ROSLINDALE BRANCH, BPL COMMUNITY PRESENTATION #2 MARTIN J. WALSH, MAYOR CITY OF BOSTON PUBLIC FACILITIES DEPARTMENT 02/07/2018

Size: px
Start display at page:

Download "ROSLINDALE BRANCH, BPL COMMUNITY PRESENTATION #2 MARTIN J. WALSH, MAYOR CITY OF BOSTON PUBLIC FACILITIES DEPARTMENT 02/07/2018"

Transcription

1 ROSLINDALE BRANCH, BPL COMMUNITY PRESENTATION #2 MARTIN J. WALSH, MAYOR CITY OF BOSTON PUBLIC FACILITIES DEPARTMENT 02/07/2018

2 MEETING AGENDA TEAM & GOALS ENTRY DESIGN PROGRESS INTERIOR PLAN DESIGN PROGRESS LANDSCAPE DESIGN PROGRESS DISCUSSION 2

3 The Team Mayor s Office of Neighborhood Services City of Boston Public Facilities Department Boston Public Library Roslindale Library Community LEERS WEINZAPFEL ASSOCIATES 3

4 This word cloud was generated via Wordle.net using comments collected from the public and staff during Phase ii. The cloud gives greater prominence to the words that were used more frequently. BOSTON PUBLIC LIBRARY 4

5 GOALS ALIGN WITH BPL STRATEGIC VISION RESPECTFUL OF ORIGINAL ARCHITECTURE COLLABORATE WITH COMMUNITY MINDFUL ALLOCATION OF FUNDS 5

6 COMMUNITY FEEDBACK Counter seating at windows; comfortable furniture Community room with AV equipment, acoustics, and kitchen Address glare issue with dome windows Toys and computers for children s area; stroller parking Modular shelving, display cases Small meeting rooms and quiet spaces Storage space for Friends of the Roslindale Public Library Potential for future programming in basement Outdoor seating Bike racks Maker space Better exterior lighting Art installations / shows 6

7 ENTRY 7

8 SOUTH STREET SUBWAY ROSLINDALE COMMUNITY CENTER COMMUTER RAIL CORINTH STREET POPLAR STREET ADAMS PARK POST OFFICE WASHINGTON STREET CUMMINS HWY POPLAR STREET ROSLINDALE BRANCH LIBRARY EXISTING CONDITIONS 8

9 EXISTING CONDITIONS 9

10 EXISTING CONDITIONS 10

11 NEW ENTRY PRESENTED AT COMMUNITY MEETING #1 11

12 NEW ENTRY CONCEPT 12

13 VIEW OF NEW ENTRY 13

14 VIEW OF NEW ENTRY 14

15 VIEW OF NEW ENTRY 15

16 VIEW OF NEW ENTRY WITH BENCH 16

17 VIEW OF NEW ENTRY WITH BENCH 17

18 VIEW OF NEW ENTRY WITH BENCH 18

19 INTERIOR 19

20 STACKS & SEATING CENTRAL SERVICE ENCLOSED SPACES GARDEN LIBRARY STAFF SPACES N PLAN DIAGRAM PRESENTED AT COMMUNITY MEETING #1 20

21 STACKS & SEATING CENTRAL SERVICE ENCLOSED SPACES GARDEN LIBRARY STAFF SPACES HIGH SUN ANGLES MID SUN ANGLES LOW SUN ANGLES SECTION DIAGRAM PRESENTED AT COMMUNITY MEETING #1 21

22 POPLAR STREET ONE WAY STACKS & SEATING CENTRAL SERVICE ENCLOSED SPACES DRIVEWAY / SERVICE TERRACE / GARDEN GARDEN LIBRARY STAFF SPACES STUDY MECH. STUDY TRANSFORMER CHILDREN TEEN ADULT WASHINGTON STREET STORAGE SHED STAIR 1 CONFERENCE STROLLER PARKING CORRIDOR CENTRAL SERVICE POINT ENTRY VESTIBULE ENTRANCE DN STAFF TOILET STAFF CORRIDOR RESTROOM BRANCH LIBRARIAN VESTIBULE AV BOOK DROP STAFF LOUNGE CUSTODIAN OFFICE R STORAGE WORKROOM MEN'S RESTROOM JAN. WOMEN'S RESTROOM STAIR CORR. STOR. STAIR 2 READING ROOM STOR. KITCHENETTE COMMUNITY ROOM OVERALL PLAN 22

23 INTERIOR ET STACKS & SEATING CENTRAL SERVICE DRIVEWAY / SERVICE TERRACE / GARDEN ENCLOSED SPACES STUDY MECH. STUDY GARDEN TRANSFORMER CHILDREN TEEN ADULT LIBRARY STAFF SPACES WASHINGTON STREET STORAGE SHED STAIR 1 CONFERENCE STROLLER PARKING CORRIDOR CENTRAL SERVICE POINT ENTRY VESTIBULE ENTRANCE DN STAFF TOILET STAFF CORRIDOR RESTROOM BRANCH LIBRARIAN VESTIBULE AV BOOK DROP STAFF LOUNGE CUSTODIAN OFFICE R STORAGE WORKROOM MEN'S RESTROOM JAN. WOMEN'S RESTROOM STAIR CORR. STOR. STAIR 2 READING ROOM STOR. KITCHENETTE COMMUNITY ROOM INTERIOR PLAN 23

24 DRIVEWAY / SERVICE TERRACE / GARDEN STUDY MECH. STUDY TEEN CHILDREN ADULT TRANSFORMER CONFERENCE STROLLER PARKING CORRIDOR CENTRAL SERVICE POINT ENTRY VESTIBULE ENTRANCE DN STAFF CORRIDOR RESTROOM BRANCH LIBRARIAN VESTIBULE AV BOOK DROP WORKROOM STORAGE MEN'S JAN. WOMEN'S STOR. ADULTS 24 STOR.

25 DRIVEWAY / SERVICE TERRACE / GARDEN STUDY MECH. STUDY TEEN CHILDREN ADULT TRANSFORMER CONFERENCE STROLLER PARKING CORRIDOR CENTRAL SERVICE POINT ENTRY VESTIBULE ENTRANCE DN STAFF CORRIDOR RESTROOM BRANCH LIBRARIAN VESTIBULE AV BOOK DROP WORKROOM STORAGE MEN'S JAN. WOMEN'S STOR. TEENS 25 STOR.

26 DRIVEWAY / SERVICE TERRACE / GARDEN STUDY MECH. STUDY TEEN CHILDREN ADULT TRANSFORMER CONFERENCE STROLLER PARKING CORRIDOR CENTRAL SERVICE POINT ENTRY VESTIBULE ENTRANCE DN STAFF CORRIDOR RESTROOM BRANCH LIBRARIAN VESTIBULE AV BOOK DROP WORKROOM STORAGE MEN'S JAN. WOMEN'S STOR. CHILDREN 26 STOR.

27 CHILDRENS AREA - MAZE CONCEPT 27

28 CHILDREN ADULT TRANSFORMER STORAGE SHED STAIR 1 CONFERENCE STROLLER PARKING CORRIDOR CENTRAL SERVICE POINT ENTRY VESTIBULE ENTRANCE DN STAFF TOILET STAFF CORRIDOR RESTROOM BRANCH LIBRARIAN VESTIBULE AV BOOK DROP STAFF LOUNGE CUSTODIAN OFFICE R STORAGE WORKROOM MEN'S RESTROOM JAN. WOMEN'S RESTROOM STAIR CORR. STOR. STAIR 2 READING ROOM STOR. KITCHENETTE COMMUNITY ROOM ENCLOSED SPACES 28

29 LANDSCAPE 29

30 EXISTING SITE 30

31 POPLAR STREET ONE WAY PLANTING WOOD DECK / BENCHES PAVERS / CONCRETE CONCRETE DRIVEWAY / SERVICE TERRACE / GARDEN STUDY MECH. STUDY TRANSFORMER CHILDREN TEEN ADULT WASHINGTON STREET STORAGE SHED STAIR 1 CONFERENCE STROLLER PARKING CORRIDOR CENTRAL SERVICE POINT ENTRY VESTIBULE ENTRANCE DN STAFF TOILET STAFF CORRIDOR RESTROOM BRANCH LIBRARIAN VESTIBULE AV BOOK DROP STAFF LOUNGE CUSTODIAN OFFICE R STORAGE WORKROOM MEN'S RESTROOM JAN. WOMEN'S RESTROOM STAIR CORR. STOR. STAIR 2 READING ROOM STOR. KITCHENETTE COMMUNITY ROOM SITE PLAN & SITE MATERIALS 31

32 area (see images on p. 3) we would like to see something like the JP rea* BOSTON PUBLIC LIBRARY CITY OF BOSTON PUBLIC FACILITIES DEPARTMENT SITE MATERIAL OPTIONS 32

33 SITE MATERIAL OPTIONS 33

34 GROUND COVER & TREE SHRUBS WOOD DECK & BENCH PERFORATED SCREEN GARDEN / TERRACE AXON 34

35 EXISTING VIEW ALONG POPLAR STREET 35

36 PROPOSED VIEW ALONG POPLAR STREET 36

37 EXISTING VIEW ALONG PLANTER AND DRIVEWAY 37

38 PROPOSED VIEW ALONG PLANTER AND DRIVEWAY WITH SECTION CUT THROUGH TERRACE 38

39 SCHEDULE 39

40 The Schedule September October November December January February March April May June July August September October November December Programming Study Schematic Design Design Development Construction Document FF & E Advertise / Bidding / Contracts Community Meeting: 06/19/2013 Community Meeting: 07/31/2013 Community Meeting: 10/24/2013 Community Meeting 1 Community Meeting 2 Community Meeting 3 Community Meeting 4 Construction 40

41 Discussion THANK YOU bpl.org

LMS A NORTH BEACH BRANCH LIBRARY SCHEMATIC DESIGN IMAGES SAN FRANCISCO PUBLIC LIBRARY

LMS A NORTH BEACH BRANCH LIBRARY SCHEMATIC DESIGN IMAGES SAN FRANCISCO PUBLIC LIBRARY LMS A SAN FRANCISCO PUBLIC LIBRARY NORTH BEACH BRANCH LIBRARY IMAGES APRIL 2009 NORTH BEACH BRANCH LIBRARY SAN FRANCISCO, CA LEDDY MAYTUM STACY Architects NORTH BEACH BRANCH LIBRARY PROJECT BACKGROUND

More information

LINCOLN HIGH SCHOOL MODERNIZATION BEX IV COMMUNITY MEETING JUNE 23, 2016

LINCOLN HIGH SCHOOL MODERNIZATION BEX IV COMMUNITY MEETING JUNE 23, 2016 LINCOLN HIGH SCHOOL MODERNIZATION BEX IV COMMUNITY MEETING JUNE 23, 2016 PROJECT OVERVIEW PROJECT OVERVIEW + PRE-DESIGN BEGAN IN FALL OF 2015 + EXISTING CONDITIONS ANALYSIS + PROJECTED GROWTH IN HIGH SCHOOL

More information

Dudley Branch Library Renovations

Dudley Branch Library Renovations Dudley Branch Library Renovations Martin J. Walsh, Mayor Project #7084 City of Boston Public Facilities Department Utile, Inc. Architecture and Planning February 7, 2017 Meeting Agenda Introductions Project

More information

ATLANTA-FULTON PUBLIC LIBRARY SYSTEM CENTRAL LIBRARY RENOVATION

ATLANTA-FULTON PUBLIC LIBRARY SYSTEM CENTRAL LIBRARY RENOVATION ATLANTA-FULTON PUBLIC LIBRARY SYSTEM CENTRAL LIBRARY RENOVATION APRIL 11, 2018 VINES ARCHITECTURE AGENDA: CONCEPT DEVELOPMENT EXTERIOR PLAZA STRATEGY PLAN DISTRIBUTION CONCEPT DEVELOPMENT EMERGING PRINCIPLES

More information

Norwood Public Library Rendering

Norwood Public Library Rendering The new Norwood Public Library is based on a lot that is a few blocks south of Highway 145 (Main Street) in Norwood, Colorado at the intersection of Pine Street and San Miguel Street. It is owned by the

More information

Maplewood Memorial Library Building Program

Maplewood Memorial Library Building Program Maplewood Memorial Library Building Program 2015 1 The Maplewood Memorial Library builds community and enriches the quality of life throughout Maplewood by bringing together diverse people, information

More information

Johnson Street Bridge Public Realm Update

Johnson Street Bridge Public Realm Update Johnson Street Bridge Public Realm Update August 20, 2015 Background Johnson Street Bridge Replacement Project impacts a diverse range of stakeholders In addition to a new bridge, the project also includes

More information

Branch Capital Improvement Feasibility Update

Branch Capital Improvement Feasibility Update Branch Capital Improvement Feasibility Update Ocean View Mission Chinatown Work to date - Conducted a Survey Monkey Design charrettes for each branch Issue charrette findings Conceptual feasibility analysis

More information

Interior Finishes January 22, 2018

Interior Finishes January 22, 2018 Public Spaces 1st Floor Finishes Floor Tile Floor/Wall Tile Accent Lighting Auditorium Entry 3 Form Panels Stone Wood Ceilings Wood Study Stairs Carpet Casework Retail Dining Paint MAIN ENTRANCE STAGE

More information

Sacramento Public Library Authority

Sacramento Public Library Authority Sacramento Public Library Authority Sacramento Public Library Policies and Procedures Title: Signature-Gathering and Petitions Administrative Policy Department: Facilities Author: Don Tucker, Director

More information

Michigan State University Barrier-Free/Accessibility Project Status Summary March 2017

Michigan State University Barrier-Free/Accessibility Project Status Summary March 2017 Projects Completed FY14, FY15 and FY16 (arranged alphabetically) Abrams Planetarium Install automatic door opener on main doors of the Planetarium. Completed: Summer 2016 Cost: $13,000 Akers Hall Renovations

More information

ANU FACILITIES AND SERVICES SFITOUT INNOVATIONS O BUILDING. Final Sketch Plans 09 th December 2010

ANU FACILITIES AND SERVICES SFITOUT INNOVATIONS O BUILDING. Final Sketch Plans 09 th December 2010 ANU FACILITIES AND SERVICES SFITOUT INNOVATIONS O BUILDING Final Sketch Plans 09 th December 2010 OUTLINE Objective Process To Date Key Fitout Concepts Final Sketch Plans Design Concept 3D images Internal

More information

PLAN ELEMENTS WORKSHOP. April 5, 2016

PLAN ELEMENTS WORKSHOP. April 5, 2016 PLAN ELEMENTS WORKSHOP April 5, 2016 needs more housing. But there is no one-size fits-all solution. Every neighborhood has its own character. In some places, density is not only appropriate it is badly

More information

Binghamton University Construction SUMMER 2012 HIGHLIGHTS

Binghamton University Construction SUMMER 2012 HIGHLIGHTS Binghamton University Construction SUMMER 2012 HIGHLIGHTS Binghamton University Construction Summer 2012 Large and small construction projects were completed during the summer 2012 construction season.

More information

Renovation Project Presentation Public Meetings

Renovation Project Presentation Public Meetings Renovation Project Presentation Public Meetings SWBR Architects and Tappé Associates made a formal presentation to both the Board and Public in early February of a conceptual design of a proposed renovation

More information

PRINCE GEORGE LIBRARY NEW ENTRANCE REPORT Patricia Boulevard Prince George, BC V2L 3V9

PRINCE GEORGE LIBRARY NEW ENTRANCE REPORT Patricia Boulevard Prince George, BC V2L 3V9 #230 177 Victoria Street P rince George, BC V2L 5R8 Tel. (250) 564-7285 F ax. (250) 564-7286 1100 Patricia Boulevard Prince George, BC V2L 3V9 PRINCE GEORGE LIBRARY NEW ENTRANCE REPORT CITY OF PRINCE GEORGE

More information

New Central Library and City Council Chambers / Community Meeting Facility Schematic Design Update January 20, 2015

New Central Library and City Council Chambers / Community Meeting Facility Schematic Design Update January 20, 2015 New Central Library and City Council Chambers / Community Meeting Facility Schematic Design Update January 20, 2015 Project Goals Main Street Remains Boundaries Access Vehicular - Controlled Pedestrian

More information

BOULDER PUBLIC LIBRARY

BOULDER PUBLIC LIBRARY BOULDER PUBLIC LIBRARY UPDATED FACILITIES SUSTAINABILITY STUDY MAIN BUILDING. o r g 12 02 15 I) INTRODUCTION Executive Summary 5 II) BACKGROUND 2013 Capital Improvement Bond Scope 7 III) UPDATED FACILITIES

More information

Schematic Design Presentation December 15, 2006 David Smith

Schematic Design Presentation December 15, 2006 David Smith Schematic Design Presentation December 15, 2006 David Smith Overview Located in Lancaster, PA 65,000 square feet 4 stories, 3 above grade Architect of record is Philip Johnson-Alan Ritchie Architects Ground

More information

Jamie Li 513 Beacon Street, Apt #6 Boston, MA

Jamie Li 513 Beacon Street, Apt #6 Boston, MA Jamie Li 513 Beacon Street, Apt #6 Boston, MA 02215 jamie.li@the-bac.edu 617.595.3245 Education Boston Architectural College, Boston, MA Candidate for Master s of Architecture Program August 2012 - Present

More information

City of Guelph - Wilson Street Parkade / Wilson Street Reconstruction Proposed Project Schedule April 21,

City of Guelph - Wilson Street Parkade / Wilson Street Reconstruction Proposed Project Schedule April 21, City of Guelph - Wilson Street Parkade / Wilson Street Reconstruction Proposed Project Schedule April 21, 2016 2016 2017 Activity Date March April May June July August September October November December

More information

TABLE OF CONTENTS: PROJECT TEAM:

TABLE OF CONTENTS: PROJECT TEAM: TABLE OF CONTENTS: 1. AERIAL VIEW - PROPOSED DESIGN IN CCSP. LANDSCAPE PLAN - LEVEL 01 3. LANDSCAPE PLAN - LEVEL 0 4. CRYTAL DRIVE AND 3RD STREET OPEN SPACE 5. CRYTAL DRIVE AND 3RD STREET OPEN SPACE 6.

More information

TALLEY STREET ELEMENTARY SCHOOL CITY SCHOOLS OF DECATUR COMMUNITY PRESENTATION DECEMBER 6, 2017

TALLEY STREET ELEMENTARY SCHOOL CITY SCHOOLS OF DECATUR COMMUNITY PRESENTATION DECEMBER 6, 2017 TALLEY STREET ELEMENTARY SCHOOL CITY SCHOOLS OF DECATUR COMMUNITY PRESENTATION DECEMBER 6, 2017 AGENDA INTRODUCTIONS RECAP OF CONSTITUENT INPUT WHAT WE HEARD SITE PLAN PRECEDENT IDEAS WHERE WE ARE 06.23.17

More information

I-70/71 Innerbelt Project

I-70/71 Innerbelt Project I-70/71 Innerbelt Project Project Progress Meeting and Design Enhancement Update November 9, 2009 Ohio Department of Transportation MS Consultants MSI Design Overview of Presentation 1. Recap Recent Project

More information

ARCHITECTURAL REVIEW BOARD SUPPLEMENTAL PACKAGE 3402 PICO BLVD SANTA MONICA, CA APRIL 10, 2017

ARCHITECTURAL REVIEW BOARD SUPPLEMENTAL PACKAGE 3402 PICO BLVD SANTA MONICA, CA APRIL 10, 2017 ARCHITECTURAL REVIEW BOARD SUPPLEMENTAL PACKAGE 3402 PICO BLVD SANTA MONICA, CA 90405 S CENTINELA AVE (E) SIDEWALK 41 42 43 44 45 (E) EXTENT OF NEW FENCE 40 39 38 37 CALTRANS LOT PARKING 68 EXISTING SPACES

More information

PLACEMAKING & MOBILITY WORKSHOP. January 27, 2016

PLACEMAKING & MOBILITY WORKSHOP. January 27, 2016 PLACEMAKING & MOBILITY WORKSHOP January 27, 2016 Boston needs more housing. But there is no one-size fitsall solution. Every neighborhood has its own character. In some places, density is not only appropriate

More information

GENE FRIEND RECREATION CENTER Civic Design Review Concept Design DECEMBER14, 2015

GENE FRIEND RECREATION CENTER Civic Design Review Concept Design DECEMBER14, 2015 GENE FRIEND RECREATION CENTER Civic Design Review Concept Design DECEMBER14, 2015 GENE FRIEND URBAN CONTEXT GENE FRIEND SITE CHARACTERISTICS NEIGHBORHOOD: HOWARD STREET 6 TH STREET IMPROVEMENTS FOLSOM

More information

Oconomowoc Area School District Facility Construction Update August 25, 2017

Oconomowoc Area School District Facility Construction Update August 25, 2017 Oconomowoc Area School District Facility Construction Update August 25, 2017 IXONIA ELEMENTARY SCHOOL Ixonia Elementary is getting ready for the start of the new school year! Interior cleaning and classroom

More information

Planning Board Hearing October 20th, 2016

Planning Board Hearing October 20th, 2016 Planning Board Hearing October 0th, 06 Developer: Real Estate Management & Leasing: Architect: Transportation Engineers: Landscape Architect: Civil Engineer: THE ARSENAL PROJECT Planning Board AGENDA Introduction

More information

Montana Rail Link Park

Montana Rail Link Park Montana Rail Link Park Neighborhood Open House A Missoula Community Partnership WITH LEADERSHIP FROM THE FRANKLIN TO THE FORT & SOUTHGATE TRIANGLE NEIGHBORHOODS Sovereign Hope Church, (1919 North Ave.)

More information

Charles River Skate Park Project

Charles River Skate Park Project Charles River Skate Park Project East Cambridge Planning Team Meeting December 12, 2012, 7:00 p.m. 9:00 pm East End House Basement Meeting Room 105 Spring Street, East Cambridge, MA Mission To protect,

More information

RATTANAK LENG INTERIOR DESIGN PORTFOLIO

RATTANAK LENG INTERIOR DESIGN PORTFOLIO RATTANAK LENG INTERIOR DESIGN PORTFOLIO 1 2 GLOBAL OFFICE DESIGN EUREKA PALOUSE MAKER SPACE 3LACROSSE POP-UP MUSEUM 4 RESIDENTIAL DESIGN 5WINE RACK DESIGN 6 DRAWING GLOBAL OFFICE DESIGN Design Studio Project,

More information

PBK K-12 Bryan ISD Administration Building Bryan Independent School District \\ Bryan, Texas. Design Presentation.

PBK K-12 Bryan ISD Administration Building Bryan Independent School District \\ Bryan, Texas. Design Presentation. PBK K-12 Bryan ISD Administration Building Bryan Independent School District \\ Bryan, Texas Design Presentation November 7, 2016 ARCHITECTURE \\ ENGINEERING \\ PLANNING \\ TECHNOLOGY \\ FACILITY CONSULTING

More information

Sacramento Public Library Authority

Sacramento Public Library Authority Sacramento Public Library Authority February 25, 2016 Agenda Item 3.0: Architecture Plan for New Orangevale Library: Concept Presentation by Group 4 Architecture TO: FROM: RE: Sacramento Public Library

More information

MASTER PLAN DIAGRAMS DISTRICT CAMPUS OVERVIEW

MASTER PLAN DIAGRAMS DISTRICT CAMPUS OVERVIEW DISTRICT CAMPUS OVERVIEW Classrooms, CR Special Education Computer Lab INTERSTATE 5 FW - Faculty Work, FL - Faculty Physical Education / Athletics Support Spaces S - Storage, T - Toilets, U - Utility,

More information

MOBILITY35 AESTHETICS

MOBILITY35 AESTHETICS MOBILITY35 AESTHETICS Aesthetics Working Group 5 August 10, 2016 Review of AWG 4 Consensus on three concepts to go to public survey Additional input received: Shading/location of trellises important Vegetation

More information

PUBLIC BUILDING COMMISSION OF CHICAGO. Chinatown Branch Library

PUBLIC BUILDING COMMISSION OF CHICAGO. Chinatown Branch Library Library Services Teen space with technology workshops Financial Literacy Programs for adults and teens Science, technology, engineering & math (STEM) programs for middle school students and teens Ethnic

More information

FEBRUARY 2018 VISIONING STARK COUNTY DISTRICT LIBRARY JACKSON BRANCH

FEBRUARY 2018 VISIONING STARK COUNTY DISTRICT LIBRARY JACKSON BRANCH FEBRUARY 2018 VISIONING STARK COUNTY DISTRICT LIBRARY JACKSON BRANCH 2018 HBM Architects TABLE OF CONTENTS Mind Breaking Outreach Boards Building Making Appendix 2015 Visioning Book - Tween Work Session

More information

RHBL 7325 ENVIRONMENTAL ANALYSIS. By: Whitney Musick

RHBL 7325 ENVIRONMENTAL ANALYSIS. By: Whitney Musick RHBL 7325 ENVIRONMENTAL ANALYSIS By: Whitney Musick UALR s Ottenheimer Library Photo Credit: http://www.flickr.com/photos/30091470@n08/4565851613/ Background Description Ottenheimer Library is centrally

More information

Philip A. Ginsburg, General Manager Toks Ajike, Acting Planning and Capital Program Director

Philip A. Ginsburg, General Manager Toks Ajike, Acting Planning and Capital Program Director Date: March 7, 2018 To: Through: From: Subject: Recreation and Park Commission Capital Committee Philip A. Ginsburg, General Manager Toks Ajike, Acting Planning and Capital Program Director Dan Mauer,

More information

Cleaning Brief City Recital Hall

Cleaning Brief City Recital Hall Floor Areas Frequency Comment Ground Floor Administration Monday to Friday Administration should be cleaned on a daily basis Box Office Daily unless noted Clean floors - mop and/or vacuum Stage Door area

More information

Beaufort County Community College. Maintenance and House Keeping Plan

Beaufort County Community College. Maintenance and House Keeping Plan Beaufort County Community College Maintenance and House Keeping Plan Summary: The College s facility management is handled by the Maintenance Department. The Director of Plant and Maintenance Operations

More information

SMEDLEY TRACT MASTER SITE PLAN Draft Master Plan Presentation

SMEDLEY TRACT MASTER SITE PLAN Draft Master Plan Presentation SMEDLEY TRACT MASTER SITE PLAN Draft Master Plan Presentation Public Meeting #3 03.16.2010 Middletown Township, Pennsylvania MEETING AGENDA Project Schedule Site Analysis Site Concepts Draft Master Site

More information

G W C C GREENMOUNT WEST COMMUNITY CENTER GWCA - COMMUNITY CENTER. design recommendations

G W C C GREENMOUNT WEST COMMUNITY CENTER GWCA - COMMUNITY CENTER. design recommendations G W C C GREENMOUNT WEST COMMUNITY CENTER design recommendations GWCA - COMMUNITY CENTER PROGRAM SIDEWALK 1... ENTRANCE/EXIT A... MECHANICAL 2... LOBBY B... ELECTRICAL 1 3... RECEPTION C... MEN S TOILET

More information

Bloomington Housing Authority Outdoor/Yard/Patio Policy

Bloomington Housing Authority Outdoor/Yard/Patio Policy Bloomington Housing Authority Outdoor/Yard/Patio Policy Section I It is necessary to adopt reasonable regulations for the benefit and well-being of the housing complex and our Residents. Therefore, The

More information

ABOUT THE SITE CITY PLAN LOCATION:NOIDA,SEC-59

ABOUT THE SITE CITY PLAN LOCATION:NOIDA,SEC-59 ABOUT THE SITE CITY PLAN LOCATION:NOIDA,SEC-59 N ABOUT THE BUILDING Pearl Academy is a private higher education institute in India-offering undergraduate, postgraduate and diploma courses in design, fashion

More information

LIVE OAK LIBRARY ANNEX PROJECT COUNTY OF SANTA CRUZ. October 22, 2018 COMMUNITY MEETING #2

LIVE OAK LIBRARY ANNEX PROJECT COUNTY OF SANTA CRUZ. October 22, 2018 COMMUNITY MEETING #2 LIVE OAK LIBRARY ANNEX PROJECT COUNTY OF SANTA CRUZ October 22, 2018 COMMUNITY MEETING #2 Capitola Measure S Planned library Improvements in Capitola and Live Oak part of the 10-branch Santa Cruz Public

More information

LEASIDE UNITED CHURCH FEASIBILITY STUDY TORONTO, ONTARIO

LEASIDE UNITED CHURCH FEASIBILITY STUDY TORONTO, ONTARIO LEASIDE UNITED CHURCH FEASIBILITY STUDY TORONTO, ONTARIO Public Presentation October 21, 2018 11:30am Mission The Mission of Leaside United Church is to grow a caring and vibrant spiritual community that

More information

St. Elizabeths East - 5 Year Anticipated Use Plan

St. Elizabeths East - 5 Year Anticipated Use Plan Agenda 1. Introductions 2. St Elizabeths East Overview 3. Stage One Infrastructure Improvements 1. Role of the D.C. Department of General Services and D.C. Department of Transportation 2. DC Water Tower

More information

r.i.s.e demonstration center

r.i.s.e demonstration center r.i.s.e demonstration center washington, dc r.i.s.e. demonstration center site context R.I.S.E. Demonstration Center is the adaptive reuse of the historic St. Elizabeths East Chapel to create an interim

More information

Grand River Ravines Georgetown Township

Grand River Ravines Georgetown Township Grand River Ravines Georgetown Township Project Description: The Grand River Ravines County Park property is composed of the 68-acre former Fillmore at the Bend Open Space purchased in 1999 and two more

More information

New Webber Park Library. Community Meeting May 10, 2014

New Webber Park Library. Community Meeting May 10, 2014 New Webber Park Library Community Meeting May 10, 2014 New Webber Park Library Agenda Welcome and opening remarks Library visits summary Library Buildings exterior design considerations What s next New

More information

Future Proposed Development

Future Proposed Development Future Proposed Development on and around Link light rail s Capitol Hill Station Meeting September 24, 2012 Tonight s Agenda 6:00 pm Open House 6:30 pm Introductions Richard Conlin, City of Seattle Councilmember/Sound

More information

VISION PLAN PRESENTATION - SEPTEMBER 28, 2013

VISION PLAN PRESENTATION - SEPTEMBER 28, 2013 AREAS OF IMPROVEMENT E A POOL HOUSE POOL DECK B B MAIN BUILDING UPPER PLAZAS A D F G C MAJOR BLEACHERS DUGOUTS FIELD MAIN COURTYARD D REGGIE PARK C E SPORT COURT ADA RAMP H F G H TENNIS COURTS KITCHENETTE

More information

SOUTH LAKE TAHOE LINEAR PARK LANDSCAPE IMPROVEMENTS

SOUTH LAKE TAHOE LINEAR PARK LANDSCAPE IMPROVEMENTS SOUTH LAKE TAHOE LINEAR PARK LANDSCAPE IMPROVEMENTS JUNE 2012 Scope of Work for Linear Park Landscape Improvements Prepare conceptual landscape design with increased lawn areas, additional accent planting,

More information

Erin McCauley The Gateway Building

Erin McCauley The Gateway Building Erin McCauley The Gateway Building Schematic Lighting Design The Gateway Building Location Syracuse, NY SUNY ESF Campus Construction August 6, 2010-2012 Project Cost $28.3 Million Size 50,000 SF Sustainable

More information

CENTERS AND CORRIDORS

CENTERS AND CORRIDORS INITIAL DESIGN STANDARDS AND GUIDELINES for CENTERS AND CORRIDORS City of Spokane Planning Services Third Floor, City Hall 808 W. Spokane Falls Blvd. Spokane, WA 99201-3329 (509) 625-6300 www.spokaneplanning.org

More information

Conceptual Design. Main Street Enhancement and Extension Project. Bothell, Washington. June 11, 2009

Conceptual Design. Main Street Enhancement and Extension Project. Bothell, Washington. June 11, 2009 Conceptual Design Main Street Enhancement and Extension Project Bothell, Washington June 11, 2009 Berger/ABAM Engineers and Cascade Design Collaborative, Inc For Main Street Bothell to succeed it must

More information

WILLIAM & MARY CUSTODIAL TASK & FREQUENCY LIST. PUBLIC SPACE: ENTRANCES, LOBBIES, AND CORRIDORS Daily Weekly Monthly Quarterly Yearly

WILLIAM & MARY CUSTODIAL TASK & FREQUENCY LIST. PUBLIC SPACE: ENTRANCES, LOBBIES, AND CORRIDORS Daily Weekly Monthly Quarterly Yearly WILLIAM & MARY CUSTODIAL TASK & FREQUENCY LIST PUBLIC SPACE: ENTRANCES, LOBBIES, AND CORRIDORS Daily Weekly Monthly Quarterly Yearly Collect & properly dispose of recycling as needed Dust, or wipe all

More information

Architectural Review Board Report

Architectural Review Board Report Architectural Review Board Report To: From: CC: Subject: Architectural Review Board Architectural Review Board Meeting: May 21, 2018 Agenda Item: 8-A Grace Page, Senior Planner Stephanie Reich, AIA, LEED

More information

DITTMAR ROSSLYN ARLINGTON COUNTY, VIRGINIA

DITTMAR ROSSLYN ARLINGTON COUNTY, VIRGINIA JANUARY 8, 2019 CLIENT DITTMAR COMPANY 8321 OLD COURTHOUSE ROAD, #300 VIENNA, VA 22182 TEL: (703) 356-6900 SHEET INDEX SHEET NE SHEET TITLE L1.01 STREETSCAPE HARDSCAPE PLAN L1.02 LEVEL 6 ROOF HARDSCAPE

More information

Silver Creek Subdivision Public Park

Silver Creek Subdivision Public Park Silver Creek Subdivision Public Park Design Team: team80026 Munding Design Lead Consultant Gaia Designs Landscape Architect Wildrye Design Landscape Architect Akamai Design Civil Engineer introduction

More information

PUBLIC RIGHT-OF-WAY IN THIS CHAPTER PUBLIC REALM

PUBLIC RIGHT-OF-WAY IN THIS CHAPTER PUBLIC REALM PUBLIC RIGHT-OF-WAY This section provides design guidelines for improvements in the public right-of-way. The public right-of-way refers to streets, sidewalks, non-vehicular thoroughfares, parks and greenways

More information

Fall 2017 Construction Update

Fall 2017 Construction Update Fall 2017 Construction Update Ward 4 Southeast Engineering Department Riverwalk Red Multi-Use Trail Bridge Rehabilitation The Riverwalk Red Multi Use Trail Bridge was awarded to Cramer and Associates,

More information

Main Street Conversion Site

Main Street Conversion Site Main Street Conversion Site Borough of Brooklyn, New York Preliminary Presentation Park Expansion Design & Development Committee 13 September 2012 Michael Van Valkenburgh Associates, Inc. Landscape Architects,

More information

ZONING: C-1-T. PARKING PROVIDED On-Site Valet 51 On-Site Holman Dedicated 14 Off-Site Valet TOTAL 113. (Mechanical Lifts)

ZONING: C-1-T. PARKING PROVIDED On-Site Valet 51 On-Site Holman Dedicated 14 Off-Site Valet TOTAL 113. (Mechanical Lifts) BUILDING CODE ANALYSIS REFERENCE CODES 0 CALIFORNIA BUILDING CODE 0 INTERNATIONAL BUILDING CODE OCCUPANCY USE AND CLASSIFICATION SECTION 0 & THE PROPOSED BUILDING CONSISTS OF STORIES OF OVER STORY OF VALET

More information

City of San Juan Capistrano PROJECT PRESENTATION NORTHWEST OPEN SPACE COMMUNITY PARK (CIP 09209) March 22, 2016 FOR THE PROJECT PRESENTATION

City of San Juan Capistrano PROJECT PRESENTATION NORTHWEST OPEN SPACE COMMUNITY PARK (CIP 09209) March 22, 2016 FOR THE PROJECT PRESENTATION City of San Juan Capistrano PROJECT PRESENTATION PROJECT PRESENTATION FOR THE NORTHWEST OPEN SPACE COMMUNITY PARK (CIP 09209) PLANNING COMMISSION 1 PROCESS & OBJECTIVES A. Develop a new Concept Plan for

More information

SF REC & PARK STANYAN STREET IMPROVEMENT. Supervisor London Breed District 5. Project Manager Dan Mauer Recreation and Parks Department

SF REC & PARK STANYAN STREET IMPROVEMENT. Supervisor London Breed District 5. Project Manager Dan Mauer Recreation and Parks Department SF REC & PARK STANYAN STREET IMPROVEMENT COMMUNITY MEETING #3 THURSDAY, JANUARY 25 TH, 2018 Supervisor London Breed District 5 Project Manager Dan Mauer Recreation and Parks Department Design Team William

More information

East Midtown Greenway East 53 rd 61 st Street. Community Board 8 Project Introduction November 16, 2017

East Midtown Greenway East 53 rd 61 st Street. Community Board 8 Project Introduction November 16, 2017 East Midtown Greenway East 53 rd 61 st Street Community Board 8 Project Introduction November 16, 2017 Agenda Overview - Development of the East Midtown Waterfront Esplanade Current East Midtown Greenway

More information

Wayne State University

Wayne State University 5557 Cass Ave WSU Project #048-251652 Issued For Bids February 24, 2015 FTC&H Project Number Fishbeck, Thompson, Carr & Huber, Inc. Engineers Scientists Architects Constructors 39500 MacKenzie Drive, Suite

More information

DESIGN WORKSHOP. November 17, 2015

DESIGN WORKSHOP. November 17, 2015 DESIGN WORKSHOP November 17, 2015 needs more housing. But there is no one-size fits-all solution. Every neighborhood has its own character. In some places, density is not only appropriate it is badly -

More information

North Loop Paving. December 18th, Street Reconstruction Project. Forrest Hardy, Transportation Planner Minneapolis Public Works

North Loop Paving. December 18th, Street Reconstruction Project. Forrest Hardy, Transportation Planner Minneapolis Public Works CITY OF MINNEAPOLIS Street Reconstruction Project December 18th, 2017 Forrest Hardy, Transportation Planner Minneapolis Public Works Forrest.Hardy@MinneapolisMN.Gov (612) 673-5951 Adam Hayow, Project Engineer

More information

REPORT TO COUNCIL City of Sacramento

REPORT TO COUNCIL City of Sacramento REPORT TO COUNCIL City of Sacramento 915 I Street, Sacramento, CA 95814-2604' www.cityofsacramento.org CONSENT August 25, 2009 Honorable Mayor and Members of the City Council Title: Contract: Valley Hi

More information

AvalonBay Communities + BRIDGE Housing. Mission Housing Habitat for Humanity Pacific Union Development Corporation

AvalonBay Communities + BRIDGE Housing. Mission Housing Habitat for Humanity Pacific Union Development Corporation AvalonBay Communities + BRIDGE Housing Mission Housing Habitat for Humanity Pacific Union Development Corporation Tonight s Agenda Recap of discussion from last CAC meeting Updates on meetings with Stakeholders

More information

4/8/2015 Item #10D Page 1

4/8/2015 Item #10D Page 1 MEETING DATE: April 8, 2015 PREPARED BY: Christy Villa, Associate Civil Engineer DEPT. DIRECTOR: Glenn Pruim DEPARTMENT: Public Works CITY MANAGER: Larry Watt SUBJECT: NORTH COAST HIGHWAY 101 STREETSCAPE

More information

LELAND & VISITACION PARK COMMUNITY MEETING

LELAND & VISITACION PARK COMMUNITY MEETING LELAND & VISITACION PARK COMMUNITY MEETING July 16th, 2016 SAN FRANCISCO RECREATION AND PARK GLS LANDSCAPE ARCHITECTURE BAYSIDE DEVELOPMENT LLC MEETING OBJECTIVES 1. FEEDBACK ON LELAND / BAYSHORE CORNER

More information

CITY COUNCIL STAFF REPORT

CITY COUNCIL STAFF REPORT CITY COUNCIL STAFF REPORT TO: Honorable Mayor and City Council DATE: April 3, 2017 FROM: PREPARED BY: SUBJECT: Matthew Bronson, City Manager Gregory A. Ray, Public Works Director/City Engineer Kathy Petker,

More information

Subject: Expo Light Rail - Revision of the Terminus Station North Entrance Design

Subject: Expo Light Rail - Revision of the Terminus Station North Entrance Design Information Item Date: June 12, 2012 To: Mayor and City Council From: David Martin, Director, Planning & Community Development Martin Pastucha, Director, Public Works Kathryn Vernez, Deputy City Manager

More information

Town of Westport. Design Guidelines Development Committee Public Informational Presentation

Town of Westport. Design Guidelines Development Committee Public Informational Presentation Town of Westport Design Guidelines Development Committee Public Informational Presentation 12.18.2018 Introduction / Overview The Town of Westport s Design Guidelines have been developed to guide the appearance,

More information

WHY RECYCLING IS IMPORTANT TO BPS

WHY RECYCLING IS IMPORTANT TO BPS + Zero Waste Guide Rethink Reduce Reuse Repurpose Recycle Rot This guide outlines zero waste best practices, offers suggestions to increase recycling in your school, and builds zero waste and sustainability

More information

This Is The High Point Public Library Prior To Expansion

This Is The High Point Public Library Prior To Expansion This Is The High Point Public Library Prior To Expansion The Expansion Will Be Located In Our Courtyard And Will Expand All Three Floors, Adding 19,000 SF But First The Screen Wall Must Come Down Tearing

More information

Remi Mendoza City Planning Academy March 13, 2017

Remi Mendoza City Planning Academy March 13, 2017 Remi Mendoza City Planning Academy March 13, 2017 1 What is the General Plan? The 2030 General Plan 5-Year Update (2035 General Plan) Questions and Answers 2 Guidebook for development and growth Required

More information

Project Goal. RRRC Living Towns Planning Workshp. Town of Halifax Revitalization Project. Dynamic Planning & Management Duo: July 12, 2006

Project Goal. RRRC Living Towns Planning Workshp. Town of Halifax Revitalization Project. Dynamic Planning & Management Duo: July 12, 2006 Project Goal Town of Halifax Revitalization Project RRRC Living Towns Planning Workshp July 12, 2006 Town of Halifax Halifax County *** Revitalization Project Goal*** To create Economic Opportunity and

More information

NYC Department of Education

NYC Department of Education Asset: NEW UTRECHT AF - BROOKLYN, 1601 80 STREET, New York, 11214 Inspection Id Inspection Type Time In Last Edited SA : Architectural - Senior 2017-10-31 4:06 PM 2018-06-13 10:51 AM AA : Architectural

More information

NYC Department of Education

NYC Department of Education Architectural Inspection Building Assessment Survey 2017-2018 Asset: LEHMAN AF - BRONX, 3000 EAST TREMONT AVENUE, New York, 10461 Inspection Id Inspection Type Time In Last Edited SA : Architectural -

More information

Baggaley Drive, Horncastle, LN9 5GE 120,000 Call us today on

Baggaley Drive, Horncastle, LN9 5GE 120,000 Call us today on Baggaley Drive, Horncastle, LN9 5GE 120,000 Call us today on 01507 524 910 THINKING OF SELLING? If you are thinking of selling your home or just curious to discover the value of your property, Hunters

More information

HISTORIC SITE AND MONUMENT COMMISSION (HSMC) Instructions for Historical Markers, Monuments, and Public Art Application

HISTORIC SITE AND MONUMENT COMMISSION (HSMC) Instructions for Historical Markers, Monuments, and Public Art Application HISTORIC SITE AND MONUMENT COMMISSION (HSMC) Instructions for Historical Markers, Monuments, and Public Art Application This document is for information purposes only and does not need to be submitted

More information

Columns REF, RESPONSIBLE and COMPL TD are provided for your numbering, assignments and control. REF ISSUE RESPONSIBLE COMPL TD

Columns REF, RESPONSIBLE and COMPL TD are provided for your numbering, assignments and control. REF ISSUE RESPONSIBLE COMPL TD PREPARING FOR THE DESIGN OF YOUR SCHOOL CAPITAL PROJECT A Checklist of Issues March 2014, v.1 This document can be used in preparing the stakeholder team for decision-making and for documenting the input

More information

Portfolio. Portfolio. Interior Design. By Kinjal Ahalpara

Portfolio. Portfolio. Interior Design. By Kinjal Ahalpara Portfolio Interior Design Portfolio By Kinjal Ahalpara 0 Table of Contents 1 Restaurant Design project 2 2 Sales office design project for Westerfield retirement community apartments 3 Commercial Retail

More information

RPD GEORGE CHRISTOPHER PLAYGROUND COMMUNITY MEETING 1 SEPTEMBER 24, Duncan St

RPD GEORGE CHRISTOPHER PLAYGROUND COMMUNITY MEETING 1 SEPTEMBER 24, Duncan St RPD GEORGE CHRISTOPHER PLAYGROUND COMMUNITY MEETING 1 SEPTEMBER 24, 2015 Duncan St Supervisorial District 8 Supervisor Scott Wiener 1 Agenda Welcome & Introductions Purpose of Meeting Ground Rules Project

More information

The Auburn Plan Designing the Future of Auburn February 28, 2005

The Auburn Plan Designing the Future of Auburn February 28, 2005 The Auburn Plan Designing the Future of Auburn February 28, 2005 Block-by-Block Bicycle Tour Aerial survey Focus Group Meetings September 7 and 8 Design Workshops October 11, 14, and 21 Revitalization

More information

Kinzie Industrial Corridor

Kinzie Industrial Corridor Mayor Emanuel s Industrial Corridor Modernization Kinzie Industrial Corridor Fulton Market Innovation District Plan Implementation October 19, Rahm Emanuel, Mayor David Reifman, Commissioner Dept. of Planning

More information

SF REC & PARK STANYAN STREET IMPROVEMENT. Supervisor London Breed District 5. Project Manager Dan Mauer Recreation and Parks Department

SF REC & PARK STANYAN STREET IMPROVEMENT. Supervisor London Breed District 5. Project Manager Dan Mauer Recreation and Parks Department SF REC & PARK STANYAN STREET IMPROVEMENT PLANNING PRESENTATION WEDNESDAY, OCTOBER 19, 2016 Supervisor London Breed District 5 Project Manager Dan Mauer Recreation and Parks Department Design Team William

More information

Revitalizing Urban Main Streets

Revitalizing Urban Main Streets MIT OpenCourseWare http://ocw.mit.edu Spring 2009 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms. Team 1: Traffic/Pedestrian Activity/Public Transportation

More information

r.i.s.e demonstration center washington, dc project category: architecture

r.i.s.e demonstration center washington, dc project category: architecture r.i.s.e demonstration center washington, dc project category: architecture R.I.S.E. Demonstration Center is the adaptive reuse of the historic Chapel at St. Elizabeths East Campus to create an interim

More information

Coffey Neighborhood Park Master Plan/Design/Rebuild Workshop. August 4, :00pm 4:00pm

Coffey Neighborhood Park Master Plan/Design/Rebuild Workshop. August 4, :00pm 4:00pm Coffey Neighborhood Park Master Plan/Design/Rebuild Workshop August 4, 2018 2:00pm 4:00pm 1 Agenda Welcome/Introductions Neighborhood Meeting Goals Master Planning Process Coffey Park Amenities (pre-fire

More information

Design Review of Facility Improvement Projects

Design Review of Facility Improvement Projects Design Review of Facility Improvement Projects Agenda Board Meeting Schedule Scope of Work Summary Overall Building Plans and Scope Summary Update on Areas of Design Development Programming and Space planning

More information

36.1. PURPOSE APPLICABILITY DESIGN REVIEW GUIDELINES

36.1. PURPOSE APPLICABILITY DESIGN REVIEW GUIDELINES CHAPTER 36: DESIGN STANDARDS 36.1. PURPOSE The purpose of this chapter is to ensure that projects are designed and constructed consistent with the Community Design Subelement of the Land Use Element and

More information

Institutional Master Plan The Arnold Arboretum of Harvard University

Institutional Master Plan The Arnold Arboretum of Harvard University Institutional Master Plan The Arnold Arboretum of Harvard University Submitted to: Boston Redevelopment Authority One City Hall Square Boston, MA 02201 Submitted by: The Arnold Arboretum of Harvard University

More information

2100 PENNSYLVANIA AVENUE, NW Z.C. CASE NO O/06-12O PRE-HEARING SUBMISSION

2100 PENNSYLVANIA AVENUE, NW Z.C. CASE NO O/06-12O PRE-HEARING SUBMISSION 2100 PENNSYLVANIA AVENUE, NW Z.C. CASE NO. 06-11O/06-12O PRE-HEARING SUBMISSION July 28, 2017 LAND OWNER GEORGE WASHINGTON UNIVERSITY 2121 Eye Street, NW, Suite 701 Washington, DC 20052 T: 202 994 6600

More information