Bostwick Road. Municipal Class Environmental Assessment. Public Information Centre #2 June 14, City of London

Size: px
Start display at page:

Download "Bostwick Road. Municipal Class Environmental Assessment. Public Information Centre #2 June 14, City of London"

Transcription

1 Bostwick Road Municipal Class Environmental Assessment Public Information Centre #2 June 14, 2017

2 Welcome! Welcome to the 2 nd Public Information Centre for the. Representatives from the and the consulting team are here to answer questions as you browse the panels. We encourage you to complete a comment sheet before leaving! 2

3 Study Overview and Purpose of the PIC This EA study is being undertaken to identify improvements required along Bostwick Road to address the anticipated growth projected for the southwest limits of the. Roadway and intersection capacity and geometric modifications Extension of Bradley Avenue to connect with Bostwick Road/Pack Road Accommodation for pedestrians and cyclists by way of improving active transportation facilities Roadway drainage and stormwater management The requirements being addressed in this EA study are based on the policies and programs established in previous planning studies: Southwest Area Plan (SWAP 2014) The London Plan (Official Plan) 2030 Transportation Master Plan SmartMoves Cycling Master Plan (London ON Bikes) The purpose of the PIC is to present and obtain comments on the corridor recommendations developed through this study. This study follows the requirements of the Municipal Class Environmental Assessment (EA) process for a Schedule C project. 3

4 Study Area The study area includes the Bostwick Road corridor from just north of Pack Road to Wharncliffe Road in the south Existing landscape is primarily agricultural with some residential and commercial uses and open space/environmental review (London OP) Several proposed developments in the lands adjacent to the corridor (mix of low and medium density residential) Bostwick Road is identified as a bike route in Cycling Master Plan The South West Area Plan (SWAP) has identified the need for a realignment of Bostwick Road in the south Project includes extension of Bradley Avenue to connect with Bostwick Road/Pack Road Plans for future intersection with Kilbourne Road extension 4

5 Need and Justification Cycling Master Plan (London ON Bikes) - Draft Proposed cycling networks along Bostwick corridor as identified in the Cycling Master Plan Update (Draft) Transportation Corridors Official Plan Amendment from SWAP Schedule C to the City of London Official Plan Proposed Future Road Corridor Landuse Official Plan Amendment from SWAP Schedule A to the City of London Official Plan Future planned land use 5

6 Problem / Opportunity (Phase 1 of the Class EA) Lands adjacent to Bostwick Road are projected to experience a significant amount of development in the near and long term future as a result of planned residential and commercial growth. To maintain the City s acceptable level of transportation service and to accommodate future developable lands in the south west area of the, improvements to the Bostwick Road corridor are required to meet future travel demands. The study also includes the identification of a preferred alignment for the Bradley Avenue Extension from Bostwick Road to Wonderland Road South. Preferred Solution (Phase 2 of the Class EA) Bostwick Road Roadway intersection / operational improvements and geometrics for future roadway connections (traffic signals, turn lanes, roundabouts, etc.) Additional lanes to increase traffic capacity and accommodate future growth in the southwest Improvements to existing facilities to encourage active transportation (walking, cycling, etc.) and improvements to accommodate future transit services Bradley Avenue Extension It was recommended that Options X & Y be carried forward for further evaluation following additional site investigations and consultation with other stakeholders. 6

7 Existing Conditions Cultural A Stage 1 Archaeological Assessment has determined that the study area has significant potential for the discovery of archaeological resources; pre-contact Aboriginal and Euro-Canadian archaeological sites Pack Road has been identified in the City s Inventory of Heritage Resources as having historical value. A Stage 2 Archaeological Assessment is required to determine impacts on archaeological resources Socio-Economic The study area is composed of primarily agricultural properties with some residential and commercial. Although most of the Bostwick Road corridor is not yet developed, the s Southwest Area Plan (SWAP) has identified this area for significant growth in the near and long term future. The s Official Plan designates the lands adjacent to Bostwick Road as Residential (Low / Medium Density), Open Space, and Community Facility. A noise assessment will be completed in Phase 3 once a recommended alignment is developed. 7

8 Existing Conditions Ecological Vegetation Patch #10064 and the associated vegetation along Thornicroft Drain are considered significant woodlands. There are three species at risk (SAR) present within the study area: Butternut (Endangered) Eastern Wood-pewee (Special Concern) Monarch Butterfly (Special Concern) There is one provincially rare vegetation community (Lowland Black Walnut Forest) within the study area. Maintaining habitat connectivity across Bradley Avenue extension is a priority. There is an opportunity to enhance habitat connectivity at the south end of Bostwick Road. A tree inventory and assessment will be conducted along the study corridor in

9 Future Traffic Conditions 9

10 Summary of Comments Received at PIC #1 Drainage improvements are needed to prevent road deterioration, flooding, and impacts to the natural environment Road safety concerns due to steep/narrow shoulders and poor sightlines Traffic signal changes to improve traffic flow Consideration to the natural environment: Avoid significant woodlot at Bradley Avenue/Pack Road Maintaining continuity and connectivity of the wooded corridors Wildlife crossings across Bostwick Road Compensatory mitigation measures 10

11 Design Alternatives Evaluation Criteria In evaluating the options to improve the Bostwick Road corridor and to extend Bradley Avenue, consideration is being given to the technical requirements of the City, as well as impacts on the area s natural, cultural, social and economic environments. Environmental Factor Groups Transportation Cultural Socio-Economic Natural Cost Planning Policies and Objectives Compatibility with Proposed Development Projects Traffic Operations / Performance Active Transportation Transit Services Roadway Drainage & Stormwater Management Archaeological Resources Cultural and Built Heritage Aboriginal / First Nations Communities Property Construction Disruption Noise Compatibility with adjacent residents and businesses (exisiting) Connectivity to community facilities / neighborhoods (planned) Buffers Species at Risk and rare species Loss of vegetation Wildlife habitat Disruption of wildlife movement Aquatic species/watercourses Water quality Locally designated areas Air Quality Capital cost Property Cost Utilities Operation and Maintenance Cost Commercial and Residential Access 11

12 Alternative Alignments Bostwick Road Option A Option B Generally maintains the current road alignment to Kilbourne (future connection with Bostwick), where it shifts significantly to the SW through planned residential development area Maintains connection with Wharncliffe in the south Corridor is realigned to the west to avoid natural heritage features Connects to existing alignment north of Kilbourne (future connection with Bostwick) down to Wharncliffe in the South Option C Option D Corridor is realigned to the west at Pack Road to minimize encroachment into natural heritage features Alignment jogs slightly to the south through planned residential development area Connects to existing alignment between the southern woodlot and north of Kilbourne (future connection with Bostwick) Maintains connection with Wharncliffe in the South Corridor is realigned to the west at Pack Road to minimize encroachment into natural heritage features Connects to existing alignment between the southern woodlot and north of Kilbourne (future connection with Bostwick) South portion of the corridor is realigned through planned residential development area to connect with Savoy Street Requires new signalized intersection at Wharncliffe Rd / Savoy St intersection West leg of Wharncliffe is closed (cul de-sac) where it currently connects with Bostwick Road 12

13 Design Alternatives Bradley Avenue Bradley Avenue is extended through a wooded area northeast of the proposed Bradley Avenue and Bostwick Road intersection. This option would connect with Pack Road at Bostwick Road at its current location. Option X Option Y Bradley Avenue is extended through a planned residential area south of the wooded area. Requires shifting the current Pack Road alignment to the south to connect with Bostwick Road. 13

14 Design Alternatives Kilbourne Road Kilbourne Road is a proposed secondary collector with a 21.5m Road Allowance; The recommended alternative is to align Kilbourne Road to the north along the existing property line to avoid impacts to the wooded area to the south. 14

15 Evaluation of Design Alternatives Bostwick Road EVALUATION CRITERIA Do Nothing Option A Option B Option C Option D TRANSPORTATION Does not address current and future transportation needs and is not consistent with the objectives of the TMP. Addresses operational requirements by providing improved alignment geometery, additional capacity and improved intersection operations. Partially addresses operational requirements by adding traffic capacity and improved intersection operations. Reduced sightlines from two curves at the south end. Addresses operational requirements with optimal alignment geometery, additional capacity and improved intersection operations. Somewhat addresses operational requirements but creates additional movements at Wharncliffe / Bostwick intersection. Introduces a dicontinuity at Wharncliffe/Exeter intersection. PLANNING POLICIES AND OBJECTIVES Is not consistent with the objectives of the London Plan and South West Area Plan (SWAP) Somewhat meets the objectives of the London Plan and South West Area Plan (SWAP). Lands at south end are fragmented limiting access options and development potential. However, impacts on adjacent natural areas and adjacent lands does not support local planning policies and objectives. Does not fully meet the objectives of the London Plan and South West Area Plan (SWAP) due to transportation and technical limitations. Land requirements are not optimally balanced. Minormoderate impact on proposed development projects. Meets the objectives of the London Plan and South West Area Plan (SWAP). Minimizes fragmentation of lands at the south end. Development potential would be generally maintained for parcels at the south end. Balances land requirement overall. Is not consistent with the objectives of the London Plan and South West Area Plan (SWAP) in specifying how future corridors are to be determined. Contradicts land use plan in SWAP. Significant impact on proposed development projects and new fire hall on Savoy. TECHNICAL REQUIREMENTS Does not meet current geometric design standards; does not address drainage deficiencies Addresses technical requirements. A single curve at south end provides better sightlines over two curves. Partially addresses technical requirements. Reduced sightlines at south end. Limits flexibility with location of proposed SWMF's. Addresses technical requirements with minimal impact on proposed development projects. Development potential would be generally maintained for parcels at the south end. Provides greater flexibility with locations of SWMF's. Somewhat addresses technical requirements. The classification of Savoy as a Collector is not compatible with the needs of the corridor. Delays to traffic along Wharncliffe due to additional signalized intersection at Wharncliffe/Savoy. SOCIO-ECONOMIC ENVIRONMENT CULTURAL HERITAGE NATURAL ENVIRONMENT COST Doing nothing would have no direct impact on the socio-economic environment. However, this option does not support the requirements of proposed community developments. Existing businesses will face access challenges as traffic volumes increase. No impacts to cultural heritage resources and/or land claims from Aboriginal or First Nations communities. No impacts to archaeological resources. This alternative would have minimal impacts to the natural environment beyond existing impacts. However, there are no opportunities to restore / enhance habitat or improve connectivity. Although there will be no initial capital cost, the cost of maintaining the existing roadway over the long term can be expected to increase. This alternative provides the maximum allowable setback from residential properties. Widening the roadway closer to the residence would still result in moderate impacts. No anticipated impacts to cultural heritage resources and/or land claims from Aboriginal or First Nations communities. Archaeological impacts to be further assessed following a stage 2 assessment. This alternative would have the most significant impact to the adjacent natural environment, particularly at the northern woodlot (Patch 10064), where a number of rare species are present. Moderate construction and property costs This alternative would have significant impacts on residential properties in the short term. No anticipated impacts to cultural heritage resources and/or land claims from Aboriginal or First Nations communities. Archaeological impacts to be further assessed following a stage 2 assessment. This alternative was ranked as having the least overall impact to the adjacent natural environment. The open space at the south portion of the study area and both woodlots at the northeast portion of the study area would be largely avoided. Moderate construction and property costs Similar to option A, this alternative provides the maximum available setback from residential properties while limiting encroachment into the adjacent natural area. Ranks as the least impactful alternative overall. No anticipated impacts to cultural heritage resources and/or land claims from Aboriginal or First Nations communities. Archaeological impacts to be further assessed following a stage 2 assessment. This alternative largely avoids encroachment into the significant woodlot at the northeast portion of the study area but would extend into the less significant central woodlot and open space at the southwest end. Higher overall construction cost of alternatives. Additional costs would be incurred for property impacts along at Wharncliffe/Bostwick/Exeter. Avoids impacts along Savoy and Fire Hall. Provides the maximum allowable setback from 3645 Bostwick Rd while limiting encroachment into the adjacent natural area. This option would alleviate the need to acquire commercial property at the south but would result in significant encroachment on residential property at the south end. Development lotting patterns already established on Savoy. No anticipated impacts to cultural heritage resources and/or land claims from Aboriginal or First Nations communities. Archaeological impacts to be further assessed following a stage 2 assessment. This alternative largely avoids encroachment into the significant woodlot at the northeast portion of the study area but would extend into the less significant central woodlot and open space at the southwest end. This alternative would eliminate potential impacts on aquatic species and watercourses at the Thornicroft Drain, as a culvert crossing would no longer be required. There is also the potential for enhancement along the southern reaches of the drain. Moderate construction costs. Additional costs would be incurred for property impacts along Savoy and Fire Hall; Avoids property at Wharncliffe/Bostwick/Exeter. EVALUATION SUMMARY NOT RECOMMENDED NOT RECOMMENDED NOT RECOMMENDED RECOMMENDED NOT RECOMMENDED 15

16 Evaluation of Design Alternatives Bradley Avenue EVALUATION CRITERIA Do Nothing Option X Option Y TRANSPORTATION / TECHNICAL REQUIREMENTS Does not address the transportation objectives in the TMP, SWAP, or the London Plan. Does not support the transportation needs of future developments. Addresses operational and technical requirements while maintaining development potential in the area. However, impacts on adjacent natural areas does not support the recommendations of local planning policies and objectives. Addresses operational and technical requirements and supports the recommendations of local planning policies and objectives. However, this alternative reduces the amount of developable land east and west of Bostwick Rd and fragments land parcels to the west, limiting development potential. SOCIO-ECONOMIC ENVIRONMENT While doing nothing would avoid direct impacts on the surrounding socio-economic environment, it would not support the transportation needs of future developments and community facilities. This alternative would have significant impacts on 6092 Pack Rd. Realigning the roadway further to the south from 6092 Pack Rd would reduce the overall impact to this residence. CULTURAL HERITAGE This alternative supports the requirements of the Ontario Heritage Act by not encroaching onto 6092 Pack Road, which has been identified in the City s Inventory of Heritage Resources as having historical value. This alternative encroaches onto 6092 Pack Road, which has been identified in the City s Inventory of Heritage Resources as having historical value. Encroachment onto properties of heritage significance should be avoided. This alternative supports the requirements of the Ontario Heritage Act by not encroaching onto 6092 Pack Road, which has been identified in the City s Inventory of Heritage Resources as having historical value. NATURAL ENVIRONMENT Doing nothing will have no impacts on the existing natural environment. This alternative would have significant impact to the adjacent natural environment (e.g. Patch 10064), where a number of rare species are present. While construction of a new road will have unavoidable ecological impacts, this alternative avoids the most significant natural heritage features and provides opportunities to enhance natural habitat and facilitate wildlife movement. COST No cost to construct new road. Similarities in overall cost of alternatives X & Y prevents this criteria from being a significant factor in determining the recommended alternative. Similarities in overall cost of alternatives X & Y prevents this criteria from being a significant factor in determining the recommended alternative. EVALUATION SUMMARY NOT RECOMMENDED NOT RECOMMENDED RECOMMENDED 16

17 Preliminary Recommended Design The recommended solution(s) identified for the Bostwick Road EA were determined to best meet the technical requirements and s planning objectives and policies for the area. Bostwick Road (Option C) Bradley Avenue (Option X) Roadway corridor to be realigned as per Option C Provides the maximum available setback from residential properties while limiting encroachment into the adjacent natural area Connects to existing alignment to the north of Kilbourne (future connection with Bostwick) South portion of the alignment jogs slightly to the south through planned residential development area and connects with Wharncliffe Bostwick Road to be widened to 4 lanes by 2035 with intersection improvements Future (2035) intersection operational improvements at Southdale and Wharncliffe intersections via additional through lanes. Signal timing improvements in the interim Future (2035) 4-lane roundabout configurations at Pack Road & Kilbourne Road. 2-lane roundabouts in the interim Active transportation improvements via continuous sidewalks and onroad bike lanes (buffered) Roadway drainage via catchbasins, curbs, gutters and stormsewers Commercial property requirements at Bostwick/Wharncliffe intersection Corridor is to be extended to the south of Patch 10064, a significant woodlot containing rare species Connects with Bostwick Road to the south of existing Pack Road intersection (requires shifting the current Pack Road alignment to the south) 2 through lanes to accommodate vehicular traffic (interim). 4 lanes in the future (ultimate) Active transportation improvements via continuous sidewalks and on-road bike lanes (buffered) Roadway drainage improvements via catchbasins, curbs, gutters and stormsewers Recommend rezoning of lands to mitigate loss of adjacent medium density developable area Recommendations to be implemented in phases 18

18 Implementation Plan Bradley Avenue The City s Development Charges Study and Capital Plan include the extension of Bradley Avenue between Wonderland Road and Bostwick Road with two lanes by Bostwick Road The realignment and widening of Bostwick Road is not currently scheduled. Following completion of the study, the City can commence with property acquisitions. Realignment and reconstruction of two lanes is anticipated by 2025 in conjunction with proposed developments. Widening to four lanes is anticipated beyond 2025 or by

19 Phasing Plan Options Bostwick Road Initial Reconstruction and Realignment of Two Lanes on East Side Of Centerline Allows for installation of sidewalks, street lighting and storm sewers in ultimate location Allows for phasing of future trunk sanitary sewer with minimal disruption. Future widening would take place on west side of centerline Allow for maintenance of traffic during construction Initial Reconstruction and Realignment of Two Lanes with Median (Recommended between Wharncliffe and Kilbourne) Allows for installation of sidewalks, street lighting and storm sewers in ultimate location Allows for maintenance of traffic during construction Median provides a safety buffer between opposing lanes Allows for construction of buffered on-road bicycle lanes Allows for flexibility in timing and construction of roundabouts. 20

20 Recommended Cross Section Bostwick Road (Ultimate) The cross sections developed for the Bostwick Road and Bradley Avenue corridors were developed to meet both technical requirements of the study and planning objectives established in the Southwest Area Plan (SWAP 2014), The London Plan (Official Plan), 2030 Transportation Master Plan SmartMoves and City of London Cycling Master Plan (London ON Bikes). 21

21 Recommended Cross Section Bradley Avenue (Ultimate) The cross sections developed for the Bostwick Road and Bradley Avenue corridors were developed to meet both technical requirements of the study and planning objectives established in the Southwest Area Plan (SWAP 2014), The London Plan (Official Plan), 2030 Transportation Master Plan SmartMoves and City of London Cycling Master Plan (London ON Bikes). 22

22 Roundabouts at Pack Road & Kilbourne Road (Future) Though no traffic signals are warranted, significant delay is anticipated at these locations in the future Roundabouts at these locations will serve to reduce unnecessary delay Pedestrian safety would be improved via new PXO treatments requiring vehicles to stop for crossing pedestrians (OTM Book 15) Additional benefits: Proven reduction in severity of accidents Reduction in vehicle emissions & noise Lower costs to maintain Provides ability to make a U-turn on a divided road 23

23 Next Steps Confirm the study recommendations (i.e. Preferred Design) in context of the comments received Meet with additional stakeholders and technically agencies as required Complete factor-specific studies Stage 2 Archaeological Assessment Tree inventory & Assessment Noise Assessment Submit an Environmental Study Report, documenting the planning process, for 30 Day public review Proceed to Phase 5: Detailed Design & Construction We encourage you to complete a comment sheet before leaving or submit your comments via / mail to one of the following project team members: Henry Huotari, P.Eng. Project Manager Parsons Inc Wellington Road South, Suite 214 London, ON N6E 2H6 Tel: Henry.Huotari@parsons.com Maged Elmadhoon, M.Eng., P.Eng. Traffic & Transportation Engineer 300 Dufferin Avenue, 8th Floor, P.O Box 5035 London, Ontario, N6A 4L9 Tel: CITY (2489) ext melmadho@london.ca Information collected for the study will be used in accordance with the Municipal Freedom of Information and Protection of Privacy Act. Except for personal information, including your name, address and property location, all comments received throughout the study will become part of the public record and included in project documentation. 24

Bostwick Road. Municipal Class Environmental Assessment. October 13, City of London. Bostwick Road Municipal Class Environmental Assessment

Bostwick Road. Municipal Class Environmental Assessment. October 13, City of London. Bostwick Road Municipal Class Environmental Assessment Bostwick Road Municipal Class Environmental Assessment October 13, 2016 Welcome! Welcome to the first Public Information Centre for the Bostwick Road Municipal Class Environmental Assessment. Representatives

More information

Municipal Class EA Study Public Information Centre No. 1 December 13, :00 pm 7:00 pm. Please sign in so we can keep you updated on this study

Municipal Class EA Study Public Information Centre No. 1 December 13, :00 pm 7:00 pm. Please sign in so we can keep you updated on this study Reconstruction of Regional Road 45 (Creek Road) Between Regional Road 27 (River Road) and Regional Road 63 (Canborough Road) in the Township of Wainfleet Municipal Class EA Study Public Information Centre

More information

Commissioners Road West Realignment Environmental Assessment

Commissioners Road West Realignment Environmental Assessment City of London Commissioners Road West Realignment Environmental Assessment Public Information Centre No. 1 March 30, 2017 Welcome to the Public Information Centre This first Public Information Centre

More information

Commissioners Road West Realignment Environmental Assessment

Commissioners Road West Realignment Environmental Assessment City of London Commissioners Road West Realignment Environmental Assessment Public Information Centre No. 2 November 29, 2017 Welcome to the Public Information Centre This 2 nd Public Information Centre

More information

Public Information Centre #1

Public Information Centre #1 and Highway 401 Interchange Improvements WELCOME Public Information Centre #1 Veterans Memorial Parkway Extension and Highway 401 Interchange Improvements Study May 23, 2012 4 p.m. to 7 p.m. Brief Overview

More information

Portage Parkway Environmental Assessment Public Information Centre No. 1

Portage Parkway Environmental Assessment Public Information Centre No. 1 City of Vaughan Portage Parkway Environmental Assessment Public Information Centre No. 1 November 25, 2015 Welcome to the Public Information Centre This first Public Information Centre (PIC) introduces

More information

GEOMETRIC IMPROVEMENTS AND WATERMAIN LOOPING MUNICIPAL CLASS ENVIRONMENTAL ASSESSMENT

GEOMETRIC IMPROVEMENTS AND WATERMAIN LOOPING MUNICIPAL CLASS ENVIRONMENTAL ASSESSMENT GEOMETRIC IMPROVEMENTS AND WATERMAIN LOOPING MUNICIPAL CLASS ENVIRONMENTAL ASSESSMENT Veterans Way (previously Powerline Road) and Klondike Park Road Wasaga Beach Welcome Please sign in Take a comment

More information

Improvements Municipal Class Environmental Assessment. Public Information Centre #1 June 11, 2015

Improvements Municipal Class Environmental Assessment. Public Information Centre #1 June 11, 2015 Western Road & Sarnia Road/Philip Aziz Avenue Improvements Municipal Class Environmental Assessment Public Information Centre #1 June 11, 2015 1. Welcome We re hosting this Public Information Centre (PIC)

More information

Better Cycling. The City will update the cycling master plan (London ON Bikes) based on the approved BRT network.

Better Cycling. The City will update the cycling master plan (London ON Bikes) based on the approved BRT network. Better Cycling Dedicated bike facilities will be constructed along BRT corridors where space is available. Nearby bike routes will also be upgraded to ensure a complete network is available for cyclists.

More information

Vaughan Metropolitan Centre (VMC) Black Creek Renewal CLASS ENVIRONMENTAL ASSESSMENT

Vaughan Metropolitan Centre (VMC) Black Creek Renewal CLASS ENVIRONMENTAL ASSESSMENT PUBLIC INFORMATION CENTRE Vaughan Metropolitan Centre (VMC) Black Creek Renewal Wednesday, May 10, 2017 6:00 p.m. to 8:00 p.m. Add photo Project Management, Environmental Assessment, Stormwater Management

More information

Heritage Road Improvements from Steeles Avenue to Rivermont Road

Heritage Road Improvements from Steeles Avenue to Rivermont Road The Corporation of the City of Brampton Heritage Road Improvements from Steeles Avenue to Rivermont Road Class Environmental Assessment Study (Schedule C) September 19, 2013 The Corporation of the City

More information

Adelaide Street / Canadian Pacific Railway (CPR) Grade Separation. Public Information Centre #1

Adelaide Street / Canadian Pacific Railway (CPR) Grade Separation. Public Information Centre #1 1 Adelaide Street / Canadian Pacific Railway (CPR) Why Are We Here? 2 The purpose of Public Information Centre (PIC) #1 is to: Introduce the study Provide the study background and context Identify the

More information

City of Toronto. Emery Village Transportation Master Plan

City of Toronto. Emery Village Transportation Master Plan City of Toronto Emery Village Transportation Master Plan May 2009 Emery Village Transportation Master Plan Toronto, ON May 2009 Consulting Inc. 100 York Blvd., Suite 300 Richmond Hill, ON L4B 1J8 Tel:

More information

Adelaide Street / Canadian Pacific Railway (CPR) Grade Separation Class Environmental Assessment. Public Information Centre 3

Adelaide Street / Canadian Pacific Railway (CPR) Grade Separation Class Environmental Assessment. Public Information Centre 3 1 Adelaide Street / Canadian Pacific Railway (CPR) Grade Separation Study Process and Purpose of PIC 3 2 Study Commencement February 2016 Phase 1: Problem and Opportunity Identify problems and opportunities

More information

Highway 427 Industrial Secondary Plan Area 47 Schedule C Class Environmental Assessment For Arterial Roadways

Highway 427 Industrial Secondary Plan Area 47 Schedule C Class Environmental Assessment For Arterial Roadways Welcome to Pubic Information Centre #1 Highway 427 Industrial Secondary Plan Area 47 Schedule C Class Environmental Assessment For Arterial Roadways Welcome to Open House # 1 Tonight, we invite you to.

More information

Public Information Centre. Welcome

Public Information Centre. Welcome Transportation Improvements from the Beaver Creek Bridge to the Entrance of Santa s Village District of Muskoka Municipal Class Environmental Assessment Welcome Please sign in Take a comment sheet Staff

More information

St. Clair Avenue West Area Transportation Master Plan

St. Clair Avenue West Area Transportation Master Plan 1 (Between Keele Street and Old Weston Road) Public Information Centre 1 December 2, 2015 2 Welcome Welcome to the first Public Information Centre for the St. Clair Avenue West Area. The panels will present

More information

City of Cornwall Municipal Class Environmental Assessment. Proposed Improvement and Extension of Lemay Street

City of Cornwall Municipal Class Environmental Assessment. Proposed Improvement and Extension of Lemay Street Welcome City of Cornwall Municipal Class Environmental Assessment Proposed Improvement and Extension of Lemay Street Redevelopment and Design of the Municipal Works Yard Public Information Centre #1 Thursday,

More information

GLEN ROAD PEDESTRIAN BRIDGE ENVIRONMENTAL ASSESSMENT STUDY PUBLIC INFORMATION CENTRE #2 OCTOBER 24, 2017

GLEN ROAD PEDESTRIAN BRIDGE ENVIRONMENTAL ASSESSMENT STUDY PUBLIC INFORMATION CENTRE #2 OCTOBER 24, 2017 GLEN ROAD PEDESTRIAN BRIDGE ENVIRONMENTAL ASSESSMENT STUDY PUBLIC INFORMATION CENTRE #2 OCTOBER 24, 2017 Glen Road Pedestrian Bridge Class Environmental Assessment 1 WELCOME! Welcome to the second Public

More information

WELCOME TO OPEN HOUSE TWO November 28, 2018

WELCOME TO OPEN HOUSE TWO November 28, 2018 Langstaff Road Weston Road to Highway 7 Class Environmental Assessment Study WELCOME TO OPEN HOUSE TWO November 28, 2018 Please sign in and join our mailing list Study Overview York Region is conducting

More information

Recreational Pathway Crossing of Richmond Street Municipal Class Environmental Assessment. Public Information Centre #2 April 22, 2015

Recreational Pathway Crossing of Richmond Street Municipal Class Environmental Assessment. Public Information Centre #2 April 22, 2015 Recreational Pathway Crossing of Richmond Street Municipal Class Environmental Assessment Public Information Centre #2 April 22, 2015 1. Study Process PHASE 1 PHASE 2 PHASE 3 PHASE 1 : Problem/Opportunity

More information

The Illinois Department of Transportation and Lake County Division of Transportation. Route 173, including the Millburn Bypass

The Illinois Department of Transportation and Lake County Division of Transportation. Route 173, including the Millburn Bypass The Illinois Department of Transportation and Lake County Division of Transportation welcome you to this Public Hearing for U.S. Route 45 from Illinois Route 132 to Illinois Route 173, including the Millburn

More information

Western Road/Wharncliffe Road North Widening from Platts Lane to Oxford Street. Municipal Class Environmental Assessment Public Information Centre #1

Western Road/Wharncliffe Road North Widening from Platts Lane to Oxford Street. Municipal Class Environmental Assessment Public Information Centre #1 Western Road/Wharncliffe Road North Widening from Platts Lane to Oxford Street Municipal Class Environmental Assessment Public Information Centre #1 June 11, 2014 Welcome Welcome to the first Public Information

More information

FANSHAWE PARK ROAD/RICHMOND STREET INTERSECTION IMPROVEMENTS. PUBLIC INFORMATION CENTRE 2 June 16, 2016

FANSHAWE PARK ROAD/RICHMOND STREET INTERSECTION IMPROVEMENTS. PUBLIC INFORMATION CENTRE 2 June 16, 2016 FANSHAWE PARK ROAD/RICHMOND STREET INTERSECTION IMPROVEMENTS Municipal Class Environmental Assessment PUBLIC INFORMATION CENTRE 2 June 16, 2016 ACCESSIBILITY Under the Accessibility Standards 2015 for

More information

Master Environmental Servicing Plan & Secondary Plan

Master Environmental Servicing Plan & Secondary Plan 1 East Side Lands Stage 2 Master Environmental Servicing Plan & Secondary Plan Public Consultation Centre #4 March 20, 2018 Welcome! Today s Agenda Please sign in at the registration table. 6:00 pm 6:30

More information

Welcome. Date: Thursday March 2, 2017 Time: 6:30 p.m. 9:00 p.m. Location: Woodview School Gym, 69 Flatt Road, Burlington Presentation Time: 7:00 p.m.

Welcome. Date: Thursday March 2, 2017 Time: 6:30 p.m. 9:00 p.m. Location: Woodview School Gym, 69 Flatt Road, Burlington Presentation Time: 7:00 p.m. Welcome Public Information Centre No.2 City of Burlington, City of Hamilton, Region of Halton Waterdown Road Widening Detailed Design Craven Avenue to Mountain Brow Road Date: Thursday March 2, 2017 Time:

More information

Purpose of Open House #3

Purpose of Open House #3 Public Meeting #3 May 9, 2009 MVVA Team Purpose of Open House #3 The main purpose of this Open House is to present and seek input on the: Evaluation of transportation and infrastructure design alternatives

More information

Public Meeting #3 May 9, 2009 MVVA Team

Public Meeting #3 May 9, 2009 MVVA Team Public Meeting #3 May 9, 2009 MVVA Team Welcome to the third Public Meeting for the Lower Don Lands Municipal Class Environmental Assessment (EA) Infrastructure Master Plan and Keating Channel Precinct

More information

Mavis Road Class Environmental Assessment

Mavis Road Class Environmental Assessment Mavis Road Class Environmental Assessment Public Information Centre #2 Wednesday November 9, 2016 6:00 to 8:00 p.m. Please sign in and complete a comment sheet Review the displays on your own or join in

More information

Appendix B-13: Community Stakeholders Group Meeting Materials and Minutes

Appendix B-13: Community Stakeholders Group Meeting Materials and Minutes Appendix B-13: Community Stakeholders Group Meeting Materials and Minutes PREPARED BY IBI Group and WSP London s Rapid Transit Initiative Community Stakeholder Group Meeting Summary Report for October

More information

Bridge Type Assessment and Evaluation

Bridge Type Assessment and Evaluation 16M-01410-01 (3216026) Glen Road Pedestrian Bridge EA Study Bridge Type Assessment and Evaluation Factor Group/Criteria Alternative 1: Steel girder with two inclined steel legs Alternative 2: Steel girder

More information

WILLIAM STREET STORM SEWER OUTFALL. PUBLIC INFORMATION CENTRE March 23, 2017

WILLIAM STREET STORM SEWER OUTFALL. PUBLIC INFORMATION CENTRE March 23, 2017 WILLIAM STREET STORM SEWER OUTFALL Municipal Class Environmental Assessment PUBLIC INFORMATION CENTRE March 23, 2017 ACCESSIBILITY Under the Accessibility Standards 2015 for Customer Service Regulation

More information

Urban Design Brief December 23, 2015 Southside Construction Group Official Plan & Zoning By-Law Amendment

Urban Design Brief December 23, 2015 Southside Construction Group Official Plan & Zoning By-Law Amendment Urban Design Brief Proposed Official Plan & Zoning By-Law Amendment 3244, 3263 and 3274 Wonderland Road South Southside Group December 23, 2015 TABLE OF CONTENTS Page No. INTRODUCTION... 1 SECTION 1 LAND

More information

Master Environmental Servicing Plan & Secondary Plan

Master Environmental Servicing Plan & Secondary Plan East Side Lands Stage 2 1 Master Environmental Servicing Plan & Secondary Plan Public Information Centre #1 June 16, 2016 Welcome! Today s Agenda Please sign in at the front desk. 5:30 pm 6:30 pm: Open

More information

INFRASTRUCTURE EXISTING INFRASTRUCTURE A. Circulation B. Signals C. Drainage D. Utilities

INFRASTRUCTURE EXISTING INFRASTRUCTURE A. Circulation B. Signals C. Drainage D. Utilities 7.01. EXISTING INFRASTRUCTURE A. Circulation B. Signals C. Drainage D. Utilities 7.02. PROPOSED INFRASTRUCTURE A. Overall Concept B. Circulation C. Signals D. Drainage 7.03. INFRASTRUCTURE MAP A. Key Infrastructure

More information

WELCOME TO OPEN HOUSE # 3

WELCOME TO OPEN HOUSE # 3 Bayview Avenue Class Environmental Assessment Study Steeles Avenue to Elgin Mills Road WELCOME TO OPEN HOUSE # 3 Please sign in and join our mailing list Why Are We Here Tonight? Study Process and Purpose

More information

SUMMARY ASSESSMENT MATRIX

SUMMARY ASSESSMENT MATRIX ASSESSMENT MATRIX Legend: Least Preferred Most Preferred Natural Environment Terrestrial Ecosystems Avoids regulated SAR habitat. Avoids regulated SAR habitat. Avoids creating a new crossing of the features.

More information

Commissioners Road West. Municipal Class Environmental Assessment. City of London

Commissioners Road West. Municipal Class Environmental Assessment. City of London Commissioners Road West Municipal Class Environmental Assessment Commissioners Road West Realignment from Springbank Drive/Byron Baseline Road to Cranbrook Road ENVIRONMENTAL STUDY REPORT B000615 Commissioners

More information

Second Line West Pedestrian/Cyclist Crossing of Highway 401 Class EA. Second Line West Pedestrian/Cyclist Crossing of Highway 401 Class EA

Second Line West Pedestrian/Cyclist Crossing of Highway 401 Class EA. Second Line West Pedestrian/Cyclist Crossing of Highway 401 Class EA 1 1 Purpose of Public Information Centre #2 To provide interested and/or potentially affected stakeholders with an opportunity to participate in the planning and decision-making process for this Municipal

More information

City of Grande Prairie Development Services Department KENNEDY DEVELOPMENTS LTD. OUTLINE PLAN OP-09-01

City of Grande Prairie Development Services Department KENNEDY DEVELOPMENTS LTD. OUTLINE PLAN OP-09-01 City of Grande Prairie Development Services Department KENNEDY DEVELOPMENTS LTD. OUTLINE PLAN OP-09-01 July 27, 2009 TABLE OF CONTENTS 1.0 Introduction... 1 1.1 Plan Area Location & Context... 1 1.2 Ownership

More information

Toronto Complete Streets Guidelines

Toronto Complete Streets Guidelines Toronto Complete Streets Guidelines 108 110 7.1 Green Infrastructure Design Principles 112 7.2 Context-Sensitive Green Streets 114 7.3 Key Green Street Elements Green infrastructure refers to natural and

More information

AMENDMENT NO. 30 TO THE OFFICIAL PLAN OF THE TOWN OF MILTON

AMENDMENT NO. 30 TO THE OFFICIAL PLAN OF THE TOWN OF MILTON AMENDMENT NO. 30 TO THE OFFICIAL PLAN OF THE TOWN OF MILTON Subject: Boyne Survey Secondary Plan and Related Official Plan Amendments The following text and schedules constitute Amendment No. 30 to the

More information

Rapid Transit Implementation Working Group

Rapid Transit Implementation Working Group Rapid Transit Implementation Working Group October 12, 2017 1 Agenda 1. Consultation Update 2. Technical Work Update 3. LTC Rapid Transit Integration 4. Next Steps 2 Consultation Update 3 Consultation

More information

Elevated Water Storage Facility and Pumping Station Municipal Class EA for Pressure District 7: PIC # 1 Summary

Elevated Water Storage Facility and Pumping Station Municipal Class EA for Pressure District 7: PIC # 1 Summary Memorandum DATE: March 14, 2018 TO: FROM: CC: OUR REF.#: SUBJECT: Winston Wang, M.A.Sc., P.Eng Project Manager, City of Hamilton Jennifer Whittard, B.E.S., PMP Shelley Kuan, Jessica Mollo WM16-0435 Elevated

More information

Shift Rapid Transit Public Participation Meeting May 3, 2017

Shift Rapid Transit Public Participation Meeting May 3, 2017 Shift Rapid Transit Public Participation Meeting May 3, 2017 Shift Rapid Transit Initiative Largest infrastructure project in the city s history. Rapid Transit initiative will transform London s public

More information

Asbury Chapel Subdivision Sketch Plan

Asbury Chapel Subdivision Sketch Plan Asbury Chapel Subdivision Sketch Plan PART 1: PROJECT SUMMARY Applicant: NVR Inc. Project Size: +/- 76.13 acres Parcel Numbers: 02101112,02116101,02116112, 02116113 Current Zoning: Transitional Residential

More information

SECTION 4(f) DE MINIMIS DOCUMENTATION

SECTION 4(f) DE MINIMIS DOCUMENTATION SECTION 4(f) DE MINIMIS DOCUMENTATION Illinois Route 60/83 IL 176 to the intersection of IL 60 (Townline Road) Lake County P-91-084-07 Mundelein Park and Recreation District Project Limit SECTION 4(f)

More information

ELMVALE ACRES SHOPPING CENTRE MASTER PLAN

ELMVALE ACRES SHOPPING CENTRE MASTER PLAN ELMVALE ACRES SHOPPING CENTRE MASTER PLAN Contents 1.0 INTRODUCTION... 2 2.0 LOCATION... 2 3.0 EXISTING CONTEXT... 2 4.0 VISION & GUIDING PRINCIPLES... 2 5.0 LAND USE AND BUILT FORM... 4 5.1 St. Laurent

More information

The Gore Road Queen Street East to Castlemore Road

The Gore Road Queen Street East to Castlemore Road Municipal Class Environmental Assessment The Gore Road Queen Street East to Castlemore Road Public Open House # 1 Date: Thursday May 29, 2014 Time: 5:30pm to 8:30pm Location: Gore Meadows Community Centre

More information

Services Department F May 28, 2007

Services Department F May 28, 2007 Report To: Development Services Committee Item: Date of Report: From: DS-07-144 May 23, 2007 Commissioner, Development File: Date of Meeting: Services Department F-7000-0013 May 28, 2007 Subject: Gibb

More information

Station Street/Haig Road Extension Environmental Assessment (EA)Study. Welcome

Station Street/Haig Road Extension Environmental Assessment (EA)Study. Welcome Station Street/Haig Road Extension Environmental Assessment (EA)Study Welcome Welcome to this Public Information Centre (PIC) meeting. Please record your attendance and obtain a comment sheet at the registration

More information

Blackfriars Bridge Municipal Class Environmental Assessment. Public Information Centre #1 November 19 th, 2014

Blackfriars Bridge Municipal Class Environmental Assessment. Public Information Centre #1 November 19 th, 2014 Blackfriars Bridge Municipal Class Environmental Assessment Public Information Centre #1 November 19 th, 2014 Why are you here tonight? To determine the future requirements of the river crossing at Blackfriars

More information

The purpose of tonight s PIC is to:

The purpose of tonight s PIC is to: The purpose of tonight s PIC is to: Provide an overview of the work completed to date and a summary of the Class EA process being followed; Provide a summary of public input received so far, including

More information

OP Council Resolution June 16, Planning and Development Services

OP Council Resolution June 16, Planning and Development Services OP-08-01 Council Resolution June 16, 2008 Planning and Development Services Kingsgate Landing Outline Plan Table of Contents 1.0 Introduction 1 1.1 Purpose of Plan 1 1.2 Plan Area Location 1 1.3 Ownership

More information

9 th Street Sub Area Plan

9 th Street Sub Area Plan 9 th Street Sub Area Plan In the 1990 s, when the Township prepared the last Master Plan, the 9 th Street corridor was studied as part of a larger 9 th Street Focus Area that included the West Main Street

More information

North York Centre South Service Road

North York Centre South Service Road North York Centre South Service Road Municipal Class Environmental Assessment Addendum Potential Changes to Doris Avenue, Bonnington Place & Tradewind Avenue Study Summary (June 11, 2015) toronto.ca/nyc-south-road.

More information

Appendix M4 - Part 1. Public Information Centre Summary Report. Appendix M4

Appendix M4 - Part 1. Public Information Centre Summary Report. Appendix M4 Appendix M4 - Part 1 Public Information Centre Summary Report Appendix M4 Public Information Centre Summary Report Sheridan Park Drive Municipal Class Environmental Assessment City of Mississauga R.J.

More information

Burloak Drive Grade Separation

Burloak Drive Grade Separation Burloak Drive Grade Separation Transit Project Assessment Process Public Meeting #1 March 30, 2017 GO Lakeshore West Service Plan Weekday Rush Hour 15-minute, two-way service between Aldershot* and Union

More information

WELCOME! 8 8:30 6: TH STREET IMPROVEMENTS. Open House. Presentation & Q&A

WELCOME! 8 8:30 6: TH STREET IMPROVEMENTS. Open House. Presentation & Q&A WELCOME! 168 TH STREET IMPROVEMENTS 6:30 Open House 7 8 Presentation & Q&A 8 8:30 Open House WELCOME Todd Pfitzer City of Omaha Engineer Bob Stubbe City of Omaha Public Works Director Jon Meyer Project

More information

McKay Road Interchange and Salem / Lockhart Crossing

McKay Road Interchange and Salem / Lockhart Crossing McKay Road Interchange and Salem / Lockhart Crossing The McKay Road Interchange Class EA has two components: 1. A new MacKay Road Interchange at Highway 400; and 2. A new bridge crossing of Highway 400

More information

Drexel, Barrell & Co.

Drexel, Barrell & Co. Drexel, Barrell & Co. June 18, 2018 Engineers/Surveyors Boulder Colorado Springs Greeley 3 South 7 th Street Colorado Springs, Colorado 80905-1501 719 260-0887 719 260-8352 Fax El Paso County Planning

More information

PREPARED FOR: PLATTEVIEW ROAD CORRIDOR STUDY EXECUTIVE SUMMARY

PREPARED FOR: PLATTEVIEW ROAD CORRIDOR STUDY EXECUTIVE SUMMARY PREPARED FOR: PLATTEVIEW ROAD CORRIDOR STUDY EXECUTIVE SUMMARY SEPTEMBER 2016 Introduction The Platteview Road Corridor Study was led by the Metropolitan Area Planning Agency (MAPA) with assistance from

More information

Public Information Centre No. 1 King-Vaughan Road Bridge Replacement Municipal Class Environmental Assessment City of Vaughan

Public Information Centre No. 1 King-Vaughan Road Bridge Replacement Municipal Class Environmental Assessment City of Vaughan Public Information Centre No. 1 King-Vaughan Road Bridge Replacement Municipal Class Environmental Assessment City of Vaughan Date: April 7, 2016 Location: Al Palladini Community Centre, Meeting Room #1

More information

Victoria Bridge Municipal Class EA Civic Works Committee

Victoria Bridge Municipal Class EA Civic Works Committee Municipal Class EA John Pucchio, P. Eng., Project Manager June 19 2018 Introduction Existing Conditions Municipal Class EA Proposed Bridge Proposed Road Reconstruction Proposed Improvements Construction

More information

CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON AUGUST 13, 2018

CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON AUGUST 13, 2018 TO: FROM: SUBJECT: CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON AUGUST 13, 2018 KELLY SCHERR, P.ENG., MBA, FEC MANAGING DIRECTOR, ENVIRONMENTAL & ENGINEERING SERVICES AND CITY ENGINEER ADELAIDE STREET

More information

Introduction. Public Information Package. Project website. Overview. Class Environmental Assessment Process

Introduction. Public Information Package. Project website. Overview. Class Environmental Assessment Process 1 Introduction Public Information Package Baseline Road Extension between Lambs Road and Bennett Road, Bowmanville Schedule B Municipal Class Environmental Assessment November 6, 2017 Overview The purpose

More information

London s Bus Rapid Transit System

London s Bus Rapid Transit System London s Bus Rapid Transit System HERITAGE WORKSHOP November 7, 2017 1 Agenda 1. Introductions 2. Overview of Transit Project Assessment Process 3. Archaeology and Heritage Approval Process 4. Role of

More information

WELCOME TO PUBLIC INFORMATION CENTRE #2. Please Sign In

WELCOME TO PUBLIC INFORMATION CENTRE #2. Please Sign In WELCOME TO PUBLIC INFORMATION CENTRE #2 Replacement of Oxtongue Lake Narrows Bridge & Oxtongue River Bridge, Highway 60 (G.W.P. 93-89-00 & G.W.P. 5550-04-00) Class Environmental Assessment (Group B) Please

More information

Description of Preferred Alternative

Description of Preferred Alternative Chapter 2 Description of Preferred Alternative 2.1 Introduction This chapter of the programmatic Sammamish Town Center Sub-area Plan Final EIS provides a more detailed description of the Preferred Alternative

More information

Land Use Amendment in Southwood (Ward 11) at and Elbow Drive SW, LOC

Land Use Amendment in Southwood (Ward 11) at and Elbow Drive SW, LOC 2018 November 15 Page 1 of 10 EXECUTIVE SUMMARY This land use amendment application was submitted by Rick Balbi Architect on 2017 August 31 on behalf of Sable Developments Ltd, and with authorization from

More information

Public Hearing. Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 14, open house at 4 p.m., formal presentation at 5 p.m.

Public Hearing. Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 14, open house at 4 p.m., formal presentation at 5 p.m. Public Hearing Charlotte County-Punta Gorda MPO - Meeting Rooms A and B March 14, 2019 open house at 4 p.m., formal presentation at 5 p.m. Welcome to the Public Hearing for the Harborview Road (CR 776)

More information

SH 199 Corridor Master Plan. Community Meeting No. 2 May 31, 2017

SH 199 Corridor Master Plan. Community Meeting No. 2 May 31, 2017 Community Meeting No. 2 May 31, 2017 Transportation Projects On or Near SH 199 SH 199 from 0.3 miles south of FM 1886 to south end of Lake Worth bridge Construct freeway mainlanes and frontage roads 10-Year

More information

URBAN DESIGN BRIEF 305, 309, & 315 SOUTHDALE ROAD WEST LONDON ONTARIO

URBAN DESIGN BRIEF 305, 309, & 315 SOUTHDALE ROAD WEST LONDON ONTARIO URBAN DESIGN BRIEF 305, 309, & 315 SOUTHDALE ROAD WEST LONDON ONTARIO CARVEST PROPERTIES LTD. December 2013 Section 1 - Land Use Planning Context 1.1 Subject Lands The subject lands are located immediately

More information

ROAD CLOSURE AND LAND USE AMENDMENT SILVER SPRINGS (WARD 1) NORTHEAST OF NOSEHILL DRIVE NW AND SILVER SPRINGS ROAD NW BYLAWS 2C2018 AND 29D2018

ROAD CLOSURE AND LAND USE AMENDMENT SILVER SPRINGS (WARD 1) NORTHEAST OF NOSEHILL DRIVE NW AND SILVER SPRINGS ROAD NW BYLAWS 2C2018 AND 29D2018 Page 1 of 19 EXECUTIVE SUMMARY This application proposes redesignating two parcels in the community of Silver Springs from Special Purpose Future Urban Development (S-FUD) District and undesignated road

More information

REVISED Terms of Reference. Riverbend South Secondary Plan. Sifton Properties Limited. May 30, Prepared by: London, ON. In Association With:

REVISED Terms of Reference. Riverbend South Secondary Plan. Sifton Properties Limited. May 30, Prepared by: London, ON. In Association With: REVISED Terms of Reference Riverbend South Secondary Plan Sifton Properties Limited Prepared by: Sifton Properties Limited London, ON In Association With: Stantec Consulting AECOM Golder Associates Paradigm

More information

280 Manse Road - Official Plan Amendment, Zoning Amendment, Draft Plan of Subdivision Applications - Preliminary Report

280 Manse Road - Official Plan Amendment, Zoning Amendment, Draft Plan of Subdivision Applications - Preliminary Report STAFF REPORT ACTION REQUIRED 280 Manse Road - Official Plan Amendment, Zoning Amendment, Draft Plan of Subdivision Applications - Preliminary Report Date: March 11, 2014 To: From: Wards: Reference Number:

More information

Rapid Transit Implementation Working Group September 14, 2017

Rapid Transit Implementation Working Group September 14, 2017 Rapid Transit Implementation Working Group September 14, 2017 BACKGROUND Council approved the Rapid Transit Master Plan and Updated Business Case on July 25, 2017. Approval of the RTMP confirmed the BRT

More information

Services Department B September 10, 2007

Services Department B September 10, 2007 Report To: Development Services Committee Item: Date of Report: DS-07-246 September 5, 2007 From: Commissioner, Development File: Date of Meeting: Services Department B7200-0001 September 10, 2007 Subject:

More information

Executive Summary. The goals of the Plan are to:

Executive Summary. The goals of the Plan are to: Executive Summary The Wiscasset Bath Road Master Plan (Plan) seeks to maximize development opportunities along Bath Road through the strategic coordination of traffic infrastructure improvements, land

More information

Public Information Centre

Public Information Centre Public Information Centre Sunnidale Road Highway 400 Transmission i Watermain Crossing January 31, 2012 Sir Robert Barrie Room, 2 nd Floor, City Hall 4:00 pm to 7:00 pm As part of the Environmental Assessment

More information

Pipeline Trail Master Plan Preliminary Concept Design. O Connor Mokrycke Consultants May 14, 2015 meeting

Pipeline Trail Master Plan Preliminary Concept Design. O Connor Mokrycke Consultants May 14, 2015 meeting Pipeline Trail Master Plan Preliminary Concept Design O Connor Mokrycke Consultants May 14, 2015 meeting 1 Purpose of the Meeting: - Share information regarding traffic studies - Present ideas arising

More information

WEST HILL BUSINESS PARK AREA STRUCTURE PLAN

WEST HILL BUSINESS PARK AREA STRUCTURE PLAN MUNICIPAL DISTRICT OF PEACE NO. 135 WEST HILL BUSINESS PARK AREA STRUCTURE PLAN Prepared by: TABLE OF CONTENTS 1.0 Introduction... 1 1.1 Purpose of Plan........ 1 1.2 Plan Area..... 1 1.3 Existing Conditions...

More information

Public Information Centre # 2 Coronation Park Drainage Improvements Town of Oakville Municipal Class Environmental Assessment

Public Information Centre # 2 Coronation Park Drainage Improvements Town of Oakville Municipal Class Environmental Assessment November 26, 2014 Public Information Centre # 2 Coronation Park Drainage Improvements Town of Oakville Municipal Class Environmental Assessment Study Area & Drainage System Legend Coronation Project Park

More information

Focus Group First Meeting Belfountain Community Centre Tuesday June 29, :00 p.m. to 9:00 p.m.

Focus Group First Meeting Belfountain Community Centre Tuesday June 29, :00 p.m. to 9:00 p.m. Focus Group First Meeting Belfountain Community Centre 7:00 p.m. to 9:00 p.m. Mississauga Road/Old Main Street and Bush Street, from Olde Base Line Road to Winston Churchill Boulevard Environmental Assessment

More information

Southwest Transitway Extension Baseline Road to Norice Street. Environmental Assessment Minor Modification Report

Southwest Transitway Extension Baseline Road to Norice Street. Environmental Assessment Minor Modification Report Southwest Transitway Extension Baseline Road to Norice Street Environmental Assessment Minor Modification Report September 2009 Environmental Assessment Minor Modification Report Southwest Transitway

More information

Drexel, Barrell & Co.

Drexel, Barrell & Co. Drexel, Barrell & Co. December 21, 2018 Engineers/Surveyors Boulder Colorado Springs Greeley 3 South 7 th Street Colorado Springs, Colorado 80905-1501 719 260-0887 719 260-8352 Fax El Paso County Planning

More information

Baby Point Wastewater Pumping Station Forcemain Class Environmental Assessment Study

Baby Point Wastewater Pumping Station Forcemain Class Environmental Assessment Study Baby Point Wastewater Pumping Station Forcemain Class Environmental Assessment Study Public Drop-in Event 1 Thursday, October 12, 2017 6:00 p.m. to 8:00 p.m. Humbercrest United Church Welcome Welcome to

More information

WELCOME TO THE PUBLIC INFORMATION CENTRE. Please Sign In

WELCOME TO THE PUBLIC INFORMATION CENTRE. Please Sign In WELCOME TO THE PUBLIC INFORMATION CENTRE Replacement of Oxtongue Lake Narrows Bridge & Oxtongue River Bridge, Highway 60 (G.W.P. 93-89-00 & G.W.P. 5550-04-00) Class Environmental Assessment (Group B) Please

More information

The transportation system in a community is an

The transportation system in a community is an 7 TRANSPORTATION The transportation system in a community is an important factor contributing to the quality of life of the residents. Without a sound transportation system to bring both goods and patrons

More information

Environmental Study Report

Environmental Study Report Environmental Study Report Britannia Road (Regional Road 6) Transportation Corridor Improvements The Regional Municipality of Halton TN1390TNA00 The Regional Municipality of Halton 1151 Bronte Road Oakville,

More information

HURON COMMUNITY PLAN

HURON COMMUNITY PLAN CITY OF KITCHENER DEPARTMENT OF DEVELOPMENT AND TECHNICAL SERVICES PD 94/7 HURON COMMUNITY PLAN Recommended by Planning and Economic Development Committee: October 31, 1994 Adopted by Kitchener City Council:

More information

City of Grande Prairie Development Services Department

City of Grande Prairie Development Services Department City of Grande Prairie Development Services Department ROYAL OAKS NORTH OUTLINE PLAN OP-07-03 NW 35-71-6 W6M May 7, 2007 Royal Oaks North Outline Plan TABLE OF CONTENTS 1.0 INTRODUCTION........ 3 1.1 Purpose

More information

Welcome. Walk Around. Talk to Us. Write Down Your Comments

Welcome. Walk Around. Talk to Us. Write Down Your Comments Welcome This is an information meeting introducing the applications for proposed redevelopment of the Yorkdale Shopping Centre site at 3401 Dufferin Street and 1 Yorkdale Road over the next 20+ years,

More information

4780 Eglinton Avenue West - Zoning By-law Amendment and Draft Plan of Subdivision Applications - Preliminary Report

4780 Eglinton Avenue West - Zoning By-law Amendment and Draft Plan of Subdivision Applications - Preliminary Report STAFF REPORT ACTION REQUIRED 4780 Eglinton Avenue West - Zoning By-law Amendment and Draft Plan of Subdivision Applications - Preliminary Report Date: May 29, 2014 To: From: Wards: Reference Number: Etobicoke

More information

5.0 Community Design Plan

5.0 Community Design Plan 5.0 Community Design Plan The Community Design Plan for the Mer Bleue area is a composite of three plans: Land Use Plan Transportation Plan Municipal Servicing Plan Read together, these Plans and associated

More information

UTSC SECONDARY PLAN COMMUNITY OPEN HOUSE

UTSC SECONDARY PLAN COMMUNITY OPEN HOUSE WELCOME TO THE UTSC SECONDARY PLAN COMMUNITY OPEN HOUSE 1 Welcome to the first Community Open House for the UTSC Secondary Plan. Hosted by the University of Toronto Scarborough (UTSC), the following panels

More information

C ity of Grande Prairie Development Services Department

C ity of Grande Prairie Development Services Department C ity of Grande Prairie Development Services Department FAIRWAY DEVELOPMENT OUTLINE PLAN OP 08 09 Approved April 6, 2009 Prepared by: Focus Corporation Table of Contents 1.0. Introduction 2 3 1.1. Plan

More information

Master Plan Class Environmental Assessment for Downtown Mississauga Road Improvements

Master Plan Class Environmental Assessment for Downtown Mississauga Road Improvements Master Plan Class Environmental Assessment for Downtown Mississauga Road Improvements Public Information Centre # 1 Wednesday June 25, 2014 5:30 p.m. to 8:00 p.m. Mississauga Civic Centre Great Hall Welcome

More information

PROJECT BACKGROUND. Preliminary Design Scope and Tasks

PROJECT BACKGROUND. Preliminary Design Scope and Tasks PROJECT BACKGROUND Preliminary Design Scope and Tasks The purpose of this Study is the development of preliminary designs for intersection improvements for Trunk Highway (TH) 36 at the intersections of

More information

S o u t h C e n t r a l O u t l i n e P l a n. Leduc Business Park. North Leduc Industrial Area Structure Plan C it y of Led u c.

S o u t h C e n t r a l O u t l i n e P l a n. Leduc Business Park. North Leduc Industrial Area Structure Plan C it y of Led u c. Leduc Business Park North Leduc Industrial Area Structure Plan C it y of Led u c Prepared for Farm Air Properties Inc. January, 2007 Table of Contents Page Number 1.0 Purpose of Plan and Definition of

More information