposals: Architectural/Design Guidelines
Request for Proposals: Architectural/Design Guidelines January 11, 2017 1.0 INTRODUCTION The City of Issaquah, Washington is soliciting proposals from qualified consulting firms to lead a community conversation
More informationOVERMOUNTAIN VICTORY TRAIL BURKE CALDELL CORRIDOR FEASIBLITY STUDY REQUEST FOR QUALIFICATIONS CALDWELL COUNTY PATHWAYS
OVERMOUNTAIN VICTORY TRAIL BURKE CALDELL CORRIDOR FEASIBLITY STUDY REQUEST FOR QUALIFICATIONS CALDWELL COUNTY PATHWAYS Caldwell County Pathways along with our co-partners City of Lenoir, Town of Gamewell,
More informationStandard of Practice - Fire Alarm Systems. NOTE: Significant revisions or additions to the previous standards are highlighted in italics.
A28.1 Standard of Practice - Fire Alarm Systems NOTE: Significant revisions or additions to the previous standards are highlighted in italics. OBJECTIVE OF STANDARD To provide compliant smart addressable
More informationBOARD OF COUNTY COMMISSIONERS
TULSA COUNTY PURCHASING DEPARTMENT MEMO DATE: SEPTEMBER 2, 2015 FROM: PURCHASING DIRECTO -~ TO: SUBJECT: BOARD OF COUNTY COMMISSIONERS PROFESSIONAL SERVICE AGREEMENT- HOWELL & VANCUREN, INC. SUBMITTED
More informationTAB C-6 KEYLESS ACCESS AND SECURITY SYSTEM GUIDELINE
TAB C-6 KEYLESS ACCESS AND SECURITY SYSTEM GUIDELINE The University of Arizona has implemented a Keyless Access and Security System program to provide a cost effective, efficient, and maintainable means
More informationElectronic Safety and Security
28 Electronic Safety and Security NOTE: This is a new section, which includes content from previous sections of the KU Design Standards, along with appropriate revisions and updates. Significant revisions
More informationWashington Metropolitan Area Transit Authority (WMATA)
Washington Metropolitan Area Transit Authority () National Transportation Safety Board (NTSB) Detailed Tracker As of 0/0/18 Description #s * Unacceptable: The hazard must be mitigated in the most expedient
More informationmaster plan of highways bus rapid transit amendment
Scope of Work master plan of highways bus rapid transit amendment September 2011 Montgomery County Planning Department M-NCPPC MontgomeryPlanning.org 1 Scope of Work master plan of highways bus rapid transit
More informationThe Owner will provide the QEI inspection and certification services.
General The Owner will provide the QEI inspection and certification services. Elevators Electric operated traction elevators are preferred; holeless hydraulic oil operation may be considered where use
More informationChapter Master Planned Communities (MPC) District
Sections 14.53.010 Purpose and Intent 14.53.020 Applicability 14.53.030 Procedure 14.53.040 MPC Standards 14.53.050 Required Findings 14.53.010 Purpose and Intent Chapter 14.53 Master Planned Communities
More informationTABLE OF CONTENTS Part 6 Legal Basis for Fire Safety Planning... 2
TABLE OF CONTENTS Part 6 Legal Basis for Fire Safety Planning... 2 6.1] GENERAL... 2 6.2] EXCERPTS FROM 2012 BC FIRE CODE PART 2 BUILDING AND OCCUPANT FIRE SAFETY... 3 6.3] EXCERPTS FROM 2012 BC FIRE CODE
More informationWinston-Salem State University Campus Master Plan 2016 Update
Winston-Salem State University Campus Master Plan 2016 Update Request for Qualifications Page 1 of 6 Overview Winston-Salem State University (WSSU) is requesting qualifications from planning firms specializing
More informationRFP/RFQ. for Concept & Schematic Design Services. for Outdoor Garden Enhancements. to Cleveland Botanical Garden
RFP/RFQ for Concept & Schematic Design Services for Outdoor Garden Enhancements to Cleveland Botanical Garden Process facilitated by Smithink Distributed: October 30, 2012 Responses Due by: November 21,
More informationPROJECT BACKGROUND. Preliminary Design Scope and Tasks
PROJECT BACKGROUND Preliminary Design Scope and Tasks The purpose of this Study is the development of preliminary designs for intersection improvements for Trunk Highway (TH) 36 at the intersections of
More informationA. Product Data: For each electrical identification product indicated. B. Comply with 29 CFR and 29 CFR
September 2012, rev. 00 26 0553 Identification for Electrical Systems PART 1. GENERAL 1.01 Summary A. Section Includes: 1.02 Submittals 1. Identification for raceways. 2. Identification of power and control
More informationUNIVERSITY OF MANITOBA PROCEDURE
UNIVERSITY OF MANITOBA PROCEDURE Procedure: UNIVERSITY BUILDING ACCESS CONTROL Parent Policy: Effective Date: July 2, 2013 Revised Date: Review Date: July 2, 2023 Approving Body: Authority: Responsible
More informationSection COMMUNICATION EQUIPMENT ROOM FITTINGS. Section Communications Cabinets, Racks, Frames and Enclosures
PART 1 GENERAL 1.1 WORK INCLUDED Section 27 11 00 COMMUNICATION EQUIPMENT ROOM FITTINGS Section 27 11 16 Communications Cabinets, Racks, Frames and Enclosures A. Provide all labor, materials, and equipment
More informationD. The work addressed in this section consists of a fire protection system, which may include coordination with one or more of the following:
PART 1 GENERAL 1.01 Scope of Standard A. This standard provides general requirements of Sam Houston State University for the design and construction of standpipe systems to include combination standpipe
More informationWashington Metropolitan Area Transit Authority Arcing/Smoke Event with Passenger Evacuation
Washington Metropolitan Area Transit Authority Arcing/Smoke Event with Passenger Evacuation L Enfant Plaza Station, Washington, D.C. January 12, 2015 Joe Gordon - IIC 1 2 North Fatality and Injuries Passengers,
More informationB. Configuration of system shall be through Schneider Electric in Homewood, Illinois (Jerry Lanfear ).
SECTION 28 13 00 - ACCESS CONTROL PART I - GENERAL 1.1 SUMMARY A. This specification section describes the furnishing, installation, commissioning, and programming of a complete, turnkey, hardwired Andover
More informationThe City of Bowie Arts Committee Bowie, Maryland ART IN PUBLIC PLACES PROGRAM Request for Proposals
The City of Bowie Arts Committee Bowie, Maryland ART IN PUBLIC PLACES PROGRAM Request for Proposals Deadline for Submission: September 1, 2016. 5 p.m. EDT Background The City of Bowie announces a Request
More informationSECTION SECURITY TESTING AND COMMISSIONING
SECTION 280800 - SECURITY TESTING AND COMMISSIONING PART 1 - GENERAL 1.1 WORK INCLUDES A. General Description: This specification section covers the provision of preliminary testing, acceptance testing,
More informationSECTION TESTING OF FIBER OPTIC CABLES
PART 1 GENERAL 1.01 DESCRIPTION A. The work covered by this section of the Specifications includes all labor necessary to perform and complete such construction, all materials and equipment incorporated
More informationFIRE & LIFE SAFTEY STANDARD
Title: Effective Date: 01/01/14 Revised Date: 1/1/14 Code References: Title 16, Chapter 16.16 of the Roseville Municipal Code, NFPA 72 Note: This standard is a summary of Fire Department clarifications
More informationFort Rouge Leisure Centre Section HVAC Upgrades Phase 2 Page 1 of 5 Bid Opportunity No March 2013 FIRE ALARM SYSTEMS
HVAC Upgrades Phase 2 Page 1 of 5 Part 1 General 1.1 SUMMARY.1 Section Includes:.1 Materials and installation for fire alarm systems upgrades..2 Audible signal devices..3 End-of-line devices..4 Sustainable
More informationIDENTIFICATION FOR ELECTRICAL SYSTEMS July Electrical Systems
SECTION 26 05 54 IDENTIFICATION FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Nameplates. 2. Labels. 3. Wire markers. 4. Conduit markers. 5. Permanent Marking. 6. Underground
More informationAPPENDIX H (DESIGN SUBMISSION CRITERIA)
APPENDIX H (DESIGN SUBMISSION CRITERIA) FIRE ALARM SYSTEM As per ACCORD standard Part 5, section 5.7 Fire Alarm System Design to be verified by ACCORD Chief Safety Inspector. Testing of the installation
More informationD3 January 14, 2015 Public Hearing
D3 January 14, 2015 Public Hearing APPLICANT: DONALD J. BOUCHER, JR. PROPERTY OWNER: D.J.B. SERVICE CENTER, LLC STAFF PLANNER: Kristine Gay REQUEST: A. Conditional Change of Zoning (I-1 to B-2) B. Conditional
More informationA Better City Request for Qualifications
A Better City Request for Qualifications Urban design proposal for the pedestrianization of Birch Street in Roslindale December 13, 2018 Responses preferred by January 8, 2019 at 11:59pm Eastern Time Request
More informationNOTICE OF AVAILABILITY (NOA) OF A DRAFT ENVIRONMENTAL IMPACT REPORT AND NOTICE OF PUBLIC HEARING 2190 Shattuck Avenue Mixed-Use Project
Planning and Development Department Land Use Planning Division NOTICE OF AVAILABILITY (NOA) OF A DRAFT ENVIRONMENTAL IMPACT REPORT AND NOTICE OF PUBLIC HEARING 2190 Shattuck Avenue Mixed-Use Project Notice
More informationCARD ACCESS CONTROL SYSTEM
SECTION 13851 CARD ACCESS CONTROL SYSTEM PART 1 GENERAL 1.01 SUMMARY A. Section Includes: A complete, operable, tested, integrated proximity access control system, to operate on a proximity principle where
More informationWEST VIRGINIA UNIVERSITY
WEST VIRGINIA UNIVERSITY Environmental Health and Safety (SOP) WV State Fire Marshal (SFM) Project Plans Review Process & Procedures West Virginia University Environmental Health & Safety Page 1 of 10
More informationTysons Circulator Study: Process and Preliminary Results Summary. March 2012
Tysons Circulator Study: Process and Preliminary Results Summary March 2012 Background: 1. The Comprehensive Plan for the Tysons Corner Urban Center calls for a System of Circulators in Tysons Corner to:
More informationBold items are particular to the City of Euless
EULESS FIRE DEPARTMENT FIRE MARSHAL S OFFICE INFORMATION LINE: Revised 8/2004 Fire Chief Lee Koontz Fire Marshal Paul Smith EFD-FMO 3-1 2003 International Fire & Building Code as Amended NFPA Standards
More informationQUALITY ASSURANCE SURVEILLANCE PLAN (QASP) INTRODUCTION
EXHIBIT 1 PLAN (QASP) CONTRACT No. G S - 01 P - 16 - BW - D - 7004 INTRODUCTION This Quality Assurance Surveillance Plan (QASP) is designed to provide the General Services Administration (GSA) with an
More information"This is only the scope of work for the project. For more information, interested parties should contact Procurement at
"This is only the scope of work for the project. For more information, interested parties should contact Procurement at purchasing@stpgov.org to ensure receipt of a full bid package, to be listed as a
More informationFire Smoke Damper Actuator Replacements SECTION COMMISSIONING OF HVAC
PART 1 GENERAL 1.01 SUMMARY SECTION 23 08 00 COMMISSIONING OF HVAC A. This section covers the Contractor's and Commissioning Authority (CA) responsibilities for commissioning; each subcontractor or installer
More informationCommercial Rules and Regulations
Commercial Rules and Regulations Public Works and Community Development Department City of Shenandoah 29955 I 45 North Shenandoah, Texas 77381 281 298 5522 www.shenandoahtx.us Construction Documents Submit
More informationRegional Training. Seminar. » EasyPower Hands-On» Protective Device Coordination» Arc Flash Hazard Analysis. March 12-16, 2018 Austin, TX
Regional Training» EasyPower Hands-On» Protective Device Coordination» Arc Flash Hazard Analysis Seminar March 12-16, 2018 Austin, TX DoubleTree Austin EasyPower, state-of-the-art Power System Analysis
More informationSPECIFIC PLAN Requirements
CITY OF LANCASTER PLANNING DEPARTMENT 44933 Fern Avenue, Lancaster, California 93534 (661) 723-6100 SPECIFIC PLAN Requirements Purpose The purpose of a specific plan is to provide for the logical development
More informationCOMMISSION ORDER. IT IS FURTHER ORDERED that the Request for Bid and Notice to Bidders be displayed on the Franklin County website.
4.e STATE OF MISSOURI County of Franklin ss. COMMISSION ORDER Commission Order No. 2016-316 Third Quarter Term 2016 Tuesday,August,09,2016 Bid Notice IN THE MATTER OF ADVERTISING FOR SEALED BIDS FOR SMOKE
More informationPrinceton Joint Unified School District Invitation for Bid Installation of District-Wide Lighting Occupancy Sensors
Princeton Joint Unified School District Invitation for Bid Installation of District-Wide Lighting Occupancy Sensors 1. SUMMARY AND BACKGROUND: Princeton Joint Unified School District located in Princeton
More informationRESOLUTION NO. R Refining the route, profile and stations for the Downtown Redmond Link Extension
RESOLUTION NO. R2018-32 Refining the route, profile and stations for the Downtown Redmond Link Extension MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee Board PROPOSED ACTION 09/13/2018
More informationRFP Addendum 2 March 31, 2016
RFP Addendum 2 March 31, 2016 For Best Value Procurement Option Three Security Upgrades Ph 1 UT Health Science Center SBC No. 540/013-04-2015 This Addendum forms a part of the Request for Proposals (RFP)
More informationCALL FOR ENTRIES FOR PROFESSIONAL LANDSCAPE ANALYSIS AND PLANNING
T H E B O S T O N S O C I E T Y O F L A N D S C A P E A R C H I T E C T S 2013 Annual Awards Program CALL FOR ENTRIES FOR PROFESSIONAL LANDSCAPE ANALYSIS AND PLANNING RECOGNIZING EXCELLENCE IN LANDSCAPE
More informationSound Transit 3. Appendix A: Detailed Description of Facilities and Estimated Costs
Sound Transit 3 Appendix A: Detailed Description of Facilities and Estimated Costs Table of Contents Sound Transit 3 Plan Map... 3 Total agency: Projects... 4 Total agency: Sources and uses of funds...
More informationCONTRACT FOR USE OF FIRE PROTECTION SYSTEM
CONTRACT FOR USE OF FIRE PROTECTION SYSTEM THIS AGREEMENT made and entered on this the day of, 20 by and between its successors and assigns, hereinafter referred to as Customer and the Jessamine County
More informationWestern Pennsylvania Conservancy Clairton & Harrison Community Greening Assessment Projects Request for Proposals July 2018
Western Pennsylvania Conservancy Clairton & Harrison Community Greening Assessment Projects Request for Proposals July 2018 Proposal Information The Western Pennsylvania Conservancy (WPC) is seeking proposals
More informationSECTION TESTING OF FIBER OPTIC CABLES
SECTION 27 08 23 TESTING OF FIBER OPTIC CABLES PART 1 GENERAL 1.01 DESCRIPTION A. The work covered by this section of the Specifications includes all labor necessary to perform and complete such construction,
More informationSECTION FIRE DETECTION AND ALARM
PART 1 - GENERAL 1.1 RELATED SECTIONS: Refer to Section 15300 for requirements regarding fire protection systems. 1.2 SCOPE OF SECTION: This section contains the requirements for equipment and installation
More informationOPERATIONAL GUIDELINE. Office of the Fire Commissioner O.G.# Revision #1 TITLE: ISSUING ORDERS Page 1 of 8
TITLE: ISSUING ORDERS Page 1 of 8 PURPOSE: SCOPE: POLICY: To ensure a consistent approach to the issuance of Province fire orders. All Local Assistants to the Fire Commissioner. All orders shall be dealt
More information