1 FACILITIES PLANNING STUDY RIVER VALLEY SCHOOL DISTRICT Plain Elementary School 1370 Cherry St. Plain, WI South Dewey Street Eau Claire, Wisconsin sdsarch.com
2 PLAIN General Overview Note: Property lines have been approximated Site Acreage: Approx. 3.4 Acres Parking Stalls: Approx. 20 Building Area: 24,110 GSF Construc on: Masonry/CMU ES Director: Mr. Jaime Hegland Students: 95 GSF/Student: 254 Grades: K through 5th Paved Area P.1 Descrip on: Staff Parking Type: Asphalt Net Area: Approx. 5,640 SF Ra ng: Paved Area P.2 Descrip on: Visitor Parking Type: Asphalt Net Area: Approx. 2,340 SF Ra ng: Paved Area P.4 Descrip on: Play Ground Type: Asphalt Net Area: Approx. 5,555 SF Ra ng: Paved Area P.5 Descrip on: Parking Type: Asphalt Net Area: Approx. 1,410 SF Ra ng: Paved Area P.3 Descrip on: Play Ground Type: Asphalt Net Area: Approx. 12,615 SF Ra ng: P.2 P.5 P.3 P.4 P.1 * See the final page of Chapter 1 for ra ng system of paved surfaces. Chapter 4 Page 2
3 Site Analysis Code/Safety Issue Site photos Chapter 4 Page 3
4 PLAIN Building Construction, Remodels and Additions * Fire ra ngs as indica ed by original construc on may currently be compromised by subsequent modifica ons. Year Project Scope Area 1991 Original Building Construc on 24,110 SF Legend 1 Founda on: Cast-in-Place Exterior Shell: Brick Cavity Wall R-VALUE: Interior: CMU Block 1 Chapter 4 Page 4
5 Roof Analysis Legend BSPM (Ballasted Single Ply EPDM) ASPM (Adhered Single Ply EPDM) Roof Area R.1 Roof Type: ASPM Net Area: 18,115 SF Year Installed: 1991 Condi on: Average Roof Area R.2 Roof Type: ASPM Net Area: 6,205 SF Year Installed: 1991 Condi on: Average R.1 R.2 Roof photos Chapter 4 Page 5
6 PLAIN Room Assignments and Building Use Legend Classroom/Instruc on Athle cs Administra on/conference Food Service Music/Arts General/Support Circula on PRE-K PRE-K 5TH GRADE MECH./ CUSTODIAL STOR AV FACULTY LOUNGE NURSE TOILET STOR ART/MUSIC COMPUTER LAB IMC OFFICE KITCHEN MULTI-PURPOSE STOR WORK/ SUPPLY PRINCIPAL OFFICE TOILET 1ST GRADE 2ND GRADE 3RD GRADE TITLE 1 PHY ED. OFFICE Chapter 4 Page 6
7 Floor Plan Analysis Damaged/worn flooring Restroom is not ADA compliant Damaged/worn cabinets/casework Damaged/worn ceiling Damaged/worn plumbing fixtures Interior Photos Code/Safety Issue Safety/Health Issue ADA/Accessibility Issue Program Related Problem Area Chapter 4 Page 7
8 PLAIN Mechanical Analysis AC Control Air Compressor EF Exhaust Fan AH Air Handling Unit FT Fin Tube Heat B CH CR CV ED Boiler Cabinet Unit Heater Condensate Return Sta on Convector Exhaust Duct KH Kitchen Hood GS Gas Service MS Mini-Split P Pump UH Unit Heater EF CH 9 UH B B UV Unit Ven lator 1) Corridors are u lized as return air plenums. CH Up to gooseneck EF EF AH AH 2) The kiln is not provided with adequate exhaust. MS 3) The building is served by hea ng only air handling units with constant volume reheat booster coils. Some spaces are provided with split systems for cooling. The air handling units and reheat MS EF KH KH coils are in good working condi on, but are nearing the end of their useful life. The split systems are in good working condi on, but nearing the end of their useful life. Hea ng is provided by two new Pres ge boilers installed in A new DDC control CH MS AH KH AH system was recently provided to serve the facility. CH Code/Safety Issue Photos Chapter 4 Page 8
9 Electrical Analysis TP D SS P A MS Switchboard 10 P E UT *pad mounted D Data Center EM Electric Meter FA Fire Alarm Control Panel MC Master Clock MS Main Service P Panel PS Paging System SS Security System UT U lity Transformer TP Phone/Data Termina on Port P D P K 1) Automa c ligh ng control is not present in all required areas of the building. 11 FA PS LIGHTING 2) Ligh ng generally consists of fluorescent recessed parabolic fixtures that are in good working condi on. P C 3) Some recent ligh ng upgrades appear to have taken place P B and include high bay fluorescent ligh ng in the gym. D TP Code/Safety Issue Photos Chapter 4 Page 9
10 PLAIN Plumbing Analysis AB Acid Neutralizing Basin CP Circula on Pump GS Gas Service GI Grease Interceptor WH WS LS Li Sta on GS S Water So ener SP Sump Pump WH Water Heater WS Water Service PLUMBING 1) The domes c water is so ened by a Hellenbrand water so ener and heated by a single A.O. Smith gas fired water heater. The plumbing equipment appears to be in good working condi on, but nearing the end of their useful life. FIRE PROTECTION 2) The building is not provided with fire protec on. WH GI Code/Safety Issue Photos Chapter 4 Page 10
11 Photographs Chapter 4 Page 11
Arena Elementary School 314 Willow St. Arena, WI 53503
FACILITIES PLANNING STUDY RIVER VALLEY SCHOOL DISTRICT Arena Elementary School 314 Willow St. Arena, WI 53503 7 South Dewey Street Eau Claire, Wisconsin 54701 715.83.1605 sdsarch.com ARENA General Overview
More informationSpring Green Elementary School 830 Daley St. Spring Green, WI 53588
FACILITIES PLANNING STUDY RIVER VALLEY SOOL DISTRICT Spring Green Elementary School 830 Daley St. Spring Green, WI 388 7 South Dewey Street Eau Claire, Wisconsin 4701 71.832.160 sdsarch.com SPRING General
More informationRiver Valley High School 660 Varsity Blvd. Spring Green, WI 53588
FACILITIES PLANNING STUDY RIVER VALLEY SCHOOL DISTRICT River Valley High School 660 Varsity Blvd. Spring Green, WI 53588 South Dewey Street Eau Claire, Wisconsin 5401 15.832.1605 sdsarch.com RIVER General
More informationVOTER BOND REFERENDUM 2018 SUMMARY OF WORK PROPOSED
Ashton Elementary School 1 Masonry Repair $ 42,781.50 2 Replace HVAC $ 375,000.00 3 Replace SAT @ Various Locations $ 92,364.00 3 Recoat & Resurface Exterior Paved Play Area $ 135,978.30 3 Various Technological
More informationMUKWONAGO AREA SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY
ARCHITECTURE ROLLING HILLS ELEMENTARY SCHOOL Rolling Hills Elementary was built in 1999 and is the newest addition to the Mukwonago Area School District. The building contains approximately 64,900 gross
More informationFlorence High School / Middle School Page 1 of 3 Florence, WI
Florence High School / Middle School Page 1 of 3 Florence, WI Plumbing Systems Review: The following report is the result of a site visit by Tim Kehoe of Muermann Engineering, LLC that occurred on October
More informationSagebrush Elementary School East Temple Place Aurora, Colorado 80015
Sagebrush Elementary School 14700 East Temple Place Aurora, Colorado 80015 Year Opened 1977 Current Square Footage 57,100 Site Acreage 7.66 sagebrush.cherrycreekschools.org Asphalt and concrete work; electrical
More informationState College Area School District High School South Building EXISTING CONDITIONS ASSESSMENT
State College Area School District High School South Building Prepared by CenterPoint Engineering 08 February 2013 FACILITY ASSESSMENT SUMMARY PHYSICAL PLANT General HVAC This report is a snapshot of the
More informationNYC Department of Education
Asset: P.S. 69 - STATEN ISLAND, 144 KEATING PLACE, New York, 10314 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-01-19 8:39 AM 2018-01-23 4:33 PM Asset Data Are there fuel tanks?
More informationPLATTEVILLE MIDDLE SCHOOL
Architectural The building has aluminum clad wood awning windows in combination with aluminum fixed glass units. They appear to be exterior glazed with insulated glazing. See photo 2. Platteville Middle
More informationMeadow Point Elementary School East Grand Avenue Aurora, Colorado 80015
Meadow Point Elementary School 17901 East Grand Avenue Aurora, Colorado 80015 Year Opened 1982 Current Square Footage 53,100 Site Acreage 7.48 meadowpoint.cherrycreekschools.org $2,081,600 Electrical system,
More informationMID MICHIGAN COMMUNITY COLLEGE HARRISON CAMPUS Harrison, Michigan 2015 MASTER PLAN
MID MICHIGAN COMMUNITY COLLEGE HARRISON CAMPUS Harrison, Michigan 2015 MASTER PLAN September 30, 2015 PBA Project No. 2015.0140.00 PETER BASSO ASSOCIATES INC. CONSULTING ENGINEERS 5145 LIVERNOIS ROAD,
More informationMUKWONAGO SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY
MUKWONAGO SCHOOL DISTRICT ARCHITECTURE PARK VIEW MIDDLE SCHOOL The original school building was dedicated in 1954 as the High School, with an addition in 1959, a library addition in 1970, and an addition/renovation
More informationGreenwood Elementary School 5550 South Holly Street Greenwood Village, Colorado 80111
Greenwood Elementary School 5550 South Holly Street Greenwood Village, Colorado 80111 Year Opened 1958 Current Square Footage 50,504 Site Acreage 8.53 greenwood.cherrycreekschools.org $220,720 Electrical
More informationHOLUM EDUCATION CENTER. Architectural. January 13, 2014 DeForest Area School District
HOLUM EDUCATION CENTER Architectural The existing building has approximately 41,823 square feet and sets on a lot about 4.14 acres in size. Parking lots are located along the east and west sides of the
More informationNYC Department of Education
Asset: P.S. 183 - QUEENS, 2-45 B 79 STREET, New York, 11693 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-03-02 8:32 AM 2018-05-16 1:44 PM Asset Data Are there fuel tanks? Total
More informationState College Area School District High School North Building EXISTING CONDITIONS ASSESSMENT
State College Area School District High School North Building Prepared by CenterPoint Engineering 08 February 2013 FACILITY ASSESSMENT SUMMARY PHYSICAL PLANT General HVAC This report is a snapshot of the
More informationNYC Department of Education
Asset: P.S. 199 ANNEX (@ ST. TERESA'S) - QUEENS, 50-15 44TH STREET, New York, 11377 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-04-18 11:39 AM 2018-05-14 12:27 PM Asset Data
More informationReed, Wells, Benson & Company Consulting Engineeers Firm Registration F-2176 #: COIT CENTRAL TOWER SUITE 1100 12001 NORTH CENTRAL EXPWY DALLAS, TEXAS 75243 RWB PHONE: (972 788-4222 FAX: (972) 788-0002
More informationNYC Department of Education
Asset: P.S. 92 - BROOKLYN, 601 PARKSIDE AVENUE, New York, 11226 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-11-13 8:31 AM 2017-11-27 11:43 AM Asset Data Are there fuel tanks?
More informationNYC Department of Education
Asset: P.S. 198 - BRONX, 1180 TINTON AVENUE, New York, 10456 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-01-24 8:14 AM 2018-01-24 9:32 PM Asset Data Are there fuel tanks? Total
More informationNYC Department of Education
Asset: P.S. 146 - BRONX, 968 CAULDWELL AVENUE, New York, 10456 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-12-01 8:57 AM 2018-05-31 2:59 PM Asset Data Are there fuel tanks? Total
More informationNYC Department of Education
Asset: P.S. 86 ANNEX - BRONX, 124 EAMES PLACE, New York, 10468 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-04-05 1:03 PM 2018-04-27 1:35 PM Asset Data Are there fuel tanks? Total
More informationNYC Department of Education
Asset: P.S. 160 - BROOKLYN, 5105 FORT HAMILTON PARKWAY, New York, 11219 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-04-03 8:01 AM 2018-05-18 1:45 PM Asset Data Are there fuel
More informationNYC Department of Education
Asset: P.S. 104 - BROOKLYN, 9115 5TH AVENUE, New York, 11209 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-02-21 8:55 AM 2018-02-21 1:09 PM Asset Data Are there fuel tanks? Total
More informationNYC Department of Education
Asset: P.S. 19 - STATEN ISLAND, 780 POST AVENUE, New York, 10310 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-10-26 8:58 AM 2017-11-14 1:37 PM Asset Data Are there fuel tanks?
More informationAllisonville Elementary School Facilities Highlights Built: 1960 Last Major Renovation: 28 years ago Capacity: 650 Current Enrollment: 767
Allisonville Elementary School Built: 1960 Last Major Renovation: 28 years ago Capacity: 650 Current Enrollment: 767 ADA improvements are Fire alarms need to be updated Playground equipment needs to be
More information2014 Bond Project Guide
2014 Bond Project Guide Bush Elementary School Page 1 Instructional Technology Computers, Projectors, Mobile Carts, Document Cameras and Printers Wireless Connectivity New Construction New Tech Center
More informationAppendix B. Facilities Assessment Report
Mile Lane Army Reserve Center Redevelopment Plan September 2008 Appendix B Facilities Assessment Report RKG Associates, Inc. Mile Lane Army Reserve Base Middletown, CT MEP System Evaluation For RKG Associates
More informationFrancis M McKay Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationNYC Department of Education
Asset: P.S. 128 - MANHATTAN, 560 WEST 169 STREET, New York, 10032 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-12-07 8:50 AM 2018-06-14 1:16 PM Asset Data Are there fuel tanks?
More informationCook - Wissahickon Elementary School
Cook - Wissahickon Elementary School 201 E. Salaignac St., Philadelphia, PA 19128 HVAC Replacement Project Scope Determination Report May 10, 2018 Prepared by: G.P. Lamina, Jr., P.E., MBA School District
More informationNYC Department of Education
Asset: P.S. 11 - MANHATTAN, 320 WEST 21 STREET, New York, 10011 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-01-23 8:27 AM 2018-01-23 3:21 PM Asset Data Are there fuel tanks?
More informationNYC Department of Education
Asset: P.S. 224 ANNEX - QUEENS, 221-21 CORBETT ROAD, New York, 11361 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-03-28 12:27 PM 2018-04-04 5:15 PM Asset Data Are there fuel tanks?
More informationChariho Regional School District Five-Year Capital Facilities Improvement Plan (2/10/15)
Chariho Regional School District Five-Year Capital Facilities Improvement Plan (2/10/15) School/Department FY 16 FY 17 FY18 FY19 FY20 Chariho Regional High School FY 16 FY 17 FY18 FY19 FY20 *Repair Bleachers
More information3. 21st Century Learning A. Districtwide Flexible Learning - Allowance for Flexible Furniture $600,000 Subtotal $600,000
1. Safety and Security A. Additional Cameras District Wide $382,000 B. Interior Locks Upgrades Allowance $300,000 C. Tilden Entrance Upgrades D. Door and Glass Improvements Allowance $500,000 E. Alert
More informationNYC Department of Education
Mechanical Inspection Asset: P.S. 1 - MANHATTAN, 8 HENRY STREET, New York, 10038 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-09-28 8:39 AM 2017-10-12 5:28 PM Asset Data Are there
More informationNYC Department of Education
Asset: P.S. 163 - BRONX, 2075 WEBSTER AVENUE, New York, 10457 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-03-22 8:33 AM 2018-03-22 3:13 PM Asset Data Are there fuel tanks? Total
More informationNYC Department of Education
Asset: P.S. 22 - STATEN ISLAND, 1860 FOREST AVENUE, New York, 10303 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-12-08 8:51 AM 2017-12-18 4:14 PM Asset Data Are there fuel tanks?
More informationENGINEERING REPORT - MECHANICAL / ELECTRICAL / PLUMBING
Mechanical Systems Information The mechanical system at Reed Middle School is comprised of seventy six Trane DX/Gas rooftop units (RTUs). The recommended useful life for DX equipment is 15 years. Seventy
More information2015 Building Condition Survey Summary Mosaic Associates Architects 02/19/16
1. General: This summary is offered as a supplement to the 2015 Building Condition Survey being filed with SED on behalf of the District. All cost estimates are preliminary, and should be re-evaluated
More informationNYC Department of Education
Asset: A. PHILLIP RANDOLPH HS - MANHATTAN, 443 WEST 135 STREET, New York, 10031 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-02-02 8:11 AM 2018-06-14 1:21 PM Asset Data Are there
More informationNYC Department of Education
Asset: P.S. 194 - MANHATTAN, 244 WEST 144 STREET, New York, 10030 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-12-12 10:48 AM 2018-01-29 10:54 AM Asset Data Are there fuel tanks?
More informationNYC Department of Education
Asset: P.S. 161 - MANHATTAN, 499 WEST 133 STREET, New York, 10027 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-03-15 8:26 AM 2018-06-08 1:37 PM Asset Data Are there fuel tanks?
More informationNYC Department of Education
Asset: P.S. 23 - BROOKLYN, 545 WILLOUGHBY AVENUE, New York, 11206 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-05-31 8:47 AM 2018-06-05 3:45 PM Asset Data Are there fuel tanks?
More informationNYC Department of Education
Asset: P.S./I.S. 194 - BRONX, 2365 WATERBURY AVENUE, New York, 10462 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-01-24 8:34 AM 2018-02-01 10:02 AM Asset Data Are there fuel tanks?
More informationNYC Department of Education
Asset: P.S. 29 - STATEN ISLAND, 1581 VICTORY BLVD, New York, 10314 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-01-10 11:28 AM 2018-01-17 11:37 AM Asset Data Are there fuel tanks?
More informationFacilities Master Planning
Facilities Master Planning DeForest Area School District DeForest, WI PRA Project #130343-01 January 13, 2014 DRAFT Table of Contents DeForest Area School District PRA Project # 130217-01 Section 1 Existing
More informationMOUNT PLEASANT MIDDLE SCHOOL HVAC. M-01 Heating Plant: M-02 Heating & Ventilating Systems: Livingston School District Mount Pleasant Middle School
MOUNT PLEASANT MIDDLE SCHOOL HVAC M-01 Heating Plant: The existing boilers have recently been upgraded. (3) steam boilers (8660 mbh each) manufactured by Weil- McLain have been installed. Newer hot water
More informationNYC Department of Education
Asset: P.S. 111 - MANHATTAN, 440 WEST 53 STREET, New York, 10019 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-03-16 8:47 AM 2018-03-21 8:02 AM Asset Data Are there fuel tanks?
More informationNYC Department of Education
Asset: P.S. 841- QUEENS, 48-25 37TH STREET, New York, 11104 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-04-02 12:54 PM 2018-05-14 12:28 PM Asset Data Are there fuel tanks? Total
More informationNYC Department of Education
Asset: P.S. 78 - QUEENS, 48-09 CENTER BLVD., New York, 11109 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-04-02 11:40 AM 2018-04-19 9:04 AM Asset Data Are there fuel tanks? Total
More informationNYC Department of Education
Asset: I.S. 45 - BRONX, 2502 LORILLARD PLACE, New York, 10458 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-12-05 9:14 AM 2017-12-20 11:42 AM Asset Data Are there fuel tanks? Total
More informationNYC Department of Education
Asset: P.S. 188 - MANHATTAN, 442 EAST HOUSTON STREET, New York, 10002 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-03-08 8:52 AM 2018-06-13 5:06 PM Asset Data Are there fuel tanks?
More informationNYC Department of Education
Asset: P.S. 310 - BRONX, 260 WEST KINGSBRIDGE RD, New York, 10463 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-12-07 8:42 AM 2017-12-13 12:31 PM Asset Data Are there fuel tanks?
More informationLINCOLN HIGH SCHOOL MODERNIZATION BEX IV COMMUNITY MEETING JUNE 23, 2016
LINCOLN HIGH SCHOOL MODERNIZATION BEX IV COMMUNITY MEETING JUNE 23, 2016 PROJECT OVERVIEW PROJECT OVERVIEW + PRE-DESIGN BEGAN IN FALL OF 2015 + EXISTING CONDITIONS ANALYSIS + PROJECTED GROWTH IN HIGH SCHOOL
More informationSHOE PALACE HUNTINGTON PARK M.200
M.200 SPLIT SYSTEM CONDENSING UNIT SCHEDULE MARK SERVICE MODEL NO. COOLING DIMENSIONS ELECTRICAL REMARKS CAPACITY AMBIENT DB REFRIGERANT LENGTH WIDTH HEIGHT WEIGHT VOLT/PHASE MCA MOP (MBH) (DEG F) (IN)
More information1080 Marina Village Parkway, Suite 501 Alameda, CA (510) Fax (510) HVAC DESIGN INTENT
Taylor Engineering 1080 Marina Village Parkway, Suite 501 Alameda, CA 94501-1142 (510) 749-9135 Fax (510) 749-9136 LLC HVAC DESIGN INTENT PART 1 - GENERAL 1.1 Overview A. The project consists of a 3-story
More informationNYC Department of Education
Asset: P.S. 2 - MANHATTAN, 122 HENRY STREET, New York, 10002 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-01-05 9:21 AM 2018-01-16 12:15 PM Asset Data Are there fuel tanks? Total
More informationJosefa Ortiz De Dominguez Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationCalmeca Academy of Fine Arts and Dual Language
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationMechanical Inspection Plumbing
0811 Fixtures Sinks, drinking fountains, water closets, showers, etc. Classroom Sinks. Classroom sinks (19) are enameled cast iron self rimming side ledge with gooseneck faucet trim with index handles,
More informationNYC Department of Education
Asset: P.S. 157 - BRONX, 757 CAULDWELL AVENUE, New York, 10456 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-12-01 8:48 AM 2017-12-06 5:36 PM Asset Data Are there fuel tanks? Total
More informationNYC Department of Education
Asset: P.S. 7 - MANHATTAN, 160 EAST 120 STREET, New York, 10035 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-03-02 8:44 AM 2018-03-12 10:45 AM Asset Data Are there fuel tanks?
More informationCharles W Earle Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationNYC Department of Education
Asset: MID MAN ADULT LRNG CTR (81) - M, 212 W 120TH ST, New York, 10027 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-01-17 8:16 AM 2018-01-17 8:17 PM Asset Data Are there fuel
More informationJoseph Brennemann Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationMECHANICAL, ELECTRICAL, PLUMBING, AND FIRE PROTECTION CONDITIONS FACILITIES MASTER PLAN MAY
MECHANICAL, ELECTRICAL, PLUMBING, AND FIRE PROTECTION CONDITIONS FACILITIES MASTER PLAN MAY 2018 57 MECHANICAL ASSESSMENT MECHANICAL ASSESSMENT This report section includes an overview of the existing
More informationNYC Department of Education
Asset: FORSYTH HS (AUXSVC-OLD 91) - M, 198 FORSYTH STREET, New York, 10002 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-09-28 8:07 AM 2018-03-20 4:47 PM Asset Data Are there fuel
More informationNYC Department of Education
Asset: P.S. 205B (ECF) - BRONX, 2375 SOUTHERN BLVD, New York, 10460 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-01-12 12:29 PM 2018-01-12 3:14 PM Asset Data Are there fuel tanks?
More informationJohn Palmer Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationNYC Department of Education Building Condition Assessment Survey :49AM :00PM
School: InspectionId Asset Data Inspection Type Building Assessment Survey 05-06 P.S. 70 - BROOKLYN, 4 EMERSON PLACE, BROOKLYN, NY, 05 Time In Last Edited 476 MECHANICAL 05-- 08:49AM 05-- 03:00PM Have
More informationNYC Department of Education
NYC Department of Education Building Assessment Survey 2017-2018 Asset: P.S. 314 - BROOKLYN, 330 59 STREET, New York, 11220 Inspection Id Inspection Type Time In Last Edited EE : Electrical 2018-04-23
More informationIchabod Crane Central School District 2018 Capital Project Preliminary Estimate
Health & Safety 1,399,000 Academics & Program 17,140,800 Physical Education & Athletics 5,922,000 Building Infrastructure 3,103,800 Site Infrastructure 1,049,600 TOTAL SCOPE OF WORK 28,615,200 PROPOSED
More informationNYC Department of Education
Asset: P.S. 32 - BRONX, 690 EAST 183 STREET, New York, 10458 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-11-13 9:25 AM 2017-11-16 5:46 PM Asset Data Are there fuel tanks? Total
More informationNYC Department of Education
Asset: P.S. 253 - BROOKLYN, 601 OCEAN VIEW AVENUE, New York, 11235 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-03-22 8:34 AM 2018-05-31 5:42 PM Asset Data Are there fuel tanks?
More informationBriar Crest Elementary
Promises Kept This document includes partial lists of major projects completed at Pattonville Schools since 1986 as part of past bond issues approved by the Pattonville community. Briar Crest Elementary
More informationGenevieve Melody Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationNYC Department of Education
Asset: J.H.S. 216 - QUEENS, 64-20 175 STREET, New York, 11365 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-11-06 8:51 AM 2017-11-22 10:04 AM Asset Data Are there fuel tanks? Total
More informationAshland School District Facility & Capacity Assessment Report 2005
Ashland School District Facility & Capacity Assessment Report 2005 Briscoe Elementary School (Closed Facility) Address: 265 N Main Street Area: 33,980 square feet Buildings: Original Building 1948 Music
More informationNYC Department of Education
Asset: P.S. 73 - BRONX, 1020 ANDERSON AVENUE, New York, 10452 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-11-16 8:29 AM 2017-11-28 10:59 AM Asset Data Are there fuel tanks? Total
More informationNYC Department of Education
Asset: I.S. 131 - BRONX, 885 BOLTON AVENUE, New York, 10473 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-10-17 8:54 AM 2017-12-05 5:41 PM Asset Data Are there fuel tanks? Total
More informationCAPITAL OUTLAY REQUEST - IDENTIFIED AND EMERGING PROJECTS - RANKED 3-Jun-14
2014-2015 CAPITAL OUTLAY REQUEST - IDENTIFIED AND EMERGING PROJECTS - RANKED 3-Jun-14 School Item Amount a. Classroom A/R (Increase CR capacity to 804, add l Resource and tutoring spaces needed. Teacher
More informationRichard Henry Lee Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More information2014 Bond District-wide Facility Repairs
Elementary Schools Aloha-Huber Park Fire Detector upgrade Replace electric backboard winches in gym Heating/cooling system controls upgrade Barnes Replace exterior windows Heating/cooling system and controls
More informationNYC Department of Education
Asset: W.E.B. DUBOIS HS - BROOKLYN, 402 EASTERN PARKWAY, New York, 11225 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-12-04 1:02 PM 2017-12-27 4:16 PM Asset Data Are there fuel
More informationNYC Department of Education
Asset: J. K. ONASSIS HS FOR INT CAREERS-M, 120 WEST 46 STREET, New York, 10036 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-12-11 11:37 AM 2017-12-26 12:18 PM Asset Data Are there
More informationNYC Department of Education
Asset: UNIVERSITY NEIGHBORHOOD - M, 200 MONROE STREET, New York, 10002 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-02-05 11:56 AM 2018-03-02 7:14 PM Asset Data Are there fuel
More informationAgustin Lara Elementary Academy
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationEdward Jenner Elementary Academy of the Arts
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationCENTRAL GEORGIA TECHNICAL COLLEGE. Maintenance, Custodial & Operation Plan Facilities & Equipment
CENTRAL GEORGIA TECHNICAL COLLEGE Maintenance, Custodial & Operation Plan Facilities & Equipment Central Georgia Technical College Maintenance, Custodial and Operation Plan In order that Central Georgia
More informationPreliminary Study Document. Horicon. Horicon, Wisconsin
Preliminary Study Document Horicon School District Horicon, Wisconsin Monday table of contents i 1 2 Introduction Section One: Van Brunt Elementary School a. Building Evolution b. Existing Site Plan c.
More informationNYC Department of Education
Asset: PRE-K CENTER @ 7401 FORT HAMILTON PARKWAY - BROOKLYN, 7401 FORT HAMILTON PARKWAY, New York, 11228 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-11-27 11:12 AM 2017-11-27
More informationOscar DePriest Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationNYC Department of Education
NYC Department of Education Building Assessment Survey 2017-2018 Asset: P.S. 16 - BROOKLYN, 157 WILSON STREET, New York, 11211 Inspection Id Inspection Type Time In Last Edited EE : Electrical 2017-11-30
More informationELECTRICAL SYSTEMS ASSESSMENT Hanover High School
ELECTRICAL SYSTEMS ASSESSMENT Hanover High School ELECTRICAL DISTRIBUTION SYSTEM:?? The existing electrical service consists of an underground primary service originating at a utility pole on Cedar Street,
More informationNYC Department of Education
Asset: MORRISANIA SEC ED COMPLEX-X, 1365 FULTON AVENUE, New York, 10456 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-11-03 8:53 AM 2017-11-03 5:47 PM Asset Data Are there fuel
More informationTighe&Bond. Groton Heights School Mechanical Evaluation. 1 Existing Conditions. 1.1 Water Service Entrance
Groton Heights School Mechanical Evaluation TO: FROM: Amy Vaillancourt, Project Manager Harley Langford, Project Manger Jason Curtis, P.E. DATE: February 24, 2016; Revised May 31, 2016 On Monday, December
More informationOld Jail HVAC Replacement Feasibility Report
Old Jail HVAC Replacement Feasibility Report Madera, CA Prepared by Kitchell for the County of Madera, California Job No. 6168A3 Executive Summary On October 21, 2016, Kitchell conducted a Feasibility
More informationNYC Department of Education
Asset: LIBERTY HS - MANHATTAN, 250 WEST 18 STREET, New York, 10011 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-01-29 11:32 AM 2018-02-01 10:16 AM Asset Data Are there fuel tanks?
More information