D. Energy Baseline Assessment

Size: px
Start display at page:

Download "D. Energy Baseline Assessment"

Transcription

1 D. Energy Baseline Assessment D.1. INTRODUCTION Erie International Airport is a publicly owned, primary commercial service airport that serves the aviation needs of Erie County, PA and its surrounding areas. As part of the Master Plan Update, McFarland Johnson performed an Energy Baseline assessment of the existing Passenger Terminal Building, the U.S. Customs and Border Control Building, the Airfield Maintenance and Fire Station Building and the Electrical Vault. The passenger terminal building is the primary transition point from surface to air transportation for the airport. The original building was constructed circa 1956 and there have been several additions and renovation projects since. At its current configuration the terminal building occupies approximately 47,6 ft 2. It is a steel frame, concrete block and face brick construction building with primarily double pane windows and skylights and a flat EPDM, gravel ballast roof. The U.S. Customs and Border Control Building is an approximately 2,2 ft 2 masonry / face brick construction building, with double pane windows and a flat EPDM roof. It was constructed in The Airfield Maintenance and Fire Station Building is a 16,5 ft 2 building. The building is a steel structure and concrete block with a brick facade and a flat built-up roof construction. The original portion was constructed at the same time that the passenger terminal building was built, in 1956, and has since had two additions added to it. A three-vehicle bay addition was constructed in 1988 on the south end of the building to accommodate the Airport s ARFF vehicles, and two vehicle bays were constructed on the north end of the building for housing maintenance equipment. The Airport is currently supplied water by the City of Erie Water Authority. A six-inch diameter water line serves the terminal complex from a water main running along West 12th Street. The passenger terminal complex is served by a six-inch diameter sanitary sewer line connected to the city s trunk line. Natural gas is supplied to the terminal building by National Fuel Gas; a natural gas line runs from West 12th Street to the meter room on the basement floor of the terminal. GPU supplies electric power to the airport via above-ground power lines running from West 12th Street to Grant Avenue, then underground to the weather bureau, terminal building, and the remaining areas on the Airport. D.2. PASSENGER TERMINAL BUILDING D.2.1. Electrical Systems Description Most of the lighting within the terminal has been upgraded to energy efficient T8 and compact fluorescent. There are still some incandescent lamps installed in downlights (café) and T12 linear D-1

2 fluorescent lamps being used in some areas in the front and back-of-house spaces (kitchen, baggage handling, airline supply spaces, offices, stairwells, cove lights behind ticketing, linear fixtures above the drop ceiling outside passenger screening). T5 fixtures have been installed in the ceiling in the area after passenger screening. The basement lighting is a mix of T12 and T8 lamp linear fixtures (4 and 8 lengths) and ceramic light bases with compact fluorescent and LED bulbs installed in them. Second floor lighting is a mix of T8 and T12 recessed troffers with acrylic lenses. All lighting is controlled with manual switching except for the two restrooms in the secure side of the terminal. These lights are controlled with motion sensors w/timers. Exterior lighting is accomplished with a mix of metal halide downlights, surface mounted metal halide, and pole mounted metal halide and high pressure sodium. There are no exterior LED light fixtures. Exit signage throughout the terminal is LED. Some of the fixtures have halogen emergency light heads installed on them, some have LED heads. Not all exit signs have emergency lighting installed. Battery tests indicated that not all of the exit signs have batteries that will operate during a power outage. Not all exit signs have battery back-up. Emergency lighting is accomplished with stand-alone emergency units and emergency ballasts installed in recessed fixtures. Emergency lighting and exit signage is powered from a Life Safety power panel which is fed from a back-up generator. D.2.2. Mechanical Systems Description The basement level of the terminal houses the terminal s controls, telephone, and electrical equipment. The heat for the passenger terminal building is provided by a combination of low pressure steam boiler (Weil-McLain Model 88) and one hot water boiler (Weil-McLain Model Ultra 31). Both boilers use natural gas as the primary energy source. An third, older boiler (Weil-McLain Model LGB-9) has been abandoned in place. The energy management system consists of a combination of electric controls (FAA offices) and pneumatic controls. The air compressor for the pneumatic controls as well as the electric controls terminal are located in the basement mechanical room. There is a wide assortment of thermostats throughout the facility characteristic of the era that they were installed, ranging from programmable thermostats to temperature sensors and traditional mercury type thermostats. The main floor of the terminal building is served by a number of roof mounted units and is supplemented in select areas by unit heaters, cabinet unit heaters, air curtains, low intensity gas fired infrared heaters, unit ventilators and thru the window packaged air conditioning units. The roof top units (RTU) serving the original 1956 portion of the building are providing heat by means of steam coils. Several roof top units have been added as part of addition/renovation projects. Heat from these units is provided either through hot water heating coils or natural gas furnaces. All roof top units provide cooling via packed direct expansion cooling coils. Most of the RTUs have far exceeded their useful life expectancy and should be scheduled for replacement with newer more efficient units. D-2

3 There are several, natural gas fired, domestic water heaters spread out throughout the terminal building to serve the facility s domestic hot water needs. Public bathrooms have sensor type faucets on the lavatories and sensor flush valves on toilets and urinals. General exhaust is provided through a number of roof exhaust fans. The Control Tower staircase is pressurized by multiple fans which are part of the smoke control system and are activated through the fire alarm panel. The restaurant kitchen is served by a commercial range hood. There are several air curtains at the passenger departure/arrival gates intended to reduce energy loss through the open doors during these times that passengers are boarding or exiting the aircrafts. All of the air curtains are either out of order or have been disabled for various reasons. The boiler and natural gas meters are both located on the basement level of the complex. The fire pump room and associated fire sprinkler risers and air compressor are also located in the basement in their own separate fire pump/sprinkler riser room adjacent to the mechanical room. Refer to Table D-1 for a more detailed listing of the equipment in the Passenger Terminal Building as well as the U.S. Customs and Border and Maintenance Buildings. Equip. No Area Served Table D-1: Passenger Terminal Building Equipment List Manufact urer Model No. Serial No. Condition Capacity Notes ERAA - Restaurant 38AE F Fair/Poor 17, BTU/HR* ERAA - Main Lobby ERAA - South ERAA - Finance Area ERAA - Car Rental Hall ERAA - Baggage Claim ERAA - Center Boarding ERAA - West Boarding 48PMMM16BR- 5-S8 48TJE5-51GA 48SS G G1497 Good Poor 25, BTU/HR Failing duct insulation 92, BTU/HR Failing duct insulation 3394G118 Fair 4, BTU/HR 48TJE G217 Fair/Poor 92, BTU/HR York D2CG18N322 5E 48TJE24-51QA 48DRO14-52AA NFHM82611 Fair 32, BTU/HR 3494F1261 Fair 216, BTU/HR Y79737 Fair/Poor 216, BTU/HR Rusted exposed duct ERAA - West 48TJE12-9 Ticketing 51GA 2494G3235 Fair/Poor 144, BTU/HR ERAA - East 48TJE12-1 Ticketing 51GA 3194G3656 Fair/Poor 144, BTU/HR ERAA - Main FAA 5AK- 11 Unit 2QAQ611HQ 337U2551 Fair AC unit ERAA - Radar 48TEF8-A- 47G5496 Good 92, BTU/HR D-3

4 12 Equipment Room Backup 511HQ ERAA - West FAA 4, BTU/HR UNKNOWN UNKNOWN Poor 13 Wing (not confirmed) 32, BTU/HR ERAA - Delta Ops 48DJE G38939 Poor (not confirmed) ERAA - Third Floor 48TJE5-16 Break Room 51GA 1694G1488 Poor 92, BTU/HR 17 ERAA - Tower Cab 48TJE G1399 Poor 74, BTU/HR ERAA - Third Floor 48TJE7-18 Equipment Room 51GA 1994G2111 Fair 92, BTU/HR ERAA - Police 19 Office 48SS G11237 Fair 33,3 BTU/HR ERAA - US Airways 2 Ops 38CK E , BTU/HR ERAA - Steam Weil 21 Boiler McLain 988R n/a Fair 2,, BTU/HR US Customs and 74, BTU/HR Trane YCD48A3LAB F414222D Borders Building (not confirmed) US Customs and 74, BUT/HR Trane YCD4ASLAB F D Borders Building (not confirmed) ERAA - FAA HW Weil- 24 Boiler McLain ULTRA 31 CP Fair 3, BTU/HR Roberts 6, BTU/HR Sidewalk Heaters Gordon CTH2-8 n/a Good 25 each Vantage II ERAA - East Commuter Walkway ERAA - West Commuter Walkway ERAA - Continental Express Ops ERAA - Control Room Restaurant Manager ERAA - Hot Water Boiler West Jetway PC Air Center Jetway PC Air York York Lennox D6CG6N992 5C DC6GO6N992 5C CG29M-21/26-1P NKEM125Y NKE M3756 Fair Fair Fair 92, BTU/HR (not confirmed) 92, BTU/HR (not confirmed) 33,3 BTU/HR (not confirmed) Liebert MMD36EPHED AC unit Liebert PFC37A-YLO 43N AC unit Weil- McLain LGB-9 n/a Poor 1,4, BTU/HR NOT IN SERVICE n/a n/a n/a -- Electric n/a n/a n/a -- Electric East Jetway PC Air n/a n/a n/a -- Electric TSA Job Trailer -1 North n/a MAC36A-AB 58N Electric D-4

5 MISC 1 MISC 2 MISC 3 MISC 4 MISC 5 TSA Job Trailer -2 South Fire Bay Overhead Tube Heaters (Typ. 4) Airfield OPS Work Area (Installed 214) Airfield Equipment Bay Tube Heaters (Typ. 4) Airfield Storage Bays Tube Heaters (5) Sand Salt Storage Tube Heaters (Typ. 2) Baggage claim tube heaters (Typ. 2) Terminal Domestic Hot Water Restaurant Hot Water Tanks 2 (8 Gallon) US Customs Hot Water Tank 4 Gallon Airfield Hot Water Tank (4 Gallon) Maintenance Building Tank (4 Gallon) n/a MAC36AAB N Electric n/a n/a n/a -- 6, BTU/HR each LENNOX KGA48S4Ds 5614P , BTU/HR n/a n/a n/a Fair n/a n/a n/a Fair n/a n/a n/a Fair n/a n/a n/a Good Bradford White Defender MI4T6FBN GL Fair n/a n/a n/a -- Bradford White MI4T6FBN KH Good n/a n/a n/a -- Whirlpool M4T Fair Source: Chief Ian A. Bogle, Erie Regional Airport Authority * Capacity information from manufacturer s catalog D.2.3. Recommendations 6, BTU/HR each 6, BTU/HR each 6, BTU/HR each 6, BTU/HR each 4, BTU/HR Input 4 Gallon Tank 4, BTU/HR Input 4 Gallon Tank 4, BTU/HR Input 4 Gallon Tank 4, BTU/HR Input 4 Gallon Tank In order to conserve energy, it is recommended that all light fixtures utilizing incandescent, T-12, and T-8 lamps be replaced with energy efficient LED light fixtures. LED lighting utilizes approximately 2% the energy of the existing light fixtures and will provide noticeable savings to the airport. Exterior lighting on the apron and in the parking lot can also be changed out to LED light fixtures to provide additional savings. Install low flow aerators on all lavatory faucets. A faucet aerator can be simply screwed onto the faucet head. Because the aerator limits the water flow through the faucet, water use is reduced by an average of 5% as compared to a faucet without an aerator. D-5

6 In interviewing facility personnel, it was discovered that due to maintenance issues a number of steam traps get stuck either in the open or the closed position. This results in either condensate backing up when the trap is stuck closed, therefore inhibiting the transfer of latent heat, or steam blowing through the trap when it's stuck open, leading to heating issues and waste of energy. A stuck or failed open steam trap can also cause issues with the remainder of the steam traps in the system as it may pressurize the condensate return line, therefore preventing condensate from the other traps from draining properly. Facility personnel also mentioned that whenever any major maintenance is needed the work is contracted to an outside firm or contractor. Regular equipment maintenance has a significant effect on both life expectancy and maintaining peak efficiency of equipment. It is suggested that a regular maintenance schedule is implemented and that maintenance personnel is trained in the required maintenance tasks. The building automation system (BAS) consists of multiple iterations of various manufacturers, some parts of it original to the building. As a result, the airport is far from realizing the full potential energy savings that a properly implemented control system would offer the capability for. A complete replacement of the energy management system could prove very costly. Factoring in the age of most of the air handling equipment, that would also need to be replaced or upgraded, this type of upgrade could only be viable as part of a capital project. D.3. U.S. CUSTOMS AND BORDER CONTROL BUILDING D.3.1. Electrical Systems Description The Custom s building light fixtures are T12, recessed light fixtures (2x4 and 2x2), T-12 surface wraparound (bathrooms), with a few metal halide recessed downlights. Light fixtures are all manual control with single pole light switches. Exit signs are old lamp style fixtures with no battery back-up. Emergency lighting is accomplished with stand-alone lighting units and battery tests indicate that these fixtures will operate during a power outage. D.3.2. Mechanical Systems Description The building is conditioned by a pair of gas fired RTUs and miscellaneous electric terminal units, and through the window AS units. The two RTUs are controlled by programmable wall mounted thermostats. Domestic hot water is generated by a Bradford White Model MI4T6FBN, 4 gallon, 4, btu/hr natural gas fired water heater. There are manual flush valves for toilets and urinals. The lavatory faucets are in fair shape and do not appear to be the low flow type. On the building exterior it was observed that the west and south exposure window caulking has disintegrated. There are also signs of water leakage within exterior block walls, possibly from water pooling on the roof. D-6

7 D.3.3. Recommendations The existing RTUs are past their useful life expectancy. It is recommended that funds are appropriated for the replacement of the units. Though operations and maintenance costs will be reduced, there is not a significant payback from energy savings to justify the replacement of the units before they are rendered inoperable. Replacement decision should be based on facility importance and the potential of having no heat in the building during the cold winter months if the units fail. Replace existing lavatory faucets and shower heads with low flow fixtures to conserve water and energy. Typical payback for this type of replacement is less than a year, depending on use time of the plumbing fixtures. This is a relatively low cost measure that can be easily implemented. It is recommended that the existing fluorescent and metal halide light fixtures be replaced with energy efficient LED fixtures. It is also recommended that automatic lighting controls be added to the offices and bathrooms. The existing exit signage shall also be replaced with LED type exit signage with battery backup. D.4. AIRFIELD MAINTENANCE AND FIRE STATION BUILDING D.4.1. Electrical Systems Description The Airfield Maintenance and Fire Station Building has T8 recessed troffers in the office area and T12 linear fixtures (4 and 8 lengths) in the truck and maintenance bays. The old salt storage area, which is now used as a two-bay truck area has 4W metal halide light fixtures. 25W and 4W high pressure sodium fixtures are installed on the exterior of the building. Interior lighting is controlled with manual switches. Exterior lighting is controlled by photocell. Exit signage throughout the AARF/Maintenance Garage is LED with battery back-up. Battery tests indicate that these fixtures will operate during a power outage. Emergency lighting is accomplished with standalone emergency fixtures with a mix of halogen and LED lamping. Battery testing indicated that some of these fixtures will not operate during a power outage. A 4kw generator was installed in 28 to supply power for life safety. D.4.2. Mechanical Systems Description The Airfield Maintenance and Fire Station Building is primarily served by multiple low intensity, gas-fired infrared heaters which are typical for this type of building use. The office area and employee is served by a packaged gas-fired RTU. The RTU and infrared heaters are controlled by programmable wall mounted thermostats. There is a partial sprinkler system serving the mezzanine area in the building but there were no alarm devices observed, which is inconsistent with NFPA standards and International Fire Code. There is an air compressor for used for maintenance on the stored vehicles and an emergency generator. D-7

8 The vehicle storage bays are also served by multiple exhaust fans controlled by wall mounted switches. The fans are intended to exhaust heat in the warm summer months. No carbon monoxide (CO) or nitrogen oxides (NOx) sensors were observed which are typically utilized for exhausting vehicle storage bays when potentially hazardous concentrations of CO and/or NOx are detected. A 4 gallon, 4, btu/hr, natural gas fired water heater (Whirlpool Model M4T91-43) provides the domestic hot water for the facility. D.4.3. Recommendations It is recommended that the existing T12 and T8 light fixtures be replaced with energy efficient LED fixtures. It is also recommended that the existing metal halide and high pressure sodium light fixtures be replaced with LED type fixtures. Automatic lighting control should be added to bathrooms and break rooms to turn lighting off when the rooms are not occupied. Emergency lighting throughout the building should be verified to be operational and nonworking units should be replaced to ensure operation during times of need. It is recommended that a CO / NOx detection system is provided for the facility and tied to the existing exhaust fans. The existing exhaust fan capacity should be reviewed for adequacy of exhaust volume capabilities. D.5. ELECTRICAL VAULT D.5.1. Electrical Systems Description The vault houses all of the constant current regulators (CCR s) for the airfield lighting. Airfield lighting has been upgraded in certain areas and is original in other areas. Runway 6/24 has all new incandescent lighting, new cable, new conduit, and new transformers and cans. Runway 2/2 is all original equipment. Taxiway A edge lighting is LED for the extended part of the taxiway. This was done in The balance of taxiway A s lighting is original (transformers, cans, cable, conduit). Taxiway C lighting between Taxiway A and Runway 2/2 is new LED and transformer utilizing original cable and cans. Taxiway D lighting between Runway 6/24 and Runway 2/2 is new LED and transformer utilizing original cable and cans. Signage on the airside is currently being changed out to LED. Twenty-three of the existing signs have yet to be changed out to LED. Existing cabling is being utilized except those signs associated with the runway. The cable feeding these signs was changed out during the runway extension project. The light fixtures in the vault building utilize T8 lamps. D.5.2. Mechanical Systems Description N/A D.5.3. Recommendations The airport is currently undertaking the replacement of some of the signage light fixtures to energy efficient LED type fixtures. It is recommended that the airport continue to replace D-8

9 signage fixtures with LED type to conserve energy. It is also recommended that old taxiway lighting be replaced with LED fixtures to match the new LED lighting along the edge of some of the taxiways. D.6. CURRENT AIRPORT ENERGY AND WATER USE D.6.1. Natural Gas Consumption The natural gas bills provided by Erie Airport were compiled into Table D-2, Figure D-1, and Figure D-2. Table D-2: Natural Gas Consumption (DTH) Meter No. Month TOTAL USAGE (DTH) Cost ($) Dec ,848 Jan ,685 Feb ,34 Mar ,268 Apr ,442 May Jun Jul Aug Sep Oct ,865 Nov ,328 Dec ,6 Source: National Fuel Resources Inc. energy Bills D-9

10 Cost ($) Cost ($) Master Plan Update Figure D-1: Total Natural Gas Consumption Source: Utility bills. Figure D-2: Natural Gas Cost $12, $1, $9,686 $9,34 $8, $7,849 $7,268 $6, $6,6 $4,328 $4, $3,442 $2, $916 $388 $348 $341 $5 $1,866 $- Source: Utility bills. D-1

11 D.6.2. Electric Consumption The electric bills provided by Erie Airport were compiled into Table D-3, Figure D-3, and Figure D- 4. Month Meter# Total Usage (KWH) Dec- 14 Jan- Feb- Table D-3: Electric Consumption (KWH) Mar- Apr- May- Jun- Jul- Aug- Sep- Oct- Nov- TOTAL USAGE (KWH) , , , ,685 4,9 3,29 5,576 3,937 3,758 2,645 2,59 2,192 2,384 2,59 3,14 3,719 39,632,522 16,4 6,565 6,143 6,646 5,754 6,368 3,4 5,517 6,167 7,983 7,916 93, ,648 1,566 1, , ,844 2, 3,487 3,746 3,654 2,81 1,94 1,697 29, , ,8 7,2 174,4 143,6 146, 136, 178, 1,6 16, 142,, 131,6 1,833,2 2,322 1,276 2,74 1, , , , ,2 3,786 28,451 3,233 19,58 2,5,758,421 13,233 14,9,574 17,876 18, ,63 Cost ($) 14,327 14,279 17,597 12,439 13,327 12,895,9 13,687 14,92 12,917 13,364 12, ,184 Source: Penelec Electricity Bills D-11

12 COST Electricity Use (KWH) Master Plan Update 25, Figure D-3: Electric Consumption 2,, 199, , , , ,667 9, , ,658 6, ,62 149,18 147,95 1, 5, - Source: Utility bills. Figure D-4: Electricity Cost $2, $18, $16, $14, $12, $17,597 $,9 $14,327 $14,279 $13,327 $13,687 $14,92 $12,895 $12,917 $13,364 $12,439 $12,346 $1, $8, $6, $4, $2, $- Source: Utility bills. D-12

13 D.6.3. Water Consumption The Water consumption bills provided by Erie Airport were compiled into Table D-4 and Figure D- 5. Table D-4: Water Consumption (cu. ft.) Meter # Month Car Wash FAA-SSC Fire Pump Main Quonset Hut Restaurant Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec TOTAL TOTAL Source: Erie Waterworks Bills Figure D-5: Water Consumption Source: Erie Waterworks Bills D-13

14 D.6.4. Metrics Comparison The compiled energy metrics from all the natural gas, electric and water usage were input into US EPA s online energy tracking tool, the Portfolio Manager. Table D-5 below is a summary of the energy use of Erie Airport compared to other facilities of similar size and function. Table D-5: Metrics Comparison Metric Median Property ERAA Source EUI (kbtu/ft 2 ) Site EUI (kbtu/ft 2 ) Source Energy Use (kbtu) 5,642,641 13,137,485 Site Energy Use (kbtu) 2,961,536 1,867,918 Total GHG Emissions (Metric Tons CO2e) ,464.6 Source: Energy Star, Portfolio Manager (portfoliomanager.energystar.gov) Figure D-6: Airport Energy Use by Calendar Month Source: Energy Star, Portfolio Manager (portfoliomanager.energystar.gov) D.6.5. International Trade Center In addition to the buildings and facilities mentioned in the paragraphs above Erie Municipal Airport Authority occupies office space at the International Trade Center (ITC). The ITC also functions as a warehouse and houses commercial leases. Even though this building was not part of energy assessment its energy consumption is outlined in the following tables. D-14

15 Month Meter# Total Usage (KWH) Dec- 14 Jan- Source: Utility bills Feb- Table D-6: ITC Electric Consumption Mar- Apr- May- Jun Jul- Aug- Sep- Oct- Nov- TOTAL USAGE (KWH) 4,477 4,18 5,17 3,744 3,535 2,466 1,513 1, ,52 2,181 32,629 4,518 4,223 5, 3,785 3,58 2,5 1,549 1, ,185 1,539 2,217 33,75 D-

Sprinkler: The building does not have a fire protection system installed. MECHANICAL / PLUMBING / SPRINKLER SYSTEMS RECOMMENDATIONS

Sprinkler: The building does not have a fire protection system installed. MECHANICAL / PLUMBING / SPRINKLER SYSTEMS RECOMMENDATIONS EXISTING MECHANICAL CONDITIONS SUMMARY The items listed below are based on our site visit on Nov 10, 2016. Our review is based on current conditions and anticipated future use of these building. In the

More information

PLATTEVILLE MIDDLE SCHOOL

PLATTEVILLE MIDDLE SCHOOL Architectural The building has aluminum clad wood awning windows in combination with aluminum fixed glass units. They appear to be exterior glazed with insulated glazing. See photo 2. Platteville Middle

More information

Tighe&Bond. Groton Heights School Mechanical Evaluation. 1 Existing Conditions. 1.1 Water Service Entrance

Tighe&Bond. Groton Heights School Mechanical Evaluation. 1 Existing Conditions. 1.1 Water Service Entrance Groton Heights School Mechanical Evaluation TO: FROM: Amy Vaillancourt, Project Manager Harley Langford, Project Manger Jason Curtis, P.E. DATE: February 24, 2016; Revised May 31, 2016 On Monday, December

More information

MOUNT PLEASANT MIDDLE SCHOOL HVAC. M-01 Heating Plant: M-02 Heating & Ventilating Systems: Livingston School District Mount Pleasant Middle School

MOUNT PLEASANT MIDDLE SCHOOL HVAC. M-01 Heating Plant: M-02 Heating & Ventilating Systems: Livingston School District Mount Pleasant Middle School MOUNT PLEASANT MIDDLE SCHOOL HVAC M-01 Heating Plant: The existing boilers have recently been upgraded. (3) steam boilers (8660 mbh each) manufactured by Weil- McLain have been installed. Newer hot water

More information

State College Area School District High School North Building EXISTING CONDITIONS ASSESSMENT

State College Area School District High School North Building EXISTING CONDITIONS ASSESSMENT State College Area School District High School North Building Prepared by CenterPoint Engineering 08 February 2013 FACILITY ASSESSMENT SUMMARY PHYSICAL PLANT General HVAC This report is a snapshot of the

More information

2 Main Office Building BLDG-955A Building Purpose Building Area Administration offices. Training room 7,610 SF Inspection Date August 16, 2016 Inspect

2 Main Office Building BLDG-955A Building Purpose Building Area Administration offices. Training room 7,610 SF Inspection Date August 16, 2016 Inspect 1 Site Summary Address 7200 Bluff Springs Road Austin, TX 78744 Number of Permanent Campus Facilities 2 Original Year of Construction 2014 Total Campus Building Area (combined) 25,314 SF Introduction The

More information

HOLUM EDUCATION CENTER. Architectural. January 13, 2014 DeForest Area School District

HOLUM EDUCATION CENTER. Architectural. January 13, 2014 DeForest Area School District HOLUM EDUCATION CENTER Architectural The existing building has approximately 41,823 square feet and sets on a lot about 4.14 acres in size. Parking lots are located along the east and west sides of the

More information

ENGINEERING REPORT - MECHANICAL / ELECTRICAL / PLUMBING

ENGINEERING REPORT - MECHANICAL / ELECTRICAL / PLUMBING Mechanical Systems Information The mechanical system at Duncanville High School is comprised entirely of DX/Gas rooftop units (RTUs) and DX split systems. A vast majority of the RTUs are Trane units that

More information

Cork County Energy Agency

Cork County Energy Agency Cork County Energy Agency Energy Audit Midleton Area Office December 2009 Table of Contents 1. Introduction...1 2. Site description...2 3. On site energy use...3 3.1 Energy management...3 3.2 Breakdown

More information

S AGE E NGINEERING A SSOCIATES, LLP

S AGE E NGINEERING A SSOCIATES, LLP S AGE E NGINEERING A SSOCIATES, LLP 1211 Western Avenue Albany, NY (518) 453 6091 F (518) 453 6092 Kingston Library Mechanical and Electrical Systems Field Report Date of Visits: Mechanical - September

More information

State College Area School District High School South Building EXISTING CONDITIONS ASSESSMENT

State College Area School District High School South Building EXISTING CONDITIONS ASSESSMENT State College Area School District High School South Building Prepared by CenterPoint Engineering 08 February 2013 FACILITY ASSESSMENT SUMMARY PHYSICAL PLANT General HVAC This report is a snapshot of the

More information

SELECTED TOPICS IN HIGH RISE MECHANICAL DESIGN

SELECTED TOPICS IN HIGH RISE MECHANICAL DESIGN SELECTED TOPICS IN HIGH RISE MECHANICAL DESIGN Simcoe Towers Toronto and Dubai Shangri-la Hotel NORR SWEGON ACADEMY MAY 2010 INTRODUCTION Topic A comparison of building mechanical practices in hot and

More information

IES Whole-Building Energy Model Baseline Energy Model Input/ Output Report. East Liberty Presbyterian Church East Liberty Presbyterian Church

IES Whole-Building Energy Model Baseline Energy Model Input/ Output Report. East Liberty Presbyterian Church East Liberty Presbyterian Church IES Whole-Building Energy Model Baseline Energy Model Input/ Output Report East Liberty Presbyterian Church 14 009 For: By: East Liberty Presbyterian Church Jeffery Ison, James Construction Date: October

More information

Energy Efficient Measures That Add Little or no. Program Lights & Appliances: How To Benefit from the Low-Hanging Fruit

Energy Efficient Measures That Add Little or no. Program Lights & Appliances: How To Benefit from the Low-Hanging Fruit Energy Efficient Measures That Add Little or no FirstEnergy Cost Energy to Construction Efficient New Homes Program Lights & Appliances: How To Benefit from the Low-Hanging Fruit 1 2 Optimizing Savings

More information

Currently, all electrical upgrades would be voluntary, but there are situations in which upgrades would be required.

Currently, all electrical upgrades would be voluntary, but there are situations in which upgrades would be required. Executive Summary The current electrical system is functional but requires some understanding in order to avoid overloading circuits. Certain outlets can be used for space heaters while others cannot and

More information

Proposed Mechanical, Plumbing, and Electrical Systems For the LEDYARD POLICE DEPARTMENT LEDYARD, CT

Proposed Mechanical, Plumbing, and Electrical Systems For the LEDYARD POLICE DEPARTMENT LEDYARD, CT DESIGN ASSOCIATES INC MECH/ELEC DESIGN & CONSULTING 422 Highland Ave, Cheshire, CT. 06410 (203) 271-3787, fax (203) 271-2886 Proposed Mechanical, Plumbing, and Electrical Systems For the LEDYARD POLICE

More information

Cook - Wissahickon Elementary School

Cook - Wissahickon Elementary School Cook - Wissahickon Elementary School 201 E. Salaignac St., Philadelphia, PA 19128 HVAC Replacement Project Scope Determination Report May 10, 2018 Prepared by: G.P. Lamina, Jr., P.E., MBA School District

More information

* Peak kw is determined by the average kw load reduction occurring between 1PM and 4PM on weekdays during June, July and August.

* Peak kw is determined by the average kw load reduction occurring between 1PM and 4PM on weekdays during June, July and August. overview Summary of Services & Incentives Effective through March 31, 2014 Last updated April 1, 2013 business programs The goal of the Focus on Energy Business Programs is to help Wisconsin s non-residential

More information

GARCIA GALUSKA DESOUSA Consulting Engineers

GARCIA GALUSKA DESOUSA Consulting Engineers L#58619/Page 1/November 1, 2017 PLUMBING Executive Summary: Presently, the Plumbing Systems serving the building are cold water, hot water, sanitary, waste and vent system, storm drain piping, and natural

More information

Francis M McKay Elementary School

Francis M McKay Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

2018 Commercial Lighting Retrofit Rebate Program

2018 Commercial Lighting Retrofit Rebate Program 2018 Commercial Lighting Retrofit Rebate Program HOW TO APPLY 1. AMU provides energy efficiency rebates for the purchase and installation of qualifying lighting equipment. Additional lighting rebates,

More information

Appendix B. Facilities Assessment Report

Appendix B. Facilities Assessment Report Mile Lane Army Reserve Center Redevelopment Plan September 2008 Appendix B Facilities Assessment Report RKG Associates, Inc. Mile Lane Army Reserve Base Middletown, CT MEP System Evaluation For RKG Associates

More information

Matt Cooper, PE, BEMP, HBDP, Group 14 Engineering Ken Urbanek, PE, HBDP MKK Consulting Engineers, Inc.

Matt Cooper, PE, BEMP, HBDP, Group 14 Engineering Ken Urbanek, PE, HBDP MKK Consulting Engineers, Inc. M&V Real Results of High Performance Design Matt Cooper, PE, BEMP, HBDP, Group 14 Engineering Ken Urbanek, PE, HBDP MKK Consulting Engineers, Inc. Overview Measurement & Verification (M&V) Plan for New

More information

The Ed Roberts Campus Berkeley, CA

The Ed Roberts Campus Berkeley, CA The Ed Roberts Campus Berkeley, CA Anderson Clemenceau Mechanical Option Penn State A.E. Senior Thesis April 14, 2015 Leddy Maytum Stacy Architects, Photo by Tim Griffith ASHRAE Climate Zone 3C 99.6% Heating

More information

SUMMARY OF SERVICES & INCENTIVES

SUMMARY OF SERVICES & INCENTIVES BUSINESS PROGRAMS 2016 SUMMARY OF SERVICES & INCENTIVES Effective through December 31, 2016 Last updated February 1, 2016 EFFICIENCY INCENTIVES SUMMARY The Focus on Energy Business Programs offer both

More information

Pro Eco-Energy. Home Assessment

Pro Eco-Energy. Home Assessment Pro Eco-Energy Home Assessment Prepared for: Prepared by: Pro Eco Energy Andrew Aliferis PO Box 445 Scotland, PA 17254 717-446-0575 ABOUT THIS REPORT Your in-home evaluation was conducted on 2/12/2013.

More information

High Performance Building Guide 1

High Performance Building Guide 1 Description This Guide is intended to be used for projects with a Vermont Certified: High Performance energy efficiency goal. This High Performance goal is a whole-building efficiency approach rather than

More information

Genevieve Melody Elementary School

Genevieve Melody Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Existing Conditions Assessment November 14, 2006 NORTH MIDDLESEX REGIONAL HIGH SCHOOL Townsend, MA L21366/ /Page 1

Existing Conditions Assessment November 14, 2006 NORTH MIDDLESEX REGIONAL HIGH SCHOOL Townsend, MA L21366/ /Page 1 L21366/101 090 00.00/Page 1 HVAC EXECUTIVE SUMMARY The North Middlesex Regional High School has received average maintenance of the HVAC systems over its occupied years. Even with adequate maintenance,

More information

Washington Irving Elementary School

Washington Irving Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Joseph Brennemann Elementary School

Joseph Brennemann Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Summary of Repairs and Deficiencies

Summary of Repairs and Deficiencies Summary of s and Deficiencies Organization Building: Station #1 178 Safety & Compliance Inspections and Certifications Sprinkler System Certifications This building is sprinkled but no inspection/ certification

More information

ThermWise Home Energy Plan Mail-In Plan

ThermWise Home Energy Plan Mail-In Plan ThermWise Home Energy Plan Mail-In Plan Thank you for taking advantage of Dominion Energy s ThermWise Home Energy Plan to help you identify ways to improve the efficiency of your home. Energy efficiency

More information

Business Customer Information. Account Number (9 digits) Account Holder Name Phone (As shown on your utility bill) Service Street Address

Business Customer Information. Account Number (9 digits) Account Holder Name Phone  (As shown on your utility bill) Service Street Address Commercial Lighting Rebate Application Please complete the application including existing and installed information. Application will be returned without valid purchase receipt/invoice or if equipment

More information

Alessandro Volta Elementary School

Alessandro Volta Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Charles W Earle Elementary School

Charles W Earle Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Better Buildings By Design 2013 Building the Renewable Energy Ready Home Solar Thermal Lessons Learned and Results

Better Buildings By Design 2013 Building the Renewable Energy Ready Home Solar Thermal Lessons Learned and Results Image Courtesy of Harvestar Better Buildings By Design 2013 Building the Renewable Energy Ready Home Solar Thermal Lessons Learned and Results Doug Merrill, Sunward Systems Doug Merrill 20 + years of manufacturing

More information

Owner Municipality Built in 1978 Rebuilt in 2001 Rink and bleachers. Surface area (footprint) 4,140 m 2 (44,700 ft 2 )

Owner Municipality Built in 1978 Rebuilt in 2001 Rink and bleachers. Surface area (footprint) 4,140 m 2 (44,700 ft 2 ) Project profile Refrigeration Technological Innovation RAPB REFRIGERATION ACTION PROGRAM For BUILDINGS Colisée des Bois-Francs Victoriaville (Québec) MAJOR RETROFIT Summary Potential for substantial heat

More information

MAKING IT GREEN AND SAVING ENERGY WITH NSP

MAKING IT GREEN AND SAVING ENERGY WITH NSP MAKING IT GREEN AND SAVING ENERGY WITH NSP Florida Housing Coalition Annual Conference September 2012 NSP PROGRAM BACKGROUND $ 3,296,917 in funding provided by Martin County 23 units of housing purchased

More information

Mechanical System Description

Mechanical System Description 1. Building Description: Mechanical System Description The building is a Type-1B construction, 9-levels, non-high rise building with 67 affordable family housing units. The first level of the structure

More information

101 EASY WAYS TO SAVE ENERGY AND MONEY.

101 EASY WAYS TO SAVE ENERGY AND MONEY. 101 EASY WAYS TO SAVE ENERGY AND MONEY. TouchstoneEnergy.com TouchstoneEnergy.com DO A LITTLE. SAVE A LOT. EVERYTHING YOU DO, NO MATTER HOW SMALL, CAN ADD UP TO BIG SAVINGS FOR YOU AND YOUR NEIGHBORS.

More information

ENGINEERING REPORT - MECHANICAL / ELECTRICAL / PLUMBING

ENGINEERING REPORT - MECHANICAL / ELECTRICAL / PLUMBING Mechanical Systems Information The mechanical system at Reed Middle School is comprised of seventy six Trane DX/Gas rooftop units (RTUs). The recommended useful life for DX equipment is 15 years. Seventy

More information

ELECTRICAL SYSTEMS ASSESSMENT Hanover High School

ELECTRICAL SYSTEMS ASSESSMENT Hanover High School ELECTRICAL SYSTEMS ASSESSMENT Hanover High School ELECTRICAL DISTRIBUTION SYSTEM:?? The existing electrical service consists of an underground primary service originating at a utility pole on Cedar Street,

More information

Note: The office/work area is not in the scope of the PER. Existing Condition

Note: The office/work area is not in the scope of the PER. Existing Condition ROBERT G. DASHIELL, JR., P.E., INC. Consulting Engineers 1225 West 26 th Street, Norfolk, Virginia 23508 (757) 623-5012 September 14, 2016 Draft Electrical Portion of the PER Petersburg Main Sanitary Sewage

More information

CL001 >400 Watt lamp basecase, up to 600 Watt replacement fixture $95.00 Fixture

CL001 >400 Watt lamp basecase, up to 600 Watt replacement fixture $95.00 Fixture Lighting Specifications Business Please read the details below to ensure you are installing a qualifying product(s). An MID inspection of the pre-existing lighting scheme is required prior to the installation

More information

CHART PERUVIAN TECHNICAL STANDARDS

CHART PERUVIAN TECHNICAL STANDARDS CHART PERUVIAN TECHNICAL STANDARDS Peruvian Technical Standards Elaborated by the Normative Technical Committee Rational Use of Energy and the Energy Efficiency - (December 2007) Electric Motors Industrial

More information

Florence High School / Middle School Page 1 of 3 Florence, WI

Florence High School / Middle School Page 1 of 3 Florence, WI Florence High School / Middle School Page 1 of 3 Florence, WI Plumbing Systems Review: The following report is the result of a site visit by Tim Kehoe of Muermann Engineering, LLC that occurred on October

More information

Energy Efficiency Programs in Action

Energy Efficiency Programs in Action Cape Light Compact Energy Efficiency Programs in Action Case Study: CYNTHIA HAUN - HYANNIS RESIDENT PROJECT DESCRIPTION Hyannis resident Cynthia Haun successfully reduced her annual electricity use by

More information

InterNACHI Home Energy Inspection for th Street

InterNACHI Home Energy Inspection for th Street InterNACHI Home Energy Inspection for 1750 30th Street Estimated Yearly Energy Costs: $1,491 per year Dear Client, This house has been scored on a scale of 1 to 100. A 100 would represent a home with perfect

More information

Lighting Retrofit Rebate

Lighting Retrofit Rebate Lighting Retrofit Rebate 2017 Rebate Application Elk River Municipal Utilities, PO Box 430, Elk River, MN 55330 Ph: 763-441-2020 Business Information Company name Billing address Installation address (if

More information

MUKWONAGO SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY

MUKWONAGO SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY MUKWONAGO SCHOOL DISTRICT ARCHITECTURE PARK VIEW MIDDLE SCHOOL The original school building was dedicated in 1954 as the High School, with an addition in 1959, a library addition in 1970, and an addition/renovation

More information

National Grid s Direct Install Program for Commercial Customers

National Grid s Direct Install Program for Commercial Customers National Grid s Direct Install Program for Commercial Customers Reduce your energy costs, water usage, and increase the value of your property. Energy represents the single fastest-growing operating cost

More information

Calmeca Academy of Fine Arts and Dual Language

Calmeca Academy of Fine Arts and Dual Language Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

2017 Lighting Incentive

2017 Lighting Incentive Commercial & Industrial Retrofit 2017 Lighting Section A: CUSTOMER INFORMATION Customer Name Electric Account Number Rate Application Number Facility Address City State Zip Service Location Identification

More information

PLAN REVIEW SUBMITTAL GUIDE

PLAN REVIEW SUBMITTAL GUIDE PLAN REVIEW SUBMITTAL GUIDE Plans, specifications and other construction documentation for the initial plan review should be as complete as possible at the time of submittal. Use this convenient guide

More information

VOTER BOND REFERENDUM 2018 SUMMARY OF WORK PROPOSED

VOTER BOND REFERENDUM 2018 SUMMARY OF WORK PROPOSED Ashton Elementary School 1 Masonry Repair $ 42,781.50 2 Replace HVAC $ 375,000.00 3 Replace SAT @ Various Locations $ 92,364.00 3 Recoat & Resurface Exterior Paved Play Area $ 135,978.30 3 Various Technological

More information

Agustin Lara Elementary Academy

Agustin Lara Elementary Academy Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

GARCIA GALUSKA DESOUSA Consulting Engineers

GARCIA GALUSKA DESOUSA Consulting Engineers L#56566/Page 1/May 23, 2017 HVAC Heating Plant The original Town Hall building and Addition building are primarily heated by a gas fired hot water plant that is located in the basement. The boiler plant

More information

TIPS ENERGY THE LESS YOU USE, 65 WAYS TO REDUCE HOME ENERGY USE THE MORE YOU SAVE CONSERVATION

TIPS ENERGY THE LESS YOU USE, 65 WAYS TO REDUCE HOME ENERGY USE THE MORE YOU SAVE CONSERVATION NEXT 1 ENERGY CONSERVATION TIPS THE LESS YOU USE, THE MORE YOU SAVE 65 WAYS TO REDUCE HOME ENERGY USE Conserving energy at home is an easy way to save money and help reduce your environmental footprint.

More information

MH Non-Residential Permit Fees All Commercial Permit fees require a 3% BBS State Tax and are subject to a plan review and base fee.

MH Non-Residential Permit Fees All Commercial Permit fees require a 3% BBS State Tax and are subject to a plan review and base fee. BUILDING New Building $.45 per sq ft $3,500 Min $.40 per sq ft $1,000 Min $.20 per sq ft $250 Min Demolition $.10 per sq ft $150 Min Accessory Structure (over 200 sq ft) $.40 per sq ft $750 Min Retaining

More information

The U.S. Appliance Standards Program. Building Technologies Office Energy Efficiency and Renewable Energy United States Department of Energy

The U.S. Appliance Standards Program. Building Technologies Office Energy Efficiency and Renewable Energy United States Department of Energy The U.S. Appliance Standards Program Building Technologies Office Energy Efficiency and Renewable Energy United States Department of Energy AGENDA 1 2 3 IMPACT OF APPLIANCE STANDARDS PROGRAM HISTORY AND

More information

ProMoss TM Plant-Based Water Treatment Solves Problems in Tobacco Manufacturing Plant Air Washer Systems

ProMoss TM Plant-Based Water Treatment Solves Problems in Tobacco Manufacturing Plant Air Washer Systems Case Study ProMoss TM Plant-Based Water Treatment Solves Problems in Tobacco Manufacturing Plant Air Washer Systems Steve Chewning, CWT, James Hall, Southeastern Laboratories, Inc. August 2017 Air washer

More information

Element Z General Design Requirements Existing Facilities Information

Element Z General Design Requirements Existing Facilities Information PART 1 - INTRODUCTION 1.01 OVERVIEW A. This Section provides general information for building systems and components. B. Refer to the Owner s Design Guideline Elements A though G and Element Z for technical

More information

Continuous Commissioning: A Valuable Partner to Retrofit Projects

Continuous Commissioning: A Valuable Partner to Retrofit Projects Continuous Commissioning: A Valuable Partner to Retrofit Projects Yeqiao Zhu Aamer Athar Kenneth Banks Ph.D. PE, CEM PE, CEM Energy Systems Laboratory Sempra Energy Solutions Sempra Energy Solutions Charles

More information

Appendix A. Glossary of Common Terms

Appendix A. Glossary of Common Terms Glossary of Common Terms Glossary of Common Terms Absorption chiller A refrigeration machine using heat as the power input to generate chilled water. Adjustable speed drive A means of changing the speed

More information

Auburn University Basketball Arena:

Auburn University Basketball Arena: Auburn University Basketball Arena: How Building Data Analytics Achieved Energy and O&M Savings While Improving Comfort and Sustainability Eric Moore, PE, CEM, Auburn University Hadas Webb, CEM, Cimetrics

More information

MID MICHIGAN COMMUNITY COLLEGE HARRISON CAMPUS Harrison, Michigan 2015 MASTER PLAN

MID MICHIGAN COMMUNITY COLLEGE HARRISON CAMPUS Harrison, Michigan 2015 MASTER PLAN MID MICHIGAN COMMUNITY COLLEGE HARRISON CAMPUS Harrison, Michigan 2015 MASTER PLAN September 30, 2015 PBA Project No. 2015.0140.00 PETER BASSO ASSOCIATES INC. CONSULTING ENGINEERS 5145 LIVERNOIS ROAD,

More information

NORTH CENTRAL MICHIGAN COLLEGE PETOSKEY CAMPUS. Facilities Conditions Assessment Mechanical And Electrical Petoskey, Michigan

NORTH CENTRAL MICHIGAN COLLEGE PETOSKEY CAMPUS. Facilities Conditions Assessment Mechanical And Electrical Petoskey, Michigan NORTH CENTRAL MICHIGAN COLLEGE PETOSKEY CAMPUS Facilities Conditions Assessment Mechanical And Electrical Petoskey, Michigan PBA Project No. 2014.0137.00 Prepared By: Wayne Kerbelis Terry Cleis September

More information

CENTRAL STATE HOSPITAL PLAN PLANT OPERATIONS UTILITIES MANAGEMENT PLAN

CENTRAL STATE HOSPITAL PLAN PLANT OPERATIONS UTILITIES MANAGEMENT PLAN Page 1 of 11 CENTRAL STATE HOSPITAL PLAN SUBJECT: PLANT OPERATIONS UTILITIES MANAGEMENT PLAN ANNUAL REVIEW MONTH: RESPONSIBLE FOR REVIEW: March CSH Safety Officer LAST REVISION DATE: November 2003 I. SCOPE:

More information

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT

EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT Factory Plot # 33-36 Sector # 07, Chittagong Chittagong Chittagong 08 Jun 2014 The Alliance for Worker Safety Page 1/18 08 Jun 2014 Introduction to the Report

More information

Pacific Gas and Electric Company Energy Efficiency Rebates for Your Business. Lighting Rebate Catalog Saving energy for a brighter future

Pacific Gas and Electric Company Energy Efficiency Rebates for Your Business. Lighting Rebate Catalog Saving energy for a brighter future Pacific Gas and Electric Company Energy Efficiency Rebates for Your Business Lighting Rebate Catalog Saving energy for a brighter future Customers may be eligible to participate in Pacific Gas and Electric

More information

Assessing Your Airfield Electrical Distribution System

Assessing Your Airfield Electrical Distribution System Assessing Your Airfield Electrical Distribution System PRESENTED AT The 2017 Airports Conference March 30, 2017 Hershey, PA PRESENTED BY Samuel Mullen, III - Burns Engineering, Inc. 1 Presentation Objective

More information

Edward Jenner Elementary Academy of the Arts

Edward Jenner Elementary Academy of the Arts Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

George B Swift Elementary Specialty School

George B Swift Elementary Specialty School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Corbin Building. Technical Assignment 2. Matthew Trethaway Lighting/ Electrical AE 481W 10/26/2011 Advisor: Ted Dannerth

Corbin Building. Technical Assignment 2. Matthew Trethaway Lighting/ Electrical AE 481W 10/26/2011 Advisor: Ted Dannerth Corbin Building Technical Assignment 2 Matthew Trethaway Lighting/ Electrical AE 481W 10/26/2011 Advisor: Ted Dannerth 10/26/2011 Technical Report II 1 Executive Summary The following report is an overview

More information

Oscar DePriest Elementary School

Oscar DePriest Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Massachusetts School Building Authority

Massachusetts School Building Authority Massachusetts School Building Authority School District Revere District Contact Paul Dakin TEL: (781) 286-8226 Name of School Submission Date 3/6/2007 The following Priorities have been included in the

More information

101 Low-Cost /No-Cost. Home Energy-Saving Measures

101 Low-Cost /No-Cost. Home Energy-Saving Measures 101 Low-Cost /No-Cost Home Energy-Saving Measures Your Touchstone Energy Cooperative has compiled this list of low-cost / no-cost energy-saving measures to help you better manage your home s energy costs.

More information

OPERATING. Salaries, wages, and benefits personnel costs for repairs and maintenance functions, including living or accommodation allowances.

OPERATING. Salaries, wages, and benefits personnel costs for repairs and maintenance functions, including living or accommodation allowances. Page 1 of 6 Maintenance Labour Salaries, wages, and benefits personnel costs for repairs and maintenance functions, including living or accommodation allowances. Maintenance Materials & Services Building

More information

Sustainable Hot Water: Better Design, Delivery, and Use

Sustainable Hot Water: Better Design, Delivery, and Use Sustainable Hot Water: Better Design, Delivery, and Use March 24, 2009 Don Fisher Amin Delagah Fisher-Nickel, inc. PG&E Food Service Technology Center The Food Service Technology Center (FSTC) program

More information

Index. Premises Information 2 About This Log Book 3 Service and Maintenance Requirements 4 8. Fire Risk Assessments 9

Index. Premises Information 2 About This Log Book 3 Service and Maintenance Requirements 4 8. Fire Risk Assessments 9 Index Premises Information 2 About This Log Book 3 Service and Maintenance Requirements 4 8 Fire Risk Assessments 9 Fire Alarm Systems 10-20 Locations 10 Servicing 11 12 Activations 13 14 Weekly Checks

More information

César Chávez Cultural Center Sustainability Audit Report

César Chávez Cultural Center Sustainability Audit Report César Chávez Cultural Center Sustainability Audit Report Audited: December 9, 2011 Submitted: January13, 2012 Audit performed by: Nick Chaney Building contact: Sasha Paape This report contains observations

More information

NYC Department of Education

NYC Department of Education Asset: LIBERTY HS - MANHATTAN, 250 WEST 18 STREET, New York, 10011 Inspection Id Inspection Type Time In Last Edited ME : Mechanical 2018-01-29 11:32 AM 2018-02-01 10:16 AM Asset Data Are there fuel tanks?

More information

SITE SYSTEMS: FANNIE MAE EXPECTED USEFUL LIFE TABLES (FMEUL)

SITE SYSTEMS: FANNIE MAE EXPECTED USEFUL LIFE TABLES (FMEUL) SITE SYSTEMS: FANNIE MAE EXPECTED USEFUL LIFE TABLES (FMEUL) Basketball Courts 15 25 Built Improvements Playgrounds, Site Furniture, etc. 20 20 Catch Basin 40 40 Cold Water Lines 40 40 Compactors DHW Supply

More information

you We are CONSERVING dedicated to serving more efficiently. 101 Low-Cost No-Cost Home Energy-Saving Measures That s the cooperative difference.

you We are CONSERVING dedicated to serving more efficiently. 101 Low-Cost No-Cost Home Energy-Saving Measures That s the cooperative difference. ? CONSERVING We are you dedicated to serving more efficiently. That s the cooperative difference. Call 478.676.3191 800.522.2930 to schedule a residential energy audit. 101 Low-Cost No-Cost Home Energy-Saving

More information

Focus on Energy Business Programs Summary of Services and Incentives July 2009

Focus on Energy Business Programs Summary of Services and Incentives July 2009 Focus on Energy Business Programs Summary of Services and Incentives July 2009 OVERVIEW Focus on Energy Business Programs goals are to educate Wisconsin s farmers, businesses, industry, schools and local

More information

Town of Windham North Fire Station Energy Assessment Report. Table of Contents

Town of Windham North Fire Station Energy Assessment Report. Table of Contents Table of Contents 1. Table of Contents 1 2. Project Description 2 3. Executive Summary 2 1. Introduction 2. Identified Energy Conservation Measures 4. Energy Usage 6 1. Electrical 2. #2 Fuel 5. Building

More information

Related Sections: TBD. Effective Date: January 1, 2016

Related Sections: TBD. Effective Date: January 1, 2016 Description: The purpose of the section is to highlight the current applicable UMCP Design Standards for the design, selection and, installation of lighting fixtures within buildings. Related Sections:

More information

Josefa Ortiz De Dominguez Elementary School

Josefa Ortiz De Dominguez Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Maintenance Road Show

Maintenance Road Show Maintenance Road Show What does it take to maintain a campus? What are the costs? Buildings: 267 Campus Sq. Feet: 3,470,408 GSF Roads: 8.28 miles Walkways: 8.81 miles Exterior lights: 1,000 Exterior stairways:

More information

1354 CHECKLIST for Project Closeout

1354 CHECKLIST for Project Closeout 1354 CHECKLIST for Project Closeout PROJECT NUMBER: BUILDING NUMBER: DESCRIPTION OF PROJECT: Describe description of work; i.e., New Construction, Addition, Modification, Renovation, etc DRAWING NUMBER

More information

John Palmer Elementary School

John Palmer Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Lighting. The vast majority of lighting was fluorescent, either compact or linear.

Lighting. The vast majority of lighting was fluorescent, either compact or linear. Sustainability Audit Report Submitted: September 24, 2008 Audit performed by: Greg Smith and Kelsey Fisher Space/Date Audited: Student Sustainability Center/July 30, 2008 Lighting The vast majority of

More information

Village of Newburgh Heights Building Department 3801 Harvard Avenue Newburgh Heights, OH Phone: (216) Fax: (216)

Village of Newburgh Heights Building Department 3801 Harvard Avenue Newburgh Heights, OH Phone: (216) Fax: (216) Heights Village of Heights Heights, OH 44105 Permit Schedule Basic Detached Garages Up to 500 sq. ft. 501 sq. ft. or more $100.0 $10.00 $1.10 $111.10 $3.30 $113.30 Electrical Plumbing Heating Ventilating

More information

Energy Efficiency RETAIL.

Energy Efficiency RETAIL. Energy Efficiency RETAIL www.energia.ie Your chance to reduce your business energy usage by as much as 20%! 20% is a significant figure and reducing your energy bill by this amount could make a real change

More information

LED Retrofit Lighting Rebate 2017 Rebate Application

LED Retrofit Lighting Rebate 2017 Rebate Application Commercial and Industrial LED Retrofit Lighting Rebate 2017 Rebate Application Business Member Information Connexus Energy 14601 Ramsey Blvd NW Ramsey, MN 55303 ConnexusEnergy.com 763.323.2600 Company

More information

IMPA Energy Efficiency Program

IMPA Energy Efficiency Program June 2016 IMPA Energy Efficiency Program tools and incentives for residential, commercial and industrial customers to reduce energy use and save money Reduce energy use. Save money. Earn incentives. The

More information

WATER WISE SURV EY. Santa Barbara City College

WATER WISE SURV EY. Santa Barbara City College WATER WISE SURV EY FI N AL REPORT Santa Barbara City College August 21, 2013 Prepared By City of Santa Barbara Water Conservation Program WATER WISE SURVEY OF SANTA BARBARA CITY COLLEGE EXECUTIVE SUMMARY

More information

Top of the World Tower

Top of the World Tower Workplace Building Preventive Maintenance Checklist conducted for Top of the World Tower Conducted on 22 Oct 2018 11:00 AM Prepared by Greg Langley Location 1247 Dartmouth St, Albany, CA 94706, USA Completed

More information

COMMERCIAL ENERGY SAVINGS GUIDE

COMMERCIAL ENERGY SAVINGS GUIDE COMMERCIAL ENERGY SAVINGS GUIDE www.touchstoneenergy.com/bea www.touchstoneenergy.com/bea USING ENERGY MORE EFFICIENTLY IMPROVES YOUR BOTTOM LINE. Cooperatives and their commercial members share a common

More information