City of Greater Sudbury Subwatershed Study Program. Public Open House Tom Davis Square, C-13 A and B March 9, 2016
|
|
- Geoffrey Andrews
- 5 years ago
- Views:
Transcription
1 City of Greater Sudbury Subwatershed Study Program Public Open House Tom Davis Square, C-13 A and B March 9, 2016
2 Welcome to the City of Greater Sudbury Subwatershed Study Program Public Open House Tom Davis Square, C-13 A and B March 9, 2016 Please sign in on the sheet provided, then feel free to walk around and view the displays. If you have any questions, our representatives will be pleased to discuss the project with you. Comment sheets are provided for those who wish to provide comments in writing. Please either place your completed sheets in the Comment Box or mail / fax them to contact information below by March 18, Thank-you for your involvement in this project. For additional information, please contact: Paul Javor, MASc, P.Eng. Drainage Engineer, Roads and Transportation Services City of Greater Sudbury 200 Brady St. Sudbury, ON P3A 5P3 Phone: ext Fax: Paul.Javor@greatersudbury.ca
3 What is a Subwatershed? A subwatershed is an area of land divided by natural features, where all water naturally drains to a particular watercourse or body of water. Subwatersheds can be further divided into smaller subwatersheds for study. Junction Creek and Ramsey Lake Subwatersheds
4 Greater Sudbury Subwatersheds Place subwatershed map from stormwater background study on this slide
5 What is a Subwatershed Study? The intent of a Subwatershed Study is to prepare goal-oriented strategies to support the City s Official Plan and identify the responsible management strategies within a Sub-watershed area with the primary focus of protecting natural ecosystem function(s); The subwatershed study will inventory and categorize the key natural features within the Subwatershed area for the purposes of establishing a baseline environmental conditions; The management strategies of these key natural features includes establishing targets for protection and maintaining key ecological function, and developing strategies to meet these targets. Subwatershed studies investigate the cumulative effects of changes in land use, identify areas of risk, and make recommendations on areas for improvement; These studies provide input on natural system and focus largely on surface water, ground water, aquatic and terrestrial habitat resources; Subwatershed studies do not influence land use designations of the Official Plan or prohibit development; In summary, they are comprehensive/high-level studies of managing surface and ground water systems through engineering and landuse planning that is based on ecology and wise resource management.
6 Subwatershed Study Process The Studies will follow the Best Management Practices for subwatershed studies identified by Conservation Ontario; These Studies will also follow the Schedule B Master Planning process under the Municipal Class Environmental Assessment process as prescribed by the Province of Ontario; and, Public Consultation will be sought throughout the process. Consultation with Stakeholders, the Public and Agencies Scope (we are here) Characterize the System Set goals, Objective and Working targets Develop Management Alternatives Evaluate Management Alternation Select Preferred Alternative Develop Implementation and Monitoring Plans Finalize Targets Subwatershed Study Process
7 Subwatershed Study Objectives Identify stormwater best management practices within the subwatershed that will preserve or enhance the quality of the runoff from the City s drainage systems. Examples: Stormwater Management Ponds Treatment Facilities Low Impact Development (LID) techniques Vortec Treatment Unit Schematic and Interior of Nepahwin Unit Enhanced Swale (photo from Toronto Regional Conservation Authority LID Guide) used in Valley areas
8 Subwatershed Study Objectives Identify stormwater best management practices within the subwatershed that will manage excessive stormwater runoff and minimizing the impacts from flooding. Examples: Stormwater Management Ponds Low Impact Development techniques Lavallee Stormwater Quality and Quantity Pond and Channel Improvements, Chelmsford
9 Subwatershed Study Objectives To complement the Official Plan and Zoning By-law by providing an additional lens to assist with the review and assessment of future development applications in the subwatershed area. Examples: Policies By-Laws Development Application Comments Runoff Quality standards (Total Suspended Solids, nutrients, etc.) Runoff Quantity standards St. Agnes Street Stormwater Quality and Quantity Pond, Azilda
10 Subwatershed Study Objectives Identify specific projects and develop an implementation plan that will manage excessive stormwater runoff, minimize the impacts from flooding and preserve or enhance the quality of the runoff from the City s drainage systems within the subwatershed. This objective will be fulfilled as part of the Schedule B Master Planning process under the Municipal Class Environmental Assessment.
11 How You Can be Involved! At this stage we are gathering input from agencies and the public that will help form the Terms of Reference for the studies of all subwatersheds identified in the 2006 Stormwater Background Study to the Official Plan. We want to know if there are certain issues that you think should be identified Is there information that you think needs to be collected to help inform decisions as the studies progress Please complete one of the Comment Forms so we have a record of your concern. Ensure you have signed in so that you will receive future correspondence as the projects progress.
12 The Next Steps... The City will develop a Terms of Reference (ToR) outlining the study requirements for inclusion in the Request for Proposal which will be used to obtain bids from Consulting Teams. The City will bring a report to Council to affirm subwatershed study priority Comments received from this Open House will be collected by the City to inform the development of the ToR and they will be provided to the successful consultant for the development of the subwatershed study for consideration Once awarded, the subwatershed studies are anticipated to require between months to complete depending on the complexity of the individual projects. Thank you for your participation!
Vaughan Metropolitan Centre (VMC) Black Creek Renewal CLASS ENVIRONMENTAL ASSESSMENT
PUBLIC INFORMATION CENTRE Vaughan Metropolitan Centre (VMC) Black Creek Renewal Wednesday, May 10, 2017 6:00 p.m. to 8:00 p.m. Add photo Project Management, Environmental Assessment, Stormwater Management
More informationTRCA Roles and Responsibilities in Planning and Development
TRCA Roles and Responsibilities in Planning and Development Regional Watershed Alliance November 14, 2018 Laurie Nelson, MCIP, RPP Associate Director, Planning and Policy Outline Roles and Legislation
More informationBostwick Road. Municipal Class Environmental Assessment. October 13, City of London. Bostwick Road Municipal Class Environmental Assessment
Bostwick Road Municipal Class Environmental Assessment October 13, 2016 Welcome! Welcome to the first Public Information Centre for the Bostwick Road Municipal Class Environmental Assessment. Representatives
More informationInfrastructure, Development and Enterprise Services. Natural Heritage Action Plan (NHAP) Project Initiation
Staff Report To Service Area Committee of the Whole Infrastructure, Development and Enterprise Services Date Monday, March 6, 2017 Subject Natural Heritage Action Plan (NHAP) Project Initiation Report
More informationArlington County Watershed Retrofits. Greg Hoffmann Center for Watershed Protection
Arlington County Watershed Retrofits Greg Hoffmann Center for Watershed Protection March 18, 2010 About the Center for Watershed Protection Non-profit 501(c)3, non-advocacy organization Work with watershed
More informationStormwater Retrofitting: The Art of Opportunity. Presented by the Center for Watershed Protection
Stormwater Retrofitting: The Art of Opportunity Presented by the Center for Watershed Protection What Are Stormwater Retrofits? Retrofits are stormwater management measures inserted in an urban or ultra-urban
More informationMaster Environmental Servicing Plan & Secondary Plan
East Side Lands Stage 2 1 Master Environmental Servicing Plan & Secondary Plan Public Information Centre #1 June 16, 2016 Welcome! Today s Agenda Please sign in at the front desk. 5:30 pm 6:30 pm: Open
More informationCentral Lake Ontario Conservation Conservation Lands Master Plan
Conservation Lands Master Plan Top 13 Frequently Asked Questions 1. What are conservation lands? Where are these conservation lands located in the Central Lake Ontario Conservation watershed? Conservation
More informationWILLIAM STREET STORM SEWER OUTFALL. PUBLIC INFORMATION CENTRE March 23, 2017
WILLIAM STREET STORM SEWER OUTFALL Municipal Class Environmental Assessment PUBLIC INFORMATION CENTRE March 23, 2017 ACCESSIBILITY Under the Accessibility Standards 2015 for Customer Service Regulation
More informationLeduc Industrial Outline Plan SE W4
Leduc Industrial Outline Plan SE 1-50-25-W4 Within the North Leduc Industrial ASP Prepared for: Leduc Energy Park Ltd. Prepared by: Stantec Consulting Ltd. File No. 1161 104655 V5 Table of Contents 1.0
More informationAshbridges Bay Erosion and Sediment Control Project
Ashbridges Bay Erosion and Sediment Control Project Project Brief Overview Toronto and Region Conservation Authority, in partnership with the City of Toronto, intends to carry out remedial erosion control
More informationPublic Information Centre # 2 Coronation Park Drainage Improvements Town of Oakville Municipal Class Environmental Assessment
November 26, 2014 Public Information Centre # 2 Coronation Park Drainage Improvements Town of Oakville Municipal Class Environmental Assessment Study Area & Drainage System Legend Coronation Project Park
More informationBLACK/HARMONY/FAREWELL CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 5 IMPERVIOUS SURFACES
BLACK/HARMONY/FAREWELL CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 5 IMPERVIOUS SURFACES Draft November 2009 TABLE OF CONTENTS 1.0 INTRODUCTION... 3 2.0 STUDY AREA AND SCOPE... 4 3.0 METHODOLOGY...
More informationCOMMUNITY SUSTAINABILITY AND ENVIRONMENTAL MASTER PLAN IMPLEMENTATION UPDATE
Attachment 1 COMMUNITY SUSTAINABILITY AND ENVIRONMENTAL MASTER PLAN IMPLEMENTATION UPDATE Priorities and Key Initiatives Committee May 2013 Page E-1 How we grow Goal 2: To ensure sustainable development
More informationThe protection of the agricultural resources of the Province;
PART II INTRODUCTION An Official Plan is a policy document, which is intended to serve as the basis for making land use decisions and managing change in any municipality in Ontario. According to the Planning
More informationSouthwest Transitway Extension Baseline Road to Norice Street. Environmental Assessment Minor Modification Report
Southwest Transitway Extension Baseline Road to Norice Street Environmental Assessment Minor Modification Report September 2009 Environmental Assessment Minor Modification Report Southwest Transitway
More informationEdgeley Pond + Park Public Meeting
Edgeley Pond + Park Public Meeting February 21, 2017 Purpose of the meeting This Public Meeting is an opportunity for you to review the project background, process and provide input. City of Vaughan staff
More informationElfrida Growth Area Study
Elfrida Growth Area Study Public Information Centre #2 December 6, 2017 6:00-8:30 pm PLANNING & ECONOMIC DEVELOPMENT DEPARTMENT Purpose of the Study The Elfrida Area has been identified as the preferred
More informationBostwick Road. Municipal Class Environmental Assessment. Public Information Centre #2 June 14, City of London
Bostwick Road Municipal Class Environmental Assessment Public Information Centre #2 June 14, 2017 Welcome! Welcome to the 2 nd Public Information Centre for the. Representatives from the and the consulting
More informationCity of Kitchener Integrated Stormwater Management Master Plan (ISWM-MP) Public Open House No. 2 April 28, 2016
City of Kitchener Integrated Stormwater Management Master Plan (ISWM-MP) Public Open House No. 2 April 28, 2016 Open House Format 20-30 min presentation Facilitated questions and answer session following
More informationRainfall Capture and Green Subdivision Design:
Rainfall Capture and Green Subdivision Design: Applying the Water Balance Model Kim Stephens, MEng, PEng, Project Coordinator Inter-Governmental Partnership from Stormwater Management to Rainwater Management
More informationOutline. Tampa Bay. Using Social Marketing Research to Foster Behavior Change Among Residents on Stormwater Ponds
Using Social Marketing Research to Foster Behavior Change Among Residents on Stormwater Ponds Paul Monaghan Emily Ott Maria Morera UF/IFAS Urban Landscape Summit Outline 1. Urban stormwater and water quality
More information4. What are the goals of the Kawarthas, Naturally Connected project? 7. What are watersheds and why are they being used as the project boundaries?
Frequently Asked Questions (FAQs) 1. What are Natural Heritage Systems (NHS)? 2. Why are they important? 3. Which areas of the province have undertaken NHS projects? 4. What are the goals of the Kawarthas,
More informationTORONTO TRANSIT COMMISSION AND THE REGIONAL MUNICIPALITY OF YORK
TORONTO TRANSIT COMMISSION AND THE REGIONAL MUNICIPALITY OF YORK NOTICE OF PREPARATION OF AN ADDENDUM REPORT TO THE HIGHWAY 7 CORRIDOR AND VAUGHAN NORTH-SOUTH LINK ENVIRONMENTAL ASSESSMENT & RESPONSE TO
More informationc. DTAH Toronto Complete Streets Guidelines
c. DTAH Toronto Complete Streets Guidelines 164 166 C.1 Project Delivery Process 168 C.5 This section provides a summary of the overarching process for delivering street projects in Toronto. The conclusion
More informationDraft Rhode Island Stormwater Design and Installation Standards Manual
Draft Rhode Island Stormwater Design and Installation Standards Manual Summary The May 2009 Public Review Draft version of the RI Stormwater Design and Installation Standards Manual consists of approximately
More informationCaledon Villas Corp. c/o Mr. John Spina 55 Blue Willow Drive Woodbridge, ON L4L 9E8 May 14, Floodplain Characteristics, Old Church Road
Caledon Villas Corp. c/o Mr. John Spina 55 Blue Willow Drive Woodbridge, ON L4L 9E8 May 14, 2013 Re: Floodplain Characteristics, Old Church Road This letter serves to confirm that I, Linda Sober, have
More informationElevated Water Storage Facility and Pumping Station Municipal Class EA for Pressure District 7: PIC # 1 Summary
Memorandum DATE: March 14, 2018 TO: FROM: CC: OUR REF.#: SUBJECT: Winston Wang, M.A.Sc., P.Eng Project Manager, City of Hamilton Jennifer Whittard, B.E.S., PMP Shelley Kuan, Jessica Mollo WM16-0435 Elevated
More informationCONSULTING SERVICES FOR THE WHITEBELT VISIONING EXERCISE ADDENDUM TO THE GTA WEST LAND USE STUDY WORK PROGRAM
CONSULTING SERVICES FOR THE WHITEBELT VISIONING EXERCISE ADDENDUM TO THE GTA WEST LAND USE STUDY 1. Introduction WORK PROGRAM The Town of Caledon is a large, local municipality located in the Greater Toronto
More informationStormwater Manuals - The Good, the Bad and the Ugly. David J. Hirschman Center for Watershed Protection Getting in Step with Phase II Charleston, WV
Stormwater Manuals - The Good, the Bad and the Ugly David J. Hirschman Center for Watershed Protection Getting in Step with Phase II Charleston, WV Manual Overview Overview Review of State & Local Manuals
More informationWEFTEC.06. ** City of Caldwell, Idaho
COST-BENEFIT ANALYSIS OF URBAN STORMWATER RETROFITS AND STREAM DAYLIGHTING USING LOW IMPACT DEVELOPMENT TECHNOLOGIES Sherrill Doran*, Dennis Cannon** * CH2M HILL, 322 East Front Street, Suite 200 Boise,
More information3 Development Process 3.1 Stage One page Stage Two page Stage Three page CENTRAL PICKERING DEVELOPMENT PLAN
3 Development Process 3.1 Stage One page 24 3.2 Stage Two page 25 3.3 Stage Three page 28 22 CENTRAL PICKERING DEVELOPMENT PLAN The Central Pickering Development Plan establishes the key elements of new
More informationInform you of the purpose and scope of the study for PTH 100 and a proposed future St. Norbert Bypass;
WELCOME The intent of today s Open House is to: Inform you of the purpose and scope of the study for PTH 100 and a proposed future St. Norbert Bypass; Review highway crossing locations, future access closures
More information1 Introduction. Chapter. In this chapter:
Chapter 1 Introduction In this chapter: 1.1 A Snapshot of the Region 1.2 Towards a Sustainable Region 1.3 The Provincial Context 1.4 Purpose and Organization The Regional Municipality of York Official
More informationPDS June 1, 2016 Page 1. Planning and Development Committee. MEETING DATE: Wednesday, June 01, 2016
Page 1 REPORT TO: Planning and Development Committee MEETING DATE: Wednesday, June 01, 2016 SUBJECT: ROPA 12: Project Initiation Report Regional Official Plan Amendment (ROPA # 12) Watercourse Policies
More informationTERRESTRIAL NATURAL HERITAGE SYSTEM STRATEGY APPENDIX F: MODEL POLICIES FOR THE IMPLEMENTATION OF THE TARGET TERRESTRIAL NATURAL HERITAGE SYSTEM
TERRESTRIAL NATURAL HERITAGE SYSTEM STRATEGY APPENDIX F: MODEL POLICIES FOR THE IMPLEMENTATION OF THE TARGET TERRESTRIAL NATURAL HERITAGE SYSTEM C H A P T E R 1 M O D E L P O L I C I E S F O R I M P L
More informationThe Development of Riparian Stream Buffers in Greensboro, NC
The Development of Riparian Stream Buffers in Greensboro, NC Why our stream banks have grown up? Presented by: Peter Schneider, Water Quality Supervisor City of Greensboro Stormwater Management Division
More informationAMENDMENT NO. 30 TO THE OFFICIAL PLAN OF THE TOWN OF MILTON
AMENDMENT NO. 30 TO THE OFFICIAL PLAN OF THE TOWN OF MILTON Subject: Boyne Survey Secondary Plan and Related Official Plan Amendments The following text and schedules constitute Amendment No. 30 to the
More informationMAYFIELD WEST SECONDARY PLAN PHASE 2
MAYFIELD WEST SECONDARY PLAN PHASE 2 Council Information Workshop February 16, 2010 Draft Preferred Land Use Plan TOWN OF CALEDON PLANNING & DEVELOPMENT DEPARTMENT Workshop Agenda TOWN OF CALEDON 1. Welcome
More informationImplementing Low Impact Development (LID) in the Lake Simcoe Watershed: Progress, lessons learned and applicability to Muskoka watershed
Implementing Low Impact Development (LID) in the Lake Simcoe Watershed: Progress, lessons learned and applicability to Muskoka watershed Ben Longstaff GM, Integrated Watershed Management September 15,
More informationLiftlock Secondary Plan and Proposed Draft Plan of Subdivision 15T Public Open House. June 21, /21/ City of Peterborough 1
Liftlock Secondary Plan and Proposed Draft Plan of Subdivision 15T-17501 Public Open House June 21, 2017 6/21/2017 1 City of Peterborough 1 Tonight s Goal To foster constructive conversation regarding
More informationAPPENDIX L3. Table of Contents. SWP EA Information Sheets
E N V I R O N M E N T A L A S S E S S M E N T APPENDIX L3 SWP EA Information Sheets Table of Contents EA Info Sheet 1... L3-1 EA Info Sheet 2... L3-3 EA Info Sheet 3... L3-5 EA Info Sheet 4... L3-7 SCARBOROUGH
More informationHAZARD MITIGATION GOALS AND OBJECTIVES
SEWRPC Community Assistance Planning Report No. 282, 2nd Edition CITY OF MILWAUKEE ALL HAZARDS MITIGATION PLAN UPDATE Chapter IV HAZARD MITIGATION GOALS AND OBJECTIVES [NOTE: Throughout this plan update
More informationPasco County Watershed Meeting for Flood Impacted Areas Port Richey Watershed
Pasco County Watershed Meeting for Flood Impacted Areas March 15, 2017 Regency Park Library, 9701 Little Road, New Port Richey, Pasco County The following is a summary of the meeting held on March 15,
More informationRed Hill Valley Project More Than A Road October 16, 2006
Red Hill Valley Project Presented By: More Than A Road October 16, 2006 September, 2007 Gerry Davis, C.M.A., Senior Director, Capital Planning and Implementation Division Public Works Department City of
More informationTHE CORPORATION OF THE TOWN OF OAKVILLE BY-LAW NUMBER
THE CORPORATION OF THE TOWN OF OAKVILLE BY-LAW NUMBER 20012-08530 A by-law to adopt an amendment to the Official Plan of the Oakville Planning Area (Official Plan Amendment 198) Land North of Dundas Street.
More informationConstructed Stormwater Wetlands
Types: Shallow Marsh System, Basin/Wetland System, Extended Detention Wetland, Pocket Wetland F. X. Browne, Inc., Lansdale, PA http://www.fxbrowne.com/html/fxb%20wetland%20cs/fxbi_constructed%20wetland_cs.htm
More informationGreen Infrastructure
New York State Water Resources Institute Green Infrastructure in the Hudson Valley May 17, 2011 Emily Vail Hudson River Estuary Program New York State Department of Environmental Conservation In cooperation
More informationMonitoring for Ecological Integrity and State of the Parks Reporting
Monitoring for Ecological Integrity and State of the Parks Reporting Donald McLennan 1 and Paul Zorn 1 National Monitoring Biologist Parks Canada, Ecological Integrity Branch 25 Eddy Street Gatineau, Québec,
More informationCitywide Integrated Stormwater Management Plan (ISMP) DRAFT ACTION PLAN REVIEW Public Consultation November 16 th, 2016
Citywide Integrated Stormwater Management Plan (ISMP) DRAFT ACTION PLAN REVIEW Public Consultation November 16 th, 2016 1 Agenda DRAFT ACTION PLAN REVIEW Public Consultation Time 6:00 6:05 6:05 6:20 6:20
More informationDesign Around Waterways and Wetlands
Design Around Waterways and Wetlands NL Green Economy Conference Newleef-2014 NEIA, St. John s, NL October 9-10 th, 2014 Wade Lewis Amherst, Nova Scotia, w_lewis@ducks.ca DUC conserves, restores and manages
More informationCITY COUNCIL AGENDA REPORT
CITY COUNCIL AGENDA REPORT Subject: DESIGNATED FLOOD LINE CARROT CREEK Recommendation(s) That Administration bring forward a Land Use Bylaw amendment in October 2014 establishing the Designated Flood Line
More information3-2 Environmental Systems
3-2 Environmental Systems 3.0 ENVIRONMENTAL SYSTEMS CONTENTS 3.1 GREENWAY SYSTEM 3.1.1 General Policies 3.1.2 Natural Heritage Network 3.1.3 Natural Heritage Network Enhancement Lands 3.1.4 Rouge Watershed
More informationFloodplain Management Plan 2016 Progress Report
PREPARED FOR: Borough of Point Pleasant Beach 416 New Jersey Ave. Point Pleasant Beach, NJ 08742 (732) 892-1118 http://www.pointpleasantbeach.org/ PREPARED BY: T&M Associates 11 Tindall Road Middletown,
More informationCherry Beach Shoreline Protection Infrastructure Conceptual Design and Class EA
Welcome Cherry Beach Shoreline Protection Infrastructure Conceptual Design and Class EA May 3, 2012 Study Area Cherry Beach neighbourhood is located in lower Stoney Creek on Lake Ontario, east of Millen
More information3/7/2013. Compliance & Sustainability
Overview www.kieser associates.com Celebrating 20 Years of Excellence in Environmental Science & Engineering WMU Arcadia Creek Stormwater Treatment and Floodplain Enhancement Project DEQ #2008 0018 and
More informationRoute Planning and Environmental Assessment Study Highway 17 Four-Laning from Sudbury to Markstay GWP
Route Planning and Environmental Assessment Study Highway 17 Four-Laning from Sudbury to Markstay GWP 5031-09-00 Presentation to City of Greater Sudbury Council: January 26, 2011 1 Roch Pilon, P.Eng. Head,
More informationUSF System Campus Master Plan Updates Goals, Objectives and Policies
2015-2025 USF System Campus Master Plan Updates Goals, Objectives and Policies Tampa Goals, Objectives, and Policies Table of Contents Executive Summary 2015 2025 USF Campus Master Plan Update Introduction
More informationREQUEST FOR PROPOSAL RFP NO. PS CONSULTANT FOR JOHN HENDRY PARK MASTER PLAN QUESTIONS AND ANSWERS NO. 1
FINANCIAL SERVICES GROUP REQUEST FOR PROPOSAL RFP NO. PS20130495 CONSULTANT FOR JOHN HENDRY PARK MASTER PLAN QUESTIONS AND ANSWERS NO. 1 ISSUED ON: July 19, 2013 Q1 Will the 1978 Park Concept Plan and
More informationBrampton. Secondary Plan. Review. Bram West. A New Direction in Planning & Public Consultation
Brampton Bram West Secondary Plan Review A New Direction in Planning & Public Consultation Introduction The Bram West Secondary Plan Review offers an important opportunity for the community to define a
More informationPSLS Surveyors' Conference Workshop Information Form Workshop Number: (leave blank if unknown) Hours: Workshop Title: Workshop Description: Suggested Speaker(s), affiliation/contact information 1. 2. 3.
More informationFinger Lakes National Forest. Backbone Horse Camp Water Hydrant Project
United States Department of Agriculture Forest Service February 2014 Backbone Horse Camp Water Hydrant Project Scoping Information Hector Ranger District Town of Lodi, Seneca County, New York For Information
More informationWest London Dyke, April 1947 Flood. Forks of the Thames, July 2000 Flood. Source: UTRCA
This Public Information Centre is the 1 st of 2. Its purpose is to inform the public and to receive input with regards to the West London Dyke Master Repair Plan. The following panels describe the history,
More informationAre Trees Green Infrastructure? Municipal policy and green infrastructure definitions
Are Trees Green Infrastructure? Municipal policy and green infrastructure definitions TENLEY CONWAY UNIVERSITY OF TORONTO MISSISSAUGA AAG 2018 Green Infrastructure and Urban Residents Project A green infrastructure
More informationLID Performance and Risk Assessment Program
LID Performance and Risk Assessment Program Jennifer Dougherty, P,Eng Manager, Water Quality Protection Credit Valley Conservation Authority Outline CVC Stormwater Monitoring Strategy Monitoring Objectives
More informationPopulation, Housing, and Employment Analysis
Population, Housing, and Employment Analysis Reviewed housing development patterns, trends, needs, affordability, and estimated employment and population capacity at full build out. Total 28,200 people
More informationWorking Group Meeting
April 4,, 2017 Parks Operations Bldg Working Group Meeting Arts Districts Overview Stormwater/RPA/Stream Considerations First Principles Agenda 7:00pm 7:05pm 7:10pm 7:40pm 8:30pm 9:40pm 9:45pm Welcome
More informationOFFICIAL PLAN FOR THE TOWN OF NEW TECUMSETH
OFFICIAL PLAN FOR THE TOWN OF NEW TECUMSETH Approved by Simcoe County- March 10, 2010 TABLE OF CONTENTS PAGE# 1.0 TITLE AND COMPONENTS... 5 2.0 INTRODUCTION... 6 2.1 Purpose... 6 2.2 Organization of the
More informationStormwater Master Plan Update. City Council Briefing January 8, 2019
Stormwater Master Plan Update City Council Briefing January 8, 2019 1 Stormwater Master Plan Update January 8, 2019 Agenda Background for Update Stormwater Modeling and Calibration Visualizations of Results
More informationGVSU Sustainable Storm Water Initiative
GVSU Sustainable Storm Water Initiative MWEA Watershed Seminar Bath, MI December 5, 2013 Dr. Peter J. Wampler Talk Road Map Brief Geomorphic History of the Grand River and Grand River Ravines Historic
More informationBetter Cycling. The City will update the cycling master plan (London ON Bikes) based on the approved BRT network.
Better Cycling Dedicated bike facilities will be constructed along BRT corridors where space is available. Nearby bike routes will also be upgraded to ensure a complete network is available for cyclists.
More informationPlanning Services Public Meeting Report
Planning Services Public Meeting Report If this information is required in an alternate accessible format, please contact the Accessibility Coordinator at 905-623-3379 ext. 2131. Report To: Planning and
More informationHeritage Road Improvements from Steeles Avenue to Rivermont Road
The Corporation of the City of Brampton Heritage Road Improvements from Steeles Avenue to Rivermont Road Class Environmental Assessment Study (Schedule C) September 19, 2013 The Corporation of the City
More informationBay County RESTORE Act Direct Component Proposals The project will encompass all of Unincorporated Bay County as a whole.
Proj # Bay PRP 2014-016 Project Name Bay County Master Plan and Capital Improvement Strategic Plan Update Project Proposer, affiliation, web site Project Description Proj. Size (acres) Economic Environmental
More informationCITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF DECEMBER 10, 2013
Item 1, Report No. 55, of the Committee of the Whole (Working Session), which was adopted without amendment by the Council of the City of Vaughan on December 10, 2013. Regional Councillor Di Biase declared
More informationFeasibility Analysis for Expansion of the Provincial Greenbelt Plan Area into Mississauga
Feasibility Analysis for Expansion of the Provincial Greenbelt Plan Area into Mississauga November 8, 2013 Natural Heritage and Urban Forest Strategy: Draft Discussion Paper #3: Table of Contents 1.0 Introduction...
More informationToronto Complete Streets Guidelines
Toronto Complete Streets Guidelines 108 110 7.1 Green Infrastructure Design Principles 112 7.2 Context-Sensitive Green Streets 114 7.3 Key Green Street Elements Green infrastructure refers to natural and
More informationTOWN OF WHITBY REPORT RECOMMENDATION REPORT
TOWN OF WHITBY REPORT RECOMMENDATION REPORT REPORT TO: Council REPORT NO: PL 95-09 DATE OF MEETING: October 13, 2009 PREPARED BY: Planning/Public Works Joint Report FILE NO(S): N/A LOCATION: N/A REPORT
More informationNORTHEAST RIVER CROSSING FUNCTIONAL PLANNING STUDY
WELCOME Northeast River Crossing Functional Planning Study Phase 2 Public Meeting 4 to 8 PM Informal drop-in format and discussion tables Meeting Purpose Introduce the Northeast River Crossing Functional
More informationPeel Region. Greenbelt Plan Conformity. Plan Review. Background & Approach
Peel Region Plan Review Background & Approach Greenbelt Plan Conformity November 2008 Page 2 of 13 2 COMMENT SHEET Region of Peel Greenbelt Plan Policy Review This comment sheet is to be used to provide
More informationTO: Mayor & Council DATE: April 12, The Planning and Development Department and the Engineering Department recommend that Council:
CORPORATE REPORT NO: R080 COUNCIL DATE: April 12, 2010 REGULAR COUNCIL TO: Mayor & Council DATE: April 12, 2010 FROM: SUBJECT: General Manager, Planning and Development General Manager, Engineering Neighbourhood
More informationKeele Campus Storm Drainage. Presented by Mark Hagesteijn September 24, 2013
Keele Campus Storm Drainage Presented by Mark Hagesteijn September 24, 2013 1 Presentation Overview Urbanization Impact on the Hydrologic Cycle Why Do We Manage Stormwater? Typical Stormwater Management
More informationGreen Infrastructure Basics
1 Green Infrastructure Basics Emily Vail Hudson River Estuary Program NYS Department of Environmental Conservation New York State Water Resources Institute at Cornell University December 8, 2016 2 Presentation
More informationPlanning and Growth Management Committee
STAFF REPORT ACTION REQUIRED By-law to Require and Govern the Construction of Green Roofs in Toronto Date: October 29, 2008 To: From: Wards: Reference Number: Planning and Growth Management Committee Chief
More informationAn Introduction to the Far North Land Use Strategy
An Introduction to the Far North Land Use Strategy December, 2013 Ministry of Natural Resources Table of Contents PREFACE... 3 About the Far North... 3 Evolution of Land Use Planning in the Far North...
More informationCommunity LID Workgroup Issue Paper #6
Community LID Workgroup Issue Paper #6 Topic: Hard and Impervious Surface Coverage Limits Objective: Minimize the amount of hard and impervious surfaces in developments to allow more stormwater to infiltrate
More informationPORT UNION VILLAGE COMMUNITY SECONDARY PLAN
4 PORT UNION VILLAGE COMMUNITY SECONDARY PLAN 4. PORT UNION VILLAGE COMMUNITY SECONDARY PLAN The following policies and principles apply to the area herein referred to as Port Union Village, as outlined
More informationSOUTH FOX MEADOW STORMWATER IMPROVEMENT PROJECT
VILLAGE OF SCARSDALE WESTCHESTER COUNTY, NEW YORK COMPREHENSIVE STORM WATER MANAGEMENT SOUTH FOX MEADOW STORMWATER IMPROVEMENT PROJECT In association with WESTCHESTER COUNTY FLOOD MITIGATION PROGRAM Rob
More informationGreenspace Master Plan
Greenspace Master Plan Strategies for Ottawa's Urban Greenspaces August 2006 ottawa.ca Greenspace Master Plan Strategies for Ottawa s Urban Greenspaces Publication: 4-01 City of Ottawa, 2006 Aussi disponible
More informationLower Don River West Remedial Flood Protection Project TABLE OF CONTENTS. Page. Executive Summary
TABLE OF CONTENTS Page Executive Summary 1.0 INTRODUCTION...1-1 1.1 Purpose of the Undertaking...1-1 1.2 Study Area Description...1-1 1.3 Description of the Undertaking...1-1 1.4 Rationale for the Undertaking...1-2
More informationDeer Creek Watershed Stakeholders Committee
Deer Creek Watershed Stakeholders Committee Stakeholder Partners East West Gateway Council of Governments Great Rivers Greenway District Local Municipalities Metropolitan St. Louis Sewer District Missouri
More informationNatural Shoreline Landscapes on Michigan Inland Lakes. Introduction. Workshop for Property Owners. Photo by Jane Herbert
Natural Shoreline Landscapes on Michigan Inland Lakes Workshop for Property Owners Introduction Photo by Jane Herbert MSU is an affirmative action, equalopportunity employer. Michigan State University
More informationClimate Smart Communities Green Infrastructure Case Studies
New York State Water Resources Institute Climate Smart Communities Green Infrastructure Case Studies Emily Vail Hudson River Estuary Program NYS Department of Environmental Conservation Cornell University
More informationOFFICIAL COMMUNITY PLANS (OCPs) AND ZONING BYLAWS (ZBs): PLANNING FOR THE FUTURE
OFFICIAL COMMUNITY PLANS (OCPs) AND ZONING BYLAWS (ZBs): PLANNING FOR THE FUTURE Official Community Plan Workshop January 20, 2016 Frontier, SK SARM Community Planning Services SARM the voice of rural
More informationIntroduction. Public Information Package. Project website. Overview. Class Environmental Assessment Process
1 Introduction Public Information Package Baseline Road Extension between Lambs Road and Bennett Road, Bowmanville Schedule B Municipal Class Environmental Assessment November 6, 2017 Overview The purpose
More informationMunicipal Class EA Study Public Information Centre No. 1 December 13, :00 pm 7:00 pm. Please sign in so we can keep you updated on this study
Reconstruction of Regional Road 45 (Creek Road) Between Regional Road 27 (River Road) and Regional Road 63 (Canborough Road) in the Township of Wainfleet Municipal Class EA Study Public Information Centre
More informationProject Background, Context & Issues Project Objectives City s perspective Resident s perspective Design details
Chris Denich, MSc. Project Background, Context & Issues Project Objectives City s perspective Resident s perspective Design details Project site is located in the Lakeview Neighbourhood within the City
More informationIntention to Designate under Part IV, Section 29 of the Ontario Heritage Act 844 Don Mills Road and 1150 Eglinton Avenue East
STAFF REPORT ACTION REQUIRED Intention to Designate under Part IV, Section 29 of the Ontario Heritage Act 844 Don Mills Road and 1150 Eglinton Avenue East Date: September 7, 2016 To: From: Toronto Preservation
More informationJuly 9, Adèle Labbé Environmental Planner City of Guelph 1 Carden Street Guelph, Ontario N1H 3A1. Dear Ms. Labbé.
July 9, 2014 Adèle Labbé Environmental Planner City of Guelph 1 Carden Street Guelph, Ontario N1H 3A1 Dear Ms. Labbé. Re: 132 Clair Road West EIS Terms of Reference North-South Environmental Inc. (hereafter,
More informationSECTION 2 - GENERAL POLICIES
SECTION 2 - GENERAL POLICIES 2.1 General Development a) Goals i) To accommodate the population and development anticipated for the Town in the planning period. ii) To provide the necessary services and