2 Transportation Improvement Alternatives

Size: px
Start display at page:

Download "2 Transportation Improvement Alternatives"

Transcription

1 Transportation Improvement Alternatives Transportation Improvement Alternatives This section documents the development of alternatives for transportation improvements in support of the redevelopment of the St. Elizabeths for the DHS Headquarters, including improvements to Martin Luther King, Jr. Avenue (MLK Avenue), Firth Sterling Avenue, and the I-95/Malcolm X Interchange as well as constructing a road from Firth Sterling Avenue to Malcolm X Avenue that will provide access to the St. Elizabeths West Campus. The Transportation Improvement Alternatives section describes the process used to develop the alternatives evaluated within this volume of the Final EIS. The National Environmental Policy Act (NEPA) requires the development and evaluation of all reasonable alternatives as part of the environmental impact statement process for a major transportation project. Alternatives are evaluated in terms of engineering feasibility, sensitivity to the environment, and ability to satisfy the project needs. The alternatives development process included a comprehensive public and agency involvement program. The affected public and regulatory agencies were involved in the development of preliminary corridors and the identification of alternatives to study in the EIS..A Alternatives Development Process To create alternatives for transportation improvements, the General Services Administration (GSA), in cooperation with the Federal Highway Administration (FHWA) and the DC Department of Transportation (DCDOT), assembled a project team of urban planners, architects, architectural historians, environmental scientists, engineers, and financial analysts. The project team identified and studied existing resources and development considerations before developing alternatives. The project team s activities included: Identifying the historic and current significant views both to and from the study area Identifying natural resources such as forested areas, streams, and protected species Identifying engineering constraints such as steep slopes and unstable soils Analyzing traffic impacts to local and regional roadways Final EIS Volume II Transportation Improvements -

2 Transportation Improvement Alternatives Analyzing availability of public transportation and other transportation management alternatives such as car-pooling, adjusted work schedules, and telecommuting As GSA developed the Transportation Improvement Alternatives, it worked to find a balance between project needs and the individual resources that could be affected by the project. Throughout the study process and the development of alternatives, GSA asked for input from public and government agencies through scoping, stakeholder meetings, public meetings with Advisory Neighborhood Commissions and the general public, and consulting parties meetings under the Section 06 process. Input from the public and government agencies is again requested on this Final EIS. 0.A. Resource Considerations As noted in the previous sections, research was conducted to identify issues and resources that needed to be considered in the development of Transportation Improvement Alternatives. Following is a summary of some of the key issues that were considered in the development of the individual Transportation Improvement Alternatives. 5.A..a St. Elizabeths Hospital East and West Campuses The St. Elizabeths Hospital is a National Historic Landmark (NHL). The NHL designation covers 8 contributing resources on the East and West Campuses including buildings, landscapes, vistas of the river and city, and the West Campus Cemetery. Since construction of an access road on the West Campus and widening of MLK Avenue would affect a NHL, Section 0(f) of the National Historic Preservation Act (NHPA) applies to the project. Section 0 requires the head of the responsible federal agency to undertake such planning and actions as may be necessary to minimize harm to a NHL. The goal of preservation under Section 0 is to protect the entire NHL. However, based on the assessments undertaken, it was determined that certain key character-defining features should be preserved to the extent possible under all of the Transportation Improvement Alternatives. These features include: The West Campus wall along MLK Avenue - Final EIS Volume II Transportation Improvements

3 Transportation Improvement Alternatives The entrance road into the West Campus from Gate to the Center Building and the associated trees along the roadway The historic internal roadway network In developing alternatives, special consideration was given to protecting the West Campus Cemetery on the slope northwest of the Center Building. All of the Transportation Improvement Alternatives were designed to not only avoid direct encroachment on the cemetery, but also to protect the landscape surrounding the cemetery. The cemetery will be placed outside of security fencing to allow for controlled public access. 9.A..b Natural Resources 0 5 The transportation study area contains natural resources including wetlands, streams, and large contiguous forested areas. The project team assessed the condition of natural resources and minimized construction in areas with mature forested areas, wetlands, and streams. A bald eagle s nest is located on Shepherd Parkway. A 660-foot radius around the nest was identified and protected with only limited encroachment at the outer edge from a perimeter fence that follows the site topography. 6.A..c Access/Roadway Network The regional roadway network and access to St. Elizabeths were studied to assist in determining the maximum number of employees that could access the site; the availability of mass transit and other intermodal solutions to access; and the need for additional vehicular access points to the site. Regional vehicular access to St. Elizabeths is provided via I-95, I-95, and I-95 from the north and south, and Route 50 and I-66 from the east and the west. Regional traffic in the vicinity of St. Elizabeths is congested at times during the rush hour periods in some locations. The local roadway network provides access from Suitland Parkway and South Capitol Street. The campus has direct access on MLK Avenue via two gates. A third gate to the campus is located below the grade level of MLK Avenue and provides a tunnel connection directly to the East Campus. Final EIS Volume II Transportation Improvements -

4 Transportation Improvement Alternatives The Anacostia Metrorail Station is approximately 0.56 miles from the West Campus Gate, approximately 0.99 miles from the West Campus Gate, and 0.7 miles from the West Campus Gate tunnel. The Congress Heights Metrorail Station is approximately.7 miles from the West Campus Gate, approximately.0 mile from the West Campus Gate, and 0.7 miles from the West Campus Gate. In addition, a number of bus routes located on MLK Avenue provide accessibility to local destinations including the Anacostia Metrorail Station. The area lacks bicycle routes and paths. 8.A..d Views Significant views toward I-95, Shepherd Parkway, and the St. Elizabeths West Campus can be found in nearby locations such as the Washington Navy Yard, Hains Point at East Potomac Park, and vehicular approaches to the campus. In addition, the views of the wooded ridge (or topographic bowl) on which St. Elizabeths stands, but not included in the hospital s landmark designation, are considered by metropolitan planning agencies to be important elements of the Washington, DC viewshed in the Federal Elements of the Comprehensive Plan for the National Capital. 6.A..e Shepherd Parkway The Shepherd Parkway, extending south of the St. Elizabeths West Campus, along the eastern side of I-95, is under the jurisdiction of the National Park Service. The Shepherd Parkway is not a road, but is part of the Fort Circle Parks, a series of parklands which contain Civil War earthworks. The Shepherd Parkway is land that was set-aside by the United States to build a road to be called Fort Circle Drive. The road was never constructed, and the Fort Circle Parks were divided between three Washington, D.C. area National Park Service units George Washington Memorial Parkway, Rock Creek Park, and National Capital Parks-East. The Shepherd Parkway is managed by the National Park Service National Capital Parks-East and is noted for containing mature native hardwood forest and unique geologic features. Within the transportation study area, Shepherd Parkway contains steep slopes (greater than 5%) and does not have recreational amenities or a designated entrance. There is substantial dumping of miscellaneous waste within the Shepherd Parkway. - Final EIS Volume II Transportation Improvements

5 Transportation Improvement Alternatives.A..f Bolling Air Force Base Historic District The first Bolling Air Field was established north of the current Air Force Base in what is now the Naval Air Station. Construction on the present Bolling Air Force Base began in 9. Transfer of personnel from the old air field was completed by 90. The General Headquarters of the Army Air Forces moved into the facility in 9. When the U.S. Air Force was established in 97, Bolling became Headquarters Command USAF. The National Register eligible historic district includes 75 buildings constructed between 9 and 95, including officers quarters, barracks, hangars, and service buildings. The Bolling Air Force Base Historic District is shown on Figure -. 0.A..g Congress Heights Firehouse; Congress Heights Historic District The Congress Heights Firehouse at 0 MLK Avenue, SE, has been a neighborhood landmark since its construction in 90. It was Washington s largest firehouse at the time of its construction. The red brick Italianate design incorporated operational and construction innovations such as an observation tower and a steel truss roof. It was listed in the D.C. Historic Inventory on July, 00. Congress Heights, the neighborhood southwest of St. Elizabeths Hospital and developed in the early twentieth century, was surveyed in and determined to be eligible for listing in the National Register. The Congress Heights Firehouse and the Congress Heights Historic District are shown on Figure -. 9.A. Alternatives Considered But Eliminated From Detailed Study In general, the goal of the project team was to develop possible routes or preliminary alternatives that would meet engineering design criteria for safety and satisfy the project needs while avoiding as many sensitive features as possible. When it is impossible to avoid impacting a feature, the study team attempted to minimize the impact as much as possible. During the preliminary alternatives development, the broadest feasible spectrum of roadway improvements was examined. The goal was to narrow the field of preliminary alternatives and only study alternatives that meet the project needs. GSA studied several alternatives and either retained or dismissed each based on whether or not they were feasible or prudent from an engineering and/or traffic standpoint. Below is a summary of the dismissed alternatives. GSA retained for detailed study the Malcolm X/I-95 interchange and construction of a new access Final EIS Volume II Transportation Improvements -5

6 Transportation Improvement Alternatives road from Malcolm X Avenue to the West Campus even though it would impact a sensitive feature, the Shepherd Parkway as it was the most feasible and prudent alternative from an engineering and traffic standpoint. Access to South Capitol Street South Capitol Street is located adjacent to and west of I-95. Alternatives to create a direct access from South Capitol Street to the St. Elizabeths West Campus were studied. South Capitol Street and the St. Elizabeths West Campus are separated by I-95; therefore it would be necessary to provide a fly-over over I-95 or a tunnel under I- 95 to create a direct access point. A fly-over over I-95 would require at least 5 feet of vertical clearance. Ramping up the road from South Capitol Street to this height would require unreasonable grades because there is not enough horizontal distance between South Capitol and I-95. Tunneling under I-95 would present similar engineering issues. Because there is insufficient space to allow for a reasonable grade for a flyover or a tunnel, direct access from South Capitol Street to the St. Elizabeths West Campus is not feasible. Direct Access from I-95 This alternative would provide for direct access between the St. Elizabeths West Campus and I-95. A design waiver from FHWA would be required for a new access point on I-95 due to the close proximity of the I-95/Suitland Parkway interchange to the north and the I-95/Malcolm X interchange to the south. The addition of a new interchange on I-95 to the St. Elizabeths campus between the existing interchanges would create weave problems on I-95. In addition, FHWA s policy for new interstate access points states that new or revised access points to the existing Interstate System should meet the following requirements: The proposed access connects to a public road only and will provide for all traffic movements This requirement cannot be met as a new interchange on I-95 would only be for employees and visitors to the St. Elizabeths West Campus, not a public road, and all traffic movements could not be accommodated. Land and buildings from the Anacostia Naval Annex would need to be acquired to construct a fly-over access ramp from southbound I- 95 to the campus. The Naval Annex does not have land available to relocate buildings that would be demolished under this alternative. Suitland Parkway (via a connection to the St. Elizabeths East Campus) Only percent of the traffic accessing the consolidated DHS Headquarters at St. Elizabeths is expected to arrive via westbound Suitland Parkway. Therefore, creating a direct connection from the Parkway for all DHS traffic coming to St. Elizabeths would not meet the project need. -6 Final EIS Volume II Transportation Improvements

7 Transportation Improvement Alternatives Access to St. Elizabeths East Campus from Suitland Parkway may be feasible via a long and relatively steep fly-over ramp from the parkway to the St. Elizabeths East Campus. Both the Suitland Parkway and the East Campus are historic resources. Access between the East Campus and the West Campus would need to be provided via the existing at-grade gates on Martin Luther King, Jr. Avenue or via a tunnel connection to the East Campus (similar to the existing tunnel connection at the West Campus Gate ). Putting West Campus traffic back on Martin Luther King, Jr. Avenue would not alleviate traffic congestion at the existing Martin Luther King, Jr. gates. Providing a vehicular tunnel connection would create security problems for the DHS Headquarters. Also, this alternative would not provide a connection to the western side of the campus close to planned parking locations, requiring the widening of roadways within the St. Elizabeths West Campus to allow two-way traffic, including delivery trucks, to traverse the site. This alternative would also require acquiring land and could potentially include demolition of historic buildings on the East Campus. Alternate access from Suitland Parkway to St. Elizabeths East Campus will likely be studied as part of future East Campus redevelopment plans. Access via Martin Luther King Jr. Avenue (new gate) Under this alternative, all traffic coming to the DHS Headquarters at St. Elizabeths would arrive via MLK Avenue. An additional gate into the St. Elizabeths West Campus from MLK Avenue would be added under this alternative. This alternative would have major impacts on local traffic as all employees, visitors, and deliveries coming to the DHS Headquarters would need to access the campus from MLK Avenue. A new access point on MLK Avenue would not provide access to the western edge of the campus close to potential parking locations without widening the historic roadways within the St. Elizabeths NHL to allow two-way traffic to traverse the site. The limited distance between adjacent gates/intersections would not allow for efficient traffic operations. Access via Firth Sterling Avenue Under this alternative, Firth Sterling Avenue would be widened to accommodate 70 percent of the vehicles coming to the St. Elizabeths West Campus, and a new access road would be constructed from Firth Sterling Avenue into the West Campus. The remaining 0 percent of vehicles accessing the DHS Headquarters would arrive via MLK Avenue. This alternative would not meet the project s purpose and need because it would not provide adequate capacity to handle the traffic generated by the DHS Headquarters. Traffic from 70 percent of the vehicles accessing the West Campus via Firth Sterling Avenue would create queuing problems on Firth Sterling Avenue from vehicles waiting to clear security checkpoints on the campus. In addition, without additional access points, the volume of traffic Final EIS Volume II Transportation Improvements -7

8 Transportation Improvement Alternatives created by the DHS Headquarters would cause intersections at Firth Sterling Avenue to fail. In order to provide adequate levels of service, the I-95 and Suitland Parkway interchange with Howard Road and Firth Sterling would need to be reconstructed which could impact the Anacostia Metrorail station and the Suitland Parkway, which is itself a Section (f) resource. In addition, Firth Sterling would need to be widened resulting in the acquisition of businesses including a Verizon facility and acquisition of portions of the Barry Farm public housing complex This alternative has been studied as Alternative I-0 in this volume of the Final EIS. This alternative is included to provide an assessment of impacts that would occur if FHWA does not approve modifications to the Malcolm X/I-95 interchange eliminating the potential to construct the access road from Malcolm X into the St. Elizabeths West Campus..B No Action Alternative Under the No Action Alternative, the DHS Headquarters would not be consolidated at St. Elizabeths and no additional traffic would be generated. Under the No Action Alternative, no land acquisition would occur. Although the No Action Alternative would not meet the purpose of and need for the project, NEPA requires GSA to consider the No Action Alternative because it provides a baseline for evaluating the environmental impacts of the alternatives for the proposed action. The No Action Alternative also serves as a basis for determining whether the public benefits of the proposed transportation improvements outweigh the probable environmental impacts. It should be noted that the No Action Alternative studied in Volume I of this EIS assesses impacts that would occur if redevelopment of St. Elizabeths for the DHS Headquarters consolidation is not undertaken. In the interest of minimizing redundancy between the two volumes, this analysis has not been repeated in Volume II..C Transportation Improvement Alternatives Four Interchange/Access Road Alternatives along with a no-build alternative (Alternative I-0) have been considered in detail in this EIS. Included in each alternative is the reconfiguration of the intersection of Firth Sterling Avenue/Stevens and Barry Roads to tie into a new access road that would enter the St. Elizabeths West Campus at the northwest perimeter to a gated entrance -8 Final EIS Volume II Transportation Improvements

9 Transportation Improvement Alternatives to the south of the West Campus Cemetery. In Alternatives I- through I-, the access road would then continue south to Shepherd Parkway before tying into a reconstructed interchange at Malcolm X Avenue and I-95. Each of these alternatives are compatible with any of the St. Elizabeths Campus Redevelopment Alternatives, shown in Volume I of this Final EIS. Two alternatives were considered for improvements to MLK Avenue, which fronts the eastern boundary of the St. Elizabeths West Campus, separating it from the East Campus to provide turn lanes for vehicles entering the St. Elizabeths West Campus. The following alternatives for improvements to MLK Avenue are compatible with any of the Interchange/Access Road Alternatives described in this section. Improvements to Firth Sterling Avenue and MLK Avenue and construction of the proposed access road would be funded by GSA. It is expected that funding for the Malcolm X Avenue/I- 95 interchange improvements would come from other Federal sources.c. Interchange/Access Road Alternatives The GSA project team worked with DDOT and FHWA to develop alternatives to improve the Malcolm X/I-95 interchange and construct a new access road from Malcolm X Avenue to Firth Sterling Avenue. At DDOT s request, GSA assessed alternatives that would improve the traffic situation not only for the DHS Headquarters, but also improve existing deficiencies associated with the I-95/Malcolm X partial interchange, the South Capitol Street/Malcolm X interchange and the main Bolling Air Force Base access gate. The project team developed a total of interchange concepts. Of these alternatives four alternatives along with a no-build alternative (Alternative I-0) have been studied in detail in this EIS. Through consultation with DDOT and FHWA, the following seven alternatives were dismissed: Full cloverleaf A full cloverleaf interchange would extend onto the Bolling Air Force base and its newly constructed security screening area. Quarter cloverleaf plus elongated loop ramp This concept would replace the existing northbound loop on-ramp with an increased I-95 loop ramp and an elongated northbound loop off-ramp. This alternative would push the proposed St. Elizabeths access road east on Malcolm X Avenue and would require significant retaining walls. Also this concept would have greater impacts on the Shepherd Parkway. Final EIS Volume II Transportation Improvements -9

10 Transportation Improvement Alternatives Half cloverleaf with wide diamond ramp This concept would separate the St. Elizabeths West Campus site access from the I-95 interchange ramps. This alternative would have significant impacts to the Shepherd Parkway since the proposed access road would be located much further east. Also this alternative would require significant retaining wall heights. Half tight diamond with site access from ramp This concept would create an undesirable situation with two-way traffic accessing St. Elizabeths mixing with one-way interstate traffic. Also the access road would require a traffic signal. A traffic signal should not be provided in the middle of an interstate on-ramp when traffic should be accelerating, not stopping. Half tight diamond with five leg intersection This alternative would require confusing and double left-turns at a five-leg intersection. Traffic demands from Bolling Air Force Base would require a double left turn lane from eastbound Malcolm X Avenue onto the I-95 northbound on-ramp. Also a double left turn lane would be required for traffic to turn onto the campus. It would be unsafe to provide double left turns for both legs at this five leg intersection. Full tight diamond with five leg site access This alternative would eliminate the Malcolm X/South Capitol Street ramps and would provide full access to I-95. However, this alternative would still provide confusing left-turns at the five-leg intersection (see half tight diamond alternative above). Also preliminary traffic analyses indicate that this alternative would not operate with acceptable traffic levels due to the close spacing between the two traffic signals that would be required at the diamond ramps. Single point interchange with one-way service road This alternative would only allow one-way access to the St. Elizabeths West Campus from Malcolm X Avenue. This alternative would not meet the access needs of the campus. As noted previously four Interchange/Access Road Alternatives along with a no-build alternative (Alternative I-0) have been considered in detail in this EIS. Included in each alternative is the reconfiguration of the intersection of Firth Sterling Avenue/Stevens and Barry Roads to tie into a new access road that would enter the St. Elizabeths West Campus at the -0 Final EIS Volume II Transportation Improvements

11 Transportation Improvement Alternatives northwest perimeter to a gated entrance to the south of the West Campus Cemetery. Three alternatives were studied for reconstructing the Firth Sterling Avenue intersection with Stevens and Barry Road to accommodate the proposed access road. The GSA project team developed alternatives to improve Firth Sterling Avenue. A total of three concepts were developed. Through consultation with DDOT, the following two alternatives were dismissed: Five legged intersection Firth Sterling Avenue would be realigned. This alignment was not compatible with the streetcar tracks that DDOT is constructing alone Firth Sterling Avenue. Roundabout four out of the five streets at the Firth Sterling Avenue intersection would feed in and out of the roundabout, while one street would only feed out. This alignment was also not compatible with the streetcar track DDOT is constructing along Firth Sterling Avenue. As noted above, a new access road would be constructed from Firth Sterling Avenue into the St. Elizabeths West Campus. In Alternatives I- through I-, the access road would parallel I-95 through the West Campus, continuing south through the Shepherd Parkway before tying into Malcolm X Avenue near the reconstructed Malcolm X/I-95 interchange. The access road has been studied as a three-lane, two-way road that connects from Firth Sterling Avenue, SE to Malcolm X Avenue. The center lane would operate as a reversible lane that would accommodate inbound and outbound peak directional traffic flow. Additional lanes will be provided at the access road intersection with Malcolm X for turn lanes and at the new entrance gate for turn lanes and vehicle queuing for security processing. It should be noted that under Alternatives and 5, it may be feasible to reduce the access road to two lanes, thereby reducing impacts associated with the roadway. If the access road is reduced to two vehicle travel lanes then a bicycle-lane and sidewalk could be accommodated from Firth Sterling Avenue into the campus within the same currently proposed cross section. The bicycle-lane and sidewalk would help provide improved access from the west campus to the Anacostia Metrorail Station, the Naval Support Facility Anacostia (the Naval Annex), and the Barry Farm Redevelopment. The bicycle-lane and sidewalk would end at the campus limits and would still allow for reduced impacts through Shepherd Parkway to Malcolm X Avenue. GSA would continue to study Final EIS Volume II Transportation Improvements -

12 Transportation Improvement Alternatives reductions to the footprint of the roadway and the provision of a bicycle-lane and sidewalk during final design. To minimize impacts to vegetation and steep slopes within the St. Elizabeths West Campus and within the Shepherd Parkway, preliminary designs for Alternatives I-0 through I- incorporated the use of retaining walls. Table - provides an overview of retaining wall heights for each of the alternatives. The surface treatment for the retaining walls would be determined during final design and would be context sensitive. Table -. Approximate Retaining Wall Heights for Interchange/Access Road Alternatives Retaining Wall Heights On Shepherd Parkway south of Malcolm X Avenue On Shepherd Parkway north of Malcolm X Avenue On St. Elizabeths West Campus Alternative I-0 Alternative I- Alternative I- Alternative I- Alternative I- No new construction No new construction 8 ft to 9 ft 8 ft to 9 ft 8 ft to 9 ft 8 ft to 0 ft ft to 8 ft ft to 57 ft ft to 55 ft 5 ft to 7 ft ft to 5 ft ft to 5 ft ft to ft ft to ft ft to ft Retaining walls with similar heights are located in the District of Columbia along the Southeast- Southwest Freeway at the following locations (Parsons, 00): From 7 th Street, SW to 5 th Street, SW, an existing retaining wall varies from 7.0 to 0.5 feet in height. From th Street, SE to 5 th Street, SE, an existing retaining wall varies from.5 feet to.5 feet in height. Between 5 th Street SW and the D Street Tunnel, an existing retaining wall varies from 7.0 to.5 feet in height. Each of the Interchange/Access Road Alternatives described below are compatible with any of the St. Elizabeths Campus Redevelopment Alternatives, shown in Volume I of this Final EIS. - Final EIS Volume II Transportation Improvements

13 Transportation Improvement Alternatives C..a Interchange/Access Road Alternative I-0 Alternative I-0 has been studied in detail in this Final EIS to provide an assessment of impacts that would occur if FHWA does not approve modifications to the Malcolm X/I-95 interchange eliminating the potential to construct the access road from Malcolm X into the St. Elizabeths West Campus. Under Alternative I-0, 70 percent of the traffic accessing the DHS Headquarters would arrive via Firth Sterling Avenue. The intersection of Firth Sterling Avenue with Stevens and Barry Roads, located a block north of St. Elizabeths West Campus, would be re-configured to allow a functional and safe tie-in of a new access road to the West Campus. DDOT s plans for a new street car track will be under construction shortly, and so the intersection design assumes the street car track along Firth Sterling Avenue as an existing condition. However, the Frontage Road and Stevens Road legs of the intersection would be realigned. A slip ramp would be constructed for movements from eastbound Firth Sterling Avenue to the West Campus via the new access road. Barry Road would be a one-way road heading northbound. After crossing the northwest perimeter of St. Elizabeths West Campus, the access road would run parallel to I-95, before tying into a four-lane, two-way gated entrance to the south of the West Campus Cemetery. Retaining walls would border the access road on both sides. The height of the east retaining wall would vary between 8 and 0 ½ feet. The west retaining wall would be 8 ½ feet high. Alternative I-0 would not meet the project s purpose and needs because it would not provide adequate capacity to handle the traffic generated by the DHS Headquarters. Having 70 percent of the traffic accessing the DHS Headquarters arrive from Firth Sterling Avenue would create queuing problems on Firth Sterling Avenue from vehicles waiting to clear security checkpoints on the campus. In addition, without additional access points, the volume of traffic created by the DHS Headquarters would cause intersections at Firth Sterling Avenue to fail. Under Alternative I-0, land along Firth Sterling Avenue would need to be acquired to allow for widening of the roadway and reconfiguration of the intersection with Stevens Road and Barry Road. Alternative I-0, shown with Campus Redevelopment Alternative, is presented in Figure -. The Firth Sterling Avenue interchange improvements are shown in Figure -. Graphics of Alternative I-0 with Campus Redevelopment Alternatives and 5 can be found in Volume IV, Final EIS Volume II Transportation Improvements -

14 Transportation Improvement Alternatives Appendix F. Alternative I-0 has been studied with Campus Redevelopment Alternative in this Volume of the EIS to present the worst case impacts that would occur if interchange improvements are not made to the Malcolm X/I-95 interchange and the access road is not constructed from Malcolm X Avenue into the West Campus..C..b Interchange/Access Road Alternative I- Alternative I- includes all of the improvements described in Alternative I-0. Under this Alternative, south of the new gated entrance, the access road would continue to parallel I-95 and cross onto Shepherd Parkway. Approximately 750 feet north of Malcolm X Avenue, the road would turn east to intersect with Malcolm X Avenue. Between the new gated entrance and Malcolm X Avenue, the east retaining wall would rise from 5 to ½ feet, and the west retaining wall would vary from 8 to ½ feet. South of Malcolm X Avenue intersection, the east retaining wall would reach a maximum height of 8 ½ feet, and the west retaining wall would reach a maximum height of feet. Under Alternative I-, the Malcolm X/I-95 interchange would be modified, and the cloverleaf loop that connects northbound I-95 to westbound Malcolm X Avenue would be closed. A flyover on-ramp would diverge from the access road, approximately,800 feet north of Malcolm X Avenue, and would connect to southbound I-95. The ramp would cross over both northbound and southbound I-95 and merge with the latter south of Malcolm X Avenue. The total length of the flyover ramp and merge lane would be approximately,900 feet. The height of the flyover would have a minimum 5-foot clearance under the structure, and may reach 0- feet at the top. A new off-ramp would provide access to Malcolm X Avenue from northbound I-95. This ramp would begin approximately,000 feet south of Malcolm X Avenue, remaining close to the interstate before turning east approximately 750 feet south of Malcolm X Avenue. The southbound I-95 bridge span over Malcolm X Avenue would be widened in order to accommodate the flyover merging lane. Under Alternative I-, land along Firth Sterling Avenue would need to be acquired to allow for widening of the roadway and reconfiguration of the intersection with Stevens Road and Barry Road. In addition, land would be needed from the Shepherd Parkway to construct the interchange improvements and the proposed access road. - Final EIS Volume II Transportation Improvements

15 Transportation Improvement Alternatives Alternative I-, in conjunction with one of the Campus Redevelopment Alternatives presented in Volume I and one of the MLK Avenue Alternatives presented below, would meet the project s purpose and need. Alternative I-, shown with Campus Redevelopment Alternative, is presented in Figures - and -. Graphics of Alternative I- with Campus Redevelopment Alternatives and 5 can be found in Volume IV, Appendix F..C..c Interchange/Access Road Alternative I- Alternative I- is similar to Alternative I- with three exceptions: ) the retaining walls between the new gated entrance and Malcolm X Avenue would be higher; ) additional construction would take place in association with access to Malcolm X Avenue; and ) there would be no flyover ramp. Under Alternative I-, the east retaining walls would vary in height from 8 ½ to 8 ½ feet between the new access gate and Malcolm X Avenue. The west retaining walls would vary between ½ and ½ feet high in the same stretch. In Alternative I-, the access road would begin to turn east approximately,000 feet before it reaches Malcolm X Avenue to accommodate a loop road that would return access road traffic to I-95 north. Alternative I- also would close the cloverleaf loop that connects northbound I-95 to westbound Malcolm X Avenue. As in Alternative I-, a new off-ramp beginning approximately,000 feet south of Malcolm X Avenue would provide access to Malcolm X Avenue from northbound I-95. Alternative I- would include an on-ramp from westbound Malcolm X Avenue to I-95 north. Alternative I- would require the closing of the existing northbound South Capitol Street offramp to Malcolm X Avenue and the partial closing of the northbound South Capitol Street onramp from Malcolm X Avenue, allowing for only right turns from westbound Malcolm X Avenue. These ramp closures would allow for the critical elimination of the existing traffic signal at Malcolm X Avenue and the northbound South Capitol Street ramps. Final EIS Volume II Transportation Improvements -5

16 Transportation Improvement Alternatives Under Alternative I-, land along Firth Sterling Avenue would need to be acquired to allow for widening of the roadway and reconfiguration of the intersection with Stevens Road and Barry Road. In addition, land would be needed from the Shepherd Parkway to construct the interchange improvements and the proposed access road. Alternative I-, in conjunction with one of the Campus Redevelopment Alternatives presented in Volume I and one of the MLK Avenue Alternatives presented below, would meet the project s purpose and need. Alternative I- is presented in Figures -5 and -6. It is shown with Campus Redevelopment Alternative. Graphics of Alternative I- with Campus Redevelopment Alternatives and 5 can be found in Volume IV, Appendix F..C..d Interchange/Access Road Alternative I- Alternative I- is also similar to Alternative I- with two exceptions: ) the retaining walls between the new gated entrance and Malcolm X Avenue would be higher; and ) additional construction would take place in association with access to Malcolm X Avenue. Under Alternative I-, the east retaining walls would vary in height from 8 ½ to 0 ½ feet between the new access gate and Malcolm X Avenue. The west retaining walls would vary between and feet high in the same stretch. In Alternative I-, a median would be constructed along Malcolm X Avenue east and west of the intersection with the proposed access road. This new Malcolm X Avenue median would extend westward to the Bolling AFB entrance, requiring the lengthening of the two I-95 bridges over Malcolm X Avenue, as well as the widening of the Malcolm X Avenue bridge over South Capitol Street. New off- and on-ramps connecting southbound I-95 to and from Malcolm X Avenue are also planned in what would be the median between I-95 and South Capitol Street. These two diamond ramps would provide direct access between I-95 southbound and Malcolm X Avenue, thereby permitting the elimination of the following ramps: -6 Final EIS Volume II Transportation Improvements

17 Transportation Improvement Alternatives Partial closing of the southbound South Capitol Street off- and on-ramps to and from Malcolm X Avenue. Only the right turn into and out of the Bolling AFB entrance would be maintained along these two ramps. The existing South Capitol Street northbound off- and on-ramps to and from Malcolm X Avenue would be closed. This three-lane ramp would replace existing access to Malcolm X Avenue from southbound I-95. As in Alternatives I- and I-, Alternative I- would close the cloverleaf loop that connects northbound I-95 to westbound Malcolm X. Under Alternative I-, land along Firth Sterling Avenue would need to be acquired to allow for widening of the roadway and reconfiguration of the intersection with Stevens Road and Barry Road. In addition, land would be needed from the Shepherd Parkway to construct the interchange improvements and the proposed access road. Alternative I-, in conjunction with one of the Campus Redevelopment Alternatives presented in Volume I and one of the MLK Avenue Alternatives presented below, would meet the project s purpose and need. Alternative I- is presented in Figures -7 and -8 and is shown with Campus Redevelopment Alternative. Graphics of Alternative I- shown with Campus Redevelopment Alternatives and 5 can be found in Volume IV, Appendix F..C..e Interchange/Access Road Alternative I- Plans for this alternative are similar to the other alternatives. Differences exist in the height of the retaining walls in the northern portion of Shepherd Parkway and in the connection of Malcolm X Avenue with north-south traffic arteries. Under Alternative I-, the east retaining walls would vary from 5 to 8 feet tall between the new gated entrance and Malcolm X Avenue. The west retaining walls would vary between 7 ½ and ½ feet high in the same stretch. The access road would intersect Malcolm X Avenue approximately 50 feet farther east in Alternative I- than in the other alternatives. A new single point urban interchange at I-95 and Malcolm X Avenue would also require a new signalized intersection between Malcolm X Avenue and the ramps to/from I-95. The on- and Final EIS Volume II Transportation Improvements -7

18 Transportation Improvement Alternatives off-ramps connecting Malcolm X Avenue to northbound I-95 would require the closing of the two existing cloverleaf loops. The on-ramp from Malcolm X Avenue would enter northbound I-95 approximately,600 feet north of Malcolm X Avenue. The off-ramp connecting I-95 northbound to Malcolm X Avenue would begin approximately,800 feet south of Malcolm X Avenue. The proposed southbound I-95 ramps to and from Malcolm X Avenue would require the closing of the existing off-ramp from southbound I-95 to South Capitol Street, as well as the closing of the two existing northbound South Capitol Street ramps to and from Malcolm X Avenue. As in Alternative I-, the southbound South Capitol Street ramps to and from Malcolm X would be partially closed, allowing only right turns into and out of the Bolling AFB entrance. Under Alternative I-, land along Firth Sterling Avenue would need to be acquired to allow for widening of the roadway and reconfiguration of the intersection with Stevens Road and Barry Road. In addition, land would be needed from the Shepherd Parkway to construct the interchange improvements and the proposed access road. Alternative I-, in conjunction with one of the Campus Redevelopment Alternatives presented in Volume I and one of the MLK Avenue Alternatives presented below, would meet the project s purpose and need. Alternative I- is presented in Figures -9 and -0 with Campus Redevelopment Alternative. Graphics of Alternative I- with Campus Redevelopment Alternatives and 5 can be found in Volume IV, Appendix F..C. MLK Avenue Alternatives Two alternatives were considered for improvements to MLK Avenue, which fronts the eastern boundary of the St. Elizabeths West Campus, separating it from the East Campus. The following alternatives for improvements to MLK Avenue are compatible with any of the Interchange/Access Road Alternatives described above. Improvements to MLK Avenue would be funded by GSA -8 Final EIS Volume II Transportation Improvements

19 Transportation Improvement Alternatives C..a MLK Avenue Alternative MLK Avenue is currently comprised of four 0-foot wide lanes, with 5-foot wide sidewalks. Under MLK Avenue Alternative, MLK Avenue would be widened approximately 5 to 7 feet to the east from Pomeroy Road to south of Elm Street, a distance of 0 feet. An existing historic wall along the west side of MLK Avenue from Gate through Redwood Drive allows for widening only on the east side. Widening to the east side of MLK Avenue would require the use of land from the St. Elizabeths East Campus. New sidewalks would be also be constructed along the east side of MLK Avenue and would be separated from the roadway by greenspace. Both MLK Avenue alternatives would examine the possibility of increasing sidewalks on the East Campus to 6 to 8 feet as recommended in the Great Streets Framework Plan. Final design would need to be coordinated with DDOT and the Unified Communications Center as widening MLK Avenue would impact its existing security berm. Depending upon the width of the sidewalk, the total widening of the road plus sidewalks would be 0-feet to -feet. Under MLK Avenue Alternative, the 0-foot lanes in each direction would be widened to an -foot through lane and a -foot outside through/right turn shared lane. Ten-foot wide left turn lanes are proposed at Gates and (Cedar Street and Pine Street), also in both the northbound and southbound directions. The proposed left turn lanes would include northbound left turn storage length of 95 feet at Gate and 60 feet at Gate. The southbound left turn storage would be 0 feet at Gate and 95 feet at Gate. A 0-foot long painted median between left turn storage areas is proposed. New traffic signals are proposed at West Campus Gates and. In conjunction with any of the Campus Redevelopment Alternatives and one of the Interchange Alternatives, MLK Avenue Alternative would meet the project s needs. MLK Avenue Alternative is presented in Figure -..C..b MLK Avenue Alternative Under MLK Avenue Alternative, MLK Avenue would be widened approximately 5 to feet to the east from Pomeroy Road south of Elm Street, a distance of 00 feet. As with Alternative, the roadway could only be widened to the east side requiring land from the St. Elizabeths East Campus. Also, as in Alternative, new sidewalks would be also be constructed along the east Final EIS Volume II Transportation Improvements -9

20 Transportation Improvement Alternatives side of MLK Avenue and would be separated from the roadway by greenspace. Both MLK Avenue alternatives would examine the possibility of increasing sidewalks on the East Campus to 6 to 8 feet as recommended in the Great Streets Framework Plan. Final design would need to be coordinated with DDOT and the Unified Communications Center as widening MLK Avenue would impact its existing security berm. Depending upon the width of the sidewalk, the total widening of the road plus sidewalks would be 0-feet to 5-feet. Under MLK Avenue Alternative, the existing northbound and southbound lanes would be widened to an - to -foot outside through/right turn shared lane and an -foot through lane in each direction. Ten-foot wide left turn lanes are proposed at Gates and (Cedar Street and Pine Street), also in both the northbound and southbound directions. The proposed left turn lanes would include northbound left turn storage length of 95 feet at Gate and 60 feet at Gate. The southbound left turn storage would be 0 feet at Gate and 95 feet at Gate. A -foot long raised median is proposed along MLK Avenue between the left turn storage areas, with a -foot uninterrupted median at the intersection to allow for left turn lanes. New traffic signals are proposed at West Campus Gates and. Under MLK Avenue Alternative, 5-foot to 8-foot wide sidewalks would be constructed along the east side of MLK Avenue. In conjunction with one of the Campus Redevelopment Alternatives and one of the Intersection Alternatives, MLK Avenue Alternative would meet the purpose and needs of the project. MLK Avenue Alternative- is presented in Figure -..D Transportation Improvements - Preferred Alternatives In accordance with 0 CFR 50.(e), which requires that a preferred alternative be identified in this Final Environmental Impact Statement, the interchange preferred alternative is Alternative I- and the MLK Avenue widening preferred alternative is MLK Alternative. GSA's identification of these alternatives as preferred is based on coordination with, and is subject to, subsequent final determinations of the Federal Highway Administration and the DC Department of Transportation, agencies that are anticipated to base their approvals in part upon this Final Environmental Impact Statement. 9-0 Final EIS Volume II Transportation Improvements

21 Transportation Improvement Alternatives Figure - Final EIS Volume II Transportation Improvements -

22 Transportation Improvement Alternatives This page intentionally left blank. - Final EIS Volume II Transportation Improvements

23 Transportation Improvement Alternatives Figure - Final EIS Volume II Transportation Improvements -

24 Transportation Improvement Alternatives This page intentionally left blank - Final EIS Volume II Transportation Improvements

25 Transportation Improvement Alternatives Figure - Final EIS Volume II Transportation Improvements -5

26 Transportation Improvement Alternatives This page intentionally left blank. -6 Final EIS Volume II Transportation Improvements

27 Transportation Improvement Alternatives Figure - Final EIS Volume II Transportation Improvements -7

28 Transportation Improvement Alternatives This page intentionally left blank -8 Final EIS Volume II Transportation Improvements

29 Transportation Improvement Alternatives Figure -5 Final EIS Volume II Transportation Improvements -9

30 Transportation Improvement Alternatives This page intentionally left blank. -0 Final EIS Volume II Transportation Improvements

31 Transportation Improvement Alternatives Figure -6 Final EIS Volume II Transportation Improvements -

32 Transportation Improvement Alternatives This page intentionally left blank - Final EIS Volume II Transportation Improvements

33 Transportation Improvement Alternatives Figure -7 Final EIS Volume II Transportation Improvements -

34 Transportation Improvement Alternatives This page intentionally left blank. - Final EIS Volume II Transportation Improvements

35 Transportation Improvement Alternatives Figure -8 Final EIS Volume II Transportation Improvements -5

36 Transportation Improvement Alternatives This page intentionally left blank -6 Final EIS Volume II Transportation Improvements

37 Transportation Improvement Alternatives Figure -9 Final EIS Volume II Transportation Improvements -7

38 Transportation Improvement Alternatives This page intentionally left blank. -8 Final EIS Volume II Transportation Improvements

39 Transportation Improvement Alternatives Figure -0 Final EIS Volume II Transportation Improvements -9

40 Transportation Improvement Alternatives This page intentionally left blank -0 Final EIS Volume II Transportation Improvements

41 Transportation Improvement Alternatives Figure - Mapping of the St. Elizabeths East Campus is based on the latest available GIS data from the District of Columbia and does not illustrate recent development such as the DC Unified Communications Center. Final EIS Volume II Transportation Improvements -

42 Transportation Improvement Alternatives 5 This page intentionally left blank - Final EIS Volume II Transportation Improvements

Transportation Improvements

Transportation Improvements Transportation Improvements 0 0 Volume II of the Final EIS for the DHS Headquarters consolidation at St. Elizabeths includes analysis to transportation improvements for the DHS Headquarters Consolidation

More information

PUBLIC HEARING. DRAFT Environmental Impact Statement. Matthews Memorial Baptist Church Washington, DC October 18, National Capital Region

PUBLIC HEARING. DRAFT Environmental Impact Statement. Matthews Memorial Baptist Church Washington, DC October 18, National Capital Region National Capital Region DRAFT Environmental Impact Statement PUBLIC HEARING Matthews Memorial Baptist Church Washington, DC October 18, 2007 Introduction Welcome and team introduction Hearing procedures

More information

ALTERNATIVES. NCDOT made an early decision to first determine how to build the project (construction method) followed by what to build (alternatives).

ALTERNATIVES. NCDOT made an early decision to first determine how to build the project (construction method) followed by what to build (alternatives). III. ALTERNATIVES A. CONSTRUCTION METHOD ALTERNATIVES NCDOT made an early decision to first determine how to build the project (construction method) followed by what to build (alternatives). One of the

More information

vi. master plan amendment concept

vi. master plan amendment concept vi. master plan amendment concept vi. master plan AMENDMENT concept Overview of the Planning Process The Master Plan for the Federal Use Parcel of the East Campus of St. Elizabeths is an Amendment to

More information

7.5 Impacts on the Section 4(f) Properties

7.5 Impacts on the Section 4(f) Properties constructive use, such as noise, air quality and visual impacts were also assessed. It was determined that this project would not introduce changes of an external nature that would affect the recreational

More information

Draft Evaluation of Alignment Alternatives Methodology and Results Report. 3 nd Draft. May 2011(rev June 17, 2011)

Draft Evaluation of Alignment Alternatives Methodology and Results Report. 3 nd Draft. May 2011(rev June 17, 2011) Draft Evaluation of Alignment Alternatives Methodology and Results Report 3 nd Draft May 2011(rev June 17, 2011) Draft Evaluation of Alignment Alternatives Methodology and Results Report Table of Contents

More information

PROPOSED IMPROVEMENTS

PROPOSED IMPROVEMENTS IV. PROPOSED IMPROVEMENTS The proposed improvements for each alternative carried forward are discussed below. A. FUNCTIONAL CLASSIFICATION AND ROADWAY CROSS-SECTIONS The classifications of the roadways

More information

APPENDIX D: Visual and Aesthetic Conditions for NCCU Station Refinement. Durham-Orange Light Rail Transit Project

APPENDIX D: Visual and Aesthetic Conditions for NCCU Station Refinement. Durham-Orange Light Rail Transit Project APPENDIX D: Visual and Aesthetic Conditions for NCCU Station Refinement Durham-Orange Light Rail Transit Project October 2016 1. Introduction The Combined FEIS/ROD summarizes the effects of the D-O LRT

More information

NORTH-SOUTH CORRIDOR STUDY EXECUTIVE SUMMARY. Executive Summary

NORTH-SOUTH CORRIDOR STUDY EXECUTIVE SUMMARY. Executive Summary Executive Summary Background As congestion continues to affect mobility in the region, the Ozarks Transportation Organization (OTO) is particularly concerned with traffic movement. The North-South Corridor

More information

112th Avenue Light Rail Options Concept Design Report JUNE 2010 PREPARED FOR PREPARED BY TBG PGH

112th Avenue Light Rail Options Concept Design Report JUNE 2010 PREPARED FOR PREPARED BY TBG PGH 112th Avenue Light Rail Options Concept Design Report JUNE 2010 PREPARED FOR PREPARED BY TBG060310124909PGH C ontents Introduction 1 Project Overview 1 Public Involvement and Technical Coordination 4 Description

More information

4.1 Build Alternative 1 Construction Phasing

4.1 Build Alternative 1 Construction Phasing SECTION 4 Implementation Plan This section discusses potential segmentation of the build alternatives into multiple projects for implementation of improvements to the NSH from Rabbit Creek Road to 36th

More information

Visual and Aesthetics

Visual and Aesthetics Such a connection could accommodate timed transfers and improve connections between local transit service and Presidio Shuttle service. Level of Service The results of the analysis are provided on a route-by-route

More information

St Elizabeths Master Plan

St Elizabeths Master Plan Department of Homeland Security Consolidated Headquarters at St. Elizabeths Washington, DC Presentation to CFA St Elizabeths Master Plan November 20, 2008 Preserving The Legacy / Realizing Potential 1

More information

The transportation system in a community is an

The transportation system in a community is an 7 TRANSPORTATION The transportation system in a community is an important factor contributing to the quality of life of the residents. Without a sound transportation system to bring both goods and patrons

More information

East Corridor Final Environmental Impact Statement

East Corridor Final Environmental Impact Statement East Corridor Final Environmental Impact Statement Alternatives Considered Operating Plan The requirements for opening day operations versus year 2030 are based on ridership and operations. Opening day

More information

Issues Requiring Future Study

Issues Requiring Future Study Issues Requiring Future Study Transportation planning is an ongoing process that tends to identify new issues as it finds solutions for others. Some issues are so complex that a solution to one problem

More information

PREPARED FOR: PLATTEVIEW ROAD CORRIDOR STUDY EXECUTIVE SUMMARY

PREPARED FOR: PLATTEVIEW ROAD CORRIDOR STUDY EXECUTIVE SUMMARY PREPARED FOR: PLATTEVIEW ROAD CORRIDOR STUDY EXECUTIVE SUMMARY SEPTEMBER 2016 Introduction The Platteview Road Corridor Study was led by the Metropolitan Area Planning Agency (MAPA) with assistance from

More information

I-70 Corridor Enhancement Plan

I-70 Corridor Enhancement Plan i - Table of Contents Table of Contents Chapter I Overview Chapter II Bridge and Roadway Improvements Chapter III Landscape Enhancements Chapter IV Riparian Corridors Chapter V Showcase Missouri Plan Chapter

More information

Eastern Terminus TECHNICAL MEMORANDUM CENTRAL BROWARD EAST-WEST TRANSIT ANALYSIS BROWARD COUNTY, FLORIDA

Eastern Terminus TECHNICAL MEMORANDUM CENTRAL BROWARD EAST-WEST TRANSIT ANALYSIS BROWARD COUNTY, FLORIDA Eastern Terminus TECHNICAL MEMORANDUM CENTRAL BROWARD EAST-WEST TRANSIT ANALYSIS BROWARD COUNTY, FLORIDA FINANCIAL PROJECT ID NUMBER 411189-2-22-01 FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 4 Prepared

More information

Project Overview. Fairfax County Parkway Widening Fairfax County. Get Involved. Public Information Meeting. Contact Information

Project Overview. Fairfax County Parkway Widening Fairfax County. Get Involved. Public Information Meeting. Contact Information Get Involved VDOT representatives will review and evaluate information received as a result of this meeting. Please fill out the comment sheet provided in this brochure if you have any comments or questions.

More information

Existing Transportation System 5-1

Existing Transportation System 5-1 5-1 The Jackson County transportation system is served by several modes of transportation including streets and highways, multi-modal, non-motorized, rail, and aviation. While the focus of the transportation

More information

Reclaiming Old West Broad Street: I-16 Ramp Removal Study

Reclaiming Old West Broad Street: I-16 Ramp Removal Study Reclaiming Old West Broad Street: I-16 Ramp Removal Study Community Meeting Summary July 15, 2014 The first community meeting for Phase II of the I-16 Ramp Removal Study was held on July 15, 2014, at the

More information

STATUS REPORT ENVIRONMENTAL REVIEW FOR IMPROVED ACCESS. at the NORTH WHITE PLAINS STATION

STATUS REPORT ENVIRONMENTAL REVIEW FOR IMPROVED ACCESS. at the NORTH WHITE PLAINS STATION STATUS REPORT ENVIRONMENTAL REVIEW FOR IMPROVED ACCESS at the NORTH WHITE PLAINS STATION May 2009 Status Report- Environmental Review for Improved Access at the North White Plains Station A. INTRODUCTION

More information

SUMMARY. Support the Southeast Arkansas Regional Intermodal Facility.

SUMMARY. Support the Southeast Arkansas Regional Intermodal Facility. SUMMARY THE I-69 LOCATION STUDY The proposed I-69 Location Study from El Dorado to McGehee, Arkansas, represents one section (Section of Independent Utility No. 13) of the nationally designated I-69 Corridor

More information

A. INTRODUCTION B. PROJECT LOCATION

A. INTRODUCTION B. PROJECT LOCATION Chapter 1: Project Description A. INTRODUCTION The Lower Manhattan Development Corporation (LMDC), a subsidiary of the New York State Urban Development Corporation, doing business as the Empire State Development

More information

North Carolina Department of Transportation Project Development and Environmental Analysis Branch

North Carolina Department of Transportation Project Development and Environmental Analysis Branch North Carolina Department of Transportation Project Development and Environmental Analysis Branch Citizens Informational Workshop I-85, from I-485 to NC 73 Mecklenburg and Cabarrus Counties October 30,

More information

Alternatives Development Three conceptual alternatives were developed for the Race Road/Jessup Village Planning Study and are described below:

Alternatives Development Three conceptual alternatives were developed for the Race Road/Jessup Village Planning Study and are described below: Race Road/Jessup Village Planning Study (H550601) Project Newsletter Spring 2015 Project Description The Study Team, consisting of staff from Anne Arundel County (Department of Public Works and Department

More information

Southern Gateway Project and Public Green

Southern Gateway Project and Public Green Southern Gateway Project and Public Green Transportation and Trinity River Project Committee May 23, 2016 Purpose of Presentation Provide the history and an overview of the Southern Gateway Project (SGP)

More information

PROJECT BACKGROUND. Preliminary Design Scope and Tasks

PROJECT BACKGROUND. Preliminary Design Scope and Tasks PROJECT BACKGROUND Preliminary Design Scope and Tasks The purpose of this Study is the development of preliminary designs for intersection improvements for Trunk Highway (TH) 36 at the intersections of

More information

FINAL MITIGATION PLAN to address

FINAL MITIGATION PLAN to address CENTRAL CORRIDOR LRT STATE CAPITOL MALL HISTORIC FINAL MITIGATION PLAN February 2010 FINAL MITIGATION PLAN to address Adverse Effects of the Central Corridor LRT Project on the State Capitol Mall Historic

More information

5.8 Visual Resources and Aesthetic Qualities

5.8 Visual Resources and Aesthetic Qualities I-70 East Supplemental Draft EIS 5.8 Visual Resources and Aesthetic Qualities 5.8 Visual Resources and Aesthetic Qualities This section discusses the visual resources and aesthetic qualities of the study

More information

(blank page) WestConnex New M Roads and Maritime Services Environmental impact statement

(blank page) WestConnex New M Roads and Maritime Services Environmental impact statement (blank page) WestConnex New M5 5-42 (blank page) WestConnex New M5 5-44 5.5 Tunnels 5.5.1 Main alignment tunnels The main alignment tunnels would be about nine kilometres long, with the western tunnel

More information

January 29, 2015 Page 1 of Annual Status Report St. Elizabeths Programmatic Agreement. PA Ref. Line Begin End. Description Timeframe Category

January 29, 2015 Page 1 of Annual Status Report St. Elizabeths Programmatic Agreement. PA Ref. Line Begin End. Description Timeframe Category 2014 Annual Report Page 1 of 7 60 64 Finalize deed conveyance per Exchange Not Specified Recitals Completed. Agreement to Transfer Five Buildings and Related Land From DC to GSA 71 74 Finalize Occupancy

More information

Right-of-Way Acquisitions and Relocations Technical Memorandum

Right-of-Way Acquisitions and Relocations Technical Memorandum Right-of-Way Acquisitions and Relocations Technical Memorandum Southeast Extension Project Lincoln Station to RidgeGate Parkway Prepared for: Federal Transit Administration Prepared by: Denver Regional

More information

Mavis Road Class Environmental Assessment

Mavis Road Class Environmental Assessment Mavis Road Class Environmental Assessment Public Information Centre #2 Wednesday November 9, 2016 6:00 to 8:00 p.m. Please sign in and complete a comment sheet Review the displays on your own or join in

More information

State Highway 121 Southwest Parkway. Fort Worth s Transportation Success Story in Design and Cooperation

State Highway 121 Southwest Parkway. Fort Worth s Transportation Success Story in Design and Cooperation State Highway 121 Southwest Parkway Fort Worth s Transportation Success Story in Design and Cooperation Greater Fort Worth Association of Realtors October 24, 2007 Presented by: Dan Lamers, P.E. North

More information

Appendix E Section 4(f) Evaluation

Appendix E Section 4(f) Evaluation Appendix E Section 4(f) Evaluation Appendix E Draft Section 4(f) Evaluation E.1 Introduction This appendix addresses a federal regulation known as Section 4(f), which protects parks, recreation areas,

More information

Access Management: An Overview

Access Management: An Overview Figures 1-5 Below Evolution of development along a highway. In the early stages, land along the road is used for farming with little traffic generated. As time passes, the highway corridor becomes a de

More information

PROJECT STATEMENT LOCATION/DESIGN PUBLIC HEARING. 19 th AVENUE NORTH EXTENSION PROJECT FROM SPRINGDALE DRIVE TO NORTH 2 ND STREET/U.S.

PROJECT STATEMENT LOCATION/DESIGN PUBLIC HEARING. 19 th AVENUE NORTH EXTENSION PROJECT FROM SPRINGDALE DRIVE TO NORTH 2 ND STREET/U.S. PROJECT STATEMENT LOCATION/DESIGN PUBLIC HEARING 19 th AVENUE NORTH EXTENSION PROJECT FROM SPRINGDALE DRIVE TO NORTH 2 ND STREET/U.S. 67 HEARING LOCATION: ERICKSEN COMMUNITY CENTER 1401 11 TH AVENUE NORTH

More information

New Stanton Project Update July 3, 2012

New Stanton Project Update July 3, 2012 New Stanton Project Update July 3, 2012 The Needs BACKGROUND INFO I-70 Geometric Concerns Substandard Horizontal & Vertical Clearance at Center Ave. Bridge (The Center Avenue Bridge is Replaced in all

More information

Mississippi Skyway Preliminary Engineering Report

Mississippi Skyway Preliminary Engineering Report EXECUTIVE SUMMARY Mississippi Skyway Preliminary Engineering Report CITY OF RAMSEY, MINNESOTA DECEMBER 2014 City of RAMSEY EXECUTIVE SUMMARY Project Need and Intent The Mississippi Skyway pedestrian bridge

More information

1.0 Introduction. Purpose and Basis for Updating the TMP. Introduction 1

1.0 Introduction. Purpose and Basis for Updating the TMP. Introduction 1 1.0 Introduction The Town of Castle Rock is situated between the metropolitan areas of Denver and Colorado Springs, amidst a unique terrain of rolling hills, mesas, ravines, and waterways. Like many Front

More information

Meeting Purpose: Date and Time: Location: Attendance: Handouts:

Meeting Purpose: Date and Time: Location: Attendance: Handouts: Meeting Purpose: Date and Time: Location: Attendance: Handouts: PA Turnpike / I-95 Interchange Project Design Advisory Committee (DAC)/Public Officials Meeting #8 April 12, 2012 at 1:30 p.m. Project Office,

More information

DRAFT SECTION 4(f) EVALUATION INTERSTATE 73 FEIS: I-95 to I-73/I-74 in North Carolina

DRAFT SECTION 4(f) EVALUATION INTERSTATE 73 FEIS: I-95 to I-73/I-74 in North Carolina DRAFT SECTION 4(f) EVALUATION INTERSTATE 73 FEIS: I-95 to I-73/I-74 in North Carolina 1.0 INTRODUCTION Section 4(f) of the Department of Transportation Act of 1966, 49 U.S.C. 303, requires that prior to

More information

CHAPTER 7: Transportation, Mobility and Circulation

CHAPTER 7: Transportation, Mobility and Circulation AGLE AREA COMMUNITY Plan CHAPTER 7 CHAPTER 7: Transportation, Mobility and Circulation Transportation, Mobility and Circulation The purpose of the Transportation, Mobility and Circulation Chapter is to

More information

WHAT IS THE PURPOSE OF THE OPEN HOUSE?

WHAT IS THE PURPOSE OF THE OPEN HOUSE? WHAT IS THE PURPOSE OF THE OPEN HOUSE? OPEN HOUSE PURPOSE The purpose of the open house is to provide an update on the study process and introduce the preliminary concept alternatives. The open house provides

More information

A raised and landscaped median will be constructed in South College Avenue between Trilby Road and Skyway Drive.

A raised and landscaped median will be constructed in South College Avenue between Trilby Road and Skyway Drive. 5.0 ACCESS CONTROL PLAN This section presents the Access Control Plan Update which has been formulated through the considerable input of the governing agencies, business owners, organized homeowner groups,

More information

Appendix E Preliminary Location Hydraulic Study

Appendix E Preliminary Location Hydraulic Study Appendix E Prepared for: State of Alaska Department of Transportation and Public Facilities Prepared by: HDR Alaska, Inc. 2525 C Street, Suite 305 Anchorage, Alaska 99503 February 2014 This page intentionally

More information

4. INITIAL CONCEPT DEVELOPMENT AND SCREENING

4. INITIAL CONCEPT DEVELOPMENT AND SCREENING 4. INITIAL CONCEPT DEVELOPMENT AND SCREENING A coordinated effort by the project team and members of the three oversight committees (Citizen Advisory, Technical Advisory, and Steering) led to 17 initial

More information

1.0 INTRODUCTION 1.1 TH 14 WEST STUDY AREA Project Description Functional Classification Purpose of the Project

1.0 INTRODUCTION 1.1 TH 14 WEST STUDY AREA Project Description Functional Classification Purpose of the Project 1.0 INTRODUCTION 1.1 TH 14 WEST STUDY AREA 1.1.1 Project Description The Trunk Highway (TH) 14 West Corridor is a two-lane roadway approximately 22 miles in length. Located in Nicollet County, the corridor

More information

LOS ANGELES MISSION COLLEGE MASTER PLAN Master Plan DESIGN & DEVELOPMENT PRINCIPLES

LOS ANGELES MISSION COLLEGE MASTER PLAN Master Plan DESIGN & DEVELOPMENT PRINCIPLES LOS ANGELES MISSION COLLEGE MASTER PLAN DESIGN & DEVELOPMENT PRINCIPLES 34 Quality Learning Along the Arroyo PROGRAM SUMMARY BY PROJECT The following are program summaries for each of the projects planned

More information

3.8 CUMULATIVE IMPACTS

3.8 CUMULATIVE IMPACTS TIER II DRAFT ENVIRONMENTAL IMPACT STATEMENT 3.8 CUMULATIVE IMPACTS 3.8.1 What are the results of the Cumulative Impacts analysis? The No Action Alternative along with the four action alternatives were

More information

IMPLEMENTATION STRATEGIES. In This Chapter. Goals & Strategies 182 Project List 183 Future Land Use 186 CHAPTER 11 IMPLEMENTATION STRATEGIES

IMPLEMENTATION STRATEGIES. In This Chapter. Goals & Strategies 182 Project List 183 Future Land Use 186 CHAPTER 11 IMPLEMENTATION STRATEGIES In This Chapter Goals & Strategies 182 Project List 183 Future Land Use 186 11 IMPLEMENTATION STRATEGIES NORTH AUGUSTA, SC 2017 COMPREHENSIVE PLAN 179 Individual commitment to a group effort that is what

More information

AUTO CIRCULATION & PARKING

AUTO CIRCULATION & PARKING CHAPTER 5 Chapter 5 Auto Circulation & Parking AUTO CIRCULATION & PARKING Parking use and automobile circulation have been topics of many discussions on street corners as well as at public workshops and

More information

Project Overview. Get Involved. Public Information Meeting. Contact Information

Project Overview. Get Involved. Public Information Meeting. Contact Information Get Involved VDOT representatives will review and evaluate information received as a result of this meeting. Please fill out the comment sheet provided in this brochure if you have any comments or questions.

More information

STATE OF TENNESSEE DEPARTMENT OF TRANSPORTATION ENVIRONMENTAL DIVISION

STATE OF TENNESSEE DEPARTMENT OF TRANSPORTATION ENVIRONMENTAL DIVISION STATE OF TENNESSEE DEPARTMENT OF TRANSPORTATION ENVIRONMENTAL DIVISION Suite 900 - James K. Polk Building 505 Deaderick Street Nashville, Tennessee 37243-0334 MEMORANDUM TO: FROM: Files Joe W. Matlock,

More information

2013 Annual Status Report St. Elizabeths Programmatic Agreement. January 29, 2014 Page 1 of 8. PA Ref. Line Begin End. Description Timeframe Category

2013 Annual Status Report St. Elizabeths Programmatic Agreement. January 29, 2014 Page 1 of 8. PA Ref. Line Begin End. Description Timeframe Category Page 1 of 8 60 64 Finalize deed conveyance per Exchange Recitals Completed. Agreement to Transfer Five Buildings and Related Land From DC to GSA 71 74 Finalize Occupancy Agreements Recitals Completed.

More information

Capital Projects in and near Odenton Town Center

Capital Projects in and near Odenton Town Center Capital Projects in and near Odenton Town Center Map ID Anne Arundel County Department of Public Works This project provides for the design, right of way acquisition, and construction of approximately

More information

I. DESCRIPTION OF PROPOSED ACTION... 1 A. General Description... 1 B. Historical Resume and Project Status... 2 C. Cost Estimates...

I. DESCRIPTION OF PROPOSED ACTION... 1 A. General Description... 1 B. Historical Resume and Project Status... 2 C. Cost Estimates... PROJECT COMMITMENTS SUMMARY... S-1 1. Type of Action... S-1 2. Description of Action... S-1 3. Summary of Purpose and Need... S-1 4. Alternatives Considered... S-2 5. NCDOT Alternatives Carried Forward...

More information

The Village of Sugar Grove, in partnership with Kane County, the Illinois Department of Transportation, and the Illinois Tollway welcomes you to the

The Village of Sugar Grove, in partnership with Kane County, the Illinois Department of Transportation, and the Illinois Tollway welcomes you to the The Village of Sugar Grove, in partnership with Kane County, the Illinois Department of Transportation, and the Illinois Tollway welcomes you to the first Public Meeting for the proposed interchange improvement

More information

Gold Line Bus Rapid Transit Transit Oriented Development (BRTOD) Helmo Station Area Plan

Gold Line Bus Rapid Transit Transit Oriented Development (BRTOD) Helmo Station Area Plan Appendix F Gold Line Bus Rapid Transit Transit Oriented Development (BRTOD) Helmo Station Area Plan Introduction and Purpose of the Plan The Gold Line Bus Rapid Transit facility is an eleven-mile dedicated

More information

Places29: List of Implementation Projects

Places29: List of Implementation Projects Important Points to Keep in Mind When Using This List Places29: List of s Each of the projects in this List represents an action needed to implement the Places29 Master Plan. The projects are grouped first

More information

2.0 PURPOSE AND NEED. 2.1 Purpose. 2.2 Need Traffic Congestion in and around Downtown Derry

2.0 PURPOSE AND NEED. 2.1 Purpose. 2.2 Need Traffic Congestion in and around Downtown Derry 2.0 PURPOSE AND NEED Taking into consideration agency and public input, the purpose and need for the Project was identified early in Project planning. As noted in Appendix A, for purposes of meeting the

More information

Southeast Extension to RidgeGate Parkway Scoping Booklet

Southeast Extension to RidgeGate Parkway Scoping Booklet Southeast Extension to RidgeGate Parkway Scoping Booklet PUBLIC SCOPING MEETING SCHEDULE Public Scoping Meeting Wednesday, November 2, 2011 6:00pm to 7:30pm City of Lone Tree Recreation Center Willow Room

More information

V. PLANNING PRINCIPLES And

V. PLANNING PRINCIPLES And V. PLANNING PRINCIPLES And Urban Design Framework V. Planning Principles And Urban Design Framework Overview The responds to the planning parameters and the development potential framework established

More information

The Illinois Department of Transportation and Lake County Division of Transportation. Route 173, including the Millburn Bypass

The Illinois Department of Transportation and Lake County Division of Transportation. Route 173, including the Millburn Bypass The Illinois Department of Transportation and Lake County Division of Transportation welcome you to this Public Hearing for U.S. Route 45 from Illinois Route 132 to Illinois Route 173, including the Millburn

More information

Stewardship. Streamlining. Consensus

Stewardship. Streamlining. Consensus Stewardship Streamlining Consensus Translating Section 106: Building Consensus among Multiple Responsible Parties For the Doyle Drive Replacement Project in the Presidio of San Francisco National Historic

More information

ARGENTA TRAIL (CSAH 28/63) REALIGNMENT SOUTH PROJECT (CP 63-25)

ARGENTA TRAIL (CSAH 28/63) REALIGNMENT SOUTH PROJECT (CP 63-25) ARGENTA TRAIL (CSAH 28/63) REALIGNMENT SOUTH PROJECT (CP 63-25) Preliminary Design Report February 2015 Prepared For: City of Inver Grove Heights Dakota County Prepared By: Kimley-Horn and Associates,

More information

Goals for Tonight s Meeting

Goals for Tonight s Meeting South Anthony Boulevard Railroad Grade Separation Study Report to Community November 30, 2011 Andorfer Commons Theatre Indiana Tech University Goals for Tonight s Meeting Recap of the meeting from last

More information

FY 2005 TRANSPORTATION CAPITAL PROGRAM

FY 2005 TRANSPORTATION CAPITAL PROGRAM Camden County Civic Center Access Study, Pennsauken 03340 This project will address operational and access improvements on Routes 30, 73 and 90 related to the Crossroads redevelopment project around the

More information

Introductions Project overview Scope of work Schedule. Agenda. Community/Stakeholder Input Process Discussion Summary/Next Steps

Introductions Project overview Scope of work Schedule. Agenda. Community/Stakeholder Input Process Discussion Summary/Next Steps CPIT / Civic Associations Meeting December 14, 2009 Introductions Project overview Scope of work Schedule Agenda Community/Stakeholder Input Process Discussion Summary/Next Steps Columbia Pike Context

More information

RECREATION AND OPEN SPACE ELEMENT GOALS, OBJECTIVES, AND POLICIES

RECREATION AND OPEN SPACE ELEMENT GOALS, OBJECTIVES, AND POLICIES RECREATION AND OPEN SPACE ELEMENT GOALS, OBJECTIVES, AND POLICIES Goal 7 To provide park facilities, recreation programs, and open space resources that are safe, adequate, and accessible to all City residents,

More information

Public input has been an important part of the plan development process.

Public input has been an important part of the plan development process. Lakewood s Comprehensive Plan recognizes that transportation helps shape the community, and that the way the community provides for the safe and efficient movement of people affects the character of the

More information

ARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of January 28, 2017 SUPPLEMENTAL REPORT

ARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of January 28, 2017 SUPPLEMENTAL REPORT ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of January 28, 2017 SUPPLEMENTAL REPORT DATE: January 26, 2017 SUBJECT: The Virginia Department of Transportation s Transform I-66 Inside the

More information

Establish a network of streetscaped vehicle and pedestrian routes that connect within and outside the Plan area.

Establish a network of streetscaped vehicle and pedestrian routes that connect within and outside the Plan area. This Plan s urban design goals are to create an urban scale, walkable community with connections to transit, parks, and services and with amenities and facilities for residents and employees. The 1992

More information

RESOLUTION NO R

RESOLUTION NO R e e RESOLUTION NO R04 0054 BE IT RESOLVED by the Mayor and City Council ofthe City ofpapillion that The Papillion Comprehensive Plan is hereby amended to incorporate the Option A Future Land Use Map Transportation

More information

ACCESS MANAGEMENT REPORT U.S S.H. 1 TO S.H. 14 S.H U.S. 287 TO I-25

ACCESS MANAGEMENT REPORT U.S S.H. 1 TO S.H. 14 S.H U.S. 287 TO I-25 ACCESS MANAGEMENT REPORT U.S. 287 - S.H. 1 TO S.H. 14 S.H. 14 - U.S. 287 TO I-25 Prepared by: City of Fort Collins Transportation Planning 7951 East Maplewood Avenue, Suite 200 210 E. Olive, P.O. Box 580

More information

I. INTRODUCTION. Project Background and Study Area

I. INTRODUCTION. Project Background and Study Area I. INTRODUCTION Project Background and Study Area Freedom Parkway is a key east-west corridor connecting I-25 on the west to the Town of Kersey on the east, running approximately one to two miles south

More information

Section 4(f) Evaluation

Section 4(f) Evaluation 5 Section 4(f) Evaluation 5.1 Introduction Under Section 4(f) of the Department of Transportation Act as amended by the Federal-Aid Highway Act of 1968 (Public Law 90-495, 49 USC 1653), the Secretary of

More information

Transportation. Strategies for Action

Transportation. Strategies for Action Transportation A major priority for the Overlake Neighborhood is to develop a multimodal transportation system. To achieve this system, a balance has to be found among travel, circulation and access needs;

More information

RZC Public View Corridors and Gateways

RZC Public View Corridors and Gateways RZC 21.42 Public View Corridors and Gateways 21.42.010 Purpose 21.42.020 Scope and Authority 21.42.030 Administration 21.42.040 Gateways Design 21.42.050 Unidentified Public Views 21.42.060 Identification

More information

Capital Projects impacting Odenton Town Center

Capital Projects impacting Odenton Town Center Capital Projects impacting Odenton Town Center 1 2 E549700 W801600/ W801602 Anne Arundel County Department of Public Works Manor View Elementary School Transmission Main - MD 32 @ Meade Phase 2 $34,399,000

More information

WARM SPRINGS PARK MASTER PLAN

WARM SPRINGS PARK MASTER PLAN TABLE OF CONTENTS page 1.0 Introduction and Overview 1 2.0 Information Gathering 2 3.0 Conceptual Alternative Development 8 4.0 Master Plan Development 14 5.0 Construction Cost Estimates 19 LIST OF FIGURES

More information

TRANSPORTATION ELEMENT GOALS, OBJECTIVES, AND POLICIES

TRANSPORTATION ELEMENT GOALS, OBJECTIVES, AND POLICIES TRANSPORTATION ELEMENT GOALS, OBJECTIVES, AND POLICIES GOAL 2 The City shall provide a safe, convenient, effective, and energy efficient multimodal transportation system which is coordinated with the Future

More information

Puget Sound Gateway Program Team. Phase 1, SR 509 Completion Project NEPA Re-evaluation

Puget Sound Gateway Program Team. Phase 1, SR 509 Completion Project NEPA Re-evaluation Land Use COPY TO: PREPARED BY: Project File DATE: November, 2017 SUBJECT 1. Introduction Puget Sound Gateway Program Team Phase 1, SR 509 Completion Project NEPA Re-evaluation This memorandum was prepared

More information

Chapter 22. Alternatives to the Proposed Project

Chapter 22. Alternatives to the Proposed Project Page 22-1 Chapter 22. Alternatives to the Proposed Project Introduction This chapter assesses the potential environmental effects of alternatives to the Proposed Project. The alternatives analyzed include

More information

V. PLANNING PRINCIPLES And

V. PLANNING PRINCIPLES And V. PLANNING PRINCIPLES And Urban Design Framewo rk V. PLANNING PRINCIPLES AND URBAN DESIGN FRAMEWORK Gate 1 Gate 2 Overview The St. Elizabeths West Campus Master Plan responds to the planning parameters,

More information

Highway & Bridge Capabilities

Highway & Bridge Capabilities Highway & Bridge Capabilities Part of a diversified family of solutions www.jmt.com An Employee Owned Company I-95/I-295/I-495 Interchange, Woodrow Wilson Memorial Bridge, Prince George s County, MD Our

More information

510 Highways, Streets & Roads Comprehensive Plan Section 510

510 Highways, Streets & Roads Comprehensive Plan Section 510 511 510 Comprehensive Plan Section 510 Highways, streets, and roads provide for the movement of people and goods from one place to another. These public ways form a network that defines the relationship

More information

Rezoning Transportation Analysis Petition Number: General Location Identifier:

Rezoning Transportation Analysis Petition Number: General Location Identifier: From: Kelsie Anderson, PE Kelsie.Anderson@charlottenc.gov 704-432-5492 Staff Reviewer: Kory Hedrick, PE, PMP Khedrick@charlottenc.gov 704-432-6511 CDOT s review of this rezoning petition is intended to

More information

Revised Long Range Transportation Plan

Revised Long Range Transportation Plan Revised Long Range Transportation Plan Auburn, Alabama Prepared for: City of Auburn, Alabama Prepared by: Skipper Consulting, Inc. June 2006 Revised Long Range Transportation Plan City of Auburn, Alabama

More information

Asbury Chapel Subdivision Sketch Plan

Asbury Chapel Subdivision Sketch Plan Asbury Chapel Subdivision Sketch Plan PART 1: PROJECT SUMMARY Applicant: NVR Inc. Project Size: +/- 76.13 acres Parcel Numbers: 02101112,02116101,02116112, 02116113 Current Zoning: Transitional Residential

More information

COMMUNITY DESIGN. GOAL: Create livable and attractive communities. Intent

COMMUNITY DESIGN. GOAL: Create livable and attractive communities. Intent COMMUNITY DESIGN Intent An attractive, well-designed County will attract quality development, instill civic pride, improve the visual character of the community, and create a strong, positive image for

More information

Midtown Corridor Alternatives Analysis. Appendix A - Initially Considered Alternatives Screening

Midtown Corridor Alternatives Analysis. Appendix A - Initially Considered Alternatives Screening Midtown Corridor Alternatives Analysis Appendix A - Initially Considered Alternatives Screening Arterial BRT on Lake Street - Overall Rating: RATING Metropolitan Council recommendations stated in the Transportation

More information

Chesterfield County Project Update

Chesterfield County Project Update Chesterfield County Project Update SOUTHEAST HIGH SPEED RAIL TIER II ENVIRONMENTAL IMPACT STATEMENT RICHMOND, VA, TO RALEIGH, NC CHESTERFIELD COUNTY, VA OFFICIALS BRIEFING February 2013 Federal Railroad

More information

Clairtrell Area Context Plan

Clairtrell Area Context Plan Clairtrell Area Context Plan March 2005 Urban Development Services City Planning Contents 1. Introduction... 4 2. Development Structure... 6 2.1 Streets... 7 2.1.1 Sheppard Avenue and Bayview Avenue...

More information

Project Purpose. Project Need

Project Purpose. Project Need Project Purpose The purpose of the project is to implement a bridge improvement solution that corrects the existing safety problem at the Strasburg Pike Bridge. The project will provide a structurally

More information

Alaskan Way, Promenade, and Overlook Walk Final EIS Appendix D - Supplemental Draft EIS Comments and Responses October 2016.

Alaskan Way, Promenade, and Overlook Walk Final EIS Appendix D - Supplemental Draft EIS Comments and Responses October 2016. B-001-001 The use of Columbia Street for two-way transit was a decision made by King County Metro as part of its Southwest Transit Pathway evaluation. This project is separate from AWPOW. B-001-002 Modeling

More information

SH 199 Corridor Master Plan. Community Meeting No. 2 May 31, 2017

SH 199 Corridor Master Plan. Community Meeting No. 2 May 31, 2017 Community Meeting No. 2 May 31, 2017 Transportation Projects On or Near SH 199 SH 199 from 0.3 miles south of FM 1886 to south end of Lake Worth bridge Construct freeway mainlanes and frontage roads 10-Year

More information

Appendix G Response to Comments

Appendix G Response to Comments Appendix G Response to Comments This appendix contains the comments received during the public circulation and comment period (May 27, 2008 to July 11, 2008). The comments have been numbered (Comment Set

More information