1 GUIDELINES FOR ENVIRONMENTAL SCREENING OF ROAD PROJECTS April, 1997 Juan Quintero The World Bank Latin America and Caribbean Region Type of Projects Much of the confusion as to the project environmental category and the type of environmental and social work required stems from the lack of an unified definition and classification of road works. Words like rehabilitation, improvements, upgrading (and sometimes 'modernization") are used interchangeably in the same report or indiscriminately across LAC. A clear definition of the type of works and activities is therefore needed. The following 5 categories, in increasing order of environmental concern, are proposed:
2 1. Maintenance Routine or periodic works to maintain the road in working conditions. All of the work is done on the existing platform. routine works, patching potholes, clearing drains; or periodic works such as resurfacing, linemarking, bridge maintenance. 2. Rehabilitation Bringing existing deteriorated roads to previous/original conditions. All of the work is done on the existing platform/ right of way. No additional land acquisition is needed. improving drainage/slopes/embankments/other structures strengthening pavements complete resurfacing recuperating civil works 3. Improvements Improving road specifications. Most of the work is done on the existing platform or right of way. Additional land acquisition may be needed. widening lanes and shoulders adding extra lanes in steep inclines improving curves strengthening bridges 4. Upgrading Changing road category (e.g. seasonal to all-weather, secondary to primary, or from gravel to paved). Land acquisition is needed in most cases. adding new lanes (2 to 4, 4 to 6, etc.) changing road surface (such as from gravel to paved) widening intersections 5. New Construction New projects built on a new alignment. Major land acquisition is needed. new roads bypasses realignments (changing in route)
3 Site Location and Sensitivity Site location and sensitivity is a major factor in determining the type and extent of the required environmental work. A three grade system (low, medium, and high sensitivity) is proposed for : natural habitats, resettlement, indigenous peoples, induced development, soil stability/erosion, and cultural heritage. If information is available, more items could be added during project preparation (such as noise, water quality, and drainage density). Low Sensitivity Medium Sensitivity High Sensitivity Natural Habitats Resettlement Indigenous peoples No critical natural habitats; no other natural habitats Low population density; dispersed population; no or little road side activities; well established businesses and legal tenure along right of way. No critical natural habitats; other nonforest natural habitats occur Medium population density; settlements; some roadside activity; mixed ownership and land tenure along right of way. No indigenous peoples Dispersed and mixed indigenous populations; mainstream (highly acculturated) indigenous populations Critical natural habitats Critical natural habitats are defined as existing and proposed protected areas, along with unprotected natural habitats of known high importance for biodiversity conservation. For details see Natural Habitats OP and all natural forests High population density; major towns and villages; intensive roadside activity; low income families and illegal ownership of land in and along right of way; communal properties. Indigenous territories and reserves; vulnerable indigenous populations
4 Induced Development Soil Stability/Erosion Cultural Heritage Area or region is well consolidated; dense road network Flat terrain; no potential erosion problems. No known or suspected cultural heritage sites Medium density road network; open lands are still available Medium slopes; some erosion potential Suspected cultural heritage sites; known heritage sites in area of influence Area or region is undeveloped; road network is incipient or non-existent Mountainous terrain; high slopes; unstable soil formations; high erosion potential Known heritage sites along the right of way Definition of Environmental Requirements A cross between project type and scale and environmental and social sensitivity is shown in the following table. For each project type and sensitivity a level of environmental work is specified, based on the most sensitive issue for a project (NOT on the "average" sensitivity of different issues). Type of Work Low Sensitivity Medium Sensitivity High Sensitivity Maintenance Level 1 Level 1 Level 1 Rehabilitation Level 1 Level 1 Level 2 Improvement Level 1 Level 2 Level 2 Upgrading Level 2 Level 2 Level 3 New construction Level 2 Level 3 Level 3 Levels of Environmental Work if Projects are Known at Appraisal Projects description should explicitly establish the type of work that will be financed (maintenance, rehabilitation, improvement, upgrading, new construction). Three levels of environmental work are defined taking into account the "highest" type of work that will be included in the project: First Level: Application of environmental guidelines for design and environmental rules for contractors Second Level: Application of above environmental guidelines and rules for
5 contractors; additional screening may be necessary; limited environmental analysis for specific issues is usually necessary; a resettlement framework/strategy to deal with minor resettlement is needed. Institutional capacity for environmental management may need to be created or strengthened. Third Level: Application of environmental guidelines and rules for contractors; a full/detailed EA is necessary. Specific mitigation/compensation measures (including resettlement plans and indigenous people's development plans) need to be identified. Institutional capacity for environmental management needs to be in place. Environmental Issues when Specific Projects are not Known at Appraisal The type of projects to be financed need nevertheless to be defined (maintenance, rehabilitation, new construction, etc.). If the specific projects are not known at appraisal and the site sensitivity cannot be determined, as a minimum the following environmental analysis will be required during project preparation: Maintenance/Rehabilitation: ensure existence/prepare environmental guidelines for road construction/maintenance Improvement: In addition to Maintenance/Rehabilitation requirements: establish environmental (including resettlement, indigenous peoples, natural habitats, cultural heritage) screening criteria environmental survey of road network most likely to be improved or upgraded define legal and institutional framework/procedures for environment, resettlement, and indigenous peoples issues (if they are lacking) ensure institutional capability to implement the above framework New Construction/ Upgrading
6 In addition to the Improvement requirements: EA and resettlement plan for first year investments indigenous peoples development plans are necessary (if applicable) annual investment programs should include environmental and social requirements for Bank review.
Municipal Class EA Study Public Information Centre No. 1 December 13, :00 pm 7:00 pm. Please sign in so we can keep you updated on this study
Reconstruction of Regional Road 45 (Creek Road) Between Regional Road 27 (River Road) and Regional Road 63 (Canborough Road) in the Township of Wainfleet Municipal Class EA Study Public Information Centre
More informationPROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: PIDC2498 Project Name EC
More informationPublic Information Centre. Welcome
Transportation Improvements from the Beaver Creek Bridge to the Entrance of Santa s Village District of Muskoka Municipal Class Environmental Assessment Welcome Please sign in Take a comment sheet Staff
More informationBACKGROUND INFORMATION DOCUMENT
BACKGROUND INFORMATION DOCUMENT PROPOSED UPGRADING OF THE N2 NATIONAL ROAD FROM KRAAIBOSCH TO DIE VLEIE BASIC ENVIRONMENTAL IMPACT ASSESSMENT The South African National Roads Agency Society Limited (SANRAL)
More informationSocial Monitoring Report
Social Monitoring Report Due Diligence Report Four Bridges Improvement Project Ganja Region, Roads: R24 and Y-05-08 Involuntary September 2013 Azerbaijan: Road Network Development Program Tranche 4 Prepared
More informationINDIA Biodiversity Conservation and Rural Livelihood Improvement Project
INDIA Biodiversity Conservation and Rural Livelihood Improvement Project Indigenous Peoples Planning Framework INDIA BIODIVERSITY CONSERVATION AND RURAL LIVELIHOOD IMPROVEMENT PROJECT Indigenous Peoples
More informationFY 2018 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects
Route 18, South of Texas Road to Rues Lane, Pavement Project ID Numbers: 11408 / 114080 Initiated from the Pavement Management System, this project will rehabilitate pavement within the project limits.,
More informationVALLEY COUNTY MINIMUM STANDARDS FOR PRIVATE ROAD DESIGN AND CONSTRUCTION
MINIMUM STANDARDS FOR PRIVATE ROAD DESIGN AND CONSTRUCTION Adopted November 28, 2005 TABLE OF CONTENTS DEFINITION OF TERMS...II I. DESIGN CRITERIA... 1 A. GENERAL DESIGN CRITERIA... 1 B. ROADWAY CLASSIFICATION...
More informationINTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 09/14/2006 INTEGRATED SAFEGUARDS DATASHEET
More information3. Highway Landscaping Assessment
Guidelines for Highway Landscaping 3-1 3. Highway Landscaping Assessment 3.1 Introduction This section outlines the steps necessary to assess the highway landscaping component of a state highway construction
More information2040 Long Range Transportation Plan
2040 Long Range Transportation Plan Adopted: April 15, 2013 APPENDIX D HIGHWAY NEEDS PLAN PROJECTS FREDERICKSBURG Existing and Committed Projects Fall Hill Avenue/Mary Washington Blvd. (Fredericksburg)
More informationBostwick Road. Municipal Class Environmental Assessment. Public Information Centre #2 June 14, City of London
Bostwick Road Municipal Class Environmental Assessment Public Information Centre #2 June 14, 2017 Welcome! Welcome to the 2 nd Public Information Centre for the. Representatives from the and the consulting
More informationINTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 28-Jan-2014
More informationZoning Ordinance Chapter 10
CHAPTER 10 - WASHES SECTION 10.0 GENERAL: A. The purpose of this Ordinance is to establish standards for development in or near Major and Minor Washes as defined in Appendix A Glossary of Terms and Definitions
More informationSocial Screening and Impact Assessment for Sub Projects
Social Screening and Impact Assessment for Sub Projects Code No: 7 A. Sub Project Description: Rehabilitation of McCallum Lock Gates and Construction of Bank Protection Wall with Linear Walk Around Beira
More informationCommissioners Road West Realignment Environmental Assessment
City of London Commissioners Road West Realignment Environmental Assessment Public Information Centre No. 1 March 30, 2017 Welcome to the Public Information Centre This first Public Information Centre
More informationVDOT Vegetation Management Policy
VDOT Vegetation Management Policy Appropriation Act Item 436 H (2010) Report to the Chairmen of House Appropriations and Transportation Committees and Senate Finance and Transportation Committees Virginia
More informationDecision Notice. Proposed Action
Decision Notice Paving Weld County Road 105 USDA Forest Service Arapaho and Roosevelt National Forest and Pawnee National Grassland Pawnee National Grassland Ranger District Weld County, Colorado November
More informationNAPA COUNTY PUBLIC WORKS Standards & Specifications
Roadway Design & Construction Manual (Table of Contents) 1. Chapter 1: General Provisions 1.1 Short Title 1.2 Jurisdiction 1.3 Purpose and Effect 1.4 Enactment Authority 1.5 Amendment and Revisions 1.6
More informationRolla Comprehensive Plan Update, 2005 COMMUNITY ISSUES MEMORANDUM 11/1/2004
COMMUNITY ISSUES MEMORANDUM 11/1/2004 Introduction Throughout the planning process, but particularly during the early phases of the update, various individuals and groups will be asked to identify and
More informationCHAPTER 4 FUTURE LAND USE AND URBAN SERVICES DISTRICTS
CHAPTER 4 FUTURE LAND USE AND URBAN SERVICES DISTRICTS Introduction This chapter discusses how Benzie County should grow and change in the future. A community can grow and change in many different ways.
More informationChapter 3 Core Strategy
Chapter 3 Core Strategy 3.0 Introduction The core strategy sets out how the development objectives in the Development Plan are consistent with the National Spatial Strategy and the Regional Planning Guidelines.
More informationYour town s subdivision or land use ordinance standards should reference the following street standards, for example:
Your town s subdivision or land use ordinance standards should reference the following street standards, for example: Streets shall be designed to move traffic safely and in a way that minimizes environmental
More informationRequest for an Exception to the Napa County Road and Street Standards
F Request for an Exception to the Napa County Road and Street Standards Shed Creek Winery Use Permit P16-327 and Use Permit Exception to the Conservation Regulations P17-178 Planning Commission Hearing
More informationThe Illinois Department of Transportation and Lake County Division of Transportation. Route 173, including the Millburn Bypass
The Illinois Department of Transportation and Lake County Division of Transportation welcome you to this Public Hearing for U.S. Route 45 from Illinois Route 132 to Illinois Route 173, including the Millburn
More informationProgramme at a glance February 2018 Kuala Lumpur
Programme at a glance 7-13 February 2018 Kuala Lumpur Wednesday 7 February 2018 Thursday 8 February 2018 09:00-10:30 Joint Opening for the WUF9 Assemblies 10:30-17:30 Women s Assembly Business Assembly
More informationFY 2018 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects
Schooleys Mountain Bridge Rehabilitation Project ID Numbers: N1707 / 173470 Schooleys Mountain Road Bridge was built in 1920 and widened in 1937. The project is a replacement of the bridge structure and
More informationA Unified Auckland The challenge of developing transport based Design Standards for the Auckland Region
A Unified Auckland The challenge of developing transport based Design Standards for the Auckland Region Chris Beasley Principle Technical Specialist, PMO Section 1 Recap on formation of Auckland Transport
More informationI602. Birdwood Precinct
I602. Birdwood Precinct I602.1. Precinct description The Birdwood Precinct applies to an area west of Don Buck Road and south of Red Hills Road in west Auckland. It incorporates subdivision and development
More informationCORNUBIA RETAIL PARK- PLANNING REPORT REVERT 3
CORNUBIA RETAIL PARK- PLANNING REPORT 19.04.2013 REVERT 3 1 FOR: BY: 28 DEVONSHIRE AVENUE GLENWOOD DURBAN 4001 P.O. BOX 17390 CONGELLA 4013 T +27 31 202 9550 F +27 31 202 9551 1st FLOOR THE MEDIA MILL
More information4-Town Comprehensive Plan DRAFT 7/30/07
4-Town Comprehensive Plan DRAFT 7/30/07 Acknowledgements ning Committee Town of Harrisburg Norman Roof Randy Nicol Town of Martinsburg Terry Thisse Paul Kelly Town of Montague Jan Bagdanowicz Wendy Perry
More informationNEW CASTLE COUNTY S ZONING DISTRICTS
NEW CASTLE COUNTY S ZONING DISTRICTS This is general information about New Castle County s zoning districts. The information included is by no means exhaustive or complete. Before designing plans to develop
More informationPennsy Greenway Trail
Town of Schererville Pennsy Greenway Trail DES. #s: 0401062, 1173595 & 1382661 Construction of Pennsy Greenway Trail beginning at Wilhelm Street and continuing northwest along the former Penn Central railroad
More informationDESIGN PUBLIC HEARING APRIL 24, 2018 MUNICIPAL OFFICE BUILDING HARDWICK, MASSACHUSETTS 7:00 PM FOR THE PROPOSED
DESIGN PUBLIC HEARING APRIL 24, 2018 AT MUNICIPAL OFFICE BUILDING HARDWICK, MASSACHUSETTS 7:00 PM FOR THE PROPOSED ROUTE 32/32A GILBERTVILLE VILLAGE RECONSTRUCTION PROJECT Roadway Project Management Section
More informationOutline of Presentation
LUSAKA CITY COUNCIL 2 nd Annual IGC Cities Conference Making Cities work for growth London School of Economics (LSE) United Kingdom. 28 th 29 th January 2016 Presenter: Alex Mwansa Town Clerk Lusaka City
More informationHighway Alignment and Route Location Survey
CHAPTER 2 Highway Route Surveys and Location Introduction To determine the geometric features of road design, the following surveys must be conducted after the necessity of the road is decided. Type of
More information3. VISION AND GOALS. Vision Statement. Goals, Objectives and Policies
Vision Statement Queen Creek s interconnected network of parks, trails, open spaces and recreation opportunities provide safe and diverse activities and programs that sustain its unique, small town, equestrian
More informationEnvision Sustainable Infrastructure
Envision Sustainable Infrastructure Marshview Park Allyson Monsour, PE, ENV SP, LEED Green Associate What Is Sustainability? Social Sustainability Fair and beneficial labor practices Community involvement
More informationSITE ASSESSMENT CHECKLIST
1. Site Details a. What is the site s name/reference? SITE ASSESSMENT CHECKLIST CR3NPWHY 3007 Gasometer Site Godstone Road CR3 0EG b. Where is the site located? Wyhteleafe; Godstone Road. Urban category1
More informationMississauga Waterfront. Parks Strategy - Draft
Potential configuration for river s edge seating. Boating on Credit River: A regatta Boating on Credit River: Active enjoyment 5.2 Port Credit Memorial Park West Priority Park 5.2.1 Site Opportunities
More information(2A) Introduction to Design (and Nepal Rural Road Standards)
(2A) Introduction to Design (and Nepal Rural Road Standards) Presentation for LRN Training Bill Seal, Engineering Team Leader September 2014 1 Overview of Design Chapter (Day 2) 2A. Introduction to Design
More informationCommunity LID Workgroup Issue Paper #6
Community LID Workgroup Issue Paper #6 Topic: Hard and Impervious Surface Coverage Limits Objective: Minimize the amount of hard and impervious surfaces in developments to allow more stormwater to infiltrate
More informationIMPLEMENTATION STRATEGIES. In This Chapter. Goals & Strategies 182 Project List 183 Future Land Use 186 CHAPTER 11 IMPLEMENTATION STRATEGIES
In This Chapter Goals & Strategies 182 Project List 183 Future Land Use 186 11 IMPLEMENTATION STRATEGIES NORTH AUGUSTA, SC 2017 COMPREHENSIVE PLAN 179 Individual commitment to a group effort that is what
More informationMODULE 3 RESTRUCTURING THE ENVIRONMENT
MODULE 3 RESTRUCTURING THE TOWNSHIP PHYSICAL ENVIRONMENT FOCUS OF THE MODULE The physical and spatial (locational) characteristics that prevent townships from developing Levels of intervention: Things
More informationEmployment and Commercial Review Analysis of Policy Directions
Employment and Commercial Review Analysis of Policy Directions Appendix A The following analysis is town staff s response to the policy directions provided by the consultants who prepared the Employment
More informationDESIGN PUBLIC HEARING MAY 10, 2018 GRANBY TOWN HALL FIRST FLOOR CONFERENCE ROOM 10 WEST STATE STREET GRANBY, MASSACHUSETTS 7:00 PM FOR THE PROPOSED
DESIGN PUBLIC HEARING MAY 10, 2018 AT GRANBY TOWN HALL FIRST FLOOR CONFERENCE ROOM 10 WEST STATE STREET GRANBY, MASSACHUSETTS 7:00 PM FOR THE PROPOSED Reconstruction of Granby Road/West State Street (Route
More information14.5 HOPEFIELD: (REFER PLAN 39 AND PLAN 40)
URBAN DYNAMICS WESTERN CAPE INC. 248 14.5 HOPEFIELD: (REFER PLAN 39 AND PLAN 40) FIGURE 83: LOCALITY - HOPEFIELD Within the context of the Saldanha Bay Municipal area, Hopefield, an historical agricultural
More informationPlumpton Neighbourhood Development Plan Revised Pre Submission Document - Regulation 14 Consultation
REPRESENTATIONS... Plumpton Parish Council Plumpton Neighbourhood Development Plan Revised Pre Submission Document - Regulation 14 Consultation Representations submitted on behalf of: Cala Homes (South
More informationWin 3! Basic Guidelines for Successful Roadside Ditch Management
Win 3! Basic Guidelines for Successful Roadside Ditch Management Rebecca Schneider Dept. Natural Resources Cornell University Cornell Local Roads Conference June 2, 2008 Town Highway Staff Responsibilities
More informationCommissioners Road West Realignment Environmental Assessment
City of London Commissioners Road West Realignment Environmental Assessment Public Information Centre No. 2 November 29, 2017 Welcome to the Public Information Centre This 2 nd Public Information Centre
More informationProposed FY 2004 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects
30 130 Collingswood/Pennsauken ( B) 155C Vicinity of Cooper River Bridge at Park Drive to 200 feet north of PATCO Railroad Bridge This project may provide for the construction of a proposed new bridge
More informationGUIDELINES FOR SELECTION/SCRUTINY OF ROADS AND BRIDGES PROJECTS UNDER NABARD SCHEME
GUIDELINES FOR SELECTION/SCRUTINY OF ROADS AND BRIDGES PROJECTS UNDER NABARD SCHEME 1. RURAL ROADS & BRIDGES Rural ruads are those roads which connect rural areas with the urban marketing, central highways,
More informationWELCOME TO THE PUBLIC INFORMATION CENTRE. Please Sign In
WELCOME TO THE PUBLIC INFORMATION CENTRE Replacement of Oxtongue Lake Narrows Bridge & Oxtongue River Bridge, Highway 60 (G.W.P. 93-89-00 & G.W.P. 5550-04-00) Class Environmental Assessment (Group B) Please
More informationCONFORMED AGREEMENT INCORPORATED REVISIONS PER AMENDMENT DATED: APRIL 2, 2013 FOR REFERENCE
CONFORMED AGREEMENT INCORPORATED REVISIONS PER AMENDMENT DATED: APRIL 2, 2013 FOR REFERENCE CITY STREETS AS PART OF STATE HIGHWAYS GUIDELINES REACHED BY THE WASHINGTON STATE DEPARTMENT OF TRANSPORTATION
More informationCity of Kingston. North King s Town Secondary Plan Open House + Workshop #1 February 28, 2018
City of Kingston North King s Town Secondary Plan Open House + Workshop #1 February 28, 2018 1 event agenda 30 min Panel Review + Discussion 30 min Presentation + Q&A 75 min Workshop Session 15 min Report
More informationAccess Management: An Overview
Figures 1-5 Below Evolution of development along a highway. In the early stages, land along the road is used for farming with little traffic generated. As time passes, the highway corridor becomes a de
More informationGreen Book 7 th Edition Summary of Changes. Jim Rosenow NCITE Geometric Design Committee August 30, 2018
Green Book 7 th Edition Summary of Changes Jim Rosenow NCITE Geometric Design Committee August 30, 2018 Outline 1. The drama 2. Chapter 1 rewrite 3. The rest of the book 2 Outline 1. The drama 2. Chapter
More informationTown of Vershire Road Erosion Inventory Report
Town of Vershire Road Erosion Inventory Report Taylor Valley Road. Photo taken by TRORC staff. Prepared by: 128 King Farm Road Woodstock, VT 05091 Inventory and report funded by the Vermont Agency of Transportation
More informationLABOR-BASED ROUTINE ROAD MAINTENANCE (LBRRM)
LABOR-BASED ROUTINE ROAD MAINTENANCE (LBRRM) A GUIDE TO THE PRACTICAL TASKS 1 Important Drainage Components Camber 2 THE IMPORTANCE OF DRAINAGE Keep water off the running surface and clear of the road
More informationINTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE
INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 15-Jul-2015 Report No.: ISDSCIO64 Date ISDS Approved/Disclosed: 20-Jul-2015 I. BASIC INFORMATION A. Basic Project Data Country:
More informationChapter 1 - General Design Guidelines CHAPTER 1 GENERAL DESIGN GUIDELINES
CHAPTER 1 GENERAL DESIGN GUIDELINES 1.0 INTRODUCTION This Publication has been developed to provide current, uniform procedures and guidelines for the application and design of safe, convenient, efficient
More informationCreating Complete Roadway Corridors:
Creating Complete Roadway Corridors: The AASHTO Guide to Transportation Landscape Architecture and Environmental Design NCHRP Project 15-33 Status Report AASHTO Standing Committee on Design Technical Committee
More information495/MetroWest Development Compact Plan Citizen Planner Training Collaborative Conference. March 17, 2012
495/MetroWest Development Compact Plan Citizen Planner Training Collaborative Conference March 17, 2012 Project Process Local and Regional Priority Areas Growth Scenarios Transportation Investment Categories
More informationTown of Portola Valley General Plan. Nathhorst Triangle Area Plan
Town of Portola Valley General Plan Amended December 10, 1997 Table of Contents Introduction... 1 Planning Area... 1 Objectives... 2 Principles... 2 Standards... 4 Description... 4 Community Commercial...
More informationBerkshire Regional Planning Commission Clearinghouse Review Report
August 19, 2013 SUBJECT: Reconstruction of Housatonic Street, Dalton, MA EOEA#: 15083 LOCATION: Dalton ESTIMATED COST: $8.1 million REVIEW TYPE: ENF PROPONENT: MassDOT and Town of Dalton COMMENTS DUE:
More informationCOMMUNITY DESIGN. GOAL: Create livable and attractive communities. Intent
COMMUNITY DESIGN Intent An attractive, well-designed County will attract quality development, instill civic pride, improve the visual character of the community, and create a strong, positive image for
More informationHeritage Road Improvements from Steeles Avenue to Rivermont Road
The Corporation of the City of Brampton Heritage Road Improvements from Steeles Avenue to Rivermont Road Class Environmental Assessment Study (Schedule C) September 19, 2013 The Corporation of the City
More informationChapter 10 IMPLEMENTATION RECOMMENDATIONS
Chapter 10 IMPLEMENTATION RECOMMENDATIONS The recommended land use plan presented in the previous chapter provides a design for the attainment of the urban and rural development and open space preservation
More informationWEST HILL BUSINESS PARK AREA STRUCTURE PLAN
MUNICIPAL DISTRICT OF PEACE NO. 135 WEST HILL BUSINESS PARK AREA STRUCTURE PLAN Prepared by: TABLE OF CONTENTS 1.0 Introduction... 1 1.1 Purpose of Plan........ 1 1.2 Plan Area..... 1 1.3 Existing Conditions...
More informationTERRESTRIAL NATURAL HERITAGE SYSTEM STRATEGY APPENDIX F: MODEL POLICIES FOR THE IMPLEMENTATION OF THE TARGET TERRESTRIAL NATURAL HERITAGE SYSTEM
TERRESTRIAL NATURAL HERITAGE SYSTEM STRATEGY APPENDIX F: MODEL POLICIES FOR THE IMPLEMENTATION OF THE TARGET TERRESTRIAL NATURAL HERITAGE SYSTEM C H A P T E R 1 M O D E L P O L I C I E S F O R I M P L
More informationInform you of the purpose and scope of the study for PTH 100 and a proposed future St. Norbert Bypass;
WELCOME The intent of today s Open House is to: Inform you of the purpose and scope of the study for PTH 100 and a proposed future St. Norbert Bypass; Review highway crossing locations, future access closures
More informationBostwick Road. Municipal Class Environmental Assessment. October 13, City of London. Bostwick Road Municipal Class Environmental Assessment
Bostwick Road Municipal Class Environmental Assessment October 13, 2016 Welcome! Welcome to the first Public Information Centre for the Bostwick Road Municipal Class Environmental Assessment. Representatives
More informationAppendix G Response to Comments
Appendix G Response to Comments This appendix contains the comments received during the public circulation and comment period (May 27, 2008 to July 11, 2008). The comments have been numbered (Comment Set
More informationCA.1 Coastal Area. Index. CA.1.1 Description and Expectations
Index.1.2.3.4 CA.2 CA.2.1 CA.2.2 CA.2.3 CA.3 CA.3.1 CA.3.2 CA.3.1 CA.4 CA.4.1 CA.4.2 CA.4.3 CA.4.4 CA.5 CA.5.1 CA.5.2 Description and Expectations Objectives Policies Guidance Note Landuse Eligibility
More informationREZONING GUIDE. Zone Map Amendment (Rezoning) - Application. Rezoning Application Page 1 of 3. Return completed form to
Zone Map Amendment (Rezoning) - Application COMMUNITY PLANNING & DEVELOPMENT REZONING GUIDE Rezoning Application Page 1 of 3 PROPERTY OWNER INFORMATION* CHECK IF POINT OF CONTACT FOR APPLICATION Property
More informationSettlement Boundaries Methodology North Northumberland Coast Neighbourhood Plan (August 2016)
Introduction This background paper sets out a methodology for the definition of settlement boundaries in the North Northumberland Coast Neighbourhood Plan. The neighbourhood plan is planning positively
More informationDigital Terrestrial Television Infrastructure Rollout. Environmental Impact Assessment - Kongola -
Digital Terrestrial Television Infrastructure Rollout Environmental Impact Assessment - Kongola - 1 1 ENVIRONMENTAL IMPACT ASSESSMENT: KONGOLA 1.1 RATIONALE FOR THE SITE Kongola is situated in the Caprivi
More informationEXHIBIT A. Tax Increment Reinvestment Zone No. 1 (Town Center) First Amended Project Plan 1
EXHIBIT A Tax Increment Reinvestment Zone No. 1 (Town Center) First Amended Project Plan 1 1 As amended by Resolution No. 2008-02-001(TR1R) of the Tax Increment Reinvestment Zone No.1, and approved to
More informationFostering metropolitan cooperation for sustainable urban development THE MONTRÉAL DECLARATION ON METROPOLITAN AREAS
Fostering metropolitan cooperation for sustainable urban development THE MONTRÉAL DECLARATION ON METROPOLITAN AREAS October 7, 2015 This document has not been proofread 2 Fostering metropolitan cooperation
More informationHighway 427 Industrial Secondary Plan Area 47 Schedule C Class Environmental Assessment For Arterial Roadways
Welcome to Pubic Information Centre #1 Highway 427 Industrial Secondary Plan Area 47 Schedule C Class Environmental Assessment For Arterial Roadways Welcome to Open House # 1 Tonight, we invite you to.
More informationNational initiatives in the field of Urban Sustainability to enhance local government role in the compliance with the ODS and the AICHI goals
5 TH GLOBAL BIODIVERSITY SUMMIT FOR CITIES AND SUBNATIONAL GOVERNMENTS Official parallel event to the Convention on Biological Diversity s 13 th Conference of the Parties 10 11 December 2016, The Moon
More informationGEOMETRIC IMPROVEMENTS AND WATERMAIN LOOPING MUNICIPAL CLASS ENVIRONMENTAL ASSESSMENT
GEOMETRIC IMPROVEMENTS AND WATERMAIN LOOPING MUNICIPAL CLASS ENVIRONMENTAL ASSESSMENT Veterans Way (previously Powerline Road) and Klondike Park Road Wasaga Beach Welcome Please sign in Take a comment
More informationSri Lanka Strategic Cities Development Project-Additional Financing (P157427) Environment Management Framework
Public Disclosure Authorized Executive Summary-Environmental Assessment & Management Framework - SCDP Sri Lanka Strategic Cities Development Project-Additional Financing (P157427) Environment Management
More informationTown of Oakville Name of public meeting/open house etc. Info. Session. Palermo Village Growth Area Review
Town of Oakville Name of public meeting/open house etc. Info. Session Palermo Village Growth Area Review Town of Oakville Name Official of Plan public Review meeting/open house etc. What is an Official
More informationAPPENDIX G: TOWN ORDINANCE REVIEW
APPENDIX G: TOWN ORDINANCE REVIEW TYLin (225740) Woodard & Curran SWMP January 2013 Stormwater LID strategies, ranked for Zoning Bylaw and Site Plan Review Standards Dimensional Requirements Permit the
More informationRochford District Council Allocations Development Plan Document: Discussion and Consultation Document Sustainability Appraisal
Option SWH1 Balanced Communities Option SWH1 1 To ensure the delivery of high quality sustainable communities where people want to live and work Will it ensure the phasing of infrastructure, including
More informationDigital Terrestrial Television Infrastructure Rollout. Site-specific Environmental Management Plan - Omega -
Digital Terrestrial Television Infrastructure Rollout Site-specific Environmental Management Plan - Omega - 2 1 ENVIRONMENTAL IMPACT ASSESSMENT: OMEGA 1.1 RATIONALE FOR THE SITE Omega is situated in the
More informationVisual Impact Rating Form - Instructions
Visual Impact Rating Form Instructions Project Name: Baron Winds Project EDR Project No: 13039 Date: 05.16.17 Reference: Visual Impact Rating Form - Instructions These instructions are intended to guide
More informationMcKay Road Interchange and Salem / Lockhart Crossing
McKay Road Interchange and Salem / Lockhart Crossing The McKay Road Interchange Class EA has two components: 1. A new MacKay Road Interchange at Highway 400; and 2. A new bridge crossing of Highway 400
More informationWelcome to our exhibition
Welcome to our exhibition The Homes & Communities Agency (HCA) welcomes you to this public exhibition explaining our proposals for the redevelopment of the former Lea Castle Hospital site. About the Homes
More informationRoadside Mowing. Spot mowing of noxious weeds should be done as necessary to reduce propagation.
Public Works Department Road and Bridge Division Roadside Mowing 1.0 Policy The primary purpose for planting and maintaining a vegetative cover on roadside areas is to prevent erosion of the soil. It is
More informationSuffolk Coastal Local Plan Review Issues and Options, August 2017, Public Consultation
Suffolk Coastal Local Plan Review Issues and Options, August 2017, Public Consultation Having reviewed the issues and options documents, the Society has made the following response: Part 1 - Strategic
More informationObservations Regarding of Environmental Issues on DPRs for Rural Roads Under CMGSY-MPRCP
Observations Regarding of Environmental Issues on DPRs for Rural Roads Under CMGSY-MPRCP 1. DPR for Navegaon to Pathkheda in Chhindwara Block of Chhindwara District, Consultant : IDC On perusal of DPR,
More informationExhibit A. 8:9 Scuffletown Rural Conservation District
Exhibit A 8:9 Scuffletown Rural Conservation District 8:9.1 Intent and Purpose The Scuffletown Rural Conservation (SRC) District is intended to provide for residential development that supports the development
More informationTransportation Research Center
Increasing Design Flexibility in the AASHTO Green Book Your Department Name Presentation to AASHTO Subcommittee on Design Doug Harwood, MRIGlobal July 2017 Transportation Research Center Resolution of
More informationPlanning Primer Legislative Background, Policy Documents and Development Review Processes. Presented by: Planning Services Date: April 6, 2017
Planning Primer Legislative Background, Policy Documents and Development Review Processes Presented by: Planning Services Date: April 6, 2017 Agenda Legislative Background 7:30 to 8:00 pm Questions 8:00
More informationWELCOME TO OPEN HOUSE TWO November 28, 2018
Langstaff Road Weston Road to Highway 7 Class Environmental Assessment Study WELCOME TO OPEN HOUSE TWO November 28, 2018 Please sign in and join our mailing list Study Overview York Region is conducting
More informationDuPage Mayors and Managers Conference June 21, 2013 TRANSPORTATION PROGRAM (STP) WORKSHOP
DuPage Mayors and Managers Conference June 21, 2013 TRANSPORTATION PROGRAM (STP) WORKSHOP Lombard Village Hall Marilin Solomon, P.E. Field Engineer West Division (Central & North Central Cook County, DuPage
More informationAMENDMENT NO. 30 TO THE OFFICIAL PLAN OF THE TOWN OF MILTON
AMENDMENT NO. 30 TO THE OFFICIAL PLAN OF THE TOWN OF MILTON Subject: Boyne Survey Secondary Plan and Related Official Plan Amendments The following text and schedules constitute Amendment No. 30 to the
More informationSection 3b: Objectives and Policies Rural Environment Updated 19 November 2010
Page 1 of Section 3b 3b RURAL ENVIRONMENT 3b.1 Introduction The Rural Environment comprises all the land outside of the Residential, Town Centre and Industrial Environments. Most land within the District
More information