1 Technical Committee on Fundamentals of Combustion Systems Hazards AGENDA Dec 4-6, 2013 Georgia Power Company Headquarters Banquet Room 241 Ralph McGill Blvd Atlanta, GA 1. Chair s welcome, call to order, and opening remarks at 8:00 a.m. EST. 2. Self-Introduction of Committee Members and Guests 3. Approval of Minutes from the January 2013 FD Meeting in Houston, TX. The minutes are posted on the NFPA 85 document information page, 4. Staff Liaison Report A. Revision Cycle Review and timeline (Attachment A) B. Committee Membership Update (For the period from Jan 4, 2013 through Nov 15, 2013) Name Category Change Date Robert Dobbins I (Principal) From Alt to P 3/7/2013 Richard Gallagher I (Alt to R. Dobbins) From P to Alt 3/7/2013 James Franks I (Principal) From Alt to P 3/7/2013 Harley Ross M (Alt to R. Kleen) Appoint 3/7/2013 Darrell Dorman M (Alt to B. Basile) Appoint 7/29/2013 Gahan Mullen U (Alt to M. Ratcliffe) Appoint 10/23/2013 James Lemanski I (Alt to J. Franks) Resign 7/8/2013 (Total Voting Members: 27. M = 30%; SE = 33%; U = 19%; I = 19%) 5. Old Business A. Gas Line Purging Task Group - Members of the task group are: B. Baesel; R. Gallagher; T. Jablkowski; R. Kleen; D. Mason; and F. Switzer. The task group submitted recommendations to the committee to designate a single equipment isolation valve and identify it in annex A figures. The committee adopted these recommendations as First Revisions. NFPA Staff notes that the First Revision resulted in modifications only to fuel gas system diagrams. The Page 1 of 29
2 committee should review the First Revisions and determine if similar changes should be made to liquid and pulverized fuel system diagrams. B. Vent Valve Sizing NFPA Staff submitted a Code Fund Request to the Fire Protection Research Foundation. The project was released as a student project with an associated stipend. However, no volunteers were identified to perform the project. Therefore, it will be resubmitted for calendar year In addition, Mr. Zadiraka reported that he has interacted with industry participants who misunderstand the purpose of the vent valve, particularly in the SIS user groups. Mr. Zadiraka recommended that a definition or annex text be developed to clarify the purpose of the vent valve. C. Referenced Documents in Fundamentals Chapters. Mr. Switzer agreed to work with Mr. Mason to review the documents referenced in mandatory text in the Fundamentals chapters. In addition, the ASME Boiler and Pressure Vessel Code committee is working on a new section 7 on combustion systems. Sections 6 and 7 are recommended practices for maintenance of boilers, mainly focused on commercial/institutional sized boilers. NFPA Staff notes that Brian Moore is no longer participating in the NFPA Boiler Committees. NFPA Staff seeks a volunteer to continue monitoring ASME activities in this area. D. Requirement for burner management system to be limited to a single boiler or HRSG. NFPA Staff contacted API task group leader on draft recommended practice API 538 and learned that the final ballot was completed, but no timeline has been established for publication of the recommended practice. NFPA Staff will contact API staff and report to the committee. E. Glossary Update. The committee requested that NFPA submit a request to the NFPA Standards Council to include the NFPA Glossary of Terms into the boilerplate text in 3.1 of every NFPA Standard. NFPA Staff did not submit the request because it is not an issue reviewable by the Standards Council. NFPA Staff has submitted the request to the NFPA task group responsible for revising the NFPA Manual of Style. NFPA Staff will advise the committee of any action taken by NFPA. F. Recognition of NFPA 85 in Latin America. NFPA Staff agreed to work with Mr. Lasarte to increase awareness of NFPA 85, perhaps through NFPA Journal Latinoamericano. NFPA Staff contacted the NFPA International Department to identify additional resources, but no further action has been taken. Page 2 of 29
3 G. Fuel gas piping maintenance and purging task group. The committee established a task group to look at possible purging requirements downstream of the equipment isolation valve. The committee created Committee Input (CI) 125 to solicit public comments and support revision of NFPA 85. The task group scope is to recommend new minimum safety requirements for opening and recharging a fuel gas system for maintenance or inspection. The task group is asked to report back in the Second Draft meeting. Task group members are: B. Baesel (chair); T. Jablkowski; J. Kane; D. Mason; and A. Zadiraka. H. Interlock requirements task group. M. Polagye agreed to request that the Correlating Committee establish a task group to make recommendations regarding the interlock issues described by Mr. Dan Lee in Public Input 44. The Correlating Committee agreed to work as a committee on this issue, rather than establish a task group. The Correlating Committee will meet off-cycle following issuance of the 2015 edition to develop recommendations for the appropriate technical committees. 6. New Business A. Document Revision. Review BCS-FUN Public Comments and Correlating Committee Notes. (Attachment B). 7. Other Items? 8. Date/Location of Next Meeting. This concludes the committee work for the F2014 revision cycle. The next meeting will be scheduled as needed. 9. Adjournment. Page 3 of 29
4 Attachment A: NFPA F2014 Revision Cycle Page 4 of 29
5 2014 FALL REVISION CYCLE *Public Input Dates may vary according to documents and schedules for Revision Cycles may change. Please check the NFPA Website for the most up to date information on Public Input Closing Dates and schedules at # (i.e. and click on the Next Edition tab Process Stage Public Input Stage (First Draft) Process Step Dates for TC Dates for TC with CC Public Input Closing Date* 1/4/2013 1/4/2013 Final date for TC First Draft Meeting 6/14/2013 3/15/2013 Posting of First Draft and TC Ballot 8/2/2013 4/26/2013 Final date for Receipt of TC First Draft ballot 8/23/2013 5/17/2013 Final date for Receipt of TC First Draft ballot recirc 8/30/2013 5/24/2013 Posting of First Draft for CC Meeting 5/31/2013 Final date for CC First Draft Meeting 7/12/2013 Posting of First Draft and CC Ballot 8/2/2013 Final date for Receipt of CC First Draft ballot 8/23/2013 Final date for Receipt of CC First Draft ballot recirc 8/30/2013 Post Final First Draft for Public Comment 9/6/2013 9/6/2013 Public Comment closing date 11/15/ /15/2013 Final Date to Publish Notice of Consent Documents (Documents That Received No Comments) 11/22/ /22/2013 Appeal Closing Date for Consent Documents (15 Days) (Documents That Received No Comments) 12/7/ /7/2013 Final date for TC Second Draft Meeting 5/2/2014 1/24/2014 Posting of Second Draft and TC Ballot 6/13/2014 3/7/2014 Comment Stage Final date for Receipt of TC Second Draft Ballot 7/7/2014 3/28/2014 (Second Draft) Final date for receipt of TC Second Draft ballot recirc 7/14/2014 4/4/2014 Posting of Second Draft for CC Mtg 4/11/2014 Final date for CC Second Draft Meeting 5/23/2014 Posting of Second Draft for CC Ballot 6/13/2014 Final date for Receipt of CC Second Draft ballot 7/7/2014 Final date for Receipt of CC Second Draft ballot recirc 7/14/2014 Post Final Second Draft for NITMAM Review 7/18/2014 7/18/2014 Tech Session Preparation (& Issuance) Notice of Intent to Make a Motion (NITMAM) Closing Date 8/22/2014 8/22/2014 Posting of Certified Amending Motions and Consent Documents 10/17/ /17/2014 Appeal Closing Date for Consent Documents (15 Days) 11/1/ /1/2014 SC Issuance Date for Consent Documents (25 Days) 11/11/ /11/2014 Tech Session Association Meeting for Documents with CAMs 6/22 25/2015 6/22 25/2015 Appeals and Issuance Appeal Closing Date for Documents with CAMs (20 Days) 7/15/2015 7/15/2015 SC Issuance Dates for Documents with CAMs 8/27/2015 8/27/2015 Page 5 of 29
6 Attachment B: Public Comments Page 6 of 29
7 of /18/ :57 AM Public Comment No. 40-NFPA [ Section No ] * Excess Air. Air supplied for combus on in excess of the stoichiometric mixture of air and theore cal amount of air required for complete combus on of a given quan ty of a speci c fuel. Dictionary defines stoichiometry as "the quantitative relationship between two or more substances especially in processes involving physical or chemical change." Combining old definition of theoretical air gives a more understandable definition. Submitter Full Name: Allan Zadiraka Organization: AJ Zadiraka LLC Submittal Date: Mon Nov 11 14:18:56 EST 2013 I, Allan Zadiraka, hereby irrevocably grant and assign to the National Fire Protection Association (NFPA) all and full rights in copyright in this Public Comment (including both the Proposed Change and the Statement of Problem and Substantiation). I understand and intend that I acquire no rights, including rights as a joint author, in any publication of the NFPA in which this Public Comment in this or another similar or derivative form is used. I hereby warrant that I am the author of this Public Comment and that I have full power and authority to enter into By checking this box I affirm that I am Allan Zadiraka, and I agree to be legally bound by the above and the terms and conditions contained therein. I understand and intend that, by checking this box, I am creating an electronic signature that will, upon my submission of this form, have the same legal force and effect as a handwritten signature Page 7 of 29
8 of /18/ :57 AM Public Comment No. 21-NFPA [ Section No ] Alarm. An audible or visible signal indicating an off-standard or abnormal condition A warning of danger. I am a member of the Glossary of Terms Task Group (GOT). The proposed definition is used by many standards. The original definition can be used for non alarm conditons also. Alarm is a higher level of alert. Submitter Full Name: Jack McNamara Organization: Bosch Security Systems Affilliation: GOT Submittal Date: Sun Oct 27 12:22:21 EDT 2013 I, Jack McNamara, hereby irrevocably grant and assign to the National Fire Protection Association (NFPA) all and full rights in copyright in this Public Comment (including both the Proposed Change and the Statement of Problem and Substantiation). I understand and intend that I acquire no rights, including rights as a joint author, in any publication of the NFPA in which this Public Comment in this or another similar or derivative form is used. I hereby warrant that I am the author of this Public Comment and that I have full power and authority to enter into By checking this box I affirm that I am Jack McNamara, and I agree to be legally bound by the above and the terms and conditions contained therein. I understand and intend that, by checking this box, I am creating an electronic signature that will, upon my submission of this form, have the same legal force and effect as a handwritten signature Page 8 of 29
9 of /18/ :57 AM Public Comment No. 22-NFPA [ Section No ] Annunciator. A device indicating an off-standard or abnormal condition by both visual and audible signals unit containing one or more indicator lamps, alphanumeric displays, computer monitor, or other equivalent means on which each indication provides status information about a circuit, condition, system, or location. I am a member of the Glossary of Terms Task Group (GOT). The proposed definition is used by many other standards. The new definiton better describes the term. Submitter Full Name: Jack McNamara Organization: Bosch Security Systems Submittal Date: Sun Oct 27 12:25:50 EDT 2013 I, Jack McNamara, hereby irrevocably grant and assign to the National Fire Protection Association (NFPA) all and full rights in copyright in this Public Comment (including both the Proposed Change and the Statement of Problem and Substantiation). I understand and intend that I acquire no rights, including rights as a joint author, in any publication of the NFPA in which this Public Comment in this or another similar or derivative form is used. I hereby warrant that I am the author of this Public Comment and that I have full power and authority to enter into By checking this box I affirm that I am Jack McNamara, and I agree to be legally bound by the above and the terms and conditions contained therein. I understand and intend that, by checking this box, I am creating an electronic signature that will, upon my submission of this form, have the same legal force and effect as a handwritten signature Page 9 of 29
10 of /18/ :57 AM Public Comment No. 10-NFPA [ Section No ] Automatic Burner Management System Recycling. A burner management system by which a furnace is purged and a burner is started, ignited, and stopped automatically and recycles on a preset pressure range Manual Burner Management System. A burner management system by which a furnace is purged and a burner is started, ignited, and stopped manually. In the first draft of Chapter 5 the Single Burner Boiler Technical Committee now uses this term and has requested that the definition be re-instated in Chapter 3. Submitter Full Name: Dale Evely Organization: Southern Company Services, Inc Submittal Date: Fri Sep 20 09:03:23 EDT 2013 I, Dale Evely, hereby irrevocably grant and assign to the National Fire Protection Association (NFPA) all and full rights in copyright in this Public Comment (including both the Proposed Change and the Statement of Problem and Substantiation). I understand and intend that I acquire no rights, including rights as a joint author, in any publication of the NFPA in which this Public Comment in this or another similar or derivative form is used. I hereby warrant that I am the author of this Public Comment and that I have full power and authority to enter into By checking this box I affirm that I am Dale Evely, and I agree to be legally bound by the above and the terms and conditions contained therein. I understand and intend that, by checking this box, I am creating an electronic signature that will, upon my submission of this form, have the same legal force and effect as a handwritten signature Page 10 of 29
11 11/20/13 TerraView Public Comment No. 85-NFPA [ Section No ] Bypass Stack. A stack applied in addition to and separate from the normal HRSG exhaust stack that allows combustion turbine exhaust gas to flow independently to the atmosphere. ***See First Revision No. 64 for deleted text of *** CC NOTE: The following CC Notes No. 5 appeared in the First Draft Report as First Revision No. 64. The Fundamentals Committee should restore the definition for Manual, Supervised Burner Management system based on the usage of the term in chapter 5. Related Item First Revision No. 64-NFPA [Sections , ] Submitter Full Name:CC on BCS-AAC Organization: CC on Boiler Combustion Hazards Submittal Date: Tue Nov 19 14:49:58 EST 2013 I, CC on BCS-AAC, hereby irrevocably grant and assign to the National Fire Protection Association (NFPA) all and full rights in copyright in this Public Comment (including both the Proposed Change and the Statement of Problem and Substantiation). I understand and intend that I acquire no rights, including rights as a joint author, in any publication of the NFPA in w hich this Public Comment in this or another similar or derivative form is used. I hereby w arrant that I am the author of this Public Comment and that I have full pow er and authority to enter into By checking this box I affirm that I am CC on BCS-AAC, and I agree to be legally bound by the above Copyright Assignment and the terms and conditions contained therein. I understand and intend that, by checking this box, I am creating an electronic signature that w ill, upon my submission of this form, have the same legal force and effect as a handw ritten signature Page 11 of 29 submittals.nfpa.org/terraviewweb/viewerpage.jsp 1/1
12 of /18/ :57 AM Public Comment No. 41-NFPA [ Section No ] Direct-Fired System. A system in which the fuel is pulverized and delivered in suspension directly to the burner(s). " Direct- Fired" should use either a "-" or a space, not both. Submitter Full Name: Allan Zadiraka Organization: AJ Zadiraka LLC Submittal Date: Mon Nov 11 14:25:06 EST 2013 I, Allan Zadiraka, hereby irrevocably grant and assign to the National Fire Protection Association (NFPA) all and full rights in copyright in this Public Comment (including both the Proposed Change and the Statement of Problem and Substantiation). I understand and intend that I acquire no rights, including rights as a joint author, in any publication of the NFPA in which this Public Comment in this or another similar or derivative form is used. I hereby warrant that I am the author of this Public Comment and that I have full power and authority to enter into By checking this box I affirm that I am Allan Zadiraka, and I agree to be legally bound by the above and the terms and conditions contained therein. I understand and intend that, by checking this box, I am creating an electronic signature that will, upon my submission of this form, have the same legal force and effect as a handwritten signature Page 12 of 29
13 of /18/ :57 AM Public Comment No. 20-NFPA [ Section No ] Induced Draft (ID) Fan. A fan downstream of the combustion process used to remove the products of combustion from the boiler, HRSG, or flue gas ductwork. The text was missing a space between ",HRSG". Submitter Full Name: Steven Graf Organization: Emerson Process Management Submittal Date: Fri Oct 25 10:24:46 EDT 2013 I, Steven Graf, hereby irrevocably grant and assign to the National Fire Protection Association (NFPA) all and full rights in copyright in this Public Comment (including both the Proposed Change and the Statement of Problem and Substantiation). I understand and intend that I acquire no rights, including rights as a joint author, in any publication of the NFPA in which this Public Comment in this or another similar or derivative form is used. I hereby warrant that I am the author of this Public Comment and that I have full power and authority to enter into By checking this box I affirm that I am Steven Graf, and I agree to be legally bound by the above and the terms and conditions contained therein. I understand and intend that, by checking this box, I am creating an electronic signature that will, upon my submission of this form, have the same legal force and effect as a handwritten signature Page 13 of 29
14 of /18/ :57 AM Public Comment No. 23-NFPA [ Section No [Excluding any Sub-Sections] ] A device that senses the presence or absence of flame and provides a usable signal radiant energy sensing fire detector that detects the radiant energy emitted by a flame. I am a member of the Glossary of Terms Task Group (GOT). The proposed definition is used by many standards including NFPA 1 and NFPA 72. Commonality in definitions across standards makes all code clearer. Submitter Full Name: Jack McNamara Organization: Bosch Security Systems Affilliation: GOT Submittal Date: Sun Oct 27 12:29:04 EDT 2013 I, Jack McNamara, hereby irrevocably grant and assign to the National Fire Protection Association (NFPA) all and full rights in copyright in this Public Comment (including both the Proposed Change and the Statement of Problem and Substantiation). I understand and intend that I acquire no rights, including rights as a joint author, in any publication of the NFPA in which this Public Comment in this or another similar or derivative form is used. I hereby warrant that I am the author of this Public Comment and that I have full power and authority to enter into By checking this box I affirm that I am Jack McNamara, and I agree to be legally bound by the above and the terms and conditions contained therein. I understand and intend that, by checking this box, I am creating an electronic signature that will, upon my submission of this form, have the same legal force and effect as a handwritten signature Page 14 of 29
15 of /18/ :57 AM Public Comment No. 49-NFPA [ Section No ] Hardwired. The method of interconnecting signals or interlocks to a logic system or between logic systems using a dedicated interconnection for each individual continuous rather than sampled signal. When the term hardwired is applied to the logic system itself, it refers to the method of using individual devices and interconnecting wiring to program and perform the logic functions without the use of software-based logic solvers. To clarify the definition by adding digital signal processing terminology. Submitter Full Name: Allan Zadiraka Organization: [ Not Specified ] Submittal Date: Mon Nov 11 16:10:36 EST 2013 I, Allan Zadiraka, hereby irrevocably grant and assign to the National Fire Protection Association (NFPA) all and full rights in copyright in this Public Comment (including both the Proposed Change and the Statement of Problem and Substantiation). I understand and intend that I acquire no rights, including rights as a joint author, in any publication of the NFPA in which this Public Comment in this or another similar or derivative form is used. I hereby warrant that I am the author of this Public Comment and that I have full power and authority to enter into By checking this box I affirm that I am Allan Zadiraka, and I agree to be legally bound by the above and the terms and conditions contained therein. I understand and intend that, by checking this box, I am creating an electronic signature that will, upon my submission of this form, have the same legal force and effect as a handwritten signature Page 15 of 29
16 0 of /18/ :57 AM Public Comment No. 24-NFPA [ Section No ] Inert Gas. Any gas that is nonflammable, chemically inactive, noncontaminating for the use intended, and oxygen deficient to the extent required A nonreactive, nonflammable, noncorrosive gas such as argon, helium, krypton, neon, nitrogen, and xenon. I am a member of the Glossary of Terms Task Group (GOT). The proposed definition is used by many standards. Common definitions are the goal of the GOT. Submitter Full Name: Jack McNamara Organization: Bosch Security Systems Affilliation: GOT Submittal Date: Sun Oct 27 12:32:50 EDT 2013 I, Jack McNamara, hereby irrevocably grant and assign to the National Fire Protection Association (NFPA) all and full rights in copyright in this Public Comment (including both the Proposed Change and the Statement of Problem and Substantiation). I understand and intend that I acquire no rights, including rights as a joint author, in any publication of the NFPA in which this Public Comment in this or another similar or derivative form is used. I hereby warrant that I am the author of this Public Comment and that I have full power and authority to enter into By checking this box I affirm that I am Jack McNamara, and I agree to be legally bound by the above and the terms and conditions contained therein. I understand and intend that, by checking this box, I am creating an electronic signature that will, upon my submission of this form, have the same legal force and effect as a handwritten signature Page 16 of 29
17 Public Comment No. 43-NFPA [ Sections , , , , ,... ] Sections , , , , , , , , , , , Normal Shutdown, High Steam Pressure Interlock. A pressure-actuated device that is arranged to effect a normal burner shutdown when the steam pressure exceeds a preset pressure Normal Shutdown, High Water Temperature Interlock. A temperature-actuated device that is arranged to effect a normal burner shutdown when the water temperature exceeds a preset temperature Process Monitoring, High Oil Temperature Interlock. A temperature-actuated device that initiates a signal when oil temperature rises above the limits that are required to maintain the viscosity range recommended by the burner manufacturer Process Monitoring, Low Oil Temperature Interlock. A temperature-actuated device that initiates a signal when the oil temperature falls below the limits that are required to maintain the viscosity range recommended by the burner manufacturer Proof of Closure Interlock. A device that provides feedback that a piece of equipment is in the closed position Safety Shutdown, Excessive Steam Pressure Interlock. A pressure-actuated device that is arranged to effect a safety shutdown of the burner when the steam pressure exceeds a preset pressure Safety Shutdown, Excessive Water Temperature Interlock. A temperature-actuated device that is arranged to effect a safety shutdown of the burner when the water temperature exceeds a preset temperature Safety Shutdown, High Gas Pressure Interlock. A pressure-actuated device that is arranged to effect a safety shutdown or to prevent starting when the gas pressure exceeds the preset value Safety Shutdown, Low Gas Pressure Interlock. A pressure-actuated device that is arranged to effect a safety shutdown or to prevent starting when the gas pressure falls below the preset value Safety Shutdown, Low Oil Pressure Interlock. A pressure-actuated device that is arranged to effect a safety shutdown or to prevent starting when the oil pressure falls below the preset value Safety Shutdown, Low Water Cutout Auxiliary Interlock. On single burner boilers, a device that is arranged to effect a safety shutdown of the burner when the water level in the boiler falls to a predetermined low level Safety Shutdown, Low Water Cutout Interlock. A device that is arranged to effect a safety shutdown or master fuel trip when the water level in the boiler or HRSG falls to a predetermined low level. New items through are a list of interlocks required by SBB in Chapter 5, not definitions. The same applies to original items through Submitter Full Name: Allan Zadiraka Organization: AJ Zadiraka LLC Page 17 of 29 3 of /18/ :57 AM
18 11/20/13 TerraView Public Comment No. 69-NFPA [ Section No ] Interlock. A device, or an arrangement of devices, in which the operation of one part or one mechanism of the device or arrangement controls the operation of another part of another mechanism Normal Shutdown, High Steam Pressure Interlock. A pressure-actuated device that is arranged to effect a normal burner shutdown when the steam pressure exceeds a preset pressure Normal Shutdown, High Water Temperature Interlock. A temperature-actuated device that is arranged to effect a normal burner shutdown when the water temperature exceeds a preset temperature Process Monitoring, High Oil Temperature Interlock. A temperature-actuated device that initiates a signal when oil temperature rises above the limits that are required to maintain the viscosity range recommended by the burner manufacturer Process Monitoring, Low Oil Temperature Interlock. A temperature-actuated device that initiates a signal when the oil temperature falls below the limits that are required to maintain the viscosity range recommended by the burner manufacturer Proof of Closure Interlock. A device that provides feedback that a piece of equipment is in the closed position Safety Shutdown, Excessive Steam Pressure Interlock. A pressure-actuated device that is arranged to effect a safety shutdown of the burner when the steam pressure exceeds a preset pressure Safety Shutdown, Excessive Water Temperature Interlock. A temperature-actuated device that is arranged to effect a safety shutdown of the burner when the water temperature exceeds a preset temperature Safety Shutdown, High Gas Pressure Interlock. A pressure-actuated device that is arranged to effect a safety shutdown or to prevent starting when the gas pressure exceeds the preset value Safety Shutdown, Low Gas Pressure Interlock. A pressure-actuated device that is arranged to effect a safety shutdown or to prevent starting when the gas pressure falls below the preset value Safety Shutdown, Low Oil Pressure Interlock. A pressure-actuated device that is arranged to effect a safety shutdown or to prevent starting when the oil pressure falls below the preset value Safety Shutdown, Low Water Cutout Auxiliary Interlock. On single burner boilers, a device that is arranged to effect a safety shutdown of the burner when the water level in the boiler falls to a predetermined low level Safety Shutdown, Low Water Cutout Interlock. A device that is arranged to effect a safety shutdown or master fuel trip when the water level in the boiler or HRSG falls to a predetermined low level. CC NOTE: The following CC Note No. 4 appeared in the First Draft Report as First Revision No Page 18 of 29 submittals.nfpa.org/terraviewweb/viewerpage.jsp 1/2
19 11/20/13 TerraView The Fundamentals committee should consider deleting through as suggested by Mr. Zadiraka in his ballot comment. The Single Burner Boilers committee should review any actions taken by Fundamentals and determine if any action is required in chapter 5 to retain these definitions. Related Item First Revision No. 147-NFPA [Sections , , , , ] Submitter Full Name:CC on BCS-AAC Organization: CC on Boiler Combustion System Hazards Submittal Date: Wed Nov 13 13:34:25 EST 2013 I, CC on BCS-AAC, hereby irrevocably grant and assign to the National Fire Protection Association (NFPA) all and full rights in copyright in this Public Comment (including both the Proposed Change and the Statement of Problem and Substantiation). I understand and intend that I acquire no rights, including rights as a joint author, in any publication of the NFPA in w hich this Public Comment in this or another similar or derivative form is used. I hereby w arrant that I am the author of this Public Comment and that I have full pow er and authority to enter into By checking this box I affirm that I am CC on BCS-AAC, and I agree to be legally bound by the above Copyright Assignment and the terms and conditions contained therein. I understand and intend that, by checking this box, I am creating an electronic signature that w ill, upon my submission of this form, have the same legal force and effect as a handw ritten signature Page 19 of 29 submittals.nfpa.org/terraviewweb/viewerpage.jsp 2/2
20 5 of /18/ :57 AM Public Comment No. 11-NFPA [ Section No ] Test Block Capability. The point on the fan head versus flow characteristic curve at which the fan is selected. This is the calculated operating point associated with the maximum continuous rating of the boiler or HRSG, plus the head and flow margins A fan s highest volumetric flow and static pressure rise capabilities for that fan s system resistance and inlet gas density. The current definition of Test Block Capability for fans does not provide a specific enough definition for the average user. This proposed new definition is meant to provide clarity to the users of the Code. Submitter Full Name: Dale Evely Organization: Southern Company Services, Inc Submittal Date: Mon Sep 30 14:27:36 EDT 2013 I, Dale Evely, hereby irrevocably grant and assign to the National Fire Protection Association (NFPA) all and full rights in copyright in this Public Comment (including both the Proposed Change and the Statement of Problem and Substantiation). I understand and intend that I acquire no rights, including rights as a joint author, in any publication of the NFPA in which this Public Comment in this or another similar or derivative form is used. I hereby warrant that I am the author of this Public Comment and that I have full power and authority to enter into By checking this box I affirm that I am Dale Evely, and I agree to be legally bound by the above and the terms and conditions contained therein. I understand and intend that, by checking this box, I am creating an electronic signature that will, upon my submission of this form, have the same legal force and effect as a handwritten signature Page 20 of 29
21 6 of /18/ :57 AM Public Comment No. 57-NFPA [ Section No ] Test Block Capability. The point on the fan head versus flow characteristic curve at which the fan is selected. This is the calculated operating point associated with the maximum continuous rating of the boiler or HRSG, plus the head and flow margins. CC NOTE: The following CC Note No. 6 appeared in the First Draft Report as First Revision No. 77. The Fundamentals committee should reconsider the definition for Test Block Capability. The first sentence should be reviewed in the context of chapters 6 and 7, specifically casing design pressures (positive and negative transient design pressures). The second sentence appears to restrict the definition to boilers and HRSGs, therefore excluding the pulverizer supply air fan. In addition, the second sentence could be interpreted as a requirement. Related Item First Revision No. 77-NFPA [Section No ] Submitter Full Name: CC on BCS-AAC Organization: CC on Boiler Combustion System Hazards Submittal Date: Wed Nov 13 13:06:26 EST 2013 I, CC on BCS-AAC, hereby irrevocably grant and assign to the National Fire Protection Association (NFPA) all and full rights in copyright in this Public Comment (including both the Proposed Change and the Statement of Problem and Substantiation). I understand and intend that I acquire no rights, including rights as a joint author, in any publication of the NFPA in which this Public Comment in this or another similar or derivative form is used. I hereby warrant that I am the author of this Public Comment and that I have full power and authority to enter into By checking this box I affirm that I am CC on BCS-AAC, and I agree to be legally bound by the above and the terms and conditions contained therein. I understand and intend that, by checking this box, I am creating an electronic signature that will, upon my submission of this form, have the same legal force and effect as a handwritten signature Page 21 of 29
22 7 of /18/ :57 AM Public Comment No. 82-NFPA [ New Section after ] TITLE OF NEW CONTENT: Single burner boilers listed and approved for unattended operation shall not require a process hazard analysis. Single burner boilers desinged and listed for unattended operation have been proven by operating history to have sufficient controls and safety interlocks to prevent unsafe operation that result in fires or explosions. When such boilers are acceptable to the authority having jurisdiction, a PHA should not have too be performed before such a boiler is installed abd operated. The submitter would have ideally liked to have added this paragraph in Chapter 5 for single burner boiles, but could not find an acceptable spot within that chapter and therefore elected to place it after the paragraph in Chapter 4 that requires a PHA for unattended boilers. Submitter Full Name: Michael Polagye Organization: FM Global Submittal Date: Fri Nov 15 16:09:20 EST 2013 I, Michael Polagye, hereby irrevocably grant and assign to the National Fire Protection Association (NFPA) all and full rights in copyright in this Public Comment (including both the Proposed Change and the Statement of Problem and Substantiation). I understand and intend that I acquire no rights, including rights as a joint author, in any publication of the NFPA in which this Public Comment in this or another similar or derivative form is used. I hereby warrant that I am the author of this Public Comment and that I have full power and authority to enter into By checking this box I affirm that I am Michael Polagye, and I agree to be legally bound by the above and the terms and conditions contained therein. I understand and intend that, by checking this box, I am creating an electronic signature that will, upon my submission of this form, have the same legal force and effect as a handwritten signature Page 22 of 29
23 8 of /18/ :57 AM Public Comment No. 58-NFPA [ Section No ] 4.1.4* Unattended and Off-Site Operation. Unattended operation, no operator at the operating location(s), or operation of the plant from an off-site operating location shall be approved and shall require a process hazard analysis (PHA). CC NOTE: The following CC Note No. 7 appeared in the First Draft Report as First Revision No. 85 and 86 and also related Public Input No. 136 and 76. The Fundamentals committee should reconsider moving this requirement from chapter 6 to chapter 4 because of the broad implications. For example, a common application of single burner boilers is unattended operation. Members of the subject committees for chapters 5 through 10 should specifically review this item to provide public comments to the Fundamentals or subject chapter as appropriate. Related Item First Revision No. 85-NFPA [New Section after 4.1.4] First Revision No. 86-NFPA [Section No ] Public Input No. 136-NFPA [Section No ] Public Input No. 76-NFPA [Section No ] Submitter Full Name: CC on BCS-AAC Organization: CC on Boiler Combustion System Hazards Submittal Date: Wed Nov 13 13:09:08 EST 2013 I, CC on BCS-AAC, hereby irrevocably grant and assign to the National Fire Protection Association (NFPA) all and full rights in copyright in this Public Comment (including both the Proposed Change and the Statement of Problem and Substantiation). I understand and intend that I acquire no rights, including rights as a joint author, in any publication of the NFPA in which this Public Comment in this or another similar or derivative form is used. I hereby warrant that I am the author of this Public Comment and that I have full power and authority to enter into By checking this box I affirm that I am CC on BCS-AAC, and I agree to be legally bound by the above and the terms and conditions contained therein. I understand and intend that, by checking this box, I am creating an electronic signature that will, upon my submission of this form, have the same legal force and effect as a handwritten signature Page 23 of 29
24 9 of /18/ :57 AM Public Comment No. 44-NFPA [ Section No ] The design shall not require any deliberate manual defeating of an interlock to start or operate equipment. Logic systems automatically bypass interlocks during startup and shutdown. Suggest adding "manual" to clarify meaning of the requirements and match & The design shall not require Submitter Full Name: Allan Zadiraka Organization: [ Not Specified ] Submittal Date: Mon Nov 11 14:35:17 EST 2013 I, Allan Zadiraka, hereby irrevocably grant and assign to the National Fire Protection Association (NFPA) all and full rights in copyright in this Public Comment (including both the Proposed Change and the Statement of Problem and Substantiation). I understand and intend that I acquire no rights, including rights as a joint author, in any publication of the NFPA in which this Public Comment in this or another similar or derivative form is used. I hereby warrant that I am the author of this Public Comment and that I have full power and authority to enter into By checking this box I affirm that I am Allan Zadiraka, and I agree to be legally bound by the above and the terms and conditions contained therein. I understand and intend that, by checking this box, I am creating an electronic signature that will, upon my submission of this form, have the same legal force and effect as a handwritten signature Page 24 of 29
25 0 of /18/ :57 AM Public Comment No. 45-NFPA [ Section No ] Where multiple boilers or HRSGs are supplied from the same fuel supply source, there shall be a means of manual isolation for each individual boiler and HRSG fuel supply. The intend is to isolate the fuel supply to individual units which is not clear in original text. Submitter Full Name: Allan Zadiraka Organization: [ Not Specified ] Submittal Date: Mon Nov 11 14:38:36 EST 2013 I, Allan Zadiraka, hereby irrevocably grant and assign to the National Fire Protection Association (NFPA) all and full rights in copyright in this Public Comment (including both the Proposed Change and the Statement of Problem and Substantiation). I understand and intend that I acquire no rights, including rights as a joint author, in any publication of the NFPA in which this Public Comment in this or another similar or derivative form is used. I hereby warrant that I am the author of this Public Comment and that I have full power and authority to enter into By checking this box I affirm that I am Allan Zadiraka, and I agree to be legally bound by the above and the terms and conditions contained therein. I understand and intend that, by checking this box, I am creating an electronic signature that will, upon my submission of this form, have the same legal force and effect as a handwritten signature Page 25 of 29
26 11/19/13 TerraView Public Comment No. 84-NFPA [ Section No ] Revise wording on table that if the fuel line size is ½ the vent line size is also ½ Vent line sizes and vent valve port diameters shall not be less than the values shown in Table Table Vent Sizes Fuel Line Size DN (mm) NPS (in.) DN (mm) Minimum Vent Line Size NPS (in.) to to to to >200 >8 Vent internal cross-sectional area 15% of the fuel line internal crosssectional area I would like the NFPA 85 committee to consider a code change on table that if the fuel line size is ½ that the vent line size be ½. Having a vent line size larger than the fuel line size is not consistent with the other vent sizing requirements listed in the table. Submitter Full Name:Melissa Wadkinson Organization: Fulton Thermal Corporation Submittal Date: Mon Nov 18 12:36:00 EST 2013 I, Melissa Wadkinson, hereby irrevocably grant and assign to the National Fire Protection Association (NFPA) all and full rights in copyright in this Public Comment (including both the Proposed Change and the Statement of Problem and Page 26 of 29 submittals.nfpa.org/terraviewweb/viewerpage.jsp 1/2
27 1 of /18/ :57 AM Public Comment No. 73-NFPA [ Section No ] * The requirements in Section shall apply to flue gas path auxiliary systems that inject fuel, oxidizer, or combustible reagent into the boiler enclosure or flue gas path when in operation. A Flue gas path auxiliary systems shall be that inject fuel, oxidizer, or combustible reagent into a boiler enclosure or flue gas path can include but are not limited to sulfur burner systems, ammonia injection systems, activated carbon injection systems, soot blowing or soot cleaning systems, and fired reheater systems. Having a requirement that defines, and limits, what a flue gas path auxiliary system is doesn't make sense. And in the case of soot blowing system, many/most don't use fuel, oxidizer, or combustible reagent and these requirements don't apply. The existing wording could create confusion as to whether or not that is the case. Also, if there are or will be other systems that should meet the requirements of this section that are not in the "list", that could be construed as the requirements not applying to them. The proposed revised wording and Annex material addresses these concerns. Submitter Full Name: Michael Polagye Organization: FM Global Submittal Date: Thu Nov 14 16:55:29 EST 2013 I, Michael Polagye, hereby irrevocably grant and assign to the National Fire Protection Association (NFPA) all and full rights in copyright in this Public Comment (including both the Proposed Change and the Statement of Problem and Substantiation). I understand and intend that I acquire no rights, including rights as a joint author, in any publication of the NFPA in which this Public Comment in this or another similar or derivative form is used. I hereby warrant that I am the author of this Public Comment and that I have full power and authority to enter into By checking this box I affirm that I am Michael Polagye, and I agree to be legally bound by the above and the terms and conditions contained therein. I understand and intend that, by checking this box, I am creating an electronic signature that will, upon my submission of this form, have the same legal force and effect as a handwritten signature Page 27 of 29
28 2 of /18/ :57 AM Public Comment No. 8-NFPA [ Section No ] The basic requirement of an interlock system for a unit boiler or combustion system shall accomplish the following: (1) Protect personnel from injury (2) Protect equipment from damage (3) Protect boiler operation by limiting actions to a prescribed operating sequence or by initiating trip devices when approaching an out-of-range or unstable operating condition The term "unit" has a definition that would inappropriately limit the application of this requirement. The term "boiler or HRSG" would not include pulverized fuel systems. The term "boiler or combustion system" should define the intended scope more appropriately. The term "boiler" was removed from the last line for the same reason. Submitter Full Name: Dale Evely Organization: Southern Company Services, Inc Submittal Date: Thu Sep 19 13:30:15 EDT 2013 I, Dale Evely, hereby irrevocably grant and assign to the National Fire Protection Association (NFPA) all and full rights in copyright in this Public Comment (including both the Proposed Change and the Statement of Problem and Substantiation). I understand and intend that I acquire no rights, including rights as a joint author, in any publication of the NFPA in which this Public Comment in this or another similar or derivative form is used. I hereby warrant that I am the author of this Public Comment and that I have full power and authority to enter into By checking this box I affirm that I am Dale Evely, and I agree to be legally bound by the above and the terms and conditions contained therein. I understand and intend that, by checking this box, I am creating an electronic signature that will, upon my submission of this form, have the same legal force and effect as a handwritten signature Page 28 of 29
29 3 of /18/ :57 AM Public Comment No. 18-NFPA [ Section No ] The response time from flame failure to the de-energization initiation of the close signal to the fuel safety shutoff devices shall not exceed 4 seconds, including any time delay associated with the flame detector. The text was revised to address that not all fuel shutoff devices are de-energized to close. For example Coal Line Shutoff Valves are typically energize to open and energize to close. On new installations, some Boiler OEMs are providing dual coil solenoid and motor operated valves for Gas and Oil igniters. Submitter Full Name: Steven Graf Organization: Emerson Process Management Submittal Date: Fri Oct 25 09:13:35 EDT 2013 I, Steven Graf, hereby irrevocably grant and assign to the National Fire Protection Association (NFPA) all and full rights in copyright in this Public Comment (including both the Proposed Change and the Statement of Problem and Substantiation). I understand and intend that I acquire no rights, including rights as a joint author, in any publication of the NFPA in which this Public Comment in this or another similar or derivative form is used. I hereby warrant that I am the author of this Public Comment and that I have full power and authority to enter into By checking this box I affirm that I am Steven Graf, and I agree to be legally bound by the above and the terms and conditions contained therein. I understand and intend that, by checking this box, I am creating an electronic signature that will, upon my submission of this form, have the same legal force and effect as a handwritten signature Page 29 of 29
Technical Committee on Fluidized Bed Boilers
Technical on Fluidized Bed Boilers AGENDA Web/Teleconference 1. Chair s welcome, call to order, and opening remarks at 1:00 pm EST. 2. Self-Introduction of Members and Guests 3. Approval of Minutes from
More informationTechnical Committee on Multiple Burner Boilers
Technical Committee on Multiple Burner Boilers AGENDA Salt River Project PERA Club 1 Continential Drive Tempe, AZ January 14-15, 2014 1. Chair s welcome, call to order, and opening remarks at 8:00 a.m.
More informationTechnical Committee on Fluidized Bed Boilers
Technical Committee on Fluidized Bed Boilers AGENDA NFPA Headquarters 1 Batterymarch Park Quincy, MA 02169 1. Chair s welcome, call to order, and opening remarks at 1:00 pm EST. 2. Self-Introduction of
More informationCommittee on NFPA 85
Committee on NFPA 85 M E M O R A N D U M TO: FROM: NFPA Technical Committee on Single Burner Boilers Patti Mucci, Technical Assistant II DATE: August 5, 2009 SUBJECT: NFPA ROP Letter Ballot The ROP letter
More informationAgenda Technical Committee on Initiating Devices for Fire Alarm and Signaling Systems June 24-25, 2013 Saint Louis, MO
Agenda Technical Committee on Initiating Devices for Fire Alarm and Signaling Systems June 24-25, 2013 Saint Louis, MO Item No. Subject 13-6-1 Call to Order (8:00 A.M) 13-6-2 Roll Call 13-6-3 Approval
More informationTECHNICAL COMMITTEE ON MANUFACTURE OF ORGANIC COATINGS First Draft Meeting Agenda March 19, :00 AM - 5:00 PM EST Web/Teleconference Meeting
TECHNICAL COMMITTEE ON MANUFACTURE OF ORGANIC COATINGS First Draft Meeting Agenda March 19, 2014 9:00 AM - 5:00 PM EST Web/Teleconference Meeting 1. Welcome. George Seuss, Chair 2. Introductions and Update
More informationPage 1 of 190 Public Input No. 22-NFPA 55-2013 [ Global Input ] Throughout the document, delete ANSI from ANSI/ASME B31.3. Current Text: (multiple locations) ANSI/ASME B31.3 (found in Subsections: 2.3.2
More informationMINUTES OF MEETING. Technical Committee on Fundamentals of Combustion Systems Hazards
MINUTES OF MEETING Technical Committee on Fundamentals of Combustion Systems Hazards January 29-30, 2013 GE Corporate Headquarters Houston, TX I. Attendance: Principal Members/Staff: Dale Evely, Technical
More informationCommittee on NFPA 85
Committee on NFPA 85 M E M O R A N D U M TO: FROM: NFPA Technical Committee on Fundamentals of Combustion Systems Hazards Jeanne Moreau DATE: April 23, 2010 SUBJECT: NFPA 85 F10 ROC Letter Ballot The ROC
More informationResolution: FR-2-NFPA Statement: The new language requires the action completed by NFPA 557 be prepared by a person that is approved.
Public Input No. 1-NFPA 557-2012 [ New Section after 1.5.3 ] 1.6 Approved Qualifications The design shall be prepared by a person with qualifications acceptable to the AHJ. The term designer is used in
More informationPage 1 of 37 Public Input No. 1-NFPA 30A-2012 [ New Section after 1.1.2 ] 1.1.3 This code shall not apply to aircraft fuel dispensing facilities. NFPA 30A is commonly referenced, in my opinion, incorrectly,
More informationNFPA 101 SAF-RES PUBLIC COMMENTS
Page 134 of 195 Public Comment No. 3-NFPA 101-2013 [ Section No. 28.7.6.1 ] 28.7.6.1 New draperies, curtains, and other similar loosely hanging furnishings and decorations shall be flame resistant as demonstrated
More informationM E M O R A N D U M. The Technical Correlating Committee on Boiler and Combustion Systems Hazards
M E M O R A N D U M TO: FROM: The Technical Correlating Committee on Boiler and Combustion Systems Hazards Jeanne Moreau DATE: June 22, 2010 SUBJECT: NFPA 85 TCC Report on Comments Letter Ballot (F10)
More informationPage 1 of 198 Public Input No. 88-NFPA 20-2013 [ New Section after 3.3.38.10 ] Add New Defination 3.3.28.11 Multiple Stage Multiple Port Pump. A single driver pump with multiple impellers operating in
More informationPublic Comment No. 7-NFPA 30A-2013 [ Section No ]
Page 1 of 13 Public Comment No. 7-NFPA 30A-2013 [ Section No. 6.4.2 ] 6.4.2 Additional Proposed Changes Each pump shall have installed on the discharge side a listed leak detection device that will provide
More informationNFPA 79 - Second Draft Meeting July 8-10, DoubleTree Hotel, Portland, ME
National Fire Protection Association 1 Batterymarch Park, Quincy, MA 02169-7471 Phone: 617-770-3000 Fax: 617-770-0700 www.nfpa.org AGENDA NFPA TECHNICAL COMMITTEE ON ELECTRICAL EQUIPMENT OF INDUSTRIAL
More informationPublic Input No. 1-NFPA [ Global Input ] Additional Proposed Changes. Statement of Problem and Substantiation for Public Input
of 280 2/6/2015 12:06 PM Public Input No. 1-NFPA 58-2013 [ Global Input ] NOTE: This public input originates from Tentative Interim Amendment 58-14-1 (TIA 1079) issued by the Standards Council on August
More informationTECHNICAL COMMITTEE ON SAFETY AT MOTORSPORTS VENUES. NFPA 610 First Draft Meeting. October 17-18, 2016
TECHNICAL COMMITTEE ON SAFETY AT MOTORSPORTS VENUES NFPA 610 First Draft Meeting October 17-18, 2016 Westin Kansas City at Crown Center 1 East Pershing Road Kansas City, MO, 64108 Conference Call Access:
More informationPublic Comment No. 2-NFPA [ Section No ]
Public Comment No. 2-NFPA 16-2013 [ Section No. 3.3.6 ] 3.3.6* Foam-Water Sprinkler System. A piping network connected to a source of foam concentrate and to a water supply. The piping network is equipped
More informationFirst Revision No. 106-NFPA [ Chapter NFPA ] Submitter Information Verification. Committee Statement and Meeting Notes
First Revision No. 106-NFPA 86-2012 [ Chapter NFPA ] 7.4.10.2* The number of safety shutoff valve cycles shall be determined by one of the following ways: (1) Counting of actual safety shutoff valve open-closed
More informationThe Committee updated the edition dates for the reference sources for extracted text within the standard per the NFPA Manual of Style.
Second Revision No. 51-NFPA 86-2013 [ Section No. 2.4 ] 2.4 References for Extracts in Mandatory Sections. NFPA 54, National Fuel Gas Code, 2009 2015 edition. NFPA 69, Standard on Explosion Prevention
More informationPublic Input No. 88-NFPA [ New Section after ] Statement of Problem and Substantiation for Public Input
of 201 1/13/2014 12:51 PM Public Input No. 88-NFPA 20-2013 [ New Section after 3.3.38.10 ] Add New Defination 3.3.28.11 Multiple Stage Multiple Port Pump. A single driver pump with multiple impellers operating
More informationAGENDA First Draft Meeting for the 2016 Edition of NFPA 70B March 12-14, 2014 San Antonio, TX
National Fire Protection Association 1 Batterymarch Park, Quincy, MA 02169-7471 Phone: 617-770-3000 Fax: 617-770-0700 www.nfpa.org Technical Committee on Electrical Equipment Maintenance (EEM-AAA) AGENDA
More informationPublic Comment No. 2-NFPA [ Section No ]
Page 1 of 13 Public Comment No. 2-NFPA 703-2013 [ Section No. 2.3.1 ] 2.3.1 ASTM Publications. ASTM International, P.O. Box C700, 100 Barr Harbor Drive, West Conshohocken, PA 19428-2959. ASTM D 2898, Standard
More informationSecond Revision No. 104-NFPA [ Section No ] Submitter Information Verification. Committee Statement
of 1 9/22/2014 1:38 PM Second Revision No. 104-NFPA 72-2014 [ Section No. 3.3.3 ] 3.3.3 Accessible, Readily (Readily Accessible). Capable of being reached quickly for operation, renewal, or inspections
More informationReport on Proposals F2007 Copyright, NFPA NFPA 499 Report of the Committee on
Report on Proposals F2007 Copyright, NFPA NFPA 499 Report of the Committee on This list represents the membership at the time the Committee was balloted on the text of this edition. Since that time, changes
More informationPublic Input No. 16-NFPA [ Section No ] Additional Proposed Changes. Statement of Problem and Substantiation for Public Input
Public Input No. 16-NFPA 211-2014 [ Section No. 2.3.1 ] 2.3.1 ASHRAE Publications. ASHRAE, Inc., 1791 Tullie Circle, NE, Atlanta, GA 30329-2305. ASHRAE Handbook: HVAC Systems and Equipment, 2008 2012.
More informationPublic Comment No. 13-NFPA [ Section No ]
Public Comment No. 13-NFPA 30-2013 [ Section No. 2.3.3 ] 2.3.3 ASTM Publications. ASTM International, 100 Barr Harbor Drive, P.O. Box C700, West Conshohocken, PA 19428-2959. ASTM A 395/A395M, Standard
More informationSecond Revision No. 3 implements the text of Committee Input No. 36 as proposed in the First Draft Report, along with the following amendments:
Second Revision No. 3-NFPA 31-2015 [ Section No. 10.5.1 ] 10.5.1* Oil burners, other than oil stoves with integral tanks, shall be provided with some means for manually stopping the flow of oil to the
More informationMEMORANDUM. NFPA Technical Committee on Solvent Extraction Plants. NFPA 36 First Draft TC FINAL Ballot Results (F2016)
National Fire Protection Association 1 Batterymarch Park, Quincy, MA 02169-7471 Phone: 617-770-3000 Fax: 617-770-0700 www.nfpa.org MEMORANDUM To: From: NFPA Technical Committee on Solvent Extraction Plants
More informationTechnical Committee on Mining Facilities First Draft Meeting - NFPA 120 and 122
Technical Committee on Mining Facilities First Draft Meeting - NFPA 120 and 122 Zurich Hosted 1400 America Lane Schaumburg, Illinois May 22 23, 2013 AGENDA 1. Chair Matt Bujewski calls meeting to order
More informationM E M O R A N D U M. NFPA Technical Committee on Wood and Cellulosic Materials Processing
National Fire Protection Association 1 Batterymarch Park, Quincy, MA 02169-7471 Phone: 617-770-3000 Fax: 617-770-0700 www.nfpa.org M E M O R A N D U M TO: FROM: NFPA Technical Committee on Wood and Cellulosic
More informationFirst Revision No. 158-NFPA [ Global Input ] Submitter Information Verification. Committee Statement
of 326 11/21/2013 1:03 PM First Revision No. 158-NFPA 72-2013 [ Global Input ] Revise 2.3.1 to update UL 864 to "2003, revised 2012" and upate ANSI/ASME A17 to 2013. Submittal Date: Wed Sep 11 11:08:52
More informationDIRECTIVE NO: D-B
DIRECTIVE NO: D-B6 100604 1 LOW PRESSURE THERMAL FLUID PLANT AUTOMATED CONTROL SYSTEMS Date of Issue: June 4, 2010 General Details This directive is being issued to owners, licensed contractors, consulting
More informationSecond Revision No. 1-NFPA 17A-2016 [ Section No ] Submitter Information Verification. Committee Statement. 1 of 14 6/22/2016 3:15 PM
1 of 14 6/22/2016 3:15 PM Second Revision No. 1-NFPA 17A-2016 [ Section No. 4.3.3 ] 4.3.3 All discharge nozzles shall be provided with caps or other suitable devices to prevent the entrance of grease vapors,
More informationFirst Revision No. 49-NFPA 17A-2015 [ Detail ] Submitter Information Verification. Committee Statement 7/30/2015 1:35 PM
of 25 7/30/2015 1:35 PM First Revision No. 49-NFPA 17A-2015 [ Detail ] Make the following change to 5.2.1.10.2: 5.2.1.10.2* The manual actuation device shall clearly identify the hazard protected and provide
More informationTechnical Committee on Incinerators and Waste Handling Systems
Technical Committee on Incinerators and Waste Handling Systems Date: April 27, 2017 To: From: Technical Committee on Incinerators and Waste Handling Systems Eric Nette, Staff Liaison/Engineer Re: Agenda
More informationPublic Input No. 1-NFPA [ Global Input ] Statement of Problem and Substantiation for Public Input. Related Public Inputs for This Document
National Fire Protection Association Report of 113 http://submittals.nfpa.org/terraviewweb/contentfetcher?commentpara... 2/9/2016 10:50 AM Public Input No. 1-NFPA 87-2015 [ Global Input ] Throughout standard
More informationLocation of Requirements Listed Category I appliances Type B gas vent 12.7 Listed appliances equipped with. Chimney Single wall metal pipe 12.
2/18/2016 National Fire Protection Association Report Committee Input No. 70 NFPA 54 2015 [ Section No. 12.5 ] This was a First Revision that failed ballot. 12.5 Type of Venting System to Be Used. 12.5.1
More information26 of 128 9/23/2014 9:25 AM
26 of 128 9/23/2014 9:25 AM Second Revision No. 105-NFPA 72-2014 [ Global Comment ] Revise the Annex F figures that include a smoke detector symbol (hexagon with a whisp of smoke) so that the new smoke
More informationPublic Input No. 4-NFPA [ Section No. 4.2 ] Statement of Problem and Substantiation for Public Input. Submitter Information Verification
Public Input No. 4-NFPA 214-2013 [ Section No. 4.2 ] 4.2 * Fire Risk Analysis. A fire risk analysis shall be conducted. The following are some of the factors that shall be considered in determining the
More informationPublic Input No. 52-NFPA [ Section No [Excluding any Sub-Sections] ]
8 of 93 11/6/2015 7:41 AM Public Input No. 52-NFPA 30-2015 [ Section No. 21.2 [Excluding any Sub-Sections] ] For the purpose of this chapter, the term in this section shall have the definitions given.
More informationNFPA 86 Commitee Inputs Page 1 of 45
of 44 1/26/2017 2:28 PM Committee Input No. 102-NFPA 86-2016 [ Global Input ] The Committee is considering language for pre-purge of the work chambers for Class A, Class B and Class C furnaces. This could
More informationAttendees Principal Members/Staff: Joseph Fehr, Chair, Sega, Inc., KS Laura Montville, NFPA Staff, MA
TECHNICAL COMMITTEE ON FUNDAMENTALS OF COMBUSTION SYSTEMS HAZARDS NFPA 85 Pre-Draft Meeting Minutes September 30, 2015 8:00 AM - 5:00 PM EDT NFPA Headquarters, Quincy, MA Attendees Principal Members/Staff:
More informationWhy AC800M High Integrity is used in Burner Management System Applications?
Why AC800M High Integrity is used in Burner Management System Applications? Prepared by: Luis Duran Product Marketing Manager Safety Systems ABB Process Automation/Control Technologies TÜV Functional Safety
More informationTECHNICAL COMMITTEE ON WATER-COOLING TOWERS. First Draft Meeting Agenda. February 7, :00 AM - 5:00 PM EST Web/Teleconference Meeting
TECHNICAL COMMITTEE ON WATER-COOLING TOWERS First Draft Meeting Agenda February 7, 2014 10:00 AM - 5:00 PM EST Web/Teleconference Meeting 1. Welcome. Robert Smith, Chair 2. Introductions and Update of
More informationFirst Revision No. 20-NFPA [ Section No ]
of 25 7/15/2015 8:30 AM First Revision No. 20-NFPA 56-2015 [ Section No. 1.1.2 ] 1.1.2 Nonapplication of Standard. This standard shall not apply to the following items: (1)* Piping systems covered by NFPA
More informationUpdate all extract references to NFPA documents (including NFPA 72) in Chapter 3 and related annex material to the latest editions.
11/16/12 TerraView First Revision No. 15-NFPA 720-2012 [ Global Input ] Update all extract references to NFPA documents (including NFPA 72) in Chapter 3 and related annex material to the latest editions.
More informationFIF AAA (F2014) Second Draft Meeting Web/Teleconference Meeting Agenda March 18, :00 5:00 p.m. ET
NFPA 804, Standard for Fire Protection for Advanced Light Water Reactor Electric Generating Plants, NFPA 805, Performance Based Standard for Fire Protection for Light Water Reactor Electric Generating
More informationNational Fire Protection Association. 1 Batterymarch Park, Quincy, MA Phone: Fax:
National Fire Protection Association 1 Batterymarch Park, Quincy, MA 02169-7471 Phone: 617-770-3000 Fax: 617-770-0700 www.nfpa.org M E M O R A N D U M TO: FROM: NFPA Technical Committee on Mercantile and
More informationPage 1 of 46 Public Input No. 17-NFPA 13E-2013 [ New Section after 3.2.4 ] New 3.2.5 Pressure-Reducing Valve. A valve designed for the purpose of reducing the downstream water pressure under both flowing
More informationKolmetz Handbook Of Process Equipment Design BURNER MANAGEMENT SYSTEMS (ENGINEERING DESIGN GUIDELINE)
Practical Engineering Guidelines for Processing Plant Solutions SOLUTIONS, STANDARDS AND SOFTWARE www.klmtechgroup.com Page : 1 of 78 Rev 1 KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman
More informationM E M O R A N D U M. NFPA Technical Committee on Building Services and Fire Protection Equipment
M E M O R A N D U M TO: FROM: NFPA Technical Committee on Building Services and Fire Protection Equipment Linda MacKay DATE: November 10, 2009 SUBJECT: NFPA 5000 A2011 ROP Letter Ballot Final Results The
More informationPublic Input No. 1-NFPA [ Global Input ] Statement of Problem and Substantiation for Public Input. Submitter Information Verification
Public Input No. 1-NFPA 36-2013 [ Global Input ] Revise the document to eliminate the use of "Exception" text. The use of "Exception" text is inconsistent with the Manual of Style. Exception text should
More informationCorrelating Committee on Automatic Sprinkler Systems
Correlating Committee on Automatic Sprinkler Systems M E M O R A N D U M DATE: May 14, 2014 TO: FROM: Principal and Alternate Members of the Correlating Committee on Automatic Sprinkler Systems Matt Klaus,
More informationProposed Changes to NFPA
2017 NFPA Conference & Expo Proposed Changes to NFPA 72-2019 Presented by: Manuelita David (SIG-FUN), Jensen Hughes Warren Olsen (SIG-SSS), Fire Safety Consultants, Inc. Merton Bunker (SIG-AAC), EYP Architecture
More informationAgenda Technical Committee on Protected Premises Fire Alarm Systems September 9-11, 2013 Saint Louis, MO
Agenda Technical Committee on Protected Premises Fire Alarm Systems September 9-11, 2013 Saint Louis, MO Item No. Subject 13-9-1 Call to Order (8:00 A.M) 13-9-2 Roll Call 13-9-3 Approval of Agenda 13-9-4
More informationDelayed Action Closer. Mechanical self-closing device that incorporates an adjustable delay prior to the initiation of closing.
9/20/2016 2:27 PM Second Revision No. 5006-NFPA 101-2016 [ Section No. 3.3.56 ] 3.3.56 Delayed Action Closer. Self-closing device that incorporates a delay prior to the initiation of closing. Mechanical
More informationObjectives. NFPA Dust Specific Documents. Combustible Dust Process Hazard Safety Overview of NFPA Standards for Combustible Dusts
Combustible Dust Process Hazard Safety Overview of NFPA Standards for Combustible Dusts Guy R. Colonna, PE Division Manager, NFPA Combustible Dust Symposium Detroit, MI September 20, 2011 1 Objectives
More informationPublic Comment No. 23-NFPA [ Section No ] Statement of Problem and Substantiation for Public Comment Related Item
Public Comment No. 23-NFPA 96-2015 [ Section No. 2.3.1 ] 2.3.1 ASTM Publications. ASTM International, 100 Barr Harbor Drive, P.O. Box C700, West Conshohocken, PA 19428-2959. ASTM E84, Standard Test Method
More informationFirst Revision No. 1-NFPA [ Section No ] Submitter Information Verification. Committee Statement 4/15/ :08 AM
First Revision No. 1-NFPA 1403-2015 [ Section No. 1.2.1 ] 1.2.1 The purpose of this standard shall be to provide a process for conducting live fire training evolutions to ensure that they are conducted
More informationTechnical Committee on Fluid Heaters
Technical Committee on Fluid Heaters Date: August 9, 2016 To: Technical Committee on Fluid Heaters From: Eric Nette, Staff Liaison/Engineer Re: Agenda Package NFPA 87 A2017 Second Draft Meeting October
More information3. Approval of Meeting Minutes from January 21, 2014 (Attachment A). Fall 2018 revision cycle schedule. (Attachment C)
TECHNICAL COMMITTEE ON FLUIDIZED BED BOILERS NFPA 85 First Draft Meeting Agenda February 16, 2017 9:30 AM 4:30 PM Eastern Time Web Meeting/Teleconference 1. Call to Order. James Walawender, Chair 2. Introductions.
More informationRevitalize Building Mechanical Systems (4619)
SECTION 235216 FIRE-TUBE CONDENSING BOILERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationCombustionONE. Improving and Sustaining the Combustion Asset. Driven by the New Standards. Bulletin 53A90A01-01E-A
1 CombustionONE TM Improving and Sustaining the Combustion Asset Driven by the New Standards Bulletin 53A90A01-01E-A 1 CombustionONE Improving and Sustaining the Combustion Asset TM Yokogawa Corporation
More informationNFPA s Standards Development Process
NFPA s Standards Development Process Revision Cycle 104 weeks or 141 weeks Guiding Principles Due process Openness Lack of dominance Seek society s balance between: Acceptable risk Commitment of resources
More informationAlarm. A warning of danger. An indication of the existence of a condition that requires immediate action. (SIG-FUN)
4 of 326 11/21/2013 1:03 PM First Revision No. 161-NFPA 72-2013 [ Section No. 3.3.11 ] 3.3.11 Alarm. A warning of danger. An indication of the existence of a condition that requires immediate action. (SIG-FUN)
More informationNational Fire Protection Association. 1 Batterymarch Park, Quincy, MA Phone: Fax:
National Fire Protection Association 1 Batterymarch Park, Quincy, MA 02169-7471 Phone: 617-770-3000 Fax: 617-770-0700 www.nfpa.org M E M O R A N D U M TO: FROM: NFPA Technical Committee on Hot Work Operations
More informationEngineering Standard. Saudi Aramco DeskTop Standards
Engineering Standard 26 October 2005 Instrumentation Standards Committee Members Al-Awami. L.H., Chairman Tuin, R.R., Vice Chairman Al-Dakhil, T.K. Al-Dhafeeri, F.T. Al-Khalifa, A.H. Al-Madhi, F.A. Alqaffas,
More informationCommittee Input No NFPA [ Global Input ] Submitter Information Verification. Committee Statement. 1 of /20/ :02 AM
1 of 213 10/20/2016 11:02 AM Committee Input No. 2505-NFPA 72-2016 [ Global Input ] Change the term visible to visual where appropriate Submitter Information Verification Submitter Full Name: SIG-NAS Organization:
More information1. Welcome. Robert Smith, Chair. 2. Introductions and Update of Committee Roster. (attached)
TECHNICAL COMMITTEE ON WATER-COOLING TOWERS NFPA 214 (F2015) Second Draft Meeting Agenda February 17, 2014 10:00 AM - 1:00 PM EST Web/Teleconference Meeting 1. Welcome. Robert Smith, Chair 2. Introductions
More informationBy Authority Of THE UNITED STATES OF AMERICA Legally Binding Document
By Authority Of THE UNITED STATES OF AMERICA Legally Binding Document By the Authority Vested By Part 5 of the United States Code 552(a) and Part 1 of the Code of Regulations 51 the attached document has
More informationMEMORANDUM. Technical Committee on Fundamentals of Fire Alarm and Signaling Systems
National Fire Protection Association 1 Batterymarch Park, Quincy, MA 02169-7471 Phone: 617-770-3000 Fax: 617-770-0700 www.nfpa.org MEMORANDUM TO: FROM: Technical Committee on Fundamentals of Fire Alarm
More informationREPORT OF THE NFPA MOTIONS COMMITTEE* ON FALL 2013 REVISION CYCLE STANDARDS
REPORT OF THE NFPA MOTIONS COMMITTEE* ON FALL 2013 REVISION CYCLE STANDARDS I. Introduction. This is the Motions Committee Report on Standards in the Fall 2013 Revision Cycle. The report identifies Certified
More informationNational Fire Protection Association M E M O R A N D U M. Technical Committee on Testing and Maintenance of Fire Alarm and Signaling Systems
National Fire Protection Association 1 Batterymarch Park, Quincy, MA 02169-7471 Phone: 617-770-3000 Fax: 617-770-0700 www.nfpa.org M E M O R A N D U M TO: FROM: Technical Committee on Testing and Maintenance
More informationM E M O R A N D U M. NFPA 5000 A2011 ROP Letter Ballot
M E M O R A N D U M TO: FROM: NFPA Technical Committee on Building Service and Fire Protection Equipment Gregory Harrington, P.E., Staff Liaison DATE: October 1, 2009 SUBJECT: NFPA 5000 A2011 ROP Letter
More informationCompliance Guidance for non-technical managers
11699 Brookpark Road Cleveland, OH 44130 USA P: 888-826-3473 F: 216-398-8403 www.combustionsafety.com -WHITEPAPER- NFPA 56 (2012 Ed.) Standard for Fire and Explosion Prevention During Cleaning and Purging
More informationSAFETY CONTROL REQUIREMENTS FOR OVENS AND FURNACES
SAFETY CONTROL REQUIREMENTS FOR OVENS AND FURNACES SAFETY CONTROL REQUIREMENTS The NATIONAL FIRE PROTECTION ASSOCIATION is organized to promote the science and improve the methods of fire protection and
More informationTechnical Committee on Residential Sprinkler Systems
Technical Committee on Residential Sprinkler Systems M E M O R A N D U M DATE: June 26, 2013 TO: FROM: Principal and Alternate Members of the Technical Committee on Residential Sprinkler Systems Matt Klaus,
More informationREFERENCE SYLLABUS. For FIRED PROCESS HEATER OPERATOR S. CERTIFICATE of COMPETENCY EXAMINATION AB-239. Edition 3, Revision 1, Issued
For CERTIFICATE of COMPETENCY EXAMINATION AB-239 Edition 3, Revision 1, Issued 2018-07-13 Visit our Website at www.absa.ca GENERAL INMATION Introduction: As provided for under the Power Engineers Regulation,
More informationReport on First Revision June 2014 NFPA 5000
5000- Log #12 BLD-BSF Final Action: (55.2 (New) ) NOTE: This proposal appeared as Comment 5000-168 (Log #86) which was held from the A11 ROC on Proposal 5000-239. Submitter: Technical Correlating Committee
More informationMEMORANDUM. Technical Committee on Notification Appliances for Fire Alarm and Signaling Systems
National Fire Protection Association 1 Batterymarch Park, Quincy, MA 02169-7471 Phone: 617-770-3000 Fax: 617-770-0700 www.nfpa.org MEMORANDUM TO: FROM: Technical Committee on Notification Appliances for
More informationTECHNICAL COMMITTEE ON FIRE PUMPS
TECHNICAL COMMITTEE ON FIRE PUMPS MEMORANDUM TO: FROM: Technical Committee on Fire Pumps Joanne Goyette, on behalf of C. Duffy / R. P. Benedetti DATE: May 2, 2011 SUBJECT: Letter Ballot on Proposals to
More informationTECHNICAL COMMITTEE ON WASTEWATER TREATMENT PLANTS First Draft Meeting Agenda September 10-12, 2013 Hampton Inn, Columbus, Ohio
TECHNICAL COMMITTEE ON WASTEWATER TREATMENT PLANTS First Draft Meeting Agenda September 10-12, 2013 Hampton Inn, Columbus, Ohio September 10 (12 PM-5 PM) September 11 (8 AM-5 PM) September 12 (8 AM-12
More informationPublic Comment No. 2-NFPA [ Section No ] Statement of Problem and Substantiation for Public Comment. Submitter Information Verification
Public Comment No. 2-NFPA 73-2014 [ Section No. 4.1.3 ] 4.1.3 Unused Openings. 4.1.3.1 Unused openings, other than those intended for the operation of equipment, those intended for mounting purposes, or
More informationPublic Input No. 3-NFPA [ Chapter 2 ]
Public Input No. 3-NFPA 655-2014 [ Chapter 2 ] Chapter 2 Referenced Publications 2.1 General. The documents or portions thereof listed in this chapter are referenced within this standard and shall be considered
More informationPre-First Draft Meeting Technical Committee on Wastewater Treatment Plants On line/conference Call November 20, PM EDT
Pre-First Draft Meeting Technical Committee on Wastewater Treatment Plants On line/conference Call vember 20, 2012 2-4 PM EDT (1-3 PM CT; 12-2 PM MT; 11-1 PM PT) 1. Welcome-Glenn McGinley, Committee Chair
More informationPublic Input No. 1-NFPA 99B-2015 [ Section No. 2.3 ] Statement of Problem and Substantiation for Public Input. Related Public Inputs for This Document
1 of 19 10/21/2015 1:20 PM Public Input No. 1-NFPA 99B-2015 [ Section No. 2.3 ] 2.3 Other Publications. 2.3.1 ASME Publications. American Society of Mechanical Engineers, Three ASME International, Two
More informationChanges for the New Edition. Senior Engineer, NFPA NFPA
Changes for the New Edition Denise Beach Senior Engineer, NFPA NFPA Overview NFPA 58-2014 Substantive Changes TIAs 2017 Edition NFPA 58-2014 Substantive Changes Bulk and Industrial Plants 3.3.10 Bulk Plant.
More informationWORKING DRAFT OF COMMITTEE MEETING OUTPUT
WORKING DRAFT OF COMMITTEE MEETING OUTPUT CONTENT NOT FINAL SUBJECT TO REVISION PRIOR TO LETTER BALLOT AND PUBLICATION OF SECOND DRAFT REPORT Document: NFPA 221 Revision Cycle: A2014 Meeting Date: 5/20/2013
More informationNational Fire Protection Association. 1 Batterymarch Park, Quincy, MA Phone: Fax:
National Fire Protection Association 1 Batterymarch Park, Quincy, MA 02169-7471 Phone: 617-770-3000 Fax: 617-770-0700 www.nfpa.org MEMORANDUM TO: FROM: Correlating Committee on Combustible Dusts Susan
More informationNFPA 85 COMPLIANCES OF BMS: A CASE STUDY OF BOILER CONTROL AT SBM OFFSHORE MALAYSIA COMPANY 1. AHMED ABOUELRISH 2 Universiti Teknologi Petronas
Journal of Contemporary Issues in Business Research ISSN 2305-8277 (Online), 2013, Vol. 2, No. 4, 109-123. Copyright of the Academic Journals JCIBR All rights reserved. NFPA 85 COMPLIANCES OF BMS: A CASE
More informationRiverside County Fire Department Office of the Fire Marshal Market St., Ste. 150, Riverside, CA Ph. (951) Fax (951)
Riverside County Fire Department Office of the Fire Marshal 2300 Market St., Ste. 150, Riverside, CA 92501 Ph. (951) 955-4777 Fax (951) 955-4886 Technical Policy Title: Plant Processing and Extraction
More informationM E M O R A N D U M. According to the final ballot results, all ballot items received the necessary affirmative votes to pass ballot.
National Fire Protection Association 1 Batterymarch Park, Quincy, MA 02169-7471 Phone: 617-770-3000 Fax: 617-770-0700 www.nfpa.org M E M O R A N D U M To: From: NFPA Technical Committee on Helicopter Facilities
More informationMeeting Agenda Technical Committee on Fire Service Occupational Safety and Health January 8 th -10 th, 2013 San Diego, Ca.
Meeting Agenda Technical Committee on Fire Service Occupational Safety and Health January 8 th -10 th, 2013 San Diego, Ca. I. Welcome and call to order of the TC by the Chair at 8am. II. Introductions-
More informationBurner Management and Combustion Control. Copyright 2014 Rockwell Automation, Inc. All Rights Reserved.
Burner Management and Combustion Control Rev 5058-CO900E Industrial Combustion Team Overview Background and Industry Experience RA s IC&PG Team Expertise 3 Extensive experience working with Factory Mutual
More informationNFPA Technical Committee on Building Systems. NFPA 900 First Draft Teleconference/Web Meeting AGENDA. Thursday, February 13, :00 a.m.
1. Call to Order: NFPA Technical Committee on Building Systems NFPA 900 First Draft Teleconference/Web Meeting AGENDA Thursday, February 13, 2014 11:00 a.m. Noon EDT Online meeting link: http://nfpa.adobeconnect.com/r366m2eaxx6/
More informationSecond Revision No. 36-NFPA [ Detail ] Submitter Information Verification. Committee Statement 5/18/2015 1:01 PM
of 66 5/18/2015 1:01 PM Second Revision No. 36-NFPA 32-2015 [ Detail ] 6.5 Solvents (See Annex C for additional information on solvents) Submittal Date: Tue Mar 17 17:20:03 EDT 2015 Committee Statement:
More informationMEMORANDUM. NFPA Technical Committee on Fundamentals of Fire Alarm and Signaling Systems (SIG- FUN)
National Fire Protection Association 1 Batterymarch Park, Quincy, MA 02169-7471 Phone: 617-770-3000 Fax: 617-770-0700 www.nfpa.org MEMORANDUM To: From: NFPA Technical Committee on Fundamentals of Fire
More informationThroughout standard remove references to the following and replace with the following:
of 105 1/21/2016 7:49 AM Public Input No. 2-NFPA 30A-2015 [ Global Input ] Throughout standard remove references to the following and replace with the following: (1) ANSI/UL and replace with UL. (2) ANSI
More information