LEARNING FROM TEXAS CITY REFINERY ( BP )

Size: px
Start display at page:

Download "LEARNING FROM TEXAS CITY REFINERY ( BP )"

Transcription

1 LEARNING FROM TEXAS CITY REFINERY ( BP )

2 Raffinate Splitter

3 Blow down Drum and Stack Blowdown Drum and ISOM Unit, After the Incident

4

5 Aerial Photograph of Isomerization Unit

6 Isomerization Unit

7 Satellite Control Room

8 Trailer

9 Double-Wide Trailer

10 THE INCIDENT Incident occur on the raffinate splitter used for processing gasoline blending components and involved an associated blow down drum and stack. The night shift established levels in the splitter using cold feed. They shut off the feed at the end of shift with the splitter level indication 100 %. The high level alarm activated and acknowledge at 72% but an independent high level alarm set at 78% did not activate. The day shift on 23rd March, 2005 reintroduced feed and started circulation and heating. The bottom valve was closed and the splitter became overfilled and overheated. During this period tower base temp. was increasing but the hydraulic head of cold liquid means no fractionation occurred.

11 When finally the operator opened the bottom valve after 3 hours of restart of feed, a rapid increase in feed temp. resulted vaporization and shortly afterwards liquid was released from overhead relief system. The relief system was not designed for such high liquid hydrocarbon flow and liquid hydrocarbon was emitted from the blow down drum and stack. A vapor cloud developed and ignited resulting explosion killing 15 persons and injured many others and damaged nearby properties.

12

13 LESSON LEARNED Critical Factors: The following critical factors are identified: Start Up and Management Oversight- -- Failure to follow start up procedure contributed to loss of process control. Key individuals did not apply their level of skills and knowledge and there was a lack of supervisory presence and oversight during this start up. Loss of Containment- -- Action taken or not taken led to overfilling of splitter resulting over pressurization and pressure relief. Hydrocarbon flow to Blow down Drum and stack resulted liquid overflowing through stack causing a vapor cloud which was ignited by an unknown source.

14 Design and Engineering of Blow down drum and stack --- The use blow down drum and stack as part of relief system of splitter close to uncontrolled areas. Control of Work Area and Trailer Placement --- Numerous personnel working elsewhere in the refinery were too close to the hazard at the blow down drum and stack during the start up operation. They ware congregated in and around of temporary trailer and were neither alerted nor evacuated. Business Context --- There was a lack of clearly defined and broadly understood context and business priorities for the Texas City site. A clear view of the key process safety priorities for the site or a sense of vision could not be identified.

15 Safety as a Priority --- Process safety, operation performance and systematic risk reduction priorities had not been set and consistently reinforced by management. Organizational Complexity and Capability --- Lack of clear accountabilities and poor communication was noticed resulting confusion in the workforce over roles and responsibilities. Inability to See Risk --- A poor level of hazard awareness and understanding of process safety on the site resulted in people accepting level of risk that were considerably higher than comparable installations.

16 Lack of Early Warning System --- Given the poor vertical communication and performance management process, there was neither an adequate early warning system of problems nor any independent means of understanding certain deteriorating condition of plant.

17 Key Issues Operator Inattention Following Procedures Supervisor Absence Communication shift handover Trailers Too Close to Hazards Some Instrumentation Did Not Work Abnormal Start-ups Investigation of Previous Incidents Blowdown Drum Vented Hydrocarbons to Atmosphere Opportunities to Replace Blowdown Drum

18 Underlying Cultural Issues Business Context Motivation Morale (Process) Safety as a Priority Emphasis on Environment and Occupational Safety Organizational Complexity & Capability Investment in People Layers and Span of Control Communication

19 Inability to See Risk Hazard Identification Skills Understanding of Process Safety Facility Siting Vehicles Lack of Early Warning Depth of Audit KPI s for Process Safety Sharing of Learning / Ideas

20 Raffinate Splitter Tower Temperatures as Level Rises

21 Decline in Feed Flow Rate as Splitter Pressure Rises

22

23 Raffinate Splitter Tower Elevation

24

25 Feed Preheat to Raffinate Splitter Tower

26 LAH-5102 is an independent alarm for high level in the Raffinate Splitter bottom LT-5100 is shown at 50% level. At this time it is not in the alarm condition. The controller is shown in Manual. DCS Screen Showing Raffinate Splitter Level Not in Alarm at 50% Level

27 LT-5100 is shown in the alarm condition with the level indication at 75.1%. The color has changed to yellow and there is an audible alarm that sounds DCS Screen Showing Raffinate Splitter Level in Alarm at 75% Level

28 Indicated Tower Base Level as Temperature Increases

29 Conclusions of the Technical Analysis The main conclusions from the technical analyses of the incident are as follows: The high peak pressures observed (63 psig) were caused by liquid filling up the 24-inch overhead line off the Splitter column. This is supported by the dynamic modeling results and supported by the flow response from the feed pump during the pressure release. As the RVs were located close to the bottom of the overhead line, the high hydrostatic pressure from a filled overhead line was sufficient to exceed the RV set pressure. Virtually all of the release was sub cooled liquid. The liquid reached the overhead line by a combination of grossly overfilling the main column with the liquid charge, and vaporization and expansion of the tower base and feed charge.

30 Aerial view of BP Texas City site of fatal 2005 explosion.

31 INDEPENDENT PANEL BP commissioned an independent panel chaired by former US Secretary of State James Baker III, to assess the effectiveness of corporate oversight of safety management systems and safety culture at its five US refineries. The panel s report was published in early 2007 and its recommendations can be grouped in 4 main headings. 1. Leadership 2. Integrated Process Safety Management System 3. Process Safety Knowledge and Expertise 4. Process Safety Culture

32 Leadership --- A new refinery management team led by a manager with great industry experience from outside BP has been appointed. A new simplified functional organization has been introduced built around an operation centric model, so that everyone involved in maintenance and operations knows what they are accountable for and to whom. HSSE Team and Practices --- The number of HSE staff at the refinery has trebled with a significant increase in the process safety team. A rigorous investigation process that includes all incidents whether they are near miss incidents or actual events has been implemented. A new site-wide transit system removing more than 500 vehicles from site has been introduced.

33

34 Workforce Engagement --- The new leadership is changing expectations. Changes in work practices including Stop campaign and employee led PULSE program have been introduced. Several jobs have been stopped by employees on the spot because of process safety and related issues. New communication practice through weekly safety meeting has been introduced. Trailer- -- More than 200 trailers have been removed from the site and 400+ personnel relocated to offsite offices. A new hurricane proof employees services building have been constructed outside the perimeter of the refinery.

35 Blow Down System blow down stacks have been removed and new flares installed in line with a new policy of no atmospheric venting of light hydrocarbons. A revalidation study of relief valves for all process units and a relief and flare system have been taken. Inspection and maintenance - -- A top to bottom continuous inspection and evaluation of the refinery started. The expanded site inspection program doubled the number of inspectors resulted change of feet of pipe and 2500 nos. of valves.

36 Control of Work- -- In light of significant construction and maintenance program a formal risk assessment has been implemented prior to any permitting job. The control of work verification process has been strengthen ensuring work is stopped when deviations occur. Operating Procedure - -- Roles, responsibilities, start up, operating and emergency procedure have been clarified. Leadership audits have been instituted to verify proper use of start up, shut down and safe procedures. Pre start up safety reviews with more detailed check requiring formal sign off have been introduced.

37 Training - -- Additional training programs for all employees have been introduced. Performance Indicators - -- A new on line system for process safety management information has been developed and is used to focus specifically on process safety in monthly management review meetings. Group Operations Risk Committee ( GORC ) - -- This committee is chaired by the CEO and membership includes the business segment chief executives and senior functional expertise to establish - --

38 CONTINUAL IMPROVEMENT 1. Incident Analysis, learning and response. 2. Monitoring performance indicators 3. Review of plan 4. Implementation of Operation Management System (OMS) 5. Operations capabilities development

39 CONCLUSION The Texas City incident was preventable. The lessons learned from the incident could help prevent others from repeating mistakes.

40

Communication and Coordination Failures in the Process Industries

Communication and Coordination Failures in the Process Industries Communication and Coordination s in the Process Industries 52 nd Annual HFES Meeting Jason Laberge Honeywell Advanced Technology Golden Valley, MN Peter Bullemer Human Centered Solutions Independence,

More information

BP TEXAS CITY REFINERY DISASTER

BP TEXAS CITY REFINERY DISASTER BP TEXAS CITY REFINERY DISASTER ACCIDENT & PREVENTION REPORT Chinedu Charles Isiadinso April 23, 2015 Contents 1 INTRODUCTION 2 2 KLETZ-TYPE PREVENTION TABLE 3 3 ANALYSIS 6 4 CONCLUSION 9 1 1 INTRODUCTION

More information

Retrospective Hazard Review

Retrospective Hazard Review Managing Fire Risks, Abu Dhabi Men s College, 12 th November 2014 Retrospective Hazard Review Identifying fire hazards/risks and typical weaknesses Texas City US, 2005 Baker Report Jan 2007 The passing

More information

2012 Honeywell Pacific Users Group. Sus tain.ability.

2012 Honeywell Pacific Users Group. Sus tain.ability. 2012 Honeywell Pacific Users Group Sus tain.ability. 1 2012 Honeywell Pacific Users Group Sus tain.ability. Nico Oosthuizen Effective Alarm and Operations Management 2 Topics Overview What is the problem?

More information

Bowties in process safety auditing

Bowties in process safety auditing Bowties in process safety auditing Mireille Busque - ERM Insert then choose Picture select your picture. Right click your picture and Send to back. May 9, 2017 Copyright 2015 by ERM Worldwide Limited and/or

More information

Kevin Brown and Chris Stearns

Kevin Brown and Chris Stearns 2013 Honeywell Users Group Americas Kevin Brown and Chris Stearns Operations and Alarm Management Reap the benefits of a healthy alarm system 1 Agenda Alarm Management Effective best practices How can

More information

New requirements for IEC best practice compliance

New requirements for IEC best practice compliance New requirements for IEC 61511 best practice compliance Proof testing and a SIL study may no longer be enough by Sven Grone Schneider Electric Safety Services Practice Leader Executive summary Since its

More information

Bowties in process safety auditing

Bowties in process safety auditing Bowties in process safety auditing Mireille Busque - ERM Insert then choose Picture select your picture. Right click your picture and Send to back. Copyright 2015 by ERM Worldwide Limited and/or its affiliates

More information

Fire Safety Management Audit Specification August 2017

Fire Safety Management Audit Specification August 2017 Fire Safety Management Audit Specification August 2017 Membership Training Qualifications Audit and Consultancy Policy and Opinion Awards Contents Page 1 Introduction to the Fire Safety Management Audit

More information

Shell Deer Park Refinery Delayed Coker Incident March 4, 2004

Shell Deer Park Refinery Delayed Coker Incident March 4, 2004 Shell Deer Park Refinery Delayed Coker Incident March 4, 2004 Brian Evans, Process Engineer Bottom of the Barrel Seminar April 19, 2005 Outline Unit Information Incident Details Resulting Impacts Plugged

More information

Emergency Response. Types of Emergencies

Emergency Response. Types of Emergencies Emergency Response All Chinook Consulting Services employees and sub-contractors need to be trained in First-Aid, CPR, TDG, WHMIS and H2S. Chinook Consulting Services will supply these courses, but it

More information

To: All SAAS Accredited Certification Bodies Subject: Clarification to Emergency and Health & Safety Requirements in the SA8000 Standard

To: All SAAS Accredited Certification Bodies Subject: Clarification to Emergency and Health & Safety Requirements in the SA8000 Standard SOCIAL ACCOUNTABILITY ACCREDITATION SERVICES To: All SAAS Accredited Certification Bodies Subject: Clarification to Emergency and Health & Safety Requirements in the SA8000 Standard Background: After an

More information

Improving the Performance and Reliability of Fired Heaters and Boilers

Improving the Performance and Reliability of Fired Heaters and Boilers Page 1 of 5 Improving the Performance and Reliability of Fired Heaters and Boilers Introduction The success of every company depends of each employee's understanding of the key business components. Employee

More information

Alarm Management Reflections

Alarm Management Reflections 1 Alarm Management Reflections Standards Certification Education & Training Nicholas P Sands, CAP, PE Manufacturing Technology Fellow, DuPont Publishing Conferences & Exhibits About the Presenter Nicholas

More information

SIL DETERMINATION AND PROBLEMS WITH THE APPLICATION OF LOPA

SIL DETERMINATION AND PROBLEMS WITH THE APPLICATION OF LOPA SIL DETERMINATION AND PROBLEMS WITH THE APPLICATION OF LOPA Alan G King Hazard & Reliability Specialist, ABB Engineering Services, Billingham, Cleveland UK. TS23 4YS For a number of years, industry has

More information

Applying Buncefield Recommendations and IEC61508 and IEC Standards to Fuel Storage Sites

Applying Buncefield Recommendations and IEC61508 and IEC Standards to Fuel Storage Sites Applying Buncefield Recommendations and IEC61508 and IEC 61511 Standards to Fuel Storage Sites John Joosten Global Product Manager Radar and Safety John.Joosten@Honeywell.com Applying Buncefield Recommendations

More information

Q&A Session from Alarm Management Workflow Webinar (Apr.24/2013)

Q&A Session from Alarm Management Workflow Webinar (Apr.24/2013) Q&A Session from Alarm Management Workflow Webinar (Apr.24/2013) Question Answer from Kevin Brown Can you define HAZOP and LOPA? HAZOP stands for Hazard and Operability Study. LOPA stands for Layers of

More information

Property Name & Address [ Property Name ] - [ Property Address ]

Property Name & Address [ Property Name ] - [ Property Address ] Emergency Procedure FIRE Property Name & Address [ Property Name ] - [ Property Address ] Purpose To ensure effective response and evacuation, by the property s Emergency Response Organization, to a fire

More information

June 2017 (Updated 18 January 2018) Fire Safety Policy. Peter Webb, Project Manager Compliance First Choice Homes Oldham Limited

June 2017 (Updated 18 January 2018) Fire Safety Policy. Peter Webb, Project Manager Compliance First Choice Homes Oldham Limited June 2017 (Updated 18 January 2018) Fire Safety Policy Peter Webb, Project Manager Compliance First Choice Homes Oldham Limited Trusted provider of quality homes, excellent landlord and support services,

More information

Health and Safety Policy. Version Author Revisions Made Date 1 Colin Campbell First Draft March 2014

Health and Safety Policy. Version Author Revisions Made Date 1 Colin Campbell First Draft March 2014 Fire Safety Policy Originator name: Section / Dept: Implementation date: Clive Parkinson Health & Safety March 2014 Date of next review: March 2017 Related policies: Health and Safety Policy Policy history:

More information

AVOID CATASTROPHIC SITUATIONS: EXPERT FIRE AND GAS CONSULTANCY OPTIMIZES SAFETY

AVOID CATASTROPHIC SITUATIONS: EXPERT FIRE AND GAS CONSULTANCY OPTIMIZES SAFETY AVOID CATASTROPHIC SITUATIONS: EXPERT FIRE AND GAS CONSULTANCY OPTIMIZES SAFETY World-class services help reduce incidents, protect the environment, and keep people and plants safe White Paper PAGE 1 Introduction

More information

Air Compressor Electrical Fire

Air Compressor Electrical Fire Purpose To share lessons learned gained from incident investigations through a small group discussion method format. To understand lessons learned through a Systems of Safety viewpoint. This material was

More information

Overview of Control System Design

Overview of Control System Design Overview of Control System Design 1. Safety. It is imperative that industrial plants operate safely so as to promote the well-being of people and equipment within the plant and in the nearby communities.

More information

Because Safety is not found in a Box

Because Safety is not found in a Box SUBTITLE, E.G. INTERNAL SEPTEMBER 18, 2018 Human Factors and their impact on Plant Safety Because Safety is not found in a Box Luis Duran Global Product Manager Safety Systems and Security Agenda Paradigm

More information

AVOID CATASTROPHIC SITUATIONS: EXPERT FIRE AND GAS CONSULTANCY OPTIMIZES SAFETY

AVOID CATASTROPHIC SITUATIONS: EXPERT FIRE AND GAS CONSULTANCY OPTIMIZES SAFETY AVOID CATASTROPHIC SITUATIONS: EXPERT FIRE AND GAS CONSULTANCY OPTIMIZES SAFETY World-class services help reduce incidents, protect the environment, and keep people and plants safe White Paper PAGE 1 Introduction

More information

NECA S System Approach to Electrical Safety for NFPA 70E

NECA S System Approach to Electrical Safety for NFPA 70E NECA S System Approach to Electrical Safety for NFPA 70E NECA s Systems Approach to NFPA 70E Easy to understand NFPA 70E employer requirements, Provides Supervisors with key on the job information, De

More information

Hazardous goods management Latest trends in petroleum industry. C. Sasi Assistant Vice President Total LPG India Limited

Hazardous goods management Latest trends in petroleum industry. C. Sasi Assistant Vice President Total LPG India Limited Hazardous goods management Latest trends in petroleum industry C. Sasi Assistant Vice President Total LPG India Limited Buncefield UK (HOSL) - December 11, 2005 Training Behaviour SMS LOPA Risk Analysis

More information

Fire and Gas Detection and Mitigation Systems

Fire and Gas Detection and Mitigation Systems Fire and Gas Detection and Mitigation Systems Dr. Lawrence Beckman, PE, TÜV FSExp SafePlex Systems, Inc., Houston, Texas ABSTRACT Fire and Gas Detection systems are key components in the overall safety

More information

M E M O R A N D U M. Please do not vote negatively because of editorial errors. However, please bring such errors to my attention for action.

M E M O R A N D U M. Please do not vote negatively because of editorial errors. However, please bring such errors to my attention for action. M E M O R A N D U M TO: FROM: NFPA Technical Committee on Fire Marshal Professional Qualifications Stacey Van Zandt DATE: July 13, 2010 SUBJECT: NFPA 1037 ROP TC Letter Ballot (F2011) The ROP letter ballot

More information

Corporate. Management. Line. Management. Plant. Manager HSSE. Maintenance Manager. (Plant. Operations Manager. Process Safety) Plant.

Corporate. Management. Line. Management. Plant. Manager HSSE. Maintenance Manager. (Plant. Operations Manager. Process Safety) Plant. Corporate Management HSSE (Corporate Process Safety) Line Management Whiting Plant Manager Maintenance Manager HSSE (Plant Process Safety) Operations Manager Maintenance Workers Plant Operators Control

More information

EMERGENCY PREPAREDNESS & RESPONSE PROCEDURE

EMERGENCY PREPAREDNESS & RESPONSE PROCEDURE 1 of 12 2 of 12 CONTENTS 1.0 OBJECTIVES...3 2.0 SCOPE...3 3.0 DEFINITION OF TERMS...3 4.0 RESPONSIBILITIES & AUTHORITIES...4 5.0...4 5.1 Emergency Scenario Identification...4 5.2 Emergency Response Team...4

More information

SBS Tank 731 Overflow

SBS Tank 731 Overflow SBS Tank 731 Overflow Executive Summary On Thursday, August 7, 2008, at approximately 09:50, the Sulfuric Acid Accumulator (Tank 731) on the SBS unit overflowed, eventually releasing approximately 2000

More information

Explosion Protection Engineering Principles

Explosion Protection Engineering Principles Handbook of Fire and Explosion Protection Engineering Principles for Oil, Gas, Chemical and Related Facilities Second edition Dennis P. Nolan ELSEVIER AMSTERDAM BOSTON HEIDELBERG LONDON NEW YORK OXFORD

More information

Chapter 5. Multiple Choice

Chapter 5. Multiple Choice Chapter 5 Multiple Choice 1. Which term refers to assessing what is happening at the scene and then using that information to devise a plan of action? A. Hazard assessment B. Size-up C. Evaluation D. Command

More information

White Paper: CCPS Process Safety Metrics Review Considerations from an ASM Perspective

White Paper: CCPS Process Safety Metrics Review Considerations from an ASM Perspective White Paper: CCPS Process Safety Metrics Review Considerations from an ASM Perspective 2008 Mary Kay O Connor Process Safety Center International Symposium 28 October 2008 Doug Metzger: Honeywell, ASM

More information

Legislation associated with Hazardous Locations. Pieter Coetzee ZONE 2 ZONE 1 ZONE 0. Be safe be Ex

Legislation associated with Hazardous Locations. Pieter Coetzee ZONE 2 ZONE 1 ZONE 0. Be safe be Ex Legislation associated with Hazardous Locations Pieter Coetzee ZONE 2 ZONE 0 ZONE 1 Be safe be Ex Contents History Introduction Occupational Health and Safety Act. (Act 85 of 1993) General Machinery Regulation

More information

The SIL Concept in the process industry International standards IEC 61508/ 61511

The SIL Concept in the process industry International standards IEC 61508/ 61511 The SIL Concept in the process industry International standards IEC 6508/ 65 Chris M. Pietersen MSc Safety Solutions Consultants BV (SSC) Director pietersen@safety-sc.com th Urea Symposium 9- May 008,

More information

PROTECTING YOUR PROPERTY INVESTMENT BEFORE DISASTERS OCCUR ARE YOU PREPARED?

PROTECTING YOUR PROPERTY INVESTMENT BEFORE DISASTERS OCCUR ARE YOU PREPARED? PROTECTING YOUR PROPERTY INVESTMENT BEFORE DISASTERS OCCUR ARE YOU PREPARED? Mike Keenan CHST Loss Control and Safety Consultant Grace / Mayer Insurance Agency PROPERTY RISK EXPOSURES Fire and explosion

More information

risk management and assessment for business Lessons Learned from Real World Application of Bow-tie Method 2010 International Symposium

risk management and assessment for business Lessons Learned from Real World Application of Bow-tie Method 2010 International Symposium risk management and assessment for business Risktec Solutions Lessons Learned from Real World Application of Bow-tie Method 2010 International Symposium BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND

More information

Value Paper Authors: Stuart Nunns CEng, BSc, FIET, FInstMC. Compliance to IEC means more than just Pfd!

Value Paper Authors: Stuart Nunns CEng, BSc, FIET, FInstMC. Compliance to IEC means more than just Pfd! Value Paper Authors: Stuart Nunns CEng, BSc, FIET, FInstMC Compliance to IEC 61508 means more than just Pfd! Compliance to IEC 61508 means more than just Pfd! Market environment Statistics relating to

More information

Low pressure boiler* inspection and maintenance

Low pressure boiler* inspection and maintenance 2-12.001 May 2011 Low pressure boiler* inspection and maintenance Introduction Even as our society evolves into a more technologically advanced, economically driven environment, many businesses and their

More information

Outline. Standards of Coverage. ICS Features 2/12/2016 ICS

Outline. Standards of Coverage. ICS Features 2/12/2016 ICS Outline Fire Department Operations Standards of Coverage What does it look like in your town? Standard Assignment House Fire, Commercial Fire, Smoke in Structure Incident Command System Arrival Reports

More information

DIRECTIVE NO: D-B

DIRECTIVE NO: D-B DIRECTIVE NO: D-B6 100604 1 LOW PRESSURE THERMAL FLUID PLANT AUTOMATED CONTROL SYSTEMS Date of Issue: June 4, 2010 General Details This directive is being issued to owners, licensed contractors, consulting

More information

ADIPEC 2013 Technical Conference Manuscript

ADIPEC 2013 Technical Conference Manuscript ADIPEC 2013 Technical Conference Manuscript Name: Heidi Fuglum Company: ABB AS Job title: Deployment Manager Address: Ole Deviksvei, Oslo, Norway Phone number: +47 91 36 98 70 Email: Heidi.Fuglum@no.abb.com

More information

Alarm Management Standards Are You Taking Them Seriously?

Alarm Management Standards Are You Taking Them Seriously? Alarm Management Standards Are You Taking Them Seriously? Executive Summary EEMUA Publication 191 ALARM SYSTEMS - A Guide to Design, Management, and Procurement was first released in 1999 and is well acknowledged

More information

SCALES NW EMERGENCY ACTION PLAN

SCALES NW EMERGENCY ACTION PLAN Purpose Each SCALES NW, INC location shall have a written Emergency Action Plan, appropriate to the hazards of the workplace, in order to respond to an emergency that may require rescue or evacuation.

More information

Fixed plant and mobile equipment fires on surface coal mines

Fixed plant and mobile equipment fires on surface coal mines Fixed plant and mobile equipment fires on surface coal mines Mines safety bulletin no. 158 21 November 2016 Version 1 Background Fires on fixed plant and mobile equipment at mines and quarries continue

More information

Design & Use of Ground Based Pumps Guidance Document

Design & Use of Ground Based Pumps Guidance Document Design & Use of Ground Based Pumps The information and recommendations in this guidance are given in good faith and belief in their accuracy at the time of publication, but do not imply any legal liability

More information

Application Bulletin. LNG / LPG Facilities FLAME AND GAS DETECTION FOR LNG FACILITIES

Application Bulletin. LNG / LPG Facilities FLAME AND GAS DETECTION FOR LNG FACILITIES FLAME AND GAS DETECTION FOR LNG FACILITIES Liquefied natural gas (LNG) is a generic name for liquefied hydrocarbon gas composed primarily of methane. When natural gas is cooled to approximately -260 F,

More information

Assessment of the Safety Integrity of Electrical Protection Systems in the Petrochemical Industry

Assessment of the Safety Integrity of Electrical Protection Systems in the Petrochemical Industry Assessment of the Safety Integrity of Electrical Protection Systems in the Petrochemical Industry 1. Introduction Author: Colin Easton ProSalus Limited ~ Independent Safety Consultants Within the United

More information

HEAT GENERATION 1.01 RELATED CORNELL DESIGN AND CONSTRUCTION STANDARDS. B. Section HVAC Basic Materials and Methods

HEAT GENERATION 1.01 RELATED CORNELL DESIGN AND CONSTRUCTION STANDARDS. B. Section HVAC Basic Materials and Methods 230520 HEAT GENERATION Cornell s Design and Construction Standards provide mandatory design constraints and acceptable or required products for all construction at Cornell University. These standards are

More information

Evacuation and Lockdown Plan

Evacuation and Lockdown Plan Evacuation and Lockdown Plan Table of Contents 1 Introduction... 2 2 Evacuation... 2 2.1 General guidelines... 2 2.2 Evacuation of persons with disabilities... 3 2.3 Accountability for students... 3 2.4

More information

SECTION 7 EVACUATION PROCEDURES

SECTION 7 EVACUATION PROCEDURES SECTION 7 EVACUATION PROCEDURES 7.1 Refinery Evacuation Procedure 2 7.1.1 Procedures for Operating Critical Equipment Prior to Evacuation 3 7.2 Sulfur Recovery Unit Evacuation Procedure 4 7.3 HF Alkylation

More information

TEN STEP PROCESS PREPARING FIRE SAFETY PLANS

TEN STEP PROCESS PREPARING FIRE SAFETY PLANS TEN STEP PROCESS PREPARING FIRE SAFETY PLANS STEP 1 CONDUCT FIRE SAFETY AUDIT IDENTIFY BUILDING FEATURES AND HUMAN RESOURCES. STEP 2 APPOINTMENT OF SUPERVISORY STAFF IDENTIFY TRAINED SUPERVISORY STAFF

More information

SIOUX FALLS FIRE RESCUE STRATEGIC PLAN

SIOUX FALLS FIRE RESCUE STRATEGIC PLAN SIOUX FALLS FIRE RESCUE The mission of Sioux Falls Fire Rescue is to protect the citizens and visitors of Sioux Falls and their property from fires and other emergencies through education, prevention,

More information

Feed Interruption Three separate incidents within Marathon petroleum. p Garyville 2005, 05 Coker Unit - Feed interruption/furnace tripped caused by wa

Feed Interruption Three separate incidents within Marathon petroleum. p Garyville 2005, 05 Coker Unit - Feed interruption/furnace tripped caused by wa Feed Interruption, Foamover, Tarball, and Cooked Drum Experience Gary Gianzon Heavy Oil Technologist gmgianzon@marathonoil.com Marathon Petroleum Company LLC April 2010 Feed Interruption Three separate

More information

!!! Sample Written Program For Your Company. For BOILER SAFETY. Provided By:!!!

!!! Sample Written Program For Your Company. For BOILER SAFETY. Provided By:!!! Sample Written Program For Your Company For BOILER SAFETY Provided By: P.O. Box 2136 Slidell, LA 70458 Phone: 985-781-1444 Fax: 985-781-1446 Email: info@se-safety.com Purpose Boiler Safety Program The

More information

Preventing Hydraulic Shock: Millard Refrigerated Services, Inc. Anhydrous Ammonia Release

Preventing Hydraulic Shock: Millard Refrigerated Services, Inc. Anhydrous Ammonia Release Preventing Hydraulic Shock: Millard Refrigerated Services, Inc. Anhydrous Ammonia Release Lucy Tyler, CSP, CIH U.S. Chemical Safety Board GCAP Ammonia Safety Day May 28, 2015 1 Meeting Agenda About the

More information

Combustible Dust Explosions and Hazards Case Study: CTA Acoustics, Inc.

Combustible Dust Explosions and Hazards Case Study: CTA Acoustics, Inc. Combustible Dust Explosions and Hazards Case Study: CTA Acoustics, Inc. John Ahlfield Washington University in St. Louis Presented to: Robert Anderson May 3, 2010 Table of Contents Executive Summary.4

More information

CO-ORDINATION OF NOTIFIED BODIES PPE Regulation 2016/425 RECOMMENDATION FOR USE

CO-ORDINATION OF NOTIFIED BODIES PPE Regulation 2016/425 RECOMMENDATION FOR USE CO-ORDINATION OF NOTIFIED BODIES PPE Regulation 2016/425 PPE-R/00.017 Version 2 RECOMMENDATION FOR USE Number of pages: 5 Approval stage : Approved on : Origin : Horizontal Committee, C2D Ad hoc group

More information

PLN9 Security Services Pvt. Ltd.

PLN9 Security Services Pvt. Ltd. PLN9 Security Services Pvt. Ltd. Introduction The PLN9 team is committed to deliver a consistent level of product and service which is reliable, safe, innovative & customer driven. Our protection solution

More information

When the Dust Settles: Combating Combustive Dust in Food Manufacturing

When the Dust Settles: Combating Combustive Dust in Food Manufacturing When the Dust Settles: Combating Combustive Dust in Food Manufacturing Nilfisk CFM, 300 Technology Drive, Malvern, PA 19355 Phone: 1-800-645-3475 www.nilfiskcfm.com When thinking about explosive materials,

More information

Using HAZOP/LOPA to Create an Effective Mechanical Integrity Program

Using HAZOP/LOPA to Create an Effective Mechanical Integrity Program Using HAZOP/LOPA to Create an Effective Mechanical Integrity Program Steven T. Maher, PE CSP & David J. Childs 949/282-0123 www.rmpcorp.com Download Presentation & Handout www.sems1.com/gcps/2017.htm Steven

More information

Joint Responsibility for Health and Safety Internal Guidance for Members and other occupiers of the Scottish Parliament Campus.

Joint Responsibility for Health and Safety Internal Guidance for Members and other occupiers of the Scottish Parliament Campus. To: Leadership Group From: Jake Fenton Extension: 86917 Date: 17/5/12 Dear Colleague, S. Joint Responsibility for Health and Safety Internal Guidance for Members and other occupiers of the Scottish Parliament

More information

Learning From Risk Control System Failures. Mike Jones

Learning From Risk Control System Failures. Mike Jones Learning From Risk Control System Failures Mike Jones MIKE JONES Chief Consultant CRA Industrial Process Assurance Process Safety/Technical Safety Consultant 43+ years experience in Industry/HSE/Consultancy

More information

Key Topics. Steven T. Maher, PE CSP. Using HAZOP/LOPA to Create an Effective Mechanical Integrity Program. David J. Childs

Key Topics. Steven T. Maher, PE CSP. Using HAZOP/LOPA to Create an Effective Mechanical Integrity Program. David J. Childs Steven T. Maher, PE CSP Using HAZOP/LOPA to Create an Effective Mechanical Integrity Program Steven T. Maher, PE CSP & 949/282-0123 www.rmpcorp.com 37-Year Engineer 33 in Process Safety Consulting Specializing

More information

FIRE INSPECTION GUIDELINES FOR FOSTER GROUP HOME PARENTS Effective June 1, 2002, Update September 2011

FIRE INSPECTION GUIDELINES FOR FOSTER GROUP HOME PARENTS Effective June 1, 2002, Update September 2011 HCFMO Harris County Fire Marshal M.S. Montgomery Fire Marshal FIRE INSPECTION GUIDELINES FOR FOSTER GROUP HOME PARENTS Effective June 1, 2002, Update September 2011 EFFECTIVE JANUARY 1, 2007 These guidelines

More information

B. Contact Information: Hannah K. Morgan Sustainability Coordinator 202 Netzer Administration Building

B. Contact Information: Hannah K. Morgan Sustainability Coordinator 202 Netzer Administration Building A. Proposal Title: Storm Water Initiative Project (SIP): An Interdisciplinary Initiative and Experiential Learning Opportunity to Promote the Campus as a Living Laboratory B. Contact Information: Hannah

More information

FIRE SAFETY POLICY June 2014

FIRE SAFETY POLICY June 2014 FIRE SAFETY POLICY June 2014 Policy Title Fire Safety Policy Reference Number Corpo11/002 Implementation Date June 2014 1 st Review Review Date June 2017 Responsible Officer Director of Performance and

More information

a) Establishment of emergency procedures to be followed at the time of an emergency;

a) Establishment of emergency procedures to be followed at the time of an emergency; 5.10 Fire Safety 5.10.1 Introduction The Corporation is responsible for carrying out the provisions of the Ontario Fire Code. This section outlines our responsibilities as well as inspections and testing

More information

To seek Cabinet approval of the Council s Fire Safety Policy. It is proposed that Cabinet approves the Fire Safety Policy.

To seek Cabinet approval of the Council s Fire Safety Policy. It is proposed that Cabinet approves the Fire Safety Policy. NORTH AYRSHIRE COUNCIL Cabinet 1 May 2018 Title: Purpose: Recommendation: Fire Safety Policy To seek Cabinet approval of the Council s Fire Safety Policy. It is proposed that Cabinet approves the Fire

More information

Burn Injury Investigation Report Preparing a Live Fire Prop for Use Miami-Dade County Fire Rescue Department, November 18, 2011

Burn Injury Investigation Report Preparing a Live Fire Prop for Use Miami-Dade County Fire Rescue Department, November 18, 2011 Burn Injury Investigation Report Preparing a Live Fire Prop for Use Miami-Dade County Fire Rescue Department, November 18, 2011 Florida Safety Investigation Report Prepared by the Safety Section Bureau

More information

Gulf Sulphur Services Ltd., LLLP. Hookers Point Terminal - Tank #8 Fires. LEPC November 20, 2013

Gulf Sulphur Services Ltd., LLLP. Hookers Point Terminal - Tank #8 Fires. LEPC November 20, 2013 Ltd., LLLP Hookers Point Terminal - Tank #8 Fires LEPC November 20, 2013 James Teets, P.E., Reliability Manager, Savage Services 0 Terminal Operations Savage is the operator of the GSS terminals GSS We

More information

Trinity River Authority of Texas

Trinity River Authority of Texas Trinity River Authority of Texas Central Regional Wastewater System 3110.005.100 November 19, 2015 Attention: Contractors / Suppliers / Delivery Personnel Subject: Central Regional Wastewater System Risk

More information

Fire Safety Plan FOR. Business/Property Name: Address: Phone Number: Occupancy Classification. Approved by Fire Inspector: Date:

Fire Safety Plan FOR. Business/Property Name: Address: Phone Number: Occupancy Classification. Approved by Fire Inspector: Date: Fire Safety Plan FOR Business/Property Name: Address: Phone Number: Occupancy Classification Approved by Fire Inspector: Date: Table of Contents Part 1 Building Resources Audit Page 3 Part 2 Human Resources

More information

NOTTINGHAM CITY HOMES

NOTTINGHAM CITY HOMES APPENDIX 1 NOTTINGHAM CITY HOMES FIRE SAFETY POLICY 2013/14 Draft for Board Uncontrolled when printed Page 1 of 14 DOCUMENT CONTROL Identification and Approval Status Document Title: Nottingham City Homes

More information

User s Information Manual

User s Information Manual Gas-fired Water boiler Series 2 NOTICE: Series 1/Series 2 identification Read the boiler rating plate to determine the series number. The rating plate is located on the right side of the boiler. User s

More information

User s Information Manual

User s Information Manual User s Information Manual Gas-fired water boilers Series 4 Featuring Flexibility Series 4 If the information in this manual is not followed exactly, a fire or explosion may result, causing property damage,

More information

A Bridge to Inspection

A Bridge to Inspection A Bridge to Inspection Mr. Roy L. Murphy Senior Marine Inspector US Coast Guard Towing Vessel National Center of Expertise 270-444-7715 Roy.L. Murphy @USCG.MIL 1 4/5/2013 Towing Vessel Bridging Program

More information

Andrew Blair CCG(Scotland)Ltd

Andrew Blair CCG(Scotland)Ltd Andrew Blair CCG(Scotland)Ltd Unreliable timekeeping Sporadic Patrols Missing in Action Sleeping on Job Poor Morale Intimidated Challenge! Improve security of our sites Reduce reliance on static guards

More information

Project System Audit Construction Environmental, Health and Safety (EH&S)

Project System Audit Construction Environmental, Health and Safety (EH&S) Project System Audit Construction Environmental, Health and Safety (EH&S) Table of Contents 1. General... 2 2. Environmental/Health/Safety (EH&S) Plan... 3 3. Emergency Procedures... 4 4. Environmental

More information

CORPORATE SERVICES HEALTH AND SAFETY

CORPORATE SERVICES HEALTH AND SAFETY CORPORATE SERVICES HEALTH AND SAFETY Mandate OHS Act No 85, 1993 Every employer which employs more than 20 person must comply with the OHS Act. To provide for the health and safety of persons at work and

More information

Fire safety procedure

Fire safety procedure Fire safety procedure Review date: October 2020 Responsible (s): Health and Safety Applicable to Staff: Accessible to Students: Accessible to general public: (including clients) Yes Yes Yes 1 Contents

More information

SAFETY EXCELLENCE AWARD 2014 TECHNICAL SUPPORT SAFETY SURVEY FORM FINAL EVALUATION

SAFETY EXCELLENCE AWARD 2014 TECHNICAL SUPPORT SAFETY SURVEY FORM FINAL EVALUATION SAFETY ECELLENCE AWARD 2014 TECHNICAL SUPPORT SAFETY SURVEY FORM FINAL EVALUATION SCORING: For each item listed below, decide if the entry meets the criteria as follows: 0 = Below Average 1 = Average 2

More information

Diocese of Cleveland Facilities Services Corporation

Diocese of Cleveland Facilities Services Corporation Diocese of Cleveland Facilities Services Corporation BOILER MAINTENANCE and SERVICING SEASONAL MAINTENANCE - to be performed by trained boiler technician or boiler contractor only: 1. Disassemble the low

More information

Evaluation and Compliance with Facility Siting Regulations in the US API RP 752 / 753 / 756

Evaluation and Compliance with Facility Siting Regulations in the US API RP 752 / 753 / 756 Evaluation and Compliance with Facility Siting Regulations in the US API RP 752 / 753 / 756 Presented by Gary Fitzgerald Director San Antonio, Texas U.S.A. Overview Safety Moment Introduction to Facility

More information

LEICESTER GRAMMAR SCHOOL TRUST FIRE SAFETY POLICY

LEICESTER GRAMMAR SCHOOL TRUST FIRE SAFETY POLICY LEICESTER GRAMMAR SCHOOL TRUST LEICESTER GRAMMAR SCHOOL POLICY STATEMENT FIRE SAFETY POLICY It is Leicester Grammar School Trust s policy to protect all persons on the Leicester Grammar School premises

More information

COMBUSTIBLE DUST HAZARD RECOGNITION

COMBUSTIBLE DUST HAZARD RECOGNITION COMBUSTIBLE DUST HAZARD RECOGNITION GUIDE FOR WORKERS AND FRONT LINE SUPERVISORS TABLE OF CONTENTS CBC Another Sawmill Explosion... 3 A] Combustible Dust Hazard Recognition Introductory Course... 3 B]

More information

Safety Systems Review Retail Guidance and specification Version

Safety Systems Review Retail Guidance and specification Version Systems Review Retail Guidance and specification Version 1 2014 Membership Training Qualifications Audit and Consultancy Policy and Opinion Awards Contents Page Systems Review 1 1 Specification for Systems

More information

F.R.A.M.E. EVENT NETWORKS used in "FRAME".

F.R.A.M.E. EVENT NETWORKS used in FRAME. EVENT NETWORKS used in "FRAME". In 2004, Dipl. Ing. Trond Maag wrote his doctorates' thesis "Risikobasierte Beurteilung der Personensicherheit von Wohnbauten im Brandfall unter Verwendung von Bayes'schen

More information

International Journal of Advance Engineering and Research Development

International Journal of Advance Engineering and Research Development Scientific Journal of Impact Factor (SJIF): 4.72 International Journal of Advance Engineering and Research Development Volume 5, Issue 01, January -2018 e-issn (O): 2348-4470 p-issn (P): 2348-6406 APPLICATION

More information

ELECTRICAL EQUIPMENT IN HAZARDOUS AREAS (EEHA) TESTING STANDARD

ELECTRICAL EQUIPMENT IN HAZARDOUS AREAS (EEHA) TESTING STANDARD Planning and Capability Group Mechanical and Electrical Services ELECTRICAL EQUIPMENT IN HAZARDOUS AREAS (EEHA) Document No.: VERSION 1 REVISION 3 AUGUST 2014 FOREWORD Electrical Equipment in Hazardous

More information

NHS Tayside. Fire Safety Policy

NHS Tayside. Fire Safety Policy NHS Tayside Fire Safety Policy Policy Manager Mark Anderson, Head of Property Policy Group Fire Safety Policy Review Group Policy Established Last Updated April 2014 Policy Review Period/Expiry April 2017

More information

NITRATE FILM PRESERVATION FACILITY

NITRATE FILM PRESERVATION FACILITY AUDIT REPORT NITRATE FILM PRESERVATION FACILITY INTERNAL AUDIT FUNCTION AUDIT AND EVALUATION DIRECTORATE JULY 2012 TABLE OF CONTENTS EXECUTIVE SUMMARY... 3 INTRODUCTION... 6 BACKGROUND... 6 RISK ASSESSMENT...

More information

COUNTY OF BERGEN DEPARTMENT OF PUBLIC SAFETY LAW AND PUBLIC SAFETY INSTITUTE POLICE, FIRE & EMS ACADEMIES 281 Campgaw Road Mahwah, N.J.

COUNTY OF BERGEN DEPARTMENT OF PUBLIC SAFETY LAW AND PUBLIC SAFETY INSTITUTE POLICE, FIRE & EMS ACADEMIES 281 Campgaw Road Mahwah, N.J. COUNTY OF BERGEN DEPARTMENT OF PUBLIC SAFETY LAW AND PUBLIC SAFETY INSTITUTE POLICE, FIRE & EMS ACADEMIES 281 Campgaw Road Mahwah, N.J. 07430 (201)785-6000 Police FAX (201)785-6036 Fire FAX (201)785-6036

More information

Initial Version Revision No. 0 Next Review Date: Preparation: Safety Mgr Authority: President Issuing Dept: Safety Page: Page 1 of 6

Initial Version Revision No. 0 Next Review Date: Preparation: Safety Mgr Authority: President Issuing Dept: Safety Page: Page 1 of 6 Revision Preparation: Safety Mgr Authority: President Issuing Dept: Safety Page: Page 1 of 6 PURPOSE The emergency response plan designates safe assembly areas, emergency coordinators, and procedures to

More information

Electrical Safety Policy and Management System

Electrical Safety Policy and Management System TITLE: PAGE: 1 OF 14 Housing Solutions Limited Electrical Safety Policy and Management System Page 1 of 15 TITLE: PAGE: 2 OF 14 FOREWORD This document details the system for the management of electrical

More information

Fire Prevention Plan

Fire Prevention Plan Hoopa Valley Tribe Insurance Department Fire Prevention Plan Draft April 2009 Hoopa Office of Tribal Safety 103 Willow Street, Suite B Hoopa, CA 95546 530.625.9200 x15 Fax 530.625.4269 Safety Officer,

More information

NECA S System Approach to Electrical Safety for NFPA 70E

NECA S System Approach to Electrical Safety for NFPA 70E NECA S System Approach to Electrical Safety for NFPA 70E NECA s Systems Approach to NFPA 70E Easy to understand NFPA 70E employer requirements, Provides Supervisors with key on the job information, De-energize

More information

Compliance Guidance for non-technical managers

Compliance Guidance for non-technical managers 11699 Brookpark Road Cleveland, OH 44130 USA P: 888-826-3473 F: 216-398-8403 www.combustionsafety.com -WHITEPAPER- NFPA 56 (2012 Ed.) Standard for Fire and Explosion Prevention During Cleaning and Purging

More information