TREMONT NAIL FACTORY. First Public Presentation. March 9, 2017
|
|
- Hester Hardy
- 5 years ago
- Views:
Transcription
1 TREMONT NAIL FACTORY First Public Presentation March 9, 2017
2 Agenda Project Team Project Process Existing Conditions Stakeholder Input Preliminary Thoughts Discussion
3 Project Team
4 Project Team Town of Wareham MassDevelopment Kenneth Buckland, AICP, Director of Planning & Community Development Derek Sullivan, Town Administrator Peter W. Teitelbaum, Esq., Clerk, Wareham Board of Selectmen Edward Starzec, Director, Land Entitlements & Master Planning Laura Barrett, Project Manager, Real Estate Union Studio Jeremy R. Lake, AIA, Senior Associate Joel VanderWeele, Architectural Designer Peregrine Group Eric J. Busch, Principal Horsley Witten Joseph E. Longo, Principal, Senior Engineer
5 Union Studio was founded in 2001 with one overriding goal: to use our skills as architects and urban designers to make a civic contribution to communities of all types.
6 We specialize in Community Design Architectural Design Civic Architecture Sustainable Design from a Holistic Perspective Design Guidelines Design Charrettes
7 Why are we here?
8 Sandwich, MA Goal: Capitalize Value of Local Amenity to Leverage Value of Town Owned Land to Promote Mixed Use Development that Creates Additional Use for Area
9 Newburyport, MA Goal: Capitalize Value of Local Amenity to Leverage Value of Town Owned Land to Promote Mixed Use Development that Draws Additional Users to Area while Generating Funds to Help Offset Long Term Maintenance Costs
10 Orange, MA Goal: Capitalize Value of Local Amenities to Promote Mixed Use Redevelopment as Catalyst for Town Renewal
11 Village of Three Rivers, MA Goal: Capitalize Value of Local Amenity and Create Needed Connections to Promote Mixed Use Redevelopment as Catalyst for Town Renewal
12 Why are we here? Goal: Capitalize Value of Local Amenities and Create Needed Connections to Promote Mixed Use Redevelopment that Draws Additional Users to Area while Generating Funds to Help Offset Stabilization/Renovation/Maintenance Costs while Respecting the Character of the Historic Structures
13 Project Process
14 Project Process Pre-Design December Visit Site and Review Overall Objectives, Opportunities and January 2017 Constraints with Project Team Stakeholder Input February 2017 Meet with Local Business Owners, Board Members and Town Officials to Gather Input First Public Presentation March 9, 2017 Preliminary Concepts/Feasibility Analysis March 2017 Study a range of options based on stakeholder and public input, review market, regulatory and physical feasibility Vision Plan/Recommendations April 2017 Generate vision plan for the site based on preferred concept including steps towards implementation Second Public Presentation Final Report TBD TBD
15 Existing Conditions
16 Project Location Project Site
17 Project Location Project Site Center Park Besse Park
18 Project Location WCTV (Old Town Hall) Fearing Tavern Day Care Historical Society Buildings Churches Proposed Senior Housing Church Proposed Cranberry Museum
19 Existing Conditions
20 Existing Conditions
21 Existing Conditions 7.2 Acre Site 48,000 sf in 8 Buildings Acquired by Town in 2004 with Community Preservation Act Funds Buildings in Fair Condition
22 Existing Conditions Factory Building Built Must be Retained
23 Existing Conditions Freight Building Built 1848 Must be Retained
24 Existing Conditions Office Building Built 1848 Addition 1979 Must be Retained
25 Existing Conditions Freight Shed Built 1900 May be Retained or Removed Restroom Building Built 1953 May be Retained or Removed Packaging Building Built 1957 May be Retained Pickling Building or Removed Built 1896 May be Retained or Removed
26 Existing Conditions Steel Building Built 1976 May be Removed
27 Existing Conditions Fish Ladder/Flume Parkers Mill Dam
28 Existing Conditions Public Kayak Launch The Yard
29 Existing Conditions
30 Existing Conditions Wetlands
31 Existing Conditions Wetlands
32 Existing Conditions New Construction Allowed at Current Elevation New Construction Allowed if Raised Above Flood Plain New Construction Not Allowed, Renovation Possible Wetlands
33 Stakeholder Input
34 Stakeholder Input Series of discussions over the past month with: Town Officials: Kenneth Buckland Director of Planning & Community Development, Town of Wareham Derek Sullivan Town Administrator, Town of Wareham Peter Teitelbaum Wareham Board of Selectmen David Riquinha Director of Inspection Services, Town of Wareham David Pichette Conservation Administrator, Town of Wareham Local Business Owners, Residents and Commission Members: Roy C. Edwards & Michael Dozier Nemasket Kayak Center (rentals on site this Spring!) Marie Oliva Cape Cod Canal Region Chamber of Commerce Traci Medeiros Gallery Consignment Shoppe Johanna Rowley Architect, Preservationist, Professor Angela Dunham Historical Commission, Historical Society Anthi Frangiadis Architect, Former Planning Board Member Linda Burke VP of Marketing & Communication, A.D. Makepeace
35 Stakeholder Input Key Takeaways: Historical Significance: Site/Buildings are listed on National Register of Historic Places but not currently in a local historic district Tremont Nail Factory represents a significant element of Wareham s history Very rare to find structures of this age (150 years+) and size (large) in this condition (still standing, not burned down) Site Regulations: Existing buildings within the 200 river setback can be renovated but only in increments based on 50% of assessed structural value Development is possible within wetland setbacks where there is existing disturbance Site was rezoned from Industrial to Wareham Village 1 to promote sympathetic reuse: The Village Districts are intended to promote compact, mixed-use development that preserves Wareham's historic character and promotes small-scale business uses. A. Wareham Village 1 (WV1):The WV1 district is intended to promote business and residential development in Wareham Village that provides a stable economic base, protects the Village's historic buildings, fosters re-use of existing buildings, and promotes visual connections to the waterfront.
36 Stakeholder Input Key Takeaways: Challenges: Dam/Bridge closure restricts vital access to the site Site does not have direct access to adjacent, major roadways (Cranberry Highway, Main Street) but does have visibility Signage will be crucial, creative challenge to be within regulations and respectful of site Site requires a lot of work ($$$) in terms of short term stabilization (seepage, structural needs), medium term renovation and long term maintenance New uses/construction will need to be sensitive to regulatory issues and periodic flooding Train runs by site (trash train year round, Cape Flyer seasonably) noise considerations Opportunities: Beautiful site with rich history, views and river access (including public boat launch) should attract use New development/uses can help offset costs, add to the local tax base, provide jobs and opportunities for new business, and bring attention/appreciation to site s history Redeveloped site can serve as anchor to northern portion of Wareham s core Redeveloped site could support a mix of uses sympathetic to surrounding uses Local historical organizations (Historic District Commission, Historical Commission, Historical Society) in place and proximate to help promote historical significance Train runs by site (Cape Flyer provides seasonal visibility)
37 Stakeholder Input Key Takeaways: Potential Uses: Cultural Uses Preserve main Factory Building space highlight industrial artifacts and building s construction Museum about Tremont Nail Factory Educational uses classrooms, historical signage, archeology Support connection to surrounding historic properties/museums Event / music venue / exhibition space Outdoor areas for festivals/farmers market and picnic areas (Antique Fair Car Show on site this summer!) Retail Uses Paddleboat rentals and sales taking advantage of public ramp Cafés/Restaurants/Microbreweries Limited amount of art gallery / studio space Residential Uses Affordable senior housing Market rate rental housing Which one makes the most sense? All of the above!
38 Preliminary Thoughts
39 Existing Conditions New Construction Allowed at Current Elevation New Construction Allowed if Raised Above Flood Plain New Construction Not Allowed, Renovation Possible Wetlands
40 Preliminary Thoughts Restroom Building: Restrooms for Events Office Building: Education/Museum, Retail, Office or Residential Use Factory Building: Main Space Preserved, Event Space/ Music Venue Ells Education/Museum or Retail Use Pickling Building: Retail or Gallery Space New Construction (Residential?) Parking/ Access Picnic Area Packaging Building: Retail or Gallery Space Freight Building: Main Space Preserved, Event Space North Ell Retail Use Freight Shed: Storage Open Space Kayak Launch Connection to Merchant s Way
41 Discussion courb.co/tnf Visit the project page at this short web address on desktop or mobile You can learn about the new project information, see the timeline and stay in the loop as the project moves forward on courbanize We ll post all the information about new plans, meetings, and milestone events here There are 2 ways you can participate 1) add comments or questions here - all comments go right to the project team and we ll respond directly 2) Follow to subscribe get project updates from the development team by
Methuen Technical Assistance Panel, June 18, 2015! City of Methuen, Massachusetts!
Methuen Technical Assistance Panel, June 18, 2015 City of Methuen, Massachusetts Methuen Technical Assistance Panel, June 18, 2015 About ULI the Urban Land Institute Mission To provide leadership in the
More informationSouth of Eastern Strategic Direction Status Update
STAFF REPORT ACTION REQUIRED South of Eastern Strategic Direction Status Update Date: July 10, 2014 To: From: Planning and Growth Management Committee Chief Planner and Executive Director, City Planning
More informationPublic Open House. Overview of the Downtown Plan Official Plan Amendment April 23, 2018
Public Open House Overview of the Downtown Plan Official Plan Amendment April 23, 2018 1 A 25-Year Plan for Downtown To ensure growth contributes positively to Toronto s Downtown as a great place to live,
More informationMAYFIELD WEST SECONDARY PLAN PHASE 2
MAYFIELD WEST SECONDARY PLAN PHASE 2 Public Open House #3 February 25, 2010 Draft Preferred Land Use Scenario TOWN OF CALEDON PLANNING & DEVELOPMENT DEPARTMENT Open House Agenda TOWN OF CALEDON 1. Welcome
More informationLINCOLN COUNTY COMMONS - REVISED MASTER PLAN. Lincoln County Public Meetings June 26-27, 2018, 6pm
LINCOLN COUNTY COMMONS - REVISED MASTER PLAN Lincoln County Public Meetings June 26-27, 2018, 6pm PROJECT OVERVIEW Lincoln County is preparing a Refined Master Plan for facilities at the Lincoln County
More informationPUBLIC WORKSHOP. Re-use of the Josiah Smith Tavern and Old Library. December 14, 2010
PUBLIC WORKSHOP Re-use of the Josiah Smith Tavern and Old Library Professional Team: The Cecil Group, Inc Peter W. Smith, Inc. Howard/Stein-Hudson Associates December 14, 2010 AGENDA Introductions The
More informationMASTER PLAN for the EARL NEWHOUSE WATERFRONT
MASTER PLAN for the EARL NEWHOUSE WATERFRONT on RESERVOIR POND - CANTON, MA Community Meeting #2 - Thursday, January 11 th PROJECT INTRODUCTION Project Goals: To prepare a MASTER PLAN which develops the
More informationTHE COMMUNITY-DRIVEN DESIGN PROCESS
THE COMMUNITY-DRIVEN DESIGN PROCESS A PUBLIC DRIVEN PROCESS STEERING COMMITEE THE COMPREHENSIVE PLAN OPPORTUNITIES AND CONSTRAINTS THE COMMUNITY DRIVEN DESIGN PROCESS A Public Driven Process Beginning
More informationBourne Downtown Site Planning
Prepared for: The Town of Bourne, MA In Cooperation with: Bourne Financial Development Corporation Prepared by:, Inc. June 24, 2009 Table of Contents Introduction and Summary... 1 Site Existing Conditions...
More informationINDEPENDENCE BOULEVARD AREA PLAN. June 24, 2008
INDEPENDENCE BOULEVARD AREA PLAN Public Meeting #1 June 24, 2008 Tonight s Agenda Introduction Welcome and Ground Rules Overview Presentation Purpose of the Plan What Brings Us Here? A Tour of the Corridor
More informationPlanning for Waterfront Communities
Planning for Waterfront Communities Redevelopment Ready Communities Supplemental Training Program OFFICE OF THE GREAT LAKES Waterfront Community Best Practices and Guidelines New supplemental criteria
More informationTOWN COUNCIL / PLANNING COMMISSION
Workshop #3 TOWN COUNCIL / PLANNING COMMISSION January 20, 2011 Consultant Team In Attendance Tonight BMS Design Group Nevada City and San Francisco Michael Smiley, AICP, ASLA Partner-in-Charge Nancy L.
More informationPresentation of the Staff Draft. July 17, 2014 SSRVP Team, Area 3
Presentation of the Staff Draft July 17, 2014 SSRVP Team, Area 3 Presentation Overview Introduction Plan Framework Plan Recommendations Implementation Next Steps and Request for Public Hearing on September
More informationARISE: The Rock Renaissance Area Redevelopment & Implementation Strategy
2014 Professional Awards 1 ARISE: The Rock Renaissance Area Redevelopment & Implementation Strategy Janesville, WI Completed December 2014 Analysis & Planning Purpose of Project 2 The purpose of the Rock
More informationMill Conversion Overlay District Zoning Bylaw Amendment
Mill Conversion Overlay District Zoning Bylaw Amendment To see if the Town will vote to amend the Zoning By-Law by adding a new Section 13, Mill Conversion Overlay District, and by amending Sections 2.1,
More informationTown Center (part of the Comprehensive Plan)
Town Center (part of the Comprehensive Plan) Mercer Island Town Center Looking North (2014) In 1994, a year-long process culminated in a set of design guidelines and code requirements for the Town Center
More informationMaster Plan Implementation Committee Meeting
MILTON VILLAGE ZONING AND WATERFRONT STUDY Master Plan Implementation Committee Meeting February 12, 2018 7:00-9:00 pm IMAGE: GOOGLE COMPILED MEETING FEEDBACK/SURVEY RESULTS Waterfront Principles - Prioritized
More informationHighland Falls Waterfront Redevelopment Feasibility Study Village Board Meeting March 20, 2017
Village Board Meeting March 20, 2017 Agenda I. Public Meeting #1 Visioning Summary II. Public Meeting #2 Comment Summary III. IV. IV. Case Study: Milton Train Station Schematic Design Concepts Schedule/Next
More informationBrice Prairie Master Plan
Brice Prairie Master Plan Town of Onalaska Community Meeting #1 Sand Lake Elementary School January 28, 2006 9 am 11 am Agenda Background What is a Master Plan? Brice Prairie Capacity Reports Starter Ideas
More informationPLAN ELEMENTS WORKSHOP. April 5, 2016
PLAN ELEMENTS WORKSHOP April 5, 2016 needs more housing. But there is no one-size fits-all solution. Every neighborhood has its own character. In some places, density is not only appropriate it is badly
More informationDRAFT ROOSEVELT ROAD. District Recommendations. Figure 5.23 The Roosevelt Road Corridor
CHAPTER 5 Figure 5.23 The Road Corridor Road will develop as a mixed-use corridor, emphasizing regional retail, west of the river and mixed-use development east of the river. KEY RECOMMENDATIONS 1. High
More informationMarket Demand and Land Use
Market Demand and Land Use Summary 57 Challenges 60-61 Guiding Principles 62 Strategy and Implementation 63-69 Establish a mix of uses that contribute to a vibrant downtown. 58 Summary Historically, downtown
More informationGloucester County s Comprehensive Plan. The Community Connection
Gloucester County s Comprehensive Plan The Community Connection Current Comp Plan Adopted in 1991 with a 20 year planning horizon Updated in 1995 with Part V- Implementation Recommendations and Appendix
More informationRIVERFRONT REDEVELOPMENT PLAN
RIVERFRONT REDEVELOPMENT PLAN PROJECT BACKGROUND DEVELOPMENT OPPORTUNITIES This project strives to connect St. Francisville s downtown Historic District to the Mississippi River through river tourism,
More informationPreliminary Plan Framework: Vision and Goals
Preliminary Plan Framework: Vision and Goals Draft: May 2015 Introduction Since the Town of Milliken s comprehensive plan was last updated in 2010, the community was heavily impacted by the 2013 flood,
More informationShip Creek Redevelopment
Ship Creek Redevelopment Three Concepts May 2013 Cambridge ARCHITECTURE Philadelphia ENGINEERING Raleigh INTERIORS San Francisco PLANNING Washington, DC www.klingstubbins.com contact@klingstubbins.com
More informationLAND USE ELEMENT. Purpose. General Goals & Policies
LAND USE ELEMENT Purpose This Land Use Element contains the goals and policies necessary to support the City s responsibility for managing land resources and guiding development through implementing regulations,
More informationChapter 6. Overall Vision RECOMMENDATIONS. More Trail and Trail. Connections. Equal Access to Park. Facilities and Programs. Water Access.
Overall Vision More Trail and Trail Connections Equal Access to Park Facilities and Programs Water Access Environment Variety Chapter 6 RECOMMENDATIONS Chapter 6 The following recommendations for park,
More informationWaterfront West December 6, 2016
1 Waterfront West December 6, 2016 Agenda 1. Development Team 2. Waterfront History As Our Guide. A Compelling Site Idea 4. Community Benefits 5. Zoning 6. Architectural Context 7. Project Renderings 8.
More informationPlease read the entire document
projects impacting the waterfront revitalization area. The waterfront revitalization area of the town will have to subareas to the west and east of the village. Page 6 of 6 Wayfinding master plan create
More informationTown of Peru Comprehensive Plan Executive Summary
Town of Peru Comprehensive Plan Executive Communities that plan grow by choice, not by chance. A plan makes growth thoughtful, understandable, and predictable. A plan shows that a community is managing
More informationExamples of Asset Based Approaches to Development. Economic and Community Development Suffield, CT
Examples of Asset Based Approaches to Development Presented by: Patrick McMahon, Director of Economic and Community Development Suffield, CT Neighborhood Commercial Development Wilson, CT Issues Elevated
More informationVIRGINIA KEY CONSENSUS MASTER PLAN
VIRGINIA KEY CONSENSUS MASTER PLAN JULY 2010 Existing Conditions JULY 2010 STAKEHOLDER INTERVIEW PROCESS, January 18-22, 2007 PUBLIC MEETING #1: SITE INVENTORY AND ANALYSIS, March 29, 2007 PUBLIC MEETING
More informationMAYFIELD WEST SECONDARY PLAN PHASE 2
MAYFIELD WEST SECONDARY PLAN PHASE 2 Council Information Workshop February 16, 2010 Draft Preferred Land Use Plan TOWN OF CALEDON PLANNING & DEVELOPMENT DEPARTMENT Workshop Agenda TOWN OF CALEDON 1. Welcome
More informationSARANAC LAKE VISION CONCEPTS
DRAFT SARANAC LAKE VISION CONCEPTS A GENUINE PLACE TO LIVE, WORK, SHOP AND EXPERIENCE CULTURE IN THE HEART OF THE ADIRONDACKS PHOTO COURTESY OF SARANAC LAKE SARANAC LAKE, NEW YORK DECEMBER 2007 SARANAC
More informationDwelling Units Max 12 dwelling units per acre/min 8 dwelling units per acre. Development Mix 80% non residential/20% residential
13. OSTEEN LOCAL PLAN Background: The Osteen Local Plan area is located in southwest Volusia County along the SR 415 corridor between Lemon Bluff Road and Acorn Lake Road and includes 3,990 acres. The
More informationMEETING PURPOSE AND OVERVIEW
MEETING PURPOSE AND OVERVIEW On February 23, 2012, the City of Elk Grove hosted the first of two community workshops related to the Southeast Policy Area. The workshop was held from 6:00 8:30 p.m. in the
More informationEXHIBIT A. Tax Increment Reinvestment Zone No. 1 (Town Center) First Amended Project Plan 1
EXHIBIT A Tax Increment Reinvestment Zone No. 1 (Town Center) First Amended Project Plan 1 1 As amended by Resolution No. 2008-02-001(TR1R) of the Tax Increment Reinvestment Zone No.1, and approved to
More informationWhat Pioneer Grove Will Look Like?
The City of Deerfield Beach has embarked on a journey to create a new town center within the old heart of Deerfield Beach. The new town center is known as Pioneer Grove. Pioneer Grove will be Everybody
More informationTHE TOWN OF WASAGA BEACH
THE TOWN OF WASAGA BEACH Downtown Development Master Plan Committee of the Whole Presentation January 26 th 2017 Uses within this designation should reflect a dependence on tourism as opposed to the permanent
More informationDanvers High Street I-1 District Study
Danvers High Street I-1 District Study Presentation of Final Recommendations Planning Board Presentation June 26 th, 2018 1 Introductions Metropolitan Area Planning Council Sam Cleaves AICP, Principal
More informationJodie Milkman, Vice President for Communications, Delaware River Waterfront Corporation (o) , (c) ,
NEWS RELEASE CONTACTS: Jodie Milkman, Vice President for Communications, Delaware River Waterfront Corporation (o) 215 629-3216, (c) 267-228-2004, jmilkman@drwc.org Anusha Alikhan, Director of Communications,
More information1. Parks & Recreation Neighborhood Parks Community Parks Special Use Sites 2. Open Space 3. Trails
Appendix A: Park Classifications The intent of parks and recreation classifications is to aid in making acquisition and design decisions for park sites, facilities and the organization of recreation space
More informationI-84 Hartford Project Open Planning Studio #12. April 25, 2017
I-84 Hartford Project Open Planning Studio #12 April 25, 2017 Meeting Agenda 1. I-84 Hartford Project alternatives update 2. Multimodal station area planning 3. I-84 / I-91 Interchange Study coordination
More informationU T D N o r t h C a m p u s T O D and D o w n t o w n D e n t o n T O D
U n i v e r s i t y o f T e x a s a t D a l l a s C i t y o f R i c h a r d s o n U T D N o r t h C a m p u s T O D and D o w n t o w n D e n t o n T O D Rick Leisner, AICP Assistant Director of Development
More informationThe Auburn Plan Designing the Future of Auburn February 28, 2005
The Auburn Plan Designing the Future of Auburn February 28, 2005 Block-by-Block Bicycle Tour Aerial survey Focus Group Meetings September 7 and 8 Design Workshops October 11, 14, and 21 Revitalization
More informationLEED-ND 101: Practical Strategies for Achieving Sustainability Goals. Travis Parker Lakewood Planning Director
LEED-ND 101: Practical Strategies for Achieving Sustainability Goals Travis Parker Lakewood Planning Director Metro Vision Idea Exchange Oct 11, 2012 West Corridor Stations West Corridor Overview West
More informationCONSULTING SERVICES FOR THE WHITEBELT VISIONING EXERCISE ADDENDUM TO THE GTA WEST LAND USE STUDY WORK PROGRAM
CONSULTING SERVICES FOR THE WHITEBELT VISIONING EXERCISE ADDENDUM TO THE GTA WEST LAND USE STUDY 1. Introduction WORK PROGRAM The Town of Caledon is a large, local municipality located in the Greater Toronto
More informationDowntown Elkton Station Area Plan, Elkton, MD. Difficult enough to get support for new starts challenge to fund Houston transit
Difficult enough to get support for new starts challenge to fund Houston transit More difficult to build Community Support for dense development at station areas Major Concerns: Traffic, Property values,
More informationS A C R A M E N T O C O U N T Y JACKSON HIGHWAY & GRANT LINE EAST VISIONING STUDY
JACKSON HIGHWAY & GRANT LINE EAST S A C R A M E N T O C O U N T Y P L A N N I N G D E P A R T M E N T SUMMARY AND WORKBOOK November 19, 2008 History of the Visioning Study Sacramento County has two growth
More informationCONTEXT: the Highway, the River + the Railroads run through us.
CONTEXT: the Highway, the River + the Railroads run through us. I-25 36 In the past they have divided us, now we have an opportunity to unite us. I-76 I-270 I-76 CSU I-25 LEGEND Cut + Cover River North
More informationDevelopment Solicitation Request for Qualifications. The Historic Hollering Place Development
City of Coos Bay Urban Renewal Agency Development Solicitation Request for Qualifications The Historic Hollering Place Development For More Information Contact: Eric Day Community Development Director
More informationTown of Westport. Design Guidelines Development Committee Public Informational Presentation
Town of Westport Design Guidelines Development Committee Public Informational Presentation 12.18.2018 Introduction / Overview The Town of Westport s Design Guidelines have been developed to guide the appearance,
More informationSTUDY AREA. Tonight s Agenda. Project Tasks Completed. Next Steps. Town of Oyster Bay Eastern Waterfront Community Vision & Revitalization Plan
Town of Oyster Bay Eastern Waterfront Community Vision & Revitalization Plan Public Meeting January 27, 2009 Opening Remarks Presentation Tonight s Agenda Introduction Study Area Overview Public Participation
More informationSupport the implementation of Cape Coral's Comprehensive Plan. Protect and utilize the unique natural resources in the City.
7.0 OVERVIEW - RECOMMENDATIONS Chapter 7 The preparation of the Cape Coral Parks and Recreation Master Plan spanned a period of approximately 12 months. Plan preparation included the input of a wide range
More informationCITY OF BIDDEFORD PLANNING DEPARTMENT PLANNING BOARD REPORT. Larry Patoine, Chair & Members of the Biddeford Planning Board
CITY OF BIDDEFORD PLANNING DEPARTMENT 2016.25 Greg D. Tansley, A.I.C.P. 205 Main Street PO Box 586 (207) 284-9115 gtansley@biddefordmaine.org PLANNING BOARD REPORT TO: Larry Patoine, Chair & Members of
More informationULI Boston Technical Assistance Panel (TAP) Program. Downtown Hyannis
ULI Boston Technical Assistance Panel (TAP) Program Downtown Hyannis ULI the Urban Land Institute Mission To provide leadership in the responsible use of land and in creating and sustaining thriving communities
More informationChapter 1.0 Introduction
Chapter 1.0 Introduction 1.1 Background The North Metro commuter rail line is part of the RTD FasTracks regional transit system expansion program to build more than 100 miles of rail transit throughout
More informationSecrest Short Cut and Monroe Expressway Small Area Plan AUGUST 29, 2018
Secrest Short Cut and Monroe Expressway Small Area Plan AUGUST 29, 2018 Background and Process Monroe Expressway will be open by the end of 2018 Union County and Indian Trail identified a need to revisit
More informationPort Marigny TND Planning and Zoning Commission Workshop September 1, 2015 Preliminary Observations - David Bailey, AIA, AICP
Planning and Zoning Commission Workshop September 1, 2015 Preliminary Observations - David Bailey, AIA, AICP Outline, per 8-27-15 Memorandum: 1. Background 2. General Observations 3. Comprehensive Plan
More informationEconomic Redevelopment of Underutilized Parcels. May 16, 2012 Northland Arboretum Brainerd, Minnesota
Economic Redevelopment of Underutilized Parcels May 16, 2012 Northland Arboretum Brainerd, Minnesota Matt Glaesman City of St. Cloud Community Development Director 1. A Tradition of Change 2. Why Now?
More informationPreliminary Sketch Plan for Fort Hunter Park
Preliminary Sketch Plan for Fort Hunter Park Public Presentation November 19, 2009 Dauphin County Parks and Recreation 100 Fort Hunter Road Harrisburg, PA 17110 (717) 599-5188 www.dauphinc.org THOMAS COMITTA
More informationNorthwest Rail Corridor and US 36 BRT Development Oriented Transit Analysis 4.4 STATION AREA FINDINGS
4.4 STATION AREA FINDINGS Each station is different, and each one requires a separate set of recommendations based on the vision for the site. This section outlines an initial TOD strategy and recommendations
More informationBURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE PUBLIC MEETING 3/26/18
BURTON STATION STRATEGIC GROWTH AREA PLAN UPDATE PUBLIC MEETING 3/26/18 1 WHERE WE ARE? 2 PRIMARY OBJECTIVES OF THE PLAN UPDATE 1. Update the land use designation for Burton Station Village to reflect
More informationHopkins. Development Guidelines May Overview. Sponsored by: Blake Road Corridor Collaborative City of Hopkins
Hopkins Blake Road LRT Station Area Development Guidelines May 2015 Sponsored by: Blake Road Corridor Collaborative City of Hopkins Overview Hopkins is a dynamic community of over 17,000 residents located
More informationSECTION II SECTION II STATEMENT OF GOALS, OBJECTIVES, PRINCIPLES, ASSUMPTIONS, POLICIES AND STANDARDS
STATEMENT OF GOALS, OBJECTIVES, PRINCIPLES, ASSUMPTIONS, POLICIES AND STANDARDS 1 2 STATEMENT OF GOALS, OBJECTIVES, PRINCIPLES, ASSUMPTIONS, POLICIES AND STANDARDS INTRODUCTION The New Jersey Municipal
More informationLUNDY S LANE COMMUNITY IMPROVEMENT PLAN STUDY
PUBLIC INFORMATION MEETING #2 October 12, 2016 LUNDY S LANE COMMUNITY IMPROVEMENT PLAN STUDY AGENDA 5:00 to 5:30pm: Open House 5:30 to 6:15pm: Presentation 6:15 to 7:00pm: Individual paced workshop with
More informationListening Sessions: Guiding Principles and Unified Development Code New Castle County, Delaware
Listening Sessions: Guiding Principles and Unified Development Code New Castle County, Delaware March 2015 AGENDA Introduction: Who We Are Work Program and Schedule Guiding Principles Discussion Project
More informationWindsor Locks Transit-Oriented Development Planning Grant Request. Project Background
Windsor Locks Transit-Oriented Development Planning Grant Request Project Background Downtown Windsor Locks runs along Main Street in the vicinity of the intersection of Routes 159 and 140. The current
More informationDowntown Dubuque...it s a great time.
Downtown Dubuque...it s a great time. Your timing could not be better to invest in Downtown. With hundreds of millions in public and private investment occurring on the City s downtown waterfront, millions
More informationMarch 21, 2018 ALCA Meeting. March 21, 2018
March 21, 2018 ALCA Meeting March 21, 2018 Agenda 1. Process and Timeline 2. Original Submission 3. Revised Submission 4. Next Steps The City of Calgary Role: The City is responsible for capturing and
More information(Exhibit A) Site Plan Adoption Detail and Support Information
McCormick Park Master Site Plan (Exhibit A) Site Plan Adoption Detail and Support Information July, 2003 McCormick Park Site Plans.... 2-3 McCormick Park Site Plan Comparison... 4 Basic Assumptions about
More informationINTEGRATING FAST FERRY SERVICE IN WOODBRIDGE
INTEGRATING FAST FERRY SERVICE IN WOODBRIDGE TECHNICAL ASSISTANCE PANEL DECEMBER 12, 2018 MONTH DATE YEAR Urban Land Institute The mission of the Urban Land Institute is to provide leadership in the responsible
More informationPublic may provide comments on the GDP within the next two weeks (December 24)
25/70 General Development Plan (GDP) Public Meeting Wednesday, December 10, 2014 6:00 8:00 P.M. District 1 Police Station Community Room 1311 W 46th Ave, Denver, CO 80211 Council Woman Montero: This particular
More informationAgenda Summary December 11, 2017
Agenda Summary December 11, 2017 Agenda Item No. 5 VT 108 Roadway Master Plan for Mountain Road Village (Including the Luce Hill / Rt.100 Intersection) Summary: David Saladino, vhb Transportation Systems
More informationStreets, Connectivity & Built Environment Working Group August 2, 2017
Streets, Connectivity & Built Environment Working Group August 2, 2017 DOWNTOWN OAKLAND SPECIFIC PLAN WELCOME Streets, Connectivity & Built Environment Working Group Social Equity Meeting August 2, 2017
More informationTECHNICAL ASSISTANCE PANEL. Graniteville TAP: Developing a Community Vision
TECHNICAL ASSISTANCE PANEL SPONSORED BY: Graniteville TAP: Developing a Community Vision Graniteville Community Development Improvement Corporation Mission To provide leadership in the responsible use
More informationDRAFT PLAN PRESENTATION
DRAFT PLAN PRESENTATION 1.23.2018 AGENDA Process Project Schedule Results from Visioning Workshop Draft Plan Highlights Concept Plans Feedback Next Steps PROJECT SCHEDULE KICK-OFF WORKSHOP August 29 th
More informationCITY OF FARGO PARKING RAMP SITE EVALUATION
CITY OF FARGO PARKING RAMP SITE EVALUATION EXECUTIVE SUMMARY Helenske Design Group (architect) and Carl Walker Inc (Parking Consultant) were retained by the City of Fargo to complete a downtown parking
More informationHUMBER BAY PARK PROJECT - BUILDING CONCEPT
WELCOME 1 Humber Bay Park, with its system of trails, rugged shoreline, and dramatic views, is a unique and rare waterfront experience within the larger metropolitan Toronto area offering a place for quiet,
More informationPublic Open House. YWCA, 87 Elm Street December 2nd, 2017, 10 a.m. 2 p.m.
Public Open House YWCA, 87 Elm Street December 2nd, 2017, 10 a.m. 2 p.m. 1 A 25-Year Downtown Plan A blueprint for future growth and infrastructure in the heart of Toronto Ensuring growth contributes positively
More informationRoosevelt Corridor. R e i n v e s t m e n t P l a n. Public Meeting Gilbert Elementary School May 12, :00 pm
Roosevelt Corridor R e i n v e s t m e n t P l a n Public Meeting Gilbert Elementary School May 12, 2009 6:00 pm Agenda 6:00 6:10 6:25 6:40 6:55 7:00 Opening Comments Councilwoman Jennifer V. Ramos District
More informationPublic Meeting March 10 th 2011
Public Meeting March 10 th 2011 Agenda 6:00-6:15 6:15-7:00 7:00-8:00 8:00-8:30 8:30-9:00 9:00 Welcome and Introductions Presentation» Project Overview» Recap Existing Conditions / Issues & Opportunities»
More informationCity of Heath. Town Center Concept
In the give-and-take of getting projects designed, financed, and approved, the famous refrain from the film Field of Dreams is heard often: if you build it, they will come. From the perspective of the
More informationPhase I Redevelopment Plan. First Community Meeting
Hoboken Terminal and Yard Phase I Redevelopment Plan First Community Meeting May 31, 2011 One Hudson Place Phase I Redevelopment Plan Redevelopment Plan First Community Meeting Agenda 1. Redevelopment
More informationESTABLISH AN EFFICIENT TOWN CENTER
ESTABLISH AN EFFICIENT TOWN CENTER 4 Overview Lisbon residents are proud of the history of Newent and at the same time recognize its current importance as a centralized location for a variety of municipal
More informationDowntown Whitby Action Plan
Downtown Whitby Action Plan Final Report October 2016 Table of Contents Introduction 1 Public Consultation 2 Walkability 3 Downtown Whitby Walkability Map 4 Vision 5 Goal & Objectives 6 Objective 1 7 Objective
More informationNassau County Cultivating Opportunities for Sustainable Development Nassau County Infill Redevelopment Feasibility Study
Nassau County Cultivating Opportunities for Sustainable Development Nassau County Infill Redevelopment Feasibility Study NY-CT Sustainable Communities Steering Committee Meeting March 14, 2014 Project
More informationIvywild On The Creek PRELIMINARY CREEK DISTRICT MASTER PLAN
Ivywild On The Creek PRELIMINARY CREEK DISTRICT MASTER PLAN Introduction: Rejuvenating an extraordinary Creekside neighborhood THE CREEKSIDE DISTRICT The Ivywild On The Creek Neighborhood District Master
More informationJohn M. Fleming Managing Director, Planning and City Planner. Old East Village Dundas Street Corridor Secondary Plan Draft Terms of Reference
Report to Planning and Environment Committee To: From: Subject: Chair and Members Planning & Environment Committee John M. Fleming Managing Director, Planning and City Planner Old East Village Dundas Street
More informationProposed Downtown Plan
Proposed Downtown Plan Harbord Village Residents Association AGM October 18, 2017 Timeline Implementation The Role of Downtown Employment Growth Downtown 432,900 jobs 502,100 jobs 850,000-915,000 jobs
More informationFUNDING CORRIDOR REVITALIZATION
FUNDING CORRIDOR REVITALIZATION Integrated corridor planning for the 21 st Century America Planning Association Annual Conference Atlanta, GA April 27, 2014 Mariia Zimmerman, MZ Strategies, LLC mariia@mzstrategies.com
More informationRogue River Recreation and Access Management Plan- Table Rocks Reach. Jackson County, Oregon Department of Fish and Wildlife, National Park Service
Rogue River Recreation and Access Management Plan- Table Rocks Reach Jackson County, Oregon Department of Fish and Wildlife, National Park Service Today s Agenda Welcome Project refresher Project status/timeline
More informationTAHOE CITY VISION PLAN June 2012
TAHOE CITY VISION PLAN June 2012 Tahoe City Public Utility District North Lake Tahoe Resort Association Sustainable Community Advocates Agenda Process Overview Purpose TRPA Regional Plan Update Conversations
More information2.1 Location and Size
2.0 Context 7 2.1 Location and Size The Saanich Penninsula The study area is centrally located within the Town boundaries on the east side of Highway 17, which runs through Sidney in a north-south direction.
More informationASPEN HILL Minor Master Plan Amendment
ASPEN HILL Minor Master Plan Amendment Project Briefing Planning Board Agenda Item #7 Andrea Gilles, Area 2 June 5, 2014 Briefing Purpose 1. Follow-up evaluation on Mixed-Use land use in the Minor Amendment
More informationPort Lavaca Future Land Use
Port Lavaca Future Land Use Introduction The City of Port Lavaca is beginning to see sustained growth, after many years of relative stable population. New single family homes, apartments, and businesses
More informationWELCOME! 8 8:30 6: TH STREET IMPROVEMENTS. Open House. Presentation & Q&A
WELCOME! 168 TH STREET IMPROVEMENTS 6:30 Open House 7 8 Presentation & Q&A 8 8:30 Open House WELCOME Todd Pfitzer City of Omaha Engineer Bob Stubbe City of Omaha Public Works Director Jon Meyer Project
More informationCommunity Conversation. Thursday, March 30, James St N 7:00 pm 9:15 pm
Community Conversation Thursday, March 30, 2017 294 James St N 7:00 pm 9:15 pm Start Time Agenda item Presenter / Facilitator 7:00 Welcome & Agenda Overview Diedre Rozema (City of Hamilton) Participation
More informationTASK FORCE MEETING #6 SUMMARY
TASK FORCE MEETING #6 SUMMARY CITY OF REDWOOD CITY INNER HARBOR SPECIFIC PLAN Tuesday, January 14, 2013 7:00 P.M. 9:30 P.M. Seaport Conference Center, 459 Seaport Court, Redwood City, CA 94063 I. WELCOME
More information