1 INSTALLATIONGUIDELINESMANUAL January2018,Revision3.0 Beforeutilizingthisdocumentas aninstallationtool,installers shoulddownloadthelatestversion oftheinstallationguidelines Manualfromthetechnical downloadssectionofourwebsite atwww.watershedgeo.com. AdvancedRevetmentTechnology
2 TABLEOFCONTENTS 1.0INTRODUCTION LIMITATIONS SUBGRADEPREPARATION(HYDROTURF CSANDZ) GEOMEMBRANELINERCOMPONENT(HYDROTURF CSONLY) GeomembranePanelDeployment GeomembraneFieldSeaming/Welding Defects ENGINEEREDTURFCOMPONENT(HYDROTURF CSANDZ) SurfacePreparation(HydroTurf CS) EngineeredTurfDeployment(HydroTurf CSandZ) EngineeredTurfSeaming[FusionSeamingMethod(HydroTurf CSandHydroTurf Z) EquipmentonEngineeredTurf(HydroTurf CSandZ) HYDROBINDER INFILL(HYDROTURF CSANDZ) PlacementofHydroBinderInfill(HydroTurfCSandZ) BrushingoftheHydroBinderInfill(HydroTurf CSandZ) HydrationoftheHydroBinder Infill(HydroTurf CSandZ) ColdWeatherPlacementandCuringoftheHydroBinder Infill(HydroTurf CSandZ) PenetratingColloidalConcreteTreatmentfortheHydroBinder Infill(OptionalforHydroTurf CSandZ) BACKFILLINGOFTHEANCHORTRENCHES(HYDROTURF CSANDZ)
3 1.0Introduction HydroTurf AdvancedRevetmentTechnologyisapatentedsystemwhichisusedasahardened armoring for protection against erosion from hydraulic forces. There are three HydroTurf Systems.Thesesystemsareasfollows: HydroTurf CSwithaStructuredGeomembraneisshowninFigure1.Thecomponentsofthis systemareasfollows: StructuredGeomembraneLiner(50HmilHDPEAgruSuperGripnet Geomembrane) EngineeredSyntheticTurf HydroBinder Infill Penetrating Colloidal Concrete Treatment (PCCT) H Optional for Freeze / Thaw Protection Figure1 SectionofHydroTurf CSwithStructuredGeomembrane HydroTurf CSwithaTexturedGeomembraneisshowninFigure2.Thecomponentsofthis systemareasfollows: TexturedGeomembraneLiner(40HmilHDPEAgruMicroSpike Geomembrane) EngineeredSyntheticTurf HydroBinder Infill Penetrating Colloidal Concrete Treatment (PCCT) H Optional for Freeze / Thaw Protection 3
4 Figure2 SectionofHydroTurf CSwithTexturedGeomembrane HydroTurf ZisshowninFigure3.Thecomponentsofthissystemareasfollows: EngineeredSyntheticTurfwithIntegratedPolyethyleneFilmBacking HydroBinder Infill Penetrating Colloidal Concrete Treatment (PCCT) H Optional for Freeze / Thaw Protection Figure3 SectionofHydroTurf Z 4
5 2.0Limitations This manual is meant as a installation guideline only. Watershed Geosynthetics LLC cannot anticipatethemanywaysthisproductmaybeappliedeitherindesignorinstallation.varyingsite conditionswillrequireclosecoordinationbetweentheengineerandtheinstallertoaccountfor siteconditionsandadjustaccordingly.whenrequiredbystateand/orlocalregulations,alicensed professionalengineerorarchitectwillberequired. HydroTurf is a U.S. registered trademark which designates a product from Watershed GeosyntheticsLLC.ThisproductisthesubjectofissuedU.S.andforeignpatentsand/orpending U.S. and foreign patent applications. All information, recommendations and suggestions appearinginthisliteratureconcerningtheuseofourproductsarebasedupontestsanddata believedtobereliable_however,thisinformationshouldnotbeusedorrelieduponforanyspecific application without independent professional examination and verification of its accuracy, suitabilityandapplicability.sincetheactualusebyothersisbeyondourcontrol,noguaranteeor warrantyofanykind,expressedorimplied,ismadebywatershedgeosyntheticsllcastothe effectsofsuchuseortheresultstobeobtained,nordoeswatershedgeosyntheticsllcassume anyliabilityinconnectionherewith.anystatementmadehereinmaynotbeabsolutelycomplete since additional information may be necessary ordesirablewhen particular or exceptional conditions or circumstances exist or because of applicable laws or government regulations.nothinghereinistobeconstruedaspermissionorasarecommendationtoinfringe anypatent. 3.0SubgradePreparation(HydroTurf CSandZ) PriortoHydroTurf systeminstallation,thesoilsubgradeshallbeinspectedbytheengineerand geosyntheticscontractor.thefollowingshallbeobserved: The soil subgrade shall be compacted to the requirements as specified by the engineer.thesubgradeshallbefirmandunyielding. The soil subgrade shall be smooth and uniform, and shall be substantially free of surfaceirregularitiesandprotrusions. Thesoilsurfaceshallbefreeofforeignandorganicmaterial,sharpobjects,particles orotherdeleteriousmaterial,andshallnotcontainstonesorotherobjectsthatcould damageanyofthehydroturf components. Maximumparticlesize(e.g.stones)shallbespecifiedbythedesignandsiteHspecific specifications. Theanchortrenchesshallbepreparedasfollows: - Anchortrenchesshallbeexcavatedtothegradesanddimensionsasspecifiedon theconstructionplans.thegradesanddimensionsshallbeconfirmedbysurvey. - Anchortrenchesshallbestraightanduniformwithnoroughedges. - Theinsideedgeoftheanchortrenchshallberoundedandsmooth. - Anchortrenchesshallbefreeofsharpobjectsandotherdeleteriousmaterial. Constructionstakesandhubshavebeenremovedandtheresultantholeshavebeen backfilled. Finalgradesontheslopesaswellasbenchesdimensionsandgradesconformtothe designgrades. Survey shots and ashbuilt drawings shall be carefully reviewed and evaluated to ensurethesurfacegradeswilldrainasintendedinthedesigndrawings. 5
6 4.0GeomembraneLinerComponent(HydroTurf CSonly) InstallationoftheGeomembraneHDPELinermustbecompletedbyanapprovedgeosynthetics contractorwhocandemonstratesignificantexperiencewithinstallationofgeomembranes.each componentofthehydroturf systemwillrequirespecifictestingandsubmittalsbefore,duringor afterinstallationofthecomponent.itistheresponsibilityofthecontractortoensurethateach priorcomponentinstallationhasbeenapprovedbytheowner srepresentativebeforecontinuing withinstallationofthenexthydroturf component. 4.1GeomembranePanelDeployment EngineershallensurethatallPreHInstallationprocedureshavebeenfollowedbeforeproceeding withdeploymentofgeomembrane.asgeomembranecomponentpaneldeploymentproceeds, theengineerandthegeosyntheticscontractorshall: Ensure the geomembrane component is placed in direct and uniform contact with underlyingprotectivecoversoilorsubgradesoil. Observethegeomembranesurfaceasitisdeployedandrecordpaneldefectsand repairofthedefects(e.g. panel rejected, patch installed,etc.) onthe repair sheet. Repairsmustbemadeinaccordancewiththetechnicalspecificationsandlocatedon arepairdrawing. Supportequipmentisnotallowedonthegeomembranecomponentduringhandling unlessapprovedbydesignengineer. Confirmthatthesurfacebeneaththegeomembranecomponenthasnotdeteriorated sincepreviousacceptance. Confirmthattherearenostones,constructiondebris,soilclogsorotherdeleterious itemsonthesubgradethatcouldcausedamagetothegeomembranecomponent. The geomembrane component shall not be dragged across a surface that could damage the material. If the geomembrane component is dragged across an unprotectedsurface,it mustbeinspectedfordamage andrepairedorrejected,as necessary. The geomembrane component shall not be deployed during inclement weather conditionsasdefinedintheprojectspecificspecifications. Personnel working on the geomembrane component shall not smoke, wear boots/shoes that could damage the HydroTurf system components, or engage in activitiesthatcoulddamagethehydroturf systemcomponents. Themethodusedtodeploythegeomembraneshallminimizeripplesandeliminate wrinkles but does not cause bridging, and that the geomembrane is anchored to preventliftingormovementbythewind(geosyntheticscontractorisresponsiblefor any damage to or from windblown geomembrane). A wrinkle is a portion of the geomembrane that does not lay relatively flat and is not the result of a subgrade irregularity.awrinkleislargeenoughthatitcanbefoldedover.arippleistheresult of manufacturing or thermal expansion. It is smaller in nature than a wrinkle and cannotbefoldedover. The geomembrane component shall acclimate to the ambient temperature prior to welding. The ambient temperature is defined as the temperature of previously deployed and welded geomembrane panels. Additional acclimation time will be required when temperatures drop below 50 degrees Fahrenheit and when solar heatingisreduced. 6
7 Afterthepanelhasacclimatedandbeforeseamingoperationsbegin,wrinkleswillbe worked toward the toe of slope. Excess material can be worked out either by manpowerorutilizationwithequipmenttopullexcessslackoutofthepanel. Thegeosyntheticscontractorshallapplytensiontechniquestopulloutexcessmaterial /slackpriortoseaming. The horizontal or cross seams on the side slopes shall be staggered so that long horizontalseamsacrosstheslopearenotproduced. 4.2GeomembraneFieldSeaming/Welding Geomembranefieldseamingandweldingoperationsshallbeperformedasfollows: Wedgeweldingmachinesshallbealowprofilemachinewithaverticalheighttonot exceed3inchestothehighestpointofthewedge.installershalldemonstratethat eachwedgeweldingmachinemeetsthisrequirement. Thegeosyntheticscontractorshallhavethenumberofweldingapparatusesandspare partsnecessarytoperformthework. EquipmentusedforweldingwillnotdamageanyHydroTurf systemcomponents. The extrusion welding machine is purged prior to beginning a weld until the heat degradedextrudateisremoved. Theambienttemperature,measured6inchesabovethegeomembranesurface,is between 35 F and 104 F, or geomembrane manufacturer s recommended temperaturelimitsiftheyaremorestringent. Thecontactsurfacesofthesheetsareclean,freeofdust,grease,dirt,debris,and moisturepriortowelding. Theweldissubstantiallyfreeofdust,soil/mud,rocks,andotherdebris. The seams are overlapped a minimum of 3 inches for extrusion and hot wedge welding, or in accordance with geomembrane manufacturer's recommendations, whicheverismorestringent. Panelsshallbeoverlapped(shingled)inthedowngradedirection. Nosolventsoradhesivesarepresentintheseamarea. The procedure used to temporarily hold the panels together does not damage the panelsanddoesnotprecludecqatesting. The panels are being welded in accordance with the plans and site specific specifications. Thereisnoobviousfreemoistureintheweldarea. Observethatattheendofeachdayorinstallationsegment,unseamededgesare anchoredwithsandbagsorotherapprovedanchoringdevice. Penetrationanchorsshallnotbeusedtosecurethegeomembrane. Becauseofwedgewelding, ridges or tenting oftheseamsmayoccur.aprocess called snapping must be employed to remove the excess slack caused by the weldingprocess. Oncetwopanelshavebeenseamedtogetherorattheapprox.1/3seamingprocess aseam snapping processshouldbeappliedbeforetheseamcoolsdown.this methodisperformedwithmanuallaborbyutilizing3h4techniciansontheopenside ofthepanelapplyingapullingpressuretosnapoutthetentedweldedseam. 7
8 Normally,thistechniquerequiresseveralpeoplelinedupalongtheopenseamatthe edgeofthegeomembraneandapplyingclampstotheedge.thepanelisthen snapped intopositionandwhenappliedproperly,theexcessslackisremoved. Thesnappingtechniquewillbeappliedwhiletheweldingseamisstillwarm. Sandbagsalongthewedgeweldedseamwillreducereboundtenting. The snapping requirementisimportantinthatitallowstheengineeredturf componenttoliemoreevenlyoverthegeomembranecomponent. 4.3Defects Anyportionofthegeomembranewithadetectedflaw,mustberepairedinaccordancewiththe projectspecifications(e.g.,materialrequirements,installation,testing,etc.). 5.0EngineeredTurfComponent(HydroTurf CSandZ) The installation of HydroTurf engineered turf consists of the placement and seaming of the engineeredturfcomponentoverthestructuredgeomembraneliner(hydroturf CS)oroverthe soilsubgrade(hydroturf Z). Boxtruckswilldeliverupto27rollsengineeredturfpertruck.Nine(9)rollswillbestrapped togetherallowingequipment(i.e.pickhuptruck,skidsteer)topullthestrappedrollstothefrontof thetruck.rollscanbemovedtoadesignatedareabyusingacarpetstingerorliftedbystraps. During unloading, the contractor and / or CQA personnel shall confirm that the following is practicedandperformed: Theengineeredturfiswrappedinrollswithprotectivecovering. Therollsarenotstackedmorethan3high. Therollsarenotdamagedduringunloading. Protect the engineered turf from damage (i.e., mud, soil, dirt, dust, debris, cutting, impactforces,etc.). Eachrollmustbemarkedortaggedwithproperidentification. Rollsthathavebeenrejectedduetodamagearetoberemovedfromthesiteorstored atalocationseparatefromacceptedrolls,designatedbytheowner/operator. 5.1SurfacePreparation(HydroTurf CS) PriortoinstallationofEngineeredTurf,thefollowingshallbecompleted: ThegeomembranecomponentoftheHydroTurf CShasbeeninstalledinaccordance withthesitespecificspecifications. The required geomembrane installation documentation has been completed and approvedbytheengineerpriortoinstallationoftheengineeredturf. Thesurfaceofthegeomembranedoesnotcontainsoil/mud,stones,debrisorlarge scrapsleftoverfromtheinstallationprocess. 8
9 5.2EngineeredTurfDeployment(HydroTurf CSandZ) EngineeredTurfshallbedeployedasfollows: Observetheengineeredturfasitisdeployedandrecorddefectsanddispositionofthe defects(panelrejected,patchinstalled,etc.).repairsaretobemadeinaccordance withthespecifications. Equipmentusedshallnotdamagetheengineeredturf,underlyinggeomembraneor subgradebyhandling,trafficking,leakageofhydrocarbons,orbyothermeans. Panelsshallbedeployedsuchthattheseamoverlapsareshingledwiththeflowof water.thepanelontheuphflow/upstreamsideshallhavetheoverlapplacedontop ofthedownhflow/downstreampanel. Thepanelsshallbedeployedinamannertoensurethattheturffilamentsare pointingupslopeandinthesamedirectionastheadjacentpanel. Theturfshallbeballastedontheopenendstopreventmovementbythewindorother means (the contractor is responsible for any resulting damage from insufficient ballast). Theturfshallremainfreeofcontaminantssuchassoil/mud,debris,grease,fuel,etc. Theturfshallbelaidsmoothandsubstantiallyfreeoftension(butnotloose),stress, folds,ripples/wrinkles,orcreases.thegeomembrane(forhydroturf CS)ortheturf (forhydroturf Z)shallbeinintimatecontactwiththeunderlyingsubgrade Onslopes,theturfshallbesecuredwithsandbaganchoringatthetopoftheslope andthenrolleddowntheslope. OnsmallersizedHydroTurfZprojects.Anchoringcanbetemporarilyperformed usinglandscapespikes(typically,galvanized3/8 diameterby8to10hinlength)and leftinplacethentheanchortrenchesbackfilled. 5.3 Engineered Turf Seaming H Fusion Seaming Method (HydroTurf CS and HydroTurf Z) SeamingoftheengineeredturfcomponentofHydroTurf CSandZmaybeperformedbyfusion (heathbond)welding.thisisdescribedasfollows: EngineeredTurffusionseamingdeviceshallbeaDemTech4Hinch,singleHwedge welderonly(modelno.vmh20/4/aprohwedgewelder120v,vm20outfittedwith 100HKIT/4S/VC/A.2WeldingKit,4Hin,220V,S.S.). Fusionseamsrequireaminimumof5inchesofoverlap. Priortostartingtheproductionfusionseaming,trialseamsmustbeperformedas outlinedinsection below. Demonstratethepreparationmethodsandequipmentutilizedforremovalofthe salvagefromtheoutsideedgeoftherollsofturf(i.e.trimming&cuttingdevices). Mechanicaltrimmingandcuttingdeviceswillbeutilizedforsalvagetrimming.Box bladesandknivesshallnotbeutilizedforsalvagepreparations.frayingofgeotextile strandswhenperformingtheremovalofsalvageisnotacceptable. Frayedorlooseedgesand/orgeotextilestrandswillbecutofforremoved. Productionfieldseamsshallbeperformedinthesamemannerastrialseams. 9
10 Anydamageand/orburnoutsthatoccurduetoproductionseamingwillberepaired asoutlinedin Anydamageoftheengineeredturfshallbepatchedasoutlinedin Allseamsnotpassingthevisualinspectionshallberepairedasoutlinedin FusionSeamingMethodTrialSeamRequirements SincethetemperatureandspeedcontrolsoftheDemTechVMH20machinearevariable andcanbeincreased/decreaseddependingonweatherandenvironmentconditions,the temperatureandspeedshallbeconfirmedwithatrialseam.thistrialseamshallbefield tested.trialseamsshallbeperformedatthebeingofeachdayandduringthedaywhen theweather(i.e.,temperature)conditionschange. 1. Priortoturfcomponentwelding,CQApersonnelshallobserveanddocumentthe following: a. Turfweldingapparatusaretested_ i. atdailystarthup_and ii. immediatelyafteranybreak_or iii. anytimethemachineisturnedoffformorethan30minutes. 2. Procedures: a. Theturftrialweldwillbecompletedunderconditionslikethoseunderthe panelsthatwillbewelded. b. Ifatanytime,theCQAPersonnelbelievethatanoperatororfusionwelding apparatus is not functioning properly, a Field Trial Seam Test shall be performed. c. Anydisputeconcerningproperinstallationtechniquesortheproperfunctionof fusion welding equipment will be resolved by the OWNER S REPRESENTATIVE. d. Thetrialweldmustbeallowedtocooltoambienttemperaturebeforeseam snappingorpaneladjustmentsareapplied. 3. TrialSampleTestResults: a. Trialweldsamplesmustcomplywith VISUALPASSINGCRITERIA Visual passingcriteriaisverifiedwhenamanualpeel/pulltestisperformedandthe topturfpaneltuftstransfertothebottomturfpanel.thetransferofapprox. 75%ofthetuftsconstitutesapassingtrialweld.Also,thetrialseamshallbe continuouswithnogaps. 4. ProductionFieldSeamTestFailure: a. Lessthanapprox.75%ofthetopturfpaneltuftsdonottransfertothebottom turfpanel. b. Productionfieldseamsshallbeobservedtobecontinuouswithnogaps. 5. AdditionalTrialSampleTestingRequirements: a. Twoconsecutivetrialweldsmeetthevisualpassingcriteria. b. Thetrialweldsamplemustbeaminimumof3feetlongand12incheswide, withtheseamcenteredlengthwise. c. Ifaweldingapparatusexceeds5hoursinthesecondhalfoftheday,another trialseammustbeperformed. 6. CQAdocumentationoftrialseamprocedureswillincludethefollowing: a. Thenamesoftheseamingpersonnel_ b. Thenameofthefusionseamingtechnician_ 10
11 c. theweldingapparatusnumber,time,date_ d. ambientairtemperature_and e. weldingapparatustemperature&speedsetting RepairsandTieHInsProceduresforEngineeredTurf(HydroTurf CSandZ) WhenRepairs,capsandtieHinsofengineeredturfareneeded,thefollowingshallbeperformed: Repairstoengineeredturfshallbecompletedbyusinga4HinoverlappedheatHbonded seam. AlltieHinseamsalongflatterslope(i.e.15%orless)withlengthgreaterthan25feet shallusethedemtechvmh20singlewedgewelder(outfittedwiththesyntheticturf weldingkit)soacontinuous,consistentpressureisachievedthroughouttheseam. AhandHheldheatgun(i.e.Leister)withhandpressureshouldbeusedinshorteror smallerconcentratedareas(i.e.,buttseams,capsorpatches). Handleisteringshallbefieldtestedwithatrialseamtoconfirmproperseamingprior toproductionseaming.trialseamingshallbeperformedinaccordancewithsection EquipmentonEngineeredTurf(HydroTurf CSandZ) Duringconstruction,ATVtypevehiclesand/orrubbertrackedskidsteermachineswillbeallowed onflatterslopesforinfillplacementiftheirgroundpressureislessthan5psi.noequipmentshall beallowedonslopesexceeding15%withoutinfillinplace.equipmentoperatorsshallinspect equipmentrubbertiresortracksforsharpprotrusionsfromforeignmatterortire/trackdamage, embedded rocks, or other foreign materials protruding from tires/track prior to driving on the syntheticturf.equipmenttravelpathsdrivenonsyntheticturfshallbeasstraightaspossiblewith no sharp turns, sudden stops or quick starts. Damage caused by having equipment on the engineeredsyntheticturf(i.e.,tears,rips,punctures,wrinkles,ripples,movement,etc.)shallbe theresponsibilityoftheinstallertorepair. Onceconstructionofthesystemiscomplete.NoequipmentshallbealloweduntilHydroBinder Infillisinplaceandfullycuredfor28days.Postconstructionandafter28daysofcuringofthe HydroBinder, drivability tire (ground) pressures on slopes greater than 10% should be limited systemtolessthan35psi.allowablerubbertireortrack(ground)pressuresonflatterareasmay increasetoasmuchas60psiaslongassustainedtrafficloadisnotexpected.drivingshouldbe limitedtoareaswherethesubgradeunderthehydroturf iswellhcompacted,firmandunyielding. Hightrafficareasshallbedesignedtohandletheexpectedloads. 6.0HydroBinder Infill(HydroTurf CSandZ) HydroBinder Infill is a dry, highhstrength cementitious mix. It is provided by Watershed GeosyntheticswiththeHydroTurfsystem.TheHydroBinder infillisplaceddry,groomedinto theengineeredsyntheticturfandhydratedafterplacement. WhentheHydroTurfsystemisinstalledandHydroBinder infillisplacedandhydrated,itcreates ahardenedrevetmentarmoringthatcanresisttheforcesfromhighhydraulicflowvelocities. 11
12 6.1PlacementofHydroBinderInfill(HydroTurfCSandZ) HydroBinder Infillshallbeplacedasfollows: HydroBinder isdeliveredtothejobsiteonpalletsineither3000#bulkbags(1per pallet)or80#bags(42perpallet).itisdeliveredonaflatbedwith16pallets(typical) pertruckload. TheHydroBinder shallbeinstalledintotheturfwhileitisinadrystate. PriortoplacingtheHydroBinder,theengineeredturfshallbedry.Iftheturfiswet fromrainordew,theinstallershallwaituntilitisdry.theinstallermayattemptto speedupthedryingprocessbyusingablower(i.e.,leafblower,industrialblower,etc.). HydroBindershallnotbeinstalledininclement,wetorrainyweather,orthethreatof inclement weather. Also, the HydroBinder shall not be installed in freezing temperatures. TheHydroBinder infillshallbeplacedataminimumthicknessof¾hin.thisthickness isachievedbyplacingapproximately6to7lbs/sfofthedryhydrobinder overthe engineeredturf. Theinfillistobeplaced/spreadusingamanualdropspreader,topHdresserand/or dropspreaderattachedtolowgroundpressureequipmentwithadequatedustcontrol. Manualhandspreadingisacceptablewhenequipmentisnotpractical. If weep holes are required for draining the internal drainage layer through the engineeredturf(hydroturf CS),removetheHydroBinder intheareasoftheweep holespriortohydrationorblocktheweepholelocationspriortoinfilling.blocksmay consistofpipe,dowels,etc.weepholesaretypically½to¾hindiameterandare locatedatthetoeofslopeon2hftcenters. 6.2BrushingoftheHydroBinderInfill(HydroTurf CSandZ) TheHydroBinder infillwillneedtobeworkedintothetuftedfibersoftheengineeredturfsuch thattheturffibersareinanuprightposition.thiscanbeachievedasfollows: Theinfillshallbeworkedintothetuftfibers,sothetuftfibersareinanuprightposition withtheinfillatameasurable7/8hinchminimumdrythicknessanda¾hinchminimum finishedthicknessafterhydrationandcuring.typically,thisisachievedwithcommon mechanicalturfbroom,powerbroom,shopbroom,yardrakes,and/orgreensgroomer rakes. Brushing of the HydroBinder infill shall be performed such that the fibers of the engineeredturfareuprightandtrappedfibersareminimal.thisshallbeconfirmedby visualinspection.multiplebrushingpassesinmultipledirectionsmayberequiredto achievethis. Depending on the turf tufted pile height and style (monofilament or slithtape). The HydroBinder mayneedtobeplacedin2to4liftswithbrushinginbetweenliftsto effectivelyworkthematerialintothetuftstoachievefibersthatareupright. ThicknessmeasurementsoftheHydroBinder infillshallbetakenusingacaliperor equivalent device. Measurements shall be taken at a minimum frequency of 5 measurementsper1,000sf(forsmallerprojects)or20measurementsperacre(for largerprojects)ofinstalledarea. The desired HydroBinder infill thickness shall be achieved prior to the hydration process. 12
13 6.3HydrationoftheHydroBinder Infill(HydroTurf CSandZ) TheHydroBinder infillshallbehydratedinplaceasfollows: The hydration process shall occur on the same day as the HydroBinder infill placement. Theinfillshallbehydratedthoroughlywithalightandconsistentsprayofwaterto avoiddisplacementofthenonhhydratedinfill.estimatedapplicationrateisbetween 0.12and0.20gallonspersquarefootofarea.Hydrationratesmayvarydependingon thegeographicallocation(i.e.lowhumidareas,dessertairclimates,etc.),timeofyear (i.e.,fall,winter,springorsummer),and/ortemperatureandclimate. Theinstallershallnotoverhydratetheinfillsothatwaterbeginstorunoffandcause lossofcementinfillduringtheprocess.thegeneralobjectiveistosoaktheareato startthehydrationprocessbutnottoinundatewithwaterbeyondsaturationoftheinfill. Visual verification can be performed that the HydroBinder infill has been fully hydrated,andnotoverhydrated.visuallyobservethatthetopofthehydrobinderhas awetsheen(denotingsaturation)butthatwaterisnotpondingontop.also,excavate (withfingerorsmalltool)intothehydrobinder toconfirmfullhydrationofthesection hasbeenachieved. Toimprovecuring,thehydratedareamaybecoveredwithplasticsheeting. The HydroBinder infill shall harden within 24 hours following hydration, and shall reach its maximum compressive strength at 28 days. If the HydroBinder has not hardenedin24hours,itmayneedtoberehhydratedoritmayneedtoberemovedand replaced. Personnel access on the HydroTurf shall be prohibited for 24Hhr following the hydrationofthehydrobinder. OncehydrationiscompletedandtheHydroBinder hassetup,backfillandcompaction oftheanchortrenchesmaybeperformed. 6.4ColdWeatherPlacementandCuringoftheHydroBinder Infill(HydroTurf CS andz) ColdweatherplacementandcuringtechniquesforHydroBinder shallbeconsistentwithindustry standard techniques used for concrete and cement products. The following guidelines are suggested: Follow the procedures in American Concrete Institute (ACI) 306 Guide to Cold WeatherConcreting. Coldweatherexistswhentheairtemperaturehasfallento,orisexpectedtofallbelow 40degreesFduringtheprotectionperiod. Theprotectionperiodisdefinedasthetimerequiredtopreventconcretefrombeing affectedbyexposuretocoldweather.protectionperiodforhydrobinderis72hours fromhydration. Ensurethatfrostorfrozensurfacesarethawedwithnostandingwater.Atthetimeof HydroBinderplacement,thesubgradeandsurfaceoftheengineeredturfshallbeata temperatureofatleast36degreesfandrising. Heatedtarpsand/orinsulatedblanketsarerequiredtomaintainthetemperatureofthe HydroBinderabove55degreesFfortheprotectionperiod. 13
14 HeatedtarpsmaydryouttheHydroBinder.Donotallowittodryout.Youmayneed toaddmoistureanduseimpermeablecovers. Theprojectdesignengineerand/orresidentengineershallprovidetechnicalspecificationsand guidance for cold weather concreting based upon your specific project particulars (i.e., geographicallocation,weather,andtimeofyear),andtheengineershouldreviewandapprove allproposedinstallationmethods. 6.5PenetratingColloidalConcreteTreatmentfortheHydroBinder Infill(Optional forhydroturf CSandZ) Penetratingcolloidalconcretetreatment(PCCT)isanoptionalliquidapplicationandtreatmentfor thefreeze/thawprotectionofthehydrobinder infill.itshouldbeappliedtothehydrobinder whenspecified.thepcctshallbeappliedasfollows: PCCTshallideallybestoredinalocationthatisdryandbetween35 Fto100 F(2 Cto 38 C)ambienttemperature.Optimalstorageisatthemiddleofthetemperaturerange. ProtectthePCCTfromfreezing. ThefollowingshallbefollowedwhenapplyingthePCCT: - ThePCCTproductandtheHydroBinder surfaceshallbeattemperatureofat least36degf(2degc)andrising. - Donotapplyonfrozensubstrateorwhentemperaturecanfallbelow32 F within24hoursofapplication. - Ensurethatfrostorfrozensurfacesarethawedwithnostandingwater. - Areasofstandingwatershallberemovedpriortoapplication. - Donotapplyunprotectedduringperiodsofhighwinds. - PCCTshallnotbeappliedininclement,wetorrainyweather,orthethreatof inclementweather. - Donotapplywhensubstrateis90 F(32 C)orhigher.Ifsurfacetemperature ishigherthan90 F(32 C)thenpreHwettingwithwaterisrequired.Besureto removeanypuddlesbeforeapplyingofscp. - Whenhottemperatureanddirectsunlightconditionsexist,applyafinemist sprayofwateronthesurfaceafterapplicationofpcct. Apply PCCT as soon as the HydroBinder infill is hard enough to walk on without damagetothesurface. Usea1,500Hpsi(10.5MPa)airlesssprayersetatapressurethatwillnotdamagethe surface[i.e.,approximately400to900psi(2.5to6.5mpa)].forsmallprojects,a pumpsprayermaybeused. HoldwandandspraythePCCT6inches(15cm)fromthesurfaceoftheHydroBinder ata90ºangle. PCCTmustbeappliedusinganoverlappingspraypatternof50%onthepreviousrun. Anyareathatabsorbsproductfasterthan10minuteswillneedtobereapplieduntil theproductnolongerabsorbsfasterthan15minutes. IfPCCThasabsorbedthoroughlyinthemajorityofthearea,butthereispoolinginthe lowareas,useabroomtospreadadditionalpcctintotheareasalreadypenetrated. DonotallowPCCTtodryinpools.RemoveexcessPCCTwithadampmop.Applyat a rate of approximately 140 ft 2 per gallon of PCCT. If necessary, spray a second applicationofpcct. 14
15 Forslopedapplications,workfromlowesttohighestelevation.Verylightandrepeated spraypassesshouldbemadeonthesameareauntiltheconcretesurfacenolonger acceptspcct.moveontonextareaafterachieving pointofrejection. 7.0BackfillingoftheAnchorTrenches(HydroTurf CSandZ) HydroTurf reliesontheanchortrenchestoserveasaterminationpoint.topanchortrenches shouldbebackfilledasquicklyaspracticalafterengineeredturfcomponentisinstalled(priorto HydroBinderinfillplacement). Verticalanchortrenchesaswellasanchortrenchesalongthetoeshouldnotbebackfilleduntil the HydroBinder infill is in place. However, backfilling the vertical and toes anchor trench backfillingmayberequireddependingonsitespecificneeds.anchortrenchdimensionswillbe showninthedesigndrawings. Backfillingand/orsandbagloadingthebottomandsideanchortrenchesshallbeperformedto reducethermalexpansionandcontraction. When utilizing HDPE geomembrane, daily permanent and/or temporary anchoring should be considered due to the nature of HDPE contracting with overnight temperature changes and thermalenergyconditionschangingtoprotectthewrinklemanagementtechniquesappliedfrom contraction. Sand bags should also be utilized at the bottom perimeter ditch and benches to manage contractinggeomembraneseams.theamountofsandbagswillbedependentontemperatures BackfillingoftheanchortrenchesfortheHydroTurf CSshallbeperformedasfollows: Thegeomembranecomponentshallbeinintimatecontactwiththeanchortrenchinside wallandbottom.wrinkles,ripples,fishmouths,and/orbunchingshallberemovedand properlypatched. Thegeomembraneshallnotextenduptheoutsidewalloftheanchortrench.Itshallbe trimmedshortoftheoutsidewallandshallextendaminimumof¾ofthewidthofthe anchortrench. The engineered synthetic turf component shall be in intimate contact with the geomembrane. Wrinkles, ripples, fish mouths, and/or bunching shall be removed and properlypatched. Theengineeredsyntheticturfshallbetrimmedsothatitdoesnotextendontothebottom of the anchor trench. It shall be trimmed just short of the bottom and shall extend a minimumof¾ofthedepthoftheanchortrench. Duringfillingoftheanchortrenchwithcompactedsoilorconcretebackfill,thecontractor shallmaintainthatthegeomembraneisinintimatecontactwiththetrenchwallandbottom andthattheengineeredsyntheticturfisinintimatecontactwiththegeomembrane. Soilbackfillshallbecompactedinaccordancewiththespecificationsforengineeredfill. VibrationoftheConcretebackfillshouldbeconsideredandinaccordancewithstandard industrytechniques. BackfillingoftheanchortrenchesfortheHydroTurf Zshallbeperformedasfollows: 15
16 The engineered synthetic turf component shall be in intimate contact with the anchor trenchinsidewallandbottom.wrinkles,ripples,fishmouths,and/orbunchingshallbe removedandproperlypatched. Theengineeredsyntheticturfshallnotextenduptheoutsidewalloftheanchortrench.It shallbetrimmedshortoftheoutsidewallandshallextendaminimumof¾ofthewidthof theanchortrench. Duringfillingoftheanchortrenchwithcompactedsoilorconcretebackfill,thecontractor shallmaintainthatthegeomembraneisinintimatecontactwiththetrenchwallandbottom and that the engineered synthetic turf is in intimate contact with the structured geomembrane. Soilbackfillshallbecompactedinaccordancewiththespecificationsforengineeredfill. Concrete backfill shall be vibrated in place in accordance with standard industry techniques. 16
17 HYDROTURF is a U.S. registered trademark which designates a product from Watershed Geosynthetics, LLC. This product is the subject of issued U.S. and foreign patents and/or pending U.S. and foreign patent applications. All information, recommendations, and suggestions appearing in this literature concerning the use of our products are based upon tests and data believed to be reliable; however, this information should not be used or relied upon for any specific application without independent professional examination and verification of its accuracy, suitability and applicability. Since the actual use by others is beyond our control, no guarantee or warranty of any kind, expressed or implied, is made by Watershed Geosynthetics LLC as to the effects of such use or the results to be obtained, nor does Watershed Geosynthetics LLC assume any liability in connection herewith. Any statement made herein may not be absolutely complete since additional information may be necessary or desirable when particular or exceptional conditions or circumstances exist or because of applicable laws or government regulations. Nothing herein is to be construed as permission or as a recommendation to infringe any patent.
GEOMEMBRANE FIELD INSTALLATION
GEOMEMBRANE FIELD INSTALLATION CONTENTS Introduction Quality Control and Quality Assurance Types of lining systems Basic Lining Design Executive Lining Design Basic Lining Design Specification Executive
More informationINSTALLATION GUIDELINES FOR GEOTEXTILES USED IN FILTRATION AND DRAINAGE APPLICATIONS
INSTALLATION GUIDELINES FOR GEOTEXTILES USED IN FILTRATION AND DRAINAGE APPLICATIONS Prepared by TenCate Geosynthetics North America 365 South Holland Drive Pendergrass, GA 30567 Tel: (706) 693-2226 Fax:
More informationSPECIFICATIONS AND TECHNICAL REQUIREMENTS FOR THE MANUFACTURING AND INSTALLATION OF POLYETHYLENE GEOMEMBRANES
SPECIFICATIONS AND TECHNICAL REQUIREMENTS FOR THE MANUFACTURING AND INSTALLATION OF POLYETHYLENE GEOMEMBRANES The following specification constitutes a guideline for the preparation of site specific geomembrane
More informationAQUAMASTER INSTALLATION GUIDE
AQUAMASTER INSTALLATION GUIDE PROUD MEMBER Geosynthetic Materials Association PROUD MEMBER Industrial Fabrics Association International TABLE OF CONTENTS 1. GENERAL...1 1.1. Scope...1 1.2. Applications...1
More informationEnkaTech Note. Installation Guide for Enkamat Slopes and Channels. Site Preparation. Anchor Trench. Enkamat Installation
EnkaTech Note Installation Guide for Enkamat Slopes and Channels Site Preparation For both slope and channel applications, the site must be shaped to the design specifications (grade, geometry, soil compaction,
More informationPVC GEOMEMBRANE FABRICATION AND INSTALLATION SPECIFICATION
PVC GEOMEMBRANE FABRICATION AND INSTALLATION SPECIFICATION August 20, 2006 PVC Geomembrane Institute Technology Program 2215 Newmark Civil Engineering Laboratory 205N. Mathews Ave. Urbana, IL 61801 217-333-3929
More informationE R O S I O N C O N T R O L
E R O S I O N C O N T R O L GEOTEXTILES T O U G H O V E R T I M E EROSION CONTROL 1.0 Features of PERMANENT PG 2 EROSION CONTROL 2.0 How Typar geotextiles PG 2 work 4.0 Installation guide PG 6 5.0 Overlap
More informationSPECIAL SPECIFICATION 3687 Impermeable Liner
1993 Specifications CSJ s 0569-01-043 & 0945-04-025 SPECIAL SPECIFICATION 3687 Impermeable Liner 1. Description. This Item shall govern for the furnishing and installation of the impermeable liner (geomembrane)
More informationChesapeake Energy Center. Submitted To: Chesapeake Energy Center 2701 Vepco Street Chesapeake, VA 23323
NOTICE OF INTENT TO CLOSE INACTIVE CCR SURFACE IMPOUNDMENT NOTICE OF INTENT Chesapeake Energy Center Submitted To: Chesapeake Energy Center 2701 Vepco Street Chesapeake, VA 23323 Submitted By: Golder Associates
More information1993 Specifications CSJ SPECIAL SPECIFICATION ITEM Impermeable Liner
1993 Specifications CSJ 0128-01-085 SPECIAL SPECIFICATION ITEM 5327 Impermeable Liner 1. Description. This Item shall govern for the furnishing and installation of the impermeable liner (geomembrane) shown
More informationAcronyms. TRI TRI Environmental, Inc. Table of Contents. iii
Table of Contents Acronyms AEG American Environmental Group, Ltd. AMEC American Environmental & Infrastructure, Inc. CAT I Category I CES ARCADIS Construction and Environmental Services Group CQA Construction
More informationSPECIFICATIONS AND TECHNICAL REQUIREMENTS FOR THE MANUFACTURING AND INSTALLATION OF POLYETHYLENE GEOMEMBRANES
SPECIFICATIONS AND TECHNICAL REQUIREMENTS FOR THE MANUFACTURING AND INSTALLATION OF POLYETHYLENE GEOMEMBRANES The following specification constitutes a guideline for the preparation of site specific geomembrane
More informationV. EROSION CONTROL. -Drainage swales separation -Under rip-rap protected -Under rip-rap unprotected
V. EROSION CONTROL This section describes three different types of erosion control applications where geotextiles can be used in conjunction with some form of stone or other energy dissipating material
More informationINTERNATIONAL ASSOCIATION OF GEOSYNTHETICS INSTALLERS (IAGI) AND FABRICATED GEOMEMBRANE INSTITUTE (FGI)
INTERNATIONAL ASSOCIATION OF GEOSYNTHETICS INSTALLERS (IAGI) AND FABRICATED GEOMEMBRANE INSTITUTE (FGI) GUIDELINES FOR INSTALLATION OF: FACTORY FABRICATED LIGHTWEIGHT (
More informationGuidelines for Installing Rolled Erosion Control Products in Slope, Channel and Shoreline Applications Laurie Honnigford
Guidelines for Installing Rolled Erosion Control Products in Slope, Channel and Shoreline Applications Laurie Honnigford Soil erosion is evident in so many situations and the environmental impact can be
More informationNOTICE OF INTENT. Submitted To: Bremo Power Station 1038 Bremo Bluff Road Bremo Bluff, VA 23022
NOTICE OF INTENT TO CLOSE INACTIVE CCR SURFACE IMPOUNDMENTS NOTICE OF INTENT Bremo Power Station Submitted To: Bremo Power Station 1038 Bremo Bluff Road Bremo Bluff, VA 23022 Submitted By: Golder Associates
More informationINSTALLATION QUALITY-ASSURANCE GUIDE FOR SOLMAX-GSE S CONDUCTIVE LINER
INSTALLATION QUALITY-ASSURANCE GUIDE FOR SOLMAX-GSE S CONDUCTIVE LINER These instructions present some general guidelines for installing and surveying Solmax-GSE s smooth edged conductive backed geomembranes
More informationSection Specification for Geotextile Used in Permanent Erosion Control Application
Project Name: Project Number: 1 GENERAL Section 02370 Specification for Geotextile Used in Permanent Erosion Control Application 1.1 SECTION INCLUDES A. Geotextile to prevent soil loss resulting in excessive
More informationD.P.E. Enviroliner. geotextile protection layer. covering new ground 2016
LEVEL 7 osynthetic clay liner www.gundle.co.za H.D.P.E. Enviroliner geosynthetic clay liner geotextile protection layer D.P.E. Enviroliner solid waste sand (leachate collection) geotextile protection layer
More informationLeak Location Geosynthetic Materials in Base Liner Systems. NY Federation SWANA. May, 2014
Leak Location Geosynthetic Materials in Base Liner Systems NY Federation SWANA May, 2014 Different ELI Surveys A. Covered Electrical Liner Integrity (ELI) Survey Dipole Method Suitable for water or soil
More informationSECTION 02230BP AGGREGATE BASE
SECTION 02230BP AGGREGATE BASE This page is intentionally left blank. Fluor-B&W Portsmouth, LLC (FBP) SITE PREPARATION INFRASTRUCTURE PHASE 1 SPECIFICATION COVER SHEET Client: U.S. Department of Energy
More informationDrop-In Specifications INTEGRATED DRAINAGE SYSTEM GEOMEMBRANE
Drop-In Specifications INTEGRATED DRAINAGE SYSTEM GEOMEMBRANE The following specification is a sample guideline to be customized by the engineer for preparing site specific specification. This information
More informationI N D U S T R I A L Y A R D S
I N D U S T R I A L Y A R D S GEOTEXTILES INDUSTRIAL YARDS 1.0 Features of INDUSTRIAL PG 2 YARDS 2.0 How Typar geotextiles PG 2 work 4.0 Installation guide PG 7 5.0 Overlap and joining PG 8 6.0 Setting
More informationAlternative Cover Systems
Alternative Cover Systems RemTech 2017 October 13, 2017 Outline Capping solutions Why use alternate cover systems Exposed geomembrane cap systems Geosynthetic Turf cap systems What is it? How is it installed?
More informationSelecting the Right Closure Cap Option for Your Surface Impoundment or CCR Landfill
2017 World of Coal Ash (WOCA) Conference in Lexington, KY - May 9-11, 2017 http://www.flyash.info/ Selecting the Right Closure Cap Option for Your Surface Impoundment or CCR Landfill Steven C. Lamb 1,
More informationGEOMEMBRANE AND DRAINAGE INSTALLATION SPECIFICATION
GEOMEMBRANE AND DRAINAGE INSTALLATION SPECIFICATION The information provided in this manual uses current quality control and quality assurance standards within the geomembrane industry. It is the sole
More informationEROSION & SEDIMENT CONTROL
EROSION & SEDIMENT CONTROL 1 EROSION & SEDIMENT CONTROL Effective Soil & Water Protection Whether you want to prevent soil erosion caused by rain, water and wind, or protect waterways from inevitable build
More informationThe use of geosynthetics in the installation of ballast layers
The use of geosynthetics in the installation of ballast layers C. Cilliers, Jones & Wagener (Pty) Ltd, South Africa, cilliers@jaws.co.za ABSTRACT The ballast layer is an essential element of any landfill
More informationDRIVABLE GRASS GUIDELINE FOR PLANTED INFILL INSTALLATION
DRIVABLE GRASS GUIDELINE FOR PLANTED INFILL INSTALLATION Please read through this instruction completely before beginning your installation. Be sure the proper equipment, and safety precautions are in
More informationRolled Erosion Control Products (RECPs) General Usage and Installation Guidelines for Slope
March 2014 Version 1.0 Rolled Erosion Control Products (RECPs) General Usage and Installation Guidelines for Slope Erosion Control Technology Council IMPORTANT NOTICE on Safety Procedures: Manufacturer
More informationSECTION 900 TURF ESTABLISHMENT
SECTION 900 901.0 DESCRIPTION This section covers the furnishing of all labor, materials, tools, equipment and performances of all work and services necessary or incidental to turf restoration as indicated
More informationHYDRAULIC DESIGN involves several basic
Chapter 6 Tools for Hydr draulic and Road Design HYDRAULIC DESIGN involves several basic concepts that must be considered to build successful projects with a minimum risk of failure (Photo 6.1). Use of
More informationINSTALLATION GUIDELINES. Landfills and mines
INSTALLATION GUIDELINES Landfills and mines Introduction Recommendations This installation manual gives general recommendations for the installation of the drainage geocomposites InterDRAIN and TechDRAIN
More informationWe Don t Have No Stinkin Dirt! Coal Ash Pond Closures (Traditional and an Alternative Method)
2017 World of Coal Ash (WOCA) Conference in Lexington, KY - May 9-11, 2017 http://www.flyash.info/ We Don t Have No Stinkin Dirt! Coal Ash Pond Closures (Traditional and an Alternative Method) Rosanna
More informationSKAPS GEOTEXTILE SUBSURFACE DRAINAGE
SKAPS INDUSTRIES 335 Athena Drive, Athens, GA 30601 Ph: (706)-354-3700 Fax: (706)-354-3737 Email: contact@skaps.com DROP-IN SPECIFICATIONS SKAPS GEOTEXTILE SUBSURFACE DRAINAGE The following drop-in specification
More information3" TO 4" OF TOPSOIL 2:1 MIRAFI HP 565 GEO FABRIC OR EQUIVALENT 9' SPILLWAY EL=7147 2:1 SPILLWAY SECTION N.T.S. TOP OF POND EL=7149' RIP-RAP D 50 8" WRAPPED IN FILTER FABRIC 45 MIL HDPE POND LINER OR EQUIVALENT
More informationIII.DRAINAGE. This section describes the use of geotextiles in underdrains for two different field conditions:
III.DRAINAGE This section describes the use of geotextiles in underdrains for two different field conditions: Protected (or light duty installations) and, Unprotected (for heavy duty installations). Both
More informationUNIFIED FACILITIES GUIDE SPECIFICATION
USACE / NAVFAC / AFCESA / NASA UFGS-31 05 19 (August 2008) --------------------------- Preparing Activity: USACE Superseding UFGS-31 05 19 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATION References
More informationAlternative Names: Erosion Control Matting, Erosion Control Netting, Rolled Erosion Control Products (RECP)
4.5-s EROSION CONTROL BLANKET SYSTEM Alternative Names: Erosion Control Matting, Erosion Control Netting, Rolled Erosion Control Products (RECP) DESCRIPTION Erosion control blanket systems are woven or
More informationSECTION TABLE OF CONTENTS GEOTEXTILE TUBES PARAGRAPH TITLE PAGE NOS.
SECTION TABLE OF CONTENTS SITE WORK GEOTEXTILE TUBES PARAGRAPH TITLE PAGE NOS. PART 1 - GENERAL 1.1 SCOPE OF WORK................................ 1 1.2 REFERENCES.................................. 1 1.3
More informationCONSTRUCTION SPECIFICATION FOR RIP RAP, ROCK PROTECTION AND GRAVEL SHEETING
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 511 FEBRUARY 1990 CONSTRUCTION SPECIFICATION FOR RIP RAP, ROCK PROTECTION AND GRAVEL SHEETING 511.01 SCOPE 511.02 REFERENCES 511.03 DEFINITIONS 511.04
More informationAPPENDIX A POND LINING TECHNICAL SPECIFICATIONS
APPENDIX A POND LINING TECHNICAL SPECIFICATIONS City of Albany WTP-17-01, Backwash Ponds Improvements Project Seals Page For specification sections: 02227,02263,02676,02680 SEALS PAGE - 1of1 SECTION 02227
More informationEngineering Report: Appendix F Volume 3 Landfill Liner Construction Specifications COWLITZ COUNTY HEADQUARTERS LANDFILL PROJECT COWLITZ COUNTY, WASHIN
Engineering Report: Appendix F Volume 3 Landfill Liner Construction Specifications COWLITZ COUNTY HEADQUARTERS LANDFILL PROJECT COWLITZ COUNTY, WASHINGTON TECHNICAL SPECIFICATIONS GENERIC CELL CONSTRUCTION
More informationGEOWEB slope & shoreline protection OVERVIEW
SOIL STABILIZATION GEOWEB slope & shoreline protection OVERVIEW THE GEOWEB SYSTEM The Presto GEOWEB slope and shoreline protection system is an effective and economical solution to challenging slope-surface
More informationGuidelines for Installation of: Factory Fabricated Compounded 0.25 to 1.52 mm (10 to 60 mil) Thickness Unsupported Geomembranes
Factory Fabricated Compounded 0.25 to 1.52 mm (10 to 60 mil) Thickness Unsupported Geomembranes Factory Fabricated Compounded 0.25 to 1.52 mm (10 to 60 mil) Thickness Unsupported Geomembranes Prepared
More informationTe c h S p e c 3. Edge Restraints for Interlocking Concrete Pavements
Te c h S p e c 3 Edge Restraints for Interlocking Concrete Pavements Introduction Edge restraints are an essential component of interlocking concrete pavements. Restraints hold the pavers tightly together,
More informationTechnical Specification Guidelines
SECTION I- DESIGN CONSIDERATIONS PAGE 1.01 APPLICABILITY...I.2 1.02 PROTECTION AND PRECAUTIONS...I.3 1.03 SITE AND SUBSTRATE CONSIDERATIONS...I.3 1.04 PRODUCT CONSIDERATIONS...I.8 1.05 FASTENING CONSIDERATIONS...I.9
More informationInstallation Manual May 9/14 No revision
815 NE 172 nd Avenue Vancouver, WA 98684 877-694-0141 Installation Manual May 9/14 No revision Installation steps include job planning, layout, excavating and preparing the soil subgrade, applying geotextiles
More informationPondless Waterfall Vault
Pondless Waterfall Vault Installation Instructions & Owner s Manual Step-by-Step Installation Instructions for the Pondless Waterfall Vault Congratulations on the purchase of the AquascapePRO Pondless
More informationSECTION AMENDED TOPSOIL
SECTION 02486 AMENDED TOPSOIL PART 1 - GENERAL 1.01 SUMMARY A. Work described in this section includes requirements for soil amendments, soil preparation, preparation and finish grading of turf restoration
More informationINSTALLATION GUIDELINES. Mirafi FM Filter Geotextiles for Basal Filtration Applications
CONTENTS 1 General 2 Product and Application 3 Material Identification, Storage and Handling 4 Fabrication of Geotextile Fascine Mattress 5 Installation of Geotextile Fascine Mattress 6 Jointing 7 Rock
More informationBEFORE INSTALLATION BEGINS
Landlok 300 Turf Reinforcement Mat SLOPE INSTALLATION AND MAINTENANCE GUIDELINES Thank you for purchasing the Landlok 300 Turf Reinforcement Mat (TRM) by Propex Operating Company, LLC (Propex). This document
More informationCLAHS #11 RACR APPENDIX G. SCS Photographic Log, Photographs
CLAHS #11 RACR APPENDIX G SCS Photographic Log, Photographs PHOTO LOG A (1-50) NUMBER DESCRIPTION 1 West Central Footing Excavation Building Q. 2 60-Mil HDPE Membrane Installation Building Q. 3 60-Mil
More informationCHAPTER 8 SLOPE STABILITY ANALYSIS
TM 5-818-1 / AFM 88-3. Chap. 7 CHAPTER 8 SLOPE STABILITY ANALYSIS 8-1. General. This chapter is concerned with characteristics and critical aspects of the stability of excavation slopes; methods of designing
More informationPRESTO GEOTERRA GTO FAST DEPLOYMENT CONSTRUCTION MAT SYSTEM SPECIFICATION & INSTALLATION GUIDELINE
GEOTERRA GTO PRESTO GEOSYSTEMS 670 N Perkins Street, Appleton, Wisconsin, USA Ph: 920-738-1328; Fax: 920-738-1222 www.prestogeo.com GTO/001 1 Oct 2013 Table of Contents GEOTERRA GTO System... 1 GEOTERRA
More informationGeosynthetics. Work platforms built with geotextile tubes at the Lach Huyen Bridge. GMA TECHLINE Exposed GM? Deformations?
FEBRUARY/MARCH 2016 VOLUME 34 NUMBER 1 SUBSCRIBE AT GeosyntheticsMagazine.com GMA TECHLINE Exposed GM? Deformations? For landfill drainage layer GIROUD & HAN Geosynthetics and unpaved roads Geosynthetics
More informationUNIFIED FACILITIES GUIDE SPECIFICATION
USACE / NAVFAC / AFCEC / NASA UFGS-31 05 19 (August 2008) --------------------------- Preparing Activity: USACE Superseding UFGS-31 05 19 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATION References
More informationINSTALLATION OF GEOTEXTILE TUBES USED FOR COASTAL AND RIVERINE STRUCTURES GLOBAL SYNTHETICS PROTUBE GEOTEXTILE TUBE
INSTALLATION OF GEOTEXTILE TUBES USED FOR COASTAL AND RIVERINE STRUCTURES GLOBAL SYNTHETICS PROTUBE GEOTEXTILE TUBE 1. SCOPE This practice provides guidelines for the installation of PROTUBE geotextile
More informationSECTION TURF AND GRASSES
SECTION 32 92 00 TURF AND GRASSES PART 1: GENERAL 1.01 DESCRIPTION Restore all disturbed grass and landscaped areas to conditions equal to or better than before the work began and to the satisfaction of
More informationSWANA/A&WMA s. Third Annual Landfill Operator s Training Geosynthetics in Landfills. February 13, 2013
SWANA/A&WMA s Third Annual Landfill Operator s Training Geosynthetics in Landfills February 13, 2013 Geosynthetics Products Applications Current Lining Requirements Tips 2 Geosynthetics polymeric products
More informationSocket Heat Fusion Techniques. A Guide for Instruction and Training in Vanguard Socket Heat Fusion
Socket Heat Fusion Techniques A Guide for Instruction and Training in Vanguard Socket Heat Fusion TABLE OF CONTENTS This brochure has been developed to assist those responsible for socket fusion joining
More informationBEFORE INSTALLATION BEGINS
ArmorMax Anchored Reinforced Vegetation System FOR SLOPE EROSION CONTROL INSTALLATION AND MAINTENANCE GUIDELINES Thank you for purchasing the ArmorMax Anchor Reinforced Vegetation System by Propex Operating
More information511 - RIP RAP - OPSS 511 ROCK PROTECTION - OPSS 511 GRAVEL SHEETING - OPSS 511 GEOTEXTILE - OPSS 511
511 - - OPSS 511 ROCK PROTECTION - OPSS 511 GRAVEL SHEETING - OPSS 511 GEOTEXTILE - OPSS 511 511.1 GENERAL 511.1.1 Rip Rap 511.1.2 Rock Protection Excavation for placing Rip Rap, Rock Protection and Gravel
More informationLow Gradient Velocity Control Short Term Steep Gradient [1] Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent
Grass Linings DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient [1] Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] May be used on short, steep
More informationStormwater protection
70 70 Visqueen High Performance Urban Drainage Geomembrane 70 Visqueen GX Geomembrane UDG 73 Hanson Aquaflow SC Membrane Stormwater protection A fully integrated stormwater management system provides relief
More informationPaving - 8 easy steps for DIY and professional landscapers
Pavers Victoria Paving - 8 easy steps for DIY and professional landscapers 18 Before you begin... These general instructions will allow an average home handyperson to design, plan and construct a path,
More informationSILT FENCE MACHINE SLICED ERO-1A STEEL FENCE POST (T-POST), MINIMUM 5' LONG, 6' MAXIMUM SPACING.
STEEL FENCE POST (T-POST), MINIMUM 5' LONG, 6' MAXIMUM SPACING. ATTACH FABRIC TO POSTS WITH MINIMUM 3 ZIP TIES (50 LB. TENSILE) PER POST IN TOP 8" OF FABRIC. MONOFILAMENT GEOTEXTILE FABRIC PER MNDOT TABLE
More informationYEAR 20 - SEPTEMBER SPECIAL EDITION INDEPENDENT JOURNAL FOR THE GEOART SECTOR
YEAR 20 - SEPTEMBER 2016 - SPECIAL EDITION INDEPENDENT JOURNAL FOR THE GEOART SECTOR 6 th EuroGeo Conference 25-28 September 2016 Ljubljana - Slovenia Geomembrane systems in The Netherlands and abroad
More information1. Vinyl wall covering. 2. Woven glass-fiber wall covering. 3. Textile wall covering. 4. Wallpaper. 5. Heavy-duty, synthetic, textile wall covering.
SECTION 09950 - WALL COVERINGS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections,
More informationAir-channel testing landfill geomembrane seams
Air-channel testing landfill geomembrane seams Results from a recent workshop help minimize destructive testing By Timothy D. Stark, John Heap, Stuart Lange, Dave McLaury and Stanford Slifer Thermal welding
More informationSHOREMAX FLEXIBLE TRANSITION MAT INSTALLATION GUIDE
SHOREMAX FLEXIBLE TRANSITION MAT INSTALLATION GUIDE Introduction to the Transition Mat FEATURES OF SHOREMAX TRANSITION MAT The North American Green RevetMax System Transition Mat is designed for protection
More informationGEOMEMBRANE INSTALLATION GUIDELINES AND SPECIFICATIONS FOR LLDPE 20, 30, AND 40 MIL UNREINFORCED & GEO-SKRIM SERIES REINFORCED LINERS.
GEOMEMBRANE INSTALLATION GUIDELINES AND SPECIFICATIONS FOR LLDPE 20, 30, AND 40 MIL UNREINFORCED & GEO-SKRIM SERIES REINFORCED LINERS. TABLE OF CONTENTS SECTION PAGE 1.0 SUBGRADE PREPARATION 3 2.0 PANEL
More informationGeotextile Separation Interlayer Guide Specification
Geotextile Separation Interlayer Guide Specification Version 1.5 October 2, 2018 Geotextile technology has become an engineering option for use in concrete pavement as a cost-effective replacement for
More informationSouth Fraser Perimeter Road (SFPR)
MSE WALLS & SLOPES PROJECT PROFILE South Fraser Perimeter Road (SFPR) Nilex provides multiple solutions for the new four-lane highway along Vancouver s Fraser River. LOCATION: Delta and Surrey, British
More informationBoise Municipal Code. Chapter 9-04 EXCAVATIONS
Chapter 9-04 EXCAVATIONS Sections: 9-04-01 DECLARATION OF POLICY AND PURPOSE 9-04-02 PERMIT REQUIRED 9-04-03 APPLICATIONS 9-04-04 BOND 9-04-05 SUPERVISION AND RESPONSIBILITY 9-04-06 GENERAL SPECIFICATIONS
More informationA Collection and Removal System for Water in the Final Cover Drainage Layer
Landfills A Collection and Removal System for Water in the Final Cover Drainage Layer A rainwater toe drainage system, by removing water from the final cover drainage layer, eliminates the possibility
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-02 56 13 (February 2010) ----------------------------- Preparing Activity: USACE Superseding UGGS-02 56 13 (October 2007) UNIFIED FACILITIES GUIDE SPECIFICATIONS References
More informationA. Contractor shall provide product data for each type of product indicated.
31 13 00 SELECTIVE TREE AND SHRUB REMOVAL AND TRIMMING SECTION 1 GENERAL 1.1 SUMMARY A. This section includes general protection and pruning of existing trees and plants that are affected by execution
More informationSECTION EARTHWORK
SECTION 02200 - EARTHWORK PART 1 GENERAL 1.1 SECTION INCLUDES A. Grading and Excavation B. Trenching C. Bedding D. Backfill and Compaction (New and Native) E. Aggregate Material F. Geotextile Fabric PART
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-33 56 19 (May 2015) -------------------------- Preparing Activity: USACE Superseding UFGS-33 56 63 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS References are
More informationA. Install all temporary erosion control measures (in accordance with MNDOT General Conditions 2573) prior to site disturbance.
The language provided in these specifications is meant to serve as a reminder and provide a generic example of the type of language that should be provided in final construction documents. This language
More informationMETROPOLITAN Construction Standard No: UTILITIES DISTRICT
Page: 1 of 8 A. GENERAL * The Plastic Pipe Institute (PPI) developed standardized butt-fusion procedures which are labeled by the industry as Generic Butt-Fusion Procedures. These procedures have been
More informationfield note Culvert foundation improvement design concepts The challenge of low-cost culvert foundations
field note Culvert improvement design concepts Mark Partington, R.P.F., M.Sc., EP 1 Papa Masseck Thiam, Ing. Jr., M.Sc. 2 Introduction Canada s northern forested landscapes feature numerous wetlands, such
More informationQualification Procedures for making PE 3408 Extra High Molecular Weight Polyethylene Heat Fusion Joints
Qualification Procedures for making PE 3408 Extra High Molecular Weight YELLOWSTRIPE@ Polyethylene Heat Fusion Joints. BULLETIN NO.106 . Fusion Butt Photographs Fusion Joints. of Qualification Procedures.
More informationGeosynthetics for the Management, Containment and Closure of Coal Combustion Residual Disposal Facilities
2013 World of Coal Ash (WOCA) Conference - April 22-25, 2013 in Lexington, KY http://www.flyash.info/ Geosynthetics for the Management, Containment and Closure of Coal Combustion Residual Disposal Facilities
More informationSilva Cell 2 Installation Guidelines
Silva Cell 2 Installation Guidelines Silva Cell 2 components Deck 1X post 3X post 2X post Base 1 Base (bottom piece) 2 Posts 1X 2X 3X (1x + 2X) 3 1X assembled 16.7 (424 mm) 4 2X assembled 30.9 (784 mm)
More information.4 Do complete installation in accordance with latest Electrical Bulletins of the local inspection authority.
Fitness Facility Addition Page 1 1.1 CODES AND STANDARDS.1 Do complete installation in accordance with the latest edition of the CSA C22.1 as amended by the latest editions of the National Building Code
More informationRevETMax TM INSTALLATION GUIDE
RevETMax TM FLexIBLE TraNSITION MAT INSTALLATION GUIDE Introduction to Mats RevetMax Mats are an integrated erosion and sediment control system designed for protection of high scour and high velocity applications.
More informationREQUIREMENTS FOR LANDS TO BE CONVEYED TO THE CITY. The Owner will be responsible to ensure that all lands which will be transferred to the City for
APPROVED BY COUNCIL FEBRUARY 15, 1994 CITY OF BE CONVEYED TO THE CITY The Owner will be responsible to ensure that all lands which will be transferred to the City for parkland, drainage or boulevard purposes
More informationGRI White Paper #8. - on - Construction Quality Assurance-Inspectors Certification Program (CQA-ICP)
Geosynthetic Certification Institute 475 Kedron Avenue Folsom, PA 19033-1208 USA TEL (610) 522-8440 FAX (610) 522-8441 GEI GRI GSI GAI GCI GII GRI White Paper #8 - on - Construction Quality Assurance-Inspectors
More informationPozidrain. A guide to the selection and specification of Pozidrain drainage geocomposite
Pozidrain A guide to the selection and specification of Pozidrain drainage geocomposite Pozidrain Pozidrain is the original wide width drainage and gas venting layer and offers a sustainable, environmentally
More informationTurfgrass Sod General
8 8.1. General 8.1.1. Purpose statement & intent 1. The intent of this section of the standard is to state standard requirements for quality grades and other classifications of grass types in turfgrass
More informationAASHTO M Subsurface Drainage
Subsurface Drainage Description: This specification is applicable to placing a geotextile against the soil to allow long-term passage of water into a subsurface drain system retaining the in -situ soil.
More informationAquaculture Lining Systems
Aquaculture Lining Systems The world relies on Infabsol Geomembranes Industrial Fabric Solutions Geomembranes Improve Your Profit Margins Ponds and tanks used for fish and shrimp farming can be greatly
More informationNondestructive Testing of Geomembranes
From NDT Technician, Vol. 11, No. 2, pp: 1 5. Copyright 2012 The American Society for Nondestructive Testing, Inc. The American Society for Nondestructive Testing www.asnt.org FOCUS Nondestructive Testing
More informationModel ESFR-17 Dry Type Pendent Sprinklers Early Suppression Fast Response 16.8 K-factor General Description
Technical Services 800-381-9312 +1-401-781-8220 www.tyco-fire.com Model ESFR-17 Dry Type Pendent Sprinklers Early Suppression Fast Response 16.8 K-factor General Description The TYCO Model ESFR-17 Dry
More informationButyl Products Ltd. Pond Guide
Butyl Products Ltd. Pond Guide Page 2 BUTYL PRODUCTS LIMITED For beautiful garden pools.. Butyl Products Pond Liner division has been manufacturing Butyl pond liners for over 35 years, and is the longest
More informationExposed Geomembrane Cover Systems for Coal Ash Facilities
2017 World of Coal Ash (WOCA) Conference in Lexington, KY - May 9-11, 2017 http://www.flyash.info/ Exposed Geomembrane Cover Systems for Coal Ash Facilities Clay Reichert, P.E. GSE Environmental, LLC,
More information815 NE 172 nd Avenue Vancouver, WA Installation Manual
815 NE 172 nd Avenue Vancouver, WA 98684 800-377-3877 www.xeripave.com info@xeripave.com Installation Manual Installation steps include job planning, layout, excavating and preparing the soil sub grade,
More informationCapping waste rock at a Superfund site An innovative design tackles pollution at a mining operation s waste repository.
Capping waste rock at a Superfund site An innovative design tackles pollution at a mining operation s waste repository. The Gilt Edge mine is located in the northern Black Hills of South Dakota on private
More information