1 MARY CRAPO CENTER 8197 Miller Road, Swartz Creek, Michigan
2 MARY CRAPO CENTER 8197 Miller Road, Swartz Creek General Information: - Instructional, Child Care Development Center (West Wing) o (2) Infant/Toddler Birth to 2.5 years 20 children o (1) Preschool/Special Needs 2.5 to 12 years 17 children o (2) Preschool 1 ½ to 2 year olds 38 children o (6) PreK 3 to 4 years 125 children - Student Population: 200 Maximum Licensed Student Population: Child Care Staff: 35 - Instructional, Alternative and Adult Education (East Wing and Central Section) o (7) Classrooms o Gymnasium with Stage - Student Population: 160 (90 alternate high school / 70 evening adult education) - Staff: 20 - Year Built: 1928 / Building Size: 47,410 square feet, total all three levels - Site Size: 5 acres - Utilities: o Natural Gas: Consumers Energy o Electricity: Consumers Energy o Water: City of Swartz Creek o Sanitary: City of Swartz Creek Site Information / Condition: See site map included. - Site Entrance: Two entry points from School Street. One entry point from Mclain Street. - Child Care Parking/Drop-off: 28 spaces on west side of building from Mclain Street. - Alternative Education Parking: 68 spaces on south side of building from School Street. - Bus Drop Off Area: No buses at this site. - Playgrounds: o Combination of older and newer play equipment surrounded with wood fiber mulch. Toddler area has cushioned mats in lieu of mulch. Entire playground is enclosed with chainlink fencing. Overall in good condition, however additional wood fiber mulch is required. Older pieces of play equipment should be replaced. Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 1
3 o (1) ballfield with fenced backstop use as practice field for JV and varsity. In good condition. o Site fencing is in good condition. - Asphalt Pavement: Overall in very poor condition. Drainage is a problem in many areas causing icy conditions during cold weather. Entry/exit drives from School Street are steep. All parking lots and drives should be pulverized, reshaped and re-paved. - Concrete Sidewalks: Overall in good condition with some areas showing some surface spalding. Areas that are broken and uneven need to be replaced. - Site Lighting: Wall mounted light fixtures. - Landscaping: Generally consists of lawn area with some major trees around the site s perimeter. General Building/Site Information: - Number of Stories: Three. - Construction Type: o Concrete frame and masonry bearing wall. o Concrete slab on steel bar joist roof structure with coal tar built-up roofing membrane o Concrete slabs on grade or steel bar joist o Windows: Combination of steel sash with single pane glazing, aluminum awning windows with single pane glazing and new aluminum casement windows with insulating glazing. - Fire Suppression: None. - Exterior Walls: Are in good condition with some brick tuckpointing required. Cracks in the masonry that have been tuckpointed in the past are solid and show no additional signs of movement. - Window Sash: Windows vary from excellent operating condition to very poor depending on the type and age of the windows. Windows are of the following types: o East Wing: Aluminum awning and fixed windows units glazed with single pane glass. o Center (Gymnasium) Section: Original steel frame windows glazed with single pane glass. Most of the windows in the gymnasium have been covered over with panels. o West Wing: New aluminum storefront with casement windows glazed with insulating glazing. - Entry Doors: All remaining wood and hollow metal doors in hollow metal frames should be replaced. Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 2
4 o East Wing: Main entry doors have been replaced with aluminum doors in aluminum frame. o Central (Gymnasium) Section: Entry doors are the original wood doors and frames and are in bad condition. o West Wing: Entry doors at center stairway have been replaced with aluminum doors in aluminum frame. Remaining entry doors are the original wood doors and frames and are in fair to bad condition. - Roof Membrane: Coal tar built-up membranes with aggregate surfacing over 1 perlite insulation and 1 to 1 ½ rigid insulation on concrete deck. Roof membranes are approximately 15 to 20 years old. o Existing R-Value of Roof Insulation R10 Required R-Value R20 - Interior Walls: Masonry construction (CMU - slag aggregate type). In some areas the masonry is exposed and painted and in other areas it is plastered over. Although structural sound the walls appear old and dated. Some new partitions in the west wing are gypsum board. - Interior Doors: Doors vary throughout the building. Very few doors comply with ADA latch side clearance requirements. o Doors and Frames: A large majority of the original wood panel doors in wood frames remain. Some doors have been replaced with hollow metal doors and frames and some with solid core wood doors in hollow metal frames. o Door Lites and Transoms: Are glazed with wire or non-wire glass. o Hardware: All knob handles should be replaced with lever handles and keyed alike throughout the building. Classroom doors must have closer installed. - Carpet Flooring: Condition varies with the age of the carpet. Generally the life expectancy is 10 to 12 years for a classroom. Carpet appears to have been laid over the original 9x9 asbestos tile flooring to encapsulate it. - Vinyl Tile Flooring: Some rooms still have the original 9x9 asbestos tile flooring exposed. Should consider flooring over to encapsulate it. - Acoustical Ceilings: Majority of ceilings throughout the building are 2x4 suspended acoustical tile. The grid appears to be original and is rusting and has discolored over time. Condition of tiles varies, but replacing the ceiling system throughout the building would greatly improve the buildings overall appearance. - Plaster Ceilings: Overall are in fair condition with only minor areas needing some patch work and painting. - Lighting: The majority of the building lighting consists of 2x4 lay-in fluorescent fixtures that have been re-lamped with T8 bulbs. All major rooms have occupancy sensors to control lighting. Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 3
5 - Emergency Lighting: Emergency lighting should be installed throughout the building to comply with current codes. - Fire Alarm System: Is original and is grandfathered for continued use, however it does not comply with current codes and should be replaced with an audible / visual system. - Plumbing Fixture Count: o Staff Toilets East (Adult Education) Wing: Women 1 water closet required, 1 unisex fixture currently Men 1 water closet required, 1 unisex fixture currently o Student Toilets East (Adult Education) Wing: Women - 3 water closets required, 3 fixtures currently Men - 3 water closets required, 8 fixtures currently o Staff Toilets West (Child Care) Wing: Women 1 water closet required, 2 unisex fixtures currently Men 1 water closet required, 2 unisex fixtures currently o Children Toilets West (Child Care) Wing: Children -? water closets required, 16 fixtures currently - Mechanical: Existing HVAC system for this building consists of a central steam heating system served by two (2) newer low efficiency gas steam boilers. These boilers are housed in a separate boiler plant and supply the main building via exposed insulated piping. The steam piping serves a combination of perimeter steam radiation, cast iron radiators, unit ventilators, unit heaters and an air handling unit. Ventilation for the facility is mainly via operable windows. The majority of existing heating and ventilation units are non-functional. Various rooms throughout the facility are provided with minimal cooling via a mix of window air conditioners, ductless split systems and portable spot coolers. - Electrical: The majority of the lighting fixtures in the Alternate Education wing are older 2x4 lay-in which have been converted from T12 fluorescent lamps to T8 fluorescent lamps. The lenses of the fixtures are showing their age and many are damaged, yellowed or sagging down out of the fixture frames. Lighting fixtures in the Child Development wing consists of 2x4 lay-in with T8 lamps. The fixtures are in good condition. The Kitchen was recently renovated and has LED lay-in light fixtures. Lighting controls in the form of occupancy sensors have been added in classrooms, storage rooms, etc, but were not seen in corridors. Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 4
6 Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 5
7 Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 6
8 Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 7
9 Inventory of Existing Building Finishes / Conditions: Condition of finishes is subjective and based on the following criteria: Good: The finish material appears similar to its original condition and with continued maintenance should last its intended life expectancy. Example: Carpeting rated Good Surface shows little wear and has an expected remaining life of 8 to 10 years of a 10 to 12 year life. Fair: The finish material shows some wear or condition issues that need maintenance. Example: Carpeting rated Fair Surface shows wear and/or staining, seams may be showing, and has an expected remaining life of 3 to 4 years. Bad: The finish material is at the end of its life expectancy and needs to be replaced. 100E Corridor Material Condition Walls Painted Plaster / Wood Panels / FRP X Base 6 Coved Vinyl, some sections damaged X Lighting (8) 1x4 Surface Mounted /(2) T8 lamps X North Stairway Treads Carpet X Handrails Round Wood, one side only Knob door handle, hollow metal door at top landing South Stairway Walls FRP X Treads Vinyl X Handrails Round Wood, one side only Knob door handle, hollow metal door at top landing 100N Corridor Material Condition Walls Painted Masonry X Lighting (8) 1x4 Surface Mounted /(2) T8 lamps X Lever door handles, hollow metal doors Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 8
10 100W Corridor Material Condition Walls Painted CMU / Plaster X Lighting (7) 2x4 Lay-in /(2) T8 lamps X Lockers 12 x 12 Single Tier, free standing X North Stairway Treads Terrazzo, worn X Lighting Handrails 1x4 Surface Mounted /(2) T8 lamps Round Wood Knob door handle, hollow metal door at top South Stairway Treads Terrazzo, worn X Lighting Handrails 1x4 Surface Mounted /(2) T8 lamps Round Wood Knob door handle, hollow metal door at top 102 Book Club Material Condition Walls Painted CMU / Plaster X Base 8 Carpet X Lighting (1) 1x4 Surface Mounted /(2) T8 lamps X Knob door handle 104 Classroom Material Condition Walls Painted Plaster / Wood Paneling X Base 8 Carpet X Lighting (14) 1x4 Surface Mounted /(2) T8 lamps X Knob door handle / panel wood door with ½ lite Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 9
11 106 Classroom Material Condition Walls Painted Plaster / Wood Paneling X Floor Carpet Tile X Lighting (6) 1x4 Surface Mounted /(2) T8 lamps X Air Conditioning Window Units Knob door handle / panel wood door 110 Office Material Condition Walls Painted Plaster / Wood Paneling X Base 8 Carpet X Lighting (6) 1x4 Surface Mounted /(2) T8 lamps X Knob door handle / wood door 110A Office Material Condition Walls Painted Plaster / Wood Paneling X Lighting (2) 2x4 Lay-in /(2) T8 lamps X Air Conditioning Window Unit Knob door handle / wood door 110B Office Material Condition Walls Painted Plaster / Wood Paneling X Lighting (2) 2x4 Lay-in /(2) T8 lamps X Air Conditioning Window Unit Knob door handle / wood door 110C Storage Material Condition Walls Painted Plaster / Wood Paneling X Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 10
12 Lighting (2) 2x4 Lay-in /(2) T8 lamps X Knob door handle / wood door 112 Classroom Material Condition Base 8 Carpet X Ceiling Plaster / 2x4 Suspended Acoustical Tile X Lighting (8) 1x4 Surface Mounted /(2) 2x4 Lay-in /(2) T8 lamps X Air Conditioning Portable Room Unit Knob door handle / panel wood door with ½ lite Adjoining Restroom Walls Painted Masonry X Floor 12x12 Vinyl Tile X Base No Base Lighting 1x4 Surface Mounted /(2) T8 lamps, very dim X Water Closet Floor Mounted Tank X Lavatory Wall Mounted with push handles, no pipe wrap X Comments: 1. Restroom is not ADA Compliant 114 Mens Restroom Material Condition Walls Painted Masonry X Floor Painted Concrete X Base No Base Lighting (12) 2x4 Lay-in /(2) T8 lamps X Stall Partitions Wood with no doors X Water Closets Floor Mounted Flush Valve, no sensors missing seat X Lavatory Wall Mounted X Urinals Wall Mounted, no sensors X Knob door handle Comments: 1. Restroom is not ADA Compliant and has 6 step up at entry door. Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 11
13 113 Classroom Material Condition Walls Painted CMU / Concrete / Wood Paneling X Lighting (6) 1x4 Surface Mounted /(2) T8 lamps X Lever door handle / wood panel door with ½ lite Adjoining Office Walls Gypsum Board, 7 foot high X Ceiling See Classroom 113 Lighting See Classroom 113 Knob door handle, wood door Adjoining Storage Walls Painted CMU / Concrete X Floor 9x9 Vinyl Tile / Carpet Tile X Base Wood X Ceiling Plaster, holes from new plumbing work above X Lighting (3) 4 foot Surface Mounted /(2) T8 lamps X 115 Classroom Material Condition Walls Painted Plaster / Concrete X Lighting (15) 1x4 Surface Mounted /(2) T8 lamps X Casework Painted Wood X Knob door handle 117 Classroom Material Condition Walls Painted Plaster / Concrete X Lighting (17) 2x4 Lay-in /(4) T8 lamps X Casework Painted Wood / Plastic Laminate X Knob door handle, wood panel door with ½ lite Adjoining Restroom Walls Glazed Tile Wainscot / Plaster X Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 12
14 Lighting (1) 1x4 Surface Mounted /(2) T8 lamps X Water Closet Floor Mounted Flush Valve, no sensor X Lavatory Wall Mounted with push handles X Knob door handles, wood panel door Comments: 1. Restroom is not ADA Compliant. 116 Special Education Material Condition Walls Painted CMU / Gypsum board X Lighting (8) 2x4 Lay-in /(2) T8 lamps X Air Conditioning Room Wall Mounted Unit Lever door handles, wood panel door with ½ lites Adjoining Offices Walls Painted Gypsum board / Concrete X Lighting (4) 2x4 Lay-in /(2) T8 lamps (each office) X Staff Restroom Material Condition Walls Glazed Tile Wainscot / Plaster X Lighting (1) 1x4 Surface Mounted /(2) T8 lamps X Water Closet Floor Mounted Flush Valve X Lavatory Wall Mounted with push handles X Knob door handle, wood panel door Comments: 1. Restroom is not ADA Compliant. 119 Kitchen Material Condition Walls FRP X Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 13
15 Lighting (11) 1x4 Lay-in / LED X Lever door handles, hollow metal doors Adjoining Storage Walls FRP / Painted CMU / Concrete X Lighting (4) 1x4 Lay-in / LED X Cafeteria (Extended Day) Material Condition Walls Painted Plaster / Concrete X Lighting (25) 2x4 Lay-in /(4) T8 lamps X Tables/Seating Portable Folding X Knob door handles, wood and hollow metal with ½ lites 123 Classroom Material Condition Walls Painted Plaster / Wood Paneling X Floor 9 x 9 Vinyl Tile X Base 4 Coved Vinyl / Wood X Lighting (12) 1x8 Stem Hung /(2) T8 lamps X Casework Wood / Plastic Laminate X Knob door handle, wood panel door 125 Storage Material Condition Walls Painted CMU / Concrete X Floor Concrete X Base No Base Ceiling 12 x 12 Acoustical Tile glued to plaster ceiling X Lighting (12) 1x4 Surface Mounted /(2) T8 lamps X Knob door handle, wood panel door Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 14
16 200E Corridor Material Condition Walls Painted CMU X Floor Terrazzo X Base Coved Terrazzo X Lighting (5) 2x4 Lay-in /(4) T8 lamps X North Stairway Walls Painted CMU / Plaster X Treads Terrazzo with Metal Nosing, worn X Handrails Round Wood, both sides Knob door handle, hollow metal door at top landing South Stairway Walls Painted CMU X Treads Terrazzo with Metal Nosing, worn X Ceiling See Corridor 200 Handrails??? 200W Corridor Material Condition Floor Terrazzo X Base Coved Terrazzo X Lighting (8) 2x4 Lay-in /(4) T8 lamps X Lockers 12 x 12 Single Tier X North Stairway Landing and Treads Terrazzo X Handrails Round Wood, both sides Knob door handle, hollow metal doors South Stairway Landing and Treads Terrazzo X Lighting Handrails (2) 1x4 Surface Mounted /(2) T8 lamps Round Wood, both sides Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 15
17 201 Child Care Infant / Toddler Material Condition Walls Painted Plaster / FRP X Lighting (12) 2x4 Lay-in /(4) T8 lamps X Knob door handle, wood panel door with ½ lite Adjoining Restroom Lighting (1) 2x4 Lay-in /(4) T8 lamps X Water Closet Floor Mounted Flush Valve, no sensor X Lavatory Wall Mounted with lever handle, no pipe wrap X Knob door handle / wood door Comments: 1. Restroom is not ADA Compliant 202 Museum Material Condition Walls Painted Plaster / Gypsum board X Lighting (12) 2x4 Lay-in /(4) T8 lamps X Knob door handle, wood panel door with ½ lite 202A Classroom Material Condition Walls Painted Plaster / Gypsum board X Lighting See Museum 202 X Knob door handle, wood panel door with ½ lite 203 Office Child Development Material Condition Base 4 Coved Vinyl / Wood X Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 16
18 Lighting (8) 2x4 Lay-in /(4) T8 lamps X Knob door handle, wood panel door with ½ lite 203A Office Material Condition Base 4 Coved Vinyl / Wood X Lighting (4) 2x4 Lay-in /(4) T8 lamps X Knob door handle, wood panel door with ½ lite Workroom Lighting (3) 2x4 Lay-in /(4) T8 Lamps X Knob door handle, wood door 204 Girls Restroom Material Condition Walls Painted Plaster / Wood Panels X Floor Terrazzo X Base Coved Terrazzo X Lighting (2) 1x4 Surface Mounted /(2) T8 lamps X Stall Partitions Metal, Floor Mounted X Water Closet Floor Mounted Flush Valve without sensors X Lavatory Floor Mounted with lever handles, enclosed pipes X Push / pull door handle Comments: 1. Restroom is not ADA Compliant. 206 Classroom Material Condition Lighting (12) 2x4 Lay-in /(4) T8 lamps X Knob door handles, wood panel door with ½ lite Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 17
19 207 Child Care Treasure Chest Material Condition Floor 12 x 12 Vinyl Tile / Carpet X Lighting (12) 2x4 Lay-in /(4) T8 lamps X Casework Painted Wood X Knob door handle / wood panel door with ½ lite 208 Office Material Condition Walls Painted Plaster / Gypsum board X Floor Carpet Tile X Lighting (10) 2x4 Lay-in /(4) T8 lamps X Lever door handles / wood panel door with ½ lite Adjoining Offices Floor Carpet Tile X Lighting (2) 2x4 Lay-in /(4) T8 lamps X Lever door handles / wood doors Adjoining Storage Floor Carpet Tile X Lighting (2) 2x4 Lay-in /(4) T8 lamps X Lever door handle / wood door Adjoining Breakroom Floor Carpet Tile X Lighting (2) 2x4 Lay-in /(4) T8 lamps X Lever door handle / wood door Adjoining Restroom Walls FRP X Floor Terrazzo X Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 18
20 Lighting (1) 2x4 Lay-in /(4) T8 lamps X Water Closet Floor Mounted Flush Valve, no sensor X Lavatory Wall Mounted with lever handle, no pipe wrap X Lever door handle / wood door Comments: 1. Restroom is not ADA Compliant 209 Child Care Infant / Toddler Material Condition Floor 12 x 12 Vinyl Tile / Carpet X Lighting (12) 2x4 Lay-in /(4) T8 lamps X Casework Painted Wood X Knob door handle / wood panel door with ½ lite 210 Classroom Material Condition Base 4 and 6 Coved Vinyl X Lighting (12) 2x4 Lay-in /(4) T8 lamps X Lever door handle, wood panel door with ½ lite 211 Child Care Kinder Day Material Condition Floor 12 x 12 Vinyl Tile / Carpet X Lighting (9) 2x4 Lay-in /(4) T8 lamps X Casework Painted Wood Knob door handle / wood panel door with ½ lite 213 Child Care Pre-K Material Condition Floor 12 x 12 Vinyl Tile / Carpet X Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 19
21 Lighting (9) 2x4 Lay-in /(4) T8 lamps X Casework Painted Wood X Knob door handle / wood panel door with ½ lite 215 Restroom Material Condition Walls Glazed Tile Wainscot / Painted Plaster / FRP X Floor Terrazzo X Base Coved Terrazzo / 6 Coved Vinyl X Lighting (2) 1x4 Surface Mounted /(2) T8 lamps X Stall Partitions Metal, Floor Mounted with Wood doors X Water Closet Floor Mounted Flush Valve without sensors X Lavatory Floor Mounted with lever handles, enclosed pipes X Push / pull door handle Comments: 1. Restroom is not ADA Compliant. Gymnasium Material Condition Walls Painted CMU X Floor 10 x 10 Sports Flooring X Lighting (12) Surface Mounted High Bays / Metal Halite Lamps X Knob door handles, hollow metal and wood doors 300E Corridor Material Condition Walls Painted CMU / Gypsum board X Floor Terrazzo X Base Coved Terrazzo X Lighting (5) 2x4 Lay-in /(4) T8 lamps X Lockers 10 x 12 Single Tier X North Stairway Walls Painted CMU X Landing and Treads Terrazzo with Metal Nosing, worn X Handrails Round Wood, both sides Knob door handle, hollow metal door Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 20
22 300W Corridor Material Condition Walls Painted CMU X Floor Terrazzo X Base Coved Terrazzo X Lighting (9) Incandescent Bulbs X Lockers 12 x 12 Single Tier X North Stairway Landing and Treads Terrazzo, worn X Handrails Round Wood, both sides Lever door handles, hollow metal doors South Stairway Landing and Treads Terrazzo, worn X Handrails Round Wood, both sides Lever door handles, hollow metal doors 301 Child Care Pre-School Material Condition Base 4 Coved Vinyl / Wood X Lighting (20) 2x4 Lay-in /(4) T8 lamps X Knob door handles / wood panel door with ½ lite Adjoining Storage Walls Painted Plaster / Gypsum board X Floor Carpet Tile X Base 4 Coved Vinyl / No base X Lighting (3) 2x4 Lay-in /(4) T8 lamps X Knob door handle / wood panel door with ½ lite Adjoining Restroom Walls Painted Gypsum board X Lighting (1) 2x4 Lay-in /(4) T8 lamps X Water Closet Floor Mounted Tank X Lavatory Wall Mounted with lever handle and pipe wrap X Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 21
23 Lever door handle / wood door Comments: 1. Restroom is ADA Compliant. 302 Classroom Material Condition Lighting (12) 2x4 Lay-in /(4) T8 lamps X Air Conditioning Portable Room Unit Knob door handle / wood panel door with ½ lite 303 Child Care CDC Resource Room Material Condition Floor 12 x 12 Vinyl Tile / Carpet X Base Wood X Lighting (12) 2x4 Lay-in /(4) T8 lamps X Casework Painted Wood X Knob door handle / wood door 305 Staff Restroom Material Condition Walls Painted Gypsum board X Lighting (1) 1x4 Lay-in /(4) T8 lamps X Water Closet Floor Mounted Tank X Lavatory Wall Mounted with lever handle and pipe wrap X Lever door handle, wood door Comments: 1. Restroom is ADA Compliant. 306 Classroom Pre-School Material Condition Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 22
24 Lighting (12) 2x4 Lay-in /(4) T8 lamps X Air Conditioning Portable Room Unit Knob door handle / wood panel door with ½ lite 307 Child Care Pre-School Material Condition Walls Painted Plaster / Gypsum X Floor 12 x 12 Vinyl Tile / Carpet X Lighting (12) 2x4 Lay-in /(4) T8 lamps X Casework Painted Wood X Knob door handle / wood panel door with ½ lite Adjoining Restroom Walls Painted Gypsum board X Lighting (1) 2x4 Lay-in /(4) T8 lamps X Water Closet Floor Mounted Tank X Lavatory Wall Mounted with lever handle and pipe wrap X Lever door handle / wood door Comments: 1. Restroom is ADA Compliant. 309 Child Care Pre-School Material Condition Walls Painted Plaster / Gypsum X Floor 12 x 12 Vinyl Tile / Carpet X Lighting (11) 2x4 Lay-in /(4) T8 lamps X Casework Painted Wood X Knob door handle / wood panel door with ½ lite Adjoining Restroom Walls Painted Gypsum board X Lighting (1) 2x4 Lay-in /(4) T8 lamps X Water Closet Floor Mounted Tank X Lavatory Wall Mounted with lever handle and pipe wrap X Lever door handle / wood door Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 23
25 Comments: 1. Restroom is ADA Compliant. 310 Classroom Material Condition Lighting (12) 2x4 Lay-in /(4) T8 lamps X Air Conditioning Window Units Lever door handle / wood panel door with ½ lite 311 Child Care Pre-School Material Condition Walls Painted Plaster / Gypsum X Floor 12 x 12 Vinyl Tile / Carpet X Base Wood X Lighting (12) 2x4 Lay-in /(4) T8 lamps X Casework Stained Wood X Knob door handle / wood panel door with ½ lite Adjoining Restroom Walls Painted Gypsum board X Lighting (1) 2x4 Lay-in /(4) T8 lamps X Water Closet Floor Mounted Tank X Lavatory Wall Mounted with lever handle and pipe wrap X Lever door handle / wood door Comments: 1. Restroom is ADA Compliant. 312 Classroom Material Condition Walls Painted Plaster / Gypsum board X Lighting Air Conditioning (6) 2x4 Lay-in /(4) T8 lamps Window Unit Lever door handle / wood panel door with ½ lite Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 24
26 Staff Workroom Walls Painted Plaster / Gypsum board X Base 6 Coved Vinyl / No base X Lighting (3) 2x4 Lay-in /(4) T8 lamps X Lever door handle / hollow metal door 313 Child Care Pre-School Material Condition Walls Painted Plaster / Gypsum X Floor 12 x 12 Vinyl Tile / Carpet X Lighting (12) 2x4 Lay-in /(4) T8 lamps X Casework Painted Wood X Knob door handle / wood panel door with ½ lite Adjoining Restroom Walls Painted Gypsum board X Lighting (1) 2x4 Lay-in /(4) T8 lamps X Water Closet Floor Mounted Tank X Lavatory Wall Mounted with lever handle and pipe wrap X Lever door handle / wood door Comments: 1. Restroom is ADA Compliant. 314 Office Material Condition Walls Painted Plaster / Gypsum board X Lighting (3) 2x4 Lay-in /(4) T8 lamps X Air Conditioning Window Unit Lever door handle / wood panel door with ½ lite 315 Girls Restroom Material Condition Walls Glazed Tile Wainscot / Painted Plaster / FRP X Floor Terrazzo X Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 25
27 Base Coved Terrazzo / 6 Coved Vinyl X Lighting (2) 1x4 Surface Mounted /(2) T8 lamps X Stall Partitions Metal, Floor Mounted with Wood doors X Water Closet Floor Mounted Flush Valve without sensors X Lavatory Floor Mounted with lever handles, enclosed pipes X Push / pull door handle Comments: 1. Restroom is not ADA Compliant. 316 Boys Restroom Material Condition Floor Terrazzo X Base Coved Terrazzo X Lighting (2) 1x4 Surface Mounted /(2) T8 lamps X Stall Partitions Plywood X Water Closet Floor Mounted Flush Valve X Lavatory Wall Mounted with knob handles, no pipe wrap X Urinals Floor Mounted without sensors X Push / pull door handle Comments: 1. Restroom is not ADA Compliant. Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 26
28 Swartz Creek Mary Crapo Center Adult Education and Day Care 1928 Original Construction 47,410 sf Mechanical Systems Existing heating ventilation and air conditioning (HVAC) system description: The existing HVAC system for this building consists of a central steam heating system served by two newer 80% natural gas steam boilers. The boilers are housed in a separate boiler plant building and supply the main building via exposed insulated steam and condensate piping. The steam piping serves a combination of perimeter steam radiation, cast iron radiators, unit ventilators, unit heaters and an air handling unit. The first floor rooms 100N, 123, and 125, and second floor gymnasium are heated by steam cast iron ceiling type radiators. Corridors 100E, 200E, 300E and stairways are heated by wall type steam cast iron radiators. A non-functional steam heat air handling unit supplies first floor rooms 104 and 106, second floor rooms 202A, 202, 206, and 210, and third floor rooms 302, 306, 310, and 314. Two small steam heat air handling units upon the stage area supply the gymnasium. First floor rooms 100W, 113, and 119 are heated by steam fin tube radiation. Rooms 115, 117 and the cafeteria are heated by steam unit heaters. Second floor rooms 201, 203, 207, 209, 211 and 213, and third floor rooms 301, 303, 307, 309, 311, and 313 are heated by steam unit ventilators and convectors. Ventilation for the facility is mainly via operable windows. The gymnasium is served by nonfunctional heating and ventilation units. Rooms 104, 106, 110, 202A, 206, 210, 302, 306, 310, and 314 are served by a non-functional (belts are off) heating and ventilating unit located in a first floor mechanical room. Rooms 201, 203, 207, 209, 211, 213, 301, 307, 309, 311, and 313 ventilation is via unit ventilators. In general most of the mechanical ventilation equipment appears to be non-functional. In general mechanical outside air ventilation is non-functional or non-existent. The majority of this facility has no air conditioning. A mix of window air conditioners, ductless split systems, and portable spot coolers are located in various rooms, that provide minimal cooling. Window air conditioners are located in rooms 110B, 110C, 310, 311, 312, and 314. Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 27
29 Portable spot coolers are located in rooms 112 and 306. Ductless split air conditioners are located in the kitchen, three offices in 110 area, rooms 207, 211, 302 and 307. Electrical Systems Electrical Service/Power Distribution The main distribution is original consisting of a 800amp 240 volt FPE disconnect switch with original FPE QMQB fed panel boards and some newer square d fused disconnect switches located in the lower level electrical room. The service comes in overhead with one single phase feed and one 3 phase feed. The main distribution is full with several tapped disconnects. Branch circuit panel boards, wiring, and general purpose receptacles are new in the Early Childhood areas and original in the West Side School Areas. Classrooms have some surface raceway and computer rooms have power poles to feed the dense receptacle loads. Recommendation: 1. Replace the obsolete FPE electrical distribution. 2. Remove the X panel and add/refeed emergency loads via : a. A new emergency generator b. A new inverter c. Individual battery units within the fixtures 3. Replace remaining original branch distribution panel boards associated conduit and wire. Lighting Interior: High School Area: A majority of the lighting fixtures are from original construction which have been converted from T12 fluorescent lamps to T8 fluorescent lamps. The lenses of the fixtures are showing their age and many are damaged, yellowed or sagging down out of the fixture frames. Kitchen/Cafeteria: Cafeteria Lighting consists of newer 2x4 lay in prismatic lensed light fixtures. The kitchen was very recently renovated with LED lay in light fixtures. Head Start: Lighting in the Head Start areas consists of 2x4 lay in prismatic lensed fixtures with T8 lamps. The fixtures are in good condition. The corridors have incandescent sockets with screw in LED A lamps. Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 28
30 The Exit lights have been replace and added over the years and provide good coverage for marking the path of egress. They are typically equipped with two emergency lighting heads which appear to be the only emergency egress lighting source. Lighting controls in for the form of occupancy sensors have been added in classrooms, storage rooms etc. but were not seen in the corridors. Exterior: Exterior lighting is limited with wood light poles in the parking lot. The wood poles are equipped with LED flood lights. There are few building mounted lights from original construction and also some wall mounted added at the entry canopy, all of which are in poor condition. Some, but not all, exit doors are equipped with light fixtures. In General the exterior lighting is inadequate and is past its useful life. Recommendation: 1. Lighting upgrades should be considered to be replaced with new high efficient LED lighting with added controls to meet current Michigan energy code requirements. 2. Emergency egress lighting is deficient and needs to be added throughout the building s interior and exit discharge areas. 3. Exterior lighting including building mounted and parking lot lighting should be replaced and added. 4. The gym lighting is original and should be replaced. 5. Replace exit and emergency lighting with new and associated wiring to meet current Life Safety and building codes. Fire Alarm The Fire Alarm system is an original Simplex brand system with limited bells and pulls stations. The fire alarm system is deficient and does not meet current Life Safety and building codes. Recommendation: 1. Replace the fire alarm system with new. Systems Public Address system is a Simplex (5110) brand DITEK from appx It appears to be functional but based on its age is most likely limited in its maintainability and expansion Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 29
31 options. Speakers are located in the walls of the classrooms and in the ceiling of the corridors. There is a handset phone in each classroom typically at the door. There is a Simplex brand wireless Master Clock system that appears to be functional with clocks in each classroom and the corridors. Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 30
32 Code Deficiencies: - Insufficient mulch cushioning on playground. - All main entrances are not ADA compliant. - Building lacks elevator. Not barrier-free accessible on all levels. - East wing, third level has only one exit stairway. - East wing stairways are not within a fire-rated enclosure. - Air shafts to classrooms not protected with fire-rated dampers. - Corridor 100N is less than 6 feet wide. Sections of corridor 100W also less than 6 feet wide. - Most room entry doors are not ADA compliant, lack latch side clearance. - Many entry/exit doors less than 32 wide clearance required. - Most corridor room doors are not fire-rated assemblies. - Classroom corridor doors lack closers. - Most classroom corridor doors have knob handles in lieu of levers. - Classrooms 115 and 123 entry doors swings in wrong direction for egress. - Door to stairway on third floor of east wing swings in wrong direction for egress. - Classroom 117 entry doors reduce corridor width. - East wing classrooms lack emergency egress windows. - All east wing toilet rooms are not ADA compliant. - Not all west wing toilet rooms are ADA compliant. - Emergency lighting insufficient throughout building. - Fire alarm is not an audio/visual system. Suggested Facility Upgrades: - Reconstruction all parking lots. - Provide site lighting. - Increase building security at main entrances. - Replace window units in Alternative and Adult Education wing. - Air condition building. Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 31
33 MARY CRAPO CENTER Proposed Site Work: Quantity of Work: Estimate of Cost: Concrete Walk Replacement 2625 sq feet $ 26, Concrete Parking Replacement 4400 sq feet $ 59, Pulverize and Reconstruct East Parking Lot (Academy Parking) Pulverize and Reconstruct West Parking Lot (Child Development) 41,250 sq feet $ 247, ,000 sq feet $ 68, New Concrete Walk at East Parking Lot 1900 sq feet $ 25, New Concrete Walks at West Parking 2900 sq feet $ 39, Lot Install Site Lighting 4 poles / 16 building $ 45, Reconstruct Paved Play Area 5000 sq feet $ 18, Total Estimated Cost of Site Work: $ 530, Proposed Code / Renovation Work: Quantity of Work: Estimate of Cost: Renovate Three Floors of Academy 14,700 sq feet $1,337, Renovate Two Floors of Gymnasium 9000 sq feet $ 900, Renovate Three Floors of Child 21,790 sq feet $1,852, Development Reroof Building 17,000 sq feet $ 102, Total Estimated Cost of Code / Renovation Work: $4,191, Proposed Building Additions: Quantity of Work: Estimate of Cost: Construct New Office and Vertical 3600 sq feet $ 810, Circulation at Academy 3 Floors Construction Elevator at Child 240 sq feet $ 60, Development 3 Floors Elevator and Equipment 2 units $ 125, Total Estimated Cost of Building Additions: $ 995, Swartz Creek Community Schools - Facility Study Mary Crapo Center - Page 32
34
35
36
37 MARY CRAPO CENTER ROOF CONDITION REPORT
38
39
HOLUM EDUCATION CENTER. Architectural. January 13, 2014 DeForest Area School District
HOLUM EDUCATION CENTER Architectural The existing building has approximately 41,823 square feet and sets on a lot about 4.14 acres in size. Parking lots are located along the east and west sides of the
More informationPLATTEVILLE MIDDLE SCHOOL
Architectural The building has aluminum clad wood awning windows in combination with aluminum fixed glass units. They appear to be exterior glazed with insulated glazing. See photo 2. Platteville Middle
More informationFlorence High School / Middle School Page 1 of 3 Florence, WI
Florence High School / Middle School Page 1 of 3 Florence, WI Plumbing Systems Review: The following report is the result of a site visit by Tim Kehoe of Muermann Engineering, LLC that occurred on October
More informationMUKWONAGO SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY
MUKWONAGO SCHOOL DISTRICT ARCHITECTURE PARK VIEW MIDDLE SCHOOL The original school building was dedicated in 1954 as the High School, with an addition in 1959, a library addition in 1970, and an addition/renovation
More informationVOTER BOND REFERENDUM 2018 SUMMARY OF WORK PROPOSED
Ashton Elementary School 1 Masonry Repair $ 42,781.50 2 Replace HVAC $ 375,000.00 3 Replace SAT @ Various Locations $ 92,364.00 3 Recoat & Resurface Exterior Paved Play Area $ 135,978.30 3 Various Technological
More informationMOUNT PLEASANT MIDDLE SCHOOL HVAC. M-01 Heating Plant: M-02 Heating & Ventilating Systems: Livingston School District Mount Pleasant Middle School
MOUNT PLEASANT MIDDLE SCHOOL HVAC M-01 Heating Plant: The existing boilers have recently been upgraded. (3) steam boilers (8660 mbh each) manufactured by Weil- McLain have been installed. Newer hot water
More informationGenevieve Melody Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationEdward Jenner Elementary Academy of the Arts
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More information3. 21st Century Learning A. Districtwide Flexible Learning - Allowance for Flexible Furniture $600,000 Subtotal $600,000
1. Safety and Security A. Additional Cameras District Wide $382,000 B. Interior Locks Upgrades Allowance $300,000 C. Tilden Entrance Upgrades D. Door and Glass Improvements Allowance $500,000 E. Alert
More information2 Main Office Building BLDG-955A Building Purpose Building Area Administration offices. Training room 7,610 SF Inspection Date August 16, 2016 Inspect
1 Site Summary Address 7200 Bluff Springs Road Austin, TX 78744 Number of Permanent Campus Facilities 2 Original Year of Construction 2014 Total Campus Building Area (combined) 25,314 SF Introduction The
More informationFrancis M McKay Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationJohn Palmer Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationAshland School District Facility & Capacity Assessment Report 2005
Ashland School District Facility & Capacity Assessment Report 2005 Briscoe Elementary School (Closed Facility) Address: 265 N Main Street Area: 33,980 square feet Buildings: Original Building 1948 Music
More informationJoseph Brennemann Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationMUKWONAGO AREA SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY
ARCHITECTURE ROLLING HILLS ELEMENTARY SCHOOL Rolling Hills Elementary was built in 1999 and is the newest addition to the Mukwonago Area School District. The building contains approximately 64,900 gross
More informationAlessandro Volta Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationDeWitt Clinton Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationJosefa Ortiz De Dominguez Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationFacility Condition Assessment Summary Report. British Columbia Institute of Technology NE6 - Plumbing and Pipefit Building
Facility Condition Assessment Summary Report British Columbia Institute of Technology NE6 - Plumbing and Pipefit Building Submitted by: VFA Canada Corp. Burnaby Centre 4211 Kingsway Burnaby, BC V5H 1Z6
More informationRichard Henry Lee Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationSidney Sawyer Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More information2014 Bond Project Guide
2014 Bond Project Guide Bush Elementary School Page 1 Instructional Technology Computers, Projectors, Mobile Carts, Document Cameras and Printers Wireless Connectivity New Construction New Tech Center
More informationAgustin Lara Elementary Academy
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationCalmeca Academy of Fine Arts and Dual Language
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationRECAPP Facility Evaluation Report
RECAPP Facility Evaluation Report Calgary School District #19 Queen Elizabeth Junior / Senior High School B2745A Calgary Report run on: March, 2010 10:02 AM Building Name: Address: Location: Building Id:
More informationWashington Irving Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationState College Area School District High School South Building EXISTING CONDITIONS ASSESSMENT
State College Area School District High School South Building Prepared by CenterPoint Engineering 08 February 2013 FACILITY ASSESSMENT SUMMARY PHYSICAL PLANT General HVAC This report is a snapshot of the
More informationGeorge B Swift Elementary Specialty School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationState College Area School District High School North Building EXISTING CONDITIONS ASSESSMENT
State College Area School District High School North Building Prepared by CenterPoint Engineering 08 February 2013 FACILITY ASSESSMENT SUMMARY PHYSICAL PLANT General HVAC This report is a snapshot of the
More informationOscar DePriest Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationCAPITAL OUTLAY REQUEST - IDENTIFIED AND EMERGING PROJECTS - RANKED 3-Jun-14
2014-2015 CAPITAL OUTLAY REQUEST - IDENTIFIED AND EMERGING PROJECTS - RANKED 3-Jun-14 School Item Amount a. Classroom A/R (Increase CR capacity to 804, add l Resource and tutoring spaces needed. Teacher
More informationNew High School Concept
Approved Bond Projects for Alamance-Burlington Schools In November 2018, Alamance County citizens approved a $150 million bond project proposal. Bond funds will pay to construct a new high school and provide
More informationSPACE TYPE: JUDICIAL CHAMBER
SPACE TYPE: JUDICIAL CHAMBER Construction Criteria The unit costs for Judicial Chamber space types are based on the construction quality and design features in the following table. This information has
More informationPlot # R019A ± 74' ± 74' ± 65' Plot # R019A LEASE OUTLINE DRAWING GROSS LEASABLE AREA ± 4,631 S.F. DEMISING FRONT WIDTH DEPTH ± 13' ± 32' Lease Line
± 4' ± 13' ± 72' Lease Line ± 6' ± 7' Plot # R019A ± 18' Lease Line Site N o : Site N ame: Lo catio n: Submitted B y: D rawn by D ate: 991 Santee Trolley Square Santee, CA ID Plans 11/10/2016 This drawing
More informationMassachusetts School Building Authority
Massachusetts School Building Authority School District Revere District Contact Paul Dakin TEL: (781) 286-8226 Name of School Submission Date 3/6/2007 The following Priorities have been included in the
More informationLibrary stacks and records storage 150 LB/SF live load
SPACE TYPE: LIBRARY Construction Criteria The unit costs for Library space types are based on the construction quality and design features in the following table. This information has been generally organized
More informationAllisonville Elementary School Facilities Highlights Built: 1960 Last Major Renovation: 28 years ago Capacity: 650 Current Enrollment: 767
Allisonville Elementary School Built: 1960 Last Major Renovation: 28 years ago Capacity: 650 Current Enrollment: 767 ADA improvements are Fire alarms need to be updated Playground equipment needs to be
More informationCharles W Earle Elementary School
Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual
More informationBriar Crest Elementary
Promises Kept This document includes partial lists of major projects completed at Pattonville Schools since 1986 as part of past bond issues approved by the Pattonville community. Briar Crest Elementary
More informationRECAPP Facility Evaluation Report
RECAPP Facility Evaluation Report Edmonton RCSSD #7 Bishop Savaryn Catholic Elementary School B58A Edmonton Report run on: July 10, 2008 3:31 PM Building Name: Address: Location: Building Id: Gross Area
More information2015 Building Condition Survey Summary Mosaic Associates Architects 02/19/16
1. General: This summary is offered as a supplement to the 2015 Building Condition Survey being filed with SED on behalf of the District. All cost estimates are preliminary, and should be re-evaluated
More informationMaster Facility Planning Update School Board Meeting May 26, 2016
Master Facility Planning Update School Board Meeting May 26, 2016 Master Facilities Committee Overview Reflection of Committee Work Review of District Wide Facility Issues Identified District Wide Facility
More informationTighe&Bond. Groton Heights School Mechanical Evaluation. 1 Existing Conditions. 1.1 Water Service Entrance
Groton Heights School Mechanical Evaluation TO: FROM: Amy Vaillancourt, Project Manager Harley Langford, Project Manger Jason Curtis, P.E. DATE: February 24, 2016; Revised May 31, 2016 On Monday, December
More informationAppendix E: Photo Documentation
Appendix E: Photo Documentation Brown County Library Central Branch Building Assessment Appendix E: Photo Documentation Architectural and Structural Brown County Library Central Branch Building Assessment
More informationDRAFT. Widen Elementary School Site Summary 74,523 SF. Introduction
1 Widen Elementary School Site Summary Address 5605 Nuckols Crossing Austin, TX 78744 Number of Permanent Campus Facilities 2 Original Year of Construction 1986 Total Campus Building Area (combined) 74,523
More informationSPACE TYPE: CHILD CARE
SPACE TYPE: CHILD CARE Construction Criteria The unit costs for Child Care Center space types are based on the construction quality and design features in the following table. This information has been
More informationIchabod Crane Central School District 2018 Capital Project Preliminary Estimate
Health & Safety 1,399,000 Academics & Program 17,140,800 Physical Education & Athletics 5,922,000 Building Infrastructure 3,103,800 Site Infrastructure 1,049,600 TOTAL SCOPE OF WORK 28,615,200 PROPOSED
More informationUnit # E ± 1,200 SF Width ± 20' Depth ± 60'
Lease Outline Drawing ±60' Lease Line Sunnymead Plaza 24907 Sunnymead Blvd., Unit # E, Moreno Valley, CA 92553 Unit # E ± 1,200 SF Width ± 20' Depth ± 60' Plans produced by: ID Plans 6/13/2017 (813) 657-2545
More information29 Bella Fontaine Park
29 Bella Fontaine Park 9565 Bellefontaine Road St. Louis County Parks Master Plan Planning Zone 2 Visit Date: July 2016 Page 1 129 Bella Fontaine Park 9565 Bellefontaine Road St. Louis County Parks Master
More informationForest Hills Facilities Plan
Forest Hills Facilities Plan Extensive updates to 8 of our 9 schools Replace Wilson Elementary Enhance learning environments across the district Build additional classrooms to accommodate gradual implementation
More informationMechanical Inspection Plumbing
0811 Fixtures Sinks, drinking fountains, water closets, showers, etc. Classroom Sinks. Classroom sinks (19) are enameled cast iron self rimming side ledge with gooseneck faucet trim with index handles,
More informationELECTRICAL SYSTEMS ASSESSMENT Hanover High School
ELECTRICAL SYSTEMS ASSESSMENT Hanover High School ELECTRICAL DISTRIBUTION SYSTEM:?? The existing electrical service consists of an underground primary service originating at a utility pole on Cedar Street,
More informationENGINEERING REPORT - MECHANICAL / ELECTRICAL / PLUMBING
Mechanical Systems Information The mechanical system at Reed Middle School is comprised of seventy six Trane DX/Gas rooftop units (RTUs). The recommended useful life for DX equipment is 15 years. Seventy
More informationRECAPP Facility Evaluation Report
RECAPP Facility Evaluation Report Edmonton RCSSD #7 Our Lady Of The Prairies Catholic Elementary School B3241A Edmonton Report run on: July 17, 2008 4:00 PM Building Name: Address: Location: Building Id:
More informationSpringpoint Architects, pc SECTION Childcare Center Architect s Project No TABLE OF CONTENTS Monroe County Comm. Sch. Corp.
Volume 1 Bidding Requirements, Contract Forms, Conditions of the Contract, Division 1, Architectural and Site Specifications 000107 Certification Page 000110 Table of Contents DIV00 PROCUREMENT AND CONTRACTING
More informationDEERFIELD SCHOOL DISTRICT REFERENDUM Committed to Excellence and Equity in Educating Our Students
DEERFIELD SCHOOL DISTRICT REFERENDUM Committed to Excellence and Equity in Educating Our Students FACILITY NEEDS THE CHALLENGE Deerfield Middle School/High School building has served the community for
More informationChariho Regional School District Five-Year Capital Facilities Improvement Plan (2/10/15)
Chariho Regional School District Five-Year Capital Facilities Improvement Plan (2/10/15) School/Department FY 16 FY 17 FY18 FY19 FY20 Chariho Regional High School FY 16 FY 17 FY18 FY19 FY20 *Repair Bleachers
More informationRECAPP Facility Evaluation Report
RECAPP Facility Evaluation Report Calgary RCSSD #1 Ecole St. Matthew Elementary / French Immersion Jr. High School B2614A Calgary Report run on: March 25, 2010 10:11 AM Building Name: Address: Location:
More informationUnit # 1038 ± 900 SF Width ± 15' Depth ± 60'
±60' Lease Line Lease Outline Drawing Needles Towne Center 1004 E. Broadway St.,, Needles, CA 92363 ± 900 SF Width ± 15' Depth ± 60' Plans produced by: ID Plans 6/16/2017 (813) 657-2545 C 2017 Site map
More informationALLISON ELEMENTARY SCHOOL 4315 Don Julio Blvd., North Highlands, CA 95660
ALLISON ELEMENTARY SCHOOL 4315 Don Julio Blvd., North Highlands, CA 95660 Year Built 1960 // Age 58 years Building Area 31,688 Square Feet Student Capacity 389 Current Enrollment (2017-2018) 466 Priority
More informationRECAPP Facility Evaluation Report
RECAPP Facility Evaluation Report Edmonton RCSSD #7 Bishop Savaryn Catholic Elementary School B358A Edmonton Report run on: March 11, 213 5:9 PM Building Name: Address: Location: Building Id: Gross Area
More informationUnit # H ± 2,000 SF Width ± 25' Depth ± 80'
±80' Lease Line Lease Outline Drawing Sunnymead Plaza 24907 Sunnymead Blvd., Unit # H, Moreno Valley, CA 92553 Unit # H ± 2,000 SF Width ± 25' Depth ± 80' Unit # H Plans produced by: ID Plans 6/13/2017
More informationHVAC / Boilers / Hot Water. Expected Life Span. very rough estimates Condition/Issue Age. Athletics / Gyms
$4,013,500.00 $4,013,500.00 $ 1,155,000.00 $ 1,000,000.00 $ 205,000.00 $ 275,000.00 $ 300,000.00 $ 360,000.00 $ 438,500.00 $ 280,000.00 School Status Item HS Boilers boiler controls replaced 2017 2002
More informationS AGE E NGINEERING A SSOCIATES, LLP
S AGE E NGINEERING A SSOCIATES, LLP 1211 Western Avenue Albany, NY (518) 453 6091 F (518) 453 6092 Kingston Library Mechanical and Electrical Systems Field Report Date of Visits: Mechanical - September
More informationVanilla Box Design Criteria
Description: 1. Floor: 2. Walls: 3. Ceiling: A. Finished and sealed 4 thick concrete slab on 10 mil poly vapor barrier on 4 of crushed stone throughout, including toilets. A. Interior gypsum board walls
More informationEstimated Repair, Replacement, and Upgrade Costs
Description Electrical Attic ventilator-mechanical $250 Baseboard heater (4') $150-$400 Ceiling fan $200 Doorbell system $80-$100 Dryer duct $100-$150 Hardwired smoke detector $60-$120 Exhaust Fan-Bathroom
More informationFacilities Master Planning
Facilities Master Planning DeForest Area School District DeForest, WI PRA Project #130343-01 January 13, 2014 DRAFT Table of Contents DeForest Area School District PRA Project # 130217-01 Section 1 Existing
More informationFirst Floor. Historic Hall of Waters Assessment and Feasibility Study
First Floor Overview The First Floor is the main floor of the building where all visitors enter, and has the highest level of historical significance. Art Deco and Mayan style ornamentation are found throughout
More informationRECAPP Facility Evaluation Report
RECAPP Facility Evaluation Report Edmonton School District No. 7 Clara Tyner Elementary School B375A Edmonton Report run on: March 16, 212 2:11 PM Building Name: Address: Location: Building Id: Gross Area
More informationGarfield Elementary School Feasibility Study for New Library Building Project Number A C
Larry Teixeira Selma Unified School District 3036 Thompson Avenue Selma, CA 93662 Subject: Feasibility Study for New Library Building Project Number A 12-8581.00 C Dear Mr. Teixeira: At your request, we
More informationRECAPP Facility Evaluation Report
RECAPP Facility Evaluation Report Edmonton School District No. 7 Coronation Elementary School B381A Edmonton Report run on: January 22, 27 11:33 AM Building Name: Address: Location: Building Id: Gross
More informationBlue Springs Park. Park Land Established: Developed Acres: 12 acres Undeveloped Acres: 2 acres
Blue Springs Park Park Location: 2204 SW South Ave. Park Land Established: 1975 Park Size: 14 acres Developed Acres: 12 acres Undeveloped Acres: 2 acres Park Type: Neighborhood Park Amenities: Softball
More informationPreliminary Study Document. Horicon. Horicon, Wisconsin
Preliminary Study Document Horicon School District Horicon, Wisconsin Monday table of contents i 1 2 Introduction Section One: Van Brunt Elementary School a. Building Evolution b. Existing Site Plan c.
More informationUnit HH Gregg. ± 30,000 SF Width ±26' Lakeland Retail Center. Lease Outline Drawing. Unit HH Gregg. Depth ± 145' HVAC Units & Information
Lease Outline Drawing Lakeland Retail Center 4000 US Hwy. 98, Unit HH Gregg, Lakeland, FL 33809 ±26' ±200' Lease Line Unit HH Gregg ±46' Lease Line ±21' Unit HH Gregg ±145' Lease Line ± 30,000 SF Width
More informationWilbur Young Park. Park Land Established: Developed Acres: 15 acres Undeveloped Acres: 25 acres
Wilbur Young Park Park Location: 1100 SE Adams Dairy Parkway Park Land Established: 1987 Park Size: 40 acres Developed Acres: 15 acres Undeveloped Acres: 25 acres Park Type: Community Park Amenities: Shelter
More informationREPORT CARD TO THE COMMUNITY MAY 15, 2018
REPORT CARD TO THE COMMUNITY MAY 15, 2018 O On May 10, 2014 voters in Greenville ISD approved a $72,275,000 bond election. BOND PROPOSAL PROJECT BOND AMOUNT CONSTRUCT A NEW BOWIE ELEMENTARY SCHOOL $17,600,000
More informationCOVIDIEN SENECA, SOUTH CAROLINA
SENECA, SOUTH CAROLINA 220,250 Square Feet on 73.30 Acres 1448 BLUE RIDGE BOULEVARD SENECA, SOUTH CAROLINA 29672 (OCONEE COUNTY) SIZE: NUMBER OF BUILDINGS: GROUND: Approximately 220,250 square feet One,
More informationRECAPP Facility Evaluation Report
RECAPP Facility Evaluation Report Wild Rose School Div #66 Pioneer School B3972A Rocky Mountain House Report run on: March 26, 213 9:48 AM Building Name: Address: Location: Building Id: Gross Area (sq.
More informationResidential Construction and Remodeling Estimates. compliments of. pillartopost.com
Residential Construction and Remodeling Estimates compliments of STRUCTURE/EXTERIOR Structure > addition (foundation to roof) $95 $130/sq.ft. > basement entrance $5250 $10500 > basement main beam $2100
More informationRECAPP Facility Evaluation Report
RECAPP Facility Evaluation Report Edmonton School District No. 7 Stratford Academic High School B3336A Edmonton Report run on: April 3, 29 1:6 AM Building Name: Address: Location: Building Id: Gross Area
More informationSHOREWOOD SCHOOL DISTRICT FACILITY ASSESSMENT. October 25, 2016 EUA Project:
October 25, 2016 EUA Project: 316125-01 Page 1 Eppstein Uhen Architects October 25, 2016 TABLE OF CONTENTS SECTION 1 EXECUTIVE SUMMARY TEAM CONTACTS PROJECT INTENT DATA GATHERING PROCESS UNDERSTANDING
More informationSummary of Repairs and Deficiencies
Summary of s and Deficiencies Organization Building: Station #1 178 Safety & Compliance Inspections and Certifications Sprinkler System Certifications This building is sprinkled but no inspection/ certification
More informationWard Park. Park Land Established: Developed Acres: 9 acres Undeveloped Acres: 4 acres
Ward Park Park Location: 1000 SW 22 nd St Park Land Established: 1979-80 Park Size: 13 acres Developed Acres: 9 acres Undeveloped Acres: 4 acres Park Type: Neighborhood Park Amenities: 2 Shelters, tennis
More informationRECAPP Facility Evaluation Report
RECAPP Facility Evaluation Report Lakeland Roman Catholic Separate School District No. 1 Ecole Notre Dame High School B266A Bonnyville Report run on: January 26, 2 : PM Bonnyville - Ecole Notre Dame High
More informationSITE SYSTEMS: FANNIE MAE EXPECTED USEFUL LIFE TABLES (FMEUL)
SITE SYSTEMS: FANNIE MAE EXPECTED USEFUL LIFE TABLES (FMEUL) Basketball Courts 15 25 Built Improvements Playgrounds, Site Furniture, etc. 20 20 Catch Basin 40 40 Cold Water Lines 40 40 Compactors DHW Supply
More informationAppendix B. Facilities Assessment Report
Mile Lane Army Reserve Center Redevelopment Plan September 2008 Appendix B Facilities Assessment Report RKG Associates, Inc. Mile Lane Army Reserve Base Middletown, CT MEP System Evaluation For RKG Associates
More informationCHAPTER 7 ALTERATIONS LEVEL
CHAPTER 7 ALTERATIONS LEVEL 2 SECTION 701 GENERAL 701.1 Scope. Level 2 alterations as described in Section 404 shall comply with the requirements of this chapter. Exception: Buildings in which the reconfiguration
More informationDMTF: Specific Building Recommendations
DMTF: Specific Building Recommendations Asset Name Project Title Total Cost BLOCKER BUILDING 22,503,303 Capital Renewal 7,640,013 DOMESTIC WATER HEATER REPLACEMENT 16,374 EXTERIOR DOOR REPLACEMENT 133,623
More informationSiemens Building Technology MEP Existing Conditions
Electrical Existing Conditions Report Executive Summary: The electrical systems for the are generally of the original vintage. The site is primary metered with the meter located in the main Electric Room.
More informationREAR. Exit 5'-9" 6'-1" 8'-3" 6'-1" Freezer Entrance Stall
North Bridges REAR 67' 8' 29' Unit # 120 10955 Jones Bridge Rd. Alpharetta, GA 30022 8' 6'-10" Freezer 7'-1" CONTINENTAL REALTY CORP. 1427 Clarkview Road Suite 500 Baltimore, MD 21209 12' 13'-3" 6' 11'-11"
More informationCustom Report // Priorities 1+2
Custom Report // Priorities + All costs are shown in 08 dollars. The cost of all work items after this date should be adjusted accordingly. Print Date: 4/3/08 Foothill High School DESCRIPTION Building
More informationRECAPP Facility Evaluation Report
RECAPP Facility Evaluation Report Canadian Rockies Reg Div #12 Exshaw School B3390A Exshaw Report run on: March 26, 2010 9:29 AM Building Name: Address: Location: Building Id: Gross Area (sq. m): Replacement
More informationTIFT COUNTY SCHOOLS E-SPLOST HISTORY
TIFT COUNTY SCHOOLS E-SPLOST HISTORY July 1, 1997 June 30, 2002 $28,766,187.16 collected July 1, 2002 June 30, 2007 $39,025,830.10 collected July 1, 2007 June 30, 2012 $41,886,155.46 collected July 1,
More informationRECAPP Facility Evaluation Report
RECAPP Facility Evaluation Report Calgary School District #19 John G Diefenbaker High School B2686A Calgary Report run on: January 1, 28 9:31 AM Building Name: Address: Location: Building Id: Gross Area
More informationParadise Marketplace. Unit # AOP +/- 1,600 SF +/- 12' +/- 11' +/- 8' 11'-7" +/- 85' +/- 74' +/- 20' MAIN FLOOR +/- 20' +/- 85' Width.
Electrical Information Breaker Panel 1: Service Type: Not Listed Panel Type: Not Listed Panel Number: Not Listed Manufacturer: Not Listed Amps: Not Listed Location: Rear of Storage Room Notes: Unlabeled
More informationKerrville ISD has called for a bond election in the amount of $88,960,000 for November 6, 2018
Kerrville ISD has called for a bond election in the amount of $88,960,000 for November 6, 2018 WHAT IS A BOND ELECTION? Provide communities an opportunity to vote to give the Board of Trustees authority
More informationElectrical Information
Electrical Information Breaker Panel 1: Service Type: Unreadable Panel Type: Unreadable Panel Number: Unreadable Manufacturer: Unreadable Amps: Unreadable Location: Storage Room Notes: Exterior Disconnect
More informationGreenwood Elementary School 5550 South Holly Street Greenwood Village, Colorado 80111
Greenwood Elementary School 5550 South Holly Street Greenwood Village, Colorado 80111 Year Opened 1958 Current Square Footage 50,504 Site Acreage 8.53 greenwood.cherrycreekschools.org $220,720 Electrical
More informationPLAN REVIEW SUBMITTAL GUIDE
PLAN REVIEW SUBMITTAL GUIDE Plans, specifications and other construction documentation for the initial plan review should be as complete as possible at the time of submittal. Use this convenient guide
More informationRECAPP Facility Evaluation Report
RECAPP Facility Evaluation Report Calgary School District #19 Sir William Van Horne High School B2852A Calgary Report run on: March 25, 2010 10:19 AM Building Name: Address: Location: Building Id: Gross
More information