Oconomowoc Area School District Facility Construction Update August 25, 2017

Size: px
Start display at page:

Download "Oconomowoc Area School District Facility Construction Update August 25, 2017"

Transcription

1 Oconomowoc Area School District Facility Construction Update August 25, 2017

2 IXONIA ELEMENTARY SCHOOL Ixonia Elementary is getting ready for the start of the new school year! Interior cleaning and classroom setup are underway and installation of the temporary main entrance and ramp are complete. The footings and poured walls for the new addition will be completed this week, then structural steel delivery will begin. The new addition will start to take shape as the steel work begins in early September. A time-lapse camera has been installed to view still photos of the construction progress at Ixonia Elementary. You can view images by clicking this link: There will be some new routines this school year as a result of the construction work and those details will be available on the Ixonia Elementary School page. BEGAN June 9, 2017 SITE PREPARATION, RETENTION POND EXCAVATION, WELL INSTALLATION, PLAYGROUND EXCAVATION, DEVELOPMENT OF BUS LOOP, AND RELOCATION OF UTILITIES BEGAN June 2017 RETENTION POND CLAY LINER INSTALLED, CONTINUED DEVELOPMENT OF BUS LOOP, UTILITIES RELOCATED, NEW WELL INSTALLED & TIED INTO INTERIOR LINES, REMOVAL OF OLD WELL BEGAN, FIRE PROTECTION SYSTEM WATER STORAGE TANK INSTALLATION BEGAN, REMOVAL OF EXTERIOR CANOPIES & CEILING SECTIONS BEGAN July 2017 INTERIOR CONCRETE WORK COMPLETED, EXTERIOR BRICK WORK FOR THE GYM DOOR & TEMPORARY MAIN OFFICE DOOR COMPLETED, FOOTINGS FOR NEW ADDITION COMPLETED, FIRE PROTECTION SYSTEM STORAGE TANK INSTALLATION COMPLETED, INTERIOR ASBESTOS ABATEMENT COMPLETED July 31-August 25, 2017 OASD CREWS FINISH INTERIOR CLEANING FOR THE START OF THE SCHOOL YEAR, STRUCTURAL STEEL WORK BEGINS, EXTERIOR DRAIN TILE INSTALLATION CONTINUES August 28-Septmber 1, 2017 CONTINUES September August 2018

3 GREENLAND ELEMENTARY SCHOOL Greenland Elementary is getting ready for the start of the new school year! Classroom cleaning and setup is complete while final cleaning is underway in the corridors. The new cooling system will be complete next week and ready for the last few weeks of summer weather. Work on the new boiler will continue in the month of September, for the system to be operational before the weather turns cold. BEGAN June 9, 2017 SITE DEMOLITION, INSTALLATION OF SERVICE & FEEDER CONDUIT, INSTALLATION OF PIPING, ROOF REMOVAL & REPLACEMENT, DUCT WORK, FIRE ALARM SYSTEM & EMERGENCY LIGHTING INSTALLATION, FURNACE/BOILER REMOVAL AND CORRIDOR LIGHTING REMOVAL & REPLACEMENT ALL BEGAN June 10-July 31, 2017 CORRIDOR & EGRESS LIGHTING INSTALLATION COMPLETED, PLANNED ELECTRICAL SHUTDOWNS FOR INSPECTION, PLANNED FIRE ALARM SYSTEM TESTS, PIPING INSULATION COMPLETED, CEILING GRID INSTALLATION COMPLETED, ROOF REPLACEMENT COMPLETED, HEATING AND COLLING SYSTEM INSTALLATION COMPLETED August 1-25, 2017 REMOVAL OF REMAINING TOOLS/MATERIALS, FINAL CORRIDOR CLEANING, PAINT TOUCH UP August 28-September 1, 2017 WELCOME BACK TO SCHOOL September 5, 2017 September 15, 2017

4 PARK LAWN ELEMENTARY SCHOOL Park Lawn is ready to welcome back students! Classrooms are clean and set for the start of the new school year and final corridor cleaning is nearly complete. Boiler work will continue in the month of September for the heating system to be operational before Fall.. BEGAN June 9, 2017 SITE DEMOLITION, CONDUIT RACK INSTALLATION, INSTALLATION OF PIPING, ROUGH-IN & INSTALLATION OF NEW UNIT VENTILATORS, FIRE ALARM SYSTEM INSTALLATION, DUCT WORK INSTALLATION, AND BOILER ROOM ELECTRICAL PANEL INSTALLATION ALL BEGAN June 10-July 31, 2017 UNIT VENTILATOR INSTALLATION COMPLETED, ROOF REMOVAL & REPLACEMENT COMPLETED, CLASSROOM & CORRIDOR CLEANING COMPLETED, FIRE ALARM SYSTEM INSTALLATION COMPLETED, PIPING INSULATION COMPLETED, ELECTRICAL UPGRADES COMPLETED August 1-25, 2017 September 29, 2017 WELCOME BACK TO SCHOOL September 5, 2017 REMOVAL OF REMAINING TOOLS/MATERIALS, FINAL CORRIDOR CLEANING, PAINT TOUCH UP August 28-September 1, 2017

5 MEADOW VIEW ELEMENTARY The OASD School Board approved initial schematic designs for the new Meadow View Elementary School at their June 20, 2017, meeting, then reviewed this initial exterior schematic design at their July 18, 2017 meeting. The design development and construction document phases of the project will continue through the spring of 2018 before public bidding and construction begin. SCHEMATIC DESIGNS PRESENTED TO OASD SCHOOL BOARD June 20, 2017 & July 18, 2017 DESIGN DEVELOPMENT & DOCUMENTS July 2017-March 2018 BIDDING OPEN March 2018 BEGINS April 2018 GROUND BREAKING CEREMONY May 2018 COMPLETE August 2019 August 2019 In early July, the archeologist s report from the Commonwealth Heritage Group was submitted to, and accepted by, the Wisconsin Historical Society. The Commonwealth Heritage Group also forwarded the approval to the DNR, and the NE Corridor project received its Notice of Intent permit from the DNR. The City of Oconomowoc began work at the site this week and initial paving is set to be completed in early November, 2017.

6 OHS: MAIN & EAST CAMPUS The OASD School Board approved initial schematic designs for the OHS Main and East Campus projects at their July 18, 2017, meeting. The presentation included designs like these, for the café/gathering space at OHS East Campus. The design development and construction document phases will continue through the fall before public bidding and construction begin in December 2017/January OHS MAIN CAMPUS & OHS EAST CAMPUS INSTRUCTIONAL SPACE PROJECT VISIONING BEGAN April 2017 DESIGN PHASE May-November 2017 PUBLIC BIDDING PHASE December 2017 BEGINS December 2017/ January 2018 COMPLETE August 2018 September 2018

Binghamton University Construction SUMMER 2012 HIGHLIGHTS

Binghamton University Construction SUMMER 2012 HIGHLIGHTS Binghamton University Construction SUMMER 2012 HIGHLIGHTS Binghamton University Construction Summer 2012 Large and small construction projects were completed during the summer 2012 construction season.

More information

REPORT CARD TO THE COMMUNITY MAY 15, 2018

REPORT CARD TO THE COMMUNITY MAY 15, 2018 REPORT CARD TO THE COMMUNITY MAY 15, 2018 O On May 10, 2014 voters in Greenville ISD approved a $72,275,000 bond election. BOND PROPOSAL PROJECT BOND AMOUNT CONSTRUCT A NEW BOWIE ELEMENTARY SCHOOL $17,600,000

More information

Greenwood Elementary School 5550 South Holly Street Greenwood Village, Colorado 80111

Greenwood Elementary School 5550 South Holly Street Greenwood Village, Colorado 80111 Greenwood Elementary School 5550 South Holly Street Greenwood Village, Colorado 80111 Year Opened 1958 Current Square Footage 50,504 Site Acreage 8.53 greenwood.cherrycreekschools.org $220,720 Electrical

More information

VOTER BOND REFERENDUM 2018 SUMMARY OF WORK PROPOSED

VOTER BOND REFERENDUM 2018 SUMMARY OF WORK PROPOSED Ashton Elementary School 1 Masonry Repair $ 42,781.50 2 Replace HVAC $ 375,000.00 3 Replace SAT @ Various Locations $ 92,364.00 3 Recoat & Resurface Exterior Paved Play Area $ 135,978.30 3 Various Technological

More information

Forest Hills Facilities Plan

Forest Hills Facilities Plan Forest Hills Facilities Plan Extensive updates to 8 of our 9 schools Replace Wilson Elementary Enhance learning environments across the district Build additional classrooms to accommodate gradual implementation

More information

MUKWONAGO AREA SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY

MUKWONAGO AREA SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY ARCHITECTURE ROLLING HILLS ELEMENTARY SCHOOL Rolling Hills Elementary was built in 1999 and is the newest addition to the Mukwonago Area School District. The building contains approximately 64,900 gross

More information

Briar Crest Elementary

Briar Crest Elementary Promises Kept This document includes partial lists of major projects completed at Pattonville Schools since 1986 as part of past bond issues approved by the Pattonville community. Briar Crest Elementary

More information

New High School Concept

New High School Concept Approved Bond Projects for Alamance-Burlington Schools In November 2018, Alamance County citizens approved a $150 million bond project proposal. Bond funds will pay to construct a new high school and provide

More information

2014 Bond Project Guide

2014 Bond Project Guide 2014 Bond Project Guide Bush Elementary School Page 1 Instructional Technology Computers, Projectors, Mobile Carts, Document Cameras and Printers Wireless Connectivity New Construction New Tech Center

More information

NEW ELEMENTARY SCHOOL AT THOMAS JEFFERSON MIDDLE SCHOOL

NEW ELEMENTARY SCHOOL AT THOMAS JEFFERSON MIDDLE SCHOOL JULY 27, 2016 NEW ELEMENTARY SCHOOL AT THOMAS JEFFERSON MIDDLE SCHOOL Joint BLPC - PFRC Meeting 1 Project Parameters 1. New Elementary School for the Henry Community 2. Support Strategic Plan Goal #4 Provide

More information

Master Project List Report

Master Project List Report Blue Hills Elementary School 01-8215 Site Utilities Replacement $52,835 01-8502 Modernization $3,135,933 01-8525 Exterior Painting $181,478 01-8552 Kindergarden Fencing $13,180 Install new backflow preventer.

More information

NASSAU COMMUNITY COLLEGE. Garden City, New York Capital Committee Meeting January 12, :00 PM

NASSAU COMMUNITY COLLEGE. Garden City, New York Capital Committee Meeting January 12, :00 PM NASSAU COMMUNITY COLLEGE Garden City, New York 11530 Capital Committee Meeting January 12, 2016 5:00 PM 1. Review and Approval of December 8, 2015 minutes: Chair: Do I have a motion to approve the minutes

More information

Meadow Point Elementary School East Grand Avenue Aurora, Colorado 80015

Meadow Point Elementary School East Grand Avenue Aurora, Colorado 80015 Meadow Point Elementary School 17901 East Grand Avenue Aurora, Colorado 80015 Year Opened 1982 Current Square Footage 53,100 Site Acreage 7.48 meadowpoint.cherrycreekschools.org $2,081,600 Electrical system,

More information

Doing Business with Bartlett Cocke General Contractors

Doing Business with Bartlett Cocke General Contractors Doing Business with Bartlett Cocke General Contractors FACTS 59 5 580 $ 700 YEARS OFFICES STATEWIDE EMPLOYEES MILLION IN REVENUE Established in 1959 by Bartlett Cocke, Jr. San Antonio (headquarters) Austin

More information

NYACK PUBLIC SCHOOLS CAPITAL IMPROVEMENT PLANNING PROCESS

NYACK PUBLIC SCHOOLS CAPITAL IMPROVEMENT PLANNING PROCESS NYACK PUBLIC SCHOOLS CAPITAL IMPROVEMENT PLANNING PROCESS DECEMBER 3, 2013 KEY QUESTIONS 1. What is the time sequence for available funding? (In what years will the funding be available?) 2. What is the

More information

7/14/2016 CITY HALL ADA ENHANCEMENT/REMODEL ACTION PLAN 1978 Construction

7/14/2016 CITY HALL ADA ENHANCEMENT/REMODEL ACTION PLAN 1978 Construction CITY HALL ADA ENHANCEMENT/REMODEL 2016 ACTION PLAN 1978 Construction 1 HISTORY At the February 2, 2016 Council Workshop Council Motions included: The direction to staff to move forward with the City Hall

More information

Grand River Ravines Georgetown Township

Grand River Ravines Georgetown Township Grand River Ravines Georgetown Township Project Description: The Grand River Ravines County Park property is composed of the 68-acre former Fillmore at the Bend Open Space purchased in 1999 and two more

More information

NAZARETH AREA SCHOOL DISTRICT MAINTENANCE DEPARTMENT 357 Tatamy Road, Nazareth, PA FAX

NAZARETH AREA SCHOOL DISTRICT MAINTENANCE DEPARTMENT 357 Tatamy Road, Nazareth, PA FAX NAZARETH AREA SCHOOL DISTRICT MAINTENANCE DEPARTMENT 357 Tatamy Road, Nazareth, PA 18064 610-759-1367 FAX 610-759-7028 TO: FROM: Dr. Riker, Superintendent of Schools Board of School Directors Lewis F.

More information

Exhibit CC BALTIMORE COUNTY PUBLIC SCHOOLS

Exhibit CC BALTIMORE COUNTY PUBLIC SCHOOLS Exhibit CC BALTIMORE COUNTY PUBLIC SCHOOLS DATE: July 10, 2007 TO: FROM: SUBJECT: ORIGINATOR: RESOURCE PERSON(S): BOARD OF EDUCATION Dr. Joe A. Hairston, Superintendent ABBREVIATED FACILITY STATUS REPORT

More information

SCO # 1 & 2 PUNCLH LIST Project Name: VANCLEAVE UPPER ELEMENTARY CLA#: 13003

SCO # 1 & 2 PUNCLH LIST Project Name: VANCLEAVE UPPER ELEMENTARY CLA#: 13003 SCO # 1 & 2 PUNCLH LIST Project Name: VANCLEAVE UPPER ELEMENTARY CLA#: 13003 No. Discipline Sent to Name Item Date Noted Date Resolved How item was resolved SCO # 1Punch listed items were noted below on

More information

Brown University Revised June 29, 2012 Facilities Design & Construction Standards SECTION ELECTRICAL DESIGN CRITERIA

Brown University Revised June 29, 2012 Facilities Design & Construction Standards SECTION ELECTRICAL DESIGN CRITERIA PART 1 - GENERAL 1.1 Background SECTION 26 00 10- ELECTRICAL DESIGN CRITERIA A. Brown University maintains it own campus electrical distribution system which serves the majority of the buildings and facilities

More information

Proposed Bond Construction Projects

Proposed Bond Construction Projects Proposed Bond Construction Projects The Facility Planning Process * September, 2006: - Board of Education established the Facilities and Asset Review Committee with the responsibility to evaluate all district

More information

TIFT COUNTY SCHOOLS E-SPLOST HISTORY

TIFT COUNTY SCHOOLS E-SPLOST HISTORY TIFT COUNTY SCHOOLS E-SPLOST HISTORY July 1, 1997 June 30, 2002 $28,766,187.16 collected July 1, 2002 June 30, 2007 $39,025,830.10 collected July 1, 2007 June 30, 2012 $41,886,155.46 collected July 1,

More information

Oxford Hills School District Capital Renewal Plan Updated March 2017

Oxford Hills School District Capital Renewal Plan Updated March 2017 Color Coding Guide Recently Completed In Progress FY 2017 Budget in FY 2018 Future Budgets/Projects 3/20/17 Capital Renewal Plan Updated March 2017 Capital Renewal Plan - Harrison Elementary Harrison add

More information

Alessandro Volta Elementary School

Alessandro Volta Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Master Facility Planning Update School Board Meeting May 26, 2016

Master Facility Planning Update School Board Meeting May 26, 2016 Master Facility Planning Update School Board Meeting May 26, 2016 Master Facilities Committee Overview Reflection of Committee Work Review of District Wide Facility Issues Identified District Wide Facility

More information

Sagebrush Elementary School East Temple Place Aurora, Colorado 80015

Sagebrush Elementary School East Temple Place Aurora, Colorado 80015 Sagebrush Elementary School 14700 East Temple Place Aurora, Colorado 80015 Year Opened 1977 Current Square Footage 57,100 Site Acreage 7.66 sagebrush.cherrycreekschools.org Asphalt and concrete work; electrical

More information

Springpoint Architects, pc SECTION Childcare Center Architect s Project No TABLE OF CONTENTS Monroe County Comm. Sch. Corp.

Springpoint Architects, pc SECTION Childcare Center Architect s Project No TABLE OF CONTENTS Monroe County Comm. Sch. Corp. Volume 1 Bidding Requirements, Contract Forms, Conditions of the Contract, Division 1, Architectural and Site Specifications 000107 Certification Page 000110 Table of Contents DIV00 PROCUREMENT AND CONTRACTING

More information

RE: Clark East Tower Renovations DATE: November 16, 2015 Ypsilanti, Michigan

RE: Clark East Tower Renovations DATE: November 16, 2015 Ypsilanti, Michigan ADDENDUM NO. 2 RE: Clark East Tower Renovations DATE: November 16, 2015 Ypsilanti, Michigan TO: All Bidders Gentlemen: You are hereby directed to make the following changes in the Project Manual and/or

More information

ROSLINDALE BRANCH, BPL COMMUNITY PRESENTATION #2 MARTIN J. WALSH, MAYOR CITY OF BOSTON PUBLIC FACILITIES DEPARTMENT 02/07/2018

ROSLINDALE BRANCH, BPL COMMUNITY PRESENTATION #2 MARTIN J. WALSH, MAYOR CITY OF BOSTON PUBLIC FACILITIES DEPARTMENT 02/07/2018 ROSLINDALE BRANCH, BPL COMMUNITY PRESENTATION #2 MARTIN J. WALSH, MAYOR CITY OF BOSTON PUBLIC FACILITIES DEPARTMENT 02/07/2018 MEETING AGENDA TEAM & GOALS ENTRY DESIGN PROGRESS INTERIOR PLAN DESIGN PROGRESS

More information

Town of Yucca Valley Capital Improvement Projects Report July 24, 2014

Town of Yucca Valley Capital Improvement Projects Report July 24, 2014 Town of Yucca Valley Capital Improvement Projects Report July 24, 2014 SR 62 Traffic and Pedestrian Improvements from Apache Trail to Palm Avenue (PLHD) The project includes construction of curbs, gutters,

More information

Chariho Regional School District Five-Year Capital Facilities Improvement Plan (2/10/15)

Chariho Regional School District Five-Year Capital Facilities Improvement Plan (2/10/15) Chariho Regional School District Five-Year Capital Facilities Improvement Plan (2/10/15) School/Department FY 16 FY 17 FY18 FY19 FY20 Chariho Regional High School FY 16 FY 17 FY18 FY19 FY20 *Repair Bleachers

More information

Richard Henry Lee Elementary School

Richard Henry Lee Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

startup. Construction of contractor entrance off University City Blvd connecting to Lot 8 has started.

startup. Construction of contractor entrance off University City Blvd connecting to Lot 8 has started. Campus Construction Situation Report #6 March 15, 2012 Hechenbleikner Lake Dam No change from previous notice Dewatering maintenance continues. Major construction activity will begin mid April and with

More information

Old Jail HVAC Replacement Feasibility Report

Old Jail HVAC Replacement Feasibility Report Old Jail HVAC Replacement Feasibility Report Madera, CA Prepared by Kitchell for the County of Madera, California Job No. 6168A3 Executive Summary On October 21, 2016, Kitchell conducted a Feasibility

More information

MASTER PLAN DIAGRAMS DISTRICT CAMPUS OVERVIEW

MASTER PLAN DIAGRAMS DISTRICT CAMPUS OVERVIEW DISTRICT CAMPUS OVERVIEW Classrooms, CR Special Education Computer Lab INTERSTATE 5 FW - Faculty Work, FL - Faculty Physical Education / Athletics Support Spaces S - Storage, T - Toilets, U - Utility,

More information

Fall 2017 Construction Update

Fall 2017 Construction Update Fall 2017 Construction Update Ward 4 Southeast Engineering Department Riverwalk Red Multi-Use Trail Bridge Rehabilitation The Riverwalk Red Multi Use Trail Bridge was awarded to Cramer and Associates,

More information

Appendix B. Facilities Assessment Report

Appendix B. Facilities Assessment Report Mile Lane Army Reserve Center Redevelopment Plan September 2008 Appendix B Facilities Assessment Report RKG Associates, Inc. Mile Lane Army Reserve Base Middletown, CT MEP System Evaluation For RKG Associates

More information

SCHEMATIC DESIGN PRESENTATION

SCHEMATIC DESIGN PRESENTATION August 5, 2014 SCHEMATIC DESIGN PRESENTATION ADDITIONS & RENOVATIONS Greenville Independent School District Acknowledgments 2 Narrative 3-6 Crockett Elementary School 7-12 L.P. Waters Early Childhood Center

More information

WESTERN ILLINOIS UNIVERSITY

WESTERN ILLINOIS UNIVERSITY WESTERN ILLINOIS UNIVERSITY Quad Cities Riverfront Campus Master Plan March 1, 2006 Preliminary Master Plan Total Site Build Out Western Illinois University Quad Cities Municipal Park Mississippi River

More information

Garfield Elementary School Feasibility Study for New Library Building Project Number A C

Garfield Elementary School Feasibility Study for New Library Building Project Number A C Larry Teixeira Selma Unified School District 3036 Thompson Avenue Selma, CA 93662 Subject: Feasibility Study for New Library Building Project Number A 12-8581.00 C Dear Mr. Teixeira: At your request, we

More information

Encumbered Balance (E-D) Branham HVAC Implementation Complete 100% 03/04/19 07/19/19 $765, $635, $635, $130, $0.

Encumbered Balance (E-D) Branham HVAC Implementation Complete 100% 03/04/19 07/19/19 $765, $635, $635, $130, $0. Branham High School Budget Remaining 1 906030 Branham HVAC Implementation Complete 100% 03/04/19 07/19/19 $765,473.00 $635,342.00 $635,342.00 $130,131.00 $0.00 2 970205 Branham Interim Housing - 12 Portable

More information

Francis M McKay Elementary School

Francis M McKay Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

The Van Ness Campus. Weekly Construction Bulletin #259

The Van Ness Campus. Weekly Construction Bulletin #259 The Van Ness Campus Weekly Construction Bulletin #259 Construction Update Week of September 24, 2018 The Van Ness Campus Weekly Bulletins are intended to help inform members of the community about upcoming

More information

Warren County Schools Plant and Operations

Warren County Schools Plant and Operations Warren County Schools Plant and Operations Buildings/Facilities/Energy Strategic Plan September 28, 2017 (Updated January 18, 2018) Donnie Caldwell; Facilities Director One Team, One Goal, High Levels

More information

Electrical Inspection Special Electrical

Electrical Inspection Special Electrical 0941 Fire Alarm System Devices, panels, wiring, conduit, etc. The present fire alarm system manufactured by Gamewell was installed with the 1982 renovation. It is a non addressable, zoned system. It includes

More information

Rt. 29 Solutions Project Delivery Advisory Panel. January 7, 2016

Rt. 29 Solutions Project Delivery Advisory Panel. January 7, 2016 Rt. 29 Solutions Project Delivery Advisory Panel January 7, 2016 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Dec

More information

3. 21st Century Learning A. Districtwide Flexible Learning - Allowance for Flexible Furniture $600,000 Subtotal $600,000

3. 21st Century Learning A. Districtwide Flexible Learning - Allowance for Flexible Furniture $600,000 Subtotal $600,000 1. Safety and Security A. Additional Cameras District Wide $382,000 B. Interior Locks Upgrades Allowance $300,000 C. Tilden Entrance Upgrades D. Door and Glass Improvements Allowance $500,000 E. Alert

More information

campus master plan VIRGINIA STATE UNIVERSITY

campus master plan VIRGINIA STATE UNIVERSITY campus master plan VIRGINIA STATE UNIVERSITY agenda 01 INTRODUCTION & GENERAL OVERVIEW 02 03 04 LAND USE CONCEPT PROGRAM ACCOMMODATION MAXIMIZE EXISTING INFRASTRUCTURE SUMMARY AND NEXT 05 STEPS agenda

More information

Draft. Security Study. Germantown School District Germantown, WI. PRA Project # February 2014

Draft. Security Study. Germantown School District Germantown, WI. PRA Project # February 2014 Draft Security Study Germantown School District Germantown, WI PRA Project # 114440 February 2014 February 2014 Germantown School District Facilities Security Study Page 1 Facilities Security Study Page

More information

DeWitt Clinton Elementary School

DeWitt Clinton Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Ichabod Crane Central School District 2018 Capital Project Preliminary Estimate

Ichabod Crane Central School District 2018 Capital Project Preliminary Estimate Health & Safety 1,399,000 Academics & Program 17,140,800 Physical Education & Athletics 5,922,000 Building Infrastructure 3,103,800 Site Infrastructure 1,049,600 TOTAL SCOPE OF WORK 28,615,200 PROPOSED

More information

Campus Middle School 4785 South Dayton Street Greenwood Village, Colorado 80111

Campus Middle School 4785 South Dayton Street Greenwood Village, Colorado 80111 Campus Middle School 4785 South Dayton Street Greenwood Village, Colorado 80111 Year Opened 1971 Current Square Footage 175,743 Site Acreage (included in CCHS) 87.22 campus.cherrycreekschools.org $2,441,170

More information

PLATTEVILLE MIDDLE SCHOOL

PLATTEVILLE MIDDLE SCHOOL Architectural The building has aluminum clad wood awning windows in combination with aluminum fixed glass units. They appear to be exterior glazed with insulated glazing. See photo 2. Platteville Middle

More information

Downtown Redevelopment Project Update

Downtown Redevelopment Project Update Downtown Redevelopment Project Update The redevelopment project will begin the week of September 4, 2017. It is anticipated that construction will be approximately 565 days, depending on weather. 7-6-18

More information

Kerrville ISD has called for a bond election in the amount of $88,960,000 for November 6, 2018

Kerrville ISD has called for a bond election in the amount of $88,960,000 for November 6, 2018 Kerrville ISD has called for a bond election in the amount of $88,960,000 for November 6, 2018 WHAT IS A BOND ELECTION? Provide communities an opportunity to vote to give the Board of Trustees authority

More information

Arena Elementary School 314 Willow St. Arena, WI 53503

Arena Elementary School 314 Willow St. Arena, WI 53503 FACILITIES PLANNING STUDY RIVER VALLEY SCHOOL DISTRICT Arena Elementary School 314 Willow St. Arena, WI 53503 7 South Dewey Street Eau Claire, Wisconsin 54701 715.83.1605 sdsarch.com ARENA General Overview

More information

HOLUM EDUCATION CENTER. Architectural. January 13, 2014 DeForest Area School District

HOLUM EDUCATION CENTER. Architectural. January 13, 2014 DeForest Area School District HOLUM EDUCATION CENTER Architectural The existing building has approximately 41,823 square feet and sets on a lot about 4.14 acres in size. Parking lots are located along the east and west sides of the

More information

UAA School of Engineering Parking Garage Master Plan Amendment. 1. Purpose

UAA School of Engineering Parking Garage Master Plan Amendment. 1. Purpose UAA School of Engineering Parking Garage Master Plan Amendment 1. Purpose Since the UAA campus master plan was drafted in 2003, adopted in 2004, and amended in 2009 a number of significant changes regarding

More information

HISTORIC RESOURCES INVENTORY - BUILDING AND STRUCTURES. Please send completed form to: National Register and State Register Coordinator,

HISTORIC RESOURCES INVENTORY - BUILDING AND STRUCTURES. Please send completed form to: National Register and State Register Coordinator, HISTORIC RESOURCES INVENTORY - BUILDING AND STRUCTURES Please send completed form to: National Register and State Register Coordinator, Connecticut Commission State Historic on Culture Preservation & Tourism,

More information

Princeton Joint Unified School District Invitation for Bid Installation of District-Wide Lighting Occupancy Sensors

Princeton Joint Unified School District Invitation for Bid Installation of District-Wide Lighting Occupancy Sensors Princeton Joint Unified School District Invitation for Bid Installation of District-Wide Lighting Occupancy Sensors 1. SUMMARY AND BACKGROUND: Princeton Joint Unified School District located in Princeton

More information

Allisonville Elementary School Facilities Highlights Built: 1960 Last Major Renovation: 28 years ago Capacity: 650 Current Enrollment: 767

Allisonville Elementary School Facilities Highlights Built: 1960 Last Major Renovation: 28 years ago Capacity: 650 Current Enrollment: 767 Allisonville Elementary School Built: 1960 Last Major Renovation: 28 years ago Capacity: 650 Current Enrollment: 767 ADA improvements are Fire alarms need to be updated Playground equipment needs to be

More information

Calmeca Academy of Fine Arts and Dual Language

Calmeca Academy of Fine Arts and Dual Language Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

PALO ALTO HIGH SCHOOL Palo Alto Unified School District MEETING NOTES. DATE: 21 September Palo Alto HS Update

PALO ALTO HIGH SCHOOL Palo Alto Unified School District MEETING NOTES. DATE: 21 September Palo Alto HS Update PALO ALTO HIGH SCHOOL Palo Alto Unified School District MEETING NOTES DATE: 21 September 2010 SUBJECT: Landscape Subcommittee Meeting Palo Alto HS Update The purpose of the meeting was to update the Landscape

More information

WLAC Facilities Committee Meeting. September 18, 2017

WLAC Facilities Committee Meeting. September 18, 2017 Campus Program Report WLAC Facilities Committee Meeting September 18, 2017 Page 1 DSA approved the plans on May 15, 2017. Notice to Proceed was issued June 8, 2017 and the project remains on schedule for

More information

SCHOOL DISTRICT PALM BEACH COUNTY BUILDING DEPARTMENT PLAN REVIEW CHECK LIST -- ELECTRICAL

SCHOOL DISTRICT PALM BEACH COUNTY BUILDING DEPARTMENT PLAN REVIEW CHECK LIST -- ELECTRICAL SCHOOL DISTRICT PALM BEACH COUNTY BUILDING DEPARTMENT PLAN REVIEW CHECK LIST -- ELECTRICAL 3300 SUMMIT BOULEVARD WEST PALM BEACH, FLORIDA 33406 TEL (561) 688-7687 FAX (561) 688-7654 http://www.palmbeach.k12.fl.us/fm/bd/index.htm

More information

WESTERN ILLINOIS UNIVERSITY

WESTERN ILLINOIS UNIVERSITY WESTERN ILLINOIS UNIVERSITY Quad Cities Riverfront Campus Preliminary Master Plan Presentation 2 February 1, 2006 Achieving Future Flexibility 1. Monitor space needs as the new buildings come on line and

More information

Electrical Inspection Special Electrical

Electrical Inspection Special Electrical 0941 Fire Alarm System Devices, panels, wiring, conduit, etc. Description of the building system The school is equipped with a hard wired fire alarm control panel, and automatic dialer. The fire alarm

More information

John Palmer Elementary School

John Palmer Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

LAMPETER-STRASBURG SCHOOL DISTRICT Lampeter, Pennsylvania 17537

LAMPETER-STRASBURG SCHOOL DISTRICT Lampeter, Pennsylvania 17537 LAMPETER-STRASBURG SCHOOL DISTRICT Lampeter, Pennsylvania 17537 Buildings and Grounds Committee Minutes March 20, 2017 The meeting was called to order at 6:30 p.m. PRESENT: Board Members, Mr. Jeffrey A.

More information

CAPITAL OUTLAY REQUEST - IDENTIFIED AND EMERGING PROJECTS - RANKED 3-Jun-14

CAPITAL OUTLAY REQUEST - IDENTIFIED AND EMERGING PROJECTS - RANKED 3-Jun-14 2014-2015 CAPITAL OUTLAY REQUEST - IDENTIFIED AND EMERGING PROJECTS - RANKED 3-Jun-14 School Item Amount a. Classroom A/R (Increase CR capacity to 804, add l Resource and tutoring spaces needed. Teacher

More information

Riverview West Side Elementary 160 Isabel Avenue East

Riverview West Side Elementary 160 Isabel Avenue East 160 Isabel Avenue East Project Summary: At the center of Hispanic culture in St. Paul is Riverview Elementary - and it s truly the center of the West Side community. Our newly renovated location offers

More information

Intelligence Community Campus- Bethesda (ICC-B)

Intelligence Community Campus- Bethesda (ICC-B) Intelligence Community Campus- Bethesda (ICC-B) MNCPPC Presentation June 20, 2013 US Army Corps of Engineers 1 NCPC Informational Agenda ICC-B Project Opening Remarks Community Engagement ICC-B Development

More information

2 Main Office Building BLDG-955A Building Purpose Building Area Administration offices. Training room 7,610 SF Inspection Date August 16, 2016 Inspect

2 Main Office Building BLDG-955A Building Purpose Building Area Administration offices. Training room 7,610 SF Inspection Date August 16, 2016 Inspect 1 Site Summary Address 7200 Bluff Springs Road Austin, TX 78744 Number of Permanent Campus Facilities 2 Original Year of Construction 2014 Total Campus Building Area (combined) 25,314 SF Introduction The

More information

University of Wisconsin-Stevens Point REQUEST FOR ARCHITECTURAL & ENGINEERING DESIGN SERVICES NEALE RESIDENCE HALL RENOVATION PROJECT.

University of Wisconsin-Stevens Point REQUEST FOR ARCHITECTURAL & ENGINEERING DESIGN SERVICES NEALE RESIDENCE HALL RENOVATION PROJECT. University of Wisconsin-Stevens Point REQUEST FOR ARCHITECTURAL & ENGINEERING DESIGN SERVICES NEALE RESIDENCE HALL RENOVATION PROJECT January 2009 DSF Project # 09L2E TABLE OF CONTENTS PAGE Project Scope

More information

THE FOLGER SHAKESPEARE LIBRARY ANC 6B Meeting

THE FOLGER SHAKESPEARE LIBRARY ANC 6B Meeting THE FOLGER SHAKESPEARE LIBRARY ANC 6B Meeting 12 MARCH 2019 1 1. Honor the Folgers gift to the nation a majestic building and peerless collection by making the 1932 Paul Cret building all it can be for

More information

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( ) SAMUEL CLEMENS ADDITIONS & RENOVATIONS (10-30-2017) BUDGET - $ 72,000,000 2020 PROJECTED COMPLETION DATE ARCHITECT MARMON MOK GENERAL CONTRACTOR Bartlett Cocke CONSTRUCTION MGMT. AG CM 18% COMPLETE SAMUEL

More information

If the address on this form is different than the address of the building, submit a written explanation.

If the address on this form is different than the address of the building, submit a written explanation. ILLINOIS DEPARTMENT OF PUBLIC HEALTH AHERA THREE YEAR REINSPECTION ASBESTOS ABATEMENT PROGRAM SCHOOL INFORMATION FORM SECTION I NAME OF SCHOOL DISTRICT: SCHOOL ID NUMBER: ADDRESS OF SCHOOL: CITY: CHICAGO

More information

2015 Building Condition Survey Summary Mosaic Associates Architects 02/19/16

2015 Building Condition Survey Summary Mosaic Associates Architects 02/19/16 1. General: This summary is offered as a supplement to the 2015 Building Condition Survey being filed with SED on behalf of the District. All cost estimates are preliminary, and should be re-evaluated

More information

Michigan State University Barrier-Free/Accessibility Project Status Summary March 2017

Michigan State University Barrier-Free/Accessibility Project Status Summary March 2017 Projects Completed FY14, FY15 and FY16 (arranged alphabetically) Abrams Planetarium Install automatic door opener on main doors of the Planetarium. Completed: Summer 2016 Cost: $13,000 Akers Hall Renovations

More information

Sidney Sawyer Elementary School

Sidney Sawyer Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Bringing the Community Together. TOWN SQUARE UPDATE November 1, 2017

Bringing the Community Together. TOWN SQUARE UPDATE November 1, 2017 Bringing the Community Together TOWN SQUARE UPDATE November 1, 2017 TOWN SQUARE COMMUNITY VISION The City currently owns 16.5 acres in downtown Boynton Beach which contains several historic structures

More information

Priorities. Public Communication & Transparency Website, CM Public Updates, Magic City Newsletter

Priorities. Public Communication & Transparency Website, CM Public Updates, Magic City Newsletter Priorities Recognition & Thanks to public servant employees Public Communication & Transparency Website, CM Public Updates, Magic City Newsletter Citizen/Customer Service Fiscal Responsibility Flood Protection

More information

Agustin Lara Elementary Academy

Agustin Lara Elementary Academy Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Genevieve Melody Elementary School

Genevieve Melody Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Main Street Conversion Site

Main Street Conversion Site Main Street Conversion Site Borough of Brooklyn, New York Preliminary Presentation Park Expansion Design & Development Committee 13 September 2012 Michael Van Valkenburgh Associates, Inc. Landscape Architects,

More information

Attachment F. Campus Capital Needs Sales Surtax Funded Detail Report

Attachment F. Campus Capital Needs Sales Surtax Funded Detail Report Facility Attachment F Campus Capital Needs Sales Surtax Funded Detail Report Facilities Services 2700 Judge Fran Jamieson Way Viera, Florida 32940-6601 Condition Code Estimate Longleaf Elementary 1.78

More information

CHESAPEAKE CHILD DEVELOPMENT CENTER

CHESAPEAKE CHILD DEVELOPMENT CENTER Client: Chesapeake Energy Corporation Completion: May 2011 Scope: 60,000 sq. ft. Cost: Withheld at Owner s Request Awards: Citation Award, AIA Oklahoma; American Architecture Award, Chicago Atheaneum;

More information

Notice Basic Information Estimated Contract Value (USD) $100, (Not shown to suppliers) Reference Number Issuing Organization

Notice Basic Information Estimated Contract Value (USD) $100, (Not shown to suppliers) Reference Number Issuing Organization Notice Basic Information Estimated Contract Value (USD) $100,000.00 (Not shown to suppliers) Reference Number 0000204787 Issuing Organization Colorado Mesa University Owner Organization Colorado Mesa University

More information

Summer 2016 Summer 2017

Summer 2016 Summer 2017 Summer 2016 Summer 2017 Why? 4800kv transformer failure outside Thurston Hall Overview - This is the 4th and final phase of the large, complex multi year campus wide site utilities infrastructure upgrade

More information

DESIGN & CONSTRUCTION GUIDELINES

DESIGN & CONSTRUCTION GUIDELINES ADMINISTRATIVE SERVICES 4202 E. FOWLER AVENUE, FPC110 PHONE: (813) 974-2625 FACILITIES PLANNING & CONSTRUCTION TAMPA, FLORIDA 33620-7550 WEBSITE: USF.EDU/FPC DESIGN & CONSTRUCTION GUIDELINES DIVISION 21

More information

PROPOSED SCOPE OF WORK

PROPOSED SCOPE OF WORK WATERTOWN CITY SCHOOL DISTRICT SCHOOL AND COMMUNITY WORKING TOGETHER SMART SCHOOLS PROJECT PROPOSED SCOPE OF WORK BCA PROJECT NO. 2017-100 NOVEMBER 2, 2017 Prepared By: & 327 Mullin Street 2136 Five Mile

More information

Ashland School District Facility & Capacity Assessment Report 2005

Ashland School District Facility & Capacity Assessment Report 2005 Ashland School District Facility & Capacity Assessment Report 2005 Briscoe Elementary School (Closed Facility) Address: 265 N Main Street Area: 33,980 square feet Buildings: Original Building 1948 Music

More information

Capital Projects in and near Odenton Town Center

Capital Projects in and near Odenton Town Center Capital Projects in and near Odenton Town Center Map ID Anne Arundel County Department of Public Works This project provides for the design, right of way acquisition, and construction of approximately

More information

DEERFIELD SCHOOL DISTRICT REFERENDUM Committed to Excellence and Equity in Educating Our Students

DEERFIELD SCHOOL DISTRICT REFERENDUM Committed to Excellence and Equity in Educating Our Students DEERFIELD SCHOOL DISTRICT REFERENDUM Committed to Excellence and Equity in Educating Our Students FACILITY NEEDS THE CHALLENGE Deerfield Middle School/High School building has served the community for

More information

Expo Line Transit Project. Project Status Update Meeting West End Corridor Segment C

Expo Line Transit Project. Project Status Update Meeting West End Corridor Segment C Exposition Light Rail Transit Project Project Status Update Meeting West End Corridor Segment C Culver City Senior Center November 18, 2010 Phase 1 Project Description Phase 1 from Downtown Los Angeles

More information

Submitted to. Texas A&M University at Commerce The Texas A&M University System. Submitted by. Guanghua Wei Craig Campbell David Claridge Dan Turner

Submitted to. Texas A&M University at Commerce The Texas A&M University System. Submitted by. Guanghua Wei Craig Campbell David Claridge Dan Turner ESL-TR-99/12-09 Report of Energy Efficiency Study and Metering/Utilities Profile for Electricity Deregulation at the Texas A&M University at Commerce (TAMU-Commerce) Commerce, Texas Submitted to Texas

More information

Australian National University

Australian National University Study Item/ Area Acton Campus Precinct Building Nos. & Names Physics/Psychology DALEY Precinct 38 (Physics Building), 38A (Physics Link Building), 38B (Gravity Wave Building), 39 (Psychology Building)

More information

ACADEMY AREA CONCEPT PLAN

ACADEMY AREA CONCEPT PLAN ACADEMY AREA Strip ling C hape l Roa d CONCEPT PLAN 7 S2 U Stripling 52 ROADWAYS AND PARKING: ADVENTURE PLAYGROUND AND SPRAYGROUND: Current roadways follow existing drives. It is recommended that the Folds

More information

CITY OF INVER GROVE HEIGHTS A G E N D A CITY COUNCIL WORK SESSION June 3, :00 PM INVER GROVE HEIGHTS CITY HALL COUNCIL CHAMBERS

CITY OF INVER GROVE HEIGHTS A G E N D A CITY COUNCIL WORK SESSION June 3, :00 PM INVER GROVE HEIGHTS CITY HALL COUNCIL CHAMBERS CITY OF INVER GROVE HEIGHTS A G E N D A CITY COUNCIL WORK SESSION June 3, 2013 6:00 PM INVER GROVE HEIGHTS CITY HALL COUNCIL CHAMBERS 1. CALL TO ORDER Mayor Tourville 2. RENTAL REGULATIONS 3. FRONT YARD

More information