1 2016 NFPA Conference & Expo Rooftop Photovoltaic (PV) Systems Examining the Risks and Researching the Options Presented by: Joel Sipe Senior Managing Engineer Exponent Inc.

2 Outline Project Background Fire Incidents Fire Testing of Roofs and PV Modules Proposed Test Plan Mitigation Solutions to be Tested

3 Introduction Typical Rooftop PV Arrays Images from - (left) (right)

4 Introduction PV installations have recently become much more prevalent in the US due largely to reduced installation cost. Reduced installation cost is driven by many factors, including: Lower manufacturing cost. Federal and state government incentives. More efficient installation practices. Rapid expansion of use has created some technical and fire service challenges. Building codes and fire service tactics are evolving.

5 Introduction Current project is developing a test plan to evaluate mitigation solutions for fires involving rooftop PV arrays. Project is funded by the NFPA Fire Protection Research Foundation (FPRF). Guidance is provided by a technical panel with members from relevant industry sectors and the NFPA Property Insurance Research Group (PIRG).

6 Introduction Dietz and Watson fire, Delanco NJ, September Images from

7 The Challenge of Rooftop Fires & PV Arrays PV arrays add fuel and potential ignition sources to roofs. Fires that develop are outside the reach of the building fire detection and suppression systems. Presence of PV modules affects fire dynamics and can lead to fast growing fires. FDs cautious about going onto roofs with PV array fires. PROJECT GOAL: Mitigate flame spread to give FD more time to implement extinguishment plan.

8 PV Array Components Cells produce ~ 0.5V Modules produce ~25-50V National Electrical Code (NEC) limits system voltage - 600V for residential V or greater for commercial

9 Potential PV Failure Modes Cables Cells Junction Boxes Inverters Heating at cable connections Ground faults Poor bus bar contact to cells Cell cracking or thin metal cells leading to resistive heating Arcing or resistive heating at mechanical or solder contacts Diode failures Electronic component failure or shorting Trace melting leading to arc flash

10 Outline Project Background Fire Incidents Fire Testing of Roofs and PV Modules Proposed Test Plan Mitigation Solutions to be Tested

11 Fires Associated with PV Arrays April 2009: Bakersfield, CA Fire at a Target big-box retail store 383 kw array on roof, 166 strings of 11 modules, 1826 modules Fire reportedly started in 2 locations Fire cause reportedly ground fault related April 2011: Mount Holly, NC Fire at National Gypsum Co., a drywall manufacturing facility Fire cause reportedly ground fault related

12 Fires Associated with PV Arrays May 2013: LaFarge, WI Green building with metal roof Roof reportedly became energized and inhibited suppression activity

13 Fires Associated with PV Arrays September 2013: Delanco, NJ (shown) Dietz and Watson warehouse Building was ~300k sq ft Over 7,000 solar modules on roof PV system reportedly inhibited fire suppression activity November 2013: Florence Twp, NJ Fire at a 700k sq ft Christmas goods warehouse Over 8,000 modules on roof, 300 modules involved in the fire

14 Outline Project Background Fire Incidents Fire Testing of Roofs and PV Modules Proposed Test Plan Mitigation Solutions to be Tested

15 Fire Testing of Roofs and Modules Roofs Tested per ASTM E108 - Class A, B, or C rating PV Modules Tested per UL Class A, B, or C rating Pre-2013 Tested without roof Post-2013 Tested as a system (module, roof, rack)

16 ASTM E108 Four fire tests: Intermittent flame exposure Spread of flame Burning brands Flying brands Roof assembly is given a Class A, B, or C rating

17 ASTM E108 - Spread of Flame Test Wind Roof Burner Wind

18 ASTM E108 Spread of Flame Gas burner 2-inch OD steel pipe with ½-inch by 36-inch slot Fire size Class A & B ~22,000 BTU/min (~387 kw) Class C ~19,000 BTU/min (~334 kw) Air flow 12 ± 0.5 mph (5.3 ± 0.2 m/s)

19 UL 1703 Pre-2013 Two fire tests: Spread of flame Burning brand Module is given a Class A, B, or C rating

20 UL and later Five fire tests: Spread of flame on top surface of module Burning brand on surface of module over steep sloped roof Spread of flame between module and steep sloped roof Spread of flame between module and low sloped roof Burning brand between module and steep sloped roof Module is given a Class A, B, or C rating

21 Development of UL Fire testing performed with PV modules on sloped roofs: Zero setback 5-inch standoff height (worst case scenario) Roof Rating PV Module Rating Flame Spread A C > 8 ft A A > 8 ft C C > 8 ft Non-combustible C > 8 ft Non-combustible A > 8 ft

22 Development of UL Mitigation solutions were tested at UL: Vertical flashing With gap Not successful Without gap - Successful Fire barriers Some success Setback Not successful Screens Not successful

23 Gaps in Available Test Data/Knowledge Large-scale roof array fire tests. Mitigation solutions: Walkways as a mitigation solution? Thermal barriers over roof insulation? Other mitigation solutions?

24 Outline Project Background Fire Incidents Fire Testing of Roofs and PV Modules Proposed Test Plan Mitigation Solutions to be Tested

25 Test Plan General parameters: Test array Ignition source Air flow Roof assemblies to be tested. Mitigation solutions to be tested.

26 Test Array 4 x 5 test array 1 x 5 and 4 x 1 target arrays Standoff height ~5

27 Test Array Three module orientations: Flat All facing same direction East-west tented Images from and Grant, C. Fire Fighter Safety and Emergency Response for Solar Power Systems, Fire Protection Research Foundation Report, October 2013, p. 16.

28 Ignition Source Options considered: Gas burner Class A burning brand Standard ignitors (plastic bag, gauze, flammable liquid) Light combustibles Decided to use a 4-foot long gas burner: Reliable and repeatable Easily set and controlled

29 Air Flow Air flow will be provided by a bank of fans. Velocity will be 12 mph (5.3 m/s). Air speed will be checked with a velocity probe at the leading edge of the array.

30 Roof Assemblies Test roofs are typical of common roof assemblies: Membrane Thermoplastic olefin (TPO) Ethylene propylene diene monomer (EPDM) Polyvinyl chloride (PVC) Polyisocyanurate insulation Steel deck Roof assembly will measure 40 feet by 30 feet Image from

31 Test Geometry

32 Outline Project Background Fire Incidents Fire Testing of Roofs and PV Modules Proposed Test Plan Mitigation Solutions to be Tested

33 Mitigation Solutions to be Tested Primary Walkways (with and without cover) Vertical barriers Non-combustible cover board on top of insulation Other possible solutions Gravel ballast on membrane Non-combustible PV module backing layer Increased standoff height

34 Test Matrix Test # Membrane Type Orientation Mitigation Solution 1 EPDM Flat None (baseline) 2 TPO Flat None (baseline) 3 PVC Flat None (baseline) 4 Worst case from 1-3 Angled None (baseline) 5 Worst case from 1-3 Tented None (baseline) 6 Worst case from 1-3 Worst case from 1-5 Walkway Cover 7 Worst case from 1-3 Worst case from 1-5 NC cover board 8 Worst case from 1-3 Worst case from 1-5 Vertical barriers 9+ Worst case from 1-3 Worst case from 1-5 TBD

35 Baseline Test Geometry

36 Test 6 Effect of Walkway Cover Walkways covered with paver blocks

37 Test 7 Non-Combustible Cover Board NC cover board under membrane across entire roof

38 Test 8 Vertical Barriers

39 Test 9+ - Potential Further Testing Repeat primary solution tests? Gravel ballast? Non-combustible backing layer? Increased standoff height?

40 Next Steps Finalize test plan Testing will be conducted in a later phase of the project

41 Thank You

42 2016 NFPA Conference & Expo CEUs: To receive CEUs for this session, scan your badge at the back of the room before leaving. Evaluation: Complete a session evaluation on the mobile app. (Search app store for NFPA 2016 C&E. ) Handouts: Handouts will be available via the mobile app and at nfpa.org/conference. Recordings: For information on audio recordings of Educational Sessions, visit nfpa.org/xchange.

Artificial Trees and Fire Performance

Artificial Trees and Fire Performance 2017 NFPA Conference & Expo Artificial Trees and Fire Performance Presented by: Dwayne Sloan Manager, Principal Engineers Building Materials & Suppression UL LLC Learning Objectives Frame the Fire Problem

More information

Roof Coatings Manufacturers Association October 18, 2012

Roof Coatings Manufacturers Association October 18, 2012 Roof Coatings Manufacturers Association October 18, 2012 Examples of Addressing New Fire Challenges & Risks With Science Bob Backstrom Kevin Faltin UL and the UL logo are trademarks of UL LLC 2012 New

More information

Dust Hazard Assessments

Dust Hazard Assessments 2017 NFPA Conference & Expo Dust Hazard Assessments The Importance of DHAs in Establishing Work Practices and Facilities Presented by: Jason Reason, CIH, CSP, CHMM Lewellyn Technology, LLC Learning Objectives

More information

Fire Dynamics Research Applied to. Fire Investigation. Overview

Fire Dynamics Research Applied to. Fire Investigation. Overview 2017 NFPA Conference & Expo Fire Dynamics Research Applied to Fire Investigations Presented by: Daniel Madrzykowski Research Engineer UL Firefighter Safety Research Institute Fire Investigation What is

More information

The Situation. Modeling Storage Occupancies Under Sloped Ceilings. Concerns (Elevation View) The Concerns 4/29/ NFPA Conference & Expo

The Situation. Modeling Storage Occupancies Under Sloped Ceilings. Concerns (Elevation View) The Concerns 4/29/ NFPA Conference & Expo 2014 NFPA Conference & Expo Modeling Storage Occupancies Under Sloped Ceilings Presented by: Kenneth E. Isman NFSA Victoria B. Valentine NFSA Andre Marshal CSS NFPA 13 defines a sloped ceiling as one where

More information

Effect of Rack Mounted Photovoltaic Modules on the Fire Classification Rating of Roofing Assemblies

Effect of Rack Mounted Photovoltaic Modules on the Fire Classification Rating of Roofing Assemblies Effect of Rack Mounted Photovoltaic Modules on the Fire Classification Rating of Roofing Assemblies Project Number: 08CA39594, 09CA40917 File Number: IN15911, R26475 Date: September 30, 2009 Revised February

More information

Large Airports Maintaining Fire Safety through the years

Large Airports Maintaining Fire Safety through the years 2017 NFPA Conference & Expo through the years Presented by: Panos Samaras Fire Safety Officer Athens International Airport Greece 1 Main Points Part 1 Identify Regulatory Environment Recent Fires in Airports

More information

Fire Risks and Safety Standards

Fire Risks and Safety Standards Fire Risks and Safety Standards Florian Reil TÜV Rheinland Group Renewable Energies 51105 Cologne, Germany Phone: + 49 221 806 27 94 Email: Florian.Reil@de.tuv.com Workshop BIPV The Increasing Role of

More information

Welcome DISCLAIMER. Testing Electric Fire Pumps You Need to Understand the Arc Flash Hazard 5/1/ NFPA Conference & Expo

Welcome DISCLAIMER. Testing Electric Fire Pumps You Need to Understand the Arc Flash Hazard 5/1/ NFPA Conference & Expo 2017 NFPA Conference & Expo Testing Electric Fire Pumps You Need to Understand the Arc Flash Hazard Presented by: Tracey D. Bellamy, PE, CFPS Chief Engineering Officer Telgian Corporation Welcome Instructor

More information

RISKTOPICS. Photovoltaic systems

RISKTOPICS. Photovoltaic systems RISKTOPICS Photovoltaic systems May May 2014 2014 INTRODUCTION Photovoltaic systems installed on or integrated into buildings components introduce a variety of potential challenges and risks. The challenges

More information

2014 NFPA Conference & Expo

2014 NFPA Conference & Expo 2014 NFPA Conference & Expo NFPA Wildland Standards Development: Where We ve Been and Where We re Going Presented by: Ryan Depew NFPA Emergency Services Spc. OVERVIEW NFPA Technical Committees NFPA Wildland

More information

Changes to NFPA 101A 2013 Edition for Health Care Facilities

Changes to NFPA 101A 2013 Edition for Health Care Facilities 2017 NFPA Conference & Expo Changes to NFPA 101A 2013 Edition for Health Care Facilities Presented by: William Koffel, P.E, FSFPE Lennon Peake, P.E. Koffel Associates Koffel Associates President Manager

More information

Foundations of Real Estate Management Module 4: Building Operations II

Foundations of Real Estate Management Module 4: Building Operations II Foundations of Real Estate Management Session 1: Fire Alarm and Fire Sprinkler Systems (75 minutes) Describe the purpose of the fire alarm system and the fire sprinkler system. List the parts and explain

More information

Protecting Special Industrial Hazards with NFPA Codes & Standards

Protecting Special Industrial Hazards with NFPA Codes & Standards 2017 NFPA Conference & Expo Protecting Special Industrial Hazards with NFPA Codes & Standards Different Facilities & Similar Risks Presented by: Bruce H. Clarke, CFPS, UL- CRP Head of Global Property Engineering

More information

Health Care Facility Rehabilitation

Health Care Facility Rehabilitation 2017 NFPA Conference & Expo Health Care Facility Rehabilitation Effective Application of NFPA 101 2012, Life Safety Code Chapter 43 Building Rehabilitation Ron Coté, P.E. NFPA Health Care Facility Rehabilitation

More information

Ground Fault Protection Improvements to Prevent Fires Description of problem and potential solutions Presented by Bill Brooks, PE Principal, Brooks

Ground Fault Protection Improvements to Prevent Fires Description of problem and potential solutions Presented by Bill Brooks, PE Principal, Brooks Ground Fault Protection Improvements to Prevent Fires Description of problem and potential solutions Presented by Bill Brooks, PE Principal, Brooks Engineering Code Official Panel Lead, SolarABCs 1 Ground-Fault

More information

Protection of Rack Stored Exposed Expanded Group A Plastics with ESFR Sprinklers and Vertical Barriers

Protection of Rack Stored Exposed Expanded Group A Plastics with ESFR Sprinklers and Vertical Barriers Protection of Rack Stored Exposed Expanded Group A Plastics with ESFR Sprinklers and Vertical Barriers Suppression, Detection and Signaling Research and Applications Conference SupDet 2015 March 5, 2015

More information

Antifreeze Solutions and Automatic Fire Sprinkler Systems. March 12, 2013

Antifreeze Solutions and Automatic Fire Sprinkler Systems. March 12, 2013 Antifreeze Solutions and Automatic Fire Sprinkler Systems March 12, 2013 Session Outline History of Antifreeze in the standards Science of Antifreeze Incidents involving i antifreeze in sprinklers Initial

More information

Materials Testing by Gregory Havel

Materials Testing by Gregory Havel Materials Testing by Gregory Havel July 24, 2017 One of the most common tests cited in the technical bulletins on building materials is ASTM E84 Standard Method of Test of Surface Burning Characteristics

More information

Technical Expert to develop grid connection guidelines and standards for the Kingdom of Bahrain

Technical Expert to develop grid connection guidelines and standards for the Kingdom of Bahrain Technical Expert to develop grid connection guidelines and standards for the Kingdom of Bahrain Fire Safety Recommendations for Distributed Solar PV Systems Draft 1.0 July 2017 www.ewa.bh Table of contents

More information

Up on the Roof Fire Prevention BY David Laks, P. Eng., CFPS, ARM, RRC

Up on the Roof Fire Prevention BY David Laks, P. Eng., CFPS, ARM, RRC Up on the Roof Fire Prevention BY David Laks, P. Eng., CFPS, ARM, RRC Every year there are a significant number of roof fires resulting from installation, neglected maintenance, or housekeeping. This article

More information

PERFORMANCE TEST REPORT. Rendered to: Metal Building Manufacturers Association Cleveland, Ohio

PERFORMANCE TEST REPORT. Rendered to: Metal Building Manufacturers Association Cleveland, Ohio PERFORMANCE TEST REPORT Report No.: F6398.01-121-24 Test Date: March 9 th & 10th, 2016 Rendered to: Metal Building Manufacturers Association Cleveland, Ohio ASSEMBLIES: Metal Roof Panels and Clay Roof

More information

Developing a Fire Test Strategy for Storage Protection Under Sloped Ceilings

Developing a Fire Test Strategy for Storage Protection Under Sloped Ceilings Developing a Fire Test Strategy for Storage Protection Under Sloped Ceilings Justin A. Geiman, Noah L. Ryder Fire & Risk Alliance, Rockville, MD, USA André W. Marshall Custom Spray Solutions, Silver Spring,

More information

Figure 1. Structure Used For the Simulations.

Figure 1. Structure Used For the Simulations. OVERVIEW: Vent, Enter, Search (VES) is one of the most talked about tactics in the fire service today. When used correctly, its positive impact can be measured by the lives it saves. The VES method is

More information

Koffel Associates, Inc.

Koffel Associates, Inc. NFPA 25: STANDARD FOR THE INSPECTION, TESTING, AND MAINTENANCE OF WATER BASED FIRE PROTECTION SYSTEMS William E. Koffel, P.E., FSFPE President Koffel Associates, Inc. www.koffel.com wkoffel@koffel.com

More information

Labeling to Article 690 of the National Electrical Code Routing and Protecting PV Cables

Labeling to Article 690 of the National Electrical Code Routing and Protecting PV Cables Labeling to Article 690 of the National Electrical Code Routing and Protecting PV Cables Article 690 labeling requirements from the NEC 2011 Edition General overview of industry labeling Labeling updates

More information

Effective Messaging on School Door Locking

Effective Messaging on School Door Locking 2017 NFPA Conference & Expo Effective Messaging on School Door Locking Ron Coté, P.E. NFPA At the conclusion of this program participants will be able to: 1. Understand the conflicting needs of security

More information

AGENDA INTRODUCTION CELLS AND COMPONENTS PV PERFORMANCE PV APPLICATIONS CODES AND STANDARDS EMERGENCY RESPONSE

AGENDA INTRODUCTION CELLS AND COMPONENTS PV PERFORMANCE PV APPLICATIONS CODES AND STANDARDS EMERGENCY RESPONSE AGENDA INTRODUCTION CELLS AND COMPONENTS PV PERFORMANCE PV APPLICATIONS CODES AND STANDARDS EMERGENCY RESPONSE We are here to make a choice between the quick and the dead Bernard Baruch, U.N. Atomic Energy

More information

Shalaby Institute of Fire Protection Heyrothsberge, Germany.

Shalaby Institute of Fire Protection Heyrothsberge, Germany. International Water Mist Conference November 3-4, 2010, Prague, Czech Republic The Influence of Droplet Size of Water Mist on Extinguishment Fire Plume Dr.Hemdan Shalaby Institute of Fire Protection Heyrothsberge,

More information

Obstructions and ESFR Sprinklers Phase 2 FINAL REPORT

Obstructions and ESFR Sprinklers Phase 2 FINAL REPORT Obstructions and ESFR Sprinklers Phase 2 FINAL REPORT PREPARED BY: Garner A. Palenske, P.E., and William N. Fletcher, P.E. Aon Fire Protection Engineering San Diego, CA, USA September 2015 Fire Protection

More information

PRODUCT PERFORMANCE TEST REPORT. Report No.: D Test Date: May 29, Rendered to: Natural Light Energy Systems Phoenix, Arizona

PRODUCT PERFORMANCE TEST REPORT. Report No.: D Test Date: May 29, Rendered to: Natural Light Energy Systems Phoenix, Arizona Architectural Testing PRODUCT PERFORMANCE TEST REPORT Report No.: D7226.01-121-24 Test Date: May 29, 2014 Rendered to: Natural Light Energy Systems Phoenix, Arizona PRODUCT TYPE: Tubular Daylight Device

More information

Adrian Milford Sereca - a Jensen Hughes Company, Project Engineer Vancouver, BC, Canada

Adrian Milford Sereca - a Jensen Hughes Company, Project Engineer Vancouver, BC, Canada Transit Vehicle Design Standards and Risk Analysis on Fire Development in Rapid Transit Vehicles Adrian Milford Sereca - a Jensen Hughes Company, Project Engineer Vancouver, BC, Canada Motivation Design

More information

Energy Storage Systems Fire Safety Considerations. Howard Hopper, FPE Regulatory Services Program Manager

Energy Storage Systems Fire Safety Considerations. Howard Hopper, FPE Regulatory Services Program Manager Energy Storage Systems Fire Safety Considerations Howard Hopper, FPE Regulatory Services Program Manager Why Energy Storage? Recently, enormous focus has been placed on expanding the energy storage infrastructure.

More information

Parts Catalog Edition v1.85. This catalog includes parts and accessories for IronRidge s Mounting Systems.

Parts Catalog Edition v1.85. This catalog includes parts and accessories for IronRidge s Mounting Systems. Parts Catalog 2016 Edition v1.85 This catalog includes parts and accessories for IronRidge s Mounting Systems. Table of Contents We ve been designing and manufacturing solar mounting products since 1996.

More information

Copyright 2018 American Wood Council 1

Copyright 2018 American Wood Council 1 Fire Tests in Support of Tall Mass Timber Buildings DES603 Sam Francis Senior Director, National Programs American Wood Council Jason Smart, P.E. Manager, Engineering Technology American Wood Council The

More information

Parts Catalog. Version This catalog includes components for IronRidge s solar mounting systems.

Parts Catalog. Version This catalog includes components for IronRidge s solar mounting systems. Parts Catalog Version 1.90 This catalog includes components for IronRidge s solar mounting systems. Table of Contents We ve been designing and manufacturing solar mounting products since 1996. Our products

More information

Parts Catalog. Version This catalog includes components for IronRidge s solar mounting systems.

Parts Catalog. Version This catalog includes components for IronRidge s solar mounting systems. Parts Catalog Version 1.93 This catalog includes components for IronRidge s solar mounting systems. Table of Contents We ve been designing and manufacturing solar mounting products since 1996. Our products

More information

REPORT NUMBER: MID-003r1 ORIGINAL ISSUE DATE: March 11, 2015 Revised Date: March 20, 2015

REPORT NUMBER: MID-003r1 ORIGINAL ISSUE DATE: March 11, 2015 Revised Date: March 20, 2015 REPORT NUMBER: 101960325MID-003r1 ORIGINAL ISSUE DATE: March 11, 2015 Revised Date: March 20, 2015 EVALUATION CENTER Intertek Testing Services NA Inc. 8431 Murphy Drive Middleton, WI 53562 TEST REPORT

More information

Yunyong P. Utiskul, Ph.D., P.E., CFEI

Yunyong P. Utiskul, Ph.D., P.E., CFEI Yunyong P. Utiskul, Ph.D., P.E., CFEI Managing Engineer Thermal Sciences 17000 Science Drive, Suite 200 Bowie, MD 20715 (301) 291-2544 tel yutiskul@exponent.com Professional Profile Dr. Utiskul applies

More information

Report on the Fire Testing of a Roofing System with a Synthetic Underlayment in Accordance with ASTM E a. Trinity ERD Columbia, SC

Report on the Fire Testing of a Roofing System with a Synthetic Underlayment in Accordance with ASTM E a. Trinity ERD Columbia, SC Report on the Fire Testing of a Roofing System with a Synthetic Underlayment in Accordance with ASTM E 108-07a Rendered to: Trinity ERD Columbia, SC WFCi Project # 10135 & 11159 Testing Completed on: April

More information

NTSP 2005 International Telecommunications Safety Conference St. Louis, Missouri September 13-15, 2005

NTSP 2005 International Telecommunications Safety Conference St. Louis, Missouri September 13-15, 2005 NTSP 2005 International Telecommunications Safety Conference St. Louis, Missouri September 13-15, 2005 Fire Safety in Telecommunications Facilities / NFPA 76 Telecommunication Facilities Yesterday Bell

More information

CONTINUING EDUCATION UNIT (CEU) MATRIX CONTINUING EDUCATION UNIT (CEU) MATRIX CONT'D

CONTINUING EDUCATION UNIT (CEU) MATRIX CONTINUING EDUCATION UNIT (CEU) MATRIX CONT'D CONTINUING EDUCATION UNIT (CEU) MATRIX UNIFORM FIRE CODE - ADMINISTRATIVE CE063 Coaching For Positive Outcomes x x x 0.5 8 CE092 Communicating For Results x x x 0.5 8 CE021 Cultural Sensitivity x x x 0.5

More information

PHOTOVOLTAIC CABLES. Photovoltaic Cable 2000V/1500V Photovoltaic Cable 2000V/1000V

PHOTOVOLTAIC CABLES. Photovoltaic Cable 2000V/1500V Photovoltaic Cable 2000V/1000V PHOTOVOLTAIC CABLES PHOTOVOLTAIC CABLES INDEX n AmerSol Dual-Certified (UL / ETL) Photovoltaic Cable 2000V/1500V....................... 2-3 n AmerSol Dual-Certified (UL / ETL) Photovoltaic Cable 2000V/1000V.......................

More information

SECTION SOLAR PHOTOVOLTAIC (PV) POWER GENERATION SYSTEM

SECTION SOLAR PHOTOVOLTAIC (PV) POWER GENERATION SYSTEM SECTION 48 14 14 SOLAR PHOTOVOLTAIC (PV) POWER GENERATION SYSTEM PART 1 GENERAL 1.1 SECTION INCLUDES The work of this section consists of furnishing a complete Solar Photovoltaic (PV) Power Generation

More information

Research Needs for the Fire Safety Engineering Profession

Research Needs for the Fire Safety Engineering Profession Research Needs for the Fire Safety Engineering Profession Note: Items highlighted in RED are identified as the highest priority for each thread. Items highlighted in BOLD are identified as the highest

More information

PHOTOVOLTAIC SYSTEMS

PHOTOVOLTAIC SYSTEMS PHOTOVOLTAIC SYSTEMS EUROPEAN PERSPECTIVE Marc Van de Velde Vice President Centre of Excellence Property Risk Engineering / GAPS NFPA Conference April 2016, Munich - Germany Objectives Introduction Cells,

More information

Fike set out to develop a better understanding of the power density trends in data centers around the world.

Fike set out to develop a better understanding of the power density trends in data centers around the world. Fike set out to develop a better understanding of the power density trends in data centers around the world. We wanted to learn how increasing power density translates into energy augmented combustion.

More information

NEW ENERGY IN THE BATTERY INFRASTRUCTURE

NEW ENERGY IN THE BATTERY INFRASTRUCTURE NEW ENERGY IN THE BATTERY INFRASTRUCTURE Maurice H. Johnson Business Development Engineer UL LLC Northbrook, IL Paper Overview Over the past several years, there has been a significant effort to address

More information

ANTIFREEZE AND AUTOMATIC FIRE SPRINKLERS UPDATE. Presented by: Jerry Schultz The FPI Consortium, Inc. July 28, 2017

ANTIFREEZE AND AUTOMATIC FIRE SPRINKLERS UPDATE. Presented by: Jerry Schultz The FPI Consortium, Inc. July 28, 2017 ANTIFREEZE AND AUTOMATIC FIRE SPRINKLERS UPDATE Presented by: Jerry Schultz The FPI Consortium, Inc. July 28, 2017 History What happened? NFPA Response Current Status OUTLINE HISTORY 1940 Non-Freezing

More information

Protection of Rack Stored Exposed Expanded Group A Plastics with ESFR Sprinklers and Vertical Barriers

Protection of Rack Stored Exposed Expanded Group A Plastics with ESFR Sprinklers and Vertical Barriers Protection of Rack Stored Exposed Expanded Group A Plastics with ESFR Sprinklers and Vertical Barriers Final Report Prepared by: UL LLC The Fire Protection Research Foundation One Batterymarch Park Quincy,

More information

Fixed plant and mobile equipment fires on surface coal mines

Fixed plant and mobile equipment fires on surface coal mines Fixed plant and mobile equipment fires on surface coal mines Mines safety bulletin no. 158 21 November 2016 Version 1 Background Fires on fixed plant and mobile equipment at mines and quarries continue

More information

Ground Fault Protection Improvement Study

Ground Fault Protection Improvement Study Ground Fault Protection Improvement Study Greg Ball DNV KEMA Solar ABCs Stakeholder Meeting July 11, 2013 San Francisco, CA Study Authors 2 Bill Brooks Brooks Engineering Andy Rosenthal New Mexico State

More information

Chapter 17, Initiating Devices

Chapter 17, Initiating Devices Chapter 17, Initiating Devices Summary. Chapter 17 was Chapter 5 in NFPA 72-2007. The term authority having jurisdiction is replaced in some sections by the term other governing laws, codes, or standards.

More information

IRC - BUILDING - ELECTRICAL - ELECTRICAL TAC

IRC - BUILDING - ELECTRICAL - ELECTRICAL TAC IRC - BUILDING - ELECTRICAL - ELECTRICAL TAC W A R N I N G Copyright Notice: This document has been reproduced solely for considering proposed changes to the Florida Building Code with the permission of

More information

Fire Performance of Translucent Systems

Fire Performance of Translucent Systems Fire Performance of Translucent Systems ASTM E-108 Burning Brand Test on Quadwall Class A Approved Light Transmitting Plastics Fire Test Performance Meets Building Code Requirements: Self-Ignition ASTM

More information

Firefighter Safety in Battery Energy Storage System Fires

Firefighter Safety in Battery Energy Storage System Fires Firefighter Safety in Battery Energy Storage System Fires Erik Archibald, P.E. Kevin Marr, PhD, P.E. NFPA SUPDET November 30, 2018 Core Team O.A. (DK) Ezekoye The University of Texas at Austin UTFRG Casey

More information

Essentials of Fire Fighting 6 th Edition Firefighter I

Essentials of Fire Fighting 6 th Edition Firefighter I 1 Essentials of Fire Fighting 6 th Edition Firefighter I Chapter 5 Fire Behavior Replace with manual graphic on slide master Learning Objective 1 2 Explain the science of fire as it relates to energy,

More information

Your Landfill Cap is an Asset, Profit from It!

Your Landfill Cap is an Asset, Profit from It! Spectro PowerCap Your Landfill Cap is an Asset, Profit from It! 40th Annual SWANA 2011 Western Regional Symposium May 17th May 17, 2011 Western Regional Symposium 1 Carlisle Companies Fast Facts: Founded

More information

FEMA Recommendations for Protection of Curtained Limited Finishing Workstations using UL 1254 Listed Pre engineered Dry Chemical Systems

FEMA Recommendations for Protection of Curtained Limited Finishing Workstations using UL 1254 Listed Pre engineered Dry Chemical Systems FEMA Recommendations for Protection of Curtained Limited Finishing Workstations using UL 1254 Listed Pre engineered Dry Chemical Systems FEMA Recommendations are based upon Live Fire Testing of Prep Stations

More information

New Power Vented Rheem FVIR Tanks

New Power Vented Rheem FVIR Tanks Technical Bulletin B06-08 Sept 26/ 2006 New Power Vented Rheem FVIR Tanks In the coming weeks new power vented FVIR tanks will be arriving in the field from our tank manufactures. We are supplying some

More information

Overview of Canal Lining Projects. Montana Association of Dam and Canal Systems October 5 and 6, Jack Haynes EDC Canal Linings, LLC Owner

Overview of Canal Lining Projects. Montana Association of Dam and Canal Systems October 5 and 6, Jack Haynes EDC Canal Linings, LLC Owner Overview of Canal Lining Projects Montana Association of Dam and Canal Systems October 5 and 6, 2011 Jack Haynes EDC Canal Linings, LLC Owner Scope of Study 34 Test Sections installed 18 Exposed Geomembranes

More information

Standards Manager Web Standards List ULC-Underwriters Laboratories of Canada

Standards Manager Web Standards List ULC-Underwriters Laboratories of Canada Standards Manager Web Standards List ULC-Underwriters Laboratories of Canada Id Number Title Year Organization Page 1 ANSI.CAN.UL. NULL 2016 ULC 64 1201 2 CAN.ULC- NULL 2016 ULC 176 60839-11-1-2016 3 CAN.ULC-IEC

More information

Photovoltaic (Solar) Array Installation Guide

Photovoltaic (Solar) Array Installation Guide Building & Safety Division Community Development Department 7351 Rosanna Street, Gilroy, CA 95020 Phone: 408 846-0451 Fax: 408 846-0429 Visit us: www.cityofgilroy.org Photovoltaic (Solar) Array Installation

More information

TRIPR FLAMMABLE LIQUID UNIT TRAINS

TRIPR FLAMMABLE LIQUID UNIT TRAINS CLICK TO EDIT MASTER TITLE STYLE TRIPR FLAMMABLE LIQUID UNIT TRAINS 7.0 SELECT AND IMPLEMENT RESPONSE OBJECTIVES v CLICK TO OBJECTIVES EDIT MASTER TITLE STYLE Outline incident management principles and

More information

High challenge warehouse case study Summary

High challenge warehouse case study Summary High challenge warehouse case study Summary February 19, 2010 Richard Gallagher Michael Gollner Zurich Services Corporation Objectives Review the results of the high challenge warehouse workshop Recognize

More information

Arc Flash Mitigation Solutions: A Proactive Approach To Arc Flash Risk

Arc Flash Mitigation Solutions: A Proactive Approach To Arc Flash Risk Arc Flash Mitigation Solutions: A Proactive Approach To Arc Flash Risk Unrestricted Siemens Industry, Inc. 2015 All rights reserved. usa.siemens.com/arc-flash Everyone is concerned about the risk of Arc

More information

First Revision No. 6-NFPA [ Section No. 2.2 ]

First Revision No. 6-NFPA [ Section No. 2.2 ] Page 1 of 18 First Revision No. 6-NFPA 555-2014 [ Section No. 2.2 ] 2.2 NFPA Publications. National Fire Protection Association, 1 Batterymarch Park, Quincy, MA 02169-7471. NFPA 12, Standard on Carbon

More information

Photovoltaic systems Roof mounted. Property considerations for the peril of fire July 2016

Photovoltaic systems Roof mounted. Property considerations for the peril of fire July 2016 July 2016 Author: Zurich Global Risk Engineering Technical Center Property Cover photo source: Rich Gallagher, Zurich Table of contents 1. Executive Summary... 1 2. Introduction... 1 2.1 The challenges...

More information

Overview of a Year of Battery Fire Testing by DNV GL for Con Ed, NYSERDA and FDNY

Overview of a Year of Battery Fire Testing by DNV GL for Con Ed, NYSERDA and FDNY 2017 NFPA Conference & Expo Overview of a Year of Battery Fire Testing by DNV GL for Con Ed, NYSERDA and FDNY Presented by: Nick Warner, Sr. Test Engineer, DNV GL Dalan Zartman, President, Rescue Methods

More information

WATER MIST FIRE PROTECTION SYSTEMS FOR INDUSTRIAL CABLE TUNNELS AND TURBINE HALLS

WATER MIST FIRE PROTECTION SYSTEMS FOR INDUSTRIAL CABLE TUNNELS AND TURBINE HALLS WATER MIST FIRE PROTECTION SYSTEMS FOR INDUSTRIAL CABLE TUNNELS AND TURBINE HALLS Jukka Vaari 1, Amit Lior 2 1 2 VTT Technical Research Centre of Finland, Espoo, Finland Marioff Corporation Oy, Vantaa,

More information

CATALOG LIQUID-TUFF FLEXIBLE LIQUIDTIGHT CONDUIT CATALOG. Industrial & Commercial Liquidtight Conduit Flexible Metal Conduit A PART OF

CATALOG LIQUID-TUFF FLEXIBLE LIQUIDTIGHT CONDUIT CATALOG. Industrial & Commercial Liquidtight Conduit Flexible Metal Conduit A PART OF CATALOG LIQUID-TUFF FLIBL LIQUIDTIGHT CONDUIT CATALOG Industrial & Commercial Liquidtight Conduit Flexible Metal Conduit A PART OF AFC s Flexible Liquidtight Conduit AFC Cable Systems is pleased to announce

More information

CLT Adhesive Tests in Support of Mass Timber Buildings

CLT Adhesive Tests in Support of Mass Timber Buildings CLT Adhesive Tests in Support of Mass Timber Buildings DES604 Jason Smart, P.E. Manager, Engineering Technology American Wood Council Sam Francis, C.B.O. Senior Director, National Programs American Wood

More information

Identifying and Preventing Dust Fire and Explosion Hazards

Identifying and Preventing Dust Fire and Explosion Hazards Identifying and Preventing Dust Fire and Explosion Hazards Warren Greenfield International Specialty Products Wayne, New Jersey ABSTRACT This paper discusses how International Specialty Products Inc. addresses

More information

Emergency Evacuations What you need to know

Emergency Evacuations What you need to know Emergency Evacuations What you need to know Wildland Fires in Boulder County Olde Stage/Neva: January 2009 3000 acres Sunshine: March 2006 4.7 acres Elk Mountain: February 2006 600 acres Plainview: January

More information

Solicitation Requirements Matrix

Solicitation Requirements Matrix Access Control Provide barrier for controlled egress and ingress Solicitation Requirements Matrix Requirements Key Design Features Comment Faregates Provide retractable or paddle (swing) type barriers

More information

COSTCO, SAN FRANCISCO A PRESCRIPTIVE AND PERFORMANCE BASED ANALYSIS OF FIRE PROTECTION SYSTEMS AND DESIGN

COSTCO, SAN FRANCISCO A PRESCRIPTIVE AND PERFORMANCE BASED ANALYSIS OF FIRE PROTECTION SYSTEMS AND DESIGN COSTCO, SAN FRANCISCO A PRESCRIPTIVE AND PERFORMANCE BASED ANALYSIS OF FIRE PROTECTION SYSTEMS AND DESIGN Presented by Ian Levine June, 2016 Photo courtesy of Google Maps PRESENTATION OVERVIEW BUILDING

More information

Modeling a real backdraft incident fire

Modeling a real backdraft incident fire Advanced Computational Methods in Heat Transfer IX 279 Modeling a real backdraft incident fire A. Tinaburri 1 & M. Mazzaro 2 1 Central Direction for Prevention and Technical Safety, Firefighters, Public

More information

Hands On Training for Fire Door Products and Fire Door Assemblies

Hands On Training for Fire Door Products and Fire Door Assemblies 2017 NFPA Conference & Expo Hands On Training for Fire Door Products and Fire Door Assemblies Presented by: Paul M. Goldense, FDAI Goldense Building Products, Inc. Jeffery S. Batick, FDAI Allegion Why

More information

Fire Service Training Update

Fire Service Training Update Fire Service Training Update Gary Keith, Vice President Engineering Standards Manager FM Global Mutual Property Insurance Company 1835 250 Standards Technically-Based: Research Engineering Standards FM

More information

The Science Behind Water Mist Protection of Typical Building Hazards

The Science Behind Water Mist Protection of Typical Building Hazards The Science Behind Water Mist Protection of Typical Building Hazards SUPDET 2014 Zachary Magnone, P.E. Zachary.Magnone@tycofp.com Presentation Goals What is water mist? How does it work? How is it tested

More information

Water Mist and Heritage Buildings Case - St. Mark s Dome, Venice

Water Mist and Heritage Buildings Case - St. Mark s Dome, Venice Water Mist and Heritage Buildings Case - St. Mark s Dome, Venice By Nino Frisina Sales Director Marioff Italy IWMA Conference I Rome I 25 October 2017 Shutterstock.com AGENDA Background Case - St. Mark

More information

Floor Protectors and Wall Shields. Solar Reflectance Roof Covering Materials

Floor Protectors and Wall Shields. Solar Reflectance Roof Covering Materials 2011 Issue 3 2 World Class UL Fire Research 4 Floor Protectors and Wall Shields 6 Gate Operators Solar Reflectance Roof Covering Materials A cool idea for saving energy By Howard Hopper / Managing Editor

More information

CLOUD CEILINGS: FIRE DYNAMICS AND CODE CONTEXT

CLOUD CEILINGS: FIRE DYNAMICS AND CODE CONTEXT Peterson Guadagnolo Consulting Engineers PC CLOUD CEILINGS: FIRE DYNAMICS AND CODE CONTEXT 1 November 7, 2016 AGENDA Introduction New York State Code - Update Ceiling Types Fire Dynamics Compartment Fire

More information

INNOVATIVE SOLAR TUNNEL DRYER

INNOVATIVE SOLAR TUNNEL DRYER ABSTRACT INNOVATIVE SOLAR TUNNEL DRYER MGIRED Journal Volume 3(2) : 28-32 ISSN 2393-9605 Food preservation or agro crop preservation means avoiding the microbial growth due to presence of moisture content

More information

Factors Affecting Efficiency of Water Mist Suppression of Solid Combustible Fires in Open Environment

Factors Affecting Efficiency of Water Mist Suppression of Solid Combustible Fires in Open Environment Factors Affecting Efficiency of Water Mist Suppression of Solid Combustible Fires in Open Environment Hong-Zeng (Bert) Yu FM Global 16 th International Water Mist Conference September 21-22, 2016 Vienna,

More information

Tire Storage. Michigan Fire Inspectors Society Fall Conference

Tire Storage. Michigan Fire Inspectors Society Fall Conference Tire Storage Michigan Fire Inspectors Society Fall Conference September 15, 2016 This material, including the illustrations, represent the opinion of the author and instructor. This material is not designed,

More information

CHEMICAL ENGINEERING TRANSACTIONS

CHEMICAL ENGINEERING TRANSACTIONS 427 A publication of CHEMICAL ENGINEERING TRANSACTIONS VOL. 48, 2016 Guest Editors: Eddy de Rademaeker, Peter Schmelzer Copyright 2016, AIDIC Servizi S.r.l., ISBN 978-88-95608-39-6; ISSN 2283-9216 The

More information

Rooftop Analysis Conducted by: June 1st, 2014 Paisley Gallagher, Kaitlin MacKenzie, Alex Sughrua, and Brandon Gilfford

Rooftop Analysis Conducted by: June 1st, 2014 Paisley Gallagher, Kaitlin MacKenzie, Alex Sughrua, and Brandon Gilfford Rooftop Analysis Conducted by: June 1st, 2014 Paisley Gallagher, Kaitlin MacKenzie, Alex Sughrua, and Brandon Gilfford Abstract: As a team we set out to assess the available locations for future solar

More information

When Standards meet experience and increase the value of PV. Dr. Francesco Groppi (CESI Middle East) Chairman of CENELEC/TC82

When Standards meet experience and increase the value of PV. Dr. Francesco Groppi (CESI Middle East) Chairman of CENELEC/TC82 When Standards meet experience and increase the value of PV (CESI Middle East) Chairman of CENELEC/TC82 About CENELEC CENELEC is the European Committee for Electrotechnical Standardization and is responsible

More information

2012 International Fire Code Significant Changes. IFC Background. Purpose IBC and 2012 NFPA 101 Significant Means of Egress Changes

2012 International Fire Code Significant Changes. IFC Background. Purpose IBC and 2012 NFPA 101 Significant Means of Egress Changes 2012 International Fire Code Significant Changes Andrew M. Schneider, P.E. Senior Fire Protection Engineer aschneider@koffel.com Koffel Associates, Inc. www.koffel.com Expertly Engineering Safety From

More information

Fire is No Accident Fire is No Accident It can be prevented.

Fire is No Accident Fire is No Accident It can be prevented. 1 Fire is No Accident It can be prevented. 2 3 States of Matter Solid Liquid Gas 3 What is Fire? Answer: Fire is a phenomena that occurs when a substance combines with fuel and has adequate oxygen. Typically

More information

Denver s Green Building Ordinance

Denver s Green Building Ordinance Denver s Green Building Ordinance Agenda I. About the new ordinance II. III. IV. Applicability and exemptions Compliance options o o Cool roofs V. Campuses New buildings Existing buildings VI. VII. Rules

More information

IEC PROJETOS EM VOTAÇÃO. IEC 62256/Ed2: Hydraulic turbines, storage pumps and pump-turbines - Rehabilitation and performance improvement.

IEC PROJETOS EM VOTAÇÃO. IEC 62256/Ed2: Hydraulic turbines, storage pumps and pump-turbines - Rehabilitation and performance improvement. IEC PROJETOS EM VOTAÇÃO IEC/TC 4 Hydraulic turbines IEC 62256/Ed2: Hydraulic turbines, storage pumps and pump-turbines - Rehabilitation and performance improvement. IEC/TC 9 - Electrical equipment and

More information

Performance Metrics for First Responder Locating/Tracking Technologies

Performance Metrics for First Responder Locating/Tracking Technologies Precision Indoor Personnel Location and Tracking for Emergency Responders Workshop Performance Metrics for First Responder Locating/Tracking Technologies Nelson Bryner and David Stroup Fire Fighting Technology

More information

Incident Summary #II (#8165) (FINAL)

Incident Summary #II (#8165) (FINAL) Incident Summary #II-727632-2018 (#8165) (FINAL) Incident Date June 26, 2018 Location White Rock SUPPORTING INFORMATION Regulated industry sector Impact Injury Damage Qty injuries 0 Injury description

More information

Infrared Business Tips & Insight

Infrared Business Tips & Insight Infrared Business Tips & Insight 2010 Infrared Training Center. All rights reserved. Intended for use by Infrared Training Center customers and prospects only Infrared Business Tips & Insight Presenter:

More information

Cool roofs and cool pavements for the reefer container yard

Cool roofs and cool pavements for the reefer container yard Cool roofs and cool pavements for the reefer container yard Knowledge Area(s): Main Area Sub-area Author(s) Affiliation e-mail Jan Christoph Ahting Jacobs University j.ahting@jacobs-university.de Distribution

More information

Arc Flash Protection Training - NFPA 70e Electrical Safety

Arc Flash Protection Training - NFPA 70e Electrical Safety Arc Flash Protection Training - NFPA 70e Electrical Safety Contact us Today for a FREE quotation to deliver this course at your company?s location. https://www.electricityforum.com/onsite-training-rfq

More information

2018 IFC Update. Based on the 2018 International Fire Code, (IFC ) Goal. Objectives. Content

2018 IFC Update. Based on the 2018 International Fire Code, (IFC ) Goal. Objectives. Content Based on the 2018 International Fire Code, (IFC ) The International Fire Code (IFC ), establishes minimum regulations for fire safety. This handout will identify important changes in the IFC from 2015

More information

Extreme Fires!

Extreme Fires! Extreme Fires! Is History Repeating Itself? 1971 - Airlie House Conference International Conference On Fire Safety In High-rise Buildings Evacuation impractical protect in place Limit fuel load prohibit

More information