In compliance with Condition 6 of the Order, NGTL encloses for filing the Fifth Year Post-Construction Monitoring Program Report for the Project.

Size: px
Start display at page:

Download "In compliance with Condition 6 of the Order, NGTL encloses for filing the Fifth Year Post-Construction Monitoring Program Report for the Project."

Transcription

1 450 1 Street SW Calgary, Alberta T2P 5H1 Tel: (403) Fax: (403) dan_wyman@transcanada.com January 25, 2017 National Energy Board Suite 210, 517 Tenth Avenue SW Calgary, Alberta T2R 0A8 Filed Electronically Attention: Ms. Sheri Young, Secretary of the Board Dear Ms. Young: Re: NOVA Gas Transmission Ltd. (NGTL) Cutbank River Lateral Loop Bald Mountain Section (Project) Order XG-N (Order) Condition 6: Post-Construction Environmental Monitoring Report NEB File: OF-Fac-Gas-N In compliance with Condition 6 of the Order, NGTL encloses for filing the Fifth Year Post-Construction Monitoring Program Report for the Project. If the Board requires additional information with respect to this filing, please contact me at (403) or by at dan_wyman@transcanada.com. Yours truly, NOVA Gas Transmission Ltd. Original Signed By Daniel RK Wyman Regulatory Project Manager Regulatory, Canadian Gas Pipelines Enclosures

2 FIFTH YEAR POST-CONSTRUCTION MONITORING PROGRAM REPORT FOR THE NOVA GAS TRANSMISSION LTD. CUTBANK RIVER LATERAL LOOP (BALD MOUNTAIN SECTION) PIPELINE PROJECT January 2017 NOVA Gas Transmission Ltd. A Wholly Owned Subsidiary of TransCanada PipeLines Limited Calgary, Alberta

3 Cutbank River Lateral Loop (Bald Mountain Section) Pipeline Project TABLE OF CONTENTS 1.0 INTRODUCTION AND PROJECT DESCRIPTION Environmental Setting Construction Summary POST CONSTRUCTION RECLAMATION MONITORING (PCRM) PROGRAM PCRM Objectives Methodology Criteria for Success and Effectiveness of Construction Mitigation Measures PCRM Methodology for Monitoring RESULTS AND RECOMMENDATIONS First Year Post Construction Monitoring Summary (2012) Second Year Post Construction Monitoring Summary (2013) Third Year Post Construction Monitoring Summary (2014) Fourth Year Post Construction Monitoring Summary (2015) Fifth Year Post Construction Monitoring Summary (2016) PCRM Consultation PCRM Assessment and Reclamation Work PCRM Planned Activities CONCLUSION Project Team Contacts REFERENCES... 8 LIST OF APPENDICES Appendix A Appendix C Appendix D Figures Tables Photos Consultation Summary January 2017 Page i

4 Cutbank River Lateral Loop (Bald Mountain Section) Pipeline Project 1.0 INTRODUCTION AND PROJECT DESCRIPTION On December 20, 2010, NOVA Gas Transmission Ltd. (NGTL), a wholly owned subsidiary of TransCanada PipeLines Limited (TransCanada), received National Energy Board (NEB) approval, pursuant to Section 58 of the NEB Act XG-N (NEB 2010), for the construction and operation of the Cutbank River Lateral Loop (Bald Mountain Section) Pipeline Project (the Project). The Project is located in northwest Alberta, approximately 30 km southwest of Grande Prairie, Alberta. The Project consisted of the construction of approximately 38 km of new 610 mm O.D. (NPS 24) pipeline (Figure 1, Appendix A). The Project utilized a 25 m wide construction right-of-way (ROW), consisting of 12 m of existing right-of-way and 13 m of new permanent ROW when paralleling an existing ROW or 25 m of new permanent ROW when existing ROW was not available. Additional temporary workspace was utilized at select locations to accommodate construction activities (for example road crossings, pipeline and watercourse crossings, sharp sidebends, steep sidehills, log decking sites). The Project route is contiguous with existing linear disturbances (e.g., seismic lines, pipelines and roads) for approximately 32.8 km (88%) of its length. Construction began in January 2011 and was completed in April Final clean-up was completed in October NGTL has committed to a Post-Construction Monitoring (PCM) Program for the construction ROW during the first, third and fifth complete growing seasons following the commencement of operation of the Project. On or before 31 January after each of the first, third, and fifth complete growing seasons following the commencement of operation of the Project, NGTL shall file with the Board a post-construction environmental monitoring report that: a) describes the methodology used for monitoring, the criteria established for evaluating success and the results found; b) assesses the effectiveness of the mitigation measures applied during construction against the criteria for success; c) identifies any deviations from plans and alternate mitigation applied as approved by the Board; d) identifies locations on a map or diagram where corrective action was taken during construction and the current status of corrective actions; and e) provides proposed measures and the schedule NGTL shall implement to address any unresolved concerns. This report presents the results of the fifth year PCM program conducted in January 2017 Page 1

5 Cutbank River Lateral Loop (Bald Mountain Section) Pipeline Project 1.1 Environmental Setting The Project is located within the Crown-owned Green Area of Alberta within the Central Mixedwood Subregion and the Lower Foothills Subregion of Alberta (Natural Regions Committee 2006). The Project is located within the Regional Municipality of Greenview (Municipal District 16). The pipeline route crosses Bald Mountain Creek, a Class C watercourse, 12 unnamed tributaries to Bald Mountain Creek, 5 unnamed tributaries to Cutbank River and two wetlands. Key environmental issues identified in the Environmental and Socio- Economic Assessment (ESA) prepared for the Project include: issues relating to soil erosion control; potential effects on downstream water quality; potential introduction and spread of weeds; potential increase in the spread of bark beetles; incremental loss of remnant native vegetation; and potential effects on wildlife. 1.2 Construction Summary Construction activities were guided by the Project Environmental Protection Plan (EPP). Clearing activities began in January Merchantable timber was salvaged and non-merchantable timber was mulched and/or burned depending on timber densities. Immediately following clearing, grading activities commenced. Snow bridges were constructed to cross all watercourses along the route, with the exception of Bald Mountain Creek (SW W6M), which utilized a clear span bridge. Trenching was conducted from February to April The Contractor utilized a combination of track hoes and ditching wheels to excavate the trench line. All watercourse crossings were installed utilizing an isolated open cut or open cut methodology depending on the presence or absence of water. Immediately following the installation and backfilling of the trench at watercourse crossings, the banks were stabilized and reclaimed to pre-construction contours utilizing bioengineering techniques. Final tie-ins and rough clean-up occurred from March to mid-april The pipeline trench was crowned with material from the trench excavation to allow for settlement through spring Cross right-of-way drainages were installed at applicable locations, grade cuts were replaced, access was removed, and erosion and sedimentation control measures were installed in preparation for 2011 spring breakup. Due to the late start of the Project, a small portion of the right-of-way was unable to be fully cleaned up prior to the onset of spring conditions. This area was stabilized and the necessary erosion and sediment control structures were installed prior to spring break-up. In spring 2011, several inspections were conducted to monitor conditions on the ROW, ensuring erosion and sediment controls installed were functioning properly. During the second inspection in August 2011, following a 1:100-year rain event, January 2017 Page 2

6 Cutbank River Lateral Loop (Bald Mountain Section) Pipeline Project erosion was noted on the pipeline ROW at Bald Mountain Creek. Water levels rose above the south bank and removed m of cover from on top of the ROW. Bank stabilization techniques functioned as designed and maintained the integrity of the banks through this abnormal rainfall event. Following the rain event, in consultation with the regulating authorities, NGTL installed rock armouring along the north and south banks to prevent future scouring to protect the existing pipeline. Additional bioengineering techniques were employed on top of the south bank to facilitate accelerated vegetation establishment and prevent erosion. In August 2011, a ground inspection was conducted by NGTL to assist in the development of a plan for final clean-up. It was determined that the optimal timing for final clean-up to commence was in September A combination of widetracked equipment and snow cats were utilized to work the trench line. Soil material with uneven settlement over the trench line was redistributed and crowned. Cross ROW drainage was returned to pre-construction conditions, where necessary. Grade cut settlement was contoured and the necessary sedimentation and erosion controls were installed. Final clean-up was completed in October In spring and summer 2012, NGTL personnel continued to monitor conditions along the ROW to assess the effectiveness of the mitigation measures employed during the construction of the pipeline. s for remedial actions and monitoring were documented. 2.0 POST CONSTRUCTION RECLAMATION MONITORING (PCRM) PROGRAM NGTL implemented the Project specific PCRM program to address the recommendations of the First Year PCM Program Report. The PCRM program was implemented on the Project in 2013 and included an assessment of the ROW, the completion of minor reclamation activities, and a rare plant survey in August In 2016 the PCRM program built on the work completed in 2013 through to 2015, with additional ROW assessments and the completion of minor reclamation activities, and vegetation control. 2.1 PCRM Objectives The objectives of the PCRM program are to: assess the success of mitigation measures implemented during construction document opportunities for procedural learning s and improvement re-establish equivalent land capability (where applicable) January 2017 Page 3

7 Cutbank River Lateral Loop (Bald Mountain Section) Pipeline Project 2.2 Methodology Criteria for Success and Effectiveness of Construction Mitigation Measures Reclamation success and effectiveness of mitigation measures applied during construction are determined by comparing the construction ROW against the representative area adjacent to and off the construction ROW (control), and observing that the ROW is restored to a condition similar to the surrounding environment and consistent with the current land use. Where environmental issues are observed, corrective actions are planned and implemented in a timely manner and over subsequent reporting years until the environmental issue has been Ultimately, the criteria established for evaluating success and determining the effectiveness of mitigation practices used during pipeline construction is a reduction in the number of issues observed in subsequent monitoring years and maintaining a positive trajectory to re-establish equivalent land capability PCRM Methodology for Monitoring Preliminary Work Preliminary work includes a review of relevant project related information, including, but not limited to, alignment sheets and drawings, EPP, previous PCM reports, and previous assessments and recommendations Physical Environment Landscape Monitoring A landscape assessment of the construction ROW is performed to document evidence of the reclamation success. The landscape assessment consists of a visual evaluation of coarse fragments (stones, gravel, woody debris, etc.), contour restoration and drainage (maintaining natural drainage patterns), and microtopography (describing terrain instability, excessive crown height, subsidence, or erosion features) along the ROW. Where these issues are present and are a direct result of construction activities, the affected area is delineated along the length of the construction ROW Vegetation Monitoring Vegetation on the ROW is visually assessed for ground cover of desirable species by estimating the total percent of live cover compared to off ROW conditions. The occurrence and type of undesirable species (i.e., weeds) are assessed by estimating the percent cover using the same method. The pipeline ROW is inspected for other vegetation issues such as poor vegetation establishment. Vegetation parameters, based on land use and issue noted, assessed may include: bare soil exposure, visible erosion, surface litter, grazing pressure and plant vigour weed species and densities present January 2017 Page 4

8 Cutbank River Lateral Loop (Bald Mountain Section) Pipeline Project Watercourse Monitoring The banks and approach slopes of the watercourse crossings are monitored for environmental issues which could potentially affect fish or alter fish habitat. Issues monitored include bank stability, morphology, invasive species, revegetation success, soil erosion and sedimentation, as well as the effectiveness of post construction erosion and sediment control measures and in-channel flow Wetland Monitoring The first year PCM Report identified that the wetlands were experiencing slow regeneration of vegetation and continued monitoring was recommended. The wetlands were expected to return to their pre-construction functional condition given additional growing seasons. This assertion was confirmed by the observation of substantial improvements in vegetation growth during the second and third growing season assessments. Continued wetland monitoring is guided by the Project s wetland monitoring plan. Wetland monitoring conducted by the PCRM Program focuses on the continued recovery through a visual assessment of substrate function, hydrologic function, water quality, vegetation cover and composition, wildlife habitat, and overall wetland function Wildlife and Wildlife Habitat Monitoring The construction ROW is monitored for the restoration of wildlife habitat by monitoring for vegetation re-establishment. Methods for vegetation monitoring are outlined above. 3.0 RESULTS AND RECOMMENDATIONS 3.1 First Year Post Construction Monitoring Summary (2012) The First Year PCM Program field work was completed by Tera Environmental Consultants (TERA) on September 14, 2012 (wetland specialists) and September 29-30, 2012 (reclamation specialists). The first year report was submitted to the NEB prior to January 31, Overall the report indicated that the Project achieved a high standard of environmental protection. Issues were varied, but focused on poor vegetation establishment, presence of weeds, and minor subsidence. 3.2 Second Year Post Construction Monitoring Summary (2013) PCRM completed a ROW assessment on May 27 28, The assessment was completed to examine unresolved environmental construction issues identified in the first year report, assess the effectiveness of mitigation efforts, identify and assess any January 2017 Page 5

9 Cutbank River Lateral Loop (Bald Mountain Section) Pipeline Project new issues related to reclamation, and recommend reclamation measures to address outstanding environmental concerns. The primary issues noted during the assessments were minor subsidence, the presence of weeds, minor erosion, and reduced vegetation cover. Rare plant specialists completed a rare plant survey on the Project on August 8, Twelve rare plant sites were visited during the survey. Eleven of the sites were resolved by locating the rare plant in question on the ROW. One location was resolved, but the target species was not located, it was determined by the rare plant specialists during the site visit that the mitigation measures were successful because the habitat to support the rare plant was restored following construction. No further rare plant assessments are required for the Project. Details of these findings are present in Table 1 (). 3.3 Third Year Post Construction Monitoring Summary (2014) PCRM program completed a ROW assessment from June 11-20, The assessment was completed to follow-up on any unresolved environmental issues identified in the previous PCRM program assessments. In addition, the assessments are used to determine the effectiveness of mitigation efforts, identify new issues related to reclamation, and recommend measures to address outstanding environmental concerns. Overall the ROW recovery is on a trajectory to a regaining pre-disturbance condition. The vegetation was in excess of 90% cover (compared to adjacent land off ROW) on the majority of the ROW. Issues noted during the 2014 assessments were the presence of noxious weeds, minor subsidence, and erosion. 3.4 Fourth Year Post Construction Monitoring Summary (2015) PCRM completed the ROW assessment in the spring 2015 (May 31 June 5 and 9, 2015). The assessment was completed to examine unresolved environmental construction issues identified in the previous PCRM program assessments, assess the effectiveness of mitigation efforts, identify and assess any new issues related to reclamation, and recommend reclamation measures to address outstanding environmental concerns. Overall the ROW recovery is on a trajectory to a regaining pre-disturbance condition. The vegetation was in excess of 90-95% cover (compared to adjacent land off ROW) on the majority of the ROW. Issues noted during the 2015 assessments were the presence of noxious weeds, minor subsidence, and erosion. Construction of an adjacent NGTL pipeline was completed over the winter of , where the new pipeline ROW encroaches upon the existing Project ROW (affecting approximately half of the width of the ROW over the majority of the length from January 2017 Page 6

10 Cutbank River Lateral Loop (Bald Mountain Section) Pipeline Project KP to ). The newly disturbed portions of the Project s ROW will be monitored as a part of the new pipeline s PCM program. 3.5 Fifth Year Post Construction Monitoring Summary (2016) PCRM Consultation NGTL continues to work closely with stakeholders to identify and address any concerns regarding the Project. A summary of NGTL s engagement efforts can be found in Appendix D PCRM Assessment and Reclamation Work PCRM completed the initial ROW assessment in June The assessment was completed to examine unresolved environmental construction issues identified in the previous PCRM program assessments, assess the effectiveness of mitigation efforts, identify and assess any new issues related to reclamation, and recommend reclamation measures to address outstanding environmental concerns. Additional assessments and remediation work were completed on the ROW in July, August, and September Construction of an adjacent NGTL pipeline was completed over the winter of , where the new pipeline ROW encroaches upon the existing Project ROW (affecting approximately half of the width of the ROW over the majority of the length from KP to ; Photo 1, Appendix C). Final cleanup of the new pipeline is scheduled to take place over the winter. These recently disturbed portions of the ROW were not assessed and no remediation activities took place during the Project s 2016 PCRM program. The newly disturbed portions of the Project s ROW will be monitored as a part of the new pipeline s PCM program. Details of the ROW assessments, findings and work completed are provided in Table 1 (). All issues on the Project related to vegetation cover and composition, erosion, subsidence, ponding, drainage, and a substantial proportion of weed issues are resolved following the completion of the fifth year of the PCRM program (Photos 2 to 6, Appendix C provide an overview of the typical conditions present on the ROW). The two wetlands (KP to 4+150, Photo 7, Appendix C and KP to , Photo 8, Appendix C; assessed in accordance with the Project s Wetlands Post-Construction Monitoring Plan) were found to be functional and no further monitoring was recommended. Noxious weeds are the only remaining issue noted on the ROW. Noxious weeds are present on the Project s ROW following the fifth growing season. The weeds remaining on the ROW are primarily perennial sow thistle, Canada thistle, tall buttercup, and meadow hawkweed. Substantial progress has been achieved in the elimination of noxious weeds over areas of the ROW and great reductions in the January 2017 Page 7

11 Cutbank River Lateral Loop (Bald Mountain Section) Pipeline Project extent of the weeds (details provided in Table 1, ). In locations where noxious weeds are remaining, the Project ROW is located adjacent to parallel and perpendicular disturbances. Weed control within these disturbances is outside the control of the Project s PCRM program. The presence of these disturbances makes the complete elimination of noxious weeds on the Project ROW unlikely. As a result, there are no further plans to monitor or control weeds through this Project s PCRM program PCRM Planned Activities The Project will be transferred to the applicable TransCanada Regional Operations and the PCRM Program will have no further involvement on this Project. 4.0 CONCLUSION The results of the NGTL PCRM assessments indicate that a high level of environmental protection has been maintained throughout the Project. There is no further work by NGTL s PCRM program planned for the Project is the fifth growing season and this report is the final scheduled postconstruction environmental monitoring report for submission to the NEB, as described in the approval for the Project (XG-N (NEB 2010)). 4.1 Project Team Contacts The Project Team is comprised of company representatives who had a role performing work on the Project and may be contacted should issues or concerns arise. Contact information of Project Team members is provided below: PCRM Program Manager Phone Address Brett Schoneck (403) st Street SW Calgary, Alberta T2P 5H1 5.0 REFERENCES National Energy Board Order XG-N National Energy Board Act Natural Regions Committee Natural Regions and Subregions of Alberta. Compiled by D.J. Downing and W.W. Pettapiece. Government of Alberta. Pub. No. T/852. January 2017 Page 8

12 Cutbank River Lateral Loop (Bald Mountain Section) Pipeline Project Appendix A Figures January 2017

13 T.75 Be Ri v er Martin Lake 74 V U La Glace Lake V U 674 Sexsmith V U V U Jones Lake Horse Lakes I.R. 152B R.13 W6M T.75 ar 9 V U V U Bear Lake V U R.25 W5M V U Kamisak V U 670 Grande Prairie Wembley 722 n C r e ek Clairmont Lake Saskatoon Mountain Natural Area V U s ku 4 5 Beaverlodge Lake Kl e Ellenwood Lake V U Economy Lake KP 0.! 68 Sto 67 ny Cr 68 MUNICIPAL DISTRICT OF GREENVIEW NO. 16 e 67 Side Lake ek Pi n 66 to C r Sardine Lake 66 ee k 65 No. KP 38! se C re ek 64 C ut b k an Ri ver 64 Musreau Lake V U BRITIS H COLU MBIA 62 Fort St. John 65 Musreau Lake Provincial Recreation Area 63 ALBERTA 62 Peace River!! Dawson! Creek 61 L i Map Ar ea ck Cr e Prince e k!! Grande 11 Cache l to Quesnel! w Williams Lake C R.26 W5M T.59 ek kc r eek.! Kilometre Post (KP) Cutbank River Lateral Loop (Bald Mountain Section) V U re Ban Hinton nc re e! Ca t8597_overview_pcm_figure1_regional Rev0.mxd! Fox Creek k 13! Grande Prairie Bo George 61! Watercourse Populated Area Waterbody Park/Protected Area Indian Reserve Municipal Boundary FIGURE 1 REGIONAL LOCATION FIRST YEAR POST-CONSTRUCTION MONITORING PROGRAM FIFTH Highway Railway UTM Zone 11N KP, Pipeline Routing: Midwest Surveys Inc. 2010; Highway, Railway: Natural Resources Canada 2012; Hydrology: IHS Inc. 2004; Indian Reserve: Government of Canada 2012; Populated Area, Municipal Boundary: AltaLIS 2012; Park/Protected Area: Alberta Tourism, Parks and Recreation 2012; Hillshade: TERA Environmental Consultants Although there is no reason to believe that there are any errors associated with the data used to generate this product or in the product itself, users of these data are advised that errors in the data may be present. FOR THE NOVA GAS TRANSMISSION LTD. CUTBANK RIVER LATERAL LOOP (BALD MOUNTAIN SECTION) PIPELINE PROJECT SCALE: 1:750, km 20 (All s Approximate)

14 i PHYSIOGRAPHY SOILS WETLANDS WAPITI PLAINS SECTION OF THE SOUTHERN ALBERTA UPLANDS PHYSIOGRAPHIC REGION CENTRAL MIXEDWOOD NATURAL SUBREGION OF THE BOREAL FOREST NATURAL REGION WETLAND ENVIRONMENTAL SETTINGS DRAINAGES WATERCOURSE CROSSINGS FISH AND FISH HABITAT VEGETATION BALD MOUNTAIN CREEK (1-WC) WILDLIFE AND WILDLIFE HABITAT HERITAGE AND TRADITIONAL LAND USE CONSTRUCTION ALIGNMENT SHEET KP KP " X 17" MOSAIC SCALE 1:20,000 DATE OF PHOTOGRAPHY: 2009 No Sheet KP1 KP2 KP r k ee Ba ld M ou n ta i n C r e e k KP ML KP7 KP8 on C l s W MUNICIPAL AUTHORITY ALBERTA CROWN - M.D. OF GREENVIEW NO PCM PROGRAM (SEE NOTE 21) ENVIRONMENTAL PROTECTION TIMBER SALVAGE ENVIRONMENTAL ISSUES ENVIRONMENTAL PROTECTION MEASURES MERCHANTABLE ROLLBACK WETLAND BALD MOUNTAIN CREEK (1-WC) REVEGETATION Kilometre Post Proposed Pipeline Ditchline LEGEND Existing Pipeline Road SOURCE 2011 SPOT CNES, Licensed by BlackBridge Geomatics Corp, Proposed Pipeline Current to 13 September 2010; Hydrography: IHS Inc. 2004; Existing Pipelines: IHS Inc. 2013; Roads: IHS Inc REV. 0 DATE REVISIONS 1:20,000 NOVA GAS TRANSMISSION LTD. CUTBANK RIVER LATERAL LOOP (BALD MOUNTAIN SECTION) ENVIRONMENTAL ALIGNMENT SHEETS DATE REV. SHEET km (All s Approximate)

15 PHYSIOGRAPHY SOILS WETLANDS WAPITI PLAINS SECTION OF THE SOUTHERN ALBERTA UPLANDS PHYSIOGRAPHIC REGION CENTRAL MIXEDWOOD NATURAL SUBREGION OF THE BOREAL FOREST NATURAL REGION GRANDE CACHE BENCHLANDS SECTION OF THE SOUTHERN ALBERTA UPLANDS PHYSIOGRAPHIC REGION ENVIRONMENTAL SETTINGS DRAINAGES WATERCOURSE CROSSINGS FISH AND FISH HABITAT VEGETATION TRIB TO BALD MOUNTAIN CREEK (2-WC) TRIB TO BALD MOUNTAIN CREEK (3-WC) TRIB TO BALD MOUNTAIN CREEK (4-WC) TRIB TO BALD MOUNTAIN CREEK (5-WC) DRAINAGE (1-D) WILDLIFE AND WILDLIFE HABITAT HERITAGE AND TRADITIONAL LAND USE CONSTRUCTION ALIGNMENT SHEET " X 17" MOSAIC SCALE 1:20,000 DATE OF PHOTOGRAPHY: KP ML KP KP KP10 KP11 KP ML KP13 15 KP B a l d Mo u n t a i n C r eek MUNICIPAL AUTHORITY ALBERTA CROWN - M.D. OF GREENVIEW NO PCM PROGRAM (SEE NOTE 21) ENVIRONMENTAL PROTECTION TIMBER SALVAGE ENVIRONMENTAL ISSUES ENVIRONMENTAL PROTECTION MEASURES MERCHANTABLE ROLLBACK TRIB TO BALD MOUNTAIN CREEK (2-WC) TRIB TO BALD MOUNTAIN CREEK (3-WC) TRIB TO BALD MOUNTAIN CREEK (4-WC) TRIB TO BALD MOUNTAIN CREEK (5-WC) DRAINAGE REVEGETATION Kilometre Post Proposed Pipeline Ditchline LEGEND Existing Pipeline Road SOURCE 2011 SPOT CNES, Licensed by BlackBridge Geomatics Corp, Proposed Pipeline Current to 13 September 2010; Hydrography: IHS Inc. 2004; Existing Pipelines: IHS Inc. 2013; Roads: IHS Inc REV. 0 DATE REVISIONS 1:20,000 NOVA GAS TRANSMISSION LTD. CUTBANK RIVER LATERAL LOOP (BALD MOUNTAIN SECTION) ENVIRONMENTAL ALIGNMENT SHEETS DATE REV. SHEET km (All s Approximate)

16 PHYSIOGRAPHY SOILS WETLANDS CENTRAL MIXEDWOOD NATURAL SUBREGION OF THE BOREAL FOREST NATURAL REGION SEASONAL DRAINAGE GRANDE CACHE BENCHLANDS SECTION OF THE SOUTHERN ALBERTA UPLANDS PHYSIOGRAPHIC REGION LOWER FOOTHILLS NATURAL SUBREGION OF THE FOOTHILLS NATURAL REGION ENVIRONMENTAL SETTINGS DRAINAGES WATERCOURSE CROSSINGS FISH AND FISH HABITAT VEGETATION TRIB TO BALD MOUNTAIN CREEK (6-WC) TRIB TO BALD MOUNTAIN CREEK (8-WC) WILDLIFE AND WILDLIFE HABITAT HERITAGE AND TRADITIONAL LAND USE CONSTRUCTION ALIGNMENT SHEET " X 17" MOSAIC SCALE 1:20,000 DATE OF PHOTOGRAPHY: 2009 KP ML KP13 KP14 B a l d M o u n t ain C KP15 r e e k KP16 KP KP ML KP MUNICIPAL AUTHORITY ALBERTA CROWN - M.D. OF GREENVIEW NO PCM PROGRAM (SEE NOTE 21) ENVIRONMENTAL PROTECTION TIMBER SALVAGE ENVIRONMENTAL ISSUES ENVIRONMENTAL PROTECTION MEASURES MERCHANTABLE ROLLBACK TRIB TO BALD MOUNTAIN CREEK (6-WC) DRAINAGE TRIB TO BALD MOUNTAIN CREEK (8-WC) REVEGETATION Kilometre Post Proposed Pipeline Ditchline LEGEND Existing Pipeline Road SOURCE 2011 SPOT CNES, Licensed by BlackBridge Geomatics Corp, Proposed Pipeline Current to 13 September 2010; Hydrography: IHS Inc. 2004; Existing Pipelines: IHS Inc. 2013; Roads: IHS Inc REV. 0 DATE REVISIONS 1:20,000 NOVA GAS TRANSMISSION LTD. CUTBANK RIVER LATERAL LOOP (BALD MOUNTAIN SECTION) ENVIRONMENTAL ALIGNMENT SHEETS DATE REV. SHEET km (All s Approximate)

17 ENVIRONMENTAL SETTINGS PHYSIOGRAPHY SOILS WETLANDS DRAINAGES WATERCOURSE CROSSINGS FISH AND FISH HABITAT VEGETATION GRANDE CACHE BENCHLANDS SECTION OF THE SOUTHERN ALBERTA UPLANDS PHYSIOGRAPHIC REGION LOWER FOOTHILLS NATURAL SUBREGION OF THE FOOTHILLS NATURAL REGION SEASONAL DRAINAGE SEASONAL DRAINAGE SEASONAL DRAINAGE SEASONAL DRAINAGE SEASONAL DRAINAGE DRAINAGE (3-D) DRAINAGE (4-D) DRAINAGE (5-D) TRIB TO BALD MOUNTAIN CREEK (10-WC) TRIB TO BALD MOUNTAIN CREEK (12-WC) TRIB TO BALD MOUNTAIN CREEK (9-WC) TRIB TO BALD MOUNTAIN CREEK (11-WC) TRIB TO BALD MOUNTAIN CREEK (13-WC) WILDLIFE AND WILDLIFE HABITAT HERITAGE AND TRADITIONAL LAND USE CONSTRUCTION ALIGNMENT SHEET " X 17" MOSAIC SCALE 1:20,000 DATE OF PHOTOGRAPHY: ML KP KP21 KP22 KP23 KP ML KP25 KP26 o B a l d M C i n unt a r eek MUNICIPAL AUTHORITY ALBERTA CROWN - M.D. OF GREENVIEW NO PCM PROGRAM (SEE NOTE 21) ENVIRONMENTAL PROTECTION TIMBER SALVAGE ENVIRONMENTAL ISSUES ENVIRONMENTAL PROTECTION MEASURES MERCHANTABLE ROLLBACK TRIB TO BALD MOUNTAIN CREEK (9-WC) TRIB TO BALD MOUNTAIN CREEK (10-WC) TRIB TO BALD MOUNTAIN CREEK (11-WC) TRIB TO BALD MOUNTAIN CREEK (12-WC) TRIB TO BALD MOUNTAIN CREEK (13-WC) DRAINAGE DRAINAGE DRAINAGE REVEGETATION Kilometre Post Proposed Pipeline Ditchline LEGEND Existing Pipeline Road SOURCE 2011 SPOT CNES, Licensed by BlackBridge Geomatics Corp, Proposed Pipeline Current to 13 September 2010; Hydrography: IHS Inc. 2004; Existing Pipelines: IHS Inc. 2013; Roads: IHS Inc REV. 0 DATE REVISIONS 1:20,000 NOVA GAS TRANSMISSION LTD. CUTBANK RIVER LATERAL LOOP (BALD MOUNTAIN SECTION) ENVIRONMENTAL ALIGNMENT SHEETS DATE REV. SHEET km (All s Approximate)

18 PHYSIOGRAPHY SOILS WETLANDS LOWER FOOTHILLS NATURAL SUBREGION OF THE FOOTHILLS NATURAL REGION GRANDE CACHE BENCHLANDS SECTION OF THE SOUTHERN ALBERTA UPLANDS PHYSIOGRAPHIC REGION UPPER FOOTHILLS NATURAL SUBREGION OF THE FOOTHILLS NATURAL REGION SEASONAL DRAINAGE SEASONAL DRAINAGE SEASONAL DRAINAGE ENVIRONMENTAL SETTINGS DRAINAGES WATERCOURSE CROSSINGS FISH AND FISH HABITAT VEGETATION DRAINAGE (7-D) WILDLIFE AND WILDLIFE HABITAT HERITAGE AND TRADITIONAL LAND USE CONSTRUCTION ALIGNMENT SHEET KP32 11" X 17" MOSAIC SCALE 1:20,000 DATE OF PHOTOGRAPHY: 2009 KP30 KP ML KP ML KP25 KP26 KP27 33 KP KP MUNICIPAL AUTHORITY ALBERTA CROWN - M.D. OF GREENVIEW NO PCM PROGRAM (SEE NOTE 21) ENVIRONMENTAL PROTECTION TIMBER SALVAGE ENVIRONMENTAL ISSUES ENVIRONMENTAL PROTECTION MEASURES MERCHANTABLE ROLLBACK DRAINAGE DRAINAGE REVEGETATION Kilometre Post Proposed Pipeline Ditchline LEGEND Existing Pipeline Road SOURCE 2011 SPOT CNES, Licensed by BlackBridge Geomatics Corp, Proposed Pipeline Current to 13 September 2010; Hydrography: IHS Inc. 2004; Existing Pipelines: IHS Inc. 2013; Roads: IHS Inc REV. 0 DATE REVISIONS 1:20,000 NOVA GAS TRANSMISSION LTD. CUTBANK RIVER LATERAL LOOP (BALD MOUNTAIN SECTION) ENVIRONMENTAL ALIGNMENT SHEETS DATE REV. SHEET km (All s Approximate)

19 GRANDE CACHE BENCHLANDS SECTION OF THE SOUTHERN ALBERTA UPLANDS PHYSIOGRAPHIC REGION PHYSIOGRAPHY UPPER FOOTHILLS NATURAL SUBREGION OF THE FOOTHILLS NATURAL REGION LOWER FOOTHILLS NATURAL SUBREGION OF THE FOOTHILLS NATURAL REGION SOILS WETLANDS SEASONAL DRAINAGE WETLAND ENVIRONMENTAL SETTINGS DRAINAGES WATERCOURSE CROSSINGS FISH AND FISH HABITAT VEGETATION DRAINAGE (8-D) DRAINAGE (9-D) TRIB TO CUTBANK RIVER (14-WC) TRIB TO CUTBANK RIVER (16-WC) TRIB TO CUTBANK RIVER (18-WC) TRIB TO CUTBANK RIVER (15-WC) TRIB TO CUTBANK RIVER (17-WC) WILDLIFE AND WILDLIFE HABITAT HERITAGE AND TRADITIONAL LAND USE CONSTRUCTION ALIGNMENT SHEET KP33 KP34 KP " X 17" MOSAIC SCALE 1:20,000 DATE OF PHOTOGRAPHY: 2009 KP32 KP36 KP KP ML No Sheet MUNICIPAL AUTHORITY ALBERTA CROWN - M.D. OF GREENVIEW NO PCM PROGRAM (SEE NOTE 21) ENVIRONMENTAL PROTECTION TIMBER SALVAGE ENVIRONMENTAL ISSUES ENVIRONMENTAL PROTECTION MEASURES MERCHANTABLE ROLLBACK DRAINAGE TRIB TO CUTBANK RIVER (14-WC) TRIB TO CUTBANK RIVER (15-WC) TRIB TO CUTBANK RIVER (16-WC) TRIB TO CUTBANK RIVER (17-WC) TRIB TO CUTBANK RIVER (18-WC) WETLAND REVEGETATION Kilometre Post Proposed Pipeline Ditchline LEGEND Existing Pipeline Road SOURCE 2011 SPOT CNES, Licensed by BlackBridge Geomatics Corp, Proposed Pipeline Current to 13 September 2010; Hydrography: IHS Inc. 2004; Existing Pipelines: IHS Inc. 2013; Roads: IHS Inc REV. 0 DATE REVISIONS 1:20,000 NOVA GAS TRANSMISSION LTD. CUTBANK RIVER LATERAL LOOP (BALD MOUNTAIN SECTION) ENVIRONMENTAL ALIGNMENT SHEETS DATE REV. SHEET km (All s Approximate)

20 Cutbank River Lateral Loop (Bald Mountain Section) Pipeline Project PCRM Site Assessment and Recommendation Table January 2017

21 Table 1: Detailed PCRM Site Assessment and Recommendations NW Treed None. June 11, 2014: Vegetation establishment 90-95% comparable to off ROW for majority of tract. High abundance of Meadow Brome along ROW within tract. Depression evident near valve site, may be associated with foreign pipeline crossing. Continue to monitor later in Abundance of amphibians present within tract. - No contouring issues evident within tract. - No subsidence issues evident within tract. June 23, KP to was sprayed with herbicide to control Canada thistle and perennial sow thistle. July 22, 2014: a hydro vac slot trench remains on adjacent pipeline ROW on the north side of existing header requires filling in a small patch of perennial sow thistle remaining at the south end of tract that was not identified at time of herbicide application Broadleaf vegetation within areas of herbicide application exhibit significant wilting, thorough affects within areas treated. Grasses do not indicate stressing. July 28, 2014: Previously identified hydro vac slot trench at North end of tract was filled. Issue Previously identified perennial sow thistle at KP and KP were controlled mechanically. NE Treed None. June 11, 2014: Vegetation establishment 90-95% compared to off ROW control. Few areas along ROW consisting of lesser vegetation cover (75%) comparable to off ROW control. Various weeds present along ROW (Dandelion, Horsetail, Vetch & Bluebell) but comparable to off ROW control. No contouring issues evident within tract. - No subsidence issued evident within tract - No further issues to report at this time. June 23, 2014 herbicide application conducted from KP and to control Canada thistle and perennial sow thistle July 22, broadleaf vegetation within areas of herbicide application exhibit significant wilting. Grasses do not indicate stressing. May 31, 2015 Vegetation is comparable to off ROW control. Sow thistle and tall buttercup were observed, implementation of control measures recommended. July 9, 2015 intermittent herbicide application conducted to control perennial sow thistle, tall buttercup and Canada thistle from KP to August 16, 2015 Perennial sow thistle was mechanically controlled adjacent to cross drain. August 31, 2015: Previous herbicide application throughout this tract appears successful. Visible signs of health degradation were noted in target species. Perennial sow thistle was observed on ditch line at KP and Fall herbicide spot spray application is recommended. September 22, 2015 Intermittent herbicide application conducted to control perennial sow thistle. May 31, 2015: Vegetation is comparable to off ROW. Sow thistle was observed, implementation of control measures recommended. July 9, 2015 intermittent herbicide application conducted to control perennial sow thistle and Canada thistle from KP to August 31, 2015 Previous herbicide application throughout this tract appears successful. Visible signs of health degradation were noted in target species. June 8, 2016: Good establishment of brome and American vetch as well as shrubs and willows. Vegetation is consistent with off right of way. 7 perennial sow thistle plants were identified along ditchline at KP Contours along pipeline right of way are consistent with off right of way land use. Depression at valve site, noted in 2014, no longer evident, issue July 4, 2016 Noxious weeds were not identified in this tract. August 13, 2016: One small patch of Canada Thistle was observed at KP Herbicide application conducted. Intermittent perennial sow thistle patches were observed throughout, herbicide application was conducted to control. Tall buttercup no longer present on ROW, issue Although still present, substantial progress in the control of Canada thistle was noted with a reduction from 150 m area (2015) to one small patch at KP in June 8, 2016: Good establishment of brome and American vetch as well as willows. Vegetation is consistent with off right of way issue with areas of reduced vegetation cover is perennial sow thistle was identified throughout the entire tract in small intermittent patches along ditchline. July 4, 2016 intermittent herbicide application conducted to control perennial sow thistle. August 13, 2016: Several patches of Canada thistle were observed in the area. Herbicide application conducted. Intermittent perennial sow thistle patches were observed throughout, herbicide application was conducted to control. Although still present, substantial progress in the control of Canada thistle was noted with a reduction from 100 m area (2015) to several patches at KP in January 2017 Page 1

22 SE Treed None. June 11, 2014: Vegetation establishment 70% comparable to off ROW control. Few areas along ROW consisting of poor vegetation cover (50%) comparable to off ROW control with 60% weeds. Small patch of Canada thistle and perennial sow thistle present within tract. Recommend spot spraying. Cross drainages along ROW functioning well at this time but show some seasonal ponding. Continue to monitor later in Erosion present along ROW near foreign access road from KP to KP Implement erosion control. No contouring issues evident within tract. - No subsidence issues evident within tract. June 23-24, 2014 herbicide application conducted between KP and to control Canada thistle and perennial sow thistle. July 11, 2013 Installed 10 straw waddle erosion prevention breakers at KP to Re-contoured eroded area and filled with material on ROW. July 22, 2014 broadleaf vegetation within areas of herbicide application exhibit significant wilting. Grasses do not indicate stressing. July 28, 2014 Previously identified perennial sow thistle at KP was controlled mechanically. September 18, 2014 herbicide application conducted to control Canada thistle. NE Treed Monitor weeds in 2013 and, if warranted, implement weed control measures. KP One scentless chamomile plant found and picked. Monitor area. A new lease access road across the ROW has been built since the spring assessment at KP on the east side of the ROW. June 11, 2014: Vegetation establishment 90-95% comparable to off ROW control. No weed issues evident within tract at this time; Annual weeds (Dandelion, Horse Tail) present but comparable to off ROW control. New lease road at KP No issues evident from implementation of new lease road at this time. Erosion within drainage of diversion berm present at KP Repairs recommended. Good vegetation establishment 85-90% at foreign pipeline crossing KP No erosion or subsidence noted near crossing. - No contour issues evident within tract. June 24, 2014 Herbicide application conducted between KP and to control Canada thistle and perennial sow thistle. July 22, 2014 KP 1+495, 1+815,and small patches of perennial sow thistle exist, not identified at time May 31, 2015: Vegetation is comparable to off ROW control. Cross drainages are functioning and well vegetated but straw wattles installed last year are no longer effective, repairs are required. Sow thistle was observed. Herbicide application recommended. July 9, 2015 intermittent herbicide application conducted to control perennial sow thistle and Canada thistle from KP to August 16, 2015 Six half and one full-length straw wattles were installed along erosion at KP August 31, 2015: Previous herbicide application throughout this tract appears successful. Visible signs of health degradation were noted in target species Perennial sow thistle was observed on ditch line at KP 0+275, 0+425, and Fall herbicide spot spray application is recommended. September 22, 2015 Intermittent herbicide application conducted to control perennial sow thistle and Canada thistle. May 31, 2015: Vegetation is comparable to off ROW control. Cross drainages are functional and well vegetated. There are depressions on ditch line that could result in ponding at 0+840, 0+880, and 1+200, continue to monitor. Tall buttercup and sow thistle were observed, mitigation measures recommended. July 9, 2015 intermittent herbicide application conducted to control perennial sow thistle, tall buttercup and Canada thistle from KP to August 31, 2015: Previous herbicide application throughout this tract appears successful. Visible signs of health degradation were noted in target species. Perennial sow thistle was observed on ditch line at KP 1+495, (on east side of ROW), and intermittently at to Canada thistle was observed on west June 8, 2016: Good establishment of brome and American vetch as well as shrubs, willows, black poplar, rose bushes, raspberry bushes. Vegetation is consistent with off right of way issues with vegetation cover and composition are Recent NGTL pipeline construction has disturbed the majority of the east portion of the right of way, from the ditchline to the east right of way boundary. This disturbed area will be monitored as a part of that pipeline s PCM program. One Canada Thistle plant was identified on ditchline at KP Canada thistle plants were identified along ditchline at KP July 4, 2016: herbicide application conducted to control Canada thistle at KP and No signs of erosion were identified, previous erosion issue at KP (2015) and KP to (2014) are no longer evident, issues Issues with cross drainages noted in 2014 and 2015 are no longer evident, issues August 13, 2016: Several patches of Canada thistle were observed. Herbicide application conducted. Intermittent perennial sow thistle patches were observed throughout herbicide application was conducted to control. Although still present, substantial progress in the control of Canada thistle and perennial sow thistle was observed. Affected area of Canada thistle reduced from 400 m (2014) down to a few patches and reduced density of perennial sow thistle over time was noted. June 8, 2016: Good establishment of vegetation- grasses, clover, vetch. Cross drains well vegetated and functioning. Depressions on ditch line that could result in ponding at 0+840, 0+880, and noted in 2015, were not identified as impeding the recovery of the ROW, therefore the issues are erosion at KP (2014) is no longer evident, issue Perennial sow thistle noted sporadically at KP to end of ¼. Mainly on ditchline and East side of ROW. Canada thistle (3 plants) observed just South of Road crossing at KP July 4, 2016 intermittent herbicide application conducted to control perennial sow thistle from KP to end of ¼ and Canada thistle at KP August 13, 2016: January 2017 Page 2

23 SE Treed Monitor vegetation growth in of herbicide application - broadleaf vegetation within areas of herbicide application exhibit significant wilting. Grasses do not indicate stressing. July 28, 2014 Previously sprayed herbicide applied intermittently throughout this tract appears successful. Broad leafed species showing signs of health degradation in the form of wilting and discoloration. Grasses mainly unaffected. Mechanical weed control completed at KP (C.thistle), and 1+440, 1+495, 1+885, and (p. sow thistle) June 11, 2014: Vegetation establishment 90-95% comparable to off ROW control. Previously stripped areas for construction show poor vegetation establishment compared to off ROW control (65-70%). Few bare areas present along ROW. Few areas with an accumulation of woody debris present along ROW. Perennial sow thistle present within tract. Recommend spot spraying. KP to KP exhibits poor drainage across ROW indicated by cattails and standing water on west side of ditchline as opposed to east side of ditchline. This may attribute to previously assessed lack of vegetation (2013). Implementation of improved cross drainage across ROW would likely remediate issue. Ephemeral draw on ROW shows ponding water at this time. Ephemeral draw is not noted on construction alignment sheets but could be attributed to the identified dugout. The dugout was identified in satellite imagery to be pre-existing to construction. Good aquatic habitat structure present within drainage. Amphibian presence is abundant. June 12, Dug two cross drains with at KP and KP at poor drainage area between work and spoil side on ROW. June 24, 2014 Herbicide application conducted between KP and to control Canada thistle and perennial sow thistle. July 22, 2014: KP a small patch of perennial sow thistle exists along ditchline, not identified at time of herbicide application cross drains implemented at KP and on June 12, 2014 have accommodated drainage of ponding water appropriately water levels have completely subsided, issue KP a considerable amount of perennial sow thistle existing on both sides of identified water body, within 30m recommend mechanical removal of noxious weeds Broadleaf vegetation within areas of herbicide application exhibit significant wilting, thorough affects within areas treated. Grasses indicate slight stressing within areas of broad herbicide application. side of ROW at KP and on ditch line at Fall herbicide spot spray application is recommended. September 22, 2015 Intermittent herbicide application conducted to control perennial sow thistle and Canada thistle. May 31, 2015: 90-95% vegetation establishment compared to off-row control. Bare patches of soil present along ditchline. Perennial sow thistle located along east side of ditchline at KP and Recommend herbicide application to mitigate weed establishment. July 9, Intermittent herbicide application conducted to control perennial sow thistle from KP to August 21, 2015 Conducted mechanical weed control for perennial sow thistle on several discrete areas between KP and August 31, 2015: Previous herbicide application throughout this tract appears successful. Visible signs of health degradation were noted in target species Perennial sow thistle was observed intermittently on ditch line at KP to 2+350, and at Fall herbicide spot spray application is recommended. September 22, 2015 Intermittent herbicide application conducted to control perennial sow thistle. Several patches of Canada thistle and intermittent perennial sow thistle were observed from KP to Herbicide application conducted to control. Scentless chamomile noted on ROW in 2012 and 2013, no longer present, issue Although still present, substantial progress in the control of Canada thistle was observed. Affected area of Canada thistle reduced from 700 m (2014) down to several patches in June 8, 2016: Good establishment of vegetation- grasses, clover, vetch. Similar weeds to off ROW. Patches of reduced vegetation noted in 2012, 2014, and 2015, no longer reported, issues Cross drains well vegetated and functioning. Perennial Sow thistle noted throughout tract. Mainly on ditchline and East side of ROW. July 7, 2016 intermittent herbicide application conducted to control perennial sow thistle. August 13, 2016 Intermittent perennial sow thistle observed. Herbicide application conducted to control. January 2017 Page 3

24 NE Treed Repair subsidence and monitor in NE to SW Treed Bog Monitor wetland in Leave for natural recovery. July 28, 2014 Previously identified Perennial Sow thistle at KP 2+115, 2+380, 2+420, 2+620, and was controlled mechanically. KP Wetland Muskeg wetland appears to have been ramped. Regeneration of natives is excellent. Black spruce, Labrador Tea, Bog Berry, and moss are recovering very well. Removed silt fence along the Cutbank Section June 11, 2014: 90% vegetation cover to off ROW. Bare spots on ditch line with 50% vegetation cover compared to off ROW control. KP 3+050, Excessive wood debris. Continue to monitor vegetation. KP 3+200, South side of access road has excessive weeds, mainly dandelion. KP KP 3+750, several depressions on ditch line, possibly screw anchor bell holes. June 11, 2014: Wetland muskeg appears to have been ramped on work side of ROW. There is no mulch present. Regeneration of native plant and tree species is excellent on work side. Moss is also recovering very well. Vegetation on ramped portion (work side) of ROW differs from spoil side. The different access methods (freeze down and ramping) are very evident through wetland portion. Ramping seems to have been very affective. Vegetation looks good on spoil side but natives don t seem to be as successful on spoil side of ROW. Minor rutting in wetland portion likely from recreational quad use. May 31, 2015: 90-95% vegetation establishment compared to off-row control. Bare patches of soil present along ditchline. Depressions along each side of ditchline at KP and KP are well vegetated, issue No noxious weeds observed within tract during assessment. August 31, 2015 Canada thistle was observed on ditch line at KP Fall herbicide spot spray application is recommended. September 21, 2015 Intermittent herbicide application conducted to control Canada thistle at KP May 31, 2015: Treed fen is functional and well vegetated with no mulch present. Black Spruce and Tamarack seedlings 15-40cm tall are establishing along ROW. Labrador Tea present within Treed Fen. No noxious weeds observed within tract during assessment. June 11, 2016: Vegetation is comparable to off ROW. Vetch, grasses, clover. Patches of reduced vegetation noted in 2014 (related to woody debris at KP 3+050) and in 2015, no longer reported, issues Cross drains functioning effectively. Small patch of Perennial Sow thistle observed at KP July 7, 2016 herbicide application conducted to control perennial sow thistle at KP August 13, 2016: Intermittent perennial sow thistle observed throughout 1/4. Herbicide application conducted to control. Canada thistle no longer present in 2016, issue Subsidence noted in 2012 (KP 3+500, 3+630, and 3+680) and screw anchor depressions noted in 2014 (KP ), are no longer noted and have not impeded the recovery of the ROW, therefore those issues are considered June 11, 2016 Treed fen is functional and well vegetated, vegetation cover issues noted in 2012 is resolved, with no mulch present. Adjacent construction has disturbed the east side of ROW within wetland. Black Spruce and Tamarack are established along ROW.- Labrador Tea present within Treed Fen. August 13, 2016 No noxious weeds were observed in the wetland. September 13, 2016 The early seral stage vegetative growth (e.g. tamarack, black spruce, willow, sphagnum moss, sedges, common cattails, reeds, bog birch, Labrador tea) is well established throughout the length of the ROW in the wetland. The slightly mounded roach has provided a good growing site for the infilling of vegetation (e.g., tamarack >150cm). There is no evidence of cross drainage hydrology issues. There has been some minor influence (ponded water) on the recovery trajectory with the recent construction of an adjacent pipeline in 2015/16. The area has had high precipitation during the summer of The wetland is functional and no further monitoring recommended. January 2017 Page 4

25 SW Treed None. June 11, 2014: % vegetation cover compared to off ROW control. Cross-drains in ¼ functioning well. June 24, 2014 Herbicide application conducted between KP and to control Canada thistle and perennial sow thistle. Bald Mountain Creek (WC1) Monitor in 2013 and, if warranted, reseed. KP Bald Mountain creek looks good. Appears to be geotechnically stable. No erosion issues noted. Banks are regenerating with native species. Some plantings are surviving but not doing any better than the natives. Removed silt fence along the Cutbank section. June 11, 2014: Erosion rill on south side of creek on edge of ditch line (KP 4+580), repairs recommended. Coir lifts are stable on banks and willow chutes are growing nicely. Moderate vegetation above south bank of creek. Continue to monitor. Removed silt fence on north side of creek. Removed steel anchor pins from straw waddles July 8, 2014 Erosion repairs completed at KP Recontoured eroded area and filled with material on ROW. July 22, 2014 KP south side of Bald Mountain Creek - ~1/4 of a large garbage bag of perennial sow thistle was handpicked. NW Treed None. June 11, 2014: Vegetation in ¼ is comparable to off ROW % vegetation coverage to off ROW. No issues with subsidence or erosion in ¼. June 24, 2014 herbicide application conducted between KP and to control Canada thistle and perennial sow thistle. July 22, broadleaf vegetation within areas of herbicide application exhibit significant wilting. Grasses do not indicate stressing. May 31, 2015: approx 95% vegetation establishment compared to off- ROW control Cross drains located within tract are functional and well vegetated. August 31, 2015 A patch of Perennial Sow thistle located at KP Recommend fall herbicide application. September 21, 2015 herbicide application completed at KP to control perennial sow thistle. May 31, 2015: Diversion berms located on north and south slopes of Cutbank Mountain Creek are functional and well vegetated. Silt fence and sand bags installed at the top of the north slope of the creek were removed for disposal. TCPL pipeline sign missing from north slope, marker posts are present. Coir lifts are stable on banks and willow chutes are growing. Moderate vegetation growth along right bank of creek. erosion repaired KP no longer evident, issue This is likely the same erosion noted in 2012, therefore that issue is also August 16, 2015 Large patch of Canada thistle located on the north bank of Water Crossing (KP 4+500) and within 30m of the water, was mechanically controlled. August 21, 2015 Conducted mechanical weed control for perennial sow thistle on north bank of water crossing located at KP May 31, 2015: Vegetation is comparable to off ROW % coverage as opposed to off ROW control. No issues with subsidence or erosion in this tract. No Noxious weeds were identified in this tract. August 31, 2015 Noxious weeds were not observed. June 8, 2016; Good establishment of brome and American vetch, as well as tamarack, willows and birch establishing along ditchline and west side of ROW. Recent NGTL pipeline construction has disturbed the majority of the east portion of the right of way, from the ditchline to the east right of way boundary. This disturbed area will be monitored as a part of that pipeline s PCM program. August 13, 2016 No noxious weeds observed. Issues with perennial sow thistle and Canada thistle June 8, 2016: Pipeline marker sign has been installed - issue Diversion berms on south facing slope, on north side of watercourse crossing well vegetated and stable. Additional silt fencing installed due to recent, adjacent pipeline construction. Recent rains have increased flow within watercourse considerably. Coir lifts remain stable, no erosion evident. Emerging willow chutes evident between coir lifts. A considerable amount of perennial sow thistle was identified along the north bank of the watercourse, on and off right of way. June 13, 2016: south side of watercourse bank and coir lifts remain stable, willows emerging along bank. Vegetation establishing well, vegetation consistent with off right of way, previous vegetation cover issues noted in 2012 and 2014 are July 7, 2016: herbicide application conducted (spot spraying) to control perennial sow thistle. Canada thistle no longer present at KP 4+500, issue June 13, 2016: Vegetation establishing well, vegetation consistent with off right of way. Good establishment of brome, American vetch and willows. One patch of perennial sow thistle identified at July 7, 2016 herbicide application conducted (spot spraying) to control perennial sow thistle at KP August 13, 2016: No noxious weeds observed. Canada thistle no longer present, issue Perennial sow thistle reduced from affecting 275 meters to 1 patch at KP January 2017 Page 5

26 NE Treed None. June 12, 2014: Vegetation establishment 90-95% comparable to off ROW for majority of tract - excessive Horsetail dominance on ditchline compared to on ROW Areas of sparse vegetation cover (60-65%) compared to off ROW control. Continue to monitor. No issues with contouring, erosion or subsidence within tract. June 24, 2014 herbicide application conducted between KP and to control Canada thistle and perennial sow thistle. July 22, 2014: KP and KP weeds identified, Canada thistle and perennial sow thistle Broadleaf vegetation within areas of herbicide application exhibit significant wilting, thorough affects within areas treated. Grasses do not indicate stressing. July 29, 2014 Previously identified Canada thistle at KP 5+065, 5+200, and were controlled mechanically. September 18, 2014 intermittent herbicide application conducted to control Canada thistle. SE Treed None. June 12, 2014: Vegetation establishment 80-85% comparable to off ROW control with excessive Horsetail dominance Several sections along ROW with woody debris present. Good vegetation establishment proliferating around areas. No issues with contouring, erosion or subsidence. June 24, 2014 herbicide application conducted between KP and to control Canada thistle and perennial sow thistle. July 22, 2014 broadleaf vegetation within areas of herbicide application exhibit significant wilting. Grasses do not indicate stressing. SW Treed None. June 12, % vegetation cover to off ROW. Willows re-establishing well on ROW 1m 1.5m tall. No issues with subsidence or erosion in this ¼. June 24, 2014 herbicide application conducted between KP and to control Canada thistle and perennial sow thistle. May 31, 2015: Vegetation establishment 90-95% comparable to off ROW control for majority of tract - excessive Horsetail dominance on ditchline. Areas of sparse vegetation no longer noted, issue No issues with contouring, erosion or subsidence within tract. No Noxious weeds were identified on this tract. August 31, 2015 A patch of Perennial Sow thistle located at KP and Recommend fall herbicide application. September 21, 2015 Intermittent herbicide application conducted to control perennial sow thistle. May 31, 2015: Vegetation establishment ~90% comparable to off ROW control with excessive Horsetail dominance as assessed previous years. Some sections along ROW with woody debris present, not inhibiting the recovery of the ROW as there is good vegetation establishment around areas. No contour, erosion or subsidence issues within tract. KP Perennial sow thistle identified in a small isolated patch. Recommend herbicide application. July 9, 2015 Intermittent herbicide application conducted to control perennial sow thistle from KP to August 31, 2015 Previous herbicide application throughout this tract appears successful. Visible signs of health degradation were noted in target species. May 31, 2015: % vegetation cover to off ROW control No contour, erosion or subsidence issues within tract. August 31, 2015 Patches of perennial sow thistle were identified from KP and Recommend fall herbicide application. June 13, 2016: Good establishment of brome, American vetch, willows and aspen; consistent with off right of way. One patch of Perennial sow thistle identified at July 7, 2016: herbicide application conducted (spot spraying) to control perennial sow thistle at KP Recent NGTL pipeline construction has disturbed the majority of the south portion of the right of way. This disturbed area will be monitored as a part of that pipeline s PCM program. August 13, 2016: Intermittent perennial sow thistle observed from KP to Herbicide application conducted to control. Canada thistle no longer present, issue June 13, 2016: Recent NGTL pipeline construction has disturbed the majority of the east portion of the right of way. This disturbed area will be monitored as a part of that pipeline s PCM program. Good establishment of brome, American vetch and willows comparable to off right of way. Previous dominance of horsetail, no longer noted, issue A patch of Perennial sow thistle was identified at KP and KP Canada thistle located at KP July 7, 2016 herbicide application conducted (spot spraying) to control perennial sow thistle at KP and KP and Canada thistle at KP August 13, 2016: Intermittent meadow hawkweed and perennial sow thistle observed throughout ¼. Several patches of Canada thistle. Herbicide application (spot spraying) conducted to control. Although still present, substantial progress in controlling Canada thistle, which was reduced from affecting 600 meter to several patches at the end of June 13, 2016: Vegetation is well established and comparable to off ROW. Vetch, grasses, clover, willows and shrubs are present. Recent NGTL pipeline construction has disturbed the majority of the east portion of the right of way. This disturbed area will be monitored as a part of January 2017 Page 6

27 NW Treed Monitor vegetation growth in 2013 and, if warranted, redistribute woody debris. July 22, 2014 KP a small patch of perennial sow thistle exists along ditchline, not identified at time of herbicide application - broadleaf vegetation within areas of herbicide application exhibit significant wilting. Grasses do not indicate stressing. July 29, 2014 perennial sow thistle identified at KP 6+300, controlled mechanically June 12, 2014: % vegetation cover compared to off ROW control. Some small areas of moderate vegetation on ditch line - 70% vegetation cover. Continue to monitor. Poor vegetation establishment (woody debris) in previous assessments are re-vegetating but are still a little behind other areas of ROW. KP 6+900, Erosion rill along east side of ditch line. Recommend re-contouring and installing cross drain to drain water into existing bar ditch paralleling road on west side of ROW. KP 6+930, isolated patch of perennial sow thistle. Recommend spot spraying with chemical herbicide. KP 7+110, new foreign pipeline recently installed crossing line. Area of crossing is in need of some clean up by foreign company. Ramped crossing is still in place and there is significant subsidence above TCPL line about 30-40cm deep and water has pooled in the subsidence. Cross drains on south side of Weyerhaeuser road are functioning well. June 24, 2014 herbicide application conducted between KP and to control Canada thistle and perennial sow thistle July 13, 2014 erosion control materials installed at previously noted erosion within tract at KP to KP Deep rivets from erosion were also filled in with soil and re-contoured appropriately. July 22, 2014: KP 6+850, 6+920, 7+290, and small patches of perennial sow thistle exist, not identified at time of herbicide application. Broadleaf vegetation within areas of herbicide application exhibit significant wilting. Grasses do not indicate stressing. KP recent foreign pipeline crossing activity has not been cleaned up. July 29, Previously identified perennial sow thistle at 6+850, 6+920, 7+290, and was controlled mechanically. September 18, 2014 intermittent herbicide application conducted to control Canada Thistle. September 21, 2015 Intermittent herbicide application conducted to control perennial sow thistle from KP to June 1, 2015: Vegetation is 90% comparable to off ROW control. There s a corduroyed access across the ditch line at Perennial sow thistle was observed from to Recommend weed control measures. Erosion was noted following ditch line from to Previously mitigated with straw wattles but they are no longer effective. There is third party disturbance at Organic soil has been stockpiled on the ROW and there is a rig mat with ponding water sitting on ditch line. June 18, 2015 KP 7+110; Issue previously reported in 2014 and 2015 assessments of matting left and mounding of soil is from 2 separate occasions one in 13/14 winter and one in 14/15 winter (confirmed with region) and are anticipated to be cleaned up this year. July 9, 2015 Intermittent herbicide application to control perennial sow thistle and Canada thistle from KP to August 21, 2015 Installed four wattles for erosion control from KP to The remaining length was well vegetated. August 31, 2015 Previous herbicide application throughout this tract appears successful. Visible signs of health degradation were noted in target species. that pipeline s PCM program. Perennial sow thistle observed at KP and to end of ¼. July 7, 2016 herbicide application conducted (spot spraying) to control perennial sow thistle at KP and KP to end of ¼. August 13, 2016 Intermittent perennial sow thistle observed throughout ¼. Herbicide application (spot spraying) conducted to control. June 13, 2016: Vegetation is well established and comparable to off ROW. Vetch, grasses, clover, willows and shrubs are present. Vegetation issue noted in 2012 no longer evident, issue Coarse fragments (woody debris) noted in 2012 no longer evident and did not impede the recovery of the ROW, issue Perennial Sow thistle intermittent throughout tract. Recommend herbicide application. July 13, 2016: herbicide application conducted (spot spraying) to control perennial sow thistle throughout ¼. Previously repaired erosion at KP to (noted as KP in 2014) has established vegetation and erosion breakers functioning effectively, issue 3rd party disturbance at KP (2014 and 2015) and (2015), no longer evident, issues Cross drains functioning. August 13, 2016 Intermittent perennial sow thistle observed throughout ¼. Herbicide application (spot spraying) conducted to control. January 2017 Page 7

28 SW Treed Monitor vegetation growth in 2013 and, if warranted, redistribute woody debris. Tributary to Bald Mountain Creek (WC2) None. KP Removed silt fencing June 13, 2014: % vegetation cover to off ROW. Areas of woody debris mentioned in previous assessments has moderate vegetation growth compared to off ROW control, however vegetation is establishing well. No weeds noted at time of assessment. KP 7+600, depression off ditch line causing water to pool. KP 8+000, minor erosion rill near cross drain, however rill is vegetating. Continue to monitor. KP 8+010, ponding on both sides of ditch line at cross drain. Cross drain needs to be dug down and possibly extended to bar ditch on parallel gravel road. June 13, 2014: Good vegetation on left and right banks. Water is ponding on ditch line. There is also ponding up stream due to beaver dams. There is some erosion coming off the parallel road into the watercourse. Not on ROW, therefore not an issue for the recovery of the ROW. SE Treed None. June 13, 2014: % vegetation cover compared to off ROW control. Willows are growing well on ROW, m tall. KP 8+275, Subsidence on spoil side of roach, minor issue that is not impacting recovery of ROW at this time, continue to monitor. No weeds noted at time of assessment. NE Treed None. June 13, 2014: Slumping along West side of ditch line, not impacting recovery of ROW, monitor Multiple drainage ditches functioning effectively throughout tract. Erosion noted on South edge of road crossing on ditch line. Scentless Chamomile was identified at South end of tract. 1 garbage bag full of the weed was picked and bagged. June 24, 2014 herbicide application conducted between KP and to control Canada thistle, perennial sow thistle, and scentless chamomile. July 22, 2014: Previously sprayed herbicide applied intermittently throughout this tract appears successful. Broad leafed species showing signs of health degradation in the form June1, 2015 Vegetation is % comparable to off of ROW control. Deciduous species are well established on the ROW. There s a corduroyed access across the ditch line at There is ponding west of ditch line at 7+600, 7+800, and 7+980, continue to monitor. KP erosion, continue to monitor. August 17, 2015: Drainage entering unnamed Creek from the road from the North causing erosion to the west of ditchline, not impacting the ROW. On ditchline cobble remains in bed of WC, excellent vegetation establishment on either bank with no signs of erosion or slumping. August 21, 2015 Probed the ditch line to ensure that the road runoff has not removed depth of cover. No refusal was encountered - depth of cover remains intact to at least 1.5mbgs, indicating pipe integrity is intact, issue June 1, 2015: Vegetation is 95% comparable to off of ROW control. No signs of subsidence or erosion. Subsidence noted in 2014 at KP 8+275, no longer evident, issue There is lathe present on the ROW as a result of recent work adjacent to the ROW, remove in September 21, 2015 Removed lathe from ROW. June 1, 2015: Vegetation is 95% comparable to off of ROW control. No signs of subsidence or erosion. Slumping and erosion noted in 2014, no longer evident, issue There is lathe present on the ROW as a result of recent work adjacent to the ROW, remove in September 21, 2015 Removed lathe from ROW. June 13, 2016: Vegetation is well established and comparable to off ROW. Vetch, grasses, clover, willows and shrubs are present. Vegetation issue noted in 2012 no longer evident issue Coarse fragments (woody debris) noted in 2012 and 2014 no longer evident and did not impede the recovery of the ROW, issue Erosion (KP and 8+000), depression/ponding (KP 7+600, 7+800, 7+980, and 8+010), and cross drain (KP 8+010) issues are no longer evident, areas are fully vegetated, issues are August 13, 2016 meadow hawkweed patches were observed from KP to Intermittent perennial sow thistle patches were observed from KP to Herbicide application (spot spraying) conducted to control. June 13, 2016 Banks are stable and well vegetated. No erosion noted. Previous ponding (2014), no longer evident, and erosion noted (2014) is well vegetated, issues June 13, 2016: Vegetation is well established and comparable to off ROW. Vetch, grasses, clover, willows and shrubs are present. Cross drains functioning effectively August 13, No noxious weeds observed. June 13, 2016: Vegetation is well established and comparable to off ROW. Vetch, grasses, clover, willows and shrubs are present. Perennial Sow thistle at KP 8+880, recommend herbicide application. Scentless Chamomile picked and bagged at KP Emerging smaller plants noted. Recommend herbicide application. July 13, 2016 herbicide application conducted (spot spraying) to control perennial sow thistle at KP and scentless chamomile at KP August 14, 2016: No noxious weeds observed. Canada thistle no longer present, issue Although still present, substantial progress was January 2017 Page 8

29 Tributary to Bald Mountain Creek (WC3) SE Treed Monitor vegetation growth in Tributary to Bald Mountain Creek (WC4) None. KP Removed silt fencing None. KP Minor subsidence - not a concern at this time, monitor in KP Removed silt fencing of wilting and discoloration. Grasses mainly unaffected. Scentless Chamomile at KP to Previous remedial efforts did not achieve desired control. Spraying or hand picking is recommended. July 28, 2014 scentless chamomile was handpicked and bagged for disposal within an area previously handpicked, but not previously sprayed. Approximately 1.5 large garbage bags were picked from location. herbicide application conducted between KP and to control scentless chamomile. June 13, 2014 Erosion material is exposed. Good vegetation establishing on banks, 95% compared to off ROW. Some ponding water may be attributed to beaver activity and/or culvert blockage. No erosion or subsidence noted. June 14, 2014: Intermittent drain, ponding water. No flow, good vegetation throughout drainage. Majority of ROW consists of 90-95% vegetation of control. Woody debris is causing some thinner vegetated patches along ROW, ~60% vegetation cover compared to control. Cross drains functioning well and vegetation establishing. June 24, 2014 intermittent herbicide application conducted between KP and to control Canada thistle, perennial sow thistle, and scentless chamomile. July 22, 2014 Previously sprayed herbicide applied intermittently throughout this tract appears successful. Broad leafed species within areas sprayed showing signs of health degradation in the form of wilting and discoloration. Grasses mainly unaffected. September 18, 2014 intermittent herbicide application conducted to control Canada thistle. June 14, 2014: Intermittent watercourse vegetation establishing 60% vegetation as opposed to off ROW. Grasses establishing. Minor slumping North/Right bank ditch line shows some cracking - Synthetic erosion material is exposed. Erosion influenced by area of thin vegetation towards East boundary on work side of ditch line, monitor. June 1, 2015: Vegetation is 95% comparable to off ROW control. Banks are well vegetated, defined and stable. Nearby road ditch run off into the creek is eroding. Recommend continued monitoring. June 1, 2015: 90-95% vegetation establishment compared to off- ROW. Intermittent bare patches of soil present along ROW. Cross drains are functional and well vegetated. No noxious weeds observed within tract during assessment. September 21, 2015 Removed lathe from ROW. June 1, 2015 Creek banks at WC4 are stable and in good condition at time of assessment. Previously noted subsidence (KP in 2013 and north/right bank in 2014) and erosion (east boundary in 2014), no longer evident, issues achieved in the control of scentless chamomile (reduced from 200 m in 2014 to one location in 2016) and perennial sow thistle (reduced from 900 m in 2014 to one location in 2016). June 13, 2016: Banks are stable and well vegetated. Previous erosion noted is well vegetated and no longer an issue. Drainage tie in from road ditch is steep in sections and flows onto and across ROW. Is not a pipe integrity or concern. Issue No marker posts present on (WC3), recommend installation. September 13, 2016 Signs and marker post installed at W3, issue resolved June 13, 2016: Excellent vegetation established and comparable to off ROW. Vetch, grasses, clover, willows and shrubs are present. Intermittent bare patches, no longer noted, issue Vegetation cover issue noted in 2012 is Cross drains are functioning effectively. August 14, 2016: Intermittent meadow hawkweed patches were observed from KP to 9+600, Canada thistle from KP to and perennial sow thistle patches were observed throughout ¼.. Herbicide application conducted to control. A very small patch of Scentless chamomile was observed at KP Chamomile was handpicked and bagged for disposal. June 13, 2016: Banks are stable and well vegetated. Coir banks are stable, excellent willow and shrub establishment. No marker posts present on (WC4), recommend installation. September 13, 2016 Installed signs and posts at WC4, issue January 2017 Page 9

30 NE Treed Monitor vegetation growth in SE Treed Monitor vegetation growth in Tributary to Bald Mountain Creek (WC5) KP Sparse Vegetation - Appears to be an area that was disturbed during final clean-up. Vegetation has improved from previous site visit continue to monitor. KP Sparse Vegetation - Appears to be an area that was disturbed during final clean-up. Vegetation has improved from previous site visit continue to monitor. None. KP Removed silt fencing. June 14, 2014: Vegetation on North half of tract 80-90% compared to control off ROW. KP , woody debris within vicinity of workspace has reduced vegetation cover, monitor in Cross drains functioning well and vegetation establishing to (Southern half) remains as previously assessed ~50-60% as opposed to off ROW consisting mainly of clover and weeds. erosion rills across ROW in Southern portion in thinly vegetated areas. Monitor in July 12, 2014 Straw waddle erosion control material was implemented within rill erosion on low-angle hill slope. Rill erosion was filled in with soil to an extent to help prevent further erosion. September 18, 2014 intermittent herbicide application conducted control Canada thistle. June 14, 2014: Vegetation comparable to off ROW, ~90% throughout tract. Cross drains show some standing water, but are functioning and vegetation is establishing. Canada thistle noted, isolated small patch KP Cross drain functioning but is lower on work side of ditch line developing ponding water. Clean out recommended. KP June 25, 2014 herbicide application conducted between KP and to control Canada thistle and perennial sow thistle. July 22, Previously sprayed herbicide applied intermittently throughout this tract appears successful. Broad leafed species showing signs of health degradation in the form of wilting and discoloration. Grasses mainly unaffected. July 29, Previously identified Canada thistle at KP was controlled mechanically. September 18, 2014 intermittent herbicide application conducted to control Canada Thistle. June 1, 2015: 90% vegetation establishment compared to off-row. Intermittent bare patches of soil present along ROW. Areas of heavy mulch present. No noxious weeds observed within tract during assessment. September 21, 2015 Removed lathe from ROW left from adjacent work earlier in June 1, 2015: 90% vegetation establishment compared to off-row. Intermittent bare patches of soil present along ROW. Cross drains are functional and well vegetated. No noxious weeds observed within tract during assessment. September 21, 2015: Removed lathe from ROW left from adjacent work earlier in Cross drain issue at KP is no longer evident, issue No concerns noted. June 1, 2015: Creek banks at WC5 are stable and in good condition at time of assessment. Bank erosion has occurred downstream (west), off ROW between ROW and road culvert, likely during spring runoff. June 13, 2016: Good establishment of brome, American vetch and willows comparable to off ROW. Previously assessed bare areas and heavy mulch locations are establishing suitable vegetation issue Vegetation issues noted in 2012, 2013, and 2014 (including vegetation composition issue noted from KP to ) are Erosion repair completed in 2014 is no longer evident, issue A patch of perennial sow thistle was identified at KP July 13, 2016 herbicide application conducted (spot spraying) to control perennial sow thistle at KP August 14, 2016: No noxious weeds observed. Canada thistle no longer present on ROW, issue June 22, 2016: Vegetation establishing well, vegetation consistent with off right of way. Good establishment of willow, aspen and shrubs. Bare patches are no longer evident, issues Vegetation issues noted in 2012 and 2013 are One patch of perennial sow thistle identified at KP July 13, herbicide application conducted (spot spraying) to control perennial sow thistle at KP August 14, 2016: No noxious weeds observed. Canada thistle no longer present on ROW, issue Although still present, perennial sow thistle aerial extent had been greatly reduced from approximately 800 m in 2014 to one patch at KP in June 22, 2016 Unnamed Tributary to Bald Mountain Creek banks are stable and well vegetated. Minimal flow is observed at this time. Previously reported erosion is establishing good vegetation, minimal depression, consistent with adjacent land use. Issue January 2017 Page 10

31 NE Treed None. June 14, 2014: Moderate vegetation influenced by excessive woody debris along ditch line KP ~90% vegetation cover, with some thinner areas observed. Good establishment of willows and deciduous trees. - perennial sow thistle noted Cross drains functioning well with vegetation establishing. At South end of tract cross drains exhibiting flow. KP , Ponding water on ditch line and East side of ROW. Erosion control material evident on bottom of drainage. June 25, 2014 intermittent herbicide application conducted between KP and to control Canada thistle and perennial sow thistle. July 22, 2014: Previously sprayed herbicide applied intermittently throughout this tract appears successful. Broad leafed species showing signs of health degradation in the form of wilting and discoloration. Grasses mainly unaffected. perennial sow thistle identified at KP July 29, 2014 Perennial sow thistle at KP was controlled mechanically. Drainage (D1) None. KP Removed silt fencing. June 14, 2014 Unnamed Creek minor slumping, along East and West side of ditch line on Left bank South side of Creek, monitor. SE Treed None. June 14, 2014: Perennial sow thistle noted on North end of Tract Cross drains functioning well with vegetation establishing. Vegetation at 90% compared to off ROW. June 25, 2014 intermittent herbicide application conducted between KP and to control Canada thistle and perennial sow thistle. July 22, 2014: Previously sprayed herbicide applied intermittently throughout this tract appears successful. Broad leafed species showing signs of health degradation in the form of wilting and discoloration. Perennial sow thistle identified at KP on ditchline, not previously sprayed. July 29, 2014 Perennial Sow Thistle at KP was controlled mechanically. September 18, 2014 intermittent herbicide application conducted to control Canada thistle. June 1, 2015: 90% vegetation establishment compared to off-row. Intermittent bare patches of soil present along ROW. Cross drains are functional and well vegetated. No noxious weeds observed within tract during assessment. September 21, 2015 Removed lathe from ROW left from adjacent work earlier in No issues noted. June 2, 2015: 90% vegetation establishment compared to off-row control. Cross drains are functioning and well vegetated. No Noxious weeds observed within tract during assessment. September 21, 2015 Removed lathe from ROW left from adjacent work earlier in June 22, 2016: Vegetation establishing well, vegetation consistent with off ROW. Good establishment of willow, aspen, shrubs, grasses and American vetch. Vegetation issue noted in 2014 at KP and intermittent bare and reduced vegetation patches noted in 2014 and 2015 are no longer evident, issues Ponding water and erosion noted in 2014 at KP are no longer evident, issues One patch of perennial sow thistle identified at KP July 13, 2016 herbicide application conducted (spot spraying) to control perennial sow thistle at KP August 14, 2016: Perennial sow thistle patches were observed from KP to Herbicide applied to control. Canada thistle no longer present, issue Although still present, perennial sow thistle extent has been reduced from approximately 750 m in 2014 to 100 m in June 13, 2016 Drainage is well vegetated, no issues noted, slumping noted in 2014 has stabilized and has not hindered the recovery of the ROW, issue June 22, 2016: Vegetation establishing well, vegetation consistent with off ROW. Good establishment of American vetch, grasses, willows and shrubs. Slopes are well vegetated and stable; no erosion issues. August 14, 2016: No noxious weeds observed. Perennial sow thistle and Canada thistle are no longer present, issues January 2017 Page 11

32 SW Treed None. June 14, 2014: ~90% vegetation established along ROW, compared to off ROW control establishing willow species present across entire ROW within portions of tract- cross drains functioning well and are well vegetated. On sections of this ¼, an excessive amount of woody debris along spoil side of ROW appears to be impacting vegetation establishment. There has been an improvement since 2013 and this should be monitored in 2015 NW Treed Monitor vegetation growth in Tributary to Bald Mountain Creek (WC6) SW Treed Monitor vegetation growth in KP Very good regeneration of woody species, infilling on ditchline. None. KP and KP Removed silt fencing. June 14, 2014: 90-95% vegetation established, good establishment of willow and deciduous species across ROW. cross drains and diversion berms functioning well, vegetated well Canada thistle identified. Other non-noxious weeds were noted on this ¼ in comparable densities to off ROW, no work required on these weeds. June 25, 2014 intermittent herbicide application conducted between KP and to control Canada thistle and perennial sow thistle. July 22, 2014: Previously sprayed herbicide applied intermittently throughout this tract appears successful. Broad leafed species showing signs of health degradation in the form of wilting and discoloration. Grasses mainly unaffected. Perennial sow thistle identified at KP and on ditchline and work side, not previously sprayed. July 29, 2014 Perennial sow thistle at KP and was controlled mechanically. September 18, 2014 intermittent herbicide application conducted to control Canada Thistle. June 14, 2014 vegetation well established, banks stable at this time, watercourse exhibiting flow at this time. North bank exhibits emerging water along ditchline mid-way up bank. Steel anchor pins removed from straw waddle along spoil side of ROW. June 15, 2014: North end of tract 95% compared to off ROW control. Deciduous species establishing well along ROW. South portion of tract exhibiting moderate vegetation establishment, may be attributed to poor soil conditions or woody debris: Cross drains and diversion berms functioning well with vegetation establishing. Perennial Sow thistle noted, June 25, 2014 intermittent herbicide application conducted between KP and to control Canada thistle June 2, 2015: 90% vegetation establishment compared to off-row control. Cross drains are functioning and well vegetated. No noxious weeds observed within tract during assessment. September 21, 2015 Removed lathe from ROW left from adjacent work earlier in June 2, 2015: 90% vegetation establishment compared to off-row. Cross drains and diversion berms within tract are functioning and well vegetated. 3 Scentless Chamomile plants observed and removed along ditchline at KP July 10, 2015 intermittent herbicide application conducted to control perennial sow thistle and Canada thistle from KP to September 21, 2015 Intermittent herbicide application conducted to control perennial sow thistle. June 2, 2015: WC6 banks are stable and well vegetated at this time. Right (north) of WC6 has subsurface water welling up along bank, has not caused any erosion, issue June 2, 2015: 95% vegetation establishment compared to off-row. Ponded water located on ROW at KP Perennial sow thistle plants observed along ditchline at KP Recommend herbicide application to mitigate. July 10, 2015 Intermittent herbicide application conducted to control perennial sow thistle from KP to June 22, 2016: Vegetation establishing well, vegetation consistent with off ROW. Good establishment of grasses, clover, willows, aspen and shrubs. Reduced vegetation associated with woody debris along spoil side noted in 2014 is no longer evident, issue Recent NGTL pipeline construction has disturbed the majority of the east portion of the right of way. This disturbed area will be monitored as a part of that pipeline s PCM program. Slopes are well vegetated and stable; no erosion issues. August 14, 2016 No noxious weeds were observed. June 22, 2016: Vegetation establishing well, vegetation consistent with off ROW. Good establishment of grasses, willows and shrubs. Vegetation issue noted in 2012, no longer present, issue Recent NGTL pipeline construction has disturbed the majority of the east portion of the right of way. This disturbed area will be monitored as a part of that pipeline s PCM program. Slopes and diversion berms are well vegetated and stable; no erosion issues. August 14, 2016 Intermittent perennial sow thistle individuals were observed throughout ¼, Several patches of Canada thistle observed. Herbicide applied to control. June 22, Unnamed Tributary to Bald Mountain Creek banks are stable and well vegetated. Moderate flow is observed at this time. June 22, 2016: Vegetation is well established with desirable species throughout ROW. South portion of ¼ no longer noted to have reduced vegetation cover (noted in 2014), issue Vegetation issue noted in 2012, no longer present, issue Willows, bushes and saplings are encroaching well onto west side of ROW. No erosion or subsidence issues. Ponding noted at KP in 2015 is no longer evident, issue January 2017 Page 12

33 and perennial sow thistle. July 22, 2014 Previously sprayed herbicide applied intermittently throughout this tract appears successful. Broad leafed species showing signs of health degradation in the form of wilting and discoloration. Grasses mainly unaffected. August 14, 2016: Several meadow hawkweed patches were observed from KP to , herbicide applied to control. Canada thistle and perennial sow thistle are no longer present on ROW, issues are Drainage (D2) None. KP Removed silt fencing. June 15, 2014 ponding water on ditchline, Workside evidently lower than off ROW and ditch line is low compared to adjacent culvert off ROW. Silt fence in place to control erosion. Minimal flow noted and vegetation establishment is 70% compared to off ROW. Evidence of slumping on South/left bank. August 21, 2015 Reassessed the slope. It is well vegetated and not in need of additional erosion control. Silt fence has a tree down on it and has been pulled off of its stakes. Removed the windfall and reset the silt fence. June 22, 2016: Recent NGTL pipeline construction has disturbed the majority of the east portion of the right of way. This disturbed area will be monitored as a part of that pipeline s PCM program. Banks of watercourse are well vegetated and stable, remove sediment fencing at KP Previously identified (2014) slumping/ponding over ditch line at KP is well vegetated and stable with no erosion issues present, issue September 13, 2016 Sediment fencing removed at KP , issue NW Treed Monitor vegetation growth in June 15, 2014 Cross drains and diversion berms functioning well with vegetation establishing. 90% vegetation establishment as opposed to off ROW, consisting of some thinner vegetated patches along ROW more apparent on ditch line. Deciduous species establishing well along ROW. September 18, 2014 intermittent herbicide application conducted to control Canada thistle. Wapiti MS recently constructed - monitor in June 15, 2014: 90-95% vegetation establishment compared to off ROW. Deciduous species establishing well along Southern half of tract. Cross Drainage across ROW at exhibiting signs of possible past erosion and is relatively well vegetated at this time - continue to monitor. June 2, 2015: 90-95% vegetation establishment compared to off-row control. No Noxious weeds observed within tract during assessment. Cross drains and diversion berms located within tract are function and well vegetated. September 20, 2015 intermittent herbicide application conducted to control sow thistle. June 22, 2016: Vegetation is well established with desirable species throughout ROW. - Willows, bushes and saplings are encroaching well onto west side of ROW. Vegetation cover issue noted in 2012, no longer present, issue No erosion or subsidence issues. August 14, 2016 No noxious weeds observed. SW Treed Monitor vegetation growth in KP Erosion gully running across ditch line Not impacting land use at this time Monitor in June 2, 2015: Vegetation is comparable to off ROW % coverage as opposed to off ROW. Some small areas of less growth establishment potentially due to woody debris , KP previously noted erosion within cross drain is well vegetated, issue KP rutting or rill erosion on slope well vegetated. continue to monitor. No Noxious weeds were identified in this tract. June 22, 2016: Vegetation is well established with desirable species throughout ROW. - Willows, bushes and saplings are encroaching well onto west side of ROW. Vegetation issues noted in 2012 and 2015 (KP and ), no longer present, issues No erosion or subsidence issues. KP , erosion no longer evident due to vegetation cover, issue August 14, meadow hawkweed patch was observed at KP and perennial sow thistle patches were observed from KP to Herbicide applied to control. Tributary to Bald Mountain Creek (WC8) None. KP Removed silt fencing. June 15, 2014: North side of tributary thin vegetation existing 70% as opposed to off ROW. Banks well vegetated and appear stable, some minor settlement or slumping in south bank. Silt fence on North side of tributary could be removed. Good establishment of willows in coir banks. Portion of drainage lacks cobble directly over and parallel to ditchline. May be an issue due to lack of substrate - continue to monitor. One Bull thistle noted and removed. June 2, 2015: Tributary to Bald Mtn. Creek No erosion or subsidence on banks, 2014 repairs were successful (KP ), issue Revetment posts functioning. banks well vegetated, vegetation issue noted on north side of tributary in 2014 is June 22, 2016: KP Banks of unnamed creek are stable and well vegetated. Due to a beaver dam the creek has little to no flow. Willows are establishing well along creek banks. Bull thistle no longer present on ROW, issue January 2017 Page 13

34 NE Treed Monitor vegetation growth in 2013 and, if warranted, redistribute woody debris. Reseed at KP and monitor in Monitor weeds in 2013 and, if warranted, implement weed control measures. SE Treed Monitor vegetation growth in 2013 and, if warranted, redistribute woody debris. Monitor weeds in 2013 and, if warranted, implement weed control measures. NE Treed Monitor vegetation growth in Diversion berm on South side of Tributary, top of slope shows signs of erosion within drainage extending across ROW. Erosion rills noted above the diversion berm initiated on spoil side of Row in thinner vegetated area. Repairs recommended (KP ). July 11, 2014 Installed 12 straw waddle erosion prevention measures at KP , 2 on North bank of tributary and 10 on South bank. Re-contoured eroded area and filled with material on ROW. Removed 15m of silt fence and posts from North bank. June 15, 2014: 90-95% vegetation established with a few areas of reduced cover along spoil side of ROW, vegetation issue noted in 2012 is erosion noted within cross drain (KP ) recommend repairs. Canada thistle identified at the south end of this tract in several locations June 25, 2014 intermittent herbicide application conducted between KP and to control Canada Thistle and Perennial Sow Thistle. July 23, 2014 broadleaf vegetation within areas of herbicide application exhibit significant wilting, thorough affects within areas treated. Grasses do not indicate stressing. July 11, 2014 Installed 4 straw waddle erosion prevention breakers at KP Re-contoured eroded area and filled with material on ROW. June 16, North portion of 1/4 exhibits 75-80% vegetation establishment compared to off ROW, Areas showing improved vegetation along workside. Deciduous species establishing well along ROW throughout entire tract. Cross drains and diversion berms functioning well with vegetation establishing. - No Scentless Chamomile observed, located on this ¼ in 2013, issue is September 19, 2014 intermittent herbicide application conducted to control Canada thistle. June 16, 2014: Scentless Chamomile identified KP , plants picked and bagged. Entire tract exhibits vegetation density of ~90% compared to off ROW. Deciduous species establishing well along ROW throughout entire tract. Cross drains and diversion berms functioning well with vegetation establishing. June 25, 2014 intermittent herbicide application conducted between KP and to control Canada thistle, perennial sow thistle, and scentless chamomile. June 2, 2015: Vegetation establishment 90-95% comparable to off ROW control. KP previous erosion mitigation with the use of straw waddle installs was effective but requires additional straw waddles, as current ones are full of silt and in some cases buried within cross drain. Vegetation starting to establish. No Noxious weeds were identified within this tract. August 21, 2015 Installed four supplemental wattles for erosion at KP September 20, 2015 Intermittent herbicide application conducted to control perennial sow thistle and Canada thistle. June 2, Vegetation establishment ~85% compared to off ROW control. - Some sections along ROW with woody debris present - Good vegetation establishment surrounding these areas. Continue to monitor. - No contour, erosion or subsidence issues within tract. - Diversion berms and cross drains well vegetated and functioning effectively. September 20, intermittent herbicide application conducted to control perennial sow thistle and Canada thistle. June 2, 2015: ~90% vegetation cover as opposed to off ROW control. Deciduous species establishing well along ROW throughout entire tract. Cross drains and diversion berms functioning well with vegetation establishing. No contour, erosion or subsidence issues within tract. Large pond on East side of ROW. KP No issues. September 20, 2015 Intermittent herbicide application conducted to control Canada thistle. June 22, 2016: Vegetation is well established with desirable species throughout ROW. - Willows, bushes and saplings are encroaching well onto west side of ROW. Vegetation issue, as well as woody debris issue, noted in 2012 and 2014, no longer present, issues No noxious weeds identified. Previously installed wattles in drainage at KP (noted as early as 2012) are functioning well. Vegetation establishment throughout and soils are stable, issue No erosion or subsidence issues. August 14, 2016: No noxious weeds observed. Canada thistle and perennial sow thistle are no longer present, issues June 22, 2016: Vegetation is well established with desirable species throughout ROW, all previously noted vegetation issues (2012 to 2015) are Associated woody debris noted in 2012 is not impacting ROW recovery, issue Willows, bushes and saplings are encroaching well onto west side of ROW. - No noxious weeds identified. No erosion or subsidence issues. August 14, 2016: meadow hawkweed patch was observed at KP , herbicide applied to control. Scentless chamomile, noted in 2012, and Canada thistle are no longer present, issues June 22, 2016: Vegetation is well established with desirable species throughout ROW, all previously noted vegetation cover issues (2012) are Willows, bushes and saplings are encroaching well onto west side of ROW. No noxious weeds identified. Hill slope and diversion berms are stable. No erosion or subsidence issues. August 14, 2016: No noxious weeds observed. January 2017 Page 14

35 SE Treed Monitor vegetation growth in Install erosion control measures on hillside, reseed and monitor at KP in NE Treed Install erosion control measures on hillside, reseed and monitor at KP in Monitor vegetation growth in KP Minor erosion across centerline, Monitor KP Good infilling of native species, lots of shrubs and forbs on ROW. KP Increased erosion since the spring assessment was completed. Filled in rill erosion and one gully by hand and then install (Bio 4) erosion blankets and waddles. KP appears fully recovered and functional. No visible crown and good regeneration of natives. KP Erosion since the spring assessment was completed. KP Filled in rill erosion and one gully by hand and then install (Bio 4) erosion blankets and waddles. July 23, 2014 broadleaf vegetation within areas of herbicide application exhibit significant wilting, thorough affects within areas treated. Grasses do not indicate stressing. June 16, 2014: Entire tract exhibits vegetation density of ~90% compared to off ROW Grasses and Deciduous species establishing well along ROW. Cross drains and diversion berms functioning well with vegetation establishing. KP , Ephemeral Draw, previously repaired erosion issue, additional erosion has occurred. Recommended repair. KP rd party activity at pipeline crossing exhibiting slumping. June 25, 2014 intermittent herbicide application conducted between KP and to control Canada thistle and perennial sow thistle. July 13, 2014 Erosion repair completed at KP July 23, 2014 broadleaf vegetation within areas of herbicide application exhibit significant wilting, thorough affects within areas treated. Grasses do not indicate stressing. June 16, 2014: Majority of ROW exhibits vegetation density of ~90% compared to off ROW. Deciduous species establishing well along ROW throughout entire tract. Cross drains and diversion berms functioning well with vegetation establishing other than mentioned issues. KP Minor erosion beginning along West side of ROW boundary into centre line - Continue to monitor. Noxious weed, Tall buttercup located on ROW. June 25, 2014 intermittent herbicide application conducted between KP and to control Canada thistle, perennial sow thistle, and tall buttercup. July 13, 2014 Erosion repairs completed at KP July 23, 2014 KP ~15 buttercup plants were picked in this area. Previous herbicide application did not cover entire area of weed presence. Broadleaf vegetation within areas of herbicide application exhibit significant wilting. Grasses do not indicate stressing. June 2, 2015: ~90% vegetation cover as opposed to off ROW control. Scentless Chamomile noted at KP Approx 30 plants plus emerging. Recommend herbicide application. 3 bull thistle identified picked and bagged at KP , - continue to monitor. Deciduous species establishing well along ROW throughout entire tract. Cross drains and diversion berms functioning well with vegetation establishing. No contour, erosion or subsidence issues within tract, repairs completed at KP were effective, issue Slumping noted in 2014 at 3rd party crossing at KP is no longer evident, issue July 10, 2015 Intermittent herbicide application conducted to control scentless chamomile from KP to Scentless Chamomile was noted off ROW. September 20, 2015 Intermittent herbicide application conducted to control Canada thistle and scentless chamomile. June 3, 2015: 90% vegetation establishment compared to off-row control. Some minor bare patches along ditchline. Erosion repairs, at KP , from previous years work are functioning and in good condition, issue Cross drains are functioning and well vegetated. No Noxious weeds observed within tract during assessment. Scentless chamomile, Canada thistle, and perennial sow thistle no longer present, issues June 22, 2016: Vegetation establishing well, vegetation consistent with off ROW. Vegetation issue noted in 2012 is Good establishment of grasses, clover, willows and shrubs. Erosion repair from 2014 (KP ) within drainage has established excellent vegetation, breakers have filled in with sedimentation, restoring natural contour to drainage. Breakers remain functional in mitigating erosion. Issue is Erosion noted in 2012 at KP , no longer evident, issue Recent NGTL pipeline construction has disturbed the majority of the east portion of the right of way. This disturbed area will be monitored as a part of that pipeline s PCM program. Slopes and diversion berms are well vegetated and stable; no erosion issues August 15, 2016: Intermittent meadow hawkweed patches were observed throughout ¼. Several Canada thistle, perennial sow thistle, and bull thistle individuals were observed in the ¼. Herbicide applied to control. Scentless chamomile no longer present, issue resolved June 23, 2016: Vegetation well established and consistent with off ROW. Good establishment of willows and shrubs. Vegetation issue noted in 2012 is No noxious weeds were identified within this tract. Erosion repair from 2014 within drainage at KP is providing adequate function, good establishment of vegetation and stabilization of soils, confirming that issue is Erosion noted in 2012 at KP (the same issue noted in 2013 at KP ) is no longer evident, issue Recent NGTL pipeline construction has disturbed the majority of the east portion of the right of way. This disturbed area will be monitored as a part of that pipeline s PCM program. Previously assessed bare areas continue to improve with establishment of vegetation trajectory approaching adjacent land capability, issue Tall buttercup was identified at KP , across the right of way on what appears to be an old trail, also located off ROW. Recommend herbicide application. January 2017 Page 15

36 SE Treed Monitor vegetation growth in July 13, 2016 herbicide application conducted (spot spraying) to control tall buttercup at KP August 15, 2016: Intermittent meadow hawkweed and perennial sow thistle patches were observed throughout ¼. Several small patches of common tansy were observed at KP Herbicide application conducted to control. Canada thistle no longer present, issue June 16, 2014 Majority of ROW exhibits vegetation density of ~90% compared to off ROW. Cross drains and diversion berms functioning well with vegetation establishing. Slope has good establishment of vegetation with no issues at this time. SW Treed None. June 16, 2014 Entire tract exhibits good vegetation density of ~90-95% compared to off ROW, good grass establishment. Deciduous species establishing well along ROW throughout entire tract. Cross drains and diversion berms functioning well with vegetation establishing. NW Tributary to Bald Mountain Creek (WC9) Drainage (D3) Monitor in 2013 and, if warranted, repair. None. KP Drain is still fully functional, it is well vegetated. KP Removed silt fencing and all steel pegs and non-biodegradable material from seasonal drain Re-distributed the cobble that is holding back water. Slight subsidence on seasonal drain areas from KP 21.9 to KP 24 no issues (not impacting reclamation efforts) at this time monitor. KP Removed silt fencing. June 16, 2014 Tributary to Bald Mtn. Creek. - Minor slumping on North and South banks, bed of water course along ditchline is slightly wider and slightly deeper than off ROW % vegetation on banks as opposed to off ROW. - continue to monitor. June 17, KP slumping along ditchline, erosion extending beyond slumping, establishing vegetation within the erosion - monitor. June 3, 2015: 90% vegetation establishment compared to off-row control. Diversion berms are functioning and well vegetated. No noxious weeds observed within tract during assessment. June 3, 2015: 90% vegetation establishment compared to off-row control. No noxious weeds observed within tract during assessment. June 3, 2015: Slumping has occurred along ditchline of both banks of WC9. Right (north) bank is well vegetated, continue to monitor. Left (south) bank has slumped approximately 1 meter from the revetment posts and has 70-75% vegetation establishment. No evidence of rills or other erosion issues at time of assessment, continue to monitor creek banks. June 3, 2015 B. Drainage D3 at KP remains as previously assessed. Minor slumping is consistent with 2014 assessment; drainage is stable. Vegetation is continuing to establish well. Minor ponding present at time of assessment. Continue to monitor. June 23, 2016: Vegetation well established and consistent with off ROW. Vegetation issue noted in 2012 is Good establishment of willows and shrubs. No noxious weeds were identified within this tract. Hill slopes and berms are stable and well vegetated. Recent NGTL pipeline construction has disturbed the majority of the east portion of the right of way. This disturbed area will be monitored as a part of that pipeline s PCM program. August 15, 2016 Several meadow hawkweed patches were observed throughout 1/4. Herbicide applied to control. June 23, 2016: Vegetation well established and consistent with off ROW. Good establishment of willows and shrubs. No noxious weeds were identified within this tract Recent NGTL pipeline construction has disturbed the majority of the east portion of the right of way. This disturbed area will be monitored as a part of that pipeline s PCM program. August 15, 2016 Several meadow hawkweed patches were observed throughout 1/4. Herbicide applied to control. June 23, 2016 WC 9 Unnamed Tributary to Bald Mountain Creek banks are stable and continue to improve with establishment of vegetation - trajectory approaching adjacent land capability, vegetation issues noted in 2014 and 2015 are Moderate flow is observed within the watercourse at this time. Minor slumping as previously reported remains unchanged since 2012; it does not impede land capability in comparison to adjacent lands, and it does not impose a safety or pipe integrity concern. Issue June 23, 2016 D3, as previously assessed exhibiting minor slumping no change to conditions; no safety or pipe integrity concerns, with land capability comparable to adjacent lands. Soil conditions remain stable with good vegetation established in and around minor slumping. Issue August 15, 2016 No noxious weeds observed. January 2017 Page 16

37 Drainage (D4) Drainage (D5) Rare Plant (snakeskin liverwort) Tributary to Bald Mountain Creek (WC10) Rare Plant (snakeskin liverwort) None. Monitor in 2013 and, if warranted, repair. Slight subsidence on seasonal drain areas from KP 21.9 to KP 24 no issues (not impacting reclamation efforts) at this time monitor. KP Removed all steel pegs and nonbiodegradable material from seasonal drain. Re-distributed the cobble that is holding back water. Checked for depth of cover with hand probe prior to any shovel work to correct drainage and cobble being re-distributed. Slight subsidence on seasonal drain areas from KP 21.9 to KP 24 no issues (not impacting reclamation efforts) at this time monitor. KP Removed silt fencing and all steel pegs and non-biodegradable material from seasonal drain. Re-distributed the cobble that is holding back water. Checked for depth of cover with hand probe prior to any shovel work to correct drainage and cobble being re-distributed. KP On August 8, 2013 Rare Plant Specialists visited the location and observed two patches of snakeskin liverwort on the rightof-way as well as golden saxifrage. Resolved and successful: no further monitoring is recommended. Issue None. KP Excellent regeneration, shrubs, conifers, and deciduous all recovering. KP On August 8, 2013 Rare Plant Specialists visited the location and observed snakeskin liverwort off the right-of-way along the west edge of the right-of-way boundary. Suitable habitat was June 17, KP Drainage, Subsidence observed. Ponding on ditchline, poor contour of drainage, standing water -continue to monitor. June 17, KP Considerable ponding water on ditchline as opposed to off ROW. Subsidence exists along East bank, monitor. June 17, 2014: KP Minor subsidence and slumping on each side. Coir banks appear effective and stable with vegetation establishing. Removed silt fencing on South side. Cross drains and diversion berms functioning well with vegetation establishing. June 3, Drainage D5 at KP exhibits good vegetation growth on slopes leading to drainage. Minor slumping on east bank remains as previously assessed. Considerable ponding on ditchline is evident at time of assessment; does not appear to be draining off ROW effectively. Recommend hand digging cross drainage deeper across ROW to allow for effective water movement and to minimize ditchline ponding. August 22, Dug a channel from the ponded water on ditch line for water to flow off of the ROW. June 3, 2015 B. banks stable with good vegetation cover (willows flourishing), minor subsidence noted in 2014 (KP ) is considered Good cobble distribution and no sediment inflow from banks. Moderate flow was evident within watercourse at time of assessment. Amphibious life present within watercourse. June 23, D4, as previously assessed exhibiting minor slumping no change to conditions; no safety or pipe integrity concerns, with land capability comparable to adjacent lands. Soil conditions remain stable with good vegetation established in and around minor slumping. Issue August 15, No noxious weeds observed. June 23, D5, as previously assessed exhibiting minor slumping, first noted in 2012 no change to conditions; no safety or pipe integrity concerns, with land capability comparable to adjacent lands. Soil conditions remain stable with good vegetation established in and around minor slumping. Issue August 15, No noxious weeds observed. June 23, 2016 banks are stable and well vegetated with grasses and willows. Moderate flow is observed within the watercourse at this time. Minor slumping as previously reported remains unchanged; it does not impede land capability in comparison to adjacent lands, and it does not impose a safety or pipe integrity concern. Confirming issue is January 2017 Page 17

38 observed on the right-of-way. Resolved and successful: no further monitoring is recommended. Issue Treed None. June 17, 2014 Vegetation establishment compared to off ROW ~95%. Good establishment of grasses. SW Treed None. June 17, 2013 Vegetation establishment compared to off ROW ~95%. Weeds (non-noxious) comparable to off ROW. Tributary to Bald Mountain Creek (WC11) Rare Plant (snakeskin liverwort) None. KP and Removed silt fencing and all steel pegs and non-biodegradable material from seasonal drain. Re-distributed the cobble that is holding back water. Checked for depth of cover with hand probe prior to any shovel work to correct drainage and cobble being re-distributed. KP to On August 8, 2013 Rare Plant Specialists visited the location and observed snakeskin liverwort on and off the right-of-way along the banks of the creek. Resolved and successful: no further monitoring is recommended. Issue June 17, 2014: Low water flow present across ROW in drainages noted, well vegetated and functioning effectively. KP minor slumping, apparent deposit of sediment in bed of ditchline- continue to monitor. Silt fencing remains on either bank and can be removed at any time. July 29, 2014: Removed previously reported sit fencing on either bank of tributary at KP Scentless Chamomile identified at KP Picked and bagged. June 3, 2015: Vegetation is 90-95% compared to off ROW control. Diversion berms within tract functioning well. Recent dig evident at KP as ground bare compared to the rest of ROW. Some grasses are beginning to establish, monitor in June 3, 2015: Vegetation within tract appears to be 90-95% compared to off ROW control. Some areas along ROW exhibiting thinner vegetation cover. Diversion berms and cross drains are stable. June 3, 2015 Minor slumping remains through tributary but both banks are well vegetated, slumping is not hindering the recovery of the ROW, issue Apparent sediment inflow into streambed from the previous assessments remains; flow is not impacted by sedimentation, issue Good cobble distribution within tributary bed. Revetment posts are stable and are functioning well. Minor exposure of plastic matting occurring on beds. Minimal flow at time of assessment. June 23, 2016: Vegetation well established and consistent with off ROW. Good establishment of willows and shrubs. No noxious weeds were identified within this tract. Recent NGTL pipeline construction has disturbed the majority of the east portion of the right of way. Recent construction project crosses over right of way at KP This disturbed area will be monitored as a part of that pipeline s PCM program. June 23, 2016: Vegetation well established and consistent with off ROW. Good establishment of willows and shrubs. Areas if thinner vegetation, noted in 2015, are no longer evident, issue Diversion berms and steep slopes are stable and well vegetated. Tall Buttercup identified for ~160m along ditchline at the south end of the tract and off ROW within foreign well site access road. July 14, 2016 herbicide application conducted (spot spraying) to control tall buttercup. August 15, 2016 Intermittent meadow hawkweed patches were observed throughout 1/4. Herbicide applied to control. June 23, 2016: banks are stable and well vegetated with grasses and emerging willows. Presence of sediment within watercourse is attributed to recent high runoff levels. Moderate flow is observed within the watercourse at this time. Minor slumping as previously reported remains unchanged; it does not impede land capability in comparison to adjacent lands, and it does not impose a safety or pipe integrity concern. Issue Scentless chamomile no longer present, issue January 2017 Page 18

39 Tributary to Bald Mountain Creek (WC12) Monitor in 2013 and, if warranted, repair. KP Cobble was installed during construction; the centerline subsided and acted as a sediment trap. The native substrate is fines; the collection of sediment on centerline is not impacting restoration. KP and Removed silt fencing NE Treed None. KP Removed silt fencing and all steel pegs and non-biodegradable material from seasonal drain. Re-distributed the cobble that is holding back water. Checked for depth of cover with hand probe prior to any shovel work to correct drainage and cobble being re-distributed. SE Treed Monitor vegetation growth in 2013 and, if warranted, redistribute woody debris. Distribute soil over right-of-way in June 17, 2014: KP minor subsidence either bank. Good vegetation establishment. Channel entering ROW has been naturally redirected and is impacting midsection of drainage slope ~2m above coir wrap on South side of drainage. This issue may require remediation - continue to monitor. Cross drains and diversion berms functioning well with vegetation establishing. Deciduous species establishing well along ROW. Hill slopes vegetating well and appear stable. KP to silt fence remaining along east side of ROW, extending into next 1/4. July 12, 2014 Removed approximately 250m of silt fence from tract, and also extending into NE M from KP to KP After silt fence was removed, all soil was placed back into the depression that was created and ground was re-contoured manually. June 17, 2014: Majority of ROW vegetation ~90% compared to off ROW. Deciduous species establishing well along ROW. Cross drains and diversion berms functioning well with vegetation establishing. Tall buttercup was located on the ROW. Diversion berm, evidence of removal of straw waddle, steel pins remain. Recommend installation of straw waddles as vegetation remains thin. KP Diversion berm exhibits small amounts of water rising on ditchline may be a spring. Continue to monitor. KP Straw waddles evidently removed from diversion berm or ephemeral draw. Continue to monitor. June 26, 2014 intermittent herbicide application conducted between KP and to control tall buttercup. July 23, 2014 broadleaf vegetation within areas of herbicide application exhibit significant wilting, thorough affects within areas treated. Grasses do not indicate stressing. June 17, 2014 Majority of ROW exhibits ~90 vegetation established compared to off ROW control. Deciduous species and willows establishing well on ROW. Cross drains well vegetated and functioning appropriately. June 26, 2015 intermittent herbicide application conducted between KP and to control weeds on ROW. July 23, 2014 broadleaf vegetation within areas of herbicide application exhibit significant wilting. Grasses do not indicate stresses. June 3, 2015 Minor slumping remains, as previously assessed in 2014, not affecting watercourse as banks are well vegetated, issue Good cobble distribution within bed of bank. Natural channel redirection upstream appears to be used only during high precipitation events, it is not impacting the recovery of the ROW, issue No evident inflow of sediment into stream. Continue to monitor. June 3, 2015 Vegetation within tract appears to be 90-95% comparable to off ROW control. Some areas along ROW exhibiting reduced vegetation. Cross drains within tract appear to be functioning well with good vegetation establishment and no evident ponding water. Diversion berms within tract appear to be stable and functioning well. Diversion berms are well vegetated. Minor ponding evident on ditchline within berm at KP as previously assesses. Issue does not appear to be affecting land-use or pipe integrity and is considered Diversion berm issues noted in 2014 are Ephemeral draw at KP exhibits two areas where waddles have been removed exhibiting minimal vegetation cover. Minimal vegetation establishment likely attributed to exposed plastic matting over areas. Recommend cutting out exposed plastic matting to promote vegetation growth. No subsidence, erosion or contour issues evident within tract. August 22, 2015 Cut out and removed exposed nonbiodegradable erosion control. June 4, 2015: Vegetation is 90-95% comparable to off ROW control with some areas exhibiting thinner vegetation cover. No noxious weeds were found within tract. No subsidence, erosion or contour issues were evident within tract. June 23, 2016 banks are stable and well vegetated with grasses and emerging willows. Minimal flow is observed within the watercourse. Minor slumping as previously reported remains unchanged, first noted in 2012; it does not impede land capability in comparison to adjacent lands, and it does not impose a safety or pipe integrity concern. Issue June 23, 2016: Vegetation well established and consistent with off ROW. Good establishment of willows, evergreens, and shrubs. Diversion berms and steep slopes are stable and well vegetated. Recent NGTL pipeline construction has disturbed the majority of the east portion of the right of way on the south half of 1/4. Recent construction project crosses over right of way at KP This disturbed area will be monitored as a part of that pipeline s PCM program. Vegetation issue noted within ephemeral draw at KP is no longer evident, issue Tall Buttercup identified for ~200m at the north end of the tract and at KP , at foreign line crossing, and to west off ROW. July 14, 2016 herbicide application conducted (spot spraying) to control tall buttercup. August 16, 2016: meadow hawkweed was observed from KP to , several bull thistle plants observed. Herbicide applied to control. Although still present, tall buttercup was reduced in extent from approximately 1100 m in 2014 to 200 m in June 23, 2016: Vegetation is well established with desirable species throughout ROW vegetation issue and associated woody debris issues are Good establishment of willows, rosebushes and poplar saplings. - No noxious weeds identified. Soil pile noted in 2012, no longer present, issue No erosion or subsidence issues. January 2017 Page 19

40 August 16, 2016 Several meadow hawkweed patches were observed throughout ¼, a few bull thistle individuals were observed in the ¼. Herbicide applied to control. NE Treed Reseed at KP and monitor in Monitor vegetation growth in SE Treed Monitor in 2013 and, if warranted, repair. Reseed at KP and monitor in If warranted, install erosion control measures. Monitor vegetation growth in Drainage (D6) None. NW Treed Monitor vegetation growth in KP Removed silt fencing. KP Good regeneration June 17, % vegetation establishment within this tract, compared to off ROW control. Extensive sections exhibiting thin vegetative cover across ROW, possibly attributed to excessive woody debris in some area. Monitor for erosion and continued vegetation establishment. Deciduous species and willows establishing well on ROW. June 18, 2014: 85-90% vegetation cover on ROW compared to off ROW control with some extensive areas exhibiting thinner vegetation. Good establishment of willow and deciduous species in sections along ROW. One bull thistle identified within tract. Hand-removed noxious weed and bagged it. Removed silt fencing stakes that were piled on the edge of ROW at KP Cross drains within tract functioning well with good vegetation proliferation within. One exception of poor water drainage within cross drain KP with ponding water on ditchline. Cross drain was hand dug at time of assessment to remediate ponding water. No erosion, subsidence or contour issues evident within tract at time of assessment. June 4, 2015: Vegetation is 90-95% comparable to off ROW control with some areas exhibiting thinner vegetation cover. Natural drainage at KP stable with good vegetation establishing within. Water is draining effectively into bar ditch running parallel to road. June 4, 2015: Vegetation is 90-95% compared to off ROW control with some areas exhibiting thinner vegetation cover. Minor ponding evident across ROW at KP Area appears to be a natural low area. Vegetation indicative of wet conditions such as bulrush and scouring rushes. No issues at this time, issue Cross drains within tract appear stable with good vegetation growth and no evident ponding issues a time of assessment, ponding issue noted in 2014 at KP is No subsidence, erosion or contour issues evident within tract. No issues noted. No issues noted. No issues noted. June 18, 2014: Majority of ROW exhibits 90% vegetation cover on ROW compared to off ROW control Good establishment of willow and deciduous species in sections along ROW. Canada thistle found within tract. Cross drain functioning well with good vegetation proliferation within. No erosion, subsidence or contour issues evident within tract at time of assessment. June 4, 2015: 90% vegetation establishment compared to off-row control. Cross drains are functioning and well vegetated. No noxious weeds observed within tract during assessment. June 23, 2016: Vegetation is well established with desirable species throughout ROW. Good establishment of willows, rosebushes and poplar saplings. Previous issues, including those noted in 2012, 2014 and 2015, with vegetation cover is No noxious weeds identified. No erosion or subsidence issues erosion issue at KP no longer present, issue August 16, 2016 Intermittent meadow hawkweed patches were observed throughout ¼, perennial sow thistle at KP Herbicide applied to control. June 23, 2016: Vegetation is well established with desirable species throughout ROW. Good establishment of willows, rosebushes and poplar saplings. Previous issue, including those noted in 2012, 2014, and 2015, with vegetation cover is No noxious weeds identified. No erosion or subsidence issues. Subsidence noted in 2012 is no longer evident, issue KP and ponding across ROW has re-appeared, but is stable with wetland vegetation well established, issue Cross drains through tract appear stable with good vegetation growth. August 16, 2016: meadow hawkweed individuals were observed throughout ¼. Herbicide applied to control. Bull thistle no longer present, issue June 23, 2016: Vegetation is well established with desirable species throughout ROW vegetation cover issues are Good establishment of willows, rosebushes and poplar saplings. No noxious weeds identified. No erosion or subsidence issues. August 16, 2016: Several meadow hawkweed individuals were observed throughout ¼. Herbicide applied to control. Canada thistle no longer present, issue January 2017 Page 20

41 NE Treed Monitor vegetation growth in Drainage (D7) Monitor in 2013 and, if warranted, repair. SE Treed Monitor vegetation growth in Monitor weeds in 2013 and, if warranted, implement weed control measures. KP and Removed silt fencing and all steel pegs and non-biodegradable material from seasonal drain. Re-distributed the cobble that is holding back water. Checked for depth of cover with hand probe prior to any shovel work to correct drainage and cobble being re-distributed. June 18, 2014: Majority of ROW exhibits 90-95% vegetation cover compared to off ROW control. Good establishment of willow and deciduous species in sections along ROW. Scentless chamomile found within tract. They were handpicked and bagged. Perennial sow thistle present within tract; Erosion evident at KP at the edge of spoil side on ROW, recommend repairs. Removed several steel pegs from straw waddles within tract. June 26, 2014 intermittent herbicide application conducted between KP and to control Canada thistle, perennial sow thistle, and scentless chamomile. July 14, 2014 Erosion repair at KP completed. July 23, 2014: broadleaf vegetation within areas of herbicide application exhibit significant wilting, thorough affects within areas treated. Grasses indicate slight stressing within this area of herbicide application KP scentless chamomile identified on either side of drainage within 30m setback, recommend hand picking. September 19, 2014 intermittent herbicide application conducted to control Canada Thistle. June 18, 2014 Cross drain D7 at KP exhibits minor subsidence on both south and north banks - monitor. Good vegetation establishment seems to have stabilized banks. June 18, 2014: Majority of ROW ~85-90% vegetation establishment compared to off ROW. Cross drains and diversion berms functioning well with vegetation establishing. Weeds (scentless chamomile) noted on ROW removed steel pins from cross drain straw waddle. KP , poor contouring on ditchline within cross drain. Slight depression providing potential for ponding of water. Vegetating well no issues at this time. June 26, 2014 intermittent herbicide application conducted between KP and to control scentless chamomile. July 23, 2014 Previously sprayed herbicide applied intermittently throughout this tract appears successful. Broad leafed species within areas sprayed showing signs of health degradation in the form of wilting and discoloration. Grasses mainly unaffected. June 4, 2015: 90% vegetation establishment compared to off-row control. Erosion repairs from previous years, at KP , work are functioning and in good condition. Issue No noxious weeds observed within tract during assessment. June 4, 2015: Some ponding occurring over ditchline at Drainage 7, but water is flowing off-row. Banks of Drainage 7 exhibit slumping, but are well vegetated, issue is June 4, 2015: 90% vegetation establishment compared to off-row control. Minor bare patches of present along Ditchline. Cross drains and diversion berms are functioning and well vegetated. No noxious weeds observed within tract during assessment. June 23, 2016: Vegetation is well established with desirable species throughout ROW vegetation issues are Good establishment of willows, rosebushes and poplar saplings. No noxious weeds identified. No erosion or subsidence issues. August 16, 2016: Several meadow hawkweed individuals were observed throughout ¼. Herbicide applied to control. Scentless chamomile, perennial sow thistle, and Canada thistle are no longer present, issues June 23, 2016 Drainage bed and banks are stable. Subsidence previously noted, first in 2012, has not impeded the recovery of the ROW, issue June 23, 2016: Vegetation is well established with desirable species throughout ROW vegetation issues are Good establishment of willows, rosebushes and poplar saplings. No noxious weeds identified. No erosion or subsidence issues. Issue noted in 2014 within cross drain at KP , no longer evident, issue August 16, 2016: meadow hawkweed was observed throughout ¼. Herbicide applied to control. Scentless chamomile noted in 2012 and 2014 is no longer present, issue January 2017 Page 21

42 NE Treed Monitor vegetation growth in SE Treed Monitor vegetation growth in NE Treed Monitor vegetation growth in 2013 and, if warranted, implement weed control measures. KP Removed all steel pegs and nonbiodegradable material from seasonal drain. Re-distributed the cobble that is holding back water. Checked for depth of cover with hand probe prior to any shovel work to correct drainage and cobble being re-distributed. KP Natural regeneration very weak (Jack pine stand) - Clover is the only species growing KP Valve Site Large number of weeds (Scentless, Ox eyed Daisy and Hawk weed was observed at the Valve site. Sprayed - assess success in June 18, 2014: Majority of ROW exhibits ~85-90% vegetation establishment compared to off ROW. Cross drains functioning well with vegetation establishing. Some ponding water, most exhibiting minimal flow. Removed steel pins from straw waddles. KP bull thistle found and removed. Tall buttercup also located. June 26, 2014 intermittent herbicide application conducted between KP and with herbicide to control tall buttercup. July 23, 2014 Previously sprayed herbicide applied intermittently throughout this tract appears successful. Broad leafed species within areas sprayed showing signs of health degradation in the form of wilting and discoloration. Grasses mainly unaffected. June 18, 2014: Majority of ROW exhibits ~95% vegetation establishment compared to off ROW. Cross drains functioning well with vegetation establishing, some exhibiting minimal flow. KP Removed steel pins from straw waddle at cross drain. Scentless chamomile noted on ROW. June 26, 2014 intermittent herbicide application conducted between KP and to control scentless chamomile. July 23, 2014 Previously sprayed herbicide applied intermittently throughout this tract appears successful. Broad leafed species within areas sprayed showing signs of health degradation in the form of wilting and discoloration. June 18, 2014: Majority of ROW exhibits 80-90% vegetation compared to off ROW control. Areas of reduced vegetation cover were noted and are associated with high levels of woody debris these areas are re-vegetating, but just a slower rate. One scentless chamomile identified on ditchline on south side of valve site. Plant was picked and bagged, continue to monitor. June 26, 2014 intermittent herbicide application conducted between KP and to control scentless chamomile. July 23, 2014: Previously sprayed herbicide applied intermittently throughout this tract appears successful. Broad leafed species within areas sprayed showing signs of health degradation in the form of wilting and discoloration. Grasses mainly unaffected. June 5, 2015: 90% vegetation establishment compared to off-row control. Cross drains are functioning and well vegetated with some minor ponded water draining out. Bare soil and ponding water present at KP , recent new foreign line crossing, continue to monitor. Bare soil present at KP , recent new foreign line crossing, continue to monitor. No Noxious weeds observed within tract during assessment. June 5, 2015: 90-95% vegetation establishment compared to off-row control. Cross drains are functioning and well vegetated. No noxious weeds observed within tract during assessment. June 5, 2015: 90% vegetation establishment compared to off-row control. Minor bare patches of present along ditchline. Cross drains are functioning and well vegetated. No noxious weeds observed within tract or within valve station located at KP June 23, 2016: Vegetation is well established with desirable species throughout ROW vegetation issues are Good establishment of willows, rosebushes and poplar saplings. No noxious weeds identified. No erosion or subsidence issues. Cross drains are vegetated and functioning, issues with ponding water are Foreign line crossing disturbances (KP and ) are stable with no significant erosion. Vegetation is establishing, issues August 16, 2016: meadow hawkweed was observed throughout. Herbicide applied to control. A small patch of scentless chamomile (3-4 plants) was handpicked and bagged for disposal. Tall buttercup and bull thistle are no longer present, issues June 23, 2016: Vegetation is well established with desirable species throughout ROW vegetation issues are Good establishment of willows, rosebushes and poplar saplings. No noxious weeds identified. No erosion or subsidence issues. Cross drains are vegetated and stable. KP Hydrovac hole identified at foreign pipeline crossing was filled in. Issue August 17, 2016: meadow hawkweed was observed throughout ¼. Herbicide applied to control. Scentless chamomile no longer present, issue June : Good establishment of grasses and native vegetation, consistent with off right of way (2013 issue of species composition is resolved) vegetation cover issue is No noxious weeds were identified within this tract. Area around valve station (KP ) has been disturbed by recent construction. This disturbed area will be monitored as a part of that pipeline s PCM program August 17, 2016: meadow hawkweed was observed throughout ¼. Herbicide applied to control. Scentless chamomile and ox-eyed daisy no longer present, issues January 2017 Page 22

43 SE Treed Monitor vegetation growth in SW Treed Monitor vegetation growth in 2013 and, if warranted, implement weed control measures. Scentless chamomile at KP to Spraying is recommended. Majority of area identified was not previously sprayed. Scentless chamomile at KP , picked and bagged (1 plant). Continue to monitor. July 28, 2014: scentless chamomile was handpicked and bagged for disposal. Approximately 0.75 large garbage bags were picked from location. Intermittent herbicide application conducted between KP and to control Scentless Chamomile. September 19, 2014 intermittent herbicide application conducted to control Canada thistle. KP Scentless chamomile was spotted along the right-of-way at same location as last year, requires picking and spraying. KP Artesian Flow Water coming to surface on centerline in bottom of a seasonal drain, monitor for pipeline integrity issues. KP to KP Weeds spot Sprayed. June 19, 2014: Majority of the ROW exhibits ~90% vegetation establishment compared to off ROW. Deciduous species establishing well Scentless chamomile identified. June 26, 2014 intermittent herbicide application conducted between KP and to control scentless chamomile. July 23, 2014: Previously sprayed herbicide applied intermittently throughout this tract appears successful. Broad leafed species within areas sprayed showing signs of health degradation in the form of wilting and discoloration. Grasses mainly unaffected. Scentless chamomile at KP on roadway at Pipeline crossing. Herbicide was not previously sprayed on roadway. Continue to monitor. July 29, 2014 Previously assessed Scentless Chamomile along road crossing at KP was picked and bagged. June 19, 2014: Majority of ROW exhibits ~95% vegetation establishment compared to off ROW. Good establishment of native grasses across ROW. Conifer species emerging and deciduous species establishing. Cross drains functioning effectively with vegetation establishing. Some water present. Ponding water adjacent to pipeline on workside and spoil side of ditchline at side bend - continue to monitor. Scentless chamomile picked and bagged. June 26, 2014 intermittent herbicide application conducted between KP and to control scentless chamomile. July 23, 2014 Previously sprayed herbicide applied intermittently throughout this tract appears successful. Broad leafed species within areas sprayed showing signs of health degradation in the form of wilting and discoloration. Grasses mainly unaffected. June 5, 2015: 90% vegetation establishment compared to off-row. No noxious weeds observed within tract during assessment. June 5, 2015: Vegetation is 90-95% comparable to off ROW control with some areas exhibiting thinner vegetation cover. Vegetation consisting of native grasses, clover, rush, Indian paintbrush as well as coniferous, poplar and willow species. Previous year spraying activities appear to have been effective as no noxious weeds were found. Ponding on west side of ROW at side bend at KP appears to be draining off ROW effectively as a result of hand digging work. Good vegetation is developing within drainage. East side of ditchline exhibits more ponding but appears to be draining off ROW effectively. KP groundwater flow issue noted in 2013, no longer evident, issue Cross drains within tract appear to be functioning effectively and exhibit good vegetation establishment within. No subsidence, erosion or contour issues evident within tract. June 24, 2016 Good establishment of grasses and native vegetation, consistent with off right of way vegetation cover issue is No noxious weeds were identified within this tract. August 17, 2016: No noxious weeds observed. Scentless chamomile no longer present, issue June 24, 2016: Good establishment of grasses, shrubs and willows along right of way, consistent with off right of way and 2015 vegetation cover issues are No noxious weeds were identified within this tract. KP , ponding no longer evident, issue August 17, 2016: intermittent meadow hawkweed patches were observed throughout ¼. Herbicide applied to control. Scentless chamomile no longer present, 2012 issue is January 2017 Page 23

44 SE Treed Monitor vegetation growth in 2013 and, if warranted, redistribute woody debris. Rare Plant (northern moonwort) SW Treed Monitor vegetation growth in 2013 and, if warranted, reseed. KP to KP Weeds spot Sprayed. KP On August 8, 2013 Rare Plant Specialists visited the location and observed northern moonwort off the right-of-way. Resolved and successful: no further monitoring is recommended. Issue June 19, 2014: ~80-85% vegetation establishment compared to off ROW. Good establishment of grasses across ROW. Many thinly vegetated areas mainly on ditchline. ATV activity evident throughout tract - defined trail. KP Cross drain exhibiting minor erosion on ROW across spoil side and ditchline, continue to monitor. KP Ponding water along spoil side of ditchline. No cross drain present- continue to monitor, no work required at this stage. July 23, 2014 Scentless chamomile at KP , picked and bagged (1 plant). Continue to monitor. June 19, 2014: ~85-90% vegetation establishment as opposed to off ROW. Good establishment of grasses across ROW. Areas of surface material disturbance having less vegetation cover at time of assessment. Cross drains functioning effectively with vegetation establishing. Some water present. Conifer species emerging and deciduous species establishing. KP , minor ponding water on work side of ditchline - no cross drainage continue to monitor. KP , thistle and scentless chamomile identified at South end of tract June 26, 2014 intermittent herbicide application conducted between KP and to control thistle and scentless chamomile. July 23, 2014 Previously sprayed herbicide applied intermittently throughout this tract appears successful. Broad leafed species within areas sprayed showing signs of health degradation in the form of wilting and discoloration. Grasses mainly unaffected. September 19, 2014 intermittent herbicide application conducted to control Canada thistle. June 5, 2015: Vegetation on ROW is 85-90% comparable to off ROW control with some areas showing thinner vegetation cover. Vegetation consisting of native grasses, clover, rush, Indian paintbrush as well as coniferous, poplar and willow species. Patch of perennial sow thistle found at KP Recommend implementation of control measures. Could not locate previously assessed ponding at ; issue appears to have been remediated naturally. Issue New pipeline construction evident along north boundary of ROW throughout tract. Cross drains appear to be functioning well within tract and are exhibiting good vegetation cover. No subsidence, erosion or contour issues evident. September 20, 2015 herbicide application conducted to control perennial sow thistle at KP June 5, 2015: Vegetation on ROW appears to be 90% comparable to off ROW control. Vegetation consisting of native grasses, clover, Indian paintbrush as well as coniferous, poplar and willow species. One bull thistle found on ditchline at KP Plant was handpicked and removed. Recent NGTL pipeline construction ends at KP ROW has been recently disturbed from KP to This disturbed area will be monitored as a part of that pipeline s PCM program. No subsidence, erosion or contour issues evident within tract. August 30, 2015 Observed a patch of bull thistle at recommend fall herbicide application. September 20, 2015 Intermittent herbicide application conducted to control perennial sow thistle and bull thistle. June 24, 2016: Good establishment of grasses, native vegetation, willows, shrubs, aspen and evergreen, consistent with off right of way and 2014 vegetation cover, and associated woody debris, issues are No noxious weeds were identified within this tract. Adequate drainage across right of way. ATV activity no longer noted, issue August 17 and 19, 2016: meadow hawkweed was observed throughout ¼. Herbicide applied to control. Scentless chamomile and perennial sow thistle are no longer present, issues June 24, 2016: Good establishment of grasses, native vegetation, willows, shrubs, and evergreen, consistent with off right of way vegetation cover issue No noxious weeds were identified within this tract. Recent NGTL pipeline construction ends at KP ROW has been recently disturbed from KP to This disturbed area will be monitored as a part of that pipeline s PCM program. KP ponding noted in 2014, no longer evident, issue August 19, 2016: meadow hawkweed was observed throughout ¼. Herbicide applied to control. Canada thistle, scentless chamomile, bull thistle, and perennial sow thistle no longer present, issues January 2017 Page 24

45 NW Treed Monitor vegetation growth in W6Drainage (D8) Monitor in 2013 and, if warranted, repair. SW Treed Reseed at KP and KP and monitor in Monitor vegetation growth in KP No Issues noted. KP Minor subsidence monitor in 2014 to determine if repairs are required. KP Removed all steel pegs and non-biodegradable material from seasonal drain. Re-distributed the cobble that is holding back water. Checked for depth of cover with hand probe prior to any shovel work to correct drainage and cobble being re-distributed. KP Rare Plant Area All rare plant areas are recovering very well June 19, % vegetation cover on ROW compared to off ROW control. Good establishment of willow, deciduous species along ROW. Natural regrowth of spruce noted along sections of ROW indicating effective, successful succession after disturbance. June Herbicide applied between KP and to control Thistle. July 23, 2014 Previously sprayed herbicide applied intermittently throughout this tract appears successful. Broad leafed species within areas sprayed showing signs of health degradation in the form of wilting and discoloration. June 19, 2014: Ephemeral draw (KP ) shows good vegetation proliferation. Minor subsidence on north and south banks. Possible minor erosion on north side of draw with good vegetation establishment within. Continue to monitor. Removed silt fencing stakes that were piled on east edge of ROW within draw. Cross drains functioning well with good vegetation with one exception, KP , which exhibits minor erosion, monitor. Removed steel pegs at this drainage. June 19, 2014: 90-95% vegetation cover on ROW compared to off ROW control. Good establishment of willow and deciduous species in sections along ROW. Cross drain functioning well within tract exhibiting good vegetation proliferation within Tall buttercup found within tract. Weeds were handpicked and bagged. Removed steel pegs from drainage. KP Diversion berm exhibits minor rill erosion, monitor. June 26, 2014 Tall buttercup present from kp to kp within rare plant area. Noxious weeds were handpicked. Continue to monitor. July 23, 2014 Previous remedial efforts (hand picking of buttercup) achieved desired control of noxious weeds. Buttercup was not identified within tract. Continue to monitor. June 5, 2015: Vegetation is 85-90% comparable to off ROW control. Vegetation consisting of native grasses, clover, poplar and willow species. Patch of scentless chamomile found within tract from KP to KP Recommend spraying. Minor erosion within cross drain at KP Drainage appears stable and exhibits good vegetation establishment; water is draining off ROW effectively. No further work required, issue is No subsidence evident within tract. July 10, 2015 intermittent herbicide application conducted to control Noxious weeds. August 30, 2015: Previous herbicide application throughout this tract appears successful. Visible signs of health degradation were noted in target species. A patch of perennial sow thistle at KP Recommend fall herbicide application. September 20, 2015 Intermittent herbicide application conducted to control perennial sow thistle and scentless chamomile. June 5, 2015: drainage stable and draining water off ROW effectively. Vegetation establishment is good within drainage. Subsidence on both north and south slopes remains as previously assessed in 2014 with good vegetation development, issue Erosion no longer evident at KP , issue June 9, 2015: Vegetation is 95% comparable to off ROW control. Areas of the tract exhibit good establishment of woody vegetation. No Noxious/Prohibited weeds observed. Intermittent patches of reduced vegetation along the ROW. Average vegetative cover in these areas is 70%. Continue to monitor. Cross drainages and seasonal drainages within the tract are functioning and well vegetated. An area of erosion rills was observed at Monitor. August 30, 2015 Noxious weeds were not observed in this tract and it was not previously sprayed in June 24, 2016: Good establishment of grasses, native vegetation, willows, aspen, shrubs, and evergreen, consistent with off right of way vegetation cover issue is A patch of Tall Buttercup was observed at KP Recommend herbicide application. July 14, 2016 herbicide application conducted (spot spraying) to control tall buttercup at KP August 19, 2016: patches of meadow hawkweed were observed throughout ¼. Herbicide applied to control. Canada thistle, scentless chamomile, and perennial sow thistle no longer present, issues resolved June 24, 2016 drainage exhibiting minor slumping, first noted in 2012, no change to conditions; no safety or pipe integrity concerns, with land capability comparable to adjacent lands. Soil conditions remain stable with good vegetation establishing in and around minor slumping, issues Minor rutting is evident attributed to recreational ATV activity. June 23, 2016: Vegetation is well established with desirable species throughout ROW. Good establishment of willows, wild rose bushes and poplar saplings. Vegetation cover issues noted in 2012 and 2015, no longer evident, issue No erosion or subsidence issues. Erosion previously noted at KP (2014 and 2015), (2012), and (2012) no longer evident, issues ATV ruts through tract. Tall buttercup identified in patches and intermittently throughout ROW. July 28, 2016 Tall buttercup with a lot of emerging plants was identified on East side of ROW at Herbicide was not applied due to proximity to rare plant populations. 2 bags of Tall buttercup were picked and bagged within the rare plant area to January 2017 Page 25

46 Rare Plant (northern moonwort) Tributary to Cutbank River (WC14) Tributary to Cutbank River (WC15) August 19, 2016: intermittent meadow hawkweed patches were observed throughout 1/4. Herbicide applied to control. No weeds observed within proximity to rare plant location. Although still present, tall buttercup was reduced in extent from approximately 450 m in 2014 to one location in KP to On August 8, 2013 Rare Plant Specialists visited the location and observed northern moonwort along the east boundary of the right-of-way as well as ascending grape fern. Resolved and successful: no further monitoring is recommended. Issue None. KP Removed all steel pegs and nonbiodegradable material from seasonal drain. Re-distributed the cobble that is holding back water. Checked for depth of cover with hand probe prior to any shovel work to correct drainage and cobble being re-distributed. None. KP Removed all steel pegs and nonbiodegradable material from seasonal drain. Re-distributed the cobble that is holding back water. Checked for depth of cover with hand probe prior to any shovel work to correct drainage and cobble being re-distributed. June 19, 2014 minor subsidence on north and south bank. Minor slumping evident along ditchline indicated by deeper ponding of water. Vegetation establishing on slopes. Minimal flow evident within tributary at time of assessment. June 19, 2014 minor slumping on north bank. ATV rutting evident on east end of tributary on edge of ROW. Exceptional vegetation establishment on both banks. Amphibians using tributary as habitat. Bed and bank appear stable at time of assessment. NW Treed None. June 19, 2014: 90% vegetation cover on ROW compared to off ROW control. Good establishment of willow and deciduous species along ROW. Tall buttercup found intermittently throughout tract. Weeds were hand-picked and bagged. Cross drains functioning well at time of assessment with no ponding and good vegetation establishment. Removed several steel pegs from straw waddles within tract. June 26, 2014 Tall buttercup present from kp to kp within rare plant area. Noxious weeds were handpicked. Continue to monitor. June 9, 2015: Well vegetated. - Minor flow observed. Banks are stabile with no erosion observed. Subsidence, previously noted, observed is well vegetated and consistent with previous condition. It is not inhibiting the recovery of the ROW. Issue No Noxious/Prohibited weeds observed. Pipeline markers are absent. Recommend installing. June 9, 2015: Well vegetated. Minor flow observed. Banks are stabile with no erosion observed. Subsidence, previously noted, observed is well vegetated and consistent with previous condition. It is not inhibiting the recovery of the ROW. Issue resolved - No Noxious/Prohibited weeds observed. Amphibians observed. Pipeline markers are absent. Recommend installing. June 9, 2015: Vegetation is 95% comparable to off ROW control. Rutting and erosion were not observed. Tall buttercup were picked and disposed of at KP and Monitor and implement additional weed control measures as required. July 10, 2015 intermittent herbicide application conducted to control tall buttercup from KP to August 30, 2015 Previous herbicide application throughout this tract appears successful. Visible signs of health degradation were noted in target species. No additional noxious weeds were identified. June 24, 2016: Tributary is stable and densely vegetated with minimal flow. No issues. Pipeline markers are absent. Recommend installing. September 14, 2016 Installed signs and marker posts on both sides of WC14, issue June 24, 2016: Tributary is stable and densely vegetated with minimal flow. No issues. Pipeline markers are absent. Recommend installing. September 14, 2016 Installed signs and marker posts on both sides of WC15, issue June 23, 2016: Vegetation is well established with desirable species throughout ROW. Good establishment of willows, wild rose bushes and poplar saplings. No erosion or subsidence issues. ATV ruts through tract. Tall buttercup identified in patches and intermittently throughout ROW. Recommend herbicide application. July 14, 2016 herbicide application conducted (spot spraying) to control tall buttercup. One oxeyed daisy was picked and bagged at Rare plant areas were identified and herbicide was not applied within proximity to the rare plant locations, weeds were handpicked within this area. January 2017 Page 26

47 Seasonal Drainage Rare Plant (northern moonwort) Monitor in 2013 and, if warranted, repair. SW Treed Monitor vegetation growth in KP Minor subsidence within drainage. No adverse effects noted, vegetation is excellent, flow is not affected. Monitor in 2014 to determine if repairs are required. KP Removed all steel pegs and nonbiodegradable material from seasonal drain. Re-distributed the cobble that is holding back water. Checked for depth of cover with hand probe prior to any shovel work to correct drainage and cobble being re-distributed. KP to On August 8, 2013 Rare Plant Specialists visited the location and observed one northern moonwort off the right-of-way along the west edge of the rightof-way boundary. Resolved and successful: no further monitoring is recommended. Issue KP Logging operation built a log and clay pad (approx. 5 meter) over the right-of-way in preparation of cut block on the west side of the ROW. Monitor in 2014 for impacts to ROW. July 23, 2014: Previous remedial efforts (hand picking of buttercup) achieved desired control of noxious weeds. Buttercup was not identified within tract. Continue to monitor. Scentless chamomile at KP , picked and bagged (1 plant). Continue to monitor. June 19, 2014 exceptional vegetation proliferation. Minor subsidence on south and north banks. Amphibians present within drainage using it as habitat. Minimal water movement at time of assessment. Removed spikes within erosion control matting, work-side of ROW. Silt fence remains, requires removal. July 14, 2014 Removed ~30m of silt fencing on North bank of drainage. June 20, 2014: 90-95% vegetation cover on ROW compared to off ROW control. Good establishment of willow, deciduous species along ROW Tall buttercup found within tract. Weeds were handpicked and bagged. Cross drains within tract functioning well within tract exhibiting good vegetation establishment. June 26, 2014 intermittent herbicide application conducted between KP and to control tall buttercup. July 23, 2014 Previously sprayed herbicide applied intermittently throughout this tract appears successful. Broad leafed species within areas sprayed showing signs of health degradation in the form of wilting and discoloration. June 9, 2015: Vegetation is 95% comparable to off ROW control. Cross drainages and seasonal drainages within the tract are functioning and well vegetated. Minor flow observed. Subsidence previously observed, first noted in 2012, was assessed as well vegetated and not posing an issue to the recovery of the ROW. Issue resolved Rutting and erosion were not observed. June 9, 2015: Vegetation is 95% comparable to off ROW control. There are areas with woody vegetation establishing. No erosion, rutting or subsidence observed. No Noxious/Prohibited weeds observed. July 10, 2015 Tall buttercup was observed and intermittent herbicide application was conducted to control from KP to August 30, 2015 Previous herbicide application throughout this tract appears successful. Visible signs of health degradation were noted in target species. No additional noxious weeds were identified. KP issue of logging operation crossing ROW, no evidence of logging operation noted, issue August 19, 2016: individuals of meadow hawkweed were observed throughout 1/4. Herbicide applied to control. No weeds observed within buffer at rare plant location at KP Scentless chamomile no longer present, issue June 23, 2016 Drainage stable and functioning. June 23, 2016: Vegetation is well established with desirable species throughout ROW vegetation cover issue is Good establishment of willows, wild rose bushes and poplar saplings. No erosion or subsidence issues. ATV ruts through tract. Tall buttercup identified in patches and intermittently throughout ROW. Recommend herbicide application. July 14, 2016 herbicide application conducted (spot spraying) to control tall buttercup. Herbicide was not applied within proximity to the rare plant locations, weeds were handpicked within this area. August 19, 2016 individual meadow hawkweed plants were observed throughout. Herbicide applied to control. January 2017 Page 27

48 Rare Plant (northern moonwort) KP to On August 8, 2013 Rare Plant Specialists visited the location and observed northern moonwort along the west boundary of the right-of-way. Resolved and successful: no further monitoring is recommended. Issue KP On August 8, 2013 Rare Plant Specialists visited the location and observed one ascending grape fern off the right-of-way along the west boundary. Resolved and successful: no further monitoring is recommended. Issue Rare Plant (ascending grape fern) Treed Bog Monitor wetland in Leave for natural recovery. June 20, 2014 exhibits good vegetation growth consisting of emergent species. Willows and deciduous species starting to advance in wetland throughout ROW. Exceptional growth of Sphagnum moss throughout wetland. Good depth of organic substrate in wetland indicates proper wetland functionality and stability. Up to 15cm of standing water present within bog at time of assessment, may be attributed to recent precipitation event. No sedimentation issues apparent within bog. No subsidence or erosion issues present within wetland. Abundance of amphibians using wetland as suitable habitat. No net loss of wetland function evident at time of assessment. June 9, 2015: Vegetation is 95% comparable to off ROW control. Woody vegetation establishing. Treed bog was found to be as described in last year s assessment, continue to monitor. September 13, 2016 This small treed bog is a shallow bowl with a seepage draining through the middle in an east-west direction. The seral stage vegetative growth (e.g. grasses, willow, and sphagnum moss) is well established throughout the length of the ROW in the wetland. There is no evidence of cross drainage hydrology issues. Recent logging activities to the NE may influence the amount of runoff draining through the wetland. The wetland is functional and no further monitoring required. Vegetation cover issue noted in 2012 is Rare Plant (leather grape fern) KP On August 8, 2013 Rare Plant Specialists visited the location and observed leather grape fern on the right-of-way. Resolved and successful: no further monitoring is recommended. Issue KP On August 8, 2013 Rare Plant Specialists visited the location and observed northern moonwort on the south slope along the creek on the right-of-way. Resolved and successful: no further monitoring is recommended. Issue Rare Plant (northern moonwort) January 2017 Page 28

49 Tributary to Cutbank River (WC16) NW Treed Monitor vegetation growth in Rare Plant (snakeskin liverwort) Rare Plant (Macloskey's violet) None. KP Removed all steel pegs and nonbiodegradable material from seasonal drain. Re-distributed the cobble that is holding back water. Checked for depth of cover with hand probe prior to any shovel work to correct drainage and cobble being re-distributed. KP On August 8, 2013 Rare Plant Specialists visited the location and did not observe snakeskin liverwort. Suitable habitat was observed at the site, indicating that mitigation was successful. Resolved and unsuccessful (as the target species was not observed): no further monitoring is recommended. Issue KP On August 8, 2013 Rare Plant Specialists visited the location and observed 20 Macloskey s violet (leaves only) on the north and south banks of the creek. Resolved and successful: no further monitoring is recommended. Issue June 20, 2014 good vegetation proliferation along both banks with slightly greater establishment on north bank. Minor subsidence evident on north and south banks. Minor slumping evident on ditchline indicated by greater ponding of water. Minimal flow within tributary at time of assessment. June 20, 2014: 90-95% vegetation cover on ROW compared to off ROW control. Good establishment of willow, deciduous species along ROW. Tall buttercup found within tract. Solitary weeds were hand-picked and bagged. June 26, 2014 intermittent herbicide application conducted between KP and to control tall buttercup and scentless chamomile. July 23, 2014 Previously sprayed herbicide applied intermittently throughout this tract appears successful. Broad leafed species within areas sprayed showing signs of health degradation in the form of wilting and discoloration. Grasses mainly unaffected. June 9, 2015: Well vegetated. Minor flow observed. Banks are stabile with no erosion observed. Subsidence, previously noted, observed and is not inhibiting the recovery of the ROW, issue Six tall buttercup were picked. Monitor. Pipeline markers are absent. Recommend installing. August 22, Mechanical weed control along ditch line and 5m north/south of the water crossing to control noxious weeds. June 9, 2015: Vegetation is comparable to off ROW % coverage as opposed to off ROW. Some small areas of less growth establishment. Tall Butter cup in extensive amounts from KP to KP on either side of WC 17, 18 and sporadically to the end of tract at Recommend herbicide application. Cross drains functioning and well vegetated. July 10, 2015 Intermittent herbicide application conducted to control tall buttercup from KP to August 30, 2015: Previous herbicide application throughout this tract appears successful. Visible signs of health degradation were noted in target species. A patch of perennial sow thistle remains at KP Recommend fall herbicide application. September 19, 2015 intermittent herbicide application conducted to control perennial sow thistle. June 24, 2016: Tributary is stable and densely vegetated with minimal to no flow. No issues. Pipeline markers are absent. Recommend installing. September 14, 2016: Installed signs and marker posts on both sides of WC16, issue Tall buttercup no longer present, issue June 24, 2016: Vegetation is well established with desirable species throughout ROW vegetation cover issue is Good establishment of willows, wild rose bushes and poplar saplings. No erosion or subsidence issues. ATV ruts through tract. Tall buttercup identified in patches and intermittently throughout ROW. Recommend herbicide application. July 14, 2016 herbicide application conducted (spot spraying) to control tall buttercup. Hand picking completed in proximity to rare plant areas. August 19, 2016: meadow hawkweed was observed from KP Herbicide applied to control. Perennial sow thistle no longer present, issue January 2017 Page 29

50 Tributary to Cutbank River (WC17) None. KP Minor subsidence monitor in 2014 to determine if repairs are required. KP Removed all steel pegs and nonbiodegradable material from seasonal drain. Re-distributed the cobble that is holding back water. Checked for depth of cover with hand probe prior to any shovel work to correct drainage and cobble being re-distributed. June 20, % vegetation cover on north bank and 75 80% vegetation cover on south bank with good willow and deciduous species proliferating. No subsidence or erosion issues within tributary. Moderate water flow within tributary at time of assessment. Amphibians using tributary as habitat. June 26, 2014 Tall buttercup present from kp to kp in extensive amount within 30m buffer of watercourse crossing and rare plant area. The watercourses involved include Tributary to Cutbank River WC 17 and Tributary to Cutbank River WC 18. Requires mechanical removal. July 4, 2014 Picked and bagged tall buttercup within 30m of watercourse. June 9, 2015: No erosion or subsidence on banks evident. Revetment posts functioning. Subsidence noted in 2013, no longer evident, issue bank vegetation establishment ~90%. Tall Butter cup in extensive amounts from KP to KP on either side of WC 17, 18 and sporadically to the end of tract at Recommend herbicide application. July 10, 2015 control implemented to address tall buttercup. August 20, 2015 A patch of tall buttercup remains at KP Recommend fall herbicide application. September 19, 2015 Intermittent herbicide application conducted to control tall buttercup. June 9, 2015: No erosion or subsidence on banks evident. Revetment posts functioning. Non biodegradable erosion fabric on South bank. bank vegetation establishment ~95%. June 24, 2016: Tributary stable and densely vegetated with minimal flow. No issues. Tall buttercup no longer present, issue Tributary to Cutbank River (WC18) None. KP Removed all steel pegs and nonbiodegradable material from seasonal drain. Re-distributed the cobble that is holding back water. Checked for depth of cover with hand probe prior to any shovel work to correct drainage and cobble being re-distributed. June 20, % vegetation cover on north bank and 80-85% vegetation cover on south bank with good willow and deciduous species proliferating. Minor subsidence evident on north bank. Moderate water flow within tributary at time of assessment. Amphibians using tributary as habitat. June 26, 2014 Tall buttercup present from kp to kp in extensive amount within 30m buffer of watercourse crossing and rare plant area. The watercourses involved include Tributary to Cutbank River WC 17 and Tributary to Cutbank River WC 18. Requires mechanical removal. July 4, 2014 Picked and bagged tall buttercup within 30m of watercourse. June 20, 2014: ~95% vegetation establishment as opposed to off ROW. Good establishment of native grasses across ROW. Deciduous species establishing. Cross drains functioning effectively with vegetation establishing. Tall buttercup and scentless chamomile located on ROW. June 26, 2014 intermittent herbicide application conducted between KP and to control tall buttercup and scentless chamomile. July 23, 2014: Previously sprayed herbicide applied intermittently throughout this tract appears successful. Broad leafed species within areas sprayed showing signs of health degradation in the form of wilting and discoloration. Grasses mainly unaffected. Scentless chamomile identified within extra workspace at KP adjacent the valve station. Area identified was not previously sprayed, control recommended. July 28, 2014 scentless chamomile was handpicked and bagged for disposal at KP Approximately 0.25 large garbage bags were picked from location. Intermittent herbicide application conducted to control scentless chamomile. September 19, 2014 Intermittent herbicide application conducted to control areas of Canada Thistle. June 24, 2016: Tributary stable and densely vegetated with minimal flow. No issues. Tall buttercup no longer present, issue SW Treed Monitor vegetation growth in June 9, 2015: Vegetation establishment 90-95% comparable to off ROW for majority of tract. Consists of grasses, clover, horsetail, bluebell, dandelion, cattail, milk vetch, Indian paintbrush, and rose Tall buttercup was identified throughout tract intermittently recommend herbicide application. Scentless Chamomile was not identified in assessments (noted in 2014). July 10, 2015 Intermittent herbicide application conducted to control tall buttercup. August 30, 2015 Previous herbicide application throughout this tract appears successful. Visible signs of health degradation were noted in target species. No additional noxious weeds were observed. June 24, 2016: Vegetation is well established with desirable species throughout ROW vegetation cover issue is Good establishment of willows, rosebushes and poplar saplings. No erosion or subsidence issues. ATV ruts through tract. Tall buttercup identified in patches and intermittently throughout ROW. Recommend herbicide application. Access road to valve site at KP is heavily infested with tall buttercup. Traffic from access road may possibly be transporting weed seeds onto ROW. July 14, 2016 herbicide application conducted (spot spraying) to control tall buttercup August 19, 2016: meadow hawkweed was observed throughout ¼. Herbicide applied to control. Scentless chamomile no longer present, issue January 2017 Page 30

51 Cutbank River Lateral Loop (Bald Mountain Section) Pipeline Project Appendix C Photos January 2017

52 Cutbank River Lateral Loop (Bald Mountain Section) Pipeline Project Appendix C Photo 1. Typical view of recent disturbance from paralleling new NGTL pipeline. The Project s ditchline is depicted with the black arrow. Photo 2. Good vegetation cover on ROW, looking north at KP Recent parallel NGTL construction is present on right side of Project ROW. January 2017 Page 1

53 Cutbank River Lateral Loop (Bald Mountain Section) Pipeline Project Appendix C Photo 3. Typical view of ROW within the NW W6. Photo 4. Excellent vegetation coverage through site of previous erosion repair at KP January 2017 Page 2

54 Cutbank River Lateral Loop (Bald Mountain Section) Pipeline Project Appendix C Photo 5. Typical view of ROW, note presence of woody vegetation at KP Photo 6. WC 17, looking north, excellent revegetation, stable bed and banks. January 2017 Page 3

55 Cutbank River Lateral Loop (Bald Mountain Section) Pipeline Project Appendix C Photo 7. View of wetland recovery at KP 3+650, looking south. Photo 8. View of wetland recovery at KP , looking north. January 2017 Page 4

Information for File # JTF

Information for File # JTF Information for File # 2013-04665-JTF Applicant Corps Contact Enbridge Energy, Limited Partnership Josh Fitzpatrick Address 1554 Highway 2, Suite 2, Two Harbors, MN 55616 E-Mail joshua.t.fitzpatrick@usace.army.mil

More information

ENBRIDGE GAS DISTRIBUTION INC. Proposed Relocation for Ninth Line, Markham and Whitchurch-Stouffville. Environmental Screening Report

ENBRIDGE GAS DISTRIBUTION INC. Proposed Relocation for Ninth Line, Markham and Whitchurch-Stouffville. Environmental Screening Report Page 1 of 18 ENBRIDGE GAS DISTRIBUTION INC. Proposed Relocation for Ninth Line, Markham and Whitchurch-Stouffville Environmental Screening Report July 2011 Page 2 of 18 Table of Contents 1.0 INTRODUCTION

More information

Stormwater Standards. Clackamas County Service District No. 1. Planting Guide for Buffers

Stormwater Standards. Clackamas County Service District No. 1. Planting Guide for Buffers Stormwater Standards Clackamas County Service District No. 1 APPENDIX B Planting Guide for Buffers Table of Contents Appendix B - Planting Guide for Buffers... Page B.1 General... 1 B.1.1 Introduction...

More information

Alberta policy and regulations for grassland reclamation criteria, evolution of the criteria from the 1995 version to today

Alberta policy and regulations for grassland reclamation criteria, evolution of the criteria from the 1995 version to today Alberta policy and regulations for grassland reclamation criteria, evolution of the criteria from the 1995 version to today Jody Spady on behalf of Reclamation Criteria Advisory Group (RCAG) Native Prairie

More information

Oil Sands Reclamation From the Ground Up : A Suncor Energy Perspective

Oil Sands Reclamation From the Ground Up : A Suncor Energy Perspective Oil Sands Reclamation From the Ground Up : A Suncor Energy Perspective Lelaynia Cox, RPF and Cecilia Jeje, PhD College of Alberta Professional Forest Technologists April 14, 2011 Overview Oil sands mining

More information

Evolution of Reclamation Practices in NE Alberta

Evolution of Reclamation Practices in NE Alberta Evolution of Reclamation Practices in NE Alberta Alfred Burk Reclamation and Remediation Coordinator CAPFT Edmonton April 14, 2011 Agenda Introduction to Cenovus Energy Reclamation in the Green Zone Forestry

More information

Soil Reclamation and Site Reinstatement

Soil Reclamation and Site Reinstatement APPENDIX 6 Soil Reclamation and Site Reinstatement Purpose To undertake soil reclamation, erosion protection, Site restoration and reinstatement, taking into account natural processes, operational requirements

More information

Decision Notice. Proposed Action

Decision Notice. Proposed Action Decision Notice Paving Weld County Road 105 USDA Forest Service Arapaho and Roosevelt National Forest and Pawnee National Grassland Pawnee National Grassland Ranger District Weld County, Colorado November

More information

Rule D Wetland and Creek Buffers

Rule D Wetland and Creek Buffers Rule D Wetland and Creek Buffers 1 Policy It is the policy of the Board of Managers to ensure the preservation of the natural resources, recreational, habitat, water treatment and water storage functions

More information

TRCA Field Staking Protocol December 2016

TRCA Field Staking Protocol December 2016 Page 1 of 6 TRCA Field Staking Protocol December 2016 This Protocol describes TRCA staff s current practice for field staking the physical top of bank, the physical toe of slope, and the limit of existing

More information

Environmental Protection Guidelines for Transmission Lines

Environmental Protection Guidelines for Transmission Lines Alberta Environment R&R/11-03 Environmental Protection Guidelines for Transmission Lines GENERAL This Guideline replaces Conservation and Information Letter 95-2 and the 1994 Guide for Transmission Lines.

More information

FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT

FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT Date June 20, 2018 Project Northern Natural Gas Company Northern Lights 2017 Expansion Project Rice, Sherburne, and Isanti Counties, Minnesota

More information

Methods, approaches, and procedures to minimize active agricultural land impacts during pipeline construction, surface restoration, and pipeline

Methods, approaches, and procedures to minimize active agricultural land impacts during pipeline construction, surface restoration, and pipeline Agricultural Impact Minimization Plan Methods, approaches, and procedures to minimize active agricultural land impacts during pipeline construction, surface restoration, and pipeline operation. PennEast

More information

Northeast Anthony Henday Drive Manning Freeway to Whitemud Drive Welcome to this Construction Information Session

Northeast Anthony Henday Drive Manning Freeway to Whitemud Drive Welcome to this Construction Information Session Manning Freeway to Whitemud Drive Welcome to this Construction Information Session Purpose To inform interested residents and businesses about the plans accommodation. Background: The Government of Alberta

More information

Urban Conservation Practice Physical Effects ESTABLISHMENT, GROWTH, AND HARVEST NUTRIENT MANAGEMENT

Urban Conservation Practice Physical Effects ESTABLISHMENT, GROWTH, AND HARVEST NUTRIENT MANAGEMENT NOT WELL 800 - Urban Stormwater Wetlands A constructed system of shallow pools that create growing conditions for wetland plants to lessen the impacts of stormwater quality and quantity in urban areas.

More information

Drainage Analysis-Newgate/Phelps & Hatchett Hill Road Areas Rev. 0 Erosion & Sediment Control Measures

Drainage Analysis-Newgate/Phelps & Hatchett Hill Road Areas Rev. 0 Erosion & Sediment Control Measures Drainage Analysis-Newgate/Phelps & Hatchett Hill Road Areas Rev. 0 Erosion & Sediment Control Measures 4.0 EROSION & SEDIMENT CONTROL MEASURES After performing the analysis summarized above, Burns & McDonnell

More information

Breakthrough Innovations

Breakthrough Innovations Breakthrough Innovations Project Title: Bioengineering for Stabilization of Critical Slopes Project Team: Lori Belz Principle Investigator John Benson Steve Kortuem Leo Holm Introduction: One of the problems

More information

UPLAND EROSION CONTROL, REVEGETATION, AND MAINTENANCE PLAN

UPLAND EROSION CONTROL, REVEGETATION, AND MAINTENANCE PLAN UPLAND EROSION CONTROL, REVEGETATION, AND MAINTENANCE PLAN 01/17/2003 VERSION UPLAND EROSION CONTROL, REVEGETATION, AND MAINTENANCE PLAN TABLE OF CONTENTS I. APPLICABILITY... 1 II. SUPERVISION AND INSPECTION...

More information

Meeting Agenda. City of Guelph. River Systems Advisory Committee. Agenda Items. Item 1, 2 and 3. Item 4 Ward to Downtown Pedestrian Bridge

Meeting Agenda. City of Guelph. River Systems Advisory Committee. Agenda Items. Item 1, 2 and 3. Item 4 Ward to Downtown Pedestrian Bridge Meeting Agenda City of Guelph River Systems Advisory Committee September 19, 2018 City Hall, Meeting Room B From 4:00 to 6:00 p.m. Meeting Chair: Mariette Pushkar Agenda Items Welcome to all Item 1, 2

More information

SECTION 6. Routine Maintenance Activity Details

SECTION 6. Routine Maintenance Activity Details SECTION 6 Routine Maintenance Activity Details 80. DEBRIS REMOVAL When Deadfall, and other objects, such as shopping carts, tires, appliances, and mattresses have accumulated in the drain. Why To prevent

More information

ADDENDUM TO BIOLOGICAL SCOPING SURVEY REPORT, BOTANICAL SURVEY AND WETLAND DELINEATION

ADDENDUM TO BIOLOGICAL SCOPING SURVEY REPORT, BOTANICAL SURVEY AND WETLAND DELINEATION ADDENDUM TO BIOLOGICAL SCOPING SURVEY REPORT, BOTANICAL SURVEY AND WETLAND DELINEATION FOR AVALON INN (APN 069-241-27 & -04) 1201 & 1211 NORTH MAIN STREET FORT BRAGG, CA MENDOCINO COUNTY prepared for:

More information

Methods, approaches, and procedures to minimize active agricultural land impacts during pipeline construction, surface restoration, and pipeline

Methods, approaches, and procedures to minimize active agricultural land impacts during pipeline construction, surface restoration, and pipeline Agricultural Impact Minimization Plan Methods, approaches, and procedures to minimize active agricultural land impacts during pipeline construction, surface restoration, and pipeline operation. PennEast

More information

Town of Essex Small Site Erosion Control Guide

Town of Essex Small Site Erosion Control Guide Town of Essex Small Site Erosion Control Guide Why do we need to protect against erosion? Water Quality: Erosion and the transport of sediment and pollutants impacts the water quality of nearby streams

More information

FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT

FEDERAL ENERGY REGULATORY COMMISSION FIELD INSPECTION REPORT FIELD INSPECTION REPORT Date September 19, 2018 Project Northern Natural Gas Company (Northern) Cedar Station Upgrade Project Dakota County, Minnesota Authority: Section 7(c) Personnel FERC Staff: Company

More information

Piles, Trenching, Inverters, Cables, Material Deliveries

Piles, Trenching, Inverters, Cables, Material Deliveries Agricultural Inspection Report General Information Project Name Albany Date of Inspection 20161012 Start/End Time 7:50 am Inspector s Name(s) Inspector s Title(s) Describe present phase of construction

More information

ST. MARY S SOIL CONSERVATION DISTRICT (SMSCD) AND DPW&T CONCEPT EROSION AND SEDIMENT CONTROL AND STORMWATER MANAGEMENT GUIDELINES AND CHECKLIST

ST. MARY S SOIL CONSERVATION DISTRICT (SMSCD) AND DPW&T CONCEPT EROSION AND SEDIMENT CONTROL AND STORMWATER MANAGEMENT GUIDELINES AND CHECKLIST St. Mary s Soil Conservation District 26737 Radio Station Way, Suite B Leonardtown, MD 20650 Phone: 301-475-8402 ext. 3 Fax: 301-475-8391 www.stmarysscd.com St. Mary s County Government Department of Public

More information

STREAM ALTERATION PRACTICES

STREAM ALTERATION PRACTICES STREAM ALTERATION PRACTICES Stream Diversion Channel SDC DEFINITION A temporary channel constructed to convey stream flow around in-stream construction. PURPOSE Stream diversion channels are used to allow

More information

/s/ Michael T. Loeffler. Michael T. Loeffler Senior Director, Certificates and External Affairs. Attachment. September 14, 2018.

/s/ Michael T. Loeffler. Michael T. Loeffler Senior Director, Certificates and External Affairs. Attachment. September 14, 2018. Northern Natural Gas Company P.O. Box 3330 Omaha, NE 68103-0330 402 398-7200 September 14, 2018 Via efiling Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington,

More information

C ity of Grande Prairie Development Services Department

C ity of Grande Prairie Development Services Department C ity of Grande Prairie Development Services Department FAIRWAY DEVELOPMENT OUTLINE PLAN OP 08 09 Approved April 6, 2009 Prepared by: Focus Corporation Table of Contents 1.0. Introduction 2 3 1.1. Plan

More information

Caledon Villas Corp. c/o Mr. John Spina 55 Blue Willow Drive Woodbridge, ON L4L 9E8 May 14, Floodplain Characteristics, Old Church Road

Caledon Villas Corp. c/o Mr. John Spina 55 Blue Willow Drive Woodbridge, ON L4L 9E8 May 14, Floodplain Characteristics, Old Church Road Caledon Villas Corp. c/o Mr. John Spina 55 Blue Willow Drive Woodbridge, ON L4L 9E8 May 14, 2013 Re: Floodplain Characteristics, Old Church Road This letter serves to confirm that I, Linda Sober, have

More information

Erosion Control for Home Builders in the. City of Jacksonville

Erosion Control for Home Builders in the. City of Jacksonville Erosion Control for Home Builders in the City of Jacksonville Eroding construction sites are a leading cause of water quality problems in Jacksonville. For every acre under construction, about a dump truck

More information

WETLAND SOD u Bare Root Wetland Plants u Deep Rooted Willows u Coir Logs u Native Trees & Shrubs u Habitat Islands u Custom Growing

WETLAND SOD u Bare Root Wetland Plants u Deep Rooted Willows u Coir Logs u Native Trees & Shrubs u Habitat Islands u Custom Growing WETLAND SOD u Bare Root Wetland Plants u Deep Rooted Willows u Coir Logs u Native Trees & Shrubs u Habitat Islands u Custom Growing 2009 PROJECT HIGHLIGHTS The following 10 projects highlight the interesting

More information

7.0 SOCIAL, ECONOMIC, AND ENVIRONMENTAL ISSUES

7.0 SOCIAL, ECONOMIC, AND ENVIRONMENTAL ISSUES 7.0 SOCIAL, ECONOMIC, AND ENVIRONMENTAL ISSUES The following list of social, economic, and environmental issues have been identified based on a preliminary inventory of resources in the project area, an

More information

STORM SEWER OUTFALLS AND CONNECTING OUTFALL CHANNELS. General Submission Requirements

STORM SEWER OUTFALLS AND CONNECTING OUTFALL CHANNELS. General Submission Requirements COMPLETE APPLICATION CHECKLIST Jan 2016 STORM SEWER OUTFALLS AND CONNECTING OUTFALL CHANNELS The following checklist has been compiled to assist the applicant in preparing their application for approval

More information

MARBLE RIVER WIND POWER PROJECT Agricultural Protection Measures

MARBLE RIVER WIND POWER PROJECT Agricultural Protection Measures MARBLE RIVER WIND POWER PROJECT Siting Considerations 1. Locate access roads and, to the extent allowed by local laws, wetlands and topography, individual wind turbines and other structures along field

More information

STREAM BANK STABILIZATION THORPS MORTIMER RECREATION AREA Grandfather Ranger District SITE LOCATION & DRAINAGE AREA

STREAM BANK STABILIZATION THORPS MORTIMER RECREATION AREA Grandfather Ranger District SITE LOCATION & DRAINAGE AREA STREAM BANK STABILIZATION THORPS CREEK @ MORTIMER RECREATION AREA SITE LOCATION & DRAINAGE AREA SITE LOCATION Drainage Area = 1.14 sq. miles STREAM BANK STABILIZATION THORPS CREEK @ MORTIMER RECREATION

More information

Alternative Route Selection

Alternative Route Selection Alternative Route Selection Multiple routes are developed within the Alternative Corridors Developed by Project Team taking into account all information gathered to date Buildings St. Vital Station to

More information

Lake Nokomis Shoreline Enhancement Project

Lake Nokomis Shoreline Enhancement Project Lake Nokomis Shoreline Enhancement Project Community Meeting 2 February 13, 2018 Agenda Current Problems Project Goals Project Status Existing Conditions Community Input Draft Schematic Design Long-term

More information

MAIN ROADS Western Australia COALFIELDS HIGHWAY PROJECTS ROADSIDE REVEGETATION MANAGEMENT

MAIN ROADS Western Australia COALFIELDS HIGHWAY PROJECTS ROADSIDE REVEGETATION MANAGEMENT MAIN ROADS Western Australia COALFIELDS HIGHWAY PROJECTS ROADSIDE REVEGETATION MANAGEMENT Presentation - South West Region - Alan Grist, Project Manager, Environment (November 2015) Protecting and enhancing

More information

WQ-23 MOUNTAINOUS AND STEEP SLOPE SITES

WQ-23 MOUNTAINOUS AND STEEP SLOPE SITES Greenville County Technical Specification for: WQ-23 MOUNTAINOUS AND STEEP SLOPE SITES 1.0 Mountainous and Steep Slope Sites 1.1 Description The geographic locations of portions of Greenville County are

More information

STREAM BUFFERS

STREAM BUFFERS 88-415 STREAM BUFFERS 88-415-01 PURPOSE In the Kansas City region and throughout the nation, vegetated stream buffers have been clearly shown to protect stream stability and related infrastructure, improve

More information

Worksheet #14 Water Runoff Management

Worksheet #14 Water Runoff Management Water Runoff Management Use this worksheet to assess how well your property minimizes the potential for water runoff and property damage.. Why should you be concerned? What can you do? Rural runoff, also

More information

Existing Conditions and Environmental Consequences Floodplains

Existing Conditions and Environmental Consequences Floodplains 3.9 Environmental Consequences 3.8 3.8.1 WHAT ARE FLOODPLAINS? are low-lying areas adjacent to rivers, streams, and other waterbodies that are susceptible to inundation (flooding) during rain events. These

More information

Information for File # ARC

Information for File # ARC Information for File # 2015-02781-ARC Applicant Corps Contact Enbridge Energy, Limited Partnership Andrew R Chambers Address 600 South Lake Avenue, Suite 211, Duluth, MN 55802 E-Mail Andrew.R.Chambers@usace.army.mil

More information

Surface Coal Mining and Reclamation in ND. Guy Welch ND Public Service Commission

Surface Coal Mining and Reclamation in ND. Guy Welch ND Public Service Commission Surface Coal Mining and Reclamation in ND Guy Welch ND Public Service Commission Surface Coal Mines in North Dakota Approximately 1500 acres are disturbed each year History of Reclamation in ND First surface

More information

OCEAN POND COTTAGE DEVELOPMENT PLAN

OCEAN POND COTTAGE DEVELOPMENT PLAN Edinburgh Group Limited 36 Cabot Avenue St. John s, NL A1A 5L9 OCEAN POND COTTAGE DEVELOPMENT PLAN ENVIRONMENTAL ASSESSMENT REGISTRATION JULY, 2014 TABLE OF CONTENTS Page 1. NAME OF UNDERTAKING... 1 2.

More information

Rangeland Health (Rangeland only)

Rangeland Health (Rangeland only) Chapter 20 Rangeland Health (Rangeland only) 20.1 Overview This chapter covers data elements relating to Rangeland Health. Rills Infiltration and Runoff Waterflow patterns Compaction Layer Pedestals and/or

More information

Clopyralid and Compost

Clopyralid and Compost Clopyralid and Compost INTRODUCTION Weed-control products containing clopyralid have been used safely and effectively for more than 14 years. Recently, incidents have been reported in which clopyralid

More information

Station Street/Haig Road Extension Environmental Assessment (EA)Study. Welcome

Station Street/Haig Road Extension Environmental Assessment (EA)Study. Welcome Station Street/Haig Road Extension Environmental Assessment (EA)Study Welcome Welcome to this Public Information Centre (PIC) meeting. Please record your attendance and obtain a comment sheet at the registration

More information

Plan of Development Mountain Valley Pipeline Project. APPENDIX M Winter Construction Plan

Plan of Development Mountain Valley Pipeline Project. APPENDIX M Winter Construction Plan APPENDIX M October 20, 2017 Appendix M Prepared by: October 20, 2017 TABLE OF CONTENTS 1.0 INTRODUCTION... M-1 2.0 STABILIZATION/WINTERIZATION... M-2 3.0 EROSION AND SEDIMENT CONTROL MEASURES... M-3 4.0

More information

Operations and Maintenance Plan

Operations and Maintenance Plan Civil Engineering Land Surveying Environmental Consulting Landscape Architecture Operations and Maintenance Plan for Solar Panel Facility Haverhill, MA Prepared By: Hancock Associates #19168 Prepared For:

More information

POST-FIRE RESTORATION Dos and Don ts

POST-FIRE RESTORATION Dos and Don ts POST-FIRE RESTORATION Dos and Don ts USDA Natural Resources Conservation Service The NRCS/RCD office is located at: 744 LA GUARDIA ST BLDG A SALINAS, CA 93905-3354 (831) 424-1036 (NRCS) (831) 424-1036

More information

City of Grande Prairie Development Services Department KENNEDY DEVELOPMENTS LTD. OUTLINE PLAN OP-09-01

City of Grande Prairie Development Services Department KENNEDY DEVELOPMENTS LTD. OUTLINE PLAN OP-09-01 City of Grande Prairie Development Services Department KENNEDY DEVELOPMENTS LTD. OUTLINE PLAN OP-09-01 July 27, 2009 TABLE OF CONTENTS 1.0 Introduction... 1 1.1 Plan Area Location & Context... 1 1.2 Ownership

More information

Town of Vershire Road Erosion Inventory Report

Town of Vershire Road Erosion Inventory Report Town of Vershire Road Erosion Inventory Report Taylor Valley Road. Photo taken by TRORC staff. Prepared by: 128 King Farm Road Woodstock, VT 05091 Inventory and report funded by the Vermont Agency of Transportation

More information

ME DOT Route 3. File No.: City and State: Bar Harbor, ME

ME DOT Route 3. File No.: City and State: Bar Harbor, ME ME DOT Route 3 File No.: 199600361 City and State: Bar Harbor, ME General Impacts: 0.28 acre tidal emergent 0.77 acre non-tidal forested 0.15 acre non-tidal emergent 0.51 acre non-tidal scrub-shrub Functions

More information

Restoration of Riparian Buffer at the Former Smelt Hill Dam Site, Falmouth, Maine

Restoration of Riparian Buffer at the Former Smelt Hill Dam Site, Falmouth, Maine Restoration of Riparian Buffer at the Former Smelt Hill Dam Site, Falmouth, Maine Final Report June 30, 2006 Page 1 of 16 I. Project Title Restoration of Riparian Buffer at the Former Smelt Hill Dam Site,

More information

SUPPORTING DOCUMENT STORMWATER POLLUTION PREVENTION PLAN (SWPPP) NARRATIVE

SUPPORTING DOCUMENT STORMWATER POLLUTION PREVENTION PLAN (SWPPP) NARRATIVE SUPPORTING DOCUMENT STORMWATER POLLUTION PREVENTION PLAN (SWPPP) NARRATIVE Please complete this narrative form and submit with your SWPPP drawings. Refer to Kitsap County Stormwater Design Manual Vol.

More information

PERMANENT SEEDING. Overview of Sedimentation and Erosion Control Practices. Practice no. 6.11

PERMANENT SEEDING. Overview of Sedimentation and Erosion Control Practices. Practice no. 6.11 Overview of Sedimentation and Erosion Control Practices Practice no. 6.11 PERMANENT SEEDING Permanent vegetation controls erosion by physically protecting a bare soil surface from raindrop impact, flowing

More information

319 Grant: Baker Creek & Centenary Creek Restoration Initiative

319 Grant: Baker Creek & Centenary Creek Restoration Initiative 319 Grant: Baker Creek & Centenary Creek Restoration Initiative Objectives: Overview of Watershed Characteristics: Discussion of Project Tasks: Discussion of Watershed Management Plan: Presented by: Erich

More information

MEMORANDUM OF BOG TURTLE HABITAT INVESTIGATION

MEMORANDUM OF BOG TURTLE HABITAT INVESTIGATION MEMORANDUM OF BOG TURTLE HABITAT INVESTIGATION 410-728-2900 Fax: 410-728-3160 www.rkk.com To: From: CC: U.S. Fish and Wildlife Service, Pennsylvania Fish and Boat Commission Jennifer A Ottenberg Miller,

More information

Design Considerations for Open Channel and Detention Pond Design. Howard Redfearn, City of Mansfield

Design Considerations for Open Channel and Detention Pond Design. Howard Redfearn, City of Mansfield Design Considerations for Open Channel and Detention Pond Design Howard Redfearn, City of Mansfield Previous Experience/Criteria/Maintenance Issues New Criteria Discussion Overview Where is Mansfield?

More information

Alternative Routes. St. Vital to La Verendrye Station - Southern Loop Transmission Corridor. 20 different segments 4 segments common to all routes

Alternative Routes. St. Vital to La Verendrye Station - Southern Loop Transmission Corridor. 20 different segments 4 segments common to all routes Alternative Routes St. Vital to La Verendrye Station - Southern Loop Transmission Corridor In a fixed right-of-way St. Vital to Letellier Station 20 different segments 4 segments common to all routes Goal

More information

COVER PAGE. Observations on Morgan County wetland restoration. 28 December 2006

COVER PAGE. Observations on Morgan County wetland restoration. 28 December 2006 COVER PAGE Observations on Morgan County wetland restoration 28 December 2006 John K. Tucker (Research Scientist) Principal Investigator: Great Rivers Field Station Illinois Natural History Survey 8450

More information

RECOMMENDED BEST MANAGEMENT PRACTICES FOR RESTORATION OF WETLANDS AFTER TEMPORARY IMPACTS

RECOMMENDED BEST MANAGEMENT PRACTICES FOR RESTORATION OF WETLANDS AFTER TEMPORARY IMPACTS RECOMMENDED BEST MANAGEMENT PRACTICES FOR RESTORATION OF WETLANDS AFTER TEMPORARY IMPACTS Prepared in partial fulfillment of a U.S. Environmental Protection Agency State Wetland Program Development Grant

More information

Section 3 Non-Structural BMPs

Section 3 Non-Structural BMPs 3.1 Stream Buffers A stream buffer or stream setback is a designated area around a stream, lake, or wetland left in a natural, densely vegetated state so as to protect the receiving water quality and provide

More information

Phase I Ecological Network Report Terms of Reference

Phase I Ecological Network Report Terms of Reference Phase I Ecological Network Report Terms of Reference INTRODUCTION In 2007, the City of Edmonton created a new Natural Area Systems Policy (C-531) and a strategic plan, Natural Connections. Together, these

More information

APPENDIX K WINDSOR OFFICIAL PLAN

APPENDIX K WINDSOR OFFICIAL PLAN CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT Replacement Span and Plaza Expansion APPENDIX K WINDSOR OFFICIAL PLAN Avalon Consulting Professionals of Ontario,

More information

PROPOSED DRAINAGE PATTERNS

PROPOSED DRAINAGE PATTERNS 1121 1118.50 Basin Floor 1120 1119 0 N 100 200 PROPOSED DRAINAGE PATTERNS Deroiser Drive Riverwood Drive County 260 0 100 200 Project Name: Riverwood Drive LITTLE FALLS TOWNHOMES Project Location: LITTLE

More information

Homeowners Guide to Stormwater BMP Maintenance

Homeowners Guide to Stormwater BMP Maintenance Homeowners Guide to Stormwater BMP Maintenance What You Need to Know to Take Care of Your Property Rain Barrel Dry Well Rain Garden Pervious Asphalt Porous Pavers City of El Monte Stormwater BMP Management

More information

SOIL EROSION AND SEDIMENT CONTROL

SOIL EROSION AND SEDIMENT CONTROL SOIL EROSION AND SEDIMENT CONTROL SECTION 1: AUTHORITY, TITLE AND PURPOSE 11. STATUTORY AUTHORIZATION This ordinance is adopted pursuant to the provisions of the Federal Water Pollution Control Act 86

More information

REPORT AND SPECIFICATION FOR RESTORATION WORKS ON NELLIES GLEN ROAD and THE 6 - FOOT TRACK NELLIES GLEN

REPORT AND SPECIFICATION FOR RESTORATION WORKS ON NELLIES GLEN ROAD and THE 6 - FOOT TRACK NELLIES GLEN REPORT AND SPECIFICATION FOR RESTORATION WORKS ON NELLIES GLEN ROAD and THE 6 - FOOT TRACK NELLIES GLEN Prepared for Crown Lands, Parramatta DEPARTMENT OF LANDS SOIL CONSERVATION SERVICE Greater Metropolitan

More information

Proposed St. Vital Transmission Complex

Proposed St. Vital Transmission Complex Proposed St. Vital Transmission Complex Round 2 Preferred Route for the St. Vital to Letellier Line What is it? Manitoba Hydro is proposing construction of two 230-kilovolt (kv) transmission lines to improve

More information

Chapter 4 - Preparation of Stormwater Site Plans

Chapter 4 - Preparation of Stormwater Site Plans Chapter 4 - Preparation of Stormwater Site Plans The Stormwater Site Plan is the comprehensive report containing all of the technical information and analysis necessary for the City to evaluate a proposed

More information

Cedar Niles Future Park Site Wetland #1

Cedar Niles Future Park Site Wetland #1 Date: October 20, 2014 Site: Landowner: Johnson County Parks Designer: Thomas R. Biebighauser Individuals Present: Thomas R. Biebighauser, Dr. Eliodora Chamberlain (US EPA), Jason Daniels (US EPA), Jeannette

More information

NORTHEAST RIVER CROSSING FUNCTIONAL PLANNING STUDY

NORTHEAST RIVER CROSSING FUNCTIONAL PLANNING STUDY WELCOME Northeast River Crossing Functional Planning Study Phase 2 Public Meeting 4 to 8 PM Informal drop-in format and discussion tables Meeting Purpose Introduce the Northeast River Crossing Functional

More information

Weston s Wetlands, Stormwater, & Open Space

Weston s Wetlands, Stormwater, & Open Space Weston s Wetlands, Stormwater, & Open Space Weston s Wetlands, Stormwater, & Open Space Conservation Commission Role and Responsibilities Laws that protect wetlands What residents can do to protect wetlands

More information

Juneau Watershed Partnership

Juneau Watershed Partnership Juneau Watershed Partnership Native Plant Resource Center Final Report A Partners for Fish and Wildlife Project Prepared for: U.S. Fish and Wildlife Service For Grant #F11C00552 Prepared by: The Juneau

More information

5.0 Storm Water Landscape Guidance Introduction

5.0 Storm Water Landscape Guidance Introduction 5.0 Storm Water Landscape Guidance Introduction Landscaping is a critical element to improve both the function and appearance of storm water management practices. Integrated storm water landscapes can

More information

Zoning Ordinance Article 3

Zoning Ordinance Article 3 Article 3 Natural Resources Protection Section 301 Natural Resources Protection 301.1. Purpose - The following natural resources protection standards are established to protect the public health, safety

More information

SOIL EROSION COMBATING IS ESSENTIAL IN ORDER TO CONSERVE OUR VALUABLE SOIL RESOURCES

SOIL EROSION COMBATING IS ESSENTIAL IN ORDER TO CONSERVE OUR VALUABLE SOIL RESOURCES SOIL EROSION COMBATING IS ESSENTIAL IN ORDER TO CONSERVE OUR VALUABLE SOIL RESOURCES A. Introduction - Land is also a precious resource. Land is needed for agriculture and occupation. Land is under pressure

More information

Environmental As-built Report for the. Enbridge Pipelines Inc. Edmonton to Hardisty Pipeline Project

Environmental As-built Report for the. Enbridge Pipelines Inc. Edmonton to Hardisty Pipeline Project Page 1 of 164 Environmental As-built Report for the Enbridge Pipelines Inc. January 2017 Page 2 of 164 Executive Summary Enbridge Pipelines Inc. (Enbridge) applied to the National Energy Board (NEB) for

More information

City of Stoughton Erosion Control Permit Application (effective 2/6/2018)

City of Stoughton Erosion Control Permit Application (effective 2/6/2018) City of Stoughton Erosion Control Permit Application (effective 2/6/2018) Incomplete applications will not be accepted Project Name: Address of subject property: Landowner Name(s): Applicant Name: Landowner

More information

PRELIMINARY DRAINAGE REPORT LATHAM 200 MMSCFD GAS PROCESSING PLANT

PRELIMINARY DRAINAGE REPORT LATHAM 200 MMSCFD GAS PROCESSING PLANT PRELIMINARY DRAINAGE REPORT LATHAM 200 MMSCFD GAS PROCESSING PLANT LOTS B, RECORDED EXEMPTION 1211-2-1, RECX13-0096 LOCATED IN THE NORTH 1/2 OF SECTION 2, TOWNSHIP 3 NORTH, RANGE 66 WEST, 6 TH PRINCIPAL

More information

Stormwater and Your Rain Garden

Stormwater and Your Rain Garden Stormwater and Your Rain Garden When rain falls on natural areas, such as a forest or meadow, it is slowed down, filtered by soil and plants, and allowed to soak back into the ground. When rain falls on

More information

FirstLight Power Shoreline Management Manual Sustainable Shoreline Designs: From Long Island to Lake Erie Webinar Series

FirstLight Power Shoreline Management Manual Sustainable Shoreline Designs: From Long Island to Lake Erie Webinar Series FirstLight Power Shoreline Management Manual Sustainable Shoreline Designs: From Long Island to Lake Erie Webinar Series Presented by Jason Williams, PLA, NCI February 19, 2017 Introduction Lakes (impoundments)

More information

Wellsite Clay Pad Removal and Peat Inversion

Wellsite Clay Pad Removal and Peat Inversion Wellsite Clay Pad Removal and Peat Inversion TECHNICAL NOTE #24 PEATLAND RESTORATION (JANUARY 2012) UPDATED: JUNE 2017 INTRODUCTION Reclaiming in-situ well pads built in peatland presents many challenges.

More information

Department of Agriculture. Conservation Service. United States. Natural Resources REVISED 8/26/16

Department of Agriculture. Conservation Service. United States. Natural Resources REVISED 8/26/16 GENERAL NOTES: SYMBOL LEGEND 1. All work shall comply with the constriction specifications, drawings, project-specific quality assurance plan and other contract requirements. 2. All notes on the drawings

More information

GUIDE: Restoration Assessment Form Preface Instructions

GUIDE: Restoration Assessment Form Preface Instructions GUIDE: Restoration Assessment Form March 24, 2006 Developed by Kerry Hecker and Chet Neufeld Last Mountain Lake National Wildlife Area and Migratory Bird Sanctuary Environment Canada- Canadian Wildlife

More information

PLAN SUBMITTER'S CHECKLIST

PLAN SUBMITTER'S CHECKLIST Page 1 of 8 PLAN SUBMITTER'S CHECKLIST FOR EROSION AND SEDIMENT CONTROL PLANS Please fill in all blanks and reference the plan sheets/pages where the information may be found, where appropriate, or write

More information

Level 1 Downstream Analysis

Level 1 Downstream Analysis Level 1 Downstream Analysis Newcastle Way Apartments Newcastle, Washington King County April 14, 2014 Revised July 10, 2014 Prepared by: Dean A. Furr, P.E. Reviewed by: Donald Scarberry, P.E. Coffman Engineering,

More information

CITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA (360) (360) (FAX)

CITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA (360) (360) (FAX) CITY OF TUMWATER 555 ISRAEL RD. SW, TUMWATER, WA 98501 (360) 754-4180 (360) 754-4126 (FAX) Email: cdd@ci.tumwater.wa.us APPENDIX II-C SHORT FORM CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN (SWPPP)

More information

Information for File MMJ Main Stem Bassett Creek Restoration Project

Information for File MMJ Main Stem Bassett Creek Restoration Project Information for File 2013-03866-MMJ Main Stem Bassett Creek Restoration Project Applicant: Minneapolis Park and Recreation Board (MPRB) Corps Contact: Melissa Jenny Address: Corps of Engineers, St. Paul

More information

PICTURE CANYON Planning Riparian-Wetland Refugia in an Urban Setting

PICTURE CANYON Planning Riparian-Wetland Refugia in an Urban Setting PICTURE CANYON Planning Riparian-Wetland Refugia in an Urban Setting Rio De Flag Existing Conditions. Ephemeral stream; Limited riparian plants, habitats.. & Opportunities Water (effluent) available Restore

More information

MANUAL OF DESIGN, INSTALLATION, AND MAINTENANCE REQUIREMENTS FOR STORMWATER MANAGEMENT PLANS

MANUAL OF DESIGN, INSTALLATION, AND MAINTENANCE REQUIREMENTS FOR STORMWATER MANAGEMENT PLANS MANUAL OF DESIGN, INSTALLATION, AND MAINTENANCE REQUIREMENTS FOR STORMWATER MANAGEMENT PLANS May 2007 SECTION 1 Responsibility of Applicant TABLE OF CONTENTS A. Stormwater Management Plan Required Information

More information

Key elements : Filter Strips must be designed within parameters required by the Fort Wayne s Development Standards/Criteria Manual.

Key elements : Filter Strips must be designed within parameters required by the Fort Wayne s Development Standards/Criteria Manual. 4.4. Filter Strips Filter Strips are densely vegetated lands that treat sheet flow storm water from adjacent pervious and impervious areas. They function by slowing runoff, trapping sediment and pollutants,

More information

PG&E WINTERS GAS OPERATIONS AND TECHNICAL TRAINING CENTER

PG&E WINTERS GAS OPERATIONS AND TECHNICAL TRAINING CENTER PG&E WINTERS GAS OPERATIONS AND TECHNICAL TRAINING CENTER CEQA scoping Meeting March 19 th, 2014 Winters City Council Chambers - 6:30 pm AGENDA FOR THE MEETING 6:30 Welcome (John Donlevy) 6:40 Overview

More information

Leduc Industrial Outline Plan SE W4

Leduc Industrial Outline Plan SE W4 Leduc Industrial Outline Plan SE 1-50-25-W4 Within the North Leduc Industrial ASP Prepared for: Leduc Energy Park Ltd. Prepared by: Stantec Consulting Ltd. File No. 1161 104655 V5 Table of Contents 1.0

More information

HAMILTON COUNTY URBAN CONSERVATION ASSOCIATION

HAMILTON COUNTY URBAN CONSERVATION ASSOCIATION HAMILTON COUNTY URBAN CONSERVATION ASSOCIATION www.hamiltoncountyuca.org Prairie Restoration Maintenance and Weed Control One of the many benefits of prairie restoration projects is the low maintenance

More information

Rain Gardens. A Welcome Addition to Your Landscape

Rain Gardens. A Welcome Addition to Your Landscape Rain Gardens A Welcome Addition to Your Landscape Where Does The Rainwater Go? Naturally, forests provide a way for rainwater to percolate into the soil, filtering pollutants while trees are allowed to

More information

OP Council Resolution June 16, Planning and Development Services

OP Council Resolution June 16, Planning and Development Services OP-08-01 Council Resolution June 16, 2008 Planning and Development Services Kingsgate Landing Outline Plan Table of Contents 1.0 Introduction 1 1.1 Purpose of Plan 1 1.2 Plan Area Location 1 1.3 Ownership

More information