1 SONORAN PARKWAY BACKGROUND City of Phoenix Street Transportation Department Important east-west alignment for congested northeast Phoenix Alignment on Street Classification map since 1987 Originally shown as two parallel arterial alignments, reduced to one in 2002 to reduce impact on Sonoran Preserve Design Concept Report completed 2004, designed as scenic corridor similar to Galvin Parkway CITIZEN COMMITTEE BACKGROUND Recognition that the east end of the Sonoran Parkway serves populated areas (Tatum Ranch, Dove Valley, Desert Ridge, Tatum Highlands, etc.) Community requested further input and more detailed study relative to the eastern connection of the corridor 12 citizens appointed by Phoenix City Councilwoman Peggy Neely, with City staff and consultants providing assistance and resources for the study Represent neighborhoods in study area Street Transportation Department staff and consultants provided information and resources to enable the members to draw their own alternatives on blank maps. A total of 18 alternatives, originally drawn by each individual Committee member (some drew more than one), were collaboratively narrowed through a systematic process to 3 for community consideration in March The members of the Committee are as follows: Representative Clancy Jayne, Chairman Steve Bowser, Tatum Highlands Laura Sobrino, Tatum Highlands Weston Brown, Tatum Ranch Virgel Cain, Tatum Ranch Beverly Montgomery, Tatum Ranch Jim Davis, Desert Ridge Bob Newman, Desert Ridge Lou Lagrave, Dove Valley Bernard Pleskoff, Dove Valley Phil Richards, Parks Board Jim Kunkel, Northeast Phoenix STUDY GOALS The Citizen Committee conducted an exercise during its second meeting (February 2005) to brainstorm Study Goals, which would later be translated into measurable criteria and used by the Committee to select the best alternative for the entire community. Improve Traffic Flow the solution should improve general traffic flow in the study area and alleviate nearcapacity traffic conditions on existing streets. Distribute Traffic Equitably The solution should equitably disperse Sonoran Parkway traffic at its eastern end so as not to disproportionately dump traffic near any one neighborhood. Achieve Consensus the Project Team and community should ensure the finality of this study process with proper community input and feedback and should consider connection roads outside the Sonoran Preserve. Minimize Social and Environmental Impact the solution should be cost-efficient, environmentally/ecologically friendly (air quality, noise, etc.), and mindful of potential property value impacts. The solution should make use of existing/planned high-traffic corridors, and avoid creation of new high-traffic corridors within the study area. To ensure that community values are incorporated into the solution 1

2 The Citizen Committee for the East Sonoran Parkway Alignment Study, after 18 months of careful review and deliberation, recommends that the City of Phoenix Street Transportation Department recommend to City Council adoption of the connections depicted below for the east end of the future Sonoran Parkway: The Committee further recommends that the City consider the following: 1. Coordinate with State Land to encourage phasing of development so that the Sonoran Parkway and Black Mountain Parkway connect to one another first, followed by simultaneous connections to Lone Mountain Road and Tatum Boulevard. 2. Consider scenic designation for the Sonoran Parkway, consistent with the 2004 Sonoran Parkway Design Concept Report. 3. Post the Sonoran Parkway for a 45 mph speed limit. 4. Build four lanes immediately when constructing the Sonoran Parkway, as opposed to an interim two-lane configuration. 5. Maintain the four-lane configuration of Tatum Boulevard through Tatum Ranch as shown on the map. 6. Use rubberized asphalt for noise protection. 7. Move forward with land acquisition to protect the Sonoran Preserve. 8. Consider community involvement in developing the alignment of the Black Mountain Parkway south of Jomax Road. 9. Consider connectivity (especially to the north) and community involvement to design the street network as new development occurs to the west of the ESPA study area. 10. Downgrade the street classification of the segment of Black Mountain Parkway between 40th Street and Carefree Highway from arterial to collector status and rename the segment. To ensure that community values are incorporated into the solution 2

3 STUDY CRITERIA In April 2005, the Committee conducted an exercise to assign a weight of importance to each of the Study Goals listed on page 1. The Committee s recommendation was based on detailed technical analysis, community input, and the study goals and criteria, especially most heavily weighted Study Goal: Distribute Traffic Equitably. CRITERION WEIGHT OF IMPORTANCE The Committee ranked the eight criteria from 1 to 8 in order of importance (8 being most important and 1 being least important) Study Goal: Improve Traffic Flow Access delay from selected side streets, measured by computerized traffic model in seconds for left turning movements Cycle failures at key intersections; measured as number of cycles through which a vehicle must wait 5.96 Level of Service on urban streets, measured in average vehicular speed 6.29 Study Goal: Distribute Traffic Equitably Percent increase of through traffic on urban streets (computerized traffic model separates local traffic from through traffic by assigning through traffic to bypass conditions 6.96 Study Goal: Minimize Social and Environmental Impact Minimize number of drainage crossings/wildlife corridors by roadway. Minimize the number of grade-separated structures Minimize disturbance to Sonoran Preserve (native vegetation and wildlife habitat areas), measured in acres or linear feet Number of front-facing residential properties on urban streets considered for connection To ensure that community values are incorporated into the solution 3

4 PUBLIC INVOLVEMENT SUMMARY City of Phoenix Street Transportation Department The 12-member Citizen Committee met 12 times from January 2005 through. Meetings were open to public observation, and on the average, 15 observers attended each meeting. In March 2005, the Committee toured the project area with City staff and consultants for an on-site review of conditions. Also in March 0f 2005, the team and committee hosted a community open house, which is described below. The community provided valuable input, also described below, which helped the Committee members begin, in May 2005, to draw their own alternative scenarios for the eastern connections of the future Sonoran Parkway. From July 2005 through February of 2006, the team and committee worked together to evaluate the various alternatives and narrow the range to three for presentation to the community in March The March 2006 community meetings are described below. INPUT MATRIX At the first Committee meeting in January 2005, Committee members worked with the facilitator to determine ground rules that would govern Committee meetings. One rule established was that observers would be welcome at Committee meetings, and that any questions or comments from those observers would be accepted in writing and responded to openly. To that end, the project team maintained an Input Status Matrix which included all comments received from Observers at Committee meetings and also comments/questioned posed via the project website (see below) with responses from the project team. PROJECT WEBSITE Information throughout the process has been available at The site includes all Committee meeting notes and other pertinent information, as well as a vehicle for providing comments, asking questions, or requesting addition to the project contact database. UPDATES Notice of all Committee and community meetings was provided to an list that currently contains more than 800 names. MARCH 2005 COMMUNITY OPEN HOUSE Publicity A project newsletter was inserted in local newspapers and ed by Citizen Committee members to local neighborhood groups. The newsletter described the study and invited participants to an open house to provide early input into the study. Coverage: Desert Advocate and Northeast Phoenix Independent. Format The 75 attendees were invited to review and comment on displays around the room that depicted existing conditions in the study area with respect to the To ensure that community values are incorporated into the solution 4

5 roadway network, utilities, land use, drainage, and the environment. Participants filled out comment forms which were synthesized by the project team for Committee review. The comments helped the Committee and team develop a more full understanding of the community and their concerns related to the project. MARCH 2006 COMMUNITY MEETINGS The photo at top right shows the March 30, 2006 community meeting at Horseshoe Trails Elementary School. The photo below shows the March 29, 2006 meeting at Pinnacle High School. Publicity A meeting notice was mailed to more than 7,800 addresses within the study area, and the Desert Advocate and Northeast Phoenix Independent newspapers covered the events. Format The 211 participants spent a few minutes browsing exhibits showing the three alternatives and a bestguess timeframe for how and when the roadway network may be developed, based on development patterns. City staff then presented information about the project and the alternatives, after which the community was invited to comment, both orally and in writing. To ensure that community values are incorporated into the solution 5

Portage Parkway Environmental Assessment Public Information Centre No. 1

Portage Parkway Environmental Assessment Public Information Centre No. 1 City of Vaughan Portage Parkway Environmental Assessment Public Information Centre No. 1 November 25, 2015 Welcome to the Public Information Centre This first Public Information Centre (PIC) introduces

More information

Alternatives Development Three conceptual alternatives were developed for the Race Road/Jessup Village Planning Study and are described below:

Alternatives Development Three conceptual alternatives were developed for the Race Road/Jessup Village Planning Study and are described below: Race Road/Jessup Village Planning Study (H550601) Project Newsletter Spring 2015 Project Description The Study Team, consisting of staff from Anne Arundel County (Department of Public Works and Department

More information

Chapter 5: Natural Resources and Environment

Chapter 5: Natural Resources and Environment NATURAL RESOURCES AND ENVIRONMENT 5-1 5 Chapter 5: Natural Resources and Environment BACKGROUND AND INTENT Urban expansion represents the greatest risk for the future degradation of existing natural areas,

More information

S A C R A M E N T O C O U N T Y JACKSON HIGHWAY & GRANT LINE EAST VISIONING STUDY

S A C R A M E N T O C O U N T Y JACKSON HIGHWAY & GRANT LINE EAST VISIONING STUDY JACKSON HIGHWAY & GRANT LINE EAST S A C R A M E N T O C O U N T Y P L A N N I N G D E P A R T M E N T SUMMARY AND WORKBOOK November 19, 2008 History of the Visioning Study Sacramento County has two growth

More information

Right-of-Way Acquisitions and Relocations Technical Memorandum

Right-of-Way Acquisitions and Relocations Technical Memorandum Right-of-Way Acquisitions and Relocations Technical Memorandum Southeast Extension Project Lincoln Station to RidgeGate Parkway Prepared for: Federal Transit Administration Prepared by: Denver Regional

More information

Date: April 10, 2017 City Council Work Session April 24, 2017: Status Report on the Comprehensive Plan Update and Transportation Master Plan

Date: April 10, 2017 City Council Work Session April 24, 2017: Status Report on the Comprehensive Plan Update and Transportation Master Plan AGENDA REPORT To: From: By: Honorable Mayor and City Council Members Warren Hutmacher, City Manager Sharon Ebert, Director Community Development Date: April 10, 2017 Agenda: City Council Work Session April

More information

TABLE OF CONTENTS LIST OF FIGURES

TABLE OF CONTENTS LIST OF FIGURES TABLE OF CONTENTS INTRODUCTION... 1 HYDRAULIC EVALUATION... 7 TRAFFIC EVALUATION & RECOMMENDATION... 8 UTILITIES... 13 GEOTECHNICAL EVALUATION... 14 ENVIRONMENTAL OVERVIEW... 15 AESTHETICS, WILDLIFE, AND

More information

4 CIRCULATION AND TRANSPORTATION

4 CIRCULATION AND TRANSPORTATION 4 CIRCULATION AND TRANSPORTATION 4.1 INTRODUCTION One of the central concepts of the Hecker Pass Specific Plan is to maintain the rural character and scenic qualities of the area. The transportation and

More information

2.0 PURPOSE AND NEED. 2.1 Purpose. 2.2 Need Traffic Congestion in and around Downtown Derry

2.0 PURPOSE AND NEED. 2.1 Purpose. 2.2 Need Traffic Congestion in and around Downtown Derry 2.0 PURPOSE AND NEED Taking into consideration agency and public input, the purpose and need for the Project was identified early in Project planning. As noted in Appendix A, for purposes of meeting the

More information

PREPARED FOR: PLATTEVIEW ROAD CORRIDOR STUDY EXECUTIVE SUMMARY

PREPARED FOR: PLATTEVIEW ROAD CORRIDOR STUDY EXECUTIVE SUMMARY PREPARED FOR: PLATTEVIEW ROAD CORRIDOR STUDY EXECUTIVE SUMMARY SEPTEMBER 2016 Introduction The Platteview Road Corridor Study was led by the Metropolitan Area Planning Agency (MAPA) with assistance from

More information

Bostwick Road. Municipal Class Environmental Assessment. Public Information Centre #2 June 14, City of London

Bostwick Road. Municipal Class Environmental Assessment. Public Information Centre #2 June 14, City of London Bostwick Road Municipal Class Environmental Assessment Public Information Centre #2 June 14, 2017 Welcome! Welcome to the 2 nd Public Information Centre for the. Representatives from the and the consulting

More information

St. Clair Avenue West Area Transportation Master Plan

St. Clair Avenue West Area Transportation Master Plan 1 (Between Keele Street and Old Weston Road) Public Information Centre 1 December 2, 2015 2 Welcome Welcome to the first Public Information Centre for the St. Clair Avenue West Area. The panels will present

More information

We d like to thank you for attending this Wekiva Parkway Section 8 Preliminary Design Update hosted by the Florida Department of Transportation.

We d like to thank you for attending this Wekiva Parkway Section 8 Preliminary Design Update hosted by the Florida Department of Transportation. We d like to thank you for attending this Wekiva Parkway Section 8 Preliminary Design Update hosted by the Florida Department of Transportation. We will provide you information on the overall project and

More information

Glenn Highway MP DSR. Landscape Narrative

Glenn Highway MP DSR. Landscape Narrative Glenn Highway MP 34-42 DSR Landscape Narrative Project Landscape Goals The Glenn Highway MP 34-42 Project extends through a variety of landscape types typical to the Matanuska-Susitna Valley. In general,

More information

ARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of February 23, 2019

ARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of February 23, 2019 ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of February 23, 2019 DATE: February 15, 2019 SUBJECT: Amendment to the Master Transportation Plan (MTP) Map to add a new section of North Kansas

More information

3. VISION AND GOALS. Vision Statement. Goals, Objectives and Policies

3. VISION AND GOALS. Vision Statement. Goals, Objectives and Policies Vision Statement Queen Creek s interconnected network of parks, trails, open spaces and recreation opportunities provide safe and diverse activities and programs that sustain its unique, small town, equestrian

More information

ROAD CLOSURE AND LAND USE AMENDMENT SILVER SPRINGS (WARD 1) NORTHEAST OF NOSEHILL DRIVE NW AND SILVER SPRINGS ROAD NW BYLAWS 2C2018 AND 29D2018

ROAD CLOSURE AND LAND USE AMENDMENT SILVER SPRINGS (WARD 1) NORTHEAST OF NOSEHILL DRIVE NW AND SILVER SPRINGS ROAD NW BYLAWS 2C2018 AND 29D2018 Page 1 of 19 EXECUTIVE SUMMARY This application proposes redesignating two parcels in the community of Silver Springs from Special Purpose Future Urban Development (S-FUD) District and undesignated road

More information

9 CITY OF VAUGHAN OFFICIAL PLAN AMENDMENT NO BOCA EAST INVESTMENTS LIMITED

9 CITY OF VAUGHAN OFFICIAL PLAN AMENDMENT NO BOCA EAST INVESTMENTS LIMITED 9 CITY OF VAUGHAN OFFICIAL PLAN AMENDMENT NO. 631 - BOCA EAST INVESTMENTS LIMITED The Planning and Economic Development Committee recommends the adoption of the recommendations contained in the following

More information

Chapter 1 - General Design Guidelines CHAPTER 1 GENERAL DESIGN GUIDELINES

Chapter 1 - General Design Guidelines CHAPTER 1 GENERAL DESIGN GUIDELINES CHAPTER 1 GENERAL DESIGN GUIDELINES 1.0 INTRODUCTION This Publication has been developed to provide current, uniform procedures and guidelines for the application and design of safe, convenient, efficient

More information

The Illinois Department of Transportation and Lake County Division of Transportation. Route 173, including the Millburn Bypass

The Illinois Department of Transportation and Lake County Division of Transportation. Route 173, including the Millburn Bypass The Illinois Department of Transportation and Lake County Division of Transportation welcome you to this Public Hearing for U.S. Route 45 from Illinois Route 132 to Illinois Route 173, including the Millburn

More information

M E M O R A N D U M January 6, 2017

M E M O R A N D U M January 6, 2017 Item #4 M E M O R A N D U M January 6, 2017 To: 2035 Corridor Planning Committee From: Kenneth Baker, Sr. Director of Planning and Development Services Subject: Item #4 Overview Fidelis Purpose: Review

More information

2. AGENCY COORDINATION AND PUBLIC INVOLVMENT

2. AGENCY COORDINATION AND PUBLIC INVOLVMENT 2. AGENCY COORDINATION AND PUBLIC INVOLVMENT This chapter discusses the process carried out for conducting agency coordination and public involvement activities. TECHNICAL ADVISORY COMMITTEE A Technical

More information

PROJECT STATEMENT LOCATION/DESIGN PUBLIC HEARING. 19 th AVENUE NORTH EXTENSION PROJECT FROM SPRINGDALE DRIVE TO NORTH 2 ND STREET/U.S.

PROJECT STATEMENT LOCATION/DESIGN PUBLIC HEARING. 19 th AVENUE NORTH EXTENSION PROJECT FROM SPRINGDALE DRIVE TO NORTH 2 ND STREET/U.S. PROJECT STATEMENT LOCATION/DESIGN PUBLIC HEARING 19 th AVENUE NORTH EXTENSION PROJECT FROM SPRINGDALE DRIVE TO NORTH 2 ND STREET/U.S. 67 HEARING LOCATION: ERICKSEN COMMUNITY CENTER 1401 11 TH AVENUE NORTH

More information

Goals for Tonight s Meeting

Goals for Tonight s Meeting South Anthony Boulevard Railroad Grade Separation Study Report to Community November 30, 2011 Andorfer Commons Theatre Indiana Tech University Goals for Tonight s Meeting Recap of the meeting from last

More information

ARGENTA TRAIL (CSAH 28/63) REALIGNMENT SOUTH PROJECT (CP 63-25)

ARGENTA TRAIL (CSAH 28/63) REALIGNMENT SOUTH PROJECT (CP 63-25) ARGENTA TRAIL (CSAH 28/63) REALIGNMENT SOUTH PROJECT (CP 63-25) Preliminary Design Report February 2015 Prepared For: City of Inver Grove Heights Dakota County Prepared By: Kimley-Horn and Associates,

More information

G. RECREATION AND OPEN SPACE ELEMENT. The following summarizes the Recreation and Open Space Element:

G. RECREATION AND OPEN SPACE ELEMENT. The following summarizes the Recreation and Open Space Element: G. RECREATION AND OPEN SPACE ELEMENT The purpose of the Element is to provide the framework and direction for a comprehensive system of public and private sites for recreation, including, but not limited

More information

26/Old Dominion Task Force

26/Old Dominion Task Force 26/Old Dominion Task Force Meeting #9: March 21, 2019 Study Area Overview Staff Name, Department (DEPT ACRONYM) Preferred Scenarios Outline 1. Task Force Feedback from 3/7 2. Refined Concepts 3. Implementation

More information

OPEN HOUSE #3. Project Manager Kristi Sebastian, PE, PTOE

OPEN HOUSE #3. Project Manager Kristi Sebastian, PE, PTOE OPEN HOUSE #3 Project Manager Kristi Sebastian, PE, PTOE kristi.sebastian@co.dakota.mn.us 952-891-7100 WHY ARE WE CONDUCTING THE ARTERIAL CONNECTOR STUDY? Dakota County and the cities of Rosemount, Inver

More information

A raised and landscaped median will be constructed in South College Avenue between Trilby Road and Skyway Drive.

A raised and landscaped median will be constructed in South College Avenue between Trilby Road and Skyway Drive. 5.0 ACCESS CONTROL PLAN This section presents the Access Control Plan Update which has been formulated through the considerable input of the governing agencies, business owners, organized homeowner groups,

More information

CHAPTER 7: Transportation, Mobility and Circulation

CHAPTER 7: Transportation, Mobility and Circulation AGLE AREA COMMUNITY Plan CHAPTER 7 CHAPTER 7: Transportation, Mobility and Circulation Transportation, Mobility and Circulation The purpose of the Transportation, Mobility and Circulation Chapter is to

More information

Interstate 10 Hassayampa Valley Roadway Framework Study. Chapter 6. Alternative Transportation Network Description and Evaluation.

Interstate 10 Hassayampa Valley Roadway Framework Study. Chapter 6. Alternative Transportation Network Description and Evaluation. Interstate 10 Hassayampa Valley Roadway Framework Study Chapter 6 Alternative Transportation Network Description and Evaluation Prepared for Prepared by Table of Contents 6.1 Alternatives Considered...6-1

More information

Mendota Heights 2040 Comprehensive Plan Draft Vers

Mendota Heights 2040 Comprehensive Plan Draft Vers 4 Parks and Trails The City of Mendota Heights boasts a variety of recreational and open space opportunities. Few cities can claim access to regional trails, riverside and lakeside parks, scenic bluffs

More information

COLLIER BOULEVARD (CR 951) CORRIDOR

COLLIER BOULEVARD (CR 951) CORRIDOR Project(s) Goals Improve Traffic Circulation, Capacity & Safety Focus on Safety During Design & Construction Address Public Concerns Design an Aesthetically Pleasing Project Limit Environmental Impacts

More information

OPEN SPACE AND RECREATION

OPEN SPACE AND RECREATION OPEN SPACE AND RECREATION The Town celebrates and maintains the spectacular visual character of our Sonoran Desert setting and we value our open space, mountain views, washes, vegetation, and wildlife.

More information

GILLESPIE COUNTY RELIEF ROUTE PRELIMINARY REPORT AND RECOMMENDATIONS

GILLESPIE COUNTY RELIEF ROUTE PRELIMINARY REPORT AND RECOMMENDATIONS GILLESPIE COUNTY RELIEF ROUTE PRELIMINARY REPORT AND RECOMMENDATIONS November 2015 Table of Contents Introduction 2 Background Information 3 Recent Reports 4 Roadway Location and Design Issues 5 Task Force

More information

S C O P E O F W O R K A P R I L

S C O P E O F W O R K A P R I L white flint 2 sector plan S C O P E O F W O R K A P R I L 2 0 1 2 MONTGOMERY COUNTY PLANNING DEPARTMENT M-NCPPC MontgomeryPlanning.org 1 white flint 2 sector plan Scope of Work abstract This scope of work

More information

510 Highways, Streets & Roads Comprehensive Plan Section 510

510 Highways, Streets & Roads Comprehensive Plan Section 510 511 510 Comprehensive Plan Section 510 Highways, streets, and roads provide for the movement of people and goods from one place to another. These public ways form a network that defines the relationship

More information

A BILL FOR AN ORDINANCE TO AMEND CHAPTER 9, KAUAI COUNTY CODE 1987, RELATING TO STREET REQUIRE:MENTS FOR SUBDIVISIONS

A BILL FOR AN ORDINANCE TO AMEND CHAPTER 9, KAUAI COUNTY CODE 1987, RELATING TO STREET REQUIRE:MENTS FOR SUBDIVISIONS ORDINANCE NO. BILL NO. { vy"yj1j A BILL FOR AN ORDINANCE TO AMEND CHAPTER 9, KAUAI COUNTY CODE 1987, RELATING TO STREET REQUIRE:MENTS FOR SUBDIVISIONS BE IT ORDAINED BY THE COUNCIL OF THE COUNTY OF KAUA'I,

More information

1.0 Circulation Element

1.0 Circulation Element 5/9/18 1.0 Circulation Element 1.1 Introduction As growth and development occur in Apache County, enhancements to its circulation system will be necessary. With time, more roads will be paved and air and

More information

Parks, Trails, and Open space Element

Parks, Trails, and Open space Element Parks, Trails, and Open space Element Parks, Trails, and Open Space element Parks, Recreation, and Open Space are important components of the quality of life desired by the residents of Elk Grove. This

More information

Figure 5. Previously Identified Viable Corridors

Figure 5. Previously Identified Viable Corridors OVERVIEW The Central Florida Expressway Authority (CFX) is evaluating the potential to expand SR 408 from its current eastern terminus along SR 50 to SR 520 in northeastern Orange County, Fl. This new

More information

DRAFT Subject to Modifications

DRAFT Subject to Modifications TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M To: Council Members AGENDA ITEM 8 From: Date: Subject: Staff May 19, 2017 Council Meeting Florida Department of Transportation Complete Streets

More information

Stakeholder Committee

Stakeholder Committee Stakeholder Committee Meeting #5 January 28, 2015 Table of Contents / Agenda Welcome... 3 Meeting Guidelines... 4 Project Updates... 5 Process & Schedule... 5 Recent & Upcoming Outreach... 6 City Council

More information

Mavis Road Class Environmental Assessment

Mavis Road Class Environmental Assessment Mavis Road Class Environmental Assessment Public Information Centre #2 Wednesday November 9, 2016 6:00 to 8:00 p.m. Please sign in and complete a comment sheet Review the displays on your own or join in

More information

Definitions. Average Daily Traffic Demand (ADT): The actual number or projected number of cars that pass a point in a 24-hour period.

Definitions. Average Daily Traffic Demand (ADT): The actual number or projected number of cars that pass a point in a 24-hour period. Definitions Access Management: A combination of physical techniques and transportation policies used to control the flow of traffic between roads and the surrounding lands. Alternative City Form Scenarios:

More information

Updating Speed Performance Measures of Minnesota s Interregional Corridor (IRCs) System

Updating Speed Performance Measures of Minnesota s Interregional Corridor (IRCs) System Updating Speed Performance Measures of Minnesota s Interregional Corridor (IRCs) System By Banette Kritzky, GIS Coordinator, MnDOT, Office of Investment Mgmt ESRI 2004 Background! Began identifying key

More information

Parks, Trails, and Open Space Element

Parks, Trails, and Open Space Element P arks, Recreation, and Open Space are important components of the quality of life desired by the residents of Elk Grove. This Element of the General Plan addresses the City s goals, policies, and actions

More information

EXECUTIVE SUMMARY. Introduction

EXECUTIVE SUMMARY. Introduction EXECUTIVE SUMMARY Introduction State Route 68 is a designated scenic route that connects the world-renowned Monterey Peninsula to US Highway 101 and the Salinas Valley. SR 68 is a key route for bicycle,

More information

COMMUNITY DESIGN. GOAL: Create livable and attractive communities. Intent

COMMUNITY DESIGN. GOAL: Create livable and attractive communities. Intent COMMUNITY DESIGN Intent An attractive, well-designed County will attract quality development, instill civic pride, improve the visual character of the community, and create a strong, positive image for

More information

OPEN SPACE TYPES. SIZE 8 acres. SIZE 20 acres. SIZE 1 acre

OPEN SPACE TYPES. SIZE 8 acres. SIZE 20 acres. SIZE 1 acre TYPICAL CHARACTERISTICS OPEN SPACE TYPES OPEN SPACE TYPES The neighborhood contains an extensive variety of open space types. Most of these spaces incorporate multiple uses and activities, so that each

More information

ROSEMONT 138kV TRANSMISSION LINE PROJECT. Public Open House Meeting #2 August 27, 2009

ROSEMONT 138kV TRANSMISSION LINE PROJECT. Public Open House Meeting #2 August 27, 2009 ROSEMONT 138kV TRANSMISSION LINE PROJECT Public Open House Meeting #2 August 27, 2009 Project Overview Tucson Electric Power (TEP), as a part of its obligation to serve, is proposing to construct and operate

More information

Description of Preferred Alternative

Description of Preferred Alternative Chapter 2 Description of Preferred Alternative 2.1 Introduction This chapter of the programmatic Sammamish Town Center Sub-area Plan Final EIS provides a more detailed description of the Preferred Alternative

More information

SECTION 4(f) DE MINIMIS DOCUMENTATION

SECTION 4(f) DE MINIMIS DOCUMENTATION SECTION 4(f) DE MINIMIS DOCUMENTATION Illinois Route 60/83 IL 176 to the intersection of IL 60 (Townline Road) Lake County P-91-084-07 Mundelein Park and Recreation District Project Limit SECTION 4(f)

More information

SUMMARY Downtown Malabar Meeting on July 30, 2013 State Road (SR) 514 (Malabar Road) Project Development and Environment (PD&E) Study

SUMMARY Downtown Malabar Meeting on July 30, 2013 State Road (SR) 514 (Malabar Road) Project Development and Environment (PD&E) Study SUMMARY Downtown Malabar Meeting on July 30, 2013 State Road (SR) 514 (Malabar Road) Project Development and Environment (PD&E) Study www.sr514malabar.com LOCATION: TIME: ATTENDEES: Malabar Town Hall 2725

More information

Implementation Guide Comprehensive Plan City of Allen

Implementation Guide Comprehensive Plan City of Allen Implementation Guide 2030 Comprehensive Plan City of Allen DRAFT 2015 Implementation Guide Allen 2030 Comprehensive Plan INTRODUCTION The Comprehensive Plan serves as a guide for the growth and development

More information

THE NE QUADRANT LAND USE PLAN

THE NE QUADRANT LAND USE PLAN THE NE QUADRANT LAND USE PLAN APPENDIX - VOLUME 3 APPEND. 9 TRANSPORTATION & APPEND. 13 DR/GR LAND USE Aug. 5, 2013 Barraco and Assoc., Inc. Stuart and Assoc. JMB Transportation Passarella and Assoc. THE

More information

PUBLIC ENGAGEMENT & SIX THEMES OF THE PLAN

PUBLIC ENGAGEMENT & SIX THEMES OF THE PLAN Connecting the heart of Eagle to the soul of the river - Kathy Chandler-Henry, Commissioner Eagle County CHAPTER 1 PUBLIC ENGAGEMENT & SIX THEMES OF THE PLAN town of eagle - river corridor plan 1 PUBLIC

More information

Introduction. Chapter 1. Purpose of the Comprehensive Plan Plan Organization Planning Process & Community Input 1-1

Introduction. Chapter 1. Purpose of the Comprehensive Plan Plan Organization Planning Process & Community Input 1-1 Chapter 1 Introduction Lakewood 2025: Moving Forward Together Purpose of the Comprehensive Plan Plan Organization Planning Process & Community Input 1-1 Purpose of the Comprehensive Plan The Comprehensive

More information

Summary Community Workshop #6 Beacon Day School Saturday, November 14, :00 a.m. 12:00 p.m.

Summary Community Workshop #6 Beacon Day School Saturday, November 14, :00 a.m. 12:00 p.m. Summary Community Workshop #6 Beacon Day School Saturday, November 14, 2009 9:00 a.m. 12:00 p.m. Workshop Format and Process The City of Oakland is preparing a Specific Plan that will help define and determine

More information

PROJECT BACKGROUND. Preliminary Design Scope and Tasks

PROJECT BACKGROUND. Preliminary Design Scope and Tasks PROJECT BACKGROUND Preliminary Design Scope and Tasks The purpose of this Study is the development of preliminary designs for intersection improvements for Trunk Highway (TH) 36 at the intersections of

More information

Staff Report and Recommendation

Staff Report and Recommendation Community Planning and Development Planning Services 201 W. Colfax Ave., Dept. 205 Denver, CO 80202 p: 720.865.2915 f: 720.865.3052 www.denvergov.org/cpd TO: City Council Neighborhoods and Planning Committee

More information

CITY PLANNING COMMISSION AGENDA ITEM: C STAFF: ROBERT TEGLER FILE NO: CPC PUD QUASI-JUDICIAL

CITY PLANNING COMMISSION AGENDA ITEM: C STAFF: ROBERT TEGLER FILE NO: CPC PUD QUASI-JUDICIAL CPC AGENDA June 8, 2006 Page 37 CITY PLANNING COMMISSION AGENDA ITEM: C STAFF: ROBERT TEGLER FILE NO: CPC PUD 05-294 - QUASI-JUDICIAL PROJECT: APPLICANT: OWNER: PARKWOOD AT WOLF RANCH NASS DESIGN ASSOCIATES

More information

TOWN OF BRUNSWICK MEETING AGENDA TOWN COUNCIL CHAMBERS TOWN HALL 85 UNION STREET TUESDAY, MAY 13, :00 P.M.

TOWN OF BRUNSWICK MEETING AGENDA TOWN COUNCIL CHAMBERS TOWN HALL 85 UNION STREET TUESDAY, MAY 13, :00 P.M. TOWN OF BRUNSWICK ZONING ORDINANCE REWRITE COMMITTEE 85 Union Street, Brunswick, ME 04011-1583 MEETING AGENDA TOWN COUNCIL CHAMBERS TOWN HALL 85 UNION STREET TUESDAY, MAY 13, 2014 4:00 P.M. 1. Discuss

More information

Creating Complete Roadway Corridors:

Creating Complete Roadway Corridors: Creating Complete Roadway Corridors: The AASHTO Guide to Transportation Landscape Architecture and Environmental Design NCHRP Project 15-33 Status Report AASHTO Standing Committee on Design Technical Committee

More information

City of Toronto. Emery Village Transportation Master Plan

City of Toronto. Emery Village Transportation Master Plan City of Toronto Emery Village Transportation Master Plan May 2009 Emery Village Transportation Master Plan Toronto, ON May 2009 Consulting Inc. 100 York Blvd., Suite 300 Richmond Hill, ON L4B 1J8 Tel:

More information

Seneca Meadows. Block 4 Locate office, technology, and medical development adjacent to I Screen views of garage structures from I-270.

Seneca Meadows. Block 4 Locate office, technology, and medical development adjacent to I Screen views of garage structures from I-270. Seneca Meadows Seneca Meadows has an industrial park in its southern end and a mixed-use employment area planned for the north end. The district benefits from extensive I-270 visibility, stream valley

More information

2.0 AREA PLANS. Lakeside Business District. Lakeside Business District Land Use Categories:

2.0 AREA PLANS. Lakeside Business District. Lakeside Business District Land Use Categories: Lakeside Business District Lakeside Business District Land Use Categories: Campus Commercial Campus Commercial means a mixture of uses which includes corporate offices, office parks, hotels, commercial,

More information

2011 ASLA Design Awards

2011 ASLA Design Awards 2011 ASLA Design Awards Interstate 70 Mountain Corridor Aesthetic Guidance Honor Award Design Workshop, Aspen / THK Associates, Inc. / CH2MHill Planning and Urban Design Project Title: Interstate70 Mountain

More information

Emery Village Road 2A Municipal Class Environmental Assessment Study

Emery Village Road 2A Municipal Class Environmental Assessment Study PW12.11 STAFF REPORT ACTION REQUIRED Emery Village Road 2A Municipal Class Environmental Assessment Study Date: March 30, 2016 To: From: Wards: Reference Number: Public Works and Infrastructure Committee

More information

Plan Overview. Manhattan Area 2035 Reflections and Progress. Chapter 1: Introduction. Background

Plan Overview. Manhattan Area 2035 Reflections and Progress. Chapter 1: Introduction. Background Plan Overview The Manhattan Urban Area Comprehensive Plan (the Comprehensive Plan) is a joint planning initiative of the City of Manhattan, Pottawatomie County, and Riley County. The 2014 Comprehensive

More information

MASTER PLAN. 201 Planning Concepts. Chapter 2

MASTER PLAN. 201 Planning Concepts. Chapter 2 Chapter 2 MASTER PLAN 201 Planning Concepts 202 Master Land Use Plan 203 Affordable Housing Program 204 Parks, Open Space, and Recreation Trails 205 Grading Concept 206 Circulation Plan 207 Landscape Concept

More information

Route 5 Corridor Land Use and Transportation Plan

Route 5 Corridor Land Use and Transportation Plan N Y S M P O Integrated Transportation Planning & Community Design Processes ALBANY Great streets do not just happen... They are streets for both pedestrians and drivers. They have definition, a sense of

More information

Cobb County Design Guidelines Mableton Parkway & Veterans Memorial Highway Community Design Workshop January 12, 2017

Cobb County Design Guidelines Mableton Parkway & Veterans Memorial Highway Community Design Workshop January 12, 2017 Community Design Workshop January 12, 2017 Agenda Opening Remarks / Introductions Scope of Work Existing Conditions Key Issues / Opportunities VPS Summary Draft Vision & Goal Statement Implementation Concepts

More information

Present. and. Future

Present. and. Future Present and Future July 1985 303 from MC 85 to I-17 included in the Regional Freeway System May 1989 State Transportation Board adopts Loop 303 1990 Revenues from Proposition 300 insufficient; 303 removed

More information

Planning Commission Staff Report March 15, 2007

Planning Commission Staff Report March 15, 2007 Planning Commission Staff Report Project: Request: Madeira East Tentative Subdivision Map, Design Review for Subdivision Layout & Abandonment of Easements Location: Phase IV of the Laguna Ridge Specific

More information

MODEL ACCESS MANAGEMENT PLAN MINNESOTA TRUNK HIGHWAY 7 COMPREHENSIVE PLAN AMENDMENT (HUTCHINSON SEGMENT)

MODEL ACCESS MANAGEMENT PLAN MINNESOTA TRUNK HIGHWAY 7 COMPREHENSIVE PLAN AMENDMENT (HUTCHINSON SEGMENT) MODEL ACCESS MANAGEMENT PLAN MINNESOTA TRUNK HIGHWAY 7 (HUTCHINSON SEGMENT) COMPREHENSIVE PLAN AMENDMENT INTRODUCTION. The purpose of this plan is to provide consistent access management in the Trunk

More information

Inform you of the purpose and scope of the study for PTH 100 and a proposed future St. Norbert Bypass;

Inform you of the purpose and scope of the study for PTH 100 and a proposed future St. Norbert Bypass; WELCOME The intent of today s Open House is to: Inform you of the purpose and scope of the study for PTH 100 and a proposed future St. Norbert Bypass; Review highway crossing locations, future access closures

More information

4.1 AESTHETICS AND VISUAL QUALITY

4.1 AESTHETICS AND VISUAL QUALITY SCOPE AND METHODOLOGY 4.1 AESTHETICS AND VISUAL QUALITY This section evaluates the potential impacts to aesthetics and visual quality. Aesthetics refers to visual resources and the quality of what can

More information

CHAPTER VIII Implementation

CHAPTER VIII Implementation CHAPTER VIII Implementation VIII. Implementation The vision for the Marlboro Pike Corridor will require that a variety of participants work together to make it a reality. The following action steps outline

More information

Executive Summary. NY 7 / NY 2 Corridor

Executive Summary. NY 7 / NY 2 Corridor Executive Summary NY 7 / NY 2 Corridor Transportation and Land Use Study December 2005 Prepared for: Town of Colonie Capital District Transportation Committee Prepared by: Introduction: Land use decisions

More information

West Broadway Transit Study Initial Screening of Alternatives Memo

West Broadway Transit Study Initial Screening of Alternatives Memo West Broadway Transit Study Initial Screening of Alternatives Memo 5/22/2015 Prepared by the SRF Consulting Group Team for Table of Contents Purpose... 1 Methodology... 1 Screening... 5 Screening Criteria...

More information

2 STATUTORY PUBLIC MEETING AND INFORMATION REPORT FOR PUBLIC MEETING ON AMENDMENT NO. 62 TO THE YORK REGION OFFICIAL PLAN

2 STATUTORY PUBLIC MEETING AND INFORMATION REPORT FOR PUBLIC MEETING ON AMENDMENT NO. 62 TO THE YORK REGION OFFICIAL PLAN 2 STATUTORY PUBLIC MEETING AND INFORMATION REPORT FOR PUBLIC MEETING ON AMENDMENT NO. 62 TO THE YORK REGION OFFICIAL PLAN Pursuant to Section 17(15) of the Planning Act, as amended, the Regional Planning

More information

BeltLine Corridor Environmental Study

BeltLine Corridor Environmental Study BeltLine Corridor Environmental Study Joint TAC and SAC Meeting December 8, 2008 What We Will Discuss Today Outreach and Agency Coordination Scoping Results Existing Conditions Historical and Archeological

More information

METROPOLITAN COUNCIL 390 North Robert Street, St. Paul, MN Phone (651) ; TDD (651)

METROPOLITAN COUNCIL 390 North Robert Street, St. Paul, MN Phone (651) ; TDD (651) DATE: December 20, 2011 METROPOLITAN COUNCIL 390 North Robert Street, St. Paul, MN 55101 Phone (651) 602-1000; TDD (651) 291-0904 TO: Metropolitan Parks and Open Space Commission FROM: Tori Dupre, Senior

More information

ACCESS MANAGEMENT REPORT U.S S.H. 1 TO S.H. 14 S.H U.S. 287 TO I-25

ACCESS MANAGEMENT REPORT U.S S.H. 1 TO S.H. 14 S.H U.S. 287 TO I-25 ACCESS MANAGEMENT REPORT U.S. 287 - S.H. 1 TO S.H. 14 S.H. 14 - U.S. 287 TO I-25 Prepared by: City of Fort Collins Transportation Planning 7951 East Maplewood Avenue, Suite 200 210 E. Olive, P.O. Box 580

More information

WELCOME TO OPEN HOUSE TWO November 28, 2018

WELCOME TO OPEN HOUSE TWO November 28, 2018 Langstaff Road Weston Road to Highway 7 Class Environmental Assessment Study WELCOME TO OPEN HOUSE TWO November 28, 2018 Please sign in and join our mailing list Study Overview York Region is conducting

More information

Chapter 13: Implementation Plan

Chapter 13: Implementation Plan Implementation A. Introduction The Implementation Plan, in table form on the following pages, provides a summary of all the Action Items recommended in Chapters 2 through 12. The table also indicates which

More information

Proposed Walkability Ordinance for City of Knoxville (6/16/17)

Proposed Walkability Ordinance for City of Knoxville (6/16/17) Proposed Walkability Ordinance for City of Knoxville (6/16/17) New or revised text is highlighted Section 1: Purpose The purpose of this ordinance is to set requirements for walkability and pedestrian

More information

Route 1 Corridor Study

Route 1 Corridor Study Route 1 Corridor Study Westbrook, Connecticut A Vision for the Connecticut Shoreline Public Informational Meeting July 28, 2015 Lower Connecticut River Valley Council of Governments Fitzgerald & Halliday,

More information

2040 Long Range Transportation Plan

2040 Long Range Transportation Plan 2040 Long Range Transportation Plan Adopted: April 15, 2013 APPENDIX D HIGHWAY NEEDS PLAN PROJECTS FREDERICKSBURG Existing and Committed Projects Fall Hill Avenue/Mary Washington Blvd. (Fredericksburg)

More information

PUBLIC HEARING. Thursday, December 14, 2017 FDOT Urban Office 2198 Edison Avenue Jacksonville, FL 32204

PUBLIC HEARING. Thursday, December 14, 2017 FDOT Urban Office 2198 Edison Avenue Jacksonville, FL 32204 DISTRICT TWO PUBLIC HEARING I 10 (SR 8) from I 295 to I 95 Project Development & Environment Study Duval County, Florida Financial Project Number 213326 2 22 01 Efficient Transportation Decision Making

More information

ALMA DRIVE CONSTRUCTION Project Public Meeting June 18, :00 pm

ALMA DRIVE CONSTRUCTION Project Public Meeting June 18, :00 pm ALMA DRIVE CONSTRUCTION Project Public Meeting June 18, 2015 6:00 pm Tim Porter, P.E. Program Manager 214.509.4581 tporter@cityofallen.org Angela Mosley, P.E. Project Manager 214.509.4579 amosley@cityofallen.org

More information

Access Management: An Overview

Access Management: An Overview Figures 1-5 Below Evolution of development along a highway. In the early stages, land along the road is used for farming with little traffic generated. As time passes, the highway corridor becomes a de

More information

ADOPTION OF THE REVISED OPEN SPACE AND CONSERVATION ELEMENT OF THE GENERAL PLAN

ADOPTION OF THE REVISED OPEN SPACE AND CONSERVATION ELEMENT OF THE GENERAL PLAN TO: FROM: SUBJECT: Honorable Mayor and City Council Planning Department ADOPTION OF THE REVISED OPEN SPACE AND CONSERVATION ELEMENT OF THE GENERAL PLAN RECOMMENDATION: It is recommended that the City Council:

More information

BROOKHILL NEIGHBORHOOD MODEL ZONING MAP AMENDMENT PREFACE TO APPLICATION

BROOKHILL NEIGHBORHOOD MODEL ZONING MAP AMENDMENT PREFACE TO APPLICATION BROOKHILL NEIGHBORHOOD MODEL ZONING MAP AMENDMENT PREFACE TO APPLICATION June 15, 2015 Revised: August 1, 2016 I. VISION Brookhill is a proposed community based upon the principles of Albemarle County

More information

Mitchell Ranch South MPUD Application for Master Planned Unit Development Approval Project Narrative. Introduction

Mitchell Ranch South MPUD Application for Master Planned Unit Development Approval Project Narrative. Introduction Mitchell Ranch South MPUD Application for Master Planned Unit Development Approval Project Narrative Introduction Mitchell Ranch South is a proposed single family (detached) residential development on

More information

Northeast Connector Expressway Extension Concept, Feasibility and Mobility Study Environmental Advisory Group Meeting #1 June 26, 2018

Northeast Connector Expressway Extension Concept, Feasibility and Mobility Study Environmental Advisory Group Meeting #1 June 26, 2018 NORTHEAST CONNECTOR EXPRESSWAY EXTENSION (NECEE) ENVIRONMENTAL ADVISORY GROUP (EAG) MEETING #1 SUMMARY Date/Time: Tuesday, June 26, 2018; 1:30 p.m. 3 p.m. Location: Central Florida Expressway Authority

More information

East Panorama Ridge Concept Plan Amendment

East Panorama Ridge Concept Plan Amendment Page 1 of 7 L003 : East Panorama Ridge Concept Plan Amendment Corporate NO: L003 Report COUNCIL DATE: March 4, 2002 REGULAR COUNCIL LAND USE TO: Mayor & Council DATE: February 27, 2002 FROM: General Manager,

More information

WASHINGTON COUNTY OREGON

WASHINGTON COUNTY OREGON WASHINGTON COUNTY OREGON July 9, 2009 Revisions to Chapter 2 of the Bethany Community Plan The North Bethany Subarea Plan Exhibit pages 7 and 8 The sections for the Core and Flexible Streets were amended

More information

Regional Mobility & the US 380 Bypass Concept. Informational Meeting February 9, 2017

Regional Mobility & the US 380 Bypass Concept. Informational Meeting February 9, 2017 Regional Mobility & the US 380 Bypass Concept Informational Meeting February 9, 2017 Purpose and Agenda Purpose: Regional Mobility Issues, Priorities, and Pressures US 380 as a Limited Access Facility

More information