1 Construction Projects Report Week of September 17 23, 2018 For general inquiries and questions, please contact the Project Management Office at (940) Street/Intersection From To CURRENT PROJECTS Ave. A Maple Eagle 3/19/18 9/30/18 Ave. C Hickory Mulberry 9/24/18 1/2/19 Bonnie Brae St. Roselawn S. Bonnie Brae St. Willowwood Eagle Dr. Edwards Rd. East of Carroll Camino Real Trl. North of Vintage FM 1515/ Airport Road 7/1/2017 7/1/2019 9/10/2018 9/21/2018 Elm 9/17/18 10/5/18 Swisher Rd. 6/4/18 9/28/18 Emery St. Alice Coit 6/25/18 10/12/18 Fulton St. Oak University 6/7/18 11/16/18 Jim Christal Rd. Western Blvd Scripture 7/3/18 10/1/18 Joyce Ln. N. Elm Gardenview 9/5/18 10/26/18 Mayhill Rd. US 380 Edwards 9/1/17 2/1/20 Mistywood Ln. Woodhaven Jamestown 9/13/18 11/25/18 See Yellow Highlighted for Major Closures UNT 2018 Residence Hall Project (Both SB Lanes Closed) UNT Monument Wall (Phase 1) Street Resurfacing Sanitary Sewer Construction Street Resurfacing Utility Line Construction Wastewater Main Reconstruction Engineering Public Works Inspections Coordinate with UNT (940) Engineering 6/14/18 Engineering 9/5/18 UNT, DISD, and DCTA New Project Intersects with Hickory Phase III Project Engineering 9/10/18 New Project Streets 5/17/2018, 9/10 HOA (940) Extended Completion Date Streets 6/11/2018, 9/10 Door Hangers (940) Water 6/5/18 (940) Water/WW (940) Streets 8/21/18 (940) Engineering 1/3/18, 1/24/18 Door Hangers Wastewater 8/23/18 (940) Page 1 of 5
2 Myrtle St. Eagle 200' North 9/4/18 5/1/19 Prominence Pkwy. Mayhill Atlanta 1/31/18 9/28/18 Riney Rd. N. Elm Solana 9/29/17 10/12/18 Shady Oaks Dr. Woodrow Loop 288 S. 8/27/18 9/17/18 Shadow Trl. Plum Hollow Windbrook 8/6/18 10/19/18 Eagle Drainage Improvements Water and Wastewater Crossing Road Removal and Replacement Full Depth Base Repairs (East Bound Lane Closures) Engineering 8/21/18 DCTA Engineering 1/24/18 Door Hangers Engineering Yes Electronic Signs Extended Completion Date Streets Businesses affected electronic (940) Streets 8/2/18 (940) Spencer Rd. Mayhill Lowe's Driveway 4/2/18 11/28/18 Water, Drainage, Road Construction Water 3/16/2018, 9/14 departments affected Extended Completion Date From 9/28/18 11/28/18 Sun Valley Dr. Stuart Dead End West 5/14/18 10/12/18 Thomas St. Oak Scripture 9/3/18 11/2/18 Streets 5/1/2018, 9/10 Door Hangers (940) Water 8/1/18 (940) Thomas St. TBD TBD Streets Construction Valley View Rd. Kings Row Sun Valley 5/14/18 9/28/18 Wayne St. Boyd Mozingo 8/29/18 11/1/18 Welch St. Mulberry Chestnut 9/17/18 9/28/18 Welch St. Mulberry Chestnut 4/11/18 9/24/18 Wastewater Reconstruction Inlet Improvements, ADA ramp installation (Northbound Temporary Lane Closures) UNT 2018 CVAD Project Drive approach/sidewalk (Southbound Temporary Lane Closures) Streets 5/1/2018, 9/10 Door Hangers (940) Wastewater 8/20/18 (940) Drainage Communicated with UNT, DCTA Engineering 3/19/18 3/30/2018, 9/12 Extended Completion Date From 9/10/18 9/28/18 (940) New Project Page 2 of 5
3 COMPLETED PROJECTS Amistad Ln. New Ballinger Tawakoni 8/27/18 9/10/18 Austin St. Sawyer E. Third 9/10/2018 9/14/2018 Bay Meadow Dr. Prescott Downs Emerson Ln. Nottingham Fairmont Park 8/27/18 9/10/18 East Emerson 150' 7/25/18 9/12/18 Highland Park Rd. Laurel Wisteria 7/25/18 8/30/18 Hickory St. North Texas Blvd. Ave C 5/21/18 9/14/18 Holiday Park Manhattan Kings Row 11/10/17 12/1/18 Hollyhill Ln. Longridge Pennsylvania 7/9/18 9/7/18 Laurel St. Highland Park Wisteria 7/25/18 8/30/18 Malone St. Scripture W. University 7/9/18 8/24/18 Nottingham Dr. 100' N Nottingham intersection 150'East Emerson 7/25/18 9/7/18 Meandering Creek Dr. Education John Pain 9/3/18 9/17/18 Oakland St. Sawyer E. 3rd 8/20/18 8/26/18 Old North Rd. University Mingo 8/27/18 9/7/18 Pine Hills Ln. Purbeck Alderbrook 8/20/18 9/3/18 Wastewater (Road and Lane Closure) (Temporary Road Closures) Wastewater Main Construction Phase II (Temporary Street Closures) Wastewater Main Reconstruction Conduit Installation Turn Lane Installation Streets 7/15/18 (940) New Completion Engineering 8/27/18 New Completion Streets 8/17/18 (940) New Completion Wastewater 7/23/18 (940) New Completion Streets 7/12/18 (940) Streets 5/15/18 Electronic Signs (940) New Completion Wastewater 11/16/18 Door Hangers (940) New Completion Streets 6/20/18 (940) New Completion Streets 7/12/18 (940) Streets 6/28/18 Electronic Signs (940) Wastewater 7/23/18 (940) New Completion Streets 8/17/18 (940) TWU s (940) Streets (940) New Completion Streets (940) New Completion Page 3 of 5
4 Poinsettia St. Manten Teal 8/13/18 8/27/18 W. Walnut St. Elm Cedar 8/6/18 9/14/18 Western Blvd. 300 S. Western NB Lane 500' N of Jim Christal UPCOMING PROJECTS 7/24/18 9/21/18 Wastewater Construction Utility Construction (Temporary Road Closures) Water and Wastewater Improvements Westpark Area (Lane Closures 4 to 2 lanes) Engineering 8/3/18 Door Hangers Engineering New Completion Water Businesses affected, electronic signs (940) N. Bell Ave Robertson Hickory 10/8/18 11/2/18 Bonnie Brae St. Roselawn I35E 1/15/19 1/15/20 Dakota Ln. Airport Shelby 10/8/18 11/2/18 Panel Replacement (Temporary Lane Closures) North South Water Main Phase 2 Panel Replacement (Temporary Lane Closures) New Addition Water New Addition Fulton St. Summer 2019 TBD Streets Hettie St. TBD TBD Water, Wastewater, and Streets Multiple Hickory St. Ave C Ave A 9/24/18 1/2/19 Hickory Creek Rd. Teasley Riverpass 1/1/19 6/1/20 Phase III New Addition Next Phase of Project Highland St. Hinkle Dr. University Windsor 1/1/19 1/1/20 Phase I Storm Water Improvements (Magnolia Drainage Ph II Temporary Lane Closures) Londonderry Ln. Teasley Westminster 11/1/18 TBD Panhandle St. Carroll Bolivar TBD TBD Street Improvements Streets 4/9/18 Door Hangers (940) Page 4 of 5
5 PEC 4 Engineering In Design Installing Underground Box Culvert Roselawn Dr. Bonnie Brae Kansas City Southern RR TBD TBD Drainage and Roadway Construction (Bonnie Brae Phase 1 One Lane traffic control) Engineering Stuart Rd. Windsor Kings Row TBD TBD Vintage Blvd. US 377 I35W 3/1/ Concrete Curb and Gutter Repair (Bonnie Brae Phase 2) Windsor Dr. TBD TBD Water, Wastewater, Drainage, Streets Page 5 of 5
Construction Projects Report. Week of July 23-29, 2018
Projects Report Week of July 23-29, 2018 For general inquiries and questions, please contact the Project Management Office at (940) 349-7227 Street/Intersection From To CURRENT PROJECTS of Amarillo St.
More informationConstruction Projects Report
Construction Projects Report Week of November 26 December 2, 2018 For general inquiries and questions, please contact the Project Management Office at (940) 349 7227 Street/Intersection From To CURRENT
More informationConstruction Projects Report. Week of June 25 - July 01, Proposed Date of Completion Brief Description of Construction Department Letters
Projects Report Week of June 25 - July 01, 2018 Street/Intersection From To CURRENT PROJECTS Ashcroft Ln. Cobblestone Row North Dead End of 5/14/18 8/9/18 Ave. A Maple Eagle 3/19/18 6/30/18 Bonnie Brae
More informationConstruction Projects Report
Construction Projects Report Week of December 31, 2018 January 6, 2019 For general inquiries and questions, please contact the Project Management Office at (940) 349 7227 Street/Intersection From To CURRENT
More informationConstruction Projects Report
Construction Projects Report Week of December 24 30, 2018 For general inquiries and questions, please contact the Project Management Office at (940) 349 7227 Street/Intersection From To CURRENT PROJECTS
More informationSee Yellow Highlighted for Major Closures
Projects Report Week of May 07-13, 2018 Street/Intersection From To CURRENT PROJECTS of Ave. A Maple Eagle 3/19/18 6/30/18 Barbara St. Audra Beverly 5/7/18 5/21/18 Bonnie Brae St. Roselawn West of UPPRR
More informationSee Yellow Highlighted for Major Closures
Projects Report Week of May 21-27, 2018 Street/Intersection From To CURRENT PROJECTS Ashcroft Ln. Cobblestone Row North Dead End 5/14/18 6/15/18 Ave. A Maple Eagle 3/19/18 6/30/18 Bonnie Brae St. Roselawn
More informationSee Yellow Highlighted for Major Closures
Projects Report Week of May 14-20, 2018 Street/Intersection From To CURRENT PROJECTS Ashcroft Ln. Cobblestone Row North Dead End of 5/14/18 6/15/18 Ave. A Maple Eagle 3/19/18 6/30/18 Barbara St. Audra
More information2014 Bond Program Booklet Summary of Proposed Bond Projects Election Date: Tuesday, November 4,
2014 Bond Program Booklet Summary of Proposed Bond Projects Election Date: Tuesday, November 4, 2014-1 - - 2 - TABLE OF CONTENTS Mayor s Letter to Denton Residents... 5 Overview of Program Areas... 6 City
More informationProject will Replace: Utilities Curb Pavement Lighting. City of Madison
Project will Replace: Utilities Curb Pavement Lighting Replace sanitary sewer main & laterals Winnebago: Existing 8 main, 1905 Linden: Existing 6 main, 1915, upsize to 8 main Atwood: Existing 12 main,
More informationIndex to Projects by Project Name
Index to Projects by Project Name Project # PROJECT NAME PAGE 2134 2119 PR-1109 Clayton Road (Market Street to Oakland Avenue) Sidewalk Repair 911 System Replacement and Dispatch Room Remodel ADA Barrier
More informationIndex to Projects by Project Name
Index to Projects by Project Name 2062 1701 & 1711 Concord Avenue Purchase and Demolition of Structures 85 1279 1024 UF-802 UF-803 Affordable Housing 77 Annual CIP/TIP Management Program 105 Arnold Industrial
More informationPublic Meeting. US Highway 14 (6TH Street) from Main Ave to Medary Ave Urban Reconstruction Project Brookings, SD P-PH 0014(179)419 PCN 027B
Public Meeting US Highway 14 (6TH Street) from Main Ave to Medary Ave Urban Reconstruction Project Brookings, SD P-PH 0014(179)419 PCN 027B Mark Leiferman Chief Road Design Engineer April 28, 2014 Why
More informationConst. ROADS - Description
Road Projects make up the bulk of the capital expenditures for the township. For the term of this CIP, road projects total $9,843,000 or 72.0% of the total capital expenditures for all capital projects
More informationHighway 15 Project - Hutchinson
Highway 15 Project - Hutchinson Agenda What are we going to talk about today? Goals and benefits of the project Details about the proposed work Project schedule and costs Any questions you may have about
More informationFOR IMMEDIATE RELEASE DATE: FRIDAY, AUGUST 31, Road Commission of Kalamazoo County Weekly Project Updates HAVE YOU SIGNED UP?
FOR IMMEDIATE RELEASE DATE: FRIDAY, AUGUST 31, 2018 Road Commission of Kalamazoo County Weekly Project Updates HAVE YOU SIGNED UP? Sign up for RCKC CONNECT to receive message alerts for road construction,
More informationRoads Plan
Roads Plan 2019-2023 Background Road conditions have been a problem for Painesville City over the past decade. Between 2009 and 2013, the city was only able to dedicate $1.9 million in total road repairs
More information4.500 Preston Road Overlay District
Section 4.500 Preston Road Overlay District 2004 Zoning Ordinance 4.500 Preston Road Overlay District (ZC 98-29; Ordinance No. 98-9-12) 4.501 Purpose To provide appropriate design standards for the use
More informationInterstate Traffic Interruptions Weekend of Oct 9, 2015-Oct 12, 2015
Interstate Traffic Interruptions Weekend of Oct 9, 2015-Oct 12, 2015 District 1 10/9/15 10/12/15 D Gwinnett/Hall I-985 NB MP 0 (I-85) 9pm 5am 1 right lane of 2 458462 to MP 20 (SR 60) ROLLING CLOSURE 10/9/15
More informationINFRASTRUCTURE EXISTING INFRASTRUCTURE A. Circulation B. Signals C. Drainage D. Utilities
7.01. EXISTING INFRASTRUCTURE A. Circulation B. Signals C. Drainage D. Utilities 7.02. PROPOSED INFRASTRUCTURE A. Overall Concept B. Circulation C. Signals D. Drainage 7.03. INFRASTRUCTURE MAP A. Key Infrastructure
More informationTOWN OF PALM BEACH FOR IMMEDIATE RELEASE. Patricia Strayer, P.E., Town Engineer Phone: ,
TOWN OF PALM BEACH DATE: October 19, 2017 FOR IMMEDIATE RELEASE MEDIA CONTACT: Patricia Strayer, P.E., Town Engineer Phone: 561-838-5440, Email: pstrayer@townofpalmbeach.com Construction and Traffic Highlights
More informationFOR IMMEDIATE RELEASE DATE: FRIDAY, SEPTEMBER 21, Road Commission of Kalamazoo County Weekly Project Updates HAVE YOU SIGNED UP?
FOR IMMEDIATE RELEASE DATE: FRIDAY, SEPTEMBER 21, 2018 Road Commission of Kalamazoo County Weekly Project Updates HAVE YOU SIGNED UP? Sign up for RCKC CONNECT to receive message alerts for road construction,
More informationSpring 2018 Construction Update
Spring 2018 Construction Update Ward 3 Southwest Engineering Department Locust Street Bridge over the Des Moines River The Locust Street Bridge over the Des Moines River project is being let through the
More informationTOWNSHIP OF HOWELL TOWNSHIP OF HOWELL ENGINEERING PROJECTS STATUS REPORT OCTOBER 19, Resurfacing of Aldrich Road West Contract # 11-06
TOWNSHIP OF HOWELL DEPARTMENT OF COMMUNITY DEVELOPMENT & LAND USE DIVISION OF ENGINEERING 251 Preventorium Road Phone: (732) 938-4500 x2300 Post Office Box 580 Fax: (732) 919-1080 Howell, NJ 07731-0580
More informationFY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects
ROUTE/ Project ID No. TIP No. Burlington County Computerized Signal Control, IV D9911 D9911 This ITS project will be a traffic responsive signal system, consisting of 24 intersections--9 on CR 607, 4 on
More informationConstruction Engineering & Inspection
Construction Engineering & Inspection Serving Florida for 20 Years CEI Engineering Planning Landscape Architecture Urban Design Construction Engineering & Inspection (CEI) I N T R O D U C T I O N Over
More informationBexar County Public Works Department Flood Control Program
Bexar County Public Works Department Flood Control Program Bulverde Rd. at Mud Creek Trib. A (SC-27) February 23 rd, 2016 Agenda Introductions Bexar County Flood Control (Engineering and PR) Office of
More informationSTI Street Maintenance & Overlay Project
6TH ST 6TH ST FOREST STELM AVE PA M ELA DR CT KING ARTHURCT S 33RD AVE RAMP RAM RAMP 5TH AVE 20TH AVE W 16TH AVE US HWY 14 BYP W US HWY 14 BYP RAMP RESEARCH PKWY STAD INNOVATION D R I UM RD N CAMPUS DR
More informationFOR IMMEDIATE RELEASE DATE: FRIDAY, SEPTEMBER 28, Road Commission of Kalamazoo County Weekly Project Updates HAVE YOU SIGNED UP?
FOR IMMEDIATE RELEASE DATE: FRIDAY, SEPTEMBER 28, 2018 Road Commission of Kalamazoo County Weekly Project Updates HAVE YOU SIGNED UP? Sign up for RCKC CONNECT to receive message alerts for road construction,
More informationMAIN STREET RECONSTRUCTION PROJECT PRE-CONSTRUCTION PUBLIC INFORMATION SESSION AGENDA
MAIN STREET RECONSTRUCTION PROJECT PRE-CONSTRUCTION PUBLIC INFORMATION SESSION 7:00 P.M. TO 8:30 P.M. NOVEMBER 21 st, 2017 PENETANGUISHENE MEMORIAL COMMUNITY CENTRE BRIAN ORSER HALL (61 Maria Street) 1.
More informationMonroe Street Reconstruction. Public Preconstruction Meeting February 21, 2018
Monroe Street Reconstruction Public Preconstruction Meeting February 21, 2018 Thank you to Edgewood College! Tonight s Agenda 1. Project Overview 2. Initial project schedule and phasing 3. Expectations
More informationCity of Cedar Rapids Public Works Tentative Bid Schedule Issued December 4, 2017 *Subject to Change*
12/6/2017 3012115-03 Northwood Dr NE, Glass to s/o Brookland $980,000.00 J. 4/16/2018 12/13/2017 3012121-02 O Ave NW, 16th to Ellis $4,065,000.00 Tippe; Lee J. 3/19/2018 Collins Rd NE from E of Northland
More informationRt. 29 Solutions Project Delivery Advisory Panel. January 7, 2016
Rt. 29 Solutions Project Delivery Advisory Panel January 7, 2016 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Dec
More informationPlanning & Zoning Commission Meeting Date: June 04, 2012
Meeting Date: June 04, 2012 Request Applicant Owner Zoning Preliminary/Final Plat of 24.114 acres of unplatted property into one lot with one reserve for landscape/open space. Extension of infrastructure
More informationREVIEW SET ONLY - NOT FOR BIDDING
LOCATION SHEET A.02 LOCATION SHEET A.03 LOCATION SHEET A.04 Grade Break Special Shaping Parking Perpendicular Curb Ramp Slope: 6.25% (target) 8.3% (max) 3 Special Shaping Existing Sidewalk Parallel Curb
More informationFREEWAY MAINLINE FAIR SHARE WEEKDAY PM PEAK HOUR
APPENDIX C FREEWAY MAINLINE FAIR SHARE WEEKDAY PM PEAK HOUR Freeway Segment Direction From To Existing Cumulative No Project Cumulative Plus Project Fair Share % * North Street Riverside Avenue 1,986 3,260
More informationCanal Road City Limits (East of Van Dyke Ave) to Saal Road
Canal Road City Limits (East of Van Dyke Ave) to Saal Road Construction Update 9/14/2018 The ashalt paving on the southside of Canal Road is expected to start Saturday, September 15 (weather permitting)
More informationExhibit A. SH 161 RTC Work Program of New Projects. Collin County
Exhibit A SH 161 RTC Work Program of New Projects Collin County 0918-24-969 N/A 0918-24-970 N/A 0918-24-973 N/A 2351-01-020 N/A 2679-03-010 N/A On Exchange Parkway from US 75 to Allen Heights On Country
More informationOctober 26, :00 pm
October 26, 2016 6:00 pm 1 Increase knowledge of the Pinellas- Anclote (West) Watershed Work together to improve drainage systems in the watershed Involve residents in developing potential solutions Provide
More information2040 Long Range Transportation Plan
2040 Long Range Transportation Plan Adopted: April 15, 2013 APPENDIX D HIGHWAY NEEDS PLAN PROJECTS FREDERICKSBURG Existing and Committed Projects Fall Hill Avenue/Mary Washington Blvd. (Fredericksburg)
More informationCity of Richmond. Engineering Design Specifications
City of Richmond Design Specifications June 2008 CITY OF RICHMOND ENGINEERING DESIGN SPECIFICATIONS JUNE 2008 THIS DOCUMENT DETAILS THE MINIMUM STANDARDS TO BE USED FOR THE DESIGN OF ENGINEERING PROJECTS
More informationRt. 29 Solutions Project Delivery Advisory Panel. December 3, 2015
Rt. 29 Solutions Project Delivery Advisory Panel December 3, 2015 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Nov
More informationProject Status. Construction is underway for Phase 3. Overall Project Area and Schedule. Schedule of Current Construction Phases.
I-95 Avenue Interchange Project Status Construction is underway for Phase 3. Overall Project Area and Schedule Phase 0: Completed 2010 Section GR0: Completed in Fallin 2010 Phase 2: Completed Section GR2:
More informationTown of Yucca Valley Capital Improvement Projects Report July 24, 2014
Town of Yucca Valley Capital Improvement Projects Report July 24, 2014 SR 62 Traffic and Pedestrian Improvements from Apache Trail to Palm Avenue (PLHD) The project includes construction of curbs, gutters,
More informationCITY OF OZARK STANDARD DRAWING DETAILS FOR PUBLIC IMPROVEMENTS
CITY OF OZARK STANDARD DRAWING DETAILS FOR PUBLIC IMPROVEMENTS 2010 EDITION CITY OF OZARK, MISSOURI REVISIONS TO THE 2009 EDITION The following revisions have been made to the 2009 edition of the city
More informationTIRZ 17/Redevelopment Authority Capital Improvements Plan Projects
Gessner Widening: T-1701 What: Widen the road from a six-lane divided boulevard to an eight-lane divided boulevard street section, increase turn lanes, update traffic signal system, improve drainage by
More informationEngineering Department
Engineering Department Department Mission It is the mission of the Engineering Department to protect and enhance the public health, safety and welfare by reviewing, inspecting and maintaining documentation
More informationPennDOT Public Meeting. S.R. 3044, Section A01 Castle Shannon Boulevard Roadway Improvement Project
PennDOT Public Meeting S.R. 3044, Section A01 Castle Shannon Boulevard Roadway Improvement Project Mt Lebanon Township, Allegheny County Mt Lebanon Township Municipal Building November 6, 2014 1 Project
More informationExpo Line Transit Project. Project Status Update Meeting West End Corridor Segment C
Exposition Light Rail Transit Project Project Status Update Meeting West End Corridor Segment C Culver City Senior Center November 18, 2010 Phase 1 Project Description Phase 1 from Downtown Los Angeles
More information5-Year Street Reconstruction Plan ( )
5-Year Street Reconstruction Plan (2006-2010) City of Delano Wenck File #0564-37 Prepared for: CITY OF DELANO 234 2 nd Street West Delano, MN 55328 Prepared by: WENCK ASSOCIATES, INC. 1800 Pioneer Creek
More informationSite Address. SAC Units. Dwell Units. WAC Fees. Permit Count. Fees. Issued. Surcharge. Fees. Permit Kind: COMMERCIAL DEMOLITION - STRUCTURE
City of Stillwater s & Report - Detail by Address From: 6/1/2016 To: 6/30/2016 Type: All Property Type: All Construction Type: All Include YTD: No Status: Not Voided # Total Type: BUILDING Kind: COMMERCIAL
More informationPROJECTS UNDER CONSTRUCTION
Project Name Project Status Project Funding Project Manager PJ 2144 Clayton Rd-Treat Blvd Intersection Improvements Widen the Clayton Road/Treat Blvd intersection and upgrade the traffic signal. Construction
More informationPROPOSED IMPROVEMENTS
IV. PROPOSED IMPROVEMENTS The proposed improvements for each alternative carried forward are discussed below. A. FUNCTIONAL CLASSIFICATION AND ROADWAY CROSS-SECTIONS The classifications of the roadways
More informationReconfiguration of The Six Points Interchange. Community Update #2 June 18, 2014
Reconfiguration of The Six Points Interchange Community Update #2 June 18, 2014 Outline 1. Project overview 2. How did we get here? 3. Etobicoke Centre 4. Existing and future road network 5. Design Update
More informationLITTLE ELM CAPTIAL IMPROVEMENT BOND STREET PRESENTATION
LITTLE ELM 2009-2014 CAPTIAL IMPROVEMENT BOND STREET PRESENTATION Denton Frisco Little Elm Lewisville Legacy Southlake Grapevine Addison DENTON COUNTY & LEWISVILLE LAKE MATCHING FUNDS DENTON COUNTY BOND
More informationMoving The Metro. A special construction update for the metro Omaha area.
Moving The Metro A special construction update for the metro Omaha area. ebraska Department of Roads Spring/Summer 2017 I-80 / I-480 / US-75 Interchange The improvements on this project consist of bridge
More informationTABLE OF CONTENTS I-1 INTRODUCTION TO STANDARD DESIGNS 03/17/08
TABLE OF CONTENTS Sheet Number Title Revision Date I-1 INTRODUCTION TO STANDARD DESIGNS 03/17/08 STREETS ST-1 LOCAL STREETS 03/17/08 ST-1A LOCAL STREETS, 2015 GENERAL PLAN 11/15/04 ST-2 COLLECTOR AND ARTERIAL
More informationAbbott Loop. Community Council Survey Capital Projects Needs Ranking Survey. Comm Council Priority Rank. Rank # ABBOTT LOOP COMMUNITY PARK
Municipality of Anchorage Community Council Survey ABBOTT LOOP COMMUNITY PARK This state funding request would be used to implement the remaining elements of the Community Park Master Plan Vision including
More informationCommunity Meeting US 101/Peninsula Avenue Interchange Project JUNE 25, 2015
Community Meeting US 101/Peninsula Avenue Interchange Project JUNE 25, 2015 Project Team Gary Heap, Engineering Division Manager Tracy Scramaglia, Senior Engineer Ramesh Sathiamurthy, AECOM Peter DeStefano,
More information2018 Primary Road Capital Improvement Plan (CIP) Projects Preservation / Structural Improvement, Non-motorized and Engineering Design Projects
2018 Primary Road Capital Improvement Plan (CIP) Projects Preservation / Structural Improvement, Non-motorized and Engineering Design Projects Preservation / Structural Improvement Projects in 2018 Ravine
More informationCreative Engineering Group Inc, (Creative) Construction Engineering and Inspection (CEI) Professionals
ABOUT US Creative Engineering Group Inc, (Creative) is a Construction Engineering and Inspection (CEI) firm established in 2006 by two Principals Rick Estripeaut & Sri Mavanur. In the last decade Creative
More informationTENNESSEE DEPARTMENT OF TRANSPORTATION Project Status. SR-37 US-19E No Projects Under Development in Carter County
CARTER COUNTY SR-37 US-19E No Projects Under Development in Carter County PIN: 125256.00 AT LM 8.7 (ROCKFALL MITIGATION) Length - 0.0 (Mitigation - Rockfall) CARTER COUNTY SR-91EXT PIN: 043975.01 FROM
More informationWelcome. Date: Thursday March 2, 2017 Time: 6:30 p.m. 9:00 p.m. Location: Woodview School Gym, 69 Flatt Road, Burlington Presentation Time: 7:00 p.m.
Welcome Public Information Centre No.2 City of Burlington, City of Hamilton, Region of Halton Waterdown Road Widening Detailed Design Craven Avenue to Mountain Brow Road Date: Thursday March 2, 2017 Time:
More informationPrince William Street Project (Grant Avenue to Wellington Road)
Prince William Street Project (Grant Avenue to Wellington Road) 1 Goals Improve pedestrian and bike traffic safety Improve street drainage with curb & gutter Upsize water mains Enhance overall street appearance
More informationThe Van Ness Campus. Weekly Construction Bulletin #259
The Van Ness Campus Weekly Construction Bulletin #259 Construction Update Week of September 24, 2018 The Van Ness Campus Weekly Bulletins are intended to help inform members of the community about upcoming
More information5-AUTOMOBILE CIRCULATION & PARKING
5-Automobile Circulation & Parking 5-AUTOMOBILE CIRCULATION & PARKING Parking and automobile circulation are always popular topics for downtowns. Citizen concerns in Georgetown have to do with high traffic
More informationChesterfield County Project Update
Chesterfield County Project Update SOUTHEAST HIGH SPEED RAIL TIER II ENVIRONMENTAL IMPACT STATEMENT RICHMOND, VA, TO RALEIGH, NC CHESTERFIELD COUNTY, VA OFFICIALS BRIEFING February 2013 Federal Railroad
More informationCity of Jersey City. Department of Administration Division of Engineering Traffic and Transportation
Division of Engineering Traffic and Transportation : Duncan Avenue Road Program Bergen Avenue Road Program PSE&G Gas System Modernization Program NJDOT Municipal Aid FY2015 Road Program Ogden Dog Park
More informationSR 483 Clyde Morris Boulevard FDOT District 5
This project occurs on a 3.0 mile section of SR 483 (Clyde Morris Blvd.) south of Beville Road (SR 400) to north of International Speedway Boulevard (SR 600). Ghyabi is providing project management and
More informationSacramento County - Department of Transportation
Sacramento County - Department of Transportation Proposed Projects to be Funded with Road Maintenance and Rehabilitation Account Funding FY 2017-18 Project Description AC Overlay Projects - Federal: Rehabilitate
More informationMOLD PROGRAM ORDERS ISSUED FOR THE MONTHS OF AUGUST 2016 AUGUST 2017
Agreed Orders Signed by the Assistant Commissioner Division for Regulatory Services ARC Abatement, Inc. RCO0163 Sun Valley Elementary School, 6803 Southwest Loop 410, San Antonio, Texas Loflin, Joseph
More informationCITYWIDE DRAINAGE ASSESSMENT REPORT
CITYWIDE DRAINAGE ASSESSMENT REPORT Department of Community Services Engineering Division November 2012 Page 1 of 34 Table of Contents Introduction 3 Summary 4 CATEGORY I DRAINAGE LOCATIONS 1. Waldron
More information2016 WORKSHOP LVR Field Trip
2016 WORKSHOP LVR Field Trip ***Note*** Many of the sites on this tour were NOT related to, or funded by, the DGLVR program. They are being shown to encourage discussion about the kinds of projects that
More informationMonroe Street Reconstruction. Final Corridor Design Presentation & Open House August 16, 2017
Monroe Street Reconstruction Final Corridor Design Presentation & Open House August 16, 2017 Thank you to Wingra School! Tonight s Agenda 1. Project Overview 2. Design Proposal & Preparing for Reconstruction
More informationWEST OAK CLIFF RED LINE EXTENSION
INITIAL ALTERNATIVES CORRIDOR EVALUATION WEST OAK CLIFF RED LINE EXTENSION Hampton C O R R I D O R I N F O R M AT I O N 408 303 Keist Keist Blvd Duncanville Rd 2 Red Bird Ln Executive Airport Boulder "
More informationKNOXVILLE/KNOX COUNTY METROPOLITAN PLANNING COMMISSION SUBDIVISION REPORT - CONCEPT/USE ON REVIEW
KNOXVILLE/KNOX COUNTY METROPOLITAN PLANNING COMMISSION SUBDIVISION REPORT - CONCEPT/USE ON REVIEW FILE #: 10-SF-17-C 10-I-17-UR AGENDA ITEM #: 12 AGENDA DATE: 11/9/2017 POSTPONEMENT(S): 10/12/2017 SUBDIVISION:
More information4.1 Build Alternative 1 Construction Phasing
SECTION 4 Implementation Plan This section discusses potential segmentation of the build alternatives into multiple projects for implementation of improvements to the NSH from Rabbit Creek Road to 36th
More informationWiles Road from University Drive to Riverside Drive
Wiles Road from University Drive to Riverside Drive Presented to: Broward County WSP Parsons Brinckerhoff is now Presented by: WSP USA Inc. Our Team.. Introduction / Project Team Cecilia Villoria, PE Project
More informationFlooding Hearing: Long and Short Term Strategies
Services of the San Francisco Public Utilities Commission Flooding Hearing: Long and Short Term Strategies Presentation to San Francisco Board of Supervisors Public Safety and Neighborhood Services Subcommittee
More informationTOWN OF PALM BEACH FOR IMMEDIATE RELEASE. Patricia Strayer, P.E., Town Engineer Phone: ,
TOWN OF PALM BEACH DATE: October 18, 2018 FOR IMMEDIATE RELEASE MEDIA CONTACT: Patricia Strayer, P.E., Town Engineer Phone: 561-838-5440, Email: pstrayer@townofpalmbeach.com Construction and Traffic Highlights
More informationSTREET IMPROVEMENT AND MAINTENANCE PROGRAMS
2018-2019 STREET IMPROVEMENT AND MAINTENANCE PROGRAMS Engineering Department Pamela S. Cooksey, City Engineer Public Works Department Jonathan Gano, Public Works Director April 2018 Attached for your information
More informationCity of Miami MIAMI RIVER BASIN WATER QUALITY IMPROVEMENT REPORT FOR FIRST AND SECOND QUARTER 2010
Action Items 1. Storm water* a. Retrofit drainage in remaining areas of Miami River starting with Pinehurst neighborhoods This project included drainage work that consist of French drains, solid piping,
More informationSt. Elizabeths Hospital/West Campus Landscape Character-Defining Features
The following list of landscape character-defining features is taken directly from Chapter VII of the 2007 St. Elizabeths West Campus Cultural Landscape Report by Heritage Landscapes and Robinson & Associates,
More informationDEPARTMENT OF PUBLIC WORKS & UTILITIES
CITY OF PORT ANGELES DEPARTMENT OF PUBLIC WORKS & UTILITIES URBAN SERVICES STANDARDS AND GUIDELINES January 2017 Craig Fulton, P.E., Director TABLE OF CONTENTS "URBAN SERVICES STANDARDS AND GUIDELINES"
More informationWHAT IS THE PURPOSE OF THE OPEN HOUSE?
WHAT IS THE PURPOSE OF THE OPEN HOUSE? OPEN HOUSE PURPOSE The purpose of the open house is to provide an update on the study process and introduce the preliminary concept alternatives. The open house provides
More informationTENNESSEE DEPARTMENT OF TRANSPORTATION Project Status. No Projects Under Development in Campbell County
I-75 No Projects Under Development in Campbell County PIN: 115778.00 TRUCK CLIMBING LANE, MP 135.5 TO MP 140.1(NBL) Length - 4.6 (Widen) The right-of-way and/or utility process is underway. I-75 PIN: 115778.01
More informationCotton Belt Regional Rail Corridor Project
Cotton Belt Regional Rail Corridor Project North Dallas AFG University of Texas at Dallas Administration Building March 1, 2018 0 Discussion Public Involvement Project Scope Alignment Stations Environmental
More informationPublic Information Centre. Welcome
Transportation Improvements from the Beaver Creek Bridge to the Entrance of Santa s Village District of Muskoka Municipal Class Environmental Assessment Welcome Please sign in Take a comment sheet Staff
More informationCASE NUMBER: 16SN0701 APPLICANT: Hanky, LLC
STAFF S ANALYSIS AND RECOMMENDATION Planning Commission (CPC) Public Hearing Date: MAY 17, 2016 CPC Time Remaining: 100 DAYS Applicant s Agent: DANIEL L. CASKIE (804-569-7060) Applicant s Contact: MICHAEL
More informationCompleting the Vision:
Completing the Vision: North A1A-Lane Reconfiguration TDLC-Transportation Design for Liveable Communities Surf Rd. Redirection of Traffic Phase III Streetscape October 30, 2012 1 Project Overview District
More informationItem # Meeting Date: February 27, 2014 AGENDA MEMORANDUM To: From: Planning Commission Sandy Vossler, Planner II, Development Services Department Date: February 26, 2014 Title: The Lanterns Planned Development
More informationBALL CAMP PIKE Phase II From Middlebrook Pike to Andes Road NEW CONSTRUCTION Spring 2007
COUNTY LOCAL PROJECTS BALL CAMP PIKE Phase II From Middlebrook Pike to Andes Road NEW ION Spring 00 DRY GAP PIKE From Dante Road to Beaver Creek WIDENING Summer 00 DUTCHTOWN ROAD From Pellissippi Parkway
More informationA. INTRODUCTION B. PROJECT LOCATION
Chapter 1: Project Description A. INTRODUCTION The Lower Manhattan Development Corporation (LMDC), a subsidiary of the New York State Urban Development Corporation, doing business as the Empire State Development
More informationWaukee. City of. The Key to Good Living
Waukee City of The Key to Good Living City of Waukee FY15 - FY20 CIP Project Summary FY2015 FY2018 Parks Windfield Park Improvements Parks Centennial Park Amphitheater Parks Grant Park Improvements Parks
More informationWELCOME! 8 8:30 6: TH STREET IMPROVEMENTS. Open House. Presentation & Q&A
WELCOME! 168 TH STREET IMPROVEMENTS 6:30 Open House 7 8 Presentation & Q&A 8 8:30 Open House WELCOME Todd Pfitzer City of Omaha Engineer Bob Stubbe City of Omaha Public Works Director Jon Meyer Project
More informationThe bid shall include the following items: 1) Bidder s Name. Address. Telephone Number. Address. 2) The amount of the bid per acre to Mow.
Beautification and Rough Mowing Services Bid #066-17 The City of Lucas is seeking bids for Beautification and Rough Mowing Services on 30 acres of land. The Mowing Season is 40 week long between March
More informationTHREE-YEAR CAPITAL IMPROVEMENT PLAN FY
THREE-YEAR CAPITAL IMPROVEMENT PLAN FY2016 2018 Annual CIP Development Process Public Works & Engineering Divisions Prepare List of Capital Needs and Recommended Deferred Maintenance Public Works & Engineering
More informationAwarded Small Works Projects
Small Works Projects Kamins Construction TBD 4th Avenue West Sidewalk Project 12/6/2018 $47,056 Tube Art Group 1451 Wayfinding Signs 9/4/2018 $11,000 POP Electric Inc 1354 Repurposed Exterior Light for
More informationSTANDARD SPECIFICATIONS Book 2 ENGINEERING DRAWINGS INCLUDES ADDENDUMS
STANDARD SPECIFICATIONS Book 2 ENGINEERING DRAWINGS INCLUDES ADDENDUMS July 23, 2018 Page 1 of 7 STANDARD LEGEND SYMBOLS (September, 1973)... AS-101A STANDARD LEGEND SYMBOLS (September, 1973)... AS-101B
More informationJohn Portman Boulevard Corridor
Corridor Multi-use Path + Streetscape Improvements February 8, 13 SOUTH SIDE BLOCK IMPROVEMENT NOTES: Consolidation of Utility/Sign Locations Remove Existing Trees Centennial Olympic Park Drive Planter
More information