1 Public Works Project Delivery Report May 2017 San Gabriel Public Works delivers reliable infrastructure & welcoming public spaces by designing, constructing, operating & maintaining the City s streets, parks, utilities, facilities & fleet. May is National Public Works Week and May 25 th is San Gabriel Public Works Day! Since 1960, APWA has sponsored National Public Works Week. Across North America, agencies use this week to energize and educate the public on the importance of public works to their daily lives: planning, building, managing and operating at the heart of their local communities to improve everyday quality of life. The 2017 National Public Works Week Poster Theme is Public Works Connects Us celebrating the vital role public works plays in connecting us all together. Thank you to the City Council, City Staff and -- most of all to the citizens of San Gabriel for your support of Public Works. This newsletter highlights the projects and other notable activities currently underway in the Public Works Department to help build, repair and maintain the public infrastructure. PROJECTS IN CONSTRUCTION More than Ever, San Gabriel is Paving the Way to Great Streets As reported in the last Delivery Report, more miles of streets will be repaved in the coming year than have ever been paved at one time in recent history and possibly in the City s history. We will use communication tools and best construction practices to minimize inconvenience, but there will certainly be some impacts while these streets are rebuilt. Thank you for your patience!
2 Page 2 of 5 ACE Haul Route Restoration Now Serving Agostino Rd, Del Mar Ave and Mission Rd The restoration of pavement and associated work on more than 3.5 miles of City streets, including several major arterials is underway. Replacement of curb ramps along all of these streets is complete. Pavement repairs began on Agostino in early April and Del Mar Ave, Grand Avenue, Main Street, and Santa Fe Ave in May. We will share the full construction schedule once ACE has worked out some issues with their contractor. ACE and Public Works will share the information on an ongoing basis with Council and the public through changeable message signs, the weekly City Beat, the City s website, and social media CDBG Street Improvement Project This new project is funded by Federal Community Development Block Grant (CDBG) funds administered by the LA County Community Develoment Commission. The contract for construction was approved on April 18 th and construction is moving quickly. San Gabriel County Water District replaced an old water main below California Street south of Broadway last month in advance of the paving project. California Street (from I- 10 to Marshall and from Agostino Road to Broadway) and Pine Street (from Agostino Road to Broadway) will be repaved with new access ramps installed at intersection corners. The project will be completed in May.
3 Page 3 of 5 San Gabriel Blvd/Mission Road Intersection Improvements Council awarded a contract to Sequel Contractors, Inc. for street improvements, construction of a right turn lane on Mission Road, and traffic signal upgrades. The contractor began work in April 2017 and the project will be completed by the end of the summer. Marshall Community Park Construction was delayed by about one month due to the heavy rains this winter, but the soils have dried and work is now progressing normally. The site is graded, utility lines have been installed and the restroom/storage building is currently being constructed. The photo to the left shows the site as of May 18. Del Mar Avenue Pavement Rehabilitation Project Phase 3 (Saxon Avenue to Norwood Place) Council awarded the construction contract on April 18. Construction will begin in June. The project involves reconstructing the existing pavement, installing new curb ramps, and restriping of the roadway to include bike lanes. Work will be complete by the end of summer.
4 Page 4 of 5 PROJECTS IN DESIGN/PRE-CONSTRUCTION Vincent Lugo Park Fitness Equipment & Picnic Shelters The contract for picnic shelters was awarded in March. Construction of the three new picnic shelters funded by a grant from Los Angeles County will be complete this summer. The City also received a grant for adult fitness equipment to be placed in several areas of Lugo Park. A purchase order for installation has been issued and work will begin in June. The image to the right simulates the completed installation at the west end of the park Great Streets Pavement Projects A Request for Proposals (RFP) for designing the 2017 and 2018 Great Streets Projects was issued last month and Engineering staff will bring a recommendation to hire a design consultant to City Council in June. The recommended streets and treatment methods that balance reconstruction with preventive maintenance will presented at that time. Del Mar Avenue Phase 2 (Bencamp Street to Chestnut Avenue) Design is underway for this project which involves the repaving of this segment of Del Mar Avenue and replacement/upgrade of the sanitary sewers below Del Mar Avenue. The design will be complete by the end of the year and construction will start in early Del Mar Avenue - Alhambra Wash Bridge Replacement This City project is funded primarily by the Federal bridge replacement program and is being designed by LA County Public Works. Design is complete, and Caltrans has issued the authorization for project construction. The project will be advertised in July 2017 with construction to begin in October. Due to restrictions on construction in the Alhambra Wash, construction will take two dry seasons to complete.
5 Page 5 of 5 Broadway/Walnut Grove Intersection Improvements Design of this federally-funded project is complete. Right-of-way appraisals and negotiations have taken longer than anticipated. A portion of the utility relocations for the project has been completed. Construction is anticipated to begin in 2018 and will be coordinated with the school calendar to minimize impacts. City Hall Renovations This project will improve customer service, efficiency and safety for several Departments in City Hall, including the City Clerk, Finance, and Human Resources Departments. Security features will be added to Finance, a desk for the new City Clerk Greeter position will be constructed, new customer service counters will be installed and the upstairs offices will be remodeled. Work has started in the City Clerk s office and the project is expected to be completed by this fall. In addition to the interior renovations, the exterior of City Hall will be repainted this summer. FOR MORE INFORMATION If you would like more information on any of these projects, please contact the Public Works Department at (626) City of San Gabriel Public Works Department 917 East Grand Avenue San Gabriel, California (626)
Fall 2017 Construction Update
Fall 2017 Construction Update Ward 4 Southeast Engineering Department Riverwalk Red Multi-Use Trail Bridge Rehabilitation The Riverwalk Red Multi Use Trail Bridge was awarded to Cramer and Associates,
More informationPROJECTS UNDER CONSTRUCTION
Project Name Project Status Project Funding Project Manager PJ 2144 Clayton Rd-Treat Blvd Intersection Improvements Widen the Clayton Road/Treat Blvd intersection and upgrade the traffic signal. Construction
More informationSpring 2018 Construction Update
Spring 2018 Construction Update Ward 3 Southwest Engineering Department Locust Street Bridge over the Des Moines River The Locust Street Bridge over the Des Moines River project is being let through the
More informationTHREE-YEAR CAPITAL IMPROVEMENT PLAN FY
THREE-YEAR CAPITAL IMPROVEMENT PLAN FY2016 2018 Annual CIP Development Process Public Works & Engineering Divisions Prepare List of Capital Needs and Recommended Deferred Maintenance Public Works & Engineering
More informationINFRASTRUCTURE EXISTING INFRASTRUCTURE A. Circulation B. Signals C. Drainage D. Utilities
7.01. EXISTING INFRASTRUCTURE A. Circulation B. Signals C. Drainage D. Utilities 7.02. PROPOSED INFRASTRUCTURE A. Overall Concept B. Circulation C. Signals D. Drainage 7.03. INFRASTRUCTURE MAP A. Key Infrastructure
More informationFlooding Hearing: Long and Short Term Strategies
Services of the San Francisco Public Utilities Commission Flooding Hearing: Long and Short Term Strategies Presentation to San Francisco Board of Supervisors Public Safety and Neighborhood Services Subcommittee
More informationMunicipality of Anchorage. Community Council Survey Capital Projects Needs Ranking Survey (ALPHABETICAL) Airport Heights
ANCHORAGE PARKS & RECREATION Nichols Park Design and improve neighborhood park 2008 Challenge Grant applicant. 2008 $500K State Grant for Neighborhood Parks. Tikishla Park Lighting, paved parking, hockey
More informationCottage Grove Road Reconstruction. City of Madison Engineering
Public Informational Meeting Cottage Grove Road Reconstruction October 8, 2015 Presentation Outline Introduction Project Purpose & Need Proposed Design Overview Environmental Concerns Pedestrian Needs
More informationExpo Line Transit Project. Project Status Update Meeting West End Corridor Segment C
Exposition Light Rail Transit Project Project Status Update Meeting West End Corridor Segment C Culver City Senior Center November 18, 2010 Phase 1 Project Description Phase 1 from Downtown Los Angeles
More informationTown of Yucca Valley Capital Improvement Projects Report July 24, 2014
Town of Yucca Valley Capital Improvement Projects Report July 24, 2014 SR 62 Traffic and Pedestrian Improvements from Apache Trail to Palm Avenue (PLHD) The project includes construction of curbs, gutters,
More informationCOLLIER BOULEVARD (CR 951) CORRIDOR
Project(s) Goals Improve Traffic Circulation, Capacity & Safety Focus on Safety During Design & Construction Address Public Concerns Design an Aesthetically Pleasing Project Limit Environmental Impacts
More informationDEPARTMENT SUMMARY. Departmental Relationship to City Council Goals: Support and Promote the Local Economy
Public Works DEPARTMENT SUMMARY Public Works Mission Statement The Department of Public Works is the caretaker of the community's infrastructure and a direct provider of sewer and refuse utility services
More informationMEETING DATE: November 12, 2013 SUBJECT: Accept Borden Road Bridge Improvement (CIP No )
AGENDA REPORT Meeting of the San Marcos City Council MEETING DATE: November 12, 2013 SUBJECT: Accept Borden Road Bridge Improvement (CIP No. 88165) Recommendation Staff recommends the City Council adopt
More informationThe Ambassador Bridge/ Gateway Project
The Ambassador Bridge/ Gateway Project Connecting Neighbors & Driving the Economy 2008 Ohio Conference on Freight Given by the Toledo Metropolitan Area Council of Governments, National Association of Regional
More informationExpo Light Rail Line. Expo Line Community Meeting Phase 2 Design Update November 2011
Expo Line Community Meeting Phase 2 Design Update November 2011 Meeting Agenda Phase 2 Design Update Meeting Meeting Purpose and Format Project Status Update Overview of Design Progress Next Steps Open
More informationRosecrans/Marquardt Grade Separation Project. Community Open House Meeting
Rosecrans/Marquardt Grade Separation Project Community Open House Meeting October 17, 2017 Rosecrans/Marquardt Presentation Agenda 1. Welcome Remarks & Introductions 2. Community Outreach 3. Project Goals
More informationPlanning Districts INTRODUCTION
INTRODUCTION To facilitate detailed examination of development prospects for all areas of the community, Delano has been divided into 14 planning districts. The location of these planning districts is
More informationRECEIVE AN UPDATE ON THE ALMOND GROVE PHASE II PROJECT
TOWN OF LOS GATOS COUNCIL AGENDA REPORT MEETING DATE: 12/20/2016 ITEM NO: 12 DATE: TO: FROM: SUBJECT: MAYOR AND TOWN COUNCIL LAUREL PREVETTI, TOWN MANAGER RECEIVE AN UPDATE ON THE ALMOND GROVE PHASE II
More informationCOMMUNICATION URBAN DESIGN REVIEW BOARD CITY OF DES MOINES, IOWA MAY 16, 2017 MEETING
COMMUNICATION URBAN DESIGN REVIEW BOARD CITY OF DES MOINES, IOWA MAY 16, 2017 MEETING Subject: Recommendation Prepared by: PRELIMINARY DESIGN REVIEW OF LOCUST STREET BRIDGE CONSTRUCTION & COURT AVENUE,
More informationPROJECT UPDATE BON AIR ROAD BRIDGE REPLACEMENT AND MAGNOLIA AVENUE WATER QUALITY FACILITIES
CITY OF LARKSPUR PROJECT UPDATE BON AIR ROAD BRIDGE REPLACEMENT AND MAGNOLIA AVENUE WATER QUALITY FACILITIES PRESENTED BY Julian Skinner Larkspur Public Works Director DATE July 13, 2016 Bon Air Bridge
More informationCITY OF SIMI VALLEY MEMORANDUM
CITY OF SIMI VALLEY MEMORANDUM AGENDA ITEM NO. 9.1 May 18, 2016 TO: FROM: Planning Commission Department of Environmental Services SUBJECT: REVIEW OF POTENTIAL FISCAL YEAR (FY) 2016-17 CAPITAL IMPROVEMENT
More informationThe Illinois Department of Transportation and Lake County Division of Transportation. Route 173, including the Millburn Bypass
The Illinois Department of Transportation and Lake County Division of Transportation welcome you to this Public Hearing for U.S. Route 45 from Illinois Route 132 to Illinois Route 173, including the Millburn
More informationClay Street Bridge Replacement Project
Clay Street Bridge Replacement Project Frequently Asked Questions (FAQs) No. 2 April 4, 2018 The project is located in downtown Placerville on Clay Street between US Highway 50 and Main Street and Cedar
More informationFOR IMMEDIATE RELEASE DATE: FRIDAY, AUGUST 31, Road Commission of Kalamazoo County Weekly Project Updates HAVE YOU SIGNED UP?
FOR IMMEDIATE RELEASE DATE: FRIDAY, AUGUST 31, 2018 Road Commission of Kalamazoo County Weekly Project Updates HAVE YOU SIGNED UP? Sign up for RCKC CONNECT to receive message alerts for road construction,
More informationPIKE PINE RENAISSANCE: ACT ONE. October 19, 2017
PIKE PINE RENAISSANCE: ACT ONE October 19, 2017 WATERFRONT SEATTLE PROGRAM PROJECT INTRODUCTION Pike and Pine streets, between First and Melrose avenues Pedestrian and streetscape improvements Budget:
More informationTransforming the Downtown Riverfront. Your Presenters. Mark Kelsey, Esq., Director, Ann Aubry, P.E., Deputy Director,
How to Herd Cats: Coordinating City Departments and Private Partnerships to Transform the Downtown Riverfront Your Presenters Mark Kelsey, Esq., Director, City of Columbus, Department of Public Service
More informationMPRD s Keith Mione (Community) Park Midlothian Road Entrance Traffic Signals
MPRD s Keith Mione (Community) Park Midlothian Road Entrance Traffic Signals Purpose: The Midlothian Road entrance to Mundelein Park & Recreation District s (MPRD s) Keith Mione (Community) Park would
More informationFDOT D4 Complete Streets
FDOT D4 Complete Streets Context Sensitive Solutions Directs that complete street solutions will complement the context of the community. Collaborative approach to decision making, project development,
More informationCity of Hermosa Beach Administrative Policy #
City of Hermosa Beach Administrative Policy # SUBJECT: Living Streets Policy Date: Approved by: City Council Authority: Public Works Department & Community Development Department Mayor, PURPOSE The City
More informationCapital Projects in and near Odenton Town Center
Capital Projects in and near Odenton Town Center Map ID Anne Arundel County Department of Public Works This project provides for the design, right of way acquisition, and construction of approximately
More informationCity of Jersey City. Department of Administration Division of Engineering Traffic and Transportation
Division of Engineering Traffic and Transportation : Duncan Avenue Road Program Bergen Avenue Road Program PSE&G Gas System Modernization Program NJDOT Municipal Aid FY2015 Road Program Ogden Dog Park
More informationEngineering Department
Engineering Department Department Mission It is the mission of the Engineering Department to protect and enhance the public health, safety and welfare by reviewing, inspecting and maintaining documentation
More informationDESIGN PUBLIC HEARING MAY 10, 2018 GRANBY TOWN HALL FIRST FLOOR CONFERENCE ROOM 10 WEST STATE STREET GRANBY, MASSACHUSETTS 7:00 PM FOR THE PROPOSED
DESIGN PUBLIC HEARING MAY 10, 2018 AT GRANBY TOWN HALL FIRST FLOOR CONFERENCE ROOM 10 WEST STATE STREET GRANBY, MASSACHUSETTS 7:00 PM FOR THE PROPOSED Reconstruction of Granby Road/West State Street (Route
More informationPublic Works Annual Report FY
Public Works Annual Report FY 2016-17 About the Department The Public Works Department is comprised of five divisions that oversee eight separate budget programs. These divisions include Administration,
More informationTOWNSHIP OF HOWELL TOWNSHIP OF HOWELL ENGINEERING PROJECTS STATUS REPORT OCTOBER 19, Resurfacing of Aldrich Road West Contract # 11-06
TOWNSHIP OF HOWELL DEPARTMENT OF COMMUNITY DEVELOPMENT & LAND USE DIVISION OF ENGINEERING 251 Preventorium Road Phone: (732) 938-4500 x2300 Post Office Box 580 Fax: (732) 919-1080 Howell, NJ 07731-0580
More informationProject Output Indicators for Federal Gas Tax Investments
Municipalities are required to report results achieved through the investment of federal Gas Tax funds under the Municipal Funding Agreement. AMO uses the indicators listed below to capture the outputs
More informationCitizen Information Meeting
Prince William County Government Citizen Information Meeting Vint Hill Road Extension May 11, 2016 Benefits: Route 28 Corridor Improvement Program Estimated significant cost savings versus bidding these
More informationConstruction Engineering & Inspection
Construction Engineering & Inspection Serving Florida for 20 Years CEI Engineering Planning Landscape Architecture Urban Design Construction Engineering & Inspection (CEI) I N T R O D U C T I O N Over
More informationDebra Larson and Director Malcolm Dougherty
District 5 District Director Timothy Gubbins Looking south at US 101/San Juan Road interchange in Monterey County Provide a safe, sustainable, integrated and efficient transportation system to enhance
More informationOlde Towne Vision Plan
Olde Towne Vision Plan Introduction In 2016, the City of Bellevue will complete its move of City offices from Olde Towne Bellevue to its new municipal complex on Wall Street. The City intends to sell its
More informationMEMORANDUM. 1. Award a contract for construction of the subject project to Apodaca Paving, Inc. in the amount of $324,375;
MEMORANDUM TO: FROM: BY: SUBJECT: GEOFF ENGLISH, PUBLIC WORKS DIRECTOR MIKE LINN, ASSISTANT CITY ENGINEER CONSIDERATION OF AN AWARD OF CONTRACT TO APODACA PAVING, INC. FOR CONSTRUCTION OF THE 2014 CITYWIDE
More informationI-25 / Rio Bravo Interchange. I-25 / Rio Bravo Interchange. Presenters 11/30/2016 THIRD PUBLIC MEETING DECEMBER 1, 2016 NMDOT CN A300280
I-25 / Rio Bravo Interchange TONIGHT S MEETING SCHEDULE OPEN HOUSE 6:00 PM TO 6:30 PM PRESENTATION BEGINS AT 6:30 PM Q & A FOLLOWING PRESENTATION CN A300280 / PNA300280 I-25 / Rio Bravo Interchange THIRD
More informationPanama City Beach Community Redevelopment Agency ON THE MOVE IN PCB
Panama City Beach Community Redevelopment Agency ON THE MOVE IN PCB Program Goals, Activities and Accomplishments I. Beach Front Multi-modal Transportation, Aesthetic and Parking Improvements III. Connector
More informationEXHIBIT A 2019 FINANCING: PROJECT AUTHORIZATIONS
EXHIBIT A 2019 FINANCING: PROJECT AUTHORIZATIONS Projects with Prior City Commission Authorization (No Changes) Downtown Canopy PW17B4CIP Prior Authorizing Ordinance: Ordinance No. 9428 Estimated Total
More informationWELCOME! 8 8:30 6: TH STREET IMPROVEMENTS. Open House. Presentation & Q&A
WELCOME! 168 TH STREET IMPROVEMENTS 6:30 Open House 7 8 Presentation & Q&A 8 8:30 Open House WELCOME Todd Pfitzer City of Omaha Engineer Bob Stubbe City of Omaha Public Works Director Jon Meyer Project
More information2040 Long Range Transportation Plan
2040 Long Range Transportation Plan Adopted: April 15, 2013 APPENDIX D HIGHWAY NEEDS PLAN PROJECTS FREDERICKSBURG Existing and Committed Projects Fall Hill Avenue/Mary Washington Blvd. (Fredericksburg)
More informationCity of Kearney Capital Improvement Update October 1, TH STREET AND 17TH AVENUE IMPROVEMENTS
56TH STREET AND 17TH AVENUE IMPROVEMENTS FUNDING: Bonded ESTIMATED COST: $3,885,000 COMPLETION DATE: Fall 2018 SCOPE OF PROJECT: Widening of 56th Street from 6th Avenue to 19th Avenue, and widening 17th
More informationCypress High School Site Improvement Project
Memorandum Date: March 8, 2018 To: From: Subject: Cypress High School Community Patricia Neely Director, Facilities Planning, Design, Construction Measure H Cypress High School Site Improvement Project
More informationCIVIC CENTER PUBLIC REALM PLAN OVERVIEW
Photo Credit: Blake Marvin. CIVIC CENTER PUBLIC REALM PLAN OVERVIEW PLANNING COMMISSION JANUARY 28, 2016 CIVIC CENTER PUBLIC REALM PLAN PRESENTATION OVERVIEW 1. Introduction 2. Planning History 3. Design
More informationEnhance the High Line Canal Projects
Enhance the High Line Canal Projects Joint Project Proposal for Arapahoe County Open Spaces Funding Partner Sponsors: South Suburban Park and Recreation District City of Centennial City of Littleton October
More information4.1 AESTHETICS AND VISUAL QUALITY
SCOPE AND METHODOLOGY 4.1 AESTHETICS AND VISUAL QUALITY This section evaluates the potential impacts to aesthetics and visual quality. Aesthetics refers to visual resources and the quality of what can
More informationSUBJECT: Program Manager s Report for January - February 2018
Item VIII Information TO: FROM: FRESNO COUNTY TRANSPORTATION AUTHORITY Diana Sedigh-Darbandi, Program Manager DATE: April 18, 2018 SUBJECT: Program Manager s Report for January - February 2018 The Program
More informationULI St. Louis Technical Assistance Panel
ULI St. Louis Technical Assistance Panel ULI St. Louis Technical Assistance Panel Sponsored by: Citizens for Modern Transit in partnership with METRO ULI St. Louis Mission Statement The mission of the
More informationGratigny Parkway East Extension Project Development & Environment (PD&E) Study
Gratigny Parkway East Extension Project Development & Environment (PD&E) Study Session 4: Presentation of Charrette Results December 8, 2010 MDX Work Program #: 92407 ETDM#: 11500 Project Location & Description
More informationCapital Projects impacting Odenton Town Center
Capital Projects impacting Odenton Town Center 1 2 E549700 W801600/ W801602 Anne Arundel County Department of Public Works Manor View Elementary School Transmission Main - MD 32 @ Meade Phase 2 $34,399,000
More informationleel NG CITY COUNCIL AGENDA REPORT Honorable Mayor and City Council Members
oe", City of RE leel NG CITY COUNCIL AGENDA REPORT Council Meeting Date: September 26, 2016 To: Honorable Mayor and City Council Members From: Ron Rosenthal, Engineering Director Agenda Item: 8J 2016 Street
More informationIssues Requiring Future Study
Issues Requiring Future Study Transportation planning is an ongoing process that tends to identify new issues as it finds solutions for others. Some issues are so complex that a solution to one problem
More informationI-95 Girard Avenue Interchange Near Neighbors Meeting. Project Status
I-95 Girard Avenue Interchange Project Status Construction is underway for Phase 1 and 2. Phase 3 construction will begin early 2014. Overall Project Area and Schedule GR0: Completed GR0: Completed in
More informationProject Overview. Fairfax County Parkway Widening Fairfax County. Get Involved. Public Information Meeting. Contact Information
Get Involved VDOT representatives will review and evaluate information received as a result of this meeting. Please fill out the comment sheet provided in this brochure if you have any comments or questions.
More informationConst. ROADS - Description
Road Projects make up the bulk of the capital expenditures for the township. For the term of this CIP, road projects total $9,843,000 or 72.0% of the total capital expenditures for all capital projects
More informationFY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects
ROUTE/ Project ID No. TIP No. Burlington County Computerized Signal Control, IV D9911 D9911 This ITS project will be a traffic responsive signal system, consisting of 24 intersections--9 on CR 607, 4 on
More informationFY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects
Route 1&9, County Road 99380 99380 Improvements are planned at the Route 1&9, County Road intersection to address operational and safety issues in the vicinity of Manhattan Avenue and County Road. COUNTY:
More information2017 General Obligation Bond
2017 General Obligation Bond Presentation of Public and Council Projects to the Transportation & Mobility Stakeholder Committee April 13, 2017 Agenda Deferred Maintenance Project Development Process Projects
More informationTOWN OF JUPITER. Honorable Mayor and Members of Town Council Andrew D. Lukasik, Town Manager
DATE: June 07, 2016 TO: THRU: TOWN OF JUPITER Honorable Mayor and Members of Town Council Andrew D. Lukasik, Town Manager FROM: Thomas V. Driscoll, P.E., Director of Engineering, Parks & Public Works SUBJECT:
More informationPine Avenue Improvement Project
Seaside Way to ocean Boulevard ocean Boulevard to 7 th Street 7 th Street to anaheim Street L O ng BeACh DeveLOpment ServiC e S Building a Better long Beach Pine Avenue Improvement Project Seaside Way
More information4/8/2015 Item #10D Page 1
MEETING DATE: April 8, 2015 PREPARED BY: Christy Villa, Associate Civil Engineer DEPT. DIRECTOR: Glenn Pruim DEPARTMENT: Public Works CITY MANAGER: Larry Watt SUBJECT: NORTH COAST HIGHWAY 101 STREETSCAPE
More informationThe Community and Transportation Linkage Planning Program
The Community and Transportation Linkage Planning Program Sandy Misiewicz, AICP Capital District Transportation Committee Senior Transportation Planner II CSS National Dialog 2 October 1, 2013 Capital
More informationPrince William Street Project (Grant Avenue to Wellington Road)
Prince William Street Project (Grant Avenue to Wellington Road) 1 Goals Improve pedestrian and bike traffic safety Improve street drainage with curb & gutter Upsize water mains Enhance overall street appearance
More informationFifth and Detroit Street Design May 2017 Capital Improvements Committee. DOWNTOWN Street Design
1 Fifth and Detroit Street Design May 2017 Capital Improvements Committee Agenda 2 Review Street Configuration Prior Meeting Review Outreach Synopsis Functional Street Design Refinements Curb Edge, Turning
More informationFOR IMMEDIATE RELEASE DATE: FRIDAY, SEPTEMBER 21, Road Commission of Kalamazoo County Weekly Project Updates HAVE YOU SIGNED UP?
FOR IMMEDIATE RELEASE DATE: FRIDAY, SEPTEMBER 21, 2018 Road Commission of Kalamazoo County Weekly Project Updates HAVE YOU SIGNED UP? Sign up for RCKC CONNECT to receive message alerts for road construction,
More informationBuilding Great Neighbourhoods. Strathcona
Building Great Neighbourhoods Strathcona March 21, 2018 Becky Redford Project Manager, Planning & Design Building Great Neighbourhoods Integrated Infrastructure Services Welcome and Purpose To provide
More informationGrand River Ravines Georgetown Township
Grand River Ravines Georgetown Township Project Description: The Grand River Ravines County Park property is composed of the 68-acre former Fillmore at the Bend Open Space purchased in 1999 and two more
More informationIndex to Projects by Project Name
Index to Projects by Project Name Project # PROJECT NAME PAGE 2134 2119 PR-1109 Clayton Road (Market Street to Oakland Avenue) Sidewalk Repair 911 System Replacement and Dispatch Room Remodel ADA Barrier
More informationWELCOME. Please make sure your valuables are SECURED in your vehicles Self Introductions
WELCOME Please make sure your valuables are SECURED in your vehicles Self Introductions Welcome to our Educational Luncheon Monthly Sponsors Sharon Hoffman Aaron Pieczonka a DBE/SBE Certified Firm Construction
More informationProject will Replace: Utilities Curb Pavement Lighting. City of Madison
Project will Replace: Utilities Curb Pavement Lighting Replace sanitary sewer main & laterals Winnebago: Existing 8 main, 1905 Linden: Existing 6 main, 1915, upsize to 8 main Atwood: Existing 12 main,
More informationProject Study Report Equivalent The Old Road Widening SIX FLAGS MAGIC MOUNTAIN. On Street The Old Road Between Magic Mountain Pkwy And Turnberry Lane
Project Study Report Equivalent The Old Road Widening SIX FLAGS MAGIC MOUNTAIN On Street The Old Road Between Magic Mountain Pkwy And Turnberry Lane On Street Henry Mayo Drive Between The Old Road And
More informationPRIME RESTAURANT/RETAIL SPACE FOR LEASE
PRIME RESTAURANT/RETAIL SPACE FOR LEASE 2425 OLYMPIC BLVD, SANTA MONICA, CA 90404 2 CBRE, INC. Zachary Card Lic. 01717802 Vice President t: +1 310 550 2542 e: zachary.card@cbre.com Casey Jahn Lic. 01875035
More informationDraft Environmental Assessment Appendix A. SHPO Correspondence, January 19, 2017
Draft Environmental Assessment Appendix A. SHPO Correspondence, January 19, 2017 Rosecrans/Marquardt Grade Separation Project April 2018 Federal Railroad Administration U.S. Department 1200 New Jersey
More informationTOWNSHIP OF HOWELL DEPARTMENT OF COMMUNITY DEVELOPMENT & LAND USE
TOWNSHIP OF HOWELL DEPARTMENT OF COMMUNITY DEVELOPMENT & LAND USE 4567 Route 9 North, 2 nd Floor Phone: (732) 938-4500 x2300 Post Office Box 580 Fax: (732) 414-3243 Howell, NJ 07731-0580 Web: www.twp.howell.nj.us
More informationAlternatives Development Three conceptual alternatives were developed for the Race Road/Jessup Village Planning Study and are described below:
Race Road/Jessup Village Planning Study (H550601) Project Newsletter Spring 2015 Project Description The Study Team, consisting of staff from Anne Arundel County (Department of Public Works and Department
More informationTENNESSEE DEPARTMENT OF TRANSPORTATION Project Status. No Projects Under Development in Campbell County
I-75 No Projects Under Development in Campbell County PIN: 115778.00 TRUCK CLIMBING LANE, MP 135.5 TO MP 140.1(NBL) Length - 4.6 (Widen) The right-of-way and/or utility process is underway. I-75 PIN: 115778.01
More informationADOPTED CAPITAL IMPROVEMENT PROGRAM BUDGET ARROYO PROJECTS
ADOPTED CAPITAL IMPROVEMENT PROGRAM BUDGET ARROYO PROJECTS HAHAMONGNA FY 212-216 Capital Improvement Program Priority Description Total Estimated Costs Appropriated Through FY 211 Adopted FY 212 FY 213
More information8 October 14, 2015 Public Hearing
8 October 14, 2015 Public Hearing APPLICANT & PROPERTY OWNER: PRICE S HOLDINGS, LLC STAFF PLANNER: Karen Lasley REQUEST: A. Conditional Use Permit (Automobile Repair Garage) B. Change in Nonconforming
More informationCity of Mahtomedi Park System Plan Public Hearing Draft: September 13, 2006
Chapter 6: IMPLEMENTATION INTRODUCTION Earlier chapters of this Plan analyzed existing conditions, identified park and recreation needs, and proposed park, trail, and open space recommendations. This chapter
More informationFY 2005 TRANSPORTATION CAPITAL PROGRAM
Camden County Civic Center Access Study, Pennsauken 03340 This project will address operational and access improvements on Routes 30, 73 and 90 related to the Crossroads redevelopment project around the
More informationPROJECT STATEMENT LOCATION/DESIGN PUBLIC HEARING. 19 th AVENUE NORTH EXTENSION PROJECT FROM SPRINGDALE DRIVE TO NORTH 2 ND STREET/U.S.
PROJECT STATEMENT LOCATION/DESIGN PUBLIC HEARING 19 th AVENUE NORTH EXTENSION PROJECT FROM SPRINGDALE DRIVE TO NORTH 2 ND STREET/U.S. 67 HEARING LOCATION: ERICKSEN COMMUNITY CENTER 1401 11 TH AVENUE NORTH
More informationMAIN STREET ECONOMIC DEVELOPMENT STRATEGY
MAIN STREET ECONOMIC DEVELOPMENT STRATEGY A PATHWAY TO A BETTER POUGHKEEPSIE DRAFT Working Paper #2: Planning Strategies Submitted December 1 st, 2015 to the City of Poughkeepsie LAND USE LAW CENTER PACE
More informationBuilding Great Neighbourhoods LAURIER HEIGHTS
Building Great Neighbourhoods LAURIER HEIGHTS Building Great Neighbourhoods Building Great Neighbourhoods (BGN) is a longterm framework that coordinates and integrates the efforts of three City of Edmonton
More informationNuts and Bolts (or Gravel and Asphalt) of the Main Street Project
Nuts and Bolts (or Gravel and Asphalt) of the Main Street Project What is the Main Street Project? The Main Street Project is a roadway project that addresses pavement, infrastructure and safety issues
More informationTOWN OF PALM BEACH FOR IMMEDIATE RELEASE. Patricia Strayer, P.E., Town Engineer Phone: ,
TOWN OF PALM BEACH DATE: October 19, 2017 FOR IMMEDIATE RELEASE MEDIA CONTACT: Patricia Strayer, P.E., Town Engineer Phone: 561-838-5440, Email: pstrayer@townofpalmbeach.com Construction and Traffic Highlights
More informationARROYO PROJECTS ADOPTED CAPITAL IMPROVEMENT PROGRAM BUDGET
A RROYO P ROJECTS ADOPTED CAPITAL IMPROVEMENT PROGRAM BUDGET FISCAL YEARS 214-218 HAHAMONGNA Priority Description 1 Hahamongna Watershed Park - Implement Master Plan 211,6 211,6 (77565) 2 Hahamongna -
More informationTRANSPORTATION COMMITTEE
TRANSPORTATION COMMITTEE CITY OF OTTAWA Ministry of Transportation Detailed Design Assignment G.W.P.# 4058-01-00 Highway 417 (Ottawa Queensway) Widening & Rehabilitation from Maitland Avenue to Island
More informationAGENDA ACTION ITEMS INFORMATION ITEMS
NOACA Bicycle and Pedestrian Advisory Council Meeting Friday, March 21 st, 2014 10:30 a.m. NOACA Office 1299 Superior Avenue Cleveland, Ohio 44114 Phone: (216) 241-2414; website: www.noaca.org AGENDA ACTION
More informationThis Review Is Divided Into Two Phases:
Semiahmoo Town Centre Review The purpose of this review: To review the Semiahmoo Town Centre Concept Plan, originally approved in 1993, to ensure that this centre will continue to serve the needs of South
More informationSilver Line Gateway. Extension of Silver Line Bus Rapid Transit (BRT) to Chelsea and East Boston. Public Informational Meeting Chelsea, MA
Silver Line Gateway Extension of Silver Line Bus Rapid Transit (BRT) to Chelsea and East Boston Public Informational Meeting Chelsea, MA August 18, 2014 Introduction / Design Process Design Team Joe Pavao,
More informationPORT CLINTON DOWNTOWN REVITALIZATION PLAN
The City has been awarded a $2.34 million Ohio Department of Transportation (ODOT), Small Cities Grant for the complete reconstruction of Madison Street AWARD WINNING PROJECT Best of Lake Erie Award Lake
More informationMetro Orange Line Extension Four Years Early and $61 Million Under Budget
White Paper: Metro Orange Line Extension Four Years Early and $61 Million Under Budget July 2013 Innovation for better mobility Metro Orange Line Extension Iteris, Inc. was the prime consultant leading
More informationDATE: May 25, Watershed Conservation Authority Governing Board. Johnathan Perisho, Project Manager. Mark Stanley, Executive Officer
DATE: May 25, 2017 TO: FROM: THROUGH: SUBJECT: Watershed Conservation Authority Governing Board Johnathan Perisho, Project Manager Mark Stanley, Executive Officer : Consideration of a resolution to approve
More information2016 WORKSHOP LVR Field Trip
2016 WORKSHOP LVR Field Trip ***Note*** Many of the sites on this tour were NOT related to, or funded by, the DGLVR program. They are being shown to encourage discussion about the kinds of projects that
More informationCURRICULUM VITAE REZA MARSHAL, MECE, PE, PTOE
CURRICULUM VITAE REZA MARSHAL, MECE, PE, PTOE SPECIALIZATION Traffic Engineering & Highway Design Traffic Signal Analysis & Design MUTCD/Design Standards Traffic Signal Warrant Investigation AASHTO/Design
More information