1 GAUTENG DEPARTMENT OF INFRASTRUCTURE DEVELOPMENT BUILDING ASSESSMENT REPORT ELECTRICAL SERVICES FOR 75 FOX STREET BUILDING September 2014
2 Contents 1. INTRODUCTION Design Criteria and Specification Scope of the Services Scheme Report PROJECT SUMMARY Project Description ELECTRICAL SYSTEMS MV Network Switchgear and Cabling Transformers Main Low Voltage Panel Emergency Power Stand-by Generator Change-over Panel Un-interrupted Power Supply LV Distribution Boards/Floor DBs Lighting Small Power Solar System Building Earthing Bonding and Lightning Protection Power Factor Correction and Harmonic Filter RECOMMENDATIONS Imbuba House/75 Fox Energy Efficiency considerations
3 1. INTRODUCTION Imbuba House is located on 75 Fox Street, Johannesburg, Gauteng (see Locality Map): Figure 1 - Locality Map The project brief, as issued by Gauteng Funding Agency (GFA), was to conduct an initial assessment of the building electrical infrastructural condition and to provide recommendations regarding the repairs and renovations of the buildings electrical infrastructure of Imbuba House/75Fox Street Design Criteria and Specification This project will be implemented in compliance with all the requirements of the National Building Regulations and SANS Scope of the Services Scheme Report This report deals with the condition of existing electrical services and recommendations on electrical services to be implemented based on the existing systems and proposed architectural changes to the building. Remedial work to be carried on the services and equipment affected. It also deals with proposed new works as per the new layouts from the Architects. 3
4 2. PROJECT SUMMARY 2.1. Project Description The building is currently occupied on all the floors. The electrical installation is still intact, and it s in a good state except for the plant room where there are signs pointing out that there was theft copper earthing cables which now puts the entire electrical installation under danger because it unknown on where exactly this took place; However it was seen that a replacement of copper with anti-theft earthing cable took place. The due diligence involved inspecting the following: MV Network Transformers Main LV Panels Emergency Power and UPS Low Voltage DBs/Floor DBS Lighting and Small power Solar system installed on the roof. Building bonding and Lightning protection Power Factor Correction 4
5 3. ELECTRICAL SYSTEMS 3.1. MV Network Switchgear and Cabling The switchgear and its cabling are in the basement in the transformer room. The switchgears are intact but quiet old. Visually they are well maintained in a good condition. The transformer room is well ventilated and clean. Figure 2 11KV Switchgear Figure 3 11KV Switchgear Figure 4 11KV Metering Cubicle Figure 5 MV Network 5
6 Figure 6 MV Network We recommend that the MV Network (Switchgears and Metering Unit) be replaced with modern equipment because after so many years (above 25years) of existence, the protection ability of the switchgears cannot be relied up on in next coming years Transformers There are four 1000KVA transformers in the basement transformer room. All of the transformers are intact and visually they are well maintained in a good condition. The transformer room is well ventilated and clean. Figure 7 11\0.4KV Transformer 1 - Figure 8 11\0.4KV Transformer 2 - Operational Operational 6
7 Figure 9 Transformer 3&4 Operational Figure 10 Cooling Fans Figure 11 Transformer Feeder Panel (TRF 3&4) We recommend that the transformers undergo maintenance tests; otherwise they are in a good condition Main Low Voltage Panel The Main low voltage panel is in the basement in the LT room. The room was neat and clean. The distribution boards for the main LV panel and its components are very old, however they are intact, well maintained and are in a good working condition. 7
8 Figure 12 Main LT Room and Panels Figure 13 Main Supply Transformer 1 Figure 14 Main Supply Transformer 2 We recommend that the Main LT equipment be upgraded to modern equipment Emergency Power Stand-by Generator The building has 2 Generator rooms in the basement, Generator room 1 has 2 of 750kVA generator sets and Generator room 2 has 1 of 1000kVA generator set. All of these generator sets are in a good working condition and do not need replacement or upgrade. 8
9 Figure 15 Two Generator Sets (750kVA) in Generator Room1 Figure 16 Generator Set (100kVA) in Generator Room2 Figure 17 Generator-A Log Book Figure 18 Generator-B Log Book Change-over Panel The generator change-over panels are well maintained, in a good condition and they are working. 9
10 Figure 19 C/O Panel Generator-A Figure 20 C/O Panel Generator-B Figure 21 Generator Controller A Figure 22 Generator Controller-B Figure 23 C/O Panel and Generator DB (100kVA Gen-Set) We recommend that the Generator and Change-Over panels be tested and commissioned Un-interrupted Power Supply The UPS System is in the UPS room, it is intact, the condition of the system is good and compliant except for the clumsy cables and earthing cables which are not labelled. 10
11 Figure 24 UPS Units 1&2 (300kVA) Figure 25 UPS Units 1&2 (630kVA) Figure 26 UPS Return 1&2 (630kVA) Figure 27 UPS Outgoing Supplies to Various DB s Figure 28 UPS Battery Store/Room Figure 29 UPS Room Cable Reticulation (Clumsy) 11
12 Figure 30 UPS Room Earth Cables (no labels) We recommend that all the cables be contained together, labeled for compliance and the UPS be tested and commissioned LV Distribution Boards/Floor DBs The DBs on most floors are in good working condition; however there are few things to be sorted such as; Containment of wires in the DBs Upgrade the some of the DBs and Panels components to modern technology Remove/clean the DB spaces Label all the cables Figure 31 DB-E14 in the Lifts control room Figure 32 Lift DB 12
13 Figure 33 Installed Floor DB-XEL14 Figure 34 Installed Bus-bar riser Figure 35 Typical Floor DBs Figure 36 Bus-bar riser (old fuser switch) We recommend that the above mentioned issues be sorted 3.5. Lighting Small Power Most of the building floors have under floor plug points with normal and emergency power. The condition of the plugs is good. The building lighting is good in areas such as the basements, plant rooms, etc, however in the floors there are issues with the lighting and below they are stated; Light fittings are old and some are not working Insufficient light levels in the office areas due the old lights, results to lux levels not meeting minimum office requirements Very Bad connection/ wiring for the lights( connection non-compliant) On fire escapes, it s dark, emergency lights (bulkheads) to be upgraded. 13
14 Figure 37 Dark office space with some Lights not working Figure 38 Office space (insufficient light levels) Figure 39 Bad and non-compliant connection Figure 40 Office space (insufficient light levels) Figure 41 Parameter lighting 3302/E&E/H/001 14
15 We recommend that the old light fittings be replaced with new energy efficient lights to achieve minimum requirements lux levels and parameter lighting be sorted out Solar System 20 solar panels were installed on the roof. Total power calculated is about 2.2kw. It could not be ascertained what the system supports since there is no drawing or information on site. The system consists of panels and inverter but no batteries. We recommend that information be made available and the system be maintained in line with energy efficiency. Figure 42 Installed solar panels (east) Figure 43 Installed solar panels (west) 15
16 Figure 44 Solar PV Array Controller (West) Figure 45 Solar PV Array Controller (East) 3.7. Building Earthing Bonding and Lightning Protection It was seen that the building bonding and lightning protection is not intact and compliant, which in turn pose danger to the building and people in it when there is lightning. Figure 46 Building Earth Figure 47 Clumsy Earth Cables 16
17 Figure 48 Loose Lightning rod and conductor Figure 49 Lightning rod with no conductor Figure 50 Lightning rod wit h no conductor Figure 51 Lightning Conductor with Intact We recommend that the building bonding and lightning protection should undergo repairs to achieve compliance Power Factor Correction and Harmonic Filter The building has Power Factor Correction Equipment both for normal power and emergency power and Harmonic Filter Equipment in the LT Room. The PFC equipment and Harmonic are intact and in a good working condition. We recommend that these equipments be tested and commissioned, otherwise they seem good. 17
18 Figure 52 PFC Equipment (normal power) Figure 53 PFC Equipment (emergency power) Figure 54 PFC Equipment (normal power) Figure 55 Harmonic Filter We recommend that these equipments be tested and commissioned, otherwise they seem good. 18
19 4. RECOMMENDATIONS The remedial work required to meet the minimum national standard and reinstate the building s electrical system and infrastructure is recommended above on each equipment and a high level budgetary cost for the remedial work is presented below Imbuba House/75 Fox All the electrical works to be designed and re-done in accordance to SANS and SANS Below is a brief summary of the remedial work to be done. 1. Install 4 new 11KV Switchgears and Ring Main Unit 2. Main Low Voltage Board and all its associated equipment be upgraded 3. It is recommended that further examination and testing of transformers is conducted 4. Generator, Change-Over panels and UPS Systems be tested and commissioned 5. Repairing of existing floor DBs 6. Rewire the building (small power and lighting) according to current building and floor layouts 7. Building Bonding and Lighting Protection be repaired 8. We recommend that the PFC and Harmonic Filter equipments be tested and commissioned 4.2. Energy Efficiency considerations The following initiatives will be implemented. 1. Occupancy sensors in storerooms, kitchens, offices and open plan areas. 2. Introducing daylight saving in public areas and offices. 3. Installation of a BMS to control and monitor Air conditioning and lighting. 4. Installation of smart meters on all floors and this will be linked to the BMS. 5. Installation of geyser control systems where water heating is installed. 6. Use of T5 Lamps and LEDs. 7. Use of DALI controlled lights for controlling light fittings. 8. Maintaining the solar system installed and use it on energy lighting 19
GAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT
GAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT BUILDING ASSESSMENT REPORT FIRE FOR 69 PRESIDENT SEPTEMBER 2014 Report for Department of Infrastructure Development Fire Services Preliminary Report: 69
More informationGAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT
GAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT BUILDING ASSESSMENT REPORT FIRE FOR 75 Fox Street Building OCTOBER 2014 Report for Department of Infrastructure Development Fire Services Preliminary Report:
More informationGAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT
GAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT BUILDING ASSESSMENT REPORT FIRE FOR LIBRARY HOTEL OCTOBER 2014 Report for Department of Infrastructure Development Fire Services Preliminary Report: Library
More informationGAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT
GAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT BUILDING ASSESSMENT REPORT VERTICAL TRANSPORT FOR ABSA BUILDING OCTOBER 2014 Report for Gauteng Department of Infrastructure Development Vertical Transport
More informationINITIAL ELECTRICAL ASSESSMENT REPORT (EAR)
INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory Assessor: 5th floor, Ehasan Tower, 227/B, Hafez Nagar, Bakalia, Chittagong. Uttaron 22 Jul 2014 The Alliance for Bangladesh Worker Safety Page 1/19 Factory
More informationELECTRIC SERVICE EVALUATIONS ELECTRICAL / BOILER REPLACEMENTS. Clarkstown Central School District. June Arch Proj. #
ELECTRICAL ELECTRIC SERVICE EVALUATIONS / BOILER REPLACEMENTS Clarkstown Central School District June 2015 CSArch Arch Proj. # 151-1501.00 151 Table of Contents SECTION 1 Executive Summary... 1 SECTION
More informationEQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT
EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Factory Sharoj Tower, Plot No, M-4/2, Section-14, Mirpur, Dhaka Dhaka Dhaka 20 May 2014 The Alliance for Worker Safety Page 1/18 20 May 2014 Introduction
More informationSECTION 1.02 DETAILED SCOPE OF WORK
SECTION 1.02 DETAILED SCOPE OF WORK 1.02.1 General 1.02.1.1 Introduction... 3 1.02.1.2 General description of the works... 4 1.02.1.3 Design criteria... 5 1.02.2 Public Health Services 1.02.2.1 Mains cold
More informationEQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT
EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Factory 169-171 Tetulzhora Union, Hemayetpur, Savar Savar Dhaka 24 May 2014 The Alliance for Worker Safety Page 1/20 24 May 2014 Introduction to the Report
More informationPalak Parikh, Lalit Lopez GE Digital Energy. Acknowledgment: Scottish and Southern Energy(SSE)
Palak Parikh, Lalit Lopez GE Digital Energy Acknowledgment: Scottish and Southern Energy(SSE) Outline Why LV network monitoring? Challenges and Opportunities LV Monitoring Node Architecture Advance LV
More informationTechnical Report 2: Electrical Systems Criteria and Existing Conditions
Technical Report 2: Electrical Systems Criteria and Existing Conditions Princeton Theological Seminary Library Princeton, NJ Stephanie Deckard Lighting Electrical Faculty Advisor Dr. Kevin Houser 10/12/2012
More informationCorbin Building. Technical Assignment 2. Matthew Trethaway Lighting/ Electrical AE 481W 10/26/2011 Advisor: Ted Dannerth
Corbin Building Technical Assignment 2 Matthew Trethaway Lighting/ Electrical AE 481W 10/26/2011 Advisor: Ted Dannerth 10/26/2011 Technical Report II 1 Executive Summary The following report is an overview
More informationTelecity. Table of Contents. Page. Section 3.2
1 3.2 System Descriptions Table of Contents 3.2 SYSTEM DESCRIPTIONS... 3 3.2.1 General Notes... 3 3.3 Power Distribution MV... 4 3.3.1 Incoming Supply... 4 3.3.2 MV Switch room... 4 3.4 Power Distribution
More informationPower Plants with Webel Solar Modules
Power Plants with Webel Solar Modules Power Plants with Webel Solar Modules 17W Nautilus Water Pump imported fm Australia X 2 80Wp Solar Panel X 1 Charge controller X 1 Galvanised Steel Pole (3 meters)
More informationELECTRICAL AND COMMUNICATION INSTALLATION DESIGN IN AN OFFICE COMPLEX
ELECTRICAL AND COMMUNICATION INSTALLATION DESIGN IN AN OFFICE COMPLEX PROJECT INDEX: PRJ017 BY F17/1765/2006 MUTUMA WALTER MURIMI SUPERVISOR: PROF. E. MWANGI EXAMINER: DR. J. MBUTHIA DATE: 27 th MAY 2011
More informationCOMPANY PROFILE Electrical & Instrumentation Contractor
COMPANY PROFILE Electrical & Instrumentation Contractor Engineering I Supply I Installation I Testing I Commissioning Maintenance I Fabrication I Ship Repairing ABOUT US The year was 2003, where there
More informationMonitoring of Electrical Equipment Failure Indicators and Alarming
Past, Present and Future Maintenance Practices: Monitoring of Electrical Equipment Failure Indicators and Alarming Author: Gabe Paoletti, P.E. Eaton Corporation Senior Member, IEEE gabrieljpaoletti@eaton.com
More informationEQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT
EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Factory Kunia, K.B.Bazar, Joy Bangla Road, Barabari, Gazipur Gazipur Dhaka 12 May 2014 The Alliance for Worker Safety Page 1/14 Factory 12 May 2014 Introduction
More informationBrown University Revised June 29, 2012 Facilities Design & Construction Standards SECTION ELECTRICAL DESIGN CRITERIA
PART 1 - GENERAL 1.1 Background SECTION 26 00 10- ELECTRICAL DESIGN CRITERIA A. Brown University maintains it own campus electrical distribution system which serves the majority of the buildings and facilities
More informationLindsay Frederick. Lighting + Electrical. Ron Dodson Faculty Advisor. Native American Cultural Center Arizona. Technical Report 2
Lindsay Frederick Lighting + Electrical Ron Dodson Faculty Advisor Native American Cultural Center Arizona Technical Report 2 Native American Cultural Center Technical Report 2 p. 2 Executive Summary The
More informationELECTRICAL SAFETY INSPECTION REPORT
ELECTRICAL SAFETY INSPECTION REPORT FOPTEX (PVT.) LTD. PLOT# A/24-25, VSCIC HOSIERYFATULLAH, CHITTAGONG, BANGLADESH. Factory List: 1. Foptex (Pvt.) Ltd. Inspected by: Tashi Penjor Report Generated by:
More informationINITIAL ELECTRICAL SAFETY ASSESSMENT - EXPANSION
INITIAL ELECTRICAL SAFETY ASSESSMENT - EXPANSION Assessor: Nalzani, Chandana Joydebpur, Gazipur Joydebpur, Gazipur Dhaka Emkay Enterprises The Alliance for Worker Safety Page 1/13 Introduction to the Report
More informationINITIAL ELECTRICAL ASSESSMENT REPORT (EAR)
INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory SFB 2 Adamjee EPZ, Siddergonj, Narayangonj, Siddhirgonj Dhaka 22 Feb 2017 The Alliance for Worker Safety Page 1/18 Factory 22 Feb 2017 Introduction to
More informationDOMESTIC INSTALLATIONS COMMERCIAL INSTALLATIONS LIGHTING SOLAR PV REPAIRS LANDLORDS SWITCH ON TO SWH ELECTRICAL SOLUTIONS
DOMESTIC INSTALLATIONS COMMERCIAL INSTALLATIONS LIGHTING SOLAR PV REPAIRS LANDLORDS SWITCH ON TO SWH ELECTRICAL SOLUTIONS SWH ELECTRICAL SOLUTIONS Domestic INSTALLATIONS Expert and reliable electrical
More informationINITIAL ELECTRICAL ASSESSMENT REPORT (EAR)
INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory Name: Plot 33-35, Dhaka (EPZ), Savar Savar Dhaka Bangladesh 06 Jul 2014 The Alliance for Bangladesh Worker Safety Page 1/19 06 Jul 2014 Introduction to
More informationINITIAL ELECTRICAL ASSESSMENT REPORT (EAR)
INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory Name: 4 YOU CLOTHING LTD 367/1 Senpara Parbata, Mirpur-10, Dhaka Dhaka Dhaka Bangladesh 27 May 2014 The Alliance for Bangladesh Worker Safety Page 1/18
More informationTABLE OF CONTENTS CHAPTER 2 WIRING AND PROTECTION CHAPTER 1 GENERAL RULES... 19
TABLE OF CONTENTS About This Textbook...xi How to Use the National Electrical Code... 1 Article 90 Introduction to the National Electrical Code... 7 90.1 Purpose of the NEC... 7 90.2 Scope of the NEC...
More informationEQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT
EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Factory 50-60, Dakkhin Panishail. N.K. Link Road, Kashimpur, Gazipur Gazipur 08 May 2014 The Alliance for Bangladesh Worker Safety Page 1/23 08 May 2014
More informationEQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT
EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Factory South Panishail, Kashimpur, Joydebpur, Gazipur Joydebpur, Gazipur 04 May 2014 The Alliance for Bangladesh Worker Safety Page 1/17 Factory 04 May
More informationEQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT
EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Hatimara Road, Barenda, Kashimpur, Gazipur, Gazipur Dhaka The Alliance for Worker Safety Page 1/18 Introduction to the Report The following report contains
More informationGARCIA GALUSKA DESOUSA Consulting Engineers
L#57297 /Page 1/July 21, 2017 ELECTRICAL SYSTEMS NARRATIVE REPORT The following is the Electrical Systems narrative, which defines the scope of work and capacities of the Power and Lighting systems, as
More informationINITIAL ELECTRICAL ASSESSMENT REPORT (EAR)
INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory Plot No. 60&61, Sector-3, KEPZ, North Patenga, Chittagong Chittagong 11 Feb 2015 The Alliance for Bangladesh Worker Safety Page 1/17 11 Feb 2015 Introduction
More information2009 ELECTRICAL CODE REQUIREMENTS
2009 ELECTRICAL CODE REQUIREMENTS ANTRIM COUNTY BUILDING DEPARTMENT PO BOX 188 205 CAYUGA STREET BELLAIRE, MI 49615 (231) 533-8373 FAX (231) 533-6041 Inspection Request Line (231) 533-3510 Electrical requirements
More informationGeyserWise MAX. Thermostat instruction manual. SANS 181 compliant. All in one hot water management
GeyserWise MAX Thermostat instruction manual SANS 181 compliant All in one hot water management Before operating and installation, carefully read all instructions. Do not discard this manual. Index Warranty
More informationGeyserWise MAX. Instruction manual. All in one hot water management
GeyserWise MAX All in one hot water management Before operating and installation, carefully read all instructions. Do not discard this manual. DISPLAY The display is the feedback mechanism to the user
More informationMODULAR TRACTION SUBSTATIONS CITY ELECTRIC TRANSPORT
CITY ELECTRIC TRANSPORT 2 MODULAR TRACTION SUBSTATION Modular traction substation produced by PrJSC Pluton is an integrated solution for reliable power supply of electric transport catenary. Modular traction
More informationSECTION CENTRAL BATTERY INVERTERS. A. This Section includes fast-transfer central battery inverters with the following features:
PART 1 - GENERAL 1.1 SUMMARY A. This Section includes fast-transfer central battery inverters with the following features: 1. Emergency-only circuits. 1.2 DEFINITIONS A. LCD: Liquid-crystal display. B.
More informationNATIONAL TRAINING BOARD (ELECTRICIAN) REGULATIONS 2008 BR 54/2008 NATIONAL OCCUPATIONAL CERTIFICATION ACT :38
BR 54/ NATIONAL OCCUPATIONAL CERTIFICATION ACT 2004 2004 :38 The National Training Board, with the approval of the Minister responsible for the National Training Board, in exercise of the powers conferred
More informationINITIAL ELECTRICAL ASSESSMENT REPORT (EAR)
INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Assessor: Karardi, Shibpur, Narsingdi Narsingdi Dhaka Bangladesh Emkay Enterprises The Alliance for Bangladesh Worker Safety Page 1/15 10 Apr 2016 Introduction
More informationAQ 100 Series. Arc Flash Protection System
AQ 100 Series Arc Flash Protection System THE CONSEQUENCES OF AN ARC FAULT IN HIGH VOLTAGE SWITCHGEAR THE CONSEQUENCES OF AN ARC FAULT IN OIL-FILLED SWITCHGEAR Arc Phenomena Arc Phenomena Arc fault - facts
More informationProject Briefing Document. Section 3 Electrical Services design guide and specifications
ESTATES SUPPORT SERVICE Project Briefing Document Section 3 Electrical Services design guide and specifications Issue 1.1 June 2014 Project Ref. Project Name Project Manager Date issued... Consultant/Contractor...
More informationSection 8 Electrical.
Design Guidelines Section 8 Electrical. www.canterbury.ac.nz/learningresources Standards in the Design Guidelines Suite Design Standard Guidelines Index: 01 General 02 Architecture 03 Audio Visual 04 Civil
More informationElectrical Design Guidelines Table of Contents
C: Compliant Rev. 3 Dated June 13 11 NC: Non-Compliant NA: Not Applicable Page1 16.1 General 16.2 Single Line Diagrams 16.3 Electric Motor Equipment and Controls 16.4 Lighting 16.5 Emergency Lighting 16.6
More informationHow to light a small storage space rabdesign.ca 1
How to light a small storage space rabdesign.ca 1 SUMMARY Storage lighting for smaller spaces in the home or workplace is often ignored, forgotten or given minimal attention. Builders and homeowners typically
More informationComprehensive Inspection Agency (CIA) RESIDENTIAL & COMMERCIAL FEE SCHEDULE
(CIA) RESIDENTIAL & COMMERCIAL FEE SCHEDULE Phone: 570-573-28251 Fax: 570-385-3010 Page 1 of 7 Phone: 570-573-2825 CIA Fax: 570-385-3010 RESIDENTIAL FEES BUILDING / MISCELLANEOUS Plan Review $ 0 New Construction,
More informationTABLE OF CONTENTS CHAPTER 1 GENERAL RULES CHAPTER 2 WIRING AND PROTECTION... 51
TABLE OF CONTENTS About This Textbook...xi How to Use the National Electrical Code... 1 Article 90 Introduction to the National Electrical Code... 7 90.1 Purpose of the NEC... 7 90.2 Scope of the NEC...
More informationPhotovoltaic (Solar) Array Installation Guide
Building & Safety Division Community Development Department 7351 Rosanna Street, Gilroy, CA 95020 Phone: 408 846-0451 Fax: 408 846-0429 Visit us: www.cityofgilroy.org Photovoltaic (Solar) Array Installation
More informationINSTALLATION AND USER MANUAL
INSTALLATION AND USER MANUAL t Thank you for choosing Aqua inverter heat pump. This manual provides you necessary information for optimal use and maintenance, please read it carefully and keep it for subsequent
More informationINSTALLATION AND USER MANUAL
INSTALLATION AND USER MANUAL Thank you for choosing inverter heat pump. This manual provides you necessary information for optimal use and maintenance, please read it carefully and keep it for subsequent
More information2 X 1996 Wartsila 18V mw Each 50hz HFO Generator Sets
2 X 1996 Wartsila 18V26 5.125mw Each 50hz HFO Generator Sets The responsibility for any and all additional charges is the purchasers. 2 x WARTSILA 5 MW Power plant 2 Units of Wartsila 18V26 @ 5 MW each,
More informationTable-1: Clarifications and modification in tender specifications based on Pre-bid meeting discussion
Table-1: Clarifications and modification in tender s based on Pre-bid meeting discussion Sr. Ref Page. 1 4 Clause Site Preparation and Partitions walls 2 11 SLD 3 18 Batteries 4 18 Batteries 5 32 to 34
More informationCurrently, all electrical upgrades would be voluntary, but there are situations in which upgrades would be required.
Executive Summary The current electrical system is functional but requires some understanding in order to avoid overloading circuits. Certain outlets can be used for space heaters while others cannot and
More informationA student investigated how much energy from the Sun was incident on the Earth s surface at her location.
A student investigated how much energy from the Sun was incident on the Earth s surface at her location. She put an insulated pan of water in direct sunlight and measured the time it took for the temperature
More informationUser Information Sheet 008 : 2010
User Information Sheet 008 : 2010 Formerly UIS008, July 2009 ELECTRICAL INSTALLATIONS ASSOCIATED WITH BULK LPG INSTALLATIONS 1. Introduction This Information Sheet describes some of the principles and
More informationHome Energy Management (Device Control): Immersion Heater Controller Use Cases, Application Note
Home Energy Management (Device Control): Immersion Heater Controller Use Cases, Application te Revision History Version 1.0, v. 2017 Initial release V1.0, v. 2017 Introduction Overview The SolarEdge Home
More informationELECTRICAL SAFETY INSPECTION REPORT ANLIMA TEXTILE LTD, DHAKA, BANGLADESH
ELECTRICAL SAFETY INSPECTION REPORT ANLIMA TEXTILE LTD, DHAKA, BANGLADESH January 14, 2014 Anlima Textile Ltd. PAGE 1 SUMMARY The Anlima compound located in Dhaka, Bangladesh was surveyed for Electrical
More informationPART 1. Executive Summary. The Frederick College of Cardiology
Executive Summary This report will summarize the electrical system of the Frederick College of Cardiology. First, an estimation of the possible building electrical loads will be performed. The actual loads
More informationADVANCE ELECTRICAL MEP CONTRACTING TRADING SERVICES
ADVANCE ELECTRICAL MEP CONTRACTING TRADING SERVICES ABOUT US Quality products, exceptional service and quick delivery of a diverse product line are the foundation of our company. By leveraging the portfolio
More informationInstallation and Maintenance Manual for Dimako NERM Panels REV 4. NERM Reference Manual NERM Panels 1 of 7
NERM Panels 1 of 7 Installation and Maintenance Manual for Dimako NERM Panels REV 4 Dimako Transformers Release VER 4 F:\Master Docs\Manuals\NERM.docx Page 1 of 7 NERM Panels 2 of 7 Table Of Contents Page
More informationEQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT
EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Factory Address: Assessor: 1Plot # 4 (half) 8, 12 (half)-16, DEPZ (Old), Dhaka EPZ, Ganakbari, Ashulia, Savar Ashulia, Savar Dhaka Bangladesh Uttaron 25
More informationWork involving High Voltage (HV) Systems and Maintenance of Plant.
University of Strathclyde Estates Services Electrical Procedure No E001 Procedure No: ELE 001 Procedure Title: Work involving High Voltage (HV) Systems and Maintenance of Plant. Visual check and operational
More informationINITIAL ELECTRICAL ASSESSMENT REPORT (EAR)
INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Address: Plot 61-64 & 70-73, Sector 02, KEPZ Karnafully, North Patenga, Chittagong Chittagong Chittagong Bangladesh The Alliance for Bangladesh Worker Safety
More informationINITIAL ELECTRICAL ASSESSMENT REPORT (EAR)
INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory Name: AJ Super Garments Ltd (Woven) Aj Garden, Goshbagh Zirabo Zirabo, Savar Savar Dhaka Bangladesh 23 Mar 2014 The Alliance for Bangladesh Worker Safety
More informationINITIAL ELECTRICAL ASSESSMENT REPORT (EAR)
INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory C-13, South Badda, Gulshan-1, Badda, Dhaka Dhaka Dhaka 22 May 2014 The Alliance for Worker Safety Page 1/21 22 May 2014 Introduction to the Report The
More informationChang Liu Lighting + Electrical M.A.E./B.A.E. Integrated Degree. Technical Assignment 2 October 12, 2012 Faculty Consultants: Ron Dodson
M.A.E./B.A.E. Integrated Degree Technical Assignment 2 October 12, 2012 Faculty Consultants: Ron Dodson Renzo Museum of American Art Executive Summary This report provides an analysis of the electrical
More informationGround Fault Protection Improvement Study
Ground Fault Protection Improvement Study Greg Ball DNV KEMA Solar ABCs Stakeholder Meeting July 11, 2013 San Francisco, CA Study Authors 2 Bill Brooks Brooks Engineering Andy Rosenthal New Mexico State
More informationENTSO-E response to GB compliance understanding
ENTSO-E response to GB compliance External Project Team / WG CNC 29 May 2017 1. Contents 1. Contents... 2 2. Response to GB compliance... 3 GB of LVFRT...3...3 No need for changes in current practice...3...3
More informationPROFILE. industrial services rental trading
PROFILE industrial services rental trading Introduction Power Corp General Trading & Contracting Company W.L.L. is incorporated by technocrats having vast experience in Engineering and Construction field
More informationComprehensive Inspection. (CIA) RESDENTAL & COMMERCIAL
Comprehensive Inspection. (CIA) Agency RESDENTAL & COMMERCIAL FEE SCHEDULE Phone: 570-573-2825 I Fax: 570-385-3010 Page 1 of 7 RESIDENTIAL FEES BUILDING'I NI!'S,OELLANEO.. Plan Review $0 New. Construction,
More informationElement D Services Electrical
PART 1 - GENERAL 1.01 OVERVIEW A. This Section includes design standards and requirements for electrical service and distribution. This is a design standard and is not intended to be used as a Specification.
More informationDevelopment of standards for MV Switchgear for Arc Flash protection. ABB Group May 20, 2013 Slide 1
Development of standards for MV Switchgear for Arc Flash protection May 20, 2013 Slide 1 Development of standards for MV Switchgear for Arc Flash protection Bryan Johnson ABB South Africa Shaping the world
More informationIntroduction Consultant shall incorporate the material in the DSS into the project specifications.
DIVISION 16 - ELECTRICAL Section 16000 - General Discussion Introduction Consultant shall incorporate the material in the DSS into the project specifications. Refer any questions, clarifications regarding
More informationCOSINE DEVELOPMENTS Reg. No. IT 1637/97
COSINE DEVELOPMENTS Reg. No. IT 1637/97 LEADERS IN LIGHTING TECHNOLOGY P O Box 10177 Tel. : +27 (31) 5793090/4 24 Ashfield Avenue Marine Parade Int. Fax. : +27 (31) 5793021 Springfield Park 4056 Local
More informationINITIAL ELECTRICAL ASSESSMENT REPORT (EAR)
INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory Name: Tetlabo, Rupgonj, Narayangonj Rupgonj Dhaka Bangladesh 27 May 2014 The Alliance for Bangladesh Worker Safety Page 1/22 27 May 2014 Introduction
More informationTIME KNITWEAR (PVT) LTD.
ELECTRICAL SAFETY INSPECTION REPORT TIME KNITWEAR (PVT) LTD. Baribogh, Enayetnagar, Fatullah, Narayangonj-1400, Bangladesh Factory List: 1. Time Knitwear (Pvt) Ltd. Inspected by: Dawa Report Generated
More informationAnnexure - D. Station Interface Matrix Power Supply, S&T, AFC,Lift & Escallators,Rolling stock and Track work. Station Civil and E & M Contractor
Item No A Item Description Power Supply contractor Connection between Secondary of Auxillary Transfomer and the LowVoltage Switch Board Station Interface Matrix Power Supply, S&T, AFC,Lift & Escallators,Rolling
More informationKTDC HOTELS & RESORTS LIMITED MASCOT SQUARE, TRIVANDRUM - 33
EMPANELMENT OF ARCHITECTS / LANDSCAPING CONSULTANT / INTERIOR DESIGNER / EVENT MANAGERS / TOURISM CONSULTANT SCOPE OF WORKS 1. Introduction It is essential to have plan for development of Tourism Destinations
More informationPANELBOARDS & BUILDING DISTRIBUTION
262416 PANELBOARDS & BUILDING DISTRIBUTION PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. Distribution panelboards 2. Power panelboards B. Related Sections: 1.02 POLICY 1. CU Standard 260500, Basic
More informationNEW ENERGY IN THE BATTERY INFRASTRUCTURE
NEW ENERGY IN THE BATTERY INFRASTRUCTURE Maurice H. Johnson Business Development Engineer UL LLC Northbrook, IL Paper Overview Over the past several years, there has been a significant effort to address
More informationFIRE SAFETY INSPECTION REPORT
FIRE SAFETY INSPECTION REPORT GLOBAL OUTWEAR LTD. PLOT # M/1, ROAD # 7, SECTION # 7, MIRPUR, DHAKA March 3, 2014 Accord - Bangladesh RMG Fire Safety Inspection Global Outwear Ltd. Page 2 SUMMARY Global
More informationABB Medium Voltage Days MEA 2016 Proactive safety ABB medium-voltage switchgear
ABB Medium Voltage Days MEA 2016 Proactive safety ABB medium-voltage switchgear Technical session Title of presentation Speaker name Speaker title Company name Location Martin Kropf Head of Local Product
More informationTONY ESPOSITO LIGHTING/ELECTRICAL TECHNICAL REPORT II SEPTEMBER 15, 2011 HUNTER S POINT SOUTH INTERMEDIATE SCHOOL AND HIGH SCHOOL QUEENS, NY
LIGHTING/ELECTRICAL TECHNICAL REPORT II SEPTEMBER 15, 2011 HUNTER S POINT SOUTH INTERMEDIATE SCHOOL AND HIGH SCHOOL QUEENS, NY 1 1A. POWER DISTRIBUTION SYSTEMS a. EXECUTIVE SUMMARY b. SUMMARY DESCRIPTION
More informationESTIMATE SET-UP PACKAGE BID SCHEDULE ENTRY AND MAINTENANCE
BIDDING INFORMATION BID DATE: PROJECT NAME: ADDRESS: ESTIMATE SET-UP PACKAGE BID SCHEDULE ENTRY AND MAINTENANCE ESTIMATE NO.: CITY: STATE: ZIP: PRIME: PROJECT MANAGER: PROJECT TYPE: SUB: $ SIZE: BID TIME:
More informationEQUIVALENT INITIAL FIRE SAFETY ASSESSMENT
EQUIVALENT INITIAL FIRE SAFETY ASSESSMENT B.K. Bari, Taltoli, Mirzapur Bazar, Gazipur Sadar Gazipur Gazipur Dhaka The Alliance for Worker Safety Page 1/11 Introduction to the Report The following report
More informationILLUMINATOR EM. CENTRAL LIGHTING INVERTER 1000 VA/W through 2800 VA/W 98% Efficiency!
ILLUMINATOR EM CENTRAL LIGHTING INVERTER 1000 VA/W through 2800 VA/W 98% Efficiency! THE ILLUMINATOR SERIES EM The Illuminator Series EM is a fast transfer Emergency Lighting Inverter utilizing Myers Power
More informationEQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT
EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Factory Assessor: 33/1, Darail, Shataish Tongi, Gazipur Tongi, Gazipur Dhaka Emkay Enterprises 26 Feb 2014 The Alliance for Worker Safety Page 1/12 26 Feb
More informationBALTIMORE CITY RENTAL LICENSE INSPECTION FORM RENTAL LICENSING INSPECTOR GUIDANCE
BALTIMORE CITY RENTAL LICENSE INSPECTION FORM RENTAL LICENSING INSPECTOR GUIDANCE Checklist items A - L may receive a result of Pass or Fail A. Railing is present for interior and exterior steps with more
More informationTeesside University upgrades its emergency lighting system with Hochiki Europe
Teesside University upgrades its emergency lighting system with Hochiki Europe Published on 11 Jun 2012 The luminaires are also equipped with battery back-up, making sure they will function in every situ
More informationConsumer unit replacement in domestic and similar premises
Consumer unit replacement in domestic and similar premises 6 Issue 2 The Electrical Safety Council is indebted to the following organisations for their contribution and/or support to the development of
More informationNPS/003/030 Technical Specification for Transformer and Switchgear Cable Boxes and their associated Bushing Assemblies
Version:- 2.0 Date of Issue:- May 2015 Page 1 of 17 NPS/003/030 Technical Specification for Transformer and Switchgear Cable Boxes and their associated Bushing Assemblies 1. Purpose The purpose of this
More informationELECTRICAL POWER SYSTEMS
Scope The various Codes applicable to the University's electrical power system are mainly based upon a model of a single utility service, connected to a single premise. The University s electrical system,
More informationSubstation Signage. Document Number: 1-11-FR-12
Substation Signage Document Number: 1-11-FR-12 VERSION 1.0 June 2018 This functional requirements document is in line with the organisation's 1-11-ACS-12 Substation Signage Asset Class Strategy Intellectual
More informationPhotovoltaic Specialists: Job Task Analysis
Photovoltaic Specialists: Job Task Analysis Photovoltaic Design, Photovoltaic Installer, Photovoltaic Commissioning & Maintenance September 2017 V. 09.17 www.nabcep.org Raising Standards. Promoting Confidence.
More informationEQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT
EQUIVALENT INITIAL ELECTRICAL SAFETY ASSESSMENT Factory Assessor: Thakurbari TEAC, Masumabad, Bhulta, Rupganj, Narayangonj Rupgonj Uttaron 18 Nov 2013 The Alliance for Bangladesh Worker Safety Page 1/12
More informationGuided Learning Hours (GLH) 8 Invigilated Assessment Hours (IA) 2 Total Qualification Time (TQT) 10
Qualification: Date Completed: 02 Feb 17 Unit: FIA AO Level 3 Fire Detection and Alarm Advanced Installer Development Group: FD&A Development Group Guided Learning Hours (GLH) 8 Invigilated Assessment
More informationelite Model ELN Centralized Emergency Lighting Inverter Systems 550 W to 1.5 KW Systems
5/25/16 rev 6 elite Model ELN General Specification 550 W to 1.5 KW elite Model ELN Centralized Emergency Lighting Inverter Systems 550 W to 1.5 KW Systems 1.0 General General Specification This specification
More informationV4 15JUNE2016 (COPYRIGHT: DEPARTMENT OF INDUSTRY)
V4 15JUNE2016 (COPYRIGHT: DEPARTMENT OF INDUSTRY) ACN 114 572 084 "Driving Sustainability through Teamwork" e: pcthomas@teamcatalyst.com.au m: 0417 405 478 CALCULATING COOL USER GUIDE V4 15JUNE2016 Page
More informationINITIAL ELECTRICAL ASSESSMENT REPORT (EAR)
INITIAL ELECTRICAL ASSESSMENT REPORT (EAR) Factory Address: 687, Al-Haj Nurl Amin Sowdagar Lane CDA, R/A, Road No 20, South Agrabad Chittagong Chittagong Bangladesh 03 Apr 2014 The Alliance for Bangladesh
More informationELECTRICAL DESIGN BRIEF
4211 Yonge Street Suite 500 Toronto Ontario M2P 2A9 416 487 8151 f 416 487 9104 smithandandersen.com ELECTRICAL DESIGN BRIEF FOR 128 HAZLETON AVENUE RESIDENTIAL CONDOMINIUM BUILDING TORONTO, ONTARIO OUR
More informationRiverdale NetZero Project Summary of Costs and Expected Performance
Riverdale NetZero Project Summary of Costs and Expected Performance Natural Resources Canada Sustainable Buildings and Communities Edmonton, Ottawa 2009 January 07 Gordon Howell, P.Eng. 2008-2009 Progressively
More information