TRANSPORTATION PROJECT UPDATE GREENSBORO URBAN AREA NCDOT
|
|
- Christine McDaniel
- 6 years ago
- Views:
Transcription
1 TRANSPORTATION PROJECT UPDATE GREENSBORO URBAN AREA This newsletter provides the latest scheduling and status information for major transportation projects in the Greensboro Urban Area - an area covering the City of Greensboro and much of Guilford County with the exception of Burlington/Gibsonville/Whitsett area in the east and the High Point/Jamestown area in the southwest. Major and City of Greensboro projects are included. Greensboro Urban Loop Spring 2015 Remaining sections of the Urban Loop are fully funded through recent determinations by the State s Strategic Transportation Investments Law. Southern Urban Loop (I-2402) I-85 open to traffic February Western Urban Loop (U-2524) The Western Urban Loop will extend from I-85 to Lawndale Drive. I-40 to Bryan Boulevard Open to traffic December Designated as I-73 and Future I-840. I-85 to I-40 Open to traffic February Designated as I-73 Future I-840. Northern/Eastern Urban Loop (U-2525) The Eastern Urban Loop will extend from I-85/I-40 to Lawndale Drive. US 70 to I-40/I-85 near McConnell Road. Open to traffic May Designated as Future I-840 and Future I-785. Battleground Avenue to Lawndale Drive Right-of-way acquisition underway. Construction to start late Bryan Boulevard to Battleground Avenue Construction completion in early US 29 to Lawndale Drive Right-of-way acquisition to start in Construction to start in US 70 to US 29 Construction complete in late project construction schedules reflect the Draft State Transportation Improvement Program (STIP) released in November 2014 and the Metropolitan Transportation Improvement Program (MTIP). For more information on the STIP & MTIP go to and For more information on active projects call Division 7 at (336) For active City of Greensboro projects call the Greensboro Engineering & Inspections Department at (336) For plans, proposals, and future transportation needs contact the Greensboro Department of Transportation at (336) To view the major projects and to determine their proximity to an address in the MPO area go to
2 NC 68 / US 220 Connector NC 68 / US 220 Connector (R-2413C) runs along existing US 220 from just south of the Haw River to the NC 68 intersection in Rockingham County. Then (R-2413A/B) follows a new alignment from US 220 just south of the Haw River, across NC 150, Brookbank Road, Bunch Road, and Alcorn Road and connect to NC 68 north of Pleasant Ridge Road. C o n s t r u c t i o n complete late High Point Road I-73 Connector I-73 Connector (I-5110) will connect R-2413AB at NC 68 with I-73 east of the airport. I-5110 will complete a major portion of I-73 in Guilford County from Rockingham County to US 220 / Future I-73 just south of Greensboro. Includes a taxiway bridge for airport. Construction complete late High Point Road (U-2412) will be widened and partially relocated from Hilltop Road to US 311 in High Point. Sections will be relocated around the old Jefferson Pilot Headquarters and south of the center of Jamestown. The interchange with the Urban Loop will be the area s first Diverging Diamond. Section A US 311 Bypass to Vickery Chapel Road. Construction unfunded. Section B Vickery Chapel to Groometown/Hilltop. Under construction with completion in U-2524AE (Urban Loop Interchange) under construction with U-2412 Section B. Completion in US 421 Interchanges US 220 Widening US 220 (R-2309AB) will be widened to four lanes with a median from Horse Pen Creek Road to Winfree Road in Summerfield. Construction complete late has constructed one of two new interchanges on US 421. (R-2612A) at Woody Mill Road Project complete. (R-2612B) at Neelley Road; Under construction, completion late
3 Gallimore Dairy Road The first section (U-4015B) from Market Street to I-40 is complete. (U-4015A) from I-40 to NC 68 is currently under study. Right-of-way and construction unfunded. McLeansville Road Increases in freight trains and the speeds of passenger trains has lead to the development of various track improvements in North Carolina by s Rail Division. McLeansville Road s at-grade crossing is being replaced with a grade separated crossing to facilitate the current and future train volumes. NC 68 NC 68 (W-5514) is being widened to three lanes from Harrell Road to Bartonshire Road to reduce traffic accidents. Construction completion Spring NC 62 NC 68 (W-5305) intersection with Groometown Road is being improved and a slip lane for southbound Groometown Road onto westbound NC 62 is to be removed. Construction completion Fall Reedy Fork Parkway / US 29 Interchange R-4707 is to reconstruct the Reedy Fork Parkway / US 29 Interchange to serve forecasted traffic demand, replace a deficient bridge, prepare for US 29 to be upgraded to interstate standards, and widen Summit Avenue south to Bryan Park Road. The City is developing an environmental study and preliminary design in cooperation with. Study completion in 2015, right-of-way acquisition and construction remain unfunded. US 70 Continuing growth and traffic increases make widening US 70 a strategic priority from Mt Hope Church Road to Rock Creek Dairy Road (U-2581B); and from Rock Creek Dairy Road into Burlington (R-2910) is being studied in a combined environmental study document. The project will connect residents to destinations and promote economic development. Programmed for planning, environmental study and design. Right-of-way and construction unfunded. US 158 (R-2577) US 158 widening from I-40 Business in Winston Salem to US 220. Completion of environmental study nearing completion, right-of-way acquisition in for portion in Forsyth County; construction unfunded. (R-2580) US 158 widening from US 220 to US 29 Business in Rockingham County. Right-of-way and construction unfunded. West Market Street West Market Street (R-2611) is being widened to four lanes with a median and sidewalks from NC 68 to west of Bunker Hill Road. Construction complete. (U-3617) from Bunker Hill Road west to NC 66 in Kernersville is unfunded. 3
4 Pedestrian Improvements Greensboro continues to gain new sidewalks through City priority, citizen petition, roadway projects, and MPO funding support, and through private development. West Market Street: Pomona Dr. to Walker Ave. West Market at United Street & West Market at Walker Avenue: intersection improvements. Walker Avenue: West Market St to Holden Rd. Ardmore Drive: Florida St to existing sidewalk. Cone Boulevard: A&Y Greenway to Lawndale Dr. Florida Street: Willow St to Lee St. Pinedale Drive: Battleground Ave to Benjamin Pkwy. Southeast Walking Trail: South St to Elm-Eugene St. Concord Street: Randleman Rd. to Soabar St. Edith Lane: Shelby Dr. to Meadowood St. Guilford Avenue: from Adams St. east & west for 275. Henderson Road: Friendly Ave to Farrar Dr. Stagecoach Trail: Friendly Ave. to Guildford Elem. School entrance. Warren Street: Spring Garden St. north for 475. Current & Upcoming Sidewalk & Trail Projects Funding made available by the MPO, and the City of Greensboro. Recent Construction West Cone Boulevard: Patriot Way to Lawndale Dr. Elm-Eugene Street: E. Terrell St. to E. Meadowview Rd. High Point Road: Lakehaven Pl. east of Marchester Way South Holden Road: Farmington Dr. to Vanstory St. Randleman Road: Long St. to Rocky Knoll Rd. Spring Garden Street: Holden Rd. to Lindell Rd. Vandalia Road: Elm-Eugene St. to Lakefield Dr. Southeast Walking Trail Ph 2: Freeman Mill Rd. to South St. W. Market Street: Starmount Dr to Ridgeway Dr., Village Ln. to N. Walnut Cir. and Meadowood Dr. to S. Walnut Cir. Elam Avenue: Cornwallis Dr to Pembroke Rd. Friendly Avenue: Holden Rd to Hobbs Rd. Lawndale Drive: Pisgah Church Rd to Cone Blvd. Pembroke Drive: Elam Ave to Starmount Farms Dr and Benjamin Pkwy to Fairway Dr. Bessemer Avenue: Headquarters Dr to Franklin Blvd. Cornwallis Drive: Lawndale Dr to Church St. Briarcliff Road: Wendover Ave to Nottingham Rd. West Market Street: Village Ln to Walnut Circle. East Wendover Avenue: Tucker St. to Penry Rd. East Wendover Avenue: Arnold St. to Rollins St. West Market Street: Walnut Circle to Pomona Drive. Current Construction Contracts City of Greensboro contract ( ): 2.8 miles of sidewalk work expected completion late Florida Street: Ashe St. to Willow Rd. Randleman Road: Creekridge Rd. to Glendale Rd. City of Greensboro contract ( ): 2.4 miles of sidewalk work expected completion late Friendly Avenue: Elam Ave to Overlook St. JJ Drive: Randleman Rd to existing McConnell Road: Willow Rd to English St. Vandalia Road: Holden Rd to Osborne Rd. Wendover Avenue: Edwardia Dr to Oak Branch Rd. City of Greensboro contract ( ): 0.7 miles of sidewalk work expected completion Spring Lee Street: Florida St to Astor Dr. Mackay Road: Adams Farm Pkwy east to existing. Old Battleground Road: Michaux Rd east to existing. Old Lake Jeanette Road: Eastern Shore Dr to east of Shoreham Ct. 16st Street Bus Stop: Summit Ave eastward 215 feet. City of Greensboro contract ( ): 0.8 miles of greenway work expected completion Summer Downtown Greenway: Phase 2E, 3A, 3C Fisher Ave Greene St to Eugene St; Eugene St Fisher Ave to Smith St; Smith St Spring Street to Prescott St. 4
5 Pedestrian Improvements Transit Improvements GTA City of Greensboro contract ( ): 1.1 miles of sidewalk work expected in 2015 with completion in Phillips Avenue: Summit Ave to Huffine Mill Rd where none exists. Future Construction 2016 Downtown Greenway Phase 1 B1: Bragg St from Eugene St to Elm St B2: Bragg St from Elm St to MLK Jr Dr. Seminole Drive: Westover Terrace to Benjamin Pkwy. College Road / New Garden Road: Guida Dr to Ballinger Rd. Northeast/Keeley Park Trail Connector: Existing trail to Keeley Park. Vance Arlington Trail: Vance St to Bragg St. Big Tree Way: Wendover to Bridford Pkwy. Four Seasons Boulevard: Vanstory St to Creekridge Rd. Bridford Parkway/Hornaday Road: Wendover Ave to west of Nicholas Rd. Hewitt Street: Norwalk St. to Merritt Dr. Rudd Station Road/Scott Road: Summit Ave to Townsend Rd. Shelby Drive: Big Tree Way to Edith Ln. Summit Avenue: Scott Rd to Creekbrooke Ct English Street: Florida St to Phillips Ave. Friendly Avenue: W. Market St to Francis King St. Lees Chapel Road: Church St to Brightwood School Rd. Pisgah Church Road: Battleground Ave to Church St. Yanceyville Street: Bessemer Ave to Lees Chapel Rd. Byers Road: Lees Chapel Rd to Byers Ridge Dr. Downtown Greenway Phase 2: Murrow Blvd to Fisher Ave and Fisher Ave for Murrow Blvd to Greene St. Green Valley Road: Friendly Ave to Battleground Ave. Rankin Road/Martin Avenue: Summit Ave to Springmont Dr. Summit Avenue: Rankin Rd to south of 16th St. Currently, 16 GTA routes are operated Mondays through Saturdays and seven routes on Sundays. In addition, there is one connector route, the Career Express that serves the airport area, and five Higher Education Area Transit (HEAT) routes. Together, GTA and HEAT vehicles drive 2,170,000 revenue miles per year, more than 231 miles of GTA routes, 49 miles of GTA connectors, and 59 miles of HEAT routes. At last count, there were 1,056 GTA bus stops and 46 HEAT bus stops in Greensboro and Jamestown. GTA and HEAT serve more than four million passenger trips per year. SCAT vehicles drive 1,400,000 revenue miles per year. Recently Routes 4 and 23 were changed to serve the new Hayes-Taylor YMCA on E. Florida Street near E. Lee Street. GTA operates within the Greensboro City Limits and serves approximately 260,000 people. The sole destination served outside the city limits is the Jamestown Campus of Guilford Technical Community College. GTA also works in partnership with PART to provide access throughout the triad and beyond. Transit Improvements PART PART ( operates express buses, Regional Vanpools, Human Service Transportation for Guilford County, Coordinates the Region s Air Quality Conformity, Manages the Regional Travel Model, conducts land use and transportation planning for our partnering agencies and performs other services in the Triad. PART has connected the Route 4 Alamance Burlington Express with the Triangle Transit Authority at UNC Hospital, the first transit connection of its kind in North Carolina. Construction of PART s new regional multi-modal transportation center in Greensboro is planned to begin Summer 2015 with completion expected by Fall
6 CITY OF GREENSBORO 2008 BOND PROJECTS On November 4, 2008 Greensboro voters approved $134 million in bonds for Transportation Improvement Projects. Many projects shown since have been funded either by State or Federal funds. Efforts continue to secure additional State and Federal funding to advance additional projects. Alamance Church Road widening from US 421 to City Limits. In design. Construction expected start in Battleground-Benjamin-Cone Intersection improvements. Construction **** Battleground-Westridge Intersection improvements. Construction **** Battleground-New Garden Intersection improvements. Construction **** Battleground-Brassfield Intersection improvements. Construction complete.**** N. Church Street widening from Wendover Ave. to Cone Blvd. Construction expected to start in 2022.**** Clifton Road / Wendover Avenue intersection improvements Project complete.*** Cone Boulevard / Nealtown Road Extension. Construction expected to start Summer High Point Road / Lee Street streetscape from I-40 to Eugene St. Phase 1 - I-40 to Coliseum Boulevard under construction. Expected completion Late 2016.** Horse Pen Creek Road widening from New Garden Rd. to Battleground Ave. Construction expected to start Late Mackay Road widening from Atwater Dr. to Williamsborough Lane. In design. Construction expected in Roadway Projects Sidewalk & Trail Projects W. Market St / College Rd / Guilford College Rd intersection improvements Right-of-Way acquisition underway and Construction expected to start in 2016.**** Benjamin Parkway widening from Wendover Ave. to Bryan Blvd. Project Construction expected to start in 2021.**** Elm Street / Pisgah Church Road intersection improvements. Construction expected to start in 2018.**** Florida Street / Randolph Avenue intersection improvements. Project complete.*** Lawndale Drive / Pisgah Church Road intersection improvements. Construction expected to start in 2020**** Vandalia Road widening from Elm-Eugene St. to Pleasant Garden Rd. In design. Construction expected to start Summer Merritt Drive I-40 widening from High Point Rd. Construction complete. Fleming Horse Pen Creek Road Connector*** Construction completion late Summit Avenue Streetscape from Murrow Blvd. to Sullivan St. Construction start Summer Funded For Design & Construction Battleground Rail Trail Phase 2 in Preliminary Design. Downtown Greenway in various stages of design and construction.* (General Sidewalk Improvements) Randleman Road - Farragut St to Shoffner Ct. Construction complete. *** Battleground Avenue - Fisher Ave. to Westridge Rd. N. Church Street - Denny Rd. to Electra Dr. In design.*** Construction expected in College Road -W. Market St. to Friendly Ave. In design.*** Construction expected in Cone Boulevard - Church St. to 16th St. In design. Construction expected in 2018.*** Holden Road - Walker Ave. to Vandalia Rd. In design. Construction starting in 2018.*** Lovett Street - Florida St. to Freeman Mill Rd. Construction expected in 2016.*** McConnell Road - Willow Rd. to English St. Constructed by Summer 2015.*** Phillips Avenue - Huffine Mill Rd. to Summit Ave. Construction in 2016.*** Spring Garden Street - Pomona Dr. to Market St. Construction expected in 2018*** W. Wendover Ave - Edwardia Dr. to Oak Branch Dr. Construction complete Fall 2015*** (Various Greenway Studies) Dudley High School Spur Trail Gracewood Greenway Muddy Creek Greenway Phase 1 & 2 North Buffalo Creek Greenway Piedmont Greenway Pine Cone Greenway South Buffalo Creek Greenway East & West Leg Southeast Connector Spurs A,B & C Vance Arlington Greenway In Design. (*) Partial Federal funding (**) Partial State funding (***) 80% Federal funding & 20% City funding (****) 100% State funding 6
7 Market-College-Guilford College Intersection Project U-5326 widen the intersection approaches to add additional left turn lanes due to the heavy volumes of left turning vehicles. Sidewalks are included in the project. Construction start in 2016 with completion in High Point Road Streetscape The City plans to widen sidewalks, increase lighting and install streetscape enhancements from Pinecroft Road to Coliseum Boulevard. Under construction with completion in late Battleground Avenue Intersections Battleground Avenue Intersections (U-5306) project involves improvements at the Cone-Benjamin, Westridge, New Garden and Brassfield intersections. The project is under design by the City of Greensboro with 100% funding provided by for right-of-way and construction. Battleground-Benjamin-Cone: Construction start Summer Battleground-Westridge: Construction start Summer Battleground-New Garden: Construction start early Battleground-Brassfield: Construction complete. Horse Pen Creek Road-Fleming Road Connector The Horse Pen Creek Road Fleming Road Connector will provide a much needed east-west route for localized traffic. Construction partially complete; remainder of construction expected to be complete by the end of Downtown Greenway The Greenway is a 4.2 mile shared-use trail that will loop around downtown Greensboro incorporating a future portion of the A&Y Greenway. Funding made available by the MPO,, the City, and Action Greensboro. Completed: Lee St to Eugene St Spring Garden St to Lee St Smith Street from Eugene St to Spring St Under Construction in : Fisher Ave and Eugene St: Greene St to Smith St Smith St: Spring St to west of Prescott St. In Design: Murrow Blvd and Fisher Ave: E. Lee St to Greene St/ Bragg St: Eugene St to Lee St. Vandalia Road Vandalia Road widening from Elm-Eugene Street to Pleasant Garden Road is under design from 2 lanes to 3 lanes with bike lanes and sidewalks. Construction is expected to begin in Summit Avenue Streetscape Summit Avenue Streetscape from Murrow Boulevard to Sullivan Street. Construction is expected to start in Alamance Church Road Alamance Church widening and improvements from Martin Luther King Jr. Drive to City Limits is under design. Sidewalks from MLK Jr Drive to Bristol Road; widening from Bristol Road to City Limits from 2 lanes to 3 lanes with bike lanes and sidewalks. Construction is expected to begin in
8 BRIDGE PROJECTS Ballinger Road Bridge at Horse Pen Creek Tributary (B-45553) Design pending by City of Greensboro. Lee Street at south Buffalo Creek Right-of-Way 2020, Construction Strawberry Road at Mears Fork Creek Completion Spring Judge Adams Road Construction at Little Alamance Creek Harvest Road at South Buffalo Creek Construction in Bunch Road at Reedy Fork Creek (B-4756) Construction Complete. High Rock Road at Buffalo Creek (B-4959) Construction start Fall Fleming Road at Brush Creek Right-of-Way 2015, Construction Knox Road at Little Alamance Creek Right-of-Way 2016, Construction Reedy Fork Parkway at US 29 Right-of-Way 2017, Construction I-40 at South Buffalo Creek Right-of-Way 2018, Construction Willow Road at I-40 Right-of-Way 2010, Construction Future Bridge Projects Patton Avenue at I-40 Wiley Lewis Road at Little Alamance Creek Summit Avenue at North Buffalo Creek Bunch Road at Reedy Fork Creek Eversfield Road at Haw River N. Church at Unnamed Branch RAIL PROJECTS Lowdermilk Street / Sykes Avenue Intersection Realignment and Pine Street Railroad Crossing Removal Design underway; right-of-way and construction schedule pending. NEW ROADWAY / INTERSECTION PROJECTS DRAFT STATE TRANSPORTATION IMPROVEMENT PROGRAM I-5712 I-40 / Sandy Ridge Road Interchange R-5725 NC 60 / NC 150 Intersection Improvement U-5754 US 29 / I-40 / Bus I-85 Ramp Improvements U-5851 Church Street Widening - Wendover to Cone U-5580 Randleman Road Widening - Glendale to Elmsley U-5852 Benjamin Parkway / Bryan Boulevard Widening - Wendover to Holden U-5812 Lawndale Drive / Pisgah Church Road / Martinsville Road - Intersections Improvements U-5841 Friendly Avenue / Lindell Road Intersection Improvements U-5842 Elm Street / Pisgah Church Road - Intersection Improvements U-5849 Aycock Street Widening & Railroad Overpass Replacement - Spring Garden Street to Lee Street FS-1507B Battleground Avenue Widening - Westridge Road to Cotswold Avenue Lead Planning Agency: City of Greensboro Department of Transportation PO Box 3136 Greensboro, NC Phone: (336) Fax: (336) guampo@greensboro-nc.gov Or visit:
ALTERNATIVES. NCDOT made an early decision to first determine how to build the project (construction method) followed by what to build (alternatives).
III. ALTERNATIVES A. CONSTRUCTION METHOD ALTERNATIVES NCDOT made an early decision to first determine how to build the project (construction method) followed by what to build (alternatives). One of the
More informationSTP DA Candidate Pedestrian Projects Funding Recommendations
STP DA Candidate Pedestrian Projects Funding Recommendations Rank Municipality Project Description Total Cost STP DA Local Notes Cumulative STP DA Funding Request Date 1 Winston Martin Luther King Jr.
More informationHenderson County Project Prioritization Discussion
French Broad River MPO Henderson County Project Prioritization Discussion A discussion on projects considered for MPO Local Input Points in the tier for P 5.0 French Broad River MPO 8-8-2018 INTRODUCTION
More informationPlanning & Zoning Board Meeting. DRAFT Comprehensive Transportation Plan Update, February 23, 2018 version
Planning & Zoning Board Meeting DRAFT Comprehensive Transportation Plan Update, February 23, 2018 version May 10, 2018 Overview Overview of Agency Comments Overview of proposed modifications to the Draft
More informationExhibit A. SH 161 RTC Work Program of New Projects. Collin County
Exhibit A SH 161 RTC Work Program of New Projects Collin County 0918-24-969 N/A 0918-24-970 N/A 0918-24-973 N/A 2351-01-020 N/A 2679-03-010 N/A On Exchange Parkway from US 75 to Allen Heights On Country
More informationPROPOSED IMPROVEMENTS
IV. PROPOSED IMPROVEMENTS The proposed improvements for each alternative carried forward are discussed below. A. FUNCTIONAL CLASSIFICATION AND ROADWAY CROSS-SECTIONS The classifications of the roadways
More informationTENNESSEE DEPARTMENT OF TRANSPORTATION Project Status. SR-37 No Projects US-19E Under Development in Carter County
CARTER COUNTY SR-37 No Projects US-19E Under Development in Carter County PIN: 125256.00 AT LM 8.7 (ROCKFALL MITIGATION) Length - 0.0 (Mitigation - Rockfall) CARTER COUNTY SR-91EXT PIN: 043975.01 FROM
More information510 Highways, Streets & Roads Comprehensive Plan Section 510
511 510 Comprehensive Plan Section 510 Highways, streets, and roads provide for the movement of people and goods from one place to another. These public ways form a network that defines the relationship
More informationNorth Carolina Department of Transportation Project Development and Environmental Analysis Branch
North Carolina Department of Transportation Project Development and Environmental Analysis Branch Citizens Informational Workshop I-85, from I-485 to NC 73 Mecklenburg and Cabarrus Counties October 30,
More informationFY 2005 TRANSPORTATION CAPITAL PROGRAM
Camden County Civic Center Access Study, Pennsauken 03340 This project will address operational and access improvements on Routes 30, 73 and 90 related to the Crossroads redevelopment project around the
More informationWelcome. Northern Segment of Hwy 100 I-90 to South of Madison Street Meeting Goals:
Welcome Northern Segment of Hwy 100 I-90 to South of Madison Street Meeting Goals: - Review Environmental Assessment - Share Preferred Alternative -Receive Public Comments 2003 EA Preferred Alternative
More information2040 Long Range Transportation Plan
2040 Long Range Transportation Plan Adopted: April 15, 2013 APPENDIX D HIGHWAY NEEDS PLAN PROJECTS FREDERICKSBURG Existing and Committed Projects Fall Hill Avenue/Mary Washington Blvd. (Fredericksburg)
More informationTransportation Projects Quarterly Report. Morrisville Planning Department May 22, 2018
Transportation Projects Quarterly Report Morrisville Planning Department May 22, 2018 Transportation Improvements Most Common Ways the Town secures transportation improvements: 1. Development 2. Grant
More informationKnoxville Area Transit (KAT) Transit Development Plan Corridor Analysis
Knoxville Area Transit (KAT) Transit Development Plan Submitted to: Knoxville-Knox County Metropolitan Planning Commission Submitted by: PB Americas, Inc. Under contract to: The Corradino Group, Inc. October
More informationTENNESSEE DEPARTMENT OF TRANSPORTATION Project Status. SR-37 US-19E No Projects Under Development in Carter County
CARTER COUNTY SR-37 US-19E No Projects Under Development in Carter County PIN: 125256.00 AT LM 8.7 (ROCKFALL MITIGATION) Length - 0.0 (Mitigation - Rockfall) CARTER COUNTY SR-91EXT PIN: 043975.01 FROM
More informationCapital Projects impacting Odenton Town Center
Capital Projects impacting Odenton Town Center 1 2 E549700 W801600/ W801602 Anne Arundel County Department of Public Works Manor View Elementary School Transmission Main - MD 32 @ Meade Phase 2 $34,399,000
More informationTransportation Committee
Transportation Committee Business Item No. 2013-286SW Meeting date: October 14, 2013 For the Metropolitan Council meeting of October 16, 2013 Subject: Southwest Light Rail Transit (Green Line Extension):
More informationIMPLEMENTATION STRATEGIES. In This Chapter. Goals & Strategies 182 Project List 183 Future Land Use 186 CHAPTER 11 IMPLEMENTATION STRATEGIES
In This Chapter Goals & Strategies 182 Project List 183 Future Land Use 186 11 IMPLEMENTATION STRATEGIES NORTH AUGUSTA, SC 2017 COMPREHENSIVE PLAN 179 Individual commitment to a group effort that is what
More informationRevised Long Range Transportation Plan
Revised Long Range Transportation Plan Auburn, Alabama Prepared for: City of Auburn, Alabama Prepared by: Skipper Consulting, Inc. June 2006 Revised Long Range Transportation Plan City of Auburn, Alabama
More informationNORTH-SOUTH CORRIDOR STUDY EXECUTIVE SUMMARY. Executive Summary
Executive Summary Background As congestion continues to affect mobility in the region, the Ozarks Transportation Organization (OTO) is particularly concerned with traffic movement. The North-South Corridor
More informationExisting Transportation System 5-1
5-1 The Jackson County transportation system is served by several modes of transportation including streets and highways, multi-modal, non-motorized, rail, and aviation. While the focus of the transportation
More informationCapital Projects in and near Odenton Town Center
Capital Projects in and near Odenton Town Center Map ID Anne Arundel County Department of Public Works This project provides for the design, right of way acquisition, and construction of approximately
More informationOconee Rivers Greenway Project. TSPLOST 2018 Project # 5 Project Concept Sub-projects 7, 8, 9, 10, & 11. Mayor & Commission Work Session
Oconee Rivers Greenway Project Project # 5 Project Concept Sub-projects 7, 8, 9, 10, & 11 Mayor & Commission Work Session February 13, 2018 North Oconee River Greenway 1 Project # 05 - Oconee Rivers Greenway
More informationPublic input has been an important part of the plan development process.
Lakewood s Comprehensive Plan recognizes that transportation helps shape the community, and that the way the community provides for the safe and efficient movement of people affects the character of the
More informationBlue Line LRT Extension
v e Noble Pkwy Noble Pkwy Xerxes Ave N Shingle Creek Penn Ave N Penn Ave N Fremont Ave N Lyndale Ave N S Washington Ave University Ave NE Blue Line LRT Extension LIGHT RAIL PLATFORM AND STATION DESIGN
More informationTIRZ 17/Redevelopment Authority Capital Improvements Plan Projects
Gessner Widening: T-1701 What: Widen the road from a six-lane divided boulevard to an eight-lane divided boulevard street section, increase turn lanes, update traffic signal system, improve drainage by
More informationCHAPTER 7: Transportation, Mobility and Circulation
AGLE AREA COMMUNITY Plan CHAPTER 7 CHAPTER 7: Transportation, Mobility and Circulation Transportation, Mobility and Circulation The purpose of the Transportation, Mobility and Circulation Chapter is to
More informationPublic Meeting May 20, 2014
Public Meeting May 20, 2014 Overview Study Purpose Study Area Overview Strategies Potential Opportunities Implementation and Discussion Skeo Solutions Raleigh Walkable Watershed Pilot 2 Purpose Develop
More informationWelcome to the. Open House
Welcome to the 5th Street to Kinsman Road Open House November 14 5:30 7:00 p.m. Please sign in Project Overview In December 2016, City Council adopted SW 5th Street as the preferred alignment to connect
More informationMunicipality of Anchorage. Community Council Survey Capital Projects Needs Ranking Survey (ALPHABETICAL) Airport Heights
ANCHORAGE PARKS & RECREATION Nichols Park Design and improve neighborhood park 2008 Challenge Grant applicant. 2008 $500K State Grant for Neighborhood Parks. Tikishla Park Lighting, paved parking, hockey
More informationMississippi Skyway Preliminary Engineering Report
EXECUTIVE SUMMARY Mississippi Skyway Preliminary Engineering Report CITY OF RAMSEY, MINNESOTA DECEMBER 2014 City of RAMSEY EXECUTIVE SUMMARY Project Need and Intent The Mississippi Skyway pedestrian bridge
More informationI. DESCRIPTION OF PROPOSED ACTION... 1 A. General Description... 1 B. Historical Resume and Project Status... 2 C. Cost Estimates...
PROJECT COMMITMENTS SUMMARY... S-1 1. Type of Action... S-1 2. Description of Action... S-1 3. Summary of Purpose and Need... S-1 4. Alternatives Considered... S-2 5. NCDOT Alternatives Carried Forward...
More informationBALL CAMP PIKE Phase II From Middlebrook Pike to Andes Road NEW CONSTRUCTION Spring 2007
COUNTY LOCAL PROJECTS BALL CAMP PIKE Phase II From Middlebrook Pike to Andes Road NEW ION Spring 00 DRY GAP PIKE From Dante Road to Beaver Creek WIDENING Summer 00 DUTCHTOWN ROAD From Pellissippi Parkway
More informationPanama City Beach Community Redevelopment Agency Condo Con Property Owner Conference & Expo November 14, 2014
Panama City Beach Community Redevelopment Agency Condo Con Property Owner Conference & Expo November 14, 2014 Front Beach Road CRA On November 30, 2000, the City created the Panama City Beach Community
More informationREGIONAL TRANSPORTATION COMMISSION OF SOUTHERN NEVADA AGENDA ITEM
REGIONAL TRANSPORTATION COMMISSION OF SOUTHERN NEVADA AGENDA ITEM Metropolitan Planning Organization [ X ] Transit [ ] Administration and Finance [ ] SUBJECT: PROJECT SELECTION PROCESS FOR TRANSPORTATION
More informationProposed FY 2004 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects
Carteret Industrial Road 98547 This project will address the upgrade of Carteret Industrial Road. The federal Transportation Equity Act for the 21st Century (TEA-21) provided funding for this project under
More informationConstruction Engineering & Inspection
Construction Engineering & Inspection Serving Florida for 20 Years CEI Engineering Planning Landscape Architecture Urban Design Construction Engineering & Inspection (CEI) I N T R O D U C T I O N Over
More informationI-95 Girard Avenue Interchange Near Neighbors Meeting. Project Status
I-95 Girard Avenue Interchange Project Status Construction is underway for Phase 1 and 2. Phase 3 construction will begin early 2014. Overall Project Area and Schedule GR0: Completed GR0: Completed in
More informationAlamance Dillard's # Boston Dr Burlington Door #2 Facing Traffic Circle. Do not block entrance/exit.
CURRENT AS OF JANUARY 18, 2018 County Store Name Street Address City Zip Notes for Troops Check in with store manager on duty during set-up. Do Alamance Big Lots 1811 S Church St Burlington 27215 not block
More information2010 Tentative Enhancement Program Allocations (FY11)
Bristol 10011 Buchanan County Buchanan County project cost $1,190,332 Bull Creek Trail - construction of a pedestrian/bicycle trail along abandoned request amount $240,323 railroad right of way. allocation
More informationI-4 Beyond the Ultimate. Florida Transportation Builders Association February 9, 2018
I-4 Beyond the Ultimate Florida Transportation Builders Association February 9, 2018 FDOT: Improving Mobility & Safety in Central Florida FDOT is Designing and building a better I-4 through Central Florida
More information4.1 Build Alternative 1 Construction Phasing
SECTION 4 Implementation Plan This section discusses potential segmentation of the build alternatives into multiple projects for implementation of improvements to the NSH from Rabbit Creek Road to 36th
More information1.0 Circulation Element
5/9/18 1.0 Circulation Element 1.1 Introduction As growth and development occur in Apache County, enhancements to its circulation system will be necessary. With time, more roads will be paved and air and
More informationNorthwest Rail Corridor and US 36 BRT Development Oriented Transit Analysis 4.4 STATION AREA FINDINGS
4.4 STATION AREA FINDINGS Each station is different, and each one requires a separate set of recommendations based on the vision for the site. This section outlines an initial TOD strategy and recommendations
More informationWHAT IS THE PURPOSE OF THE OPEN HOUSE?
WHAT IS THE PURPOSE OF THE OPEN HOUSE? OPEN HOUSE PURPOSE The purpose of the open house is to provide an update on the study process and introduce the preliminary concept alternatives. The open house provides
More informationPlaces29: List of Implementation Projects
Important Points to Keep in Mind When Using This List Places29: List of s Each of the projects in this List represents an action needed to implement the Places29 Master Plan. The projects are grouped first
More informationIssues Requiring Future Study
Issues Requiring Future Study Transportation planning is an ongoing process that tends to identify new issues as it finds solutions for others. Some issues are so complex that a solution to one problem
More informationA Connected Region for Our Future. Tampa Bay Regional Planning Council
A Connected Region for Our Future Tampa Bay Regional Planning Council TBARTA Vision A world class transportation network for the Tampa Bay region that will connect people and places, move goods and services,
More informationPrepared for the Citizens of Forsyth County by the City-County Planning Board
Prepared for the Citizens of Forsyth County by the City-County Planning Board Bryce A. Stuart Municipal Building 100 East First Street, Winston-Salem, NC 27101 336.727.8000 www.cityofws.org/planning www.legacy2030.com
More informationFairfax County Parkway (Route 286) Widening Project
Fairfax County Parkway (Route 286) Widening Project Route 29 (Lee Highway) to Route 123 (Ox Road) State Project No. 0286-029-259, P101; UPC 107937 Fairfax Station HOA Meeting January 30, 2018 7:00 to 9:00
More informationComprehensive Development Guide
INDUSTRIAL ELEMENT Comprehensive Development Guide 1 Industrial Element 7.1 Hardin County Industrial Overview BG PKWY Fort Knox Industrial Corridor Comprised of 11 parcels totaling 720 acres of land 68
More informationAtlanta BeltLine. Subareas 9 & 10. Master Plan Updates. March 26, Washington Park Jamboree 1
Atlanta BeltLine Subareas 9 & 10 Master Plan Updates March 26, 2018 Washington Park Jamboree 1 22 miles, connecting 45 neighborhoods 22 MILES of transit 46 MILES of streetscapes and complete streets 33
More informationThe Long Road from Planning to Breaking Ground:
The Long Road from Planning to Breaking Ground: A Collaboration Between Roanoke County and VDOT Megan G. Cronise, AICP VDOT Coordinating Transportation and Land Use Planning Forum May 10, 2018 Where is
More informationThe Illinois Department of Transportation and Lake County Division of Transportation. Route 173, including the Millburn Bypass
The Illinois Department of Transportation and Lake County Division of Transportation welcome you to this Public Hearing for U.S. Route 45 from Illinois Route 132 to Illinois Route 173, including the Millburn
More informationMORRISVILLE TRANSPORTATION PLAN TOWN COUNCIL PRESENTATION AUGUST 22, 2017
TOWN COUNCIL PRESENTATION AUGUST 22, 2017 SCENARIO PLANNING CORRIDORS Town Hall Drive Baseline + 2 McCrimmon Parkway Baseline + 2 NC 54 Baseline + 2 7 subregion model runs determining carrying capacity
More informationWelcome. South Seminole Heights Civic Association, Inc. Tampa Interstate Study Supplemental Environmental Impact Statement.
Welcome South Seminole Heights Civic Association, Inc. October 17, 2018 Tampa Interstate Study Supplemental Environmental Impact Statement 1 Stephen Benson Opening FDOT District Seven 2 3 Our solutions
More information12/9/2013. HOLLYWOOD/PINES CORRIDOR PROJECT AMPO 2013 Annual Conference October 24, Our Perspective. Broward.
HOLLYWOOD/PINES CORRIDOR PROJECT AMPO 2013 Annual Conference October 24, 2013 Our Perspective Broward Fort Lauderdale 1 Broward Metropolitan Planning Organization Fort Lauderdale Fort Lauderdale Skyline
More informationThe GATEWAYS Sub Area Master Plan. City of Walker
The GATEWAYS Sub Area Master Plan City of Walker Introduction: The Walker City Commission and Planning Commission decided in 2011 to create a sub-area master plan for the Remembrance Road and Wilson Avenue
More informationReclaiming Old West Broad Street: I-16 Ramp Removal Study
Reclaiming Old West Broad Street: I-16 Ramp Removal Study Community Meeting Summary July 15, 2014 The first community meeting for Phase II of the I-16 Ramp Removal Study was held on July 15, 2014, at the
More informationShift Rapid Transit Public Participation Meeting May 3, 2017
Shift Rapid Transit Public Participation Meeting May 3, 2017 Shift Rapid Transit Initiative Largest infrastructure project in the city s history. Rapid Transit initiative will transform London s public
More informationSOUTHWEST TRANSITWAY (STAGE 2) PUBLIC OPEN HOUSE
WELCOME! SOUTHWEST TRANSITWAY (STAGE 2) PUBLIC OPEN HOUSE Monday, November 18, 2013 3:30 to 5:30PM and 7:00 to 9:00PM Tuesday, November 19, 2013 3:30 to 5:30PM and 7:00 to 9:00PM Welcome to the Southwest
More informationApril 21, 2007 CCRP Workshop Summary
April 21, 2007 CCRP Workshop Summary Group 1 1. Reuse around BART with a lot of housing and jobs 2. Greenway around creek 3. Transit and auto connection all through the site from Kirker Pass to Port Chicago
More informationPLANNING COORDINATING COMMITTEE
PLANNING COORDINATING COMMITTEE Fall Meeting/Luncheon Welcome! October 16, 2009 PLANNING COORDINATING COMMITTEE Fall Meeting/Luncheon WELCOME! WELCOME! October 16, 2009 October 16, 2009 Agenda I. Lunch/Socialize
More information2017 General Obligation Bond
2017 General Obligation Bond Presentation of Public and Council Projects to the Transportation & Mobility Stakeholder Committee April 13, 2017 Agenda Deferred Maintenance Project Development Process Projects
More informationMemorandum CITY OF DALLAS. Riverfront Boulevard Design From Continental Avenue to Cadiz Street
Memorandum DATE November 10, 2011 CITY OF DALLAS TO Trinity River Corridor Project Committee Members: Vonciel Jones Hill (Chair) Linda Koop (Vice Chair), Monica Alonzo, Scott Griggs, Angela Hunt, and Delia
More informationAUTO CIRCULATION & PARKING
CHAPTER 5 Chapter 5 Auto Circulation & Parking AUTO CIRCULATION & PARKING Parking use and automobile circulation have been topics of many discussions on street corners as well as at public workshops and
More informationInnovative Transportation Planning, Design & Technology in Fairfax County, VA
Innovative Transportation Planning, Design & Technology in Fairfax County, VA American Society of Highway Engineers (ASHE) November 16, 2016 Presented By W. Todd Minnix, PE Chief, Transportation Design
More information124 Subarea Visions. Vision Plan. A. Nelessen Associates, INC I Visioning I Planning I Urban Design
Subareas 124 Subarea Visions The next seven sections describe specific recommendations tailored to each subarea. Each subarea is discussed separately except for certain aspects of 95th Street and Antioch
More informationPUBLIC HEARING. DRAFT Environmental Impact Statement. Matthews Memorial Baptist Church Washington, DC October 18, National Capital Region
National Capital Region DRAFT Environmental Impact Statement PUBLIC HEARING Matthews Memorial Baptist Church Washington, DC October 18, 2007 Introduction Welcome and team introduction Hearing procedures
More informationWelcome to the. Citizen Information Meeting for the Martinsville Southern Connector Study. The purpose of this meeting is to:
Route Environmental Impact Statement Welcome to the Citizen Information Meeting for the Martinsville Southern Connector Study The purpose of this meeting is to: Introduce the Martinsville Southern Connector
More informationTHREE-YEAR CAPITAL IMPROVEMENT PLAN FY
THREE-YEAR CAPITAL IMPROVEMENT PLAN FY2016 2018 Annual CIP Development Process Public Works & Engineering Divisions Prepare List of Capital Needs and Recommended Deferred Maintenance Public Works & Engineering
More informationADOPTED AT NOVEMBER 15, 2012 PACC MEETING
ADOPTED AT NOVEMBER 15, 2012 PACC MEETING STAFF MEMORANDUM TO PACC-TECH TO: PACC-Tech FROM: Elaine K. Echols, AICP, Missy Creasy, AICP, and Julia Monteith, AICP TOPIC: Review of Area B Recommendations
More information2017 Investment in Infrastructure Expo February 28, 2017 Jason Jonas, P.E. Public Works Director
2017 Investment in Infrastructure Expo February 28, 2017 Jason Jonas, P.E. Public Works Director 1 Jefferson County, Missouri Road and Bridge Sales Tax: Jefferson County has a one-half cent sales tax that
More informationTransportation. Strategies for Action
Transportation A major priority for the Overlake Neighborhood is to develop a multimodal transportation system. To achieve this system, a balance has to be found among travel, circulation and access needs;
More informationTENNESSEE DEPARTMENT OF TRANSPORTATION Project Status. No Projects Under Development in Campbell County
I-75 No Projects Under Development in Campbell County PIN: 115778.00 TRUCK CLIMBING LANE, MP 135.5 TO MP 140.1(NBL) Length - 4.6 (Widen) The right-of-way and/or utility process is underway. I-75 PIN: 115778.01
More informationProject Overview. Fairfax County Parkway Widening Fairfax County. Get Involved. Public Information Meeting. Contact Information
Get Involved VDOT representatives will review and evaluate information received as a result of this meeting. Please fill out the comment sheet provided in this brochure if you have any comments or questions.
More informationA. INTRODUCTION B. PREFERRED ALTERNATIVE
Chapter 2: Project Alternatives A. INTRODUCTION This chapter presents the Preferred Alternative (also referred to throughout this Environmental Assessment [EA] as the Wyandanch Intermodal Transit Facility
More informationTable 5.2. Short-Term Work Program Jackson County,
Chapter 5, Policies and Implementation, Jackson, GA, Community Agenda (June 21, 2010) Table 5.2. Short-Term Program Jackson, 2011-2015 NATURAL RESOURCES Seek resolution of or mitigate encroachments in
More informationFall 2017 Construction Update
Fall 2017 Construction Update Ward 4 Southeast Engineering Department Riverwalk Red Multi-Use Trail Bridge Rehabilitation The Riverwalk Red Multi Use Trail Bridge was awarded to Cramer and Associates,
More informationPromoting Economic Development Through Upfront SEPA Review: Lessons from South Downtown Tacoma
Promoting Economic Development Through Upfront SEPA Review: Lessons from South Downtown Tacoma 1 This session will focus on the City of Tacoma s South Downtown Subarea Plan and associated Non-Project SEPA
More informationOpen House RIVER DES PERES GREENWAY: LANSDOWNE SHREWSBURY METROLINK TO FRANCIS R. SLAY PARK
Open House 10.12.16 RIVER DES PERES GREENWAY: LANSDOWNE SHREWSBURY METROLINK TO FRANCIS R. SLAY PARK MEETING AGENDA Great Rivers Greenway and Project Partners River des Peres Greenway Overview Project
More informationOnondaga County Sustainable Streets Project. Onondaga County Planning Federation June 7, Onondaga County Sustainable Streets Project 1
Onondaga County Sustainable Streets Project Onondaga County Planning Federation June 7, 2012 Onondaga County Sustainable Streets Project 1 Sustainable Streets 1. Introduction to the SMTC 2. Sustainable
More informationExecutive Summary. The Mebane CLP is not a regulatory document, but is intended to guide land development decisions. The plan includes:
Executive Summary P URPOSE AND O RGANIZATION OF THE P LAN The City of Mebane, with input from citizens and an appointed CLP Advisory Committee, adopted Mebane by Design, a Comprehensive Land Development
More informationFY 2018 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects
Schooleys Mountain Bridge Rehabilitation Project ID Numbers: N1707 / 173470 Schooleys Mountain Road Bridge was built in 1920 and widened in 1937. The project is a replacement of the bridge structure and
More informationPotential Green Infrastructure Strategies May 6, 2015 Workshop
Potential Green Infrastructure Strategies May 6, 2015 Workshop Background The City of Cortland is developing the Tioughnioga Urban Headwaters Green Infrastructure Action Plan with funding from the National
More informationSH 199 Corridor Master Plan. Community Meeting No. 2 May 31, 2017
Community Meeting No. 2 May 31, 2017 Transportation Projects On or Near SH 199 SH 199 from 0.3 miles south of FM 1886 to south end of Lake Worth bridge Construct freeway mainlanes and frontage roads 10-Year
More informationSouthern Gateway Project and Public Green
Southern Gateway Project and Public Green Transportation and Trinity River Project Committee May 23, 2016 Purpose of Presentation Provide the history and an overview of the Southern Gateway Project (SGP)
More informationGratigny Parkway East Extension Project Development & Environment (PD&E) Study
Gratigny Parkway East Extension Project Development & Environment (PD&E) Study Session 4: Presentation of Charrette Results December 8, 2010 MDX Work Program #: 92407 ETDM#: 11500 Project Location & Description
More informationPlanning Districts INTRODUCTION
INTRODUCTION To facilitate detailed examination of development prospects for all areas of the community, Delano has been divided into 14 planning districts. The location of these planning districts is
More informationProject Overview. Get Involved. Public Information Meeting. Contact Information
Get Involved VDOT representatives will review and evaluate information received as a result of this meeting. Please fill out the comment sheet provided in this brochure if you have any comments or questions.
More informationCity of Jersey City. Department of Administration Division of Engineering Traffic and Transportation
Division of Engineering Traffic and Transportation : Duncan Avenue Road Program Bergen Avenue Road Program PSE&G Gas System Modernization Program NJDOT Municipal Aid FY2015 Road Program Ogden Dog Park
More informationRight-of-Way Acquisitions and Relocations Technical Memorandum
Right-of-Way Acquisitions and Relocations Technical Memorandum Southeast Extension Project Lincoln Station to RidgeGate Parkway Prepared for: Federal Transit Administration Prepared by: Denver Regional
More informationUNIVERSITY CITY AREA PLAN. Volume Two: Implementation Plan
UNIVERSITY CITY AREA PLAN Volume Two: Implementation Plan Transforming the University City MSD into the vibrant, people-oriented place envisioned in the University City Plan will occur incrementally through
More informationCorridor Vision. 1Pursue Minnehaha-Hiawatha Community Works Project. Mission of Hennepin County Community Works Program
1Pursue Minnehaha-Hiawatha Community Works Project Minnehaha-Hiawatha Community Works is a project within the Hennepin Community Works (HCW) program. The mission of the HCW program is to enhance how the
More informationCOASTAL REGION METROPOLITAN PLANNING ORGANIZATION APRIL 2012 MPO MEETINGS
COASTAL REGION METROPOLITAN PLANNING ORGANIZATION APRIL 2012 MPO MEETINGS Agenda Item: Presenter: Summary: The project priorities for the CORE MPO s FY 2013-2016 Transportation Improvement Program (TIP)
More informationRutherford County Projects
Rutherford Projects 5307 Urban Operating for Rover Public Transit - Relax & Ride Service TIP # 2005-006 Transit Operations Murfreesboro Public Transit Rutherford Length 0.00 Regional Plan ID Consistent
More informationAPPENDIX D: Visual and Aesthetic Conditions for NCCU Station Refinement. Durham-Orange Light Rail Transit Project
APPENDIX D: Visual and Aesthetic Conditions for NCCU Station Refinement Durham-Orange Light Rail Transit Project October 2016 1. Introduction The Combined FEIS/ROD summarizes the effects of the D-O LRT
More informationSeneca Meadows. Block 4 Locate office, technology, and medical development adjacent to I Screen views of garage structures from I-270.
Seneca Meadows Seneca Meadows has an industrial park in its southern end and a mixed-use employment area planned for the north end. The district benefits from extensive I-270 visibility, stream valley
More informationEastern Terminus TECHNICAL MEMORANDUM CENTRAL BROWARD EAST-WEST TRANSIT ANALYSIS BROWARD COUNTY, FLORIDA
Eastern Terminus TECHNICAL MEMORANDUM CENTRAL BROWARD EAST-WEST TRANSIT ANALYSIS BROWARD COUNTY, FLORIDA FINANCIAL PROJECT ID NUMBER 411189-2-22-01 FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 4 Prepared
More informationYORK COUNTY GOVERNMENT
YORK COUNTY GOVERNMENT Planning & Development Services MEMORANDUM TO: FROM: RE: DATE: May 9, 2016 York County Council York County Planning Commission Eddie Moore, Development Services Manager PROPOSED
More information