1 Facilities Master Plan 2012 Update Summary for All Planning Periods (includes completed construction) Number GSF New Construction 56 5,456,234 Building Renovations 65 3,987,873 Building Demolitions ,964 Landscape and Transportation Improvements 63 N/A East Campus Mixed Use Development 3 1,800,000 Totals ,785,071 Completed Construction (projects completed from January 2011 to June 2012) Number GSF New Construction 4 263,769 Building Renovations 3 82,124 Building Demolitions - - Landscape and Transportation Improvements - N/A East Campus Mixed Use Development - N/A Totals 7 345,893 (July December 2020) Number GSF New Construction 21 1,820,205 Building Renovations 29 1,904,223 Building Demolitions ,071 Landscape and Transportation Improvements 36 N/A East Campus Mixed Use Development 1 940,000 Totals 116 4,973,499 (January December 2030) Number GSF New Construction 31 3,372,260 Building Renovations 33 2,001,526 Building Demolitions ,893 Landscape and Transportation Improvements 27 N/A East Campus Mixed Use Development 2 860,000 Totals 122 6,465,679

2 FMP 2012 Update - Projects Completed (Between January June 2012) New Construction Site Project District GSF S4 Van Munching Hall Addition/Renovation 15,282 NW2 Oakland Hall (711 beds) Auxiliary 231,704 N1 Shuttle-UM Facility 10,075 N3 Heavy Equipment Building 6,708 Total GSF New Construction Completed 263,769 Renovation Bldg. # Building District GSF 059 Chincoteague Hall Renovation CC 22, Engineering Lab Building Renovation (partial) NE 5, Severn Building Conversion Phase I and IA OC 53,677 Total GSF Renovations Completed 82,124 Comments Comments For East Campus relocations S:\Facilities Planning\FMP_Update_2012\Projects Completed.xls

3 FMP 2012 Update - New Construction Campus Core Site Project Building Type GSF Floors Edward St. John Learning and Teaching Center & CC1 SCUB (addition / renovation to Holzapfel Hall) 68,400 3 CC3 Administrative Office Building 57,100 4 CC2 Benjamin Building Addition and Center for Young Children Replacement 95,700 5 South Site Project Building Type GSF Floors School of Public Policy Building and Site S2 74,800 4 Development S3 S6 Public Protection and Security Research Building, SCUB Expansion and Site Development Prince Frederick Hall (463 Beds), SCUB Expansion and Site Development 134,000 5 Auxiliary 185,500 6 S7 South Campus Recreation Building Auxiliary 70,000 3 S8 Worcester Hall Replacement (233 beds), SCUB Expansion and Site Development Auxiliary 84,600 4 S1 Architecture Building Additions 122,250 3 S5 Visual Arts and Cultures Building 112,300 4 S9 Behavioral and Social Sciences Research Building 120,000 5 West Site Project Building Type GSF Floors W1 University House 12,600 2 W2 Ludwig Soccer Stadium Upgrades (12,000 to 18,000 seats) Auxiliary 105,700 1 W3 Varsity Team House and Indoor Practice Facility and Site Improvements Auxiliary 128,100 2 W4 Shipley Field Upgrades Auxiliary 16,900 1 W5 Gossett Football Team House Addition Auxiliary 7,500 1 W6 Campus Drive Parking Garage (2,200 spaces) Auxiliary 660,000 6 (5 story "read") Northwest Site Project Building Type GSF Floors School of Public Health Building NW1 Addition/Conversion - Phase II 27,299 3 NW3 Undergraduate Housing 1 (515 Beds) Auxiliary 169,950 9 NW4 Undergraduate Housing 2 (515 Beds) Auxiliary 169,950 9 Replacement housing (650 beds) & Residential NW5 Facilities Relocation Auxiliary 240,300 8 S:\Facilities Planning\FMP_Update_2012\New Construction List.xls

4 FMP 2012 Update - New Construction North Site Project Building Type GSF Floors N2 Paint Branch Parking Garage Phase (1,000 spaces) Auxiliary 300,000 5 (4-Story "Read") N4 New Electric Sub-Station Utility 5,400 1 Building and Landscape Services Office Building 12,000 2 N2 Paint Branch Parking Garage Phase 2 (1,000 spaces) Auxiliary 300,000 5 (4-Story "Read") N2 Paint Branch Parking Garage Phase 3 (1,000 spaces) Auxiliary 300,000 5 (4-Story "Read") N5 Environmental Service Facility Expansion 10,100 2 N6 Comcast Center Office Expansion Auxiliary 7,020 1 N7 Field Hockey and Lacrosse Complex Expansion Auxiliary 5,800 1 N8 Comcast Center Addition (Basketball Practice Facility) Auxiliary 22,500 1 N9 Comcast Center Addition (Gymnastics Practice Facility) Auxiliary 15,000 1 N10 Robert E. Taylor Stadium Expansion Auxiliary 2,640 1 N11 New Energy Plant & Grounds Buildings addition Utility 60,000 2 Northeast Site Project Building Type GSF Floors NE1 Animal Science Consolidated Activities Pavilion 18,200 1 NE2 Bioscience Research Facility Phase 1 126,000 5 NE3 Bioscience Research Facility Phase 2 111,600 5 NE4 Physical Sciences Complex - Phase 1 160,246 NE6 Bioengineering Building -Phase 1 and SCUB expansion 156,610 6 NE5 Physical Sciences Complex - Phase 2 106,300 6 NE7 Nutrition and Food Sciences Building 94,000 6 Computer Science and Computer Engineering NE8 Building 182,000 9 NE9 Physical Sciences Complex - Phase 3 102,400 7 S:\Facilities Planning\FMP_Update_2012\New Construction List.xls

5 FMP 2012 Update - New Construction NE10 New IT Building 100,000 4 NE11 Bioengineering Building -Phase 2 54,500 6 NE12 Aerospace Engineering Building 106,800 6 East Site Project Building Type GSF Floors E1 East Campus Mixed Use Development - Phase I East Campus 940,000 varies E2 East Campus Mixed Use Development - Phase II East Campus 630,000 varies E3 Day Care Facility Auxiliary 13,500 2 E4 East Campus Mixed Use Development - Phase III East Campus 230,000 varies Golf Course Site Project Building Type GSF Floors GC1 Indoor Driving Range Auxiliary 1,000 1 GC2 Golf Course Maintenance Facilities Auxiliary 10,400 1 GC3 Grounds Maintenance Complex Replacement 20,000 1 Outlying Properties Site Project Building Type GSF Floors OP1 Chesapeake Bay Mesocosm (near Gudelsky Veterinary Medicine Center) 8,000 1 Off-Campus Site Project Building Type GSF Floors Central Maryland Research and Education N/A Center Office Building (near Ellicott City) 34,500 TBD N/A New Data Center (Research Park) 83,000 TBD Total GSF Periof 1 2,760,205 Total GSF Period 2 4,232,260 Total GSF 6,992,465 NOTES: Worcester Replacement: Building is 77,600 GSF plus 7,000 GSF for half of existing SCUB II. Public Protection and Security Research: Building is 120,000 GSF plus 7K GSF for half of existing SCUB II and 7K GSF for future SCUB expansion for future development. Benjamin Building: Building is 85,000 GSF plus 10,700 GSF for CYC replacement. New Electric Sub-station: Footprint is 10% larger than footprint of Mowatt sub-station. New Energy Plant: 30K footprint plus 10K outside area for trucks/storage if this becomes bio-mass. Bioengineering Building Ph I: Building is 148,070 GSF plus 8,540 for SCUB expansion. East Campus (site E1): GSF includes parking garage, GSF from Real Estate Office. GSFs for sites E2 and E4 were calculated assuming same land use density as site E1. S:\Facilities Planning\FMP_Update_2012\New Construction List.xls

6 FMP 2012 Update - Building Renovations Bldg. # Building District GSF 047 Woods Hall Renovation CC 24, H. J. Patterson Hall Wing 1 Renovation CC 56, Holzapfel Hall CC 27, Jimenez Hall Renovation CC 63, Francis Scott Key Hall Renovation CC 24, Dorchester Hall Renovation CC 35, Rossborough Inn Renovation CC 8, Architecture Building Renovation S 67, Cecil Hall Renovation S 20, South Campus Dining Hall Renovation S 138, Centreville Hall Renovation NW 128, Cumberland Hall Renovation NW 124, Bel Air Hall Renovation NW 29, Chestertown Hall Renovation NW 29, Cambridge Hall Renovation NW 55, Elkton Hall Renovation NW 114, Easton Hall Renovation NW 115, Ellicott Hall Renovation NW 118, Hagarstown Hall Renovation NW 119, La Plata Hall Renovation NW 132, Toll Physics Building South Wing Renovation NE 74, Chemistry Building Wings 1 & 2 Renovation NE 200, Pocomoke Building Alteration E 30, Upgrade Central Heating Plant E 39, Severn Building Conversion OC 22, Severn Building Conversion Phase II OC 49, Sorority House Renovation OC 10, Sorority House Renovation OC 11, Tawes Theatre Conversion W 31,550 Total 1,904,223 Comments Renovated as part of the University Learning and Teaching Center Ground and first floors For Department of Public Safety For remote library storage For East Campus relocations Convert to offices/classrooms S:\Facilities Planning\FMP_Update_2012\Renovation List.xls

7 FMP 2012 Update - Building Renovations Bldg. # Building District GSF 073 H. J. Patterson Hall Wing 2 Renovation CC 62, Symons Hall Renovation CC 54, Benjamin Building Renovation CC 112, Morrill Hall Renovation CC 16, Taliaferro Hall Renovation CC 47, Marie Mount Hall Renovation CC 114, Tydings Hall Renovation CC 101, Mitchell Building Renovation (partial) CC 19, Reckord Armory Renovation (Ground Floor) CC 35, Memorial Chapel Renovation CC 25, Main Administration Building Renovation CC 41, Lee Building Renovation (partial) CC 20, Turner Hall Renovation CC 25, Van Munching Hall Renovation (partial) S 34, Tawes Theater Conversion W 36, Byrd Stadium Concessions Building 1 Renov. W 4, Byrd Stadium Concessions Building 2 Renov. W 2, Byrd Stadium Concessions Building 3 Renov. W 2, Byrd Stadium Concessions Building 4 Renov. W 11, Byrd Stadium Concessions Building 5 Renov. W 9, Gossett Football Team House Renov. (partial) W TBD 162 Cole Student Activities Building Renovation W 248, Biology-Psychology Building Renovation NE 250, Toll Physics Building North Wing Renovation NE 163, Geology Building Renovation NE 24, Animal Sciences Building Wing 1 Renovation NE 62, Mathematics Building Ground Floor Renovatio NE 25, A.V. Williams Building Renovation NE 236, Wind Tunnel Renovation NE 31, Hornbake Ground and First floors Renovation NE 30, Microbiology Building Renovation NE 88, Indoor Practice Facility (Tennis Bubble) Conv. GC 20, Severn Building Conversion Phase III OC 38,900 Total 2,001,526 Comments Center and north wings Convert lecture halls to other use School of Public Policy wing Includes infill floors For classroom upgrades For College of Information Services Convert to multi-purpose practice For Physical Distribution Warehouse S:\Facilities Planning\FMP_Update_2012\Renovation List.xls

8 FMP 2012 Update Landscapes / Transportation Campus Core Site Project Project Type CC_L1 Rossborough Inn Gardens Improvements Landscape CC_L2 McKeldin Library Hardscape and Landscape Landscape CC_L3 McKeldin Mall Improvements (phased) Landscape CC_L4 South Chapel Lawn Enhancements Landscape CC_L5 Chapel Fields Improvements Landscape CC_L6 South Gate Landscape Improvements Landscape CC_T1 Campus Drive at Anne Arundel: Create Pedestrian/Bike Paths Transportation CC_T2 Purple Line and Streetscape / Landscape Improvements Transportation CC_L7 Garden of Reflection and Remembrance Phase II Landscape CC_L8 Morrill Hall Quad Improvements Landscape CC_L9 Anne Arundel Green Landscape CC_L10 Lot Y Conversion and Landscape Improvements Landscape CC_L12 Tawes Plaza Improvements Landscape South Site Project Project Type S_L1 Lehigh Road Gateway and Pedestrian Enhancements Transportation S_T1 East-West Pedestrian Boulevard Improvements Transportation West Site Project Project Type W_L1 Byrd Stadium Field Replacement (artificial turf) Sports Field W_L2 Garden Walk at Clarice Smith Performing Arts Center and Perimeter Landscape Improvements University Blvd. Landscape W_L3 Garden of Peace and Friendship Phase II Landscape W_L4 Botanical Garden and Landscape Improvements Phase I Landscape W_L5 Arboretum Outreach Center Landscape Improvements Landscape W_L6 Field Turf Extension and Site Improvements Sports Field W_T1 Lot 1 Road/Pedestrian/Bicycle Safety Improvements Transportation W_T2 Campus Drive West Gateway Enhancements Landscape & Transportation W_T3 Stadium Drive and Golf Course Gateway Enhancements Landscape & Transportation W_T4 Purple Line and Streetscape/Landscape Improvements Transportation W_L7 Botanical Garden Phase II Landscape W_T5 Stadium and Farm Drives Enhancements Transportation Northwest Site Project Project Type NW_L1 School of Public Health Building Garden Landscape NW_L2 Hagerstown Woods Improvements Landscape NW_L3 Campus Creek Trail and Ecosystem Enhancements Landscape NW_L4 Multi-Sport Recreation Field (220' x 150', artificial turf) Sports Field NW_L5 Volleyball and/or Basketball Courts Sports Field S:\Facilities Planning\FMP_Update_2012\FMP Landscape.xlsx

9 FMP 2012 Update Landscapes / Transportation North Site Project Project Type Landscape & N_L1 Paint Branch Drive Gateway Enhancements Transportation N_T1 Pedestrian/Bicycle Improvements at Comcast Center Transportation N_L2 Recreation Fields on Paint Branch Parking Garage Roof Sports Field N_L3 Terrapin Trail Retention Pond Improvements Landscape N_L4 Paint Branch Drive Wooded Wetlands Improvements Landscape N_L5 Wooded Hillock Conservation Garden and Perimeter Landscape Landscape N_L6 Track and Throwing Area Sports Field N_L7 ICA/CRS Field (Infield of Track) Sports Field Northeast Site Project Project Type NE_L1 Hornbake Plaza Improvements Landscape NE_L2 Bioretention Garden Improvements (Technology Drive) Landscape NE_L3 North Gate Park (West) Landscape Improvements Landscape NE_T1 Regents Drive Improvements Transportation NE_T2 Pedestrian/Bicycle Improvements at Stadium Drive East Transportation NE_T3 Paint Branch Drive Improvements Transportation NE_T4 Bicycle Connection and pedestrian bridge at AV Williams, North Transportation NE_L4 Animal Sciences Building Courtyard Improvements Landscape NE_L5 Kim Engineering Building Plaza Improvements Landscape NE_L6 Mathematics Building Courtyard Improvements Landscape NE_L7 Outdoor Volleyball Courts (4 sand or artificial turf, 50'x80' each, Sports Field including buffer space) East Site Project Project Type Route 1 Pedestrian Median Improvements (to be implemented by MD E_L1 Landscape State Highway Administration) E_L2 Fraternity Row - multi-field layout, artificial turf (4 fields, 270' x 660' Sports Field E_T1 Purple Line and Streetscape/Landscape Improvements Transportation E_L3 East Campus Phase II Park Landscape Golf Course Site Project Project Type GC_L1 Holman Short Game Expansion Sports Field GC_L2 Golf Course Ponds and Storm Water Management Improvements Landscape GC_L3 Perimeter Landscape Improvements University Blvd. and Adelphi Road Landscape S:\Facilities Planning\FMP_Update_2012\FMP Landscape.xlsx

10 FMP 2012 Update Landscapes / Transportation Outlying Properties Site Project Project Type OP_L2 Campus Tree Nursery Landscape OP_L1 Greenmead Drive Entry Enhancements Transportation OP_L3 Avrum Gudelsky Veterinary Center Retention Pond Improvements Landscape Wetland Marsh Nature Walk and Perimeter Landscape Improvements OP_L4 University Blvd. OP_T1 Bicycle Trail Improvements Landscape Landscape S:\Facilities Planning\FMP_Update_2012\FMP Landscape.xlsx

11 FMP 2012 Update - Building Demolitions Bldg. # Building District GSF 075 Shriver Laboratory CC 22, Carroll Hall S 17, Wicomico Hall S 17, Caroline Hall S 17, Preinkert Field House S 19, West Education Annex S 2, Grounds Office Building N 3, Institute for Physical Sciences & Technology NE 17, Engineering Annex NE 8, Central Animal Research Facility NE 7, Harrison Laboratory E 56, Service Building E 59, Plant Operations & Maintenance Building E 15, Motor Transportation E 6, Plant Operations & Maintenance Shop E 11, Shuttle Bus Facility E 5, Shuttle Bus Trailer E Motorcycle Storage Bldg E Plant Operations and Maintenance Storage E Plant Operations & Maintenance Shop E 1, Plant Operations & Maintenance Shop E 1, Shuttle Bus Trailer E Plant Operations & Maintenance Storage E Plant Operations & Maintenance Shop E 1, Building Services Operations E 3, Heavy Equipment Building E 3, Solid Waste Storage E Campus Mail Facility E 4, Pest Control Trailer E 610 Total 309,071 Reason for Demolition Site development project S:\Facilities Planning\FMP_Update_2012\Demolition List.xls

12 FMP 2012 Update - Building Demolitions Bldg. # Building District GSF 067 Satelite Central Utility Building 2 S 13, Varsity Sports Teamhouse W 12, Byrd Stadium Building W 3, Center for Young Children NW 10, Environmental Service Facility N 6,090 Building and Landscape Services Office Bldg N 12, Grounds Material & Equipment Building N 6, Grounds Operations & Maintenance Bldg. N 3, Grounds Herbicide/Pesticide Storage Bldg. N ITV Building NE 2, Jull Hall NE 9, Leonardtown Office Building E 10, Temporary Building (South of 201) E 1, Temporary Building (West of 201) E Temporary Building (West of 201) E Temporary Building E Leonardtown Apartment E 10, Leonardtown Apartment E 12, Leonardtown Apartment E 10, Leonardtown Apartment E 6, Leonardtown Apartment E 10, Leonardtown Apartment E 5, Leonardtown Apartment E 13, Leonardtown Apartment E 13, Leonardtown Apartment E 13, Leonardtown Apartment E 13, Leonardtown Apartment E 13, Leonardtown Apartment E 13, Leonardtown Apartment E 3,660 Total 231,893 Reason for Demolition Replaced by new facility Site development project S:\Facilities Planning\FMP_Update_2012\Demolition List.xls

13

14

15

16

NORTHEAST DISTRICT. Description. Opportunities

NORTHEAST DISTRICT. Description. Opportunities VI plan and major recommendations district plans northeast disrict NORTHEAST DISTRICT Description The Northeast District comprises approximately 38 acres. It is bounded by Campus Creek to the north, the

More information

NORTH DISTRICT. Description

NORTH DISTRICT. Description VI plan and major recommendations district plans north disrict NORTH DISTRICT Description The North District comprises approximately 105 acres and is bounded by two important bio-habitats and corridors

More information

RESIDENTIAL FACILITIES WINTER BREAK WORK PLANS (Residence Halls)

RESIDENTIAL FACILITIES WINTER BREAK WORK PLANS (Residence Halls) Inspections and Routine and Preventive Maintenance: Preparations for New Residents: Where new Spring Semester residents will move into recently vacated spaces, Housekeepers and Urban Biology staff will

More information

UMBC Facilities Management. UMBC Facilities Master Plan Update

UMBC Facilities Management. UMBC Facilities Master Plan Update Management UMBC 2009-2019 February 19, 2010 A is the Vision for buildings, lands, open spaces and infrastructure Framework for the shape and development of the campus built environment driven by the University

More information

210 PART 2 LANDSCAPE DESIGN GUIDELINES AND PRECINCT PLANS

210 PART 2 LANDSCAPE DESIGN GUIDELINES AND PRECINCT PLANS Appendix The consolidated development parameters matrix contains key development guidelines for all potential building sites identified in the plan. It prescribes the following: total area of each development

More information

Achieving a Vision. Master Plan 2009 Belknap Campus August 10 11, UofL Belknap Campus Master Plan Update

Achieving a Vision. Master Plan 2009 Belknap Campus August 10 11, UofL Belknap Campus Master Plan Update Achieving a Vision Master Plan 2009 Belknap Campus August 10 11, 2009 Consultant Team The Campus Studio Ann Arbor Michigan Team Leader Campus Planning Site Design JRA Architects Louisville Kentucky Assistant

More information

Illustrative Campus Plan with Proposed Development

Illustrative Campus Plan with Proposed Development Illustrative Campus Plan with Proposed Development Approved Compiled Plan January 2003 Figure IV-52 89 The supportive relationship and interaction between the campus and the surrounding community is an

More information

Neighborhood Districts

Neighborhood Districts NEIGHBORHOOD DISTRICTS SEVEN MAIN DISTRICTS Neighborhood Districts While the Development Plan provides a broad-scale overview of the neighborhood, this section focuses on uses and relationships at the

More information

This is the East Carolina University Comprehensive Facilities Master Plan Final Draft Plan Review. This workbook reviews the campus draft master plan

This is the East Carolina University Comprehensive Facilities Master Plan Final Draft Plan Review. This workbook reviews the campus draft master plan This is the East Carolina University Comprehensive Facilities Master Plan Final Draft Plan Review. This workbook reviews the campus draft master plan first presented on campus on June 29 and June 30, 2011.

More information

PROJECT SUMMARY. University of California, Irvine Humanities Building. Project No FINAL INITIAL STUDY/MITIGATED NEGATIVE DECLARATION

PROJECT SUMMARY. University of California, Irvine Humanities Building. Project No FINAL INITIAL STUDY/MITIGATED NEGATIVE DECLARATION PROJECT SUMMARY University of California, Irvine Humanities Building Project No. 991077 FINAL INITIAL STUDY/MITIGATED NEGATIVE DECLARATION State Clearinghouse No. 2007011035 March 2007 Humanities Building

More information

Preci nct P l ans Figure 56 Campus Aerial Photo, 2008 CAL STATE EAST BAY, HAYWARD CAMPUS MASTER PLAN

Preci nct P l ans Figure 56 Campus Aerial Photo, 2008 CAL STATE EAST BAY, HAYWARD CAMPUS MASTER PLAN 9 Precinct Plans This section contains a detailed discussion of the planning and design concepts for specific areas or precincts of the Cal State East Bay Hayward campus. The Precinct Plans pertain to

More information

UAA School of Engineering Parking Garage Master Plan Amendment. 1. Purpose

UAA School of Engineering Parking Garage Master Plan Amendment. 1. Purpose UAA School of Engineering Parking Garage Master Plan Amendment 1. Purpose Since the UAA campus master plan was drafted in 2003, adopted in 2004, and amended in 2009 a number of significant changes regarding

More information

UNCW CAMPUS MASTER PLAN

UNCW CAMPUS MASTER PLAN UNCW CAMPUS MASTER PLAN JULY 27, 2017 MASTER PLAN FRAMEWORK RECOMMENDATIONS BOARD OF TRUSTEES PRESENTATION UNCW Campus Master Plan Update Board of Trustees Presentation July 27, 2017 The attached Campus

More information

Capital Projects in and near Odenton Town Center

Capital Projects in and near Odenton Town Center Capital Projects in and near Odenton Town Center Map ID Anne Arundel County Department of Public Works This project provides for the design, right of way acquisition, and construction of approximately

More information

Moreno Valley College: Conceptual Master Planning - Site Analysis Lasselle Street, Moreno Valley, CA 92551

Moreno Valley College: Conceptual Master Planning - Site Analysis Lasselle Street, Moreno Valley, CA 92551 Master Plan Architect School Name Moreno Valley College District Riverside Community College District Architecture and Urban Design 5898 Blackwelder Street Ground Floor Culver City, CA 90232 T: 310.559.5720

More information

SmithGroupJJR 5. PROPOSED PROJECT PHASING

SmithGroupJJR 5. PROPOSED PROJECT PHASING SmithGroupJJR 5. PROPOSED PROJECT PHASING CAMPUS INSTITUTIONAL DISTRICT MASTER PLAN - Adopted July 18, 2017 173 5.1 Project Phasing In order for a master plan to be successful, it must be appropriately

More information

WESTERN ILLINOIS UNIVERSITY

WESTERN ILLINOIS UNIVERSITY WESTERN ILLINOIS UNIVERSITY Quad Cities Riverfront Campus Master Plan March 1, 2006 Preliminary Master Plan Total Site Build Out Western Illinois University Quad Cities Municipal Park Mississippi River

More information

Building Addresses and Assembly Areas

Building Addresses and Assembly Areas Adams 10456 Presidents Park Dr. Grass area in front of Inside Alan and Sally Merten 4441 George Mason Blvd Courtyard in front of The Alan Police and Safety Headquarters parking and Sally Merten lot Amherst

More information

FACILITIES MASTER PLAN UPDATE FINAL REFINEMENT PHASE PRESIDENT S COUNCIL PRESENTATION

FACILITIES MASTER PLAN UPDATE FINAL REFINEMENT PHASE PRESIDENT S COUNCIL PRESENTATION FINAL REFINEMENT PHASE 10.29.14 PRESIDENT S COUNCIL PRESENTATION 1 Process Overview 2 Campus Master Plans 3 Realizing the Vision 4 Final Thoughts Agenda Process Overview Master Planning Process Task One

More information

Michigan State University Barrier-Free/Accessibility Project Status Summary March 2017

Michigan State University Barrier-Free/Accessibility Project Status Summary March 2017 Projects Completed FY14, FY15 and FY16 (arranged alphabetically) Abrams Planetarium Install automatic door opener on main doors of the Planetarium. Completed: Summer 2016 Cost: $13,000 Akers Hall Renovations

More information

U n i v e r s i t y o f S o u t h C a r o l i n a A i k e n. Land Plan Study

U n i v e r s i t y o f S o u t h C a r o l i n a A i k e n. Land Plan Study U n i v e r s i t y o f S o u t h a r o l i n a A i k e n Land Plan Study 06.27.2008 Goals ampus Growth Develop a Land Plan that allows for the orderly expansion of the campus over the next ten years and

More information

a) Inventory of all existing privately-owned, state-owned, or local governmentowned recreational facilities and open spaces within the context area

a) Inventory of all existing privately-owned, state-owned, or local governmentowned recreational facilities and open spaces within the context area 8.0 RECREATION AND OPEN SPACE ELEMENT (1) DATA REQUIREMENTS a) Inventory of all existing privately-owned, state-owned, or local governmentowned recreational facilities and open spaces within the context

More information

PARKS & RECREATION SUBCOMMITTEE. Oct. 1, 2015

PARKS & RECREATION SUBCOMMITTEE. Oct. 1, 2015 PARKS & RECREATION SUBCOMMITTEE Oct. 1, 2015 1999 Bond - $22,000,000 Land Acquisition Allen Station Phase II Neighborhood Parks PREVIOUS BOND ELECTIONS 1999 & 2007 2002 Bond - $4,000,000 Allen Senior Recreation

More information

2013 CAMPUS MASTER PLAN UPDATE

2013 CAMPUS MASTER PLAN UPDATE The University of North Carolina at Greensboro 2013 CAMPUS MASTER PLAN UPDATE Board of Trustees December 6, 2013 MASTER PLAN GOALS 1. Plan for an engaging, collaborative learning environment that aligns

More information

WESTERN ILLINOIS UNIVERSITY

WESTERN ILLINOIS UNIVERSITY WESTERN ILLINOIS UNIVERSITY Quad Cities Riverfront Campus Preliminary Master Plan Presentation 2 February 1, 2006 Achieving Future Flexibility 1. Monitor space needs as the new buildings come on line and

More information

campus master plan VIRGINIA STATE UNIVERSITY

campus master plan VIRGINIA STATE UNIVERSITY campus master plan VIRGINIA STATE UNIVERSITY agenda 01 INTRODUCTION & GENERAL OVERVIEW 02 03 04 LAND USE CONCEPT PROGRAM ACCOMMODATION MAXIMIZE EXISTING INFRASTRUCTURE SUMMARY AND NEXT 05 STEPS agenda

More information

University of the District of Columbia Van Ness Campus Master Plan Community Open House 3. December 8, 2010

University of the District of Columbia Van Ness Campus Master Plan Community Open House 3. December 8, 2010 University of the District of Columbia Van Ness Campus Master Plan Open House 3 December 8, 2010 Introductions Sequence of Work: Campus Master Plan BEGIN: INTRODUCE AND START WORK Project Initiation Team

More information

LOS ANGELES MISSION COLLEGE MASTER PLAN Master Plan DESIGN & DEVELOPMENT PRINCIPLES

LOS ANGELES MISSION COLLEGE MASTER PLAN Master Plan DESIGN & DEVELOPMENT PRINCIPLES LOS ANGELES MISSION COLLEGE MASTER PLAN DESIGN & DEVELOPMENT PRINCIPLES 34 Quality Learning Along the Arroyo PROGRAM SUMMARY BY PROJECT The following are program summaries for each of the projects planned

More information

Goal 1: To Encourage the Orderly, Harmonious and Judicious Use of University Resources in the Development of University Land.

Goal 1: To Encourage the Orderly, Harmonious and Judicious Use of University Resources in the Development of University Land. 2.0 Future Land Use Goal 1: To Encourage the Orderly, Harmonious and Judicious Use of University Resources in the Development of University Land. Objective 1.1: Make available future building sites that

More information

Belknap Campus Master Plan Update

Belknap Campus Master Plan Update Belknap Campus Master Plan Update Campus Visit 3 January 10-20, 2008 The Campus Studio Rowland Design JRA Architects Staggs & Fisher Gordon Garner Visit 3 1. A process of developing, sharing and refining

More information

Precinct. Strategies5

Precinct. Strategies5 This section describes the distinct precincts that make up the campus and the specific opportunities and proposed initiatives associated with each. It sets the stage for the Precinct Plans, which provide

More information

The. University of. Mississippi 2017 MASTER PLAN UPDATE

The. University of. Mississippi 2017 MASTER PLAN UPDATE The University of Mississippi 2017 MASTER PLAN UPDATE CHUCKY MULLINS DR NORTHGATE DR JACKSON AVE JACKSON AVE REBEL DR SORORITY ROW GROVE LOOP UNIVERSITY AVE GERTRUDE FORD BLVD ALL AMERICAN DR W ROW UNIVERSITY

More information

MUNICIPAL SEPARATE STORM SEWER SYSTEM 2008 ANNUAL REPORT

MUNICIPAL SEPARATE STORM SEWER SYSTEM 2008 ANNUAL REPORT MUNICIPAL SEPARATE STORM SEWER SYSTEM 2008 ANNUAL REPORT Permit Number 85-03-0-04 March 2009 Prepared by: Iowa State University Department of Environmental Health and Safety 2809 Daley Drive Ames, Iowa

More information

C a m p u s I d e n t i t y

C a m p u s I d e n t i t y Campus Identity This Week 1) Campus Identity a) Landscape Guidelines i. Materials ii. Components iii. Composition b) Wayfinding i) Refinement c) Focus Areas i) Green Spine ii) Warriner Mall iii) A Street

More information

The Capital Design Advisory Committee St. Mary s College of Maryland & Historic St. Mary s City

The Capital Design Advisory Committee St. Mary s College of Maryland & Historic St. Mary s City The Capital Design Advisory Committee St. Mary s College of Maryland & Historic St. Mary s City Welcome April 21, 2010 Capital Design Advisory Presentation: Relocating Margaret Brent Hall Traffic Calming

More information

FOCUS GROUP 4 Housing, Support Facilities & Student Life

FOCUS GROUP 4 Housing, Support Facilities & Student Life Meeting Minutes By: Perkins+Will - GK Date: 12/17/2012 Meeting Date: 12/4/2012 Project Name: BT-857 FIU-Campus Master Plan Update 2010-2020 Meeting Time: 8:00am-10:00am Project : 810369.000 Meeting Location:

More information

SITE FEASIBILITY TEST FIT LAYOUT NORTHERN AREA INTERNATIONAL SCHOOL DECEMBER 2016

SITE FEASIBILITY TEST FIT LAYOUT NORTHERN AREA INTERNATIONAL SCHOOL DECEMBER 2016 SITE FEASIBILITY TEST FIT LAYOUT NORTHERN AREA INTERNATIONAL SCHOOL DECEMBER 2016 OWNER & DESIGN TEAM GENERAL BACKGROUND INFORMATION PGCPS received a Carnegie Corporation Opportunity by Design grant to

More information

L a n d s c a p e A r c h i t e c t s & P l a n n e r s. imagine. create. solutions

L a n d s c a p e A r c h i t e c t s & P l a n n e r s. imagine. create. solutions imagine. create. solutions imagine. create. solutions RSLA is an award-winning Landscape Architecture & Planning fi rm with studios on Long Island, New York and in Chesapeake, Virginia. Our mission is

More information

AUSTIN MEDICAL DISTRICT MASTER PLAN"

AUSTIN MEDICAL DISTRICT MASTER PLAN AUSTIN MEDICAL DISTRICT MASTER PLAN"!"#$%&'"()(&$*+,--$ ,$?+,'=2,)0$!)=@,+'=03$AB,+-(C)'$ DE,$!)=@,+'=03$C/$D,F-'$-0$%&'()$ $?-),H='0'P$.(/$0&1"23$ $ G,)=C+$,$?+,'=2,)0$ G,0C)$

More information

NEIGHBORS SOUTHWEST NEIGHBORHOOD MEETING December 17, 2014 BEAVERTON SCHOOL DISTRICT SOUTH COOPER MOUNTAIN HIGH SCHOOL

NEIGHBORS SOUTHWEST NEIGHBORHOOD MEETING December 17, 2014 BEAVERTON SCHOOL DISTRICT SOUTH COOPER MOUNTAIN HIGH SCHOOL NEIGHBORS SOUTHWEST NEIGHBORHOOD MEETING December 17, 2014 AGENDA NEIGHBORHOOD MEETING Design Criteria Review 3 Concepts Discussion Q&A DESIGN CRITERIA NEIGHBORHOOD MEETING IMAGE & IDENTITY CIVIC PRESENCE

More information

3 CUMULATIVE METHODS AND PROJECTS

3 CUMULATIVE METHODS AND PROJECTS 3 CUMULATIVE METHODS AND PROJECTS 3.1 INTRODUCTION This chapter is an introduction to the cumulative impacts analysis contained within each respective environmental impact category subsection of Chapter

More information

III. PROJECT DESCRIPTION

III. PROJECT DESCRIPTION III. PROJECT DESCRIPTION LOCATION AND BOUNDARIES The City of Manhattan Beach is located in the South Bay region of Los Angeles County, California, approximately 2 miles south of the Los Angeles International

More information

THE 355/270 CORRIDOR:

THE 355/270 CORRIDOR: THE 355/270 CORRIDOR: Strategic Ideas for Sustaining a Livable Work Place Project Summary ACCESS LIFE DESIGN HEALTH WORK Montgomery County Planning Department The Maryland-National Capital Park and Planning

More information

January 11, New benches installed. Paving of parking lot adjacent to piers and the canoe put-in. Near complete with clean up remaining.

January 11, New benches installed. Paving of parking lot adjacent to piers and the canoe put-in. Near complete with clean up remaining. Project Updates January 11, 2018 CENTERVILLE CHESAPEAKE ARBORETUM BELLS MILL CITY CREEKWOOD SOUTH DEEP CREEK LOCK WORK TO BE PERFORMED/UPDATES Improvements to the parking lot include installation of a

More information

MASTER PLAN DIAGRAMS DISTRICT CAMPUS OVERVIEW

MASTER PLAN DIAGRAMS DISTRICT CAMPUS OVERVIEW DISTRICT CAMPUS OVERVIEW Classrooms, CR Special Education Computer Lab INTERSTATE 5 FW - Faculty Work, FL - Faculty Physical Education / Athletics Support Spaces S - Storage, T - Toilets, U - Utility,

More information

Seneca Meadows. Block 4 Locate office, technology, and medical development adjacent to I Screen views of garage structures from I-270.

Seneca Meadows. Block 4 Locate office, technology, and medical development adjacent to I Screen views of garage structures from I-270. Seneca Meadows Seneca Meadows has an industrial park in its southern end and a mixed-use employment area planned for the north end. The district benefits from extensive I-270 visibility, stream valley

More information

5 Year Capital Improvement Plan Update

5 Year Capital Improvement Plan Update 5 Year Capital Improvement Plan Update Board Approved May 10, 2016 Collierville Schools Board of Education Wanda Chism Wright Cox Mark Hansen, Chairman Cathy Messerly Kevin Vaughan Superintendent John

More information

February 27, 2018 City Council Presentation The Crown Jewel Park in the City of Fairfax

February 27, 2018 City Council Presentation The Crown Jewel Park in the City of Fairfax February 27, 2018 City Council Presentation The Crown Jewel Park in the City of Fairfax Master Planning Charge Van Dyck Park s first Master Plan will provide the City with a road map as to how best incorporate

More information

MUNICIPAL SEPARATE STORM SEWER SYSTEM 2009 ANNUAL REPORT

MUNICIPAL SEPARATE STORM SEWER SYSTEM 2009 ANNUAL REPORT MUNICIPAL SEPARATE STORM SEWER SYSTEM 2009 ANNUAL REPORT Permit Number 85 03 0 04 March 2010 Prepared by: Iowa State University Department of Environmental Health and Safety 2809 Daley Drive Ames, Iowa

More information

FROST CAMPUS MASTER PLAN SIR SANDFORD FLEMING COLLEGE

FROST CAMPUS MASTER PLAN SIR SANDFORD FLEMING COLLEGE FROST CAMPUS MASTER PLAN SIR SANDFORD FLEMING COLLEGE SEPT 2015 TABLE OF CONTENTS 1.0 Introduction 01 1.1 Master Plan Purpose 1.2 About The Campus 2.0 The Campus Master Plan 05 2.1 Vision Statement 2.2

More information

Open Space and Recreational Resources

Open Space and Recreational Resources Chapter 3: Open Space and Recreational Resources A. INTRODUCTION Under the 2012 City Environmental Quality Review (CEQR) Technical Manual guidelines, open space is defined as publicly accessible, publicly

More information

THE NEIGHBORHOOD TODAY

THE NEIGHBORHOOD TODAY THE NEIGHBORHOOD TODAY CORE AREA VISION How are we Good Urbanism A Site s DNA thinking about Elements of great Unique elements urban communities embedded in a place the site and design? ELEMENTS LIKE:

More information

Campus Master Plan Description Section 6 Storm water management and people places at campus buildings. Section 6 Campus MP Description

Campus Master Plan Description Section 6 Storm water management and people places at campus buildings. Section 6 Campus MP Description Campus Master Plan Description Section 6 Storm water management and people places at campus buildings Section 6 Campus MP Description THIS PAGE INTENTIONALLY LEFT BLANK. appendix The following provides

More information

Planning Projects: Highlights

Planning Projects: Highlights Planning Projects: Highlights In Process, Under Review, and Under Construction. Transportation Advisory Commission October 23, 2014 Overview of Planning Process PPR Entitlement Design Review Building Permit

More information

Ohlone College Measure G Project Scope Revisions

Ohlone College Measure G Project Scope Revisions Scope Revisions Current Title Revised Title Current Scope Revised Scope 6101 Relocated Baseball Field Athletic Fields Create new sustainable baseball field with synthetic turf, bleacher seating and batting

More information

Pedestrian and Bike Bridge LOGO

Pedestrian and Bike Bridge LOGO 6.2.2 Pedestrian and Bike Bridge The proposed pedestrian and bike crossing re-envisions the existing bridge at Pismo Creek on Cypress Street. The bridge is currently underutilized by vehicular through

More information

Boise State University October 8 - Workshop # 2. MASTER PLAN UPDATE Executive Committee Ayers Saint Gross

Boise State University October 8 - Workshop # 2. MASTER PLAN UPDATE Executive Committee Ayers Saint Gross Boise State University October 8 - Workshop # 2 MASTER PLAN UPDATE Executive Committee Ayers Saint Gross WORKSHOP AGENDA 01 WORK SESSION SUMMARY Program clarifications res life, trans, STEM Concept Plan

More information

2010 Campus Master Plan Update - USF TAMPA Campus Master Plan Update USF TAMPA

2010 Campus Master Plan Update - USF TAMPA Campus Master Plan Update USF TAMPA 2010 Campus Master Plan Update USF TAMPA Purpose of the Update: Required by the Board of Governors Provides a framework for planned growth in a context of sustainability Master Plan Update Approval Process

More information

Campus Planning and Capital Project Update. November 2017

Campus Planning and Capital Project Update. November 2017 Campus Planning and Capital Project Update November 2017 Campus Planning Updates Process Updates Master Planning Progress Space Planning Major Studies Real Estate Issues City Updates Process Updates Program

More information

urban design Introduction

urban design Introduction ACHIEVE SP RI NGF I ELD.3 Introduction Urban Design Areas Design Areas are areas within Springfield that have a unique and recognizable character that is different from other areas in the community. The

More information

East Side District Map. Pha s e 2 Report 19

East Side District Map. Pha s e 2 Report 19 Preferred Plans The Preferred Plan represents a culmination of the Phase 2 master planning process, whereby issues, goals and observations collected in Phase 1 were applied to the campus at a macro scale,

More information

Cambridge. West Cambridge site. What is a Shared Facilities Hub? Welcome

Cambridge. West Cambridge site. What is a Shared Facilities Hub? Welcome Cambridge West Cambridge site What is a Shared Facilities Hub? Welcome Thank you for taking the time to attend our public exhibition on proposals for the Shared Facilities This will be a landmark building

More information

Appendix E Section 4(f) Evaluation

Appendix E Section 4(f) Evaluation Appendix E Section 4(f) Evaluation Appendix E Draft Section 4(f) Evaluation E.1 Introduction This appendix addresses a federal regulation known as Section 4(f), which protects parks, recreation areas,

More information

Capital Projects impacting Odenton Town Center

Capital Projects impacting Odenton Town Center Capital Projects impacting Odenton Town Center 1 2 E549700 W801600/ W801602 Anne Arundel County Department of Public Works Manor View Elementary School Transmission Main - MD 32 @ Meade Phase 2 $34,399,000

More information

SOUTHEAST SPORTS COMPLEX MASTER PLAN

SOUTHEAST SPORTS COMPLEX MASTER PLAN REPORT TO SOUTHGATE NEIGHBORHOOD COUNCIL APRIL 13, 2016 Visioning Process April 30: Stakeholder Meeting with Sports Groups May 5: Stakeholder Meeting with Southgate Land Use Committee May 13: SNC Meeting

More information

NEIGHBORHOOD 8: NORTHEAST AREA

NEIGHBORHOOD 8: NORTHEAST AREA NEIGHBORHOOD 8: NORTHEAST AREA Carillon Tower Aerial View of Northeast Area Northeast Area Map 288 neighborhoods NEIGHBORHOOD 8: NORTHEAST AREA Campus View Apartments Student Recreational Sports Center

More information

OPEN SPACE TYPES. SIZE 8 acres. SIZE 20 acres. SIZE 1 acre

OPEN SPACE TYPES. SIZE 8 acres. SIZE 20 acres. SIZE 1 acre TYPICAL CHARACTERISTICS OPEN SPACE TYPES OPEN SPACE TYPES The neighborhood contains an extensive variety of open space types. Most of these spaces incorporate multiple uses and activities, so that each

More information

18 May 2016 CAMPUS MASTER PLAN UPATE

18 May 2016 CAMPUS MASTER PLAN UPATE 18 May 2016 CAMPUS MASTER PLAN UPATE Council of the Deans ( Over view) AGENDA Engagement & What We Heard Focus Elements: 1. Development Framework Plan 2. Campus Mobility 3. Campus Guidelines 4. Wayfinding

More information

UNIVERSITY OF MICHIGAN:

UNIVERSITY OF MICHIGAN: Chapter Eight UNIVERSITY OF MICHIGAN: North Campus I. Introduction The University of Michigan currently owns approximately 800 acres of land in the northeast section of Ann Arbor. North Campus refers to

More information

Parking: Yes! Add parking capacity, at Gage site or at parking deck/ramp opposite CSU

Parking: Yes! Add parking capacity, at Gage site or at parking deck/ramp opposite CSU Memorandum To: File From: Kathy Wallace Project: MSU Mankato Master Plan Project Number: 12-0433 Subject: Options Open Houses Input from Students Date: February 20, 2013 Copy To: File Darryl Pratte and

More information

Northeast Quadrant Plan

Northeast Quadrant Plan Northeast Quadrant Plan Northeast Quadrant Distinctive Features Land Use The Northeast Quadrant includes all the area within the planning area that is east of Interstate 5 and to the north of State Route

More information

Streetscape Advisory Committee

Streetscape Advisory Committee City Council Work Session Update January 17, 2016 Beautification is Economic Development Update Outline: I. Advisory Summary and Update II. Commercial Landscape Compliance III. Emerald Ash Bore Infestation

More information

ITA and Vicinity Master Plan Update

ITA and Vicinity Master Plan Update 1 ITA and Vicinity Master Plan Update PHASE 3 SEPTEMBER 27, 2017 Three Phase Process 2 Phase 1 - Understanding October 13th Public Meeting Phase 2A - Exploring Ideas November 17th Public Meeting Phase

More information

Overview and Update of the Rutgers-New Brunswick Physical Master Plan. January 2015

Overview and Update of the Rutgers-New Brunswick Physical Master Plan. January 2015 Overview and Update of the Rutgers-New Brunswick Physical Master Plan January 2015 Failure To Plan, is Planning For Failure Winston Churchill 2 Good Planning; The Key to Success 3 The university physical

More information

PROJECT SPOTLIGHT TOUR: LANGAN LEADER JANUARY 2018

PROJECT SPOTLIGHT TOUR: LANGAN LEADER JANUARY 2018 PROJECT SPOTLIGHT TOUR: LANGAN LEADER JANUARY 2018 Learn more about Langan's involvement in our featured projects. Armed Forces Retirement Home - Washington DC The Morgan School - Clinton CT Modera San

More information

Parker Pine Curve Master Plan January 28th, 2009, Public Workshop Comments

Parker Pine Curve Master Plan January 28th, 2009, Public Workshop Comments Group 1 Big Ideas Pedestrian friendly within and to development - bridge over Main Street from downtown. Campus feel. Parking garage like Castle Rocks - Taj garage may be tucked in hillside. Large (big

More information

2.4 FUTURE LAND USE ELEMENT Goals, Objectives and Policies

2.4 FUTURE LAND USE ELEMENT Goals, Objectives and Policies GOAL 1: To create developmental patterns that direct future growth to appropriate areas on campus, in a manner that promotes the educational mission of the University, the protection of environmentally

More information

CHAPTER 20: INSTITUTIONAL USE DEVELOPMENT STANDARDS

CHAPTER 20: INSTITUTIONAL USE DEVELOPMENT STANDARDS CHAPTER 20: INSTITUTIONAL USE DEVELOPMENT STANDARDS ARTICLE 1: GENERAL INSTITUTIONAL USE STANDARDS 320-01. Application The provisions of this Chapter shall apply to the following uses in any zone: (e)

More information

Appendix A. Park Land Definitions

Appendix A. Park Land Definitions Appendix A Park Land Definitions Mini Park May serve specific function for any and all ages, depending on need of the user area. Size range 1-5 acres with optimum size being 3 acres. Service area is sub-neighborhood

More information

LANGAN LANDSCAPE ARCHITECTURE + PLANNING FOR COLLEGES & UNIVERSITIES

LANGAN LANDSCAPE ARCHITECTURE + PLANNING FOR COLLEGES & UNIVERSITIES LANGAN LANDSCAPE ARCHITECTURE + PLANNING FOR COLLEGES & UNIVERSITIES CONTACT Philadelphia Pennsylvania 1818 Market Street Suite 3300 Philadelphia PA 19103 215.845.8900 215.845.8901 ST. JOSEPH'S UNIVERSITY

More information

6.1 University Projects

6.1 University Projects The Campus Master Plan provides a framework and guidelines for uottawa s evolution over the next 20 or more years. This chapter provides direction for the near term, identifying current and proposed initiatives

More information

2015 Campus Master Plan Update

2015 Campus Master Plan Update September 15, 2015 2015 Campus Master Plan Update Campus and Community Analysis Summary Presentation A G E N D A 1. Scope & Schedule of the Master Plan 2. Planning Principles & Draft Goals 3. Background

More information

Update on University Avenue Study. September 21, 2015

Update on University Avenue Study. September 21, 2015 Update on University Avenue Study September 21, 2015 Existing Building Capacity Analysis Desired Potential Programs for Corridor District University Commons 50,000 +/- GSF Consolidate Student Services

More information

AREA-WIDE PEDESTRIAN AND BICYCLE CIRCULATION

AREA-WIDE PEDESTRIAN AND BICYCLE CIRCULATION OUSD LANEY CHILD CARE CENTER ART BUILDING LANEY COLLEGE BALL FIELDS PCCD OFFICES PERALTA PARK AQUATIC CENTER & ESTUARY PARK EDOFF MEMORIAL BANDSTAND SNOW PARK COURT HOUSE OAKLAND MUSEUM OAK ST AREA-WIDE

More information

Welcome! UBC Community Conversations. Proposed new community garden space in Chancellor Place and Wesbrook Place. Traffic flow on Iona Drive

Welcome! UBC Community Conversations. Proposed new community garden space in Chancellor Place and Wesbrook Place. Traffic flow on Iona Drive 1 Welcome! UBC Community Conversations Thank you for joining us this evening, please take a feedback form, help yourself to some food and have a look around! We have information available on: Proposed

More information

UNIVERSITY OF WASHINGTON MASTER PLAN SEATTLE CAMPUS

UNIVERSITY OF WASHINGTON MASTER PLAN SEATTLE CAMPUS UNIVERSITY OF WASHINGTON MASTER PLAN SEATTLE CAMPUS Approved Compiled Plan January 2003 Appoved Compiled Plan Janauary 2003 Table of Contents I. Introduction 1 The Visioning Project 3 1998 City University

More information

FOCUS GROUP 2 Open Space, Recreation, Land Use, Conservation and Coastal Management

FOCUS GROUP 2 Open Space, Recreation, Land Use, Conservation and Coastal Management Meeting Minutes By: Perkins+Will - GK Date: 12/17/2012 Meeting Date: 12/3/2012 Project Name: BT-857 FIU-Campus Master Plan Update 2010-2020 Meeting Time: 2:00pm-4:00pm Project : 810369.000 Meeting Location:

More information

UNIVERSITY OF DENVER. APPENDIX G Open Space Typologies

UNIVERSITY OF DENVER. APPENDIX G Open Space Typologies UNIVERSITY OF DENVER APPENDIX G Open Space Typologies Open Space Typology The range of open space types found on college campuses extends from large, open fields to intimate enclaves. The importance of

More information

UNIVERSITY OF MARYLAND CONNECTS

UNIVERSITY OF MARYLAND CONNECTS CONNECTS OEHME, van SWEDEN ARUP DESIGN COLLECTIVE Brailsford and Dunlavey / Davis Langdon / EHT Traceries / G.E. Fielder / Toole Design Facilities Master Plan Update : 2011-2030 Open Forums February 21-22,

More information

TIFT COUNTY SCHOOLS E-SPLOST HISTORY

TIFT COUNTY SCHOOLS E-SPLOST HISTORY TIFT COUNTY SCHOOLS E-SPLOST HISTORY July 1, 1997 June 30, 2002 $28,766,187.16 collected July 1, 2002 June 30, 2007 $39,025,830.10 collected July 1, 2007 June 30, 2012 $41,886,155.46 collected July 1,

More information

PLANNING STAFF REVIEW

PLANNING STAFF REVIEW Rezoning Petition 2016-087 Pre-Hearing Staff Analysis October 17, 2016 REQUEST Current Zoning: R-3 (single family residential), O-1(CD) (office, conditional), and INST (institutional) Proposed Zoning:

More information

UNIVERSITY OF VIRGINIA BOARD OF VISITORS MEETING OF THE BUILDINGS AND GROUNDS COMMITTEE DECEMBER 11, 2008

UNIVERSITY OF VIRGINIA BOARD OF VISITORS MEETING OF THE BUILDINGS AND GROUNDS COMMITTEE DECEMBER 11, 2008 UNIVERSITY OF VIRGINIA BOARD OF VISITORS MEETING OF THE BUILDINGS AND GROUNDS COMMITTEE DECEMBER 11, 2008 BUILDINGS AND GROUNDS COMMITTEE Thursday, December 11, 2008 2:00 4:00 p.m. Lower East Oval Room,

More information

CAMPUS MASTER PLAN UPDATE

CAMPUS MASTER PLAN UPDATE 13 April 2016 CAMPUS MASTER PLAN UPDATE Focus Group Landscape AGENDA What We Heard Review of Campus Observations & Analysis Campus Framework & Open Space Network Table-Top Exercise Landscape Guideline

More information

CARMODY PARK MASTER PLAN

CARMODY PARK MASTER PLAN the site Smith Reservoir Cottonwood Lake Kendrick Lake Carmody Rec Center Carmody Middle School Pool Court Play Carmody Pond Sanderson Ditch Sports Fields Foothills Ice Arena Open Field why a master plan?

More information

UNIVERSITY TOWN NEIGHBOURHOODS 5.2 ECO-CORRIDOR MELBOURNE CAMPUS MASTER PLAN 2014

UNIVERSITY TOWN NEIGHBOURHOODS 5.2 ECO-CORRIDOR MELBOURNE CAMPUS MASTER PLAN 2014 5.2 ECO-CORRIDOR 37 ECO-CORRIDOR EXISTING CONDITIONS & VISION NEIGHBOURHOOD VISION Investment in the Eco-corridor Neighbourhood will signify the University s commitment to supporting local ecology and

More information

Planning Districts INTRODUCTION

Planning Districts INTRODUCTION INTRODUCTION To facilitate detailed examination of development prospects for all areas of the community, Delano has been divided into 14 planning districts. The location of these planning districts is

More information

FOCUS GROUP 7 Inter-governmental Coordination, Advancement, Alumni Affairs

FOCUS GROUP 7 Inter-governmental Coordination, Advancement, Alumni Affairs Meeting Minutes By: Perkins+Will - GK Date: 12/18/2012 Meeting Date: 12/5/2012 Project Name: BT-857 FIU-Campus Master Plan Update 2010-2020 Meeting Time: 3:00pm-5:00pm Project : 810369.000 Meeting Location:

More information

MUNICIPAL SEPARATE STORM SEWER SYSTEM 2011 ANNUAL REPORT

MUNICIPAL SEPARATE STORM SEWER SYSTEM 2011 ANNUAL REPORT MUNICIPAL SEPARATE STORM SEWER SYSTEM 2011 ANNUAL REPORT Permit Number 85-03-0-04 March 2012 Prepared by Department of Environmental Health and Safety and Facilities Planning and Management 2809 Daley

More information

Gold Line Bus Rapid Transit Transit Oriented Development (BRTOD) Helmo Station Area Plan

Gold Line Bus Rapid Transit Transit Oriented Development (BRTOD) Helmo Station Area Plan Appendix F Gold Line Bus Rapid Transit Transit Oriented Development (BRTOD) Helmo Station Area Plan Introduction and Purpose of the Plan The Gold Line Bus Rapid Transit facility is an eleven-mile dedicated

More information

RENEWING THE MASTER PLAN

RENEWING THE MASTER PLAN 1 RENEWING THE MASTER PLAN Harkins Hall renovation Greene Hall renovation New Classroom Building Payne Center Expansion Centennial Green improvements Quad redevelopment Front lawn improvements Southern

More information