1 BIDDING & CONTRACT REQUIREMENTS DATE: June 27, 2014 State of Illinois CAPITAL DEVELOPMENT BOARD Architechniques, Ltd. Mark Feldhake, AIA, LEED AP 817 S. Park Ave. Herrin, Illinois TO: PROSPECTIVE BIDDERS SUBJECT: ADDENDUM NO. 1TO THE BIDDING DOCUMENTS FOR CDB Life Safety Upgrades Facility Wide Choate Mental Health and Development Center Anna, Union County, Illinois This addendum forms a part of the bidding and contract documents and modifies the original bidding documents, dated March 19,2014. Acknowledge receipt of this addendum in space provided on Bid Form. FAILURE TO DO SO MAY SUBJECT BIDDER TO DISQUALIFICATION. ***************************************************************************** PROJECT MANUAL: 1. SECTION ALTERNATE BIDS: AMEND the following text. a. 2.5, A: Alternate Bid No. V4: Deduct/Delete the Ventilating Construction work to provide full life safety upgrades in the following building BG SECTION DOOR HARDWARE: ADD the following manufacturer s products as follows: a. 2.4, 7, o, 1, d: STANLEY COMMERCIAL QDC111 b. 2.4, 7, o, 2, d: STANLEY COMMERCIAL QDC SECTION GLAZING: ADD the following to manufacturer s products as follows: a. 2.4, B, 1, d: SuperLite I by SaftiFirst. b. 2.4, B, 1, e: SuperLite IIXL 60, 90, and 120 by SaftiFirst. 4. SECTION TOILET, BATH AND LAUNDRY ACCESSORIES: ADD the following manufacturer s products as follows: a. 2.1, A, 4: American Specialties, Inc. (ASI) b. 2.1, B, 4: ASI 0030 c. 2.1, C, 4: ASI 0210 d. 2.1, D, 4: ASI 0347 e. 2.1, E, 4: ASI 3700 series CDB Addendum #1

2 f. 2.1, F, 4: ASI 0625 g. 2.2, A, 4: American Specialties, Inc. (ASI) h. 2.2, B, 4: ASI 1224 i. 2.2, C, 4: ASI 1200V j. 2.2, D, 4: ASI 8206L/R k. 2.3, A, 11: American Specialties, Inc. (ASI) l. 2.3, B, 4: ASI 7305 m. 2.3, D, 4: ASI 0953 n. 2.3, E, 4: ASI 7345 o. 2.3, F, 4: ASI 3000 series 5. SECTION ENCLOSURE SWITCHES A. Add the following in the spec section. (BELOW) 2. AUTOMATIC TRANSFER SWITCHES A. Manufacturers: 1. Cummins. 2. ASCO 3. Caterpillar. 4. Zenith 5. Cutler Hammer B. Description: NEMA ICS 2, automatic transfer switch. C. Standard features: BIDDING & CONTRACT REQUIREMENTS 1. Switch ampacity as indicated on oneline diagram, 4 pole switch, rated for 3 phase, wire, 60 Hertz. a. Withstand rating of at least 32,000 amperes. b. Rated at 600 VAC for all classes of load. c. Bus bars: Silverplated copper. d. Capable of closing on loads with inrush fault currents described in ANSI/NRTL Switch shall not contain any integral overcurrent devices in the switching poles to avoid conflict with coordination scheme. e. Transfer Switch SBATS shall be provided with closed transition transfer. D. Locations: Refer to power plan for transfer switch location. E. Transfer switches shall also include: 1. Indicating Lights: Mount in cover of enclosure to indicate NORMAL SOURCE AVAILABLE, ALTERNATE SOURCE AVAILABLE, SWITCH POSITION. CDB Addendum #1

3 BIDDING & CONTRACT REQUIREMENTS Provide switch position indicating contacts. 2. Test Switch: Mount in cover of enclosure to simulate failure of normal source. 3. Return to Normal Switch: Mount in cover of enclosure to initiate manual transfer from alternate to normal source. 4. Normal Source Monitor: Monitor each line of normal source voltage and frequency; initiate transfer when voltage drops below 85 percent or frequency varies more than 3 percent from rated nominal value. 5. Alternate Source Monitor: Monitor alternate source voltage and frequency; inhibit transfer when voltage is below 85 percent or frequency varies more than 3 percent from rated nominal value. 6. Switched Neutral. F. Automatic Sequence of Operation. 1. Initiate Time Delay to Start Alternate Source Engine Generator: Upon initiation by normal source monitor. 2. Time Delay To Start Alternate source Engine Generator: 0 to 15 seconds, adjustable. 3. Initiate Transfer Load to Alternate Source: Upon initiation by normal source monitor and permission by alternate source monitor. 4. Time Delay Before Transfer to Alternate Power Source: 0 to 120 seconds, adjustable. 5. Before transfer to alternate power source initiate disconnect circuit to disconnect large motors for 15 seconds. 6. Initiate Retransfer Load to Normal Source: Upon permission by normal source monitor. 7. Time Delay Before Transfer to Normal Power: 0 to 30 minutes, adjustable; bypass time delay in event of alternate source failure. 8. Time Delay Before Engine Shut Down: 0 to 10 minutes, adjustable, of unloaded operation. 9. Engine Exerciser: Start engine every 7 days; run for 30 minutes before shutting down. Bypass exerciser control if normal source finals during exercising period. 10. Alternate System Exerciser: Transfer loads at each transfer switch to alternate source during engine exerciser period. 6. SECTION : Structured Wiring System A. Section 1.4A, 2: Revise to be "Optical Fiber Singlemode and 62.5micron multimode". B. Section 2.5: Add section to include FIBER OPTIC CABLING: " General: The optical fiber cable construction shall consist of both (6) singlemode and (6) 62.5/125 µm multimode fibers (OM1). These groups and individual fibers shall be identifiable in accordance with ANSI//TIA606. These groups are assembled to form a single compact core, which is covered by a armored protective sheath. Rating: NRTLlisted fiber optic cable Indoor (OFNR) / Outdoor. C. Section 2.6: Add section to include FIBER OPTIC CONNECTORS: "Connectors shall be "SC" duplex type for the singlemode cabling and "ST" type for the multimode cabling. Optical fiber optic connectors shall be capable of terminating optical glass cables with outside diameters ranging from 125 to 900 microns for the multimode cabling and 8 to 10 microns for the singlemode cabling. Fabricate connectors with optical fiber, self centering, axial alignment mechanisms. CDB Addendum #1

4 BIDDING & CONTRACT REQUIREMENTS D. Section 2.7: Add section to include FIBER OPTIC TERMINATION CABINET: "Cabinet shall be wallmounted and shall meet TIA568 and 606 requirements. Cabinet shall be fully populated with the sufficient quantity of load (adapter) plates and adapter/connectors to fully terminate the fiber optic cabling indicated on the electrical drawings and within these specifications." 7. SECTION : Fire Alarm and Smoke Detection System A. Section 1.6A: Add paragraph 13 to read: "DRILL Sequence of Operation: a) Activate local building fire alarm notification appliances; b) Transmit signal to release door hold open devices to maintain fire and/or smoke ratings of the structure. B. Section 2.1B: Add paragraph 16 to read: "At interior of each building's fire alarm system control panel, provide a tone generator with a minimum of four tones in addition to the typical temporal3 tone utilized for fire alarm: weather advisory, medical alarm, lockdown and disaster. Each tone shall be selectable from the Supervising Station at the Power Plant (building 075)." DRAWINGS: 1. SHEET D100.0: Note 9: AMEND to PLUMBING CONTRACTOR TO REMOVE EXISTING HILOW DRINKING FOUNTAIN AND CAP LINES. COORDINATE WITH A100.0 AND PLUMBING DRAWINGS FOR NEW DRINKING FOUNTAIN LOCATION. GENERAL CONTRACTOR TO PATCH/REPAIR WALL WITH 20GA. STAINLESS STEEL SHEET WITH ROLLED EDGES AND TAMPER PROOF SCREWS OVER OPENING. GENERAL CONTRACTOR IS ALSO TO INSTALL NEW HANDRAILING ACROSS OPENING. 2. SHEET D100.1: Note 11: AMEND to PLUMBING CONTRACTOR TO RELOCATE EXISTING HILOW DRINKING FOUNTAIN AND CAP LINES. COORDINATE WITH A100.1 AND PLUMBING DRAWINGS FOR NEW DRINKING FOUNTAIN LOCATION. GENERAL CONTRACTOR TO PATCH/REPAIR WALL WITH 20GA. STAINLESS STEEL SHEET WITH ROLLED EDGES AND TAMPER PROOF SCREWS OVER OPENING. GENERAL CONTRACTOR IS ALSO TO INSTALL NEW HANDRAILING ACROSS OPENING. 3. SHEET D100.2: Note 7: AMEND to PLUMBING CONTRACTOR TO DEMOLISH EXISTING DRINKING FOUNTAIN AND CAP LINES. COORDINATE WITH A100.2 AND PLUIMBING DRAWINGS FOR NEW DRINKING FOUNTAIN LOCATION. GENERAL CONTRACTOR TO PATCH/REPAIR WALL WITH 20GA. STAINLESS STEEL SHEET WITH ROLLED EDGES AND TAMPER PROOF SCREWS OVER OPENING. GENERAL CONTRACTOR IS ALSO TO INSTALL NEW HANDRAILING ACROSS OPENING. 4. SHEET D102.0: Note 9: AMEND to PLUMBING CONTRACTOR TO REMOVE EXISTING DRINKING FOUNTAIN AND CAP LINES. COORDINATE WITH A102.0 AND PLUMBING DRAWINGS FOR NEW LOCATION. GENERAL CONTRACTOR TO PATCH/REPAIR WALL WITH 20GA. STAINLESS STEEL SHEET WITH ROLLED CDB Addendum #1

5 BIDDING & CONTRACT REQUIREMENTS EDGES AND TAMPER PROOF SCREWS OVER OPENING. GENERAL CONTRACTOR IS ALSO TO INSTALL NEW HANDRAILING ACROSS OPENING. 5. SHEET D103.0: Note 6: AMEND to PLUMBING CONTRACTOR TO REMOVE EXISTING DRINKING FOUNTAIN AND CAP LINES. COORDINATE WITH A103.0 AND PLUMBING DRAWINGS FOR NEW LOCATION. GENERAL CONTRACTOR TO PATCH/REPAIR WALL WITH 20GA. STAINLESS STEEL SHEET WITH ROLLED EDGES AND TAMPER PROOF SCREWS OVER OPENING. GENERAL CONTRACTOR IS ALSO TO INSTALL NEW HANDRAILING ACROSS OPENING. 6. SHEET D103.1: Note 10: AMEND to PLUMBING CONTRACTOR TO REMOVE EXISTING DRINKING FOUNTAIN AND CAP LINES. COORDINATE WITH A103.1 AND PLUMBING DRAWINGS FOR NEW LOCATION. GENERAL CONTRACTOR TO PATCH/REPAIR WALL WITH 20GA. STAINLESS STEEL SHEET WITH ROLLED EDGES AND TAMPER PROOF SCREWS OVER OPENING. GENERAL CONTRACTOR IS ALSO TO INSTALL NEW HANDRAILING ACROSS OPENING. 7. SHEET D103.2: Note 7: AMEND to PLUMBING CONTRACTOR TO REMOVE AND REUSE EXISTING DRINKING FOUNTAIN AND CAP LINES. COORDINATE WITH A AND PLUMBING DRAWINGS FOR NEW LOCATION. GENERAL CONTRACTOR TO PATCH/REPAIR WALL WITH 20GA. STAINLESS STEEL SHEET WITH ROLLED EDGES AND TAMPER PROOF SCREWS OVER OPENING. GENERAL CONTRACTOR IS ALSO TO INSTALL NEW HANDRAILING ACROSS OPENING. 8. SHEET D108.1: ADD Note 9: PLUMBING CONTRACTOR TO REMOVE AND RELOCATE EXISTING HILOW DRINKING FOUNTAIN ON WESTERN END OF CORRIDOR 203 AND CAP LINES. COORDINATE WITH PLUMBING DRAWINGS FOR NEW LOCATION OF DRINKING FOUNTAIN. GENERAL CONTRACTOR TO PATCH/REPAIR WALL WITH 20GA. STAINLESS STEEL SHEET WITH ROLLED EDGES AND TAMPER PROOF SCREWS OVER OPENING. 9. SHEET A102.0: ADD Note 16: GENERAL CONTRACTOR TO INSTALL NEW V.C.T. TO TOILET ROOM B102B. 10. SHEET A108.1: ADD Note 21: GENERAL CONTRACTOR TO MODIFY NEW HANDRAILS AROUND RELOCATED DRINKING FOUNTAIN PER DETAIL 10/A SHEETS ALL VENTILATION SHEETS (V100.1, V100.2, V101.1, V101.2, V102.1, V 102.2, V103.1, V103.2, V104.1, V104.2, V105.1, V105.2, V106.1, V107.1): ADD/MODIFY General Note 5: Add/Change to VENTILATION CONTRACTOR TO ADD ½ DUCT LINER AND 1 DUCT WRAP TO NEW SUPPLY, RETURN, AND EXHAUST DUCTS IN CONDITIONED SPACES. VENTILATION CONTRACTOR TO AS 2 DUCT WRAP TO NEW SUPPLY, RETURNS, AND EXHAUST DUCTS IN NON CONDITIONED SPACES. 12. SHEET V102.1: ADD General Note 6: ALL WORK SHOWN WITH SYCAMORE HALL WILL BE PART OF THE BASE BID. ALTERNATE BID V4 WILL BE TO SUBTRACT CDB Addendum #1

6 BIDDING & CONTRACT REQUIREMENTS ALL ASSOCIATED WORK WITH SYCAMORE HALL FROM THE BASE BID EXCEPT FOR THE BARRIER PARTITIONS AS CALLED OUT. 13. SHEET V102.2: ADD General Note 6: ALL WORK SHOWN WITH SYCAMORE HALL WILL BE PART OF THE BASE BID. ALTERNATE BID V4 WILL BE TO SUBTRACT ALL ASSOCIATED WORK WITH SYCAMORE HALL FROM THE BASE BID EXCEPT FOR THE BARRIER PARTITIONS AS CALLED OUT. 14. SHEET P002.0: Note 8: AMEND to SAW CUT EXISTING CONCRETE AND TERRAZZO FLOOR TO EXPOSE SANITARY PIPING. PATCH FLOOR WITH SEALED CONCRETE ONCE NEW WAST PIPING HAS BEEN INSTALLED. 15. SHEET P006.0: Note 8: AMEND to SAW CUT EXISTING CONCRETE AND TERRAZZO FLOOR TO EXPOSE SANITARY PIPING. PATCH FLOOR WITH SEALED CONCRETE ONCE NEW WAST PIPING HAS BEEN INSTALLED. 16. SHEET E0.0: ELECTRICAL SYMBOLS A. FIRE ALARM SYMBOLS: Revise eight symbol from top ("V" inscribed by square with attached triangle) to note "Speaker/Strobe" and not "Horn/Strobe" all audible fire alarm notification devices shall be speaker capable of reproducing voice and tone and not simply a horn appliance. 17. SHEET E0.1: ELECTRICAL PROJECT GENERAL NOTES A. DEMOLITION: Add D9 to read: "For existing systems to be demolished, all raceway and wiring shall be disconnected to the fullest extent possible. Where raceway is above an inaccessible ceiling and cannot be accessed from any sort of existing access panel, light fixture, ceiling cavity, etc., Electrical Contractor may abandon in place; however, wiring shall be disconnected and removed. Raceway and wiring shall be disconnected and fully removed in all other areas that include accessible ceilings (including layin, spline, etc.) or exposed installations." Add D10 to read: "Several buildings include large format exterior annunciator panels that shall be disconnected and removed by the Electrical Contractor under this project. Restore existing surface behind panel to the highest extent possible and provide sealant at all penetrations. E.C. may also have to fabricate new stainless steel or aluminum panel to sufficiently cover backbox for annunciator panel paint cover to match adjacent surfaces, and provide all weather resistant hardware." B. ELECTRICAL GENERAL WORK: Add E4 to read: "After completion of penetrations through floor, electrical contractor shall restore surrounding floor material (carpeting, tile, wood, etc.) to match the existing adjacent surfaces. If floor surface is unable to be restored to match existing, E.C. shall provide collar or plate to fully conceal penetration and match the existing surfaces. E.C. shall also be responsible for repairing or replacing and damaged floor surfaces affected during construction." Add E5 to read: "Electrical contractor shall be responsible for painting all surface raceway, all surface backboxes, and miscellaneous electrical devices to match adjacent surfaces, maintaining a consistent finish with existing devices in same room or building. E. C. Shall be responsible for patching and painting all surfaces (walls, ceilings, etc.) Affected by work in this contract. CDB Addendum #1

7 BIDDING & CONTRACT REQUIREMENTS In any instance where installation of conduit remains exposed, electrical contractor shall paint raceway to match adjacent surfaces. Where raceway is surfacemounted ("exposed) and in finished areas, raceway shall match existing prevalent type (either conduit or surface wireway) and shall be painted (either by factory or electrical contractor) to match the adjacent surfaces. Device backboxes and junction boxes shall also be painted to match the same. Where raceway is exposed and in mechanical, electrical or similaruse rooms or spaces, raceway shall be conduit and shall be painted red, again by factory or E.C. coverplates shall be red as well (backboxes or junction boxes do not also need to be red). Where raceway is installed above an accessible ceiling, raceway shall be conduit and shall be painted red, by factory or E.C. coverplates shall be red as well (again, backboxes and jboxes do not also need to be red). Add E6 to read: "Majority of interior routing of power wiring and fire alarm cabling has not been indicated on individual building electrical plans. Other then where specifically noted on plans, electrical contractor shall determine best routing in the field. All cable routing is only suggested path based on casual field observations. Actual cable and raceway routing shall be determined by contractor with equipment requirements prior to installation. Indicate actual installed cabling, raceways, device addresses & routing in record documents." Add E7 to read: "New ceiling or wallmounted devices are indicated at best approximated location. If existing device (e.g. light fixture, fire alarm smoke detector, or architectural appliance) conflicts with indicated location, move new device to nearest location without obstruction. If new location is in question, contact a/e or university's representative (i.e. building engineer) for verification." C. FIRE ALARM WORK: Revise F2 to read: "All remote power supplies shown shall be monitored and controlled by remote fire alarm modules. Provide modules, boxes, and cabling adjacent to each location. Exact locations of remote power supplies may vary depending upon existing equipment or potential obstructions at indicated location. E.C. may use an alternate location adjacent existing electrical panel, contingent upon review by a/e and university. Provide smoke detector in close proximity of each power supply." Add F4 to read: "Where permanent fixture or obstruction prohibits location or acceptable mounting height of notification appliance, E.C. may substitute ceilingmounted device for wallmounted unit, contingent upon review of section NFPA 72 spacing requirements (2010 edition)." Add F5 to read: "Existing fire alarm is to be kept in full operation during construction, and shall only be disconnected once the new system is fully programmed and functional. The one caveat to this operation involves the provisions of a fire watch while either systems are nonrational. E.C. shall furnish, at their own expense, a fire watch during these periods." D. Delete fire alarm system oneline diagram depicted by detail #2 (common signaling) retain oneline diagram / detail #1. Add the following buildings to the listing: BG029 (Greenhouse), BG047 (Carwash), BG114 (Therapy Pool), BG115 (Chapel). ALL buildings (28 total) shall now include voice evacuation. 18. SHEET E1.0: ELECTRICAL SITE PLAN and ALTERNATE BIDS LISTING A. Revise keyed note 1 to read: EC shall provide fire alarm work under base bid and provide life safety upgrades under alternate bid E SHEET E1.3: ELECTRICAL SITE TUNNEL PLAN CDB Addendum #1

8 BIDDING & CONTRACT REQUIREMENTS A. Revise general note 1 to include: " Each building shall include (1) 6strand singlemode and (1) 6strand 62.5um multimode indoor/outdoor hybrid fiber optic cable (both fiber optic cables shall be under a single armored hybrid/composite jacket) from its FTC to a similar highdensity cabinet at Building 075 ". All other notes shall remain. Revise ALL references on the actual tunnel plan from 62.5um multimode to include singlemode and for the cable to be hybrid and armored. B. Add keyed note 1 to Goodner Hall (BG009) to read: "Existing fire alarm system includes combined aerial / underground communication cable between Goodner Hall and Staff Cottage #4 (BG108) using same route, extend (7) new singlemode/multimode fiber optic cables (detailed by General Note 1) from Goodner to Staff Cottage #4. Then from Staff Cottage #4, provide (1) new singlemode/multimode fiber optic cable of the same type to each of the six other cottages (BG044, BG045, BG109, BG107, BG106, BG105). Provide fiber optic cable in (1) 1" underground conduit (with tracer wire) at a minimum of 30" below grade to each of the six cottages. Provide all necessary trenching (and/or directional boring) and site restoration to existing conditions upon completion of trench / boring activities." C. Add keyed note 2 to Fire House / Carwash (BG047) to read: "Provide (1) new singlemode/multimode fiber optic cable (detailed by General Note 1) from fiber termination cabinet (FTC) adjacent fire alarm control panel at Carwash to Chapel (BG115). Provide fiber optic cable in (1) 1" underground conduit (with tracer wire) at a minimum of 30" below grade. Provide all necessary trenching (and/or directional boring) and site restoration to existing conditions upon completion of trench/boring activities." D. Add keyed note 3 to Therapy Pool (BG114) to read: "Provide (1) new singlemode/multimode fiber optic cable (detailed by General Note 1) from fiber termination cabinet (FTC) adjacent fire alarm control panel at Therapy Pool to Dewey Cottage (BG017). Provide fiber optic cable in (1) 1" underground conduit (with tracer wire) at a minimum of 30" below grade. Provide all necessary trenching (and/or directional boring) and site restoration to existing conditions upon completion of trench/boring activities." E. Add keyed note 4 to Chapel (BG115) to read: "Provide (2) new singlemode/multimode fiber optic cable (detailed by General Note 1) from fiber termination cabinet (FTC) adjacent fire alarm control panel at Chapel to Dewey Cottage (BG017). Provide fiber optic cable in (1) 1" underground conduit (with tracer wire) at a minimum of 30" below grade. Provide all necessary trenching (and/or directional boring) and site restoration to existing conditions upon completion of trench/boring activities." F. Add keyed note 5 to Greenhouse (BG029) to read: "Provide (1) new singlemode/multimode fiber optic cable (detailed by General Note 1) from fiber termination cabinet (FTC) adjacent fire alarm control panel at Greenhouse to existing service tunnel to the south. Provide fiber optic cable in (1) 1" underground conduit (with tracer wire) at a minimum of 30" below grade. Provide all necessary trenching (and/or directional boring) and site restoration to existing conditions upon completion of trench/boring activeties." G. Revise quantity of fiber optic cables between BG107 (Dewey Cottage) and intersection of tunnel to the west of BG018 (Rehab Services Bldg.) to be (4) in lieu of (1); revise quantity to the south of the intersection to now be (6) in lieu of (2). CDB Addendum #1

9 BIDDING & CONTRACT REQUIREMENTS H. Revise quantity of fiber optic cables between BG031 (Athlon Cottage) and intersection of tunnel to the east of BG022 (Life Skills) to be (2) in lieu of (1); revise quantity of fiber optic cables to the west of the same intersection to be (3) in lieu of (2). I. Revise quantity of fiber optic cables between BG019 (Bakery/Cannery) and BG034 (Barnes Hall) to be (26) in lieu of (21); revise quantity of fiber optic cables between BG034 (Barnes Hall) and BG075 (Power Plant) to be (27). 20. SHEET E1.4: ELECTRICAL SITE PLAN and ALTERNATE BIDS LISTING A. Revise the temporary transformer to be 4160v in lieu of 12470v. 21. SHEET DE001.0: MAIN BUILDING (BG001) BASEMENT DEMOLITION A. Revise the light fixture being demolition in corr B25, stor B24, stor. B27 and corr B29. See attached sheet DE001.1 ADD1(A). 22. SHEET E001.0: MAIN BUILDING (BG001) BASEMENT A. Revise the light fixture being installed in corr B25, stor B24, stor. B27 and corr B29. See attached sheet E001.1 ADD1(A). B. Add keyed note 2 next to FACP. Keyed note 2 shall read EC shall provide (2)#12 and (1)#12 ground in 3/4" conduit from panel A circuit #1. Add panel A to the east wall north of Mech B20 in the room with FACP. 23. SHEET E002.0: CEDAR HALL (BG002) BASEMENT A. Add circuit to FACP002, panel LS0(002)11,13. Provide (4)#12 and (1)#12 in 3/4" conduit from panel to FACP. B. Add circuit to FACP003, panel LS0(002)15,17. Provide (4)#12 and (1)#12 in 3/4" conduit from panel to FACP. 24. SHEET E002.1: CEDAR HALL (BG002) 1ST FLOOR A. Add lighting control contactor next to panel LS1(002). The new wall pack C fixture shall be circuited to the lighting contactor. B. Add keyed note 6 to lighting control contactor. Keyed note 6 shall read Lighting contactor shall control C fixtures. See contactor detail on this sheet. C. Add attached lighting contactor to the E002.1, see attached sheet E002.1 ADD1(A). D. Add (2) 20 amp single pole breaker to panel LS1(002). E. Add (4) control monitor for the smoke dampers between dining room 225 and 5 person bedroom 223. Provide (2)#12 and (1)#12 in 3/4" conduit from panel LS1(002) SHEET E002.2: CEDAR HALL (BG002) 2ND FLOOR A. Add (4) control monitor for the smoke dampers between dining room 125 and 4 person bedroom 123. Provide (2)#12 and (1)#12 in 3/4" conduit from panel LS1(002) SHEET E002.4: ELECTRICAL DETAIL BG002, BG003, BG004 A. Add keyed note #6 to ATS LS SHEET E003.1: DOGWOOD HALL (BG003) 1ST FLOOR A. Add lighting control contactor next to panel LS1(003). The new wall pack C fixture shall be circuited to the lighting contactor. CDB Addendum #1

10 BIDDING & CONTRACT REQUIREMENTS B. Add keyed note 6 to lighting control contactor. Keyed note 6 shall read Lighting contactor shall control C fixtures. See contactor detail on this sheet. C. Add attached lighting contactor to the E008.1, see attached sheet E003.1 ADD1(A). D. Add (2) 20 amp single pole breaker to panel LS1(003). E. Add (2) control monitor for the smoke dampers for stair 142. (1) between stair 142 and restroom 104 and (1) between stair 142 and corr 141. Provide (2)#12 and (1)#12 in 3/4" conduit from panel LS1(003)10. F. Add (2) control monitor for the smoke dampers for stair 137. (2) between stair 137 and corr 138. Provide (2)#12 and (1)#12 in 3/4" conduit from panel LS1(003)10. G. Add (2) control monitor for the smoke dampers for stair 135. (1) between stair 135 and laundry 130 and (1) between stair 135 and corr 136. Provide (2)#12 and (1)#12 in 3/4" conduit from panel LS1(003) SHEET E003.2: DOGWOOD HALL (BG003) 2ND FLOOR A. Add (3) control monitor for the smoke dampers for stair 137. (2) between stair 137 and linen 220 and (1) between stair 137 and lobby 237. Provide (2)#12 and (1)#12 in 3/4" conduit from panel LS1(003) SHEET E004.0: CYPRUS HALL (BG004) BASEMENT A. Add circuit to FACP004, panel LS0(004)9,11. Provide (4)#12 and (1)#12 in 3/4" conduit from panel to FACP. B. Add keyed note 7 in electrical room B116. Note 7 shall read Provide (4)#10 and (1)#10 ground from the 3/4" conduit to the temporary generator from the existing emergency panel for the generator heater and charger.. Provide (2) 20amp single pole breakers in the GE AQF panel. 30. SHEET E004.1: CYPRUS HALL (BG004) 1ST FLOOR A. Add lighting control contactor next to panel LS1(004). The new wall pack C fixture shall be circuited to the lighting contactor. B. Add keyed note 6 to lighting control contactor. Keyed note 6 shall read Lighting contactor shall control C fixtures. See contactor detail on this sheet. C. Add attached lighting contactor to the E008.1, see attached sheet E004.1 ADD1(A). D. Add (2) 20 amp single pole breaker to panel LS1(004). E. Add (2) control monitor for the smoke dampers for stair 154. (1) between stair 152 and sally port 153 and (1) between stair 154 and person room 100. Provide (2)#12 and (1)#12 in 3/4" conduit from panel LS1(004)12. F. Add (2) control monitor for the smoke dampers for stair 149. (1) between stair 149 and corr 151 and (1) between stair 149 and sally port 150. Provide (2)#12 and (1)#12 in 3/4" conduit from panel LS1(004)12. G. Add (2) control monitor for the smoke dampers for stair 144. (1) between stair 144 and sally port 145 and (1) between stair 144 and laundry room 142. Provide (2)#12 and (1)#12 in 3/4" conduit from panel LS1(004) SHEET E004.2: CYPRUS HALL (BG004) 2ND FLOOR A. Add (3) control monitor for the smoke dampers for stair 149. (2) between stair 149 and staff tlt 222 and (1) between stair 149 and sally port 242. Provide (2)#12 and (1)#12 in 3/4" conduit from panel LS1(004)12. CDB Addendum #1

11 B. Revise the location of panel LS2(004) to Jan 228 west wall. BIDDING & CONTRACT REQUIREMENTS 32. SHEET E006.0: REDBUD HALL (BG006) BASEMENT A. Add circuit to FACP LS0(006)11,13. Provide (4)#12 and (1)#12 in 3/4" conduit from panel to FACP. 33. SHEET E006.1: REDBUD HALL (BG006) 1ST FLOOR A. Add lighting control contactor next to panel LS1(006). The new wall pack C fixture shall be circuited to the lighting contactor. B. Add keyed note 10 to lighting control contactor. Keyed note 10 shall read Lighting contactor shall control C fixtures. See contactor detail on this sheet. C. Add attached lighting contactor to the E006.1, see attached sheet E006.1 ADD1(A). Add (2) 20 amp single pole breaker to panel LS1(006). D. Add keyed note 11 to metal gate in the courtyard. Keyed note 11 shall read EC shall disconnect the existing magnetic door holder. EC shall protect the circuit and conductors. EC shall provide connection to the new magnetic door holder. E. Add (2) control monitor for the smoke dampers for stair 142. (2) between stair 142 and corr 144. Provide (2)#12 and (1)#12 in 3/4" conduit from panel LS1(006)12. F. Add (1) control monitor for the smoke dampers between office 110 and break room 108. Provide (2)#12 and (1)#12 in 3/4" conduit from panel LS1(006)12. G. Add (2) control monitor for the smoke dampers for office 116. (1) between office 116 and breaker room 108 and (1) between office 116 and corr 141. Provide (2)#12 and (1)#12 in 3/4" conduit from panel LS1(006) SHEET E006.2: REDBUD HALL (BG006) 2ND FLOOR i. Add (2) control monitor for the smoke dampers in the pent house next to stair 142. Provide (2)#12 and (1)#12 in 3/4" conduit from panel LS1(006) SHEET E007.1: DOGWOOD HALL (BG007) 1ST FLOOR A. Add lighting control contactor next to panel LS1(007). The new wall pack C fixture shall be circuited to the lighting contactor. B. Add keyed note 9 to lighting control contactor. Keyed note 9 shall read Lighting contactor shall control C fixtures. See contactor detail on this sheet. C. Add attached lighting contactor to the E007.1, see attached sheet E007.1 ADD1(A). D. Add (2) 20 amp single pole breaker to panel LS1(007). E. Add (2) control monitor for the smoke dampers for stair 144. (1) between stair 144 and toilet 106 and (1) between stair 144 and corr 143. Provide (2)#12 and (1)#12 in 3/4" conduit from panel LS1(007)14. F. Add (2) control monitor for the smoke dampers for stair 137. (2) between stair 137 and corr to the west of stair 137. Provide (2)#12 and (1)#12 in 3/4" conduit from panel LS1(007)14. G. Add (2) control monitor for the smoke dampers for stair 135. (1) between stair 135 and laundry 132 and (1) between stair 135 and corr 136. Provide (2)#12 and (1)#12 in 3/4" conduit from panel LS1(007) SHEET E007.2: DOGWOOD HALL (BG007) 2ND FLOOR CDB Addendum #1

12 BIDDING & CONTRACT REQUIREMENTS A. Add (3) control monitor for the smoke dampers for stair 137. (2) between stair 137 and storage 222 and (1) between stair 137 and corr 239. Provide (2)#12 and (1)#12 in 3/4" conduit from panel LS1(007) SHEET E008.0: MAGNOLIA HALL (BG008) BASEMENT A. Add circuit to FACP008 LS1(008)11,13 and FACP007 LS1(008)15,17. B. Add panel LS0(008) in room Elec C. Add keyed note 3 in electrical room B116. Note 3 shall read Provide (4)#10 and (1)#10 ground from the 3/4" conduit to the temporary generator from the existing emergency panel for the generator heater and charger. Provide (2) 20amp single pole breakers in the GE AQF panel. 38. SHEET E008.1: MAGNOLIA HALL (BG008) 1ST FLOOR A. Add lighting control contactor next to panel LS1(008). The new wall pack C fixture shall be circuited to the lighting contactor. B. Add keyed note 9 to lighting control contactor. Keyed note 9 shall read Lighting contactor shall control C fixtures. See contactor detail on this sheet. C. Add attached lighting contactor to the E008.1, see attached sheet E008.1 ADD1(A). D. Add (5) 20 amp single pole breaker to panel LS1(008). E. Add keyed note 10 to metal gate in the courtyard. Keyed note 10 shall read EC shall disconnect the existing magnetic door holder. EC shall protect the circuit and conductors. EC shall provide connection to the new magnetic door holder. F. Add (2) control monitor for the smoke dampers for stair 148. (1) between stair 142 and storage 144 and (1) between stair 148 and corr 152. Provide (2)#12 and (1)#12 in 3/4" conduit from panel LS1(008)14. G. Add (2) control monitor for the smoke dampers for stair 147. (1) between stair 147 and corr 150 and (1) between stair 147 and corr 151 Provide (2)#12 and (1)#12 in 3/4" conduit from panel LS1(008)14. H. Add (2) control monitor for the smoke dampers for stair 145. (1) between stair 145 and house keeping 121 and (1) between stair 145 and corr 149. Provide (2)#12 and (1)#12 in 3/4" conduit from panel LS1(008) SHEET E008.2: MAGNOLIA HALL (BG008) 2ND FLOOR A. Add (3) control monitor for the smoke dampers for stair 147. (2) between stair 147 and toilet 231 and (1) between stair 147 and corr 249. Provide (2)#12 and (1)#12 in 3/4" conduit from panel LS1(008) SHEET DE009.0: GOODNER HALL (BG009) BASEMENT DEMOLITION A. Add sheet in its interiority. 41. SHEET E009.0: GOODNER HALL (BG009) BASEMENT A. Add keyed note 3 next to the FACP. Keyed note 3 shall read Provide (4)#12 and (1)#12 ground in 3/4" from the FACP and AMP to emergency panel in mechanical 005. FACP and AMP shall be circuited to the (2) spare 20amp 1 pole breaker in the emergency panel. CDB Addendum #1

13 BIDDING & CONTRACT REQUIREMENTS 42. SHEET E009.0: GOODNER HALL (BG009) BASEMENT A. Add, FACP and AMP shall be circuited to LS1(022)8,12 (provide (2) 20amp breaker in panel LS1(022)). Provide (4)#12 and (1)#12 ground in 3/4" conduit from FACP to LS1(022). 43. SHEET E017.0: DEWEY COTTAGE (BG017) BASEMENT A. Add, FACP and AMP shall be circuited to existing panel A on west wall in Classroom B1 circuit number 4 and 6. Provide (4)#12 and (1)#12 ground in 3/4" conduit from FACP to panel. 44. SHEET E033.1: OAK HALL (BG033) 1ST FLOOR A. Add keyed note 15 to lighting control contactor. Keyed note 15 shall read Lighting contactor shall control C fixtures. See contactor detail on E B. Add (1) B fixtures and (1) switch next to the door in the new (4) mechanical spaces, one on each corner of the building. The new B fixture between mech 262 and 261 shall be circuited to LS1(003)5. The new B fixture between mech 245 and 246 shall be circuited to LS1(003)5. The new B fixture between mech 227 and 226 shall be circuited to LS1(003)3. The new B fixture between mech 213 and 212 shall be circuited to LS1(003)3. C. Add GFIC receptacle on the south wall off 2 person bedroom 219 in the corridor side for the new water cooler. The receptacle shall be circuited to the existing panel B. Provide (2)#12 and (1)#12ground in 3/4" from the receptacle to the panel. Use blank breaker in the panel for water cooler. Coordinate location with attached plumbing sheet. 45. SHEET E033.2: ELECTRICAL DETAILS (BG033) A. Add lighting control contactor next to panel LS1(033). The new wall pack C fixture shall be circuited to the lighting contactor. B. Add attached lighting contactor to the E033.2, see attached sheet E033.2 ADD1(A). C. Add (1) 20 amp single pole breaker to panel LS1(033). 46. SHEET E029: GREENHOUSE (BG029) BASEMENT and FIRST FLOOR A. Revise fire alarm communicator / transmitter (C/T) at west wall of Stor 001 to be NIC network interface card (fiber optic). Add fiber termination cabinet (FTC) and amplifier (AMP) to system for voice evacuation. 47. SHEET E044: COTTAGE #6 (BG044) 1ST FLOOR and BASEMENT A. Add Keyed note 13 to read Provide (2)#12 and (1)#12 ground from the exit sign to the inverter. See detail 2 on sheet E5.0 B. Add (3) fixtures to be demoed in storage 001 (in basement). Add (3) A fixtures to be installed in the new ceiling in the basement. See attached sheet E044 ADD1(A). 48. SHEET E045: COTTAGE #7 (BG045) 1ST FLOOR and BASEMENT A. Add (3) fixtures to be demoed in storage 001 (in basement). Add (3) A fixtures to be installed in the new ceiling in the basement. The work is the same is the same as E044 ADD1(A). CDB Addendum #1

14 BIDDING & CONTRACT REQUIREMENTS 49. SHEET E047: CARWASH/FIREHOUSE (BG047) 1ST FLOOR and ATTIC A. Revise fire alarm communicator / transmitter (C/T) at north wall of Fire Truck Room (100) to be NIC network interface card (fiber optic). Add fiber termination cabinet (FTC) and amplifier (AMP) to system for voice evacuation. 50. SHEET E144: THERAPY POOL (BG047) 1ST FLOOR A. Revise fire alarm communicator / transmitter (C/T) at north wall of Fire Truck Room (100) to be NIC network interface card (fiber optic). Add fiber termination cabinet (FTC) and amplifier (AMP) to system for voice evacuation. 51. SHEET E145: CHAPEL (BG115) FIRST FLOOR A. Revise fire alarm communicator / transmitter (C/T) at north wall of Mechanical 106 to be NIC network interface card (fiber optic). Add fiber termination cabinet (FTC) and amplifier (AMP) to system for voice evacuation. 52. SHEET FA006.1: REDBUD HALL (BG006) 1ST FLOOR FIRE ALARM A. Revise fire alarm control panel (FACP) at east wall of Corr. 139 to be an annunciator panel (FAAP). 53. SHEET FA020.0: KITCHEN/CAFETERIA (BG020) 1ST FLOOR FIRE ALARM A. Add, FACP and AMP shall be circuited to existing KP7 panel on the wall next to the FACP, circuit number 18 and 20. Provide (4)#12 and (1)#12 ground in 3/4" conduit from FACP to KP7 panel. Add keyed note 2 and panel KP7 on the north wall office 110. Keyed note 2 shall read Provide (3) new 20 amp 1 pole breakers in panel KP7 for FACP, AMP and door holder. Panel KP7 is a GE AQF panel. B. Add note to door holder to read KP722. Add keyed note 3 next to door holder control module to read EC shall provide a junction box above each door holder with the indicated circuit. EC shall connect (2)#12 and (1)#12 ground to the door holder. 54. SHEET FA021.1: GENERAL STORE (BG021) 1ST FLOOR FIRE ALARM A. Add, FACP and AMP shall be circuited to existing panel A on the north wall in storage room 108, circuit number 15 and 14. Provide (4)#12 and (1)#12 ground in 3/4" conduit from FACP to existing panel A. 55. SHEET FA034.0: BG034 (BARNES HALL) BASEMENT A. Add, FACP and AMP shall be circuited to existing panel A on the east wall in mech room B2, circuit number 42 and 40. Provide (4)#12 and (1)#12 ground in 3/4" conduit from FACP to existing panel A. Add keyed note 1 and panel A on the west wall mech B2. Keyed note 2 shall read Provide (2) new 20 amp 1 pole breakers in panel A for FACP, AMP and door holder. Panel A is a square D QCL panel. 56. SHEET P033: PLUMBING BASE BID BG033 A. Existing bilevel drinking fountain shall be moved as indicated on sketch P033 ADD 1(A). CDB Addendum #1

15 BIDDING & CONTRACT REQUIREMENTS 57. SHEET P047: PLUMBING BASE BID BG047 A. Keyed note on the DEMO PLAN shall be labeled 14 instead of 4. See sketch P047 ADD1(A). CLARIFICATION: 1. Question came up during the walk through about who will be patching the holes left from the electrical demo work. 1) See Project General Note #2 on sheet E Do the temporary generator feeders have to be in conduit in the crawl space? 1) The temporary generator feeders do not have to be in conduit in the crawl space. The feeder has to be supported from the structure. Also, the feeders have to be in conduit outside and in the crawl space. The temporary generator feeders shall be removed by the EC. BID DATE: 1. This Addendum does not alter the previously published bid date(s). Very truly yours, 06/30/14 Mark Feldhake, AIA, LEED AP This addendum consists of 28 pages. Attachment P033 ADD1 P047ADD1 DE001.0 ADD1 DE009.0 E001.0 ADD1 E002.1 ADD1 E003.1 ADD1 E004.1 ADD1 E006.1 ADD1 E007.1 ADD1 E008.1 ADD1 E033.2 ADD1 E044.2 ADD1 11/14/30 CDB Addendum #1

16

17

18

19

20

21

22

23

24

25

26

27

28

Memphis Housing Authority High Rise Fire Alarm Upgrades. Questions from Contractors (Through Addendum #2) Communications Systems, Inc.

Memphis Housing Authority High Rise Fire Alarm Upgrades. Questions from Contractors (Through Addendum #2) Communications Systems, Inc. Memphis Housing Authority High Rise Fire Alarm Upgrades Questions from Contractors (Through Addendum #2) Communications Systems, Inc.: Legend 1. DL - Dome light symbol should be on the tenant emergency

More information

ADDENDUM NO. 1. for. MARQUETTE HOUSING COMMISSION Pine Ridge Apartments Fire Alarm Replacement Project #A1140. Marquette, Michigan.

ADDENDUM NO. 1. for. MARQUETTE HOUSING COMMISSION Pine Ridge Apartments Fire Alarm Replacement Project #A1140. Marquette, Michigan. ADDENDUM NO. 1 for MARQUETTE HOUSING COMMISSION Pine Ridge Apartments Fire Alarm Replacement Project #A1140 Marquette, Michigan December 12, 2016 TO: ALL BIDDERS OF RECORD This addendum forms a part of

More information

SECTION AUTOMATIC TRANSFER SWITCHES

SECTION AUTOMATIC TRANSFER SWITCHES PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 36 23 SPEC WRITER NOTE: Use this section only for NCA projects. Delete between //--// if not applicable to project. Also, delete any other item or paragraph

More information

Garfield Elementary School Feasibility Study for New Library Building Project Number A C

Garfield Elementary School Feasibility Study for New Library Building Project Number A C Larry Teixeira Selma Unified School District 3036 Thompson Avenue Selma, CA 93662 Subject: Feasibility Study for New Library Building Project Number A 12-8581.00 C Dear Mr. Teixeira: At your request, we

More information

SECTION GENERATOR PARALLELING CONTROLS

SECTION GENERATOR PARALLELING CONTROLS PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 23 13 GENERATOR PARALLELING CONTROLS SPEC WRITER NOTE: Delete between // -- // if not applicable to project. Also delete any other item or paragraph not applicable

More information

M001. Revenue Services ISSUED FOR CONSTRUCTION SEPTEMBER. 2, East State Parkway Schaumburg, Illinois Do Not Scale Drawings

M001. Revenue Services ISSUED FOR CONSTRUCTION SEPTEMBER. 2, East State Parkway Schaumburg, Illinois Do Not Scale Drawings 1 T Consultant: NOTES, SYMBOLS & ABBREVIATIONS - MECHANICAL Number Description M001 Vestibule 117 LAN/IT Coffee 115 116 Mail Room 118 114 113 112 Scanning 119 Open Office 101 FIRST FLOOR PLAN - MECHANICAL

More information

RE: Clark East Tower Renovations DATE: November 16, 2015 Ypsilanti, Michigan

RE: Clark East Tower Renovations DATE: November 16, 2015 Ypsilanti, Michigan ADDENDUM NO. 2 RE: Clark East Tower Renovations DATE: November 16, 2015 Ypsilanti, Michigan TO: All Bidders Gentlemen: You are hereby directed to make the following changes in the Project Manual and/or

More information

TABLE OF CONTENTS GENERAL... 2 A. DEFINITIONS DIGITAL, ADDRESSABLE FIRE ALARM SYSTEM... 2

TABLE OF CONTENTS GENERAL... 2 A. DEFINITIONS DIGITAL, ADDRESSABLE FIRE ALARM SYSTEM... 2 Division 28 ELECTRONIC SAFETY AND SECURITY TABLE OF CONTENTS 28 0000 GENERAL... 2 A. DEFINITIONS...2 28 3111 DIGITAL, ADDRESSABLE FIRE ALARM SYSTEM... 2 A. DESIGN REQUIREMENTS...2 B. CONSTRUCTION REQUIREMENTS...2

More information

FIRE ALARM: BY OTHERS, IF REQUIRED.

FIRE ALARM: BY OTHERS, IF REQUIRED. x x x x x x OS LIGHTING S FLUORESCENT LIGHT FIXTURE, SEE LIGHT FIXTURE SCHEDULE FOR SIZE AND MOUNTING. FLUORESCENT STRIP LIGHT FIXTURE, SEE LIGHT FIXTURE SCHEDULE FOR SIZE AND MOUNTING. WALL BRACKET FLUORESCENT

More information

FIRE ALARM: BY OTHERS, IF REQUIRED.

FIRE ALARM: BY OTHERS, IF REQUIRED. x x x x x x OS LIGHTING S FLUORESCENT LIGHT FIXTURE, SEE LIGHT FIXTURE SCHEDULE FOR SIZE AND MOUNTING. CAPITAL LETTER DENOTES TYPE, LOWER CASE LETTER DENOTES SWITCH LEG. FLUORESCENT STRIP LIGHT FIXTURE,

More information

Building Division 201 SE 3 rd STREET (Second Floor) OCALA, FL Phone: (352) BUILDING CODE GUIDELINES FOR ELECTRICAL INSPECTIONS

Building Division 201 SE 3 rd STREET (Second Floor) OCALA, FL Phone: (352) BUILDING CODE GUIDELINES FOR ELECTRICAL INSPECTIONS BUILDING CODE GUIDELINES FOR ELECTRICAL INSPECTIONS Building Code compliance is the obligation of design professionals and/or contractors. Plan Review and Inspection Guidelines are intended to be used

More information

SECTION : FIRE ALARM & DETECTION SYSTEMS

SECTION : FIRE ALARM & DETECTION SYSTEMS SECTION 28 31 10: FIRE ALARM & DETECTION SYSTEMS 1. GENERAL A. This section applies to fire detection/alarm system and carbon monoxide system components and equipment installed during new construction

More information

SECTION DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM

SECTION DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM SECTION 283111 - DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

SECTION ISOLATED POWER SYSTEMS

SECTION ISOLATED POWER SYSTEMS PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 20 11 ISOLATED POWER SYSTEMS SPEC WRITER NOTE: Delete between //---// if not applicable to project. Also, delete any other item or paragraph not applicable to

More information

HMC ARCHITECTS 2495 Natomas Park Drive, Studio 100 Sacramento, California ADDENDUM NO. 3

HMC ARCHITECTS 2495 Natomas Park Drive, Studio 100 Sacramento, California ADDENDUM NO. 3 HMC ARCHITECTS 2495 Natomas Park Drive, Studio 100 Sacramento, California 95833 September 15, 2016 Woodland Joint Unified School District Spring Lake Area Elementary School HMC No. 3535003.000 DSA Appl.

More information

NOTICE TO ALL FIRMS. Bid RFI Questions and Answers

NOTICE TO ALL FIRMS. Bid RFI Questions and Answers Purchasing Department 227 West 27 th Street New York, NY 10001 Purchasing Dept. Tel. 212-217-3630 Purchasing Dept. Fax 212-217-3631 Purchasing@fitnyc.edu NOTICE TO ALL FIRMS Date: March 8, 2018 To: From:

More information

PLATTEVILLE MIDDLE SCHOOL

PLATTEVILLE MIDDLE SCHOOL Architectural The building has aluminum clad wood awning windows in combination with aluminum fixed glass units. They appear to be exterior glazed with insulated glazing. See photo 2. Platteville Middle

More information

CITY OF PORTSMOUTH Department of Public Works MUNICIPAL COMPLEX FIRE ALARM. Bid # Addendum #1

CITY OF PORTSMOUTH Department of Public Works MUNICIPAL COMPLEX FIRE ALARM. Bid # Addendum #1 CITY OF PORTSMOUTH Department of Public Works MUNICIPAL COMPLEX FIRE ALARM Bid #56-09 Addendum #1 This Addendum forms part of the original document marked Bid #56-09 MUNICIPAL COMPLEX FIRE ALARM. Device

More information

DONALD H. BERG, ARCHITECT

DONALD H. BERG, ARCHITECT DONALD H. BERG, ARCHITECT DVA PROJECT 632-CSI-402 PET/CT ROOM #A0-10 RENOVATION BASEMENT LEVEL, BUILDING 200 ARCHITECT S PROJECT No. 0917-02 ADDENDUM NO. 1 JUNE 25, 2018 Page 1 of 1 ARCHITECTURAL 1. Specifications:

More information

SECTION FIRE ALARM STANDARDS REVISED CONSTRUCTION STANDARD

SECTION FIRE ALARM STANDARDS REVISED CONSTRUCTION STANDARD PART 1 - GENERAL PURPOSE This Standard is intended to assure that fire detection/alarm systems at The University of Texas at Austin provide the highest level of fire safety possible. SCOPE This standard

More information

2. The Group F occupancy has have an a combined occupant load of 500 or more above or below the lowest level of exit discharge.

2. The Group F occupancy has have an a combined occupant load of 500 or more above or below the lowest level of exit discharge. 2. The Group F occupancy has have an a combined occupant load of 500 or more above or below the lowest level of exit discharge. Exception: Manual fire alarm boxes are not required where the building is

More information

Smoke Detector Activation of any smoke detector shall start the alarm verification mode.

Smoke Detector Activation of any smoke detector shall start the alarm verification mode. Description: The purpose of the section is to provide the UMCP Design Standards for the design and implementation of Fire Alarm Systems at the UMCP campus. Related Sections: TBD Effective Date: July 10,

More information

COUNTY OF KINGS KINGS COUNTY JAIL EXPANSION PHASE III

COUNTY OF KINGS KINGS COUNTY JAIL EXPANSION PHASE III SECTION 28 3111 - DIGITAL ADDRESSABLE FIRE ALARM SYSTEM PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. General provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

.4 Do complete installation in accordance with latest Electrical Bulletins of the local inspection authority.

.4 Do complete installation in accordance with latest Electrical Bulletins of the local inspection authority. Fitness Facility Addition Page 1 1.1 CODES AND STANDARDS.1 Do complete installation in accordance with the latest edition of the CSA C22.1 as amended by the latest editions of the National Building Code

More information

SECTION AUTOMATIC TRANSFER SWITCHES PART 1 - GENERAL

SECTION AUTOMATIC TRANSFER SWITCHES PART 1 - GENERAL SECTION 16400 AUTOMATIC TRANSFER SWITCHES 1.01 RELATED DOCUMENTS PART 1 - GENERAL A. Drawings and general provisions of Contract, including General Conditions and Division 1 Specification sections, apply

More information

DIVISION 28 ELECTRONIC SAFETY AND SECURITY

DIVISION 28 ELECTRONIC SAFETY AND SECURITY 281300 - ACCESS CONTROL A. General DIVISION 28 ELECTRONIC SAFETY AND SECURITY At the beginning of the project, schedule a meeting with the Facilities Access/Maintenance Coordinator with questions and concerns.

More information

Standard of Practice - Fire Alarm Systems. NOTE: Significant revisions or additions to the previous standards are highlighted in italics.

Standard of Practice - Fire Alarm Systems. NOTE: Significant revisions or additions to the previous standards are highlighted in italics. A28.1 Standard of Practice - Fire Alarm Systems NOTE: Significant revisions or additions to the previous standards are highlighted in italics. OBJECTIVE OF STANDARD To provide compliant smart addressable

More information

PROJECT NO. CWA SEPTEMBER 24, 2014 ADDENDUM NO. 6 BESSEMER RECREATION & WELLNESS CENTER

PROJECT NO. CWA SEPTEMBER 24, 2014 ADDENDUM NO. 6 BESSEMER RECREATION & WELLNESS CENTER PROJECT NO. CWA 2013-04 SEPTEMBER 24, 2014 ADDENDUM NO. 6 BESSEMER RECREATION & WELLNESS CENTER BIDS RECEIVED: CITY HALL, CITY OF BESSEMER TIME: 2:00pm DATE: October 2, 2014 City of Bessemer --------------------------------------------------------------------------------------------------------------------------------------------

More information

Springpoint Architects, pc SECTION Childcare Center Architect s Project No TABLE OF CONTENTS Monroe County Comm. Sch. Corp.

Springpoint Architects, pc SECTION Childcare Center Architect s Project No TABLE OF CONTENTS Monroe County Comm. Sch. Corp. Volume 1 Bidding Requirements, Contract Forms, Conditions of the Contract, Division 1, Architectural and Site Specifications 000107 Certification Page 000110 Table of Contents DIV00 PROCUREMENT AND CONTRACTING

More information

Port of Portland Conveying Equipment Guidelines

Port of Portland Conveying Equipment Guidelines Role: Consultant for the Port Design Guidelines Port of Portland Conveying Equipment Guidelines ELEVATOR, ESCALATOR, AND MOVING WALK DESIGN OVERVIEW The Division 14 specification sections include appropriate

More information

Exhibit J. Subcontract Agreement No.

Exhibit J. Subcontract Agreement No. Exhibit J SUBCONTRACTOR TRADE INTERFACE AGREEMENT Subcontract Agreement No. PROJECT: NEW EASTSIDE REGIONAL PARK PHASE I PARTICIPANTS (PARTIES): Sundt Construction, Inc. PURPOSE: General Contractor (Sundt)

More information

PWGSC Ontario MULTIPLEX FIRE ALARM SYSTEM Sect Region Project Page 1 Number R

PWGSC Ontario MULTIPLEX FIRE ALARM SYSTEM Sect Region Project Page 1 Number R Region Project Page 1 PART 1 - GENERAL 1.1 REFERENCES.1 CAN/ULC-S524-2006, Standard for the Installation of Fire Alarm Systems..2 CAN/ULC-S525-2007, Audible Signal Device for Fire Alarm Systems..3 CAN/ULC-S526-2007,

More information

NFPA 101, 2012 EDITION IMPACT ON NEW AND EXISTING HEALTH CARE FACILITIES

NFPA 101, 2012 EDITION IMPACT ON NEW AND EXISTING HEALTH CARE FACILITIES NFPA 101, 2012 EDITION IMPACT ON NEW AND EXISTING HEALTH CARE FACILITIES Sharon S. Gilyeat, P.E., Principal Koffel Associates, Inc. www.koffel.com sgilyeat@koffel.com Expertly Engineering Safety From Fire

More information

SCHOOL DISTRICT PALM BEACH COUNTY BUILDING DEPARTMENT PLAN REVIEW CHECK LIST -- ELECTRICAL

SCHOOL DISTRICT PALM BEACH COUNTY BUILDING DEPARTMENT PLAN REVIEW CHECK LIST -- ELECTRICAL SCHOOL DISTRICT PALM BEACH COUNTY BUILDING DEPARTMENT PLAN REVIEW CHECK LIST -- ELECTRICAL 3300 SUMMIT BOULEVARD WEST PALM BEACH, FLORIDA 33406 TEL (561) 688-7687 FAX (561) 688-7654 http://www.palmbeach.k12.fl.us/fm/bd/index.htm

More information

FIRE AND SAFETY PROJECT REVIEW REPORT

FIRE AND SAFETY PROJECT REVIEW REPORT 1. A001 2. A001 3. A001 4. D102/103 5. A102/103 *VA enforces/applies the National Fire Protection Association (NFPA) 101 (current edition is 2015) and not the International Building Code (IBC). Ideally

More information

Hinesville First United Methodist Church SECTION DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM

Hinesville First United Methodist Church SECTION DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM SECTION 28 3111 DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM PART 1 - GENERAL 1.01 SUMMARY A. Section Includes: 1. Fire-alarm control unit. 2. Manual fire-alarm boxes. 3. System smoke detectors. 4. Heat detectors.

More information

A. Connected to the equipment ground B. Bonded to the box C. Connected to nearest water pipe D. Connected to a ground rod

A. Connected to the equipment ground B. Bonded to the box C. Connected to nearest water pipe D. Connected to a ground rod Journeyman and Master Common Exam 2 1 The grounding terminal of a grounding-type receptacle installed in a metal box shall be? A. Connected to the equipment ground B. Bonded to the box C. Connected to

More information

GARCIA GALUSKA DESOUSA Consulting Engineers

GARCIA GALUSKA DESOUSA Consulting Engineers L#57297 /Page 1/July 21, 2017 ELECTRICAL SYSTEMS NARRATIVE REPORT The following is the Electrical Systems narrative, which defines the scope of work and capacities of the Power and Lighting systems, as

More information

A. This Section includes transfer switches rated 600 V and less, including the following:

A. This Section includes transfer switches rated 600 V and less, including the following: SECTION 16415 - TRANSFER SWITCHES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

Fire Alarm Systems ARTICLE. Introduction to Article 760 Fire Alarm Systems. Part I. General

Fire Alarm Systems ARTICLE. Introduction to Article 760 Fire Alarm Systems. Part I. General ARTICLE 760 Fire Alarm Systems Introduction to Article 760 Fire Alarm Systems Article 760 covers the installation of wiring and equipment for fire alarm systems, including all circuits controlled and powered

More information

Electronic Safety and Security

Electronic Safety and Security 28 Electronic Safety and Security NOTE: This is a new section, which includes content from previous sections of the KU Design Standards, along with appropriate revisions and updates. Significant revisions

More information

ARCHITECT S PRE-BID ADDENDUM

ARCHITECT S PRE-BID ADDENDUM ARCHITECT S PRE-BID ADDENDUM 14203 487 Main Street Suite 500 Buffalo, New York Addendum No: 001 Date Issued: Feb. 8, 2019 Project: The West End (CWM Project No. 18.122) Location: 240-260 Lakefront Blvd.

More information

Photovoltaic (Solar) Array Installation Guide

Photovoltaic (Solar) Array Installation Guide Building & Safety Division Community Development Department 7351 Rosanna Street, Gilroy, CA 95020 Phone: 408 846-0451 Fax: 408 846-0429 Visit us: www.cityofgilroy.org Photovoltaic (Solar) Array Installation

More information

SECTION AUTOMATIC TRANSFER SWITCHES

SECTION AUTOMATIC TRANSFER SWITCHES PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 36 23 This section specifies the furnishing, complete installation, and connection of automatic transfer switches. 1.2 RELATED WORK A. Section 14 21 00, ELECTRIC

More information

SECTION FIRE DETECTION AND ALARM

SECTION FIRE DETECTION AND ALARM PART 1 - GENERAL 1.1 DESCRIPTION SECTION 28 46 00 SPEC WRITER NOTES: 1. The A/E must obtain a copy of the VA ENGINEERING GUIDE FOR FIRE PROTECTION DESIGN which provides fire alarm system criteria that

More information

Replacement of Fire Pump and Generator Upgrade, H Building, Sexton Campus

Replacement of Fire Pump and Generator Upgrade, H Building, Sexton Campus ADDENDUM FORM INVITATION TO TENDER: 2016-067 ADDENDUM NO: 1 DATE ISSUED: June 23, 2016 ISSUED BY: Monty Thibeault DESCRIPTION: Replacement of Fire Pump and Generator Upgrade, H Building, Sexton Campus

More information

SECTION (16140) - WIRING DEVICES

SECTION (16140) - WIRING DEVICES SECTION 26 27 26 (16140) - WIRING DEVICES PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. Receptacles, Connectors, Switches, and Finish Plates. B. Related Sections: 1. Section 00 31 13.43 (00370) -

More information

APPENDIX - L INTERNATIONAL RESIDENTIAL CODE ELECTRICAL

APPENDIX - L INTERNATIONAL RESIDENTIAL CODE ELECTRICAL This Appendix (2000 IRC Appendix-L) is produced, copyrighted, and maintained by the National Fire Protection Association Association, all rights reserved. Use of this Appendix is pursuant to license with

More information

MECKLENBURG COUNTY FIRE MARSHAL S OFFICE

MECKLENBURG COUNTY FIRE MARSHAL S OFFICE Effective Date: 11/01/02 Purpose: MECKLENBURG COUNTY To establish a set of guidelines for performance testing of all newly installed or upgraded fire alarm systems in order to ensure that all devices and

More information

Town of Cicero Local Code Amendments

Town of Cicero Local Code Amendments Town of Cicero Local Code Amendments 2009 International Residential Code Local Amendments: DELETE Table R302.1 (Exterior Walls), see Attachment A. DELETE Exception for Subsection R313.2 (One and Two-Family

More information

University Design Standard Fire Alarm Systems

University Design Standard Fire Alarm Systems 1.0 Overview University Design Standard Fire Alarm Systems This document provides Virginia Tech s standards for the design and installation of fire alarm systems and equipment in new construction, retrofit

More information

Subcontract Agreement No.

Subcontract Agreement No. ATTACHMENT G TRADE INTERFACE AGREEMENT Subcontract Agreement No. PROJECT: TEXASTECH UNIVERSITY HEALTH SCIENCES CAMPUS, EL PASO, TEXAS MEDICAL SCIENCE BUILDING II PARTICIPANTS: Sundt Construction, Inc.

More information

Moreno Valley Fire Department Fire Prevention Bureau. New and Existing Fire Alarm & Signaling Systems Guideline

Moreno Valley Fire Department Fire Prevention Bureau. New and Existing Fire Alarm & Signaling Systems Guideline Moreno Valley Fire Department Guideline Approved and Authorized By: Adria Reinertson, Fire Marshal Issued: May 8, 2017 Alarm & Signaling Systems PURPOSE Fire alarm and signaling systems are designed to

More information

ENGINE GENERATORS AND ACCESSORIES

ENGINE GENERATORS AND ACCESSORIES ENGINE GENERATORS AND ACCESSORIES GENERAL INFORMATION 1.1 This section applies to engine generators and accessories. DESIGN REQUIREMENTS 2.1 The Engineer of Record will consult with the University s Engineering

More information

SECTION LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES (600 VOLTS AND BELOW)

SECTION LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES (600 VOLTS AND BELOW) SECTION 26 05 21 PART 1 - GENERAL 1.1 DESCRIPTION This section specifies the furnishing, installation, and connection of the low voltage power and lighting wiring. 1.2 RELATED WORK A. Excavation and backfill

More information

GROUP SR SPECIAL RESIDENCE (ASSISTED SELF-PRESERVATION) OCCUPANCIES

GROUP SR SPECIAL RESIDENCE (ASSISTED SELF-PRESERVATION) OCCUPANCIES [B] APPENDIX SR GROUP SR SPECIAL RESIDENCE (ASSISTED SELF-PRESERVATION) OCCUPANCIES The provisions contained in this appendix are adopted by the Building Codes Division of the State of Oregon SECTION SR101

More information

FIRE SAFETY REQUIREMENTS FOR PRE RESIDENTIAL BUILDINGS OF THREE OR MORE STORIES (DOROTHY MAE ORDINANCE - NO. 158,963)

FIRE SAFETY REQUIREMENTS FOR PRE RESIDENTIAL BUILDINGS OF THREE OR MORE STORIES (DOROTHY MAE ORDINANCE - NO. 158,963) INFORMATION BULLETIN / PUBLIC - MECHANICAL CODE REFERENCE NO.: LAMC 91.8604 Effective: 6-20-84 DOCUMENT NO. P/MC 2002-005 Revised: 6-15-00 Previously Issued As: MGD #74 FIRE SAFETY REQUIREMENTS FOR PRE-

More information

CITY OF FARMINGTON 800 Municipal Drive Farmington, NM (505) Fax (505)

CITY OF FARMINGTON 800 Municipal Drive Farmington, NM (505) Fax (505) CITY OF FARMINGTON 800 Municipal Drive Farmington, NM 87401-2663 (505) 599-1373 Fax (505) 599-1377 http://www.fmtn.org IMMEDIATE ATTENTION Construction Services for Municipal Operations Center Expansion

More information

LOCAL AMENDMENTS TO THE INTERNATIONAL FIRE CODE 2006 EDITION

LOCAL AMENDMENTS TO THE INTERNATIONAL FIRE CODE 2006 EDITION CHAPTER 23.45 Sections LOCAL AMENDMENTS TO THE INTERNATIONAL FIRE CODE 2006 EDITION 23.45.100 Local amendments to the International Fire Code, 2006 Edition... 2 23.45.102.1 Construction and design provisions...

More information

DIVISION 26 ELECTRICAL SECTION FIRE ALARM SYSTEM

DIVISION 26 ELECTRICAL SECTION FIRE ALARM SYSTEM DIVISION 26 ELECTRICAL SECTION 26 81 11 PART 1 GENERAL 1.01 DESCRIPTION A. Furnish and install all equipment and accessories for a complete local, analog addressable, manually and automatically actuated,

More information

FIRE & LIFE SAFTEY STANDARD

FIRE & LIFE SAFTEY STANDARD Title: Effective Date: 01/01/14 Revised Date: 1/1/14 Code References: Title 16, Chapter 16.16 of the Roseville Municipal Code, NFPA 72 Note: This standard is a summary of Fire Department clarifications

More information

SECTION PANELBOARDS. A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section.

SECTION PANELBOARDS. A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section. PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section. 1.2 SUMMARY A. This Section includes the

More information

SECTION INTRUSION DETECTION

SECTION INTRUSION DETECTION (NOTE TO DESIGNER: These Specifications are basic minimum criteria to be met in preparing the final specifications for this section, which is the responsibility of the Designer.) SECTION 28 16 00 INTRUSION

More information

Michigan State University Construction Standards FIRE DETECTION AND ALARM PAGE

Michigan State University Construction Standards FIRE DETECTION AND ALARM PAGE PAGE 283100-1 SECTION 283100 - DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

SANTA ROSA FIRE DEPARTMENT FIRE PREVENTION BUREAU PLAN REVIEW CHECKLIST FIRE ALARM SYSTEM INSTALLATION

SANTA ROSA FIRE DEPARTMENT FIRE PREVENTION BUREAU PLAN REVIEW CHECKLIST FIRE ALARM SYSTEM INSTALLATION July 1, 2010 SANTA ROSA FIRE DEPARTMENT FIRE PREVENTION BUREAU PLAN REVIEW CHECKLIST FIRE ALARM SYSTEM INSTALLATION Address: Permit #: Inspector: Date: Status: Inspector: Date: Status: A-Approved; AC-Approved

More information

GROUP SR SPECIAL (ASSISTED SELF-PRESERVATION) OCCUPANCIES

GROUP SR SPECIAL (ASSISTED SELF-PRESERVATION) OCCUPANCIES [B] APPENDIX SR GROUP SR SPECIAL (ASSISTED SELF-PRESERVATION) OCCUPANCIES The provisions contained in this appendix are adopted by the Building Codes Division of the State of Oregon. SECTION SR101 GENERAL

More information

Agency for Health Care Administration

Agency for Health Care Administration Page 1 of 92 FED - K0000 - INITIAL COMMENTS Title INITIAL COMMENTS Type Memo Tag FED - K9999 - FINAL OBSERVATIONS Title FINAL OBSERVATIONS Type Memo Tag FED - KA100 - General Requirements - Other Title

More information

Agency for Health Care Administration

Agency for Health Care Administration Page 1 of 51 FED - K0000 - INITIAL COMMENTS Title INITIAL COMMENTS CFR Type Memo Tag FED - K0130 - MISCELLANEOUS Title MISCELLANEOUS OTHER LSC DEFICIENCY NOT ON 2786 FED - K9999 - FINAL OBSERVATIONS Title

More information

SANTA CLARA COUNTY Winchester Blvd., Los Gatos, CA (408) (408) (fax)

SANTA CLARA COUNTY Winchester Blvd., Los Gatos, CA (408) (408) (fax) FIRE DEPARTMENT SANTA CLARA COUNTY 14700 Winchester Blvd., Los Gatos, CA. 95032-1818 (408) 378-4010 (408) 378-9342 (fax) www.sccfd.org STANDARD DETAILS & SPECIFICATIONS Spec No C-4 Rev. Date 03/10/10 SUBJECT:

More information

SECTION ADDRESSABLE FIRE ALARM SYSTEM

SECTION ADDRESSABLE FIRE ALARM SYSTEM SECTION 16723 ADDRESSABLE FIRE ALARM SYSTEM 1 PART 1 GENERAL 1.1 DESCRIPTION A. This section outlines the requirements for the installation, programming and configuration of Addressable Fire Alarm System

More information

PLAN REVIEW SUBMITTAL GUIDE

PLAN REVIEW SUBMITTAL GUIDE PLAN REVIEW SUBMITTAL GUIDE Plans, specifications and other construction documentation for the initial plan review should be as complete as possible at the time of submittal. Use this convenient guide

More information

16.34 Multiplex Fire Alarm System Construction Standards Page 1 of 5

16.34 Multiplex Fire Alarm System Construction Standards Page 1 of 5 Construction Standards Page 1 of 5.1 General Description.1 The University requires that all new fire alarm system control panel, components, and devices, as required for the project, be Secutron 2900 Series

More information

Major Changes Nova Scotia Building Code 2011 Construction and Maintenance Regulatory Change Industry Briefing

Major Changes Nova Scotia Building Code 2011 Construction and Maintenance Regulatory Change Industry Briefing Major Changes Nova Scotia Building Code 2011 Construction and Maintenance Regulatory Change Industry Briefing Ted Ross Labour & Advanced Education Gerard Donahoe Labour & Advanced Education Overview Where

More information

The following information shall become and form part of the contract documents.

The following information shall become and form part of the contract documents. October 4, 206 To: Attention: Re: All Bidders All Bidders JCBE Gymnasium HVAC Upgrades BC#: 206433 Edmonds Project No.: BHM6090 All bidders, The following information shall become and form part of the

More information

Electrical Tech Note 107

Electrical Tech Note 107 Electrical Tech Note 107 Biosystems & Agricultural Engineering Department Michigan State University Understanding the Construction Code Rules, Part 8 1 Based on the 2014 NEC and the 2015 MRC The State

More information

SECTION ELECTRICAL GENERAL PROVISIONS

SECTION ELECTRICAL GENERAL PROVISIONS PART 1 GENERAL 1.01 SECTION INCLUDES A. General provisions for Electrical Systems B. Wire and cable for 600 volts and less. C. Wiring connectors. D. Electrical tape. E. Heat shrink tubing. F. Wire pulling

More information

1. Floor above/floor below notification. 2. Private alarm notification. 3. Not Used 4. Voice alarm notification. 5. Not Used.

1. Floor above/floor below notification. 2. Private alarm notification. 3. Not Used 4. Voice alarm notification. 5. Not Used. PART 1 GENERAL 1.01 Scope of Standard A. This Standard is intended to assure that fire alarm and signaling systems at Sam Houston State University provide the highest level of life safety possible. This

More information

SECTION P01 LIGHTING AND APPLIANCE PANELBOARDS - A-SERIES

SECTION P01 LIGHTING AND APPLIANCE PANELBOARDS - A-SERIES PART 1 GENERAL A. The requirements of the Contract, Division 1, and Division 16 apply to work in this Section. 1.01 SECTION INCLUDES A. Lighting and appliance panelboards 1.02 RELATED SECTIONS A. 16475,

More information

CONSTRUCTION DOCUMENTS U OF U BUILDING 72 REMODEL FOR EAE GSBS PROJECT NO

CONSTRUCTION DOCUMENTS U OF U BUILDING 72 REMODEL FOR EAE GSBS PROJECT NO CONTRACT DOCUMENTS ADDENDUM No. 1 April 25, 2016 University of Utah EAE remodel of Building 72 Project No. 21843 This Addendum forms a part of the Contract Documents and modifies the original Bidding Documents

More information

DEPARTMENT OF HEALTH AND HUMAN SERVICES K 011 K 011 NFPA 101 LIFE SAFETY CODE STANDARD

DEPARTMENT OF HEALTH AND HUMAN SERVICES K 011 K 011 NFPA 101 LIFE SAFETY CODE STANDARD CENTERS FOR MEDICARE & MEDICA SERVICES OMB NO. 0938-0391 (X1) PROVER/SUPPLIER/CLIA ENTIFICATION NUMBER: (X3) SURVEY NAME OF PROVER OR SUPPLIER PROVER'S PLAN OF CORRECTION K 011 NFPA 101 LIFE SAFETY CODE

More information

First Aspen Federal Regulation Set: K LSC 2000 Health Existing

First Aspen Federal Regulation Set: K LSC 2000 Health Existing First Aspen Federal Regulation Set: K 01.01 LSC 2000 Health Existing K 0000 Title CFR Type INITIAL COMMENTS Memo K 0011 If the building has a common wall with a nonconforming building, the common wall

More information

HOLUM EDUCATION CENTER. Architectural. January 13, 2014 DeForest Area School District

HOLUM EDUCATION CENTER. Architectural. January 13, 2014 DeForest Area School District HOLUM EDUCATION CENTER Architectural The existing building has approximately 41,823 square feet and sets on a lot about 4.14 acres in size. Parking lots are located along the east and west sides of the

More information

PROJ. NO SECTION PAGING, SPEAKERS AND HARD-WIRED CLOCK SYSTEMS

PROJ. NO SECTION PAGING, SPEAKERS AND HARD-WIRED CLOCK SYSTEMS SECTION 26 92 50 PAGING, SPEAKERS AND HARD-WIRED CLOCK SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

Fire & Life Safety Code Compliance. Common Safety Deficiencies and Tips for Compliance for Long Term Care and Skilled Nursing Facilities

Fire & Life Safety Code Compliance. Common Safety Deficiencies and Tips for Compliance for Long Term Care and Skilled Nursing Facilities Fire & Life Safety Code Compliance Common Safety Deficiencies and Tips for Compliance for Long Term Care and Skilled Nursing Facilities LTC, Skilled Nursing Facilities COMMON LIFE SAFETY DEFICIENCIES

More information

TABLE LIGHTING POWER DENSITIES FOR BUILDING EXTERIORS ASHRAE Uncovered Parking Areas. Building Grounds. Walkways 10 feet wide or greater

TABLE LIGHTING POWER DENSITIES FOR BUILDING EXTERIORS ASHRAE Uncovered Parking Areas. Building Grounds. Walkways 10 feet wide or greater TABLE 9.4.5 LIGHTING POWER DENSITIES FOR BUILDING EXTERIORS ASHRAE 90.1 Uncovered Parking Areas Parking Lots and drives Building Grounds Walkways less that 10 feet wide Walkways 10 feet wide or greater

More information

DMTF: Specific Building Recommendations

DMTF: Specific Building Recommendations DMTF: Specific Building Recommendations Asset Name Project Title Total Cost BLOCKER BUILDING 22,503,303 Capital Renewal 7,640,013 DOMESTIC WATER HEATER REPLACEMENT 16,374 EXTERIOR DOOR REPLACEMENT 133,623

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-23 83 00.00 20 (April 2006) -------------------------------- Preparing Activity: NAVFAC Replacing without change UFGS-15768N (September 1999) UNIFIED FACILITIES GUIDE

More information

Habitability Guidelines

Habitability Guidelines Habitability Guidelines for Relocated Manufactured Homes dced.pa.gov/mh @PADCEDnews Purpose The purpose of these habitability guidelines is to provide a reasonable level of assurance that the relocated

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 26 0519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

SANTA ROSA FIRE DEPARTMENT FIRE PREVENTION BUREAU INSPECTION CHECKLIST

SANTA ROSA FIRE DEPARTMENT FIRE PREVENTION BUREAU INSPECTION CHECKLIST July 1, 2010 SANTA ROSA FIRE DEPARTMENT FIRE PREVENTION BUREAU INSPECTION CHECKLIST FIRE AND LIFE SAFETY SYSTEMS FOR STRUCTURES FIVE OR MORE STORIES IN HEIGHT AND LESS THAN 75 FEET IN HEIGHT FROM THE POINT

More information

SECTION DIGITAL, ADDRESSABLE FIRE ALARM SYSTEM

SECTION DIGITAL, ADDRESSABLE FIRE ALARM SYSTEM SECTION 283111 DIGITAL, ADDRESSABLE FIRE ALARM PART 1 - GENERAL 1.1 GENERAL A. This Section includes the following: 1. Fire-alarm control panel. 2. Manual fire-alarm boxes. 3. Smoke detectors. 4. Heat

More information

PRINTED: 06/09/2017 FORM APPROVED CENTERS FOR MEDICARE & MEDICAID SERVICES OMB NO (X2) MULTIPLE CONSTRUCTION A. BUILDING 03 - A BUILDING

PRINTED: 06/09/2017 FORM APPROVED CENTERS FOR MEDICARE & MEDICAID SERVICES OMB NO (X2) MULTIPLE CONSTRUCTION A. BUILDING 03 - A BUILDING SUMMARY PROVER'S PLAN OF CORRECTION K 000 INITIAL COMMENTS K 000 A Life Safety Code Survey was conducted by the State Fire Marshal beginning on May 9th, 2017 and ending on May 10th, 2017. Adair Acute Care

More information

SECTION FIRE ALARM SYSTEMS

SECTION FIRE ALARM SYSTEMS SECTION 28 3100 PART 1 -GENERAL 1.01 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this

More information

CT CABINET AND UTILITY METERING WELL AND BOOSTER PUMP CONTROL 12"x12" WIREWAY 200A MCB 200A, 120/208V, 3Ø, 4W BOARD TVSS CIA ALARM 400A, DOUBLE-THROW SWITCH PORTABLE GENERATOR CONNECTION ENCLOSURE EXISTING

More information

CHAPTER 8 ELECTRICAL

CHAPTER 8 ELECTRICAL CHAPTER 8 0 8.1 GENERAL... 3 8.2 REQUEST FOR PROPOSAL DEVELOPMENT... 3 8.3 DESIGN DEVELOPMENT... 3 8.3.1 CONCEPT (30%) DESIGN SUBMITTAL REQUIREMENTS... 3 8.3.1.1 Concept Design Analysis... 3 8.3.1.1.1

More information

SECTION FIRE ALARM AND SMOKE DETECTION SYSTEMS

SECTION FIRE ALARM AND SMOKE DETECTION SYSTEMS PART 1 GENERAL 1.1 SECTION INCLUDES A. Fire alarm and smoke detection systems 1.2 REFERENCES A. NFPA 72 B. NFPA 101 1.3 REGULATORY REQUIREMENTS A. System: UL listed B. Conform to requirements of NFPA 101

More information

2016 CDM Smith All Rights Reserved July 2016 SECTION FIBER OPTIC DATA NETWORK

2016 CDM Smith All Rights Reserved July 2016 SECTION FIBER OPTIC DATA NETWORK PART 1 GENERAL 1.01 SCOPE OF WORK SECTION 27 12 23 FIBER OPTIC DATA NETWORK A. Furnish, install, terminate, and test all fiber optic equipment and cabling necessary for a complete and functional data highway

More information

IMPORTANT NOTICE BUILDERS AND CONTRACTORS WORKING IN NORTH RICHLAND HILLS, TEXAS. June 17th, 2016

IMPORTANT NOTICE BUILDERS AND CONTRACTORS WORKING IN NORTH RICHLAND HILLS, TEXAS. June 17th, 2016 IMPORTANT NOTICE BUILDERS AND CONTRACTORS WORKING IN NORTH RICHLAND HILLS, TEXAS June 17th, 2016 RE: City Council Adopts 2014 National Electrical Code with Pool Alarm Requirements On April 25th, 2016 the

More information

Lake County / Multi-Department Storage Facility / Project / December 12, 2016 SECTION DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM

Lake County / Multi-Department Storage Facility / Project / December 12, 2016 SECTION DIGITAL, ADDRESSABLE FIRE-ALARM SYSTEM PART 1 - GENERAL 1.1 RELATED DOCUMENTS SECTION 283111 A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to

More information

SECTION AUTOMATIC TRANSFER SWITCHES

SECTION AUTOMATIC TRANSFER SWITCHES SECTION 26 36 23 AUTOMATIC TRANSFER SWITCHES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. General provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information