1 Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual observation only; they do not test operability or perform destructive testing inside walls, ceilings or floors. The rankings below reflect the assessors visual evaluations of the property condition as of that date. For additional information, you may review the detailed assessment report linked on this school s profile page and visit the Facilities Standards webpage under CPS Policies and Guidelines at Condition ings and Descriptions 7: The item/system is new or in good condition and no work is required. 6: The item/system requires general cleaning and/or routine maintenance. 5: The item/system requires repairs and has not reached the end of its serviceable life. 4: The item/system has reached its expected useful life, but is still fully operational. CPS will maintain until replacement occurs. : The item/system has surpassed its expected useful life and has limited operability. CPS will maintain until replacement occurs. : The item/system has surpassed its expected useful life and has low operability. CPS will maintain until replacement occurs. : The item s/system s failure leads to an immediate life safety condition for occupants or to the potential of an uninhabitable facility.¹ Definitions means, for each item, the total number (or amount) of that item that exists and was evaluated. Within that, different portions may have different rankings. means the generally accepted standard unit of measure for each item. Some items, like doors, are measured individually and use the unit of measurement EA for each. Other items, like chimneys, are measured in terms of linear feet ( LF ). Still other items, like flooring, are generally measured in square feet ( SF ). means a basic estimate for each item needing some level of repair or replacement. does not include all expenses that would be necessary to complete a repair or replacement project. This is because, depending on the item and on the overall scope of a construction project, repair/replacement projects can include additional costs such as destructive testing, environmental needs, discovered conditions, and additional work triggered by building codes. For the same reason, the Campus Need listed at the end of this report reflects only a portion of what it would actually cost to repair/replace all of the listed features. Campus Need also does not reflect features that do not yet exist at a particular facility, such as: programmatic improvements, school-wide ADA compliance, air conditioning, space reconfiguration, or construction to alleviate overcrowding; these are viewed as separate capital needs. EXTERIOR CANOPY Metal Canopy CHIMNEY Metal Flue GRE SF $4,356 $4, LF $2,252 $2,252 Assessment Date: 4/10/2013 Page 1 of 16
2 DOORS Exterior FRP Door Exterior Steel Door GRE GRE EA $12,807 6 EA $1,652 $14,459 ENTRANCE Concrete Exterior Stairs Concrete Ramp Entrance Controls - Audio and Video Ramp Handrails Stair Handrails GRE GRE GRE LF $2, LF $4, LF 19 LF $6,757 FOUNDATION Concrete Foundation GRE 7 1,695 1,695 LF LIGHTING Exterior Lights - Wall Mounted LINTELS Lintels - Steel GRE GRE EA $7,722 $7, LF $28,276 $28,276 Assessment Date: 4/10/2013 Page 2 of 16
3 PARAPET Coping - Stone Parapet 16" to 30" Height LF 103 LF $21,387 $21,387 ROOF SYSTEM Exterior Downspouts Interior Downspouts Metal Roof Modified Bitumen Roof Roof Structure: Steel/Metal Deck/Concrete Topping GRE ,229 GRE 6 28,391 7 GRE 7 46, LF $ LF 18,229 SF $137,636 28,391 SF $200,966 46,620 SF $339,420 SUPERSTRUCTURE Concrete Slab on Grade Steel GRE 7 10,687 GRE 7 15,191 GRE 7 17,704 10,687 SF 15,191 SF 17,704 SF WALLS Brick GRE 6 24, ,981 SF $160,488 $160,488 WINDOWS Window - Guards perforated Windows - Sash Aluminum Double-pane Windows - Sash Lexan/ Glass Double-pane ,631,649 2,599 YEL ,642 SF $841 4,248 SF $79, SF $9,672 Assessment Date: 4/10/2013 Page 3 of 16
4 $89,760 EXTERIOR $674,876 ELECTRICAL EMERGENCY SYSTEM Automatic Transfer switch Emergency A/C power - Corridors and Stairs Emergency A/C power - Gym and Lunch rooms Emergency A/C power - Students Toilets Emergency Battery Packs - Corridors and Stairs Emergency Battery Packs - Lunchroom and Gym Emergency Battery Packs - Toilets Exit Signs - Corridors and Stairs Exit Signs - Lunchroom - Gym - multipurpose rooms Independent Electrical Service for emergency power Public Announcement System Security System - CCTV Security System - Intrusion detection GRE GRE 6 2,790 4,246 GRE 7 3,324, GRE GRE 6 6 GRE BLU ORA 2 3 GRE 6 2 GRE 6 43,582 BLU 5 43,582 GRE 6 25,878 $2,860 7,036 SF $1,197 3,324 SF 1,879 SF $ EA $536 6 EA $ EA $ EA $5,577 3 EA $2,789 $2,860 43,582 SF $26,175 43,582 SF $124,645 25,878 SF $24,054 $192,255 MAIN SERVICE Main Electrical service - Live Front A and below 120/208/3PH Main Electrical service - Live Front A 120/208/3PH Main Electrical service - Live Front A 120/208/3PH Main Electrical service 1000 A and below 120/208/3PH POWER DISTRIBUTION Lighting and power panels 4 YEL 4 1 YEL 4 1 YEL $96,096 $130,416 $161,304 $6,435 $394, EA $22,594 Assessment Date: 4/10/2013 Page 4 of 16
5 Main distribution panels amp Main distribution panels above 600 amp ELECTRICAL FIRE PROTECTION FIRE ALARM Fire Alarm Strobe Lights Fire Alarm System SPRINKLER SYSTEM GRE 6 43,582 GRE 6 32, EA $16,445 $2,145 $41,184 $627,690 43,582 SF $15,581 32,895 SF $39,984 $55,564 Sprinkler Heads Wet Sprinkler System FIRE PROTECTION GRE 7 15,191 GRE 7 15,191 15,191 SF 15,191 SF $55,564 MECHANICAL AIR CONDITIONING Chillers - Air Cooled - Rotary/Screw type - Ground Mounted 100 to 200 tons Condensing - Roof Mounted less than 5 tons Window A/C GRE 7 1 GRE 7 1 $215 $215 AIR HANDLING SYSTEMS Air intake for all Air Handling s except built up AHU Fan Coil - Hot Water and Chilled Water GRE 7 6 $1,430 6 EA Assessment Date: 4/10/2013 Page 5 of 16
6 Make Up Air - Indoor Mounted - Hot Water less than 6000 cfm Return Duct Work - Sheet Metal - Exterior Vertical Shaft and Ducts Roof Top - Single Zone - Electric 21 to 30 tons BOILER SYSTEMS GRE YEL 4 1 $2, LF $47,190 $50,622 Boiler Assembly - Condensing Hot Water Boiler 1,001MBH-2,000 MBH Boiler Assembly - Non-Condensing Flexible Tube Hot Water Boiler 2,001MBH-3,000 MBH Boiler Auxiliary - Condensing Hot Water Boiler 1,001MBH-2,000 MBH Boiler Auxiliary Non-Condensing Hot Water Boiler 2,001MBH-3,000 MBH Chemical Pot Feeder - Hot Water Combustion Dampers Gas Boosters Glycol Feed System GRE 7 2 BLU 5 2 GRE 7 2 BLU BLU GRE $102,960 $55,770 $300 3 EA $6,149 $2,803 $167,982 HEATING DEVICES Cabinet Heaters With Hot Water Coils Fin Tube Hot Water Heater - Hot Water Wall Heater - Electric GRE GRE 7 8 GRE GRE EA $3,003 8 LF 3 EA $2, EA $5,863 MECHANICAL PLUMBING Piping - Hydronic Supply and Return - Steel or Galvanized Pumps - Dual Temperature Water 5 to 10 HP Pumps - Hot Water less than 5 HP GRE GRE 7 2 GRE LF $3,546 $2,860 $6,406 Assessment Date: 4/10/2013 Page 6 of 16
7 TEMPERATURE CONTROL Direct Digital Control (DDC) System Thermostats - Direct Digital Control (DDC) GRE 7 28,391 GRE ,391 SF 33 EA UNIT VENTILATION Ventilators - Hot Water and Chilled Water Ventilators - Hot Water and Self Contained Electric Cooling Ventilators - Self Contained Electric Heating and Cooling GRE ORA EA 1 $17,303 $17,160 $34,463 VENTILATION Exhaust Fan - Indoor Exhaust Fans - Roof Mounted 1,501 to 8,000 cfm Exhaust Fans - Roof Mounted 500 to 1,500 cfm Exhaust Fans - Roof mounted less than 500 CFM Type I Exhaust Hood - Kitchen or Culinary Arts Type II Exhaust Hood - Warming Kitchen MECHANICAL GRE GRE 7 1 ORA 2 1 GRE 7 1 $501 7 EA $858 $229 $26,884 $28,471 $294,022 PLUMBING HOT WATER Hot Water Heater - Gas 150, ,000 BTU/HR Hot Water Heater - Gas less than 150,000 BTU/HR GRE $3,575 $3,575 Assessment Date: 4/10/2013 Page 7 of 16
8 PIPING Domestic Piping Cold Water Horizontal lines Domestic Piping Hot Water Horizontal lines Domestic Piping Hot Water Return Lines Sanitary Piping Storm Piping Vent Piping PLUMBING ,191 28,391 5,191 28,391 GRE 7 10,687 GRE 6 28,391 15,191 BLU 5 28,391 GRE 6 28,391 15,191 43,582 SF $3,476 43,582 SF $3,041 10,687 SF 43,582 SF $17,458 28,391 SF $13,398 43,582 SF $10,150 $47,522 $51,097 INTERIOR ADMINISTRATIVE SUITES Ceiling - Lay-In Ceiling - Plaster/Drywall Flooring - Carpet Flooring - Tile Ceramic/Porcelain Flooring - Tile/Sheet Lighting - Lay-In Walls - Concrete Block Walls - Plaster/Drywall ,443 1,153 GRE 7 62 GRE GRE 6 62,944 GRE 7 36 GRE 6 4,532 1,140 GRE ,596 SF $3, SF 652 SF $ SF $158 1,944 SF $2, SF 5,672 SF $12, SF $1,347 $21,274 AUDITORIUM - DEDICATED Stage Platform GRE SF $1,550 $1,550 Assessment Date: 4/10/2013 Page 8 of 16
9 CORRIDOR Student Lockers DOORS GRE EA $13,585 $13,585 Interior Steel Doors incl hw Interior Wood Doors incl hw GRE GRE EA $6, EA $21,802 $28,031 DRINKING FOUNTAINS Double Fountain Single Fountain GRE 7 1 GRE EA $772 $772 GYMNASIUM / AUDITORIUM Ceiling - Exposed Flooring - Tile/Sheet Lighting - Metal Halide/Sodium Vapor Stage Curtain Walls - Concrete Block GRE 7 3,324 GRE 6 3,324 0 GRE 6 4 GRE 7 5,458 3,324 SF 3,324 SF $4, EA $1,788 4 EA $37,752 5,458 SF $44,293 KITCHEN Ceiling - Plaster/Drywall Flooring - Tile Quarry Lighting - Lay-In Wall - Concrete Block 4 5 6,294,294 5, ,294 SF $4,885 1,294 SF $4, SF $11 1,168 SF $3,340 Assessment Date: 4/10/2013 Page 9 of 16
10 $12,696 LIBRARY Casework Flooring Tile/ Sheet Lighting - Lay-In LOCKER/SHOWER ROOM Lockers LUNCHROOM Serving Line MDF/IDF ,644 GRE GRE LF $3,497 1,644 SF $2, SF $18 $5, EA $491 $ LF $1,115 $1,115 Finishes Ventilation and Cooling GRE SF $708 $1,401 $2,109 MECHANICAL/SERVICE ROOMS Boiler Room Janitor's Closet Mechanical/Service Rooms Storage Room Vaults GRE GRE 6 3 GRE 6 668,771 GRE SF $4,544 3 SF $ SF $3,152 1,771 SF $8, SF $425 $16,493 Assessment Date: 4/10/2013 Page 10 of 16
11 STAFF RESTROOM Accessories Ceiling - Lay-In Ceiling - Plaster/Drywall Floor Drain Flooring - Concrete Flooring - Tile Ceramic/Porcelain Flooring - Tile/Sheet Hand Dryer Lavatory Lighting - Lay-In Lighting - Pendant/ Surface Partitions Urinals Wall - Concrete Block Wall - Structural Glazed Tile Water Closet GRE 6 2,436 GRE 6 512,924 7 GRE 6 2 9,142, GRE GRE 7 12 GRE GRE GRE 6 5,641 GRE GRE ,436 SF $18, SF $1,098 1,924 SF $5,448 1 $601 1,142 SF $5,389 1,188 SF $3, SF $152 5 EA 19 EA $5, SF 18 SF $17 24 EA $3, EA $2,974 5,641 SF $16, SF $5, EA $11,898 $80,134 VOCATIONAL SHOP Work Sink INTERIOR ROOM CASEWORK GRE EA $1,931 $1,931 $230,339 Casework GRE LF $14,836 $14,836 Assessment Date: 4/10/2013 Page 11 of 16
12 CEILING Exposed Ceiling Lay-In/Drop GRE 7 3,264 GRE 6 5,200 17,662 3,264 SF 22,862 SF $11,154 $11,154 CHALK BOARD Chalk Board YEL LF $24,310 $24,310 CLASSROOM Laptop Charging Station GRE 7 2 CORRIDORS Concrete Block Drop/Lay-In Lay-In Pendant/Surface Plaster/Drywall Splined Stair Handrails Tile Ceramic/Porcelain Tile/Sheet Flooring ,614 GRE 6 5,276 GRE 6 2,666 7 GRE 7 1,760 GRE 6 260,440 GRE 7 24,231 GRE 6 5,805 12,614 SF $36,076 5,276 SF $11,317 2,666 EA $1,906 1,760 EA 260 SF $613 1,440 SF $3, LF 1,231 SF $3,133 5,805 SF $8,301 $64,436 CORRIDORS CEILING Plaster/Drywall GRE SF $906 Assessment Date: 4/10/2013 Page 12 of 16
13 $906 FLOOR Tile/Sheet LIBRARY_CEILING Drop/Lay-In LIBRARY_WALL Concrete Block LIGHTING GRE 6 26, , , ,119 SF $37,350 $37,350 1,644 SF $3,526 $3,526 1,530 SF $4,376 $4,376 Lay-In GRE EA $3,432 $3,432 MARKER BOARD Marker Board GRE LF $1,373 $1,373 STAIRS Asphalt GRE SF Assessment Date: 4/10/2013 Page 13 of 16
14 WALL Concrete Block Metal/Folding Panel Plaster/Drywall ROOM GRE 6 9,080 6,104 GRE ,146 15,184 SF $25, SF $1,307 15,146 SF $35,737 $63,013 $228,712 SITE CIVIL/DRAINAGE Catch Basin Site Manhole FENCING GRE 6 6 GRE EA $3,260 4 EA $2,917 $6,178 Chain Link Ornamental Iron , GRE 6 2,744 1,251 LF $15,046 2,744 LF $51,796 $66,841 LANDSCAPE Asphalt Play Area/Hardscape Benches Grass Hardscape - Concrete Parkway trees Planting Beds/ Areas Trash Receptacles GRE 6 9,106 6,081 GRE 7 5 GRE 6 57,826,926 GRE 6 54,772 GRE ,187 SF $25,783 5 EA 57,826 SF $23,154 1,926 SF $3, EA $15,444 1,772 SF $68,016 Assessment Date: 4/10/2013 Page 14 of 16
15 MODULAR Classroom Modular Building BLU Classroom Modular Building YEL 4 1 $1,358,500 $1,358,500 PARKING LOT Asphalt Concrete Concrete Curbs Trash Enclosure 4 5 6,396 8,957 7 GRE 7 1,192 GRE GRE ,353 SF $11,638 1,192 SF 278 LF $1, SF $7,465 $20,780 PLAYGROUND Playground Equipment - School Age 5-12 Playground Surfacing - Poured Surface GRE 7 2 GRE 6 6,350 6,350 SF $16,799 $16,799 SIDEWALKS Internal Walks Perimeter Sidewalks GRE , LF $3,690 12,235 SF $23,095 $26,785 SIGNAGE Flag Pole SITE $1,563,899 Assessment Date: 4/10/2013 Page 15 of 16
16 Campus Need ² ³ $3,726,200 ¹ It is very rare for an assessor to find a feature in this condition. If they do, they are required to report it immediately to CPS, and CPS addresses it immediately. Thus, no features will be ranked 1 in summary reports; by the time the report is compiled, they have been resolved. ² As stated above, Assessed Campus Need does not include the addition of features not already in a particular facility, such as programmatic improvements, school-wide ADA compliance, air conditioning, space reconfiguration or construction to alleviate overcrowding; these items are treated as separate capital needs. The Assessed Campus Need includes current deficiencies and is based on current unit cost estimates; it does not reflect a complete project cost. ³ The overall condition of different items can change after an assessment date due to many variables, including newly occurring deficiencies, renovation or repairs and cost changes. These dollar figures in this report are estimates only and are based solely on the data that was collected as of the assessment date in the footer below. Assessment Date: 4/10/2013 Page 16 of 16
Agustin Lara Elementary Academy
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationJosefa Ortiz De Dominguez Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationWashington Irving Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationJoseph Brennemann Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationGenevieve Melody Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationEdward Jenner Elementary Academy of the Arts
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationCharles W Earle Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationCalmeca Academy of Fine Arts and Dual Language
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationOscar DePriest Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationJohn Palmer Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationAlessandro Volta Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationSidney Sawyer Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationFrancis M McKay Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationDeWitt Clinton Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationGeorge B Swift Elementary Specialty School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationMUKWONAGO AREA SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY
ARCHITECTURE ROLLING HILLS ELEMENTARY SCHOOL Rolling Hills Elementary was built in 1999 and is the newest addition to the Mukwonago Area School District. The building contains approximately 64,900 gross
More informationVOTER BOND REFERENDUM 2018 SUMMARY OF WORK PROPOSED
Ashton Elementary School 1 Masonry Repair $ 42,781.50 2 Replace HVAC $ 375,000.00 3 Replace SAT @ Various Locations $ 92,364.00 3 Recoat & Resurface Exterior Paved Play Area $ 135,978.30 3 Various Technological
More informationTighe&Bond. Groton Heights School Mechanical Evaluation. 1 Existing Conditions. 1.1 Water Service Entrance
Groton Heights School Mechanical Evaluation TO: FROM: Amy Vaillancourt, Project Manager Harley Langford, Project Manger Jason Curtis, P.E. DATE: February 24, 2016; Revised May 31, 2016 On Monday, December
More informationSITE SYSTEMS: FANNIE MAE EXPECTED USEFUL LIFE TABLES (FMEUL)
SITE SYSTEMS: FANNIE MAE EXPECTED USEFUL LIFE TABLES (FMEUL) Basketball Courts 15 25 Built Improvements Playgrounds, Site Furniture, etc. 20 20 Catch Basin 40 40 Cold Water Lines 40 40 Compactors DHW Supply
More information3. 21st Century Learning A. Districtwide Flexible Learning - Allowance for Flexible Furniture $600,000 Subtotal $600,000
1. Safety and Security A. Additional Cameras District Wide $382,000 B. Interior Locks Upgrades Allowance $300,000 C. Tilden Entrance Upgrades D. Door and Glass Improvements Allowance $500,000 E. Alert
More informationBriar Crest Elementary
Promises Kept This document includes partial lists of major projects completed at Pattonville Schools since 1986 as part of past bond issues approved by the Pattonville community. Briar Crest Elementary
More informationPLAN REVIEW SUBMITTAL GUIDE
PLAN REVIEW SUBMITTAL GUIDE Plans, specifications and other construction documentation for the initial plan review should be as complete as possible at the time of submittal. Use this convenient guide
More informationMechanical Inspection Plumbing
0811 Fixtures Sinks, drinking fountains, water closets, showers, etc. Classroom Sinks. Classroom sinks (19) are enameled cast iron self rimming side ledge with gooseneck faucet trim with index handles,
More informationChariho Regional School District Five-Year Capital Facilities Improvement Plan (2/10/15)
Chariho Regional School District Five-Year Capital Facilities Improvement Plan (2/10/15) School/Department FY 16 FY 17 FY18 FY19 FY20 Chariho Regional High School FY 16 FY 17 FY18 FY19 FY20 *Repair Bleachers
More informationNYC Department of Education
Asset: P.S. 128 - MANHATTAN, 560 WEST 169 STREET, New York, 10032 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-12-07 8:50 AM 2018-06-14 1:16 PM Asset Data Are there fuel tanks?
More informationCAPITAL OUTLAY REQUEST - IDENTIFIED AND EMERGING PROJECTS - RANKED 3-Jun-14
2014-2015 CAPITAL OUTLAY REQUEST - IDENTIFIED AND EMERGING PROJECTS - RANKED 3-Jun-14 School Item Amount a. Classroom A/R (Increase CR capacity to 804, add l Resource and tutoring spaces needed. Teacher
More informationGARCIA GALUSKA DESOUSA Consulting Engineers
L#56566/Page 1/May 23, 2017 HVAC Heating Plant The original Town Hall building and Addition building are primarily heated by a gas fired hot water plant that is located in the basement. The boiler plant
More informationNYC Department of Education
Asset: LIBERTY HS - MANHATTAN, 250 WEST 18 STREET, New York, 10011 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-01-29 11:32 AM 2018-02-01 10:16 AM Asset Data Are there fuel tanks?
More informationNYC Department of Education
Asset: P.S. 198 - BRONX, 1180 TINTON AVENUE, New York, 10456 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-01-24 8:14 AM 2018-01-24 9:32 PM Asset Data Are there fuel tanks? Total
More informationMUKWONAGO SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY
MUKWONAGO SCHOOL DISTRICT ARCHITECTURE PARK VIEW MIDDLE SCHOOL The original school building was dedicated in 1954 as the High School, with an addition in 1959, a library addition in 1970, and an addition/renovation
More informationNYC Department of Education
Asset: P.S./I.S. 194 - BRONX, 2365 WATERBURY AVENUE, New York, 10462 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-01-24 8:34 AM 2018-02-01 10:02 AM Asset Data Are there fuel tanks?
More information2014 Bond Project Guide
2014 Bond Project Guide Bush Elementary School Page 1 Instructional Technology Computers, Projectors, Mobile Carts, Document Cameras and Printers Wireless Connectivity New Construction New Tech Center
More informationNYC Department of Education
Asset: P.S. 86 ANNEX - BRONX, 124 EAMES PLACE, New York, 10468 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-04-05 1:03 PM 2018-04-27 1:35 PM Asset Data Are there fuel tanks? Total
More informationMARY CRAPO CENTER Miller Road, Swartz Creek, Michigan
MARY CRAPO CENTER 8197 Miller Road, Swartz Creek, Michigan MARY CRAPO CENTER 8197 Miller Road, Swartz Creek General Information: - Instructional, Child Care Development Center (West Wing) o (2) Infant/Toddler
More informationFacility Condition Assessment Summary Report. British Columbia Institute of Technology NE6 - Plumbing and Pipefit Building
Facility Condition Assessment Summary Report British Columbia Institute of Technology NE6 - Plumbing and Pipefit Building Submitted by: VFA Canada Corp. Burnaby Centre 4211 Kingsway Burnaby, BC V5H 1Z6
More informationNYC Department of Education
Asset: P.S. 146 - BRONX, 968 CAULDWELL AVENUE, New York, 10456 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-12-01 8:57 AM 2018-05-31 2:59 PM Asset Data Are there fuel tanks? Total
More informationSECTION HVAC TABLE OF CONTENTS PART 1 - SYSTEM DESCRIPTION / OUTLINE SPECIFICATIONS FILED SUB BID PROJECT OVERVIEW...
SECTION 230001 TABLE OF CONTENTS SECTION 230001 PART 1 - SYSTEM DESCRIPTION / OUTLINE SPECIFICATIONS... 1 1.00 FILED SUB BID... 1 1.01 PROJECT OVERVIEW... 2 1.02 DESIGN CRITERIA... 4 1.03 CODE ISSUES...
More informationNYC Department of Education
Asset: MID MAN ADULT LRNG CTR (81) - M, 212 W 120TH ST, New York, 10027 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-01-17 8:16 AM 2018-01-17 8:17 PM Asset Data Are there fuel
More informationNYC Department of Education
Asset: P.S. 111 - MANHATTAN, 440 WEST 53 STREET, New York, 10019 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-03-16 8:47 AM 2018-03-21 8:02 AM Asset Data Are there fuel tanks?
More informationNYC Department of Education
Asset: P.S. 22 - STATEN ISLAND, 1860 FOREST AVENUE, New York, 10303 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-12-08 8:51 AM 2017-12-18 4:14 PM Asset Data Are there fuel tanks?
More informationNYC Department of Education
Asset: P.S. 69 - STATEN ISLAND, 144 KEATING PLACE, New York, 10314 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-01-19 8:39 AM 2018-01-23 4:33 PM Asset Data Are there fuel tanks?
More informationMaster Facility Planning Update School Board Meeting May 26, 2016
Master Facility Planning Update School Board Meeting May 26, 2016 Master Facilities Committee Overview Reflection of Committee Work Review of District Wide Facility Issues Identified District Wide Facility
More informationDOCUMENT TABLE OF CONTENTS
DOCUMENT 00003 June 16, 2005 TABLE OF CONTENTS DOCUMENT NO. INTRODUCTORY INFORMATION DOCUMENT 00003 TABLE OF CONTENTS DIVISION 1 GENERAL REQUIREMENTS SECTION 01011 SECTION 01025 SSP21.1-1 SECTION 01026
More informationHOLUM EDUCATION CENTER. Architectural. January 13, 2014 DeForest Area School District
HOLUM EDUCATION CENTER Architectural The existing building has approximately 41,823 square feet and sets on a lot about 4.14 acres in size. Parking lots are located along the east and west sides of the
More informationCook - Wissahickon Elementary School
Cook - Wissahickon Elementary School 201 E. Salaignac St., Philadelphia, PA 19128 HVAC Replacement Project Scope Determination Report May 10, 2018 Prepared by: G.P. Lamina, Jr., P.E., MBA School District
More informationNYC Department of Education
Asset: P.S. 4 - MANHATTAN, 500 WEST 160TH STREET, New York, 10032 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-12-08 8:29 AM 2017-12-08 3:44 PM Asset Data Are there fuel tanks?
More information2 Main Office Building BLDG-955A Building Purpose Building Area Administration offices. Training room 7,610 SF Inspection Date August 16, 2016 Inspect
1 Site Summary Address 7200 Bluff Springs Road Austin, TX 78744 Number of Permanent Campus Facilities 2 Original Year of Construction 2014 Total Campus Building Area (combined) 25,314 SF Introduction The
More informationAshland School District Facility & Capacity Assessment Report 2005
Ashland School District Facility & Capacity Assessment Report 2005 Briscoe Elementary School (Closed Facility) Address: 265 N Main Street Area: 33,980 square feet Buildings: Original Building 1948 Music
More informationNYC Department of Education
Asset: P.S. 92 - BROOKLYN, 601 PARKSIDE AVENUE, New York, 11226 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-11-13 8:31 AM 2017-11-27 11:43 AM Asset Data Are there fuel tanks?
More informationNYC Department of Education
Asset: J. K. ONASSIS HS FOR INT CAREERS-M, 120 WEST 46 STREET, New York, 10036 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-12-11 11:37 AM 2017-12-26 12:18 PM Asset Data Are there
More informationNYC Department of Education
Asset: P.S. 188 - MANHATTAN, 442 EAST HOUSTON STREET, New York, 10002 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-03-08 8:52 AM 2018-06-13 5:06 PM Asset Data Are there fuel tanks?
More informationRECAPP Facility Evaluation Report
RECAPP Facility Evaluation Report Calgary School District #19 John G Diefenbaker High School B2686A Calgary Report run on: January 1, 28 9:31 AM Building Name: Address: Location: Building Id: Gross Area
More informationFlorence High School / Middle School Page 1 of 3 Florence, WI
Florence High School / Middle School Page 1 of 3 Florence, WI Plumbing Systems Review: The following report is the result of a site visit by Tim Kehoe of Muermann Engineering, LLC that occurred on October
More informationState College Area School District High School South Building EXISTING CONDITIONS ASSESSMENT
State College Area School District High School South Building Prepared by CenterPoint Engineering 08 February 2013 FACILITY ASSESSMENT SUMMARY PHYSICAL PLANT General HVAC This report is a snapshot of the
More informationNYC Department of Education
Asset: MORRISANIA SEC ED COMPLEX-X, 1365 FULTON AVENUE, New York, 10456 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-11-03 8:53 AM 2017-11-03 5:47 PM Asset Data Are there fuel
More informationNYC Department of Education
Asset: P.S. 104 - BROOKLYN, 9115 5TH AVENUE, New York, 11209 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-02-21 8:55 AM 2018-02-21 1:09 PM Asset Data Are there fuel tanks? Total
More informationNYC Department of Education
Asset: W.E.B. DUBOIS HS - BROOKLYN, 402 EASTERN PARKWAY, New York, 11225 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-12-04 1:02 PM 2017-12-27 4:16 PM Asset Data Are there fuel
More informationNYC Department of Education
Asset: P.S. 7 - MANHATTAN, 160 EAST 120 STREET, New York, 10035 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-03-02 8:44 AM 2018-03-12 10:45 AM Asset Data Are there fuel tanks?
More informationMaster Project List Report
Blue Hills Elementary School 01-8215 Site Utilities Replacement $52,835 01-8502 Modernization $3,135,933 01-8525 Exterior Painting $181,478 01-8552 Kindergarden Fencing $13,180 Install new backflow preventer.
More informationNYC Department of Education Building Condition Assessment Survey :49AM :00PM
School: InspectionId Asset Data Inspection Type Building Assessment Survey 05-06 P.S. 70 - BROOKLYN, 4 EMERSON PLACE, BROOKLYN, NY, 05 Time In Last Edited 476 MECHANICAL 05-- 08:49AM 05-- 03:00PM Have
More informationDEERFIELD SCHOOL DISTRICT REFERENDUM Committed to Excellence and Equity in Educating Our Students
DEERFIELD SCHOOL DISTRICT REFERENDUM Committed to Excellence and Equity in Educating Our Students FACILITY NEEDS THE CHALLENGE Deerfield Middle School/High School building has served the community for
More informationNYC Department of Education
Asset: P.S. 73 - BRONX, 1020 ANDERSON AVENUE, New York, 10452 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-11-16 8:29 AM 2017-11-28 10:59 AM Asset Data Are there fuel tanks? Total
More informationAppendix B. Facilities Assessment Report
Mile Lane Army Reserve Center Redevelopment Plan September 2008 Appendix B Facilities Assessment Report RKG Associates, Inc. Mile Lane Army Reserve Base Middletown, CT MEP System Evaluation For RKG Associates
More information1354 CHECKLIST for Project Closeout
1354 CHECKLIST for Project Closeout PROJECT NUMBER: BUILDING NUMBER: DESCRIPTION OF PROJECT: Describe description of work; i.e., New Construction, Addition, Modification, Renovation, etc DRAWING NUMBER
More informationNYC Department of Education
Asset: AUTOMOTIVE TRADES VOC HS - K, 50 BEDFORD AVENUE, New York, 11222 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-05-01 8:09 AM 2018-05-10 2:18 PM Asset Data Are there fuel
More informationRECAPP Facility Evaluation Report
RECAPP Facility Evaluation Report Calgary RCSSD #1 Ecole St. Matthew Elementary / French Immersion Jr. High School B2614A Calgary Report run on: March 25, 2010 10:11 AM Building Name: Address: Location:
More informationPLATTEVILLE MIDDLE SCHOOL
Architectural The building has aluminum clad wood awning windows in combination with aluminum fixed glass units. They appear to be exterior glazed with insulated glazing. See photo 2. Platteville Middle
More informationNYC Department of Education
Mechanical Inspection Asset: P.S. 1 - MANHATTAN, 8 HENRY STREET, New York, 10038 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-09-28 8:39 AM 2017-10-12 5:28 PM Asset Data Are there
More informationIchabod Crane Central School District 2018 Capital Project Preliminary Estimate
Health & Safety 1,399,000 Academics & Program 17,140,800 Physical Education & Athletics 5,922,000 Building Infrastructure 3,103,800 Site Infrastructure 1,049,600 TOTAL SCOPE OF WORK 28,615,200 PROPOSED
More informationTHIS IS A DESIGN GUIDE NOT A SPECIFICATION. Montgomery County Public Schools Facilities Guide DIVISION 15 MECHANICAL
SECTION 15100 PART 1 GENERAL THIS IS A DESIGN GUIDE NOT A SPECIFICATION Montgomery County Public Schools Facilities Guide DIVISION 15 MECHANICAL HVAC SYSTEMS APPLICATIONS 1.1 SCOPE: The intent of this
More informationNYC Department of Education
Asset: A. PHILLIP RANDOLPH HS - MANHATTAN, 443 WEST 135 STREET, New York, 10031 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-02-02 8:11 AM 2018-06-14 1:21 PM Asset Data Are there
More informationNYC Department of Education
Asset: I.S. 131 - BRONX, 885 BOLTON AVENUE, New York, 10473 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-10-17 8:54 AM 2017-12-05 5:41 PM Asset Data Are there fuel tanks? Total
More informationNYC Department of Education
Asset: P.S. 29 - STATEN ISLAND, 1581 VICTORY BLVD, New York, 10314 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-01-10 11:28 AM 2018-01-17 11:37 AM Asset Data Are there fuel tanks?
More informationNYC Department of Education
Asset: I.S. 45 - BRONX, 2502 LORILLARD PLACE, New York, 10458 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-12-05 9:14 AM 2017-12-20 11:42 AM Asset Data Are there fuel tanks? Total
More informationGarfield Elementary School Feasibility Study for New Library Building Project Number A C
Larry Teixeira Selma Unified School District 3036 Thompson Avenue Selma, CA 93662 Subject: Feasibility Study for New Library Building Project Number A 12-8581.00 C Dear Mr. Teixeira: At your request, we
More informationExisting Conditions Assessment November 14, 2006 NORTH MIDDLESEX REGIONAL HIGH SCHOOL Townsend, MA L21366/ /Page 1
L21366/101 090 00.00/Page 1 HVAC EXECUTIVE SUMMARY The North Middlesex Regional High School has received average maintenance of the HVAC systems over its occupied years. Even with adequate maintenance,
More informationKerrville ISD has called for a bond election in the amount of $88,960,000 for November 6, 2018
Kerrville ISD has called for a bond election in the amount of $88,960,000 for November 6, 2018 WHAT IS A BOND ELECTION? Provide communities an opportunity to vote to give the Board of Trustees authority
More informationNYC Department of Education
Asset: P.S. 32 - BRONX, 690 EAST 183 STREET, New York, 10458 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-11-13 9:25 AM 2017-11-16 5:46 PM Asset Data Are there fuel tanks? Total
More informationNYC Department of Education
Asset: FORSYTH HS (AUXSVC-OLD 91) - M, 198 FORSYTH STREET, New York, 10002 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-09-28 8:07 AM 2018-03-20 4:47 PM Asset Data Are there fuel
More informationNew High School Concept
Approved Bond Projects for Alamance-Burlington Schools In November 2018, Alamance County citizens approved a $150 million bond project proposal. Bond funds will pay to construct a new high school and provide
More informationSCHEDULE OF FEES. Penalty Fees. Building Fee Schedule FEE
SCHEDULE OF S Penalty Fees. The fee for construction work performed before securing permit(s), where required, may be charged a fee of TWO TIMES THE COST OF THE PERMIT (S). Building Fee Schedule Residential
More informationNYC Department of Education
Asset: CLINTON AF - BRONX, 100 W. MOSHOLU PKWY S, New York, 10468 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-11-20 8:24 AM 2017-12-31 2:04 PM Asset Data Are there fuel tanks?
More informationEvaluation. ems. Prepared By: Martha. a s Vineyard. Box P.O. Box June 2015
Martha a s Vineyard Regional High School Vineyard Haven, MA 2 2015 HVAC Syste ems Evaluation Prepared For: Martha s Vineyard Regional School District Box 1385 Oaks Bluff, MA 02557 Prepared By: BLW Engineers,
More informationNYC Department of Education
Asset: P.S. 194 - MANHATTAN, 244 WEST 144 STREET, New York, 10030 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-12-12 10:48 AM 2018-01-29 10:54 AM Asset Data Are there fuel tanks?
More information$ Each additional variance per petition. $ All Other Zoning Districts: One variance per petition
2015 SCHEDULE COMMUNITY DEVELOPMENT DEPT. ENGINEERING PLAN REVIEW Single Family New Construction All Other Plan Reviews Minimum Engineering Fee Planned Unit Development - PUD: Step #1: Step #2: See Site
More informationNYC Department of Education
Asset: ACHIEVEMENT FIRST ENDEAVOR CHARTER SCHOOL- BROOKLYN, 510 WAVERLY AVENUE, New York, 11238 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-03-14 8:42 AM 2018-03-23 10:17 AM
More informationNYC Department of Education
Asset: UNIVERSITY NEIGHBORHOOD - M, 200 MONROE STREET, New York, 10002 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-02-05 11:56 AM 2018-03-02 7:14 PM Asset Data Are there fuel
More informationNYC Department of Education
Asset: P.S. 163 - BRONX, 2075 WEBSTER AVENUE, New York, 10457 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-03-22 8:33 AM 2018-03-22 3:13 PM Asset Data Are there fuel tanks? Total
More informationNYC Department of Education
Asset: P.S. 199 ANNEX (@ ST. TERESA'S) - QUEENS, 50-15 44TH STREET, New York, 11377 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-04-18 11:39 AM 2018-05-14 12:27 PM Asset Data
More informationMechanical System Description
1. Building Description: Mechanical System Description The building is a Type-1B construction, 9-levels, non-high rise building with 67 affordable family housing units. The first level of the structure
More informationFORT ERIE SECONDARY SCHOOL FACILITY INFORMATION. Lake Erie Corridor Secondary Schools Accommodation Review
FORT ERIE SECONDARY SCHOOL FACILITY INFORMATION Lake Erie Corridor Secondary Schools Accommodation Review November 2012 LAKE ERIE CORRIDOR SECONDARY SCHOOLS ACCOMMODATION REVIEW Fort Erie Secondary School
More informationMOUNT PLEASANT MIDDLE SCHOOL HVAC. M-01 Heating Plant: M-02 Heating & Ventilating Systems: Livingston School District Mount Pleasant Middle School
MOUNT PLEASANT MIDDLE SCHOOL HVAC M-01 Heating Plant: The existing boilers have recently been upgraded. (3) steam boilers (8660 mbh each) manufactured by Weil- McLain have been installed. Newer hot water
More informationNYC Department of Education
Asset: PRE-K CENTER @ 7401 FORT HAMILTON PARKWAY - BROOKLYN, 7401 FORT HAMILTON PARKWAY, New York, 11228 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-11-27 11:12 AM 2017-11-27
More informationRECAPP Facility Evaluation Report
RECAPP Facility Evaluation Report Calgary School District #19 Queen Elizabeth Junior / Senior High School B2745A Calgary Report run on: March, 2010 10:02 AM Building Name: Address: Location: Building Id:
More informationNYC Department of Education
Asset: P.S. 161 - MANHATTAN, 499 WEST 133 STREET, New York, 10027 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-03-15 8:26 AM 2018-06-08 1:37 PM Asset Data Are there fuel tanks?
More informationMID MICHIGAN COMMUNITY COLLEGE HARRISON CAMPUS Harrison, Michigan 2015 MASTER PLAN
MID MICHIGAN COMMUNITY COLLEGE HARRISON CAMPUS Harrison, Michigan 2015 MASTER PLAN September 30, 2015 PBA Project No. 2015.0140.00 PETER BASSO ASSOCIATES INC. CONSULTING ENGINEERS 5145 LIVERNOIS ROAD,
More informationForest Hills Facilities Plan
Forest Hills Facilities Plan Extensive updates to 8 of our 9 schools Replace Wilson Elementary Enhance learning environments across the district Build additional classrooms to accommodate gradual implementation
More informationNYC Department of Education
Asset: P.S. 160 - BROOKLYN, 5105 FORT HAMILTON PARKWAY, New York, 11219 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-04-03 8:01 AM 2018-05-18 1:45 PM Asset Data Are there fuel
More informationNYC Department of Education
Asset: P.S. 19 - STATEN ISLAND, 780 POST AVENUE, New York, 10310 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2017-10-26 8:58 AM 2017-11-14 1:37 PM Asset Data Are there fuel tanks?
More informationMadeira City Schools Madeira, Ohio. HVAC Assessment. December 2011 (Revised February 2012)
Madeira City Schools Madeira, Ohio HVAC Assessment December 2011 (Revised February 2012) Prepared by: CMTA Engineering Consultants, Inc. 10411 Meeting Street Prospect, KY 40059 www.cmtaegrs.com (502) 326-3085
More information