PROJECT SPECIFICATIONS Post Access Control Point & CCTV Installation E Pinal Air Park Rd Marana, AZ 85653
|
|
- Miles Kelly
- 5 years ago
- Views:
Transcription
1 PROJECT SPECIFICATIONS Post Access Control Point & CCTV Installation E Pinal Air Park Rd Marana, AZ SBAH ACP E Pinal Air Park Rd Marana, AZ 85653Points of Contact:
2 TABLE OF CONTENTS PART I - STATEMENT OF WORK 1.0 OVERVIEW 1.1 SCOPE 2.0 REQUIREMENTS
3 PART I. Statement of Work 1.0 Overview: This Statement of Work (SOW) establishes requirements for: a. The installation of access control equipment, hydrolic/electric vehicle access control devices, CCTV cameras & HVR and an AiPhone system. b. The State of Arizona requires two quotes from each bidding vender, one for equipment only and one for equipment plus installation. Selection will be based on meeting the requirements within this scope and State available funds. 1.1 Scope a. The Electronic Security Systems (ESS) department of the Arizona Department of Emergency Military Affiars & the Arizona Army National Guard requires the installation of an ACP (access control point) to aid in the vehicle access control point for the Silverbell Army Heliport located in Marana, Arizona. The new ACP has the required infrastrtucture installed with required conduit and cable paths. If the installation cost is greater than what the State of Arizona anticipates, then the state will revert to the lowest responsible bid for the equipment only quotation. b. The selected contractor shall install new, completely functional access control hardware that meets the specification listed in this scope of work. The specific equipment model numbers listed in this scope are required and shall not be substituted, they will be labeled with required. c. Specifically, the contractor shall install access control hardware three lanes of traffic entering the base, a visitor lane (lane 1), employee lane (lane 2) and a large vehicle lane (lane 3). Equipment listed, installing gate arms with concrete pads, mounting panels, card readers and CCTV cameras. AZARNG ESS staff will program head end equipment and the LNL-2220 intelligent dual reader controller (IDRC).
4 2.0 Requirements a. Lane 1 is the visitor lane, located nearest the guard shack (see attachment A0 01r1- AREA SITE PLAN_ pdf). This lane of traffic will require the installation of one 14' HySecurity strong Arm part number HTG ST / required. 1 in ground vehicle sensing loop (reset function) to control closure, so that arm 1 Edge sensor to re-open the arm if an obstruction is encountered. Gate arm will be controlled by push button and toggle switch located in the 1 concrete mounting slab that is a minimum of 20 x20 x20 with the electrical b. Lane 2 is the employee lane. located in between the visitor lane1 and the large vehicle lane 3 (see attachment A0 01r1- AREA SITE PLAN_ pdf). This lane of traffic will require the installation of two 14' HySecurity strong Arm part number HTG ST / required. 2 in ground vehicle sensing loops (reset function) to control closure, so that arm 2 Edge sensors to re-open the arm if an obstruction is encountered. Gate arms will be controlled by push button and toggle switch located in the 2 concrete mounting slabs that are a minimum of 20 x20 x20 with the electrical 1 AX-DVF-P video door station w/hid reader. Mounted on stanction c. Lane 3 is is the large vehicle lane. located the furthest from the guard shack (see attachment A0 01r1- AREA SITE PLAN_ pdf). This lane of traffic will require the installation of one 14' HySecurity strong Arm part number HTG ST / required. 1 in ground vehicle sensing loop (reset function) to control closure, so that arm 1 Edge sensor to re-open the arm if an obstruction is encountered. Gate arm will be controlled by push button and toggle switch located in the 1 concrete mounting slab that is a minimum of 20 x20 x20 with the electrical d. The Guard Shack This is the building that all the head end equipment will be located. The room labeled IT in (A1 01r1 PLANS_ (2).pdf). 1 LNL-2220 Lenel IDRC Access Control Panel /Required 1 AX-084C AX Series Exchange Unit /Required 1 AX-8MV Audio Video Master Station/Required 1 NET5400 PELCO / Digital Century NET5400 encoder /Required 1 DSSRV-090DVD-US-D PELCO / Digital Century NVR/Required
5 1 AX-TV Altronix power supply 24vac 25amp PD8 /Required 1 AL1012ULXPD8 Altronix Power Supply 12/24 VDC w/pd8 /Required 2 Samsung p LED monitors with overhead mounting. 2.1 CCTV The CCTV system shall be installed by the selected contractor. The HVR listed below will be mounted in the room labeled IT in (A1 01r1 PLANS_ (2).pdf). All Coaxial / CAT5 cable will be run and terminated by selected contractor. The contractor will mount all cameras and run 24VDC/VAC or 12VDC power accordingly. The HVR will be placed on the ESS SECNET network by IT staff. 1 NET5400 PELCO / Digital Century NET5400 encoder /Required 1 DSSRV-090DVD-US-D PELCO / Digital Century NVR/Required 4 C20DW-6 Analog Day/Night Fixed Camera /Required 4 13VDIR LENS 1/3 DAY/NIGHT MM F1.4 AI for C20DW-6 Cameras. /Required 4 EH Camera Enclosures for C20DW-6 Cameras /Required 2 EM1109 Pole Mount Kit for EH enclosures /Required 2 EM3512 Wall Mount Kit for EH enclosures /Required 2 PA3512 Pole mount adaptor for EH enclosures /Required 2 IMP519-1EP Pelco IP Sarix Professional Enviornmental Pendant /Required 2 WMVE-SR Wall mount kit for IMP519 /Required 2 PA101 Pole mount adaptor for WMVE-SR /Required 1 S5220-EG1 Pelco Spectra IV 20x 1080p HD Pendant Network Speed Dome /Required 1 PA402 Pole mount for Spectra Dome /Required 1 IWM-GY Wall mount for PA402 pole mount /Required 1 MCS4-2B 24VAC Power Supply for Spectra Dome/Required 2.2 Additional requirements a. Project shall include one year warranty on parts and labor. b. All bids shall include complete installation, cabling and controller termination in neat and organized fashion. c. Awarded contractor will be selected based on the lowest bid meeting the requirements listed in this scope. d. In addition for parts and labor bid, please also submit a parts only bid. e. See Attached equipment list spreadsheet for equipment only bids. (SBAH ACP Equipment List.xlsx)
A. Drawings and general provisions of Contract, including General and Supplementary Conditions apply to work of this section.
SECTION 16770 PAGE 1 PART 1 - GENERAL 1.1 RELATED DOCUMENTS: A. Drawings and general provisions of Contract, including General and Supplementary Conditions apply to work of this section. B. Division 16
More informationGARCIA GALUSKA DESOUSA Consulting Engineers
L#57297 /Page 1/July 21, 2017 ELECTRICAL SYSTEMS NARRATIVE REPORT The following is the Electrical Systems narrative, which defines the scope of work and capacities of the Power and Lighting systems, as
More informationUSD 380 Centralia, Frankfort & Vermillion
PROJECT MANUAL District Wide Security Upgrade Project Software and Hardware Specifications Covering Locking Hardware Access Control Software & Hardware Video Software & Hardware January 30, 2018 USD 380
More informationAppendix 1 LACCD Districtwide Security Performance Requirements
Appendix 1 LACCD Districtwide Security Performance Requirements SECTION LISTING 28 01 10 Overview 28 13 00 Access Control System 28 13 01 Access Control System Installation 28 13 26 Access Control Remote
More informationREQUEST FOR QUOTE. Bid Reference ACWMC Security Surveillance Access Control and Intrusion Equipment Package
April 13, 2015 REQUEST FOR QUOTE Bid Reference 09-15 ACWMC Security Surveillance Access Control and Intrusion Equipment Package REQUESTED BY: ALLEN COUNTY PURCHASING DEPARTMENT ON BEHALF OF: THE BOARD
More informationHEAD OFFICE, SECURITY DEPARTMENT
BANK OF INDIA HEAD OFFICE, SECURITY DEPARTMENT RATE TO BE QUOTED BY THE VENDOR Sr. no. Description Make Model Unit Rate Tax Total Amount I BURGLAR ALARM SYSTEM A Burglar/Intruder Alarm System.B Control
More informationFor Dealers / Integrators / Architects. IS Series. Video Intercom. Building Communication. Controlling Security.
For Dealers / Integrators / Architects IS Series Video Intercom Building Communication. Controlling Security. IS Series helps save money Control multiple functions from any location to help reduce overall
More informationSPECIFICATIONS FOR PURCHASE AND INSTALLATION OF A NEW ACCESS CONTROL AND CCTV SECURITY SYSTEM FOR LARSON ICE CENTER. (Revised February 13, 2014)
SPECIFICATIONS FOR PURCHASE AND INSTALLATION OF A NEW ACCESS CONTROL AND CCTV SECURITY SYSTEM FOR LARSON ICE CENTER (Revised February 13, 2014) BID OPENING, FEBRUARY 25, 2014 GOVERNMENT CENTER, Rm. 241,
More informationHARDwired Installation/ Owner s Manual
HARDwired Installation/ Owner s Manual Use this manual for circuit - Revision L or higher. For Models:,, and Multi-Door Access Controller Wiegand Compatable --R-- Provides Access Control System to manage
More informationAMENDMENT NO.: III INVITATION FOR BID NO.: GPA FOR
January 26, 2018 AMENDMENT NO.: III TO INVITATION FOR BID NO.: GPA-022-18 FOR PHYSICAL SECURITY AND ACCESS CONTROL SYSTEM (ACS) REPAIR AND UPGRADE AT VARIOUS GPA LOCATIONS Prospective Bidders are hereby
More informationBLUEPRINT FOR PERIMETER, PHYSICAL SECURITY AND ACCESS CONTROL AT ELDO LAKES EXT. 5 & 6
BLUEPRINT FOR PERIMETER, PHYSICAL SECURITY AND ACCESS CONTROL AT ELDO LAKES EXT. 5 & 6 Compiled by: Sybrand vd Berg Feb 2005 Rev. 2 1. Introduction BLUEPRINT FOR PERIMETER-, PHYSICAL SECURITY AND ACCESS
More informationCHAPTER SIX Automatic Gates
CHAPTER SIX Automatic Gates Contents: Steps to Obtain Permits Installation Requirements Electrical Requirements Gate Construction Knox Key Switch Placement and Installation Preemption Automatic Gate Signage
More informationE-BOOK - CCTV INSTALLATION BOOK OWNERS MANUAL EBOOK
11 January, 2018 E-BOOK - CCTV INSTALLATION BOOK OWNERS MANUAL EBOOK Document Filetype: PDF 218.9 KB 0 E-BOOK - CCTV INSTALLATION BOOK OWNERS MANUAL EBOOK ADT Health / Medical Alert User Manuals and Quick
More information[Project Location] SECTION FUSION STAINLESS STEEL DOME HOUSING MOOG VIDEOLARM A&E SPECIFICATION SSDP SERIES
SECTION 28 23 29 FUSION STAINLESS STEEL DOME HOUSING MOOG VIDEOLARM A&E SPECIFICATION SSDP SERIES DIVISION 28- ELECTRONIC SAFETY AND SECURITY 28 20 00 ELECTRONIC SURVEILLANCE 28 23 00 VIDEO SURVEILLANCE
More information2013 Honeywell Users Group EMEA. Adrian Fielding Security from Day One
2013 Honeywell Users Group EMEA Adrian Fielding Security from Day One 1 2 Safety Moment Agenda Experion Industrial Security Integration of Security Layers Introduction to Digital Video Manager Console
More informationCARD ACCESS CONTROL SYSTEM
SECTION 13851 CARD ACCESS CONTROL SYSTEM PART 1 GENERAL 1.01 SUMMARY A. Section Includes: A complete, operable, tested, integrated proximity access control system, to operate on a proximity principle where
More informationMarch 11, 2013 ADDENDUM #1. RFP-DEM-12/ FDEM Facility Security System Replacement
STATE OF FLORIDA DIVISION OF EMERGENCY MANAGEMENT RICK SCOTT Governor BRYAN W. KOON Director March 11, 2013 ADDENDUM #1 RFP-DEM-12/13-015 FDEM Facility Security System Replacement The Division is issuing
More informationTAB C-6 KEYLESS ACCESS AND SECURITY SYSTEM GUIDELINE
TAB C-6 KEYLESS ACCESS AND SECURITY SYSTEM GUIDELINE The University of Arizona has implemented a Keyless Access and Security System program to provide a cost effective, efficient, and maintainable means
More information17.25 (438 mm) 37.5 (953 mm) 3.5 (89 mm) 3.0 (76 mm) 28 (711 mm) or 36 (915 mm)
ALVARADO Supervisor 2000-SM Optical Monitor Lane for Bi-directional Control Technical Specifications Dimensions Cabinet Length: Cabinet Height: Center Cabinet Width: End Cabinet Width: Clear Passage Width:
More informationPhysical Security Standards WARREN J. BUJOL, IBERIABANK MATTHEW RONIGER, IBERIABANK
Physical Security Standards WARREN J. BUJOL, IBERIABANK MATTHEW RONIGER, IBERIABANK Physical Security Standards Agenda Making a Case for Physical Security Why have Standards? Risk Assessments - Justifications
More informationESTIMATE SET-UP PACKAGE BID SCHEDULE ENTRY AND MAINTENANCE
BIDDING INFORMATION BID DATE: PROJECT NAME: ADDRESS: ESTIMATE SET-UP PACKAGE BID SCHEDULE ENTRY AND MAINTENANCE ESTIMATE NO.: CITY: STATE: ZIP: PRIME: PROJECT MANAGER: PROJECT TYPE: SUB: $ SIZE: BID TIME:
More informationDIVISION 28 ELECTRONIC SAFETY AND SECURITY
281300 - ACCESS CONTROL A. General DIVISION 28 ELECTRONIC SAFETY AND SECURITY At the beginning of the project, schedule a meeting with the Facilities Access/Maintenance Coordinator with questions and concerns.
More informationStandards and Procedures. Installation of Cameras and Camera Systems At University of North Carolina at Wilmington UNCW
Standards and Procedures Installation of Cameras and Camera Systems At University of North Carolina at Wilmington UNCW REV 062817 Provided by UNCW Physical Security and Access 1 INDEX OVERVIEW. 3 RESPONSIBILITIES..
More informationElectronic Safety and Security
28 Electronic Safety and Security NOTE: This is a new section, which includes content from previous sections of the KU Design Standards, along with appropriate revisions and updates. Significant revisions
More informationInstallation Instructions. CAR COMING Pedestrian Alert Safety Signs (PASS)
Installation Instructions CAR COMING Pedestrian Alert Safety Signs (PASS) Pedestrian Alert Safety System (PASS) www.passsigns.com support@passsigns.com 480-689-1993 Quick Guide Please read the entire guide
More informationPre-Bid Meeting Minutes 2018 A & E RFP February 6, :00 a.m.
Attendees: Pre-Bid Meeting Minutes 2018 A & E RFP February 6, 2019 10:00 a.m. Anthony Shomin Sue Martin Architectural & Engineer Professionals KCKHA Modernization Coordinator KCKHA Modernization Admin.
More informationIR Intelligent Speed Dome Installation Manual
IR Intelligent Speed Dome Installation Manual Version 1.0.0 Table of Contents 1 INSTALLATION PREPARATION... 1 1.1 Basic Requirement... 1 1.2 Installation Check... 1 1.3 Cable Preparation... 1 1.3.1 The
More informationBSD Technical Standard. Division 28: Electronic Safety & Security
Division 28: Electronic Safety & Security I. PURPOSE This Technical Standard is a narrative describing Beaverton School District s (BSD s) basis of design for electronic safety and security in BSD facilities.
More informationSECTION DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM
SECTION 283111 - DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division
More informationEG Controls. SLIMVIEW 120 VOLT FLOAT SERIES DUPLEX PUMP CONTROL PANEL SPECIFICATION for CITY OF E G
E SLIMVIEW 120 VOLT FLOAT SERIES DUPLEX PUMP CONTROL PANEL SPECIFICATION for CITY OF DATE: 11/13/06 2/1/07 1 Copyright, E, Inc. E 1. ENERAL...4 1.1 Scope Of Work... 4 1.2 Codes and Standards... 4 2. PRODUCTS...5
More informationSECTION VIDEO SUREVEILLANCE SYSTEM
SECTION 27 66 00 PART 1 - GENERAL 1.01 SCOPE A. Refer to Section 27 00 00 for additional project scope information. 1.02 PRECEDENCE A. Obtain, read and comply with General Conditions and applicable sub-sections
More informationWhy use CCTV... Domestic & Commercial Solutions. We believe CCTV has a major role to play in the prevention, detection and prosecution of crime
Why use CCTV... To Deter& Detect Criminal Activity To Identify Suspects To Gather Evidence To Gather Intelligence To Aid Prosecutions To Monitor Anti-Social Behaviour To Assist Emergency Services Traffic
More informationAccess Control. Total Perimeter Protection Solutions from one Source
Access Control Total Perimeter Protection Solutions from one Source FENCE SOLUTIONS IN ORNAMENTAL CHAIN LINK WOOD PVC ACCESS CONTROL WWW.MERCHANTSMETALS.COM 866-888-5611 A C C E S S C O N T R O L The success
More informationCCTV WIRING GUIDE PDF
CCTV WIRING GUIDE PDF - Are you looking for cctv wiring guide Books? Now, you will be happy that at this time cctv wiring guide PDF is available at our online library. With our complete resources, you
More informationConstruction Method, Material Selection, Fire Prevention & Building Security System For Project 9a : Board 4 ; For Project 9b : Part 4
Construction Method, Material Selection, Fire Prevention & Building Security System For Project 9a : Board 4 ; For Project 9b : Part 4 Issued by: Sr Dr. Md Azree Othuman Mydin 1. Construction Method Which
More informationAUDIO VIDEO Proposal
AUDIO VIDEO Proposal Home Theater System designed for Thomas & Jennifer Douglas 327 Canyon View Terrace Belair, CA 90246 310-457-2457 Submitted by: ELITE AV SYSTEMS Harold Wilford h.wilford@eliteav.com
More informationGuide Specifications. HyperPod System PART 1 - GENERAL 1.01 SUMMARY
Guide Specifications HyperPod System THIS GUIDE SPECIFICATION IS WRITTEN IN ACCORDANCE WITH THE CONSTRUCTION SPECIFICATIONS INSTITUTE (CSI) MASTERFORMAT. THIS SECTION MUST BE CAREFULLY REVIEWED AND EDITED
More informationNZQA registered unit standard 5881 version 6 Page 1 of 5. Demonstrate knowledge of electronic security devices
Page 1 of 5 Title Demonstrate knowledge of electronic security devices Level 2 Credits 6 Purpose People credited with this unit standard are able to demonstrate knowledge of the purpose and application
More informationCUSTOMER JOB NO. 7582
Bloomer Constructions PO Box 5480 Capalaba QLD 4161 Job No: 7582 Site: Bloomers - 138 Albion Rd Site Contact: Site Phone: Salesperson: Brett Muller Scope of Quote : - Electrical & communication allowances
More informationSecurityScan Inspection Certificate
SecurityScan Inspection Certificate For Sample Inspection Report 123 Main Street Kalamazoo, MI 49007 Tested to applicable Standards This Inspection was performed in accordance with applicable Standards.
More informationSecurity Considerations for Secure Workplaces
Security Considerations for Secure Workplaces Mitchell Factor HMA Consulting, Inc. USA Canada UK UAE Overview Security Risk Assessment The Process Security Design Process Technology Updates & Design Considerations
More informationUL TEST REPORT AND PROCEDURE
Issue Date: 2011-01-24 Page 1 of 18 Report Reference # E183863-A17-UL UL TEST REPORT AND PROCEDURE Standard: Certification Type: CCN: UL 60950-1, 2nd Edition, 2007-03-27 (Information Technology Equipment
More informationRFP Addendum 2 March 31, 2016
RFP Addendum 2 March 31, 2016 For Best Value Procurement Option Three Security Upgrades Ph 1 UT Health Science Center SBC No. 540/013-04-2015 This Addendum forms a part of the Request for Proposals (RFP)
More informationEcoAisle Thermal Containment System
Guide Specifications EcoAisle Thermal Containment System THIS GUIDE SPECIFICATION IS WRITTEN IN ACCORDANCE WITH THE CONSTRUCTION SPECIFICATIONS INSTITUTE (CSI) MASTERFORMAT. THIS SECTION MUST BE CAREFULLY
More informationINTREPID Perimeter Intrusion Detection System
TM INTREPID Perimeter Intrusion Detection System Next Generation Perimeter Protection icropoint Cable combines patented Southwest Microwave technology with microprocessor power and laptop computer convenience.
More informationSECTION Power over Ethernet (PoE) Enabled Camera Housing Moog Videolarm SM5, ACH13, FDW75
SECTION 28 23 29 Power over Ethernet (PoE) Enabled Camera Housing Moog Videolarm SM5, ACH13, FDW75 DIVISION 28 ELECTRONIC SAFETY AND SECURITY 28 20 00 ELECTRONIC SURVEILLANCE 28 23 00 Video Surveillance
More informationProduct Specifications Dialog Room Controller* (*patent pending)
1 Product Specifications Dialog Room Controller* (*patent pending) 1. GENERAL 1.1. OVERVIEW 1.1.1. Provide a complete stand-alone, decentralized, low voltage, digital lighting control system for classrooms,
More informationIntelligent Single Loop Fire Alarm Control Panel
Intelligent Single Loop Fire Alarm Control Panel The CAX-CTL-1L Intelligent Single Loop Fire Alarm Control Panel is a member of the industry leading Axis AX Series Intelligent Fre Alarm Control Panels
More informationUNIVERSITY OF MANITOBA PROCEDURE
UNIVERSITY OF MANITOBA PROCEDURE Procedure: UNIVERSITY BUILDING ACCESS CONTROL Parent Policy: Effective Date: July 2, 2013 Revised Date: Review Date: July 2, 2023 Approving Body: Authority: Responsible
More informationTPW-900ETS01. Product Manual. Intelligent Swing Gate Turnstile
TPW-900ETS01 Intelligent Swing Gate Turnstile Product Manual Contents Product Description... 1 Structure Chart... 2 Dimension Figure Unit mm... 2 Product Parameters... 3 Product Function... 3 Custom-made
More informationSECTION LIGHTING
SECTION 26 50 00 LIGHTING PART 1 GENERAL 1.1 DESCRIPTION A. Scope: 1. CONTRACTOR shall provide all labor, materials, equipment, and incidentals as shown, specified, and required to furnish and install
More informationBL41 Extra-long Barrier
BL41 Extra-long Barrier NAM-BL41-ES-EN-A 1/8g ENGINEERING SPECIFICATIONS BL41 Extra-long Barrier PART I GENERAL SECTION 08 34 56 Security Gates SECTION 11 12 33 Parking Gates SECTION 28 13 00 Access Control
More informationCHICAGO ZOOLOGICAL SOCIETY REQUEST FOR PROPOSAL (RFP) FOR HOLIDAY MAGIC 2016
The Chicago Zoological Society is soliciting proposals to provide lighting and entertainment options for Holiday Magic 2016. This document outlines the Society s guidelines for your responses. The Proposal
More information2017 UPDATE AUDIO/ VIDEO &SMART HOME PREWIRE. QUICK GUIDE A reference for low voltage wiring.
2017 UPDATE AUDIO/ VIDEO &SMART HOME PREWIRE QUICK GUIDE A reference for low voltage wiring. INTRODUCTION Thanks for downloading our Prewire Quick Guide. We created it to be a helpful resource for our
More informationDSS. Dahua VMS Platform
DSS Dahua VMS Platform CATALOG 1 2 3 4 5 Introduction Functions Add-ons Advantages Vertical DSS7016D/DSS4004 DSS DSS Mobile phone Embedded Linux client WEB, PC Client DSS7016D/DSS4004 Centre management
More informationCITY OF FARMINGTON 800 Municipal Drive Farmington, NM (505) Fax (505)
CITY OF FARMINGTON 800 Municipal Drive Farmington, NM 87401-2663 (505) 599-1373 Fax (505) 599-1377 http://www.fmtn.org IMMEDIATE ATTENTION Construction Services for Municipal Operations Center Expansion
More informationSTATEMENT OF WORK ELECTRICAL REPAIR / MAINTENANCE BUILDING PROJECT FDC RACCOON CREEK STATE PARK (BEAVER COUNTY)
STATEMENT OF WORK ELECTRICAL REPAIR / MAINTENANCE BUILDING PROJECT FDC-213-100797 RACCOON CREEK STATE PARK (BEAVER COUNTY) I. SCOPE OF WORK: The Commonwealth of Pennsylvania, Department of Conservation
More informationSustain.Ability. Adrian Fielding Integrated Safety & Security Honeywell Users Group EMEA
Sustain.Ability. Adrian Fielding Integrated Safety & Security 2012 Honeywell Users Group EMEA 1 Safety Moment DALE EARNHARDT Sr. 1951-2001 76 NASCAR Wins in 677 Races Refused to wear his HANS (Head and
More informationANNEXURE-III BUILDING MANAGEMENT SYSTEM (BMS) BMS Total ANNEXURE-III. SL DESCRIPTION OF ITEM UNIT QTY Rate in figures Rate in words AMOUNT
PRICE BID Name of the Project : Supply, Installation, Testing and Commissioning of BMS, PA, CCTV, AVS, Access Control System for Construction of Partially completed Building at Centre for Development of
More information6 Inch Speed Dome Installation Manual V2.0.0
6 Inch Speed Dome Installation Manual V2.0.0 2010-01 1 Thank you for purchasing our product. If there is any question or request, please do not hesitate to contact dealer. This manual is applicable to
More informationCampus Wide Fire Alarm Repairs
BID # 15-24 Campus Wide Fire Alarm Repairs SECTION "C" TECHNICAL SPECIFICATIONS OWNER Board of Trustees Middlesex County College 2600 Woodbridge Avenue P.O. Box 3050 Edison, New Jersey 08818-3050 PREPARED
More informationTABLE OF CONTENTS. Tender Forms Letter of Tender A20 Appendix to Tender A20 A20 Contract Agreement A20
TABLE OF CONTENTS VOLUME I TENDER DOCUMENTS Part 1 Instructions to Tenderers... thru - 27 Part 2 Part 3 A16 Part 4 Tender Forms Letter of Tender A20 Appendix to Tender A20 A20 Contract Agreement A20 Forms
More informationDell and Lenel Grow Globally, Together
technology Dell and Lenel Grow Globally, Together CASE STUDY OnGuard Delivers Flexible Capabilities and Ability to Handle Eventualities That We Couldn t Even Yet Predict. At age 19, Michael Dell founded
More information2-inch HDCVI Speed Dome Installation Manual
2-inch HDCVI Speed Dome Installation Manual Version 1.0.1 Table of Contents 1 INSTALLATION PREPARATION... 1 1.1 Basic Requirements... 1 1.2 Installation Check... 1 1.3 Cable Preparation... 1 1.3.1 Cable
More informationSmart Home Security System
Company Profile Smart Home Security System Founded in 2007, Ansee Co., Ltd is a national HI-TECH Company who professionally focus on smart security system. We are the pioneer in China that perfectly integrate
More informationJM Series. 7-inch Touchscreen Intercom
JM Series 7-inch Touchscreen Intercom JM Series A perfect solution! The JM Series features a large 7-inch touchscreen monitor for clear visitor identification and easy operation control. The JM Series
More informationSMART NITRO SOLUTION
SMART NITRO SOLUTION Integrated Security System V1.5 Page 1 Introduction NITRO Group is the well established security solution provider. Our group of company has started the development of our own integrated
More information6-inch Intelligent Speed Dome Installation Manual
6-inch Intelligent Speed Dome Installation Manual Version 1.0.2 Table of Contents 1 INSTALLATION PREPARATION... 1 1.1 Basic Requirements... 1 1.2 Installation Check... 1 1.3 Cable Preparation... 1 1.3.1
More informationCCTV Camera - Global Market Outlook ( )
Published on Market Research Reports Inc. (https://www.marketresearchreports.com) Home > CCTV Camera - Global Market Outlook (2015-2022) CCTV Camera - Global Market Outlook (2015-2022) Publication ID:
More informationACM8 & ACM8CB. Access Power Controllers Installation Guide. - Fused Outputs - Fused Outputs. - PTC Outputs - PTC Outputs. Models Include: Rev.
ACM8 & ACM8CB Access Power Controllers Installation Guide Models Include: ACM8 ACM8E - Fused Outputs - Fused Outputs ACM8CBE ACM8CB - PTC Outputs - PTC Outputs Rev. 092503 Overview: These units convert
More informationPRODUCT. Access Control Systems ILS/UTC 125Khz Prox Offline Lock Toledo Handle with SFIC Key ILS C4P6MFXSCR0 $ % $497.
Department of Information Resources Contract No. DIR TSO 3464 Products and Related Services for Surveillance, Security and Monitoring BID PACKAGE 2 PRICING SHEET COMPANY NAME: KRATOS PUBLIC SAFETY & SECURITY
More informationDOOR MONITORING/DURESS SYSTEM
SECTION PART 1 - GENERAL 1.1 RELATED SECTIONS A. Comply with the requirements of Section 27 05 00 Common Work Results for Communications. 1.2 DEFINITIONS A. Not used. 1.3 DESCRIPTION OF SYSTEM: A. Provide
More informationSMALL WORKS PROJECT REQUEST FOR SEALED BIDS
SMALL WORKS PROJECT REQUEST FOR SEALED BIDS PIERCE COUNTY FIRE PROTECTION DISTRICT #22 18421 OLD BUCKLEY HIGHWAY BONNEY LAKE, WA 98391 (253) 863-1800 (253) 863-1848 (FAX) Date Bid Requested: 5/24/2012
More informationPort of Portland Conveying Equipment Guidelines
Role: Consultant for the Port Design Guidelines Port of Portland Conveying Equipment Guidelines ELEVATOR, ESCALATOR, AND MOVING WALK DESIGN OVERVIEW The Division 14 specification sections include appropriate
More informationACSI MODEL 1410 POWER SUPPLY INSTALLATION INSTRUCTIONS
II 1400-3 ACSI MODEL 1410 POWER SUPPLY INSTALLATION INSTRUCTIONS Features: For use with doors or groups of doors that must interlock with each other to regulate control of accessing one area from another,
More informationWARNING. Installation Tip: Try out this unit before installing onto a fire door system. Test and learn the release INTRODUCTION
WARNING 1. CAUTION: Review all installation instructions, procedures, cautions and warnings contained within this manual prior to installing and/or servicing this product. As with all releasing device
More informationSTATEMENT OF WORK. Physical Protection Equipment Upgrades for Al-Tuwaitha Site in Iraq
STATEMENT OF WORK Physical Protection 1. Background 1.1. This Statement of Work (SOW) describes the requirements for providing equipment for physical protection and nuclear security at the Al-Tuwaitha
More informationGE LightSweep Lighting Control System Guideform Specification
GE Lighting Control GE LightSweep Lighting Control System Guideform Specification If you have any questions at all regarding this specification, please contact your local GE Lighting Control representative,
More informationTable-1: Clarifications and modification in tender specifications based on Pre-bid meeting discussion
Table-1: Clarifications and modification in tender s based on Pre-bid meeting discussion Sr. Ref Page. 1 4 Clause Site Preparation and Partitions walls 2 11 SLD 3 18 Batteries 4 18 Batteries 5 32 to 34
More informationAE Security Group. Qualification Statement
Qualification Statement 1 AE Security Group Executive Summary AE Security Group (d/b/a of AE of Ohio, Inc.) is an experienced security system contractor for prisons and jails. We are located in Columbus
More informationIntelligent 2 & 4 Loop Fire Alarm Control Panels
Intelligent 2 & 4 Loop Fire Alarm Control Panels Advanced has combined the latest technology with many years of fire experience, to create the Axis AX Series Intelligent Fire Alarm Control Panels. The
More informationSECTION INTRUSION DETECTION
(NOTE TO DESIGNER: These Specifications are basic minimum criteria to be met in preparing the final specifications for this section, which is the responsibility of the Designer.) SECTION 28 16 00 INTRUSION
More informationCALL FOR A FREE SURVEY
CCTV FIRE & SECURITY SOLUTIONS MADE SAFE CCTV Systems specifically designed and tailored for the commercial CCTV market What is CCTV? Closed-circuit television (CCTV), also known as video surveillance,
More informationBLG77 Rising Fenced Barrier
BLG77 Rising Fenced Barrier 1/8 ENGINEERING SPECIFICATIONS BLG77 Rising Barrier PART I GENERAL SECTION 08 34 56 Security Gates SECTION 11 12 33 Parking Gates SECTION 28 13 00 Access Control SECTION 34
More information1 Company Profile 2018
1 Company Profile 2018 Grow Your Business with us 2 About Versatile TechnoLasb PVT.LTD Versatile Technolabs PVT. LTD is a leading solution provider, turnkey system Integrator and innovative solution consultant
More informationProposed Development at Likoni Road, Nairobi for NTSA - Security Systems Installations works bills of Quantities
DESCRIPTION QTY UNIT RATE (Ksh.) AMOUNT (Ksh.) BILL 1: CCTV INSTALLATION - INSPECTION BUILDING SUPPLY, DELIVER, INSTALL SET TO WORK AND COMMISSION THE FOLLOWING:- A. GROUND FLOOR 1.01 CAT6E UTP 4 Pair
More informationSpeedStile FP. Full-Panel Speed Gate with Sliding Glass Barrier
The SpeedStile FP continues to be one of Gunnebo s most popular and sought after optical turnstile products. The SpeedStile FP can be designed in a wide variety of finishes such as stainless steel, brass,
More informationSECTION NURSE CALL SYSTEM
NURSE CALL SMARTCARE NURSE CALL SOLUTION Architectural Specifications Part 1 General SECTION 275223 - NURSE CALL SYSTEM 1.0 Summary 1.1 This section includes nurse call system and requirements for system
More information2015 List of Exempt Machinery and Equipment Steel Products The Department of General Services (DGS) has reviewed all comments and supporting documentation received prior to the end of the thirty-day (30)
More informationBi-Directional Barrier Arm Turnstile
ES831 *Custom model shown in stone and bronze Bi-Directional Barrier Arm Turnstile Model ES831 Optical Turnstiles > ES831 Series > Optical Turnstiles w/ Barrier Arms > Design Overview The ES831 bi-directional
More informationMEDUSA. Universal dome housing for discreet surveillance Revision 1027
Universal dome housing for discreet surveillance Revision 1027 Main Features Top-opening system Indoor/Outdoor installations Universal internal adapter for several speed domes and network PTZ cameras Camera
More informationFour-Door Access Controller User s Manual
Four-Door Access Controller User s Manual V1.0.0 1 Table of Contents 1 Overview... 1 2 Device Appearance... 2 3 Device Installation and Uninstallation... 3 3.1 Device Installation... 3 3.2 Device Uninstallation...
More informationFALCO Access Control. Product Training
FALCO Access Control Product Training FALCO are leaders in the design and manufacture of state of the art access control and security solutions. Since our inception in 2000, over 100,000 FALCO systems
More informationDesigning the Right Access Control System A Case Study. 12 th May 2010
Designing the Right Access Control System A Case Study 12 th May 2010 Partner of Choice Approach Committed to working together to deliver innovative security solutions - End User - System Integrator -
More informationACCOMMODATION AND REAL ESTATE SERVICES (ARES) SECURITY SYSTEM SPECIFICATIONS
ACCOMMODATION AND REAL ESTATE SERVICES (ARES) SECURITY SYSTEM SPECIFICATIONS Table of Contents 1. GENERAL... 3 1.1. LICENCES, APPROVALS, PERMITS, & STANDARDS... 3 1.2. GENERAL CONDITIONS... 3 1.3. DOCUMENTATION...
More informationSpecifications Occupancy/Vacancy Sensors CSI ASHRAE AIA Division 16 Section 16950
1 Specifications Occupancy/Vacancy Sensors CSI 26.09.23. ASHRAE 90.1-2010 AIA Division 16 Section 16950 1. PART 1 - General 1.1 Overview 1.1.1 Provide Occupancy/Vacancy sensors as shown on the plans and
More information1. Functional Block Diagram: Show single-line interconnections between components for signal transmission. Show cable types and sizes.
SECTION 16726 - VIDEO SURVEILLANCE SYSTEM PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. The General Provisions of the Contract, including the General Conditions, Supplementary Conditions and Special Conditions,
More informationACCESS CONTROL ENTERPRISE SYSTEM (ACES) CARD ACCESS DIVISION , ISSUE # 6, JANUARY,
Page 1 of 31 ACCESS CONTROL ENTERPRISE SYSTEM (ACES) CARD ACCESS DIVISION 28 13 00, ISSUE # 6, JANUARY, 2018 http://maps.stanford.edu/fdg_available ISSUE AUTHOR, DATE APPROVED BY, DATE EFFECTIVE DATE 1
More informationEngineering Specifications
BL229 Rising Barrier NAM-BL229-ES-EN-A 1/8g ENGINEERING SPECIFICATIONS BL229 Rising Barrier PART I GENERAL SECTION 08 34 56 Security Gates SECTION 11 12 33 Parking Gates SECTION 28 13 00 Access Control
More informationPower Supplies. Overview
Power Supplies Overview Access control provides enhanced security, audit trails, and custom credentials. The power supply is necessary to make the entire system operational. Power supplies offer accurate
More information