Boise State University October 8 - Workshop # 2. MASTER PLAN UPDATE Executive Committee Ayers Saint Gross

Size: px
Start display at page:

Download "Boise State University October 8 - Workshop # 2. MASTER PLAN UPDATE Executive Committee Ayers Saint Gross"

Transcription

1 Boise State University October 8 - Workshop # 2 MASTER PLAN UPDATE Executive Committee Ayers Saint Gross

2 WORKSHOP AGENDA 01 WORK SESSION SUMMARY Program clarifications res life, trans, STEM Concept Plan comments 02 PREFERRED PLAN 03 DISCUSSION 04 NEXT STEPS 2

3 01 WORKSHOP SUMMARY Work sessions on Res Life, Transportation and STEM programs 3

4 Planned Projects Fine Arts Building Green space Improvements Kinesiology + Natatorium Bronco Gym Athletic Field + Volleyball Courts Alumni Center Science & Research Building Projects in Planning and Construction 4

5 Planned Projects Underway or in Planning - Greenspace Improvements at Admin Bldg. (under construction) - Alumni Center - Fine Arts Building - Athletics Football Practice Field + Volleyball Courts - Science + Research Building #2 - Kinesiology + Natatorium + Brono Gym/Olympic Sports Venue Potential: - Learning Commons (incl. writing center, etc.) - General Academic-Lab Facilities - Living-Learning Communities (ideal at 300 beds) - Additional Parking Structures (to replace lost surface parking) - Facilities: Physical Plant/Chiller, Central Receiving Development Program Elements 5

6 Parking Analysis: - Demand is being well managed, permits don t sell out - improve transit, bike, walking options - Students are living closer to campus - Average commute has dropped from 20 miles to 3 miles Strategy: - Garages closer to perimeter - Larger is better (phased if needed) *Unclear what enrollment mechanism was used in 2008 Development Program Elements 6

7 Plan Goals Framework for Plan Update A. Flexibility to meet changing 21 st Century demands B. Integrate Boise River Greenbelt into campus C. Reinforce a Pedestrian Campus Environment D. Urban University and a good neighbor 7

8 Flexibility to meet changing demands Developm ent Areas 8

9 Integrate Boise River Greenbelt into campus Developm ent Areas R iver C o n n e c t ions 9

10 Reinforce a Pedestrian Campus Environment Developm ent Areas R iver C o n n e c t ions Pedestrian Connectio n s 10

11 Urban University and Good Neighbor Developm ent Areas R iver C o n n e c t ions Pedestrian Connectio n s Cam pus Gateways 11

12 02 CONCEPT PLAN COMMENTS 12

13 Projects sited as currently planned Most of the south expansion = housing + rec Existing church properties remain Lower scale along perimeter 1. STAY THE COURSE (2008 plan) 13

14 Towers + Park will be replaced over the next ten years move garage closer to Boise Does hotel block stadium views? Gateway character? more housing than will be needed? Rec expansion better connected to existing building share with Kinesiology? 1. STAY THE COURSE (2008 plan) 14

15 New academic close to existing academic core Creates STEM super block Locate Rec Fields with each housing village Options for Ministries 2. Academic Lining University 15

16 how does new performing arts venue relate to Special Events Center? does pedestrian bridge block Capital view? love opening quad to the river, concerned about losing space library expansion on river is great like expanded orientation-admissions STEM district feels cut-off 2. Academic Lining University 16

17 Open quad and views to river Create new Malls River View Mall University Mall Stadium View Mall STEM-Health Science Mall new academic district south of University Gateways are Enterprise Zones 3. Open View Corridors + Malls 17

18 no fans of this development at gateway love opening quad to the river, concerned about losing space hate garage in this location like kinesiology closer to STEM, not in the middle of event-entertainment district 3. Open View Corridors + Malls 18

19 Create new central street New academic district south of University East Gateway reinforces Boise State s brand and identity on University 4. New central street 19

20 new intersection improve pedestrian routes to the river like new road as alternative to University 4. New central street 20

21 COMMITTEE COMMENTS: Achieving Framework Goals: option 4 modified FLEXIBILITY connect academic areas (core, STEM) INTEGRATE BOISE RIVER open mall to river (demo old COB, add library terrace) PEDESTRIAN CAMPUS - University Ave mall, Library mall, URBAN CAMPUS/GOOD NEIGHBOR add Capital crossings, new U street Evaluate Options 21

22 03 PREFERRED CONCEPT 22

23 Existing Academic Core Academic Core 23

24 Existing Academic Core 2008 STEM District Academic Core 24

25 Existing Academic Core 2013 STEM District Academic Core 25

26 DRAFT CONCEPT PLAN 26

27 27

28 28

29 BEFORE 29

30 AFTER 30

31 Achieve Framework Goals: FLEXIBILITY Additional space in STEM District to include: Health Sci / other disciplines Research / incubator space / business engagement Zone S. of Belmont can be academic/research/other depending on future needs INTEGRATE BOISE RIVER Network of greenspaces that can be linked to the greenbelt PEDESTRIAN CAMPUS Create direct, simple + activated connections across campus URBAN CAMPUS/GOOD NEIGHBOR Move parking to the perimeter Integrate uses to create a vibrant 24hr campus DRAFT CONCEPT PLAN 31

32 Proposed Phasing: CONCEPT PLAN FIRST STEPS 32

33 Demolish Bronco Gym (teams utilize Taco Bell Arena) Construct Football Practice Field Demolish CWI Bldgs Construct Science + Research Bldg #2 Construct Alumni Center Construct Surface Parking CONCEPT PLAN FIRST STEPS 33

34 Construct Natatorium Construct Additional STEM Bldgs CONCEPT PLAN FIRST STEPS 34

35 Demolish Natatorium Construct Olympic Sports Venue Demolish Academic / Career Svcs Bldg Construct STEM Bldg STEM Buildings Construct Shared Rec / Kinesiology Bldg Parking Shared Large Classroom Bldg CONCEPT PLAN FIRST STEPS 35

36 PPP Gateway Project Complete STEM District Parking CONCEPT PLAN FIRST STEPS 36

37 OPEN TO DISCUSSION for DECISIONS & DIRECTION Study Area 37

38 Thank you! w w w. a s g - a r c h i t e c t s. c o m Client Logo Here 38

Boise State University October 7-8 Workshop # 2 MASTER PLAN UPDATE. Ayers Saint Gross

Boise State University October 7-8 Workshop # 2 MASTER PLAN UPDATE. Ayers Saint Gross Boise State University October 7-8 Workshop # 2 MASTER PLAN UPDATE Ayers Saint Gross WORKSHOP AGENDA 01 PROCESS UPDATE 02 WORKSHOP 1 SUMMARY Issues + Opportunities Plan-Program Elements 03 PLANNING FRAMEWORK

More information

University of the District of Columbia Van Ness Campus Master Plan Community Open House 3. December 8, 2010

University of the District of Columbia Van Ness Campus Master Plan Community Open House 3. December 8, 2010 University of the District of Columbia Van Ness Campus Master Plan Open House 3 December 8, 2010 Introductions Sequence of Work: Campus Master Plan BEGIN: INTRODUCE AND START WORK Project Initiation Team

More information

CAMPUS MASTER PLAN DRAFT PLAN UPDATE JANUARY

CAMPUS MASTER PLAN DRAFT PLAN UPDATE JANUARY NEW MEXICO HIGHLANDS UNIVERSITY CAMPUS MASTER PLAN DRAFT PLAN UPDATE JANUARY 27 2010 MASTER PLANNING GOALS TO BALANCE THE STRATEGIC GOALS OF THE UNIVERSITY WITH THE PHYSICAL CAMPUS through the assessment

More information

U n i v e r s i t y o f S o u t h C a r o l i n a A i k e n. Land Plan Study

U n i v e r s i t y o f S o u t h C a r o l i n a A i k e n. Land Plan Study U n i v e r s i t y o f S o u t h a r o l i n a A i k e n Land Plan Study 06.27.2008 Goals ampus Growth Develop a Land Plan that allows for the orderly expansion of the campus over the next ten years and

More information

University of Saskatchewan CAMPUS MASTER PLAN. Senate Meeting Preliminary Presentation. April 21, 2018 DIALOG ECS DA WATT

University of Saskatchewan CAMPUS MASTER PLAN. Senate Meeting Preliminary Presentation. April 21, 2018 DIALOG ECS DA WATT University of Saskatchewan CAMPUS MASTER PLAN Senate Meeting Preliminary Presentation April 21, 2018 DIALOG ECS DA WATT project process presentation agenda Stakeholder Engagement Project Control phase1

More information

campus master plan VIRGINIA STATE UNIVERSITY

campus master plan VIRGINIA STATE UNIVERSITY campus master plan VIRGINIA STATE UNIVERSITY agenda 01 INTRODUCTION & GENERAL OVERVIEW 02 03 04 LAND USE CONCEPT PROGRAM ACCOMMODATION MAXIMIZE EXISTING INFRASTRUCTURE SUMMARY AND NEXT 05 STEPS agenda

More information

CAMPUS MASTER PLAN UPATE

CAMPUS MASTER PLAN UPATE 19 MAY 2016 CAMPUS MASTER PLAN UPATE Metropolitan Planning Organization AGENDA Introductions Planning Scope Observation & Analysis: Mobility Systems Campus Development Plan Mobility Planning Scenarios

More information

REPORT TO BOARD ON PREFERENCES tbp/architecture CCSF Facilities Master Plan, October 23, 2016

REPORT TO BOARD ON PREFERENCES tbp/architecture CCSF Facilities Master Plan, October 23, 2016 PURPOSE The purpose of this report is to update the Board on the Facilities Master Plan initiative. PROCESS The Board conducted a Study Session about Phase 1 Needs on August 18, 2016. Since that time,

More information

11 February CAMPUS MASTER PLAN UPDATE Focus Group - Research Park

11 February CAMPUS MASTER PLAN UPDATE Focus Group - Research Park 11 February 2016 CAMPUS MASTER PLAN UPDATE Focus Group - Research Park AGENDA Introductions Planning Scope The 2004 Campus Plan Observations SWOT Exercise Analysis Goals and Advice Questions & Discussion

More information

Overview and Update of the Rutgers-New Brunswick Physical Master Plan. January 2015

Overview and Update of the Rutgers-New Brunswick Physical Master Plan. January 2015 Overview and Update of the Rutgers-New Brunswick Physical Master Plan January 2015 Failure To Plan, is Planning For Failure Winston Churchill 2 Good Planning; The Key to Success 3 The university physical

More information

UNCW CAMPUS MASTER PLAN

UNCW CAMPUS MASTER PLAN UNCW CAMPUS MASTER PLAN JULY 27, 2017 MASTER PLAN FRAMEWORK RECOMMENDATIONS BOARD OF TRUSTEES PRESENTATION UNCW Campus Master Plan Update Board of Trustees Presentation July 27, 2017 The attached Campus

More information

18 May 2016 CAMPUS MASTER PLAN UPATE

18 May 2016 CAMPUS MASTER PLAN UPATE 18 May 2016 CAMPUS MASTER PLAN UPATE Council of the Deans ( Over view) AGENDA Engagement & What We Heard Focus Elements: 1. Development Framework Plan 2. Campus Mobility 3. Campus Guidelines 4. Wayfinding

More information

THE NEIGHBORHOOD TODAY

THE NEIGHBORHOOD TODAY THE NEIGHBORHOOD TODAY CORE AREA VISION How are we Good Urbanism A Site s DNA thinking about Elements of great Unique elements urban communities embedded in a place the site and design? ELEMENTS LIKE:

More information

12 February CAMPUS MASTER PLAN UPDATE Focus Group - Wayfinding & Signage

12 February CAMPUS MASTER PLAN UPDATE Focus Group - Wayfinding & Signage 12 February 2016 CAMPUS MASTER PLAN UPDATE Focus Group - Wayfinding & Signage AGENDA Introductions Planning Scope The 2004 Campus Plan Observations SWOT Exercise Analysis Goals and Advice Questions & Discussion

More information

11 February CAMPUS MASTER PLAN UPDATE Focus Group - Design Guidelines

11 February CAMPUS MASTER PLAN UPDATE Focus Group - Design Guidelines 11 February 2016 CAMPUS MASTER PLAN UPDATE Focus Group - Design Guidelines AGENDA Introductions Planning Scope The 2004 Campus Plan Observations Design Guidelines - 2004 Plan SWOT Exercise Analysis Goals

More information

1 Welcome! UBC Okanagan Master Plan Update - Open House

1 Welcome! UBC Okanagan Master Plan Update - Open House 1 Welcome! UBC Okanagan Master Plan Update - Open House UBC is updating the Master Plan for the Okanagan Campus. The purpose of today s Open House is to: Present the draft 2015 Master Plan Answer any questions

More information

210 PART 2 LANDSCAPE DESIGN GUIDELINES AND PRECINCT PLANS

210 PART 2 LANDSCAPE DESIGN GUIDELINES AND PRECINCT PLANS Appendix The consolidated development parameters matrix contains key development guidelines for all potential building sites identified in the plan. It prescribes the following: total area of each development

More information

FACILITIES MASTER PLAN UPDATE FINAL REFINEMENT PHASE PRESIDENT S COUNCIL PRESENTATION

FACILITIES MASTER PLAN UPDATE FINAL REFINEMENT PHASE PRESIDENT S COUNCIL PRESENTATION FINAL REFINEMENT PHASE 10.29.14 PRESIDENT S COUNCIL PRESENTATION 1 Process Overview 2 Campus Master Plans 3 Realizing the Vision 4 Final Thoughts Agenda Process Overview Master Planning Process Task One

More information

Technical Appendix L, University Community Plan Town Center

Technical Appendix L, University Community Plan Town Center Technical Appendix L, University Community Plan Town Center Table of Contents L.1 Executive Summary L.2 Merced County University Community Plan, 2004 Findings L.2.1 Visioning L.2.2 UCP Goals, Objectives

More information

Preci nct P l ans Figure 56 Campus Aerial Photo, 2008 CAL STATE EAST BAY, HAYWARD CAMPUS MASTER PLAN

Preci nct P l ans Figure 56 Campus Aerial Photo, 2008 CAL STATE EAST BAY, HAYWARD CAMPUS MASTER PLAN 9 Precinct Plans This section contains a detailed discussion of the planning and design concepts for specific areas or precincts of the Cal State East Bay Hayward campus. The Precinct Plans pertain to

More information

Subcampus Recommendations

Subcampus Recommendations T he campus is is comprised of three major areas. These subcampus areas are known as WestCampus, South Campus, Campus Oakland and Drive East Campus. and Future East growth Campus. requires a Future careful

More information

CAL POLY MASTER PLAN UPDATE, March 2015

CAL POLY MASTER PLAN UPDATE, March 2015 Some Key Themes in the General Guiding Principles Academic Mission The plan must foremost advance the University s academic mission and student success. Foresight and Adaptability The plan should take

More information

This is the East Carolina University Comprehensive Facilities Master Plan Final Draft Plan Review. This workbook reviews the campus draft master plan

This is the East Carolina University Comprehensive Facilities Master Plan Final Draft Plan Review. This workbook reviews the campus draft master plan This is the East Carolina University Comprehensive Facilities Master Plan Final Draft Plan Review. This workbook reviews the campus draft master plan first presented on campus on June 29 and June 30, 2011.

More information

Academics Efficient use of space will be used to enhance investments in new pedagogies such as active learning classrooms.

Academics Efficient use of space will be used to enhance investments in new pedagogies such as active learning classrooms. Goals and Assumptions Physical Planning Goals and Objectives The guiding principles of this Master Plan were developed in consultation with various constituencies that make up the NMSU community and were

More information

PUBLIC. Ai + Architecture LLC., 90 Belknap Street, Concord, MA 01742, USA (t) (f)

PUBLIC. Ai + Architecture LLC., 90 Belknap Street, Concord, MA 01742, USA (t) (f) PUBLIC Ai + Architecture LLC., 90 Belknap Street, Concord, MA 01742, USA www.ai-architecture.com +1 978 369 2730 (t) +1 978 369 2731 (f) 2004 Olympic Sailing Center & Marina Village Agios Kosmas, Athens,

More information

UBC Athletics + Recreation Facilities Strategy

UBC Athletics + Recreation Facilities Strategy UBC Athletics + Recreation Facilities Strategy Purpose of the Strategy Support UBC s delivery of outstanding sport and recreation experiences for students, staff, faculty, and the community at the UBC

More information

UNIVERSITY OF KENTUCKY 2012 Campus Plan Update. Ross Tarrant Architects

UNIVERSITY OF KENTUCKY 2012 Campus Plan Update. Ross Tarrant Architects UNIVERSITY OF KENTUCKY 2012 Campus Plan Update AGENDA TEAM 1 2 3 4 5 ENGAGEMENT PUBLIC INPUT PROCESS GOALS AND OBJECTIVES PLANNING PROCESS AND SCHEDULE TOPICS AND DISCUSSION Team SASAKI UNIVERSITY OF PENNSYLVANIA

More information

UAA School of Engineering Parking Garage Master Plan Amendment. 1. Purpose

UAA School of Engineering Parking Garage Master Plan Amendment. 1. Purpose UAA School of Engineering Parking Garage Master Plan Amendment 1. Purpose Since the UAA campus master plan was drafted in 2003, adopted in 2004, and amended in 2009 a number of significant changes regarding

More information

FOCUS GROUP 4 Housing, Support Facilities & Student Life

FOCUS GROUP 4 Housing, Support Facilities & Student Life Meeting Minutes By: Perkins+Will - GK Date: 12/17/2012 Meeting Date: 12/4/2012 Project Name: BT-857 FIU-Campus Master Plan Update 2010-2020 Meeting Time: 8:00am-10:00am Project : 810369.000 Meeting Location:

More information

Existing Conditions. Planning and Design Principles

Existing Conditions. Planning and Design Principles penn s south bank enn s South Bank is located south of the Schuylkill River at the intersection of 4th Street and. This acre former heavy industrial site offers the opportunity to accommodate a variety

More information

FOCUS GROUP 2 Open Space, Recreation, Land Use, Conservation and Coastal Management

FOCUS GROUP 2 Open Space, Recreation, Land Use, Conservation and Coastal Management Meeting Minutes By: Perkins+Will - GK Date: 12/17/2012 Meeting Date: 12/3/2012 Project Name: BT-857 FIU-Campus Master Plan Update 2010-2020 Meeting Time: 2:00pm-4:00pm Project : 810369.000 Meeting Location:

More information

STEERING COMMITTEE MEETING # 5 SEPTEMBER 18, 2018

STEERING COMMITTEE MEETING # 5 SEPTEMBER 18, 2018 STEERING COMMITTEE MEETING # 5 SEPTEMBER 18, 2018 STEERING COMMITTEE MEETING #5 AGENDA 1. Introduction 2. Market Conditions 3. Preliminary Development Concepts 4. Open Discussion 5. Next Steps PLANNING

More information

10 February CAMPUS MASTER PLAN UPDATE Focus Group - Landscape & Hensel Park

10 February CAMPUS MASTER PLAN UPDATE Focus Group - Landscape & Hensel Park 10 February 2016 CAMPUS MASTER PLAN UPDATE Focus Group - Landscape & Hensel Park AGENDA Introductions Planning Scope The 2004 Campus Plan & Survey Observations 2004 Landscape Plan SWOT Exercise Analysis

More information

Phase 1 : Understanding the Campus Context. Phase 2 : APPROACHES - Alternates & Preferred Plan

Phase 1 : Understanding the Campus Context. Phase 2 : APPROACHES - Alternates & Preferred Plan Introduction MASTER PLAN PURPOSE WHY A CAMPUS MASTER PLAN? The purpose of the Master Plan at the University of Illinois at Chicago is to translate UIC s strategic goals and objectives into a compelling

More information

2013 CAMPUS MASTER PLAN UPDATE

2013 CAMPUS MASTER PLAN UPDATE The University of North Carolina at Greensboro 2013 CAMPUS MASTER PLAN UPDATE Board of Trustees December 6, 2013 MASTER PLAN GOALS 1. Plan for an engaging, collaborative learning environment that aligns

More information

District Facilities Master Plan

District Facilities Master Plan W o r k s h o p B o a r d District Facilities Master Plan February 29, 2012 BACKGROUND + CONTEXT ANALYSIS OPTIONS RECOMMENDATIONS NEXT STEPS DFMP AGENDA BACKGROUND + CONTEXT ANALYSIS OPTIONS RECOMMENDATIONS

More information

Campus Sign Plan. Adopted by the Campus Planning Committee Adopted: June 26, 2006 Revised: April 14, 2016

Campus Sign Plan. Adopted by the Campus Planning Committee Adopted: June 26, 2006 Revised: April 14, 2016 Campus Sign Plan Adopted by the Campus Planning Committee Adopted: June 26, 2006 Revised: April 14, 2016 INTRODUCTION Oregon State University requires an effective system of visual communication that projects

More information

PLAN ELEMENTS WORKSHOP. April 5, 2016

PLAN ELEMENTS WORKSHOP. April 5, 2016 PLAN ELEMENTS WORKSHOP April 5, 2016 needs more housing. But there is no one-size fits-all solution. Every neighborhood has its own character. In some places, density is not only appropriate it is badly

More information

FOCUS GROUP 7 Inter-governmental Coordination, Advancement, Alumni Affairs

FOCUS GROUP 7 Inter-governmental Coordination, Advancement, Alumni Affairs Meeting Minutes By: Perkins+Will - GK Date: 12/18/2012 Meeting Date: 12/5/2012 Project Name: BT-857 FIU-Campus Master Plan Update 2010-2020 Meeting Time: 3:00pm-5:00pm Project : 810369.000 Meeting Location:

More information

1 October Dear Citizens of Charlotte and Mecklenburg County,

1 October Dear Citizens of Charlotte and Mecklenburg County, 1 October 2011 Dear Citizens of Charlotte and Mecklenburg County, As co-chairs of the Center City 2020 Vision Plan Steering Committee, we are proud to present the Center City 2020 Vision Plan, which sets

More information

COMPREHENSIVE PLAN & UNIFIED DEVELOPMENT ORDINANCE

COMPREHENSIVE PLAN & UNIFIED DEVELOPMENT ORDINANCE Village of Forsyth COMPREHENSIVE PLAN & UNIFIED DEVELOPMENT ORDINANCE Community Planning #6 Prepared by: Vision Statement We envision the Forsyth Community as one which will continue to maintain a small

More information

East Side District Map. Pha s e 2 Report 19

East Side District Map. Pha s e 2 Report 19 Preferred Plans The Preferred Plan represents a culmination of the Phase 2 master planning process, whereby issues, goals and observations collected in Phase 1 were applied to the campus at a macro scale,

More information

2015 Campus Master Plan Update

2015 Campus Master Plan Update September 15, 2015 2015 Campus Master Plan Update Campus and Community Analysis Summary Presentation A G E N D A 1. Scope & Schedule of the Master Plan 2. Planning Principles & Draft Goals 3. Background

More information

C a m p u s I d e n t i t y

C a m p u s I d e n t i t y Campus Identity Campus Identity a) Landscape Guidelines i. Materials ii. Components iii. Composition b) Wayfinding i) Entrance Features ii) Vehicular iii) Pedestrian c) Focus Areas i) Green Spine ii) Warriner

More information

U Boulevard Area, 2018 Update. U Boulevard Area Update. Public Consultation Summary Report

U Boulevard Area, 2018 Update. U Boulevard Area Update. Public Consultation Summary Report U Boulevard Area 2018 Update Public Consultation Summary Report March 16 to April 8, 2018 1 Table of Contents 1. Executive Summary... 3 2. The History and Changing Needs of the U Boulevard Area... 3 3.

More information

Achieving a Vision. Master Plan 2009 Belknap Campus August 10 11, UofL Belknap Campus Master Plan Update

Achieving a Vision. Master Plan 2009 Belknap Campus August 10 11, UofL Belknap Campus Master Plan Update Achieving a Vision Master Plan 2009 Belknap Campus August 10 11, 2009 Consultant Team The Campus Studio Ann Arbor Michigan Team Leader Campus Planning Site Design JRA Architects Louisville Kentucky Assistant

More information

4.0 Demonstration Plan

4.0 Demonstration Plan 4.0 Demonstration Plan This section presents an illustrative demonstration of one way in which the principles and planning strategies might be implemented. The plan illustrates those projects that will

More information

AvalonBay Communities + BRIDGE Housing. Mission Housing Habitat for Humanity Pacific Union Development Corporation

AvalonBay Communities + BRIDGE Housing. Mission Housing Habitat for Humanity Pacific Union Development Corporation AvalonBay Communities + BRIDGE Housing Mission Housing Habitat for Humanity Pacific Union Development Corporation Tonight s Agenda Recap of discussion from last CAC meeting Updates on meetings with Stakeholders

More information

MASTER PLAN DIAGRAMS DISTRICT CAMPUS OVERVIEW

MASTER PLAN DIAGRAMS DISTRICT CAMPUS OVERVIEW DISTRICT CAMPUS OVERVIEW Classrooms, CR Special Education Computer Lab INTERSTATE 5 FW - Faculty Work, FL - Faculty Physical Education / Athletics Support Spaces S - Storage, T - Toilets, U - Utility,

More information

a) Inventory of all existing privately-owned, state-owned, or local governmentowned recreational facilities and open spaces within the context area

a) Inventory of all existing privately-owned, state-owned, or local governmentowned recreational facilities and open spaces within the context area 8.0 RECREATION AND OPEN SPACE ELEMENT (1) DATA REQUIREMENTS a) Inventory of all existing privately-owned, state-owned, or local governmentowned recreational facilities and open spaces within the context

More information

Northwest commuter rail station US 36 BRT. Westminster Station

Northwest commuter rail station US 36 BRT. Westminster Station Northwest commuter rail station Westminster Station US 36 BRT Westminster Center US 36 & Church Ranch Broomfield Flatiron/96 th St. US 36 & McCaslin Table Mesa Boulder Junction 13-month effort that will

More information

University of Denver Land Use Plan Update I. Executive Summary

University of Denver Land Use Plan Update I. Executive Summary Executive Summary The task of developing a Land Use Plan for the University of Denver has been an exciting collaborative process that engaged a variety of interested people, including members of the University

More information

The University District envisions, in its neighborhood

The University District envisions, in its neighborhood Envisioning the University District Link Light Rail in Seattle s neighborhoods CIY OF SEALE CONCEP-LEVEL SAION AREA PLANNING RECOMMENDAION RESOLUION # 30165 EXHIBI L Vision 08.2000 he University District

More information

Status Report: MD 355 Project

Status Report: MD 355 Project Status Report: MD 355 Project OCTOBER 2006 M-NCPPC MONTGOMERY COUNTY PLANNING DEPARTMENT Summary of Community Comments, and break to the Results of the MD 355 Participation Session Brookside Gardens -

More information

Community Workshop #2 December 4, 2014 Team Tonight s Agenda 6:00 pm Welcome! 6:05 pm The Future of Downtown Tustin Ideas, Strategies and Recommendations 6:35 pm Questions and Comments 6:50 pm Open

More information

Bus Rapid Transit Backgrounder. December 2016

Bus Rapid Transit Backgrounder. December 2016 Bus Rapid Transit Backgrounder December 2016 Background The City of London is completing the second stage of Shift, its public transit planning exercise. Shift, focuses on rapid transit, along with vehicular

More information

E N V I S I O N

E N V I S I O N E N V I S I O N 2 0 3 5 C A L S T A T E N O R T H R I D G E C A M P U S M A S T E R P L A N: Scenarios PROJECT TEAM AC MARTIN PARTNERS MASTER PLANNING AND URBAN DESIGN THE SWA GROUP LANDSCAPE ARCHITECTURE

More information

BELLEVUE COLLEGE Campus Master Plan February 29, 2016 (Space Needs Updated on 04/13/2016) Bellevue College Campus Master Plan April 13, :08 PM

BELLEVUE COLLEGE Campus Master Plan February 29, 2016 (Space Needs Updated on 04/13/2016) Bellevue College Campus Master Plan April 13, :08 PM BELLEVUE COLLEGE Campus Master Plan February 29, 2016 (Space Needs Updated on 04/13/2016) AGENDA / STEERING COMMITTEE MEETING 15:00 PLANNING PROCESS: 15:05 GUIDING PRINCIPLES: 15:10 SPACE NEEDS: 15:30

More information

8.0 Built Form Framework

8.0 Built Form Framework Figure C-40. RIC and Laboratory Building Internal Pedestrian Node 8.0 Built Form Framework The built form framework defines the desired future character and function of built elements within the campus

More information

Parking: Yes! Add parking capacity, at Gage site or at parking deck/ramp opposite CSU

Parking: Yes! Add parking capacity, at Gage site or at parking deck/ramp opposite CSU Memorandum To: File From: Kathy Wallace Project: MSU Mankato Master Plan Project Number: 12-0433 Subject: Options Open Houses Input from Students Date: February 20, 2013 Copy To: File Darryl Pratte and

More information

Laney College 2012 Facilities Master Plan

Laney College 2012 Facilities Master Plan laney college 2012 Facilities Master Plan Purpose of the master plan The purpose of the 2012 Long Range Facilities Master Plan is to create a roadmap for facilities development that addresses the educational

More information

Draft Cary Community Plan Review Part 3: Shop, Engage, Serve, Special Area Plans, Other Updates. October 27, 2015 Police Department Training Room

Draft Cary Community Plan Review Part 3: Shop, Engage, Serve, Special Area Plans, Other Updates. October 27, 2015 Police Department Training Room Draft Cary Community Plan Review Part 3: Shop, Engage, Serve, Special Area Plans, Other Updates Committee for the Future October 27, 2015 Police Department Training Room AGENDA 1. Welcome and Call to Order

More information

theme 4 : Penn connects...

theme 4 : Penn connects... 38TH STREET STREETSCAPE WALNUT STREET STREETSCAPE GENERATIONAL BRIDGE LOCUST WALK RESTORATION SHOEMAKER GREEN 34TH STREET STREETSCAPE LOCUST WALK RESTORATION penn park SPRUCE STREET PLAZA HAMILTON WALK

More information

SCCCD District Wide Facilities Master Plan

SCCCD District Wide Facilities Master Plan Draft Board Update March 2012 1 2 3 4 5 Completion of the Educational Master Plans Fresno City College Reedley College North Centers Review of Educational Master Plans with the Authors Analysis of the

More information

Niagara GO Hub and Transit Stations Study

Niagara GO Hub and Transit Stations Study Niagara GO Hub and Transit Stations Study Public Open House #2 June 2017 Study Purpose The purpose of this study is to prepare four key deliverables for each station area: 1. Work with Metrolinx to provide

More information

PLANNING ADVISORY BOARD AGENDA OCTOBER

PLANNING ADVISORY BOARD AGENDA OCTOBER ! City of Langley PLANNING ADVISORY BOARD AGENDA OCTOBER 1, 2014 3-5pm LANGLEY CITY HALL - 112 2 nd Street, Langley WA 1) Call to Order and Roll Call 2) Approval of the Minutes September 10, 2014 3) Public

More information

R.O.M. = Rough Order of Magnitude

R.O.M. = Rough Order of Magnitude 3. SITE DEVELOPMENT GENERAL LOCATION The City of Corpus Christi is located on Texas coast of the Gulf of Mexico about a third of the way from the Mexican border to the Louisiana border. It is on the west

More information

CAMPUS MASTER PLAN UPDATE

CAMPUS MASTER PLAN UPDATE CAMPUS MASTER PLAN UPDATE Wayf inding and Signage DISCLAIMER: The following presentation represents in-progress work generated to test various elements of the ongoing campus planning effort along with

More information

264 neighborhoods NEIGHBORHOOD 6: WOODLAWN AND TENTH STREET

264 neighborhoods NEIGHBORHOOD 6: WOODLAWN AND TENTH STREET NEIGHBORHOOD 6: WOODLAWN AND TENTH STREET Existing Aerial View Looking North EXISTING CHARACTER The area north of East Tenth Street and south of the railroad tracks has been identified for significant

More information

U T D N o r t h C a m p u s T O D and D o w n t o w n D e n t o n T O D

U T D N o r t h C a m p u s T O D and D o w n t o w n D e n t o n T O D U n i v e r s i t y o f T e x a s a t D a l l a s C i t y o f R i c h a r d s o n U T D N o r t h C a m p u s T O D and D o w n t o w n D e n t o n T O D Rick Leisner, AICP Assistant Director of Development

More information

University of Minnesota. MINNEAPOLIS CAMPUS DEVELOPMENT FRAMEWORK February 11, 2016

University of Minnesota. MINNEAPOLIS CAMPUS DEVELOPMENT FRAMEWORK February 11, 2016 MINNEAPOLIS CAMPUS DEVELOPMENT FRAMEWORK DEVELOPMENT FRAMEWORK of use shape the campus today and may inform the future. Form, meaning how the shape, size, orientation, and arrangement of buildings, spaces,

More information

MASTER PLAN KICK-OFF Open House #1A, April 28, 2015

MASTER PLAN KICK-OFF Open House #1A, April 28, 2015 "The beginning is the most important part of the work." Plato, The Republic MASTER PLAN KICK-OFF Open House #1A, April 28, 2015 YOUR CAMPUS PLANNING TEAM Campus Planners Landscape Architects Urban Designers

More information

Atlanta BeltLine. Subareas 9 & 10. Master Plan Updates. March 26, Washington Park Jamboree 1

Atlanta BeltLine. Subareas 9 & 10. Master Plan Updates. March 26, Washington Park Jamboree 1 Atlanta BeltLine Subareas 9 & 10 Master Plan Updates March 26, 2018 Washington Park Jamboree 1 22 miles, connecting 45 neighborhoods 22 MILES of transit 46 MILES of streetscapes and complete streets 33

More information

AUSTIN MEDICAL DISTRICT MASTER PLAN"

AUSTIN MEDICAL DISTRICT MASTER PLAN AUSTIN MEDICAL DISTRICT MASTER PLAN"!"#$%&'"()(&$*+,--$ ,$?+,'=2,)0$!)=@,+'=03$AB,+-(C)'$ DE,$!)=@,+'=03$C/$D,F-'$-0$%&'()$ $?-),H='0'P$.(/$0&1"23$ $ G,)=C+$,$?+,'=2,)0$ G,0C)$

More information

Lehigh Acres Land Development Regulations Community Planning Project

Lehigh Acres Land Development Regulations Community Planning Project Lehigh Acres Land Development Regulations Planning Effort Summary In July, 2010 Commissioner Frank Mann invited the Lehigh Acres community to start discussing how to achieve their recently adopted community

More information

Envision Front Royal Workshop 1 of 2

Envision Front Royal Workshop 1 of 2 Envision Front Royal Workshop 1 of 2 September 12, 2013 Summary The Envision Front Royal project held the first of two public workshops on September 12, 2013. The purpose of the workshop was to evaluate

More information

City of Farmington. Downtown Plan. Amendment to the 1998 Master Plan Adopted October 11, 2004

City of Farmington. Downtown Plan. Amendment to the 1998 Master Plan Adopted October 11, 2004 City of Farmington Amendment to the 1998 Master Plan Adopted October 11, 2004 Introduction Planning Background 1 Scope and Components of the Plan Amendment 2 Concept Introduction 3 Plan Concepts 3 Conceptual

More information

Phasing and Implementation

Phasing and Implementation Phasing and Implementation Adaptive Reuse and New Construction Opportunities The reuse of existing buildings at UW Tacoma S 21st St S 17th St Tacoma Ave is highly valued for maintaining the history, character,

More information

C a m p u s I d e n t i t y

C a m p u s I d e n t i t y Campus Identity This Week 1) Campus Identity a) Landscape Guidelines i. Materials ii. Components iii. Composition b) Wayfinding i) Refinement c) Focus Areas i) Green Spine ii) Warriner Mall iii) A Street

More information

Welcome! UBC Community Conversations. Proposed new community garden space in Chancellor Place and Wesbrook Place. Traffic flow on Iona Drive

Welcome! UBC Community Conversations. Proposed new community garden space in Chancellor Place and Wesbrook Place. Traffic flow on Iona Drive 1 Welcome! UBC Community Conversations Thank you for joining us this evening, please take a feedback form, help yourself to some food and have a look around! We have information available on: Proposed

More information

DOWNTOWN PARKS. and PUBLIC SPACES. I. Introduction. PREPARED FOR: City of Boise PREPARED BY: City of Boise Planning and Development Services

DOWNTOWN PARKS. and PUBLIC SPACES. I. Introduction. PREPARED FOR: City of Boise PREPARED BY: City of Boise Planning and Development Services DOWNTOWN PARKS and PUBLIC SPACES PREPARED FOR: City of Boise PREPARED BY: City of Boise Planning and Development Services SEPTEMBER 2016 Vision and Purpose Introduction The vision of the Downtown s and

More information

Workshop #3 June 13, 2016

Workshop #3 June 13, 2016 Downtown Ocoee Master Plan Workshop #3 June 13, 2016 Our Team Our Team and Tonight s Goal Quick Recap: Why a Downtown Plan? How are we developing the plan? How can you still be involved? What s left to

More information

Workshop 3. City of Burlington Waterfront Hotel Planning Study. September 14, The Planning Partnership

Workshop 3. City of Burlington Waterfront Hotel Planning Study. September 14, The Planning Partnership Workshop 3 City of Burlington Waterfront Hotel Planning Study September 14, 2017 The Planning Partnership The Waterfront Hotel Planning Study 01 The Brant & Lakeshore Planning Study will establish a Strategic

More information

Hilltop Town Garden City

Hilltop Town Garden City Page 1 of 14 4.1 CITY PLANNING PRECEDENTS Oakridge is a Hybrid of the positive aspects of these urban design strategies that integrate nature within the city: Hilltop Town Garden City Using topography

More information

Broadway District Specific Plan. Community Workshop #2 February 23,2016

Broadway District Specific Plan. Community Workshop #2 February 23,2016 Broadway District Specific Plan Community Workshop #2 February 23,2016 1 Agenda Introductions Project Progress Status Upcoming Milestones Emerging Framework Land Use Urban Design Circulation Infrastructure

More information

Planning Charlotte s Future. Transportation & Planning Committee March 14, 2016

Planning Charlotte s Future. Transportation & Planning Committee March 14, 2016 Planning Charlotte s Future Transportation & Planning Committee March 14, 2016 Charlotte s Vision Livable city Vibrant economy Thriving natural environment Diverse population Choices for housing, education,

More information

W O R K S H O P S U M M A R Y

W O R K S H O P S U M M A R Y W O R K S H O P S U M M A R Y Community Workshop #2: Preliminary Design Strategies October 27, 2007 Upper Market Community Workshop Series and Design Plan Page 1 of 13 INTRODUCTION The Upper Market Community

More information

1.0 Purpose of a Secondary Plan for the Masonville Transit Village

1.0 Purpose of a Secondary Plan for the Masonville Transit Village Report to Planning and Environment Committee To: Chair and Members Planning & Environment Committee From: John M. Fleming Managing Director, Planning and City Planner Subject: Masonville Transit Village

More information

Planning Charlotte s Future. Planning Committee June 21, 2016

Planning Charlotte s Future. Planning Committee June 21, 2016 Planning Charlotte s Future Planning Committee June 21, 2016 Charlotte s Vision Livable city Vibrant economy Thriving natural environment Diverse population Choices for housing, education, employment Safe

More information

NEIGHBORHOOD 7: FEE LANE AREA. Aerial View of Briscoe and McNutt Dormitories

NEIGHBORHOOD 7: FEE LANE AREA. Aerial View of Briscoe and McNutt Dormitories NEIGHBORHOOD 7: FEE LANE AREA Aerial View of Briscoe and McNutt Dormitories Fee Lane Area Map Briscoe Dormitory 278 neighborhoods NEIGHBORHOOD 7: FEE LANE AREA EXISTING CHARACTER The Fee Lane Area neighborhood

More information

CAMPUS MASTER PLAN UPDATE

CAMPUS MASTER PLAN UPDATE 13 April 2016 CAMPUS MASTER PLAN UPDATE Focus Group Landscape AGENDA What We Heard Review of Campus Observations & Analysis Campus Framework & Open Space Network Table-Top Exercise Landscape Guideline

More information

NORTH LAKE SPECIFIC PLAN AREA

NORTH LAKE SPECIFIC PLAN AREA NORTH LAKE SPECIFIC PLAN AREA June 21, 2018 WELCOME Workshop Agenda Introduction Provide information about the program and introduce the team Background Information Share information about the North Lake

More information

UCSF Parnassus Heights Re-Envisioning Process

UCSF Parnassus Heights Re-Envisioning Process UCSF Parnassus Heights Re-Envisioning Process Community Working Group Meeting #5 February 27, 2019 Agenda Welcome, Introductions, Agenda Overview, and Review of Last Meeting Summary of Community Ideas

More information

Prosperity Hucks Area Plan. Transportation and Planning Committee May 11, 2015

Prosperity Hucks Area Plan. Transportation and Planning Committee May 11, 2015 Prosperity Hucks Area Plan Transportation and Planning Committee May 11, 2015 Presentation Outline 1. Background and Location 2. Community Dialog Process 3. Activity Center Recommendations 4. Wedge Recommendations

More information

E N V I S I O N

E N V I S I O N E N V I S I O N 2 0 3 5 C A L S T A T E N O R T H R I D G E D R A F T M A S T E R P L A N PROJECT TEAM AC MARTIN PARTNERS MASTER PLANNING AND URBAN DESIGN THE SWA GROUP LANDSCAPE ARCHITECTURE KAKU ASSOCIATES

More information

NORTHEAST DISTRICT. Description. Opportunities

NORTHEAST DISTRICT. Description. Opportunities VI plan and major recommendations district plans northeast disrict NORTHEAST DISTRICT Description The Northeast District comprises approximately 38 acres. It is bounded by Campus Creek to the north, the

More information

WESTERN ILLINOIS UNIVERSITY

WESTERN ILLINOIS UNIVERSITY WESTERN ILLINOIS UNIVERSITY Quad Cities Riverfront Campus Preliminary Master Plan Presentation 2 February 1, 2006 Achieving Future Flexibility 1. Monitor space needs as the new buildings come on line and

More information

Physical Structure. This historic image from 1882 emphasizes the dramatic topography that distinguishes Cornell s setting at the top of East Hill.

Physical Structure. This historic image from 1882 emphasizes the dramatic topography that distinguishes Cornell s setting at the top of East Hill. Physical Structure The natural, agrarian and urban setting for Cornell s campus is a precious resource to protect and enhance. It has also shaped the physical structure of the campus. Buildings, roads

More information

Review of Opportunity Area C Draft Comprehensive Plan and Draft BOS Follow-On Motions. Special Working Group Meeting March 4, 2015

Review of Opportunity Area C Draft Comprehensive Plan and Draft BOS Follow-On Motions. Special Working Group Meeting March 4, 2015 Review of Opportunity Area C Draft Comprehensive Plan and Draft BOS Follow-On Motions Special Working Group Meeting March 4, 2015 The slides that follow identify where the draft Comprehensive Plan has

More information

CITY OF UNION CITY MINUTES GENERAL PLAN ADVISORY COMMITTEE

CITY OF UNION CITY MINUTES GENERAL PLAN ADVISORY COMMITTEE CITY OF UNION CITY MINUTES GENERAL PLAN ADVISORY COMMITTEE WEDNESDAY, MARCH 4, 2015, 6:30 P.M. IN THE CITY COUNCIL CONFERENCE ROOM OF CITY HALL 34009 ALVARADO-NILES BLVD., UNION CITY, CALIFORNIA Attachment

More information