ASHE 2017 Transportation Update. Dean C. Ringle, P.E. & P.S. Franklin County Engineer Cornell Robertson, P.E. & P.S. Chief Deputy Engineer

Size: px
Start display at page:

Download "ASHE 2017 Transportation Update. Dean C. Ringle, P.E. & P.S. Franklin County Engineer Cornell Robertson, P.E. & P.S. Chief Deputy Engineer"

Transcription

1 ASHE 2017 Transportation Update Dean C. Ringle, P.E. & P.S. Franklin County Engineer Cornell Robertson, P.E. & P.S. Chief Deputy Engineer

2 Construction Projects Hamilton Road from Clark State Road to US 62 In conjunction with Gahanna Contractor: Shelly & Sands Construction Cost: $12,200,000

3 Roadway Infrastructure Construction Riggins Road (Avery Road to Wilcox Road) In partnership with Hilliard & Columbus Design by: American Structurepoint (east portion) Design by: EMHT (west portion) Contractor: George Igel Combined Construction Cost: $7,700,000

4 Roadway Infrastructure 2017 Program Working with The Ohio State University on Smart Vehicle and Autonomous Technology and Connectability of Local Transportation Infrastructure Working with City of Columbus on Smart City Program (Transportation Infrastructure and GIS Mapping)

5 Roadway Infrastructure 2017 Construction Sunbury Road at Smothers Road and to North Construction Management (for Westerville) SR 161 & Cosgray Road Roundabout (with Dublin, ODOT & Union County)

6 Roadway Infrastructure 2017 Construction Winchester Pike & Ebright/Shannon Intersection Upgrade Design Consultant: ms Estimated Construction Cost: $2,300,000 Bid Opening: February 2017

7 2017 Construction Projects Big Run Road Bridge 0.27 over Scioto Big Run Design Consultant: Strand Estimated Construction Cost: $350,000 Bid Opening February/March 2017

8 2017 Construction Projects Bridge End Dam Repair/Bridge Rehabilitation Design Consultant: OHM-Advisors Estimated Construction Cost: $275,000 Bid Opening March/April 2017 Major Bridge Inspections 2017 Consultant: Jones-Stuckey, a Division of Pennoni

9 2017 Construction Projects Smothers Road Bridge 2.73 over Hoover Reservoir Design by: B&N Contractor: Kokosing Construction: $3,900,000

10 Roadway Infrastructure 2017 Construction Resurfacing County Annual Program Resurfacing Township Annual Program

11 2018 Construction Projects Morse Kitzmiller Road Roundabout Design Consultant: Carpenter Marty Estimated Construction Cost: $2,000,000

12 2018 Construction Projects Smothers Schott Road & Red Bank Road Roundabout Joint project with Delaware County Design by: AECOM Estimated Construction Cost: $1,800,000

13 Roadway Infrastructure 2018 Construction Alum Creek Rohr Road Intersection Upgrade Design Consultant: Gannett-Fleming Estimated Construction Cost: $2,000,000

14 Bridge Infrastructure 2018 Construction Borror Road Bridge 3.84 over Patzer Run Design Consultant: CEC Borror Road Bridge 1.66 over Plum Run Design Consultant: TBD

15 Bridge Infrastructure 2018 Construction Livingston Avenue Bridge 5.62 over Blacklick Creek Design by: CT Consultants Estimated cost: $1,000,000

16 2018 Construction Projects Wilson Road Bridge 0.63 over Railroad Deck Replacement In partnership with City of Columbus Bike & Pedestrian Path

17 2019+ Construction Projects Leppert Road: R-t-T to Hayden Run Road Partnering with Hilliard Design Consultant: TBD Norton Johnson Road Roundabout Design Consultant: OHM Advisors Estimated Construction Cost: $2,500,000

18 2019+ Construction Projects Rohr SR 317 Intersection Upgrade Design Consultant: Parsons Brinkerhoff Estimated Construction Cost: $2,000,000 Trabue Road Bridge 7.55 over Railroad Design Consultant: EL Robinson Estimated Construction Cost: $4,500,000

19 2019+ Construction Projects Dublin-Granville Road Bridge over Rocky Fork Creek Design Consultant: Mead & Hunt Estimated cost: $1,400,000

20

US 24 & SR 66 Interchange Modification and Corridor Improvement Project Public Involvement Meeting December 5, 2007

US 24 & SR 66 Interchange Modification and Corridor Improvement Project Public Involvement Meeting December 5, 2007 US 24 & SR 66 Interchange Modification and Corridor Improvement Project Public Involvement Meeting December 5, 2007 Sponsored by: The Ohio Department of Transportation and The City of Defiance Project

More information

2018 Capital Improvements Report

2018 Capital Improvements Report 2018 Capital Improvements Report March 19, 2018 Board of County Commissioners Butler County Government Services Center 315 High Street Hamilton, Ohio 45011-2759 RE: 2018 Capital Improvements Report Board

More information

Kankakee River Bridge & Track Improvements Supplemental Environmental Assessment. May 5, 2016

Kankakee River Bridge & Track Improvements Supplemental Environmental Assessment. May 5, 2016 Kankakee River Bridge & Track Improvements Supplemental Environmental Assessment May 5, 2016 1 History: Chicago-St. Louis Corridor Since 1980 s IDOT has been looking at this corridor for high-speed service

More information

Wilson County Projects

Wilson County Projects Wilson Projects SR-109 Reconstruction & Widening TIP # 2009-72-036 Road Widening TDOT Wilson Length 3.50 Regional Plan ID 1072-348-2 Air Quality Status Non-Exempt TDOT PIN 100281.03 $34,000,000.00 SR-109

More information

2017 Capital Improvements Report

2017 Capital Improvements Report 2017 Capital Improvements Report March 20, 2017 Board of County Commissioners Butler County Government Services Center 315 High Street Hamilton, Ohio 45011-2759 RE: 2017 Capital Improvements Report Board

More information

Highway & Bridge Capabilities

Highway & Bridge Capabilities Highway & Bridge Capabilities Part of a diversified family of solutions www.jmt.com An Employee Owned Company I-95/I-295/I-495 Interchange, Woodrow Wilson Memorial Bridge, Prince George s County, MD Our

More information

Transforming the Downtown Riverfront. Your Presenters. Mark Kelsey, Esq., Director, Ann Aubry, P.E., Deputy Director,

Transforming the Downtown Riverfront. Your Presenters. Mark Kelsey, Esq., Director, Ann Aubry, P.E., Deputy Director, How to Herd Cats: Coordinating City Departments and Private Partnerships to Transform the Downtown Riverfront Your Presenters Mark Kelsey, Esq., Director, City of Columbus, Department of Public Service

More information

Engineering Department

Engineering Department Engineering Department Department Mission It is the mission of the Engineering Department to protect and enhance the public health, safety and welfare by reviewing, inspecting and maintaining documentation

More information

Fall 2017 Construction Update

Fall 2017 Construction Update Fall 2017 Construction Update Ward 4 Southeast Engineering Department Riverwalk Red Multi-Use Trail Bridge Rehabilitation The Riverwalk Red Multi Use Trail Bridge was awarded to Cramer and Associates,

More information

I-70/71 Innerbelt Project

I-70/71 Innerbelt Project I-70/71 Innerbelt Project Project Progress Meeting and Design Enhancement Update November 9, 2009 Ohio Department of Transportation MS Consultants MSI Design Overview of Presentation 1. Recap Recent Project

More information

2019 Engineering Excellence Awards. March 14, 2019 Bridgewater Banquet & Conference Center Columbus, Ohio

2019 Engineering Excellence Awards. March 14, 2019 Bridgewater Banquet & Conference Center Columbus, Ohio 2019 Engineering Excellence Awards March 14, 2019 Bridgewater Banquet & Conference Center Columbus, Ohio Recognizing engineering firms for projects that demonstrate a high degree of achievement, value

More information

Capital Projects impacting Odenton Town Center

Capital Projects impacting Odenton Town Center Capital Projects impacting Odenton Town Center 1 2 E549700 W801600/ W801602 Anne Arundel County Department of Public Works Manor View Elementary School Transmission Main - MD 32 @ Meade Phase 2 $34,399,000

More information

AGENDA ACTION ITEMS INFORMATION ITEMS

AGENDA ACTION ITEMS INFORMATION ITEMS NOACA Bicycle and Pedestrian Advisory Council Meeting Friday, March 21 st, 2014 10:30 a.m. NOACA Office 1299 Superior Avenue Cleveland, Ohio 44114 Phone: (216) 241-2414; website: www.noaca.org AGENDA ACTION

More information

Construction Engineering & Inspection

Construction Engineering & Inspection Construction Engineering & Inspection Serving Florida for 20 Years CEI Engineering Planning Landscape Architecture Urban Design Construction Engineering & Inspection (CEI) I N T R O D U C T I O N Over

More information

RANCHO PALOS VERDES MICHAEL THRONE, PE, DIRECTOR OF PUBLIC WORKS~ CAROLYNN PETRU, ACTING CITY MANAGE~

RANCHO PALOS VERDES MICHAEL THRONE, PE, DIRECTOR OF PUBLIC WORKS~ CAROLYNN PETRU, ACTING CITY MANAGE~ CITY OF RANCHO PALOS VERDES MEMORANDUM TO: FROM: DATE: SUBJECT: REVIEWED: Project Manager: HONORABLE MAYOR AND CITY COUNCIL MEMBERS MICHAEL THRONE, PE, DIRECTOR OF PUBLIC WORKS~ JUNE 17, 2014 REVIEW AND

More information

NEWSLETTER. August

NEWSLETTER. August 1 Summer NEWSLETTER August 2013 www.centralohioashe.org www.ashe.pro The President s Message 2013-2014 Board of Directors In May the Central Ohio Section of ASHE chose me as President. It was a tremendous

More information

Preserving Our Past. Securing Our Future.

Preserving Our Past. Securing Our Future. Heritage Woods/Traffic Montrose West Intersection Springside Dr./S.R. 18Intersection Flight Memorial Dr./ S.R. 18Intersection Red Roof Inn High Density Development Ridgewood/ Cleve-Mass Intersection Ridgewood/

More information

CITY OF WESTERVILLE, PLANNING AND DEVELOPMENT. BASSEM BITAR / (614) /

CITY OF WESTERVILLE, PLANNING AND DEVELOPMENT. BASSEM BITAR / (614) / Staff Report Meeting Date: September 21, 2016 Case #: PC 2016-17 WESTERVILLE PLANNING COMMISSION Request: Applicant: Staff Liaison: RECOMMEND TO CITY COUNCIL FOR ITS FURTHER ACTION THE IMAGINE WESTERVILLE

More information

Historic Bridge Adoption Information Packet

Historic Bridge Adoption Information Packet Historic Bridge Adoption Information Packet Falls County CR 179 over Big Elm Creek Bridge October 2017 Table of Contents Announcement... 3 Bridge Location... 4 Bridge Information... 4 Bridge Condition

More information

2017 Investment in Infrastructure Expo February 28, 2017 Jason Jonas, P.E. Public Works Director

2017 Investment in Infrastructure Expo February 28, 2017 Jason Jonas, P.E. Public Works Director 2017 Investment in Infrastructure Expo February 28, 2017 Jason Jonas, P.E. Public Works Director 1 Jefferson County, Missouri Road and Bridge Sales Tax: Jefferson County has a one-half cent sales tax that

More information

Schedule of Events Friday - July 13, 2018 Zanesville Open Gardens Friday, noon to 4:30 See garden listings for locations

Schedule of Events Friday - July 13, 2018 Zanesville Open Gardens Friday, noon to 4:30 See garden listings for locations Gemstone Photo by B. Veldey The Central Ohio Hosta Society welcomes you to the 8 th annual HOSTA TAILGATE WEEKEND 2018 Schedule of Events Friday - July 13, 2018 Zanesville Open Gardens Friday, noon to

More information

I-4 Beyond the Ultimate. Florida Transportation Builders Association February 9, 2018

I-4 Beyond the Ultimate. Florida Transportation Builders Association February 9, 2018 I-4 Beyond the Ultimate Florida Transportation Builders Association February 9, 2018 FDOT: Improving Mobility & Safety in Central Florida FDOT is Designing and building a better I-4 through Central Florida

More information

Capital Projects in and near Odenton Town Center

Capital Projects in and near Odenton Town Center Capital Projects in and near Odenton Town Center Map ID Anne Arundel County Department of Public Works This project provides for the design, right of way acquisition, and construction of approximately

More information

Pickaway-New Structure. Structure. Suppression. Single Family 0.00 Permit Active NEW HOUSE Accessory. Mech/Plumb/El ec Permit Active

Pickaway-New Structure. Structure. Suppression. Single Family 0.00 Permit Active NEW HOUSE Accessory. Mech/Plumb/El ec Permit Active Permit Number File Date Permit Issued DAddress Valuation Permit Type Permit Status Notes Total Fees Paid 00031 2/2/2018 29113 JACKSON 5/18/2018 RD New Structure 150,000.00 Permit Commercial Remodel 00078

More information

ANNUAL REPORT WARREN COUNTY ENGINEER S OFFICE

ANNUAL REPORT WARREN COUNTY ENGINEER S OFFICE 2017 ANNUAL REPORT WARREN COUNTY ENGINEER S OFFICE Contents Letter from the County Engineer Financial Highlights 2017 Year in Review 2018 Administrative Staff Dear Citizens of Warren County, I started

More information

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions) ADA Central, Contract 1 DBNUM: 15417 / UPC: 154170 This contract will bring projects into compliance with current ADA design requirements that could not be completed within original design or construction

More information

Luminous Bodies and the Corridor of Light for Lynn Street Rosslyn

Luminous Bodies and the Corridor of Light for Lynn Street Rosslyn Luminous Bodies and the Corridor of Light for Lynn Street Rosslyn Artist & landscape architect Cliff Garten, Venice, CA selected Harbor View, Long Beach, CA Avenue of Light, Fort Worth, TX The project

More information

HISTORIC BRIDGE FOR SALE COLUMBIA BRIDGE IN JACKSON PARK, CHICAGO, ILLINOIS

HISTORIC BRIDGE FOR SALE COLUMBIA BRIDGE IN JACKSON PARK, CHICAGO, ILLINOIS HISTORIC BRIDGE FOR SALE COLUMBIA BRIDGE IN JACKSON PARK, CHICAGO, ILLINOIS In Accordance With Illinois Law, The City of Chicago presents this information package as part of an effort to offer this historic

More information

Complete Streets Master Plan for Downtown New Britain CRCOG Transportation Committee Meeting Monday, December 9, 2013

Complete Streets Master Plan for Downtown New Britain CRCOG Transportation Committee Meeting Monday, December 9, 2013 CRCOG Transportation Committee Meeting Monday, December 9, 2013 Introduction Why the Project was Initiated About Downtown New Britain Master Plan Goals Master Plan Overview Master Plan Study Areas and

More information

FDOT D4 Complete Streets

FDOT D4 Complete Streets FDOT D4 Complete Streets Context Sensitive Solutions Directs that complete street solutions will complement the context of the community. Collaborative approach to decision making, project development,

More information

David Clark, P.E. RW Armstrong & Associates, Inc. June 20, 2012

David Clark, P.E. RW Armstrong & Associates, Inc. June 20, 2012 David Clark, P.E. RW Armstrong & Associates, Inc. June 20, 2012 The City of Indianapolis is undergoing the completion of RebuildIndy projects. Through Mayor Ballard s RebuildIndy initiative, investments

More information

July 12, Columbus City Council City Hall 90 West Broad Street Columbus, OH RE: I-70/71 Columbus Crossroads Project

July 12, Columbus City Council City Hall 90 West Broad Street Columbus, OH RE: I-70/71 Columbus Crossroads Project OHIO DEPARTMENT OF TRANSPORTATION DISTRICT 6 400 EAST WILLIAM STREET DELAWARE, OHIO 43015 800.372.7714 Columbus City Council City Hall 90 West Broad Street Columbus, OH 43215-9015 RE: I-70/71 Columbus

More information

Overall Map. Chicago. St. Louis. Summit. Joliet. Dwight. Pontiac. Bloomington-Normal Lincoln. Springfield. Carlinville. Alton EXPERIENCE IT YOURSELF.

Overall Map. Chicago. St. Louis. Summit. Joliet. Dwight. Pontiac. Bloomington-Normal Lincoln. Springfield. Carlinville. Alton EXPERIENCE IT YOURSELF. Overall Map Summit Chicago Bloomington-Normal Lincoln New Station Planned New Station Planned Dwight Pontiac Joliet Pedestrian overpass and second platform planned Higher speed service began in this section

More information

TEXAS TRANSPORTATION COMMISSION

TEXAS TRANSPORTATION COMMISSION TEXAS TRANSPORTATION COMMISSION VARIOUS Counties MINUTE ORDER Page 1 of1 VARIOUS Districts Pursuant to Transportation Code, Chapter 223, Subchapter A, and Title 43, Texas Administrative Code, Chapter 9,

More information

ODOT DISTRICT CONSTRUCTION PROGRAM JOHN R. KASICH, OHIO GOVERNOR JERRY WRAY, ODOT DIRECTOR SONJA R. SIMPSON, DISTRICT DEPUTY DIRECTOR

ODOT DISTRICT CONSTRUCTION PROGRAM JOHN R. KASICH, OHIO GOVERNOR JERRY WRAY, ODOT DIRECTOR SONJA R. SIMPSON, DISTRICT DEPUTY DIRECTOR ODOT DISTRICT 5 2018 CONSTRUCTION PROGRAM SERVING COSHOCTON, FAIRFIELD, GUERNSEY, KNOX, LICKING, MUSKINGUM, AND PERRY COUNTIES JOHN R. KASICH, OHIO GOVERNOR JERRY WRAY, ODOT DIRECTOR SONJA R. SIMPSON,

More information

Honorable Members of the Mobility Solutions, Infrastructure and Sustainability Committee

Honorable Members of the Mobility Solutions, Infrastructure and Sustainability Committee Memorandum DATE January 23, 2019 CITY OF DALLAS TO Honorable Members of the Mobility Solutions, Infrastructure and Sustainability Committee SUBJECT I-30 East Project Update On Monday, January 28, 2019,

More information

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects ROUTE/ Project ID No. TIP No. Burlington County Computerized Signal Control, IV D9911 D9911 This ITS project will be a traffic responsive signal system, consisting of 24 intersections--9 on CR 607, 4 on

More information

FY 2018 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects

FY 2018 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects Schooleys Mountain Bridge Rehabilitation Project ID Numbers: N1707 / 173470 Schooleys Mountain Road Bridge was built in 1920 and widened in 1937. The project is a replacement of the bridge structure and

More information

The transportation system in a community is an

The transportation system in a community is an 7 TRANSPORTATION The transportation system in a community is an important factor contributing to the quality of life of the residents. Without a sound transportation system to bring both goods and patrons

More information

FOR IMMEDIATE RELEASE DATE: FRIDAY, SEPTEMBER 21, Road Commission of Kalamazoo County Weekly Project Updates HAVE YOU SIGNED UP?

FOR IMMEDIATE RELEASE DATE: FRIDAY, SEPTEMBER 21, Road Commission of Kalamazoo County Weekly Project Updates HAVE YOU SIGNED UP? FOR IMMEDIATE RELEASE DATE: FRIDAY, SEPTEMBER 21, 2018 Road Commission of Kalamazoo County Weekly Project Updates HAVE YOU SIGNED UP? Sign up for RCKC CONNECT to receive message alerts for road construction,

More information

FOR IMMEDIATE RELEASE DATE: FRIDAY, SEPTEMBER 28, Road Commission of Kalamazoo County Weekly Project Updates HAVE YOU SIGNED UP?

FOR IMMEDIATE RELEASE DATE: FRIDAY, SEPTEMBER 28, Road Commission of Kalamazoo County Weekly Project Updates HAVE YOU SIGNED UP? FOR IMMEDIATE RELEASE DATE: FRIDAY, SEPTEMBER 28, 2018 Road Commission of Kalamazoo County Weekly Project Updates HAVE YOU SIGNED UP? Sign up for RCKC CONNECT to receive message alerts for road construction,

More information

MINNESOTA ARCHITECTURE - HISTORY INVENTORY FORM

MINNESOTA ARCHITECTURE - HISTORY INVENTORY FORM Identification Historic Name Dean Parkway Bridge Current Name Bridge 90661 Field # Address Midtown Greenway over Dean Parkway City/Twp Minneapolis County Hennepin Legal Desc. Twp 29N Range 24W Sec 32 QQ

More information

PennDOT Public Meeting. S.R. 3044, Section A01 Castle Shannon Boulevard Roadway Improvement Project

PennDOT Public Meeting. S.R. 3044, Section A01 Castle Shannon Boulevard Roadway Improvement Project PennDOT Public Meeting S.R. 3044, Section A01 Castle Shannon Boulevard Roadway Improvement Project Mt Lebanon Township, Allegheny County Mt Lebanon Township Municipal Building November 6, 2014 1 Project

More information

2017 Summer Field Notes

2017 Summer Field Notes Jeff Stauch, County Engineer Volume 33 Issue 1 A Message From The Engineer s Desk A portion of this issue of Field Notes outlines another busy road and bridge construction season for our organization.

More information

North Street Reconstruction & Integrated Stormwater Management System

North Street Reconstruction & Integrated Stormwater Management System OWEA Watershed Workshop-October 30 th, 2014 North Street Reconstruction & Integrated Stormwater Management System Ted Blahnik, PE Principal-Williams Creek Consulting North Street: A Case Study for Integrated

More information

Proposed FY 2004 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects

Proposed FY 2004 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects 30 130 Collingswood/Pennsauken ( B) 155C Vicinity of Cooper River Bridge at Park Drive to 200 feet north of PATCO Railroad Bridge This project may provide for the construction of a proposed new bridge

More information

Daniel J. Sporik, P.E. Civil Engineer

Daniel J. Sporik, P.E. Civil Engineer Daniel J. Sporik, P.E. Civil Engineer Work Experience Areas of Expertise Transit Planning and Design Highway Design Stormwater Management Hydraulics and Hydrology Erosion and Sediment Control Years of

More information

Innovative Transportation Planning, Design & Technology in Fairfax County, VA

Innovative Transportation Planning, Design & Technology in Fairfax County, VA Innovative Transportation Planning, Design & Technology in Fairfax County, VA American Society of Highway Engineers (ASHE) November 16, 2016 Presented By W. Todd Minnix, PE Chief, Transportation Design

More information

WARREN COUNTY ENGINEER S OFFICE

WARREN COUNTY ENGINEER S OFFICE WARREN COUNTY ENGINEER S OFFICE ANNUAL REPORT 2016 Contents Letter from the County Engineer Financial Highlights 2016 Year in Review 2017 Administrative Staff Dear Citizens of Warren County, What a great

More information

DRAFT ROOSEVELT ROAD. District Recommendations. Figure 5.23 The Roosevelt Road Corridor

DRAFT ROOSEVELT ROAD. District Recommendations. Figure 5.23 The Roosevelt Road Corridor CHAPTER 5 Figure 5.23 The Road Corridor Road will develop as a mixed-use corridor, emphasizing regional retail, west of the river and mixed-use development east of the river. KEY RECOMMENDATIONS 1. High

More information

S T V. P E R F O R M A N C E M A T T E R S. highways + bridges

S T V. P E R F O R M A N C E M A T T E R S. highways + bridges S T V. P E R F O R M A N C E M A T T E R S. highways + bridges STV s bridge and highway assignments traverse major metropolitan areas, cities and towns as well as rural corridors. Reflecting the tenets

More information

CLAY BRICK PERVIOUS PAVEMENT CASE STUDY CITY OF NEW ALBANY

CLAY BRICK PERVIOUS PAVEMENT CASE STUDY CITY OF NEW ALBANY OWEA COLLECTIONS CONFERENCE 2012 CLAY BRICK PERVIOUS PAVEMENT CASE STUDY CITY OF NEW ALBANY May 10, 2012 Travis Eifert, PE, LEED AP Doug Turney, PE, CFM, LEED AP EMH&T STORMWATER MASTER PLAN VILLAGE CENTER

More information

I-75/I-475 Interchange Upgrade Project Informational Meeting Tuesday, July 27, 2010

I-75/I-475 Interchange Upgrade Project Informational Meeting Tuesday, July 27, 2010 I-75/I-475 Interchange Upgrade Project Informational Meeting Tuesday, July 27, 2010 I-75/I-475 Interchange Upgrade Project David R. Dysard, AICP District Two Deputy Director Theresa Pollick Public Information

More information

TENNESSEE DEPARTMENT OF TRANSPORTATION Project Status. SR-37 US-19E No Projects Under Development in Carter County

TENNESSEE DEPARTMENT OF TRANSPORTATION Project Status. SR-37 US-19E No Projects Under Development in Carter County CARTER COUNTY SR-37 US-19E No Projects Under Development in Carter County PIN: 125256.00 AT LM 8.7 (ROCKFALL MITIGATION) Length - 0.0 (Mitigation - Rockfall) CARTER COUNTY SR-91EXT PIN: 043975.01 FROM

More information

Green Infrastructure Retrofit and Maintenance Strategies in Indianapolis Road School 2017

Green Infrastructure Retrofit and Maintenance Strategies in Indianapolis Road School 2017 Green Infrastructure Retrofit and Maintenance Strategies in Indianapolis Road School 2017 3/9/2017 www.williamscreek.net +1.877.668.8848 1 info@williamscreek.net www.williamscreekmgt.com GREEN INFRASTRUCTURE

More information

Alternatives Development Three conceptual alternatives were developed for the Race Road/Jessup Village Planning Study and are described below:

Alternatives Development Three conceptual alternatives were developed for the Race Road/Jessup Village Planning Study and are described below: Race Road/Jessup Village Planning Study (H550601) Project Newsletter Spring 2015 Project Description The Study Team, consisting of staff from Anne Arundel County (Department of Public Works and Department

More information

Sacramento County - Department of Transportation

Sacramento County - Department of Transportation Sacramento County - Department of Transportation Proposed Projects to be Funded with Road Maintenance and Rehabilitation Account Funding FY 2017-18 Project Description AC Overlay Projects - Federal: Rehabilitate

More information

Infrastructure Engineering Planning Construction Suite 300 Minneapolis, MN Tel: Fax:

Infrastructure Engineering Planning Construction Suite 300 Minneapolis, MN Tel: Fax: Infrastructure Engineering Planning Construction 701 Xenia Avenue outh uite 300 Minneapolis, MN 55416 Tel: 763-541-4800 Fax: 763-541-1700 Memorandum To: Minnehaha Creek Watershed District Board From: Tony

More information

Spring 2018 Construction Update

Spring 2018 Construction Update Spring 2018 Construction Update Ward 3 Southwest Engineering Department Locust Street Bridge over the Des Moines River The Locust Street Bridge over the Des Moines River project is being let through the

More information

District Department of Transportation Office of Civil Rights. Disadvantaged Business Enterprise Supportive Services

District Department of Transportation Office of Civil Rights. Disadvantaged Business Enterprise Supportive Services District Department of Transportation Office of Civil Rights Disadvantaged Business Enterprise Supportive Services Doing Business with Parsons Brinckerhoff Information & Networking Session Tuesday, October

More information

FY 2018 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects

FY 2018 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects Route 18, South of Texas Road to Rues Lane, Pavement Project ID Numbers: 11408 / 114080 Initiated from the Pavement Management System, this project will rehabilitate pavement within the project limits.,

More information

DBE Commitments at Bidtime - Letting Date

DBE Commitments at Bidtime - Letting Date DBE Commitments at Bidtime - Letting Date 17-01-19 Contract ID ADA91969 BROWN COUNTY ASPHALT INC $1,430,000.00 6 6.01% SHELLY COMPANY $1,512,584.80 6 11.58% BROWN COUNTY CONSTRUCTION CO INC $1,526,631.71

More information

TOWN OF JUPITER. Honorable Mayor and Members of Town Council Andrew D. Lukasik, Town Manager

TOWN OF JUPITER. Honorable Mayor and Members of Town Council Andrew D. Lukasik, Town Manager DATE: June 07, 2016 TO: THRU: TOWN OF JUPITER Honorable Mayor and Members of Town Council Andrew D. Lukasik, Town Manager FROM: Thomas V. Driscoll, P.E., Director of Engineering, Parks & Public Works SUBJECT:

More information

CENTRAL ESTUARY PLAN AVISION FOR OAKLAND S WATERFRONT

CENTRAL ESTUARY PLAN AVISION FOR OAKLAND S WATERFRONT Central Estuary Plan A VISION FOR OAKLAND S WATERFRONT Specific Plan and Environmental Assessment Presentation to the Parks and Recreation Advisory Commission December 9, 2009 This Afternoon s Presentation

More information

PORT CLINTON DOWNTOWN REVITALIZATION PLAN

PORT CLINTON DOWNTOWN REVITALIZATION PLAN The City has been awarded a $2.34 million Ohio Department of Transportation (ODOT), Small Cities Grant for the complete reconstruction of Madison Street AWARD WINNING PROJECT Best of Lake Erie Award Lake

More information

CENTERTON ROAD BRIDGE REPLACEMENT

CENTERTON ROAD BRIDGE REPLACEMENT CENTERTON ROAD BRIDGE REPLACEMENT FEASIBILITY STUDY BURLINGTON COUNTY BRIDGE C4.4 OVER RANCOCAS CREEK TOWNSHIPS OF MOUNT LAUREL, WESTAMPTON & WILLINGBORO 1 prepared for: BOARD OF CHOSEN FREEHOLDERS BURLINGTON

More information

Umass Amherst Design Center in Springfield - Court Square

Umass Amherst Design Center in Springfield - Court Square Umass Amherst Design Center in Springfield - Court Square UMass Amherst Design Center in Springfield, MA The Springfield Initiative: UMass plan to help revitalize the City of Springfield Support from:

More information

WARREN COUNTY ENGINEER S OFFICE. Annual Report

WARREN COUNTY ENGINEER S OFFICE. Annual Report WARREN COUNTY ENGINEER S OFFICE 2015 Contents Letter from the County Engineer Financial Highlights 2015 Year in Review 2016 Administrative Staff Dear Citizens of Warren County, 2015 was an exciting year

More information

2014 Annual Report Franklin Soil and Water Conservation District

2014 Annual Report Franklin Soil and Water Conservation District 2014 Annual Report Our Mission To promote responsible land use decisions for the conservation, protection and improvement of soil and water resources by providing information assistance through effective

More information

NASHVILLE AREA MPO FY TIP - ADOPTED DECEMBER

NASHVILLE AREA MPO FY TIP - ADOPTED DECEMBER SUMNER NASHVILLE AREA MPO FY -2017 TIP - ADOPTED DECEMBER 11, 2013 Rockland Road Widening TIP # 2002-028 Road Widening Hendersonville Sumner Length 1.50 Regional Plan ID 1052-177 Air Quality Status Non-Exempt

More information

water resource specialists

water resource specialists Vaughn Collins, PE, CFM, Northwest Hydraulic Consultants Brad Livingston, Oregon Department of Transportation Melissa Reich, North Coast Land Conservancy Location Necanicum River 75 sq mi watershed Active

More information

I-90 Mississippi River Bridge & Interchange Project

I-90 Mississippi River Bridge & Interchange Project I-90 Mississippi River Bridge & Interchange Project Presentation Outline I. Background: Context & Need for Project II. Preferred Alternative Overview III. Project Development IV. Project Management Tools

More information

Date: April 10, 2017 City Council Work Session April 24, 2017: Status Report on the Comprehensive Plan Update and Transportation Master Plan

Date: April 10, 2017 City Council Work Session April 24, 2017: Status Report on the Comprehensive Plan Update and Transportation Master Plan AGENDA REPORT To: From: By: Honorable Mayor and City Council Members Warren Hutmacher, City Manager Sharon Ebert, Director Community Development Date: April 10, 2017 Agenda: City Council Work Session April

More information

LOCATION AND DESIGN DIVISION

LOCATION AND DESIGN DIVISION VIRGINIA DEPARTMENT OF TRANSPORTATION LOCATION AND DESIGN DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Landscape Architecture Program NUMBER: SPECIFIC SUBJECT: Integration of Landscape

More information

Planning Districts INTRODUCTION

Planning Districts INTRODUCTION INTRODUCTION To facilitate detailed examination of development prospects for all areas of the community, Delano has been divided into 14 planning districts. The location of these planning districts is

More information

Derby-Shelton Bridge Pedestrian and Bicyclist Enhancements [1]

Derby-Shelton Bridge Pedestrian and Bicyclist Enhancements [1] nhancements [1] STATUS OF PROJECT: The project has recently moved from the Preliminary Design Phase to the Final Design Phase following the most recent Public Involvement Meeting held on January 9, 2019

More information

I-95 Girard Avenue Interchange Near Neighbors Meeting. Project Status

I-95 Girard Avenue Interchange Near Neighbors Meeting. Project Status I-95 Girard Avenue Interchange Project Status Construction is underway for Phase 1 and 2. Phase 3 construction will begin early 2014. Overall Project Area and Schedule GR0: Completed GR0: Completed in

More information

ATTACHMENT 14. Public Involvement

ATTACHMENT 14. Public Involvement ATTACHMENT 14 Public Involvement Bob Sullivan Robert_Sullivan@CSX.com February 19, 2010 RE: Open House Public Involvement Meeting, National Gateway, Pennsylvania Dear Public Official / Business-Property

More information

Oroville Area Urban Greening Plan. Joint Meeting of the Oroville Planning, Park, and Arts Commissions October 12, 2015

Oroville Area Urban Greening Plan. Joint Meeting of the Oroville Planning, Park, and Arts Commissions October 12, 2015 Oroville Area Urban Greening Plan Joint Meeting of the Oroville Planning, Park, and Arts Commissions October 12, 2015 Project Team Lead Agency Butte County Department of Development Services Claudia Stuart,

More information

Project Description WOO/LUC-SR /0.00. Waterville Bridge Replacement

Project Description WOO/LUC-SR /0.00. Waterville Bridge Replacement Ohio Department of Transportation District 2 317 East Poe Rd. Bowling Green, Ohio 43402 (419) 353-8131 John R. Kasich, Governor Jerry Wray, Director Todd Audet, P.E., District Deputy Director Project Description

More information

Roads Plan

Roads Plan Roads Plan 2019-2023 Background Road conditions have been a problem for Painesville City over the past decade. Between 2009 and 2013, the city was only able to dedicate $1.9 million in total road repairs

More information

Welcome & Introductions

Welcome & Introductions Creating a Pedestrian Friendly Street American Public Works Association: 2009 Congress Session 4791 September 16, 2009 Welcome & Introductions Doug Roberts, P.E. Transportation Design Section Manager City

More information

AMENDMENT NUMBER 2 TO AGREEMENT FOR PROFESSIONAL SERVICES BETWEEN URS CORPORATION GREAT LAKES AND THE CITY OF ANN ARBOR

AMENDMENT NUMBER 2 TO AGREEMENT FOR PROFESSIONAL SERVICES BETWEEN URS CORPORATION GREAT LAKES AND THE CITY OF ANN ARBOR AMENDMENT NUMBER 2 TO AGREEMENT FOR PROFESSIONAL SERVICES BETWEEN URS CORPORATION GREAT LAKES AND THE CITY OF ANN ARBOR The City of Ann Arbor, a Michigan municipal corporation, with offices at 301 E. Huron

More information

2017 COLUMBUS URBAN FARM TOUR SERIES. Sponsored by: Ohio State University Extension Franklin County Columbus Urban Farmers Network

2017 COLUMBUS URBAN FARM TOUR SERIES. Sponsored by: Ohio State University Extension Franklin County Columbus Urban Farmers Network 2017 COLUMBUS URBAN FARM TOUR SERIES Sponsored by: Ohio State University Extension Franklin County Columbus Urban Farmers Network There is no fee or advance registration required to participate in these

More information

STREET IMPROVEMENT AND MAINTENANCE PROGRAMS

STREET IMPROVEMENT AND MAINTENANCE PROGRAMS 2018-2019 STREET IMPROVEMENT AND MAINTENANCE PROGRAMS Engineering Department Pamela S. Cooksey, City Engineer Public Works Department Jonathan Gano, Public Works Director April 2018 Attached for your information

More information

Cottage Grove Road Reconstruction. City of Madison Engineering

Cottage Grove Road Reconstruction. City of Madison Engineering Public Informational Meeting Cottage Grove Road Reconstruction October 8, 2015 Presentation Outline Introduction Project Purpose & Need Proposed Design Overview Environmental Concerns Pedestrian Needs

More information

ROAD CONSTRUCTION. 36 June 2014 ROADS&BRIDGES

ROAD CONSTRUCTION. 36 June 2014 ROADS&BRIDGES ROAD CONSTRUCTION 36 June 2014 ROADS&BRIDGES Young is full of life Recent expansion completes continuous, multilane arterial By Donald Hammack, P.E. Contributing Author The Florida Department of Transportation

More information

Blueprint Columbus GI Implementation & Design Guidelines One Water 2014 Technical Conference & Expo

Blueprint Columbus GI Implementation & Design Guidelines One Water 2014 Technical Conference & Expo Blueprint Columbus GI Implementation & Design Guidelines One Water 2014 Technical Conference & Expo Jason Sanson, PE John Herchl, LEEP AP August 29, 2014 Agenda SECTION 1 Blueprint Columbus SECTION 2 Stormwater

More information

Thursday, April 13, 2017 Page 1 of 3 7/1/2017. Electricians are installing lights and continue to pull wire. Preliminary Design underway.

Thursday, April 13, 2017 Page 1 of 3 7/1/2017. Electricians are installing lights and continue to pull wire. Preliminary Design underway. Status Updates on Active Projects sorted by Cost $13,733,749.69 Niki Ensor Niki Ensor Raw Water Intake Replacement (1.5 M EDA Grant) $7,500,000.00 Ryan McReynolds Thompson, Michael SR 347 (Rock Springs

More information

Enhance the High Line Canal Projects

Enhance the High Line Canal Projects Enhance the High Line Canal Projects Joint Project Proposal for Arapahoe County Open Spaces Funding Partner Sponsors: South Suburban Park and Recreation District City of Centennial City of Littleton October

More information

Delaware River Waterfront Corporation

Delaware River Waterfront Corporation Delaware River Waterfront Corporation Delaware River Waterfront Corporation Created in January 2009 to replace Penn s Landing Corporation o Open, accountable, effective leadership o New Board of Directors

More information

TAC/CAC, TPO Project Update February 2016

TAC/CAC, TPO Project Update February 2016 A1A MULTIMODAL CORRIDOR PLANNING AND ENGINEERING ANALYSIS Florida Department of Transportation TAC/CAC, TPO Update February 2016 PRESENTATION FOOTERT Meeting Agenda What We Plan To Discuss Background New

More information

City of Guelph - Wilson Street Parkade / Wilson Street Reconstruction Proposed Project Schedule April 21,

City of Guelph - Wilson Street Parkade / Wilson Street Reconstruction Proposed Project Schedule April 21, City of Guelph - Wilson Street Parkade / Wilson Street Reconstruction Proposed Project Schedule April 21, 2016 2016 2017 Activity Date March April May June July August September October November December

More information

Regional and Local Perspectives

Regional and Local Perspectives Regional and Local Perspectives Transportation Engineering and Safety Conference Tom Zilla Principal Transportation Planner Centre County Metropolitan Planning Organization We are here! We are here! 1

More information

Community-based Green Infrastructure Initiative in New Jersey

Community-based Green Infrastructure Initiative in New Jersey Community-based Green Infrastructure Initiative in New Jersey Rutgers Cooperative Extension Water Resources Program www.water.rutgers.edu February 21, 2018 Christopher C. Obropta, Ph.D., P.E. obropta@envsci.rutgers.edu

More information

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM Transportation Authorities Project Descriptions

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM Transportation Authorities Project Descriptions Bridge Rehabilitation Burlington County Bridge Commission Burlington-Bristol Bridge This project includes the replacement of the existing span decks, repairs to the existing walkway, railing and ladder

More information

Citizen s Advisory Committee

Citizen s Advisory Committee Citizen s Advisory Committee 13 Members 6 Meetings (5 Locations) 1 Public Meeting Numerous Report Drafts Countless Hours of Review Immeasurable Input Special Thank You To: Jack Cohen Brian Kile George

More information

2017 General Obligation Bond

2017 General Obligation Bond 2017 General Obligation Bond Presentation of Public and Council Projects to the Transportation & Mobility Stakeholder Committee April 13, 2017 Agenda Deferred Maintenance Project Development Process Projects

More information

Reconnecting New Haven: Downtown Crossing

Reconnecting New Haven: Downtown Crossing Reconnecting New Haven: Downtown Crossing Phase 2 Update Introduction to Phase 3 November 16, 2017 City of New Haven, Connecticut Toni N. Harp, Mayor Reconnecting New Haven Introduction Project Overview

More information

TRANSPORTATION PROJECTS

TRANSPORTATION PROJECTS TRANSPORTATION PROJECTS 40 BUFFALO S LWRP PROPOSED PROJECTS T1. Niagara Street/Great Lakes Seaway Trail Streetscape Project City of Buffalo Department of Public Works Niagara Street from Niagara Square

More information