1 ELECTRICAL SAFETY INSPECTION REPORT MUAZUDDIN TEXTILES LTD. Plot # 235/236, East Chandura, Shafipur, Kaliakor, Gazipur, Bangladesh. Factory List: 1. Inspected by: Younten Jamtsho Report Generated by: Stabak Das Inspected on March 18, 2014

2 SUMMARY. is housed in one six-storied building and five separate sheds. The building and sheds were constructed in 2006 for industrial purpose. There were 1550 workers in the premises during the inspection. The Factory was surveyed for electrical safety by Woosun Energy and Construction Co., Ltd. (WEC). The purpose of the survey was to identify significant electrical safety issues and to provide recommendations for remediation based on applicable standards specified by the Accord. The scope of this initial electrical safety inspection was limited to the review and identification of major electrical safety issues. The inspection did not include identification of minor deficiencies, which will be further addressed as part of follow-up inspections. Table below summarizes the major electrical safety issues identified during the inspection. Recommendations have been provided to address each issue. An implementation schedule shall be developed by the factory to remediate each of the findings. The specific timing of improvements, including any requested extensions due to design / installation constraints, shall be submitted to the Accord for approval. Page 2 of 9

3 FINDINGS AND RECOMMENDATIONS Finding No: E- 1 Category: SERVICE LINE HT service cable dropping from pole is not protected near the base of the pole. HT cable dropping from HT pole must be protected in steel pipe of required size at least 2m from the ground level to protect from physical damage. Remediation Timeframe: 6 months Service line dropping from pole is not protected and filled up with dust in its base. Finding No: E- 2 Category: SERVICE LINE Service line entering building without support. Service cables passing through walls must be protected in steel pipes. The openings remaining after passing of the cables should be sealed with fire rated materials. Remediation Timeframe: 3 months Service cable entering to building is not protected. Page 3 of 9

4 Finding No: E- 3 Category: TRANSFORMER ROOM Silica gel in transformer breather, discolored. Shut down the transformer and replace the silica gel or perform maintenance to remove moisture from it. Remediation Timeframe: 3 month Silica gel of transformer is discolored. Finding No: E- 4 Category: ROOM TRANSFORMER HT cable entering panel touching sharp steel edges of the enclosures. Cables must be protected from possible damage due to sharp edge installing cable glands at entry and cable-tie(instead of wire) should be used for tying the cable. Remediation Timeframe: 3 month HT cable touching sharp edge HT of panel. Finding No: E- 5 Category: WIRINGS Wiring in flexible PVC conduit not supported. Wiring in flexible PVC conduit must be supported on cable-tray or riser and protected where required.flexible conduit must not be used for long point wiring (except for special wirings). Wiring in flexible PVC conduit near boiler room is not supported Page 4 of 9

5 Finding No: E- 6 Panel is installed on cable tray. Panel base must be securely fixed to the foundation/wall, with appropriate fixations. Panel base frame may be used on foundation to mount the panel. Panel is situated on cable tray. Finding No: E- 7 Panel base plates removed to allow cable entry. Make circular hole at the base plate of panel and provide cable gland according to the respective cable size for cable entry and exit so that the cables are not stressed on the sharp edges of the hole of panels. Provide covers (of noncombustible material) if any additional gap remains after installing cable glands. Base plate of panel is not installed. Finding No: E- 8 Panel not readily accessible. Panels located below stairs must be relocated to safe place for ease of access to panel. Distribution panel is not protected Page 5 of 9

6 Finding No: E- 9 Control and protection devices in the systems are not coordinated. Control devices used to control and protect the system must be rearranged such as the downstreambreakers trip before the main circuit breaker. Incoming and outgoing wires are not coordinated Finding No: E- 10 Cable inside panel touching bare bus bar. Cables inside panel must be securely fastened, through PVC wiring-ducts to avoid crossing live parts. Cable touching bus bar. Finding No: E- 11 Cables terminating at panel, not supported. Cables behind panel must be supported and arranged on covered cable trays or ladder. Cable terminating inside distribution panels. Page 6 of 9

7 Finding No: E- 12 Cables connecting to bus bar/mccb inside panel without cable lugs. Cables connecting to bus bar/mccb inside panel must be connected firmly with cable lugs according to cable size.cable terminating to the MCCB must be fixed with proper size nuts and bolt. Cables connecting to MCCB without cable lug Finding No: E- 13 Barrier/separators between different phases are not installed. Install separators between different phases of MCCB. Standard separators provided by the MCCB manufacturer must be used. Phase separator is not used in MCCB Finding No: E- 14 Looping arrays of MCBs with jumper wires in panel. Use individual cable from bus bar for each MCB or plug-in bus bar instead of looping. Connection inside distribution panels. Page 7 of 9

8 Finding No: E- 15 Multiple wires installed in single lug/terminal. Every wire terminating must be installed using individual lug/terminal. Terminate each cable individually on the bus bar. Multiple cables shall not be terminated on same point of bus bar. Cables connecting to MCCB without cable lug Finding No: E- 16 Category: CABLE & CABLE SUPPORTS Excessive lint deposit in cable duct.. Disconnect the power source of the cable laid into channel and clean dust and debris of all interior components. Establish a periodic cleaning program and maintain records of the activities. Provide cover made of noncombustible material on the channel for preventing ingress of dust and debris in future. Phase separator is not used in MCCB Finding No: E- 17 Category: CABLE & CABLE SUPPORTS Wires exposed while transiting between different wiring systems. Wires in wiring must be protected and supported throughout its length. Wiring exposed between different wiring systems may be prevented by selecting appropriate adapter to connect. Connection inside distribution panels. Page 8 of 9

9 Finding No: E- 18 Category: CABLE & CABLE SUPPORTS Cables are laid in floor and covered with dust. Cables must be supported on covered cable trays and riser to prevent any physical damage. Cables are laid in floor and covered with dust. Finding No: E- 19 Combustible materials stored near panels and electrical installations. Cloths piled or stored near panel(s) must be removed and ensure flammable objects are not touching the electrical installations. Cloths are stored near panel of MCB Page 9 of 9

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT SIKDER APPAREL HOSIERY LTD. Khadun (Dug No. 342/343), Tarabo, Rupgonj, Narayanganj, Bangladesh. Factory List: 1. Sikder Apparel Hosiery Ltd. Inspected by: Pema Wangdi

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT MILLENNIUM TEXTILES (SOUTHERN) LTD., Bara Rangamatia, Ashulia, Savar, Dhaka 1341, Bangladesh Factory List: MILLENNIUM TEXTILES (SOUTHERN) LTD., Inspected on April 8,

More information

TIME KNITWEAR (PVT) LTD.

TIME KNITWEAR (PVT) LTD. ELECTRICAL SAFETY INSPECTION REPORT TIME KNITWEAR (PVT) LTD. Baribogh, Enayetnagar, Fatullah, Narayangonj-1400, Bangladesh Factory List: 1. Time Knitwear (Pvt) Ltd. Inspected by: Dawa Report Generated

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT SIDKO LIMITED PLOT NO. 36, ROAD NO. 46, GULSHAN NORTH C/A, DHAKA. Factory List: 1. N. A. Garments 2. 3. Sidko Apparels 4. Delta Ties Ltd. Inspected on April 17, 2014

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT FOPTEX (PVT.) LTD. PLOT# A/24-25, VSCIC HOSIERYFATULLAH, CHITTAGONG, BANGLADESH. Factory List: 1. Foptex (Pvt.) Ltd. Inspected by: Tashi Penjor Report Generated by:

More information

ELECTRICAL SAFETY INSPECTION REPORT ANLIMA TEXTILE LTD, DHAKA, BANGLADESH

ELECTRICAL SAFETY INSPECTION REPORT ANLIMA TEXTILE LTD, DHAKA, BANGLADESH ELECTRICAL SAFETY INSPECTION REPORT ANLIMA TEXTILE LTD, DHAKA, BANGLADESH January 14, 2014 Anlima Textile Ltd. PAGE 1 SUMMARY The Anlima compound located in Dhaka, Bangladesh was surveyed for Electrical

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT PIMKIE APPARELS LTD. PLOT # 328, BLOCK # F, TONGI, INDUSTRAL AREA OTHER FACTORIES: NONE May 25, 2014 Page 2 SUMMARY was surveyed for fire safety on 5/25/2014 by Hughes Associates,

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT PORTLAND TEXTILE LTD. ACCORD ID: 11873 PLOT NO. 14-15, SECTOR 6, CHITTAGONG EXPORT PROCESSING ZONE, CHITTAGONG OTHER FACTORIES: NONE November 3, 2015 Page 2 SUMMARY was surveyed

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT ABA FASHIONS LTD. SENA KALYAN COMMERCIAL COMPLEX (2ND FLOOR), PLOT # 9, BLOCK # F, TONGI, GAZIPUR March 16, 2014 Accord - Bangladesh RMG Fire Safety Inspection ABA Fashions

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT A-PLUS IND LTD PLOT # 28, MILK VITA ROAD, SECTION #07, MIRPUR, DHAKA - 1216, BANGLADESH March 10, 2014 Page 2 SUMMARY was surveyed for fire safety on 3/10/2014 by Hughes Associates,

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT YOUNG INTERNATIONAL PLOT NO. 32-36, SECTOR 5-CEPZ, CHITTAGONG OTHER FACTORIES: NONE July 20, 2014 Page 2 SUMMARY was surveyed for fire safety on 7/20/2014 by Hughes Associates,

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT KAROONI KNIT COMPOSITE RATANPUR, SHAFIPUR KALIAKOIR OTHER FACTORIES: NONE April 5, 2014 Page 2 SUMMARY was surveyed for fire safety on 4/5/2014 by Hughes Associates, Inc.

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT MAGPIE COMPOSITE TEXTILE LTD. 832/833, DEWAN IDRIS ROAD, AMTOLI, ASHULIA, SAVAR, DHAKA OTHER FACTORIES: NONE May 17, 2014 Page 2 SUMMARY was surveyed for fire safety on 5/17/2014

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT CHAITY COMPOSITE LTD. CHOTTO SHILMONDI, TRIPURDI, SONARGAON OTHER FACTORIES: NONE April 7, 2014 Page 2 SUMMARY was surveyed for fire safety on 4/7/2014 by Hughes Associates,

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT GLOBAL OUTWEAR LTD. PLOT # M/1, ROAD # 7, SECTION # 7, MIRPUR, DHAKA March 3, 2014 Accord - Bangladesh RMG Fire Safety Inspection Global Outwear Ltd. Page 2 SUMMARY Global

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT RAISA FASHIONS LTD. ACCORD ID: 11741 PLOT# B63, BSCIC INDUSTRIAL ESTATE, KANCHPUR, SONORGAON, NARAYANGANJ OTHER FACTORIES: NONE February 27, 2015 Page 2 SUMMARY was surveyed

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT AMAZON TEX KNIT FASHION LTD JOBEDA PLAZA, 85 AC DHAR ROAD KALIRBAZAR May 21, 2014 Page 2 SUMMARY was surveyed for fire safety on 5/21/2014 by Hughes Associates, Inc. This

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT N.A GARMENTS PLOT # 36, ROAD # 46, GULSHAN NORTH C/A, DHAKA OTHER FACTORIES: SIDKO LIMITED, SIDKO APPARELS LIMITED, DELTA TIES LIMITED April 17, 2014 Page 2 SUMMARY was surveyed

More information

FIRE SAFETY INSPECTION REPORT REDPOINT JACKETS LTD, DHAKA, BANGLADESH

FIRE SAFETY INSPECTION REPORT REDPOINT JACKETS LTD, DHAKA, BANGLADESH FIRE SAFETY INSPECTION REPORT REDPOINT JACKETS LTD, DHAKA, BANGLADESH January 3, 2014 Redpoint Jackets Ltd. PAGE 1 SUMMARY The four story factory housing Redpoint Jackets Ltd. located in Dhaka Export Processing

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT M.S.ATTIRES LTD. ACCORD ID: 10887 A. RAHMAN PLAZA, SHANSHONGAON, FATULLAH, NARAYANGONJ OTHER FACTORIES: AISA FASHION LTD.; PRINT GARDEN LTD.; S.M. COLLECTION LTD. February

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT AMITY DESIGNS LTD. HOUSE#7&9, ROAD#9 BLOCK D, SECTION #11MIRPUR DHAKA OTHER FACTORIES: NONE April 21, 2014 Page 2 SUMMARY was surveyed for fire safety on 4/21/2014 by Hughes

More information

INITIAL ELECTRICAL SAFETY ASSESSMENT - EXPANSION

INITIAL ELECTRICAL SAFETY ASSESSMENT - EXPANSION INITIAL ELECTRICAL SAFETY ASSESSMENT - EXPANSION Assessor: Nalzani, Chandana Joydebpur, Gazipur Joydebpur, Gazipur Dhaka Emkay Enterprises The Alliance for Worker Safety Page 1/13 Introduction to the Report

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT COMFORT APPAREL, ( PVT ) LTD. 96, DARUS SALAM, MIRPUR, DHAKA OTHER FACTORIES: SALMA FASHION WEARS LTD, COMFORT KNIT FASHION LTD March 27, 2014 Page 2 SUMMARY was surveyed

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT TUBA GARMENTS LTD. PLOT # 1682, ANANDA NAGAR, MERUL BADDA, BADDA, DHAKA OTHER FACTORIES: NONE July 5, 2014 Page 2 SUMMARY was surveyed for fire safety on 7/5/2014 by Hughes

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT MAHID APPAREL LTD ACCORD ID: 11956 NOWPARA, MADHABDI, NARSINGDI, DHAKA-1604 OTHER FACTORIES: NONE February 20, 2015 Page 2 SUMMARY was surveyed for fire safety on 2/20/2015

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT PADMA SWEATERS LTD. 1/B DARUS SALAM ROAD, SECTION 1. MIRPUR OTHER FACTORIES: NONE. July 9, 2014 Page 2 SUMMARY was surveyed for fire safety on 7/9/2014 by Hughes Associates,

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT ALAUDDIN GARMENTS LTD. 88, KAZI NAZRUL ISLAM AVENUE, TAJGAON, DHAKA- 1215 OTHER FACTORIES: CAMBRIDGE GARMENTS, PRIMODIAL April 27, 2014 Page 2 SUMMARY was surveyed for fire

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Assessor: Karardi, Shibpur, Narsingdi Narsingdi Dhaka Bangladesh Emkay Enterprises The Alliance for Bangladesh Worker Safety Page 1/15 10 Apr 2016 Introduction

More information

INITIAL ELECTRICAL SAFETY ASSESSMENT - EXPANSION

INITIAL ELECTRICAL SAFETY ASSESSMENT - EXPANSION INITIAL ELECTRICAL SAFETY ASSESSMENT - EXPANSION Yunusco (BD) Ltd(Formerly Shore To Shore Textiles Ltd.) Plot# 224-233, Adamjee EPZ, Shiddirgonj, Narayangonj Siddirgonj The Alliance for Bangladesh Worker

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT HAN A HATS & CAPS LTD. ACCORD ID: 12339 DAG NO. CS &SA-115/117, RS-188/181, KHOTION NO. CS-128, SA-274, BAIPAIL, ASHULIA, SAVAR, DHAKA. OTHER FACTORIES: TEXTSTREAM FASHION

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory Name: AJ Super Garments Ltd (Woven) Aj Garden, Goshbagh Zirabo Zirabo, Savar Savar Dhaka Bangladesh 23 Mar 2014 The Alliance for Bangladesh Worker Safety

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory Address: 687, Al-Haj Nurl Amin Sowdagar Lane CDA, R/A, Road No 20, South Agrabad Chittagong Chittagong Bangladesh 03 Apr 2014 The Alliance for Bangladesh

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT DANNY'S KNITWEAR LTD. ACCORD ID: 12228 SURABARI, GAZIPUR, SADAR, GAZIPUR Other Factories: ne October 17, 2015 Page 2 Fire Safety Inspection Report Introduction manufacturing

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory Assessor: 5th floor, Ehasan Tower, 227/B, Hafez Nagar, Bakalia, Chittagong. Uttaron 22 Jul 2014 The Alliance for Bangladesh Worker Safety Page 1/19 Factory

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT VINTAGE GARMENTS LTD EAST NARSHINGPUR, BURI PARA, ASHULIA, SAVAR Other Factories: ne June 1, 2014 Page 2 Fire Safety Inspection Report Introduction manufacturing complex was

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT MULTIFABS LTD KASHIMPUR, NAYAPARA Other Factories: ne April 9, 2014 Page 2 Fire Safety Inspection Report Introduction manufacturing complex was surveyed for fire safety on

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Address: Plot 61-64 & 70-73, Sector 02, KEPZ Karnafully, North Patenga, Chittagong Chittagong Chittagong Bangladesh The Alliance for Bangladesh Worker Safety

More information

SECTION PANELBOARDS Painting Wire and Cable Overcurrent Protective Devices.

SECTION PANELBOARDS Painting Wire and Cable Overcurrent Protective Devices. SECTION 16470 PANELBOARDS PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 09900 - Painting. 2. 16120 - Wire and Cable. 3. 16475 - Overcurrent Protective Devices. 1.02 SYSTEM DESCRIPTION A. Performance

More information

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Factory South Panishail, Kashimpur, Joydebpur, Gazipur Joydebpur, Gazipur 04 May 2014 The Alliance for Bangladesh Worker Safety Page 1/17 Factory 04 May

More information

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Hatimara Road, Barenda, Kashimpur, Gazipur, Gazipur Dhaka The Alliance for Worker Safety Page 1/18 Introduction to the Report The following report contains

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT BEQ KNIT LTD. ZIRABO, ASHULIA, SAVAR, DHAKA Other Factories: Beq Sweaters Ltd., Tammam Design Ltd. April 22, 2014 Page 2 Fire Safety Inspection Report Introduction manufacturing

More information

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT Assessor: Konabari, Neelnagar, Gazipur Gazipur Dhaka Bangladesh Uttaron The Alliance for Bangladesh Worker Safety Page 1/13 Introduction to the Report The following

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT Factory Name: AB APPARELS LTD ACCORD ID: 12589 ADDRESS: 225, SINGAIR ROAD, HEMAYETPUR, SAVAR Other Factories: None Inspected By: Md. Mah mudur Rahman & Shusmita Saha Date:

More information

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Factory Sharoj Tower, Plot No, M-4/2, Section-14, Mirpur, Dhaka Dhaka Dhaka 20 May 2014 The Alliance for Worker Safety Page 1/18 20 May 2014 Introduction

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory 81, Kalmessar, "Jalal Shopping Complex" Board Bazar, Gazipur. 20 May 2014 The Alliance for Bangladesh Worker Safety Page 1/21 20 May 2014 Introduction

More information

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Factory Address: Assessor: 1Plot # 4 (half) 8, 12 (half)-16, DEPZ (Old), Dhaka EPZ, Ganakbari, Ashulia, Savar Ashulia, Savar Dhaka Bangladesh Uttaron 25

More information

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Factory 50-60, Dakkhin Panishail. N.K. Link Road, Kashimpur, Gazipur Gazipur 08 May 2014 The Alliance for Bangladesh Worker Safety Page 1/23 08 May 2014

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory Name: Maks Fashion Ltd 1 Kapashgola Road Chawkbazar Chittagong Chittagong Bangladesh 19 Apr 2014 The Alliance for Bangladesh Worker Safety Page 1/15 19

More information

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT 171-181, Baizid Bostami Road Nasirabad I/A, Chittagong Chittagong The Alliance for Bangladesh Worker Safety Page 1/14 Introduction to the Report The following

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT FIRE SAFETY INSPECTION REPORT TOYO COMPOSITE KNIT GARMENTS LTD 1, SOUTH KAMALAPUR SARDER COMPLEX, DHAKA Other Factories: Pure Cotton Ltd, Knit and Knitwear Ltd June 7, 2014 Page 2 Fire Safety Inspection

More information

INSTALLATION, INSTRUCTION AND SERVICE MANUAL

INSTALLATION, INSTRUCTION AND SERVICE MANUAL PLATINUM SMART-HEAT ELECTRIC HEATER SERIES II BY BROMIC INSTALLATION, INSTRUCTION AND SERVICE MANUAL AVAILABLE IN 2300W VERSION Original Instructions IMPORTANT READ THIS MANUAL CAREFULLY. SEE INSIDE COVER

More information

INITIAL FIRE ASSESSMENT REPORT (FAR)

INITIAL FIRE ASSESSMENT REPORT (FAR) INITIAL FIRE ASSESSMENT REPORT (FAR) Factory 94/95 (OLD) 46 NEW (Ground To 5th), BLOCK C TONGI INDUSTRIAL AREA,, TONGI, GAZIPUR, GAZIPUR, 0, BD GAZIPUR Dhaka Bangladesh 11 Apr 2014 The Alliance for Bangladesh

More information

INITIAL FIRE SAFETY ASSESSMENT

INITIAL FIRE SAFETY ASSESSMENT INITIAL FIRE SAFETY ASSESSMENT Factory Name: Maks Fashion Ltd 1 Kapashgola Road Chawkbazar Chittagong Chittagong Bangladesh 19 Apr 2014 The Alliance for Bangladesh Worker Safety Page 1/16 19 Apr 2014 Introduction

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory Name: Plot 33-35, Dhaka (EPZ), Savar Savar Dhaka Bangladesh 06 Jul 2014 The Alliance for Bangladesh Worker Safety Page 1/19 06 Jul 2014 Introduction to

More information

A. Section includes distribution panelboards and lighting and appliance branch-circuit panelboards.

A. Section includes distribution panelboards and lighting and appliance branch-circuit panelboards. SECTION 262416 - PANELBOARDS PART 1 - GENERAL 1.1 SUMMARY A. Section includes distribution panelboards and lighting and appliance branch-circuit panelboards. 1.2 PERFORMANCE REQUIREMENTS A. Seismic Performance:

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory SFB 2 Adamjee EPZ, Siddergonj, Narayangonj, Siddhirgonj Dhaka 22 Feb 2017 The Alliance for Worker Safety Page 1/18 Factory 22 Feb 2017 Introduction to

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory Name: 4 YOU CLOTHING LTD 367/1 Senpara Parbata, Mirpur-10, Dhaka Dhaka Dhaka Bangladesh 27 May 2014 The Alliance for Bangladesh Worker Safety Page 1/18

More information

1. Distribution panelboards. 2. Lighting and appliance branch-circuit panelboards. 3. Load centers.

1. Distribution panelboards. 2. Lighting and appliance branch-circuit panelboards. 3. Load centers. September 2012, rev. 00 26 2416 Panelboards PART 1. GENERAL 1.01 Summary A. Section includes: 1.02 Definitions 1. Distribution panelboards. 2. Lighting and appliance branch-circuit panelboards. 3. Load

More information

INITIAL FIRE SAFETY ASSESSMENT

INITIAL FIRE SAFETY ASSESSMENT INITIAL FIRE SAFETY ASSESSMENT Factory Address: Plot 1175 & 1179, Bashan Sarak, Vogra, PO. National University, Gazipur Sadar, Gazipur Gazipur Dhaka Bangladesh 15 Jun 2016 The Alliance for Bangladesh Worker

More information

PRINTED: 06/09/2017 FORM APPROVED CENTERS FOR MEDICARE & MEDICAID SERVICES OMB NO (X2) MULTIPLE CONSTRUCTION A. BUILDING 03 - A BUILDING

PRINTED: 06/09/2017 FORM APPROVED CENTERS FOR MEDICARE & MEDICAID SERVICES OMB NO (X2) MULTIPLE CONSTRUCTION A. BUILDING 03 - A BUILDING SUMMARY PROVER'S PLAN OF CORRECTION K 000 INITIAL COMMENTS K 000 A Life Safety Code Survey was conducted by the State Fire Marshal beginning on May 9th, 2017 and ending on May 10th, 2017. Adair Acute Care

More information

Student Services & Classroom Addition. A. Section includes distribution panelboards and lighting and appliance branch-circuit panelboards.

Student Services & Classroom Addition. A. Section includes distribution panelboards and lighting and appliance branch-circuit panelboards. SECTION 262416 - PANELBOARDS PART 1 - GENERAL 1.1 SUMMARY A. Section includes distribution panelboards and lighting and appliance branch-circuit panelboards. 1.2 PERFORMANCE REQUIREMENTS A. Seismic Performance:

More information

INSTALLATION, INSTRUCTION AND SERVICE MANUAL

INSTALLATION, INSTRUCTION AND SERVICE MANUAL PLATINUM SMART-HEAT ELECTRIC HEATER SERIES II BY BROMIC INSTALLATION, INSTRUCTION AND SERVICE MANUAL AVAILABLE IN 2300W & 3400W VERSION Original Instructions Version 2.2 US IMPORTANT READ THIS MANUAL CAREFULLY.

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory Plot No. 60&61, Sector-3, KEPZ, North Patenga, Chittagong Chittagong 11 Feb 2015 The Alliance for Bangladesh Worker Safety Page 1/17 11 Feb 2015 Introduction

More information

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Factory 169-171 Tetulzhora Union, Hemayetpur, Savar Savar Dhaka 24 May 2014 The Alliance for Worker Safety Page 1/20 24 May 2014 Introduction to the Report

More information

INSTALLATION, INSTRUCTION AND SERVICE MANUAL

INSTALLATION, INSTRUCTION AND SERVICE MANUAL PLATINUM SMART-HEAT ELECTRIC HEATER SERIES II BY BROMIC INSTALLATION, INSTRUCTION AND SERVICE MANUAL AVAILABLE IN 2300W VERSION Original Instructions IMPORTANT READ THIS MANUAL CAREFULLY. SEE INSIDE COVER

More information

User Information Sheet 008 : 2010

User Information Sheet 008 : 2010 User Information Sheet 008 : 2010 Formerly UIS008, July 2009 ELECTRICAL INSTALLATIONS ASSOCIATED WITH BULK LPG INSTALLATIONS 1. Introduction This Information Sheet describes some of the principles and

More information

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Factory Assessor: 33/1, Darail, Shataish Tongi, Gazipur Tongi, Gazipur Dhaka Emkay Enterprises 26 Feb 2014 The Alliance for Worker Safety Page 1/12 26 Feb

More information

FIRE SAFETY INSPECTION REPORT

FIRE SAFETY INSPECTION REPORT Page 1 FIRE SAFETY INSPECTION REPORT Impress Fashion Ltd. ACCORD ID: 12245 Dag No. 2224, Matuial, Konapara, Katherpool, Jatrabari, Dhaka-1362 Other Factories: None Date: August 27, 2015 Sl No. Category

More information

Electrical Safety Requirements

Electrical Safety Requirements Electrical Safety Requirements Purpose This document defines the minimum required control measures to reduce the risk of injury or illness related to electricity. Scope Applicable to all Coca-Cola system

More information

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT

EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Factory Kunia, K.B.Bazar, Joy Bangla Road, Barabari, Gazipur Gazipur Dhaka 12 May 2014 The Alliance for Worker Safety Page 1/14 Factory 12 May 2014 Introduction

More information

INITIAL FIRE SAFETY ASSESSMENT

INITIAL FIRE SAFETY ASSESSMENT INITIAL FIRE SAFETY ASSESSMENT Factory Bashtoli, Sinabah, Sofipur, Kaliakoir, Gazipur Gazipur Dhaka 08 Sep 2014 The Alliance for Worker Safety Page 1/10 Factory 08 Sep 2014 Introduction to the Report The

More information

P-16 ENGINEER NO. DATE DESCRIPTION 1 01/19/2016 FOR CONSTRUCTION 2 03/11/2016 REVISION # 2 DRAWN BY: CHECKED BY: DATE: SCALE: DRAWING NUMBER

P-16 ENGINEER NO. DATE DESCRIPTION 1 01/19/2016 FOR CONSTRUCTION 2 03/11/2016 REVISION # 2 DRAWN BY: CHECKED BY: DATE: SCALE: DRAWING NUMBER PRESSIONAL P-16 PRESSIONAL PRESSIONAL PRESSIONAL 1 ONE LINE DIAGRAM 3 EMEGENCY LIGHTING SCHEME 2 FEEDER SCHEDULE PRESSIONAL PRESSIONAL PRESSIONAL PRESSIONAL LOCAL SINGLE POLE SWITCH 3-WAY SWITCH 3-WAY

More information

INITIAL FIRE SAFETY ASSESSMENT

INITIAL FIRE SAFETY ASSESSMENT INITIAL FIRE SAFETY ASSESSMENT Cha 72/1/C, Ground-4th FL, Progoti Swarani, Uttar Badda, Dhaka Dhaka The Alliance for Bangladesh Worker Safety Page 1/16 Introduction to the Report The following report contains

More information

INSTALLATION INSTRUCTIONS FOR 9330F4552 FREE DELIVERY PLENUM KITS

INSTALLATION INSTRUCTIONS FOR 9330F4552 FREE DELIVERY PLENUM KITS RV Products Division INSTALLATION INSTRUCTIONS FOR 9330F4552 FREE DELIVERY PLENUM KITS 8330-752 CONTROL BOX KIT (12 VDC COOL ONLY) 9330C755 CONTROL BOX KIT (12 VDC HEAT READY) 8530-750 CONTROL BOX KIT

More information

VACUUM BREAKER MEDIUM VOLTAGE AUTOMATIC TRANSFER SWITCHES

VACUUM BREAKER MEDIUM VOLTAGE AUTOMATIC TRANSFER SWITCHES Part One General 1.01 Scope A. It is the intent of this specification to provide a medium voltage automatic transfer system. B. All components, testing and services specified and required for a complete

More information

Letter of Recognition

Letter of Recognition Letter of Recognition The on Fire and Building Safety () hereby recognizes that: KARIM TEXTILES LIMITED (9297) orbag, Kaliakoir, Gazipur Has successfully completed all remediation measures required from

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory Name: Tetlabo, Rupgonj, Narayangonj Rupgonj Dhaka Bangladesh 27 May 2014 The Alliance for Bangladesh Worker Safety Page 1/22 27 May 2014 Introduction

More information

INITIAL FIRE SAFETY ASSESSMENT

INITIAL FIRE SAFETY ASSESSMENT INITIAL FIRE SAFETY ASSESSMENT Factory Anowara, Plot # G1 and G2, Korean EPZ, Chittagong Chittagong 21 May 2015 The Alliance for Bangladesh Worker Safety Page 1/22 21 May 2015 Introduction to the Report

More information

SECTION PANELBOARDS. A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section.

SECTION PANELBOARDS. A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section. PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section. 1.2 SUMMARY A. This Section includes the

More information

HEA USER MANUAL. 1 Version: 22. June 2010

HEA USER MANUAL. 1 Version: 22. June 2010 HEA USER MANUAL 1 Version: 22. June 2010 INDEX PAGE RECEIPT OF EQUIPMENT....... 3 LIFTING AND HANDLING.... 3 INSTALLATION INSTRUCTIONS...... 4 MAINTENANCE INSTRUCTIONS... 5 CONTROL OF INSULATION... 6 THERMOSTATS.

More information

Fixed Electrical Instillation Inspection

Fixed Electrical Instillation Inspection Fixed Electrical Installation Inspection Fixed Electrical Instillation Inspection Client: Contact: Company Name Name Report No.: 001-01-12 Survey Date: 26 TH of January 2012 Contact: Liam Taylor Donal

More information

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR)

INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory C-13, South Badda, Gulshan-1, Badda, Dhaka Dhaka Dhaka 22 May 2014 The Alliance for Worker Safety Page 1/21 22 May 2014 Introduction to the Report The

More information

Office Safety: Housekeeping

Office Safety: Housekeeping Office Safety: Housekeeping March 2017 Housekeeping Safety Simple changes in basic housekeeping practices can go a long way towards keeping our office safe. Use our tips on the following topics to keep

More information

RESIDENTIAL ELECTRICAL INSPECTIONS CHECKLISTS

RESIDENTIAL ELECTRICAL INSPECTIONS CHECKLISTS RESIDENTIAL ELECTRICAL INSPECTIONS CHECKLISTS Key Questions for Residential Inspections 1. What wiring methods will be used, and are the wiring methods suitable for the conditions? 2. Will multiwire branch

More information

INITIAL FIRE SAFETY ASSESSMENT

INITIAL FIRE SAFETY ASSESSMENT INITIAL FIRE SAFETY ASSESSMENT Factory Assessor: Plot no. A102, BSCIC Industrial Estate, Tongi, Gazipur Tongi, Gazipur Emkay Enterprises 06 Jul 2014 The Alliance for Bangladesh Worker Safety Page 1/22

More information

Electrical Preventive Maintenance (EPM) Program

Electrical Preventive Maintenance (EPM) Program Electrical Preventive Maintenance (EPM) Program Only qualified and properly trained persons may work on electric circuit parts or equipment. Such persons shall be capable of working safely and shall be

More information

INITIAL FIRE ASSESSMENT REPORT (FAR)

INITIAL FIRE ASSESSMENT REPORT (FAR) INITIAL FIRE ASSESSMENT REPORT (FAR) Factory SQ Station, Plot # 221-223, Jamirdia, Valuka, Mymensingh Mymensingh 17 Jun 2014 The Alliance for Bangladesh Worker Safety Page 1/17 Factory 17 Jun 2014 Introduction

More information

EL DORADO COUNTY REGIONAL FIRE PROTECTION STANDARD

EL DORADO COUNTY REGIONAL FIRE PROTECTION STANDARD EL DORADO COUNTY REGIONAL FIRE PROTECTION STANDARD INSTALLATION OF COMMERCIAL FIRE SPRINKLER SYSTEMS STANDARD #C-001 EFFECTIVE 03-25-2009 PURPOSE: To ensure that sprinkler plans submitted for review contain

More information

INITIAL FIRE SAFETY ASSESSMENT

INITIAL FIRE SAFETY ASSESSMENT INITIAL FIRE SAFETY ASSESSMENT Assessor: 28 S.S. Tower, Vogra, Joydebpur, Gazipur Joydebpur, Gazipur Dhaka Uttaron The Alliance for Worker Safety Page 1/17 12 Apr 2015 Introduction to the Report The following

More information

ENGINE GENERATORS AND ACCESSORIES

ENGINE GENERATORS AND ACCESSORIES ENGINE GENERATORS AND ACCESSORIES GENERAL INFORMATION 1.1 This section applies to engine generators and accessories. DESIGN REQUIREMENTS 2.1 The Engineer of Record will consult with the University s Engineering

More information

DC POWER DISTRIBUTION BOARD

DC POWER DISTRIBUTION BOARD DC POWER DISTRIBUTION BOARD February 2016 Engineering Department WEST BENGAL STATE ELECTRICITY TRANSMISSION COMPANY LIMITED Regd. Office: VidyutBhawan, Block DJ, Sector-II, Bidhannagar, Kolkata 700091.

More information

INSTALLATION, INSTRUCTION AND SERVICE MANUAL

INSTALLATION, INSTRUCTION AND SERVICE MANUAL PLATINUM SMART-HEAT ELECTRIC HEATER SERIES II BY BROMIC INSTALLATION, INSTRUCTION AND SERVICE MANUAL AVAILABLE IN 2300W & 3400W VERSION Original Instructions Version 3.2 AU IMPORTANT READ THIS MANUAL CAREFULLY.

More information

Installation and Maintenance Manual for Dimako NERM Panels REV 4. NERM Reference Manual NERM Panels 1 of 7

Installation and Maintenance Manual for Dimako NERM Panels REV 4. NERM Reference Manual NERM Panels 1 of 7 NERM Panels 1 of 7 Installation and Maintenance Manual for Dimako NERM Panels REV 4 Dimako Transformers Release VER 4 F:\Master Docs\Manuals\NERM.docx Page 1 of 7 NERM Panels 2 of 7 Table Of Contents Page

More information

Nirmal Chandra Sinha. Supposed to complete(dd/ MM/YYYY) Comments after Physical Inspection

Nirmal Chandra Sinha. Supposed to complete(dd/ MM/YYYY) Comments after Physical Inspection Factory Name Address Fire Safety Follow up INTIMATE APPARELS LTD Karnaphuli EPZ, Plot no. 91-93, rth Patenga Date 05/20/2014 Date Report Received 11-August/15 Date of 1 st Follow-up 08-vember/15 Date of

More information

INSTALL AN ELECTRIC SHOWER

INSTALL AN ELECTRIC SHOWER INSTALL AN ELECTRIC SHOWER The plumbing and wiring involved in installing an electric shower requires sound basic skills in both areas of expertise. Ensure that wiring and plumbing are properly installed.

More information

IT Module. User Manual. Document Revision Number 1 07/2013

IT Module. User Manual. Document Revision Number 1 07/2013 IT Module User Manual Document Revision Number 1 07/2013 Schneider Electric IT Module User Manual Table of Contents Table of Contents... 2 1. Safety Information... 3 2. Transportation and Installation...

More information

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT Vill: Golora, Post: Kaitta P.S. Saturia, Manikgonj Manikgonj, Dhaka The Alliance for Bangladesh Worker Safety Page 1/14 Introduction to the Report The following

More information

IMC Significant Changes Summary Tier I

IMC Significant Changes Summary Tier I 2009-2015 IMC Significant Changes Summary Tier I 202 Environmental Air The definition of environmental air has been expanded through the addition of parking garage exhaust. 306.1 Access More than just

More information

INITIAL FIRE SAFETY ASSESSMENT

INITIAL FIRE SAFETY ASSESSMENT INITIAL FIRE SAFETY ASSESSMENT Factory Mouza Chandra, Shafipur, Kaliakoir, Gazipur Gazipur Dhaka 24 Mar 2014 The Alliance for Worker Safety Page 1/12 24 Mar 2014 Introduction to the Report The following

More information

INITIAL FIRE SAFETY ASSESSMENT - EXPANSION

INITIAL FIRE SAFETY ASSESSMENT - EXPANSION INITIAL FIRE SAFETY ASSESSMENT - EXPANSION Factory Plot 47-52 & 68-73, KEPZ North Patenga Chittagong Chittagong 06 Mar 2017 The Alliance for Bangladesh Worker Safety Page 1/23 06 Mar 2017 Introduction

More information