1 Final Design Meeting September 25, 2014 Creating Bridges As Art 1 Welcome & Introductions Terry Ward - Project Manager 2
2 VQRC Final Design Meetings Meeting Date Items for Discussion Final Design Meeting #1 Final Design Meeting #2 Final Design Meeting #3 Final Design Meeting #4 February 4, 2014 March 18, 2014 May 20, 2014 Today Bridge Piers and Overlooks Bridge Pier Refinements Abutments, Retaining Walls and Pedestrian Railing Abutment and Railing Refinements, Bridge Color, Aesthetic Lighting Bridge Lighting, Trail Update, Feature Refinements, Summary/Next Steps 3 Bridge Lighting 4
3 Deck Lighting 5 Deck Lighting - Concept from Preliminary Design VQRC Meetings New bridge: Pole mounted LED lights on barrier between sidewalk and roadway. Enhanced pole and luminaire preferred Replicate historic light poles (approaches) and down lights (within truss) 6
4 Deck Lighting - Light Pole Configuration 7 Deck Lighting - Light Pole Configuration Option 1: Light Provided By Roadway Fixtures Roadway lights 8
5 Deck Lighting - Light Pole Configuration Option 1: Light Provided By Roadway Fixtures 9 Deck Lighting - Pedestrian/Trail Option 1: Light Provided By Roadway Fixtures 10
6 Deck Lighting - Pedestrian/Trail Option 1: Light Provided By Roadway Fixtures 11 Deck Lighting - Light Pole Configuration Option 2: Light Provided By Roadway Fixtures Plus Separate Trail Fixture At Each Overlook Roadway lights Trail Lights 12
7 Deck Lighting - Light Pole Configuration Option 2: Light Provided By Roadway Fixtures Plus Separate Trail Fixture At Each Overlook 13 Deck Lighting - Pedestrian/Trail Option 2: Light Provided By Roadway Fixtures Plus Separate Trail Fixture At Each Overlook 14
8 Deck Lighting - Pedestrian/Trail Option 2: Light Provided By Roadway Fixtures Plus Separate Trail Fixture At Each Overlook 15 Deck Lighting - Light Pole Configuration Option 3: Separate Light Fixture For Roadway And Trail Roadway Lights Separate Trail Lights Trail Lights 16
9 Deck Lighting - Light Pole Configuration Option 3: Separate Light Fixture For Roadway And Trail 17 Deck Lighting - Pedestrian/Trail Option 3: Separate Light Fixture For Roadway And Trail 18
10 Deck Lighting - Pedestrian/Trail Option 3: Separate Light Fixture For Roadway And Trail 19 Deck Lighting - Pedestrian/Trail Discussion 20
11 Deck Lighting Pedestrian/Trail Preferences 21 Deck Lighting - LED Fixtures MnDOT Standard LED Enhanced Fixture Type A Enhanced Fixture Type B 22
12 MnDOT Standard LED Fixtures Next To Planned Fixture For Existing Bridge Fixture Planned for Existing Bridge MnDOT Standard LED Fixture 23 MnDOT Standard LED Fixtures 24
13 MnDOT Standard LED Fixtures 25 Enhanced Fixture Type A Next To Planned Fixture For Existing Bridge Fixture Planned for Existing Bridge Enhanced Fixture Type A 26
14 Enhanced Fixture Type A 27 Enhanced Fixture Type A 28
15 Enhanced Fixture Type B Next To Planned Fixture For Existing Bridge Fixture Planned for Existing Bridge Enhanced Fixture Type B 29 Enhanced Fixture Type B 30
16 Enhanced Fixture Type B 31 Deck Lighting Fixture Discussion MnDOT Standard LED Fixture Planned for Existing Bridge Option for New Bridge Enhanced Fixture Type A Fixture Planned for Existing Bridge Option for New Bridge Enhanced Fixture Type B Fixture Planned for Existing Bridge Option for New Bridge 32
17 Deck Lighting Fixtures Preferences 33 Main Span Unit Aesthetic Lighting 34
18 Existing Bridge Aesthetic Lighting LED dimable white lights Light truss interior by washing interior side of truss members with light (Renderings from Preliminary Design VQRC Meetings) 35 Existing Bridge Aesthetic Lighting Wash of light on pier faces Wash of light on pier faces (Renderings from Preliminary Design VQRC Meetings) 36
19 Main Span Unit Aesthetic Lighting New Bridge Initial Concept Light interior faces of main river piers Wash of light on bottom of box girder (Renderings from Preliminary Design VQRC Meetings) Concepts to be finalized in Final Design Implementation to be agreed/coordinated between MnDOT and City 37 Main Pier Lighting 38
20 Main Pier Lighting - Locations Latsch Island Winona Main River Piers (with overlooks) Main Transition Piers 39 Bridge Overall View 40
21 Main Pier Lighting 41 Main Pier Lighting Option 1 - Floodlights on sides and interior of twin wall columns with wash on bottom soffit of superstructure 42
22 Main Pier Lighting Option 2 - Same as Option 1 plus two additional floodlights under overlook 43 Main Pier Lighting Option 3 - Same as Option 2 plus linear outline of pier curves 44
23 Transition Pier Lighting 45 Transition Pier Lighting - Locations Latsch Island Winona Main River Piers (with overlooks) Main Transition Piers 46
24 Bridge Overall View 47 Transition Pier 48
25 Transition Pier Lighting Option A - No Lights Option B - Floodlights on sides (Downlights) 49 Transition Pier Lighting Option C - Floodlights on sides with wash on bottom soffit of superstructure 50
26 Main Span Unit Aesthetic Lighting Main Pier Option 1 with Transition Pier (No Lights) 51 Main Span Unit Aesthetic Lighting Main Pier Option 1 with Transition Pier Floodlights on Sides (Downlights) 52
27 Main Span Unit Aesthetic Lighting Main Pier Option 1 with Transition Pier Floodlights on Sides and Light Wash on Superstructure 53 Main Span Unit Aesthetic Lighting Main Pier Option 2 with Transition Pier (No Lights) 54
28 Main Span Unit Aesthetic Lighting Main Pier Option 2 with Transition Pier Floodlights on Sides (Downlights) 55 Main Span Unit Aesthetic Lighting Main Pier Option 2 with Transition Pier Floodlights on Sides and Light Wash on Superstructure 56
29 Main Span Unit Aesthetic Lighting Main Pier Option 3 with Transition Pier (No Lights) 57 Main Span Unit Aesthetic Lighting Main Pier Option 3 with Transition Pier Floodlights on Sides (Downlights) 58
30 Main Span Unit Aesthetic Lighting Main Pier Option 3 with Transition Pier Floodlights on Sides and Light Wash on Superstructure 59 Option 1 with Transition Pier (No Lights) Option 1 with Transition Pier Floodlights on Sides (Downlights) Option 1 with Transition Pier Floodlights on Sides & Light Wash on Superstructure 60
31 Option 2 with Transition Pier (No Lights) Option 2 with Transition Pier Floodlights on Sides (Downlights) Option 2 with Transition Pier Floodlights on Sides & Light Wash on Superstructure 61 Option 3 with Transition Pier (No Lights) Option 3 with Transition Pier Floodlights on Sides (Downlights) Option 3 with Transition Pier Floodlights on Sides & Light Wash on Superstructure 62
32 Main Span Unit Aesthetic Lighting Discussion Option 1 Option 2 Option 3 Transition Pier (No Lights) Transition Pier (No Lights) Transition Pier (No Lights) Floodlights on Sides (Downlights) Floodlights on Sides (Downlights) Floodlights on Sides (Downlights) Floodlights on Sides & Light Wash on Superstructure Floodlights on Sides & Light Wash on Superstructure Floodlights on Sides & Light Wash on Superstructure 63 Main Span Unit Aesthetic Lighting Preferences 64
33 South Abutment Lighting 65 South Abutment 66
34 South Abutment 67 South Abutment Lighting Options Option 1 Wash of Light on Insets Option 2 Spotlights on Insets Option 3 Wash of Light on Abutment Wall 68
35 South Abutment Lighting Option 1 - Wash of Light on Insets 69 South Abutment Lighting Option 1 - Wash of Light on Insets 70
36 South Abutment Lighting Option 2 - Spotlights on Inset 71 South Abutment Lighting Option 2 - Spotlights on Inset 72
37 South Abutment Lighting Option 3 - Wash of Light on Abutment Wall 73 South Abutment Lighting Option 3 - Wash of Light on Abutment Wall 74
38 South Abutment Lighting Discussion Option 1 Wash of Light on Insets Option 2 Spotlights on Insets Option 3 Wash of Light on Abutment Wall 75 South Abutment Lighting Preferences 76
39 Pedestrian Trail Update 77 South Side Trails in Winona (Image from Preliminary Design VQRC Meeting) 78
40 North Side Trails on Latsch Island Existing North Abutment 79 Existing North Abutment 80
41 Existing North Abutment 81 North Side Trails on Latsch Island Rendering View 82
42 Latsch Island Trail Slope Treatment Stone Concrete 83
43 Latsch Island Trail Railing/Slope Treatment Option 1 - Chain Link with Stone 85 Latsch Island Trail Railing/Slope Treatment Option 1 - Chain Link with Concrete 86
44 Latsch Island Trail Railing/Slope Treatment Option 2 - Enhanced Chain Link with Concrete 88
45 Latsch Island Trail Railing/Slope Treatment Option 3 - Ornamental Metal with Concrete 90
46 Latsch Island Trail Railing/Slope Treatment Discussion Option 1 Chain Link with Stone Chain Link with Concrete Option 2 Enhanced Chain Link with Stone Option 3 Ornamental Metal with Stone Enhanced Chain Link with Concrete Ornamental Metal with Concrete 91 R TAT I O N PA R T M E N T PO DE Latsch Island Trail Railing/Slope Treatment Preferences NNESOTA MI OF TRAN S %$ $ "%! '!$% &!# % $% &!# % "%! ' "%! ' # % % 92
47 Existing Historic Bridge (Bridge 5900) Update Keith Molnau - Design Manager 93 Feature Refinements 94
48 Bridge Color Color of existing historical bridge was sampled at various locations and times with color samples and photographs Existing bridge color has variations Rehabilitated bridge will have color similar to matched existing color New bridge color to be selected for palette of compatible colors 95 Existing Bridge Color 96
49 Match Existing Bridge Color (with photo) Existing Bridge Color 177,165, Match Existing Bridge Color (color samples) MnDOT Color Match Bridge 5900 Coating MnDOT Standard Pearl Gray MnDOT Color Match Bridge 5900 Aged Concrete MnDOT Standard Light Buff 98
50 Surface Match #27722 Pearl Gray #26622 Match Existing Bridge Photo Match Aged Concrete #23525 Light Buff # Railing Color Existing historic bridge truss and railing metal will be flat finish metallic color New bridge railings will be metallic color with blue wave on pedestrian railing 100
51 Railing color Exact railing color on new bridge to be determined from palette of compatible colors with historic bridge Comments? 101 Entry Sign/Monument MnDOT to discuss further with City of Winona 102
52 Summary of Preferred Features 103 VQRC Final Design Meetings Meeting Date Items for Discussion Final Design Meeting #1 February 4, 2014 Bridge Piers and Overlooks Final Design Meeting #2 Final Design Meeting #3 Final Design Meeting #4 March 18, 2014 May 20, 2014 Today Bridge Pier Refinements Abutments, Retaining Walls and Pedestrian Railing Abutment and Railing Refinements, Bridge Color, Aesthetic Lighting Bridge Lighting, Trail Update, Feature Refinements, Summary/Next Steps 104
53 Bridge Pier and Overlook Preferences 105 Bridge Pier Types Five basic pier types: Latsch Island Winona Beam Piers Main River Piers (with overlooks) Flat Slab Transition Pier Beam Piers Main Transition Piers Flat Slab Piers 106
54 Main River Piers 107 Bridge Pier Types Five basic pier types: Latsch Island Winona Beam Piers Main River Piers (with overlooks) Flat Slab Transition Pier Beam Piers Main Transition Piers Flat Slab Piers 108
55 Main Transition Piers 109 Bridge Pier Types Five basic pier types: Latsch Island Winona Beam Piers Main River Piers (with overlooks) Flat Slab Transition Pier Beam Piers Main Transition Piers Flat Slab Piers 110
56 Beam Piers 111 Bridge Pier Types Five basic pier types: Latsch Island Winona Beam Piers Main River Piers (with overlooks) Flat Slab Transition Pier Beam Piers Main Transition Piers Flat Slab Piers 112
57 Flat Slab Transition Pier 113 Bridge Pier Types Five basic pier types: Latsch Island Winona Beam Piers Main River Piers (with overlooks) Flat Slab Transition Pier Beam Piers Main Transition Piers Flat Slab Piers 114
58 Flat Slab Pier 115 Abutment/Retaining Wall Preferences 116
59 South Abutment and Retaining Wall (North Abutment Similar) 117 Abutment Connection Preferences 118
60 South Abutment Connection Wall 119 Pedestrian Railing and Curb Preferences 120
61 Pedestrian Railing Three pedestrian railing types: 4-6 High Typical Railing 6-0 High Typical Railing Latsch Island Winona 4-6 High Railing * 6-0 High Railing Main River Piers (with overlooks) RR Tracks * 6-0 high railing approved by railroad (8-0 normally required) 121 Typical 4-6 Railing (Concrete Curb) 122
62 Typical 6-0 Railing 123 Railing At Overlooks 124
63 Railing At Overlooks 125 Bridge/ Railing Color 126
64 Surface Match #27722 Pearl Gray #26622 Match Existing Bridge Photo Match Aged Concrete #23525 Light Buff # Railing Color Metallic Color Blue Powder Coated For Long Life & Low Maintenance 128
65 Bridge Lighting 129 Deck Lighting - Pedestrian/Trail 130
66 Deck Lighting Fixture MnDOT Standard LED Fixture Planned for Existing Bridge Option for New Bridge Enhanced Fixture Type A Fixture Planned for Existing Bridge Option for New Bridge Enhanced Fixture Type B Fixture Planned for Existing Bridge Option for New Bridge 131 Main Span Unit Aesthetic Lighting Discussion Option 1 Option 2 Option 3 Transition Pier (No Lights) Transition Pier (No Lights) Transition Pier (No Lights) Floodlights on Sides (Downlights) Floodlights on Sides (Downlights) Floodlights on Sides (Downlights) Floodlights on Sides & Light Wash on Superstructure Floodlights on Sides & Light Wash on Superstructure Floodlights on Sides & Light Wash on Superstructure 132
67 South Abutment Lighting Option 1 Wash of Light on Insets Option 2 Spotlights on Insets Option 3 Wash of Light on Abutment Wall 133 Latsch Island Trail Railing/Slope Treatment Option 1 Chain Link with Stone Option 2 Enhanced Chain Link with Stone Option 3 Ornamental Metal with Stone Chain Link with Concrete Enhanced Chain Link with Concrete Ornamental Metal with Concrete 134
68 Next Steps and Timeline Construction will be in four (4) main stages: Stage 1 Bridge (New) and site demolition Stage 2 Roadway Stage 3 Bridge 5900 (Rehabilitate existing) Stage 4 Roadway/Landscaping 135 Construction Staging Stage 1 - Bridge No (New) & Site Demolition 136
69 Construction Staging Stage 2 - Bridge No (New) & Site Demolition 137 Construction Staging Stage 2 - Roadway 138
70 Construction Staging Stage 2 - Roadway 139 Construction Staging Stage 3 - Bridge No
71 Construction Staging Stage 3 - Bridge No Construction Staging Stage 4 - Roadway/Landscaping 142
72 Construction Staging Stage 4 - Roadway/Landscaping 143 Current Construction Activity Construction access on the levee near Pier
73 Current Construction Activity Main Pier 11 cofferdam construction 145 Current Construction Activity Construction laydown area on Latsch Island 146
74 Creating Bridges As Art 147
Winona Bridge Project
Winona Bridge Project Visual Quality Manual February 11, 2014 Acknowledgements Minnesota Department of Transportation Consulting Team SRF Consulting Group TY LIN Illumination Arts 2 WINONA BRIDGE PROJECT
More informationCOMMUNICATION URBAN DESIGN REVIEW BOARD CITY OF DES MOINES, IOWA MAY 16, 2017 MEETING
COMMUNICATION URBAN DESIGN REVIEW BOARD CITY OF DES MOINES, IOWA MAY 16, 2017 MEETING Subject: Recommendation Prepared by: PRELIMINARY DESIGN REVIEW OF LOCUST STREET BRIDGE CONSTRUCTION & COURT AVENUE,
More informationINNERBELT BRIDGE PUBLIC MEETING #2
Welcome to the INNERBELT BRIDGE PUBLIC MEETING #2 Today s Discussion Welcome and Introductions (Bob Brown, City of Cleveland) Innerbelt Project Status (Craig Hebebrand, ODOT) Bridge Type Selection Update
More informationMINNESOTA ARCHITECTURE - HISTORY INVENTORY FORM
Identification Historic Name Dean Parkway Bridge Current Name Bridge 90661 Field # Address Midtown Greenway over Dean Parkway City/Twp Minneapolis County Hennepin Legal Desc. Twp 29N Range 24W Sec 32 QQ
More informationCleveland Innerbelt Bridge / Central Viaduct City Planning Commission November 6, 2009
Cleveland Innerbelt Bridge / Central Viaduct City Planning Commission November 6, 2009 Process for Aesthetics Subcommittee June 25, 2009 Kick off Meeting June 26, 2009 Gateway and Tremont Focus Groups
More informationVictoria Bridge Municipal Class EA Civic Works Committee
Municipal Class EA John Pucchio, P. Eng., Project Manager June 19 2018 Introduction Existing Conditions Municipal Class EA Proposed Bridge Proposed Road Reconstruction Proposed Improvements Construction
More informationMiddlebury RS 0174(8)
Middlebury RS 0174(8) Preferred Alternative Meeting VT 125 Bridge #13 over Middlebury River August 6, 2012 Presented to Presented by Town of Middlebury VTrans & VHB Introductions: Jennifer Fitch VTrans
More informationNational Register of Historic Places Continuation Sheet
NPS Form 10-900-a (Rev. 8/2002) OMB No. 1024-0018 (Expires 5-31-2012) United States Department of the Interior National Park Service National Register of Historic Places Continuation Sheet Bridge No. 5721
More informationVictoria Street Pedestrian Bridge
Township of Centre Wellington Victoria Street Pedestrian Bridge Class Environmental Assessment County of Wellington & Township of Centre Wellington Badley Bridge Replacement/Rehabilitation (County of Wellington),
More informationCentury Park to Ellerslie Road Preliminary Engineering
Century Park to Ellerslie Road Preliminary Engineering South LRT Extension Stakeholder Information Panel Brochure March 2010 www.edmonton.ca/lrtprojects LRT Station (left) and Transit Centre Architectural
More informationCleveland Innerbelt Bridge / Central Viaduct Cleveland City Planning Commission October 2, 2009
Cleveland Innerbelt Bridge / Central Viaduct Cleveland City Planning Commission October 2, 2009 New Westbound Bridge Schedule December 1, 2009 Contract Documents/Plan Package March 1, 2010 Request for
More informationWELCOME TO PUBLIC INFORMATION CENTRE #2. Please Sign In
WELCOME TO PUBLIC INFORMATION CENTRE #2 Replacement of Oxtongue Lake Narrows Bridge & Oxtongue River Bridge, Highway 60 (G.W.P. 93-89-00 & G.W.P. 5550-04-00) Class Environmental Assessment (Group B) Please
More informationGLEN ROAD PEDESTRIAN BRIDGE ENVIRONMENTAL ASSESSMENT STUDY PUBLIC INFORMATION CENTRE #2 OCTOBER 24, 2017
GLEN ROAD PEDESTRIAN BRIDGE ENVIRONMENTAL ASSESSMENT STUDY PUBLIC INFORMATION CENTRE #2 OCTOBER 24, 2017 Glen Road Pedestrian Bridge Class Environmental Assessment 1 WELCOME! Welcome to the second Public
More informationThe purpose of tonight s PIC is to:
The purpose of tonight s PIC is to: Provide an overview of the work completed to date and a summary of the Class EA process being followed; Provide a summary of public input received so far, including
More informationWelcome to the Sellwood Bridge Project Pre-Construction Open House
Welcome to the Sellwood Bridge Project Pre-Construction Open House 5:30 7:30 p.m. Please sign in here Information stations and project staff are located throughout the room. Goals for Tonight s Meeting
More informationPreservation: Why Not In Pennsylvania? Presented By: Nathan Holth
Preservation: Why Not In Pennsylvania? Presented By: Nathan Holth PA Preservation Barriers Why Not Pennsylvania? Pennsylvania has an unrivaled collection of historic bridges, particularly metal truss bridges,
More informationMississippi Skyway Preliminary Engineering Report
EXECUTIVE SUMMARY Mississippi Skyway Preliminary Engineering Report CITY OF RAMSEY, MINNESOTA DECEMBER 2014 City of RAMSEY EXECUTIVE SUMMARY Project Need and Intent The Mississippi Skyway pedestrian bridge
More information6 BRIDGES. 6.1 Design philosophy. Proposed bridges
SECTION 6 BRIDGES 6 BRIDGES Throughout the Project, bridges are a key visual element and marker for road users, pedestrians and cyclists. The design of bridges, as with other visible structures, has been
More informationCorridor Enhancements
Corridor Enhancements Safety is MoDOT s first priority in widening and rebuilding I-70 across the state of Missouri. MoDOT also understands that the interstate - and its interchanges and overpasses - are
More informationMoving The Metro. A special construction update for the metro Omaha area.
Moving The Metro A special construction update for the metro Omaha area. ebraska Department of Roads Spring/Summer 2017 I-80 / I-480 / US-75 Interchange The improvements on this project consist of bridge
More informationNorth River Mills Bridge Hampshire County State Project # S314-45/ Federal Project # ARRA-4520(003)D FR#: HM-1
North River Mills Bridge Hampshire County State Project # S314-45/20-2.40 02 Federal Project # ARRA-4520(003)D FR#: 10-1463-HM-1 STATE LEVEL OF HISTORIC DOCUMENTATION November 2010 West Virginia Department
More informationWELCOME TO THE PUBLIC INFORMATION CENTRE. Please Sign In
WELCOME TO THE PUBLIC INFORMATION CENTRE Replacement of Oxtongue Lake Narrows Bridge & Oxtongue River Bridge, Highway 60 (G.W.P. 93-89-00 & G.W.P. 5550-04-00) Class Environmental Assessment (Group B) Please
More informationHISTORIC BRIDGE FOR SALE COLUMBIA BRIDGE IN JACKSON PARK, CHICAGO, ILLINOIS
HISTORIC BRIDGE FOR SALE COLUMBIA BRIDGE IN JACKSON PARK, CHICAGO, ILLINOIS In Accordance With Illinois Law, The City of Chicago presents this information package as part of an effort to offer this historic
More informationBeckett Bridge Replacement (Design) Riverside Drive from west of Chesapeake Drive to Pampas Avenue
Pinellas County Public Works Traffic & Roadway Division Transportation Engineering Section Replacement (Design) Riverside Drive from west of Chesapeake Drive to Pampas Avenue Agenda - Aesthetics Committee
More informationI-90 Mississippi River Bridge & Interchange Project
I-90 Mississippi River Bridge & Interchange Project Presentation Outline I. Background: Context & Need for Project II. Preferred Alternative Overview III. Project Development IV. Project Management Tools
More informationCITY AND COUNTY OF DENVER DEPARTMENT OF PUBLIC WORKS CONTRACT NO CONFLUENCE BIKE/PED RAMPS-SOUTH PLATTE GREENWAY STATEMENT OF QUANTITIES
01050-1 Construction Surveying 1 LS 01500-1 Temporary Fences & Barricades 1,500 LF 02600-1 Shoring, Cofferdam, Temp. Sheeting, & Dewatering 1 LS 01565-1 Storm Drainage & Erosion Sediment Control 1 LS 01565-2
More informationHistoric Bridge Foundation Facebook Archives
Historic Bridge Foundation Facebook Archives Focus Bridges: Firth of Forth Bridges September 2017 The Firth of Forth in Scotland is a unique location perhaps one of the only locations in the world where
More informationDESIGN OF FOOTBRIDGES
Civil Engineering Technical Requirement CIVIL-SR-006 DESIGN OF FOOTBRIDGES Revision: 9 Updated: 26/08/2015 Queensland Rail 2015 Reproduction by any means (including electronic, mechanical, photocopying,
More informationMINNESOTA ARCHITECTURE - HISTORY INVENTORY FORM
Identification Historic Name Bridge L8849 Current Name Bridge L8849 Field # Address Municipal Road 99 over the Chippewa River City/Twp Montevideo County Chippewa Legal Desc. Twp 117N Range 40W Sec 07 QQ
More informationImportant Forces. Distance Range. Design Features. Suspension Bridge. Truss Bridge. Beam Bridge. Bridge Type. Arch Bridge
Bridge Type Beam Bridge Truss Bridge Arch Bridge Suspension Bridge Design Features Distance Range Important Forces Last name: First name: Date: Period: BRIDGES INTRO Welcome to Craggy Rock! COM INC COM*
More informationDowntown Redevelopment Project Update
Downtown Redevelopment Project Update The redevelopment project will begin the week of September 4, 2017. It is anticipated that construction will be approximately 565 days, depending on weather. 7-6-18
More informationHISTORIC PRESERVATION COMMISSION MEETING AGENDA November 20, 2007, 7:00 p.m. City of Geneva, City Hall 109 James Street, Geneva, IL
GENEVA HISTORIC PRESERVATION COMMISSION 22 S. FIRST STREET GENEVA, IL 60134 630/938.4541 HISTORIC PRESERVATION COMMISSION MEETING AGENDA November 20, 2007, 7:00 p.m. City of Geneva, City Hall 109 James
More informationWest Dennis Center: Bass River to Old Main Street. West Dennis Business District: Old Main Street to Dennis Commons
West Dennis Center: Bass River to Old Main Street West Dennis Business District: Old Main Street to Dennis Commons Dennisport Center: Dennis Commons to Division Street Main Street Project Goals Project
More informationVisitor's Guide to Historic Bridge Park
Visitor's Guide to Historic Bridge Park Located in Calhoun County, Michigan, southeast of Battle Creek, the park is open year-round from 8:00 AM to 8:00 PM. Entry to the park is free of charge. Guide produced
More informationReconstruction Project. Wayzata Task Force Meeting September 3, 2009
CSAH 101 Reconstruction Project Wayzata Task Force Meeting September 3, 2009 Agenda 700 7:00 Re-Introductions ti 7:05 2008 Activity Recap / 2009 Activities-to-date 7:10 Discussion of Layout Revisions (per
More informationConcord, BRF-X-5099 (021), Draft Alternative Analysis
THE CITY OF CONCORD in conjunction with the STATE OF NEW HAMPSHIRE, DEPARTMENT OF TRANSPORTATION BUREAU OF ENVIRONMENT and the FEDERAL HIGHWAY ADMINISTRATION Concord, BRF-X-5099 (021), 12004 Draft Alternative
More informationAPPENDIX A: Willamette River Bridge Survey
APPENDIX A: Willamette River Bridge Survey The Oregon Department of Transportation is in the final phase of completing the Environmental Assessment which outlines the potential environmental impacts of
More informationOverall Map. Chicago. St. Louis. Summit. Joliet. Dwight. Pontiac. Bloomington-Normal Lincoln. Springfield. Carlinville. Alton EXPERIENCE IT YOURSELF.
Overall Map Summit Chicago Bloomington-Normal Lincoln New Station Planned New Station Planned Dwight Pontiac Joliet Pedestrian overpass and second platform planned Higher speed service began in this section
More informationChain Bridge Road Sidewalk Improvements Citizen Council Work Session
Chain Bridge Road Sidewalk Improvements Citizen Council Work Session May 10, 2016 Project Location 2 Project Objectives Provide a continuous pedestrian facility (sidewalk) connection from Downtown City
More informationCharles River Reservation Footbridge Projects/Trail Corridor Proposal. May 7, 2009, 6:30 8:00 pm Newton-Wellesley Hospital Auditorium, Newton
Charles River Reservation Footbridge Projects/Trail Corridor Proposal May 7, 2009, 6:30 8:00 pm Newton-Wellesley Hospital Auditorium, Newton Commonwealth of Massachusetts Governor Deval L. Patrick Lieutenant
More informationWelcome. Mill Creek Ravine Pedestrian Bridges Rehabilitation. Public Information Session #1. Thursday, October 27, :00 8:00 p.m.
Welcome Mill Creek Ravine Pedestrian Bridges Rehabilitation Public Information Session #1 Thursday, October 27, 2016 5:00 8:00 p.m. Tonight you can: Learn about the rehabilitation of 5 pedestrian bridges
More informationAASHTO SUBCOMMITTEE ON DESIGN. June 15, 2006 MARK ROBINSON, P.E. DISTRICT 5 INTERSTATE PROGRAM MANAGER FLORIDA DEPARTMENT OF TRANSPORTATION
AASHTO SUBCOMMITTEE ON DESIGN June 15, 2006 MARK ROBINSON, P.E. DISTRICT 5 INTERSTATE PROGRAM MANAGER FLORIDA DEPARTMENT OF TRANSPORTATION CENTRAL FLORIDA INTERSTATE 4 FACTS Trucks and Others 12% Tourist
More informationDESIGN SCENE SUBJECT INDEX
DESIGN SCENE SUBJECT INDEX CHAPTER 1: TITLE SHEET and GENERAL LAYOUT AREA OF ENVIRONMENTAL SENSITIVITY BRIDGE & APPROACH PLANS CONSTRUCTION PLAN FOR EXCEPTIONS EXCEPTION CLARIFICATION GOVERNING SPECIFICATIONS
More informationPublic Information Meeting
Today s Agenda: Open House - (5:30-7PM) Presentation- (5:45PM) County Project: P-5351-1 FDOT Project :242172-1-58-01 Public Information Meeting Technical Design Team Volusia County Jim White, P.E.- Project
More information10/18/2010. Today s presentation will focus on what the construction engineer can do to help deliver a successful bridge project
Field Construction Engineering Aspects of Bridge Construction Virginia Tech Construction Engineering Conference Thomas DeHaven, P.E. Executive Vice President - Figg Bridge Inspection, Inc. October 1, 2010
More informationROME WATERFRONT VILLAGE PROJECT NARRATIVE January 25, 2018
January 25, 2018 The Rome Waterfront Village project is intended to foster the revitalization of the area between South James Street and Erie Boulevard north of the Erie Canal as well as improve public
More informationDallas CBD Second Light Rail Alignment (D2)
Dallas CBD Second Light Rail Alignment (D2) Subway Project Refinement City of Dallas Transportation and Trinity River Project Committee February 13, 2017 Discussion Items Background Schedule Public/Stakeholder
More informationFall 2017 Construction Update
Fall 2017 Construction Update Ward 4 Southeast Engineering Department Riverwalk Red Multi-Use Trail Bridge Rehabilitation The Riverwalk Red Multi Use Trail Bridge was awarded to Cramer and Associates,
More informationLighting Existing Conditions and Design Criteria Report Brian Regan Ltg./Elect. Virginia Historical Society 10/8/03
Lighting Existing Conditions and Design Criteria Report Brian Regan Ltg./Elect. Virginia Historical Society 10/8/03 Executive Summary The existing lighting conditions and design criteria report describes
More information(BRIDGE NO. 36C-0223)
City of Palo Alto Newell Road Bridge Replacement (BRIDGE NO. 36C-0223) TYPE SELECTION REPORT DRAFT November 2012 City of Palo Alto Newell Road Bridge Replacement (BRIDGE NO. 36C-0223) TYPE SELECTION REPORT
More informationWelcome to the. Open House
Welcome to the 5th Street to Kinsman Road Open House November 14 5:30 7:00 p.m. Please sign in Project Overview In December 2016, City Council adopted SW 5th Street as the preferred alignment to connect
More information5.7.6 St Peters Interchange Portal
5.7.6 St Peters Interchange Portal Design intent At St Peters interchange the design approach to the tunnel portals differs from that adopted for the western portals at Kingsgrove. An entirely different
More informationSTANDARD SPECIFICATIONS Book 2 ENGINEERING DRAWINGS INCLUDES ADDENDUMS
STANDARD SPECIFICATIONS Book 2 ENGINEERING DRAWINGS INCLUDES ADDENDUMS July 23, 2018 Page 1 of 7 STANDARD LEGEND SYMBOLS (September, 1973)... AS-101A STANDARD LEGEND SYMBOLS (September, 1973)... AS-101B
More informationLAND USE ASSESSMENT REPORT (LUAR) PROPOSED AFFORDABLE HOUSING COMPLEX MAIN ROAD PDE FILE NUMBER: REZ
LAND USE ASSESSMENT REPORT (LUAR) PROPOSED AFFORDABLE HOUSING COMPLEX 560-564 MAIN ROAD PDE FILE NUMBER: REZ13-00008 PREPARED FOR P.O. BOX 908 ST. JOHN'S, NL CANADA A1B 4C4 PROPONENT BROOKSIDE DEVELOPMENTS
More informationOption A FINAL AESTHETIC SIGNATURE BRIDGE PROPOSAL. SR 836/I-395/I-95 Project
ELECTRONIC COPY AESTHETIC VOLUME 2 2.28.17 APPROVED SIGNATURE BRIDGE PACKAGE, APTES, AND SIGNATURE BRIDGE RELATED ATCS SR 836/I-395/I-95 Project Florida Department of Transportation District 6 & Miami-Dade
More informationCity of Edmonton. Walterdale Bridge Replacement and Approach Roads Evaluation. Concept Planning Study. Final Report
City of Edmonton Final Report Walterdale Bridge Replacement and Approach Roads Evaluation April, 2011 Walterdale Bridge Replacement and Approach Roads Evaluation Final Report April 2011 Acknowledgement
More informationParapet/Formliner/Fencing
Parapet/Formliner/Fencing Cross Parapet/Formliner/Fencing Street Aesthetic Features Context The I-290 Phase I study is evaluating improvements along 13 miles of the Eisenhower Expressway, from west of
More informationSpring 2018 Construction Update
Spring 2018 Construction Update Ward 3 Southwest Engineering Department Locust Street Bridge over the Des Moines River The Locust Street Bridge over the Des Moines River project is being let through the
More informationPublic Meeting #3 May 9, 2009 MVVA Team
Public Meeting #3 May 9, 2009 MVVA Team Welcome to the third Public Meeting for the Lower Don Lands Municipal Class Environmental Assessment (EA) Infrastructure Master Plan and Keating Channel Precinct
More informationPurpose of Open House #3
Public Meeting #3 May 9, 2009 MVVA Team Purpose of Open House #3 The main purpose of this Open House is to present and seek input on the: Evaluation of transportation and infrastructure design alternatives
More informationDerby-Shelton Bridge Pedestrian and Bicyclist Enhancements [1]
nhancements [1] STATUS OF PROJECT: The project has recently moved from the Preliminary Design Phase to the Final Design Phase following the most recent Public Involvement Meeting held on January 9, 2019
More informationDRAFT SECTION 4(F) EVALUATION LIFT BRIDGE
DRAFT SECTION 4(F) EVALUATION I. DESCRIPTION OF SECTION 4(F) RESOURCE The Section 4(f) resource affected by the proposed action is the Lift Bridge, a property listed on the National Register of Historic
More informationTRANSPORTATION COMMITTEE
TRANSPORTATION COMMITTEE CITY OF OTTAWA Ministry of Transportation Detailed Design Assignment G.W.P.# 4058-01-00 Highway 417 (Ottawa Queensway) Widening & Rehabilitation from Maitland Avenue to Island
More informationBeckett Bridge PD& E Study. Presentation to: Board of County Commissioners
Beckett Bridge PD& E Study Presentation to: Board of County Commissioners October 22, 2013 Introduction Study Began January 2012 Alternatives Presented to Commission October 2013 Alternatives Presented
More informationMINNESOTA ARCHITECTURE - HISTORY INVENTORY FORM
Identification Historic Name Nicollet Avenue Bridge Current Name Nicollet Avenue Bridge Field # Address Nicollet Avenue over Minnehaha Creek City/Twp Minneapolis SHPO Inventory Number Review and Compliance
More informationWater Works: Downtown Minneapolis Riverfront Destination
Water Works: Downtown Minneapolis Riverfront Destination Previous conceptual design process for Water Works began in 2012 along with the Central Mississippi Riverfront Regional Park Master Plan Update
More informationHistoric Bridge Adoption Information Packet
Historic Bridge Adoption Information Packet Falls County CR 179 over Big Elm Creek Bridge October 2017 Table of Contents Announcement... 3 Bridge Location... 4 Bridge Information... 4 Bridge Condition
More informationROAD CONSTRUCTION. 36 June 2014 ROADS&BRIDGES
ROAD CONSTRUCTION 36 June 2014 ROADS&BRIDGES Young is full of life Recent expansion completes continuous, multilane arterial By Donald Hammack, P.E. Contributing Author The Florida Department of Transportation
More informationCENTERTON ROAD BRIDGE REPLACEMENT
CENTERTON ROAD BRIDGE REPLACEMENT FEASIBILITY STUDY BURLINGTON COUNTY BRIDGE C4.4 OVER RANCOCAS CREEK TOWNSHIPS OF MOUNT LAUREL, WESTAMPTON & WILLINGBORO 1 prepared for: BOARD OF CHOSEN FREEHOLDERS BURLINGTON
More informationDallas CBD Second Light Rail Alignment (D2)
Dallas CBD Second Light Rail Alignment (D2) Subway Project Refinement Public Meetings January 19, 2017 Discussion Items Background Schedule Public/Stakeholder Involvement Subway Construction Overview Potential
More informationTable of Contents Programmatic 4(f) Evaluation. Programmatic 4(f) Evaluation 77
Table of Contents Programmatic 4(f) Evaluation Programmatic 4(f) Evaluation 77 6.1 Introduction 77 6.2 Project Background 77 6.3 Constraints 77 6.4 Purpose and Need 83 6.5 Programmatic Section 4(f) Applicability
More informationPRELIMINARY PUBLIC NOTICE 1-161
Commander (dpb) First Coast Guard District 1 South Street Battery Park Building New York, NY 10004-1466 March 9, 2018 PRELIMINARY PUBLIC NOTICE 1-161 The United States Coast Guard is soliciting public
More informationMississauga Waterfront. Parks Strategy - Draft
Potential configuration for river s edge seating. Boating on Credit River: A regatta Boating on Credit River: Active enjoyment 5.2 Port Credit Memorial Park West Priority Park 5.2.1 Site Opportunities
More informationBelmont Bridge Replacement
Belmont Bridge Replacement Board Of Architectural Review Meeting September 18, 2018 Corridor Plan Introduction August 15, 2017 BAR Meeting Comments The combination of landscaping, engineering, and planning
More informationGreat Lakes North Central South Central FAX: (718) CONTACT PERSON: ADDRESS: Daniel Hom, PE, Engineer-in-Charge
AMERICAN SOCIETY OF HIGHWAY ENGINEERS National Project of the Year Award OFFICIAL ENTRY FORM AWARD CATEGORY (Check One): Under $20 Million Over $20 Million SPONSORING REGION (Check One): Northeast Mid-Atlantic
More informationRt. 29 Solutions Project Delivery Advisory Panel. January 7, 2016
Rt. 29 Solutions Project Delivery Advisory Panel January 7, 2016 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Dec
More informationCommunity Sensitive Design: (Context Sensitive Design)
What is? Community Sensitive Design: (Context Sensitive Design) The process by which urban design, land-use planning and aesthetic enhancements are applied to a project to make it an integral part of the
More informationPROJECT SITE The Proposed Project includes the Allen and Pike Street malls between Delancey and South Streets (see Figure 2C-1).
Chapter 2, Section C: A. INTRODUCTION This chapter considers the potential of the proposed Reconstruction of the Allen and Pike Street Malls project to affect the urban design characteristics and visual
More informationTHE STILLWATER BRIDGE STORY
THE STILLWATER BRIDGE STORY 1931 Stillwater Bridge Part I: The Backstory Behind the Bridge Undoubtedly the highest profile road project in Minnesota is the new bridge at Stillwater, the St. Croix Crossing.
More informationViews from the Bridge
Chapter 2 Views from the Bridge Alternative 2A would primarily have adverse visual impacts to views from the Bridge, with the exception of a strongly adverse visual impact from Viewpoint 11 (Car View East)
More informationREHABILITATION FEASIBILITY STUDY ER#
REHABILITATION FEASIBILITY STUDY MILLER FARM ROAD BRIDGE PROJECT VENANGO COUNTY BRIDGE NO. 34 CARRYING S.R. 7212, SECTION L00 OVER OIL CREEK OIL CREEK AND CHERRYTREE TOWNSHIPS VENANGO COUNTY, PENNSYLVANIA
More informationDorrance H. Hamilton Building
Dorrance H. Hamilton Building Josh Kreutzberger Penn State Architectural Engineering Technical Report 3 Advisor: Dr. Mistrick Site Overview Martin Building December 2006 Scott Library & Administrative
More informationPublic Open House. Welcome! Presentation at 5:15 p.m. Please sign-in at the registration table
Public Open House Welcome! Presentation at 5:15 p.m. Please sign-in at the registration table The Grand Avenue Extension Location and Environmental Study will determine the location of the extension of
More informationBEST PRACTICES FOR DETAILED APPLICATIONS TA/SRTS Program
BEST PRACTICES FOR DETAILED APPLICATIONS 2019 TA/SRTS Program Criteria Evaluation Categories (Program Guide Table 3) Safety Connectivity & Accessibility Quality of Life Economic Development Encouragement
More informationERIE-ATTICA RAILROAD BRIDGE AND TRAIL FEASIBILITY STUDY
ERIE-ATTICA RAILROAD BRIDGE AND TRAIL FEASIBILITY STUDY Prepared for: Village of Avon 74 Genesee Street Avon, New York 14414 Prepared by: 2165 Brighton-Henrietta Townline Road Rochester, New York 14623
More informationBethlehem Pike Streetscape Master Plan
Bethlehem Pike Streetscape Master Plan Prepared for Springfield Township October 2008 By Michael Baker Jr., Inc. Carter Van Dyke Associates Table of Contents 1. Introduction 3 2. General Corridor Wide
More informationPage. I. Introduction 1. II. Project Purpose and Need 2. IV. Description of Section 4(f) Property 2. V. Impacts to Section 4(f) property 3
Table of Contents Programmatic Section 4(f) Evaluation for use of a Historic Bridge Replacement of Route 30/130 Bridge over the Cooper River Structure No. 0405-153 City of Camden, Borough of Collingswood,
More informationChapter 8. Visualizations
Examples of Effective Techniques for Improving the Quality of Environmental Documents Chapter 8. Visualizations Visualizations help the reader to see what the project would look like in the real world.
More informationBRADENTON RIVERWALK EXPANSION MASTER PLAN
BRADENTON RIVERWALK EXPANSION MASTER PLAN INTRODUCTION & AGENDA Process Update Community Engagement Summary Center for Active Design (CfAD) Recommendations Context and Existing Conditions Master Plan Alternatives
More informationMINNESOTA ARCHITECTURE - HISTORY INVENTORY FORM
Historic Name Bridge R0437 Identification SHPO Inventory Number Review and Compliance Number Current Name Bridge R0437 (Stone Arch Bridge at Terrace Mill) Field # Address N/A Crossing over Chippewa River
More informationProject Purpose. Project Need
Project Purpose The purpose of the project is to implement a bridge improvement solution that corrects the existing safety problem at the Strasburg Pike Bridge. The project will provide a structurally
More informationPopp s Ferry Causeway Park Back Bay Environmental Educational Center CASHIO COCHRAN LLC
Popp s Ferry Causeway Park Back Bay Environmental Educational Center CASHIO COCHRAN LLC A LIMITED LIABILITY COMPANY Popp s Ferry Causeway Park Master Plan Prepared for: City of Biloxi Department of Parks
More informationSecond Line West Pedestrian/Cyclist Crossing of Highway 401 Class EA. Second Line West Pedestrian/Cyclist Crossing of Highway 401 Class EA
1 1 Purpose of Public Information Centre #2 To provide interested and/or potentially affected stakeholders with an opportunity to participate in the planning and decision-making process for this Municipal
More informationFrom local initiatives to some of the largest and most complex projects, KOA leads the field in:
Krech Ojard & Associates offers a highly capable multidisciplined team that provides the professional services needed to deliver successful transportation facility improvements. Our team provides multidisciplinary
More informationPROPOSED DEVELOPMENT CONCEPTS
MEMORANDUM To Planning and Zoning Commission From Sally Vecchio, Ass t Town Mgr, Community Development Date November 9, 2011 Re Revised Lot 61 Design Concept work session SUMMARY Bob Ballard and Rick Daugherty
More informationEnhance the High Line Canal Projects
Enhance the High Line Canal Projects Joint Project Proposal for Arapahoe County Open Spaces Funding Partner Sponsors: South Suburban Park and Recreation District City of Centennial City of Littleton October
More informationHow can landscape architects aide in transportation planning process? John Dempsey, PLA Toole Design Group July 24, 2015
How can landscape architects aide in transportation planning process? John Dempsey, PLA Toole Design Group July 24, 2015 What is Landscape Architecture? Landscape Architecture 1863 What is Landscape Architecture?
More informationPlanning Districts INTRODUCTION
INTRODUCTION To facilitate detailed examination of development prospects for all areas of the community, Delano has been divided into 14 planning districts. The location of these planning districts is
More informationPRELIMINARY DESIGN + DEVELOPMENT PLAN
WELCOME! To The Public Open House May 30 th, 2017 HARBOUR WEST PARKS Vision Project Overview The City s vision for Port Credit Harbour West Parks is to develop a vibrant waterfront destination that integrates
More informationKenilworth Station Art and Landscape Committee (KSALC) July 16, 2015
Kenilworth Station Art and Landscape Committee (KSALC) July 16, 2015 1 Today s Topics Welcome and Introductions Review Proposed Concepts in Development Upcoming Events/Next Steps Questions and Open Discussion
More information