Masterplan for Active and Sustainable Transport Assessment: A5 New Buildings to Aughnacloy

Size: px
Start display at page:

Download "Masterplan for Active and Sustainable Transport Assessment: A5 New Buildings to Aughnacloy"

Transcription

1 Masterplan for Active and Sustainable Transport Assessment: A5 New Buildings to Aughnacloy RSP17/003

2 Masterplan for Active and Sustainable Transport Assessment Masterplan for Active and Sustainable Transport Assessment: A5 New Buildings to Aughnacloy R-064 Prepared by: WSP Shorefield House 30 Kinnegar Drive Holywood County Down Northern Ireland BT18 9JQ T F W Prepared for: Seamus Keenan A5WTC Project Sponsor Department for Infrastructure County Hall Drumragh Avenue Omagh BT79 7AF T F W

3 Masterplan for Active and Sustainable Transport Assessment Document Control Sheet Project Title Report Title A5 New Buildings to Aughnacloy Masterplan Report: Active and Sustainable Transport Assessment Version 1.0 Status Draft Control Date 14 September 2017 Issue Control Name Signature Date Author Paul Docherty June 17 Checked Martin Hughes August 17 Approved Peter Edwards August 17 Authorised for Issue Michele Kilfeather-Hughes August 17 Issue History Rev. Issue Status Author Date Checked Date Approved Date Authorised for Issue Date 1.0 Final P Doherty 16/10/17 M Hughes 20/11/17 P Edwards 21/11/17 M Kilfeather-Hughes 21/11/17 WSP 2017 i

4 Limitations This report is presented to the Department for Infrastructure - (DfI Roads) in respect of A5 Western Transport Corridor (A5WTC) and may not be used or relied on by any other person. It may not be used by DfI in relation to any other matters not covered specifically by the agreed scope of this Report. Notwithstanding anything to the contrary contained in the report, WSP Limited is obliged to exercise reasonable skill, care and diligence in the performance of the services required by DfI Roads and WSP Limited shall not be liable except to the extent that it has failed to exercise reasonable skill, care and diligence, and this report shall be read and construed accordingly. This report has been prepared by WSP Limited. No individual is personally liable in connection with the preparation of this report. By receiving this report and acting on it, the client or any other person accepts that no individual is personally liable whether in contract, tort, for breach of statutory duty or otherwise. WSP 2017 ii

5 Contents 1 Introduction Scheme Background Principles Objectives Masterplan Structure Methods of Improving Active and Sustainable Transport Introduction Improved NMU Facilities Improved Park & Ride and Park & Share Facilities Key Drivers De-trunking of the Existing A Legislation, Policy Documents and Design Standards Document Review Stakeholder Consultation A5ASTA Stakeholder Consultation Stakeholder Consultation Meetings Additional Stakeholder Consultation Existing A5 Active and Sustainable Transport Infrastructure Introduction Urban Areas Rural Areas Identified Opportunities Introduction Urban Areas Rural Areas Connections between Urban and Rural Areas Traffic Figures Introduction Programme and Cost Introduction A5WTC Construction Phasing Potential Construction Phasing of Identified Opportunities Costing Assumptions and Constraints A5WTC Northern Ireland Greenway Network Conclusion Way Forward WSP 2017 iii

6 Appendix 1: Urban Area Memos... Appendix 2: Rural Area Memo... Appendix 3: Traffic Figures... Appendix 4: Cost Estimates... WSP 2017 iv

7 Glossary Term Controlled Pedestrian Crossing Central Refuge Director of Engineering Memorandum (DEM) Departure from Standard (DfS) Design Manual for Roads and Bridges (DMRB) Greenways Manual for Streets Non-Motorised Users (NMU) Park & Ride Park & Share Relaxation of Standard (RoS) Roads Policy and Procedure Guides (RSPPG) Definition Controlled pedestrian crossings shall be taken to include Zebra, Pelican, Toucan and Puffin Crossings. A refuge island, also known as a pedestrian refuge or pedestrian island, is a small section of pavement or footway, completely surrounded by asphalt or other road materials, where pedestrians can stop before finishing crossing a road. It is typically used when a street is very wide, as the pedestrian crossing can be too long for some individuals to cross in one traffic light cycle. Part of a suite of DfI Roads policies, procedures and documents relating to the construction, development, improvement and maintenance of the roads network. Except where Relaxations are permitted, any variation or waiving of a requirement contained within a DMRB or MCHW document must be considered to be a Departure from that Standard and will require approval from the appropriate Overseeing Organisation (in NI this is DfI). The DMRB is a series of 15 volumes that provide standards, advice notes and other documents relating to the design, assessment and operation of trunk roads, including motorways in the UK. Greenways are traffic-free routes connecting communities to various destinations for commuting, everyday journeys and / or leisure and recreation. Guidance published by Chartered Institution of Highways and Transportation for practitioners involved in the design, planning and approval of new residential streets and modifications to existing ones. Non-Motorised Users (NMU) are considered to be pedestrians, cyclists and equestrians. Particular consideration should be given to the needs of disabled people, who may use any of these modes and / or other equipment such as wheelchairs The term Park & Ride is usually applied to a dedicated bus service linking a purpose built car park with the nearest town/city centre, or to a railway station designed or adapted to provide good access by car. The term Park & Share is usually applied to dedicated car parks at key road junctions intended to act as meeting points for those travelling onward as part of a party of two or more in the same vehicle. A number of DMRB documents contain within them provision for Relaxations where experience has shown that certain requirements may be varied within defined limits in particular situations. Any Relaxations will require approval from the appropriate Overseeing Organisation (in NI this is DfI). Part of a suite of DfI Roads policies, procedures and documents relating to the construction, development, improvement and maintenance of the roads network. WSP 2017 v

8 Rural Area Shared Use Facility Speed Table Uncontrolled Pedestrian Crossing Urban Area A rural area is a geographic area that is located outside cities and towns. A shared use facility is an unsegregated facility used by more than one type of NMU, for example pedestrians and cyclists, or pedestrians, cyclists and equestrians. The use of motorcycles and mopeds are normally prohibited. Speed tables are a raised section of road, with a ramp on both sides. The ramps are painted with white arrows to make them visible to motorised users. The aim of the speed table is to ensure motorised users remain at a safe speed, as the ramps become uncomfortable for vehicle drivers if they are driven over too fast. A speed table is normally around 75mm high, and can vary in length. Uncontrolled at grade crossings consist of dropped kerbs along with appropriate tactile paving. It should be noted that other facilities defined as uncontrolled pedestrian crossing facilities include central refuges, footway build-outs and speed tables. An urban area is the region surrounding a city and is normally well developed, with a density of human structures such as houses, commercial buildings, roads, bridges, and railways. WSP 2017 vi

9 1 Introduction 1.1 Scheme Background The proposed A5 Western Transport Corridor (A5WTC) comprises 88km of new trunk road including 85km of new dual carriageway, from New Buildings to the border at Aughnacloy. During the design process it was decided that the scheme would be divided into three sections: Section 1: New Buildings Sion Mills; Section 2: Sion Mills South of Omagh; and Section 3: South of Omagh Aughnacloy. It is currently proposed that the construction works will be progressed in five phases as funding is made available by the Executive. The phases are as follows: Phase 1a: New Buildings to north of Strabane (within Section 1) o Construction proposed Phase 1b: South of Omagh to Ballygawley (within Section 3) o Construction proposed Phase 2a: North of Strabane to south of Strabane (within Section 1) o Construction proposed Phase 2b: South of Strabane to south of Omagh (Section 2) o Construction proposed Phase 3: Ballygawley to Aughnacloy (comprises remainder of Section 3) o Construction proposed Following completion of construction works for all phases of the A5WTC (New Buildings to Aughnacloy) the respective sections of the existing A5 will be de-trunked, categorised as a B class road and no longer form part of the Western Key Transport Corridor. In response to the publishing of Draft Orders in February 2016, representations were made to the Department for Infrastructure (DfI Roads) indicating that opportunities for the implementation of active and sustainable transport initiatives on and in the vicinity of the existing A5 had not been fully explored. Consequently the Department committed to the development of a strategic Masterplan that would seek to identify these opportunities between New Buildings and Aughnacloy. 1 See Section 9.3 for further information regarding the proposed construction programme for Phase 3. WSP 2017 Page 1 of 25

10 WSP was tasked with assessing opportunities for active and sustainable transport infrastructure on and in the vicinity of the existing A5 and the subsequent development of this strategic Masterplan; hereafter this assessment will be referred to as the A5 Active and Sustainable Transport Assessment (A5ASTA). The assessment considers potential opportunities that could be introduced following construction of the A5WTC dual carriageway in its entirety and the associated reduction in traffic flows from the existing road network, as well as the identification of possible opportunities following completion of the respective construction phases. It should be noted that the opportunities identified in the strategic Masterplan will not be delivered as part of the A5WTC project but as separate packages of works. Implementation of these opportunities is also dependent upon the budget available to implementation bodies once the A5WTC is complete. Any identified opportunities in the Masterplan, if progressed as discrete improvements, will be subject to a full design and consultation process in due course. 1.2 Principles The Masterplan report (A5ASTA) aligns with advice provided in a wide range of national design and guidance documents, such as Design Manual for Roads and Bridges (DMRB), Manual for Streets (MfS), Manual for Streets 2 (MfS2), disability legislation and Departmental (DfI Roads) policy documents RSPPG s and DEM s. This list is not exhaustive and designers are encouraged to review the list of references on pages Non-Motorised User (NMU) improvement schemes within urban areas and on the rural road network normally requires DMRB standards to inform the design of highway geometry elements and ultimately it will be for DfI Roads to approve any alternative standard utilised on a site by site basis. Notwithstanding this requirement, designer flexibility is recommended with regards to using the most appropriate standard for site specific locations to facilitate the delivery of safe and sustainable (NMU) improvement opportunities identified along the existing A5 route. Consultation with DfI Roads should be undertaken during the concept development stages of the schemes. Collaborative working is encouraged between all stakeholders. The establishment of multi-disciplinary development teams should be considered by implementation agencies and their designers who wish to deliver NMU opportunities. In the context of Northern Ireland, joint working may involve government and public sector bodies such as the Department of Communities, Local Councils, Housing Executive, Department for Infrastructure and also non-government organisations and community groups. To accommodate the provision of a successful coordinated quality design process, it is strongly recommended that discussion and joint working occurs at the earliest possible opportunity for the implementation of individual or groups of NMU opportunities. Promotion of modal shift from private car to public transport, Park and Ride/Share use, walking and cycling is encouraged as behavioural changes of this nature have been WSP 2017 Page 2 of 25

11 attributed to improvement in physical health together with evidence that transport choices can also influence mental health and well-being. Streets should have a local distinctiveness and have a sense of place and movement functions. Designers and other stakeholders are therefore encouraged to consider the function of streets when reviewing and implementing NMU opportunities in the fifteen urban areas detailed in this report. The development of highway improvement schemes will require assessment and justification, which normally covers aspects of the Environment, Safety, Economy, Accessibility and Integration. Implementation of some NMU opportunities may also require community consultation and Police Service of Northern Ireland (PSNI) and DfI (Roads) specific site assessments. It is envisaged that the A5ASTA report will be used to deliver various NMU opportunities on the existing A5 over the proposed A5WTC Dual Carriageway phased construction programme period 2017 to 2028 and beyond. It is therefore, important that implementation agencies keep up to date with any new design standards or guidance published that may help inform the design process, which may also include the review of Local Area Plans, environmental improvement schemes and town centre Masterplans. 1.3 Objectives The primary objective of the Masterplan is to review the existing A5 trunk road between New Buildings and Aughnacloy and the immediately adjacent road and Non-Motorised User (NMU) networks to seek to identify potential new opportunities for active and sustainable transport infrastructure, such as: Cycling routes that could be developed as a result of changes in traffic patterns along the existing A5 route; Potential new links between walking, cycling and public transport, considering park and ride sites in particular; Potential opportunities for urban cycling networks in populated areas; Improved facilities for equestrians; An examination of potential opportunities deriving from the Strategic Plan for Greenways, and Potential for new links between communities, and safer routes to schools initiatives. A further objective of the Masterplan is to report upon the timing (in relation to the construction phasing of the A5WTC scheme) for delivery of potential active and WSP 2017 Page 3 of 25

12 sustainable transport opportunities, as well as the estimated costs to implement the potential opportunities. 1.4 Masterplan Structure This document is the Masterplan for Active & Sustainable Transport Opportunities: A5 New Buildings to Aughnacloy. It summarises the findings of WSP s assessment of potential active and sustainable infrastructure that could be introduced on and in the vicinity of the existing A5 trunk road between New Buildings and Aughnacloy. The Masterplan is structured as follows: Section 1 Introduction : Background and objectives to the A5WTC and A5ASTA, Section 2 Methods of Improving Active and Sustainable Transport: Outlines the types of potential opportunities that could be implemented on or around the existing A5; Section 3 Key Drivers : Outlines the reasons why the A5ASTA has been undertaken; Section 4 Legislation, Policy Documents and Design Standards: Details the various guidelines that WSP took cognisance of during the A5ASTA and states the primary clauses that have informed the potential opportunities identified; Section 5 Stakeholder Consultation : Outlines the extent of the stakeholder consultation exercise undertaken, lists the 3rd party organisations with whom WSP consulted during the A5ASTA, and identifies the primary outcomes of each liaison; Section 6 Existing A5 Active and Sustainable Transport Infrastructure : Summarises the existing active and sustainable infrastructure in place on and around the existing A5 (drawings and memos are included in Appendix 1 and 2 providing more detail of the existing facilities); and Section 7 Identified Opportunities : Summarises the active and sustainable infrastructure that could potentially be introduced on or around the existing A5 (drawings and memos are included in Appendix 1 and 2 providing more detail of the potential opportunities). Section 8 Traffic Figures : Summarises the traffic flows on the existing A5 in the Do-Minimum scenario (no scheme in place), and flows following completion of the phased delivery of the Do-Something (A5WTC scheme) scenario. Section 9 Programme and Cost : discusses the anticipated programme for delivery of potential transport opportunities, in relation to the phased construction of the A5WTC, and estimated costs associated with these opportunities. WSP 2017 Page 4 of 25

13 Section 10 Assumptions and Constraints : details the assumptions and constraints associated with determining potential opportunities. Section 11 Conclusions : outlines the report s conclusions and recommendations. Figure 1: Location plan of the A5WTC Proposed Scheme (source: WSP 2017 Page 5 of 25

14 2 Methods of Improving Active and Sustainable Transport 2.1 Introduction In advance of commencing the exercise of identifying potential improvement opportunities, WSP determined that improved active and sustainable transport opportunities on and around the existing A5 could be achieved through a variety of means, described in Sections 2.2 and 2.3. It should be noted that while the below initiatives have been referenced in this report, due cognisance was taken of all relevant and evolving Government strategies, plans, guidelines and initiatives during the development of the Masterplan. The opportunities identified have been included in Memos included within Appendix 1 and Improved NMU Facilities Sections to describe the means by which existing non-motorised user (NMU) facilities on and around the existing A5 and on adjacent road and NMU networks could be improved. The A5ASTA undertaken assessed the existing infrastructure in accordance with these potential methods of improvement. For information, please see the below map of the current cycle network in Northern Ireland Repurposing the Existing A5 and/ or Adjacent Roads Repurposing is the term that is used in this document for opportunities which relate to reassigning part of an existing carriageway width for the sole use of NMUs e.g. an opportunity that relates to developing a cycle lane within the existing A5 carriageway width by reducing the paved surface width for vehicular traffic would be referred to as repurposing of the Existing A5' Improving NMU Facilities on the Existing A5 and/ or Adjacent Roads Prior to commencing assessment work, a number of methods for improving the existing NMU facilities on and around the existing A5 and on and around the roads immediately adjacent to the existing A5 were identified: Improved pedestrian and cycle facilities such as provision of adjacent shared use facilities, upgrading of existing NMU facilities in accordance with current standards if applicable, upgraded provisions for NMUs at junctions, etc.; Enhanced connections to existing and suitable connections to planned NMU facilities, including works associated with the proposed A5WTC; Improved NMU crossing facilities in urban areas, such as signal controlled crossings; WSP 2017 Page 6 of 25

15 Provide additional parking provision at discrete locations along the route to enable pedestrian access to places of interest, where deemed necessary; Improved signage for NMUs; Suitable positioning of street furniture so as to avoid obstruction of NMU routes; Improved facilities for vulnerable NMUs including disabled persons, the elderly and young persons; Consider incorporating appropriate actions from the Northern Ireland Road Safety Strategy to 2020; i.e. Action 4 20mph speed limits on approaches to schools; The implementation of suitable drainage facilities where new paved areas for NMUs are identified as possible improvement options; Improved geometry to provide adequate visibility, appropriate longitudinal gradients and crossfalls for NMUs; Designs that alleviate personal safety concerns; Simplification of layouts to avoid confusion to NMUs; Review of interaction with private accesses along the route in respect of improving safety for cyclists; Reduced speed limits for motorised vehicles at discrete locations along the route due to the potential provision of adjacent NMU facilities; and Facilitating connections to leisure and tourist NMU routes such as the Ulster Way particularly where it crosses the existing A5, and the Foyle Valley Cycle Route NMU Connections to the Northern Ireland Greenway Network The Northern Ireland Greenway Network is a proposal to construct an approximate 600 mile network of pathways throughout Northern Ireland. The pathways would utilise, where possible, the network of Northern Ireland s disused railway lines and also disused towpaths. Refer to Figure 2 overleaf for the proposed Greenway network as defined in Exercise, Explore, Enjoy. A Strategic Plan for Greenways, published by the Department for Infrastructure. WSP 2017 Page 7 of 25

16 Figure 2: Map of Primary and Secondary Greenway Routes (source: Exercise, Explore, Enjoy A Strategic Plan for Greenways) The plans for Greenways have been assessed to determine if their implementation would improve the NMU provisions on and in the vicinity of the existing A5 between New Buildings and Aughnacloy, and where possible would negate the requirement to improve existing NMU facilities in their locality. Furthermore, the potential to connect existing and identified potential NMU routes in the vicinity of the existing A5 between New Buildings and Aughnacloy to the proposed Northern Ireland Greenway Network is a further possible active and sustainable transport opportunity that has been assessed during this work. It should be noted that one of the proposed Greenways is located between Londonderry and Omagh, an area also covered by the existing and proposed A5 roads. The Department for Infrastructure published A Strategic Plan for Greenways on 9 th November 2016; this document has been used to inform the active and sustainable transport opportunities during assessment work, in addition to other information received from stakeholders relating to Greenways Connecting Communities/ Active School Travel Creating new links between communities in the vicinity of the existing A5 is another potential active and sustainable transport opportunity that has been assessed during this work. Part of this assessment work involved reviewing potential opportunities relating to both creating and improving cycling and pedestrian facilities for school children travelling to and from school, the aim of which is to encourage sustainable travel to school and discourage the use of motorised travel to school. WSP 2017 Page 8 of 25

17 The Rural Safe Routes to Schools initiative by Sustrans has two key objectives, which are: Reducing car use on the school run by 10%; and Increasing levels of cycling and walking. The Rural Safe Routes to Schools initiative attempts to satisfy the range of policies produced by the government departments responsible for school travel, including the Department for Infrastructure and Department of Education. The initiative 2 has so far trialled pilot Active School Travel programmes for eighteen primary schools across Northern Ireland, with the aim of further Active School Travel programmes being rolled out across more schools in Northern Ireland. This work has taken cognisance of the two key objectives of the Rural Safe Routes to Schools initiative. 2.3 Improved Park & Ride and Park & Share Facilities The use of Park & Ride (P&R) facilities is a sustainable transport initiative. Existing and desirable locations for P&R facilities in the vicinity of the existing A5 have been assessed during this study work through liaison with Translink and local authorities. The use of Park & Share facilities is another sustainable transport initiative. Existing and desirable locations for Park & Share facilities in the vicinity of the existing A5 have been assessed during this study work through liaison with DfI. A strategic report has been prepared for DfI Network Development on new locations for park and share and park and ride facilities in DfI Western Division. The report has been produced by Amey and is entitled Preliminary Options Appraisal Report Western Division Park and Ride/Share Sites (CO401467/PLOR-001). 2 Full details of the initiatives review have been published by Sustrans Rural Safe Routes to Schools Project Review (January 2009) and is available at the following location: WSP 2017 Page 9 of 25

18 3 Key Drivers 3.1 De-trunking of the Existing A5 The A5WTC scheme was essentially the main driver for this work. Following completion of the construction phases of the A5WTC between New Buildings and Aughnacloy the respective sections of the existing A5 will be de-trunked and also no longer carry the status currently accorded to it as part of the Western Key Transport Corridor (KTC). It is anticipated that there will be a significant reduction in the number of motorised vehicles (particularly heavy goods vehicles) utilising the existing A5, potentially making the road more attractive to NMUs. It was deemed prudent to develop this Masterplan as a consequence of the above, with the aim to identify potential new opportunities deriving from the construction of the A5WTC for active and sustainable infrastructure on and in the vicinity of the existing A5 trunk road between New Buildings and Aughnacloy. WSP 2017 Page 10 of 25

19 4 Legislation, Policy Documents and Design Standards 4.1 Document Review Prior to commencing assessment work, a review of the applicable legislation, policy documents and design standards relating to active and sustainable infrastructure was undertaken. This exercise ensured that opportunities were identified and assessed in accordance with the relevant published guidance. The following documents were reviewed in order to inform the Masterplan: Ensuring a Sustainable Transport Future A New Approach to Regional Transportation : This document is used to guide strategic transport interventions beyond 2015 Changing Gear A Bicycle Strategy for Northern Ireland : This document sets out the DRD s Bicycle strategy for NI between 2015 and 2040 Regional Development Strategy (RDS) 2035 : This document is the Executive s overarching spatial planning strategy for the future development of NI to 2035 United Kingdom Rural Development Programme (Regional) - Northern Ireland Sustainable Development Strategy : This document was agreed across Government Departments and outlines strategic objectives and targets for sustainable development, with varying timescales for achieving targets Tourism Strategy - public consultation on a Draft Tourism Strategy took place in spring The Department for Economy website refers the reader to the Draft Programme for Government Framework : This document outlines 14 strategic outcomes supported by 42 indicators, which include active and sustainable transport initiatives Regional Transportation Strategy for Northern Ireland : Not current Investing for Health, covers the period 2002 to 2012 : Not current Sustainable Rural Communities : This document refers the reader to United Kingdom Rural Development Programme (Regional) - Northern Ireland (see above) Building an Active Travel Future for Northern Ireland : This document is essentially the Northern Ireland Active Travel Strategy which sets out targets for improving active travel in NI by 2020 An Action Plan for Active Travel in Northern Ireland : This document details walking and cycling initiatives delivered between 2012 and 2015, and is the follow-up document to the Building an Active Travel Future for Northern Ireland (see above) WSP 2017 Page 11 of 25

20 Rural Safe Routes to Schools - Published by Sustrans Roads Service Policy & Procedure Guide (RSPPG): RSPPG_E070 Road Safety at Schools Cycling and Walking to/from work in Northern Ireland 2015/16 - DfI Cycling in Northern Ireland, DfI Bus stop design guide DfI MfS2007 Manual for Streets (2007) - Thomas Telford MfS2010 Manual for Streets 2: Wider Application of the Principles (2010) - Chartered Institution of Highways and Transportation Interim Advice Note 195/16 - Cycle Traffic and the Strategic Road Network. Also refer to the normative and informative references listed on pages 67 and 68 of this document Section 75 - Equality of Opportunity Human Rights Act Inclusive Mobility RSPPG-E005 Controlled Crossings: Assessment Procedures DMRB TA91/05 Provision for Mon-Motorised Users RSPPG_E010 Use of Tactile Paving Surfaces RSPPG_E009 Pedestrian Facilities for the Visually Impaired at Signal Controlled Crossings RSPPG_E043 Provision of Dropped Kerbs DMRB HD 42/17 Walking, Cycling & Horse-Riding Assessment and Review DMRB TA 90/05 The Geometric Design of Pedestrian, Cycle and Equestrian Routes DMRB TA 68/96 The Assessment and Design of Pedestrian Crossings, Local Transport Notes 1/95 and 2/95 RSPPG_E027 Road Safety Engineering Procedures DMRB TA 57/87 Roadside Features Beuret K and Koch A (2015). Involving the Public and Other Stakeholders. Chartered Institution of Highways and Transportation. WSP 2017 Page 12 of 25

21 Ewens A, Pinkett B, Wylie, D and Ross, A (2016). A Transport Journey to a Healthier Life. Chartered Institution of Highways and Transportation. Gallagher R and Parkin J (2014). Planning for cycling. Chartered Institution of Highways and Transportation. Mitchell K and Bendixon T (2015). Planning for Walking. Chartered Institution of Highways and Transportation. Phillotts,M (2015). Designing for Walking. Chartered Institution of Highways and Transportation. York I, Bradbury A, Reid S, Ewings T and Paradise R (2007). The Manual for Streets: Evidence and Research. TRL Report TRL 661. Department for Infrastructure (2016). Exercise, Explore, Enjoy. A Strategic Plan for Greenways. London Cycling Design Standards, Published by Transport for London (2014). Sustrans: Health and Active Travel. Available from: DfI Sustrans: Physical Activity and Health. Facts and Figures. Available from: Sustrans: Economic benefits of Active Travel. Available from: Sustrans: Sustainable travel to everyday designations. Available from: Due cognisance was taken of relevant and evolving Government strategies, plans, guidelines and initiatives during the development of the Masterplan. WSP 2017 Page 13 of 25

22 5 Stakeholder Consultation 5.1 A5ASTA Stakeholder Consultation To inform the identification and assessment of potential active and sustainable transport opportunities and the subsequent development of the Masterplan, a consultation exercise was undertaken. The A5WTC Stakeholder Consultation was used as a starting point for establishing a list of stakeholders to be contacted in relation to the A5ASTA i.e. the list of A5WTC consultees was assessed with the aim of identifying which of these consultees would have an interest in active and sustainable transport initiatives that could potentially be introduced on and in the vicinity of the existing A5 between New Buildings and Aughnacloy. This initial list of stakeholders was developed through liaison with DfI, and formed the basis for the A5ASTA consultation exercise, with the list being supplemented through further liaison with DfI. 5.2 Stakeholder Consultation Meetings After establishing the list of consultees to be contacted in relation to the A5ASTA, it was agreed with DfI that a formal meeting would not require to be held with all consultees. The consultees who attended formal meetings are as follows: Sustrans Derry & Strabane District Council (a joint meeting was held with Sustrans) DfI Cycling and Inland Waterways Unit Translink DfI Traffic Management & Network Development Mid Ulster District Council 5.3 Additional Stakeholder Consultation Those consultees identified as not requiring a formal meeting were contacted via e- mail and/or telephone. The consultees who were contacted in this manner are as follows: Northern Ireland Tourist Board; Ulster Federation of Rambling Clubs; British Horse Society; Disability Action; Fermanagh and Omagh District Council; Sion Mills Anglers; Strabane and Lifford Anglers Association; Department Agriculture, Environment & Rural Affairs (Inland Fisheries); Department for Communities (Equality Unit); Department of Education Northern Ireland; Education Authority Southern; Education Authority Western; WSP 2017 Page 14 of 25

23 Loughs Agency, and The Police Service of Northern Ireland (PSNI) Cognisance has been taken of feedback received from stakeholders during the identification and assessment of potential active and sustainable transport opportunities and the subsequent development of the Masterplan. Every effort has been made to incorporate stakeholders ideas/ needs when identifying potential improvement options. Particular attention has been paid to designing for the needs of vulnerable NMUs such as disabled persons, the elderly and young persons. WSP 2017 Page 15 of 25

24 6 Existing A5 Active and Sustainable Transport Infrastructure 6.1 Introduction The extents of the current NMU provisions on and in the vicinity of the existing A5 generally varies between urban and rural areas i.e. there are generally more provisions in urban areas compared to rural areas. 6.2 Urban Areas The following urban areas were assessed in order to inform the Masterplan report: New Buildings; Magheramason; Bready; Grangefoyle / Burndennett; Cloghcor; Ballymagorry; Strabane; Sion Mills; Victoria Bridge; Newtownstewart; Mountjoy; Omagh; Garvaghy; Ballygawley; and Aughnacloy. In many of the urban areas within the extents of the study area, the following infrastructure is commonly found: Footways (of varying widths); Online parking provision (i.e. immediately adjacent to the existing A5) and offline parking (i.e. not immediately adjacent to the existing A5); NMU crossing facilities on both the existing A5 and on immediately adjacent roads (both controlled e.g. pelican crossings, and uncontrolled e.g. non signalised crossings with or without refuge islands); and Bus stops (with or without a bus lay-by). Details of the existing NMU provisions within the fifteen urban areas assessed as part of the A5ASTA are contained within the memos and accompanying drawings which can be found in Appendix Rural Areas In many of the rural areas within the extents of the study area, the following infrastructure is commonly found (note that this infrastructure is not always in the immediate vicinity of the existing A5 i.e. existing cyclist facilities are sometimes offset WSP 2017 Page 16 of 25

25 over 100m from the existing A5, but do influence the decision making along the existing A5): National Cycle Network Routes refer to Figure 3 below Regional Cycle Routes Local Cycle Routes The Ulster Way; Refer to Figure 3 below for the current National Cycle Network in Northern Ireland. Figure 3: National Cycle Network (source: Details of the existing NMU provisions within the rural areas assessed as part of the A5ASTA are contained within the memos and accompanying drawings which can be found in Appendix 2. WSP 2017 Page 17 of 25

26 7 Identified Opportunities 7.1 Introduction As outlined in Section 2, improved active and sustainable transport opportunities on and around the existing A5 between New Buildings and Aughnacloy could be achieved through a variety of means including: repurposing the existing A5 (at discrete locations) and/or adjacent roads; improving NMU facilities on the existing A5 and/or adjacent roads; the implementation of the Greenways plans on or in the vicinity of the existing A5; and the construction of suitable connections (from both existing and identified potential NMU routes in the vicinity of the existing A5) to the proposed Northern Ireland Greenway Network. 7.2 Urban Areas A range of potential opportunities have been identified during the assessment work undertaken; these vary from relatively minor improvements such as enhancing existing gateways to urban areas to the potential introduction of 3m wide shared use NMU facilities. Details of the potential opportunities within the urban areas listed in Section 6.2 are contained within the memos and accompanying drawings which can be found in Appendix Rural Areas The main focus of the assessments of the rural areas, the areas located between the urban areas discussed in Section 7.2, was a review of the Greenway proposals received from stakeholders during the consultation exercise. The assumption was made during the assessment that where the Greenway proposals show a facility either immediately adjacent to the existing A5 or broadly parallel to (but offset from) the existing A5, such facilities will generally negate the requirement to repurpose the existing A5. Where no Greenway facilities are proposed an assessment of whether the existing A5 can be repurposed in order to provide enhanced NMU facilities has been undertaken. Details of potential opportunities within the rural areas are contained within the memo and accompanying drawings which can be found in Appendix Connections between Urban and Rural Areas Part of the assessment undertaken involved evaluating potential connectivity between NMU facilities in urban and rural areas. Generally, this involved assessing the connectivity between the existing and/or potential NMU facilities in the urban areas (identified in Appendix 1) and potential NMU facilities in the rural areas (identified in Appendix 2). The potential connections between these urban and rural facilities are labelled as potential opportunities on the rural areas drawings with supporting text in the respective memo, which can be found in Appendix 2. WSP 2017 Page 18 of 25

27 8 Traffic Figures 8.1 Introduction Following the construction of all phases of the A5WTC between New Buildings and Aughnacloy, the respective sections of the existing A5 will be de-trunked and will no longer form part of the Western KTC. It is expected that this will result in strategic traffic no longer utilising the existing A5, potentially making the road more attractive to NMUs. Traffic figures have been extracted from the A5WTC traffic model (Mark 1 Model), used to report traffic figures at the 2016 Public Inquiry, to assess the expected reduction in traffic using the existing A5. Table 8.1 shows the estimated traffic flows on the existing A5 between New Buildings and Aughnacloy for four different periods and for two scenarios. The years specified in Table 8.1 below represent the following: 2013: existing traffic on the existing A5 2019: traffic flows following the completion of the first phase (Phase 1a / 1b) 2023: traffic flows following the completion of the second phase (Phase 2a / 2b) 2028: traffic flows following the completion of Phase 3 (the complete scheme) The two scenarios are Do Minimum which assumes the A5WTC will not be constructed, whereas the Do Something represents the construction of the A5WTC as outlined earlier in the report. The difference in traffic flows between the two scenarios is also specified for 2019 and Please also refer to the drawings in Appendix 3 for the further detailed traffic figures. Location Phase Year Do Minimum Do Something Reduction AADT HGV AADT HGV AADT HGV , % - - New Buildings , % 2, % 83.0% 92.0% , % 3, % 81.0% 91.0% , % - - Magheramason , % 3, % 81.0% 91.0% , % 3, % 81.0% 91.0% , % - - Bready , % 2, % 84.0% 98.0% , % 2, % 84.0% 98.0% Grangefoyle / Burndennett Cloghcor Ballymagorry Phase 1a , % , % 2, % 84.0% 98.0% , % 2, % 84.0% 98.0% , % , % 2, % 84.0% 96.0% , % 2, % 84.0% 95.0% , % , % 3, % 74.0% 92.0% , % 3, % 76.0% 92.0% Table 8.1 (i) Anticipated Traffic Flows on the Existing A5 : New Buildings to Ballymagorry WSP 2017 Page 19 of 25

28 Do Minimum Do Something Reduction Location Phase Year AADT HGV AADT HGV AADT HGV Strabane Sion Mills Victoria Bridge Newtownstewart Mountjoy Omagh Garvaghy Ballygawley Aughnacloy Phase 3 Phase 1b Phase 2b Phase 2a , % , % 10, % 49.0% 50.0% , % 10, % 50.0% 53.0% , % , % 11, % 24.0% 56.0% , % 12, % 23.0% 53.0% , % , % 2, % 78.0% 70.0% , % 2, % , % , % 2, % 81.0% 95.0% , % 2, % 80.0% 95.0% , % , % 4, % 64.0% 82.0% , % 5, % 63.0% 81.0% , % , % 19, % , % 20, % , % , % 3, % 72.0% 4.0% , % 2, % 86.0% 62.0% , % , % 4, % 69.0% 5.0% , % 2, % 81.0% 63.0% , % , % 7, % 31.0% -12.0% Table 8.1 (ii) Anticipated Traffic flows on the Existing A5: Strabane to Aughnacloy WSP 2017 Page 20 of 25

29 9 Programme and Cost 9.1 Introduction This section of the Masterplan discusses the anticipated timing, for delivery of potential active and sustainable transport opportunities, in relation to the construction phasing of the A5WTC scheme, and the estimated costs associated with implementing these opportunities. 9.2 A5WTC Construction Phasing As outlined in Section 1.1, it is currently proposed that construction of the A5WTC will be progressed in five phases; the currently anticipated periods of construction for each phase are listed below: Phase Anticipated Construction Period Phase 1a: New Buildings to north of Strabane; Phase 1b: South of Omagh to Ballygawley; Phase 2a: North of Strabane to south of Strabane; Phase 2b: South of Strabane to south of Omagh; and Phase 3: Ballygawley to Aughnacloy Table 9.1: Proposed Construction Phasing for the A5WTC 9.3 Potential Construction Phasing of Identified Opportunities It is proposed that construction of the identified opportunities could be considered following the completion of each discrete phase. The Department will not be proceeding with Phase 3 at this time, reflecting the recommendation of the 2011 public inquiry not to do so until the Irish government decides to proceed with the N2 Improvement Scheme south of the border. 9.4 Costing Current market value rates were used for the costing of the potential opportunities described in the memos included in Appendix 1. For a complete schedule of the costings, please refer to Appendix 4. It should be noted that not all opportunities presented within the memos have been costed as some are subject to third party detailed design and consultation. It is important to note that when carrying out this exercise, there were certain aspects that were not considered due to the level of uncertainty associated with that particular element at this stage of development. More detailed, accurate costings would be required when opportunities are taken forward and further detailed design is carried out. The costs not considered at this stage include: Any impacts on statutory undertaker s apparatus, including road lighting. Site clearance. WSP 2017 Page 21 of 25

30 Land acquisition. All street furniture and existing infrastructure if affected, is assumed to have been replaced as new. Costs have not been included for removal and disposal/storage of existing infrastructure. Removal of existing road markings. Provision of Park and Ride Facilities. Incorporation of Strategy 2020 (change of speed limits). Design fees and surveys. Following the costing exercise, the opportunities were then placed into price bands to illustrate the opportunities in an order of magnitude. Placing the opportunities in bands, may help the planning of future works within budget constraints. The pricing bands selected are as follows: < 2.5k > 2.5 < 5k > 5k < 7.5k > 7.5k < 10k > 10k < 12.5K > 12.5k < 15k > 15k < 50k > 50k The total number of costed opportunities per pricing band, per location are shown in Table 9.2 below. Location <2.5K >2.5 & <5K >5 & <7.5K Cost Banding >7.5 & <10k >10k & <12.5k >12.5k & <15k >15k & <50k New Buildings Magheramason Bready Grangefoyle / Burndennett Cloghcor Ballymagorry Strabane Sion Mills Victoria Bridge Newtownstewart Mountjoy Omagh Garvaghy Ballygawley Aughnacloy Total Nr of Opportunities Per Cost Band Table 9.2: Number of Opportunities per Cost Banding per Location >50k WSP 2017 Page 22 of 25

31 Table 9.3 provides an indication of the cost of incorporating the opportunities identified in the memos and drawings included in Appendix 1, per location. Urban Area Memo Ref. Total No. of Opportunities Costed Total Cost New Buildings DM , Magheramason DM , Bready DM , Grangefoyle/Burndennett DM , Cloghcor DM , Ballymagorry DM , Strabane DM , Sion Mills DM , Victoria Bridge DM , Newtownstewart DM , Mountjoy DM , Omagh DM ,233, Garvaghy DM , Ballygawley DM , Aughnacloy DM , ,457, Table 9.3: Total Cost of Opportunities per Location WSP 2017 Page 23 of 25

32 10 Assumptions and Constraints 10.1 A5WTC A5WTC Funding/ Public Inquiry Outcome As stated in Section 9.3, it has been assumed during the development of this Masterplan that the A5WTC will be constructed in accordance with the dates indicated in Table 9.1: Proposed Construction Phasing for the A5WTC. As indicated in section 8, it is anticipated that construction of the A5WTC will result in the removal from the existing A5 of a significant proportion of the strategic traffic currently using the route, potentially making the existing A5 more attractive to NMUs. If there is a decision not to construct one or more of the five phases of the A5WTC then it may result in there being no requirement to implement the corresponding active and sustainable transport opportunities identified in the Masterplan. This will depend on the nature of each improvement option identified, as some of the improvement opportunities may still be deemed worthy of implementation in spite of the corresponding Phase of the A5WTC not being progressed i.e. implementation of the active/ sustainable transport opportunities may not rely upon the removal of a significant amount of the strategic traffic from the corresponding section of the existing A5 in order to justify their implementation A5WTC Programme Any delay to the construction programme for one or more of the five Phases of the A5WTC could result in a delay to constructing the corresponding active and sustainable transport opportunities identified in the Masterplan (this could occur where implementation of the active/ sustainable transport opportunities relies upon the removal of a significant amount of the strategic traffic from the corresponding section of the existing A5 in order to justify their implementation). In this case, construction of the active/ sustainable transport opportunities would likely be delayed until the corresponding section of the A5WTC has been constructed. The Masterplan has been developed assuming that construction of the A5WTC will be constructed in accordance with the dates indicated in Table 9.1: Proposed Construction Phasing for the A5WTC Northern Ireland Greenway Network As mentioned in section 2.2.3, the construction of approximately 600 miles of pathways throughout Northern Ireland is proposed, utilising the network of disused railway lines and disused towpaths. The Masterplan was developed assuming that the Northern Ireland Greenway Network will be constructed i.e. WSP s identified potential opportunities have assessed the practicalities of connecting to the proposed Greenway Network. WSP 2017 Page 24 of 25

33 11 Conclusion 11.1 Way Forward As stated at the start of this report, the objective of this Masterplan is to identify potential new opportunities that could be taken forward as a result of the A5WTC scheme. The realisation of these opportunities may be taken forward upon completion of works and opening to traffic of each phase, and upon publication of a De-trunking Order for the applicable length of existing A5 in some instances. The Department has made no commitment to deliver any of the opportunities identified in the strategic Masterplan, as further detailed assessment work will be required for each identified opportunity. Agreement on proposals, including identification of sufficient funding, have yet to be agreed with potential implementation agencies (identified in the strategic Masterplan). The cost banding of the opportunities outlined in Section 9, will allow the Department to consider a plan of delivery, whether it be Location-driven or Opportunity-driven. However, it is important to note that the principle of selecting quick wins in isolation should be avoided where possible, so that the strategic delivery of beneficial infrastructure/facilities for non-motorised users is achieved. WSP 2017 Page 25 of 25

INTERIM ADVICE NOTE 143/11

INTERIM ADVICE NOTE 143/11 INTERIM ADVICE NOTE 43/ Supplementary Advice and requirements for the Accessibility during planning, design, construction and handover of Improvement Schemes Summary This document provides additional advice

More information

North Somerset Council Local Development Framework

North Somerset Council Local Development Framework North Somerset Council Local Development Framework Sites and Policies Development Plan Document Evidence Paper Re-opening Portishead Railway Line and Options for the Location of Portishead Railway Station

More information

Summer North West Greenway Network - Information Booklet

Summer North West Greenway Network - Information Booklet NORTH WEST GREENWAY NETWORK Summer 2018 1 Overview This leaflet provides an overview of the North West Greenway Network, a project led by Derry City and Strabane District Council working in partnership

More information

Newcourt Masterplan. November Exeter Local Development Framework

Newcourt Masterplan. November Exeter Local Development Framework Newcourt Masterplan November 2010 Exeter Local Development Framework Background The Exeter Core Strategy Proposed Submission sets out the vision, objectives and strategy for the development of Exeter up

More information

CORRECTIONS WITHIN DESIGN MANUAL FOR ROADS AND BRIDGES AUGUST 2009

CORRECTIONS WITHIN DESIGN MANUAL FOR ROADS AND BRIDGES AUGUST 2009 DESIGN MANUAL FOR ROADS AND BRIDGES CORRECTIONS WITHIN DESIGN MANUAL FOR ROADS AND BRIDGES AUGUST 2009 SUMMARY OF CORRECTION HA 200/08 VOLUME 11, SECTION 1, PART 1 AIMS AND OBJECTIVES OF ENVIRONMENTAL

More information

Interim Advice Note 76 / 06 ASSESSMENT PART 1 AIMS AND OBJECTIVES OF ENVIRONMENTAL ASSESSMENT. Contents

Interim Advice Note 76 / 06 ASSESSMENT PART 1 AIMS AND OBJECTIVES OF ENVIRONMENTAL ASSESSMENT. Contents Interim Advice Note 76 / 06 VOLUME 11 SECTION 1: ENVIRONMENTAL ASSESSMENT INTRODUCTION PART 1 AIMS AND OBJECTIVES OF ENVIRONMENTAL ASSESSMENT Contents 1. Introduction and Application 2. Aims and Objectives

More information

Department for Infrastructure The Roads (Northern Ireland) Order 1993 The Local Government Act (Northern Ireland) 1972

Department for Infrastructure The Roads (Northern Ireland) Order 1993 The Local Government Act (Northern Ireland) 1972 Department for Infrastructure The Roads (Northern Ireland) Order 1993 The Local Government Act (Northern Ireland) 1972 Statement by The Department on the Report on the Local Inquiries into the Environmental

More information

Strategic Environmental Assessment Screening Report. Dublin Port Masterplan Review 2017

Strategic Environmental Assessment Screening Report. Dublin Port Masterplan Review 2017 Strategic Environmental Assessment Screening Report Dublin Port Masterplan Review 2017 Table of Contents 1 Introduction... 1 2 Purpose of the Masterplan... 2 3 Task 1.1 Pre-Screening Check... 5 4 Task

More information

Ebbsfleet Development Corporation

Ebbsfleet Development Corporation Title of Paper Planning and Housing Delivery Report September 2018 Presented by Sub-Committee Mark Pullin, Chief Planning Officer Planning Committee Purpose of Paper and Executive Summary This paper provides

More information

volume 11 environmental assessment section 2 environmental impact assessment Part 7 ha 218/08

volume 11 environmental assessment section 2 environmental impact assessment Part 7 ha 218/08 DESIGN MANUAL FOR ROADS AND BRIDGES volume 11 environmental assessment section 2 environmental impact assessment Part 7 ha 218/08 glossary of terms Used in DMRB Volume 11, Sections 1 and 2 SUMMARY This

More information

Construction of the A30 Bodmin India Queens Improvement

Construction of the A30 Bodmin India Queens Improvement Construction of the Bodmin India Queens Improvement This case study involved the construction of the Bodmin-India Queens Improvement Scheme. The scheme upgraded this section of the to dual carriageway

More information

TRANSPORT & INFRASTRUCTURE

TRANSPORT & INFRASTRUCTURE Pegasus Group PEGASUS GROUP TRANSPORT & INFRASTRUCTURE OUR SERVICES PLANNING DESIGN ENVIRONMENT ECONOMICS Our specialist team of transport planners, traffic engineers and infrastructure designers provide

More information

THAT the attached Terms of Reference for the Thornhill Centre Street Study be approved.

THAT the attached Terms of Reference for the Thornhill Centre Street Study be approved. COMMITTEE OF THE WHOLE AUGUST 18, 2003 THORNHILL CENTRE STREET STUDY PLANNING FILE: 15.92 Recommendation The Commissioner of Planning recommends: THAT the attached Terms of Reference for the Thornhill

More information

DESIGN AND MANAGEMENT OBJECTIVES PART 7 HA 92/01 SCHEME DEVELOPMENT, IMPLEMENTATION & MANAGEMENT SUMMARY

DESIGN AND MANAGEMENT OBJECTIVES PART 7 HA 92/01 SCHEME DEVELOPMENT, IMPLEMENTATION & MANAGEMENT SUMMARY DESIGN MANUAL FOR ROADS AND BRIDGES VOLUME 10 SECTION 0 ENVIRONMENTAL DESIGN AND MANAGEMENT ENVIRONMENTAL OBJECTIVES PART 7 HA 92/01 SCHEME DEVELOPMENT, IMPLEMENTATION & MANAGEMENT SUMMARY This Advice

More information

Boyne Valley to Lakelands County Greenway. Feasibility Report. Navan Kingscourt Railway Committee

Boyne Valley to Lakelands County Greenway. Feasibility Report. Navan Kingscourt Railway Committee Boyne Valley to Lakelands County Greenway Feasibility Report Navan Kingscourt Railway Committee June 2013 Quality Control Issue/revision Issue 1 Revision 1 Remarks DRAFT FINAL Date April 2013 June 19 th

More information

GREATER CAMBRIDGE CITY DEAL. Urban Design Guidance for Transport Infrastructure Projects

GREATER CAMBRIDGE CITY DEAL. Urban Design Guidance for Transport Infrastructure Projects GREATER CAMBRIDGE CITY DEAL Urban Design Guidance for Transport Infrastructure Projects KEY OBJECTIVES OF CITY DEAL The City Deal aims to help Greater Cambridge maintain and grow its status as a prosperous

More information

WELCOME GYPSY LANE. Wider Site Location plan. Proposals for the development of LAND OFF FOXLYDIATE LANE WEBHEATH. Proposals for the development of

WELCOME GYPSY LANE. Wider Site Location plan. Proposals for the development of LAND OFF FOXLYDIATE LANE WEBHEATH. Proposals for the development of WELCOME The developers are preparing an outline planning application for a residential led development and need the community s views in order to develop the proposals further WHAT IS PROPOSED? A high

More information

Barton-under-Needwood Village Improvement Scheme

Barton-under-Needwood Village Improvement Scheme Barton-under-Needwood Village Improvement Scheme Brief for consultancy support July 2013 1 Introduction Barton-under-Needwood Parish Council has an ambition to improve the environment along the main spine

More information

Town of Oakville Streetscape Strategy

Town of Oakville Streetscape Strategy Town of Oakville Streetscape Strategy Endorsed by PDC on February 10, 2014 (PD-011-14) Town of Oakville Streetscape Strategy [endorsed by PDC February 10, 2014] 0 Town of Oakville Streetscape Strategy

More information

WHITELEY TOWN COUNCIL NORTH WHITELEY DEVELOPMENT SEPTEMBER 2014

WHITELEY TOWN COUNCIL NORTH WHITELEY DEVELOPMENT SEPTEMBER 2014 WHITELEY TOWN COUNCIL NORTH WHITELEY DEVELOPMENT SEPTEMBER 2014 Dear Resident This Special Edition of the Whiteley Voice which has been prepared in conjunction with the North Whiteley Consortium is to

More information

ROCHFORD LOCAL DEVELOPMENT FRAMEWORK: Sustainability Appraisal/ Strategic Environmental Assessment. Rochford Core Strategy Preferred Options Document

ROCHFORD LOCAL DEVELOPMENT FRAMEWORK: Sustainability Appraisal/ Strategic Environmental Assessment. Rochford Core Strategy Preferred Options Document ROCHFORD LOCAL DEVELOPMENT FRAMEWORK: Sustainability Appraisal/ Strategic Environmental Assessment Non Technical Summary Rochford Core Strategy Preferred Options Document October 2008 SUSTAINABILITY APPRAISAL

More information

Overview Report. Proposed Development

Overview Report. Proposed Development Overview Report Proposed Development the construction of a 1km cycle/pedestrian trail including a new footbridge, new car park and entrance road at Drumshanbo Lock and a new pedestrian/cycle road crossing,

More information

Colchester Northern Gateway Master Plan Vision Review Draft. July 2016

Colchester Northern Gateway Master Plan Vision Review Draft. July 2016 Colchester Northern Gateway Master Plan Vision Review Draft July 2016 Contents Introduction 4 Context 8 Purpose of the Report 8 Strategic Position 9 Overview of the Process 11 2012 Master Plan Vision 12

More information

Scottish Natural Heritage. Better places for people and nature

Scottish Natural Heritage. Better places for people and nature Scottish Natural Heritage Better places for people and nature Contents Summary... 3 SNH approach... 5 Place-making in policy and practice... 6 Developing the contribution of the natural heritage to place-making...

More information

UTT/16/1466/DFO GREAT DUNMOW MAJOR

UTT/16/1466/DFO GREAT DUNMOW MAJOR UTT/16/1466/DFO GREAT DUNMOW MAJOR PROPOSAL: LOCATION: APPLICANT: AGENT: Reserved matters approval for the accesses to the site and principal roads within the site including spine road following outline

More information

BRIDGE OF DON MASTERPLAN & PLANNING SUMMARY

BRIDGE OF DON MASTERPLAN & PLANNING SUMMARY BRIDGE OF DON MASTERPLAN & PLANNING SUMMARY SITE LOCATION The site of the existing AECC lies in an area of predominately residential and business use in Bridge of Don and extends approximately 50 acres.

More information

WOKING DESIGN SUPPLEMENTARY PLANNING DOCUMENT (SPD)

WOKING DESIGN SUPPLEMENTARY PLANNING DOCUMENT (SPD) Agenda Item No. 5 EECUTIVE - 15 JANUARY 2015 Executive Summary WOKING DESIGN SUPPLEMENTARY PLANNING DOCUMENT (SPD) The report outlines the various responses to the consultation on the Design Supplementary

More information

3. Neighbourhood Plans and Strategic Environmental Assessment

3. Neighbourhood Plans and Strategic Environmental Assessment 1. Introduction This report sets out a draft Screening Determination for the Preston Parish Council s Neighbourhood Plan and has been prepared by rth Hertfordshire District Council. The purpose of the

More information

Inspiring Technovation

Inspiring Technovation 1 2 Table of content List of table and figures... Executive summary... 1. Introduction... 2. Material and methods... 3. Results... 3.1 Today s facts about Versailles: a diagnostic approach... 3.1 Vision

More information

Environmental Impact Assessment

Environmental Impact Assessment Environmental Impact Assessment Environmental impact assessment (EIA) is the process of systematically drawing together an assessment of the likely significant environmental effects of a development project.

More information

Road Safety Impact Assessment

Road Safety Impact Assessment Road Safety Impact Assessment October 2016 TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS About TII Transport Infrastructure Ireland (TII) is responsible for managing and improving the country s national

More information

Haydock Point. Welcome

Haydock Point. Welcome Welcome Peel Logistics Property, alongside Peel Land and Property, is preparing a planning application for Haydock Point, a high-quality logistics park east of Haydock. The purpose of this exhibition is

More information

9 CITY OF VAUGHAN OFFICIAL PLAN AMENDMENT NO BOCA EAST INVESTMENTS LIMITED

9 CITY OF VAUGHAN OFFICIAL PLAN AMENDMENT NO BOCA EAST INVESTMENTS LIMITED 9 CITY OF VAUGHAN OFFICIAL PLAN AMENDMENT NO. 631 - BOCA EAST INVESTMENTS LIMITED The Planning and Economic Development Committee recommends the adoption of the recommendations contained in the following

More information

Chapter 2: OUTLINE PLANNING APPLICATION PROPOSALS. A New Garden Neighbourhood Matford Barton 17

Chapter 2: OUTLINE PLANNING APPLICATION PROPOSALS. A New Garden Neighbourhood Matford Barton 17 Chapter 2: OUTLINE PLANNING APPLICATION PROPOSALS A New Garden Neighbourhood Matford Barton 17 2.1. SUMMARY AND STATUS OF THE PROPOSALS 2.1.1. The parameter plans and associated wording in this chapter

More information

Sustainability Statement. Whitby Business Park Area Action Plan

Sustainability Statement. Whitby Business Park Area Action Plan Sustainability Statement Whitby Business Park Area Action Plan November 2014 Contents Page 1. Introduction 1 2. Scoping 3 3. Sustainability Appraisal of Options 6 4. Assessment of Draft Area Action Plan

More information

7. The Landscape. 7.1 Introduction. Environmental Impact Statement (EIS) Scoping Report

7. The Landscape. 7.1 Introduction. Environmental Impact Statement (EIS) Scoping Report 7. The Landscape 7.1 Introduction The purpose of this section of the EIS Scoping Report is to describe the scope of work and methods to be applied in the identification and assessment of landscape and

More information

Derry City and Strabane District Council Planning Committee Report

Derry City and Strabane District Council Planning Committee Report Derry City and Strabane District Council Planning Committee Report COMMITTEE DATE: 29 th November 2017 APPLICATION No: APPLICATION TYPE: PROPOSAL: LOCATION: APPLICANT: AGENT: LA11/2016/0854/O Outline Shared

More information

INTRODUCTION NORTH HEYBRIDGE GARDEN SUBURB

INTRODUCTION NORTH HEYBRIDGE GARDEN SUBURB INTRODUCTION This event is being hosted by the promoters of the proposed North Heybridge Garden Suburb who are working with Maldon District Council and other key stakeholders on the preparation of a comprehensive

More information

Statement of Community Involvement LAND OFF SOUTHDOWN ROAD HORNDEAN, HAMPSHIRE

Statement of Community Involvement LAND OFF SOUTHDOWN ROAD HORNDEAN, HAMPSHIRE LAND OFF SOUTHDOWN ROAD HORNDEAN, HAMPSHIRE CONTENTS Page 1. Introduction 3 2. Pre-application Discussions 4 3. The Consultation Process 5 4. Consultation Feedback 7 5. Responses to Consultation Feedback

More information

Making the case for Sustainable Transport Project Potential

Making the case for Sustainable Transport Project Potential Making the case for Sustainable Transport Project Potential The Structural Investment Fund (SIF) Strategy for Greater Lincolnshire identifies the barriers to growth identified by having poor transport

More information

The Site. Welcome to the public exhibition for Boothferry Road, Hessle.

The Site. Welcome to the public exhibition for Boothferry Road, Hessle. LINDEN HOMES Welcome to the public exhibition for Boothferry Road, Hessle. We would like to hear your views about our proposals before we submit a planning application later this year. If there is anything

More information

Drainage. Alignment K:\D (D102241) SHERFORD\CONSOLIDATED PLANNING DOCUMENTS\MAIN STREET\SHERFORD MAIN STREET NARRATIVE REVISION

Drainage. Alignment K:\D (D102241) SHERFORD\CONSOLIDATED PLANNING DOCUMENTS\MAIN STREET\SHERFORD MAIN STREET NARRATIVE REVISION The Main Street therefore provides a key link for a HQPT bus system between the Park and Ride, through Sherford onto the A379 and Plymouth City Centre. There is no definitive description of an HQPT system,

More information

BETTER PUBLIC TRANSPORT PROJECT WATERBEACH TO SCIENCE PARK AND EAST CAMBRIDGE CORRIDORS

BETTER PUBLIC TRANSPORT PROJECT WATERBEACH TO SCIENCE PARK AND EAST CAMBRIDGE CORRIDORS Report To: Greater Cambridge Partnership Joint Assembly 20 th September 2018 Lead Officer: Peter Blake GCP Director of Transport BETTER PUBLIC TRANSPORT PROJECT WATERBEACH TO SCIENCE PARK AND EAST CAMBRIDGE

More information

FIRE SAFETY POLICY June 2014

FIRE SAFETY POLICY June 2014 FIRE SAFETY POLICY June 2014 Policy Title Fire Safety Policy Reference Number Corpo11/002 Implementation Date June 2014 1 st Review Review Date June 2017 Responsible Officer Director of Performance and

More information

CITY OF CHARLOTTESVILLE, VIRGINIA CITY COUNCIL AGENDA

CITY OF CHARLOTTESVILLE, VIRGINIA CITY COUNCIL AGENDA CITY OF CHARLOTTESVILLE, VIRGINIA CITY COUNCIL AGENDA Agenda Date: December 16, 2013 Action Required: Adoption of Resolution Presenter: Staff Contacts: Title: James E. Tolbert, AICP, Director of NDS James

More information

HS2 Hybrid Bill Petitioning. Summary of SMBC Asks 23/09/13. Background

HS2 Hybrid Bill Petitioning. Summary of SMBC Asks 23/09/13. Background Summary of SMBC Asks 23/09/13 Background The Council has a developed a significant number of asks and propositions for consideration by HS2 Ltd and Government throughout further development of the HS2

More information

Kibworth Harcourt. Introduction. Introduction

Kibworth Harcourt. Introduction. Introduction Introduction Introduction Welcome to this public exhibition on the proposals for the delivery of new homes on land at The Kibworths. The purpose of today s exhibition is to give you the opportunity to

More information

RE: AMENDMENT C375 GEELONG PLANNING SCHEME 1900 BARWON HEADS ROAD, BARWON HEADS

RE: AMENDMENT C375 GEELONG PLANNING SCHEME 1900 BARWON HEADS ROAD, BARWON HEADS Reference: #V157080 14 August 2018 Barwon Heads Lifestyle Group Pty Ltd C/- Best Hooper Lawyers Level 9, 451 Little Bourke Street MELBOURNE VIC 3000 Attention: Mr. Edward Mahony (Lawyer) Dear Edward RE:

More information

NORTH CIRCULAR ROAD - REGENERATION IN ACTION

NORTH CIRCULAR ROAD - REGENERATION IN ACTION NORTH CIRCULAR ROAD - REGENERATION IN ACTION Notting Hill Housing is a social enterprise which has been at the forefront of vibrant urban regeneration since 1963. Notting Hill has over 25,000 homes across

More information

Proposed Bunnings Warehouse. 90 Benalla Road Shepparton

Proposed Bunnings Warehouse. 90 Benalla Road Shepparton 90 Benalla Road Shepparton April 2015 CONTENTS 1. Introduction 1 2. Proposed Development 1 3. Existing Conditions 3 3.1 Location and Land Use 3 3.2 Road Network 5 3.3 Turning Movement Counts 8 4. Car Parking

More information

Cambridge to Cambourne Busway (A428) Planning Appraisal. Prepared by Strutt & Parker LLP & Atkins on behalf of Greater Cambridge Partnership

Cambridge to Cambourne Busway (A428) Planning Appraisal. Prepared by Strutt & Parker LLP & Atkins on behalf of Greater Cambridge Partnership Cambridge to Cambourne Busway (A428) Planning Appraisal Prepared by Strutt & Parker LLP & Atkins on behalf of Greater Cambridge Partnership August 2017 1 CONTENTS 1. Executive Summary 3 2. Introduction...5

More information

Former North Works, Lickey Road, Longbridge, Birmingham

Former North Works, Lickey Road, Longbridge, Birmingham Committee Date: 14/11/2013 Application Number: 2013/06431/PA Accepted: 27/08/2013 Application Type: Full Planning Target Date: 26/11/2013 Ward: Longbridge Former North Works, Lickey Road, Longbridge, Birmingham

More information

Harbour-front Enhancement Committee. Wan Chai Development Phase II. Planning and Engineering Review

Harbour-front Enhancement Committee. Wan Chai Development Phase II. Planning and Engineering Review Paper No. 4/2004 For discussion on 6 May 2004 Harbour-front Enhancement Committee Wan Chai Development Phase II Planning and Engineering Review PURPOSE This paper briefs Members on the scope, approach,

More information

c. DTAH Toronto Complete Streets Guidelines

c. DTAH Toronto Complete Streets Guidelines c. DTAH Toronto Complete Streets Guidelines 164 166 C.1 Project Delivery Process 168 C.5 This section provides a summary of the overarching process for delivering street projects in Toronto. The conclusion

More information

HS2 Interchange Station Design

HS2 Interchange Station Design Working on behalf of HS2 Interchange Station Design October 2018 www.hs2.org.uk 1 Interchange Station, Solihull Introduction In February 2018, HS2 Ltd appointed Arup to take forward the design of Interchange

More information

Longbridge Town Centre Phase 2 Planning Application

Longbridge Town Centre Phase 2 Planning Application Longbridge Town Centre Phase 2 Planning Application Non-Technical Summary of the Environmental Statement December 2013 Introduction A full application for Planning Permission has been submitted to Birmingham

More information

1. Welcome. Background

1. Welcome. Background 1. Welcome The purpose of this exhibition is to provide you with an update on progress on the Kilnwood Vale Scheme. In order to improve the scheme and deliver key facilities earlier in the development,

More information

PUBLIC REALM STRATEGY

PUBLIC REALM STRATEGY CONSULTATION DRAFT PUBLIC REALM STRATEGY Trenchard Street & Frogmore Street City Design Group Place Directorate Public Realm Strategy Trenchard Street & Frogmore Street Contents 1. Introduction 2. Understanding

More information

SCARBOROUGH SUBWAY EXTENSION. Scarborough Subway Extension. Final Terms of Reference

SCARBOROUGH SUBWAY EXTENSION. Scarborough Subway Extension. Final Terms of Reference Scarborough Subway Extension Final Terms of Reference 1 1.0 Introduction and Background 1.1 Introduction Toronto City Council recently confirmed support for an extension of the Bloor-Danforth Subway from

More information

3.1 The hybrid planning application proposes the following description of development:

3.1 The hybrid planning application proposes the following description of development: CHAPTER 3: PROPOSED DEVELOPMENT 3.1 The hybrid planning application proposes the following description of development: Hybrid (part-outline/part-full) planning application for a single composite development

More information

volume 11 environmental assessment section 2 environmental impact assessment Part 4 ha 204/08 scoping of environmental impact assessments

volume 11 environmental assessment section 2 environmental impact assessment Part 4 ha 204/08 scoping of environmental impact assessments DESIGN MANUAL FOR ROADS AND BRIDGES volume 11 environmental assessment section 2 environmental impact assessment Part 4 ha 204/08 scoping of environmental impact assessments SUMMARY This Advice Note provides

More information

Sustainable Urban Drainage Systems (SuDS): Design and Implementation

Sustainable Urban Drainage Systems (SuDS): Design and Implementation Sustainable Urban Drainage Systems (SuDS): Design and Implementation Climate Northern Ireland in collaboration with Institution of Civil Engineers and Business in the Community/Arena Network Thursday 5th

More information

John M. Fleming Managing Director, Planning and City Planner. Old East Village Dundas Street Corridor Secondary Plan Draft Terms of Reference

John M. Fleming Managing Director, Planning and City Planner. Old East Village Dundas Street Corridor Secondary Plan Draft Terms of Reference Report to Planning and Environment Committee To: From: Subject: Chair and Members Planning & Environment Committee John M. Fleming Managing Director, Planning and City Planner Old East Village Dundas Street

More information

TOWN AND COUNTRY PLANNING ACT 1990 (AS AMENDED).

TOWN AND COUNTRY PLANNING ACT 1990 (AS AMENDED). FAO: D. Williams Isle of Anglesey County Council Council Offices Llangefni Anglesey LL77 7TW 16 November 2017 DCRM Ref. No: WN0904-QUD-OS-LET-00002_English Dear Mr Williams TOWN AND COUNTRY PLANNING ACT

More information

TENNESSEE STATE ROUTE 109 CORRIDOR MANAGEMENT AGREEMENT MEMORANDUM OF UNDERSTANDING CORRIDOR MANAGEMENT ALONG STATE ROUTE 109

TENNESSEE STATE ROUTE 109 CORRIDOR MANAGEMENT AGREEMENT MEMORANDUM OF UNDERSTANDING CORRIDOR MANAGEMENT ALONG STATE ROUTE 109 TENNESSEE STATE ROUTE 109 CORRIDOR MANAGEMENT AGREEMENT MEMORANDUM OF UNDERSTANDING CORRIDOR MANAGEMENT ALONG STATE ROUTE 109 I. Purpose The purpose of this Agreement is to provide a framework for the

More information

Variation No 1: Dundalk & Environs Development Plan Core Strategy

Variation No 1: Dundalk & Environs Development Plan Core Strategy Variation No 1: Dundalk & Environs Development Plan 2009-2015 Core Strategy Adopted on 29 th August 2011 CONTENTS Page Section 1 1.0 Synopsis 1 1.1 Background Document 1 1.2 Variation of Dundalk and Environs

More information

WEST BLACKHALL STREET PUBLIC REALM + TOWN CENTRE CONNECTIONS Public Exhibition 28 th June 2018

WEST BLACKHALL STREET PUBLIC REALM + TOWN CENTRE CONNECTIONS Public Exhibition 28 th June 2018 WEST BLACKHALL STREET PUBLIC REALM + TOWN CENTRE CONNECTIONS Public Exhibition 28 th June 2018 Welcome Introduction Design Your Involvement Thank you for coming Engagement We would like to gather to this

More information

Proposed Student Accommodation Development

Proposed Student Accommodation Development Statement of Response to the Notice of Pre- Application Consultation Opinion Former "Matts of Cabra" public house and lands to the rear, Fassaugh Avenue, Cabra, Dublin 7 Proposed Student Accommodation

More information

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF NOVEMBER 15, 2016

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF NOVEMBER 15, 2016 Item 11, Report No. 38, of the Committee of the Whole, which was adopted without amendment by the Council of the City of Vaughan on November 15, 2016. Regional Councillor Di Biase declared an interest

More information

Town and Country Planning (Local Planning) (England) Regulations 2012, Regulation 22 Submission of Legacy Corporation Local Plan

Town and Country Planning (Local Planning) (England) Regulations 2012, Regulation 22 Submission of Legacy Corporation Local Plan Level 10, 1 Stratford Place Montfichet Road London E20 1EJ Tel: +44 (0) 20 3288 8821 Fax: +44 (0) 20 3288 1851 alex.savine@londonlegacy.co.uk Stuart Liddington The Planning Inspectorate 3/12 Kite Wing

More information

Public Consultation. Land at Monks Farm, North Grove. Welcome

Public Consultation. Land at Monks Farm, North Grove. Welcome Welcome Welcome to our public exhibition for development on Land at Monks Farm, orth Grove. Gallagher Estates and Gleeson Strategic Land are preparing an outline planning application for new homes, open

More information

THE GARDEN CITY PLAN. City of St. Catharines Official Plan. City of St. Catharines

THE GARDEN CITY PLAN. City of St. Catharines Official Plan. City of St. Catharines THE GARDEN CITY PLAN City of St. Catharines Official Plan City of St. Catharines August 2010 APPROVAL INFORMATION This Official Plan of the City of St. Catharines Planning Area, known as the Garden City

More information

BEFORE THE AUCKLAND UNITARY PLAN INDEPENDENT HEARINGS PANEL STATEMENT OF EVIDENCE OF MARTIN PEAKE ON BEHALF OF AUCKLAND COUNCIL

BEFORE THE AUCKLAND UNITARY PLAN INDEPENDENT HEARINGS PANEL STATEMENT OF EVIDENCE OF MARTIN PEAKE ON BEHALF OF AUCKLAND COUNCIL BEFORE THE AUCKLAND UNITARY PLAN INDEPENDENT HEARINGS PANEL IN THE MATTER of the Resource Management Act 1991 and the Local Government (Auckland Transitional Provisions) Act 2010 AND IN THE MATTER of Topic

More information

Local Growth Planning in North Central Green Line Communities

Local Growth Planning in North Central Green Line Communities 2018 April 30 Page 1 of 6 EXECUTIVE SUMMARY This report outlines a high-level scope for local growth planning for north central Green Line communities. The catalyst for this review is the significant investments

More information

Design Guidance. Introduction, Approach and Design Principles. Mauritius. November Ministry of Housing and Lands. .. a

Design Guidance. Introduction, Approach and Design Principles. Mauritius. November Ministry of Housing and Lands. .. a sig evelo r D Mauritius s. Utilities.. Individu a s. er itects.to ls chpers.po e Public. T. h rban D Sc U e me Promot e h ners. A Design Guidance o.h Planne rs n w iticians r l useholde National Development

More information

A46 Coventry Junctions Public information exhibitions

A46 Coventry Junctions Public information exhibitions A46 Coventry Junctions Public information exhibitions February 2017 We re making journeys better in the Midlands by operating, maintaining and modernising major A roads and motorways delivering an extensive

More information

Parish of Repton NEIGHBOURHOOD DEVELOPMENT PLAN

Parish of Repton NEIGHBOURHOOD DEVELOPMENT PLAN Parish of Repton NEIGHBOURHOOD DEVELOPMENT PLAN BASIC CONDITIONS STATEMENT December 2018 CEF 4 Legal Requirements This statement has been produced by the NDP Working Group on behalf of Repton Parish Council

More information

Protocol between Local Housing Authorities and Fire and Rescue Authorities to improve fire safety

Protocol between Local Housing Authorities and Fire and Rescue Authorities to improve fire safety Protocol between Local Housing Authorities and Fire and Rescue Authorities to improve fire safety Foreword by Communities and Local Government Ministers It is always a priority to ensure safety from the

More information

Thank you for coming. We want to hear your views on proposed improvements to the A1 between junction 65 (Birtley) and junction 67 (Coal House).

Thank you for coming. We want to hear your views on proposed improvements to the A1 between junction 65 (Birtley) and junction 67 (Coal House). Welcome Thank you for coming. We want to hear your views on proposed improvements to the between junction 65 (Birtley) and junction 67 (Coal House). This is your opportunity to provide comments on our

More information

2002/ Modernisation Road N 4

2002/ Modernisation Road N 4 2002/000-606.02 - Modernisation Road N 4 1. Basic Information 1.1. CRIS Number 2002/000-606.02 1.2. Title: Modernisation of the national road No 4 1.3 Sector : Cross Border Co-operation / Infrastructure

More information

Cranfield University Masterplan

Cranfield University Masterplan Central Bedfordshire Council EXECUTIVE Tuesday, 5 December 2017 Cranfield University Masterplan Report of: Cllr Nigel Young, Executive Member for Regeneration, (nigel.young@centralbedfordshire.gov.uk )

More information

Derry City and Strabane District Council Planning Committee Report

Derry City and Strabane District Council Planning Committee Report Derry City and Strabane District Council Planning Committee Report COMMITTEE DATE: 20.12.2017 APPLICATION No: APPLICATION TYPE: PROPOSAL: LOCATION: APPLICANT: AGENT: A/2014/0495/F Full Construction of

More information

Humber Bay Shores Precinct Plan Final Report

Humber Bay Shores Precinct Plan Final Report STAFF REPORT ACTION REQUIRED Humber Bay Shores Precinct Plan Final Report Date: May 21, 2010 To: From: Wards: Reference Number: Etobicoke York Community Council Director, Community Planning, Etobicoke

More information

High Speed Rail (London- West Midlands)

High Speed Rail (London- West Midlands) High Speed Rail (London- West Midlands) Draft Environmental Minimum Requirements Annex 3: Draft Heritage Memorandum November 2013 ESA 4.4 High Speed Rail (London- West Midlands) Draft Environmental Minimum

More information

~!VAUGHAN NOV Z November 21, Mr. Denis Kelly, Regional Clerk The Regional Municipality of York Yonge Street Newmarket, ON L3Y 6Z1

~!VAUGHAN NOV Z November 21, Mr. Denis Kelly, Regional Clerk The Regional Municipality of York Yonge Street Newmarket, ON L3Y 6Z1 ~!VAUGHAN NOV Z 5 2016 November 21, 2016 Mr. Denis Kelly, Regional Clerk The Regional Municipality of York 17250 Yonge Street Newmarket, ON L3Y 6Z1 Dear Mr. Kelly: RE: NEW KIRBY GO STATION IN BLOCK 27

More information

Village Enhancement Scheme Barton under Needwood

Village Enhancement Scheme Barton under Needwood Barton Village Enhancement Scheme Village Enhancement Scheme Barton under Needwood Executive summary May 2014 Village enhancement scheme: executive summary 1 Barton Village Enhancement Scheme Executive

More information

BEDFORD BOROUGH COUNCIL PLAN IMPLEMENTATION MONITORING REPORT

BEDFORD BOROUGH COUNCIL PLAN IMPLEMENTATION MONITORING REPORT BEDFORD BOROUGH COUNCIL PLAN IMPLEMENTATION MONITORING REPORT 2017-18 Summary 1 Progress on local development documents 1 Local development documents adopted in the monitoring period 1st April 2017 31st

More information

The journey so far. The new masterplan for Dargavel Village

The journey so far. The new masterplan for Dargavel Village The journey so far Our vision for Dargavel Village began over ten years ago when the original masterplan for transforming the former Royal Ordnance Factory site into a thriving community was established.

More information

The Illinois Department of Transportation and Lake County Division of Transportation. Route 173, including the Millburn Bypass

The Illinois Department of Transportation and Lake County Division of Transportation. Route 173, including the Millburn Bypass The Illinois Department of Transportation and Lake County Division of Transportation welcome you to this Public Hearing for U.S. Route 45 from Illinois Route 132 to Illinois Route 173, including the Millburn

More information

Appendix 2 Waterbeach Greenway Review

Appendix 2 Waterbeach Greenway Review Appendix 2 Waterbeach Greenway Review Nigel Brigham & Associates A report for 1 Introduction This report is based on fieldwork carried out in 2016 to review the Greenway network around Cambridge as shown

More information

SOUTH EAST LINCOLNSHIRE LOCAL PLAN: HOUSING PAPER DONINGTON (JUNE 2016)

SOUTH EAST LINCOLNSHIRE LOCAL PLAN: HOUSING PAPER DONINGTON (JUNE 2016) SOUTH EAST LINCOLNSHIRE LOCAL PLAN: HOUSING PAPER DONINGTON (JUNE 2016) 1 DONINGTON S PLACE IN THE SPATIAL STRATEGY 1.1 Policy 2 of the South East Lincolnshire Local Plan 2011-2036 Draft for Public Consultation

More information

PART 1. Background to the Study. Avenue Study. The Danforth

PART 1. Background to the Study. Avenue Study. The Danforth The Danforth 1.1/ Study Purpose & Key Municipal Goals 1.2/ The Local Advisory Committee 1.3/ The Project Team 1.4/ Study Process/Summary of Method 1.5/ Summary of Consultation 1.1 Study Purpose and Key

More information

Implementing sustainable water strategy through development industry engagement

Implementing sustainable water strategy through development industry engagement Implementing sustainable water strategy through development industry engagement Ian Director, Organica Engineering, Melbourne, Australia E-mail: iadams@organicaeng.com.au Edward Cotter Sustainability Leader,

More information

Welcome to our exhibition

Welcome to our exhibition Welcome to our exhibition housing development A46 Wildmoor Alcester Road Canal Quarter A422 Town Centre housing development Warwickshire-based IM Properties, one of the UK s largest privately owned property

More information

Town of Portola Valley General Plan. Nathhorst Triangle Area Plan

Town of Portola Valley General Plan. Nathhorst Triangle Area Plan Town of Portola Valley General Plan Amended December 10, 1997 Table of Contents Introduction... 1 Planning Area... 1 Objectives... 2 Principles... 2 Standards... 4 Description... 4 Community Commercial...

More information

SUBJECT: Waterfront Hotel Planning Study Update TO: Planning and Development Committee FROM: Department of City Building. Recommendation: Purpose:

SUBJECT: Waterfront Hotel Planning Study Update TO: Planning and Development Committee FROM: Department of City Building. Recommendation: Purpose: Page 1 of Report PB-23-18 SUBJECT: Waterfront Hotel Planning Study Update TO: Planning and Development Committee FROM: Department of City Building Report Number: PB-23-18 Wards Affected: 2 File Numbers:

More information

Examination of South Cambridgeshire Local Plan

Examination of South Cambridgeshire Local Plan Matter SC6A - Policy SS/5 Waterbeach New Town Historic England( formerly English Heritage) 874 Rep Nos 59748, 60250, 60253 Examination of South Cambridgeshire Local Plan Historic England, Hearing Statement

More information

Proposed Amendment to the

Proposed Amendment to the Proposed Amendment to the Carrigaline Electoral Area Local Area Plan Amendment No 1: Carrigaline (T-02, O-02 & U-02) August 2012 Proposed Amendment to the Carriagline Electoral Area Local Area Plan 2011

More information

Chapter 9 Route window W18 Slough station. Transport for London

Chapter 9 Route window W18 Slough station. Transport for London Chapter 9 Route window W18 Slough station Transport SLOUGH STATION 9 Route window W18 Slough station 9.6 Wexham Road bridge worksite north; and Wexham Road bridge worksite south. Uxbridge Road bridge

More information

Elodie Gonthier (Team leader) Kevin Ramirez Sandra Velasco Krishna Chandran Anna Aghvanyan Sirin Hamsho

Elodie Gonthier (Team leader) Kevin Ramirez Sandra Velasco Krishna Chandran Anna Aghvanyan Sirin Hamsho 2 T he nature of today s global economy highlights our interdependence and the need for much better global policies. Inspiring Technovation is pleased to present its report on transforming the city of

More information