Additional personnel accompanying me on the site inspection today included Paula Fitzgerald (Biosar) and Ryan Molsee (Enel).

Size: px
Start display at page:

Download "Additional personnel accompanying me on the site inspection today included Paula Fitzgerald (Biosar) and Ryan Molsee (Enel)."

Transcription

1 Dodge Center Date of Inspection Start/End Time 12:00 pm Assembly complete, CCTV cabling and trenching, Decompaction equipment testing Partly cloudy, temperature in the low to mid-40 s Additional personnel accompanying me on the site inspection today included Paula Fitzgerald (Biosar) and Ryan Molsee (Enel). Equipment and methods to meet de-compaction needs were tried and assessed. A disk was found to be inadequate as there was not enough weight to push the disk through the compacted areas. A small chisel/ripper was found to achieve the best results. A John Deere 6400 with three-point attachment was used to control the depth of the implement. One pass with the chisel achieved was sufficient in softer areas, but the chisel floated on more compacted areas, resulting in only one to two inches of scarification over a severely compacted zone. Additional passes with the chisel improved results. There was an extended discussion on the methods and steps needed to complete final restoration work. Power will be required to a site in order to rotate the panels and provide adequate work space for the equipment. Prior to de-compaction, all interior silt fences and similar erosion and sediment control devices will need to be removed or placed so that they will not interfere with the work. General site clean up to remove trash, soil and imported material piles, reclaim laydown yards, residual spoil piled under arrays, etc. must occur prior to de-compaction. Approximately two to three days will be necessary to de-compact most sites. Following de-compaction, the sites will need to be stabilized with straw mulch or equivalent, and seeded with a cover crop or final seed mix. Dodge Center

2 Given the amount of pre-work necessary to finalize the restoration measures, most of these activities will likely occur in Spring, The only compliance item noted at the time of the site visit was the presence of subsoils and aggregate that was improperly added to the topsoil stockpile at the lower laydown yard in the northern portion of the site. Subsoils and aggregate added to the topsoil stockpile. Corrective actions discussed onsite included: Remove subsoils and other material from the topsoil stockpile. Photos: Photo 1: Subsoil and other non-topsoil material added to topsoil stockpile on northern end of the site. Dodge Center

3 West Faribault Date of Inspection Start/End Time 3:30 pm Piles, inverters, SCADA, assembly, material delivery. Mostly cloudy, temperature in the upper 40s. Additional personnel accompanying me on the site inspection today included Paula Fitzgerald (Biosar). Site is in very good condition. There is little rutting and soils are well segregated throughout the site, including re-work on the PCU and SCADA conduits. Two dewatering setups used felt sediment bags that have not been effective at other sites; however, due to the low volume and velocity of pumping activities, only a minor amount of sediment was observed on the bags and the issue is not considered to be significant. No compliance items were observed. No significant issues were observed. Corrective actions discussed onsite included: None. West Faribault

4 Chisago Date of Inspection Start/End Time 7:00 am Assembly complete, placement of ground wire around facilities, commissioning later this week. Cloudy/overcast, temperature in the upper 30s to lower 40s. Additional personnel accompanying me on the site inspection today included Paula Fitzgerald (Biosar), Jacob Thompson (Barr), and Ryan Molsee (Enel). Site is in good condition. Assembly of the site is complete. Some trash remains onsite and Toby (Biosar site manager) stated that a cleanup day is planned for tomorrow. No compliance concerns were noted. None. Corrective actions discussed onsite included: None. Chisago

5 Lawrence Creek Date of Inspection Start/End Time 8:30 am POI boring in progress, assembly complete, commissioning later this week. Mostly cloudy, temperature in the low to mid 40s. Additional personnel accompanying me on the site inspection today included Jacob Thompson (Barr Engineering), Ryan Molsee (Enel), and Paula Fitzgerald (Biosar). Site is in good condition. There are a number of cleanup items required before restoration takes place, such as open trench pits, piles of aggregate, scattered construction mats, subsoils on surface, spoil pile remnants under panels, etc. Subsoil spoils were found to have been spread over two travel routes. Brandon (Biosar assistant site manager) said that he was relatively new to the site and wasn t sure why the spoils were spread. Subsoil material spread over topsoil on two travel routes. Various piles of aggregate, small spoil piles under arrays, etc. remaining on topsoil surface. Corrective actions discussed onsite included: Reclaim/remove all subsoils, small spoil piles, imported aggregate and rock material from topsoil surface prior to restoration activities. Lawrence Creek

6 Photos: Photo 1: Subsoil spoils spread over travel route between arrays. Photo 2: One of several residual material piles that still need to be removed from site. Lawrence Creek

7 Hastings Date of Inspection Start/End Time 10:45 am Assembly, pile driving, pile drilling, material deliveries, inverters, SCADA, trenching and cabling. Partly cloudy, temperature in the low 50s. Additional personnel accompanying me on the site inspection today included Ryan Molsee (Enel), Paula Fitzgerald (Biosar), and Jacob Thompson (Barr). Site was in good condition. Area that requires additional grading to achieve proper pile reveal height has a trench interfering with that work; grading will be complete after trench is backfilled. A large area near the entrance access road has been cleared of topsoil in order to permanently stockpile excess subsoil and rock that was removed from trenches. The stockpile will be capped with topsoil soon. Trenches have very good separation of soil horizons. One spoil pile was found to contain both topsoil and subsoil. The materials were not mixed and will be separated when removed from this location. Crews are doing a good job of utilizing a limited number of designated access routes through the site. Mulching of the site to stabilize soils is being held up by pile remediation work at the top of the slope. No compliance items were noted. No significant compliance were noted. Corrective actions discussed onsite included: None. Hastings

8 Pine Island Date of Inspection Start/End Time 1:30 pm Piles, inverter and SCADA housing set, trenching, assembly. Mostly cloudy, temperature in the low to mid 50s. Additional personnel accompanying me on the site inspection included Paula Fitzgerald (Biosar), Jacob Thompson (Barr) and Ryan Molsee (Enel). The main part of the site is in reasonably good condition. Ruts have been back bladed and have dried out. The south side of the site is still inundated with significant ruts. Two drain tiles were damaged during the excavation of the MV trench through the middle of the site. Both tiles were repaired. The southernmost tile contained flowing water and the northern was dry. Both tiles were also flushed but each backed water within 30 seconds to three minutes, indicating that there is a blockage further down the system. The northern tile was blocked up-gradient from the trench as well. Drain tile damage or blockages are likely causing the inundation in the southern part of the site and the drainage system should be assessed by a qualified tile contractor prior to final restoration to ensure the system is working properly. Trash control on the site is adequate. We discussed work strategies with Rob (Biosar site manager) in preparation for the incoming weather event and wet working conditions that will likely result. Blockage of drain tile system. Pine Island

9 Corrective actions discussed onsite included: Drain tile system will need to be assessed by a qualified contractor prior to final restoration to determine the repairs or replacement necessary to ensure the system is functioning properly. Pine Island

10 Eastwood Date of Inspection Start/End Time 7:00 am Piles, deliveries, inverters, trenching, cabling, SCADA, assembly. Clear, temperature in the upper 20s to low 30s. Additional personnel accompanying me on the site inspection today included Paula Fitzgerald (Biosar), Ryan Molsee (Enel), and Mandy Bohnenblust (Barr). There is a significant amount of deep rutting through the western portion of the site resulting from material staging and assembly activities. Rutting is exacerbated by continually saturated sections of the work area that may be indicative of damaged drain tile. A drain tile contractor is scheduled to investigate the site for needed tile repairs next week. Topsoils in this area of the site are deep enough that deep ruts are not posing a concern for soil horizon mixing. Trash on this site is reasonably well controlled; some personal trash items were observed on the northern side of the parking area, but the green straps and plastic that can interfere with restoration equipment were largely contained. Spoils are well separated in the trenched areas. Broken drain tiles that were discovered or caused by trenching activities have been repaired. Workers are dewatering several open trenches into the northernmost trench on the east side of the project. Improper dewatering setups have been identified on this site previously. According to Joe (Biosar site manager), Blattner personnel have been informed repeatedly that the sediment bags that were on hand were not adequately filtering pumped water, and that dewatering activities were to stop until suitable filter bags were obtained. Blattner refused to stop pumping and instructed their crews to continue dewatering. This was confirmed by Blattner manager, Craig Arneson. A large felt-type bag that was not filtering properly was found last week on the southern edge of the site, behind and adjacent to the unstabilized subsoil stockpile. This setup was found to still be in place Eastwood

11 and had been used recently. Several other areas of subsoil sediment from dewatering were observed along the ends of trenches on the eastern edge of the site. Some areas where sediment had accumulated were rutted, causing loss of the subsoil sediment into the topsoil. A dewatering bag that contained a large amount of sediment had subsoil material covering its surface. It was assumed to have burst or otherwise failed according to Joe. In the northeast corner of the site, a 4-inch hose was found to have discharged beyond the perimeter fence and outside of any perimeter sediment control. Ruts were present outside of the perimeter fence, presumably from removing a sediment bag. According to Joe, it was believed that a filter bag was used in this area for a time but was not monitored, resulting in a burst filter bag and an unknown amount of unfiltered dewatering. A significant amount of inches-deep subsoil sediment was found in the area, extending approximately 100 feet west from the discharge point and 60 feet north beyond the perimeter fence. All sediment is believed to have remained on project-owned property. The issue was addressed with Blattner site personnel who were instructed to obtain sediment bags that sufficiently filtered pumped water, and to continually monitor the dewatering setup to ensure that discharged water was adequately treated. Potential drain tile issue in chronically wet portions of the western side of the site. Subsoils remaining on topsoil surface in some areas. Improper dewatering setups. Corrective actions discussed onsite included: Continue corrective items identified during last week s inspection. Remove excess subsoils when conditions are suitable. Drain tile contractor is coming to investigate potential drain tile damages next week; repairs are likely to be made next spring. Sediment from improper dewatering setups will need to be removed when site conditions allow. Obtain and implemented sediment bags that sufficiently treat pumped water. Ensure that pumped water is clear when discharging from the site. Continually monitor dewatering setups to ensure that water treatment is adequate and sediment bags are changed before they fail. Eastwood

12 Photos: Photo 1: Excess subsoils at risk of being incorporated into topsoil due to work in saturated conditions. Photo 2: Chronically saturated conditions on western side of site may be indicative of damaged draintile. Eastwood

13 Photos: Photo 3: Deep ruts and compaction will need to be addressed when site conditions allow or at time of restoration. Photo 4: Dewatering setup adjacent to unsecured subsoil stockpile. Eastwood

14 Photos: Photo 5: One of several areas of sediment observed to have resulted from improper dewatering setups. Photo 6: Dewatering setup discharging outside of perimeter fence, beyond any sediment control device. Eastwood

15 Photos: Photo 7: Sediment deposits from improper dewatering setup extended well beyond the perimeter fence. Eastwood

16 Lake Emily Date of Inspection Start/End Time 9:30 am Piles, inverters, SCADA excavations, trenching and cabling, assembly. Mostly clear, temperature in the lower 40s. Additional personnel accompanying me on the site inspection today included Mandy Bohnenblust (Barr), Paula Fitzgerald (Biosar), and Ryan Molsee (Enel). Site is dry and is in good condition. All trenches on the site have been excavated with good separation of soil horizons. Approximately 25-30% of the excavated trench had been backfilled at the time of our site visit. We discussed the planned work activities for the upcoming week and the expected wet site conditions with Mark Smiley (Biosar). Paula suggested staging modules in the arrays while conditions were still dry to the extent possible to minimize rutting. Also, workers were parking on the access road and driving into the laydown yard along the road shoulder. If this practice continues while conditions are wet, extensive rutting and mixing of road material with soils can be expected. There were a minimal number of small construction mats onsite at the time of inspection, but these will be removed from site and there are no plans to utilize mats at this location. Drain tile strikes have been repaired as they have been encountered during trenching activities. An unknown number of tiles have been impacted by piles, but at least some level of interference is expected. Tile strike investigation and repair will likely occur in the spring. No compliance items were noted at this time. Lake Emily

17 No compliance items were noted at this time. Corrective actions discussed onsite included: None. Lake Emily

18 West Waconia Date of Inspection Start/End Time 11:30 am Piles, inverters, setting SCADA house, cabling, trenching, assembly. Clear, temperature in the upper 50s to 60 degrees.. Additional personnel accompanying me on the site inspection today included Mandy Bohnenblust (Barr), Paula Fitzgerald (Biosar), and Ryan Molsee (Enel). Site condition has improved since last week due to drier conditions. Ruts have been mostly filled and smoothed. There is a high degree of compaction in some areas that will be addressed during restoration. There also continues to be some mixing of excavated material, and removal of subsoil spoil piles that were displaced by sand during backfilling will be necessary. The dewatering set up was being actively monitored when we arrived. The sediment bag was adequate and although a minor amount of scouring was noted at first, controls were being added and the pump velocity lowered to eliminate the issue. Discharge area had newly installed perimeter controls. All panels have been staged in the field, and access roads are matted which should help reduce the likelihood of significant site impacts due to working in wet conditions next week. There is a significant amount of trash, including the green packing straps and plastic wrapping that can become lodged in mud and cause issues with restoration equipment. Trash is becoming excessive in assembly areas. West Waconia

19 Corrective actions discussed onsite included: Consolidate trash and remove prior to wet and freezing conditions next week. West Waconia

20 Montrose Date of Inspection Start/End Time 2:30 pm Assembly complete, trenching and cabling for POI in progress, commissioning next week. Mostly clear, temperature near 60 degrees. Additional personnel accompanying me on the site inspections included Ryan Molsee (Enel), Paula Fitzgerald (Biosar), and Mandy Bohnenblust (Barr). The site was in good condition overall. Crane mats have been removed from portions of the access road and the laydown yard in preparation of site completion. Subsoils that have been documented in the prior two inspections have not yet been cleaned up from the topsoil surface. A small amount of trash remains onsite but cleanup efforts are good overall. A significant amount of standing water is still present in the southeast portion of the site and may result from a damaged drain tile. Standing water after an extended period of dry weather may indicate a damaged drain tile. Corrective actions discussed onsite included: Investigate potential for drain tile damage. Remove accumulated subsoils from soil surface that were identified in previous inspections. Montrose

21 Lake Pulaski Date of Inspection Start/End Time 3:45 pm Grading, piles, inverters, SCADA, assembly, material deliveries. Partly cloudy, temperature in the upper 50s. Additional personnel accompanying me on the site inspection today Ryan Molsee (Enel), Paula Fitzgerald (Biosar), and Mandy Bohnenblust (Barr). The site is in relatively good condition overall and Dane (Biosar site manager) has encountered no major issues. There are a couple of very deep ruts in the lowest area of the site where a lull sank into the saturated soils. Due to deep topsoil in this area no soil mixing was observed to have occurred. Areas of the site that were significantly impacted during the previous rain event will likely need to be remulched to provide soil stability through the winter. Trash is well controlled. We discussed the need to be proactive in planning work activities with the incoming weather expected to again create wet work conditions. No new or significant compliance issues were noted. No significant new issues were noted. Corrective actions discussed onsite included: None. Lake Pulaski

22 Albany Date of Inspection Start/End Time 7:00 am Piles, Trenching, Inverters, SCADA, Cables, Racking, Assembly, POI Trenching Mostly cloudy, 42 degrees. Additional personnel accompanying me on the site inspection today included Karl Everett (Biosar), Ryan Molsee (Enel) and Jacob Thompson (Barr). Site was in good condition. Crews have scheduled a cleanup day today to ensure trash is contained ahead of expected snow and freezing conditions. Trenching activities for the POI trench had good soil separation; the crew did a good job of reclaiming spoils off of the grassed areas when backfilling without damaging the ground surface. There was some mixing of access road material and fabric with soils in backfilled trench along the south side of the access road west of SCADA and adjacent PCU. Fabric will need to be removed from the trenched area and road material recovered to the extent possible. Some fabric and road material in backfilled trench along central access road west of SCADA house. Corrective actions discussed onsite included: Remove fabric from backfilled trench; assess the area during restoration to determine if additional topsoil is needed. Albany

23 Photos: Photo 1: Fabric and road material in backfilled trench west of SCADA house. Albany

24 Paynesville Date of Inspection Start/End Time 9:30 am Piles installed, trenching, cabling, inverters, SCADA work, assembly, deliveries. Overcast, temperature in the low 40s. Additional personnel accompanying me on the site inspection today included Karl Everett (Biosar), Jacob Thompson (Barr), and Ryan Molsee (Enel). Site is in the same condition as was reported last week. We discussed removing trash, smoothing ruts and staging materials to the extent possible in preparation for the incoming precipitation event and subsequent freeze with Mark (Biosar site manager). No new compliance items noted. No new compliance items noted. Corrective actions discussed onsite included: None Albany

25 Atwater Date of Inspection Start/End Time 11:45 am Piles, Inverters, Equipment Demob, Assembly. Cloudy, temperature in the upper 40s. Additional personnel accompanying me on the site inspection today included Jacob Thompson (Barr), Ryan Molsee (Enel), and Karl Everett (Biosar). Site is in good condition. The straw mulch that was observed during last week s inspection was found to be insufficiently secured. The underlying soils were too compacted for the disk to properly anchor the straw, and the mulch was observed being blown off of some areas and building up in others. Additional disking or other method to secure the mulch may be required. Straw mulch was insufficiently anchored. Corrective actions discussed onsite included: Effects of the incoming weather event will be observed and the area will be reassessed to determine the best action to take. Atwater

26 Photos: Photo 1: Water bubbling to the surface at location of newly installed telecommunications cable. Atwater

27 Annandale Date of Inspection Start/End Time 1:50 pm Piles, inverters, SCADA, assembly nearly complete, POI trenching. Mostly cloudy, temperature in the mid 50s. Additional personnel accompanying me on the site inspection today included Jacob Thompson (Barr), Karl Everett (Biosar), and Ryan Molsee (Enel). Site is in good condition overall. Crews were working on the POI trench at the time of the inspection. Trash is well controlled through most of the site. No new compliance items were noted, though potential for erosion related issues was discussed with Nate (Biosar site manager) in preparation for incoming precipitation event. No new compliance items were noted. Corrective actions discussed onsite included: Proactive steps to reduce likelihood of serious precipitation-related compliance items. Annandale

Piles, inverters, trenching, cabling, assembly.

Piles, inverters, trenching, cabling, assembly. Agricultural Inspection Report General Information Project Name Montrose Date of Inspection 11/9/2016 Start/End Time 7:00 am Inspector s Name(s) Inspector s Title(s) Describe present phase of construction

More information

Piles, Trenching, Inverters, Cables, Material Deliveries

Piles, Trenching, Inverters, Cables, Material Deliveries Agricultural Inspection Report General Information Project Name Albany Date of Inspection 20161012 Start/End Time 7:50 am Inspector s Name(s) Inspector s Title(s) Describe present phase of construction

More information

Methods, approaches, and procedures to minimize active agricultural land impacts during pipeline construction, surface restoration, and pipeline

Methods, approaches, and procedures to minimize active agricultural land impacts during pipeline construction, surface restoration, and pipeline Agricultural Impact Minimization Plan Methods, approaches, and procedures to minimize active agricultural land impacts during pipeline construction, surface restoration, and pipeline operation. PennEast

More information

MARBLE RIVER WIND POWER PROJECT Agricultural Protection Measures

MARBLE RIVER WIND POWER PROJECT Agricultural Protection Measures MARBLE RIVER WIND POWER PROJECT Siting Considerations 1. Locate access roads and, to the extent allowed by local laws, wetlands and topography, individual wind turbines and other structures along field

More information

Methods, approaches, and procedures to minimize active agricultural land impacts during pipeline construction, surface restoration, and pipeline

Methods, approaches, and procedures to minimize active agricultural land impacts during pipeline construction, surface restoration, and pipeline Agricultural Impact Minimization Plan Methods, approaches, and procedures to minimize active agricultural land impacts during pipeline construction, surface restoration, and pipeline operation. PennEast

More information

Wisconsin Contractors Institute Continuing Education

Wisconsin Contractors Institute Continuing Education Wisconsin Contractors Institute Continuing Education Erosion & Sediment Control Course # 12775 2 hours Wisconsin Contractors Institute N27 W23953 Paul Road, Suite 203 Pewaukee, WI 53072 Website: www.wicontractorsinstitute.com

More information

Information for File # JTF

Information for File # JTF Information for File # 2013-04665-JTF Applicant Corps Contact Enbridge Energy, Limited Partnership Josh Fitzpatrick Address 1554 Highway 2, Suite 2, Two Harbors, MN 55616 E-Mail joshua.t.fitzpatrick@usace.army.mil

More information

UPLAND EROSION CONTROL, REVEGETATION, AND MAINTENANCE PLAN

UPLAND EROSION CONTROL, REVEGETATION, AND MAINTENANCE PLAN UPLAND EROSION CONTROL, REVEGETATION, AND MAINTENANCE PLAN 01/17/2003 VERSION UPLAND EROSION CONTROL, REVEGETATION, AND MAINTENANCE PLAN TABLE OF CONTENTS I. APPLICABILITY... 1 II. SUPERVISION AND INSPECTION...

More information

Plan of Development Mountain Valley Pipeline Project. APPENDIX M Winter Construction Plan

Plan of Development Mountain Valley Pipeline Project. APPENDIX M Winter Construction Plan APPENDIX M October 20, 2017 Appendix M Prepared by: October 20, 2017 TABLE OF CONTENTS 1.0 INTRODUCTION... M-1 2.0 STABILIZATION/WINTERIZATION... M-2 3.0 EROSION AND SEDIMENT CONTROL MEASURES... M-3 4.0

More information

SECTION PLANTING PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SECTION PLANTING PART 1 - GENERAL 1.1 RELATED DOCUMENTS SECTION 329000 PLANTING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Special Conditions and Division 01 Specification Sections, apply

More information

Erosion Control for Home Builders in the. City of Jacksonville

Erosion Control for Home Builders in the. City of Jacksonville Erosion Control for Home Builders in the City of Jacksonville Eroding construction sites are a leading cause of water quality problems in Jacksonville. For every acre under construction, about a dump truck

More information

Shelbyville, KY Stormwater Best Management Practices. Section 2 EROSION PREVENTION AND SEDIMENT CONTROL PLAN

Shelbyville, KY Stormwater Best Management Practices. Section 2 EROSION PREVENTION AND SEDIMENT CONTROL PLAN Section 2 EROSION PREVENTION AND SEDIMENT CONTROL PLAN 2.1 Requirements The City of Shelbyville, KY will require an Erosion Prevention and Sediment Control (EPSC) Plan for most types of development construction.

More information

A. Install all temporary erosion control measures (in accordance with MNDOT General Conditions 2573) prior to site disturbance.

A. Install all temporary erosion control measures (in accordance with MNDOT General Conditions 2573) prior to site disturbance. The language provided in these specifications is meant to serve as a reminder and provide a generic example of the type of language that should be provided in final construction documents. This language

More information

SECTION 6. Routine Maintenance Activity Details

SECTION 6. Routine Maintenance Activity Details SECTION 6 Routine Maintenance Activity Details 80. DEBRIS REMOVAL When Deadfall, and other objects, such as shopping carts, tires, appliances, and mattresses have accumulated in the drain. Why To prevent

More information

A. Contractor shall provide product data for each type of product indicated.

A. Contractor shall provide product data for each type of product indicated. 31 13 00 SELECTIVE TREE AND SHRUB REMOVAL AND TRIMMING SECTION 1 GENERAL 1.1 SUMMARY A. This section includes general protection and pruning of existing trees and plants that are affected by execution

More information

5/15/2013. Basin Area. Vegetation. Rainfall & Runoff. Soil Type. Topics. Factors Influencing Erosion. Factors Influencing Erosion

5/15/2013. Basin Area. Vegetation. Rainfall & Runoff. Soil Type. Topics. Factors Influencing Erosion. Factors Influencing Erosion Topics Erosion, TESC and Construction sequencing Procedures and timing Remedies for failing sites Curtis Hinman WSU Extension and Bio Systems Eng. Faculty Low Impact Development Specialist chinman@wsu.edu

More information

SILT FENCE MACHINE SLICED ERO-1A STEEL FENCE POST (T-POST), MINIMUM 5' LONG, 6' MAXIMUM SPACING.

SILT FENCE MACHINE SLICED ERO-1A STEEL FENCE POST (T-POST), MINIMUM 5' LONG, 6' MAXIMUM SPACING. STEEL FENCE POST (T-POST), MINIMUM 5' LONG, 6' MAXIMUM SPACING. ATTACH FABRIC TO POSTS WITH MINIMUM 3 ZIP TIES (50 LB. TENSILE) PER POST IN TOP 8" OF FABRIC. MONOFILAMENT GEOTEXTILE FABRIC PER MNDOT TABLE

More information

FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT

FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT FIELD INSPECTION REPORT Date September 19, 2018 Project Northern Natural Gas Company (Northern) Cedar Station Upgrade Project Dakota County, Minnesota Authority: Section 7(c) Personnel FERC Staff: Company

More information

3" TO 4" OF TOPSOIL 2:1 MIRAFI HP 565 GEO FABRIC OR EQUIVALENT 9' SPILLWAY EL=7147 2:1 SPILLWAY SECTION N.T.S. TOP OF POND EL=7149' RIP-RAP D 50 8" WRAPPED IN FILTER FABRIC 45 MIL HDPE POND LINER OR EQUIVALENT

More information

Soil Reclamation and Site Reinstatement

Soil Reclamation and Site Reinstatement APPENDIX 6 Soil Reclamation and Site Reinstatement Purpose To undertake soil reclamation, erosion protection, Site restoration and reinstatement, taking into account natural processes, operational requirements

More information

2018 Annual Landfill Inspection Report

2018 Annual Landfill Inspection Report 2018 Annual Landfill Inspection Report Landfill H.W. Pirkey Plant Southwestern Electric Power Company Hallsville, Texas December 17, 2018 Prepared for: Southwestern Electric Power Company H.W. Pirkey Plant

More information

Town of Essex Small Site Erosion Control Guide

Town of Essex Small Site Erosion Control Guide Town of Essex Small Site Erosion Control Guide Why do we need to protect against erosion? Water Quality: Erosion and the transport of sediment and pollutants impacts the water quality of nearby streams

More information

A. Install all temporary erosion control measures (in accordance with MNDOT General Conditions 2573) prior to site disturbance.

A. Install all temporary erosion control measures (in accordance with MNDOT General Conditions 2573) prior to site disturbance. The language provided in these specifications is meant to serve as a reminder and provide a generic example of the type of language that should be provided in final construction documents. This language

More information

RAIN GARDEN ILLINOIS URBAN MANUAL PRACTICE STANDARD. (feet) CODE 897 DEFINITION

RAIN GARDEN ILLINOIS URBAN MANUAL PRACTICE STANDARD. (feet) CODE 897 DEFINITION ILLINOIS URBAN MANUAL PRACTICE STANDARD RAIN GARDEN (feet) CODE 897 Source: Kendall County Soil and Water Conservation District DEFINITION Rain gardens are small, shallow, flat bottomed depressions constructed

More information

TECH. BULLETIN ISSUE TWENTY

TECH. BULLETIN ISSUE TWENTY 1.0 Scope The scope of this Guideline is to: Define construction techniques associated with cold weather installation of the backfill zone; and, Identify measures that have been used successfully to allow

More information

SUPPORTING DOCUMENT STORMWATER POLLUTION PREVENTION PLAN (SWPPP) NARRATIVE

SUPPORTING DOCUMENT STORMWATER POLLUTION PREVENTION PLAN (SWPPP) NARRATIVE SUPPORTING DOCUMENT STORMWATER POLLUTION PREVENTION PLAN (SWPPP) NARRATIVE Please complete this narrative form and submit with your SWPPP drawings. Refer to Kitsap County Stormwater Design Manual Vol.

More information

Urban Conservation Practice Physical Effects ESTABLISHMENT, GROWTH, AND HARVEST NUTRIENT MANAGEMENT

Urban Conservation Practice Physical Effects ESTABLISHMENT, GROWTH, AND HARVEST NUTRIENT MANAGEMENT NOT WELL 800 - Urban Stormwater Wetlands A constructed system of shallow pools that create growing conditions for wetland plants to lessen the impacts of stormwater quality and quantity in urban areas.

More information

DIVISION 40 PUMP STATION SITE WORK AND LANDSCAPING

DIVISION 40 PUMP STATION SITE WORK AND LANDSCAPING DIVISION 40 PUMP STATION SITE WORK AND LANDSCAPING 40.01 SCOPE: The contractor shall furnish all labor, materials, equipment, and supplies; and shall perform all work necessary for the installation of

More information

Department of Agriculture. Conservation Service. United States. Natural Resources REVISED 8/26/16

Department of Agriculture. Conservation Service. United States. Natural Resources REVISED 8/26/16 GENERAL NOTES: SYMBOL LEGEND 1. All work shall comply with the constriction specifications, drawings, project-specific quality assurance plan and other contract requirements. 2. All notes on the drawings

More information

December 13, 2005 Meeting Status of NPDES Post Fire BMPs

December 13, 2005 Meeting Status of NPDES Post Fire BMPs December 13, 2005 Meeting Status of NPDES Post Fire BMPs Agenda Overview of Current Operations At SSFL Impacts of Fire At SSFL Rebuilding & Improvement of BMPs Future Activities Site Tour Close-out 1 Santa

More information

Low Flow Rates Low Filtration Sandy Soils Medium Flow Rates Medium Filtration Clayey Soils [1] High Flow Rates High Filtration Polluted Soils

Low Flow Rates Low Filtration Sandy Soils Medium Flow Rates Medium Filtration Clayey Soils [1] High Flow Rates High Filtration Polluted Soils Filter Ponds DE-WATERING SEDIMENT CONTROL TECHNIQUE Low Flow Rates Low Filtration Sandy Soils Medium Flow Rates Medium Filtration Clayey Soils [1] High Flow Rates High Filtration Polluted Soils [1] Capture

More information

EROSION & SEDIMENT CONTROL

EROSION & SEDIMENT CONTROL EROSION & SEDIMENT CONTROL Surface Water Protection During Well Site Construction Kelly Kees, PE WVDEP, Office of Oil and Gas SEDIMENT & EROSION CONTROL PLANS Per West Virginia State Code 22-6-6(d) 22-6A-7(c),

More information

SOP 6: Erosion and Sedimentation Control SOP 6: EROSION AND SEDIMENTATION CONTROL

SOP 6: Erosion and Sedimentation Control SOP 6: EROSION AND SEDIMENTATION CONTROL Standard Operating Procedures Central Massachusetts Regional Stormwater Coalition SOP 6: Erosion and Sedimentation Control SOP 6: EROSION AND SEDIMENTATION CONTROL Erosion and sedimentation from land-disturbing

More information

Preventing Storm Water Pollution: What We Can Do

Preventing Storm Water Pollution: What We Can Do Preventing Storm Water Pollution: What We Can Do ~Employee Training Series~ Land Disturbances PREPARED IN COOPERATION WITH THE Texas Commission on Environmental Quality AND U.S. ENVIRONMENTAL PROTECTION

More information

SOIL EROSION AND SEDIMENT CONTROL

SOIL EROSION AND SEDIMENT CONTROL SOIL EROSION AND SEDIMENT CONTROL SECTION 1: AUTHORITY, TITLE AND PURPOSE 11. STATUTORY AUTHORIZATION This ordinance is adopted pursuant to the provisions of the Federal Water Pollution Control Act 86

More information

City of Stoughton Erosion Control Permit Application (effective 2/6/2018)

City of Stoughton Erosion Control Permit Application (effective 2/6/2018) City of Stoughton Erosion Control Permit Application (effective 2/6/2018) Incomplete applications will not be accepted Project Name: Address of subject property: Landowner Name(s): Applicant Name: Landowner

More information

Site Formation Excavation - 6' depth square yard $8.00 $0.00 Grading square yard $1.50 $0.00 Hauling off-site - 6' depth square yard $10.00 $0.

Site Formation Excavation - 6' depth square yard $8.00 $0.00 Grading square yard $1.50 $0.00 Hauling off-site - 6' depth square yard $10.00 $0. SURFACE SAND FILTER COST ESTIMATE WORKSHEET 2005 Prices Project Title Owner Location Project Number Date Description Units Quantity Unit Cost Total Estimated Price Site Preparation Tree removal - up to

More information

Caribbean Area PO Box San Juan, PR Page Topics

Caribbean Area PO Box San Juan, PR Page Topics Caribbean Area PO Box 364868 San Juan, PR 00936-4868 IBM Plaza 654 Muñoz Rivera Ave. Suite 604 Hato Rey, PR 00918-4123 Page Topics Guide to Erosion and Sediment Control in Urban Areas Erosion and Sedimentation

More information

2016 Annual Inspection Report

2016 Annual Inspection Report 2016 Annual Inspection Report for Compliance with the Coal Combustion Residuals Rule (40 CFR Part 257) Hayden Station 13125 U.S. Highway 40 Hayden, Colorado 81638 January 18, 2017 Table of Contents Certification...

More information

FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT

FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT Date June 20, 2018 Project Northern Natural Gas Company Northern Lights 2017 Expansion Project Rice, Sherburne, and Isanti Counties, Minnesota

More information

2012 FINAL SOILS AREA 2 Envirothon Questions Answer KEY

2012 FINAL SOILS AREA 2 Envirothon Questions Answer KEY 2012 FINAL SOILS AREA 2 Envirothon Questions Answer KEY Questions 1-6 to be answered at the soil pit: 1. Soil scientists categorize soils by drainage classes. What is the drainage class of the soil at

More information

WQ-07 INFILTRATION TRENCH

WQ-07 INFILTRATION TRENCH Greenville County Technical Specification for: WQ-07 INFILTRATION TRENCH 1.0 Infiltration Trench 1.1 Description Infiltration Trenches are excavations filled with stone to create an underground reservoir

More information

Illinois Urban Manual

Illinois Urban Manual Illinois Urban Manual Jim Nelson: Association of Illinois Soil and Water Conservation Districts (AISWCD) Funding for this project provided, in part, by the Grand Victoria Foundation of Elgin IL, the Governor

More information

Project: Developer/Designer: Reviewer: I. Narrative: 1. Project Description: Describes the nature and purpose of the land disturbing activity.

Project: Developer/Designer: Reviewer: I. Narrative: 1. Project Description: Describes the nature and purpose of the land disturbing activity. City of Charlottesville, Virginia Erosion and Sediment Control Plan Review Checklist 610 East Market Street, Charlottesville, VA 22902 Telephone 434-970-3182; Fax 434-970-3359 Project: Developer/Designer:

More information

PLAN SUBMITTER'S CHECKLIST

PLAN SUBMITTER'S CHECKLIST Page 1 of 8 PLAN SUBMITTER'S CHECKLIST FOR EROSION AND SEDIMENT CONTROL PLANS Please fill in all blanks and reference the plan sheets/pages where the information may be found, where appropriate, or write

More information

Revetting and Supporting River Banks 4.7 Bank revetment using low steel sheet piling and coir rolls

Revetting and Supporting River Banks 4.7 Bank revetment using low steel sheet piling and coir rolls .7 Bank revetment using low steel sheet piling and coir rolls River Thames Location - Clifton Lock Cut, Oxfordshire SU 59 Date of construction - September 1996 Length 10m Cost 5,000 Figure.7.1 Section

More information

Breakthrough Innovations

Breakthrough Innovations Breakthrough Innovations Project Title: Bioengineering for Stabilization of Critical Slopes Project Team: Lori Belz Principle Investigator John Benson Steve Kortuem Leo Holm Introduction: One of the problems

More information

Structural Storm Water Best Management Practices (BMPs)

Structural Storm Water Best Management Practices (BMPs) Structural Storm Water Best Management Practices (BMPs) Storm Water Permitting: The SWPPP Revealed By Deron Austin, PE January 11, 2006 3:30-5:00 PM Orlando, Florida Presentation Outline Preface About

More information

THE FOLLOWING IS AN EXCERPT FROM THE 2011 CITY OF SEATTLE STANDARD SPECIFICATIONS WITH MINOR CORRECTIONS MADE TO SECTION 9-03.SEATTLE.

THE FOLLOWING IS AN EXCERPT FROM THE 2011 CITY OF SEATTLE STANDARD SPECIFICATIONS WITH MINOR CORRECTIONS MADE TO SECTION 9-03.SEATTLE. THE FOLLOWING IS AN EXCERPT FROM THE 2011 CITY OF SEATTLE STANDARD SPECIFICATIONS WITH MINOR CORRECTIONS MADE TO SECTION 9-03.2 THE COMPLETE 2011 EDITION MAY BE FOUND AT: HTTP://WWW.SEATTLE.GOV/UTIL/ENGINEERING/STANDARD_PLANS_&_SPECS/INDEX.ASP

More information

SITE TOPSOIL & FINISH GRADING

SITE TOPSOIL & FINISH GRADING CITY OF BRAMPTON LANDSCAPE SPECIFICATIONS SECTION 02911-1 PART 1 GENERAL 1.1 Related Work.1 Section 02311 Site Grading.2 Section 02315 Excavating, Trenching, & Backfilling.3 Section 02906 Planting of Trees,

More information

POST CONSTRUCTION STORMWATER MANAGEMENT FOR "WHITE OAK SEWER INTERCEPTOR"

POST CONSTRUCTION STORMWATER MANAGEMENT FOR WHITE OAK SEWER INTERCEPTOR POST CONSTRUCTION STORMWATER MANAGEMENT PLAN FOR "WHITE OAK SEWER INTERCEPTOR" Located in Newberry Township, York County March 21, 2008 Prepared by: Mellott Engineering, Inc. 7500 Devonshire Heights Road

More information

REQUIREMENTS FOR LANDS TO BE CONVEYED TO THE CITY. The Owner will be responsible to ensure that all lands which will be transferred to the City for

REQUIREMENTS FOR LANDS TO BE CONVEYED TO THE CITY. The Owner will be responsible to ensure that all lands which will be transferred to the City for APPROVED BY COUNCIL FEBRUARY 15, 1994 CITY OF BE CONVEYED TO THE CITY The Owner will be responsible to ensure that all lands which will be transferred to the City for parkland, drainage or boulevard purposes

More information

PROTECTIVE MEASURES FOR TREES DURING CONSTRUCTION

PROTECTIVE MEASURES FOR TREES DURING CONSTRUCTION PROTECTIVE MEASURES FOR TREES DURING CONSTRUCTION NO CONSTRUCTION OR EXCAVATION IS TO OCCUR ON LOTS THAT REQUIRE TREE PRESERVATION UNTIL PROPER APPROVALS HAVE BEEN GIVEN BY A CITY ARBORIST 1. When trees

More information

Town of Fuquay-Varina

Town of Fuquay-Varina 170 LANDSCAPING 170.01 GENERAL 170.01.01 Street trees shall be provided in accordance with the Land Development Ordinance for site plans and subdivisions 170.01.02 Street trees, landscape areas, landscape

More information

Eric Konzelmann, CPESC, CPSWQ Assistant District Manager. Montgomery County Conservation District

Eric Konzelmann, CPESC, CPSWQ Assistant District Manager. Montgomery County Conservation District Eric Konzelmann, CPESC, CPSWQ Assistant District Manager Montgomery County Conservation District Topics Covered E&S Conveyance & Inlet Protection Soil Stabilization Requirements & Effectiveness Soil Compaction

More information

2.1.4 Roof Downspout Rain Gardens

2.1.4 Roof Downspout Rain Gardens 2008 SWMM, 2010 Revision City of Tacoma 2.1.4 Roof Downspout Rain Gardens Purpose and Definition Bioretention areas are shallow stormwater retention facilities designed to mimic forested systems by controlling

More information

Landscape Restoration Specifications

Landscape Restoration Specifications Landscape Restoration Specifications Table of Contents Parks and Parkways Landscape 1.01 Irrigation Mainline Altering...2 2.01 Head Placement...2 3.01 Electronic Valve Replacement or Repair...3 4.01 Quick

More information

Living Snow Fence Training in Beerston, New York, Region 9: Wednesday May 25, 2011 and Thursday May 26, 2011

Living Snow Fence Training in Beerston, New York, Region 9: Wednesday May 25, 2011 and Thursday May 26, 2011 Living Snow Fence Training in Beerston, New York, Region 9: Wednesday May 25, 2011 and Thursday May 26, 2011 On May 25 th and 26 th, Tim Volk, a researcher from the State University of New York s College

More information

CHAPTER 102 REQUIREMENTS CRITCAL STAGES DURING CONSTRUCTION ACTIVITIES

CHAPTER 102 REQUIREMENTS CRITCAL STAGES DURING CONSTRUCTION ACTIVITIES CHAPTER 102 REQUIREMENTS CRITCAL STAGES DURING CONSTRUCTION ACTIVITIES TOPICS Steps Prior to construction Pre-Construction Meeting Defining the Critical Stages with the Contractor Brady s Run Lake Site

More information

Information for File # ARC

Information for File # ARC Information for File # 2015-02781-ARC Applicant Corps Contact Enbridge Energy, Limited Partnership Andrew R Chambers Address 600 South Lake Avenue, Suite 211, Duluth, MN 55802 E-Mail Andrew.R.Chambers@usace.army.mil

More information

SECTION 900 TURF ESTABLISHMENT

SECTION 900 TURF ESTABLISHMENT SECTION 900 901.0 DESCRIPTION This section covers the furnishing of all labor, materials, tools, equipment and performances of all work and services necessary or incidental to turf restoration as indicated

More information

Ohio Pipeline Standard and Construction Specifications

Ohio Pipeline Standard and Construction Specifications Ohio Pipeline Standard and Construction Specifications December 28, 2015 PURPOSE This document provides measures intended to limit the impact of construction of a pipeline on agricultural productivity

More information

Low Gradient Velocity Control Short Term Steep Gradient [1] Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent

Low Gradient Velocity Control Short Term Steep Gradient [1] Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent Grass Linings DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient [1] Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] May be used on short, steep

More information

Alternative Names: Erosion Control Matting, Erosion Control Netting, Rolled Erosion Control Products (RECP)

Alternative Names: Erosion Control Matting, Erosion Control Netting, Rolled Erosion Control Products (RECP) 4.5-s EROSION CONTROL BLANKET SYSTEM Alternative Names: Erosion Control Matting, Erosion Control Netting, Rolled Erosion Control Products (RECP) DESCRIPTION Erosion control blanket systems are woven or

More information

Tips for Maintaining and Enhancing Stormwater Management Areas

Tips for Maintaining and Enhancing Stormwater Management Areas 4 4 N. Second Street, Denton, Md. 21629 (410) 479-3625 (410) 479-3534 fax www.dentonmaryland.com Tips for Maintaining and Enhancing Stormwater Management Areas Information provided by the Town of Denton

More information

A. INTRODUCTION AND SUMMARY OF FINDINGS B. EXISTING CONDITIONS. Table 10-1 Adjacent Storm Drains

A. INTRODUCTION AND SUMMARY OF FINDINGS B. EXISTING CONDITIONS. Table 10-1 Adjacent Storm Drains Chapter 10: Stormwater Management A. INTRODUCTION AND SUMMARY OF FINDINGS This chapter describes existing and proposed stormwater management on the Site. Potential impacts to stormwater infrastructure

More information

IMPROVED STORMWATER MANAGEMENT BMPS AND FLOOD PREPAREDNESS FOR 2016 EL NIÑO STORMS

IMPROVED STORMWATER MANAGEMENT BMPS AND FLOOD PREPAREDNESS FOR 2016 EL NIÑO STORMS IMPROVED STORMWATER MANAGEMENT BMPS AND FLOOD PREPAREDNESS FOR 2016 EL NIÑO STORMS Denise Yaffe, Southern California Edison, Rosemead, CA Julia Lakes, Southern California Edison, Rosemead, CA Chijioke

More information

4.6. Low Impact and Retentive Grading

4.6. Low Impact and Retentive Grading 4.6. Low Impact and Retentive Grading Low Impact Grading techniques focus on utilizing existing topography during Site layout to minimize cost. Proposing structures, roads, and other impervious surfaces

More information

6.1 Bioretention Areas

6.1 Bioretention Areas SAN MATEO COUNTYWIDE WATER POLLUTION PREVENTION PROGRAM 6.1 Bioretention Areas Figure 6-1. Bioretention Area. Source: City of Brisbane Bioretention areas 1, or rain gardens, are concave landscaped areas

More information

INSTALLATION GUIDELINES FOR GEOTEXTILES USED IN FILTRATION AND DRAINAGE APPLICATIONS

INSTALLATION GUIDELINES FOR GEOTEXTILES USED IN FILTRATION AND DRAINAGE APPLICATIONS INSTALLATION GUIDELINES FOR GEOTEXTILES USED IN FILTRATION AND DRAINAGE APPLICATIONS Prepared by TenCate Geosynthetics North America 365 South Holland Drive Pendergrass, GA 30567 Tel: (706) 693-2226 Fax:

More information

Part IV(a): BMPs for Erosion, Sediment, Velocity Control

Part IV(a): BMPs for Erosion, Sediment, Velocity Control Part IV(a): BMPs for Erosion, Sediment, Velocity Control Find Design Standards and Specifications for Iowa Erosion and Sediment Control Practices at: www.iowasudas.org Erosion Control Keeping the soil

More information

ARROW BOWEN PIPELINE ENVIRONMENTAL MANAGEMENT PLAN OUTLINE SOIL MANAGEMENT PLAN

ARROW BOWEN PIPELINE ENVIRONMENTAL MANAGEMENT PLAN OUTLINE SOIL MANAGEMENT PLAN APPENDIX J ARROW BOWEN PIPELINE ENVIRONMENTAL MANAGEMENT PLAN OUTLINE SOIL MANAGEMENT PLAN Contents 1 Introduction... 1 1.1 Purpose of the Soil Management Plan... 1 1.2 Project description... 1 1.3 Legislation

More information

LABOR-BASED ROUTINE ROAD MAINTENANCE (LBRRM)

LABOR-BASED ROUTINE ROAD MAINTENANCE (LBRRM) LABOR-BASED ROUTINE ROAD MAINTENANCE (LBRRM) A GUIDE TO THE PRACTICAL TASKS 1 Important Drainage Components Camber 2 THE IMPORTANCE OF DRAINAGE Keep water off the running surface and clear of the road

More information

ENVIRONMENTAL ENGINEERING LAND SURVEYING

ENVIRONMENTAL ENGINEERING LAND SURVEYING ENVIRONMENTAL ENGINEERING LAND SURVEYING Closure Plan Scrubber Solids Pond No. 3 Sherburne County Generating Plant Introduction This plan describes the closure requirements for Scrubber Solids Pond No.

More information

APPENDIX G-3 Agricultural Impact Mitigation Plan Ohio

APPENDIX G-3 Agricultural Impact Mitigation Plan Ohio APPENDIX G-3 Agricultural Impact Mitigation Plan Ohio G3-1 Appendix G-3 Appendix G-3 G3-2 ROVER PIPELINE LLC Rover Pipeline Project AGRICULTURAL IMPACT MITIGATION PLAN OHIO April 2015 G3-3 Appendix G-3

More information

Section Seeding

Section Seeding Section 02936 Seeding PART 1 - GENERAL 1.01 SECTION INCLUDES A. Fertilizing. B. Seeding. C. Hydroseeding. D. Mulching. E. Maintenance. F. Sodding. 1.02 RELATED WORK A. Documents affecting work of this

More information

Grand River Ravines Georgetown Township

Grand River Ravines Georgetown Township Grand River Ravines Georgetown Township Project Description: The Grand River Ravines County Park property is composed of the 68-acre former Fillmore at the Bend Open Space purchased in 1999 and two more

More information

The Low Risk Site Handbook

The Low Risk Site Handbook The Low Risk Site Handbook for Erosion Prevention and Sediment Control The content of this Handbook is adapted from the New York State Standards and Specifications for Erosion and Sediment Control-August

More information

STREAM ALTERATION PRACTICES

STREAM ALTERATION PRACTICES STREAM ALTERATION PRACTICES Stream Diversion Channel SDC DEFINITION A temporary channel constructed to convey stream flow around in-stream construction. PURPOSE Stream diversion channels are used to allow

More information

Bioretention. Matt Scharver Northeast Ohio Regional Sewer District. #ProjectCleanLake

Bioretention. Matt Scharver Northeast Ohio Regional Sewer District. #ProjectCleanLake Bioretention Matt Scharver Northeast Ohio Regional Sewer District Stormwater Management Training for MS4 Municipal Employees Training Session Agenda Pre-Training Survey Presentation & Site Visit Post-Training

More information

RECOMMENDED BEST MANAGEMENT PRACTICES FOR RESTORATION OF WETLANDS AFTER TEMPORARY IMPACTS

RECOMMENDED BEST MANAGEMENT PRACTICES FOR RESTORATION OF WETLANDS AFTER TEMPORARY IMPACTS RECOMMENDED BEST MANAGEMENT PRACTICES FOR RESTORATION OF WETLANDS AFTER TEMPORARY IMPACTS Prepared in partial fulfillment of a U.S. Environmental Protection Agency State Wetland Program Development Grant

More information

M-231 and Water Quality. Ottawa County Water Quality Forum November 21, 2016 James Fortney, MDOT

M-231 and Water Quality. Ottawa County Water Quality Forum November 21, 2016 James Fortney, MDOT M-231 and Water Quality Ottawa County Water Quality Forum November 21, 2016 James Fortney, MDOT M-231 Facts: 7-Miles long 2-Lane Limited Access Highway Connects I-96 and M-45 M-231 Facts: Includes Michigan

More information

Guidelines to Minimize Phytophthora Contamination in Restoration Projects

Guidelines to Minimize Phytophthora Contamination in Restoration Projects Guidelines to Minimize Phytophthora Contamination in Restoration Projects These guidelines aim to avoid contamination of restoration sites with exotic pathogenic Phytophthora species or other plant pathogens

More information

Tree Pits Construction Guide

Tree Pits Construction Guide Tree Pits Construction Guide What are tree pits? Tree pits collect stormwater runoff from small carpark areas or roads. Runoff filters through the tree roots and surrounding soil mix, trapping sediment

More information

REFERENCE DRAWINGS FOR 332 W. MAIN STREET ROCK HILL, SOUTH CAROLINA

REFERENCE DRAWINGS FOR 332 W. MAIN STREET ROCK HILL, SOUTH CAROLINA REFERENCE DRAWINGS FOR REET ROCK HILL, SOUTH CAROLINA COVER SHEET 1 OF 6 GENERAL NOTES 2 OF 6 REMOVE WIRE AND NYLON TWINE FROM BALL AND CANOPY. SOAK ROOT BALL AND PLANT PIT IMMEDIATELY AFTER INSTALLATION.

More information

EROSION & SEDIMENT CONTROL

EROSION & SEDIMENT CONTROL EROSION & SEDIMENT CONTROL 1 EROSION & SEDIMENT CONTROL Effective Soil & Water Protection Whether you want to prevent soil erosion caused by rain, water and wind, or protect waterways from inevitable build

More information

Construction Management & Engineering Division. Understanding Swales

Construction Management & Engineering Division. Understanding Swales Construction Management & Engineering Division Understanding Swales The Florida hydrological cycle it all starts and ends here. Rainfall becomes stormwater when it can no longer soak into the ground and

More information

Placido Bayou Community Association Waterway Inspection Report 8/13/14 Management Summary To the Pond and Lake Committee of Placido Bayou, We sincerely applaud your efforts thus far to improve the water

More information

Gryme s Dyke, Stanway Green

Gryme s Dyke, Stanway Green Gryme s Dyke, Stanway Green A short assessment of the archaeological impact of contractor s groundworks at the southern end of the Gryme s Dyke Middle earthwork February 2000 Archive report on behalf of

More information

Adaptive Management of Erosion and Sediment Control Best Management Practices (BMPs) Presenter: Denis Rushton, P. Eng. Date: May 18, 2016

Adaptive Management of Erosion and Sediment Control Best Management Practices (BMPs) Presenter: Denis Rushton, P. Eng. Date: May 18, 2016 Adaptive Management of Erosion and Sediment Control Best Management Practices (BMPs) Presenter: Denis Rushton, P. Eng. Date: May 18, 2016 Adaptive Management (AM) The definition of AM for the purpose of

More information

NOTICE OF INTENT. Submitted To: Bremo Power Station 1038 Bremo Bluff Road Bremo Bluff, VA 23022

NOTICE OF INTENT. Submitted To: Bremo Power Station 1038 Bremo Bluff Road Bremo Bluff, VA 23022 NOTICE OF INTENT TO CLOSE INACTIVE CCR SURFACE IMPOUNDMENTS NOTICE OF INTENT Bremo Power Station Submitted To: Bremo Power Station 1038 Bremo Bluff Road Bremo Bluff, VA 23022 Submitted By: Golder Associates

More information

Butte Creek Canyon. The New Road Built in April of 2015 by Signalized Intersection West, LLC. Presentation slides from December 2015 through June 2016

Butte Creek Canyon. The New Road Built in April of 2015 by Signalized Intersection West, LLC. Presentation slides from December 2015 through June 2016 Butte Creek Canyon The New Road Built in April of 2015 by Signalized Intersection West, LLC Presentation slides from December 2015 through June 2016 1 Dry Creek Bed: Because there is no culvert, rainwater

More information

Case Study Bioretention Installation and Maintenance

Case Study Bioretention Installation and Maintenance Case Study Bioretention Installation and Maintenance Bioretention Crime Scene Investigation A reality TV series where you get to watch disturbing bioretention crimes and use advanced forensics to solve

More information

All materials in this presentation are taken from materials produced by:

All materials in this presentation are taken from materials produced by: 1 PART I 2 All materials in this presentation are taken from materials produced by: Georgia Soil and Water Conservation Commission 4310 Lexington Road P.O. Box 8024 Athens, GA 30603 706-542-3065 Fax 706-542-4242

More information

Bioengineered designs

Bioengineered designs Bioengineered designs In bioengineered designs, plants are essential for the long-term integrity of the water s edge. Certain hard elements may be included, such as driven wooden piles, but their functions

More information

Mosquito Control Guidelines

Mosquito Control Guidelines Appendix F Mosquito Control Guidelines This appendix presents guidance from the Countywide Program s Vector Control Plan for designing and maintaining stormwater treatment measures to control mosquitoes.

More information

CHAPTER 4. SPECIAL CONDITION EROSION CONTROL MEASURES

CHAPTER 4. SPECIAL CONDITION EROSION CONTROL MEASURES CHAPTER 4. SPECIAL CONDITION EROSION CONTROL MEASURES 4.1 INFILTRATION BASIN AND TRENCH Figure 4.1. Infiltration basin and trench (Source: Department of Civil, Construction, and Environmental Engineering,

More information

Bowling Green, Kentucky Stormwater Best Management Practices (BMPs) Erosion Prevention Practices (EPPs) Activity: Nets and Mats (N and M)

Bowling Green, Kentucky Stormwater Best Management Practices (BMPs) Erosion Prevention Practices (EPPs) Activity: Nets and Mats (N and M) Bowling Green, Kentucky Stormwater Best Management Practices (BMPs) Erosion Prevention Practices (EPPs) Activity: Nets and Mats (N and M) EPP-11 PLANNING CONSIDERATIONS: Design Life: 1 yr Acreage Needed:

More information

If you are not able to turn in your notebook see me or Dan ASAP

If you are not able to turn in your notebook see me or Dan ASAP Notebook Collection Collecting hard copies now OR Electronic versions using Catalyst drop box Due by 5:30 pm today Use website for link If you are not able to turn in your notebook see me or Dan ASAP URBAN

More information

Key Topics. Bioretention Crime Scene Investigation The Bioretention Construction and Maintenance Sequence

Key Topics. Bioretention Crime Scene Investigation The Bioretention Construction and Maintenance Sequence Key Topics Bioretention Crime Scene Investigation The Bioretention Construction and Maintenance Sequence Bioretention Crime Scenes Investigation A 9 part reality TV series where you get to watch disturbing

More information