Albany County School District No. 1 New Slade Elementary School Project Preliminary Schematic Design Meeting Minutes October 20, 2015

Size: px
Start display at page:

Download "Albany County School District No. 1 New Slade Elementary School Project Preliminary Schematic Design Meeting Minutes October 20, 2015"

Transcription

1 Albany County School District No. 1 New Slade Elementary School Project Preliminary Schematic Design Attendees: Organization: Jubal Yennie ACSD#1 Superintendent jyennie@acsd1.org Ed Goetz ACSD#1 Business Manager egoetz@acsd1.org Heather Moro ACSD#1 Principal Slade School hmoro@acsd1.org Ashley McKinney ACSD#1 2 nd Grade Teacher amckinney@acsd1.org Cari Warren ACSD#1 Title One Teacher cwarren@acsd1.org Connie Bassett ACSD#1 Music Teacher cjbassett@acsd1.org Chris Rothfuss Wyoming Senator chris.rothfuss@wyoleg.gov David Hansen Parent Volunteer dhanse21@uwyo.edu Dave Bennett ACSD#1 Director of Maintenance dbennett@acsd1.org Christopher Livingston ACSD#1 4 th Grade Teacher clivingston@acsd1.org Mary Thorsness ACSD#1 Trustee mthorsness@acsd1.org Steve Slyman Director of Individualized Instruction slymans@acsd1.org Ruth Castor ACSD#1 Board Member rcastor@acsd1.org John Weigel ACSD#1 Asst. Superintendent jweigel@acsd1.org Dan Odasz Plan One/Architects dodasz@planone.com Taylor Lee Plan One/Architects tlee@planone.com Ron Yount Plan One/Architects ryount@planone.com Distribution: All attendees and: Kathy Walsh Community Member klwalsh05@aol.com Kacee Schutterle Community Member kaceeks@hotmail.com Tony Czech Director of Technology and Comm. tony@acsd1.org Randy Hunt City of Laramie rhunt@cityoflaramie.org Kevin Troyer Terracon Environmental Services kmtroyer@terracon.com Mark McGuire Cator Ruma mmcguire@catorruma.com Joe Hall KL&A, Inc. jhall@klaa.com Greg Shavlik KL&A, Inc. gshavlik@klaa.com Craig Shavlik JLM Engineering cshavlik@jlmengineering.com Michael Miles H-C Design & Consulting michael@h-cdesign.com Summary: This meeting was held with the Design Advisory Group at the Slade Elementary School library. The purpose of the meeting was for the Design Team to present the preliminary schematic design to the group, which included a site plan, floor plan, and 3D imagery. The images of each are attached herein, including the design concepts there were discussed:

2 Page 2 1. Site Plan: The site plan incorporated the following design concepts: a. Vehicular Traffic: i. Bus Drop Off: The bus loop is located on the north side of the site, off of Reynolds Street. This allows the bus loop to be located closer to the school, near the dining room on the north side of the building. It also removes the busses off of Shield Street, which cleans up the site circulation and does not congest the site near the main entrance. ii. Parent Drop Off: The parent drop off is located near the main entrance, parallel to the K-1 wing. This is an ideal location, as parents will be very close to both the main entrance and the pre-kindergarten rooms. iii. Visitor Parking: The visitor parking is located on the south end of the site, next to the parent drop-off loop. It is positioned in a way so as to not cross pedestrian traffic on the parent drop off loop. It is still located

3 Page 3 near the main entrance, but off to one side of this area, which allows for a nicer front approach to the main entrance. iv. Staff Parking: Located in close proximity to Administration and Dining areas, the access to staff parking is off an arterial street along with deliveries and service access. Main traffic for these functions is kept separate from parent drop-off and visitor parking. b. Site Features i. Raised Bed Gardens: The garden will have southern exposure for optimal sunlight with close proximity to the entry for visual presentation. The location is also close to Dining for healthy eating demonstrations and interactive opportunity. ii. Natural Amphitheater: Just outside the Administration area, the double-purposed fire lane access is visually enhanced without impeding on access for site maintenance and the fire lane. This is also a viable exterior classroom learning experience. iii. Exterior Courtyards: Outside each wing there are protected areas for outdoor learning, passive activities, and exterior dining opportunities. These can minimize outdoor play distractions for classrooms while experiencing an outdoor environment. c. Playgrounds i. Locations: Pre-Kindergarten and Kindergarten playgrounds are located near the K-1 wing. Age appropriate separated play spaces create segregated use of the site area. ii. Perimeters: The entire area is secured by a perimeter fence. A tree windbreak and raised berm protect from prevailing west winds in the area. The tree line and berm will be positioned in a way to not compromise the view from the street for authorities. 2. Floor Plan: The floor plan incorporated the following design concepts: a. Specialty Rooms i. Science 3D Exploratorium: This space is located near dining for expanded lessons and displays. It also features exterior access for exterior learning opportunities. b. Corridors i. 3-Wing Concept: This allows for shorter corridors for all grades, with efficient use of space. The wings are separated into K-1, 2-3, and 4-5 for age appropriate separation. Each wing will feature various pull-out spaces (cul-de-sacs) for PLC s and other various team teaching uses. c. Solar Orientation i. Wings: Each wing rotates an average of 15 degrees from south for optimal solar orientation. This will allow for proper daylight, reduced late afternoon glare, and low solar heat-gain from the west.

4 Page 4 d. Entries i. North: This entrance is located off the bus loop for drop-off and close proximity to the dining for the breakfast program. There will also be direct access to the west courtyards and playgrounds. ii. South: The Main Entry is directly off the drop-off loop. The administration area is located adjacent to the front entrance for enhanced supervision. There is also a security vestibule for controlled entrance to the facility. iii. East: The staff parking area, located to the east of the facility, will have several entrances into the building. There will be a direct corridor that leads to the front office administration area, and another entry that will lead through the dining area and into the main mall. iv. Pre-K and Kindergarten: This separate entry is adjacent to the drop-off loop and is set apart specially for this age group. e. Central Mall i. Concept: This raised spine runs through the length of the building with clerestory natural light infiltrating all the way through. Roof top units are screened from view, located strategically at each wing on flat roof areas. ii. Spaces: Shared space and multi-use areas are located throughout the central mall for equivalent access from each wing. iii. Administration: This administration area is located with good visual observation of the central area, entrance, and front parent drop off.

5 Page 5

6 Page D Imagery: The first 3D imagery of the school was presented to the group. The following design features were discussed: a. Front Entrance: The front entrance will be situated directly off the parent drop off loop, and will be a raised form to denote entry. The raised spine will continue throughout the central mall in order to provide adequate volume within the multi-use areas, as well as allow for natural daylight entering in from the clerestory windows. b. Wing Design: The current design includes gable forms on each wing, as they are an efficient method and blend well with the surrounding architecture in the area. This will also allow for the potential of covered roof top units on the roof in order to protect them from the weather. c. Materials: Although still quite early in design, the current thought is to use durable materials such as brick veneer and steel paneling.

7 Page 7

8 Page 8 4. Closing Comments: The group was asked to offer one item to the group that was of importance to them: a. Movable Wall at Music Room: There is initial concern over having an operable wall at the music room due to sound transmission to adjacent spaces, however this should be alleviated based on careful planning of neighboring areas and construction methods. b. Teacher Input: The group appreciated being heard and seeing the design begin to take shape based off of teacher and staff input. c. Cul-De-Sacs: The teaching staff realized the importance of the cul-de-sac and how important the design of them will be for proper utilization and efficient use of space. d. Planning for the Future: It is very important to plan for the future; not only for each wing having available room to grow, but other spaces as well, including the dining room and kitchen. e. Built In Scalability: In regards to future growth, having a scalable plan that can grow with the population is of great importance. f. Responsiveness: The group appreciated the quick response of the design group. g. Bus Loop: It was mentioned that the bus loop location must be part of the 9 total developed acres on site. h. Special Education: The group had questions about the amount of special education space that was shown. The design team mentioned that the floor plan is still schematic and not all spaces were shown, but they will all be accounted for on future plan iterations. i. Similar Schools: One individual mentioned that the school resembled the Indian Paintbrush school in Laramie, but with 3 classroom wings. j. Parking: The committee is very excited about the amount of available parking that the new facility will have. k. Daylighting: The team loves the idea of natural daylight at each classroom, including the central mall area at the center of the school. Conclusion: One major question the group had was assurance that there would be adequate room for each space on the facility list. As the plan that was presented was still fairly schematic and did not detail the rooms in full, Plan One/Architects assured the group that each space on the facility list would be accounted for. After this meeting took place, the Design Team was able to meet with Heather Moro for a focused workshop dealing with the revised floor plan. Plan One was able to input all spaces and their appropriate sizes from the facility list. The items discussed will be more detailed in the minutes from that meeting. If any of the above information is believed to be incorrect or incomplete, please notify Plan One/Architects as soon as possible. Minutes by: Taylor Lee, AIA

Solana Ranch Elementary School

Solana Ranch Elementary School 2015 Exhibition of School Planning and Architecture Solana Ranch Elementary School Category: New Construction Solana Beach School District Solana Beach, CA Project name Project name Landscape Plan Community

More information

UNCW CAMPUS MASTER PLAN

UNCW CAMPUS MASTER PLAN UNCW CAMPUS MASTER PLAN JULY 27, 2017 MASTER PLAN FRAMEWORK RECOMMENDATIONS BOARD OF TRUSTEES PRESENTATION UNCW Campus Master Plan Update Board of Trustees Presentation July 27, 2017 The attached Campus

More information

WESTERN ILLINOIS UNIVERSITY

WESTERN ILLINOIS UNIVERSITY WESTERN ILLINOIS UNIVERSITY Quad Cities Riverfront Campus Master Plan March 1, 2006 Preliminary Master Plan Total Site Build Out Western Illinois University Quad Cities Municipal Park Mississippi River

More information

E. RURAL COMMERCIAL/INDUSTRIAL PARK MODEL

E. RURAL COMMERCIAL/INDUSTRIAL PARK MODEL E. RURAL COMMERCIAL/INDUSTRIAL PARK MODEL 1. PURPOSE The purpose of the Rural Commerce/Industrial Park Model is to provide parameters within which a grouping of business buildings with parking, loading

More information

Planned Residential Neighborhoods Land Use Goals

Planned Residential Neighborhoods Land Use Goals Planned Residential Neighborhoods Land Use Goals Issue: Guidelines that provide for diverse high quality residential areas that include a variety of housing styles and layouts are needed. Goal 1: Create

More information

HALF MOON BAY CATHOLIC ELEMENTARY SCHOOL SITE PLAN CONTROL DESIGN BRIEF

HALF MOON BAY CATHOLIC ELEMENTARY SCHOOL SITE PLAN CONTROL DESIGN BRIEF HALF MOON BAY CATHOLIC ELEMENTARY SCHOOL SITE PLAN CONTROL DESIGN BRIEF February 12, 2015 BRYDEN MARTEL ARCHITECTS INCORPORATED 1066 somerset street west, suite 200, ottawa, ontario K1Y 4T3 tel: (613)

More information

Workshop 3. City of Burlington Waterfront Hotel Planning Study. September 14, The Planning Partnership

Workshop 3. City of Burlington Waterfront Hotel Planning Study. September 14, The Planning Partnership Workshop 3 City of Burlington Waterfront Hotel Planning Study September 14, 2017 The Planning Partnership The Waterfront Hotel Planning Study 01 The Brant & Lakeshore Planning Study will establish a Strategic

More information

AGENDA. 1. Call to Order. 2. Approval of Minutes. 3. Approval of Invoices and Commitments. 4. Review Updated Site Analysis and Permitting

AGENDA. 1. Call to Order. 2. Approval of Minutes. 3. Approval of Invoices and Commitments. 4. Review Updated Site Analysis and Permitting PROJECT MANAGEMENT AGENDA Project: George Keverian School Feasibility Study Project No.: 16049 Re: School Building Committee Meeting Meeting Date: 3/22/2017 Meeting Location: Mayor s Conference Room, City

More information

This Review Is Divided Into Two Phases:

This Review Is Divided Into Two Phases: Semiahmoo Town Centre Review The purpose of this review: To review the Semiahmoo Town Centre Concept Plan, originally approved in 1993, to ensure that this centre will continue to serve the needs of South

More information

2014 Exhibition of School Planning and Architecture

2014 Exhibition of School Planning and Architecture 2014 Exhibition of School Planning and Architecture PARKSIDE ELEMENTARY Des Moines, WA A replacement elementary school for highline public schools PARKSIDE ELEMENTARY SCHOOL PARKSIDE ELEMENTARY SCHOOL

More information

Davisville/Spectrum Rebuild NSRT Meeting Tuesday March , 7 pm Hodgson Senior Public School 282 Davisville Avenue (Gym)

Davisville/Spectrum Rebuild NSRT Meeting Tuesday March , 7 pm Hodgson Senior Public School 282 Davisville Avenue (Gym) Davisville/Spectrum Rebuild NSRT Meeting Tuesday March 30 2017, 7 pm Hodgson Senior Public School 282 Davisville Avenue (Gym) Present: Shelley Laskin - Trustee, Ian Allison Superintendent of Education,

More information

Design and Sustainability for Winter Operations

Design and Sustainability for Winter Operations Design and Sustainability for Rational: For Operations staff to be more involved in the Design of our road infrastructure. What gets designed and built by others, Becomes our maintenance legacy The Regional

More information

Lehigh Acres Land Development Regulations Community Planning Project

Lehigh Acres Land Development Regulations Community Planning Project Lehigh Acres Land Development Regulations Planning Effort Summary In July, 2010 Commissioner Frank Mann invited the Lehigh Acres community to start discussing how to achieve their recently adopted community

More information

LOS ANGELES MISSION COLLEGE MASTER PLAN Master Plan DESIGN & DEVELOPMENT PRINCIPLES

LOS ANGELES MISSION COLLEGE MASTER PLAN Master Plan DESIGN & DEVELOPMENT PRINCIPLES LOS ANGELES MISSION COLLEGE MASTER PLAN DESIGN & DEVELOPMENT PRINCIPLES 34 Quality Learning Along the Arroyo PROGRAM SUMMARY BY PROJECT The following are program summaries for each of the projects planned

More information

Master Facility Planning Update School Board Meeting May 26, 2016

Master Facility Planning Update School Board Meeting May 26, 2016 Master Facility Planning Update School Board Meeting May 26, 2016 Master Facilities Committee Overview Reflection of Committee Work Review of District Wide Facility Issues Identified District Wide Facility

More information

CITY OF GARDEN CITY. Garden City Design Review Committee Staff Contact: Chris Samples STAFF REPORT: DSRFY Page 1

CITY OF GARDEN CITY. Garden City Design Review Committee Staff Contact: Chris Samples STAFF REPORT: DSRFY Page 1 Page 1 CITY OF GARDEN CITY 6015 Glenwood Street Garden City, Idaho 83714 Phone (208)472-2921 Fax (208)472-2926 File Number: DSRFY2018-12 For: Brilliant Services - New Commercial Structure Location: 211

More information

III. PROJECT DESCRIPTION

III. PROJECT DESCRIPTION III. PROJECT DESCRIPTION LOCATION AND BOUNDARIES The City of Manhattan Beach is located in the South Bay region of Los Angeles County, California, approximately 2 miles south of the Los Angeles International

More information

Section 9 NEIGHBORHOOD DESIGN

Section 9 NEIGHBORHOOD DESIGN Section 9 NEIGHBORHOOD DESIGN City of Lancaster Comprehensive Plan D u n k i n, S e f k o & A s s o c i a t e s, I n c. NEIGHBORHOOD DESIGN INTRODUCTION There are many ways in which a neighborhood can

More information

Simple Security Improvements Can Go A Long Way

Simple Security Improvements Can Go A Long Way Simple Security Improvements Can Go A Long Way James Henderson, AIA and William Laughlin, AIA, REFP As communities across our nation seek to understand the tragedies that have struck schools, the safety

More information

December 1, 2014 (revised) Preliminary Report -- Thomas Jefferson Site Evaluation

December 1, 2014 (revised) Preliminary Report -- Thomas Jefferson Site Evaluation December 1, 2014 (revised) TO: FROM: RE Arlington County Board Thomas Jefferson Site Evaluation Working Group by Carrie Johnson, Chair Preliminary Report -- Thomas Jefferson Site Evaluation The Thomas

More information

2014 Exhibition of School Planning and Architecture. White Hill Middle School Campus Master Plan & Design. Ross Valley School District Fairfax, CA

2014 Exhibition of School Planning and Architecture. White Hill Middle School Campus Master Plan & Design. Ross Valley School District Fairfax, CA 2014 Exhibition of School Planning and Architecture White Hill Middle School Campus Master Plan & Design Ross Valley School District Fairfax, CA Main Exterior Image Main Exterior Image Main Site Diagram

More information

14 October 10, 2012 Public Hearing APPLICANT: MPB, INC

14 October 10, 2012 Public Hearing APPLICANT: MPB, INC 14 October 10, 2012 Public Hearing APPLICANT: MPB, INC PROPERTY OWNER: MUNDEN & ASSOCIATES, LP STAFF PLANNER: Karen Prochilo REQUEST: Conditional Change of Zoning (AG-1 & AG-2 to Conditional O-2) ADDRESS

More information

Pomegranate Center and Tully s Coffee Gathering Grounds program partnership Butterfly Park Gathering Place Project Preliminary Design I.

Pomegranate Center and Tully s Coffee Gathering Grounds program partnership Butterfly Park Gathering Place Project Preliminary Design I. Pomegranate Center and Tully s Coffee Gathering Grounds program partnership Pomegranate Center, ARTS /A Reason To Survive, Olivewood Gardens, San Diego Foundation, and City of National City Butterfly Park

More information

Chapter 13 Residential Areas: Appendices APPENDIX 1 Residential Areas

Chapter 13 Residential Areas: Appendices APPENDIX 1 Residential Areas Chapter 13 Residential Areas: Appendices Page 1 Chapter 13 Residential Areas: Appendices APPENDIX 1 Residential Areas Design Code for Intensive Housing INTRODUCTION DESIGN ELEMENTS A NEIGHBOURHOOD DESIGN

More information

PROTOTYPE DESIGN/INTRODUCTION

PROTOTYPE DESIGN/INTRODUCTION PART III: PROTOTYPE DESIGN These concepts and guidelines described earlier were used to develop a prototype design for an emerging suburban area located west of the City of Milwaukee. This was done to

More information

This is the East Carolina University Comprehensive Facilities Master Plan Final Draft Plan Review. This workbook reviews the campus draft master plan

This is the East Carolina University Comprehensive Facilities Master Plan Final Draft Plan Review. This workbook reviews the campus draft master plan This is the East Carolina University Comprehensive Facilities Master Plan Final Draft Plan Review. This workbook reviews the campus draft master plan first presented on campus on June 29 and June 30, 2011.

More information

West Loop. Neighborhood Plan. Prepared by: Neighbors of West Loop, Chicago, IL August 14, 2018

West Loop. Neighborhood Plan. Prepared by: Neighbors of West Loop, Chicago, IL August 14, 2018 West Loop Neighborhood Plan Prepared by: Neighbors of West Loop, Chicago, IL August 14, 2018 Introduce Neighbors of West Loop (NoWL) Present the draft Neighborhood Plan Gather your input Identify ways

More information

Higher Education Energy Efficiency Partnership Program BEST PRACTICES AWARDS

Higher Education Energy Efficiency Partnership Program BEST PRACTICES AWARDS Higher Education Energy Efficiency Partnership Program BEST PRACTICES AWARDS UC / CSU Sustainability Conference, June 2005 A program created by the UC/CSU/IOU Partnership under the auspices of the California

More information

Sustainable Strategies for School Development in Urbanizing Areas

Sustainable Strategies for School Development in Urbanizing Areas Sustainable Strategies for School Development in Urbanizing Areas A1 A2 A Corridor School as a part of a mixed- use development in Arlington VA PRECEDENT ANALYSIS Elementary Schools in different contexts

More information

WESTERN ILLINOIS UNIVERSITY

WESTERN ILLINOIS UNIVERSITY WESTERN ILLINOIS UNIVERSITY Quad Cities Riverfront Campus Preliminary Master Plan Presentation 2 February 1, 2006 Achieving Future Flexibility 1. Monitor space needs as the new buildings come on line and

More information

Food Literacy Workshops

Food Literacy Workshops LFS 350, Group 20 Food Literacy Workshops Proposal for Project at David Livingstone Elementary School Ann Cribb, Emma Louie, Jasminder Brar, John Tseng, Katie Kennedy & Suzanna Su October 9, 2016 I. Introduction

More information

University of Illinois Business Instructional Facility LEED Gold Design. University of Illinois Business Instructional Facility

University of Illinois Business Instructional Facility LEED Gold Design. University of Illinois Business Instructional Facility LEED Gold Design University of Illinois LEED Gold Design Keys to success: Sustainable design strategies included early. Clear and early benchmarking choice. Integrated design process. Consensus building.

More information

Subject: City of Richfield Cedar Avenue Corridor Plan Comprehensive Plan Amendment, Review File No

Subject: City of Richfield Cedar Avenue Corridor Plan Comprehensive Plan Amendment, Review File No Committee Report Business Item No. 2017-21 Community Development Committee For the Metropolitan Council meeting of January 25, 2017 Subject: City of Richfield Cedar Avenue Corridor Plan Comprehensive Plan

More information

Welcome! Community Meeting FOR YOUR NEW WEBBER PARK LIBRARY

Welcome! Community Meeting FOR YOUR NEW WEBBER PARK LIBRARY Community Meeting FOR YOUR NEW WEBBER PARK LIBRARY Tuesday, April 21, 6 p.m. to 7:30 p.m. Webber Community Center Multipurpose Room 4400 Dupont Ave. N., Minneapolis, MN 55412 Welcome! Please join Hennepin

More information

CITY OF CHARLOTTESVILLE, VIRGINIA CITY COUNCIL AGENDA

CITY OF CHARLOTTESVILLE, VIRGINIA CITY COUNCIL AGENDA CITY OF CHARLOTTESVILLE, VIRGINIA CITY COUNCIL AGENDA Agenda Date: December 16, 2013 Action Required: Adoption of Resolution Presenter: Staff Contacts: Title: James E. Tolbert, AICP, Director of NDS James

More information

Regency Developments. Urban Design Brief. Holyrood DC2 Rezoning

Regency Developments. Urban Design Brief. Holyrood DC2 Rezoning Regency Developments Urban Design Brief Holyrood DC2 Rezoning Stantec Consulting Ltd. 7-31-2017 1. Overview Regency Developments intends to rezone the lands located at 8510 and 8511 93 Avenue, within the

More information

Introduction Each adult working at the School will familiarise themselves with a copy of the detailed fire and evacuation procedure for the school.

Introduction Each adult working at the School will familiarise themselves with a copy of the detailed fire and evacuation procedure for the school. Policy and Procedure: Fire and Evacuation Procedure Date of Board Approval: April 2018 Updated September 2018 Review date: September 2019 Introduction Each adult working at the School will familiarise

More information

STAFF SUMMARY FOR S17-02 SPECIAL USE PERMIT APPLICATION

STAFF SUMMARY FOR S17-02 SPECIAL USE PERMIT APPLICATION APPLICATION SUMMARY Case Number: S17-02 Request: STAFF SUMMARY FOR S17-02 SPECIAL USE PERMIT APPLICATION SUP application in order to develop a convenience food store. Applicant: Property Owner(s): Cindee

More information

Little Mountain UDP Presentation

Little Mountain UDP Presentation Summary of UDP Evaluation of Dec 2015 Plan Dec 2015 Site Plan Transitional edges work well Central spine and permeability are strong Tree retention is good Establish Big Idea Sameness of built form contributes

More information

Urban Design Brief 1576 Richmond Street City of London

Urban Design Brief 1576 Richmond Street City of London Urban Design Brief City of London Treadstone Developments October 31, 2014 Urban Design Brief October 31, 2014 TABLE OF CONTENTS Page No. INTRODUCTION... 1 SECTION 1 LAND USE PLANNING CONCEPT... 1 1.1

More information

CHAPTER FOUR: DEVELOPMENT AND DESIGN

CHAPTER FOUR: DEVELOPMENT AND DESIGN CHAPTER FOUR: DEVELOPMENT AND DESIGN 4.1 Introduction This Chapter presents development and design plans and guidelines, including design concepts for focus areas, and states implementation measures for

More information

Please take time to view our latest plans, speak to the development team and ask any questions you may have. EALING BROADWAY A4020

Please take time to view our latest plans, speak to the development team and ask any questions you may have. EALING BROADWAY A4020 WELCOME Durston House School is a successful school in the heart of Ealing. With 90 per cent of our pupils living in the borough, we have a strong connection to the local area. We are proposing to consolidate

More information

City of Redlands Architectural Guidelines for Non-Residential Development

City of Redlands Architectural Guidelines for Non-Residential Development 14. Building articulation shall be included in the design of building, in order to create a formal entry statement. Avoid this Do this Page 11 15. Give special attention to creating pedestrian scale and

More information

Preci nct P l ans Figure 56 Campus Aerial Photo, 2008 CAL STATE EAST BAY, HAYWARD CAMPUS MASTER PLAN

Preci nct P l ans Figure 56 Campus Aerial Photo, 2008 CAL STATE EAST BAY, HAYWARD CAMPUS MASTER PLAN 9 Precinct Plans This section contains a detailed discussion of the planning and design concepts for specific areas or precincts of the Cal State East Bay Hayward campus. The Precinct Plans pertain to

More information

Allisonville Elementary School Facilities Highlights Built: 1960 Last Major Renovation: 28 years ago Capacity: 650 Current Enrollment: 767

Allisonville Elementary School Facilities Highlights Built: 1960 Last Major Renovation: 28 years ago Capacity: 650 Current Enrollment: 767 Allisonville Elementary School Built: 1960 Last Major Renovation: 28 years ago Capacity: 650 Current Enrollment: 767 ADA improvements are Fire alarms need to be updated Playground equipment needs to be

More information

Urban Design Brief Proposed Residential Development 5219 Upper Middle Road City of Burlington

Urban Design Brief Proposed Residential Development 5219 Upper Middle Road City of Burlington Urban Design Brief Proposed Residential Development 5219 Upper Middle Road City of Burlington Prepared by Weston Consulting Prepared for BLOOMFIELD DEVELOPMENT INC. Date: March 2017 Table of Contents 1.

More information

MEMORANDUM. I2 District Downtown Parking Overlay District 24,000 square feet /.55 acres. Industrial Employment District North Loop Small Area Plan

MEMORANDUM. I2 District Downtown Parking Overlay District 24,000 square feet /.55 acres. Industrial Employment District North Loop Small Area Plan Department of Community Planning & Economic Development 50 South 4th Street, Room 300 Minneapolis, MN 5545-385 MEMORANDUM To: City Planning Commission, Committee of the Whole Prepared By: Peter Crandall,

More information

Route 7/15 Norwalk. Route 7/15 Norwalk Project Project Advisory Committee Meeting #5. Wednesday, November 14 th, Norwalk City Hall

Route 7/15 Norwalk. Route 7/15 Norwalk Project Project Advisory Committee Meeting #5. Wednesday, November 14 th, Norwalk City Hall Route 7/15 Norwalk Project Project Advisory Committee Meeting #5 Route 7/15 Norwalk PAC Meeting #5 November 14, 2018 Wednesday, November 14 th, Norwalk City Hall Route 7/15 Norwalk - AGENDA Introductions

More information

SCHEMATIC DESIGN PRESENTATION

SCHEMATIC DESIGN PRESENTATION August 5, 2014 SCHEMATIC DESIGN PRESENTATION ADDITIONS & RENOVATIONS Greenville Independent School District Acknowledgments 2 Narrative 3-6 Crockett Elementary School 7-12 L.P. Waters Early Childhood Center

More information

Department of Neighborhood & Development Services 1565 First Street, RM 301, Sarasota, Florida Phone: (941)

Department of Neighborhood & Development Services 1565 First Street, RM 301, Sarasota, Florida Phone: (941) City of Sarasota Department of Neighborhood & Development Services 1565 First Street, RM 301, Sarasota, Florida 34236 Phone: (941) 954-2612 Application No. 15-CW-13 To: Meeting Attendees Date: July 1,

More information

Wold Architects and Engineers. 332 Minnesota Street Suite W2000 Saint Paul, MN

Wold Architects and Engineers. 332 Minnesota Street Suite W2000 Saint Paul, MN Wold Architects and Engineers 332 Minnesota Street Suite W2000 Saint Paul, MN 55101 651 227 7773 PLANNERS ARCHITECTS ENGINEERS ISD #15 St. Francis Area Schools East Bethel Elementary School Additions and

More information

CITY COUNCIL STUDY SESSION MEMORANDUM

CITY COUNCIL STUDY SESSION MEMORANDUM City and County of Broomfield, Colorado CITY COUNCIL STUDY SESSION MEMORANDUM To: From: Prepared by: Mayor and City Council Charles Ozaki, City and County Manager Kevin Standbridge, Deputy City and County

More information

REQUEST FOR COUNCIL ACTION 6A AGENDA ITEM ORIGINATING DEPT. AGENDA ITEM CITY ADMINISTRATOR APPROVAL

REQUEST FOR COUNCIL ACTION 6A AGENDA ITEM ORIGINATING DEPT. AGENDA ITEM CITY ADMINISTRATOR APPROVAL DATE REQUEST FOR COUNCIL ACTION 6A AGENDA ITEM ORIGINATING DEPT. AGENDA ITEM CITY ADMINISTRATOR APPROVAL Community Development Territorial Greens PUD Concept Plan Development Stage Plan Subdivision (Preliminary

More information

New School Construction: Safe School Opening. OAR and IOR Joint Training February 17, 2005

New School Construction: Safe School Opening. OAR and IOR Joint Training February 17, 2005 New School Construction: Safe School Opening OAR and IOR Joint Training February 17, 2005 1 Purpose Provide information on process moving from construction to occupancy and opening schools 2 School Opening

More information

2014 Exhibition of School Planning and Architecture

2014 Exhibition of School Planning and Architecture 2014 Exhibition of School Planning and Architecture Quarry Park Corporate Child Care Facility Private development Calgary, Alberta Quarry Park Corporate Child Care Facility Main Exterior Image Quarry Park

More information

STAFF SUMMARY FOR S17-02 SPECIAL USE PERMIT APPLICATION

STAFF SUMMARY FOR S17-02 SPECIAL USE PERMIT APPLICATION APPLICATION SUMMARY Case Number: S17-02 Request: STAFF SUMMARY FOR S17-02 SPECIAL USE PERMIT APPLICATION SUP application in order to develop a convenience food store. Applicant: Property Owner(s): Cindee

More information

Alternatives Development Three conceptual alternatives were developed for the Race Road/Jessup Village Planning Study and are described below:

Alternatives Development Three conceptual alternatives were developed for the Race Road/Jessup Village Planning Study and are described below: Race Road/Jessup Village Planning Study (H550601) Project Newsletter Spring 2015 Project Description The Study Team, consisting of staff from Anne Arundel County (Department of Public Works and Department

More information

U n i v e r s i t y o f S o u t h C a r o l i n a A i k e n. Land Plan Study

U n i v e r s i t y o f S o u t h C a r o l i n a A i k e n. Land Plan Study U n i v e r s i t y o f S o u t h a r o l i n a A i k e n Land Plan Study 06.27.2008 Goals ampus Growth Develop a Land Plan that allows for the orderly expansion of the campus over the next ten years and

More information

CAMPUS MASTER PLAN DRAFT PLAN UPDATE JANUARY

CAMPUS MASTER PLAN DRAFT PLAN UPDATE JANUARY NEW MEXICO HIGHLANDS UNIVERSITY CAMPUS MASTER PLAN DRAFT PLAN UPDATE JANUARY 27 2010 MASTER PLANNING GOALS TO BALANCE THE STRATEGIC GOALS OF THE UNIVERSITY WITH THE PHYSICAL CAMPUS through the assessment

More information

DESIGN REVIEW COMMITTEE AGENDA ITEM

DESIGN REVIEW COMMITTEE AGENDA ITEM DESIGN REVIEW COMMITTEE AGENDA ITEM AGENDA DATE: AUGUST 2, 2017 TO: THRU: FROM: SUBJECT: Chair Imboden and Members of the Design Review Committee Anna Pehoushek, Assistant Community Development Director

More information

Redemption Prayer Garden Plan Overview

Redemption Prayer Garden Plan Overview Redemption Prayer Garden Plan Overview The Coryell Community Church in Gatesville, Texas is growing and is planning several new and very interesting projects. The Church has grown from 19 members in 2001

More information

18 May 2016 CAMPUS MASTER PLAN UPATE

18 May 2016 CAMPUS MASTER PLAN UPATE 18 May 2016 CAMPUS MASTER PLAN UPATE Council of the Deans ( Over view) AGENDA Engagement & What We Heard Focus Elements: 1. Development Framework Plan 2. Campus Mobility 3. Campus Guidelines 4. Wayfinding

More information

Master Site Development Plan (MSDP) Rocky View County Campus at Balzac East

Master Site Development Plan (MSDP) Rocky View County Campus at Balzac East Master Site Development Plan (MSDP) Rocky View County Campus at Balzac East Balzac East, Alberta July 2009 CONTENTS 1.0 purpose 1 2.0 guiding principles 2 3.0 site description 3 4.0 site analysis and county

More information

Danvers High Street I-1 District Study

Danvers High Street I-1 District Study Danvers High Street I-1 District Study Presentation of Final Recommendations Planning Board Presentation June 26 th, 2018 1 Introductions Metropolitan Area Planning Council Sam Cleaves AICP, Principal

More information

APPENDIX C: PUBLIC INPUT SUMMARY

APPENDIX C: PUBLIC INPUT SUMMARY APPENDIX C: PUBLIC INPUT SUMMARY OVERVIEW The public process for the development of the GO! Green Oshtemo Plan was designed to follow both the legislative requirements for master plan adoption and the

More information

PROCTOR TERRACE ELEMENTARY SCHOOL

PROCTOR TERRACE ELEMENTARY SCHOOL SCHL DAA Address: Bryden Lane Santa Rosa, CA 95404 Established: 50 Permanent Classrooms: 3 Portable Classrooms: 9 Building Area: Site Area: 40, sq ft 5 acres Students in 5: 484 Students in (Projected):

More information

Cherry Hill Public Schools BUILDING A SOLID FUTURE

Cherry Hill Public Schools BUILDING A SOLID FUTURE Cherry Hill Public Schools BUILDING A SOLID FUTURE Who We Are The Cherry Hill School District is the 12 th largest in the state, serving 11,500 students 19 Locations 2 High Schools, 3 Middle Schools, 12

More information

EMERYVILLE PLANNING COMMISSION STAFF REPORT

EMERYVILLE PLANNING COMMISSION STAFF REPORT EMERYVILLE PLANNING COMMISSION STAFF REPORT Agenda Date: Report Date: April 19, 2012 TO: FROM: SUBJECT: Planning Commission Planning and Building Department Miroo Desai, Senior Planner (ECCL) (UPDR12-001)

More information

City of Heath. Town Center Concept

City of Heath. Town Center Concept In the give-and-take of getting projects designed, financed, and approved, the famous refrain from the film Field of Dreams is heard often: if you build it, they will come. From the perspective of the

More information

Smart Growth Development Checklist

Smart Growth Development Checklist 2004 Smart Growth Development Checklist Smart Growth Development Checklist Corporation of the City of New Westminster Guide and manage growth in a manner which is consistent with the principles of sustainable

More information

A. INTRODUCTION B. PROJECT LOCATION

A. INTRODUCTION B. PROJECT LOCATION Chapter 1: Project Description A. INTRODUCTION The Lower Manhattan Development Corporation (LMDC), a subsidiary of the New York State Urban Development Corporation, doing business as the Empire State Development

More information

30% Design Community Meeting

30% Design Community Meeting Monday, September 17, 2018 30% Design Community Meeting Site 85-E-W-4 Please sign in on your mobile device: http//communitymeeting.ocps.net/ Site 85-E-W-4 Meeting Agenda September 17, 2018, 6:45PM Welcome

More information

MONTGOMERY COUNTY PLANNING DEPARTMENT

MONTGOMERY COUNTY PLANNING DEPARTMENT MONTGOMERY COUNTY PLANNING DEPARTMENT THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION Ashburton Elementary School Addition, Mandatory Referral, MR2018009 MCPB Item No. Date: 02-15-18 Troy Leftwich,

More information

Casa Loma Heritage Conservation District Study Community Advisory Group Meeting #2 Summary

Casa Loma Heritage Conservation District Study Community Advisory Group Meeting #2 Summary Casa Loma Heritage Conservation District Study Community Advisory Group Meeting #2 Summary 1. Meeting Details Thursday, April 5 th, 2018, 7:00 pm 9:00 pm Spadina House, Basement Meeting Room, 285 Spadina

More information

DESIGN REVIEW STANDARDS CITY OF LANGLEY

DESIGN REVIEW STANDARDS CITY OF LANGLEY DESIGN REVIEW STANDARDS CITY OF LANGLEY I. INTRODUCTION The City of Langley is fortunate to have a strong sense of place and unique quality. This comes in part from its special setting along Saratoga Passage,

More information

SUBJECT: Waterfront Hotel Planning Study Update TO: Planning and Development Committee FROM: Department of City Building. Recommendation: Purpose:

SUBJECT: Waterfront Hotel Planning Study Update TO: Planning and Development Committee FROM: Department of City Building. Recommendation: Purpose: Page 1 of Report PB-23-18 SUBJECT: Waterfront Hotel Planning Study Update TO: Planning and Development Committee FROM: Department of City Building Report Number: PB-23-18 Wards Affected: 2 File Numbers:

More information

Moreno Valley College: Conceptual Master Planning - Site Analysis Lasselle Street, Moreno Valley, CA 92551

Moreno Valley College: Conceptual Master Planning - Site Analysis Lasselle Street, Moreno Valley, CA 92551 Master Plan Architect School Name Moreno Valley College District Riverside Community College District Architecture and Urban Design 5898 Blackwelder Street Ground Floor Culver City, CA 90232 T: 310.559.5720

More information

University of Wisconsin - Whitewater Universal Design Guidelines

University of Wisconsin - Whitewater Universal Design Guidelines University of Wisconsin - Whitewater Universal Design Guidelines The purpose of these guidelines is to foster good design and discussion that fully encompasses the principals of Universal Design (UD) into

More information

North Oakville East Parks Facilities Distribution Plan. November, 2009

North Oakville East Parks Facilities Distribution Plan. November, 2009 North Oakville East November, 2009 POLICY CONTEXT 1) Purpose a) The purpose of this document is to be a guide for the location, configuration, design and development of the parks system for the North Oakville

More information

NOTES FILED WITH TOWN CLERK

NOTES FILED WITH TOWN CLERK Page 1 of 6 Town of Farmington Parks Master Plan Advisory Committee FILED WITH TOWN CLERK August 18, 2015 TOWN OF FARMINGTON PARKS MASTER PLAN ADVISORY COMMITTEE NOTES FROM THE BEAVER CREEK PARK SITE WALK,

More information

South th E ast Communit ity Centre (SECC)

South th E ast Communit ity Centre (SECC) South East Community Centre (SECC) 1 New Park Design & Community Centre Update Thursday, February 8, 2018 Public Open House Thank you for attending this Open House! The town and the Consulting Team will

More information

Public Workshop #2 Summary

Public Workshop #2 Summary Public Workshop #2 Summary Project Number: Project Title: 2320.01 (R&M) MOA Parks and Recreation Muldoon Town Square Park Master Plan Subject: Muldoon Town Square Park Master Plan Public Workshop #2 Author:

More information

Ohlone College Measure G Project Scope Revisions

Ohlone College Measure G Project Scope Revisions Scope Revisions Current Title Revised Title Current Scope Revised Scope 6101 Relocated Baseball Field Athletic Fields Create new sustainable baseball field with synthetic turf, bleacher seating and batting

More information

TETON COUNTY FIRE PROTECTION RESOLUTION FOR NEW SUBDIVISIONS 2008 Edition. Chapter I General Provisions

TETON COUNTY FIRE PROTECTION RESOLUTION FOR NEW SUBDIVISIONS 2008 Edition. Chapter I General Provisions TETON COUNTY FIRE PROTECTION RESOLUTION FOR NEW SUBDIVISIONS 2008 Edition Chapter I General Provisions SECTION 1.1: TITLE. This Resolution shall be known as the Teton County Fire Protection Resolution

More information

CITY OF CHARLOTTESVILLE DEPARTMENT OF NEIGHBORHOOD DEVELOPMENT SERVICES STAFF REPORT TO THE ENTRANCE CORRIDOR REVIEW BOARD (ERB)

CITY OF CHARLOTTESVILLE DEPARTMENT OF NEIGHBORHOOD DEVELOPMENT SERVICES STAFF REPORT TO THE ENTRANCE CORRIDOR REVIEW BOARD (ERB) CITY OF CHARLOTTESVILLE DEPARTMENT OF NEIGHBORHOOD DEVELOPMENT SERVICES STAFF REPORT TO THE ENTRANCE CORRIDOR REVIEW BOARD (ERB) ENTRANCE CORRIDOR CERTIFICATE OF APPROPROPRIATENESS DATE OF PLANNING COMMISSION

More information

2015 Campus Master Plan Update

2015 Campus Master Plan Update September 15, 2015 2015 Campus Master Plan Update Campus and Community Analysis Summary Presentation A G E N D A 1. Scope & Schedule of the Master Plan 2. Planning Principles & Draft Goals 3. Background

More information

Commercial Development Permit Area

Commercial Development Permit Area City of Kamloops KAMPLAN Commercial Development Permit Area PURPOSE The purpose of this Development Permit Area (DPA) is to establish objectives and provide guidelines for the form and character of commercial

More information

POLICY AMENDMENT AND LAND USE AMENDMENT KILLARNEY/GLENGARRY (WARD 8) NW CORNER OF RICHMOND ROAD AND 33 STREET SW BYLAWS 1P2015 AND 7D2015

POLICY AMENDMENT AND LAND USE AMENDMENT KILLARNEY/GLENGARRY (WARD 8) NW CORNER OF RICHMOND ROAD AND 33 STREET SW BYLAWS 1P2015 AND 7D2015 Page 1 of 13 EXECUTIVE SUMMARY This application seeks to redesignate an RC-2 (Residential Contextual One/Two Dwelling) parcel to MC-Gd72 (Multi-Residential Contextual Grade-Oriented) to allow for multi-residential

More information

Welcome! UBC Community Conversations. Proposed new community garden space in Chancellor Place and Wesbrook Place. Traffic flow on Iona Drive

Welcome! UBC Community Conversations. Proposed new community garden space in Chancellor Place and Wesbrook Place. Traffic flow on Iona Drive 1 Welcome! UBC Community Conversations Thank you for joining us this evening, please take a feedback form, help yourself to some food and have a look around! We have information available on: Proposed

More information

Metro. Activity Center Design Guidelines. Recommendations For Developing Focused, Mixed-Use Commercial/Residential Centers

Metro. Activity Center Design Guidelines. Recommendations For Developing Focused, Mixed-Use Commercial/Residential Centers Metro Activity Center Design Guidelines Recommendations For Developing Focused, Mixed-Use Commercial/Residential Centers Metro Activity Centers What is a MAC? Legacy, the adopted guide for the future growth

More information

LANGAN LANDSCAPE ARCHITECTURE + PLANNING FOR COLLEGES & UNIVERSITIES

LANGAN LANDSCAPE ARCHITECTURE + PLANNING FOR COLLEGES & UNIVERSITIES LANGAN LANDSCAPE ARCHITECTURE + PLANNING FOR COLLEGES & UNIVERSITIES CONTACT Philadelphia Pennsylvania 1818 Market Street Suite 3300 Philadelphia PA 19103 215.845.8900 215.845.8901 ST. JOSEPH'S UNIVERSITY

More information

PALO ALTO HIGH SCHOOL. Palo Alto Unified School District SCHEMATIC DESIGN TO DESIGN DEVELOPMENT TRANSITION MEETING. 21 January 2010, 12:30pm-2:00pm

PALO ALTO HIGH SCHOOL. Palo Alto Unified School District SCHEMATIC DESIGN TO DESIGN DEVELOPMENT TRANSITION MEETING. 21 January 2010, 12:30pm-2:00pm PALO ALTO HIGH SCHOOL SCHEMATIC DESIGN TO DESIGN DEVELOPMENT TRANSITION MEETING DATE: SUBJECT: 21 January 2010, 12:30pm-2:00pm Math/Social Sciences Department ATTENDEES: Radu Toma, Paly Math IS Aimee Lopez,

More information

AR Wickes Elementary School (Cossatot River School District) 130 School Drive Wickes AR School Parent and Family Engagement Plan

AR Wickes Elementary School (Cossatot River School District) 130 School Drive Wickes AR School Parent and Family Engagement Plan AR Wickes Elementary School (Cossatot River School District) 130 School Drive Wickes AR 71973 870 385 2346 10/01/2018 School Parent and Family Engagement Plan District Name: Cossatot River School District

More information

Board of Commissioners; Planning Board; George Wood, County Manager From: Randolph S. Williams, AICP, Principal Planner CC:

Board of Commissioners; Planning Board; George Wood, County Manager From: Randolph S. Williams, AICP, Principal Planner CC: Lincoln County Planning & Inspections Department Memo To: Board of Commissioners; Planning Board; George Wood, County Manager From: Randolph S. Williams, AICP, Principal Planner CC: Kelly Atkins, Director

More information

Goals and Objectives. Garfield Blvd. Washngton Park

Goals and Objectives. Garfield Blvd. Washngton Park N 3 Neighborhood, Node, and Network Red Line Metra State St Green Line Garfield Blvd Washngton Park Land Use Plan Mixed use Commercial Institutional Open space Goals and Objectives I. Neighborhood: Enhance

More information

St. Kevin s Area Planning Collaborative

St. Kevin s Area Planning Collaborative Table of Contents page 2 EXECUTIVE SUMMARY 3 MISSION STATEMENT 4 NEIGHBORHOOD CONTEXT 6 STREET CHARACTER 7 SITE PARAMETERS 9 COMMUNITY CHARRETTE - VISIONING GROUP TABLE 1 11 GROUP TABLE 2 12 GROUP TABLE

More information

Health Sciences City The available land area, although limited, combined with the unique partnership between the primary institutions and the supporting partnerships of the development interests within

More information

7.0 OPEN SPACE 7.1 OPEN SPACE DEDICATION CHAPTER 7: OPEN SPACE

7.0 OPEN SPACE 7.1 OPEN SPACE DEDICATION CHAPTER 7: OPEN SPACE 7.0 OPEN SPACE The intent of these requirements is to allow for the usage of centrally located unencumbered land as neighborhood open spaces and not to permit the use of leftover or otherwise unusable

More information

A Healthy Future Walkability Through Community Design. Fit Families North Carolina October 18, 2004

A Healthy Future Walkability Through Community Design. Fit Families North Carolina October 18, 2004 A Healthy Future Walkability Through Community Design Fit Families North Carolina October 18, 2004 Joe Morris, AICP Planning & CD Manager jmorr@salisburync.gov 704-638-5324 Dan Mikkelson, PE Land Management

More information

Sheridan Boulevard S TAT I O N A R E A P L A N S H E R I D A N B O U L E VA R D S TAT I O N A R E A P L A N

Sheridan Boulevard S TAT I O N A R E A P L A N S H E R I D A N B O U L E VA R D S TAT I O N A R E A P L A N Sheridan Boulevard S TAT I O N A R E A P L A N 1 City of Lakewood Adopted November, 2006 S H E R I D A N B O U L E VA R D S TAT I O N A R E A P L A N The Vision The City of Lakewood s overall vision is

More information