Document Code: 1 (5) Issuing date: Status:
|
|
- Roland Evans
- 5 years ago
- Views:
Transcription
1 Document Code: 1 (5) Project : MULTI FUEL CFB BOILER SIMULATOR Author: Approved: Language: JJA Document title: SYSTEM DESCRIPTION MAIN CONDENSATE PUMPING Submitted for: Customer reference: Other information:
2 Document Code: 2 (5) TABLE OF CONTENTS 1 GENERAL DESIGN DATA EQUIPMENT DATA AUTOMATION AND INSTRUMENTATION Condenser level control OPERATION Start-up Normal operation Operating disturbances CONNECTED SYSTEMS... 5
3 Document Code: 3 (5) 1 GENERAL Function of the main condensate pumping system is to pump condensate from the condenser through the LP preheaters to feed water tank. It also supplies spray water to the LP bypass station (S1 LBB20 AA201) to be adjusted with control valve (S1 LCE10 AA201) and cooling/seal water for Turbine Island users. System is shown on P&I diagram S1LC -MFB1001. Condenser itself (also the gland steam condenser) is in Turbine Island scope of supply. The system is equipped with 2x100 % main condensate pumps (S1 LCB10/20 AP101). During normal operation one pump is running with constant rotation speed and the level in the condenser is regulated with control valve S1 LCA30 AA201. From the condenser water is pumped through LP preheaters (3 pcs.) to feed water tank. Flows entering the condenser are: Turbine exhaust Cold reheat Feed water HP- & LP preheaters and turbine drainages LP 1 preheater condensate Demineralised make-up water (according to feed water tank level) Steam from LP preheater by-pass station (start-up, turbine trip, shut-down) After the pumps there is a flow measurement and during the start-up / other boiler part load situation adequate flow for the pumps is secured with minimum flow valve. From the hot reheat piping there is a LP bypass station to condenser. Bypass station is used during start-up / shutdown and in case of steam turbine trip. Spray water for the LP bypass is taken from the main condensate pumps. In steam turbine trip bypass station in controlling hot reheat steam pressure and large amount of condensate is taken quickly to spray water purposes (hydraulic valves). In order to keep the main condensate pumps in right operation range, in turbine trip second main condensate pump is started automatically. Both main condensate pumps are running always when LP-bypass is at maximum. From the main condensate line water is taken also to steam turbine cooling during start-up- / shutdown and sealing waters to valve / water seals. During normal operation these connections are closed.
4 Document Code: 4 (5) 2 DESIGN DATA System design is based on situation where boiler load is at 100 % (ambient air +9 C, cooling water +12 C) and make-up up water flow is calculated based on 3 % blow down. When LPbypass is at maximum flow (turbine trip), both main condensate pumps are running. 3 EQUIPMENT DATA Main condensate pumps S1 LCB10/20 AP101 Function of the main condensate pumps is to pump condensate arising to condenser through the LP preheaters to feed water tank. Pumps are located in the pump pit underneath condenser. Number of units 2x 100 % Type KSB / MTC-A 150/ Flow rate 80,1 kg/s Head 159 m Pumping temperature 23 C Motor power 200 kw 4 AUTOMATION AND INSTRUMENTATION 4.1 Condenser level control Main condensate pumps are running with constant speed and the level is controlled with valve S1LCA30 AA201. Low-level protection for the main condensate pumps is done by level measurement interlock and low-level switch. To main condensate pumping is also related the minimum flow control. During start-up and other low load situations minimum flow for the pumps and for the gland steam condenser is ensured with control loop FIC S1 LCA30 CF201.
5 Document Code: 5 (5) 5 OPERATION 5.1 Start-up Turbine and condenser start-up (vacuum pumps etc.) in detail is in Turbine Manufacturers scope of supply. Before the main condensate pumping system can be started, condenser and suction lines to pumps are filled with water. One main condensate pump is started against closed discharge valve (motorised), control valve S1 LCA30 AA201 is closed. Motorised valve S1 LCA10 AA101 (or S1 LCA20 AA101) is opened partly. When pressure S1 LCA30 CP201 after the pump starts to increase, also the minimum flow valve is opened partly. Finally motorised valve is opened fully and minimum flow control S1 LCA30 AA201/-CF201 is set to Auto mode. Piping system from the control valve S1 LCA30 AA201 to feed water tank is filled by opening control valve partly. In initial start-up lines are vented manually. When the system is filled with water, condenser level control LICSA S1MAG10 CL201 is set to Auto mode. In hot/ warm start-up (lines / heat exchangers full of water) start-up procedure can be handled from the control room. Main condensate pump is started against closed MOV (S1 LCA10/20 AA101) and the valve is opened. Both minimum flow control and condenser level control are set to Auto mode. 5.2 Normal operation One main condensate pump is running while the other is stand-by. All the condensates from the condenser are pumped to feed water tank and connections to LP bypass spray and to turbine cooling are closed. 5.3 Operating disturbances. Failure of the running main condensate pump Second pump will automatically start. Turbine trip Second main condensate pump starts and LP bypass station is opened automatically. 6 CONNECTED SYSTEMS LP preheating system HP steam system Condenser Feed water system HP preheaters Make up water system S1 LCC -MFB1001 S1 LB -MFB1001 S1 LB -BFB2506 S1 LA -MFB1001 S1 LAD -MFB1001 S1 GHC -MFB1001
Document Code: 1 (13) Issuing date: Status:
Document Code: 1 (13) Project : MULTI FUEL CFB BOILER SIMULATOR Author: Approved: Language: JJA Document title: SYSTEM DESCRIPTION REHEAT STEAM SYSTEM Submitted for: Customer reference: Other information:
More informationDocument Code: 1 (15) Issuing date: Status:
Document Code: 1 (15) Project : MULTI FUEL CFB BOILER SIMULATOR Author: Approved: Language: HSK Document title: SYSTEM DESCRIPTION BOILER WATER SYSTEM Submitted for: Customer reference: Other information:
More informationDocument code: 1 (10) Issuing date: Status:
Document code: 1 (10) Project : MULTI FUEL CFB BOILER SIMULATOR Author: Approved: Language: JJA Document title: SYSTEM DESCRIPTION DUCT BURNERS Submitted for: Customer reference: Other information: Document
More informationCHAPTER 3 BASIC STEAM CYCLE
CHAPTER 3 BASIC STEAM CYCLE To understand steam generation, you must know what happens to the steam after it leaves the boiler. A good way to learn the steam plant on your ship is to trace the path of
More informationSULPHUR RECOVERY UNIT
19 October 2015 SULPHUR RECOVERY UNIT START-UP CONSIDERATIONS SHRIKANT KOLI BLACK & VEATCH, MUMBAI Agenda - Burner Management System - Control Loops - Refractory Dry-Out - Start-up Experiences 2 Burner
More informationAnnex A-8 CONCENTRATED SOLAR POWER UNITS INDEX TO SYSTEM/COMPONENT CAUSE CODES
Annex A-8 CONCENTRATED SOLAR POWER UNITS INDEX TO SYSTEM/COMPONENT CAUSE CODES SOLAR ENERGY GATHERING EQUIPMENT Solar Field 6500-6559 Thermal Storage 6570-6589 Operational Problems 6590-6599 STEAM TURBINE
More informationSteam and Power Conversion System
9 Chapter Major Balance-of-Plant Features It is difficult to completely standardize the plant design beyond the nuclear island. In addition to utility preferences in the steam and power conversion system,
More informationCold Weather Preparedness Plant Winterization Lessons Learned & Best Practices
Cold Weather Preparedness Plant Winterization Lessons Learned & Best Practices Cold Weather Preparedness RF Criteria For Plant Visits: Generating facilities that experienced repeated freezing or cold weather
More informationFoster Wheeler Condensers and Feedwater Heaters. High Quality Steam Components
Foster Wheeler Condensers and Feedwater Heaters High Quality Steam Components A HISTORY OF EXCELLENCE IN THE DESIGN AND FABRICATION OF CONDENSER AND FEEDWATER HEATER EQUIPMENT 1 SAFELY DELIVERING COST-EFFECTIVE,
More informationClearFire Economizer Model ECF Integral or External. Addendum to manuals CFH and CFV
ClearFire Economizer Model ECF Integral or External Addendum to manuals 750-295 CFH and 750-269 CFV CB-8466 08/2011 1-GENERAL The Model ECF economizer is a stainless steel coil tube arrangement using
More informationExisting Mechanical System Operation
majority of the air handlers. There are louvers along the north side of the building that allow for outdoor air to come in and feed the air handlers. On levels 4-8 the research laboratories are variable
More informationANNEX A-1 GEOTHERMAL UNITS INDEX TO SYSTEM/COMPONENT CAUSE CODES BOILER BALANCE OF PLANT STEAM TURBINE GENERATOR MISCELLANEOUS - GEOTHERMAL EXTERNAL
ANNEX A-1 GEOTHERMAL UNITS INDEX TO SYSTEM/COMPONENT CAUSE CODES Boiler Piping System 0500-0620 Condensing System 3110-3199 Circulating Water Systems 3210-3285 Waste Water (zero discharge) 3290-3299 Condensate
More informationEfficiency Maximiser for Solid Fuel Central Heating
Efficiency Maximiser for Solid Fuel Central Heating INSTALLATION AND TECHNICAL MANUAL CONTENTS CONTENTS AND CAUTION 1 INTRODUCTION AND INSTRUCTIONS BEFORE LIGHTING BOILER STOVE 2 INSTALLATION INSTRUCTIONS
More informationDocument Code: 1 (6) Issuing date: Status:
Document Code: 1 (6) Issuing date: Status: Project : MULTI FUEL CFB BOILER SIMULATOR Author: Approved: Employer: JJA Document title: SYSTEM DESCRIPTION BOTTOM ASH SYSTEM Submitted for: Employer reference:
More informationCONTENTS. B. System Design and Performance Requirements
15625 Water Chillers This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications or in notes
More informationSilhouette. Feedwater Heater. Boiler Feedwater
Roth Roth Low Low Silhouette Silhouette TRAY DEAERATORS Boiler Boiler Feedwater Feedwater Heater Heater Capacities Capacities to to 50,000 50,000 lb/hr lb/hr Model RDTV-150-5-1-2 vertical tray type deaerator
More informationSteam Generator (Boiler) & Steam Turbine. Steam Generator (Boiler) ME 268. Model Lab
Steam Generator (Boiler) ME 268 Model Lab Aashique Alam Rezwan Lecturer Department of Mechanical Engineering, BUET, Dhaka-1000 http://teacher.buet.ac.bd/aashiquear ME 268 Aashique Alam Rezwan 1 Modern
More informationBuildingName The Description of the Project P DOCUMENTS
ARCHITECTURE, ENGINEERING AND CONSTRUCTION P00000000 0000 DOCUMENTS ARCHITECTURE & ENGINEERING 326 East Hoover, Mail Stop B Ann Arbor, MI 48109-1002 Phone: 734-764-3414 Fax: 734-936-3334 SPECIFICATION
More informationCity of Duluth Festival Center 04/25
SECTION 230593 - TESTING, ADJUSTING, AND BALANCING FOR HVAC PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and
More informationTITLE: SPECIFICATION NO. PE-MSE-VD-ACC VOLUME:
(For Vendor Registration Purpose) SHEET 1 of 6 1.00.00 GENERAL INFORMATION 1.01.00 The general guidelines as illustrated in the subsequent clauses of this section shall be applicable for air cooled condenser
More informationRaising the Efficiency of Gas-Fired Power Plants and CCPP. GEA Heat Exchangers
Raising the Efficiency of Gas-Fired Power Plants and CCPP Content 1 2 Double-Tube Safety Gas Preheater Technology Basics (Equipment/Technology) Detection Successful Application Basic reasons for installation
More informationOn-Load Boiler Cleaning with Steam
On-Load Boiler Cleaning with Steam CBW Clyde Bergemann Wesel 10.2007 - Rev. 5 March 16, 2018 FPK II Combustion Chemistry II Åbo Akademi University, Åbo Content Steam sootblower solution Different types
More informationSingle Zone System. One duct system Used mostly in small buildings Forced air system All spaces controlled by a single thermostat Single air return
Single Zone System One duct system Used mostly in small buildings Forced air system All spaces controlled by a single thermostat Single air return Multi Zone System Used in small to medium sized buildings
More informationMILL IN SERVICE FIRST COAL FIRES AT MEDUPI
Smoke from Chimney Tuesday 2 nd December 2014 MILL IN SERVICE FIRST COAL FIRES AT MEDUPI First Coal Fires On Thursday 27 th November the team at Medupi successfully brought the first mill into service
More information/ / Take the technological step into MODERN Condensate Handling Equipment for steam systems MANUFACTURED IN AMERICA with craftsmanship and quality.
Take the technological step into MODERN Condensate Handling Equipment for steam systems MANUFACTURED IN AMERICA with craftsmanship and quality. Condensate Return Units / Shippensburg / / Fill Tanks / Boiler
More informationBoiler Condensate Return Basics. Presented by Steve Connor February 24, 2016
Boiler Condensate Return Basics Presented by Steve Connor February 24, 2016 What We Are Covering Today? Brief review of the total steam system Why a proper condensate return system is so important Condensate
More informationRenovation, Modernization and Life Time Extension Measures on Steam Turbines Sustainable Growth - Strategies for efficiency Increase
NTPC O&M CONFERENCE 2013 Renovation, Modernization and Life Time Extension Measures on Steam Turbines Sustainable Growth - Strategies for efficiency Increase Subrata Kumar Kundu, Siemens Ltd. & Markus
More informationCONSIDERATIONS IN CONVERTING A DUAL SHELL OR A DUAL PRESSURE COAL FIRED PLANT CONDENSER INTO A COMBINED CYCLE PLANT CONDENSER
Proceedings of the ASME 2013 Power Conference POWER2013 July 29-August 1, 2013, Boston, Massachusetts, USA POWER2013-98062 CONSIDERATIONS IN CONVERTING A DUAL SHELL OR A DUAL PRESSURE COAL FIRED PLANT
More informationCOMcheck Software Version Mechanical Compliance Certificate
COMcheck Software Version 4.0.6.2 Mechanical Compliance Certificate Project Information Energy Code: Location: Climate Zone: Project Type: 90.1 (2007) Standard HALCYON Bldg. 400 Alpharetta, Georgia 3a
More informationHEAT GENERATION 1.01 RELATED CORNELL DESIGN AND CONSTRUCTION STANDARDS. B. Section HVAC Basic Materials and Methods
230520 HEAT GENERATION Cornell s Design and Construction Standards provide mandatory design constraints and acceptable or required products for all construction at Cornell University. These standards are
More informationImproved safety system in a nitric acid plant
NITR IC ACI D ALAR ARM AND SAFE FETY SYSTEM Improved safety system in a nitric acid plant The existing alarm and safety system in a nitric acid plant in Croatia was replaced by a new microprocessor-based
More informationElement D Services Heating, Ventilating, and Air Conditioning
PART 1 - GENERAL 1.01 OVERVIEW A. This section includes criteria for the design of building heat generating systems including all isolation valves and steam piping and fittings, steam specialties, control
More informationLaboratory exercise 3: Condensing water heater
Chapter 1 Laboratory exercise 3: Condensing water heater The laboratory exercise Condensing water heater is placed on the Faculty of Mechanical Engineering in the Laboratory for Water and Turbine Machinery.
More informationNEW CHILLER SCHEDULE
TITLE: REPLACE CHILLER MACC MAXIMO # 4542690 PROJECT # 14M108CN MACC # 14-0459 ATTACHMENTS: 1. MAXIMO Equipment update form SCOPE OF WORK: The contractor shall provide all material, labor, equipment, and
More informationTECHNICAL SPECIFICATIONS FOR PLUSHER WDS 12 SERIES INSTRUMENT WASHER DISINFECTORS
TECHNICAL SPECIFICATIONS FOR PLUSHER WDS 12 SERIES INSTRUMENT WASHER DISINFECTORS PRODUCT PLUSHER WDS 12 series instrument washer disinfectors are offered with single or double door formation with manual
More informationAPPLICATION BULLETIN COMBUSTION TURBINE FACILITIES. Overview
Overview Modern combustion (or gas) turbine packages typically include an axial compressor, a combustion section and a turbine. Both compressor and turbine sections consist of one or more sets of fixed
More informationCast Line Heaters The Benefits of This Space Saving Electric Heater
WHITE PAPER Cast Line Heaters The Benefits of This Space Saving Electric Heater Introduction Cast line heaters, or cast-in heaters, offer an alternative to the more common inline process heaters that have
More informationAIR-CONDITIONING SYSTEMS AND APPLICATIONS. Abdullah Nuhait Ph D. King Saud University
AIR-CONDITIONING SYSTEMS AND APPLICATIONS Abdullah Nuhait Ph D. King Saud University AIR-CONDITIONING SYSTEMS Earliest air conditioning system used only for heating (winter) Provided heated air for comfort
More informationFINISHING EQUIPMENT NOVA-S-PLUS. Vacuum/blowing ironing table
FINISHING EQUIPMENT FINISHING EQUIPMENT 1 NOVA-S-PLUS Vacuum/blowing ironing table TECHNICAL DATA NOVA-S-Plus Vacuum motor 0,60 kw Motor for blowing 0,60 kw Board heating elements 1,2 kw Boiler heating
More informationPortable honeycomb matrix compact dryer, with loading, combines dehumidifying plastic resin and conveying into a single unit.
Portable honeycomb matrix compact dryer, with loading, combines dehumidifying plastic resin and conveying into a single unit. Comet s CCD series compact honeycomb matrix dryers incorporate drying and dehumidifying
More informationNFPA 85 COMPLIANCES OF BMS: A CASE STUDY OF BOILER CONTROL AT SBM OFFSHORE MALAYSIA COMPANY 1. AHMED ABOUELRISH 2 Universiti Teknologi Petronas
Journal of Contemporary Issues in Business Research ISSN 2305-8277 (Online), 2013, Vol. 2, No. 4, 109-123. Copyright of the Academic Journals JCIBR All rights reserved. NFPA 85 COMPLIANCES OF BMS: A CASE
More informationYarway Narvik Steam Desuperheater Series 4300 TempLow
For precise and economical control of steam temperature Features and benefits Easy installation Installation in straight, vertical or horizontal pipe. Minimal headroom is required for mounting Only standard
More informationDeaerator. Specifications
ESI, INC. OF TENNESSEE RENTAL EQUIPMENT Deaerator Description The deaerator, built in 1996, is a spray-type deaerating feedwater heater and storage tank with stainless steel internals. The deaerator is
More informationPrecision air handling cabinets Ciatronic MICRO/EXPAIR
/ Reducted footprint Double-wall construction Built-in voltage variator PLC control Variable speed condenser fan ENVIRONMENTALLY HFC R410A PROTECTION DE FRIENDLY L'ENVIRONNEMENT Cooling capacity: 5 to
More informationTemptek Auxiliary Equipment
Temptek Auxiliary Equipment Mold Temperature Controllers - Water Units VT-275-LX VT Series Mold Temperature Controllers are used to process temperature control to 250 F. These units use an incoloy heater
More informationPHRT HEAT PUMP WITH HYDRAULIC EQUIPMENT AIR / WATER 9 to 18 KW
TECHNICAL INSTRUCTIONS PHRT HEAT PUMP WITH HYDRAULIC EQUIPMENT AIR / WATER to KW PHRT PHRT PHRT PHRT For terminal units and boiler overhaul applications Heating Cooling PHRT.00 kw -. kw PHRT.0 kw /.0 kw
More informationINTRODUCTION TO SOLAR THERMAL POWER STATIONS We shall look at some of the different methods of supplying solar energy to the power stations.
SOLAR THERMAL POWER PLANTS There are different types of solar thermal power stations where the energy from the sun is collected by an arrangement of mirrors. These rotate or tilt to follow the suns arcing
More informationTECHNICAL INFORMATION L / A 1
1 WORKING MACHINE WITH SOLVENT: HYDROCARBON MACHINE CAPACITY (RATIO 1:20) Lbs 60 BASKET Diameter Depth Volume Wash speed Extract speed Door opening inches 39.4 inches 25.2 132 rpm 12 50 rpm 300 540 inches
More informationBoiler. Fire tube Boiler:
Boiler What is Boiler? A closed metallic vessel in which the water is heated beyond the boiling temperature by the application of heat by the combustion of fuels to convert it into steam. The function
More informationProblem Cause Remedial action. Gauge glass There was excess chemical dosage The normal ph recommended was 9.5 to See photo 3 & 4.
CASE STUDIES OF STEAM SYSTEM AUDIT IN SOME PLANTS By K.K.Parthiban, Venus Energy Audit System Introduction This article outlines the outcome of auditing of steam system conducted in process Industries.
More informationDynamic Simulation of a CFB Boiler System
71th IEA-FBC Technical Meeting Dynamic Simulation of a CFB Boiler System 2015. 11. 05, Seoul, Korea Sang Min CHOI Thermal Engineering Lab Thermal Engineering Laboratory KAIST Introduction Dynamic Performance
More informationUnion County Vocational - Technical Schools Scotch Plains, New Jersey
SECTION 230593 - TESTING, ADJUSTING, AND BALANCING FOR HVAC PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Balancing Air Systems: a. Constant-volume air systems. b. Variable-air-volume systems. 2.
More informationFLORIDA A&M UNIVERSITY PERFORMANCE CONTRACT SCOPE OF WORK
FLORIDA A&M UNIVERSITY PERFORMANCE CONTRACT SCOPE OF WORK ENERGY CONSERVATION MEASURE 1 Partial Steam System Decentralization SIEMENS will Furnish and Install condensing hot water boilers with associated
More informationImproved Dryer Control
Improved Dryer Control Kenneth C. Hill President Kadant Johnson Systems Division David Vijh Senior Process Control Engineer Technical White Paper Series EXECUTIVE SUMMARY Significant improvements in dryer
More informationGPPS-2017-Put 4 digit paper number here
Proceedings of Shanghai 2017 Global Power and Propulsion Forum 30 th October 1 st November, 2017 http://www.gpps.global GPPS-2017-Put 4 digit paper number here THE RESEARCH ABOUT INFLUENCE OF WET STEAM
More informationAppendix B3 System/Component Cause Codes
Appendix B3 System/Component Cause Codes NUCLEAR UNITS INDEX TO SYSTEM/COMPONENT CAUSE CODES (Unit Codes 200-299) Cause Code NUCLEAR REACTOR Ranges Page No. Core/Fuel 2010-2090 B-NU-3 Control Rods and
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-23 09 93 (November 2015) ----------------------------- Preparing Activity: USACE Superseding UFGS-23 09 23 (May 2011) UNIFIED FACILITIES GUIDE SPECIFICATIONS References
More informationCONTENTS. B. System Design and Performance Requirements
15515 Watertube Boilers This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications or in
More informationSperansa 2008: Round table: Nuclear and sustainable development Universitad Politecnica de Valencia \UPV - Passive safety systems -
Universitad Politecnica de Valencia \UPV - Passive safety systems - complete+annex.doc 1 1.1 Definition of Passive Safety Systems...3 2. Passive safety systems for core decay heat removal....4 2.1 Pre-Pressurized
More informationDavid Cronin-Ohio Valley Area Manager. Heat Transfer, Controls & Instrumentation, Metering.
David Cronin-Ohio Valley Area Manager Heat Transfer, Controls & Instrumentation, Metering. Heat Exchangers Selection Issues Selection Issues Maximum design Capacity Steam Supply pressure Materials of construction
More informationSpray Flow II cc/liter Atmospheric Deaerator. industrialsteam.com
Spray Flow II Pressurized and Atmospheric Deaerators.005 cc/liter Atmospheric Deaerator CONSTANT RECYCLING guarantees deaeration of all dissolved oxygen in excess of.005 cc/liter from 0% to 100% of deaerator
More informationSpray Flow II cc/liter Atmospheric Deaerator. industrialsteam.com
Spray Flow II.00 cc/liter Atmospheric Deaerator Pressurized and Atmospheric Deaerators CONSTANT RECYCLING guarantees deaeration of all dissolved oxygen in excess of.00 cc/liter from 0% to 100% of deaerator
More information2x58 MW Coal Fired Power Plant at Mauritius
2x58 MW Coal Fired Power Plant at Mauritius The coal-fired power plant produces electricity by the burning of coal and air in a Circulating Fluidized Bed Combustion Boiler (CFBC), where it heats water
More informationCL44eR DISHWASHER STANDARD FEATURES MODEL OPTIONS AT EXTRA COST ACCESSORIES DIRECTION OF OPERATION VOLTAGE. Item # Quantity C.S.I.
Item # Quantity C.S.I. Section 11400 DISHWASHER STANDARD FEATURES Energy recovery 202 racks per hour Opti-RinSe system 30 KW electric booster heater Rapid return conveyor drive mechanism Insulated hinged
More informationBoiler Technical Specifications (2013)
ACT Bioenergy Boiler Dimensions 0.5-0.85 Million Btu/h (150-250kW) Model CP500 CP600 CP750 CP850 Heat Output in MBtu/h (kw) 510 (150) 610 (180) 750 (220) 850 (250) Height ft (mm) 6 1 (1855) 6 1 (1855)
More informationMedupi Unit 6 ACC hot cleaning: Method and results
Medupi Unit 6 ACC hot cleaning: Method and results Johannes Pretorius and Pieter Rosslee China International ACC user s group meeting 13-16 October 2015 Overview Background Medupi ACC hot cleaning - general
More informationRefrigerated Air Dryers VF Series. DHT Series. Non-Cycling 10-2,000 scfm scfm
Refrigerated Air Dryers VF Series Non-Cycling 10-2,000 scfm DHT Series Front High Inlet Page Temperature 20-125 scfm 1 VF Series Non-Cycling Refrigerated Air Dryer 10-2,000 scfm Since 1994, Aircel has
More informationTHERMODYNAMICS STEAM P7690 AND STEAM BENCHES CUSSONS TECHNOLOGY LABORATORY RECOMMENDATION
cussons TECHNOLOGY THERMODYNAMICS STEAM P7690 AND STEAM BENCHES CUSSONS TECHNOLOGY LABORATORY RECOMMENDATION Thermodynamics is a branch of physical science concerned with the inter-relationship and inter-conversion
More informationAppendix B9 Geothermal Unit Cause Codes
Appendix B9 Geothermal Unit Cause Codes GEOTHERMAL UNITS INDEX TO SYSTEM/COMPONENT CAUSE CODES (Unit Codes 800 899) Cause Code BOILER Ranges Page No. Boiler Piping System 0500-0620 B-GE-2 BALANCE OF PLANT
More informationWHISPA III 5000 WM & 9000 WM. heatingthroughinnovation. Installation, Operating, Maintenance and After Sales Manual. Part Number: Issue 1
Installation, Operating, Maintenance and After Sales Manual. WHISPA III 5000 WM & 9000 WM heatingthroughinnovation. Product Serial Number: Installation Date: Part Number: 1371054 Issue 1 Tested to UL &
More informationPOWERENERGY
ASME 2016 POWER CONFERENCE JUNE 26 JUNE 30, 2016 CHARLOTTE, NORTH CAROLINA, USA POWERENERGY2016-59067 EVACUATION SYSTEMS FOR STEAM SURFACE CONDENSERS: VACUUM PUMPS OR STEAM JET AIR EJECTORS? Ranga Nadig,
More informationPHYSICAL FACILITIES Consultant s Handbook Specifications Division 21 Fire Suppression 3000 Fire Pumps
Note: The A/E must choose all design values in brackets below before using in project specifications 1 General 1.1 Provide UL listed and FM approved fire pump complete with pump, driver, controller and
More informationSANTA ROSA FIRE DEPARTMENT FIRE PREVENTION BUREAU PLAN REVIEW CHECKLIST
July 1, 2010 SANTA ROSA FIRE DEPARTMENT FIRE PREVENTION BUREAU PLAN REVIEW CHECKLIST FIRE PUMP REVIEW Address: Permit #: Inspector: Date: Status: Inspector: Date: Status: A-Approved; AC-Approved w/comments;
More informationENGINE GENERATORS AND ACCESSORIES
ENGINE GENERATORS AND ACCESSORIES GENERAL INFORMATION 1.1 This section applies to engine generators and accessories. DESIGN REQUIREMENTS 2.1 The Engineer of Record will consult with the University s Engineering
More informationDesign and analysis of the piping systems
Design and analysis of the piping systems Over all schematic diagram of the total system along with equipment and connecting piping is shown in Fig.. Different piping systems are described as follows:.
More informationSECTION 7 AIR CONDITIONING (COOLING) UNIT 41 TROUBLESHOOTING
SECTION 7 AIR CONDITIONING (COOLING) UNIT 41 TROUBLESHOOTING UNIT OBJECTIVES After studying this unit, the reader should be able to Select the correct instruments for checking an air conditioning unit
More informationCOMcheck Software Version Mechanical Compliance Certificate
COMcheck Software Version 4.0.8.1 Mechanical Compliance Certificate Project Information Energy Code: Location: Climate Zone: Project Type: 90.1 (2013) Standard Buda, Texas 2a New Construction Construction
More informationTECHNICAL SPECIFICATIONS FOR PLUSHER WDS 18 SERIES INSTRUMENT WASHER DISINFECTORS
TECHNICAL SPECIFICATIONS FOR PLUSHER WDS 18 SERIES INSTRUMENT WASHER DISINFECTORS PRODUCT PLUSHER WDS 18 series instrument washer disinfectors are offered with single or double door formation with vertical
More informationRefrigerated Compressed Air Dryer
Manual Instruction for Refrigerated Compressed Air Dryer Warning: Place the dryer machine horizontal. Never upside down Dino-power Industry & Trade Co., Ltd www.aircompressorschina.com Dino-power 1 PREPARED
More informationCPF PRODUCT DESCRIPTION
CPF 175 340 PRODUCT DESCRIPTION The CHICAGO PNEUMATIC CPF 175-340 compressor is a quiet, complete and ready-for-use unit for the production of compressed air in industrial applications. OVERVIEW The CHICAGO
More information"A Case Study of Three Drum Parameter Control in Boiler Using Discrete PID Controller Based on Simulation"
"A Case Study of Three Drum Parameter Control in Boiler Using Discrete PID Controller Based on Simulation" Ram Kishan Raikwar 1, V. K Tripathi 1 Department of Electrical Engg, SHIATS Allahabad India 1
More informationPLYWOOD INDUSTRY JOB EVALUATION PROGRAM JOB DESCRIPTION. Points: 242 Grade: 18
PLYWOOD INDUSTRY JOB EVALUATION PROGRAM JOB DESCRIPTION Date Revised: 16-Feb-12 Points: 237 Grade: 17 Date Prepared: 30-Apr-14 Points: 242 Grade: 18 Person Interviewed or Comment: No. of Incumbents: 1.
More informationForm 2143 Date: 4/3/03 Repl: 2/1/99 BRYAN STEAM LLC. Installation and Operating Service Manual BOILER FEED SYSTEM
0 Form 2143 Date: 4/3/03 Repl: 2/1/99 BRYAN STEAM LLC Installation and Operating Service Manual BOILER FEED SYSTEM INSTALLATION AND OPERATION SERVICE MANUAL BOILER FEED SYSTEM Bryan Steam LLC 783 North
More informationDESIGN CLASS FUNCTION
PROFESSIONAL QUALITY COOKING EQUIPMENT INSTALLATION MANUAL FOR PERFORMER SLIDE-IN COOK TOPS MODEL NUMBERS: AROBSCT-424, AROBSCT-242GD, AROBSCT-24X2GR, AROBSCT-430, AROBSCT-636, AROBSCT-436GD, AROBSCT-436GR,
More informationPOWER GENySYS P ROJECT E XPERIENCE I NFORMATION - D ISTRIBUTED G ENERATION
POWER GENySYS Burlington, Ontario. PORT COLBORNE GENERAL HOSPITAL Above: Entrance of,. 2 nd Hospital Cogeneration System in Ontario (1993) In 1993 Marsh Energy Inc. was awarded a turnkey contract by the
More informationVertical Laboratory Autoclave A series:
Vertical Laboratory Autoclave A series: of Labtron Vertical Laboratory Autoclave LVA-A series is a top loading sterilizer which provides safe, Made up of SUS304 stainless steel Dual scale numerical pressure
More informationEXPAIR. Use. Precision air handling cabinets. Reducted footprint Dual-wall construction
Reducted footprint Dual-wall construction Built-in variable frequency drive PLC control Variable speed condenser fan Cooling capacity: 5 to 50 kw Air flow: 1 000 to 12 000 m 3 /h ErP READY Use Precision
More informationLaddomat. Mixing valves for solid fuel boilers. Version 1.01
Laddomat Mixing valves for solid fuel boilers Version 1.01 Laddomat > Mixing valves for solid fuel boilers Why Laddomat This is the answer to those who burn wood or pellets and wonder why you should complement
More informationHomework Chapter2. Homework Chapter3
Homework Chapter2 2/1 A storage tank holds methane at 120 K, with a quality of 25 %, and it warms up by 5 C per hour due to a failure in the refrigeration system. How long time will it take before the
More informationUnderstand and apply domestic central heating system installation and maintenance techniques
Level: 2 Credit value: 10 URN: Y/602/2888 Unit aim This combination unit provides basic learning in the installation, maintenance, decommissioning and soundness testing of a basic range of wet central
More informationAn Instrumentation and Control for Loop Test
An Instrumentation and Control for Loop Test 21-24 Aug. 2012 S.H. Ahn, J.T. Hong, C.Y. Joung, S.J. Park Neutron Utilization Technology Division 0 Contents 1 Introduction Click to of add HANARO Title 2
More informationTHE NEXT GENERATION IN CONDENSING BOILERS M-SERIES
M-SERIES M-SERIES More Efficiency For You And Your Customers Why the "M" Series? For maximum momentum. Using proven technology, these boilers are designed to keep your work day moving quickly and your
More informationOPERATIONS AND MAINTENANCE MANUAL FOR THE 8-TON TURF CART ENVIRONMENTAL CONTROL UNIT (ECU) PART NUMBER
OPERATIONS AND MAINTENANCE MANUAL FOR THE 8-TON TURF CART ENVIRONMENTAL CONTROL UNIT (ECU) PART NUMBER 2001927 Prepared by: 860 Douglas Way PO Box 530 Natural Bridge Station, VA 24579 1 1.0 SCOPE: This
More informationSECTION AIR COILS
PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Specification Sections, apply to this Section. B. Related Sections:
More informationMEP 599 Diploma Design Project- Fall Term 2016
MEP 599 Diploma Design Project- Fall Term 2016 Control of Burner Management System (BMS) using PLC Technology by Eng. Sherif Hassan Hafez Supervised by Dr. Mohsen Sayed Soliman, ACC Manager and Dr. Amro
More informationPellet Stove Test Manual
Pellet Stove Test Manual Stricter Emission Standards Adopt stricter emission standards than the EPA. 1. Washington: 4.5 grams per hour for non-catalytic and pellet stoves; 2.5 grams per hour for catalytic
More informationFacilities Services Utilities Shutdown Request Form
Page 1 of 6 Facilities Services Utilities Shutdown Request Form Please complete all the fields before submitting the form to the shutdown coordinator. If you require additional space, please attach a separate
More informationWhat to Expect from Your EtaPRO Investment
What to Expect from Your EtaPRO Investment Benefits of Deployment Introduction Power plants seeking to improve their competitive position have recognized unit heat rate as an indicator of plant health
More informationSTEAMPAK Series BurnerPAK BMS Burner Management Systems
BurnerPAK BMS Burner Management Systems Sequence of operation, ignition and control of burners Meets NFPA 85 safety standard MFT alarming with manual reset, first-out indication Optional enhanced alarming
More informationENVIRONMENTAL CONTROL UNIT (ECU) PART NUMBER OPERATIONS AND MAINTENANCE MANUAL
ENVIRONMENTAL CONTROL UNIT (ECU) PART NUMBER 2001829 OPERATIONS AND MAINTENANCE MANUAL Prepared by: 860 Douglas Way PO Box 530 Natural Bridge Station, VA 24579 1.0 SCOPE: This Operations and Maintenance
More information