Avon Board of Education. Capital Improvement Plan Presentation to Board of Education October 17, 2017

Size: px
Start display at page:

Download "Avon Board of Education. Capital Improvement Plan Presentation to Board of Education October 17, 2017"

Transcription

1 Avon Board of Education Capital Improvement Plan Presentation to Board of Education October 17, 2017

2 AGENDA Summary of Requests HVAC Status Requests

3 Summary of Requests 1. District-Replacement BOE Truck 2002 $ 65, PGS Air Handling/RTU Replacement (PH II) $340, District-LED Light Replacement $120,000 TOTAL $525,000 Parking Lot Asphalt and Milling

4 Avon High School Type / # Install Date Age Service Life (years) Boiler (2) RTU s (20) RTU s (16) Water Heater (2) Avon Middle School Type / # Install Date Age Service Life(years) Boiler (2) RTU s (13) Thompson Brook School Type / # Install Date Age Service Life (years) Boiler (2) Chiller (1) AHU (7) FCU (57) Water Heater (1)

5 Pine Grove School Type / # Install Date Age Service Life (years) Boiler (2) Water Heater (1) Water Heater (1) HC Coils (18) Condensing Units (5) RTU s (4) Roaring Brook School Type / # Install Date Age Service Life (years) Boiler (2) RTU s (3) RTU s (11) RTU s (7) RTU s (1)

6 Summary of Requests 1. District Security Upgrades (PH I) $265, AHS Fire Alarm Replacement $130, AHS Air Handling/RTU Replacement (PH l) $240, District-LED Light Replacement (PH II) $100, District Field Mower Replacement $ 72, PGS-Water Boiler Replacement $ 25, DW Baseball Field Repair (PH I) $ 35, TBS Carpet Replacement $ 35,000 TOTAL $902,000

7 Security Upgrades (PH I) Install electronic locks on all exterior entrance doors (40) During a lockdown, all exterior doors can be can be secured immediately Terminated employees denied access to buildings If key card/fob lost/stolen, access is terminated without changing locks Lock system will be same as Town, facilitating access to First Responders Add visitor doors to AMS and AHS to control access Replace entrance doors at Central Office

8 AHS Fire Alarm Replacement Parts are no longer available for current system. Replace current Siemens system with Honeywell Systems, same as RBS, TBS, and AMS, as well as Town Buildings. Replacement to include upgrades such as panic buttons.

9 AHS Air Handling/RTU Replacement (PH l) Equipment Lifespan is 15 years Equipment age is 20 years (Installed 1998) Phase I Academic Wing $240,000 Phase II Gallery/Central Area $425,000 Phase III Gym/Cafeteria Area $425,000

10 DW - LED Lighting (PH II) Replacement of lights with more energy efficient LED lighting Eversource rebate available 10%-40% Future costs off set by rebates Project is coordinated with Town RBS completed this year Priority: AMS $100,000 AHS Out year TBS Out year PGS Out year

11 Field Mower Replacement The current mower is over 17 years old Requires extensive maintenance. Only District owned large mower Used to mow the athletic fields on a daily basis 3 seasons of the year.

12

13 PGS Water Boiler Replacement Equipment Lifespan is 20 years Equipment age is 27 years (Installed 1998) One of 2 boilers.

14 DW-Baseball Field Repairs (PH I) Requires extensive maintenance and reconditioning. Replace dugout benches Fields are used by High School and Rec teams. Phase I-High School Phase II Middle School

15 TBS - Carpet Replacement Removal/Replacement of worn carpet with tile Administration Office, Chorus Room, 5 classrooms Does not include asbestos abatement (unknown at this time)

16 Summary of Requests 1. District Security Upgrades (PH I) $265, AHS Fire Alarm Replacement $130, AHS Air Handling/RTU Replacement (PH l) $240, District-LED Light Replacement (PH II) $100, District Field Mower Replacement $ 72, PGS-Water Boiler Replacement $ 25, DW Baseball Field Repair (PH I) $ 35, TBS Carpet Replacement $ 35,000 TOTAL $902,000

School District of Milton 5- Year Capital Maintenance and Improvement Plan

School District of Milton 5- Year Capital Maintenance and Improvement Plan Updated - 02/21/17 School District of Milton 5- Year Capital Maintenance and Improvement Plan 101 East Elementary 1 Parking Lot/Traffic Flow Project 615,175 Includes Construction and Engineering 2 Bathroom

More information

5 Year Capital Improvement Plan Update

5 Year Capital Improvement Plan Update 5 Year Capital Improvement Plan Update Board Approved May 10, 2016 Collierville Schools Board of Education Wanda Chism Wright Cox Mark Hansen, Chairman Cathy Messerly Kevin Vaughan Superintendent John

More information

Master Facility Planning Update School Board Meeting May 26, 2016

Master Facility Planning Update School Board Meeting May 26, 2016 Master Facility Planning Update School Board Meeting May 26, 2016 Master Facilities Committee Overview Reflection of Committee Work Review of District Wide Facility Issues Identified District Wide Facility

More information

Kenmore Town of Tonawanda Union Free School District : Capital Improvement Project Phase 2

Kenmore Town of Tonawanda Union Free School District : Capital Improvement Project Phase 2 Kenmore Town of Tonawanda Union Free School District : Capital Improvement Project Phase 2 Adams Field Kenmore East High School Kenmore West High School Crosby Field Charles Lindbergh Elementary Thomas

More information

TIFT COUNTY SCHOOLS E-SPLOST HISTORY

TIFT COUNTY SCHOOLS E-SPLOST HISTORY TIFT COUNTY SCHOOLS E-SPLOST HISTORY July 1, 1997 June 30, 2002 $28,766,187.16 collected July 1, 2002 June 30, 2007 $39,025,830.10 collected July 1, 2007 June 30, 2012 $41,886,155.46 collected July 1,

More information

Binghamton University Construction SUMMER 2012 HIGHLIGHTS

Binghamton University Construction SUMMER 2012 HIGHLIGHTS Binghamton University Construction SUMMER 2012 HIGHLIGHTS Binghamton University Construction Summer 2012 Large and small construction projects were completed during the summer 2012 construction season.

More information

Board of Education Meeting

Board of Education Meeting Geneva Community Unit School District #304 Operations and Maintenance-Security 7 Year Capital Improvement Plans Board of Education Meeting December 8 th, 2014 O&M-Security 7 Year Capital Improvement Plans

More information

2014 Bond Project Guide

2014 Bond Project Guide 2014 Bond Project Guide Bush Elementary School Page 1 Instructional Technology Computers, Projectors, Mobile Carts, Document Cameras and Printers Wireless Connectivity New Construction New Tech Center

More information

Community Unit School District 200 Facilities

Community Unit School District 200 Facilities Community Unit School District 200 Facilities Committee of the Whole Presentation February 27, 2013 Community Unit School District 200 Facilities Update The purpose of this CUSD 200 Facilities update is

More information

2014 Bond District-wide Facility Repairs

2014 Bond District-wide Facility Repairs Elementary Schools Aloha-Huber Park Fire Detector upgrade Replace electric backboard winches in gym Heating/cooling system controls upgrade Barnes Replace exterior windows Heating/cooling system and controls

More information

Exhibit CC BALTIMORE COUNTY PUBLIC SCHOOLS

Exhibit CC BALTIMORE COUNTY PUBLIC SCHOOLS Exhibit CC BALTIMORE COUNTY PUBLIC SCHOOLS DATE: July 10, 2007 TO: FROM: SUBJECT: ORIGINATOR: RESOURCE PERSON(S): BOARD OF EDUCATION Dr. Joe A. Hairston, Superintendent ABBREVIATED FACILITY STATUS REPORT

More information

2014 Bond District-wide Facility Repairs

2014 Bond District-wide Facility Repairs Elementary Schools Aloha-Huber Park Fire Detector upgrade Replace electric backboard winches in gym Heating/cooling system controls upgrade Barnes Replace exterior windows Heating/cooling system and controls

More information

Madeira City Schools Madeira, Ohio. HVAC Assessment. December 2011 (Revised February 2012)

Madeira City Schools Madeira, Ohio. HVAC Assessment. December 2011 (Revised February 2012) Madeira City Schools Madeira, Ohio HVAC Assessment December 2011 (Revised February 2012) Prepared by: CMTA Engineering Consultants, Inc. 10411 Meeting Street Prospect, KY 40059 www.cmtaegrs.com (502) 326-3085

More information

Forest Hills Facilities Plan

Forest Hills Facilities Plan Forest Hills Facilities Plan Extensive updates to 8 of our 9 schools Replace Wilson Elementary Enhance learning environments across the district Build additional classrooms to accommodate gradual implementation

More information

3. 21st Century Learning A. Districtwide Flexible Learning - Allowance for Flexible Furniture $600,000 Subtotal $600,000

3. 21st Century Learning A. Districtwide Flexible Learning - Allowance for Flexible Furniture $600,000 Subtotal $600,000 1. Safety and Security A. Additional Cameras District Wide $382,000 B. Interior Locks Upgrades Allowance $300,000 C. Tilden Entrance Upgrades D. Door and Glass Improvements Allowance $500,000 E. Alert

More information

MUKWONAGO AREA SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY

MUKWONAGO AREA SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY ARCHITECTURE ROLLING HILLS ELEMENTARY SCHOOL Rolling Hills Elementary was built in 1999 and is the newest addition to the Mukwonago Area School District. The building contains approximately 64,900 gross

More information

Phase II: School Safety Report_ _15:42

Phase II: School Safety Report_ _15:42 Phase II: School Safety Report_10112017_15:42 Phase II: School Safety Report Timothy Underwood 2431 W. KY 10 Tollesboro, Kentucky, 41189 United States of America Target Completion Date: 10/12/2017 Last

More information

New High School Concept

New High School Concept Approved Bond Projects for Alamance-Burlington Schools In November 2018, Alamance County citizens approved a $150 million bond project proposal. Bond funds will pay to construct a new high school and provide

More information

Littleton Fields Master Plan

Littleton Fields Master Plan Town of Littleton Littleton Fields Master Plan September 25, 2017 Gale Associates, Inc. John M. Perry, P.E. Jeffrey F. Georges, MRLA About Gale Agenda Introduction and Purpose Background Investigation

More information

HVAC / Boilers / Hot Water. Expected Life Span. very rough estimates Condition/Issue Age. Athletics / Gyms

HVAC / Boilers / Hot Water. Expected Life Span. very rough estimates Condition/Issue Age. Athletics / Gyms $4,013,500.00 $4,013,500.00 $ 1,155,000.00 $ 1,000,000.00 $ 205,000.00 $ 275,000.00 $ 300,000.00 $ 360,000.00 $ 438,500.00 $ 280,000.00 School Status Item HS Boilers boiler controls replaced 2017 2002

More information

Greenwood Elementary School 5550 South Holly Street Greenwood Village, Colorado 80111

Greenwood Elementary School 5550 South Holly Street Greenwood Village, Colorado 80111 Greenwood Elementary School 5550 South Holly Street Greenwood Village, Colorado 80111 Year Opened 1958 Current Square Footage 50,504 Site Acreage 8.53 greenwood.cherrycreekschools.org $220,720 Electrical

More information

West Hartford Public School District

West Hartford Public School District West Hartford Public School District Agenda Item: Adoption of Capital Improvement Plan for 2018-19 Meeting Date: February 6, 2018 From: Through: Andy Morrow, Assistant Superintendent for Administration

More information

LAMPETER-STRASBURG SCHOOL DISTRICT Lampeter, Pennsylvania 17537

LAMPETER-STRASBURG SCHOOL DISTRICT Lampeter, Pennsylvania 17537 LAMPETER-STRASBURG SCHOOL DISTRICT Lampeter, Pennsylvania 17537 Buildings and Grounds Committee Minutes March 20, 2017 The meeting was called to order at 6:30 p.m. PRESENT: Board Members, Mr. Jeffrey A.

More information

REPORT CARD TO THE COMMUNITY MAY 15, 2018

REPORT CARD TO THE COMMUNITY MAY 15, 2018 REPORT CARD TO THE COMMUNITY MAY 15, 2018 O On May 10, 2014 voters in Greenville ISD approved a $72,275,000 bond election. BOND PROPOSAL PROJECT BOND AMOUNT CONSTRUCT A NEW BOWIE ELEMENTARY SCHOOL $17,600,000

More information

2015 Building Condition Survey Summary Mosaic Associates Architects 02/19/16

2015 Building Condition Survey Summary Mosaic Associates Architects 02/19/16 1. General: This summary is offered as a supplement to the 2015 Building Condition Survey being filed with SED on behalf of the District. All cost estimates are preliminary, and should be re-evaluated

More information

MUKWONAGO SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY

MUKWONAGO SCHOOL DISTRICT CAPITAL IMPROVEMENT / MAINTENANCE STUDY MUKWONAGO SCHOOL DISTRICT ARCHITECTURE PARK VIEW MIDDLE SCHOOL The original school building was dedicated in 1954 as the High School, with an addition in 1959, a library addition in 1970, and an addition/renovation

More information

Design Presentation. Chief Operations Officer Willie Burroughs

Design Presentation. Chief Operations Officer Willie Burroughs Design Presentation Chief Operations Officer Willie Burroughs Agenda Introduction Community Feedback Project updates 2 Feedback Citizens Advisory Committee meetings Growth and Development meetings Community

More information

Ichabod Crane Central School District 2018 Capital Project Preliminary Estimate

Ichabod Crane Central School District 2018 Capital Project Preliminary Estimate Health & Safety 1,399,000 Academics & Program 17,140,800 Physical Education & Athletics 5,922,000 Building Infrastructure 3,103,800 Site Infrastructure 1,049,600 TOTAL SCOPE OF WORK 28,615,200 PROPOSED

More information

Design Review of Facility Improvement Projects

Design Review of Facility Improvement Projects Design Review of Facility Improvement Projects Agenda Board Meeting Schedule Scope of Work Summary Overall Building Plans and Scope Summary Update on Areas of Design Development Programming and Space planning

More information

BOARD OF EDUCATION FIVE YEAR CAPITAL PLAN FY

BOARD OF EDUCATION FIVE YEAR CAPITAL PLAN FY BOARD OF EDUCATION FIVE YEAR CAPITAL PLAN FY 218-223 IPRIORITY GLASSIFICATION NARRATIVE CRITIGALiiProjects in this category are grouped due to the immediate or emergency needs in the district. This need

More information

Facilities Management Services

Facilities Management Services Facilities Management Services Operating Budget Facilities Management (FM) receives an Operating Budget each year predicated on funding the routine, predictable costs of cleaning, maintaining,, and repairing,

More information

VOTER BOND REFERENDUM 2018 SUMMARY OF WORK PROPOSED

VOTER BOND REFERENDUM 2018 SUMMARY OF WORK PROPOSED Ashton Elementary School 1 Masonry Repair $ 42,781.50 2 Replace HVAC $ 375,000.00 3 Replace SAT @ Various Locations $ 92,364.00 3 Recoat & Resurface Exterior Paved Play Area $ 135,978.30 3 Various Technological

More information

Oxford Hills School District Capital Renewal Plan Updated March 2017

Oxford Hills School District Capital Renewal Plan Updated March 2017 Color Coding Guide Recently Completed In Progress FY 2017 Budget in FY 2018 Future Budgets/Projects 3/20/17 Capital Renewal Plan Updated March 2017 Capital Renewal Plan - Harrison Elementary Harrison add

More information

HVAC 101. H V A C S y s t e m s

HVAC 101. H V A C S y s t e m s H V A C 1 0 1 S y s t e m s Introduction & Overview Should you care? Mechanical System Types Components & operation Popular Application Key Issues and Design Considerations System Comparisons First Cost

More information

Attachment F. Campus Capital Needs Sales Surtax Funded Detail Report

Attachment F. Campus Capital Needs Sales Surtax Funded Detail Report Facility Attachment F Campus Capital Needs Sales Surtax Funded Detail Report Facilities Services 2700 Judge Fran Jamieson Way Viera, Florida 32940-6601 Condition Code Estimate Williams Elementary 1.40

More information

Cherry Hill Public Schools BUILDING A SOLID FUTURE

Cherry Hill Public Schools BUILDING A SOLID FUTURE Cherry Hill Public Schools BUILDING A SOLID FUTURE Who We Are The Cherry Hill School District is the 12 th largest in the state, serving 11,500 students 19 Locations 2 High Schools, 3 Middle Schools, 12

More information

Mechanical Technical Report 1. ASHRAE Standard 62.1 Ventilation Compliance Evaluation

Mechanical Technical Report 1. ASHRAE Standard 62.1 Ventilation Compliance Evaluation Mechanical Technical Report 1 Standard 62.1 Ventilation Compliance Evaluation Lutheran Theological Seminary at Philadelphia The New Learning Center Prepared For: William P. Bahnfleth, Ph.D., P.E. Department

More information

RHCC Heating System Upgrade. Project Summary

RHCC Heating System Upgrade. Project Summary RHCC Heating System Upgrade Project Summary I. Boiler Replace current Smith Mills fuel oil fired boiler with a cascade system of three Buderus GB162 (290 MBH), Wall Hung, Gas Fired, Condensing Boilers.

More information

Design Standard. Thermal Systems (Chilled Water and Hot Water Systems) Detailed specifications follow. CHW AND HHW SUPPLY TEMPERATURE RESET

Design Standard. Thermal Systems (Chilled Water and Hot Water Systems) Detailed specifications follow. CHW AND HHW SUPPLY TEMPERATURE RESET Design Standard Detailed specifications follow. PART 1 CHW AND HHW SUPPLY TEMPERATURE RESET 1.1 The Utilities & Energy Services Department (UES) at Texas A&M University is actively identifying and implementing

More information

Briar Crest Elementary

Briar Crest Elementary Promises Kept This document includes partial lists of major projects completed at Pattonville Schools since 1986 as part of past bond issues approved by the Pattonville community. Briar Crest Elementary

More information

Service Description Service Shop Customer Charge Comments. Electronic Shop. Electric Shop Yes additional circuits for equipment

Service Description Service Shop Customer Charge Comments. Electronic Shop. Electric Shop Yes additional circuits for equipment Fire alarm repairs Electronic Shop Fire alarm sound level testing Electronic Shop Fire system inspections Electronic Shop Installation of additional fire detection/alarm/supression devices Electronic Shop

More information

NAZARETH AREA SCHOOL DISTRICT MAINTENANCE DEPARTMENT 357 Tatamy Road, Nazareth, PA FAX

NAZARETH AREA SCHOOL DISTRICT MAINTENANCE DEPARTMENT 357 Tatamy Road, Nazareth, PA FAX NAZARETH AREA SCHOOL DISTRICT MAINTENANCE DEPARTMENT 357 Tatamy Road, Nazareth, PA 18064 610-759-1367 FAX 610-759-7028 TO: FROM: Dr. Riker, Superintendent of Schools Board of School Directors Lewis F.

More information

Department of Facilities Management Division of Maintenance. The Division of Maintenance: Supporting Student Success

Department of Facilities Management Division of Maintenance. The Division of Maintenance: Supporting Student Success The : Supporting Student Success April 2013 1 PURPOSE Provide an overview of the Division of Maintenance, including - Mission and Functions Organization and Staffing Outline the various types of maintenance

More information

NARRATIVE REPORT. Engineering Administration was originally constructed in 1965; the building has had no major renovations.

NARRATIVE REPORT. Engineering Administration was originally constructed in 1965; the building has had no major renovations. NARRATIVE REPORT 1.0 BUILDING INFORMATION Engineering Administration was originally constructed in 1965; the building has had no major renovations. Engineering Administration is a three-story, 9,579 ft

More information

Existing Facilities Assessment

Existing Facilities Assessment DRAFT Patrick Henry Elementary School 4643 Taney Ave, Alexandria, VA 22304 Existing Facilities Assessment Alexandria City Public Schools Planning, Design & Construction Office 1340 Braddock Place Alexandria,

More information

Safety & Security Updates and Training. December 21, 2017

Safety & Security Updates and Training. December 21, 2017 Strong Schools Strong Community Safety & Security Updates and Training December 21, 2017 WPS Safety & Security Team Members Members of the Safety & Security Team include: Assistant Superintendent for Administration

More information

Evaluation. ems. Prepared By: Martha. a s Vineyard. Box P.O. Box June 2015

Evaluation. ems. Prepared By: Martha. a s Vineyard. Box P.O. Box June 2015 Martha a s Vineyard Regional High School Vineyard Haven, MA 2 2015 HVAC Syste ems Evaluation Prepared For: Martha s Vineyard Regional School District Box 1385 Oaks Bluff, MA 02557 Prepared By: BLW Engineers,

More information

Richard Henry Lee Elementary School

Richard Henry Lee Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

FLORIDA A&M UNIVERSITY PERFORMANCE CONTRACT SCOPE OF WORK

FLORIDA A&M UNIVERSITY PERFORMANCE CONTRACT SCOPE OF WORK FLORIDA A&M UNIVERSITY PERFORMANCE CONTRACT SCOPE OF WORK ENERGY CONSERVATION MEASURE 1 Partial Steam System Decentralization SIEMENS will Furnish and Install condensing hot water boilers with associated

More information

Ashland School District Facility & Capacity Assessment Report 2005

Ashland School District Facility & Capacity Assessment Report 2005 Ashland School District Facility & Capacity Assessment Report 2005 Briscoe Elementary School (Closed Facility) Address: 265 N Main Street Area: 33,980 square feet Buildings: Original Building 1948 Music

More information

DEERFIELD SCHOOL DISTRICT REFERENDUM Committed to Excellence and Equity in Educating Our Students

DEERFIELD SCHOOL DISTRICT REFERENDUM Committed to Excellence and Equity in Educating Our Students DEERFIELD SCHOOL DISTRICT REFERENDUM Committed to Excellence and Equity in Educating Our Students FACILITY NEEDS THE CHALLENGE Deerfield Middle School/High School building has served the community for

More information

Updated: 8/16/ Facilities Profile

Updated: 8/16/ Facilities Profile Updated: 8/16/17 2017-2018 Facilities Profile Purpose This package is put together to provide general information to District Administration, the School board and the public. The information contained

More information

Consent Agenda. Meeting of June 14,2018

Consent Agenda. Meeting of June 14,2018 continued on Page 2 and for automated HVAC building control system maintenance services from Honeywell International Inc., Improvement Fund (3029) in the amount of $12,898.75 from the General Library Improvements

More information

Submitted to. Texas A&M University at Commerce The Texas A&M University System. Submitted by. Guanghua Wei Craig Campbell David Claridge Dan Turner

Submitted to. Texas A&M University at Commerce The Texas A&M University System. Submitted by. Guanghua Wei Craig Campbell David Claridge Dan Turner ESL-TR-99/12-09 Report of Energy Efficiency Study and Metering/Utilities Profile for Electricity Deregulation at the Texas A&M University at Commerce (TAMU-Commerce) Commerce, Texas Submitted to Texas

More information

NYACK PUBLIC SCHOOLS CAPITAL IMPROVEMENT PLANNING PROCESS

NYACK PUBLIC SCHOOLS CAPITAL IMPROVEMENT PLANNING PROCESS NYACK PUBLIC SCHOOLS CAPITAL IMPROVEMENT PLANNING PROCESS DECEMBER 3, 2013 KEY QUESTIONS 1. What is the time sequence for available funding? (In what years will the funding be available?) 2. What is the

More information

HOLUM EDUCATION CENTER. Architectural. January 13, 2014 DeForest Area School District

HOLUM EDUCATION CENTER. Architectural. January 13, 2014 DeForest Area School District HOLUM EDUCATION CENTER Architectural The existing building has approximately 41,823 square feet and sets on a lot about 4.14 acres in size. Parking lots are located along the east and west sides of the

More information

Ohlone College Measure G Project Scope Revisions

Ohlone College Measure G Project Scope Revisions Scope Revisions Current Title Revised Title Current Scope Revised Scope 6101 Relocated Baseball Field Athletic Fields Create new sustainable baseball field with synthetic turf, bleacher seating and batting

More information

MID MICHIGAN COMMUNITY COLLEGE HARRISON CAMPUS Harrison, Michigan 2015 MASTER PLAN

MID MICHIGAN COMMUNITY COLLEGE HARRISON CAMPUS Harrison, Michigan 2015 MASTER PLAN MID MICHIGAN COMMUNITY COLLEGE HARRISON CAMPUS Harrison, Michigan 2015 MASTER PLAN September 30, 2015 PBA Project No. 2015.0140.00 PETER BASSO ASSOCIATES INC. CONSULTING ENGINEERS 5145 LIVERNOIS ROAD,

More information

Master Project List Report

Master Project List Report Blue Hills Elementary School 01-8215 Site Utilities Replacement $52,835 01-8502 Modernization $3,135,933 01-8525 Exterior Painting $181,478 01-8552 Kindergarden Fencing $13,180 Install new backflow preventer.

More information

Safety & Security. Plainview-Old Bethpage Central School District

Safety & Security. Plainview-Old Bethpage Central School District Safety & Security Plainview-Old Bethpage Central School District Agenda Security Enhancements 2017/2018 School Year Emergency Drill Requirements, Training & Expectations In-Progress Security Enhancements

More information

The work also involved determining the extent of existing stone damage and foundation settlement, and a recommendation on its repair.

The work also involved determining the extent of existing stone damage and foundation settlement, and a recommendation on its repair. The cotton mill in Cannelton provided many of the uniforms for the Union Army during the Civil War. One tower shows the effect of a cannon ball shot from a Confederate gun boat sailing on the Ohio River.

More information

Sagebrush Elementary School East Temple Place Aurora, Colorado 80015

Sagebrush Elementary School East Temple Place Aurora, Colorado 80015 Sagebrush Elementary School 14700 East Temple Place Aurora, Colorado 80015 Year Opened 1977 Current Square Footage 57,100 Site Acreage 7.66 sagebrush.cherrycreekschools.org Asphalt and concrete work; electrical

More information

Working Together to Keep our Kids Safe. Baker Middle School Families + Staff + Montgomery County Police Department = Safety

Working Together to Keep our Kids Safe. Baker Middle School Families + Staff + Montgomery County Police Department = Safety Working Together to Keep our Kids Safe Baker Middle School Families + Staff + Montgomery County Police Department = Safety See Something? Hear Something? Say Something! Recent Upgrades to Safety and Security

More information

January 11, New benches installed. Paving of parking lot adjacent to piers and the canoe put-in. Near complete with clean up remaining.

January 11, New benches installed. Paving of parking lot adjacent to piers and the canoe put-in. Near complete with clean up remaining. Project Updates January 11, 2018 CENTERVILLE CHESAPEAKE ARBORETUM BELLS MILL CITY CREEKWOOD SOUTH DEEP CREEK LOCK WORK TO BE PERFORMED/UPDATES Improvements to the parking lot include installation of a

More information

Phase II: School Safety Report_ _08:56

Phase II: School Safety Report_ _08:56 Phase II: School Safety Report_10192017_08:56 Phase II: School Safety Report Robert Pollard 76 Patriot Lane Hindman, Kentucky, 41822 United States of America Target Completion Date: 10/31/2017 Last Modified:

More information

State College Area School District High School North Building EXISTING CONDITIONS ASSESSMENT

State College Area School District High School North Building EXISTING CONDITIONS ASSESSMENT State College Area School District High School North Building Prepared by CenterPoint Engineering 08 February 2013 FACILITY ASSESSMENT SUMMARY PHYSICAL PLANT General HVAC This report is a snapshot of the

More information

Section 3. Preparedness. Shelton School District Emergency Response Plan

Section 3. Preparedness. Shelton School District Emergency Response Plan Section 3 Preparedness Preparedness Preparedness: Developing a School-Based Emergency Plan...3.1 Importance of Preparedness...3.1 Organization of this Preparedness Section...3.1 Developing a Site-Specific

More information

ANCHORAGE PARK REPORT CARD Assessing A Park s Appearance, Function, & Condition

ANCHORAGE PARK REPORT CARD Assessing A Park s Appearance, Function, & Condition ANCHORAGE PARK REPORT CARD Assessing A Park s Appearance, Function, & Condition Park Name: Is Your Park an A or an F? Your Name: Contact Information Optional: Date: General Instructions: Phone: Email:

More information

Loudoun County Public Schools Continuity of Operations Plan (COOP) Facilities Assessment Study Related to Critical Systems

Loudoun County Public Schools Continuity of Operations Plan (COOP) Facilities Assessment Study Related to Critical Systems Continuity of Operations Plan (COOP) Facilities Assessment Study Related to Critical Systems October 24, 2017 By: Office of Support Services Division of Construction Services Division of Facilities Services

More information

Josefa Ortiz De Dominguez Elementary School

Josefa Ortiz De Dominguez Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

University of the District of Columbia Van Ness Campus Master Plan Community Open House 3. December 8, 2010

University of the District of Columbia Van Ness Campus Master Plan Community Open House 3. December 8, 2010 University of the District of Columbia Van Ness Campus Master Plan Open House 3 December 8, 2010 Introductions Sequence of Work: Campus Master Plan BEGIN: INTRODUCE AND START WORK Project Initiation Team

More information

ALLEGHANY COUNTY PUBLIC SCHOOLS Maintenance Work Request Completion Analysis

ALLEGHANY COUNTY PUBLIC SCHOOLS Maintenance Work Request Completion Analysis ALLEGHANY COUNTY PUBLIC SCHOOLS Maintenance Work Request Completion Analysis 204-205 YEAR-TO-DATE Custodial Supplies 88.00 9.50 $,643. $26,39.60 $27,782.7 Preventive Maintenance 67.00,74.00 $20,372.68

More information

NARRATIVE REPORT. Underlayment Paper for Linoleum. The Asbestos Bulk Sample Results Table includes asbestos sampling data.

NARRATIVE REPORT. Underlayment Paper for Linoleum. The Asbestos Bulk Sample Results Table includes asbestos sampling data. NARRATIVE REPORT 1.0 BUILDING INFORMATION Engineering and Technology was originally constructed in 1913; although specific information is unavailable, several renovations are evident. Engineering and Technology

More information

E-SPLOST V. Facts and Information. August 2018

E-SPLOST V. Facts and Information. August 2018 E-SPLOST V Facts and Information August 2018 Education Special Purpose Local Option Sales Tax What is E-SPLOST? It is a one penny sales tax that allows for shared contribution to education, including visitors

More information

Encumbered Balance (E-D) Branham HVAC Implementation Complete 100% 03/04/19 07/19/19 $765, $635, $635, $130, $0.

Encumbered Balance (E-D) Branham HVAC Implementation Complete 100% 03/04/19 07/19/19 $765, $635, $635, $130, $0. Branham High School Budget Remaining 1 906030 Branham HVAC Implementation Complete 100% 03/04/19 07/19/19 $765,473.00 $635,342.00 $635,342.00 $130,131.00 $0.00 2 970205 Branham Interim Housing - 12 Portable

More information

WPUMC Capital Report Existing Facilities February 19, Maintenance Coordinator George Smit

WPUMC Capital Report Existing Facilities February 19, Maintenance Coordinator George Smit WPUMC Capital Report Existing Facilities February 19, 2017 Maintenance Coordinator George Smit Facility Overview Buildings Sanctuary Building (SB) Sanctuary, Narthex, Lobby Choir Room. Dr. Lee s Office,

More information

NYC Department of Education

NYC Department of Education Asset: NEW UTRECHT AF - BROOKLYN, 1601 80 STREET, New York, 11214 Inspection Id Inspection Type Time In Last Edited SA : Architectural - Senior 2017-10-31 4:06 PM 2018-06-13 10:51 AM AA : Architectural

More information

PARISH SELF-INSPECTION GUIDE

PARISH SELF-INSPECTION GUIDE PARISH SELF-INSPECTION GUIDE Gallagher Bassett Services, Inc. Risk Control Consulting Division June 2008 Gallagher Bassett Services, Inc. The information contained in this report was obtained from sources,

More information

CAPITAL OUTLAY REQUEST - IDENTIFIED AND EMERGING PROJECTS - RANKED 3-Jun-14

CAPITAL OUTLAY REQUEST - IDENTIFIED AND EMERGING PROJECTS - RANKED 3-Jun-14 2014-2015 CAPITAL OUTLAY REQUEST - IDENTIFIED AND EMERGING PROJECTS - RANKED 3-Jun-14 School Item Amount a. Classroom A/R (Increase CR capacity to 804, add l Resource and tutoring spaces needed. Teacher

More information

Chariho Regional School District Five-Year Capital Facilities Improvement Plan (2/10/15)

Chariho Regional School District Five-Year Capital Facilities Improvement Plan (2/10/15) Chariho Regional School District Five-Year Capital Facilities Improvement Plan (2/10/15) School/Department FY 16 FY 17 FY18 FY19 FY20 Chariho Regional High School FY 16 FY 17 FY18 FY19 FY20 *Repair Bleachers

More information

Worried aboutthe air quality in your schools?

Worried aboutthe air quality in your schools? Worried aboutthe air quality in your schools? Now you can breathe a little easier. (And so can everyone else.) EMA Chicago, Inc. The Situation The Environmental Protection Agency Documented that in 1995

More information

(SCHOOL DISTRICT NAME) MAINTENANCE/MANAGEMENT SPECIFICATIONS FOR ATHLETIC FIELDS AND OUTDOOR FACILITIES (SUGGESTED TEMPLATE)

(SCHOOL DISTRICT NAME) MAINTENANCE/MANAGEMENT SPECIFICATIONS FOR ATHLETIC FIELDS AND OUTDOOR FACILITIES (SUGGESTED TEMPLATE) (SCHOOL DISTRICT NAME) MAINTENANCE/MANAGEMENT SPECIFICATIONS FOR ATHLETIC FIELDS AND OUTDOOR FACILITIES (SUGGESTED TEMPLATE) I. ATHLETIC FACILITIES: PROFESSIONAL FIELDS A. Turf 1. Mow baseball outfield

More information

Draft. Security Study. Germantown School District Germantown, WI. PRA Project # February 2014

Draft. Security Study. Germantown School District Germantown, WI. PRA Project # February 2014 Draft Security Study Germantown School District Germantown, WI PRA Project # 114440 February 2014 February 2014 Germantown School District Facilities Security Study Page 1 Facilities Security Study Page

More information

Campus Middle School 4785 South Dayton Street Greenwood Village, Colorado 80111

Campus Middle School 4785 South Dayton Street Greenwood Village, Colorado 80111 Campus Middle School 4785 South Dayton Street Greenwood Village, Colorado 80111 Year Opened 1971 Current Square Footage 175,743 Site Acreage (included in CCHS) 87.22 campus.cherrycreekschools.org $2,441,170

More information

Edward Jenner Elementary Academy of the Arts

Edward Jenner Elementary Academy of the Arts Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

Campus Police Department Fire Safety Guidelines

Campus Police Department Fire Safety Guidelines Campus Police Department Fire Safety Guidelines Please take a few minutes to review these fire safety guidelines... The following information is provided to assist students, faculty, staff, and visitors

More information

400 Park Road, Watertown, CT

400 Park Road, Watertown, CT Industrial & Commercial: A Yankee Tradition Established in 1954 400 Park Road, Watertown, CT SUMMARY Modern class A office, manufacturing, warehouse, and laboratory space in approximately 140,000 SF building.

More information

Emergency Management Resource Guide. Appendix A: Crime Prevention Through Environmental Design CPTED Principles Checklist for Kentucky Public Schools

Emergency Management Resource Guide. Appendix A: Crime Prevention Through Environmental Design CPTED Principles Checklist for Kentucky Public Schools Appendix A: Crime Prevention Through Environmental Design CPTED Principles Checklist for Kentucky Public Schools 143 Crime Prevention Through Environmental Design CPTED Principles Checklist for Kentucky

More information

LONG-TERM OPERATIONS AND MAINTENANCE PLAN

LONG-TERM OPERATIONS AND MAINTENANCE PLAN LONG-TERM OPERATIONS AND MAINTENANCE PLAN May, 2017 BOARD OF EDUCATION Cathe Russe President Jackie Lutz Vice President Sam Ach Member John Heggie Member Natalie Jachtorowycz Member John J. Murphy Member

More information

Major Public Facilities. Section 4

Major Public Facilities. Section 4 Major Public Facilities Section 4 Significant Public Facilities Section Index Facility Page Alphabetical by Title (sort) Broadmeadow Elementary School 419 Center at the Heights (Senior Center) 447 Chestnut

More information

Community Response Buchanan Elementary. December 13, 2016

Community Response Buchanan Elementary. December 13, 2016 Community Response Buchanan Elementary December 13, 2016 SITE EVALUATION FOLLOWING INITIAL COMMUNITY INPUT BUCHANAN ELEMENTARY SCHOOL Design Concepts for the new Buchanan Elementary School have been shared

More information

UAA School of Engineering Parking Garage Master Plan Amendment. 1. Purpose

UAA School of Engineering Parking Garage Master Plan Amendment. 1. Purpose UAA School of Engineering Parking Garage Master Plan Amendment 1. Purpose Since the UAA campus master plan was drafted in 2003, adopted in 2004, and amended in 2009 a number of significant changes regarding

More information

NYC Department of Education

NYC Department of Education Asset: COLUMBUS AF - BRONX, 925 ASTOR AVENUE, New York, 10469 Inspection Id Inspection Type Time In Last Edited SA : Architectural - Senior 2017-10-31 9:21 AM 2017-11-29 8:45 AM AA : Architectural - Associate

More information

City of Summer side. Turf Management Procedures

City of Summer side. Turf Management Procedures City of Summer side Turf Management Procedures The City of Summerside Parks and Recreation Department is dedicated to creating positive experiences by providing quality parks, facilities, services and

More information

Beaufort County Community College. Maintenance and House Keeping Plan

Beaufort County Community College. Maintenance and House Keeping Plan Beaufort County Community College Maintenance and House Keeping Plan Summary: The College s facility management is handled by the Maintenance Department. The Director of Plant and Maintenance Operations

More information

Canal Winchester Parks Master Plan. Public Meeting 2 Thursday, February 2 6:30pm

Canal Winchester Parks Master Plan. Public Meeting 2 Thursday, February 2 6:30pm Canal Winchester Parks Master Plan Public Meeting 2 Thursday, February 2 6:30pm Meeting Agenda 1. Project overview 2. Project schedule 3. Public input results Survey Public Meeting #1 Stakeholder Interviews

More information

Charles W Earle Elementary School

Charles W Earle Elementary School Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

School Property REVIEWING YOUR BUILDINGS & GROUNDS

School Property REVIEWING YOUR BUILDINGS & GROUNDS School Property REVIEWING YOUR BUILDINGS & GROUNDS Risk Management CHECKLIST Instructions: Use this checklist to record issues that may affect your school s security and safety. Check needs attention and

More information

Table of Contents Board of Education of Queen Anne's County Comprehensive Maintenance Plan Page

Table of Contents Board of Education of Queen Anne's County Comprehensive Maintenance Plan Page Table of Contents Board of Education of Queen Anne's County Comprehensive Maintenance Plan 2015 2020 Page Purpose of Plan... 1 Objectives of Maintenance... 1 Personnel Organization... 1 Supporting Services...

More information

Computing Services Center

Computing Services Center Continuous Commissioning Report for the Computing Services Center Building #516 Submitted to: Utilities Energy Office Physical Plant Department Texas A&M University Prepared by: Energy Systems Laboratory

More information