1 CAMPUS MASTER PLAN Steering Committee Meeting July 29, 2014 WORKSHOP A R C H I T E C T S, INC L H B, INC

2 PROCESS & SCHEDULE Research Space needs data Athletics/recreational sports Previous master plan Facility condition assessment Infrastructure/utility condition assessment Planning concept explorations, development & refinement Campus development Phased implementation plan Landscape improvement plan Architectural & site design guidelines Documentation Executive summary Master plan documentation

3 AGENDA Long term campus plan One option each for North & South campus Linkage between identified needs & recommendations Phasing recommendations Updates Facilities assessment Utility recommendations Design Guidelines Site Architectural

4 NORTH CAMPUS LONG TERM PLAN

5 SOUTH CAMPUS LONG TERM PLAN

6 MAIN THEMES & GOALS Reinvigorate Old Main Address Athletic Facility Needs Focus on Student Success Accommodate Different Teaching and Learning Styles Foster Pride of Place to Better Enable Recruitment & Retention Utilize Campus Landscape in Developing a Memorable Campus Experience Influence Adjacent Development Optimize Space Develop One-Stop Shop Expand Research Space Showcase Multi-Cultural Community Refresh Residential Facilities Support Strategic Plan

7 STRATEGIC PLAN ACTION STEPS Values Statement At the University of Wisconsin-Superior, we are committed to academic excellence, with an emphasis on: student-focused learning, intellectual development, continuous improvement, inclusivity, and community partnerships Four Guiding Principles Student Focused Recognized Excellence in Selected Fields Efficient and Effective Use of Resources Regional Partner of Choice

8 STRATEGIC PLAN ACTION STEPS Strategic Initiative 1 The University will provide students with transformative, collaborative, flexible and career-relevant learning experiences. Strategic Initiative 2 The University will deliver innovative programs that enhance the vitality of the region. Potential Master Plan Action Steps Increase the number and quality of collaborative/ active learning environments. Create a memorable campus environment that celebrates the student s experience at UW Superior. Enhance the visibility and quality of on-campus research spaces. Improve connections to surrounding community (entry, roads, views in to campus, Belknap development, increasing welcoming perimeter?).?

9 STRATEGIC PLAN ACTION STEPS Strategic Initiative 3 The University will be a diverse community that attracts, supports, and recognizes high-achieving students and employees. Strategic Initiative 4 The University will establish and maintain an infrastructure to promote accountability, sustainability, and continuous improvement. Potential Master Plan Action Steps Create improved athletic facilities to attract student athletes, a population that has a high record of academic success and timely graduation. Commit to annual reduction in energy use and develop conservation initiatives.?

10 PHASING NORTH CAMPUS Short-term (<6 years) Renovate Old Main Track & Field Stadium Belknap Gateway Landscape Connection Across Catlin Upgrade Data & Telecommunications Mid-term (6-12 years) Holden Fine Arts Renovation Dome Above Track & Field Women s Softball Men s Baseball Multipurpose Field Gates Addition Long-term (12-18 years) Newman Center Acquisition Landscape Campus Core Residence Hall Renovation & Addition Future (20+ years) Replace Science Building Property Acquisitions Entry/parking near YU Wessman Addition Natural Lands Enhancement Utilities Projects

11 PHASING NORTH CAMPUS SHORT-TERM Short-term (<6 years) Renovate Old Main Track & Field Stadium Belknap Gateway Landscape Connection Across Catlin Upgrade Data & Telecommunications Mid-term (6-12 years) Holden Fine Arts Renovation Dome Above Track & Field Women s Softball Men s Baseball Multipurpose Field Gates Addition Long-term (12-18 years) Newman Center Acquisition Landscape Campus Core Residence Hall Renovation & Addition Future (20+ years) Replace Science Building Property Acquisitions Entry/parking near YU Wessman Addition Natural Lands Enhancement Utilities Projects

12 PHASING NORTH CAMPUS MID-TERM Short-term (<6 years) Renovate Old Main Track & Field Stadium Belknap Gateway Landscape Connection Across Catlin Upgrade Data & Telecommunications Mid-term (6-12 years) Holden Fine Arts Renovation Dome Above Track & Field Women s Softball Men s Baseball Multipurpose Field Gates Addition Long-term (12-18 years) Newman Center Acquisition Landscape Campus Core Residence Hall Renovation & Addition Future (20+ years) Replace Science Building Property Acquisitions Entry/parking near YU Wessman Addition Natural Lands Enhancement Utilities Projects

13 PHASING SOUTH CAMPUS MID-TERM Short-term (<6 years) Renovate Old Main Track & Field Stadium Belknap Gateway Landscape Connection Across Catlin Upgrade Data & Telecommunications Mid-term (6-12 years) Holden Fine Arts Renovation Dome Above Track & Field Women s Softball Men s Baseball Multipurpose Field Gates Addition Long-term (12-18 years) Newman Center Acquisition Landscape Campus Core Residence Hall Renovation & Addition Future (20+ years) Replace Science Building Property Acquisitions Entry/parking near YU Wessman Addition Natural Lands Enhancement Utilities Projects

14 PHASING NORTH CAMPUS LONG-TERM Short-term (<6 years) Renovate Old Main Track & Field Stadium Belknap Gateway Landscape Connection Across Catlin Upgrade Data & Telecommunications Mid-term (6-12 years) Holden Fine Arts Renovation Dome Above Track & Field Women s Softball Men s Baseball Multipurpose Field Gates Addition Long-term (12-18 years) Newman Center Acquisition Landscape Campus Core Residence Hall Renovation & Addition Future (20+ years) Replace Science Building Property Acquisitions Entry/parking near YU Wessman Addition Natural Lands Enhancement Utilities Projects

15 PHASING NORTH CAMPUS FUTURE Short-term (<6 years) Renovate Old Main Track & Field Stadium Belknap Gateway Landscape Connection Across Catlin Upgrade Data & Telecommunications Mid-term (6-12 years) Holden Fine Arts Renovation Dome Above Track & Field Women s Softball Men s Baseball Multipurpose Field Gates Addition Long-term (12-18 years) Newman Center Acquisition Landscape Campus Core Residence Hall Renovation & Addition Future (20+ years) Replace Science Building Property Acquisitions Entry/parking near YU Wessman Addition Natural Lands Enhancement Utilities Projects

16 PHASING SOUTH CAMPUS FUTURE Short-term (<6 years) Renovate Old Main Track & Field Stadium Belknap Gateway Landscape Connection Across Catlin Upgrade Data & Telecommunications Mid-term (6-12 years) Holden Fine Arts Renovation Dome Above Track & Field Women s Softball Men s Baseball Multipurpose Field Gates Addition Long-term (12-18 years) Newman Center Acquisition Landscape Campus Core Residence Hall Renovation & Addition Future (20+ years) Replace Science Building Property Acquisitions Entry/parking near YU Wessman Addition Natural Lands Enhancement Utilities Projects

17 PROPERTY ACQUISITION Current Boundary Recommend Acquisition Area of Influence Pros Cons 1 2 Opportunity to extend street & parking; owner interest in sale Shape identity at Belknap Willingness of BK to sell, cost 3 Opportunity to extend street & parking: identity on Grand Difficulty of purchasing multiple homes; awkward intersection with Grand 4 Space for athletics and/or parking Willingness of railroad to sell 5 5 Identity & pedestrian safety on Caitlin Difficulty of purchasing multiple homes

18 FACILITIES ASSESSMENT PHYSICAL RATING Good (minimal renovation) Satisfactory (limited renovation) Fair (moderate renovation) Poor (significant renovations FUNCTIONAL RATING A. Excellent B. Satisfactory C. Conditional D. Development Required

19 FACILITIES ASSESSMENT PHYSICAL RATING Good (minimal renovation) Satisfactory (limited renovation) Fair (moderate renovation) Poor (significant renovations FUNCTIONAL RATING A. Excellent B. Satisfactory C. Conditional D. Development Required

20 UTILITIES Data & Communications System is at the limit due to age and changing technology Replacement of PBX with VOIP is a large driver Infrastructure will require several replacements over the 20 year life due to rapid rate of change.

21 UTILITIES Electricity Generally in good condition Flood mitigation fixes are the major opportunity. Over the next 20 years some sort of distributed generation will occur.

22 UTILITIES Steam Generally in good condition. Distribution system is in near new condition due to recent improvements Boiler plant will require major replacement in the next 20 years due to age and need to reduce carbon production.

23 UTILITIES Natural Gas System is owned by third party No projected need for the campus to do any work internally except to coordinate future work.

24 UTILITIES Sewer Unknown condition, but city owned infrastructure to the west is undersized and causes issues during rain events Installation of backwater valves on affected connections to the city mains is recommended.

25 UTILITIES Water System is owned by a third party and is in good shape with more than adequate fire flow and domestic capacity. Existing CI lines are up to 95 years old, but are being replaced with HDPE. Coordinate future projects.

26 BREAK

27 DESIGN GUIDELINES

28 DESIGN GUIDELINES PURPOSE AND GOALS A. CAMPUS DESIGN GUIDELINES ARE INTENDED TO: 1. Enhance the image and identity that is uniquely UW Superior; 2. Honor the history of the campus context; and 3. Describe the distinguishing characteristics of the campus architecture and grounds. B. CAMPUS DESIGN GUIDELINES WILL HELP TO: 1. Influence the decision making process regarding how construction projects should be designed to enhance the campus image and identity; 2. Advocate a legacy of high quality architecture and contextual design throughout campus; and 3. Promote essential design characteristics yet allow for creative expression.

29 DESIGN GUIDELINES SITE GUIDELINES OUTDOOR SPACES Enhance the open park-like quality of the quad by utilizing canopy trees instead of coniferous trees. Use canopy trees to provide shade and structure. Use ornamental trees and shrubs to define more intimate spaces. Use coniferous trees or shrubs as wind screens in large open areas. Use landscape treatments to reinforce a variety of open spaces created for either passive or active uses. Preserve unobstructed sight lines between Old Main and Yellowjacket Union. Maintain clear viewing between 3 (understory) and 12 (canopy). UWS Princeton University Yale University University of Michigan, Ann Arbor

30 DESIGN GUIDELINES SITE GUIDELINES LANDSCAPE PALETTE Use a diverse planting palette that includes native species as well as select non-native species. Provide color throughout the year and especially during the winter. Use a variety of plant species to develop the campus as a living laboratory. Select plants from the campus plant list. Retain the scale of mature plantings to enhance the institutional nature of the UW-Superior campus. A variety of canopy trees should dominate the campus academic core. Maintain a campus plant list to support biological education yet create a more unified appearance around buildings. Selection of resilient species and massed installation in naturalistic patterns will be strongly favored to limit maintenance operations. Example of Color in Winter University of the Pacific, South Quad UWS

31 DESIGN GUIDELINES SITE GUIDELINES LANDSCAPE PALETTE Consider fast-growing species where appropriate. Use coniferous trees in a manner consistent with promoting safety and security. Use understory plants to supplement canopy trees and maintain sightlines between building entrances. Use landscaping to unite north and south campus. Locate plantings near building facades to maintain clear views to entrances, allow sunlight, and air circulation. Install mulched beds around all mass understory plants in Maintenance Level 1 to limit moisture loss and weed growth. Use natural mulch material. Use the same material throughout campus. UWS Harvard University

32 DESIGN GUIDELINES SITE GUIDELINES UWS WAYFINDING Accentuate major pedestrian and vehicular routes with canopy trees. Accentuate routes to or between outdoor spaces and buildings. Encourage tree groupings and natural, irregular spacing. Direct attention to entrances through the use of plant height, width, and color. Accent building entries with low distinctive plant material. Maintain clear visibility to entries.

33 DESIGN GUIDELINES SITE GUIDELINES GATEWAYS Incorporate distinctive vertical element(s) (focal points) epitomizing the campus. Design major campus entry signage to complement standard campus building signage. Entry signage does not need to match building signage. Utilize plant material that helps identify, establish, and strengthen campus entry points. Supplement signage or other gateway elements with colorful and visually open plantings. UWS Marquette University Hiram University University of Wyoming

34 DESIGN GUIDELINES SITE GUIDELINES EDGES Maintain campus edges that are defined but not too structured, relating to the adjacent uses and welcoming to the surrounding community without losing the identity of the campus. Create a distinct soft edge while maintaining views into campus through repetitive and natural patterns of canopy trees and low shrubs. Screen utility and trash collection areas from public views using dense plant materials in conjunction with walls or fencing. UWS MLK Gateway, Portland, Oregon

35 DESIGN GUIDELINES SITE GUIDELINES Light Pole with Banners SITE FURNISHINGS Continue implementing previous furnishings. Implement street light banner guidelines. Utilize 18 x 36 banners with blackout vinyl or Sunbrella type fabric, brackets and hardware. Use brackets that either bend or break-away under strong winds to avoid stress to the poles. Select banner color(s) and designs based on the season or special events. Signage Benches Tables and Chairs Planters Trash Receptacles

36 DESIGN GUIDELINES SITE GUIDELINES LANDSCAPE MAINTENANCE LEVELS LEVEL 1, HIGH: Lawn Maintenance: Mowing, fertilization, weed control, and replacement. Tree Maintenance: Pruning, fertilization, and replacement. Understory Maintenance: Pruning, fertilization, replacement, and mulching. Annuals: Limited seasonal planting will be supported. LEVEL 2, MODERATE: Lawn Maintenance: Same as Level 1. Tree Maintenance: Same as Level 1. Athletic Fields: Natural turf fields require mowing, watering, weeding, fertilization, disease/insect control, and over-seeding. Synthetic fields require brushing, and frequent removal of weeds, moss and stains. LEVEL 3, LOW: Remove invasive species and fell dead trees. Clear and maintain trails.

37 THANK YOU!

Assessment of the Extent and Quality of the Landscape Features of the Campus.

Assessment of the Extent and Quality of the Landscape Features of the Campus. Assessment of the Extent and Quality of the Landscape Features of the Campus. 1. In 2012 the University used geographic information systems to create georeferenced layers for all landscape and hardscape

More information

CAMPUS MASTER PLAN UPDATE

CAMPUS MASTER PLAN UPDATE 13 April 2016 CAMPUS MASTER PLAN UPDATE Focus Group Landscape AGENDA What We Heard Review of Campus Observations & Analysis Campus Framework & Open Space Network Table-Top Exercise Landscape Guideline

More information

PUBLIC RIGHT-OF-WAY IN THIS CHAPTER PUBLIC REALM

PUBLIC RIGHT-OF-WAY IN THIS CHAPTER PUBLIC REALM PUBLIC RIGHT-OF-WAY This section provides design guidelines for improvements in the public right-of-way. The public right-of-way refers to streets, sidewalks, non-vehicular thoroughfares, parks and greenways

More information

Phase 1 : Understanding the Campus Context. Phase 2 : APPROACHES - Alternates & Preferred Plan

Phase 1 : Understanding the Campus Context. Phase 2 : APPROACHES - Alternates & Preferred Plan Introduction MASTER PLAN PURPOSE WHY A CAMPUS MASTER PLAN? The purpose of the Master Plan at the University of Illinois at Chicago is to translate UIC s strategic goals and objectives into a compelling

More information

CAMPUS MASTER PLAN DRAFT PLAN UPDATE JANUARY

CAMPUS MASTER PLAN DRAFT PLAN UPDATE JANUARY NEW MEXICO HIGHLANDS UNIVERSITY CAMPUS MASTER PLAN DRAFT PLAN UPDATE JANUARY 27 2010 MASTER PLANNING GOALS TO BALANCE THE STRATEGIC GOALS OF THE UNIVERSITY WITH THE PHYSICAL CAMPUS through the assessment

More information

NEIGHBORHOOD 7: FEE LANE AREA. Aerial View of Briscoe and McNutt Dormitories

NEIGHBORHOOD 7: FEE LANE AREA. Aerial View of Briscoe and McNutt Dormitories NEIGHBORHOOD 7: FEE LANE AREA Aerial View of Briscoe and McNutt Dormitories Fee Lane Area Map Briscoe Dormitory 278 neighborhoods NEIGHBORHOOD 7: FEE LANE AREA EXISTING CHARACTER The Fee Lane Area neighborhood

More information

4. INDUSTRIAL 53 CASTLE ROCK DESIGN

4. INDUSTRIAL 53 CASTLE ROCK DESIGN 4. INDUSTRIAL 53 CASTLE ROCK DESIGN CASTLE ROCK DESIGN 54 4. INDUSTRIAL Overview Well-designed and attractive industrial centers are the product of blending economic realities with both functional and

More information

Academics Efficient use of space will be used to enhance investments in new pedagogies such as active learning classrooms.

Academics Efficient use of space will be used to enhance investments in new pedagogies such as active learning classrooms. Goals and Assumptions Physical Planning Goals and Objectives The guiding principles of this Master Plan were developed in consultation with various constituencies that make up the NMSU community and were

More information

U n i v e r s i t y o f S o u t h C a r o l i n a A i k e n. Land Plan Study

U n i v e r s i t y o f S o u t h C a r o l i n a A i k e n. Land Plan Study U n i v e r s i t y o f S o u t h a r o l i n a A i k e n Land Plan Study 06.27.2008 Goals ampus Growth Develop a Land Plan that allows for the orderly expansion of the campus over the next ten years and

More information

University of Denver Land Use Plan Update I. Executive Summary

University of Denver Land Use Plan Update I. Executive Summary Executive Summary The task of developing a Land Use Plan for the University of Denver has been an exciting collaborative process that engaged a variety of interested people, including members of the University

More information

NEIGHBORHOOD 3: UNIVERSITY EDGE

NEIGHBORHOOD 3: UNIVERSITY EDGE NEIGHBORHOOD 3: UNIVERSITY EDGE Aerial View of North Indiana Avenue EXISTING CHARACTER The University Edge neighborhood represents the primary town/gown interface between the campus and the city of Bloomington,

More information

Community Design Plan

Community Design Plan Gardena General Plan 2006 Authority While the is not a required element of a General Plan, it is included because improving the community appearance and image is paramount to the overall quality of life

More information

1 Welcome! UBC Okanagan Master Plan Update - Open House

1 Welcome! UBC Okanagan Master Plan Update - Open House 1 Welcome! UBC Okanagan Master Plan Update - Open House UBC is updating the Master Plan for the Okanagan Campus. The purpose of today s Open House is to: Present the draft 2015 Master Plan Answer any questions

More information

11 February CAMPUS MASTER PLAN UPDATE Focus Group - Design Guidelines

11 February CAMPUS MASTER PLAN UPDATE Focus Group - Design Guidelines 11 February 2016 CAMPUS MASTER PLAN UPDATE Focus Group - Design Guidelines AGENDA Introductions Planning Scope The 2004 Campus Plan Observations Design Guidelines - 2004 Plan SWOT Exercise Analysis Goals

More information

CAL POLY MASTER PLAN UPDATE, March 2015

CAL POLY MASTER PLAN UPDATE, March 2015 Some Key Themes in the General Guiding Principles Academic Mission The plan must foremost advance the University s academic mission and student success. Foresight and Adaptability The plan should take

More information

Achieving a Vision. Master Plan 2009 Belknap Campus August 10 11, UofL Belknap Campus Master Plan Update

Achieving a Vision. Master Plan 2009 Belknap Campus August 10 11, UofL Belknap Campus Master Plan Update Achieving a Vision Master Plan 2009 Belknap Campus August 10 11, 2009 Consultant Team The Campus Studio Ann Arbor Michigan Team Leader Campus Planning Site Design JRA Architects Louisville Kentucky Assistant

More information

University of Saskatchewan CAMPUS MASTER PLAN. Senate Meeting Preliminary Presentation. April 21, 2018 DIALOG ECS DA WATT

University of Saskatchewan CAMPUS MASTER PLAN. Senate Meeting Preliminary Presentation. April 21, 2018 DIALOG ECS DA WATT University of Saskatchewan CAMPUS MASTER PLAN Senate Meeting Preliminary Presentation April 21, 2018 DIALOG ECS DA WATT project process presentation agenda Stakeholder Engagement Project Control phase1

More information

242 neighborhoods NEIGHBORHOOD 4: JORDAN AVENUE CORRIDOR

242 neighborhoods NEIGHBORHOOD 4: JORDAN AVENUE CORRIDOR NEIGHBORHOOD 4: JORDAN AVENUE CORRIDOR Aerial View of Jordan Avenue Corridor EXISTING CHARACTER The Jordan Avenue Corridor is the portion of North Jordan Avenue that extends north from East Third Street

More information

SOUTH DAKOTA STATE UNIVERSITY GROUNDS MANAGEMENT PLAN FY 2013

SOUTH DAKOTA STATE UNIVERSITY GROUNDS MANAGEMENT PLAN FY 2013 SOUTH DAKOTA STATE UNIVERSITY GROUNDS MANAGEMENT PLAN FY 2013 SOUTH DAKOTA STATE UNIVERSITY GROUNDS MANAGEMENT PLAN Table of contents: Introduction & Goals 03 Prioritization 03 Improvement Strategies 07

More information

EXISTING CONDITIONS 41. Existing Conditions

EXISTING CONDITIONS 41. Existing Conditions EXISTING CONDITIONS 41 Existing Conditions The Existing Analysis phase of the planning process involved a study of the existing conditions on the campus in order to identify key planning issues to be addressed

More information

A Campus Within Context

A Campus Within Context A Campus Within Context A Comprehensive Master Plan for East Carolina University Optimize Valuable Resources Guide Future Development Establish Capital Priorities Create a Sense of Place Sustainable Campus

More information

Landscape and Streetscape Design 2.5

Landscape and Streetscape Design 2.5 Landscape and Streetscape Design 2.5 2.5.1 Goals 2.5.2 Planting 2.5.3 Sidewalks and Pavement 2.5.4 Furnishings 2.5.5 Walls 2.5.6 Lighting 2.5.7 Stormwater 2.5.8 Street Cross Sections 2.5 LANDSCAPE AND

More information

Urban Design Manual PLANNING AROUND RAPID TRANSIT STATIONS (PARTS) Introduction. Station Study Areas

Urban Design Manual PLANNING AROUND RAPID TRANSIT STATIONS (PARTS) Introduction. Station Study Areas 111111 PLANNING AROUND RAPID TRANSIT STATIONS (PARTS) Introduction The ION rapid transit system will link Waterloo, Kitchener and Cambridge through a central transit corridor (CTC). There are a number

More information

implementation r expression in landscape

implementation r expression in landscape 6 ubc okanagan implementation campus plan r expression in landscape 68 6 implementation campus plan sections The Campus Plan supports the academic mission, values and commitments of the University by providing

More information

VEHICULAR AND PEDESTRIAN CIRCULATION

VEHICULAR AND PEDESTRIAN CIRCULATION This perspective sketch communicates the intended character and quality of a proposed streetscape design. Locate benches near a major intersection where people tend to gather. Seating and lighting provide

More information

OBJECTIVE 1.1: To develop and adopt a Landscape Master Plan for the University of Central Florida campus by 2015.

OBJECTIVE 1.1: To develop and adopt a Landscape Master Plan for the University of Central Florida campus by 2015. Goals, Objectives and Policies GOAL 1: To create an exemplary campus outdoor environment that promotes comfort, security, sustainability, and a regional sense of place. and to create a rich and horticulturally

More information

38 Queen s University Campus Master Plan Part 1

38 Queen s University Campus Master Plan Part 1 38 Queen s University Campus Master Plan Part 1 46 The Campus at the City Scale Chapter 4 The Campus at the City Scale 39 Queen s is an urban University centrally located in Kingston. Decisions made by

More information

neighborhoods NEIGHBORHOOD 5: EAST OF JORDAN

neighborhoods NEIGHBORHOOD 5: EAST OF JORDAN NEIGHBORHOOD 5: EAST OF JORDAN East of Jordan Neighborhood EXISTING CHARACTER East of Jordan is defined as the residential neighborhood east of North Jordan Avenue and south of the railroad tracks. This

More information

The University District envisions, in its neighborhood

The University District envisions, in its neighborhood Envisioning the University District Link Light Rail in Seattle s neighborhoods CIY OF SEALE CONCEP-LEVEL SAION AREA PLANNING RECOMMENDAION RESOLUION # 30165 EXHIBI L Vision 08.2000 he University District

More information

campus master plan VIRGINIA STATE UNIVERSITY

campus master plan VIRGINIA STATE UNIVERSITY campus master plan VIRGINIA STATE UNIVERSITY agenda 01 INTRODUCTION & GENERAL OVERVIEW 02 03 04 LAND USE CONCEPT PROGRAM ACCOMMODATION MAXIMIZE EXISTING INFRASTRUCTURE SUMMARY AND NEXT 05 STEPS agenda

More information

3.0 master plan concept

3.0 master plan concept 3.0 master plan concept 3.1 introduction The purpose of the Huron Church Road Master Plan Concept is to provide an overview of the Master Plan design process, identify preliminary streetscape installations

More information

WELLINGTON STREET WEST COMMUNITY DESIGN PLAN

WELLINGTON STREET WEST COMMUNITY DESIGN PLAN 36 3.CDP POLICIES 37 Wellington Street West CDP Vision Statement 38 3.1 Introduction 3.1.1 Purpose The development of buildings and public spaces is influenced by a variety of factors over time. City of

More information

New-Cast Mixed-use Development Proposal King Street West, Newcastle, Ontario

New-Cast Mixed-use Development Proposal King Street West, Newcastle, Ontario URBAN DESIGN BRIEF New-Cast Mixed-use Development Proposal King Street West, Newcastle, Ontario TABLE OF CONTENTS: 1.0 Executive Summary 2.0 Creating Vibrant and Sustainable Urban Places: Excerpts from

More information

Urban Design 9Identity

Urban Design 9Identity Urban Design 9Identity URBAN DESIGN IDENTITY Urban design is about connecting people to their places through the built environment, nature, and overall urban form. Done well, it creates a memorable space

More information

V. Gateways GATEWAYS / V-1

V. Gateways GATEWAYS / V-1 V. GATEWAYS / V-1 Many of Chesapeake s gateways are located on highways and call for bold and attractive designs that motorists can understand, appreciate, and enjoy. can also take the form of natural

More information

Moreno Valley College: Conceptual Master Planning - Site Analysis Lasselle Street, Moreno Valley, CA 92551

Moreno Valley College: Conceptual Master Planning - Site Analysis Lasselle Street, Moreno Valley, CA 92551 Master Plan Architect School Name Moreno Valley College District Riverside Community College District Architecture and Urban Design 5898 Blackwelder Street Ground Floor Culver City, CA 90232 T: 310.559.5720

More information

C a m p u s I d e n t i t y

C a m p u s I d e n t i t y Campus Identity Campus Identity a) Landscape Guidelines i. Materials ii. Components iii. Composition b) Wayfinding i) Entrance Features ii) Vehicular iii) Pedestrian c) Focus Areas i) Green Spine ii) Warriner

More information

8.0 Built Form Framework

8.0 Built Form Framework Figure C-40. RIC and Laboratory Building Internal Pedestrian Node 8.0 Built Form Framework The built form framework defines the desired future character and function of built elements within the campus

More information

UNIVERSITY OF KENTUCKY 2012 Campus Plan Update. Ross Tarrant Architects

UNIVERSITY OF KENTUCKY 2012 Campus Plan Update. Ross Tarrant Architects UNIVERSITY OF KENTUCKY 2012 Campus Plan Update AGENDA TEAM 1 2 3 4 5 ENGAGEMENT PUBLIC INPUT PROCESS GOALS AND OBJECTIVES PLANNING PROCESS AND SCHEDULE TOPICS AND DISCUSSION Team SASAKI UNIVERSITY OF PENNSYLVANIA

More information

District Facilities Master Plan

District Facilities Master Plan W o r k s h o p B o a r d District Facilities Master Plan February 29, 2012 BACKGROUND + CONTEXT ANALYSIS OPTIONS RECOMMENDATIONS NEXT STEPS DFMP AGENDA BACKGROUND + CONTEXT ANALYSIS OPTIONS RECOMMENDATIONS

More information

REGIONAL ACTIVITY CENTER

REGIONAL ACTIVITY CENTER DRAFT REGIONAL ACTIVITY CENTER 70 EAST BENCH MASTER PLAN DRAFT 06 Introduction The East Bench Regional Activity center is comprised of large educational, research, medical, and employment centers. These

More information

WESTERN ILLINOIS UNIVERSITY

WESTERN ILLINOIS UNIVERSITY WESTERN ILLINOIS UNIVERSITY Quad Cities Riverfront Campus Preliminary Master Plan Presentation 2 February 1, 2006 Achieving Future Flexibility 1. Monitor space needs as the new buildings come on line and

More information

TH E U N IVE RSIT Y O F FLO R I DA LANDSCAPE MASTER PLAN REPORT

TH E U N IVE RSIT Y O F FLO R I DA LANDSCAPE MASTER PLAN REPORT TH E U N IVE RSIT Y O F FLO R I DA LANDSCAPE MASTER PLAN REPORT O C T O B E R 2 018 THE UNIVERSITY OF FLORIDA LANDSCAPE MASTER PLAN REPORT OCTOBER 2018 prepared by: CRJA-IBI Group GAI Community Solutions

More information

\\ Comprehensive Facilities Master Plan. Design Guidelines

\\ Comprehensive Facilities Master Plan. Design Guidelines Design Guidelines CU-Boulder What are Design Guidelines? Institution Character Continuity of Fabric Accelerate Design Process, constrained options MIT Descriptive Buildings on the campus reflect many styles,

More information

FLORIDA ATLANTIC UNIVERSITY. GOALS, OBJECTIVES AND POLICIES 3 Urban Design

FLORIDA ATLANTIC UNIVERSITY. GOALS, OBJECTIVES AND POLICIES 3 Urban Design 3 URBAN DESIGN ELEMENT Goal 1 To establish and follow conceptual principles for the organization of future development, including buildings and open spaces, on the University's campuses. Objective 1A Protect

More information

Foreword to the Third + Edition

Foreword to the Third + Edition U n i v e r s i t y of Oregon Campus Plan - Third + Edition, 2017 i Foreword to the Third + Edition Third + Edition (November 2017) This third + edition of the 2005 Campus Plan integrates amendments approved

More information

264 neighborhoods NEIGHBORHOOD 6: WOODLAWN AND TENTH STREET

264 neighborhoods NEIGHBORHOOD 6: WOODLAWN AND TENTH STREET NEIGHBORHOOD 6: WOODLAWN AND TENTH STREET Existing Aerial View Looking North EXISTING CHARACTER The area north of East Tenth Street and south of the railroad tracks has been identified for significant

More information

SITE FURNISHINGS STANDARDS MANUAL

SITE FURNISHINGS STANDARDS MANUAL University Planner's Office Architecture, Engineering & Construction University of Michigan January, 2011 http://www.umaec.umich.edu/ Table of Contents Introduction page 3 Campus Landscape Design Elements

More information

Creating a sense of arrival at campus entrances and at the primary entrances to the Campus Core.

Creating a sense of arrival at campus entrances and at the primary entrances to the Campus Core. 16.0 LANDSCAPE DESIGN GUIDELINES ELEMENT In campus planning, design professionals whose focus is the outdoors must be sensitive to transitions from building to open space, the need for common areas and

More information

EXTERlOR DESlGN LANGUAGE. Exterior Design Language PAGE 1 OF 27

EXTERlOR DESlGN LANGUAGE. Exterior Design Language PAGE 1 OF 27 EXTERlOR DESlGN LANGUAGE Exterior Design Language PAGE 1 OF 27 INTRODUCTION EXTERIOR DESIGN LANGUAGE What is this document and who is it for? Exterior Design Language is a supplement to the original Design

More information

CHAPPLES PARK MASTER PLAN

CHAPPLES PARK MASTER PLAN CHAPPLES PARK MASTER PLAN Presentation of Preliminary Development Options Public Open House #2 Wednesday November 2 nd, 2016 TONIGHT S AGENDA 1. Welcome & Introductions 2. Presentation by Sierra Planning

More information

Redevelopment Concept. Site Potential

Redevelopment Concept. Site Potential CAMPUS MASTER PLAN Site Potential The projected site for development is the area that has become available since the removal of Johnstone. However, the development possibilities increase dramatically if

More information

Table of Contents. Elm Avenue Improvement Plan City of Waco, Texas. Introduction 1. Existing Context 1 Figure 1 2.

Table of Contents. Elm Avenue Improvement Plan City of Waco, Texas. Introduction 1. Existing Context 1 Figure 1 2. Table of Contents Introduction 1 Existing Context 1 Figure 1 2 Plan Guidelines 3 Future Urban Form 4 The West-End 4 Main Street 6 The East-End 7 Figure 2 9 Public Improvement Recommendations 7 General

More information

R STREET CORRIDOR NEIGHBORHOOD Site Plan and Design Review Supplemental Guidelines Checklist

R STREET CORRIDOR NEIGHBORHOOD Site Plan and Design Review Supplemental Guidelines Checklist R STREET CORRIDOR NEIGHBORHOOD Site Plan and Design Review Supplemental Guidelines Checklist Applicant s Name: Project Address: Phone: Email: Applicant shall fill out the design guidelines checklist for

More information

Health Sciences City The available land area, although limited, combined with the unique partnership between the primary institutions and the supporting partnerships of the development interests within

More information

Appendix A COMMUNITY IMPROVEMENT PLAN DESIGN GUIDELINES

Appendix A COMMUNITY IMPROVEMENT PLAN DESIGN GUIDELINES Appendix A COMMUNITY IMPROVEMENT PLAN DESIGN GUIDELINES INTRODUCTION The continuous and desirable improvement of Arnprior requires a clear understanding of what is envisioned for the Town. These Design

More information

SECTION V: DESIGN GUIDELINE EXAMPLES

SECTION V: DESIGN GUIDELINE EXAMPLES SECTION V: DESIGN GUIDELINE EXAMPLES Introduction The Syracuse Town Center is envisioned as an area that creates a sense of place, a community downtown. As such, the Town Center Committee recommended the

More information

University of Minnesota. MINNEAPOLIS CAMPUS DEVELOPMENT FRAMEWORK February 11, 2016

University of Minnesota. MINNEAPOLIS CAMPUS DEVELOPMENT FRAMEWORK February 11, 2016 MINNEAPOLIS CAMPUS DEVELOPMENT FRAMEWORK DEVELOPMENT FRAMEWORK of use shape the campus today and may inform the future. Form, meaning how the shape, size, orientation, and arrangement of buildings, spaces,

More information

Policies and Code Intent Sections Related to Town Center

Policies and Code Intent Sections Related to Town Center Policies and Code Intent Sections Related to Town Center The Town Center Vision is scattered throughout the Comprehensive Plan, development code and the 1994 Town Center Plan. What follows are sections

More information

EXISTING VEHICULAR & PEDESTRIAN CIRCULATION

EXISTING VEHICULAR & PEDESTRIAN CIRCULATION 46 EXISTING CONDITIONS EXISTING VEHICULAR & PEDESTRIAN CIRCULATION Vehicular and pedestrian circulation patterns are illustrated on this graphic. Campus entry points and major vehicular circulation routes

More information

FOCUS GROUP 3 Urban, Architectural & Landscape Design Guidelines

FOCUS GROUP 3 Urban, Architectural & Landscape Design Guidelines Meeting Minutes By: Perkins+Will - GK Date: 11/30/2012 Meeting Date: 10/03/2012 Project Name: BT-857 FIU-Campus Master Plan Update 2010-2020 Meeting Time: 8:00am-10:00am Project : 810369.000 Meeting Location:

More information

Jewel. Platte. of the. Plattsmouth Main Street Landscape Architecture by HDR

Jewel. Platte. of the. Plattsmouth Main Street Landscape Architecture by HDR Jewel of the Platte Plattsmouth Main Street Landscape Architecture by HDR Plattsmouth, Nebraska is a historic community of 6,500 residents located along the west bank of the Missouri River, just south

More information

Charles P. Johnson and Associates. Annapolis Landscape Architects

Charles P. Johnson and Associates. Annapolis Landscape Architects Charles P. Johnson and Associates Annapolis Landscape Architects AGENDA Introduction Project Limits and Scope Site Analysis Opportunities & Constraints Program Goals Image Boards Design Alternatives Pros

More information

The Vision. Photo provided by The Minervini Group. 46 Vision, Objectives & Strategies

The Vision. Photo provided by The Minervini Group. 46 Vision, Objectives & Strategies Vision, Objectives & Strategies The is the public framework and guide for future development of the Grand Traverse Commons. The establishes public polices for infrastructure, the preservation of natural

More information

Commercial Development Permit Area

Commercial Development Permit Area City of Kamloops KAMPLAN Commercial Development Permit Area PURPOSE The purpose of this Development Permit Area (DPA) is to establish objectives and provide guidelines for the form and character of commercial

More information

Long Branch-Wayne Local Park Renovation Project

Long Branch-Wayne Local Park Renovation Project Montgomery Parks Long Branch-Wayne Local Park Renovation Project Community Meeting #2 September 20, 2016 Oak View Elementary School 7:00-9:00 PM Welcome / Team Introductions M-NCPPC (Montgomery Parks)

More information

13. New Construction. Context & Character

13. New Construction. Context & Character 13. New Construction Context & Character While historic districts convey a sense of time and place which is retained through the preservation of historic buildings and relationships, these areas continue

More information

BUSINESS DISTRICT DESIGN GUIDELINES

BUSINESS DISTRICT DESIGN GUIDELINES Des Plaines, Illinois Prepared for the City of Des Plaines by: The Lakota Group Laurie Marston, AICP March 2005 Section 5: Streetscape Elements Business District Design Guidelines STREETSCAPE ELEMENTS

More information

UCSF Parnassus Heights Re-Envisioning Process

UCSF Parnassus Heights Re-Envisioning Process UCSF Parnassus Heights Re-Envisioning Process Community Working Group Meeting #5 February 27, 2019 Agenda Welcome, Introductions, Agenda Overview, and Review of Last Meeting Summary of Community Ideas

More information

CAMPUS LANDSCAPE AND OPEN SPACE

CAMPUS LANDSCAPE AND OPEN SPACE LANDSCAPE CHARACTER I hope our alumni will always insist upon retention of our precious islands of green and serenity our most important physical asset, transcending even classrooms, libraries, and laboratories

More information

12 February CAMPUS MASTER PLAN UPDATE Focus Group - Wayfinding & Signage

12 February CAMPUS MASTER PLAN UPDATE Focus Group - Wayfinding & Signage 12 February 2016 CAMPUS MASTER PLAN UPDATE Focus Group - Wayfinding & Signage AGENDA Introductions Planning Scope The 2004 Campus Plan Observations SWOT Exercise Analysis Goals and Advice Questions & Discussion

More information

Littleton Fields Master Plan

Littleton Fields Master Plan Town of Littleton Littleton Fields Master Plan September 25, 2017 Gale Associates, Inc. John M. Perry, P.E. Jeffrey F. Georges, MRLA About Gale Agenda Introduction and Purpose Background Investigation

More information

Loebl Schlossman & Hackl

Loebl Schlossman & Hackl Loebl Schlossman & Hackl in association with PSA-Dewberry Chicago, IL EIU Experience 1999 Plan Eastern Illinois University 1999 and 2002 Campus Master Plans Charleston, IL 2002 Update Highly Participatory

More information

Campus Identity & Design Guidelines

Campus Identity & Design Guidelines WSU RFP 7840-GC23215 Exhibit E Campus Identity & Design Branding Specification Washington State University Tri-Cities Campus Campus Identity & Design Guidelines G G L O architecture I interior design I

More information

THE CIVIC DISTRICT DEVELOPMENT OPPORTUNITIES

THE CIVIC DISTRICT DEVELOPMENT OPPORTUNITIES 1 THE CIVIC DISTRICT DEVELOPMENT OPPORTUNITIES The Civic District is the physical and emotional heart of the downtown. It is also a major gateway into the central core, establishing the image and identity

More information

Toronto Complete Streets Guidelines

Toronto Complete Streets Guidelines Toronto Complete Streets Guidelines 108 110 7.1 Green Infrastructure Design Principles 112 7.2 Context-Sensitive Green Streets 114 7.3 Key Green Street Elements Green infrastructure refers to natural and

More information

3. VISION AND GOALS. Vision Statement. Goals, Objectives and Policies

3. VISION AND GOALS. Vision Statement. Goals, Objectives and Policies Vision Statement Queen Creek s interconnected network of parks, trails, open spaces and recreation opportunities provide safe and diverse activities and programs that sustain its unique, small town, equestrian

More information

APPENDIX K WINDSOR OFFICIAL PLAN

APPENDIX K WINDSOR OFFICIAL PLAN CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT Replacement Span and Plaza Expansion APPENDIX K WINDSOR OFFICIAL PLAN Avalon Consulting Professionals of Ontario,

More information

GUIDELINES EXHIBITION PLACE LOCATION: OBJECTIVES. Structure Plan URBAN DESIGN GUIDELINES

GUIDELINES EXHIBITION PLACE LOCATION: OBJECTIVES. Structure Plan URBAN DESIGN GUIDELINES Development in the Exhibition Place lands will be consistent with the following urban design guidelines. They provide a framework for new development of the lands and are to be read in conjunction with

More information

FLORIN ROAD CORRIDOR Site Plan and Design Review Guidelines Checklist

FLORIN ROAD CORRIDOR Site Plan and Design Review Guidelines Checklist FLORIN ROAD CORRIDOR Site Plan and Design Review Guidelines Checklist Applicant s Name: Project Address: Phone: Email: Applicant shall fill out the design guidelines checklist for all guidelines applicable

More information

CITY OF GAINESVILLE PARKS, RECREATION AND CULTURAL AFFAIRS DEPARTMENT VISION 2020

CITY OF GAINESVILLE PARKS, RECREATION AND CULTURAL AFFAIRS DEPARTMENT VISION 2020 CITY OF GAINESVILLE PARKS, RECREATION AND CULTURAL AFFAIRS DEPARTMENT VISION 2020 A BLUE PRINT FOR THE NEXT 20 YEARS The PRCA Vision 2020 Master Plan, adopted in November 2012, addresses the current state

More information

This is the East Carolina University Comprehensive Facilities Master Plan Final Draft Plan Review. This workbook reviews the campus draft master plan

This is the East Carolina University Comprehensive Facilities Master Plan Final Draft Plan Review. This workbook reviews the campus draft master plan This is the East Carolina University Comprehensive Facilities Master Plan Final Draft Plan Review. This workbook reviews the campus draft master plan first presented on campus on June 29 and June 30, 2011.

More information

Campus Sign Plan. Adopted by the Campus Planning Committee Adopted: June 26, 2006 Revised: April 14, 2016

Campus Sign Plan. Adopted by the Campus Planning Committee Adopted: June 26, 2006 Revised: April 14, 2016 Campus Sign Plan Adopted by the Campus Planning Committee Adopted: June 26, 2006 Revised: April 14, 2016 INTRODUCTION Oregon State University requires an effective system of visual communication that projects

More information

SCCCD District Wide Facilities Master Plan FRESNO CITY COLLEGE TOWN HALL MEETING MAY2012

SCCCD District Wide Facilities Master Plan FRESNO CITY COLLEGE TOWN HALL MEETING MAY2012 FRESNO CITY COLLEGE TOWN HALL MEETING MAY2012 1 Facilities Master Planning Committees Structure The planning process for the SCCCD Facilities Master Plan was highly participatory, engaging the many constituencies

More information

urban design Introduction

urban design Introduction ACHIEVE SP RI NGF I ELD.3 Introduction Urban Design Areas Design Areas are areas within Springfield that have a unique and recognizable character that is different from other areas in the community. The

More information

Public Art Plan. We have elected to submit Public Art Plans before or concurrently with the CSP Submittal per the FDP Manual

Public Art Plan. We have elected to submit Public Art Plans before or concurrently with the CSP Submittal per the FDP Manual Public Art Plan The intent of the Horizon Uptown Public Arts Program is to create great places that engage the community and leverage the neighborhood development and economic vitality. The Horizon Uptown

More information

University of the District of Columbia Van Ness Campus Master Plan Community Open House 3. December 8, 2010

University of the District of Columbia Van Ness Campus Master Plan Community Open House 3. December 8, 2010 University of the District of Columbia Van Ness Campus Master Plan Open House 3 December 8, 2010 Introductions Sequence of Work: Campus Master Plan BEGIN: INTRODUCE AND START WORK Project Initiation Team

More information

SECTION TWO: Overall Design Guidelines

SECTION TWO: Overall Design Guidelines SECTION TWO: Overall Design Guidelines This section provides overall design principles and guidelines for the Gardnerville Mixed-use Overlay. They provide criteria for mixed-use places consisting of residential,

More information

UNIVERSITY OF DENVER. APPENDIX G Open Space Typologies

UNIVERSITY OF DENVER. APPENDIX G Open Space Typologies UNIVERSITY OF DENVER APPENDIX G Open Space Typologies Open Space Typology The range of open space types found on college campuses extends from large, open fields to intimate enclaves. The importance of

More information

EXISTING COMPREHENSIVE PLAN

EXISTING COMPREHENSIVE PLAN EXISTING COMPREHENSIVE PLAN Town Center Land Use Element: V. LAND USE POLICIES Town Center Mercer Island's business district vision as described in "Your Mercer Island Citizen-Designed Downtown" was an

More information

WEST LOOP DESIGN GUIDELINES CHECKLIST

WEST LOOP DESIGN GUIDELINES CHECKLIST WEST LOOP DESIGN GUIDELINES CHECKLIST Section 1.0 General Strategies 1.1 DESIGN EXCELLENCE: ENCOURAGE HIGH QUALITY AND INNOVATIVE DESIGN OF NEW BUILDINGS WITHIN THE WEST LOOP WITHOUT BEING PRESCRIPTIVE

More information

Downtown Streetscape Manual & Built Form Standards

Downtown Streetscape Manual & Built Form Standards City of Guelph Downtown Streetscape Manual & Built Form Standards July 2014 Prepared by Brook McIlroy Inc. in association with Unterman McPhail Associates and McCormick Rankin Inc. City of Guelph Downtown

More information

Technical Appendix L, University Community Plan Town Center

Technical Appendix L, University Community Plan Town Center Technical Appendix L, University Community Plan Town Center Table of Contents L.1 Executive Summary L.2 Merced County University Community Plan, 2004 Findings L.2.1 Visioning L.2.2 UCP Goals, Objectives

More information

Arlington, Virginia is a worldclass

Arlington, Virginia is a worldclass EXECUTIVE S U M M A RY Arlington maintains a rich variety of stable neighborhoods, quality schools and enlightened land use policies, and received the Environmental Protection Agency s highest award for

More information

WESTERN ILLINOIS UNIVERSITY

WESTERN ILLINOIS UNIVERSITY WESTERN ILLINOIS UNIVERSITY Quad Cities Riverfront Campus Master Plan March 1, 2006 Preliminary Master Plan Total Site Build Out Western Illinois University Quad Cities Municipal Park Mississippi River

More information

Cit of Kitchener Ur 6 an Design Manual PARTA. Desi n for _--::

Cit of Kitchener Ur 6 an Design Manual PARTA. Desi n for _--:: Cit of Kitchener Ur 6 an Design Manual Date PARTA Year ) Desi n for k Nodes Corridors _--:: Section Page 01 of 12 2 INTRODUCTION Purpose & Application Nodes and Corridors have been identified as key intensification

More information

Future Five. Design/ Development Guidelines. January 2008 Amended June 08 per City Council motion

Future Five. Design/ Development Guidelines. January 2008 Amended June 08 per City Council motion Future Five Design/ Development Guidelines January 2008 Amended June 08 per City Council motion 5-Points Design Guidelines Table of Contents I. Introduction 3 II. Area boundaries 4 III. Review Process

More information

10 February CAMPUS MASTER PLAN UPDATE Focus Group - Landscape & Hensel Park

10 February CAMPUS MASTER PLAN UPDATE Focus Group - Landscape & Hensel Park 10 February 2016 CAMPUS MASTER PLAN UPDATE Focus Group - Landscape & Hensel Park AGENDA Introductions Planning Scope The 2004 Campus Plan & Survey Observations 2004 Landscape Plan SWOT Exercise Analysis

More information

There are five comprehensive goals that inform the Urban Design element at FIU. They are:

There are five comprehensive goals that inform the Urban Design element at FIU. They are: 3.0 URBAN DESIGN ELEMENT This Comprehensive Master Plan Update reflects the University s commitment to the refinement and extension of the base concepts earlier master planning efforts have created. FIU

More information

Sign System Recommendations

Sign System Recommendations 4.1 Sign System Recommendations 4.2 Recommended sign types required for a complete wayfinding system on the TCNJ campus are described below. Detailed sign messages and their typical locations are included

More information