Oakdale Primary School Expansion Project Appendix A - MEP Schedule of Works
|
|
- Austen Bryant
- 6 years ago
- Views:
Transcription
1 Oakdale Primary School Expansion Project Appendix A - MEP Schedule of Works HBS-SH-MEP-801 May 2017 For Peterborough City Council ver. author date checked comment P1 KA TC TENDER ISSUE 1
2 1. Mechanical Services Schedule of Works (Tender Return) Phase Preliminaries including design 1.02 Liaise with utility companies and isolate/strip-out existing water and gas supplies to existing Nursery Building to be demolished 1.03 External trench from boiler room to Block N with pre-insulated heating flow/return pipework and mains water supply pipework Design/ Supply/ Install 1.04 Strip-out existing boiler plant 1.05 New boiler plant installation including boilers, flues, pressurisation unit, pumps, hot water cylinder, control panel, pipework and fittings, thermal insulation, control wiring etc. Design/ Supply/ Install 1.06 Heating services including pipework, radiators, insulation, valves, drain cocks, brackets and thermal insulation. Design/ Supply/ Install 1.07 Hot and cold water services including water heaters, pipework, insulation, valves, drain cocks, brackets and thermal insulation. Design/ Supply/ Install 1.08 Above ground drainage Design/ Supply/ Install 1.09 Mechanical ventilation system (extract fans) to cleaner store and server room, including fan units, ductwork etc. Design/ Supply/ Install 1.10 Mechanical ventilation (heat recovery ventilation unit) to pupil toilets, including unit, wiring, control system and commissioning by manufacturer. - Design/ Supply/ Install 1.11 Classroom natural ventilation; attenuated louvres with motorised dampers including controls - Design/ Supply/ Install 1.12 Classroom natural ventilation; window motors including controls - Design/ Supply/ Install 1.13 Test and commissioning of all mechanical and public health services including automatic controls 1.14 Chlorination of hot and cold water services installation 1.15 Water treatment to new and existing heating system 1.16 Provision of O&M Maintenance manuals and record drawings Provision of Installation Drawings 2
3 1.18 Provision of Record Drawings 1.19 Provision of as-built Part L BRUKL document and Energy Performance Certificate PHASE 1: MECHANICAL TO BE CARRIED FORWARD TO MAIN TENDER SUMMARY 3
4 Phase Preliminaries including design 2.02 Heating services including pipework, radiators, insulation, valves, drain cocks, brackets and thermal insulation. Design/ Supply/ Install 2.03 Hot and cold water services including water heaters, pipework, insulation, valves, drain cocks, brackets and thermal insulation. Design/ Supply/ Install 2.04 Above ground drainage Design/ Supply/ Install 2.05 Mechanical ventilation systems (extract fans) to cleaner stores, showers, toilets including fan units, ductwork etc. Design/ Supply/ Install 2.06 Test and commissioning of all mechanical and public health services including automatic controls 2.07 Chlorination of hot and cold water services installation 2.08 Water treatment to heating system 2.09 Provision of O&M Maintenance manuals and record drawings Provision of Installation Drawings 2.11 Provision of Record Drawings PHASE 2: MECHANICAL TO BE CARRIED FORWARD TO MAIN TENDER SUMMARY 4
5 Phase Preliminaries including design 3.02 Heating services including pipework, radiators, insulation, valves, drain cocks, brackets and thermal insulation. Design/ Supply/ Install 3.03 Diversion and lowering of existing incoming gas and water services as required where new car parking surface is formed. Liaise with utility companies as required Hot and cold water services including water heaters, pipework, insulation, valves, drain cocks, brackets and thermal insulation. Design/ Supply/ Install 3.05 Above ground drainage Design/ Supply/ Install 3.06 Mechanical ventilation systems (extract fans) to cleaner stores, showers, toilets including fan units, ductwork etc. Design/ Supply/ Install 3.07 Test and commissioning of all mechanical and public health services including automatic controls 3.08 Chlorination of hot and cold water services installation 3.09 Water treatment to new and existing heating system 3.10 Provision of O&M Maintenance manuals and record drawings Provision of Installation Drawings 3.12 Provision of Record Drawings PHASE 3: MECHANICAL TO BE CARRIED FORWARD TO MAIN TENDER SUMMARY 5
6 2. Electrical Services Schedule of Works (Tender Return) Enabling phase E.01 Preliminaries including design E.02 Employ the services of Serco to divert existing fibre by City wide fibre into new server locationref: SWB WO Oakdale Primary School City Fibre Move E.03 Design, supply and install all power, lighting requirements into new server room. (currently part of bin store) E.04 Design, supply and install relocated existing data cabinet from ICT suite or provide new 42 u data cabinet and terminate existing data cables into new patch panels (see item 6.11) E.05 Liaise with utility companies and isolate/strip-out existing electricity and telecoms supplies to existing Nursery Building to be demolished E.06 Strip out and remove all electrical services from Nursery prior to demolition as required by demolition contractor. Phase Preliminaries including design 4.02 Design, Supply and install new MCCB in existing 6 way panel Design, Supply and install new LV Sub mains to new TP&N dist board. route, duct, containment to new dist board Design, Supply and install new MCB Distribution Board in new classroom block, DB-H 4.05 New Primary Containment/ Design / Supply / Install 4.06 Fire Stopping/ Design / Supply / Install 4.07 Secondary Containment / Design / Supply / Install 6
7 4.08 Small Power/ Design / Supply / Install 4.09 Internal Lighting Circuits and Controls/ Design / Supply / Install 4.10 Internal Lighting / Design / Supply / Install 4.11 Emergency lighting / Design / Supply / Install 4.12 External Lighting Circuits and Controls/ Design / Supply / Install 4.13 External Lighting Supply and Installation on building / Design / Supply / Install 4.14 Earthing and Bonding 4.15 Fire Detection System / Design / Supply / Install / Commission / Include link to existing main panel.(temp) 4.16 Security Alarm System / Design / Supply / Install / Commission/ Include link to existing main panel.(temp) 4.17 Class change bell system linked to school existing / Design / Supply / Install New lightning protection system linked to existing / Design / Supply / Install Mechanical Services Supplies and Containment wire ways for Mech supplies, accessories and cabling, final connection at source, supplied and installed by others / Design / Supply / Install Verification / testing & certification of systems 4.21 Provision of O&M Documentation and Record drawings 4.22 Provision of installation drawings ENABLING PHASE AND PHASE 1: ELECTRICAL TO BE CARRIED FORWARD TO MAIN TENDER SUMMARY 7
8 Phase Preliminaries including design 5.02 Strip out existing electrical installation ahead of demolition/refurbishment Design, Supply and install new MCCB in existing 6 way panel Design, Supply and install new LV Sub mains, route, duct / containment to new dist board Design, Supply and install new MCB Distribution Boards, DB-A, DB-B, DB-C including sub metering New Primary Containment/ Design / Supply / Install 5.07 Fire Stopping/ Design / Supply / Install 5.08 Secondary Containment / Design / Supply / Install 5.09 Small Power/ Design / Supply / Install 5.10 Data cabinet in nursery and cat5e data cabling including terminations / Design / Supply / Install (inc patch panels & RJ45 double front plates) 5.11 From main Data cabinet provide data cabling including terminations to all non-nursery areas / Design / Supply / Install (inc patch panels & RJ45 double frontplates) 5.12 Design, Supply and install data fibre link between main school data cabinet and data cabinet in store room of nursery Internal Lighting Circuits and Controls/ Design / Supply / Install 5.14 Internal Lighting / Design / Supply / Install 5.15 Emergency lighting / Design / Supply / Install 5.16 External Lighting Circuits and Controls/ Design / Supply / Install 8
9 5.17 External Lighting Supply and Installation on building / Design / Supply / Install 5.18 Earthing and Bonding 5.19 Fire Detection System / Design / Supply / Install / Commission / Include link to existing main panel Security Alarm System / Design / Supply / Install / Commission / Include link to existing main panel Class change bell system linked to school existing / Design / Supply / Install Access control system to / Design / Supply / Install / Commission 5.23 Mechanical Services Supplies and Containment wire ways for Mech supplies, accessories and cabling, final connection at source, supplied and installed by others / Design / Supply / Install Telecommunications & Data / Design / Supply / Install / Commission 5.25 New lightning protection system linked to existing / Design / Supply / Install Verification / testing & certification of systems 5.27 Provision of O&M Documentation and Record drawings 5.28 Provision of installation drawings PHASE 2: ELECTRICAL TO BE CARRIED FORWARD TO MAIN TENDER SUMMARY 9
10 Phase Preliminaries including design 6.02 Design/and arrange the diversion and lowering of incoming telecoms and electrical services as required where new car parking spaces is formed and were widened apron is formed. Liaise with utility companies as required Strip out existing electrical installation ahead of demolition/refurbishment Design, Supply and install new 8 way MCCB to replace existing located in main intake 6.05 Design, Supply and install new LV Sub mains from new MCCB board to sub boards 6.06 Design, Supply and install new MCB Distribution Boards DB-D,DB-E,DB-F & DB-G 6.07 New Primary Containment/ Design / Supply / Install 6.08 Fire Stopping/ Design / Supply / Install 6.09 Secondary Containment / Design / Supply / Install 6.10 Small Power/ Design / Supply / Install 6.11 Design, supply and install new 42 u data cabinet and terminate existing data cables into new patch panels. (remove existing cabinet) 6.12 From main Data cabinet provide data cabling including terminations / Design / Supply / Install (inc patch panels & RJ45 double frontplates) 6.13 Internal Lighting Circuits and Controls/ Design / Supply / Install 6.14 Internal Lighting / Design / Supply / Install 6.15 Emergency lighting / Design / Supply / Install 10
11 6.16 External Lighting Circuits and Controls/ Design / Supply / Install 6.17 External Lighting Supply and Installation on building / Design / Supply / Install 6.18 Earthing and Bonding 6.19 Fire Detection System / Design / Supply / Install / Commission / Include new main panel Terminate fire alarm cables from phase 1 & 2 into new fire alarm panel / Design / Supply / Install / 6.21 Security Alarm System & new panel / Design / Supply / Install / Commission 6.22 Terminate intruder alarm cables from phase 1 & 2 into new intruder alarm panel. / Design / Supply / Install / 6.23 Class change bell system linked to school existing / Design / Supply / Install Mechanical Services Supplies and Containment wire ways for Mech supplies, accessories and cabling, final connection at source, supplied and installed by others / Design / Supply / Install op1 Relocation of Telecommunications system & BT lines / into new office meeting room & BT lines / Design / Supply / Install / Commission 6.25-op2 Relocation of Telecommunications system & BT lines / into new server room & BT lines / Design / Supply / Install / Commission 6.26 Verification / testing & certification of systems 6.27 Provision of O&M Documentation and Record drawings 6.28 Provision of installation drawings PHASE 3: ELECTRICAL TO BE CARRIED FORWARD TO MAIN TENDER SUMMARY 11
FUME EXTRACT STRATEGY STATEMENT
FUME EXTRACT STRATEGY STATEMENT : New Islington Free School No: 7/4781 The site is located in central Manchester on an area of disused land adjacent to the Rochdale canal. The site forms a roughly rectangular
More informationOakdale Primary School Expansion Project Appendix C Elec Equipment Schedule
Oakdale Primary School Expansion Project Appendix C Elec Equipment Schedule HBS-SH-MEP-803 May 2017 For Peterborough City Council ver. author date checked comment P1 DH 19-05-17 TJC TENDER ISSUE 1 Ref
More informationPlanning Application for the Aylesbury Estate Regeneration. Plot 18 Reserved Matters Application. Ventilation Statement. Aecom
Planning Application for the Aylesbury Estate Regeneration Plot 18 Reserved Matters Application Ventilation Statement Aecom v1 Aylesbury Regeneration: Plot 18 Reserved Matters Application Ventilation Statement
More informationEco Active H E A T R E C O V E R Y S Y S T E M S H Y B R I D U N I T. W: T:
Eco Active H Y B R I D U N I T W: www.gdl.co.uk T: 01457 861538 Eco Active Hybrid Unit The Eco Active Hybrid unit is designed to provide ventilation in both summer and winter seasons. Ventilation is achieved
More informationSCHEDULE OF RATES SHEET PRELIMINARIES
Page : 1 PRELIMINARIES 1 CONTAINER BUDGET ALLOWANCE 1,100.00 1,100.00 1 SUPERVISION 3,900.00 3,900.00 1 ACCOMMODATION 5,390.00 5,390.00 1 TRAVEL ALLOWANCE 7,800.00 7,800.00 Sub- 18,190.00 18,190.00 Page
More informationGARCIA GALUSKA DESOUSA Consulting Engineers
L#57295/Page 1/July 21, 2017 HVAC SYSTEMS NARRATIVE REPORT The following is the HVAC system narrative, which defines the scope of work and capacities of the HVAC system as well as the Basis of Design.
More informationGOLDFIELDS PRIMARY SCHOOL. TENDER SPECIFICATION For ELECTRICAL SERVICES MECHANICAL ENGINEER:
GOLDFIELDS PRIMARY SCHOOL TENDER SPECIFICATION For ELECTRICAL SERVICES PROJECT MANAGER: School Support Dunedin ARCHITECTURAL DESIGNER: Katipo Design ELECTRICAL ENGINEER: Pedersen Read Dunedin MECHANICAL
More informationOperating Performance
INFORMATION SHEET 1 Jackson Engineering Advisers are specialist Building Services Engineers. This information sheet is offered as an aid to Building Owners and Managers as a guide to plant life expectancies.
More informationMEP Syllabus CAREER DEVELOPMENT CENTRE SHRISTI MEP. Trichy-26
SHRISTI MEP CAREER DEVELOPMENT CENTRE Trichy-26 MEP Syllabus Contact : dhinesh.shristimep@gmail.com / sangeetha.shristimep@gmail.com +91-80984 49847, 97158 67493 ELECTRICAL DESIGNING AND DRAUGHTING FUNDAMENTALS
More informationNES. What s New June Contents: Detailed Technical guidance. Work section updates. (key points)
Contents: Section 1. Section 2. Section 3. Section 4 SUMMARY DETAIL OF WORK SECTION UPDATES & AUDITS SCHEDULES DETAIL CHANGES TO REFERENCE DOCUMENTS A full record of the content revisions can be obtained
More informationTelecity. Table of Contents. Page. Section 3.2
1 3.2 System Descriptions Table of Contents 3.2 SYSTEM DESCRIPTIONS... 3 3.2.1 General Notes... 3 3.3 Power Distribution MV... 4 3.3.1 Incoming Supply... 4 3.3.2 MV Switch room... 4 3.4 Power Distribution
More informationSCHOOL OF ENGINEERING. BSc(HONS) IN QUANTITY SURVEYING & COMMERCIAL MANAGEMENT SEMESTER 1 EXAMINATION 2015/2016 RISK AND VALUE MANAGEMENT
TW45 SCHOOL OF ENGINEERING BSc(HONS) IN QUANTITY SURVEYING & COMMERCIAL MANAGEMENT SEMESTER 1 EXAMINATION 2015/2016 RISK AND VALUE MANAGEMENT MODULE NO: CAS6003 Date: Wednesday 13 January 2016 Time: 2.00
More informationSECTION HVAC TABLE OF CONTENTS PART 1 - SYSTEM DESCRIPTION / OUTLINE SPECIFICATIONS FILED SUB BID PROJECT OVERVIEW...
SECTION 230001 TABLE OF CONTENTS SECTION 230001 PART 1 - SYSTEM DESCRIPTION / OUTLINE SPECIFICATIONS... 1 1.00 FILED SUB BID... 1 1.01 PROJECT OVERVIEW... 2 1.02 DESIGN CRITERIA... 4 1.03 CODE ISSUES...
More informationIndoor Swimming Pools:
Indoor Swimming Pools: The Technologies 20 th November 2017 Amnon Holland BE Eng, M.AIRAH www.esbsconsult.com.au 1 Agenda The driver Code Compliance of Ventilation The Technologies - Heat exchange and
More informationIf a peak space temperature to about 28ºC is acceptable to the occupants then a naturally ventilated solution is a viable option.
Air handling units Aesthetic Not to add significantly to the existing ambient noise levels. Functional requirements If a peak space temperature to about 28ºC is acceptable to the occupants then a naturally
More informationInstallation Instructions
Installation Instructions The energy you need Accessories/PFGHRD 60/100 Passive Flue Gas Heat Recovery Device Explanation of Symbols a DANGER: Risk of injuries. The PFGHRD is an integral part of the flue
More informationAppendix B. Facilities Assessment Report
Mile Lane Army Reserve Center Redevelopment Plan September 2008 Appendix B Facilities Assessment Report RKG Associates, Inc. Mile Lane Army Reserve Base Middletown, CT MEP System Evaluation For RKG Associates
More informationELECTRICAL AND COMMUNICATION INSTALLATION DESIGN IN AN OFFICE COMPLEX
ELECTRICAL AND COMMUNICATION INSTALLATION DESIGN IN AN OFFICE COMPLEX PROJECT INDEX: PRJ017 BY F17/1765/2006 MUTUMA WALTER MURIMI SUPERVISOR: PROF. E. MWANGI EXAMINER: DR. J. MBUTHIA DATE: 27 th MAY 2011
More informationCPC-150-ABIAB. Important Installation Notes.
6 7 8 9 10 28 11 20 19 18 13 4 1 17 23 2 3 5 30 HX14 Pandora Heat Bank thermal store [] 150 litres, 530mm diameter x 1300mm high L18-14 plate heat exchanger for mains pressure hot water (30 l/min), Heatguard
More informationThe works comprise the complete supply and installation of new Electrical Engineering Services to the site comprising:-
3.0 ELECTRICAL SPECIFICATION 3.1 SCHEDULE OF WORKS 3.1.1 Introduction The works comprise the supply and installation of new Electrical Services within the refurbishment of an existing warehouse to form
More informationRoyal Wolfson Foundation Laboratory Refurbishment Grants Scheme Final Report: University of Glasgow, Prof Lee Cronin
Royal Wolfson Foundation Laboratory Refurbishment Grants Scheme Final Report: University of Glasgow, Prof Lee Cronin Background In January 2011, the Royal Society Wolfson Laboratory Refurbishment Scheme
More informationARCHIVED. Compliance Document for New Zealand Building Code Clause G4 Ventilation Second Edition. Prepared by the Department of Building and Housing
Compliance Document for New Zealand Building Code Clause G4 Ventilation Second Edition Prepared by the Department of Building and Housing This Compliance Document is prepared by the Department of Building
More informationSBI INFRA MANAGEMENT SOLUTIONS PVT. LTD.
SBI INFRA MANAGEMENT SOLUTIONS PVT. LTD. (A Wholly Owned Subsidiary of SBI) CIRCLE OFFICE: 4TH FLOOR, SBI LOCAL HEAD OFFICE III/1-PANDIT J N MARG, KHARAVELA NAGAR BHUBANESWAR, ODISHA-751001 Part-II PRICE
More informationFixed Electrical Instillation Inspection
Fixed Electrical Installation Inspection Fixed Electrical Instillation Inspection Client: Contact: Company Name Name Report No.: 001-01-12 Survey Date: 26 TH of January 2012 Contact: Liam Taylor Donal
More informationInstallation and Servicing Instructions. Alpha FlowSmart
Installation and Servicing Instructions Alpha FlowSmart Hot Water System incorporating an Alpha InTec 30/40GS Condensing Combination Boiler with Integrated Flue Gas Heat Recovery Device and wall mounted
More informationMini Tender Section 1.1 External Wall Insulation, Mechanical and Electrical Installation
Mini Tender Section 1.1 External Wall Insulation, Mechanical and Electrical Installation BOILER ONLY INSTALLATION ALL ITEMS BLEOW SHOULD BE INCLUDED WITHIN TENDER COST OR CONSIDER WITHIN BIDDERS SUBMISSION
More informationFire Risk Assessment Borough High Street
Fire Risk Assessment Borough High Street Page 1 of 8 / BHS Fire Risk Assessment / 07/2017 / V4.0 / ES Premises Details Occupier Premises Address Premises Description FIRE RISK ASSESSMENT Report of Audit
More informationELECTRICAL SAFETY INSPECTION REPORT
ELECTRICAL SAFETY INSPECTION REPORT SIDKO LIMITED PLOT NO. 36, ROAD NO. 46, GULSHAN NORTH C/A, DHAKA. Factory List: 1. N. A. Garments 2. 3. Sidko Apparels 4. Delta Ties Ltd. Inspected on April 17, 2014
More informationSteel, Civil, MEP & Telecommunication Infrastructure Service Providers MEP Profile
Steel, Civil, MEP & Telecommunication Infrastructure Service Providers MEP Profile 1 Gulf Turrets Presence BAHRAIN QATAR U.A.E. - Dubai U.A.E. - Abu Dhabi OMAN ISO 9001:2008 ISO 14001:2004 OHSAS 18001:2007
More informationMains Pressure Hot Water from an existing vented copper cylinder... Allows the cold water tank to be removed, freeing loft space.
DPS Hi-Flow Mains Pressure Hot Water from an existing vented copper cylinder... Converts an existing hot water cylinder to provide potable mains pressure hot water at high flow rates to all existing outlets.
More informationVerification Methods For New Zealand Building Code Clause G4 Ventilation
Acceptable Solutions and Prepared by the Ministry of Business, Innovation and Employment Verification Methods For New Zealand Building Code Clause G4 Ventilation G4 Status of Verification Methods and Acceptable
More informationARCHIVED. Compliance Document for New Zealand Building Code Clause G4 Ventilation Third Edition. Prepared by the Department of Building and Housing
Compliance Document for New Zealand Building Code Clause G4 Ventilation Third Edition Prepared by the Department of Building and Housing This Compliance Document is prepared by the Department of Building
More informationAndromeda. Product Manual. Copyright HS Europe Limited Printed in the UK
Andromeda Product Manual Copyright HS Europe Limited 2009 All rights reserved. No part of this document may be stored in a retrieval system, or transmitted in any form or by any means to persons not employed
More informationR E F E R E N C E S. (SUMMARY OF THE MAIN BUILDINGS WHERE COMPANY TERMOSISTEM Ltd. HAS PERFORMED HVAC WORKS IN THE LAST FEW YEARS)
R E F E R E N C E S (SUMMARY OF THE MAIN BUILDINGS WHERE COMPANY TERMOSISTEM Ltd. HAS PERFORMED HVAC WORKS IN THE LAST FEW YEARS) PROJECTS IN PROGRESS: 1. High class business object CAPITAL PLAZA - Podgorica
More informationExisting Conditions Assessment November 14, 2006 NORTH MIDDLESEX REGIONAL HIGH SCHOOL Townsend, MA L21366/ /Page 1
L21366/101 090 00.00/Page 1 HVAC EXECUTIVE SUMMARY The North Middlesex Regional High School has received average maintenance of the HVAC systems over its occupied years. Even with adequate maintenance,
More informationAssessment Schedule - TS.6
The Assessor shall determine the business s commitment and support to good and safe working practices; also that it has a positive culture in all aspects of its work. In particular, the assessor shall
More informationEnergy Efficiency Rating
Energy Performance Certificate Northern Ireland 49, Donard Avenue BANGOR BT20 3QD Date of assessment: 08 December 2017 Date of certificate: 08 December 2017 Reference number: 9663-0022-7739-7078-8902 Type
More informationThis manual must be kept with the appliance
This manual must be kept with the appliance October 2010 Part No E835 FASTflo Installation Design Guide Continuous Flow Wall Hung Balanced Flue Water Heaters for Natural Gas and Propane WH42, WH56, WHX56,
More informationWHHR Midi & Midi Lite
WHHR Midi & Midi Lite Residential Whole House Heat Recovery Units with Low Energy EC Motors Optional - Integral LCD Installation, Operating and Maintenance Instructions Image of model with LCD screen Page
More informationhxi High Efficiency Heating Only 24hxi hxi High Efficiency Heating Only 30hxi hxi High Efficiency Heating Only 38hxi
cxi sxi ranges product specifications Product Range Type Model 12 15 18 24 30 38 cxi Combi 24cxi cxi Combi 30cxi cxi Combi 38cxi sxi System 18sxi sxi System 30sxi ppearance esthetic Casing dimensions (h
More informationPassivhaus. sally godber MEng CEng MIMechE WARM: Low Energy Building Practice. The first 3 in the UK.
Passivhaus The first 3 in the UK sally godber MEng CEng MIMechE www.peterwarm.co.uk Intro to me/warm Mechanical Engineer Background in building services Set up WARM Jan 2009 Involved in 5 Passivhaus schools
More informationProposed Development at Likoni Road, Nairobi for NTSA - Electrical Installations Bills of Quantities. DESCRIPTION QTY UNIT RATE AMOUNT KSh. 28 No.
BILL 1 GROUND FLOOR Supply, Deliver, Install, Set to Work and Commission the Following: 1.01 Lighting point completely wired in 3x1.5mm² single core PVC insulated copper cables drawn in 20mm diameter HG
More informationAlpha FlowSmart 25 and 50
Installation and Servicing Instructions Alpha FlowSmart 25 and 50 Hot Water System incorporating a Flue Gas Heat Recovery Device, Primary Store and an Alpha CD Condensing Combination Boiler For Technical
More informationChapter One Commercial Kitchen Fires
Table of Contents Table of Contents Chapter One Commercial Kitchen Fires COMMERCIAL KITCHEN FIRES... 2 The Commercial Kitchen Fire Problem... 2 Unreported Fires... 2 Cooking By-Products... 3 Grease Accumulation
More informationCPC-180-ABNAB. 180 litres, 535mm x 1550mm high
6 8 9 10 1 3 7 2 4 11 13 17 5 28 21 20 19 18 30 Wiring Pandora Heat Bank. 100kW Plate Heat Exchanger with 22mm Thermostatic Mixing Valve. Indirectly Heated. Cylinder Thermostat. Manually Filled store -
More informationATMOSPHERIC GAS BOILER INSTALLATION, OPERATING AND MAINTENANCE MANUAL
STREBEL GENEVA CE ATMOSPHERIC GAS BOILER INSTALLATION, OPERATING AND MAINTENANCE MANUAL INDEX TABLE 1 TECHNICAL DATA SECTION 1 SECTION 2 SECTION 3 SECTION 4 SECTION 5 SECTION 6 SECTION 7 SECTION 8 SECTION
More informationPrimo Hotel. General. Indoor climate units for hotel rooms
Indoor climate units for hotel rooms General Primo Hotel indoor climate unit Ceiling-mounted indoor climate units for ventilation, cooling and heating High capacity; occupies little space Dry system without
More informationPROPOSED NEW BUILDING
HYDRAULIC DRAWINGS MATERIALS SERVICES TO BE CONSTRUCTED FROM MATERIAL AS LISTED BELOW UNLESS NOTED OTHER WISE SHOWN ON DRAWINGS. SERVICE MATERIAL REMARKS SEWER DRAINAGE upvc SOLVENT WELDED JOINTS SEWER
More informationInstructions for Robust Fiber Appendix 4 Robust sites and nodes. Ver 1.2
Instructions for Robust Fiber Appendix 4 Robust sites and nodes Ver 1.2 2 CONTENTS 1. Introduction 3 2. Sites and nodes 4 2.1 Classification of sites and nodes 4 2.2 Establishing sites and nodes 5 2.2.1
More informationFacility Condition Assessment Summary Report. British Columbia Institute of Technology NE6 - Plumbing and Pipefit Building
Facility Condition Assessment Summary Report British Columbia Institute of Technology NE6 - Plumbing and Pipefit Building Submitted by: VFA Canada Corp. Burnaby Centre 4211 Kingsway Burnaby, BC V5H 1Z6
More informationECP OPTICAL FIBRE SPLICING, TESTING AND COMMISSIONING REQUIREMENTS
Network(s): Summary: ENGINEERING COMMISSIONING PROCEDURE ECP 11-0009 OPTICAL FIBRE SPLICING, TESTING AND COMMISSIONING REQUIREMENTS EPN, LPN, SPN This standard details the requirements for the splicing,
More informationSECTION 1.02 DETAILED SCOPE OF WORK
SECTION 1.02 DETAILED SCOPE OF WORK 1.02.1 General 1.02.1.1 Introduction... 3 1.02.1.2 General description of the works... 4 1.02.1.3 Design criteria... 5 1.02.2 Public Health Services 1.02.2.1 Mains cold
More informationINSTALLATION AND SERVICING INSTRUCTIONS
9/4CBi, 4/9CBi, 9/4CBi WALL MOUNTED BOILERS FOR CENTRAL HEATING AND INDIRECT SUPPLY OF DOMESTIC HOT WATER INSTALLATION AND SERVICING INSTRUCTIONS Worcester supports the Benchmark code of practice This
More informationCommercial Kitchen Ventilation Services. Ventilation Systems. Canopies. Ductwork. Gas Interlock Systems
Commercial Kitchen Ventilation Services ACK offers a full range of commercial kitchen ventilation services including design and planning, manufacture, installation, maintenance and servicing as well as
More informationINTEGRA PLUS ABC. 230V~ 50Hz. Stock Ref. N. Installation and Wiring Instructions IPX2
INTEGRA PLUS Installation and Wiring Instructions Stock Ref. N INTEGRA PLUS 437666 230V~ 50Hz ABC PLEASE READ INSTRUCTIONS IN CONJUNCTION WITH ILLUSTRATIONS. PLEASE SAVE THESE INSTRUCTIONS. IPX2 VENT-AXIA
More informationBMS Commissionability Review. October Four Seasons Hotel Park Lane PROJECT:
BMS Commissionability Review October 2009 PROJECT: Four Seasons Hotel Park Lane Summary This report details our review of the BMS specification produced by i.d.a. Building Services Consulting Engineers,
More informationRoof: sound attenuation Category B. 4.0 DOORS
APPENDIX I DEFINITION OF LANDLORD BASE BUILD 1.1 PARTICULAR LANDLORD/TENANT WORKS - RETAIL LEASED AREAS S 1.0 WALLS 1.1 Internal skin of external wall. Fairfaced block work with rubbed joints. 1.2 To service
More informationAnnexure - D. Station Interface Matrix Power Supply, S&T, AFC,Lift & Escallators,Rolling stock and Track work. Station Civil and E & M Contractor
Item No A Item Description Power Supply contractor Connection between Secondary of Auxillary Transfomer and the LowVoltage Switch Board Station Interface Matrix Power Supply, S&T, AFC,Lift & Escallators,Rolling
More informationStandard Assessment Procedure Instantaneous Waste Water Heat Recovery Systems Design Checklist for 'System A' Installation Configuration
Design Checklist Version 11 27.06.12 Customer Details: Customer Name: Address: Telephone Number: Date of Installation: Name of Lead Contractor: Installer Name/Company: Project Reference Number: NCM (SAP)
More informationMID MICHIGAN COMMUNITY COLLEGE HARRISON CAMPUS Harrison, Michigan 2015 MASTER PLAN
MID MICHIGAN COMMUNITY COLLEGE HARRISON CAMPUS Harrison, Michigan 2015 MASTER PLAN September 30, 2015 PBA Project No. 2015.0140.00 PETER BASSO ASSOCIATES INC. CONSULTING ENGINEERS 5145 LIVERNOIS ROAD,
More informationHomepage > Products > Decentralised ventilation systems > Vertical units > Type FSL-V-ZAB/SEK FSL-V-ZAB/SEK
Homepage > Products > Decentralised ventilation systems > Vertical units > Type FSL-V-ZAB/SEK FSL-V-ZAB/SEK SUPPLY AND EXTRACT AIR UNIT WITH HEAT EXCHANGER AND HEAT RECOVERY, SECONDARY AIR OPTION, FOR
More informationGRP Ducting and Glass Tube Heat Exchanger Installation
2 GRP Ducting and Glass Tube Heat Exchanger Installation Don Valley Maltings Division Don Valley Engineering is the leading UK provider of Process Plant and Support to the Malting Industry, and the only
More informationLarch house and Lime house review of systems design and implementation
Larch house and Lime house review of systems design and implementation This report reviews the design of building services at Larch and Lime houses, Ebbw Vale, and the onsite systems assessment carried
More informationEfficiency Maximiser for Solid Fuel Central Heating
Efficiency Maximiser for Solid Fuel Central Heating INSTALLATION AND TECHNICAL MANUAL CONTENTS CONTENTS AND CAUTION 1 INTRODUCTION AND INSTRUCTIONS BEFORE LIGHTING BOILER STOVE 2 INSTALLATION INSTRUCTIONS
More informationSwegon CASA W130. Ventilation unit with counter-flow plate heat exchanger HOME VENTILATION
Swegon CASA W130 Ventilation unit with counter-flow plate heat exchanger Ventilation unit for residential houses under 250 m². The unit has counter-flow plate heat exchanger. Suitable also for renovation
More informationTighe&Bond. Groton Heights School Mechanical Evaluation. 1 Existing Conditions. 1.1 Water Service Entrance
Groton Heights School Mechanical Evaluation TO: FROM: Amy Vaillancourt, Project Manager Harley Langford, Project Manger Jason Curtis, P.E. DATE: February 24, 2016; Revised May 31, 2016 On Monday, December
More informationRADIANT PANELS COMMERCIAL BUILDINGS INNOVATIVE VENTILATION & HEATING
RADIANT PANELS COMMERCIAL BUILDINGS A guide to Radiant Panels, including our unique product range, consultancy service and accessories. INNOVATIVE VENTILATION & HEATING www.pricetwa.co.uk FLEXIBLE, INTEGRATED
More information5.5 CD/14 (Warning & Advice Notice)
5.5 CD/14 (Warning & Advice Notice) 5.5.1 General This form can be used to formally notify oil users and/or persons responsible for oil-fired equipment of potential and immediate risks associated with
More informationINSTALLATION DO S AND DON TS
4.0 NOISE CONTROL Figure 4.1. - Transitions Abrupt transitions immediately adjacent to an attenuator will cause the attenuator pressure drop to increase. Ensure transitions close to attenuators are gradual
More informationInstallation and Servicing Instructions. Alpha GasSaver GS-2
Installation and Servicing Instructions Alpha GS- Passive Flue Gas Heat Recovery Device (PFGHRD) for use with an Alpha Condensing Combination s IMPORTANT: Read these instructions BEFORE installing the
More informationVisitor & Intruder Security Policy
Visitor & Intruder Security Policy Reviewed: October 2019 GENERAL The Management responsibility for school security is shared between the local authority, Spie, the governing body and the Headteacher.
More informationMAXIMISER Semi-Storage Calorifiers
MAXIMISER Semi-Storage Calorifiers Introduction THE RYCROFT MAXIMISER HAS BEEN DEVELOPED TO MEET TODAY S NEED FOR A COMPACT CALORIFIER WHICH WILL RESPOND TO HIGH PEAK LOADS WITH MINIMAL DEMAND FOR BOILER
More informationGuide Spec Summary. Option List. Date: 05/21/2001. EarthWise VAV Terminal Units Full Spec. Prepared by: Phone Number: Prepared for:
Date: 05/21/2001 Time: 02:57:44 PM Job Name: EarthWise VAV Terminal Units Full Spec Location: AnyTown, Earth Prepared by: Phone Number: Prepared for: Guide Spec Summary Option List SINGLE & DUAL DUCT UNIT
More informationStandard Assessment Procedure Instantaneous Waste Water Heat Recovery Systems Design Checklist for Configurations A, B & C
Standard Assessment Procedure Instantaneous Waste Water Heat Recovery Systems Design Checklist for Configurations A, B & C Design Checklist Version 9 28.05.12 Customer Details: Customer Name: Address:
More informationRADIANT PANELS COMMERCIAL BUILDINGS INNOVATIVE VENTILATION & HEATING
RADIANT PANELS COMMERCIAL BUILDINGS A guide to Radiant Panels, including our unique product range, consultancy service and accessories. INNOVATIVE VENTILATION & HEATING www.pricetwa.co.uk FLEXIBLE, INTEGRATED
More informationMODEL ENGINEERING SPECIFICATION
MODEL ENGINEERING SPECIFICATION C04 Mechanical ventilation and air conditioning systems 1997 STATUS IN WALES ARCHIVED For queries on the status of this document contact info@whe.wales.nhs.uk or telephone
More informationInstallation instructions PYROMAT ECO. for contractors PYROMAT ECO GB 8/2012 Dispose after installation.
Installation instructions for contractors PYROMAT ECO PYROMAT ECO 8/2012 Dispose after installation. Safety instructions Please follow these safety instructions closely to prevent accidents and material
More informationInstallation and Servicing Instructions. Alpha GasSaver GS-1
Installation and Servicing Instructions Alpha GS-1 Passive Flue Gas Heat Recovery Device (PFGHRD) for use with an Alpha CD Condensing IMPORTANT: Read these instructions BEFORE installing the boiler For
More informationSECTION HEATING TERMINAL UNITS
SECTION 15830 HEATING TERMINAL UNITS PART 1 - GENERAL 1.01 SUMMARY A. Section Includes: 1. Baseboard or Fin-Tube Radiation. 2. Convectors. 3. Cabinet Unit Heaters. 4. Unit Heaters - Hot Water. 5. Hydronic
More informationabout your house Before You Start an Energy-Efficient Retrofit Mechanical Systems
about your house CE 28i Before You Start an Energy-Efficient Retrofit Mechanical Systems One of the best ways to make your home more comfortable, healthier and less expensive to operate is to upgrade the
More informationDocument Information Cover Sheet
Document Information Cover Sheet Asite/Document Reference Number: LOR-CO-SW-RP-0015 Document Title: Equipment Interface Document Revision: F02 Publisher: Laing O Rourke Published: 23/04/2013 Outline Description/Comments
More informationDACC Health Sciences Building Air Handler Assessment/Study
DACC Health Sciences Building Air Handler Assessment/Study NMSU Facilities and Services Department P.O. Box 30001 Las Cruces, NM 88003-8001 June 14, 2016 Final Submittal 1065 S. Main St., Bldg. D, Ste.
More informationDenco has been producing and installing. equipment specifically designed for the precise. control of air temperature, humidity and quality
Denco has been producing and installing equipment specifically designed for the precise control of air temperature, humidity and quality for 60 years. Today, clean rooms, telecommunications centres and
More information$ Each additional variance per petition. $ All Other Zoning Districts: One variance per petition
2015 SCHEDULE COMMUNITY DEVELOPMENT DEPT. ENGINEERING PLAN REVIEW Single Family New Construction All Other Plan Reviews Minimum Engineering Fee Planned Unit Development - PUD: Step #1: Step #2: See Site
More informationOVERVIEW and SYSTEM GUIDE. Swegon CASA. Residential ventilation for optimal operating economy and the greatest comfort.
OVERVIEW and SYSTEM GUIDE Swegon CASA Residential ventilation for optimal operating economy and the greatest comfort. www.swegon.com Swegon your system supplier Supply air diffuser Vapour barrier for duct
More information30C, 40C, 50C & 60C open flue gas fired boiler
30C, 40C, 50C & 60C open flue gas fired boiler FOR USE WITH NATURAL GAS (G20) ONLY Read these instructions thoroughly before working on the boiler. Leave the instructions adjacent to the gas meter. GENERAL
More information2006 Washington State Nonresidential Energy Code Compliance Form Washington State Nonresidential Energy Code Compliance Forms Revised July 2007
Mechanical Summary 2006 Washington State nresidential Energy Code Compliance Form MECH-SUM 2006 Washington State nresidential Energy Code Compliance Forms Revised July 2007 Project Info Project Address
More informationCBC - Active Chilled Beam. Halton CBC. Active Chilled Beam
Halton CBC Active Chilled Beam Combined cooling, heating, and supply air unit for flush installation within a suspended ceiling Well suited for spaces with high cooling loads and low humidity load Ideal
More informationUnvented Calorifier Range. Operating and Maintenance Manual. For Models & 500
Unvented Calorifier Range. Operating and Maintenance Manual. For Models 125 300 & 500 Telephone 08456 448802 Fax 08456 448803 Emial info@mhgheating.co.uk Web www.mhgheating.co.uk TABLE OF CONTENTS. Section
More information900 N. Via Piemonte Ontario, CA
2 3 L 8 5'-0" 6'-1" 5'-0" 4'-0" 2'-0" D.5 6" 9'-9" K 2 1 2 " 5'-0" 2'-0" 1'-2" 8" 4 4.3 7'-0" C.6 1'-8 1 2 " 7'-0" 8" 10'-6" 5'-0" 8" 6" 6'-6" 6'-3" PLUMBING SCOPE OF WORK - DRAINS 7'-3" 6'-8" KEC TO PROVIDE:
More information1. When using the COMcheck software, the compliance report submitted by the permit holder shall indicate that the applicable code is.
2018 NC Energy Conservation Code Commercial Mechanical Module 7 CHAPTER 5 [CE] WORKSHEET 1. When using the COMcheck software, the compliance report submitted by the permit holder shall indicate that the
More informationNewport County Council Bettws High School Electrical Particular Specification and Data Sheets. Contract
Electrical Particular Specification and Data Sheets Contract Electrical Particular Specification and Data Sheets August 2008 4 Pierhead Street, Capital Waterside, Cardiff CF10 4QP Tel +44 (0)29 2047 3727
More informationSECTION AIR DUCT ACCESSORIES
SECTION 23 33 00 AIR DUCT ACCESSORIES PART 1 - GENERAL 1.1 SUMMARY A. Section includes back-draft dampers, combination fire-and-smoke dampers, duct access doors, fire dampers, smoke dampers, volume control
More informationREPLACEMENT PARTS MANUAL
Date Issued Product Section Details Section No 1-Apr-09 H10.11 B5 High Efficiency Ducted Gas Central Heating Issue Status Page A Models: B5 15, 21, 21xa, 30, 30xa, 35 5120003 BV5 15I 15Kw Internal 5120013
More informationTEMPRA. Wall Mounted Fan Flue System boiler. Wall mounted fanned flue boiler INSTALLATION AND USE INSTRUCTIONS. Appr. nr. B A - CE 0063 AQ 2150
Wall Mounted Fan Flue System boiler Appr. nr. B 94.04 A - CE 0063 AQ 2150 Phone numbers: Installer Service Engineer Serial N Wall mounted fanned flue boiler INSTALLATION AND USE INSTRUCTIONS Please read
More informationDOCUMENT TABLE OF CONTENTS
DOCUMENT 00003 June 16, 2005 TABLE OF CONTENTS DOCUMENT NO. INTRODUCTORY INFORMATION DOCUMENT 00003 TABLE OF CONTENTS DIVISION 1 GENERAL REQUIREMENTS SECTION 01011 SECTION 01025 SSP21.1-1 SECTION 01026
More informationHigh Performance Building Guide 1
Description This Guide is intended to be used for projects with a Vermont Certified: High Performance energy efficiency goal. This High Performance goal is a whole-building efficiency approach rather than
More informationBrown University Revised June 29, 2012 Facilities Design & Construction Standards SECTION ELECTRICAL DESIGN CRITERIA
PART 1 - GENERAL 1.1 Background SECTION 26 00 10- ELECTRICAL DESIGN CRITERIA A. Brown University maintains it own campus electrical distribution system which serves the majority of the buildings and facilities
More informationAnnex 4a Common Minimum Technical Competency Requirements for Oil Appliance Installation Work (Domestic)
Annex 4a Oil Appliance installation (Domestic) Annex 4a Common Minimum Technical Competency Requirements for Oil Appliance Installation Work (Domestic) Route 1 Qualifications/Certification Level 3 NVQ
More informationWalkthrough Inspection Checklist
Walkthrough Inspection Checklist Name: School: Room or Area: Date Completed: Signature: Instructions 1. Read the IAQ Backgrounder and the Background Information for this checklist. 2. Keep the Background
More information