1 RECAPP Facility Evaluation Report Wild Rose School Div #66 Pioneer School B3972A Rocky Mountain House Report run on: March 26, 213 9:48 AM

2 Building Name: Address: Location: Building Id: Gross Area (sq. m): Replacement : Construction : Facility Details Pioneer School Street Rocky Mountain House B3972A 4, $17,222, 1976 Evaluation Company: Bacz Engineering Ltd. Evaluation Date: September Evaluator Name: Evaluation Details Eric Lumley Total Maintenance Events Next 5 years: $813,2 5 year Facility Condition Index (FCI): 4.72% General Summary: The Pioneer School is a single-storey masonry block, split faced concrete block veneer and steel framed structure originally constructed in The building was destroyed by fire and was reopened after reconstruction in. Two of the portables on the original school were relocated and incorporated into the floor plan. The building has a total floor area of approximately 7292 square metres. Structural Summary: The school foundations consist of a cast-in-place concrete foundation walls with strip footings. There are pad footings and stub columns under the steel frame. All portions of the school have load-bearing masonry block walls and reinforced cast-in-place concrete floors. The roof structural frame for all sections of the school is a metal deck supported by open web steel joists and steel wide flange beams. Envelope Summary: Exterior finishes include split faced concrete block and pre-finished vertical metal siding. The roof is pre-finished metal standing seam. Entrance doors are typically pre-finished metal set in painted metal frames. Exterior windows are fixed and operable aluminum windows with double glazing. Interior Summary: The majority of the school has vinyl tile flooring. Some classrooms, the teachers staff room and the library have carpet flooring. Mechanical spaces and storage rooms have painted/sealed concrete floors. The majority of the interior walls consist of painted masonry block and painted gypsum board and steel framed walls. The majority of the building has either a suspended acoustic panel ceiling system or fireproofed exposed roof structure. Mechanical Summary: The school is heated by two hot water boilers. There are three glycol/water air handling units serving the school. Two air handling units are used to ventilate and heat the school, one is used to ventilate and heat the gymnasium. Heating system for the school consist of perimeter radiant panels, re-heat coils and force flow heaters. Each classroom have control of the temperature with individual thermostats. Cooling is provided by two outdoor condensing units complete with refrigerant piping to AHU's DX coils. Domestic hot water is generated by one gas fired boiler complete with storage tank and pumps. Conventional plumbing fixtures throughout the facility. Fire protection is provided in the form of wet sprinkler system, fire extinguishers and fire department connections. Control system is a Johnson Controls digital programmable BMCS. Overall mechanical system is in acceptable condition. Electrical Summary: The building has a 12 Amp, 347/6 volt service fed from site pad mounted transformer; the main distribution consists with main electrical switchboard with 6V distribution section, a 15 KVA secondary transformer and 12/28V CDP. There are three 45 KVA transformer located at varies locations to feed 12/28V panels. Interior lighting is combined with fluorescent and metal halide light fixtures. Exterior lighting is provided by metal halide wall packs around the building. Emergency lighting in the building is provided by battery pack emergency lighting fixtures. Exit lighting in the building is provided by LED. The fire alarm, telephone and security systems meet current school facility requirements. In general the overall condition of the electrical distribution and systems are "Good". Report run on: March 26, 213 9:48 AM Page 2 of 32

3 Guide Condition Performance 1 - Critical Unsafe, high risk of injury or critical system failure. 2 - Poor Does not meet requirements, has significant deficiencies. May have high operating/maintenance costs. 3 - Marginal Meets minimum requirements, has significant deficiencies. May have above average operating maintenance costs. Meets present requirements, minor deficiencies. Average operating/maintenance costs. Meets all present requirements. No deficiencies. 6 - Excellent As new/state of the art, meets present and foreseeable requirements. S1 STRUCTURAL A11 Standard Foundations* Concrete foundation walls and strip footings. Pad footing and stub columns under the steel frame. A13 Slab on Grade* Cast-in-place concrete slab-on-grade. B11.2 Structural Interior Walls Supporting Floors (or Roof)* Load-bearing masonry block walls and steel framed walls are provided throughout the building and support the roof structure. B11.5 Mezzanine Construction* Mezzanines, off the main entrance atrium, are constructed of concrete topping on metal decking on a steel frame. B12.1 Roof Structural Frame* The roof structural frame consists of metal decking supported by open web steel joists and steel columns and beams. B12.4 Canopies* There is a steel canopy with curved glazing over the main entrance way. Other entrances are recessed with the roof structure forming canopies. Report run on: March 26, 213 9:48 AM Page 3 of 32

4 S2 ENVELOPE B Concrete Block: Ext. Wall Skin* Split faced and smooth concrete block exterior veneer. B Metal Siding** There is a vertical pre-finished metal siding fascia around the perimeter of the building The upper walls and gymnasium have metal siding. 4 Replace metal siding with new metal siding. B.O.E. 915 sq.m. 235 $13, : B Expansion Control: Ext. Wall* Control joints are provided at periodic intervals within the masonry cladding system for expansion control. B Joint Sealers (caulking): Ext. Wall** Joint sealant is applied to control joints and on the perimeters of exterior window units and doors on all sides of the building. 2 Replace caulking with new caulking. B.O.E. 45m 216 $15, : B21.3 Exterior Wall Vapour Retarders, Air Barriers, and Insulation* It is assumed the concrete block inner wythe has a peel-and-stick air/vapour retarder in the cavity, with rigid or semi-rigid cavity insulation. Where there are steel studs and gypsum board finish to the interior of the exterior walls it is assumed there is a peel-and-stick air/vapour retarder on sheathing, and rigid or semi-rigid insulation in the cavity. Report run on: March 26, 213 9:48 AM Page 4 of 32

5 B21.6 Exterior Louvers, Grilles, and Screens* Pre-finished metal louvers located in the metal siding at the upper portion of the building's perimeter. B21.9 Exterior Soffits* Pre-finished perforated aluminum soffits are provided at recessed entrances. B Aluminum Windows (Glass & Frame)** Exterior windows on the building consists of fixed and operable, insulating glazing units set in pre-finished aluminum frames 4 Replace the exterior windows with new aluminum windows. B.O.E. 97 sq.m. 235 $122, : B Metal Entrance Door** Entrance door consist of insulated hollow metal doors in steel frames. Replace metal entrance doords with new metal doors. B.O.E. 2 doors 235 $53, : B31.1 Deck Vapour Retarder and Insulation* The roof deck is presumed to have a single ply air/vapour barrier and rigid insulation. Report run on: March 26, 213 9:48 AM Page 5 of 32

6 B31.7 Sheet Metal Roofing** The entire roof is standing seam metal roofing. 4 Replace metal roofing with new standing seam metal roofing. B.O.E. 415 sq.m. 235 $1,825, : B Metal Gutters and Downspouts** There are metal gutters and downspouts located at the canopy at the main entrance of the building. 3 Replace metal gutters and downspouts with new gutters and downspouts. B.O.E. 2m 225 $5 : Report run on: March 26, 213 9:48 AM Page 6 of 32

7 S3 INTERIOR C11.1 Interior Fixed Partitions* The majority of the schools interior walls are painted load-bearing masonry block walls. Interior walls between classrooms are steel-stud framed with gypsum board C11.3 Interior Operable Folding Panel Partitions** There are operable folding panel partitions located in the gymnasium and between classroom clusters. 3 Replace the operable folding partitions. B.O.E. 32 sq.m. 225 $24, : C11.4 Interior Balustrades and Screens, Interior Railings* There are painted metal railings to the perimeter of mezzanines and as stair railings. C11.5 Interior Windows* The interior windows are single glazed fixed units set in painted wood frames or aluminum frames. C12.1 Interior Swinging Doors (& Hardware)* The majority of interior swinging doors consist of metal doors and frames with inset glazing or glazing sidelights with single-paned wired glass. The administration doors are birch veneer solid core wood doors set in metal frames. C12.3 Interior Fire Doors* There are fire rated metal doors and metal frames in corridors, storage rooms and mechanical rooms. Report run on: March 26, 213 9:48 AM Page 7 of 32

8 C13.1 Visual Display Boards** Whiteboards and tackboards are provided in the classrooms throughout the school 2 Replace the whiteboards and tackboards. B.O.E. 115 units 216 $49, : C13.2 Fabricated Compartments (Toilets/Showers)** Pre-finished metal stall partitions are provided in each student washroom in the building. 3 Replace the washroom stalls. B.O.E. 1 cubicles 225 $17,3 : C13.1 Lockers** There are built-in metal lockers throughout the corridors. 3 Replace the lockers. B.O.E. 2 lockers Concern: 225 $19, : C13.12 Storage Shelving* There are fixed wood shelving units throughout the school. Report run on: March 26, 213 9:48 AM Page 8 of 32

9 C13.14 Toilet, Bath, and Laundry Accessories* Wall-mounted mirrors as well as soap and paper towel dispensers are provided in each washroom in the building. Toilet paper dispensers are also provided in each washroom stall. C21 Stair Construction* The stair construction throughout the school is concrete filled steel pan stairs on metal stringers. C22.5 Resilient Stair Finishes** Interior stairs have a sheet vinyl treads. 2 Replace the sheet vinyl stair treads. B.O.E. 216 $6,8 : C22.6 Carpet Stair Finishes** The stairs located in the library are carpeted. 1 Replace the carpet on the library stairs. B.O.E. 21 treads 216 $1,9 : C22.8 Stair Railings and Balustrades* All of the interior stairs have painted metal railings. Report run on: March 26, 213 9:48 AM Page 9 of 32

10 C31.6 Tile Wall Finishes** The change rooms are finished with ceramic wall tile. 4 Replace the tile wall. B.O.E. 17 sq.m. 235 $41, : C31.9 Acoustical Wall Treatment** There are wooden acoustic panels on the walls of the music room, and suspended acoustic ceiling baffles. 2 Replace the acoustic panels on the walls and ceiling. B.O.E. 125 sq.m. 216 $125, : C31.11 Interior Wall Painting* The majority of the interior walls throughout the school are painted. C Painted Concrete Floor Finishes* The floor in the mechanical room is painted. Report run on: March 26, 213 9:48 AM Page 1 of 32

11 C32.2 Tile Floor Finishes** The washrooms and the change rooms have tile floors. 5 Replace the tile floor finish. B.O.E. 177 sq.m. 245 $28,32 : C32.4 Wood Flooring** The gymnasium has a cushioned hardwood floor. 3 Replace the gymnasium wood flooring. B.O.E. 656 sq.m. 225 $186, : C32.7 Resilient Flooring** The classrooms and corridors have vinyl flooring. 2 Replace the vinyl flooring. B.O.E sq.m. 216 $362, : Report run on: March 26, 213 9:48 AM Page 11 of 32

12 C32.8 Carpet Flooring** The library and the main office area have carpet flooring. 15 Replace the carpet flooring. B.O.E. 3 sq.m. 216 $22,5 : C33.6 Acoustic Ceiling Treatment (Susp. T-Bar)** The majority of the school has acoustic ceiling tiles. 25 Replace the acoustic ceiling tiles. B.O.E sq.m. 22 $325, : C33.7 Interior Ceiling Painting* Storage areas, washrooms and change rooms have painted gypsum board ceilings. The gym, mechanical room and atrium have painted metal deck. Report run on: March 26, 213 9:48 AM Page 12 of 32

13 S4 MECHANICAL D21.4 Sinks** Single and double compartment stainless steel sinks located in administration areas and classrooms. Molded stone mop sinks in Janitor Rooms. Semi circular stainless steel wash fountain in IA area. 3 Replace 22 sinks. 225 $33, : D21.5 Showers** Built up showers serving gymnasium Change Rooms. 3 Replace 6 showers. 225 $18, : D21.8 Drinking Fountains/Coolers** Mixture of two-station stainless steel and vitreous china non-refrigerated drinking fountains located throughout the school. 35 Replace 6 drinking fountains. 23 $14, : Report run on: March 26, 213 9:48 AM Page 13 of 32

14 D21.1 Washroom Fixtures (WC, Lav, Urnl)** WC - floor mounted, vitreous china water closets, flush tank and flush valves. UR - wall-mounted, flush valve vitreous china urinals. LV - stainless steel lavatories in washrooms. 35 Replace 32 Washroom Fixtures 23 $48, : D Pipes and Tubes: Domestic Water* Domestic hot and cold water lines are copper throughout the school. D Valves: Domestic Water** Isolation valves in place on the domestic plumbing lines. 4 Replace 18 domestic water valves. 235 $36, : D Piping Specialties (Backflow Preventers)** Backflow prevention device on the water service in meter room. Check valve installed on glycol feed system. Vacuum breakers serving mop sinks and hose bibbs. 2 Replace 1 backflow preventors. 216 $14, : Report run on: March 26, 213 9:48 AM Page 14 of 32

15 D Plumbing Pumps: Domestic Water** Grundfoss domestic hot water recirculation pumps Replace 2 DHW reciculation pumps. 225 $5, : D Water Storage Tanks** Westeel 5 l domestic hot water storage tank. 3 Replace DHW storage tank. (1) 225 $5, : D Domestic Water Heaters** The domestic hot water in the school is provided be a Raypack E kw heating capacity, gas-fired boiler. 2 Replace domestic hot water boiler.(1) 216 $25, : D23.1 Waste and Vent Piping* Cast iron and PVC sanitary piping throughout the school. All fixtures are vented through the roof. Report run on: March 26, 213 9:48 AM Page 15 of 32

16 D24.1 Rain Water Drainage Piping Systems* Rain water drainage piping is generally cast iron inside the building. D31.2 Gas Supply Systems* The natural gas piping feeds the heating and domestic hot water boilers, and furnaces in the relocatable classroom. D Heating Boilers and Accessories: H.W.** The school has two Raypak E-25 boilers with an input capacity of 659 kw. The boilers are complete with low water cut off, flow switch, hot water expansion tank and chemical feeder. The heating water/glycol mixture is circulated through air separator to primary circulation pumps. Two in-line pumps circulate glycol/water mixture to AHU's heating coils. Each pump is complete with strainer and check valve. Bladder type expansion tank. 35 Replace boiler plant. (1) 23 $165, : Report run on: March 26, 213 9:48 AM Page 16 of 32

17 D Chimneys (& Comb. Air): H.W. Boiler** Insulated common vents up through the roof. Insulated combustion air duct. 3 - Marginal 35 Replace breeching and common vent serving boilers. BOE: 9m length. Concern: It was reported that when two boilers are operational a significant backdrafting occurs. Existing common breeching serving boilers appears to be undersized for the type of boilers installed and heating input of these units. Recommendation: It is recommended to replace boilers breeching and main stack with new adequate size vent. Repair 214 $1, Medium : Replace chimneys and combustion air duct. BOE: 16m combined length. 23 $16, : D Water Treatment: H. W. Boiler* Pot feeders are connected to the boilers, and a water treatment program is provided for the hot water system. D Refrigerant Condensing Units** Two York air-cooled condensing units with capacities of 21 kw and 36 kw serve the DX cooling in air handling units. 25 Replace 2 air-cooled condensing units. 22 $1, : Report run on: March 26, 213 9:48 AM Page 17 of 32

18 D Air Handling Units: Air Distribution** Three air handling units serve the ventilation in the school: AS1, Trane 4719 l/s, serves the gymnasium and is equipped with a glycol heating coil, supply fan and return fan. AS2, Haakon 14 l/s, consists of a DX cooling coil, steam humidifier, glycol heating coil, supply fan and return fan. AS3, Haakon 1515 l/s, consists of a DX cooling coil, steam humidifier, glycol heating coil supply fan, and return fan. 3 Replace 3 air handling units. 225 $275, : D Air Cleaning Devices: Air Distribution* Air handling units are complete with replaceable media air filters. D Ducts: Air Distribution* Galvanized steel supply and return air ducts are used throughout the school. Ductwork distribution via ceiling space or exposed in Gymnasium. All ducts up to SMACNA standards. D Air Outlets & Inlets: Air Distribution* T-Bar ceiling mounted diffusers and grilles are throughout the building to provide supply air. Report run on: March 26, 213 9:48 AM Page 18 of 32

19 D Hot Water Distribution Systems** Heating system distribution is served by four in-line circulation pumps serving primary and secondary loops. Pumps are manufactured by Armstrong and have capacities of 15.7 and 5.67 lps. Glycol heating distribution is through original insulated steel piping to heating coils, radiation panels, reheat coils and fan coil units in the building. 4 Replace hot water distribution system. BOE: 4363 sq.m. GFA. 235 $38, : D Fans: Exhaust** Roof-top exhaust fans, and their capacities range from 378 l/s to 1888 l/s. Exhaust fans serve Storage Rooms, Janitor Rooms, Industrial Arts and Washroom Exhausts. 3 Replace 8 exhaust fans. 225 $24, : D Fans: Exhaust** - Dust Collector Murphy dust collector serving I.A. Area Replace dust collector. (1) 216 $3, : D Ducts: Exhaust* Galvanized steel exhaust air ducts. Report run on: March 26, 213 9:48 AM Page 19 of 32

20 D Air Outlets and Inlets: Exhaust* Wall and ceiling mounted grilles serve as exhaust air inlets. D Fan Coil Units** 6 ceiling or wall-mounted fan coil units are provided at the entrances and stairwells of the building. 3 Replace 6 Fan Coil Units. 225 $3, : D35.2 Air Coils** Duct mounted reheat coils serving temperature controlled zones in the building. 3 Replace 15 reheat coils. 225 $25, : D35.3 Humidifiers** Steam humidifiers are installed in AS2 and AS3. The humidification system not used. 25 Replace 2 steam humidifiers in AHUs. 22 $3, : Report run on: March 26, 213 9:48 AM Page 2 of 32

21 D Finned Tube Radiation** Finned tube wall mounted radiation heaters are installed in the Student Gathering Area and corridors. 4 Replace 3 finned tube radiation heaters. 235 $45, : D Unit Heaters** Engineered Air H series cabinet unit heaters complete with hot water coils. 3 Replace 2 unit heaters 225 $1, : D Radiant Heating (Ceiling & Floor)** Radiant ceiling panels serving classrooms, 61mm width aluminum linear type, mounted in the T-bar, GWB ceiling or suspended. 35 Replace ceiling radiation panels. BOE: 4363 sq.m. 23 $26, : Report run on: March 26, 213 9:48 AM Page 21 of 32

22 D Building Systems Controls (BMCS, EMCS)** The mechanical equipment in the school is controlled by a pneumatic and DDC combined control system. Johnson Controls energy management program is provided. 2 Replace BMS. BOE: 4363 sq.m. 216 $11, : D41 Sprinklers: Fire Protection* The building is sprinkled as per NFPA13. Automatic sprinkler system consists of wet pipes. Automatic wet pipe sprinkler alarm valve. Fire department connection at the entrance, alarm provided. D43.1 Fire Extinguisher, Cabinets and Accessories* Fire extinguishers provided throughout:- carbon dioxide, multi-purpose dry chemical. All units complete with up-to-date certification tags. Report run on: March 26, 213 9:48 AM Page 22 of 32

23 S5 ELECTRICAL D Main Electrical Transformers (Utility Owned)* Pad mounted transformer is by utility company D51.2 Secondary Electrical Transformers (Interior)** A 347/6 volt to 12/28 volt 15 KVA Siemens transformer located in the mechanical room and three 45 KVA transformers located at various locations. 4 Replace Secondary Electrical Transformers. (1) 235 $39, : D51.3 Main Electrical Switchboards (Main Distribution)** The Siemens main distribution switchboard is 347/6 Volts, 3 Phase, 4 wire and rated 12A; the service is underground fed from site pad mounted transformer. 4 Replace main electrical switchboard. (1) 235 $45, : D51.5 Electrical Branch Circuit Panelboards (Secondary Distribution)** Branch panelboards are manufactured by Siemens and Westinghouse. Both 12/28V and 347/6V panels panelboards have spare capacity for future usage. 3 Replace 15 eletrical branch panelboards 225 $75, : Report run on: March 26, 213 9:48 AM Page 23 of 32

24 D Switchboards, Panelboards, and (Motor) Control Centers** A Siemens 12/28V 6 amp motor control center is provided in the mechanical room. It serves air handling units, pumps, and compressors in the school. 3 Replace Motor Control Center. (1) 225 $25, : D Motor Starters and Accessories** Stand alone Motor starters are used for mechanical pumps and exhaust fans in the school. 3 Replace 1 motor starters 225 $6, : D52.1 Electrical Branch Wiring* The electrical wiring in the building is standard copper wire in conduit. The BX wires, flexible conduits and cabling are used for all the mechanical equipment. D Lighting Accessories: Interior (Lighting Controls)* The low voltage switching is used for gym and common lighting control. The line voltage switching provides locally lighting controls. Report run on: March 26, 213 9:48 AM Page 24 of 32

25 D Interior Fluorescent Fixtures** Fluorescent fixtures were retrofit with T-8 lamps and electronic ballasts. Most of fixture are lay-in t-bar recessed and surface mounted fluorescent. 3 Replace 45 Fluorescent Fixtures 225 $18, : D Interior Metal Halide Fixtures* Metal halide fixtures are provided in the gymnasium and open common areas. D Emergency Lighting Battery Packs** The battery packs are original installed with building and the tests have been carried out annually; the batteries have been replaced as per lifecycle requirements. 2 Replace 35 Emergency Lighting Battery Packs 216 $42, : D Exit Signs* LED type Exit signs are provided throughout the building. MAR-8 D Exterior Metal Halide Fixtures* Exterior lighting around the building is provided by wall-mounted and pole mounted metal halide fixtures. Report run on: March 26, 213 9:48 AM Page 25 of 32

26 D Lighting Accessories: Exterior (Lighting Controls)* Exterior lighting is controlled by photo-cell and timer D53.1 Detection and Fire Alarm** The hardwired Simplex 462 fire alarm panel is used for facility fire alarm detection system. 25 Replace Detection and Fire Alarm System. (1) 22 $12, : D Intrusion Detection** The Regency security system is used for intrusion detection system has motion sensors located in corridors and public areas and door contactors at all the exterior doors. 25 Replace Intrusion Detection System. (1) Concern: Estimate based on the replacement of the security panel and 3 motion sensors. 22 $6, : D Video Surveillance** The DIGI Merge system is used for CCTV system and has cameras located throughout the interior of school Replace CCTV system. (1) 236 $2, : Report run on: March 26, 213 9:48 AM Page 26 of 32

27 D53.3 Clock and Program Systems* The Edwards Clock system is no long in use; the Battery powered clocks are installed throughout the school. D Telephone Systems* The Panasonic KX-TD2 telephone machine is used for telephone system and it interconnects to Bogen to provide facility paging functions. The telephone sets are installed through entire school offices and classrooms. 211 D Local Area Network Systems* 3COM network switch system is installed in communication room complete with Category 6 cable. 25 MAR-8 D53.5 Public Address and Music Systems** With inter-connected with Telephone system, the Bogen TPU 25 unit provides PA system for entire school facility Replace Public Address and Music Systems. (1) 231 $8, : D53.7 Other Communications and Security Systems* The Supernet is used for connecting school data system to local school board. 25 Report run on: March 26, 213 9:48 AM Page 27 of 32

28 D59.1 Uninterruptible Power Supply Systems** The stand alone UPS units are used for school server computers Replace Three Uninterruptible Power Supply Units 235 $3,6 : Report run on: March 26, 213 9:48 AM Page 28 of 32

29 E19.4 Residential Equipment* S6 EQUIPMENT, FURNISHINGS AND SPECIAL CONSTRUCTION Residential-style appliances are provided in the staff room with appliances generally include a refrigerator, stove, oven, microwave and dishwasher. E19.7 Athletic, Recreational, and Therapeutic Equipment* 4 sideswing and 4 motorized upswing basketball backstops and a scoreboard are mounted to the walls of the gymnasium. E21.2 Fixed Casework** There is fixed casework throughout the school. 35 Replace the fixed casework. B.O.E. 415 m Recommendation: We have allowed for 32 room units at $1, per room. 23 $36, : E Blinds** Manually-operated, horizontal aluminum blinds are provided on the majority of exterior and interior window units (approximately 4) throughout the building. 3 Replace the horizontal blinds. B.O.E.4 units 225 $9,6 : Report run on: March 26, 213 9:48 AM Page 29 of 32

30 F Grandstands and Bleachers** There are wood faced steel framed bleachers located in the gymnasium. They are estimated to have capacity for approximately 5 people. 3 Replace the bleachers. B.O.E. 5 seats 235 $13, : Report run on: March 26, 213 9:48 AM Page 3 of 32

31 S8 SPECIAL ASSESSMENT K41.2 Barrier Free Entrances* The main entrance doors have automatic door openers. K41.3 Barrier Free Interior Circulation* The main floor is accessible. None of the mezzanines are wheelchair accessible. K41.4 Barrier Free Washrooms* There is one barrier-free washroom located in the 1 wing area of the building. K43.1 Asbestos* There was no noted asbestos and none reported K43.4 Mould* There was no mould observed and none reported. K43.9 Other Hazardous Materials* There were no hazardous materials observed and none were reported. Report run on: March 26, 213 9:48 AM Page 31 of 32

32 K51.1 Site Documentation* Prime Consultant: Bacz Engineering Ltd. of Evaluation: 212 Building Area Evaluated: 4363 m2 212 Site Plan K51.2 Building Documentation* The Pioneer School is a single-storey masonry block, split faced concrete block veneer and steel framed structure originally constructed in The building was destroyed by fire and was reopened after reconstruction in. 212 Main Floor Plan Report run on: March 26, 213 9:48 AM Page 32 of 32

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Edmonton RCSSD #7 Bishop Savaryn Catholic Elementary School B58A Edmonton Report run on: July 10, 2008 3:31 PM Building Name: Address: Location: Building Id: Gross Area

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Alberta Health Services-Edmonton Glenrose Energy Centre B25I Edmonton Report run on: February 15, 213 1:9 AM Building Name: Address: Location: Building Id: Gross Area

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Calgary RCSSD #1 Ecole St. Matthew Elementary / French Immersion Jr. High School B2614A Calgary Report run on: March 25, 2010 10:11 AM Building Name: Address: Location:

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Edmonton RCSSD #7 Our Lady Of The Prairies Catholic Elementary School B3241A Edmonton Report run on: July 17, 2008 4:00 PM Building Name: Address: Location: Building Id:

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Edmonton RCSSD #7 Bishop Savaryn Catholic Elementary School B358A Edmonton Report run on: March 11, 213 5:9 PM Building Name: Address: Location: Building Id: Gross Area

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Calgary School District #19 John G Diefenbaker High School B2686A Calgary Report run on: January 1, 28 9:31 AM Building Name: Address: Location: Building Id: Gross Area

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Edmonton School District No. 7 Clara Tyner Elementary School B375A Edmonton Report run on: March 16, 212 2:11 PM Building Name: Address: Location: Building Id: Gross Area

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Edmonton School District No. 7 Stratford Academic High School B3336A Edmonton Report run on: April 3, 29 1:6 AM Building Name: Address: Location: Building Id: Gross Area

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Edmonton RCSSD #7 Blessed Kateri School B36A Edmonton Report run on: April 3, 29 1:1 AM Building Name: Address: Location: Building Id: Gross Area (sq. m): Replacement

More information

MUKWONAGO AREA SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY

MUKWONAGO AREA SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY ARCHITECTURE ROLLING HILLS ELEMENTARY SCHOOL Rolling Hills Elementary was built in 1999 and is the newest addition to the Mukwonago Area School District. The building contains approximately 64,900 gross

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Edmonton RCSSD #7 Cardinal Leger Catholic Junior High School B371A Edmonton Report run on: April 3, 29 1:1 AM Building Name: Address: Location: Building Id: Gross Area

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Edmonton RCSSD #7 Sir John Thompson Catholic Junior High School B3275A Edmonton Report run on: March 5, 29 1:43 AM Building Name: Address: Location: Building Id: Gross

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Alberta Health Services-Central Breton Health Centre B999A Breton Report run on: March 7, 214 11:1 AM Building Name: Address: Location: Building Id: Gross Area (sq. m):

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Canadian Rockies Reg Div #12 Exshaw School B3390A Exshaw Report run on: March 26, 2010 9:29 AM Building Name: Address: Location: Building Id: Gross Area (sq. m): Replacement

More information

Facility Condition Assessment Summary Report. British Columbia Institute of Technology NE6 - Plumbing and Pipefit Building

Facility Condition Assessment Summary Report. British Columbia Institute of Technology NE6 - Plumbing and Pipefit Building Facility Condition Assessment Summary Report British Columbia Institute of Technology NE6 - Plumbing and Pipefit Building Submitted by: VFA Canada Corp. Burnaby Centre 4211 Kingsway Burnaby, BC V5H 1Z6

More information

2 Main Office Building BLDG-955A Building Purpose Building Area Administration offices. Training room 7,610 SF Inspection Date August 16, 2016 Inspect

2 Main Office Building BLDG-955A Building Purpose Building Area Administration offices. Training room 7,610 SF Inspection Date August 16, 2016 Inspect 1 Site Summary Address 7200 Bluff Springs Road Austin, TX 78744 Number of Permanent Campus Facilities 2 Original Year of Construction 2014 Total Campus Building Area (combined) 25,314 SF Introduction The

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Lakeland Roman Catholic Separate School District No. 1 Ecole Notre Dame High School B266A Bonnyville Report run on: January 26, 2 : PM Bonnyville - Ecole Notre Dame High

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Edmonton School District No. 7 Harry Ainlay Composite High School B3145A Edmonton Report run on: March 2, 27 3:27 PM Building Name: Address: Location: Building Id: Gross

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Parkland School Division #7 Meridian Heights School B9397A Stony Plain Report run on: January 22, 27 2:45 PM Building Name: Address: Location: Building Id: Gross Area

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Prairie Land Regional Div #25 Berry Creek Community School B2933A Cessford Report run on: March 21, 213 9:46 AM Building Name: Address: Location: Building Id: Gross Area

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Evergreen Catholic Separate Regional Division #2 St. Mary School B4244A Westlock Report run on: January 22, 27 2:4 PM Building Name: Address: Location: Building Id: Gross

More information

MUKWONAGO SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY

MUKWONAGO SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY MUKWONAGO SCHOOL DISTRICT ARCHITECTURE PARK VIEW MIDDLE SCHOOL The original school building was dedicated in 1954 as the High School, with an addition in 1959, a library addition in 1970, and an addition/renovation

More information

DOCUMENT TABLE OF CONTENTS

DOCUMENT TABLE OF CONTENTS DOCUMENT 00003 June 16, 2005 TABLE OF CONTENTS DOCUMENT NO. INTRODUCTORY INFORMATION DOCUMENT 00003 TABLE OF CONTENTS DIVISION 1 GENERAL REQUIREMENTS SECTION 01011 SECTION 01025 SSP21.1-1 SECTION 01026

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Edmonton School District No. 7 Coronation Elementary School B381A Edmonton Report run on: January 22, 27 11:33 AM Building Name: Address: Location: Building Id: Gross

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Calgary School District #19 Queen Elizabeth Junior / Senior High School B2745A Calgary Report run on: March, 2010 10:02 AM Building Name: Address: Location: Building Id:

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report East Central Health Viking Community Health Services B1178A Viking Report run on: March 22, 21 9:58 AM Building Name: Address: Location: Building Id: Gross Area (sq. m):

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Calgary School District #19 Sir William Van Horne High School B2852A Calgary Report run on: March 25, 2010 10:19 AM Building Name: Address: Location: Building Id: Gross

More information

Genevieve Melody Elementary School

Genevieve Melody Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Alberta Health Services-Edmonton Strathcona County Health Centre B1421A Sherwood Park Report run on: March 18, 214 1:22 PM Building Name: Address: Location: Building Id:

More information

Calmeca Academy of Fine Arts and Dual Language

Calmeca Academy of Fine Arts and Dual Language Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report E Central Francophone Ed Reg# Ecole Du Sommet School B89A St. Paul Report run on: January 26, 2 :28 PM St. Paul - Ecole Du Sommet School (B89A) Facility Details Building

More information

Agustin Lara Elementary Academy

Agustin Lara Elementary Academy Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Parkland School Division #7 Duffield School B938A Duffield Report run on: May 11, 26 4:38 PM Duffield - Duffield School (B938A) Facility Details Building Name: Duffield

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Alberta Health Services-Edmonton Capital Care - Norwood - North Pavilion B25A Edmonton Report run on: March 12, 214 12:41 PM Building Name: Address: Location: Building

More information

VOTER BOND REFERENDUM 2018 SUMMARY OF WORK PROPOSED

VOTER BOND REFERENDUM 2018 SUMMARY OF WORK PROPOSED Ashton Elementary School 1 Masonry Repair $ 42,781.50 2 Replace HVAC $ 375,000.00 3 Replace SAT @ Various Locations $ 92,364.00 3 Recoat & Resurface Exterior Paved Play Area $ 135,978.30 3 Various Technological

More information

SPACE TYPE: JUDICIAL CHAMBER

SPACE TYPE: JUDICIAL CHAMBER SPACE TYPE: JUDICIAL CHAMBER Construction Criteria The unit costs for Judicial Chamber space types are based on the construction quality and design features in the following table. This information has

More information

PLATTEVILLE MIDDLE SCHOOL

PLATTEVILLE MIDDLE SCHOOL Architectural The building has aluminum clad wood awning windows in combination with aluminum fixed glass units. They appear to be exterior glazed with insulated glazing. See photo 2. Platteville Middle

More information

State College Area School District High School South Building EXISTING CONDITIONS ASSESSMENT

State College Area School District High School South Building EXISTING CONDITIONS ASSESSMENT State College Area School District High School South Building Prepared by CenterPoint Engineering 08 February 2013 FACILITY ASSESSMENT SUMMARY PHYSICAL PLANT General HVAC This report is a snapshot of the

More information

Joseph Brennemann Elementary School

Joseph Brennemann Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Richard Henry Lee Elementary School

Richard Henry Lee Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Greater St. Albert Catholic Regional Division No. 29 Vincent J. Maloney School B484A St. Albert Report run on: June 16, 26 2:24 PM St. Albert - Vincent J. Maloney School

More information

John Palmer Elementary School

John Palmer Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

State College Area School District High School North Building EXISTING CONDITIONS ASSESSMENT

State College Area School District High School North Building EXISTING CONDITIONS ASSESSMENT State College Area School District High School North Building Prepared by CenterPoint Engineering 08 February 2013 FACILITY ASSESSMENT SUMMARY PHYSICAL PLANT General HVAC This report is a snapshot of the

More information

RECAPP Facility Evaluation Report

RECAPP Facility Evaluation Report RECAPP Facility Evaluation Report Graminia School B451A Spruce Grove Report run on: January 3, 26 1:36 PM Facility Details Building Name: Graminia School Address: 5111 R. R. 271 Location: Spruce Grove

More information

Josefa Ortiz De Dominguez Elementary School

Josefa Ortiz De Dominguez Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Oscar DePriest Elementary School

Oscar DePriest Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Alessandro Volta Elementary School

Alessandro Volta Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Charles W Earle Elementary School

Charles W Earle Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Edward Jenner Elementary Academy of the Arts

Edward Jenner Elementary Academy of the Arts Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

3. 21st Century Learning A. Districtwide Flexible Learning - Allowance for Flexible Furniture $600,000 Subtotal $600,000

3. 21st Century Learning A. Districtwide Flexible Learning - Allowance for Flexible Furniture $600,000 Subtotal $600,000 1. Safety and Security A. Additional Cameras District Wide $382,000 B. Interior Locks Upgrades Allowance $300,000 C. Tilden Entrance Upgrades D. Door and Glass Improvements Allowance $500,000 E. Alert

More information

HOLUM EDUCATION CENTER. Architectural. January 13, 2014 DeForest Area School District

HOLUM EDUCATION CENTER. Architectural. January 13, 2014 DeForest Area School District HOLUM EDUCATION CENTER Architectural The existing building has approximately 41,823 square feet and sets on a lot about 4.14 acres in size. Parking lots are located along the east and west sides of the

More information

Tighe&Bond. Groton Heights School Mechanical Evaluation. 1 Existing Conditions. 1.1 Water Service Entrance

Tighe&Bond. Groton Heights School Mechanical Evaluation. 1 Existing Conditions. 1.1 Water Service Entrance Groton Heights School Mechanical Evaluation TO: FROM: Amy Vaillancourt, Project Manager Harley Langford, Project Manger Jason Curtis, P.E. DATE: February 24, 2016; Revised May 31, 2016 On Monday, December

More information

Francis M McKay Elementary School

Francis M McKay Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

MOUNT PLEASANT MIDDLE SCHOOL HVAC. M-01 Heating Plant: M-02 Heating & Ventilating Systems: Livingston School District Mount Pleasant Middle School

MOUNT PLEASANT MIDDLE SCHOOL HVAC. M-01 Heating Plant: M-02 Heating & Ventilating Systems: Livingston School District Mount Pleasant Middle School MOUNT PLEASANT MIDDLE SCHOOL HVAC M-01 Heating Plant: The existing boilers have recently been upgraded. (3) steam boilers (8660 mbh each) manufactured by Weil- McLain have been installed. Newer hot water

More information

Appendix B. Facilities Assessment Report

Appendix B. Facilities Assessment Report Mile Lane Army Reserve Center Redevelopment Plan September 2008 Appendix B Facilities Assessment Report RKG Associates, Inc. Mile Lane Army Reserve Base Middletown, CT MEP System Evaluation For RKG Associates

More information

Springpoint Architects, pc SECTION Childcare Center Architect s Project No TABLE OF CONTENTS Monroe County Comm. Sch. Corp.

Springpoint Architects, pc SECTION Childcare Center Architect s Project No TABLE OF CONTENTS Monroe County Comm. Sch. Corp. Volume 1 Bidding Requirements, Contract Forms, Conditions of the Contract, Division 1, Architectural and Site Specifications 000107 Certification Page 000110 Table of Contents DIV00 PROCUREMENT AND CONTRACTING

More information

Florence High School / Middle School Page 1 of 3 Florence, WI

Florence High School / Middle School Page 1 of 3 Florence, WI Florence High School / Middle School Page 1 of 3 Florence, WI Plumbing Systems Review: The following report is the result of a site visit by Tim Kehoe of Muermann Engineering, LLC that occurred on October

More information

Washington Irving Elementary School

Washington Irving Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

SPACE TYPE: CHILD CARE

SPACE TYPE: CHILD CARE SPACE TYPE: CHILD CARE Construction Criteria The unit costs for Child Care Center space types are based on the construction quality and design features in the following table. This information has been

More information

George B Swift Elementary Specialty School

George B Swift Elementary Specialty School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

SITE SYSTEMS: FANNIE MAE EXPECTED USEFUL LIFE TABLES (FMEUL)

SITE SYSTEMS: FANNIE MAE EXPECTED USEFUL LIFE TABLES (FMEUL) SITE SYSTEMS: FANNIE MAE EXPECTED USEFUL LIFE TABLES (FMEUL) Basketball Courts 15 25 Built Improvements Playgrounds, Site Furniture, etc. 20 20 Catch Basin 40 40 Cold Water Lines 40 40 Compactors DHW Supply

More information

Sidney Sawyer Elementary School

Sidney Sawyer Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Vanilla Box Design Criteria

Vanilla Box Design Criteria Description: 1. Floor: 2. Walls: 3. Ceiling: A. Finished and sealed 4 thick concrete slab on 10 mil poly vapor barrier on 4 of crushed stone throughout, including toilets. A. Interior gypsum board walls

More information

Mechanical Inspection Plumbing

Mechanical Inspection Plumbing 0811 Fixtures Sinks, drinking fountains, water closets, showers, etc. Classroom Sinks. Classroom sinks (19) are enameled cast iron self rimming side ledge with gooseneck faucet trim with index handles,

More information

DeWitt Clinton Elementary School

DeWitt Clinton Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

DESIGNER KITCHEN WITH PREMIUM APPLIANCES 1407 & 1409 Military Trail Features & Finishes 1. Open concept kitchen with NEFF designer cabinetry and Caesa

DESIGNER KITCHEN WITH PREMIUM APPLIANCES 1407 & 1409 Military Trail Features & Finishes 1. Open concept kitchen with NEFF designer cabinetry and Caesa DESIGNER KITCHEN WITH PREMIUM APPLIANCES 1407 & 1409 Military Trail Features & Finishes 1. Open concept kitchen with NEFF designer cabinetry and Caesarstone countertop. 2. 4 x 16 ceramic tile backsplash.

More information

MARY CRAPO CENTER Miller Road, Swartz Creek, Michigan

MARY CRAPO CENTER Miller Road, Swartz Creek, Michigan MARY CRAPO CENTER 8197 Miller Road, Swartz Creek, Michigan MARY CRAPO CENTER 8197 Miller Road, Swartz Creek General Information: - Instructional, Child Care Development Center (West Wing) o (2) Infant/Toddler

More information

Library stacks and records storage 150 LB/SF live load

Library stacks and records storage 150 LB/SF live load SPACE TYPE: LIBRARY Construction Criteria The unit costs for Library space types are based on the construction quality and design features in the following table. This information has been generally organized

More information

Axiom Property Inspections

Axiom Property Inspections Cover Page Axiom Property Inspections Property Inspection Report 868 Wally Avenue, Henderson NV, 89178 Inspection prepared for: John Doe Agent: David Lawson - Axiom Inspection Date: 8/12/2010 Time: 2:30

More information

Residential Construction and Remodeling Estimates. compliments of. pillartopost.com

Residential Construction and Remodeling Estimates. compliments of. pillartopost.com Residential Construction and Remodeling Estimates compliments of STRUCTURE/EXTERIOR Structure > addition (foundation to roof) $95 $130/sq.ft. > basement entrance $5250 $10500 > basement main beam $2100

More information

Design Standards Manual

Design Standards Manual Design Standards Manual Table of Contents: Part III (Divisions 1-32) Section No. Title Revision DIVISION 1: GENERAL REQUIREMENTS 01524 Construction Waste Management 05/07 01815 HVAC Commissioning Requirements

More information

PLAN REVIEW SUBMITTAL GUIDE

PLAN REVIEW SUBMITTAL GUIDE PLAN REVIEW SUBMITTAL GUIDE Plans, specifications and other construction documentation for the initial plan review should be as complete as possible at the time of submittal. Use this convenient guide

More information

Unit HH Gregg. ± 30,000 SF Width ±26' Lakeland Retail Center. Lease Outline Drawing. Unit HH Gregg. Depth ± 145' HVAC Units & Information

Unit HH Gregg. ± 30,000 SF Width ±26' Lakeland Retail Center. Lease Outline Drawing. Unit HH Gregg. Depth ± 145' HVAC Units & Information Lease Outline Drawing Lakeland Retail Center 4000 US Hwy. 98, Unit HH Gregg, Lakeland, FL 33809 ±26' ±200' Lease Line Unit HH Gregg ±46' Lease Line ±21' Unit HH Gregg ±145' Lease Line ± 30,000 SF Width

More information

ELECTRICAL SYSTEMS ASSESSMENT Hanover High School

ELECTRICAL SYSTEMS ASSESSMENT Hanover High School ELECTRICAL SYSTEMS ASSESSMENT Hanover High School ELECTRICAL DISTRIBUTION SYSTEM:?? The existing electrical service consists of an underground primary service originating at a utility pole on Cedar Street,

More information

2014 Bond Project Guide

2014 Bond Project Guide 2014 Bond Project Guide Bush Elementary School Page 1 Instructional Technology Computers, Projectors, Mobile Carts, Document Cameras and Printers Wireless Connectivity New Construction New Tech Center

More information

GARCIA GALUSKA DESOUSA Consulting Engineers

GARCIA GALUSKA DESOUSA Consulting Engineers L#58619/Page 1/November 1, 2017 PLUMBING Executive Summary: Presently, the Plumbing Systems serving the building are cold water, hot water, sanitary, waste and vent system, storm drain piping, and natural

More information

Estimated Repair, Replacement, and Upgrade Costs

Estimated Repair, Replacement, and Upgrade Costs Description Electrical Attic ventilator-mechanical $250 Baseboard heater (4') $150-$400 Ceiling fan $200 Doorbell system $80-$100 Dryer duct $100-$150 Hardwired smoke detector $60-$120 Exhaust Fan-Bathroom

More information

Inspecta-Homes 2469 University Avenue West St. Paul MN Ph#: (651)

Inspecta-Homes 2469 University Avenue West St. Paul MN Ph#: (651) Page 1 Doc #: Inspector: Date: Dwelling Address: Client Name: Client's Agent: Real Estate Company: Please refer to the General Home Inspection Contract. Thank you for using Minnesota and Western Wisconsin's

More information

Unit # 1038 ± 900 SF Width ± 15' Depth ± 60'

Unit # 1038 ± 900 SF Width ± 15' Depth ± 60' ±60' Lease Line Lease Outline Drawing Needles Towne Center 1004 E. Broadway St.,, Needles, CA 92363 ± 900 SF Width ± 15' Depth ± 60' Plans produced by: ID Plans 6/16/2017 (813) 657-2545 C 2017 Site map

More information

Dates of Construction Construction Start 2/28/1999 Date of Completion 4/2000 Occupancy 5/2000

Dates of Construction Construction Start 2/28/1999 Date of Completion 4/2000 Occupancy 5/2000 Executive Summary The Milton S. Hershey Medical Center Academic Support Building is located on The Pennsylvania State University's campus in Hershey, PA. The building is owned by The Pennsylvania State

More information

TABLE OF CONTENTS. Part I Administrative... 1

TABLE OF CONTENTS. Part I Administrative... 1 Part I Administrative............................ 1 CHAPTER 1 ADMINISTRATION............... 1 R101 Title, Scope and Purpose.................... 1 R102 Applicability.............................. 1 R103

More information

AFFORDABLE CANADIAN HOME INSPECTIONS

AFFORDABLE CANADIAN HOME INSPECTIONS AFFORDABLE CANADIAN HOME INSPECTIONS Al Wright Hamilton, Ontario Cell: 905-730-9300 Expectancy of Household Components Appliances Compactors 7-12 Dishwashers 9-16 Disposal, Food Waste 11-16 Dryers 11-16

More information

AVS. Asset Assessment Report. Cold Lake Health Centre B1012A

AVS. Asset Assessment Report. Cold Lake Health Centre B1012A AVS Asset Assessment Report Cold Lake Health Centre B1012A Page 1 of 117 Asset ID Asset Name Location Address B1012A Cold Lake Health Centre Cold Lake 314-25 Street Verification Audit Maintenance Costs

More information

Cook - Wissahickon Elementary School

Cook - Wissahickon Elementary School Cook - Wissahickon Elementary School 201 E. Salaignac St., Philadelphia, PA 19128 HVAC Replacement Project Scope Determination Report May 10, 2018 Prepared by: G.P. Lamina, Jr., P.E., MBA School District

More information

DRAFT. Widen Elementary School Site Summary 74,523 SF. Introduction

DRAFT. Widen Elementary School Site Summary 74,523 SF. Introduction 1 Widen Elementary School Site Summary Address 5605 Nuckols Crossing Austin, TX 78744 Number of Permanent Campus Facilities 2 Original Year of Construction 1986 Total Campus Building Area (combined) 74,523

More information

Unit # E ± 1,200 SF Width ± 20' Depth ± 60'

Unit # E ± 1,200 SF Width ± 20' Depth ± 60' Lease Outline Drawing ±60' Lease Line Sunnymead Plaza 24907 Sunnymead Blvd., Unit # E, Moreno Valley, CA 92553 Unit # E ± 1,200 SF Width ± 20' Depth ± 60' Plans produced by: ID Plans 6/13/2017 (813) 657-2545

More information

Unit # H ± 2,000 SF Width ± 25' Depth ± 80'

Unit # H ± 2,000 SF Width ± 25' Depth ± 80' ±80' Lease Line Lease Outline Drawing Sunnymead Plaza 24907 Sunnymead Blvd., Unit # H, Moreno Valley, CA 92553 Unit # H ± 2,000 SF Width ± 25' Depth ± 80' Unit # H Plans produced by: ID Plans 6/13/2017

More information

S AGE E NGINEERING A SSOCIATES, LLP

S AGE E NGINEERING A SSOCIATES, LLP S AGE E NGINEERING A SSOCIATES, LLP 1211 Western Avenue Albany, NY (518) 453 6091 F (518) 453 6092 Kingston Library Mechanical and Electrical Systems Field Report Date of Visits: Mechanical - September

More information

Ashland School District Facility & Capacity Assessment Report 2005

Ashland School District Facility & Capacity Assessment Report 2005 Ashland School District Facility & Capacity Assessment Report 2005 Briscoe Elementary School (Closed Facility) Address: 265 N Main Street Area: 33,980 square feet Buildings: Original Building 1948 Music

More information

Nebraska Department of Correctional Services

Nebraska Department of Correctional Services Nebraska Department of Correctional Services Feasibility Study for the former Lancaster County Jail Facility Lincoln Air Park 4420 NW 41 st Street Lincoln, NE September 29, 2015 TABLE OF CONTENTS I. Introduction

More information

Appendix E: Photo Documentation

Appendix E: Photo Documentation Appendix E: Photo Documentation Brown County Library Central Branch Building Assessment Appendix E: Photo Documentation Architectural and Structural Brown County Library Central Branch Building Assessment

More information

The following report was prepared for the buyers of the home and property at 1400 Main St. Anywhere City, Tennessee. The inspection was conducted on

The following report was prepared for the buyers of the home and property at 1400 Main St. Anywhere City, Tennessee. The inspection was conducted on HOME PROPERTY SCAN INSPECTIONS The following report was prepared for the buyers of the home and property at 1400 Main St. Anywhere City, Tennessee. The inspection was conducted on January 11, 2010 and

More information

Massachusetts School Building Authority

Massachusetts School Building Authority Massachusetts School Building Authority School District Revere District Contact Paul Dakin TEL: (781) 286-8226 Name of School Submission Date 3/6/2007 The following Priorities have been included in the

More information

Camden. Included Features. Prices are non-negotiable. Continued on Back ATTRACTIVE INTERIORS:

Camden. Included Features. Prices are non-negotiable. Continued on Back ATTRACTIVE INTERIORS: Camden Included Features ATTRACTIVE INTERIORS: Satin Nickel Door Hardware Shed Resistant, Continuous Filament Carpet with Stainguard 1/2 -Inch, 6-Pound Nominal Carpet Pad Crown Molding in 1st Story Entry,

More information

Siemens Building Technology MEP Existing Conditions

Siemens Building Technology MEP Existing Conditions Electrical Existing Conditions Report Executive Summary: The electrical systems for the are generally of the original vintage. The site is primary metered with the meter located in the main Electric Room.

More information

Electrical Information

Electrical Information Electrical Information Breaker Panel 1: Service Type: Unreadable Panel Type: Unreadable Panel Number: Unreadable Manufacturer: Unreadable Amps: Unreadable Location: Storage Room Notes: Exterior Disconnect

More information

Existing Conditions Assessment November 14, 2006 NORTH MIDDLESEX REGIONAL HIGH SCHOOL Townsend, MA L21366/ /Page 1

Existing Conditions Assessment November 14, 2006 NORTH MIDDLESEX REGIONAL HIGH SCHOOL Townsend, MA L21366/ /Page 1 L21366/101 090 00.00/Page 1 HVAC EXECUTIVE SUMMARY The North Middlesex Regional High School has received average maintenance of the HVAC systems over its occupied years. Even with adequate maintenance,

More information

REPAIR ESTIMATE GUIDE

REPAIR ESTIMATE GUIDE REPAIR ESTIMATE GUIDE STRUCTURE Foundation Addition (foundation to roof)... $125 - $170/sq.ft. Basement entrance... $6485 - $13690 Basement main beam... $2740 Basement support post/foundation... $650 -

More information

SCHEDULE OF FEES. Penalty Fees. Building Fee Schedule FEE

SCHEDULE OF FEES. Penalty Fees. Building Fee Schedule FEE SCHEDULE OF S Penalty Fees. The fee for construction work performed before securing permit(s), where required, may be charged a fee of TWO TIMES THE COST OF THE PERMIT (S). Building Fee Schedule Residential

More information

Inspection Report. 1 Inspection Way Orlando, FL Prepared for: Wanda Figueroa Prepared by: ACF Home Inspections Inc

Inspection Report. 1 Inspection Way Orlando, FL Prepared for: Wanda Figueroa Prepared by: ACF Home Inspections Inc Inspection Report 1 Inspection Way Orlando, FL 32825 Prepared for: Wanda Figueroa Prepared by: Page 1 of 25 Needs Service Summary This summary is not the entire report. The complete report may include

More information