SHOREWOOD SCHOOL DISTRICT FACILITY ASSESSMENT. October 25, 2016 EUA Project:

Size: px
Start display at page:

Download "SHOREWOOD SCHOOL DISTRICT FACILITY ASSESSMENT. October 25, 2016 EUA Project:"

Transcription

1 October 25, 2016 EUA Project:

2 Page 1 Eppstein Uhen Architects October 25, 2016

3 TABLE OF CONTENTS SECTION 1 EXECUTIVE SUMMARY TEAM CONTACTS PROJECT INTENT DATA GATHERING PROCESS UNDERSTANDING THE FACILITY ASSESSMENT SUMMARY OF FINDINGS DEFICIENCIES MATRIX RECOMMENDED NEXT STEPS SECTION 2 CAPACITY AND UTILIZATION SECTION 3 EDUCATIONAL ADEQUACY ASSESSMENT (EAA) BEST PRACTICES IN EDUCATIONAL DESIGN FOR 21 st CENTURY LEARNING ATWATER ELEMENTARY SCHOOL LAKE BLUFF ELEMENTARY SCHOOL SHOREWOOD INTERMEDIATE SCHOOL SHOREWOOD HIGH SCHOOL SECTION 4 ASSESSMENT PLANS AND OBSERVATIONS HISTORICAL PLANS HISTORIC PLANS SITE ASSESSMENT EXTERIOR ASSESSMENT INTERIOR ASSESSMENT PLUMBING ASSESSMENT (Muermann Engineering) MECHANICAL ASSESSMENT (Fredericksen Engineering) ELECTRICAL ASSESSMENT (Muermann Engineering) SECTION 5 APPENDIX ENROLLMENT PROJECTIONS APPLIED POPULATION LABORATORY MAY 2016 DISTRICT PROVIDED ASSESSMENTS: RIGGING SURVEY REPORT THE CHICAGO FLYHOUSE 2014 SHOREWOOD HIGH SCHOOL LIGHTING SYSTEM INSPECTION REPORT CLEARWING SYSTEMS INTEGRATION AUG/SEP 2015 TUNNEL REPORT HARWOOD ENGINEERING AUGUST 2013 LIMITED FUNGAL AIR SAMPLING INDOOR AIR QUALITY DIAGNOSTICS, INC JUNE 2013 STRATEGIC FACILITY PLANNING GUIDE FY ADMINISTRATION MECHANICAL, ELECTRICAL, AND PLUMBING ENGINEER RECOMMENDATIONS Page 2 Eppstein Uhen Architects October 25, 2016

4 TEAM CONTACTS Project Shorewood School District Facility Assessment 1701 East Capitol Drive Shorewood, WI Contact: Patrick Miller (414) Architect Electrical Eppstein Uhen Architects Muermann Engineering 333 E Chicago Street 116 Fremont Street Milwaukee, WI Kiel, WI (414) Ext. 129 Teresa Wadzinski, AIA Curt Krupp, PE Mechanical Plumbing Fredericksen Engineering Muermann Engineering Corporate Pkwy. Suite N Broadway Mequon, WI De Pere, WI (262) Ext.112 (920) Ext. 306 Randy All, PE Juli-Anna Simonet, PE Page 3 Eppstein Uhen Architects October 25, 2016

5 INTRODUCTION The Facilities Assessment is a critical first step in the planning process helping school districts and their stakeholders better understand the current state of its facilities and how well these facilities support educational goals. The Districtwide Facilities Assessment provides an objective analysis of present building and site conditions and capabilities, and is a critical step needed to understand how today s facilities and sites support the District goals. The Facilities Assessment provides an independent, objective analysis of the present conditions and capabilities of the district s facilities and grounds. It also serves as a foundational resource document to support fiscally responsible immediate and long term facilities planning. The information presented in this report was gathered through on-site inspections of the sites and buildings, and interviews with various building administrators, teachers, support staff, and maintenance staff. Included in this report is an analysis of the existing building capacities, ADA facility assessments, educational adequacy, building exterior and interior assessments, and an overview of the sites occupied by the district. Please reference the complete Districtwide Facilities Assessment for comprehensive details, supporting data, and additional research. DISTRICT OVERVIEW Shorewood School District Mission Statement The mission of the School District of Shorewood is to provide a liberal arts education that prepares students to embrace the challenges of the future. We will foster a love of learning and the acquisition of knowledge and skills that will serve as the foundation and catalyst for a lifetime of learning. Shorewood School District Strategic Initiative: Modernizing Historic Facilities Vision: The Shorewood School District will provide safe, healthy, and efficiently operated school facilities, equipped for 21 st century learning, while honoring the history of our buildings. The Shorewood School District serves approximately 2100 students in grades 4K-12 in ten buildings. The district is comprised of four campuses: Atwater Elementary Campus o Main Elementary School Building (K-6) o Early Education Center (4K-5K) o (Powerhouse) o (Storage Shed) Lake Bluff Elementary Campus o Main Elementary School Building (K-6) o Early Education Center (4K-5K) o (Powerhouse) o (Storage Shed) Shorewood Intermediate School Campus (7-8) Shorewood High School Campus (9-12) o Administration Building o Science/Art Building Page 4 Eppstein Uhen Architects October 25, 2016

6 o Auditorium o PE/Arena Building o PE/SHS Pool o Fitness Center o VHE Pool o (Powerhouse) o (Garage) For each building and major section of this report, Eppstein Uhen Architects (EUA), Fredericksen Engineering, and Muermann Engineering have identified professional observations and recommendations to inform future facilities planning. PROJECT INTENT The first step of planning includes the assessment of building and site conditions. The study reviews major building systems and building operations: Mechanical Electrical Plumbing Building Exterior Building Interior Site Accessibility/ADA Building Capacity Analysis This report is based upon industry standards and practices in architecture and engineering in the areas of mechanical, electrical, plumbing, and fire protection. Observations and recommendations included in this report are based on a cursory visual assessment and interviews on site. It is important to note that the buildings are generally well maintained and maintenance needs have been prioritized based on safety concerns and severity of need. While there are some findings within this report that demonstrate a more urgent need, many of the items could be addressed through ongoing scheduled maintenance. This study also includes observations related to compliance with applicable building codes and regulations. With district buildings designed as early as 1915 and 1924, under building codes that were less stringent, these schools now face significant code compliance issues, such as with the Americans with Disabilities Act (ADA) guidelines. Although older buildings are legally grandfathered by the previous codes, some items will require corrections in the event that renovations or additions be completed in the future. DATA GATHERING PROCESS Team site visits took place in June and July 2016 and included EUA, Fredericksen Engineering, and Muermann Engineering. The team met with administration, staff, and facilities staff to review priorities and concerns and gather general building information. The team walked through the building to conduct their own observations and analyses. Conditions observed were not field measured and require additional review if future action is to be taken. Page 5 Eppstein Uhen Architects October 25, 2016

7 UNDERSTANDING THE The Building Condition Assessment includes a comprehensive review of the building s exterior shell (roof, wall systems, windows/doors, etc.); interior finishes and materials (flooring, casework, etc.); mechanical, electrical, and plumbing systems; and compliance with the Americans with Disabilities Act (ADA) relative to accepted industry standards. The building assessment involves visual assessment of current conditions, documentation of observations, and general recommendations for repair and/or replacement of building components or systems where necessary. On-site observations include the review of system and component age, construction methods, material adequacy, and longevity. The Facility Assessment compiles visual assessment data, meeting discussions, and source documents to identify known deficiencies. The Facility Assessment does NOT include: Detailed validation of as-built conditions Hazardous material assessments Destructive testing or observation of concealed systems, below grade conditions, or components buried within walls, ceilings, or roofing systems Specific details about electrical panels, mechanical equipment, or plumbing components that are not readily visible Measurement of electrical loads or temperatures of any electrical equipment Actual efficiencies or performance testing of HVAC equipment (pumps, fans, boilers, etc.) Adequacy of fire or life safety components associated with building systems including code requirements, dampers, fire rating of systems, etc. Functionality and performance of the Plumbing equipment (pumps, water heaters, etc.) The Americans with Disabilities Act (ADA) Assessment considers the compliance relative to accepted industry standards. A building s adherence with ADA is based on the review of the accessible routes to and through the building and site, as well as accessible features and accommodations inside the building as defined by ADA design guidelines and the International Building Code. The Educational Adequacy Assessment (EAA) is a comprehensive review of the educational program activities, use of the building, and physical spaces required for each activity and provides analysis of how effectively the spaces support student learning and program delivery. This is done with input from building principals and staff. The Building Capacity Analysis reviews the student capacity and evaluates the data against several nationally recognized educational planning recommendations. There are three different capacity calculations used that are detailed in the complete Facility Assessment. In general, over the past decade, recommended space provided per student has increased. The major reasons are: Space is needed to support children with special needs; students with disabilities, cognitively disabled students, and special education needs. Page 6 Eppstein Uhen Architects October 25, 2016

8 Space needed to support specialists in the area of reading, speech, occupational therapy, physical therapy, and Title I programs. Space needed to support paraprofessionals, volunteers, and parent support groups. Space needed to support personalized learning, team teaching, and flexible collaboration in common areas. Space to accommodate technology and its infrastructure. The following tables summarize information of district facilities and current enrollment as of September Building Current Enrollment (September 2016) Capacity Based on Square Feet per Student in Learning Environments Capacity Based on District Staff to Student Ratio Capacity Based on Gross Square Footage of School Atwater Elementary Lake Bluff Elementary Shorewood Intermediate a, b 508 c 845 d a, b 574 c 726 d a, b 491 c 490 d Shorewood High a, b 971 c 1050 d a. Based on 55 SF per Kindergarten student, 35 SF per student grades 1-5, and 30 SF per student for general classrooms grades Science Rooms, FACE Labs, and Art Rooms use 50 SF per student. Tech Ed Lab spaces use sq. ft. per student depending on the academic focus. b. Functional Design Capacity is 90% of maximum capacity at elementary, and 80% of the maximum capacity in intermediate and high schools. c. Based on recommended students per instructor as provided by Shorewood School District d. Based on 150 SF per student at Elementary, 180 SF per student at Intermediate, and 230 SF per student at High Page 7 Eppstein Uhen Architects October 25, 2016

9 SUMMARY OF FINDINGS BY BUILDING/CAMPUS Atwater Elementary Statistics Year Built: 1915 (additions/renovations in 1968) Site Size: 7.55 acres Building Size: 126,723 sq. ft. Current Enrollment (Sept. 2016): 544 Grade Levels: 4K-6 Building Condition Assessment ATWATER ELEMENTARY Exterior of Atwater Elementary is generally in good-to-fair condition. Windows are in fair condition; however, the upper sash of the windows has been screwed shut. All window screens have failed. Exterior doors should be addressed with general maintenance to confirm proper operation for exiting. The built-up roof is in good condition and well maintained; however, there is the need for tuckpointing at the parapets and chimney. (Chimney may need more extensive brick repair/removal.) Roof expansion joint covers should be replaced at all district buildings. In general, site landscaping should be cleaned up and site grading should be addressed to direction water away from the building and windows at grade. The original wood doors from 1915 are in poor condition. Acoustical lay in ceilings (ACT) are showing signs of sag or discoloration, and portions of the grid have discolored or rusted. Sporadic ceiling replacements have taken place. An area of further investigation should be a crack in the wall that travels the entire height of the building at the center stair, which was observed by staff as seemingly getting bigger. ADA Observations ATWATER ELEMENTARY There is one ADA entrance on the north side of the building; however, the ramp is secluded and in poor condition. There are no restrooms in Atwater that meet ADA compliance. Classroom entries are non ADA-compliant. Stairs and handrails do not meet current building code. Mechanical/Electrical/Plumbing Assessment ATWATER ELEMENTARY Six air handling units contain steam heating coils but lack air conditioning. Separate units with air conditioning serve the Office and Computer Lab. The steam heating system consists of two steam boilers located in the basement. These boilers were installed in 2014 and are in good condition. This building has both digital and pneumatic controls. Despite the fairly new steam heating plant, much of the other HVAC equipment in the building is at or nearing the end of its expected service life. The 1993 addition is fully sprinkled; the original building is not. Page 8 Eppstein Uhen Architects October 25, 2016

10 The main electric service for this building has been recently replaced in 1993 to a 2000A, 120/208V 3 phase, 4 wire service. Most panelboards throughout the building are nearing the end of their lifespan. Lighting throughout most spaces consists of 2 x4 recessed parabolic 3-lamp T8 fixtures. Emergency lighting is minimal. The clock/bell schedule system is in the main office is old but in good working condition. The access control system controls 4 exterior doors via card readers and 2 via keypad. Some exterior doors lack door contacts. The intercom system is antiquated but in good working condition. The Notifier fire alarm system is in nearing the end of its useful lifespan and should be scheduled for future replacement. Fire alarm smoke detection coverage is adequate throughout spaces. Fire/smoke doors are no longer functional. Fire alarm notification coverage is lacking in areas. The CCTV system consists of 6 cameras throughout the building, monitored at the front office. The water piping in this facility is mostly original and is copper piping that is in fair to poor condition. Many of the valves are also original and there are not enough isolation valves for proper system maintenance. The incoming water main was replaced in the 1980 s. The sanitary piping is cast iron piping that is original in most cases. The storm piping is cast iron original piping. The owner has stated that they have groundwater issues with water coming up thru the floor in the multipurpose room on the lower level. The school is built in a high water area and has issues with water in lower level. Most of the plumbing fixtures in the building appear to be original and are in poor condition. Educational Adequacy Assessment ATWATER ELEMENTARY The site is well maintained and has adequate space for outdoor activity and play. There are current efforts to replace outdated furniture with newer, more flexible furniture. The school is equipped with wireless technology and has projection capabilities in most learning spaces. Almost all learning spaces have large windows which provide ample natural light. Not all building perimeter entry points are monitored. Buildings do not have appropriate controlled access sequences for students and visitors. Entry access codes are provided to nonemployees (parents). Lack of transparency inside the building inhibits passive supervision of common areas. Many spaces are too small for their intended use. Building typically does not provide flexible learning spaces or access to different types of learning spaces to support different forms of learning. A lack of visual connectivity between spaces, and from learning spaces to common areas, further restricts learning options. A number of spaces are partially below grade, limiting the amount of natural daylight and views to outside. Building typically does not provide flexible furniture. Building is old and showing signs of wear which impacts the environment for learning. Windows and screens are difficult to operate. Page 9 Eppstein Uhen Architects October 25, 2016

11 Lake Bluff Elementary Statistics Year Built: 1924 (additions/renovations in 1968) Site Size: acres Building Size: 108,941 sq. ft. Current Enrollment (Sept. 2016): 618 Grade Levels: 4K-5 Building Condition Assessment LAKE BLUFF ELEMENTARY The masonry is in good condition. Windows are fair, and screens have also failed. The roof is generally in good condition except for areas of water ponding and the roof over the cafetorium. Exterior doors should be maintained to ensure proper operation for exiting. Lake Bluff has hallway cubbies that are original to the building, but no longer functional. There are also three fireplaces that are original to the building. ADA Observations LAKE BLUFF ELEMENTARY There is one ADA entrance into the building. There are no restrooms that meet ADA compliance. Classroom entries are non ADA-compliant. Stairs and handrails do not meet current building code. Mechanical/Electrical/Plumbing Assessment LAKE BLUFF ELEMENTARY The unit ventilators utilize hot water heat and serve all of the classroom and office areas. There are two air handling units that serve this building. The unit serving the gym does not provide adequate heat, and there are many temperature complaints in winter. The building is served by multiple exhaust fan systems of varying ages and conditions. The building is not air conditioned. The boiler plant was replaced in 2014 and is in good condition. Most of this building has been updated to digital controls. Some of the office and storage areas still have the original pneumatic controls. The hot water system and the classroom unit ventilators are in good condition and should continue to serve the school for the next years. The main electric service for this building is 120/208V 3phase 4 wire and is nearing the end of its lifespan, fed from an exterior pad mounted transformer at the southwest corner of the building. Most panelboards throughout the building are nearing the end of their lifespan. Lighting throughout most spaces consists of 2 x4 recessed parabolic 3-lamp T8 fixtures. Emergency lighting is minimal. The phone system is a Cisco IP phone system and is in good working condition. The school is interconnected to the high school s data network via radio antenna. The clock/bell schedule system is in the main office and is relatively old but in good working condition. The access control system controls various exterior doors via card readers and 2 via keypad, controlled via electric strikes. Electric strikes are in good working condition. Page 10 Eppstein Uhen Architects October 25, 2016

12 Some exterior doors lack door contacts. The intercom system is antiquated but in good working condition. The Simplex fire alarm system is in good working condition. Fire alarm smoke detection coverage is adequate throughout spaces. Fire/smoke doors are no longer functional. Fire alarm notification coverage is lacking in areas. The CCTV system consists of 4 cameras throughout the building, monitored at the front office. The majority of the copper water piping in this facility is original and is in fair to poor condition. Many of the valves are also original, and there are not enough isolations valves for system maintenance. The incoming water main was replaced in the 1980 s. The sanitary piping is cast iron or clay piping that is original in most cases. The owner noted problems with tree roots in the clay piping mains. The storm piping is cast iron and is original to the building. The owner has stated that they have site drainage issues at the east side of the building. Most of the plumbing fixtures in the building appear to be original and are in poor condition. The original building is not sprinkled. The 1993 is fully sprinkled. Educational Adequacy Assessment LAKE BLUFF ELEMENTARY The site is well maintained, and has adequate space for play. Equipment is in relatively good condition and age appropriate. Multiple areas for outdoor learning. There are current efforts to replace outdated furniture with newer, more flexible furniture. The school is equipped with wireless technology and has projection capabilities in most learning spaces. Almost all learning spaces have large windows which provide ample natural light. Not all building perimeter entry points are monitored. Buildings do not have appropriate controlled access sequences for students and visitors. Entry access codes are provided to nonemployees (parents). Lack of transparency inside the building inhibits passive supervision of common areas. Many spaces are too small for their intended use. Building typically does not provide flexible learning spaces, or access to different types of learning spaces to support different forms of learning. A lack of visual connectivity between spaces, and from learning spaces to common areas, further restricts learning options. Building typically does not provide flexible furniture. Building is old and showing signs of wear which impacts the environment for learning. Windows are difficult to operate. Page 11 Eppstein Uhen Architects October 25, 2016

13 Atwater / Lake Bluff EEC Statistics Year Built: 1968 Site Size: N/A Building Size: 8,670 sq. ft. Grade Levels: 4K-5K Building Condition Assessment ATWATER / LAKE BLUFF EEC The masonry is in good condition. Windows are fair but are not operable. The roofs are overall in poor condition. Bathrooms are in poor condition. ACT ceilings are in fair condition. ADA Observations ATWATER / LAKE BLUFF EEC There are no restrooms that meet ADA compliance. The classroom sinks do not meet ADA compliance. Mechanical/Electrical/Plumbing Assessment ATWATER / LAKE BLUFF EEC All of the HVAC systems in this building have exceeded their expected service life. The access control system controls 2 exterior doors via card readers, controlled via electric strikes. The simplex fire alarm system is in relatively new and in good working condition. Fire alarm smoke detection coverage is adequate throughout spaces. The main electric service is most likely original to the building, and is a 400A, 120/208V 3 phase, 4 wire service. There are no surge suppression provisions. The service is at full capacity and has no room for future additions. The electric service equipment throughout the building is nearing the end of their lifespan. The copper water piping in this facility is mostly original and is in fair condition. The sanitary and storm piping is cast iron and original to the building. The owner has not indicated any issues with the sanitary or storm piping. Most of the plumbing fixtures in the building appear to be original and are in poor condition. An 80 gallon electric water heater supplies the building hot water. There is no fire protection (sprinkler system) at either building. Educational Adequacy Assessment ATWATER / LAKE BLUFF EEC Building typically does not provide flexible learning spaces, or access to different types of learning spaces to support different forms of learning. Building typically does not provide flexible furniture. Not all building perimeter entry points are monitored. Spaces typically lack ability to passively supervise adjacent spaces. Page 12 Eppstein Uhen Architects October 25, 2016

14 Shorewood Intermediate School Statistics Year Built: 1970 (additions/renovations in 1993) Site Size: 19.8 acres (shared site with HS) Building Size: 88,274 sq. ft. Current Enrollment (Sept. 2016): 320 Grade Levels: 6-8 Building Condition Assessment SHOREWOOD INTERMEDIATE SCHOOL Exteriors are generally in good condition. Acoustical lay-in ceilings (ACT) are showing signs of sag or discoloration, and portions of the grid have discolored or rusted. Casework is worn and in poor condition. Flooring (VCT) is worn and dated. The interior doors are original to the 1970 building. ADA Observations SHOREWOOD INTERMEDIATE SCHOOL There are no ADA-compliant restrooms in the Intermediate building. Restrooms were upgraded, but they do not meet current code compliance in regards to the size of stalls and entry. A few of the drinking fountains meet ADA, but not all. Door hardware has been replaced sporadically to meet ADA. The cafeteria is also not ADA accessible. There are no ramps or railings to access the cafeteria. Mechanical/Electrical/Plumbing Assessment SHOREWOOD INTERMEDIATE SCHOOL Heating and ventilation is provided to the Intermediate School by five air handling units. A majority of the units are at or nearing the end of their expected service life. The boiler plant was installed in 1993 and is nearing the end of its expected service life. A Trane chiller, installed in 2002, and cooling tower are in good condition. The building controls are a combination of digital and pneumatic. Many of the HVAC systems serving this building are at or nearing the end of their service life. Plans should be made for a substantial HVAC renovation for this building. The main electric service is most likely original to the building, and is a 2000A, 277/480V 3 phase, 4 wire service, fed from an exterior pad mounted transformer at the southeast corner of the building. There are no surge suppression provisions. The service is at full capacity and has no room for future additions. There is a relatively new 30kW roof mounted generator that is in good working condition; however, the life safety system has non-life safety loads connected. Lighting throughout most spaces consists of 2 x4 recessed parabolic 3-lamp T8 fixtures. Emergency lighting is minimal. The phone system is a Cisco IP phone system and is in good working condition. The Simplex clock/bell schedule system is in the main office and is in good working condition. The intercom system is IP based and is in good working condition. Page 13 Eppstein Uhen Architects October 25, 2016

15 The access control system monitors all of the exterior doors via door contacts. There are 4 sets of doors controlled via card readers and magnetic door locks. The building did not have a security system. The Simplex fire alarm system is in good working condition. Fire alarm smoke detection coverage is adequate throughout spaces. Fire/smoke doors are no longer functional. Fire alarm notification coverage is lacking in areas. There was no CCTV camera system. The copper water piping in this facility is original and is in fair to poor condition and has had many leaks. Many of the valves are also original, and there are not enough isolations valves for system maintenance. The sanitary piping is cast iron and galvanized and is original to the building in most cases. The owner has reported issues with the drains in the kitchen. The storm piping is also cast iron and original to the building. Most of the plumbing fixtures in the building appear to be original and are in poor condition. The hot water source equipment for the building consists of three gas-fired water heaters located in the boiler room. Two of the water heaters are not in operation. A new dishwasher was install in the kitchen that is chemically sanitized, so high temperature hot water is not required for the dishwasher. There is no fire protection. Educational Adequacy Assessment SHOREWOOD INTERMEDIATE SCHOOL Main office has visual supervision of visitors entering building and a relatively secure entrance sequence. Most learning spaces are appropriately sized and provide ample room for flexibility within the space. The school is equipped with wireless technology and has projection capabilities in most learning spaces. Most learning spaces have windows which provide natural light. The site is smaller than recommended and does not provide adequate outdoor play areas. There is no separation of pedestrian and vehicular traffic. Not all building perimeter entry points monitored and security cameras do not all function properly. Lack of transparency inside the building inhibits passive supervision of common areas. Most learning spaces are awkwardly shaped due to the building design. Building typically does not provide flexible learning spaces, or access to different types of learning spaces to support different forms of learning. A lack of visual connectivity between spaces, and from learning spaces to common areas, further restricts learning options. Building typically does not provide flexible furniture. Building is dated and showing signs of wear which impacts the environment for learning. Several learning spaces have acoustic issues due to movable or partial height walls. Windows do not functions well. Page 14 Eppstein Uhen Architects October 25, 2016

16 Shorewood High School Statistics Year Built Admin: 1924 Arts & Science: 1929 Auditorium: 1934 PE/Arena: 1927 PE/SHS Pool: 1929 Fitness Center: 1924 VHE Pool: 1975 Powerhouse: 1928 Garage: 1989 Site Size: 19.8 acres (shared site with IS) Building Size: 541,852 sq. ft. (total for all buildings) Current Enrollment (Sept. 2016): 679 Grade Levels: 9-12 Building Condition Assessment SHOREWOOD HIGH SCHOOL General Drainage issues throughout the site; no curbing at asphalt and general washing out of asphalt. Most, if not all, site handrails are showing signs of corrosion at their bases. Several areas of grass that drain back to building. Track drainage issues. Building exteriors are generally in good-to-fair condition. In general, flooring materials are in poor condition, with the exception of the original terrazzo. Roof expansion joint covers should be replaced; however, roofs are generally in good condition. Some acoustical lay in ceilings (ACT) are showing signs of sag or discoloration, and portions of the grid have discolored or rusted. Sporadic ceiling replacements have taken place. An area of further investigation should be a crack in the wall at the lower level Arena building. ADA Observations SHOREWOOD HIGH SCHOOL General Several exterior exits have stairs that do not meet ADA and building code compliance. Some restrooms do not meet ADA compliance; restrooms in buildings that were built or renovated after 200x have levels of ADA compliance. The locker rooms in the PE building are not ADA-compliant. Not all drinking fountains are ADA-compliant. Some classroom entries ADA-compliant. Interior stairs and handrails do not meet current building code. An ADA chair lift is provide at the 1929 pool deck. Mechanical/Electrical/Plumbing SHOREWOOD HIGH SCHOOL General All of the heating for this campus is provided from the central hot water boiler plant located in the Campus Powerhouse. Individual buildings have dedicated hot water pumps for distribution within the building. Lighting throughout most spaces consists of 2 x4 recessed parabolic 3-lamp T8 fixtures. There are no emergency lighting provisions throughout the campus buildings. The clock/bell schedule system is in good working condition. This system controls clocks/bells throughout the high school campus. There is a mixture of clocks, ranging from Universal brand, Page 15 Eppstein Uhen Architects October 25, 2016

17 Howard Miller, and International brand that are still connected to the clock system to battery operated clocks that are not controlled by the clock system. The intercom system is interconnected to the IP phone system through a dedicated phone in the main office of the Administrative Building. There are paging amplifiers in each building that provide intercom service throughout the whole campus. There are new speakers installed in areas where the existing speakers no longer function. The original speakers were abandoned in place. The system is in good working condition. Most spaces lack receptacles and some even have nuisance tripping problems due to overloaded circuits. Most wiring devices are installed in surface raceway. The access control system is Altronix brand. Most exterior doors are monitored. There are card readers that release electric strikes or magnetic door locks. Magnetic door locks are in the process of being phased out with new electric strikes. Access control wiring at doors is run in surface raceway. The Simplex fire alarm system is in good working condition. The control panel serves the Administrative, Arts and Science, and Pool Buildings. Fire alarm smoke detection coverage is adequate throughout spaces. Fire/smoke doors are no longer functional. None of the buildings on campus are interconnected. Fire alarm notification coverage is lacking in areas. The CCTV system is IP based and has various issues including nuisance malfunctioning, recording problems, and inferior image quality. Various camera manufacturers and types were indicated throughout campus. There are two monitoring locations, one in the main office and one in the power house. The sanitary piping is cast iron piping and galvanized piping that is original in most cases. The storm piping is cast iron original piping. Many of the plumbing fixtures in the building appear to have been replaced and are in good condition. Original plumbing fixtures are in fair to poor condition. Hot water for this building comes from the Powerhouse Building. There is no fire protection, with the exception of the Administration Building, which has a wet fire protection system to serve the fire hose cabinets in the building (no sprinkler heads) and the Auditorium, which has a fire protection riser is located in the lower level and a system that supplies fire hose valves and wet sprinkler system for the building. Educational Adequacy Assessment SHOREWOOD HIGH SCHOOL General The site is well maintained, and has become an iconic part of the city. Nice outdoor spaces for students to gather or learn. There are current efforts to replace outdated furniture with newer, more flexible furniture. The school is equipped with wireless technology and has projection capabilities in most learning spaces. Almost all learning spaces have large windows which provide ample natural light. It is a very open campus. Buildings are open to the public, and building perimeter entry points (doors) are not fully monitored. Wayfinding is challenging for visitors and first-time students. Lack of transparency creates many areas that are difficult to supervise. Many educational spaces are too small for their intended uses. Building typically does not provide flexible learning spaces, or access to different types of learning spaces to support different forms of learning. A lack of visual connectivity between spaces, and from learning spaces to common areas, further restricts learning options. Page 16 Eppstein Uhen Architects October 25, 2016

18 There is no student commons, and little breakout space available for student use or group activities. Building is showing signs of wear and tear due to its age, which impacts the environment for learning. SHOREWOOD HIGH SCHOOL Admin Building All windows were replaced 1993; however, there is corroding of lintels above windows. Heating, ventilation, and air conditioning systems consist of fan coil units and unit ventilators. Sanitary piping that has been replaced is PVC. Many of the plumbing chases and janitor s closets have visible water damage at the ceiling due to pipe leaks and breaks. The toilet room plumbing fixtures appear to be in good condition, and many of the flush valves and faucets have been replaced. The main electric service for this building has been recently replaced within the last 15 years to a 2000A, 120/208V 3 phase, 4 wire service, fed from an exterior pad mounted transformer at the southeast corner of the building. Most branch panelboards have also been replaced and are in good working condition. SHOREWOOD HIGH SCHOOL PE / Arena Building Original glass block openings. There is some damage to bleacher seats. Gym flooring is in good condition. Gym partition is in poor condition. Kitchen is in good condition. Roof is in fair condition, but tuck-pointing is needed around chimney and at decorative parapet. Roof hatch is rusted. There are areas of water damage on arena ceiling. There are areas of wall damage and settlement in the lower level that should continue to be monitored. The heating, ventilation, and air conditioning systems consist of three air handling units. Two units have hot water heat and one of the units has air conditioning. These air handling units should continue to serve the building for the next years. A third air handling unit serves the Arena. This unit is original to the building and has exceeded its expected service life. An electric water heater in the kitchen serves the kitchen hot water loads. Most of the plumbing fixtures in the building appear to be in fair to poor condition and many are original. The faucets in the toilets rooms have been replaced and are in good condition. The main electric service for this building has been recently replaced within the last 10 years to a 1200A, 120/208V 3 phase, 4 wire service, fed from a pole mounted transformer at the southeast corner of the building. Most branch panelboards serving the PE building are relatively new and in good working condition. Panelboards serving the arena are past their useful lifespan. There is an emergency panel that was previously connected to the emergency backup generator. The generator is now abandoned and no longer functional. Staff indicated that when the air conditioner, elevator, and kitchen coolers turn on at the same time, it will trip the main breaker. Page 17 Eppstein Uhen Architects October 25, 2016

19 A wall mounted data rack serving the arena is in the arena storage room and a wall mounted rack serving the PE building is located in the basement. The data racks are interconnected to the main data rack in the administrative building via fiber optic cabling. SHOREWOOD HIGH SCHOOL Art and Science Building All windows were replaced 1993; however, there is corroding of lintels above windows. There is horizontal cracking in the CMU and chipping and cracking at floor slab. Heating, ventilation, and air conditioning are provided by unit ventilators. Most of the plumbing fixtures in the building are original and are in fair to poor condition. Some of the toilet room faucets and flush valves have been replaced and are in good condition. The main electric service for this building has been recently replaced within the last 10 years to a 800A, 120/208V 3 phase, 4 wire service, fed from an exterior pad mounted transformer at the west side of the building. Most branch panelboards have been replaced and are in good working condition. A wall mounted data rack serving the facility is in the electrical room. This rack serves as the data distribution for the art & science building. The data rack is interconnected to the main data rack in the administrative building via fiber optic cabling. SHOREWOOD HIGH SCHOOL Auditorium All windows were replaced 1993; however, there is corroding of lintels above windows. Auditorium louver screens and exterior decorative wood trim has chipped and peeling paint. Heating, ventilation, and air conditioning systems consist of air handling units and unit ventilators. The air handling units were installed new in The classrooms are served by the unit ventilators. The main electric service for this building has been recently replaced within the last 15 years to a 1600A, 120/208V 3 phase, 4 wire service, fed from an exterior pad mounted transformer at the south side of the building. Most branch panelboards have been replaced and are in good working condition; however, they do not have sufficient available space for future additions to the system. The dimming and electrical distribution system for the auditorium theatrical systems has very serious fire hazard issues and code violations that should be further investigated and resolved as soon as possible; improper installations and safety hazards were seen throughout, including theatrical light fixtures without safety rigging cables, theatrical wiring blocking fire doors, and even melted electrical raceway connectors. A wall mounted data rack serving the facility is near the elevator mechanical room. This rack serves as the data distribution for the Auditorium building. The data rack is interconnected to the main data rack in the administrative building via fiber optic cabling. There is Cat5e riser rated cable in plenum spaces. SHOREWOOD HIGH SCHOOL Pool Second level walkway does not have guardrail, which would be required in the current building code. Areas of chipped floor tile. Bleachers are in good condition. Corrosion at base of steel columns. Page 18 Eppstein Uhen Architects October 25, 2016

20 Heating and ventilation are provided by two separate units. The first unit utilizes hot water heat to serve the Pool. The second unit is located in the second floor mechanical room and provides heat and ventilation to the Locker Rooms and Lobby. Both are in good condition. The exhaust systems serving the building are in satisfactory condition, but are approaching the end of the expected service life. The boiler plant is in good condition and should continue to serve the building for another years. Solar panels and storage tank are installed for pool heating. The main electric service for this building has been recently replaced within the last 15 years to a 800A, 120/208V 3 phase, 4 wire service, fed from an exterior pad mounted transformer at the south side of the building. The main disconnect is located outside at the CT cabinet. The branch panelboards have been replaced and are in good working condition; there is sufficient available space for future additions to the system. Lighting in the pool area consists of large metal halide fixtures. There were no occupancy sensors in any rooms. There was no exterior lighting at the main entrances. A wall mounted data rack serving the facility is located in the basement. This rack serves as the data distribution for the pool building. The data rack is interconnected to the main data rack in the administrative building via fiber optic cabling. The equipment shows premature aging/corrosion due to it being near the pool cleaning equipment. Most of the plumbing fixtures in the building appear to have been recently replaced and are in good condition. SHOREWOOD HIGH SCHOOL Community Fitness Center Interiors are new. The heating, ventilation, and air conditioning is provided by three gas fired rooftop units. These units are approximately years old and are at the end of their expected service life. The sanitary piping is cast iron piping. Plumbing fixtures in the building are in good working condition. The hot water for the building comes from a gas-fired water heater located in a storage room. A new combination water service comes into a closet in the girl s locker room. A 3 water meter with bypass and a fire protection riser are located in this closet. Page 19 Eppstein Uhen Architects October 25, 2016

21 DEFICIENCIES MATRIX LIFE SAFETY AND CODE COMPLIANCE ADA ACCESSIBILITY Atwater Elementary Atwater ECC Lake Bluff Elementary Lake Bluff ECC Intermediate School HS Admin Building HS Arena HS Art and Science HS Auditorium HS Fitness Center HS P.E. Building HS Pool EXTERIOR WALL SYSTEMS (MASONRY) INTERIOR WALL SYSTEMS (PLASTER) ROOFING 4 DOORS/FRAMES , , WINDOWS FLOORING - TILE FLOORING - TERRAZZO FLOORING - CARPET CEILINGS CASEWORK PARKING SAFETY FIELDS/PLAYGROUNDS 16 WALKWAYS/ASPHALT DRAINAGE ELECTRICAL EQUIPMENT PLUMBING PIPING PLUMBING FIXTURES LIGHTING ? HVAC SYSTEMS FIRE ALARM SYSTEM DATA/TELCOM/SECURITY DEFICIENT Notes: (1) See facility assessment plans for specific areas exterior wall deficiencies. (2) Interior walls are in good condition overall, but some areas of minor damage are prevalent. See facility assessment plans for locations. (3) Major areas of cracking were identified at specific sections of the building, which should be further investigated (see Facility Assessment Plans in Section 4). Other minor areas of cracking are within the expected limits, given the products age. Page 20 Eppstein Uhen Architects October 25, 2016

22 (4) Specific areas of roofing were identified as deficient, as well as potential issues with wall flashing, which are identified on the plans. (5) Overall, interior doors throughout the building are in good condition with only minor cosmetic damage to the frame and/or door finish. (6) Exterior doors and associated hardware are nearing the end of their useful life expectancy. (7) Nearly all window screens show signs of damage, and double hung windows are not functioning properly. (8) Steel lintels show signs of corrosion. (9) Areas of VCT throughout the building are in poor condition. (10) Minor areas of damaged floor/base tile were identified. (11) Minor cracking in terrazzo flooring was identified through the building. (12) The building has a mix of new and heavily used carpet. (13) The building has a mix of new and worn ceiling tile. (14) Areas of water damage were identified and should be further investigated (see Facility Assessment Plans in Section 4). (15) Some casework has damaged hardware as well as areas where the plastic laminate is delaminating. (16) The tennis court surface has major cracking. (17) The fire alarm notification system is lacking coverage. (18) The building lacks lighting control systems such as occupancy sensors and diming capabilities. (19) The air handling and exhaust equipment is at the end of its service life. (20) The chiller and associated cooling system is in good condition. (21) The exhaust system and associated equipment is at the of its service life. (22) The air handling unit which serves the arena is at the end of its service life. (23) The exhaust system on the original portion of the building and the condensing units on the 1993 addition are at the end of their service lives. Page 21 Eppstein Uhen Architects October 25, 2016

23 Recommended Next Steps At the conclusion of a Facilities Assessment, many school districts ask how to best proceed. It is our recommendation that the Administration closely review the document for content and understand the observations and recommendations. For the Shorewood School District, the next step will involve sharing the key findings with the broader community through Community Workshops in November. It will be very helpful to gather initial feedback from a variety of district stakeholders to establish priorities for long-term facilities master planning. Once priorities have been discussed, the identified needs should again be considered with targeted areas confirmed for additional research and preliminary costing developed with the support of Miron Construction, the district s Construction Manager/Estimators. From there, each recommendation can be prioritized in a way that best works with your funding strategy and shared for further community feedback. This will develop a phased approach to building your long-term facilities master plan and to resolving the most pressing facility needs at Shorewood School District. Thank you for the opportunity to participate in this endeavor. If you have any questions or concerns regarding this summary, please feel free to contact the EUA team. Sincerely, Teresa Wadzinski, Associate Project Manager Page 22 Eppstein Uhen Architects October 25, 2016

Florence High School / Middle School Page 1 of 3 Florence, WI

Florence High School / Middle School Page 1 of 3 Florence, WI Florence High School / Middle School Page 1 of 3 Florence, WI Plumbing Systems Review: The following report is the result of a site visit by Tim Kehoe of Muermann Engineering, LLC that occurred on October

More information

HOLUM EDUCATION CENTER. Architectural. January 13, 2014 DeForest Area School District

HOLUM EDUCATION CENTER. Architectural. January 13, 2014 DeForest Area School District HOLUM EDUCATION CENTER Architectural The existing building has approximately 41,823 square feet and sets on a lot about 4.14 acres in size. Parking lots are located along the east and west sides of the

More information

PLATTEVILLE MIDDLE SCHOOL

PLATTEVILLE MIDDLE SCHOOL Architectural The building has aluminum clad wood awning windows in combination with aluminum fixed glass units. They appear to be exterior glazed with insulated glazing. See photo 2. Platteville Middle

More information

MUKWONAGO AREA SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY

MUKWONAGO AREA SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY ARCHITECTURE ROLLING HILLS ELEMENTARY SCHOOL Rolling Hills Elementary was built in 1999 and is the newest addition to the Mukwonago Area School District. The building contains approximately 64,900 gross

More information

VOTER BOND REFERENDUM 2018 SUMMARY OF WORK PROPOSED

VOTER BOND REFERENDUM 2018 SUMMARY OF WORK PROPOSED Ashton Elementary School 1 Masonry Repair $ 42,781.50 2 Replace HVAC $ 375,000.00 3 Replace SAT @ Various Locations $ 92,364.00 3 Recoat & Resurface Exterior Paved Play Area $ 135,978.30 3 Various Technological

More information

Edward Jenner Elementary Academy of the Arts

Edward Jenner Elementary Academy of the Arts Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

MOUNT PLEASANT MIDDLE SCHOOL HVAC. M-01 Heating Plant: M-02 Heating & Ventilating Systems: Livingston School District Mount Pleasant Middle School

MOUNT PLEASANT MIDDLE SCHOOL HVAC. M-01 Heating Plant: M-02 Heating & Ventilating Systems: Livingston School District Mount Pleasant Middle School MOUNT PLEASANT MIDDLE SCHOOL HVAC M-01 Heating Plant: The existing boilers have recently been upgraded. (3) steam boilers (8660 mbh each) manufactured by Weil- McLain have been installed. Newer hot water

More information

MUKWONAGO SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY

MUKWONAGO SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY MUKWONAGO SCHOOL DISTRICT ARCHITECTURE PARK VIEW MIDDLE SCHOOL The original school building was dedicated in 1954 as the High School, with an addition in 1959, a library addition in 1970, and an addition/renovation

More information

2014 Bond Project Guide

2014 Bond Project Guide 2014 Bond Project Guide Bush Elementary School Page 1 Instructional Technology Computers, Projectors, Mobile Carts, Document Cameras and Printers Wireless Connectivity New Construction New Tech Center

More information

3. 21st Century Learning A. Districtwide Flexible Learning - Allowance for Flexible Furniture $600,000 Subtotal $600,000

3. 21st Century Learning A. Districtwide Flexible Learning - Allowance for Flexible Furniture $600,000 Subtotal $600,000 1. Safety and Security A. Additional Cameras District Wide $382,000 B. Interior Locks Upgrades Allowance $300,000 C. Tilden Entrance Upgrades D. Door and Glass Improvements Allowance $500,000 E. Alert

More information

Genevieve Melody Elementary School

Genevieve Melody Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

John Palmer Elementary School

John Palmer Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

MARY CRAPO CENTER Miller Road, Swartz Creek, Michigan

MARY CRAPO CENTER Miller Road, Swartz Creek, Michigan MARY CRAPO CENTER 8197 Miller Road, Swartz Creek, Michigan MARY CRAPO CENTER 8197 Miller Road, Swartz Creek General Information: - Instructional, Child Care Development Center (West Wing) o (2) Infant/Toddler

More information

Agustin Lara Elementary Academy

Agustin Lara Elementary Academy Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Josefa Ortiz De Dominguez Elementary School

Josefa Ortiz De Dominguez Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

New High School Concept

New High School Concept Approved Bond Projects for Alamance-Burlington Schools In November 2018, Alamance County citizens approved a $150 million bond project proposal. Bond funds will pay to construct a new high school and provide

More information

Alessandro Volta Elementary School

Alessandro Volta Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Washington Irving Elementary School

Washington Irving Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

George B Swift Elementary Specialty School

George B Swift Elementary Specialty School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Joseph Brennemann Elementary School

Joseph Brennemann Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

State College Area School District High School South Building EXISTING CONDITIONS ASSESSMENT

State College Area School District High School South Building EXISTING CONDITIONS ASSESSMENT State College Area School District High School South Building Prepared by CenterPoint Engineering 08 February 2013 FACILITY ASSESSMENT SUMMARY PHYSICAL PLANT General HVAC This report is a snapshot of the

More information

2 Main Office Building BLDG-955A Building Purpose Building Area Administration offices. Training room 7,610 SF Inspection Date August 16, 2016 Inspect

2 Main Office Building BLDG-955A Building Purpose Building Area Administration offices. Training room 7,610 SF Inspection Date August 16, 2016 Inspect 1 Site Summary Address 7200 Bluff Springs Road Austin, TX 78744 Number of Permanent Campus Facilities 2 Original Year of Construction 2014 Total Campus Building Area (combined) 25,314 SF Introduction The

More information

Tighe&Bond. Groton Heights School Mechanical Evaluation. 1 Existing Conditions. 1.1 Water Service Entrance

Tighe&Bond. Groton Heights School Mechanical Evaluation. 1 Existing Conditions. 1.1 Water Service Entrance Groton Heights School Mechanical Evaluation TO: FROM: Amy Vaillancourt, Project Manager Harley Langford, Project Manger Jason Curtis, P.E. DATE: February 24, 2016; Revised May 31, 2016 On Monday, December

More information

Chariho Regional School District Five-Year Capital Facilities Improvement Plan (2/10/15)

Chariho Regional School District Five-Year Capital Facilities Improvement Plan (2/10/15) Chariho Regional School District Five-Year Capital Facilities Improvement Plan (2/10/15) School/Department FY 16 FY 17 FY18 FY19 FY20 Chariho Regional High School FY 16 FY 17 FY18 FY19 FY20 *Repair Bleachers

More information

Briar Crest Elementary

Briar Crest Elementary Promises Kept This document includes partial lists of major projects completed at Pattonville Schools since 1986 as part of past bond issues approved by the Pattonville community. Briar Crest Elementary

More information

Richard Henry Lee Elementary School

Richard Henry Lee Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Calmeca Academy of Fine Arts and Dual Language

Calmeca Academy of Fine Arts and Dual Language Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Charles W Earle Elementary School

Charles W Earle Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Francis M McKay Elementary School

Francis M McKay Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Facility Condition Assessment Summary Report. British Columbia Institute of Technology NE6 - Plumbing and Pipefit Building

Facility Condition Assessment Summary Report. British Columbia Institute of Technology NE6 - Plumbing and Pipefit Building Facility Condition Assessment Summary Report British Columbia Institute of Technology NE6 - Plumbing and Pipefit Building Submitted by: VFA Canada Corp. Burnaby Centre 4211 Kingsway Burnaby, BC V5H 1Z6

More information

Oscar DePriest Elementary School

Oscar DePriest Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Master Facility Planning Update School Board Meeting May 26, 2016

Master Facility Planning Update School Board Meeting May 26, 2016 Master Facility Planning Update School Board Meeting May 26, 2016 Master Facilities Committee Overview Reflection of Committee Work Review of District Wide Facility Issues Identified District Wide Facility

More information

State College Area School District High School North Building EXISTING CONDITIONS ASSESSMENT

State College Area School District High School North Building EXISTING CONDITIONS ASSESSMENT State College Area School District High School North Building Prepared by CenterPoint Engineering 08 February 2013 FACILITY ASSESSMENT SUMMARY PHYSICAL PLANT General HVAC This report is a snapshot of the

More information

DeWitt Clinton Elementary School

DeWitt Clinton Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Mechanical Inspection Plumbing

Mechanical Inspection Plumbing 0811 Fixtures Sinks, drinking fountains, water closets, showers, etc. Classroom Sinks. Classroom sinks (19) are enameled cast iron self rimming side ledge with gooseneck faucet trim with index handles,

More information

ELECTRICAL SYSTEMS ASSESSMENT Hanover High School

ELECTRICAL SYSTEMS ASSESSMENT Hanover High School ELECTRICAL SYSTEMS ASSESSMENT Hanover High School ELECTRICAL DISTRIBUTION SYSTEM:?? The existing electrical service consists of an underground primary service originating at a utility pole on Cedar Street,

More information

Forest Hills Facilities Plan

Forest Hills Facilities Plan Forest Hills Facilities Plan Extensive updates to 8 of our 9 schools Replace Wilson Elementary Enhance learning environments across the district Build additional classrooms to accommodate gradual implementation

More information

S AGE E NGINEERING A SSOCIATES, LLP

S AGE E NGINEERING A SSOCIATES, LLP S AGE E NGINEERING A SSOCIATES, LLP 1211 Western Avenue Albany, NY (518) 453 6091 F (518) 453 6092 Kingston Library Mechanical and Electrical Systems Field Report Date of Visits: Mechanical - September

More information

Sidney Sawyer Elementary School

Sidney Sawyer Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Ashland School District Facility & Capacity Assessment Report 2005

Ashland School District Facility & Capacity Assessment Report 2005 Ashland School District Facility & Capacity Assessment Report 2005 Briscoe Elementary School (Closed Facility) Address: 265 N Main Street Area: 33,980 square feet Buildings: Original Building 1948 Music

More information

Allisonville Elementary School Facilities Highlights Built: 1960 Last Major Renovation: 28 years ago Capacity: 650 Current Enrollment: 767

Allisonville Elementary School Facilities Highlights Built: 1960 Last Major Renovation: 28 years ago Capacity: 650 Current Enrollment: 767 Allisonville Elementary School Built: 1960 Last Major Renovation: 28 years ago Capacity: 650 Current Enrollment: 767 ADA improvements are Fire alarms need to be updated Playground equipment needs to be

More information

Electrical Inspection Special Electrical

Electrical Inspection Special Electrical 0941 Fire Alarm System Devices, panels, wiring, conduit, etc. The present fire alarm system manufactured by Gamewell was installed with the 1982 renovation. It is a non addressable, zoned system. It includes

More information

Facilities Master Planning

Facilities Master Planning Facilities Master Planning DeForest Area School District DeForest, WI PRA Project #130343-01 January 13, 2014 DRAFT Table of Contents DeForest Area School District PRA Project # 130217-01 Section 1 Existing

More information

PLAN REVIEW SUBMITTAL GUIDE

PLAN REVIEW SUBMITTAL GUIDE PLAN REVIEW SUBMITTAL GUIDE Plans, specifications and other construction documentation for the initial plan review should be as complete as possible at the time of submittal. Use this convenient guide

More information

SITE SYSTEMS: FANNIE MAE EXPECTED USEFUL LIFE TABLES (FMEUL)

SITE SYSTEMS: FANNIE MAE EXPECTED USEFUL LIFE TABLES (FMEUL) SITE SYSTEMS: FANNIE MAE EXPECTED USEFUL LIFE TABLES (FMEUL) Basketball Courts 15 25 Built Improvements Playgrounds, Site Furniture, etc. 20 20 Catch Basin 40 40 Cold Water Lines 40 40 Compactors DHW Supply

More information

Kerrville ISD has called for a bond election in the amount of $88,960,000 for November 6, 2018

Kerrville ISD has called for a bond election in the amount of $88,960,000 for November 6, 2018 Kerrville ISD has called for a bond election in the amount of $88,960,000 for November 6, 2018 WHAT IS A BOND ELECTION? Provide communities an opportunity to vote to give the Board of Trustees authority

More information

CAPITAL OUTLAY REQUEST - IDENTIFIED AND EMERGING PROJECTS - RANKED 3-Jun-14

CAPITAL OUTLAY REQUEST - IDENTIFIED AND EMERGING PROJECTS - RANKED 3-Jun-14 2014-2015 CAPITAL OUTLAY REQUEST - IDENTIFIED AND EMERGING PROJECTS - RANKED 3-Jun-14 School Item Amount a. Classroom A/R (Increase CR capacity to 804, add l Resource and tutoring spaces needed. Teacher

More information

FORT ERIE SECONDARY SCHOOL FACILITY INFORMATION. Lake Erie Corridor Secondary Schools Accommodation Review

FORT ERIE SECONDARY SCHOOL FACILITY INFORMATION. Lake Erie Corridor Secondary Schools Accommodation Review FORT ERIE SECONDARY SCHOOL FACILITY INFORMATION Lake Erie Corridor Secondary Schools Accommodation Review November 2012 LAKE ERIE CORRIDOR SECONDARY SCHOOLS ACCOMMODATION REVIEW Fort Erie Secondary School

More information

Master Project List Report

Master Project List Report Blue Hills Elementary School 01-8215 Site Utilities Replacement $52,835 01-8502 Modernization $3,135,933 01-8525 Exterior Painting $181,478 01-8552 Kindergarden Fencing $13,180 Install new backflow preventer.

More information

DEERFIELD SCHOOL DISTRICT REFERENDUM Committed to Excellence and Equity in Educating Our Students

DEERFIELD SCHOOL DISTRICT REFERENDUM Committed to Excellence and Equity in Educating Our Students DEERFIELD SCHOOL DISTRICT REFERENDUM Committed to Excellence and Equity in Educating Our Students FACILITY NEEDS THE CHALLENGE Deerfield Middle School/High School building has served the community for

More information

GARCIA GALUSKA DESOUSA Consulting Engineers

GARCIA GALUSKA DESOUSA Consulting Engineers L#58619/Page 1/November 1, 2017 PLUMBING Executive Summary: Presently, the Plumbing Systems serving the building are cold water, hot water, sanitary, waste and vent system, storm drain piping, and natural

More information

DRAFT. Widen Elementary School Site Summary 74,523 SF. Introduction

DRAFT. Widen Elementary School Site Summary 74,523 SF. Introduction 1 Widen Elementary School Site Summary Address 5605 Nuckols Crossing Austin, TX 78744 Number of Permanent Campus Facilities 2 Original Year of Construction 1986 Total Campus Building Area (combined) 74,523

More information

Preliminary Study Document. Horicon. Horicon, Wisconsin

Preliminary Study Document. Horicon. Horicon, Wisconsin Preliminary Study Document Horicon School District Horicon, Wisconsin Monday table of contents i 1 2 Introduction Section One: Van Brunt Elementary School a. Building Evolution b. Existing Site Plan c.

More information

HVAC / Boilers / Hot Water. Expected Life Span. very rough estimates Condition/Issue Age. Athletics / Gyms

HVAC / Boilers / Hot Water. Expected Life Span. very rough estimates Condition/Issue Age. Athletics / Gyms $4,013,500.00 $4,013,500.00 $ 1,155,000.00 $ 1,000,000.00 $ 205,000.00 $ 275,000.00 $ 300,000.00 $ 360,000.00 $ 438,500.00 $ 280,000.00 School Status Item HS Boilers boiler controls replaced 2017 2002

More information

Greenwood Elementary School 5550 South Holly Street Greenwood Village, Colorado 80111

Greenwood Elementary School 5550 South Holly Street Greenwood Village, Colorado 80111 Greenwood Elementary School 5550 South Holly Street Greenwood Village, Colorado 80111 Year Opened 1958 Current Square Footage 50,504 Site Acreage 8.53 greenwood.cherrycreekschools.org $220,720 Electrical

More information

REPORT CARD TO THE COMMUNITY MAY 15, 2018

REPORT CARD TO THE COMMUNITY MAY 15, 2018 REPORT CARD TO THE COMMUNITY MAY 15, 2018 O On May 10, 2014 voters in Greenville ISD approved a $72,275,000 bond election. BOND PROPOSAL PROJECT BOND AMOUNT CONSTRUCT A NEW BOWIE ELEMENTARY SCHOOL $17,600,000

More information

Ichabod Crane Central School District 2018 Capital Project Preliminary Estimate

Ichabod Crane Central School District 2018 Capital Project Preliminary Estimate Health & Safety 1,399,000 Academics & Program 17,140,800 Physical Education & Athletics 5,922,000 Building Infrastructure 3,103,800 Site Infrastructure 1,049,600 TOTAL SCOPE OF WORK 28,615,200 PROPOSED

More information

2015 Building Condition Survey Summary Mosaic Associates Architects 02/19/16

2015 Building Condition Survey Summary Mosaic Associates Architects 02/19/16 1. General: This summary is offered as a supplement to the 2015 Building Condition Survey being filed with SED on behalf of the District. All cost estimates are preliminary, and should be re-evaluated

More information

School District of Milton 5- Year Capital Maintenance and Improvement Plan

School District of Milton 5- Year Capital Maintenance and Improvement Plan Updated - 02/21/17 School District of Milton 5- Year Capital Maintenance and Improvement Plan 101 East Elementary 1 Parking Lot/Traffic Flow Project 615,175 Includes Construction and Engineering 2 Bathroom

More information

Massachusetts School Building Authority

Massachusetts School Building Authority Massachusetts School Building Authority School District Revere District Contact Paul Dakin TEL: (781) 286-8226 Name of School Submission Date 3/6/2007 The following Priorities have been included in the

More information

Campus Middle School 4785 South Dayton Street Greenwood Village, Colorado 80111

Campus Middle School 4785 South Dayton Street Greenwood Village, Colorado 80111 Campus Middle School 4785 South Dayton Street Greenwood Village, Colorado 80111 Year Opened 1971 Current Square Footage 175,743 Site Acreage (included in CCHS) 87.22 campus.cherrycreekschools.org $2,441,170

More information

ALLISON ELEMENTARY SCHOOL 4315 Don Julio Blvd., North Highlands, CA 95660

ALLISON ELEMENTARY SCHOOL 4315 Don Julio Blvd., North Highlands, CA 95660 ALLISON ELEMENTARY SCHOOL 4315 Don Julio Blvd., North Highlands, CA 95660 Year Built 1960 // Age 58 years Building Area 31,688 Square Feet Student Capacity 389 Current Enrollment (2017-2018) 466 Priority

More information

Extra Mile Inspection, Inc.

Extra Mile Inspection, Inc. Cover Page Property Inspection Report Inspection prepared for: Jerry and Lynne Richardson Real Estate Agent: Polly Richardson - BHKR Lake Forest Date of Inspection: 3/13/2017 Time: 12 pm Age of Home: built

More information

Design Presentation. Chief Operations Officer Willie Burroughs

Design Presentation. Chief Operations Officer Willie Burroughs Design Presentation Chief Operations Officer Willie Burroughs Agenda Introduction Community Feedback Project updates 2 Feedback Citizens Advisory Committee meetings Growth and Development meetings Community

More information

NYC Department of Education

NYC Department of Education Asset: COLUMBUS AF - BRONX, 925 ASTOR AVENUE, New York, 10469 Inspection Id Inspection Type Time In Last Edited SA : Architectural - Senior 2017-10-31 9:21 AM 2017-11-29 8:45 AM AA : Architectural - Associate

More information

Building Self-Inspection Program

Building Self-Inspection Program Building Self-Inspection Program www.tridentinsurance.net Lines of Business: Property, General Liability, Worker s Compensation, Public Official Liability Risk Control Strategy/Key Issues: Reduce physical

More information

5 Year Capital Improvement Plan Update

5 Year Capital Improvement Plan Update 5 Year Capital Improvement Plan Update Board Approved May 10, 2016 Collierville Schools Board of Education Wanda Chism Wright Cox Mark Hansen, Chairman Cathy Messerly Kevin Vaughan Superintendent John

More information

Design Review of Facility Improvement Projects

Design Review of Facility Improvement Projects Design Review of Facility Improvement Projects Agenda Board Meeting Schedule Scope of Work Summary Overall Building Plans and Scope Summary Update on Areas of Design Development Programming and Space planning

More information

MID MICHIGAN COMMUNITY COLLEGE HARRISON CAMPUS Harrison, Michigan 2015 MASTER PLAN

MID MICHIGAN COMMUNITY COLLEGE HARRISON CAMPUS Harrison, Michigan 2015 MASTER PLAN MID MICHIGAN COMMUNITY COLLEGE HARRISON CAMPUS Harrison, Michigan 2015 MASTER PLAN September 30, 2015 PBA Project No. 2015.0140.00 PETER BASSO ASSOCIATES INC. CONSULTING ENGINEERS 5145 LIVERNOIS ROAD,

More information

Cherry Hill Public Schools BUILDING A SOLID FUTURE

Cherry Hill Public Schools BUILDING A SOLID FUTURE Cherry Hill Public Schools BUILDING A SOLID FUTURE Who We Are The Cherry Hill School District is the 12 th largest in the state, serving 11,500 students 19 Locations 2 High Schools, 3 Middle Schools, 12

More information

NORTH CENTRAL MICHIGAN COLLEGE PETOSKEY CAMPUS. Facilities Conditions Assessment Mechanical And Electrical Petoskey, Michigan

NORTH CENTRAL MICHIGAN COLLEGE PETOSKEY CAMPUS. Facilities Conditions Assessment Mechanical And Electrical Petoskey, Michigan NORTH CENTRAL MICHIGAN COLLEGE PETOSKEY CAMPUS Facilities Conditions Assessment Mechanical And Electrical Petoskey, Michigan PBA Project No. 2014.0137.00 Prepared By: Wayne Kerbelis Terry Cleis September

More information

NYACK PUBLIC SCHOOLS CAPITAL IMPROVEMENT PLANNING PROCESS

NYACK PUBLIC SCHOOLS CAPITAL IMPROVEMENT PLANNING PROCESS NYACK PUBLIC SCHOOLS CAPITAL IMPROVEMENT PLANNING PROCESS DECEMBER 3, 2013 KEY QUESTIONS 1. What is the time sequence for available funding? (In what years will the funding be available?) 2. What is the

More information

Axiom Property Inspections

Axiom Property Inspections Cover Page Axiom Property Inspections Property Inspection Report 868 Wally Avenue, Henderson NV, 89178 Inspection prepared for: John Doe Agent: David Lawson - Axiom Inspection Date: 8/12/2010 Time: 2:30

More information

Bayshore House Inspections LLC

Bayshore House Inspections LLC Cover Page Bayshore House Inspections LLC Property Inspection Report 32963 Inspection prepared for: Ron Rosenthal Date of Inspection: 3/23/2017 Time: 10:30am Age of Home: 1950 Size: 3284 Weather: Clear

More information

SUMMARY 1234 Main St.Severn Buyer Name 07/18/2018 9:00AM

SUMMARY 1234 Main St.Severn Buyer Name 07/18/2018 9:00AM SUMMARY 1234 Main St.Severn 21144 Buyer Name 07/18/2018 9:00AM Henry Toman MD License 32391 1st American Home Inspection, LLC 443-685-4062 henrytoman61@gmail.com The summary is meant to organize the defects

More information

LAMPETER-STRASBURG SCHOOL DISTRICT Lampeter, Pennsylvania 17537

LAMPETER-STRASBURG SCHOOL DISTRICT Lampeter, Pennsylvania 17537 LAMPETER-STRASBURG SCHOOL DISTRICT Lampeter, Pennsylvania 17537 Buildings and Grounds Committee Minutes March 20, 2017 The meeting was called to order at 6:30 p.m. PRESENT: Board Members, Mr. Jeffrey A.

More information

Oxford Hills School District Capital Renewal Plan Updated March 2017

Oxford Hills School District Capital Renewal Plan Updated March 2017 Color Coding Guide Recently Completed In Progress FY 2017 Budget in FY 2018 Future Budgets/Projects 3/20/17 Capital Renewal Plan Updated March 2017 Capital Renewal Plan - Harrison Elementary Harrison add

More information

Appendix B. Facilities Assessment Report

Appendix B. Facilities Assessment Report Mile Lane Army Reserve Center Redevelopment Plan September 2008 Appendix B Facilities Assessment Report RKG Associates, Inc. Mile Lane Army Reserve Base Middletown, CT MEP System Evaluation For RKG Associates

More information

GARCIA GALUSKA DESOUSA Consulting Engineers

GARCIA GALUSKA DESOUSA Consulting Engineers L#57297 /Page 1/July 21, 2017 ELECTRICAL SYSTEMS NARRATIVE REPORT The following is the Electrical Systems narrative, which defines the scope of work and capacities of the Power and Lighting systems, as

More information

EDUCATIONAL SPECIFICATIONS NEW CONSTRUCTION TO: Oxford Middle School Location to be determined November 4, 2016 Approved by BOE on November 29, 2016

EDUCATIONAL SPECIFICATIONS NEW CONSTRUCTION TO: Oxford Middle School Location to be determined November 4, 2016 Approved by BOE on November 29, 2016 EDUCATIONAL SPECIFICATIONS NEW CONSTRUCTION TO: Oxford Middle School Location to be determined November 4, 2016 Approved by BOE on November 29, 2016 Educational Specifications Page 1 Project Overview:

More information

Electrical Inspection Special Electrical

Electrical Inspection Special Electrical 0941 Fire Alarm System Devices, panels, wiring, conduit, etc. Description of the building system The school is equipped with a hard wired fire alarm control panel, and automatic dialer. The fire alarm

More information

F. GENERAL REQUIREMENTS Electrical Design Criteria 2006 Edition 4/3/06 School District Palm Beach County Page-1 of 15

F. GENERAL REQUIREMENTS Electrical Design Criteria 2006 Edition 4/3/06 School District Palm Beach County Page-1 of 15 ELECTRICAL DESIGN CRITERIA TABLE OF CONTENTS I GENERAL...2 II CRITERIA...2 A. POWER DISTRIBUTION SYSTEMS...2 1. NORMAL POWER:...2 2. EMERGENCY POWER...3 B. LIGHTING...4 1. GENERAL...4 2. AVERAGE MAINTAINED

More information

PROCTOR TERRACE ELEMENTARY SCHOOL

PROCTOR TERRACE ELEMENTARY SCHOOL SCHL DAA Address: Bryden Lane Santa Rosa, CA 95404 Established: 50 Permanent Classrooms: 3 Portable Classrooms: 9 Building Area: Site Area: 40, sq ft 5 acres Students in 5: 484 Students in (Projected):

More information

Inspection Report. Prepared for: Tonia Mann. Property Address: 402 Leslie Court McDonough, GA Date: March 07, 2013

Inspection Report. Prepared for: Tonia Mann. Property Address: 402 Leslie Court McDonough, GA Date: March 07, 2013 Inspection Report Prepared for: Tonia Mann Property Address: 402 Leslie Court McDonough, GA 30253 Date: March 07, 2013 Inspector: Charles Mann Edifice Inspections, Inc. (770) 594-2222 www.edificeinspections.com

More information

NAZARETH AREA SCHOOL DISTRICT MAINTENANCE DEPARTMENT 357 Tatamy Road, Nazareth, PA FAX

NAZARETH AREA SCHOOL DISTRICT MAINTENANCE DEPARTMENT 357 Tatamy Road, Nazareth, PA FAX NAZARETH AREA SCHOOL DISTRICT MAINTENANCE DEPARTMENT 357 Tatamy Road, Nazareth, PA 18064 610-759-1367 FAX 610-759-7028 TO: FROM: Dr. Riker, Superintendent of Schools Board of School Directors Lewis F.

More information

Unit # 1038 ± 900 SF Width ± 15' Depth ± 60'

Unit # 1038 ± 900 SF Width ± 15' Depth ± 60' ±60' Lease Line Lease Outline Drawing Needles Towne Center 1004 E. Broadway St.,, Needles, CA 92363 ± 900 SF Width ± 15' Depth ± 60' Plans produced by: ID Plans 6/16/2017 (813) 657-2545 C 2017 Site map

More information

HOME INSPECTION REPORT

HOME INSPECTION REPORT HOME INSPECTION REPORT 75-5748 Alahou Street 2F Report Prepared For: Barbara Little Report Prepared By: Warren d'aquin Page 2 of 23 TABLE OF CONTENTS TABLE of CONTENTS... 2 SUMMARY REPORT... 3 GENERAL

More information

Campus Master Plan Update

Campus Master Plan Update TENNESSEE BOARD OF REGENTS Dr. Charles Manning, Chancellor Dr. Gary Goff, President Campus Master Plan Update 2006 SBC No. 166/027-01-05 10651 Coward Mill Road Knoxville, Tennessee 37931 (865) 637-0890

More information

I. STRUCTURAL SYSTEMS

I. STRUCTURAL SYSTEMS I. STRUCTURAL SYSTEMS A. Foundations Type of Foundation(s): Pier & Beam - Crawlspace Opinion: All exposed areas of the foundation were examined visually. Examination of the foundation was limited to photographs

More information

Summary of Repairs and Deficiencies

Summary of Repairs and Deficiencies Summary of s and Deficiencies Organization Building: Station #1 178 Safety & Compliance Inspections and Certifications Sprinkler System Certifications This building is sprinkled but no inspection/ certification

More information

FOR LEASE ROCKWOOD OFFICE PARK

FOR LEASE ROCKWOOD OFFICE PARK WILMINGTON, DE 19809 www.cbre.us/rockwood 11 PROPERTY HIGHLIGHTS Owner: Asset Manager: Address: Rockwood Office Park Associates, L.P. AIG Global Real Estate Investment Group 501, 503 & 505 Carr Road Site:

More information

NYC Department of Education

NYC Department of Education Asset: NEW UTRECHT AF - BROOKLYN, 1601 80 STREET, New York, 11214 Inspection Id Inspection Type Time In Last Edited SA : Architectural - Senior 2017-10-31 4:06 PM 2018-06-13 10:51 AM AA : Architectural

More information

DMTF: Specific Building Recommendations

DMTF: Specific Building Recommendations DMTF: Specific Building Recommendations Asset Name Project Title Total Cost BLOCKER BUILDING 22,503,303 Capital Renewal 7,640,013 DOMESTIC WATER HEATER REPLACEMENT 16,374 EXTERIOR DOOR REPLACEMENT 133,623

More information

SPACE TYPE: JUDICIAL CHAMBER

SPACE TYPE: JUDICIAL CHAMBER SPACE TYPE: JUDICIAL CHAMBER Construction Criteria The unit costs for Judicial Chamber space types are based on the construction quality and design features in the following table. This information has

More information

Siemens Building Technology MEP Existing Conditions

Siemens Building Technology MEP Existing Conditions Electrical Existing Conditions Report Executive Summary: The electrical systems for the are generally of the original vintage. The site is primary metered with the meter located in the main Electric Room.

More information

Sagebrush Elementary School East Temple Place Aurora, Colorado 80015

Sagebrush Elementary School East Temple Place Aurora, Colorado 80015 Sagebrush Elementary School 14700 East Temple Place Aurora, Colorado 80015 Year Opened 1977 Current Square Footage 57,100 Site Acreage 7.66 sagebrush.cherrycreekschools.org Asphalt and concrete work; electrical

More information

NYC Department of Education

NYC Department of Education Architectural Inspection Building Assessment Survey 2017-2018 Asset: LEHMAN AF - BRONX, 3000 EAST TREMONT AVENUE, New York, 10461 Inspection Id Inspection Type Time In Last Edited SA : Architectural -

More information

Facility Improvements

Facility Improvements AP-SI-03 BICYCLE RACK ADDITION AP-SI-05 EXTERIOR BENCH ADDITIONS Installation of bike rack will allow for designated and secure storage of bicycles. Installation of exterior benches will provide an outdoor

More information

FAIRA TRANSPARENCY REPORTS. November 21, 2016

FAIRA TRANSPARENCY REPORTS. November 21, 2016 608 State St. South Kirkland, WA 98033 www.faira.com hello@faira.com +1.800.571.FAIR Thank you for your interest in this Faira Certified home. FAIRA TRANSPARENCY REPORTS 7307 22 nd Ave NW, Seattle, WA

More information

Existing Facilities Assessment

Existing Facilities Assessment DRAFT Patrick Henry Elementary School 4643 Taney Ave, Alexandria, VA 22304 Existing Facilities Assessment Alexandria City Public Schools Planning, Design & Construction Office 1340 Braddock Place Alexandria,

More information