1 Terminal Commissioning Case Study- Terminal A Logan International Airport ACI-NA Environmental and Operations & Technical Conference May 4, 2008 Brad Jones, PE, AP Sebesta Blomberg Sam Sleiman, PE, CCM Massport

2 AGENDA Commissioning What is Commissioning? Who Performs Commissioning? How to Internalize Commissioning? What are the Costs of Commissioning? Keys to Success Case Study: Terminal A Logan International Airport

3 Commissioning On your projects, have you ever experienced: When the project is over, have you ever felt that you did not get the building you wanted and paid for? Incomplete training of your O&M staff? Lack of quality as-built drawings and/or systems manuals? Inheriting incomplete work from your contractor, that now has to be completed by your O&M staff?

4 Commissioning On your projects, would you prefer: the Terminal A project has been by far the best project that was turned over to Massport to have our personnel available to visit the site, comment and to be a part in the Commissioning process was invaluable. Manager, CHP/HVAC

5 Boston Logan Terminal A 500,000 sf 22 Gates $500M Three Contract Packages Terminal, Tunnel, Satellite First Certified Airport Terminal

6 Project Highlights Developed by Delta Air Lines, turned over to Massport for operations Multiple engineers mechanical & electrical by different firms Proprietary systems fire alarm and building controls established airport systems Delta utilized third party commissioning for and to demonstrate to Massport that systems were properly functioning (Note: Massport requires meeting requirements for any development on land it owns)

7 Definition of Commissioning Systematic process of assuring by verification and documentation, from the design phase to a minimum of one year after construction, that all project systems function and perform interactively in accordance with the design documentation and intent, and in accordance with the owner s operational needs, including training preparation of O&M personnel.

8 What Is Commissioning? Deliver a Building that Works Develop an Operations Team that can keep it working Documentation Testing Training

9 What Is Commissioning? How does Commissioning differ from Inspections? Building Inspections Required by law and are minimum standards Construction Inspections Review of static installation Building Commissioning Proactive process that builds from installation inspections through performance checks of dynamic operation of systems

10 Question: Aren t I already paying for this?

11 Answer: 1995 Study of New Buildings 50% suffered from controls problems 40% had HVAC equipment problems 25% had malfunctioning: Energy management systems Economizers Variable speed drives 15% had missing equipment

12 Cx Review Question: How will large equipment be moved into and out of the penthouse mechanical room in the future there doesn t appear to be any roof access? Answer: That s a Day 2 project. Architect

13 Design Review Comment: The sequence of operations is general and will not provide enough information to the controls contractor. Answer: That s how we always do it. Engineer

14 Scheduling Question: So now that the fire alarm vendor has finished his check out, are we ready to schedule the system tests? Answer: I can get a good look at a T-bone by sticking my head up a bull s ass, but I d rather take the butcher s word for it. Electrical Contractor

15 The presence of an independent third party commissioning agent helped to keep design and construction teams focused on developing resolutions to construction issues that would not impact long term building operations. The easy resolution was often not the best for the long term building operation.

16 Commissioning Process Pre-Design Phase Design Phase Construction Phase Acceptance Phase Warranty Phase

17 Commissioning Process FUND. FUND.

18 Design Phase Cx Activities FUND. FUND. Design Intent Document ENHANCED ENHANCED FUND. FUND.

19 Early Construction Phase Cx milestones into the master construction schedule Keeps Cx off Critical Path Activities Review Commissionability Accessibility & maintainability Design Intent Document ENHANCED ENHANCED ENHANCED ENHANCED ENHANCED ENHANCED

20 Testing and Training Phase ENHANCED ENHANCED FUND. FUND. All Cx Activities Blank Test Procedures FUND. FUND.

21 Warranty Phase ENHANCED ENHANCED FUND. FUND. O&M Staff meeting ENHANCED Areas of concern ENHANCED wish list for system optimization Update with warranty phase activities

22 Who Provides Commissioning? Designers Contractors Third Party Professional Owner Design/Construction Team Operators Someone leads effort as Cx Authority, but it s a TEAM EFFORT!

23 What Systems are Commissioned? Factors influencing decision: Past problems? Risks of malfunction? Political implications of poor system operation? How easily will issues be identified with out Cx? How many parties involved with design & construction of the system? resolution of issues Program requirements, utility

24 What Systems Are Commissioned? HVAC Building Controls System Electrical Life Safety Lighting Plumbing Building Envelope Specialty Systems Selected to meet project needs,

25 Systems Commissioning

26 Streamlining the Cx Process Integration w/ Authorities Having Jurisdiction Massport Fire & Rescue Simulated Power Outage Test Smoke Evacuation Tests Fire Alarm - Check of AHU s start/stop, but not damper operation

27 Importance of Systems Testing Example: Tunnel Fire Alarm Testing

28 Importance of Systems Testing Example: Tunnel Fire Alarm Testing

29 Importance of Systems Testing Architect Mechanical Engineer Electrical Engineer Code Consultant Delta Owner s Rep Massport Owner s Rep Massport Facilities Massport Fire & Rescue Massport Code Consultant Construction Manager Mechanical Contractors (3) Electrical Contractors (3) Sheet Metal Subs (3) Air Balancing (3) Controls Contractor Fire Alarm Contractor

30 Overview of Results Short Circuit & Coordination Study Caught Incorrect Breaker Settings Minimum speed settings on VFD s and damper operation in smoke evacuation mode safety issues Conflicts between designed and installed operating sequences identified and clarified (e.g. preheat coil valves) Impact of programmed sequences at central plant Control point alarm labels clarified at central facilities identified and resolved AHU piping and clearances for coil pulls Duct work access panels Timers for sump trap primers

31 Owner Commissioning? How to Internalize Commissioning Needs Support at All Levels Identify Champion Build Proper Procedures Know Resources/Limitations Funding Sources Capital Planning? Operations? Ask for Help

32 Cost of Commissioning 0.5-1% of Total Construction Cost 2-5% of the Construction Cost of the Systems Being Commissioned Recommended not Using $/S.F. Unit Costs (too many variables in scope)

33 Benefits of Commissioning for Terminal A Supports Effective QC Eases Building Turn-Over Reduces Warranty Callbacks Energy Savings Persistence of Savings Occupant Acceptance Certification/Accreditation

34 Keys to Success Develop effective relationships with all team members Mutual respect for each team member s contribution Involve Operations Staff wherever practical Early & Diligent Scheduling Manage Expectations Facilitate a Win-Win Conclusion for All

35 Summary What is Commissioning? Systems-based Documentation, Testing, Training; 0.5-1% of project cost Why Commission your building? Independent party keeps focus on owner s needs When does Commissioning start? Ideally early design phase; project dependent based on needs Who Commissions the building? Whole project team; Commissioning Agent leads & facilitates What to Commission? Project dependent based on needs

36 QUESTIONS? Brad Jones, PE, AP Sam Sleiman, PE, CCM

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 21 0800 - COMMISSIONING OF FIRE SUPPRESSION SYSTEMS GENERAL 1.1 SUMMARY General 1. Work under this contract shall meet the requirements of Division 01, General Requirements, Conditions of Contract,

More information

Prescriptions for Critical Healthcare Cx. John D. Villani, P.E. Associate Grumman/Butkus Associates

Prescriptions for Critical Healthcare Cx. John D. Villani, P.E. Associate Grumman/Butkus Associates Prescriptions for Critical Healthcare Cx John D. Villani, P.E. Associate Grumman/Butkus Associates AIA Quality Assurance Learning Objectives 1. Medical Industry Changes and how they impact Design, Construction,

More information

CAN/ULC S Integrated Systems Testing of Fire Protection and Life Safety Systems and Fire Protection Commissioning

CAN/ULC S Integrated Systems Testing of Fire Protection and Life Safety Systems and Fire Protection Commissioning CAN/ULC S1001-11 Integrated Systems Testing of Fire Protection and Life Safety Systems and Fire Protection Commissioning Presentation To: Canadian Fire Alarm Association (CFAA) National Capital Region

More information

TESTING, ADJUSTING AND BALANCING

TESTING, ADJUSTING AND BALANCING PART 1 GENERAL 1.01 DESCRIPTION A. Work Included: After completion of the work of installation, owner is responsible for procuring an air balancing and testing agency to test and regulate all components

More information

Case Study: Furman University Charles H. Townes Center for Science. Michael K. Mantai, PE, CCP President System WorCx

Case Study: Furman University Charles H. Townes Center for Science. Michael K. Mantai, PE, CCP President System WorCx Case Study: Furman University Charles H. Townes Center for Science Michael K. Mantai, PE, CCP President System WorCx AIA Quality Assurance Learning Objectives 1. Case study example of Chilled Beam technology

More information

Subcontract Agreement No.

Subcontract Agreement No. ATTACHMENT G TRADE INTERFACE AGREEMENT Subcontract Agreement No. PROJECT: TEXASTECH UNIVERSITY HEALTH SCIENCES CAMPUS, EL PASO, TEXAS MEDICAL SCIENCE BUILDING II PARTICIPANTS: Sundt Construction, Inc.

More information

CAN/ULC-S INTEGRATED SYSTEMS TESTING OF FIRE PROTECTION AND LIFE SAFETY SYSTEMS

CAN/ULC-S INTEGRATED SYSTEMS TESTING OF FIRE PROTECTION AND LIFE SAFETY SYSTEMS 2013 Randal Brown & Associates Engineering Ltd. 1 RANDAL BROWN & ASSOCIATES ENGINEERING LTD. CONSULTING ENGINEERS LIFE SAFETY & FIRE PROTECTION 105 6 LANSING SQUARE TORONTO, ONTARIO CAN/ULC-S1001-11 INTEGRATED

More information

Exhibit J. Subcontract Agreement No.

Exhibit J. Subcontract Agreement No. Exhibit J SUBCONTRACTOR TRADE INTERFACE AGREEMENT Subcontract Agreement No. PROJECT: NEW EASTSIDE REGIONAL PARK PHASE I PARTICIPANTS (PARTIES): Sundt Construction, Inc. PURPOSE: General Contractor (Sundt)

More information

SECTION FUNCTIONAL PERFORMANCE TESTING (FPT) PROCEDURES - CONSTRUCTION MANAGER EDITION

SECTION FUNCTIONAL PERFORMANCE TESTING (FPT) PROCEDURES - CONSTRUCTION MANAGER EDITION Montgomery County Public Schools Facilities DIVISION 1 - GENERAL REQUIREMENTS SECTION 01915 - FUNCTIONAL PERFORMANCE TESTING (FPT) PROCEDURES - CONSTRUCTION MANAGER EDITION PART 1 GENERAL 1.1 Section includes:

More information

An HVAC Audit of the Canberra Institute of Technology

An HVAC Audit of the Canberra Institute of Technology An HVAC Audit of the Canberra Institute of Technology 30 th November 2016 Amnon Holland amnon.holland@esbsconsult.com.au www.esbsconsult.com.au Agenda Overview CIT and various other sites The sites Type

More information

CAN/ULC-S1001, INTEGRATED SYSTEMS TEST OF FIRE PROTECTION AND LIFE SAFETY SYSTEMS

CAN/ULC-S1001, INTEGRATED SYSTEMS TEST OF FIRE PROTECTION AND LIFE SAFETY SYSTEMS RANDAL BROWN & ASSOCIATES ENGINEERING LTD. CONSULTING ENGINEERS LIFE SAFETY & FIRE PROTECTION 105 6 LANSING SQUARE TORONTO, ONTARIO CAN/ULC-S1001, INTEGRATED SYSTEMS TEST OF FIRE PROTECTION AND LIFE SAFETY

More information

Retrocommissioning Findings Summary: Building X #1 Priority: Major Comfort/Control Problems

Retrocommissioning Findings Summary: Building X #1 Priority: Major Comfort/Control Problems IMPORTANT NOTICE: This sample document is provided for instructional purposes only. CCC is not rendering advice concerning any commission project or practices. This document is neither approved nor intended

More information

Demonstration and Training of MEP Systems Page 1 of 15

Demonstration and Training of MEP Systems Page 1 of 15 Page 1 of 15 Last Update: May 17, 2018 A. General: 1. Demonstrations and Training of various MEP and other systems is very important to BSU Facilities, especially on new building or major renovation projects.

More information

SECTION PACKAGED COMPRESSOR AND CONDENSER UNITS

SECTION PACKAGED COMPRESSOR AND CONDENSER UNITS SECTION 236200 - PACKAGED COMPRESSOR AND CONDENSER UNITS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions apply

More information

AIR HANDLING SYSTEM RETRO-COMMISSIONING TRENDING ANALYSIS

AIR HANDLING SYSTEM RETRO-COMMISSIONING TRENDING ANALYSIS AIR HANDLING SYSTEM RETRO-COMMISSIONING TRENDING ANALYSIS 1 AIR HANDLING UNIT TRENDS 2 1. The trending charts provided on the following pages prepared as part of a retro-commissioning investigation. The

More information

CAN/ULC-S1001, INTEGRATED SYSTEMS TESTING OF FIRE PROTECTION & LIFE SAFETY SYSTEMS Simon Crosby, LEL, CET, CFPS October 21, 2015

CAN/ULC-S1001, INTEGRATED SYSTEMS TESTING OF FIRE PROTECTION & LIFE SAFETY SYSTEMS Simon Crosby, LEL, CET, CFPS October 21, 2015 CAN/ULC-S1001, INTEGRATED SYSTEMS TESTING OF FIRE PROTECTION & LIFE SAFETY SYSTEMS Simon Crosby, LEL, CET, CFPS October 21, 2015 Fire Commissioning in Canadian Codes and Standards BACKGROUND Why Commissioning?

More information

CxA to Answer this Section

CxA to Answer this Section EXHIBIT 01 91 13-3, SAMPLE Construction checklist items are to be completed as part of initial checkout and subsequent startup, preparatory to Functional testing. This checklist does not take the place

More information

Automatic Fire Alarm Association Webinar On Inspection, Testing, And Maintenance Of Fire Alarm Systems

Automatic Fire Alarm Association Webinar On Inspection, Testing, And Maintenance Of Fire Alarm Systems Automatic Fire Alarm Association Webinar On Inspection, Testing, And Maintenance Of Fire Alarm Systems Your Presenter: Merton Bunker, PE Inspections and tests are intended to reduce or limit: Loss of life

More information

Matt Cooper, PE, BEMP, HBDP, Group 14 Engineering Ken Urbanek, PE, HBDP MKK Consulting Engineers, Inc.

Matt Cooper, PE, BEMP, HBDP, Group 14 Engineering Ken Urbanek, PE, HBDP MKK Consulting Engineers, Inc. M&V Real Results of High Performance Design Matt Cooper, PE, BEMP, HBDP, Group 14 Engineering Ken Urbanek, PE, HBDP MKK Consulting Engineers, Inc. Overview Measurement & Verification (M&V) Plan for New

More information

Air Handler Unit (AHU) Equipment Purchase and Delivery Invitation to Bid

Air Handler Unit (AHU) Equipment Purchase and Delivery Invitation to Bid DATE: February 1, 2018 SUBJECT: Letter of Clarification #2 RE: TO: Air Handler Unit (AHU) Equipment Purchase and Delivery Invitation to Bid All Prospective Bidders Houston First Corporation ( HFC ) issues

More information

STATE FIRE MARSHAL S REQUIRED FIRE PROTECTION SYSTEMS NARRATIVE REPORT

STATE FIRE MARSHAL S REQUIRED FIRE PROTECTION SYSTEMS NARRATIVE REPORT STATE FIRE MARSHAL S REQUIRED FIRE PROTECTION SYSTEMS NARRATIVE REPORT The interaction of fire protection systems can be extremely complex. The detection of a fire in a building by an automatic device

More information

City of Duluth Festival Center 04/25

City of Duluth Festival Center 04/25 SECTION 230593 - TESTING, ADJUSTING, AND BALANCING FOR HVAC PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and

More information

SECTION Fire Pumps

SECTION Fire Pumps SECTION 21 30 00 Fire Pumps PART 1 GENERAL 1.1 WORK INCLUDED A. Furnish, install and test a motor-driven fire pump, jockey pump, and controllers in the space provided and as shown in the contract drawings.

More information

ADDENDUM No: 3 JOSEPHINE COUNTY BUILDING OPERATIONS DEPARTMENT. February 29, NO CHANGE: March 8, 2012 / NOT LATER THAN 2:00 PM

ADDENDUM No: 3 JOSEPHINE COUNTY BUILDING OPERATIONS DEPARTMENT. February 29, NO CHANGE: March 8, 2012 / NOT LATER THAN 2:00 PM ADDENDUM No: 3 JOSEPHINE COUNTY BUILDING OPERATIONS DEPARTMENT February 29, 2012 RFP NO: 17 PROJECT: Josephine County Justice Center HVAC Upgrades BID CLOSING DATE: NO CHANGE: March 8, 2012 / NOT LATER

More information

HVAC Controls Upgrades: Requirement Details ( )

HVAC Controls Upgrades: Requirement Details ( ) REQUIRED CONTROLS/FEATURES HVAC non CENTRAL PLANT 1) Zone Level Scheduling & Override for all air handlers (supply and exhaust) to match occupied hours by zone DDC or occupancy sensors (OS) allowed. (403.2.4.3,

More information

November 11, City of Sparks 215 S. 21 st St. Sparks, NV

November 11, City of Sparks 215 S. 21 st St. Sparks, NV November 11, 2014 City of Sparks 215 S. 21 st St. Sparks, NV 89432-0857 Attn: Brian Cason Re: Sparks City Hall HVAC Upgrade Project-Alerton Direct Digital HVAC Control System to Match Existing City of

More information

SOCIETY OF FIRE PROTECTION ENGINEERS POSITION STATEMENT P THE ROLE OF THE FIRE PROTECTION ENGINEER IN THE CONSTRUCTION DESIGN PROCESS

SOCIETY OF FIRE PROTECTION ENGINEERS POSITION STATEMENT P THE ROLE OF THE FIRE PROTECTION ENGINEER IN THE CONSTRUCTION DESIGN PROCESS SOCIETY OF FIRE PROTECTION ENGINEERS POSITION STATEMENT P-02-07 THE ROLE OF THE FIRE PROTECTION ENGINEER IN THE CONSTRUCTION DESIGN PROCESS March, 2007 Society of Fire Protection Engineers - 1 - Position

More information

KINGS COUNTY JAIL EXPANSION PHASE III COUNTY OF KINGS SECTION

KINGS COUNTY JAIL EXPANSION PHASE III COUNTY OF KINGS SECTION SECTION 237433, PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to

More information

Fire Prevention Coffee Break Training. February 2017

Fire Prevention Coffee Break Training. February 2017 Fire Prevention Coffee Break Training February 2017 Agenda FDC s - Lund Standpipes - Phelan Fire Alarm Testing Phelan/Dooley Questions and Answers Open Forum Standpipe requirement Standpipes are required

More information

FIRE & LIFE SAFTEY STANDARD

FIRE & LIFE SAFTEY STANDARD Title: Effective Date: 01/01/14 Revised Date: 1/1/14 Code References: Title 16, Chapter 16.16 of the Roseville Municipal Code, NFPA 72 Note: This standard is a summary of Fire Department clarifications

More information

SECTION GAS-FIRED RADIANT HEATERS

SECTION GAS-FIRED RADIANT HEATERS SECTION 23 55 23 PART 1 - GENERAL 1.1 DESCRIPTION SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Delete between // // if not applicable to project. Also delete any other item or paragraph

More information

Purpose : Project Manager. Professional. Contractor: devices/system. compatibility

Purpose : Project Manager. Professional. Contractor: devices/system. compatibility I. Title: Fire Alarm Systems Design, Construction and Commissioning II. Purpose : Define activities, identify stakeholders, and assign responsibilities as it relates to the installation of fire alarm devices

More information

Element Z General Design Requirements Existing Facilities Information

Element Z General Design Requirements Existing Facilities Information Charles M. LeMaistre PART 1 - INTRODUCTION 1.01 OVERVIEW A. This Section provides general information for building systems and components. B. Refer to the Owner s Design Guideline Elements A though G and

More information

SECTION ELECTRICAL SYSTEMS COMMISSIONING

SECTION ELECTRICAL SYSTEMS COMMISSIONING SECTION 16990 PART 1 - GENERAL 1.01 SECTION INCLUDES A. Section Includes: 1. General requirements for Commissioning (Cx) of lighting systems components, lighting controls and HVAC systems line voltage

More information

1.1 DESCRIPTION A. The purpose of this section is to specify Division 23 responsibilities in the commissioning (Cx) process.

1.1 DESCRIPTION A. The purpose of this section is to specify Division 23 responsibilities in the commissioning (Cx) process. SECTION 239950 MECHANICAL COMMISSIONING SYSTEMS PART 1 - GENERAL 1.1 DESCRIPTION A. The purpose of this section is to specify Division 23 responsibilities in the commissioning (Cx) process. B. Commissioning

More information

A. Product Data: Include rated capacities, operating characteristics, furnished specialties, and accessories.

A. Product Data: Include rated capacities, operating characteristics, furnished specialties, and accessories. SECTION 238113 - PACKAGED TERMINAL AIR CONDITIONERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

SECTION SEQUENCE OF OPERATION FOR HVAC CONTROLS PART 1 GENERAL

SECTION SEQUENCE OF OPERATION FOR HVAC CONTROLS PART 1 GENERAL SECTION 15910 SEQUENCE OF OPERATION FOR HVAC CONTROLS PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

The M & V Guided Recommissioning Process. Energy & Water Conservation Program. September 2015 MOO

The M & V Guided Recommissioning Process. Energy & Water Conservation Program. September 2015 MOO The M & V Guided Recommissioning Process MOO Energy & Water Conservation Program September 2015 EWC Agenda MOO EWC Overview Our approach Progress Fault Detection Zone & customer feedback Variance reporting

More information

Impacts of Optimized Cold & Hot Deck Reset Schedules on Dual Duct VAV Systems - Theory and Model Simulation

Impacts of Optimized Cold & Hot Deck Reset Schedules on Dual Duct VAV Systems - Theory and Model Simulation Impacts of Optimized Cold & Hot Deck Reset Schedules on Dual Duct VAV Systems - Theory and Model Simulation Mingsheng Liu, Ph.D., P.E. Energy Systems Laboratory Texas A&M University College Station, Texas

More information

ATSP3. Advanced Technology Support Program III. Comprehensive Solutions for Obsolescence and Performance Issues:

ATSP3. Advanced Technology Support Program III. Comprehensive Solutions for Obsolescence and Performance Issues: Advanced Technology Support Program III ATSP3 Comprehensive Solutions for Obsolescence and Performance Issues: Electronic Hardware Software Design Integrated System and Sub-Systems Honeywell Aerospace

More information

SECTION INTEGRATED AUTOMATION COMMISSIONING

SECTION INTEGRATED AUTOMATION COMMISSIONING SECTION 25 08 00 INTEGRATED AUTOMATION COMMISSIONING PART 1. GENERAL 1.01 SECTION INCLUDES: A. BAS and equipment testing and start-up B. Validation of proper and thorough installation of BAS and equipment

More information

Fire System Impairment Policy

Fire System Impairment Policy Fire System Impairment Policy Purpose: To establish procedures to be followed, when a fire protection or suppression system is taken out of service, due to construction, alteration, power outage, repair,

More information

THE DESIGN FIRM ADDENDUM #1 PINE GROVE BAPTIST FELLOWSHIP HALL RENOVATION 759 PINE GROVE RD. HARVEST, AL MAY 10, 2017

THE DESIGN FIRM ADDENDUM #1 PINE GROVE BAPTIST FELLOWSHIP HALL RENOVATION 759 PINE GROVE RD. HARVEST, AL MAY 10, 2017 THE DESIGN FIRM A N I T A J. D E N S O N A R C H I T E C T 102 ASHWOOD DRIVE! DECATUR, ALABAMA 35603! OFFICE: 256-340-5795 HOME: 256-351-0435! CELL: 256-318-4690 E-MAIL ADDRESS: thedesignfirm@ bellsouth.net

More information

INTEGRATED LIFE SAFETY COMPLIANCE TESTING AND ITS PROCEDURES

INTEGRATED LIFE SAFETY COMPLIANCE TESTING AND ITS PROCEDURES INTEGRATED LIFE SAFETY COMPLIANCE TESTING AND ITS PROCEDURES By: Mehrdad Ghods Integrated Engineering Student Sept. 06, 2002 University of British Columbia Vancouver, BC i PREFACE: The purpose of this

More information

HVAC Controls Upgrades: Requirement Details ( )

HVAC Controls Upgrades: Requirement Details ( ) REQUIRED CONTROLS/FEATURES To qualify the upgrade must add or substantially modify 3 or more sequences/system capabilities. Also, all sequences and items listed under the required section are needed in

More information

BES-TECH TECHNOLOGY & SYSTEM INTEGRATION

BES-TECH TECHNOLOGY & SYSTEM INTEGRATION BES-TECH TECHNOLOGY & SYSTEM INTEGRATION BES-TECH TECHNOLOGY & SYSTEM INTEGRATION DIGI-ACC Digi-ACC is a control kit for air cooled chiller systems, optimizing both chiller and pumps thereby reducing consumption

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-23 09 93 (November 2015) ----------------------------- Preparing Activity: USACE Superseding UFGS-23 09 23 (May 2011) UNIFIED FACILITIES GUIDE SPECIFICATIONS References

More information

Smoke Management in Operating Room Renovations

Smoke Management in Operating Room Renovations Smoke Management in Operating Room Renovations Sandy Bonderman PE, LEED AP Sean Riley PE, LEED AP Brian Robinett PE, LEED AP Notkin Mechanical Engineers Overview Smoke Management in OR Renovations Why

More information

CITY OF CHARLOTTESVILLE, VIRGINIA CITY COUNCIL AGENDA

CITY OF CHARLOTTESVILLE, VIRGINIA CITY COUNCIL AGENDA CITY OF CHARLOTTESVILLE, VIRGINIA CITY COUNCIL AGENDA Agenda Date: December 16, 2013 Action Required: Adoption of Resolution Presenter: Staff Contacts: Title: James E. Tolbert, AICP, Director of NDS James

More information

Electronic Safety and Security

Electronic Safety and Security 28 Electronic Safety and Security NOTE: This is a new section, which includes content from previous sections of the KU Design Standards, along with appropriate revisions and updates. Significant revisions

More information

10+ HVAC Troubleshooting Tips for Healthcare Facilities Jerry Hirsch JCI Facility O&M Performance Development Manager.

10+ HVAC Troubleshooting Tips for Healthcare Facilities Jerry Hirsch JCI Facility O&M Performance Development Manager. 10+ HVAC Troubleshooting Tips for Healthcare Facilities Jerry Hirsch JCI Facility O&M Performance Development Manager 2019 WHEA Webinar Johnson Controls Institute Overview Operation & Maintenance (O&M)

More information

Communication and Coordination Failures in the Process Industries

Communication and Coordination Failures in the Process Industries Communication and Coordination s in the Process Industries 52 nd Annual HFES Meeting Jason Laberge Honeywell Advanced Technology Golden Valley, MN Peter Bullemer Human Centered Solutions Independence,

More information

MIDWEST HEALTH CONFERENCE

MIDWEST HEALTH CONFERENCE MIDWEST HEALTH CONFERENCE A Practical Approach to Maintaining Compliant Humidity Levels Greg Lavriha, PE KEY PERSONNEL Greg Lavriha, PE Greg Lavriha is an experienced mechanical engineer who specializes

More information

"This is only the scope of work for the project. For more information, interested parties should contact Procurement at

This is only the scope of work for the project. For more information, interested parties should contact Procurement at "This is only the scope of work for the project. For more information, interested parties should contact Procurement at purchasing@stpgov.org to ensure receipt of a full bid package, to be listed as a

More information

1080 Marina Village Parkway, Suite 501 Alameda, CA (510) Fax (510) HVAC DESIGN INTENT

1080 Marina Village Parkway, Suite 501 Alameda, CA (510) Fax (510) HVAC DESIGN INTENT Taylor Engineering 1080 Marina Village Parkway, Suite 501 Alameda, CA 94501-1142 (510) 749-9135 Fax (510) 749-9136 LLC HVAC DESIGN INTENT PART 1 - GENERAL 1.1 Overview A. The project consists of a 3-story

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 23 0594 - TESTING, ADJUSTING, AND BALANCING (TAB) PART 1 - GENERAL 1.1 SUMMARY A. This Section includes testing, adjusting and balancing HVAC systems to provide design conditions as indicated by

More information

COMMERCIAL CONDENSING BOILER OPTIMIZATION

COMMERCIAL CONDENSING BOILER OPTIMIZATION COMMERCIAL CONDENSING BOILER OPTIMIZATION Russ Landry, PE, LEED AP Senior Mechanical Engineer This project was supported in part by a grant from the Minnesota Department of Commerce, Division of Energy

More information

1. Floor above/floor below notification. 2. Private alarm notification. 3. Not Used 4. Voice alarm notification. 5. Not Used.

1. Floor above/floor below notification. 2. Private alarm notification. 3. Not Used 4. Voice alarm notification. 5. Not Used. PART 1 GENERAL 1.01 Scope of Standard A. This Standard is intended to assure that fire alarm and signaling systems at Sam Houston State University provide the highest level of life safety possible. This

More information

AIRPORT OFFICE BUILDING. Smoke Control System. Testing Procedures Manual. September 10, 2016

AIRPORT OFFICE BUILDING. Smoke Control System. Testing Procedures Manual. September 10, 2016 IMPACT ENGINEERING, INC. AIRPORT OFFICE BUILDING Smoke Control System Testing Procedures Manual September 10, 2016 All Rights Reserved This manual is protected by the U.S. Copyright Law (Title 17 United

More information

Fire Smoke Damper Actuator Replacements SECTION COMMISSIONING OF HVAC

Fire Smoke Damper Actuator Replacements SECTION COMMISSIONING OF HVAC PART 1 GENERAL 1.01 SUMMARY SECTION 23 08 00 COMMISSIONING OF HVAC A. This section covers the Contractor's and Commissioning Authority (CA) responsibilities for commissioning; each subcontractor or installer

More information

Properties that are determined to be architecturally and/or historically significant may be designated as one of the following:

Properties that are determined to be architecturally and/or historically significant may be designated as one of the following: Preparation for disasters, both natural and manmade, is essential for the protection of your building. This is particularly true of historic resources, which often consist of unique and often irreplaceable

More information

Auburn University Basketball Arena:

Auburn University Basketball Arena: Auburn University Basketball Arena: How Building Data Analytics Achieved Energy and O&M Savings While Improving Comfort and Sustainability Eric Moore, PE, CEM, Auburn University Hadas Webb, CEM, Cimetrics

More information

The Technical Committee on Commissioning and Integrated Testing

The Technical Committee on Commissioning and Integrated Testing National Fire Protection Association 1 Batterymarch Park, Quincy, MA 02169-7471 Phone: 617-770-3000 Fax: 617-770-0700 www.nfpa.org TO: FROM: The Technical Committee on Commissioning and Integrated Testing

More information

Brown University Revised June 29, 2012 Facilities Design & Construction Standards SECTION ELECTRICAL DESIGN CRITERIA

Brown University Revised June 29, 2012 Facilities Design & Construction Standards SECTION ELECTRICAL DESIGN CRITERIA PART 1 - GENERAL 1.1 Background SECTION 26 00 10- ELECTRICAL DESIGN CRITERIA A. Brown University maintains it own campus electrical distribution system which serves the majority of the buildings and facilities

More information

T-Series Climate Changer Air Handler. It s Hard To Stop A Trane.

T-Series Climate Changer Air Handler. It s Hard To Stop A Trane. T-Series Climate Changer Air Handler TM It s Hard To Stop A Trane. T-Series Climate Changer Air Handler The Trane tradition of excellence continues with the T-Series Climate Changer air handler. Using

More information

AGENDA ITEM # 13A/B. AGENDA ITEM EXECUTIVE SUMMARY Village Board Meeting December 10, 2018

AGENDA ITEM # 13A/B. AGENDA ITEM EXECUTIVE SUMMARY Village Board Meeting December 10, 2018 AGENDA ITEM # 13A/B AGENDA ITEM EXECUTIVE SUMMARY Village Board Meeting December 10, 2018 Item Title: Main Street Parking Improvements Parking Lot Project Change Order #2 and Final Pay Request Staff Contact:

More information

HVAC System Consideration$ 05/14/2012 SAVING MONEY IN HVAC SYSTEMS

HVAC System Consideration$ 05/14/2012 SAVING MONEY IN HVAC SYSTEMS SAVING MONEY IN HVAC SYSTEMS Rod Rhoads, GDS Associates Inc HVAC System Consideration$ What percent of a commercial business s energy usage comes from their HVAC system? How much money do commercial facilities

More information

ASHRAE Guideline 36P: High Performance Sequences of Operation for HVAC Systems

ASHRAE Guideline 36P: High Performance Sequences of Operation for HVAC Systems ASHRAE Guideline 36P: Hih Performance Sequences of Operation for HVAC Systems Jim Cooan, PE Siemens Buildin Technoloies ASHRAE Distinuished Lecture Proram February 2018, Wisconsin Chapter Pae 1 Aenda ASHRAE

More information

Pre-Bid Meeting Minutes 2018 A & E RFP February 6, :00 a.m.

Pre-Bid Meeting Minutes 2018 A & E RFP February 6, :00 a.m. Attendees: Pre-Bid Meeting Minutes 2018 A & E RFP February 6, 2019 10:00 a.m. Anthony Shomin Sue Martin Architectural & Engineer Professionals KCKHA Modernization Coordinator KCKHA Modernization Admin.

More information

CARRIER edesign SUITE NEWS. Modeling 100% OA Constant Volume Air Systems. Volume 6, Issue 1. Page 1 Modeling 100% OA Constant Volume Air Systems

CARRIER edesign SUITE NEWS. Modeling 100% OA Constant Volume Air Systems. Volume 6, Issue 1. Page 1 Modeling 100% OA Constant Volume Air Systems Volume 6, Issue 1 CARRIER edesign SUITE NEWS Modeling 100% OA Constant Volume Air Systems This article provides an overview of how to model a stand-alone constant air volume (CAV) 100% OA system in HAP.

More information

Technical Paper. Functional Safety Update IEC Edition 2 Standards Update

Technical Paper. Functional Safety Update IEC Edition 2 Standards Update Technical Paper Functional Safety Update IEC 61511 Edition 2 Standards Update Functional Safety Update Table of Contents 1.0 Introduction 2.0 IEC 61511-1 changes 3.0 IEC 61511-2 changes 4.0 IEC 61511-3

More information

The SKD direct steam injection system uses low pressure steam from an in-house boiler to humidify the air.

The SKD direct steam injection system uses low pressure steam from an in-house boiler to humidify the air. The SKD direct steam injection system uses low pressure steam from an in-house boiler to humidify the air. SKD Advantages 4Custom designed to meet your specific steam capacity and non-wetting distance

More information

ASHRAE JOURNAL ON REHEAT

ASHRAE JOURNAL ON REHEAT Page: 1 of 7 ASHRAE JOURNAL ON REHEAT Dan Int-Hout Chief Engineer Page: 2 of 7 Overhead Heating: A lost art. March 2007 ASHRAE Journal Article Dan Int-Hout Chief Engineer, Krueger VAV terminals provide

More information

ISO/TR TECHNICAL REPORT. Fire-safety engineering Technical information on methods for evaluating behaviour and movement of people

ISO/TR TECHNICAL REPORT. Fire-safety engineering Technical information on methods for evaluating behaviour and movement of people TECHNICAL REPORT ISO/TR 16738 First edition 2009-08-01 Fire-safety engineering Technical information on methods for evaluating behaviour and movement of people Ingénierie de la sécurité incendie Informations

More information

D. The work addressed in this section consists of a fire protection system, which may include coordination with one or more of the following:

D. The work addressed in this section consists of a fire protection system, which may include coordination with one or more of the following: PART 1 GENERAL 1.01 Scope of Standard A. This standard provides general requirements of Sam Houston State University for the design and construction of standpipe systems to include combination standpipe

More information

Virginia Tech Standards for Building Automation System

Virginia Tech Standards for Building Automation System March 1, 2016 Virginia Tech Standards for Building Automation System A. Existing Conditions: The Campus Building Automation System is Siemens Apogee and controls all significant campus facilties. Virginia

More information

SEQUENCE OF OPERATION GUIDELINE. AIR TERMINAL UNITS SINGLE DUCT VARIABLE AIR VOLUME with HOT WATER REHEAT or ELECTRIC HEAT

SEQUENCE OF OPERATION GUIDELINE. AIR TERMINAL UNITS SINGLE DUCT VARIABLE AIR VOLUME with HOT WATER REHEAT or ELECTRIC HEAT SEQUENCE OF OPERATION GUIDELINE AIR TERMINAL UNITS SINGLE DUCT VARIABLE AIR VOLUME with HOT WATER REHEAT or ELECTRIC HEAT Document: VAV-HTG rev1 Revision: 1.0 Rev. Date: July 22, 2011 NOTES: 1. THIS SEQUENCE

More information

A. Base Bid: 1. Heating Contractor provide: a. Control sequences for HVAC systems, subsystems, and equipment.

A. Base Bid: 1. Heating Contractor provide: a. Control sequences for HVAC systems, subsystems, and equipment. SECTION 23 09 93 - SEQUENCE OF OPERATIONS FOR HVAC CONTROLS PART 1 - GENERAL 1 WORK INCLUDES A. Base Bid: Heating Contractor provide: Control sequences for HVAC systems, subsystems, and equipment. B. Alternate

More information

HAP e-help. Modeling Induction Beams in HAP v4.8 QB TIP 001

HAP e-help. Modeling Induction Beams in HAP v4.8 QB TIP 001 This HAP e-help provides a high-level overview of induction beams, how they work and how to model them in HAP 4.8 (and later versions). The first half of the article explains how induction beams work.

More information

I. INTRODUCTION Codes, Rules, Laws, & Requirements

I. INTRODUCTION Codes, Rules, Laws, & Requirements I. INTRODUCTION 1.03 Codes, Rules, Laws, & Requirements A. Buildings and sites are to be designed in conformance to the applicable requirements of the following: 1. The Texas Engineering Practice Act and

More information

SPECIFICATION DELETED SECTION CENTRIFUGAL HVAC FANS

SPECIFICATION DELETED SECTION CENTRIFUGAL HVAC FANS SECTION 23 34 16 CENTRIFUGAL HVAC FANS PART 1 - GENERAL 1.01 RELATED DOCUMENT A. Drawings and general provisions of the contract, including General and Special Conditions and Division 01 Specification

More information

VDOT Tunnel Facilities Action Plan

VDOT Tunnel Facilities Action Plan VDOT Tunnel Facilities Action Plan The report prepared by Earth Tech, Inc., entitled Programmatic Review of Critical Fire Life Safety Systems and Procedures, assessed the current state of Fire Life Safety

More information

I. Scope: II. Environmental Health and Safety Fire Alarm System Impairment Program - Guideline Revision Date: April, 2018

I. Scope: II. Environmental Health and Safety Fire Alarm System Impairment Program - Guideline Revision Date: April, 2018 Environmental Health and Safety Fire Alarm System Impairment Program - Guideline Revision Date: April, 2018 Prepared by: EH&S The probability of casualties and major structural damage increases when fire

More information

IMC Significant Changes Summary Tier I

IMC Significant Changes Summary Tier I 2009-2015 IMC Significant Changes Summary Tier I 202 Environmental Air The definition of environmental air has been expanded through the addition of parking garage exhaust. 306.1 Access More than just

More information

WESTIN HOTEL. Smoke Control System. Testing Procedures Manual. October 10, Copyright Impact Engineering, Inc All Rights Reserved

WESTIN HOTEL. Smoke Control System. Testing Procedures Manual. October 10, Copyright Impact Engineering, Inc All Rights Reserved IMPACT ENGINEERING, INC. WESTIN HOTEL Smoke Control System Testing Procedures Manual October 10, 2016 Copyright Impact Engineering, Inc. 2016 All Rights Reserved This manual is protected by the U.S. Copyright

More information

Welsh Commissioning Group, Inc.

Welsh Commissioning Group, Inc. Ongoing Commissioning with Building Automation System and Data Loggers Bryan W. Welsh, P.E. President Welsh Commissioning Group, Inc. AIA Quality Assurance Learning Objectives 1. General understanding

More information

Improving Control of Dual-Duct Single-Fan Variable Air Volume Systems

Improving Control of Dual-Duct Single-Fan Variable Air Volume Systems Improving Control of Dual-Duct Single-Fan Variable Air Volume Systems Guanghua Wei, P.E. Joe Martinez Tom Minihan Assistant Research Engineer Research Engineering Associate Graduate Student Tim Brundidge

More information

SECTION SEQUENCE OF OPERATIONS FOR HVAC CONTROLS

SECTION SEQUENCE OF OPERATIONS FOR HVAC CONTROLS SECTION 23 09 93 SEQUENCE OF OPERATIONS FOR HVAC CONTROLS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes control sequences for HVAC systems, subsystems, and equipment. B. See Division 23 Section

More information

Introduction PLAYING NICE: HVAC AND LIGHTING CONTROLS INTEGRATION. Why should I care? Background Integration VAV box Occ sensor

Introduction PLAYING NICE: HVAC AND LIGHTING CONTROLS INTEGRATION. Why should I care? Background Integration VAV box Occ sensor PLAYING NICE: HVAC AND LIGHTING CONTROLS INTEGRATION www.kw-engineering.com Lyn Gomes, PE, LEED AP kw Engineering Introduction 2 Why should I care? Background Integration VAV box Occ sensor 4 methods for

More information

Florida Department of Transportation

Florida Department of Transportation Page 1 of 7 RICK SCOTT GOVERNOR Florida Department of Transportation 1109 S. Marion Avenue Lake City, Florida 32025 ANANTH PRASAD SECRETARY September 27, 2011 To: Proposal Holders Addendum No: 1, E2Q23,

More information

Building Electrical System Overview

Building Electrical System Overview Philip Mackey L/E Dr. Mistrick Holy Cross Hospital North Addition Silver Spring, MD 0/3/05 Building Electrical System Overview Executive Summary: The following report describes the existing emergency power

More information

Continuous Commissioning: A Valuable Partner to Retrofit Projects

Continuous Commissioning: A Valuable Partner to Retrofit Projects Continuous Commissioning: A Valuable Partner to Retrofit Projects Yeqiao Zhu Aamer Athar Kenneth Banks Ph.D. PE, CEM PE, CEM Energy Systems Laboratory Sempra Energy Solutions Sempra Energy Solutions Charles

More information

Successful Applications Using ISA100 Wireless Technology

Successful Applications Using ISA100 Wireless Technology Successful Applications Using ISA100 Wireless Technology Standards Certification Education & Training Publishing Conferences & Exhibits Phil Ng Honeywell Sr. Product Manager Wireless May 22, 2013 Presenter

More information

PURCHASING DEPARTMENT LOUISVILLE, KENTUCKY

PURCHASING DEPARTMENT LOUISVILLE, KENTUCKY PURCHASING DEPARTMENT LOUISVILLE, KENTUCKY Date: June 14, 2017 Invitation No: IB-096-17 Title: Student Activity Center Renovation and Addition, Bid Package V Addendum No. Three (3) The following shall

More information

Narrative Reports As Regulated by 780 CMR, Section 903.0

Narrative Reports As Regulated by 780 CMR, Section 903.0 EXHIBIT 20 Narrative Reports As Regulated by 780 CMR, Section 903.0 903.1.1 - FIRE PROTECTION CONSTRUCTION DOCUMENTS a. Basis (methodology) of design for the protection of the occupancy and hazard for

More information

PIP PCTPA001 Testing of Process Analyzer Systems

PIP PCTPA001 Testing of Process Analyzer Systems January 2016 Process Control PIP PCTPA001 Testing of Process Analyzer Systems PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES In an effort to minimize the cost of process industry facilities, this Practice

More information

THE 2012 EDITION OF THE LIFE SAFETY CODE HOSPITAL EDITION SESSION #6

THE 2012 EDITION OF THE LIFE SAFETY CODE HOSPITAL EDITION SESSION #6 THE 2012 EDITION OF THE LIFE SAFETY CODE HOSPITAL EDITION SESSION #6 WELCOME Moderator: Richard Schieferdecker support.webinato.com Audio 1 QUESTIONS How To Ask a Question: POLLING There will be occasional

More information

Minimum Standards for Engineers Practicing Fire Protection Engineering in the State of Oklahoma September 14, 2016

Minimum Standards for Engineers Practicing Fire Protection Engineering in the State of Oklahoma September 14, 2016 1. Introduction The intent of this document is to establish minimum standards for the practice of fire protection engineering within the State of Oklahoma as conducted by licensed professional engineers.

More information

RESOLUTION NO. WHEREAS, the City of San José (City ) owns and operates the Norman Y. Mineta San José International Airport ( Airport ); and

RESOLUTION NO. WHEREAS, the City of San José (City ) owns and operates the Norman Y. Mineta San José International Airport ( Airport ); and RESOLUTION NO. A RESOLUTION OF THE COUNCIL OF THE CITY OF SAN JOSE AUTHORIZING THE NORMAN Y. MINETA SAN JOSE AIRPORT TO SOLE-SOURCE CERTAIN PRODUCTS AND/OR SERVICES AS PART OF ANY FUTURE CAPITAL IMPROVEMENT

More information

Humidity Control Design Tips. R. Mark Nunnelly, PE, CxA, LEED AP President

Humidity Control Design Tips. R. Mark Nunnelly, PE, CxA, LEED AP President Humidity Control Design Tips R. Mark Nunnelly, PE, CxA, LEED AP President AIA Quality Assurance The Building Commissioning Association is a Registered Provider with The American Institute of Architects

More information